SlideShare a Scribd company logo
PM
‫باهلل‬ ‫إال‬ ‫توفيقي‬ ‫وما‬
Cost Management
(Planning , Control & Improvements)
Dr. Attia Gomaa
Industrial Engineering Professor & Consultant
Mechanical Eng. Department – Shoubra Faculty of Eng. - Benha University
& Engineering and Science Services - American University in Cairo
Facebook: Attia Gomaa & Group: Project Management - Dr Attia Gomaa
October 2018
PM 2
Cost Management Best Practice - Dr. Attia Gomaa - 2018
Course Contents:
1. Cost Management
2. Cost Estimation
3. Cost Analysis
4. Cash Flow Analysis
5. Financial Analysis
6. Project Cost Analysis
7. Project Cost Control
8. Case Studies
Cost Management
(Planning , Control & Improvements)
PM 3
Cost Management Best Practice - Dr. Attia Gomaa - 2018
Rules of the Course
This is an Open Discussion Course:
Team Approach
Remember … You can’t do it alone!
Let us be a teamwork.
– Share Knowledge
– Share Experiences
– Share Best Practices
– Share Questions
–
‫المعرفة‬ ‫تبادل‬
–
‫الخبرات‬ ‫تبادل‬
–
‫الجيدة‬ ‫التجارب‬ ‫تبادل‬
–
‫األسئلة‬ ‫تبادل‬
PM 4
Cost Management Best Practice - Dr. Attia Gomaa - 2018
Project Triple Constraints:
PM 5
Cost Management Best Practice - Dr. Attia Gomaa - 2018
1) Material
2) Machine
3) Manpower
4) Method
5) Money
(Cost)
Resources Analysis (5 M’s):
Project Constraints:
1. Scope of Work (Specs)
2. Quality (Service Quality)
3. Time (Schedule)
4. Cost (Budget)
PM 6
Cost Management Best Practice - Dr. Attia Gomaa - 2018
Cost Management
(1)
Resource
Planning
(2)
Cost
Estimation
(3)
Cost
Budgeting
(4)
Cost
Control
Cost Planning
(5)
Cost
Forecasting
2017
2018
2019
PM 7
Cost Management Best Practice - Dr. Attia Gomaa - 2018
• Resource planning: determining what resources and
quantities of them should be used.
• Cost estimating: developing an estimate of the costs and
resources needed to complete a project.
• Cost budgeting: allocating the overall cost estimate to
individual work items to establish a baseline for measuring
performance.
• Cost control: controlling changes to the project budget.
COST MANAGEMENT - Definitions
PM 8
Cost Management Best Practice - Dr. Attia Gomaa - 2018
(1) Resource Planning (2) Cost Estimating
1. Work breakdown structure (WBS)
2. Main activities
3. Resource allocation
4. Resource limits (constraints)
5. Resource requirements
6. Cost rates
7. Cost estimation
8. Cost analysis
(3) Cost Budgeting (4) Cost Control
9. Cost baseline
10.Cash in / cash out
11.Budget plan
12.Budget limits (constraints)
13.Planned performance
14.Actual performance
15.Change requests
16.Performance reports
Source: PMBOK Standard
Cost Management
PM 9
Cost Management Best Practice - Dr. Attia Gomaa - 2018
Discuss briefly the resource estimation sheet for the following item:
• Project scope of Work: Office Building (250 m2 * 5 floors)
• Main Item: Plain Concerete
• Activity: Concrete Casting For Foundation (250 kg/cm2)
• BOQ: 300 m3 Duration: 3 day
Resource Estimation:
• Resource Allocation (Standard Information):
Materials Rates:
 Cement = 0.4 ton/m3 700 LE/ton
 Sand = 0.5 m3/m3 30 LE/m3
 Gravel = 0.8 m3/m3 90 LE/m3
 Water = 160 liter/m3 0.1 LE/liter
Labor Rates:
 Concrete Crew = 5 man/day 80 LE/man-day
 Carpenter Crew = 3 man/day 90 LE/man-day
Equipment Rates:
 Mixer =1 Eq./day 250 LE/day
 Loader =1 Eq./day 200 LE/day
Margin Factor = Overhead + Profit = 50% Direct Cost
PM 10
Cost Management Best Practice - Dr. Attia Gomaa - 2018
Activity
ID
Activity
Description
BOQ
(units)
Dur.
Day
Resource
Type
Resource
Name
Resource
Units
Resource
Quantity
Resource
Price/unit
Item Cost
LE
C250
Concrete
Casting
For
Foundation
(strength
250
kg/cm2)
by
Concrete
Mixer
300
m3
3
day
Materials
Cement
0.4
ton/m3
120
ton
700
LE/ton 84000
114900
Sand
0.5
m3/m3
150
m3
30
LE/m3
4500
Gravel
0.8
m3/m3
240
m3
90
LE/m3
21600
Water
160
liter/m3
48000
liter
0.1
LE/liter
4800
Labor Concrete
Crew
5
man/day
15
man-day
80
LE/man-d
1200
2010
Carpenter
Crew
3
man/day
9
man-day
90
LE/man-d
810
Equipment
Mixer
1
Eq./day
3
Eq.-day
250
LE/day 750
1350
Loader
1
Eq./day
3
Eq.-day
200
LE/day 600
Total Direct Cost = 118,260
Margin Factor = Overhead + Profit = 50% Direct Cost 59,130
Total Income (LE) 177,390
Unit Price (LE/m3) 591
Project scope of Work: Office Building (250 m2 * 5 floors) Main Item: Foundation Activity
Resource Estimation Sheet:
PM 11
Cost Management Best Practice - Dr. Attia Gomaa - 2018
Activity
ID
Activity
Description
BOQ
(units)
Dur.
Day
Resource
Type
Resource
Name
Resource
Units
Resource
Quantity
Resource
Price/unit
Item Cost
LE
C250
Concrete
Casting
For
Foundation
(strength
250
kg/cm2)
by
Concrete
Mixer
300
m3
3
day
Materials
Cement
0.4
ton/m3
120
ton
700
LE/ton 84000
114900
Sand
0.5
m3/m3
150
m3
30
LE/m3
4500
Gravel
0.8
m3/m3
240
m3
90
LE/m3
21600
Water
160
liter/m3
48000
liter
0.1
LE/liter
4800
Labor Concrete
Crew
5
man/day
15
man-day
80
LE/man-d
1200
2010
Carpenter
Crew
3
man/day
9
man-day
90
LE/man-d
810
Equipment
Mixer
1
Eq./day
3
Eq.-day
250
LE/day 750
1350
Loader
1
Eq./day
3
Eq.-day
200
LE/day 600
Total Direct Cost = 118,260
Margin Factor = Overhead + Profit = 50% Direct Cost 59,130
Total Income (LE) 177,390
Unit Price (LE/m3) 591
Project scope of Work: Office Building (250 m2 * 5 floors) Main Item: Foundation Activity
Resource Estimation Sheet:
ID Item Name
Cost Duration
Responsibility
C250 Plain Concrete
118260 LE 3 Days
Eng. Attia Gomaa
PM 12
Cost Management Best Practice - Dr. Attia Gomaa - 2018
Cost
Tracking
Schedule
Responsibility
Quality
QA/QC
WBS
Work Breakdown Structure (WBS)
For example; MIS Project for Resource Planning
20% 27% 53%
100%
37%
100%
41% 22%
Project
Main Items
PM 13
Cost Management Best Practice - Dr. Attia Gomaa - 2018
Work Breakdown Structure (WBS)
Requirements
Design
Resource Module
Cost Module
Resource Module
Cost Module
For example; MIS Project for Resource Planning
PM 14
Cost Management Best Practice - Dr. Attia Gomaa - 2018
Project: Computer Lab 30 Users
Work Breakdown Structure (WBS)
Client: AUC
WBS - LAB
Electrical
Works
Mechanical
Works
Civil Works
IT Works
Finishing
PM 15
Cost Management Best Practice - Dr. Attia Gomaa - 2018
Cost Breakdown Structure
Unit Profit
- (-%)
Labour
Cost
- (-%)
Machine
Cost
- (- %)
Office
Overhead
- (-%)
Overhead
- (-%)
Technical Cost
- (-%)
Unit Price
- $/unit
Unit Cost
- (100%)
Critical
Resources
Technical Direct Cost
- (-%)
Materials
Cost
- (- %)
Technical
Overhead
- (-%)
Base
PM 16
Cost Management Best Practice - Dr. Attia Gomaa - 2018
The cost classification matrix for a project (First year 2016) is as follows:
Unit Price = 300 $/unit (Market Price) Planned Capacity = 100,000 units/year
Case Study:
Cost Elements
Total Cost
1,000,000 $
Direct
Costs
Raw Materials 10
Technical labors 5
Equipment & Tools 10
Overheads
Technical Overhead 2
Office Overhead 1
Total 1,000,000 $ 28
Based on this information, discuss briefly the Cost Breakdown Structure
PM 17
Cost Management Best Practice - Dr. Attia Gomaa - 2018
Cost Breakdown Structure
Total Profit
2 (7.1 %)
Labour
Cost
10 (35.7%)
Machine
Cost
5 (17.8 %)
Office
Overhead
1 (3.5%)
Overhead
3 (10.7%)
Factory Cost
27 (96.4%)
Total Price
30 M$
Total Cost
28 (100%)
Critical
Resources
Technical Direct Cost
25 (89.2%)
Materials
Cost
10 (35.7 %)
Technical
Overhead
2 (7.1 %)
Base
Annual Level
Planned Capacity
= 100,000
units/year
PM 18
Cost Management Best Practice - Dr. Attia Gomaa - 2018
Cost Breakdown Structure
Unit Profit
20 (7.1 %)
Labour
Cost
100 (35.7%)
Machine
Cost
50 (17.8 %)
Office
Overhead
10 (3.5%)
Overhead
30 (10.7%)
Factory Cost
270 (96.4%)
Unit Price
300 $/unit
Unit Cost
280 (100%)
Critical
Resources
Technical Direct Cost
250 (89.2%)
Materials
Cost
100 (35.7 %)
Technical
Overhead
20 (7.1 %)
Base
Unit Level
Planned Capacity
= 100,000
units/year
Price Policy:
Target Price = 300 $/unit
Worst Price = 270 $/unit
PM 19
Cost Management Best Practice - Dr. Attia Gomaa - 2018
• Planned Cost
• Actual Cost
• Variance Analysis
Each Indicator:
• Value ($)
• Ratio (%)
• Factor
Profit
Ratio
Value
Added
Margin
Factor
Markup
Factor
Breakeven
Point
Cost Analysis
Main Indicators:
- Profit = Price - Cost  Total Productivity
- Value Added Factor = Price / Mat. Cost  Material Productivity
- Margin Factor = Price / Direct Cost  Direct Resource Productivity
- Markup Factor = Price /Factory Cost  Factory Productivity
- Breakeven Point = F / (p-v)  Margin of Safety
PM 20
Cost Management Best Practice - Dr. Attia Gomaa - 2018
Price
TC
Profit
Total
Cost
Value
Added
1.5 to 2.5
 2.0
External
Resource
Cost
Margin
Factor
1.3 to 1.7
 1.5
Direct
Cost
Markup
Factor
1.2 to 1.3
 1.25
Factory
Cost
Or
Site Cost
Contribution
Margin
1.4 to 1.6
 1.5
Variable
Cost
Cost Analysis
PM 21
Cost Management Best Practice - Dr. Attia Gomaa - 2018
Price Structure Analysis: (Cost KPIs - Objectives)
Contract Price
Margin = Price - Direct
Direct Cost
Total Cost = Direct Cost + Overhead Profit
Value Added = Price - Outsource
Outsource Cost
or rough cut estimation by using the value added
or rough cut estimation by using the margin factor
or rough cut estimation by using the markup factor
Markup (Cost Plus)
= Office O/h + Profit
Labor
Mat. Jobsite OH
Subs
Equip
Factory Cost = Direct + Tech. O/h
For same scope of work
For different scope of work
For Cost Plus Contract
PM 22
Cost Management Best Practice - Dr. Attia Gomaa - 2018
The project cost information is as follows:
• Project : Office Building 10 Floors
• Bill of Quantity (BOQ): 6000 m2
----------------
• Direct Material Cost: 18,000,000 LE
• Direct Machine Cost: 6,000,000 LE
• Direct Labor Cost: 6,000,000 LE
----------------
• Site Overhead 3,000,000 LE
• Office Overhead: 1,500,000 LE
• Unit Price: 7,000 LE/m2
Based on this information, discuss briefly the Cost Breakdown Structure
Case Study:
Actual Cost
(2018)
Inflation Rate
15% Annually
Cost
Estimation
(2019 , 2020)
PM 23
Cost Management Best Practice - Dr. Attia Gomaa - 2018
Cost Breakdown Structure
Total Profit
7.5 (21.7%)
Labour
Cost
6 (17.4%)
Machine
Cost
6 (17.4 %)
Office
Overhead
1.5 (4.3%)
Overhead
4.5 (13.0%)
Site Cost
33 (95.6%)
Total Price
42 M.LE
Total Cost
34.5 (100%)
Critical
Resources
Technical Direct Cost
30 (86.9%)
Materials
Cost
18 (52.2 %)
Site
Overhead
3 (8.6%)
Base
Project Level
Actual Cost
(2018)
PM 24
Cost Management Best Practice - Dr. Attia Gomaa - 2018
Cost Breakdown Structure
Unit Profit
1250 (21.7%)
Labour Cost
1000 (17.4%)
Machine Cost
1000 (17.4 %)
Office
Overhead
250 (4.3%)
Overhead
750 (13.0%)
Site Cost
5500 (95.6%)
Unit Price
7000 LE/unit
Unit Cost
5750 (100%)
Critical
Resources
Technical Direct Cost
5000 (86.9%)
Materials Cost
3000(52.2 %)
Site
Overhead
500 (8.6%)
Base
Unit Level
Actual Cost
(2018)
Inflation Rate
15%
PM 25
Cost Management Best Practice - Dr. Attia Gomaa - 2018
Cost Breakdown Structure
Unit Profit
1437 (21.7%)
Labour Cost
1150 (17.4%)
Machine Cost
1150 (17.4 %)
Office
Overhead
287 (4.3%)
Overhead
862 (13.0%)
Site Cost
6325 (95.6%)
Unit Price
8050 LE/unit
Unit Cost
6613 (100%)
Critical
Resources
Technical Direct Cost
5750 (86.9%)
Materials Cost
3450 (52.2 %)
Site
Overhead
575 (8.6%)
Base
Unit Level
Cost
Estimation
(2019)
Inflation Rate
15%
PM 26
Cost Management Best Practice - Dr. Attia Gomaa - 2018
Price Structure Analysis: (Cost KPIs - Objectives)
Contract Price = 7000 LE/m2
Margin =7000-5000= 2000 LE
Direct Cost =5000
Total Cost = Direct Cost + Overhead = 5750
Profit
1250 LE
Value Added = 7000-3000= 4000 LE
Outsource Cost
3000
or rough cut estimation by using the value added
or rough cut estimation by using the margin factor
or rough cut estimation by using the markup factor
Markup (Cost Plus)
=7000-5500= 1500 LE
Labor
Mat. Jobsite OH
Subs
Equip
Site Cost = Direct + Tech. O/h = 5500
For same scope of work
For different scope of work
For Cost Plus Contract
Actual Cost
(2018)
PM 27
Cost Management Best Practice - Dr. Attia Gomaa - 2018
Price Structure Analysis: (Cost KPIs - Objectives)
Contract Price = 7000 LE/m2
Margin Factor =7000/5000= 1.4
(1 Direct : 1.4 Income)
Direct Cost =5000
Total Cost = Direct Cost + Overhead = 5750
Profit
21.7%
Value Added Factor = 7000/3000= 2.33
Material Productivity = (1 Material : 2.33 Income)
Outsource Cost
3000
or rough cut estimation by using the value added
or rough cut estimation by using the margin factor
or rough cut estimation by using the markup factor
Markup Factor
=7000/5500= 1.27
(Cost Plus)
Labor
Mat. Jobsite OH
Subs
Equip
Site Cost = Direct + Tech. O/h = 5500
For same scope of work
For different scope of work
For Cost Plus Contract
Actual Cost
(2018)
PM 28
Cost Management Best Practice - Dr. Attia Gomaa - 2018
Unit Profit
-- (21.7%)
Labour Cost
--- (17.4%)
Machine Cost
-- (17.4 %)
Office
Overhead
-- (4.3%)
Overhead
-- (13.0%)
Site Cost
-- (95.6%)
Unit Price
--- LE/unit
Unit Cost
--- (100%)
Critical
Resources
Technical Direct Cost
-- (86.9%)
Materials Cost
-- (52.2 %)
Site
Overhead
-- (8.6%)
Base
Given:
Raw Material Cost
= 4000 LE/unit
Cost Estimation #1:
PM 29
Cost Management Best Practice - Dr. Attia Gomaa - 2018
The project cost information is as follows:
• Project : Office Building 10 Floors
• Bill of Quantity (BOQ): 6000 m2
• Direct Material Cost: 18 M.LE
• Direct Machine Cost: 6 M.LE
• Direct Labor Cost: 6 M.LE
----------------
• Technical Overhead 10% Direct Cost
• Office Overhead: 5% Direct Cost
• Profit Ratio 22% Cost
Total Cost = Direct + Overhead = 30*1.15 = 34.5 M.LE
Price = Total Cost + Profit = 34.5 * 1.22 = 42 M.LE
Cost Estimation #2:
PM 30
Cost Management Best Practice - Dr. Attia Gomaa - 2018
The project cost information is as follows:
• Project : Office Building 10 Floors
• Bill of Quantity (BOQ): 600*10 = 6000 m2
----------------
• Direct Material Cost: 18 M.LE
• Direct Machine Cost: 6 M.LE
• Direct Labor Cost: 6 M.LE
----------------
• Margin Factor 40 % Direct
(Margin Factor = Overhead + Profit = Price - Direct)
Price = Direct Cost * Margin Factor = 30 * 1.4 = 42 M.LE
Cost Estimation #3:
PM 31
Cost Management Best Practice - Dr. Attia Gomaa - 2018
The project cost information is as follows:
• Project : Office Building 10 Floors
• Bill of Quantity (BOQ): 6000 m2
----------------
• Direct Material Cost: 18 M.LE
----------------
• Value Added Factor 2.333
(Value Added Factor = Price / Material)
Price = Material Cost * Value Added Factor = 18*2.333 = 42 M.LE
Cost Estimation #4:
PM 32
Cost Management Best Practice - Dr. Attia Gomaa - 2018
The project cost information is as follows:
• Project : Office Building One Floor
• Bill of Quantity (BOQ): 300 m2
----------------
• Direct Material Cost: 600,000 LE
• Direct Machine Cost: 100,000 LE
• Direct Labor Cost: 300,000 LE
----------------
• Site Overhead 100,000 LE
• Office Overhead: 50,000 LE
• Unit Price: 5,000 LE/m2
Based on this information, discuss briefly the Cost Breakdown Structure
Example: Actual Cost
PM 33
Cost Management Best Practice - Dr. Attia Gomaa - 2018
The project cost information is as follows:
• Item (Main Activity): Plain Concrete
• Bill of Quantity (BOQ) 300 m3
• Direct Material Cost 120,000 LE
• Direct Machine Cost 54,000 LE
• Direct Labor Cost 24,000 LE
• Factory Overhead 33,000 LE
• Office Overhead 16,500 LE
• Unit Price 1,100 LE/m3
Based on this information, discuss briefly the Cost Breakdown Structure
Example:
PM 34
Cost Management Best Practice - Dr. Attia Gomaa - 2018
The project cost information is as follows:
• Item (Main Activity): Power Cable
• Bill of Quantity (BOQ) 1000 m
• Direct Material Cost 1,500,000
• Direct Machines 500,000
• Direct Labors 400,000
• Tech. Overhead 15% Direct Cost
• Office Overhead 5% Direct Cost
• Profit 20% Total Cost
Brainstorming:
Based on this information, discuss briefly the Cost Breakdown Structure
PM 35
Cost Management Best Practice - Dr. Attia Gomaa - 2018
The project cost information is as follows: (Main Contractor)
• Project : Gas Pipe Line
• Bill of Quantity (BOQ) 100 Km
• Direct Material Cost 1,000,000 $
• Direct Sub-Contactor $ 400,000
• Direct Engineers $ 100,000
-----------
• Tech. Overhead 7% Total Cost
• Office Overhead 3% Total Cost
• Profit 20% Total Cost
Brainstorming:
Based on this information, discuss briefly the Cost Breakdown Structure
PM 36
Cost Management Best Practice - Dr. Attia Gomaa - 2018
Cost Breakdown Structure
Total Profit
0.333 (20%)
Engineers
Cost
0.1 (6 %)
Subcontractor
Cost
0.4 (24 %)
Office
Overhead
0.050 (3%)
Overhead
0.167 (10%)
Site Cost
1.617(97%)
Total Price
2.0 M.$
Total Cost
1.667 (100%)
Critical
Resources
Technical Direct Cost
1.5 (90%)
Materials
Cost
1.0 (60 %)
Site
Overhead
0.117(7%)
Base
Project Level
PM 37
Cost Management Best Practice - Dr. Attia Gomaa - 2018
Cost Breakdown Structure
Total Profit
333 (20%)
Engineers
Cost
100 (6%)
Subcontractor
Cost
400 (24 %)
Office
Overhead
50 (3%)
Overhead
167 (10%)
Site Cost
1,617(97%)
Total Price
20,000 $/km
Total Cost
1,667 (100%)
Critical
Resources
Technical Direct Cost
1,500 (90%)
Materials
Cost
1,000 (60 %)
Site
Overhead
117 (7%)
Base
Unit Level
PM 38
Cost Management Best Practice - Dr. Attia Gomaa - 2018
Break-Even Analysis
PM 39
Cost Management Best Practice - Dr. Attia Gomaa - 2018
Total costs = fixed costs + variable costs
– Total fixed cost (TFC) is the cost of fixed inputs, inputs that do not
vary with output (e.g., rent)
– Total variable cost (TVC) is the cost of all inputs that vary with output
(e.g., wages, raw materials)
Breakeven Quantity of Sales:
BE
Total Fixed Costs
Q =
Price Var.Cost per unit

PM 40
Cost Management Best Practice - Dr. Attia Gomaa - 2018
• Determines at what level cost and revenue are in equilibrium
• Break-even point
– Obtained directly by mathematical calculations
– Usually presented in graphic form known as break-even chart
Break-Even Analysis:
Breakeven quantity =
(Total Fixed Cost) / (unit price – unit variable cost)
Fixed cost
Variable cost
Total cost line
Total revenue line
Profit
Breakeven point
Total cost = Total revenue
Profit = 0
Production Volume (units/period)
Cost
Loss
Cost-Volume-Profit Chart
PM 41
Cost Management Best Practice - Dr. Attia Gomaa - 2018
Breakeven - Margin of Safety
PM 42
Cost Management Best Practice - Dr. Attia Gomaa - 2018
Planned Capacity 60 units
Annual Fixed Cost 300
Annual Variable Cost 360
Revenue $ 900
Example:
Planned Capacity = 60 units
Unit variable cost = 360/60 = 6 $/unit
Unit Price = 900/60 = 15
BEP = F / (p-v) = 300 / (15-6) = 33.3 = 34
Margin of safety = 60 – 34 = 26 units
PM 43
Cost Management Best Practice - Dr. Attia Gomaa - 2018
Example:
Demand (units) 500
Unit price ($) 50
Unit Variable cost ($) 15
Fixed Cost ($) 10,000
Based on this information, discuss the profit & breakeven analysis
Profit = Revenue – Total Cost
= 500*50 – (10000 + 500*15) =
BEP:
Q = F / (p-v) = 10000 / (50-15) = 285.7
Q % = 285.7 / 500 = 57.14 %
Safety Margin = 100 – 57.14 = 42.86% > 30% (Excellent)
PM 44
Cost Management Best Practice - Dr. Attia Gomaa - 2018
Scenario Analysis
Worst-Case
Scenario
Most-Likely-
Case Scenario
Best-Case
Scenario
Demand (units) 400 500 600
Unit price ($) 48 50 53
Unit Variable cost ($) 17 15 12
Fixed Cost ($) 11,000 10,000 8,000
Based on this information, discuss the profit & breakeven analysis
Total Cost
Revenue
Profit ($)
Profit (%)
BEQ (units)
BEQ (%)
Safety Margin (%)
Comment
PM 45
Cost Management Best Practice - Dr. Attia Gomaa - 2018
A company is building a workshop for producing metal windows. There is a
considerable degree of uncertainty in cost terms.
• Annual fixed costs = $ 300,000 to 500,000
• Variable cost per unit = $ 500 to 600
• Selling price per unit = $ 1,000 to 1,200
• Annual Production = 900 to 1,100 units
Based on this information, discuss the profit & breakeven analysis
Worst-Case
Scenario
Most-Likely-
Case Scenario
Best-Case
Scenario
Demand (units) 900 1000 1100
Unit price ($) 1000 1100 1200
Unit Variable cost ($) 600 550 500
Fixed Cost ($) 500,000 400,000 300,000
Example:
PM 46
Cost Management Best Practice - Dr. Attia Gomaa - 2018
Year 1 2 3 4 5
Income:
Sales Quantity, units 4000 5000 6000 7000 8000
Unit Price; $ 3000 3250 3500 3750 4000
Variable Cost ($1000):
Production Cost 1000 1250 1500 1750 2000
Technical Overhead 500 625 750 875 1000
Fixed Cost ($1000):
Depreciation 5000 5000 5000 5000 5000
Maintenance (3% of investment) 900 900 900 900 900
Insurance (1% of investment) 300 300 300 300 300
Production Cost 1000 1250 1500 1750 2000
Technical Overhead 500 625 750 875 1000
Office Overhead 500 625 750 875 1000
1) Economical Analysis (Unit Cost , Profit Ratio for each period , …)
2) Risk Analysis (Breakeven Analysis for each period )
3) Risk Analysis (Sensitivity Analysis for Market Price Change ± 10%)
4) Risk Analysis (Sensitivity Analysis for variable Cost Change ± 10%)
Based on this information, discuss the following:
PM 47
Cost Management Best Practice - Dr. Attia Gomaa - 2018
A manager is trying to decide between two
machines (A or B) to produce a certain product:
• Alt. 1: Machine A:
– Fixed Costs:
• Annual Depreciation: $120,000
• Annual Maintenance: $20,000
– Variable costs:
• Material: $2.25 / unit
• Labor: $6.25 / unit
• Alt. 2: Machine B:
– Fixed Costs:
• Annual Depreciation : $165,000
• Annual Maintenance: $35,000
– Variable costs:
• Material: $2.25 / unit
• Labor: $2.25 / unit
Based on this information, select the best machine.
Example: • Alt. 1: Machine A:
– Fixed Costs: 140,000
– Variable costs: 8.5 /unit
– TC(A) = 140,000 + 8.5 Q
• Alt. 2: Machine B:
– Fixed Costs: 200,000
– Variable costs: 4.5 /unit
– TC(B) = 200,000 + 4.5 Q
At BEQ:
TC(A) = TC(B)
140,000 + 8.5 Q = 200,000 + 4.5 Q
Q = 15,000
<15000 15000 >15000
A A,B B
B
A
15000
BEP
PM 48
Cost Management Best Practice - Dr. Attia Gomaa - 2018
EGR 312 - 22 48
Two alternatives exist for a machining process.
Alternative 1 has an initial cost of $10,000 and a salvage value of
$1000 after 5 years. Alternative 1 also has a variable cost of $1/unit
of product produced and an annual maintenance of $1000.
Alternative 2 has an initial cost of $15,000 and a salvage value of
$2,000 after 7 years. Alternative 2 also has a variable cost of
$0.80/unit of product produced and an annual maintenance cost of
$1200.
Example:
Based on this information, select the best machine.
PM 49
Cost Management Best Practice - Dr. Attia Gomaa - 2018
Total Cost
‫الكلية‬ ‫التكاليف‬
Capital Cost
‫اإلستثمار‬ ‫التكليف‬
‫ية‬
Running Cost
‫التشغيل‬ ‫التكاليف‬
‫ية‬
CAPEX and OPEX Analysis
PM 50
Cost Management Best Practice - Dr. Attia Gomaa - 2018
Assets:
The economic resources owned by a business that
can be used for future operations
‫األصول‬
:
Fixed Assets: ‫ثابته‬ ‫أصول‬
• Land
• Building
• Equipment
Current Assets: ‫متداولة‬ ‫أصول‬
• Cash
• Accounts Receivable
• Inventories
• Raw Materials
• Supplies
Intellectual Assets:
‫ملموسة‬ ‫غير‬ ‫أصول‬
)
‫فكرية‬
(
• Brand , Know-how
PM 51
Cost Management Best Practice - Dr. Attia Gomaa - 2018
CAPEX and OPEX Analysis
CAPEX Ratio + OPEX Ratio = 100%
Capital Expenses = CAPEX Ratio (Best CAPEX ≥ 25%)
= Fixed Asset Depreciation / Annual Total cost
Operating Expenses = OPEX Ratio (Best OPEX ≤ 75%)
= 100 – CAPEX
PM 52
Cost Management Best Practice - Dr. Attia Gomaa - 2018
The cost classification matrix for a project (First year 2018) is as follows:
Product / Project: xxxxxxx
Unit Price= -- LE/unit Planned Capacity = --- units/year
Product Cost Analysis: (Information)
Cost Classification Matrix
Cost Elements
Annual Fixed
Cost
Annual Variable
Cost
Direct Costs
1) Materials
2) Technical labors
3) Equipment & Tools
4) Sub-Contractor
Overheads
5) Technical Overhead Costs
6) Office Overhead Costs
Cost Analysis?
Cost
Account
PM 53
Cost Management Best Practice - Dr. Attia Gomaa - 2018
The cost classification matrix for a project (First year 2016) is as follows:
Unit Price= 300 $/unit (Market Price) Planned Capacity = 100,000 units/year
Cost Elements
Annual Fixed Cost
1,000,000 $
Annual Variable Cost
1,000,000 $
Direct
Costs
Raw Materials - 10
Technical labors 3 2
Equipment & Tools 9 1
Overheads
Technical Overhead 1 1
Office Overhead 1 -
Based on this information, discuss the following:
a) Cost breakdown structure
b) Break even ratio & Margin of safety
c) Sensitivity analysis for material cost and unit price change (±20%)
Case Study:
PM 54
Cost Management Best Practice - Dr. Attia Gomaa - 2018
The cost classification matrix for a project (First year 2016) is as follows:
Unit Price= 300 $/unit (Market Price) Planned Capacity = 100,000 units/year
Cost Elements
Annual Fixed
Cost
1,000,000 $
Annual Variable
Cost
1,000,000 $
Total Cost
1,000,000 $
Direct
Costs
Raw Materials - 10 10
Technical labors 3 2 5
Equipment &
Tools
9 1 10
Overhe
ads
Technical
Overhead
1 1 2
Office Overhead 1 - 1
Total 1,000,000 $ 14 14 28
Unit Cost = 28,000,000 / 100,000 = 280 $/unit
Unit Profit = 300 – 280 = 20 $/unit (7.14%) << 20% “Low Profit Ratio”
PM 55
Cost Management Best Practice - Dr. Attia Gomaa - 2018
Cost Breakdown Structure
Total Profit
2 (7.1 %)
Labour
Cost
10 (35.7%)
Machine
Cost
5 (17.8 %)
Office
Overhead
1 (3.5%)
Overhead
3 (10.7%)
Factory Cost
27 (96.4%)
Total Price
30 M$
Total Cost
28 (100%)
Critical
Resources
Technical Direct Cost
25 (89.2%)
Materials
Cost
10 (35.7 %)
Technical
Overhead
2 (7.1 %)
Base
Annual Level
Planned Capacity
= 100,000
units/year
PM 56
Cost Management Best Practice - Dr. Attia Gomaa - 2018
Cost Breakdown Structure
Unit Profit
20 (7.1 %)
Labour
Cost
100 (35.7%)
Machine
Cost
50 (17.8 %)
Office
Overhead
10 (3.5%)
Overhead
30 (10.7%)
Factory Cost
270 (96.4%)
Unit Price
300 $/unit
Unit Cost
280 (100%)
Critical
Resources
Technical Direct Cost
250 (89.2%)
Materials
Cost
100 (35.7 %)
Technical
Overhead
20 (7.1 %)
Base
Unit Level
Planned Capacity
= 100,000
units/year
Price Policy:
Target Price = 300 $/unit
Worst Price = 270 $/unit
PM 57
Cost Management Best Practice - Dr. Attia Gomaa - 2018
Total Fixed Cost = 14,000,000 $ Unit Variable Cost = 140 $/unit Unit Price= 300 $/unit
Breakeven %
BEP = Total Fixed Cost / (Unit Price - Unit Variable Cost)
= 14,000,000 / (300 – 140) = 87,500 unit
Planned Capacity = 100,000 units/year
BE % = 87,500 / 100,000 = 87.5%
Margin of Safety = 12.5% <<< 30 % (Very Low  High Risk)
Corrective Action: Try to reduce fixed cost by 20%
Fixed cost
Variable cost
Total cost line
Total revenue line
Profit
Breakeven point
87,500 units
Production Volume (units/period)
Cost
Loss
Cost-Volume-Profit Chart
PM 58
Cost Management Best Practice - Dr. Attia Gomaa - 2018
Sensitivity analysis for material cost and unit price change (±20%)
Deviation -20% -10%
0%
Base
10% 20%
Unit price -40 -10 20 50 80
Unit Material 40 30 20 10 0
Profit Matrix ($/unit)
Scenario Profit $/unit
Pessimistic 80
Most Likely 20
Optimistic -40
PM 59
Cost Management Best Practice - Dr. Attia Gomaa - 2018
The cost classification matrix for a project (First year 2016) is as follows:
Unit Price= 300 $/unit (Market Price) Planned Capacity = 100,000 units/year
Cost Elements
Annual Fixed Cost
1,000,000 $
Annual Variable Cost
1,000,000 $
Direct
Costs
Raw Materials - 10
Technical labors 2 3
Equipment & Tools 6 4
Overheads
Technical Overhead 1 1
Office Overhead 1 -
Based on this information, discuss the following:
a) Cost breakdown structure
b) Break even ratio & Margin of safety
c) Sensitivity analysis for material cost and unit price change (±20%)
Case Study:
PM 60
Cost Management Best Practice - Dr. Attia Gomaa - 2018
The cost classification matrix for a project (First year 2016) is as follows:
Unit Price= 300 $/unit (Market Price) Planned Capacity = 100,000 units/year
Cost Elements
Annual Fixed
Cost
1,000,000 $
Annual Variable
Cost
1,000,000 $
Total Cost
1,000,000 $
Direct
Costs
Raw Materials - 10 10
Technical labors 2 3 5
Equipment &
Tools
6 4 10
Overhe
ads
Technical
Overhead
1 1 2
Office Overhead 1 - 1
Total 1,000,000 $ 10 18 28
Unit Cost = 28,000,000 / 100,000 = 280 $/unit
Unit Profit = 300 – 280 = 20 $/unit (7.14%) << 20% “Low Profit Ratio”
PM 61
Cost Management Best Practice - Dr. Attia Gomaa - 2018
Cost Breakdown Structure
Total Profit
2 (7.1 %)
Labour
Cost
10 (35.7%)
Machine
Cost
5 (17.8 %)
Office
Overhead
1 (3.5%)
Overhead
3 (10.7%)
Factory Cost
27 (96.4%)
Total Price
30 M$
Total Cost
28 (100%)
Critical
Resources
Technical Direct Cost
25 (89.2%)
Materials
Cost
10 (35.7 %)
Technical
Overhead
2 (7.1 %)
Base
Annual Level
Planned Capacity
= 100,000
units/year
PM 62
Cost Management Best Practice - Dr. Attia Gomaa - 2018
Cost Breakdown Structure
Unit Profit
20 (7.1 %)
Labour
Cost
100 (35.7%)
Machine
Cost
50 (17.8 %)
Office
Overhead
10 (3.5%)
Overhead
30 (10.7%)
Factory Cost
270 (96.4%)
Unit Price
300 $/unit
Unit Cost
280 (100%)
Critical
Resources
Technical Direct Cost
250 (89.2%)
Materials
Cost
100 (35.7 %)
Technical
Overhead
20 (7.1 %)
Base
Unit Level
Planned Capacity
= 100,000
units/year
Price Policy:
Target Price = 300 $/unit
Worst Price = 270 $/unit
PM 63
Cost Management Best Practice - Dr. Attia Gomaa - 2018
Total Fixed Cost = 10,000,000 $ Unit Variable Cost = 180 $/unit Unit Price= 300 $/unit
Breakeven %
BEP = Total Fixed Cost / (Unit Price - Unit Variable Cost)
= 10,000,000 / (300 – 180) = 83,333 unit
Planned Capacity = 100,000 units/year
BE % = 83,333 / 100,000 = 83.3%
Margin of Safety = 16.7% <<< 30 % (Very Low  High Risk)
Corrective Action: Try to reduce fixed cost by 20%
Fixed cost
Variable cost
Total cost line
Total revenue line
Profit
Breakeven point
83,333 units
Production Volume (units/period)
Cost
Loss
Cost-Volume-Profit Chart
PM 64
Cost Management Best Practice - Dr. Attia Gomaa - 2018
Sensitivity analysis for material cost and unit price change (±20%)
Deviation -20% -10%
0%
Base
10% 20%
Unit price -40 -10 20 50 80
Unit Material 40 30 20 10 0
Profit Matrix ($/unit)
Scenario Profit $/unit
Pessimistic 80
Most Likely 20
Optimistic -40
PM 65
Cost Management Best Practice - Dr. Attia Gomaa - 2018
PM 66
Cost Management Best Practice - Dr. Attia Gomaa - 2018
PM 67
Cost Management Best Practice - Dr. Attia Gomaa - 2018
PM 68
Cost Management Best Practice - Dr. Attia Gomaa - 2018
PM 69
Cost Management Best Practice - Dr. Attia Gomaa - 2018
PM 70
Cost Management Best Practice - Dr. Attia Gomaa - 2018
PM 71
Cost Management Best Practice - Dr. Attia Gomaa - 2018
The cost classification matrix for a project (First year 2018) is as follows:
Product Name : Microwave Product Code: FMW-25KC-S
Unit Price= 2000 LE/unit Planned Capacity = 20,000 units/year
Product Cost Analysis:
Cost Classification Matrix
Cost Elements Fixed Cost Variable Cost
Direct
Cost
1) Materials 20,000,000
2) Technical labors 3,000,000 2,000,000
3) Equipment & Tools 2,000,000 1,000,000
4) Sub-Contractor - -
Overhead
Cost
5) Technical Overhead Costs 1,500,000 1,500,000
6) Office Overhead Costs 1,500,000 500,000
Cost Analysis?
PM 72
Cost Management Best Practice - Dr. Attia Gomaa - 2018
Cash Flow Analysis
Time is money;
there is a difference between $1000 today and $1000 after 3 years.
If the interest rate (i) 10% annual; then:
$ 1000 today = $ 1331 after 3 years
How
Financial Analysis
(Long Term  Project Life)
F = P (1 + i)n
P = F / (1 + i)n
PM 73
Cost Management Best Practice - Dr. Attia Gomaa - 2018
Cash Flow
Cash Out
Initial
Investment
Running
Cost
• Equipment
• Building
• Know-How
• … etc.
• Production
• Salaries
• Marketing
• Maintenance
• … etc.
Cash In
Sales
Revenue
Salvage
Value
• Quantity
• Price
• … etc.
• Equipment
• Building
• … etc.
Cash Flow Analysis:
CAPEX OPEX CAPEX
PM 74
Cost Management Best Practice - Dr. Attia Gomaa - 2018
Year 0 1 2 3 4 … …
Equipment (Assets)
Building (Assets)
Production Cost
……
……
……
Cost Elements (1000 LE):
Sales Quantities, units
Unit Market Price
Salvage Value 4000
Cash Out Analysis
Cash In Analysis
Income (1000 LE):
Analysis Tools?
Based on this information, discuss the following:
Comments?
Salvage Value
‫المصروفات‬ ‫قائمة‬
:
‫اإلرادات‬ ‫قائمة‬
:
Source:
Technical Study
Source:
Market Study
Project:
Feasibility Study: ‫الجدوي‬ ‫دراسة‬
:
PM 75
Cost Management Best Practice - Dr. Attia Gomaa - 2018
Year 0 1 2 3 4 5 6
Equipment (Assets) 7000
Building (Assets) 3000
Production Cost 2000 2600 2600 2600 2600 2600
Salaries Cost 300 300 300 300 300 300
Marketing Cost 200 250 250 250 250 250
Overhead 100 100 100 100 100 100
Sales Quantities, units 400 550 600 600 600 600
Unit Market Price 10 10 10 10 10 10
Salvage Value 4000
Based on this information, discuss the following:
Salvage Value 4000
Cost Elements (1000 LE): Cash Out Analysis ‫المصروفات‬ ‫قائمة‬
:
Cash In Analysis
Income (1000 LE): ‫اإلرادات‬ ‫قائمة‬
:
Project: ABC Manufacturing Company
Feasibility Study: ‫الجدوي‬ ‫دراسة‬
:
1) Cash Flow Analysis
2) Financial Analysis (Payback Period , IRR , … )
3) Economical Analysis (Unit Cost , Profit Ratio for each period , …)
4) Risk Analysis (Sensitivity Analysis for Market Price Change ± 10%)
PM 76
Cost Management Best Practice - Dr. Attia Gomaa - 2018
Cash Flow Analysis
i = Interest rate (%) n = Life time (year)
P = Present value  Value at time = 0
F= Future value  Value at time > 0
A= Annual uniform value  Equal value over time
• Interest rate  Certain bank  i% given (10%)
• Minimum Attractive Rate of Return (MARR)
• Internal Rate return  Cash In/out for Certain project
P
A F
Cost
(Cash Out)
Revenue
(Cash In)
(-)
(+)
F = P (1 + i)n
0
(F , P , i , n )
PM 77
Cost Management Best Practice - Dr. Attia Gomaa - 2018
Analysis Tools?
Financial
&
Economical
Analysis
1) Financial Analysis (Project Life):
• Net Cash Flow
• Payback Period
• Internal Rate of Return IRR
---------------------------
• Net Present Value NPV at i %
• CAPEX% & OPEX%
• Return On Investment
• ……
1
)
‫المالي‬ ‫التحليل‬
)
‫عمر‬ ‫إلجمالي‬
‫المشروع‬
:)
•
‫المالي‬ ‫التدفق‬ ‫صافي‬
•
‫فترة‬
‫المال‬ ‫رأس‬ ‫استرداد‬
•
‫الداخلي‬ ‫المعدل‬
‫المالي‬ ‫للعائد‬
---------------------------
•
‫للمشروع‬ ‫الحالية‬ ‫القيمة‬ ‫صافي‬
•
‫المصروفات‬ ‫نسبة‬
‫مالية‬ ‫الرأس‬
/
‫التشغيلية‬
•
‫اإلستثمار‬ ‫علي‬ ‫العائد‬ ‫متوسط‬
•
…..
‫للمشروع‬
‫واإلقتصادي‬
‫المالي‬
‫التحليل‬
2) Economical Analysis (Annually):
• Unit Cost
• Annual Profit%
---------------------------
• Cost Breakdown Structure
• CAPEX% & OPEX%
2
)
‫االقتصادي‬ ‫التحليل‬
)
‫سنويا‬
:)
•
‫تكلفة‬
‫الوحدة‬
•
‫السنوي‬ ‫الربح‬ ‫نسبة‬
---------------------------
•
‫التكاليف‬ ‫عناصر‬ ‫هيكل‬
•
‫المصروفات‬ ‫نسبة‬
‫مالية‬ ‫الرأس‬
/
‫التشغيلية‬
3) Risk Analysis (Financial / Economical) :
• Break Even Point
• Sensitivity Analysis for Material
Cost & Unit Price Change
•
3
)
‫المخاطر‬ ‫تحليل‬
)
‫مالي‬ ‫المحتملة‬
/
‫إقتصادي‬
:)
•
‫إنتاج‬ ‫حجم‬
‫نقطة‬
‫التعادل‬
•
‫الخامات‬ ‫تكلفة‬ ‫تغير‬ ‫إحتمال‬ ‫حساسية‬ ‫تحليل‬
‫وخالفه‬ ‫الوحدة‬ ‫وسعر‬
•
Feasibility Study: ‫الجدوي‬ ‫دراسة‬
:
PM 78
Cost Management Best Practice - Dr. Attia Gomaa - 2018
Project Financial Analysis:
• Payback Period (Breakeven Period); (years)
•
‫المال‬ ‫رأس‬ ‫إسترداد‬ ‫فترة‬
• Net Present Value (NPV)  (i% given)
•
‫للمشروع‬ ‫الحالية‬ ‫القيمة‬
• Profitability Index  (i% given)
•
‫الربجية‬ ‫معامل‬
• Internal Rate of Return (IRR)  (i% Unknown)
•
‫الداخلي‬ ‫العائد‬ ‫معدل‬
)
‫االستثمار‬ ‫علي‬ ‫العائد‬ ‫معدل‬
(
• Minimum Attractive Rate of Return (MARR)  Given
•
‫للمستثمر‬ ‫جاذب‬ ‫عائد‬ ‫معدل‬ ‫أقل‬
Most Common
PM 79
Cost Management Best Practice - Dr. Attia Gomaa - 2018
Example:
Payback period = 2 + 25 / 75 = 2.333 years
Firm recovers its initial investment in 2.333 years
Year
Net Cash
Flow
Cumulative
Cash Flow
0 –100 –100
1 25 –75
2 50 –25
3 75 50
Payback Period
Definition:
The length of time until the original investment has been recouped by the project
• Ignore time value of money
• Does not consider profitability
• A shorter payback period is better
PM 80
Cost Management Best Practice - Dr. Attia Gomaa - 2018
Example:
Payback Period = (2 to 3) years
= 2 + 300/350 = 2.857 years = 2 years & 11 months
$1000
$350
years
1 2 3 4
$350
$350 $350
Year 0 1 2 3 4
Cost -1000
Revenue +350 +350 +350 +350
Cumulative
Cash Flow
-1000 - 650 - 300 + 50 +400
1400
1000
Payback Period
PM 81
Cost Management Best Practice - Dr. Attia Gomaa - 2018
Example:
Payback Period = (2 to 3) years
= 2 + 300/500 = 2.6 years = 2 years & 7.2 months
$1000
$300
years
1 2 3 4
$500
$400 $400
Year 0 1 2 3 4
Cost -1000
Revenue +300 +400 +500 +400
Cumulative
Cash Flow
-1000 - 700 - 300 + 200 +600
1600
1000
Payback Period
PM 82
Cost Management Best Practice - Dr. Attia Gomaa - 2018
Net Present Value (NPV)
Converting Cash Flows to Present Value
End of project
Time zero:
Initial Investment = $105,000
TIME
Year 1 Year 2 Year 3
$38,463 $38,463 $38,463
= ??
= ??
= ??
Annual Savings
• A higher NPV is better
• Higher the discount rate lower the NPV
 
 



n
t t
t
i
F
P 1
0
1
NPV
PM 83
Cost Management Best Practice - Dr. Attia Gomaa - 2018
Net Present Value
 
63
64
.
0
*
350
71
.
0
*
350
80
.
0
*
350
89
.
0
*
350
000
,
1
12
.
1
350
12
.
1
350
12
.
1
350
12
.
1
350
000
,
1 4
3
2














Investment
NPV
Interest rate
of i =12%.
-$1,000
$350
years
1 2 3 4
$350
$350 $350
Example:
P = F / (1 + i)n
‫؟‬
(NPV +)  IRR > 12%
NPV (cash inflow)
Loan
or
MARR
-
0
+
IRR < i
IRR = i
IRR > i
NPV
PM 84
Cost Management Best Practice - Dr. Attia Gomaa - 2018
Profitability Index:
• Allows a comparison of the costs and benefits of different projects to be
assessed and thus allow decision making to be carried out
NPV (cash inflow)
Profitability Index = ---------------------------
Initial Capital Cost
PI < 1.0 Losses  Rejected (or Service projects)
PI = 1.0 Break even point  short term projects
PI > 1.0 Profit  Accepted )Best ≥ 1.20)
-$1,000
$350
years
1 2 3 4
$350
$350 $350
Profitability Index = 1063 / 1000 = 1.063 > 1.0 Accepted
Cost Benefits
(B/C)
B
C
Interest rate
of 12%
NPV (cash inflow)
PM 85
Cost Management Best Practice - Dr. Attia Gomaa - 2018
Internal Rate of Return (IRR)
Definition:
The rate of return that yields a Net Present Value of zero.
(rate at which NPV=0)
Example:
-$1,000
$350
years
1 2 3 4
$350
$350 $350
15
.
0
0
000
,
1
)
1
(
350
)
1
(
350
)
1
(
350
1
350
4
3
2











IRR
IRR
IRR
IRR
IRR
Example:
P = F / (1 + i)n
14.96%
IRR
(i% Unknown)
PM 86
Cost Management Best Practice - Dr. Attia Gomaa - 2018
Return On Investment (ROI)
Year 0 1 2 3 Total to end Year 3
Cost (Outflows) 100 30 30 35 195
Income (Inflows) 0 100 95 75 265
ROI is a ratio comparing net gains to net costs.
(measure of investment profitability)
For example:
PM 87
Cost Management Best Practice - Dr. Attia Gomaa - 2018
A
Year 0 1 2 3
ROI = 20%
IRR = 10%
Cost (Outflows) 10 2 2 2
Income (Inflows) 6 6 6
Net Flows -10 4 4 4
ROI & IRR
B
Year 0 1 2 3
ROI = 20%
IRR = 11%
Cost (Outflows) 10 1 1 4
Income (Inflows) 6 6 6
Net Flows -10 5 5 2
C
Year 0 1 2 3
ROI = 20%
IRR = 9%
Cost (Outflows) 10 4 1 1
Income (Inflows) 6 6 6
Net Flows -10 2 5 5
PM 88
Cost Management Best Practice - Dr. Attia Gomaa - 2018
You can purchase a building for $350,000. The investment will generate
$16,000 in cash flows (i.e. rent) during the first three years. At the end
of three years you will sell the building for $450,000.
What is the IRR on this investment?
0 350 000
16 000
1
16 000
1
466 000
1
1 2 3
  





,
,
( )
,
( )
,
( )
IRR IRR IRR
IRR = 12.96% ≥ MARR
Example:
350
16
years
1 2 3
16
450
16 P = F / (1 + i)n
Feasibility Study For Small Projects
PM 89
Cost Management Best Practice - Dr. Attia Gomaa - 2018
Period Cash 2 Years 3 Years
0 200,000 75,000 60,000
1 - 75,000 60,000
2 - 75,000 60,000
3 60,000
You need to buy a new car, three alternatives are available :
Based on this information, discuss the following:
1. Cash Flow Diagram
2. Internal Rate of Return (IRR)
Example:
Feasibility Study For Small Projects
PM 90
Cost Management Best Practice - Dr. Attia Gomaa - 2018
2
)
1
(
75
1
75
75
200
i
i 




3
2
)
1
(
60
)
1
(
60
1
60
60
200
i
i
i 






75
years
1 2
0
75 75
P= 200
=
B
P= 200
=
60
years
1 2 3
0
60 60 60
C
Internal Rate of Return (IRR)
i = IRR = 13.066%
i = IRR = 13.7009%
PV (A) < PV (B) < PV (C) & IRR (B) < IRR (C)
The best choice is A then B then C
PM 91
Cost Management Best Practice - Dr. Attia Gomaa - 2018
Initial Cost: $4000
Annual M&O Costs: $500
Salvage Value $500
1- Pump (A)
Initial Cost: $4500
Annual M&O Costs: $400
Salvage Value $500
Based on this information, discuss & select the best pump.
- Centrifugal Pump 1.0 HP - Interest rate is 10%
- Average Annual Costs are constant - Life 10 years
Assumptions / Calculations:
2- Pump (B)
Example:
Feasibility Study For Small Projects
PM 92
Cost Management Best Practice - Dr. Attia Gomaa - 2018
Initial Cost: $4000
Annual M&O Costs: $500
Capital Maintenance
after 6 years $3000
Salvage Value $500
1- Pump (A)
Initial Cost: $5000
Annual M&O Costs: $400
Capital Maintenance
after 6 years $2000
Salvage Value $500
Based on this information, discuss & select the best pump.
- Centrifugal Pump 1.0 HP - Interest rate is 10%
- Average Annual Costs are constant - Life 10 years
Assumptions / Calculations:
2- Pump (B)
PV: A= 8,572.9 B= 8,394.0 (Ranking: B < A)
Example:
Feasibility Study For Small Projects
PM 93
Cost Management Best Practice - Dr. Attia Gomaa - 2018
A company needs a mobile crane for the next 10 years. Two alternatives are
available to buy or to lease the crane.
1) The buy decision includes a first cost of 800,000 LE with a market value
after 10 years of 100,000 LE and annual O&M cost of 30,000 LE.
2) To lease a similar crane, the annual charge will be 120,000 LE
including everything.
If the company earns 20% annually which alternative is to be selected.
Example:
Feasibility Study For Small Projects
By using IRR method.
PM 94
Cost Management Best Practice - Dr. Attia Gomaa - 2018
800
30
100
120
680
100
90
IRR = 5.1 < 20% (Rent)
or NPV(20%) = - 305.9
Net
800
30
100
120
MARR 20%
Cash Out
Cash In
0
0
IRR
PM 95
Cost Management Best Practice - Dr. Attia Gomaa - 2018
800
30
100
120
MARR 20%
Buy
Rent
NPV (i=20%) =
909.6
NPV (i=20%) =
603.7 (min.)
0
0
NPV
PM 96
Cost Management Best Practice - Dr. Attia Gomaa - 2018
Feasibility Study For Small Projects
‫المشروع‬ ‫وصف‬
‫المكان‬
:
‫الجديدة‬ ‫القاهرة‬
/
‫األندلس‬ ‫منطقة‬
‫األرض‬ ‫مساحة‬
:
500
‫م‬
2
‫مباني‬ ‫مساحة‬
:
6000
‫م‬
2
‫المواصفات‬
:
‫بدروم‬
+
‫أرضي‬
+
3
‫أدوار‬
+
‫رووف‬
‫األرضي‬
:
‫شقة‬
180
‫م‬
2
+
‫دوبلكس‬
330
‫م‬
2
‫الدور‬
:
‫عدد‬
2
‫شقة‬
*
180
‫م‬
2
=
360
‫م‬
2
‫التكاليف‬ ‫عناصر‬ ‫متوسط‬
)
2017
)
‫األرض‬ ‫قيمة‬
:
6000
‫جنيه‬
/
‫م‬
2
‫التنفيذ‬ ‫تكاليف‬
:
6000
‫جنيه‬
/
‫م‬
2
‫اإلشراف‬ ‫نسبة‬
:
10
%
‫التنفيذ‬ ‫من‬
‫التسويق‬ ‫نسبة‬
:
5
%
‫المبيعات‬ ‫من‬
‫الحديد‬ ‫سعر‬
:
12300
‫جنيه‬
/
‫طن‬
‫سعر‬
‫األسمنت‬
:
830
‫جنيه‬
/
‫طن‬
‫المبيعات‬ ‫عناصر‬ ‫متوسط‬
)
2017
)
‫األرضي‬
:
‫شقة‬
:
7300
‫جنيه‬
/
‫م‬
2
‫دوبلكس‬
:
5500
‫جنيه‬
/
‫م‬
2
‫األدوار‬
:
‫شقة‬
:
7500
‫جنيه‬
/
‫م‬
2
‫الجراج‬
:
50000
‫جنيه‬
‫التضخم‬ ‫معامل‬
1
1
%
‫سنويا‬
‫عقاري‬ ‫إلستثمار‬ ‫جدوي‬ ‫دراسة‬
‫التنفيذ‬ ‫مدة‬
=
12
‫شهر‬
PM 97
Cost Management Best Practice - Dr. Attia Gomaa - 2018
Project: Car Rent
Initial Investment = 500,000 LE
Project Life = 10 years Salvage Value 100,000
Annual Running Cost = 8% Initial investment
Annual Maintenance Cost = 3% Initial investment
Annual Risk and Insurance = 1% Initial investment
Annual Working Days = 200 day/year
Daily Rent Price = 700 LE/day
Feasibility Study For Small Projects
PM 98
Cost Management Best Practice - Dr. Attia Gomaa - 2018
Year 0 1 2 3 4 5 6
Equipment (Assets) 7000
Building (Assets) 3000
Production Cost 2000 2600 2600 2600 2600 2600
Salaries Cost 300 300 300 300 300 300
Marketing Cost 200 250 250 250 250 250
Overhead 100 100 100 100 100 100
Sales Quantities, units 400 550 600 600 600 600
Unit Market Price 10 10 10 10 10 10
Salvage Value 4000
Based on this information, discuss the following:
Salvage Value 4000
Cost Elements (1000 LE): Cash Out Analysis ‫المصروفات‬ ‫قائمة‬
:
Cash In Analysis
Income (1000 LE): ‫اإلرادات‬ ‫قائمة‬
:
Project: ABC Manufacturing Company
Feasibility Study: ‫الجدوي‬ ‫دراسة‬
:
1) Cash Flow Analysis
2) Financial Analysis (Payback Period , IRR , … )
3) Economical Analysis (Unit Cost , Profit Ratio for each period , …)
4) Risk Analysis (Sensitivity Analysis for Market Price Change ± 10%)
PM 99
Cost Management Best Practice - Dr. Attia Gomaa - 2018
(1000 LE):
Year 0 1 2 3 4 5 6
Total Cost 10000 2600 3250 3250 3250 3250 3250
Salvage Value 4000
Sales Revenue 4000 5500 6000 6000 6000 6000
Net Cash Flow -10000 1400 2250 2750 2750 2750 6750
Cash Flow Analysis:
Payback Period = 4 + 850 / 2750 = 4.31 years = 4 year + 4 months
Accumulative Net Cash -10000 -8600 -6350 -3600 -850 +1900 +8650
1) Financial Analysis
-15000
-10000
-5000
0
5000
10000
0 2 4 6 8
Manual
PM 100
Cost Management Best Practice - Dr. Attia Gomaa - 2018
Internal Rate of Return (IRR) = 16.7% ≥ MARR
(1000 LE):
Year 0 1 2 3 4 5 6
Total Cost 10000 2600 3250 3250 3250 3250 3250
Salvage Value 4000
Sales Revenue 4000 5500 6000 6000 6000 6000
Net Cash Flow -10000 1400 2250 2750 2750 2750 6250
Cash Flow Analysis:
P = F / (1 + i)n
NPV = 0 = -10000 + {1400/(1+i)1 +2250/ (1+ i)2 +2750/ (1+ i)3
+2750/ (1+ i)4 +2750/ (1+ i)5 +6250/ (1+ i)6 }
1) Financial Analysis
Or Trail & error method:
i= 10%  NPV = + 2,312.13
i= 20%  NPV = - 1,154.93
i ?  NPV = 0
i = IRR
= 16.7%
NPV
i %
0
Manual
F = P (1 + i)n
PM 101
Cost Management Best Practice - Dr. Attia Gomaa - 2018
Year 1 2 3 4 5 6
Annual Depreciation 1000 1000 1000 1000 1000 1000
Production 2000 2500 2500 2500 2500 2500
Salaries 300 300 300 300 300 300
Marketing 200 250 250 250 250 250
Overhead 100 100 100 100 100 100
Total Cost 3600 4150 4150 4150 4150 4150
Sales Quantities 400 550 600 600 600 600
Unit Price 10 10 10 10 10 10
Sales Revenue 4000 5500 6000 6000 6000 6000
Unit Cost 9.0 7.5 6.9 6.9 6.9 6.9
Unit Price 10 10 10 10 10 10
Profit % 11.1% 32.5% 44.6% 44.6% 44.6% 44.6%
Annual Cost (1000 LE):
Annual Revenue (1000 LE):
2) Economical Analysis:
Cost Analysis (1000 LE):
Annual Depreciation = (10000 – 4000)/6 = 1000
(Straight Line Method)
PM 102
Cost Management Best Practice - Dr. Attia Gomaa - 2018
Sensitivity Analysis for Market Price Change ± 10%
3) Risk Analysis:
Indicator
Change in Market Price
- 10% 0% + 10%
Payback Period ; years 5.13 4.31 3.61
IRR 10.5% 16.7% 22.6%
Financial
Risk:
Economical
Risk
(Year #1):
Indicator
Change in Market Price
- 10% 0% + 10%
Unit Cost 9.0 9.0 9.0
Unit Price 9.0 10 11
Profit % 0 % 11.1% 22.2%
Year 0 1 2 3 4 5 6
Unit Market Price (Base) 10 10 10 10 10 10
+10% 11 11 11 11 11 11
-10% 9 9 9 9 9 9
PM 103
Cost Management Best Practice - Dr. Attia Gomaa - 2018
(1000 LE):
Year 0 1 2 3 4 5 6
Total Cost 10000 2600 3250 3250 3250 3250 3250
Salvage Value 4000
Sales Revenue 4400 6050 6600 6600 6600 6600
Net Cash Flow -10000 1800 2800 3350 3350 3350 7350
Cash Flow Analysis:
Payback Period = 3 + 2050 / 3350 = 3.61 years = 3 year + 7 months
Accumulative Net Cash -10000 -8200 -5400 -2050 1300 4650 12000
Financial Risk Change in Market Price +10% = 11 LE/unit
Internal Rate of Return (IRR) = 22.6% ≥ MARR
-15000
-10000
-5000
0
5000
10000
15000
0 1 2 3 4 5 6 7
PM 104
Cost Management Best Practice - Dr. Attia Gomaa - 2018
(1000 LE):
Year 0 1 2 3 4 5 6
Total Cost 10000 2600 3250 3250 3250 3250 3250
Salvage Value 4000
Sales Revenue 3600 4950 5400 5400 5400 5400
Net Cash Flow -10000 1000 1700 2150 2150 2150 6150
Cash Flow Analysis:
Payback Period = 5 + 850 /6150 = 3.13 years = 3 year + 1 month
Accumulative Net Cash -10000 -9000 -7300 -5150 -3000 -850 5300
Financial Risk Change in Market Price -10% = 9 LE/unit
-15000
-10000
-5000
0
5000
10000
15000
0 1 2 3 4 5 6 7 8
Internal Rate of Return (IRR) = 10.5% ≥ MARR
PM 105
Cost Management Best Practice - Dr. Attia Gomaa - 2018
Sensitivity Analysis for Operating Cost Change ± 10%
3) Risk Analysis:
Indicator
Change in Market Price
- 10% 0% + 10%
Payback Period ; years 4.31
IRR 16.7%
Financial
Risk:
Economical
Risk
(Year #1):
Indicator
Change in Market Price
- 10% 0% + 10%
Unit Cost 9.0
Unit Price 10
Profit % 11.1%
Year 0 1 2 3 4 5 6
Operating Cost (Base) 2600 3250 3250 3250 3250 3250
+10% 2860 3575 3575 3575 3575 3575
-10% 2340 2925 2925 2925 2925 2925
PM 106
Cost Management Best Practice - Dr. Attia Gomaa - 2018
Year 0 1 2 3 4 ….
Income:
Sales Quantity, units
Unit Price, $
Initial Investment ($1000):
Equipment (Assets)
Building (Assets)
Cost Elements ($1000):
Direct Production Cost
Study
Assumptions:
Project: Manufacturing Company
Feasibility Study Guidelines (Dr. Attia Gomaa)
• Annual Maintenance Cost = 3% of initial investment
• Annual Insurance = 1% of initial investment
• Salvage Value after 5 years = 50% of initial investment
• Salvage Value after 10 years = 20% of initial investment
• Technical Overhead = 50% of Direct Production Cost
• Office Overhead = 25% of Direct Production Cost
PM 107
Cost Management Best Practice - Dr. Attia Gomaa - 2018
Year 0 1 2 3 4 5
Income:
Sales Quantity, units 4000 5000 6000 7000 8000
Unit Price, $ 3000 3250 3500 3750 4000
Initial Investment ($1000):
Equipment (Assets) 25000
Building (Assets) 5000
Cost Elements ($1000):
Direct Production Cost 2000 2500 3000 3500 4000
• Annual Maintenance Cost = 3% of initial investment
• Annual Insurance = 1% of initial investment
• Salvage Value after 5 years = 50% of initial investment
• Technical Overhead = 50% of Direct Production Cost
• Office Overhead = 25% of Direct Production Cost
Based on this information, discuss the following:
Study
Assumptions:
Project: ABC Manufacturing Company
1) Financial Analysis (Cash Flow, Payback Period , IRR , … )
2) Economical Analysis (Unit Cost , Profit Ratio for each period , …)
3) Risk Analysis (Sensitivity Analysis for Market Price & Production Cost Change ± 10%)
PM 108
Cost Management Best Practice - Dr. Attia Gomaa - 2018
Year 0 1 2 3 4 5
Income:
Sales Quantity, units 4000 5000 6000 7000 8000
Unit Price, $ 3000 3250 3500 3750 4000
Initial Investment ($1000):
Equipment (Assets) 25000
Building (Assets) 5000
Salvage Value 15000
Cost Elements ($1000):
Direct Production Cost 2000 2500 3000 3500 4000
Technical Overhead 1000 1250 1500 1750 2000
Office Overhead 500 625 750 875 1000
Maintenance (3% of investment) 900 900 900 900 900
Insurance (1% of investment) 300 300 300 300 300
Based on this information, discuss the following:
1) Financial Analysis (Cash Flow, Payback Period , IRR , … )
2) Economical Analysis (Unit Cost , Profit Ratio for each period , …)
3) Risk Analysis (Sensitivity Analysis for Market Price & Production Cost Change ± 10%)
Project: ABC Manufacturing Company
PM 109
Cost Management Best Practice - Dr. Attia Gomaa - 2018
Year 0 1 2 3 4 5 6
Income:
Sales Quantity, units 500 550 600 650 700 750
Unit Price, $ 10.0 10.5 11.0 11.5 12.0 12.5
Initial Investment ($1000):
Equipment (Assets) 8000
Building (Assets) 3000
Cost Elements ($1000):
Direct Production Cost 2000 2500 3000 3500 4000 4500
• Annual Maintenance Cost = 3% of initial investment
• Annual Insurance = 1% of initial investment
• Salvage Value after 6 years = 40% of initial investment
• Technical Overhead = 50% of Direct Production Cost
• Office Overhead = 25% of Direct Production Cost
Based on this information, discuss the following:
Study
Assumptions:
Project: ABC Manufacturing Company
1) Financial Analysis (Cash Flow, Payback Period , IRR , … )
2) Economical Analysis (Unit Cost , Profit Ratio for each period , …)
3) Risk Analysis (Sensitivity Analysis for Market Price & Production Cost Change ± 10%)
PM 110
Cost Management Best Practice - Dr. Attia Gomaa - 2018
Project (B)
Project (A)
Item
7
5
Initial Investment; M$
2
2
Annual Running Cost; M$/year
5
4
Annual Revenue; M$/year
2
1
Salvage Value; M$
4
4
Project Life; years
A manager is trying to decide between two projects (A or B):
Based on this information, discuss the following:
1. Cash Flow Diagram
2. Payback Period
3. Internal Rate of Return (IRR)
4. Which offer should you accept and why?
5. Sensitivity analysis for annual revenue , salvage value & initial investment (±10%)
Minimum Attractive Rate of Return (MARR) 20%
Example:
PM 111
Cost Management Best Practice - Dr. Attia Gomaa - 2018
Project (A)
Cash Flow Diagram: Project (B)
Payback Period = 5/2 = 2.5 years
= 2 years & 6 months
IRR = 26.40 % > 20% MARR (Accepted)
Payback Period = 7/3 = 2.33 years
= 2 years & 4 months
IRR = 31.56 % > 20% MARR (Accepted)
NPV = 0 = - 5 +2/(1+i) + 2/(1+i)^2
+ 2/(1+i)^3 + 3/(1+i)^4
NPV = 0 = - 7 +3/(1+i) + 3/(1+i)^2
+ 3/(1+i)^3 + 5/(1+i)^4
IRR (B) > IRR (A) > MARR 20%
Project B is better than project A
7
1 2
0 3 4
2
5
2
7
0 1 2 3 4
3 2
5
1 2
0 3 4
2
4
1
5
0 1 2 3 4
2 1
Net cash flow =
Cash inflows - Cash outflows
PM 112
Cost Management Best Practice - Dr. Attia Gomaa - 2018
Project (B)
Payback Period = 7/2.5 = 2.8 years
= 2 years & 10 months
IRR = 22.96 %
NPV = 0 = - 7 +2.5/(1+i) + 2.5/(1+i)^2
+ 2.5/(1+i)^3 + 4.5/(1+i)^4
7
1 2
0 3 4
2
5-0.5 2
7
0 1 2 3 4
2.5 2
Project (B)
Payback Period = 7/3.5 = 2 years
IRR = 39.94 %
NPV = 0 = - 7 +3.5/(1+i) + 3.5/(1+i)^2
+ 3.5/(1+i)^3 + 5.5/(1+i)^4
7
1 2
0 3 4
2
5+0.5 2
7
0 1 2 3 4
3.5 2
Sensitivity Analysis for Project (B) Annual revenue (±10%)
PM 113
Cost Management Best Practice - Dr. Attia Gomaa - 2018
Financial Risk Analysis:
Indicator
Change in Annual Revenue
- 10% 0% + 10%
Payback Period ; years 3 3 2
IRR 22.96 % 31.56 % 39.94 %
Sensitivity Analysis for Project (B)
Indicator
Change in Salvage Value
- 10% 0% + 10%
Payback Period ; years 3 3 3
IRR 31.02 31.56 % 32.09
Indicator
Change in Initial Investment
- 10% 0% + 10%
Payback Period ; years 3 3 3
IRR 37.70 31.56 % 26.37
Scenarios
analysis (IRR%):
Optimistic 39.94
Most likely 31.56
Pessimistic 22.96
PM 114
Cost Management Best Practice - Dr. Attia Gomaa - 2018
Sensitivity Analysis Graph for Project (B)
IRR%
-5
5
10
20
30
40
60
80
-30 -20 -10 0 10 20 30
Base
Annual
revenue
Initial
Invest
% change from base
Deviation -20% -15% -10% -5%
0%
Base
5% 10% 15% 20%
Annual revenue 22.96 31.56 % 39.94
Salvage value 31.56 %
Initial Investment 31.56 %
IRR Matrix
Sketch
PM 115
Cost Management Best Practice - Dr. Attia Gomaa - 2018
Project (B)
Project (A)
Item
8
6
Initial Investment; M$
3
3
Annual Running Cost; M$/year
6
5
Annual Revenue; M$/year
3
2
Salvage Value; M$
5
5
Project Life; years
Based on this information, discuss the following:
1. Cash Flow Diagram
2. Payback Period
3. Internal Rate of Return (IRR)
4. Which offer should you accept and why?
5. Sensitivity analysis for annual revenue , salvage value & initial investment (±10%)
Minimum Attractive Rate of Return (MARR) 20%
A manager is trying to decide between two projects (A or B):
Example:
PM 116
Cost Management Best Practice - Dr. Attia Gomaa - 2018
Project (A) Project (B)
Payback Period = 3 years
IRR = 25.25% > MARR 20%
Payback Period = 2.67 years
IRR = 30.7% > MARR 20%
Sensitivity analysis:
Deviation -10%
0%
Base
10%
Annual revenue 4.5 5 5.5
IRR% 15.12 25.2 % 35
Payback Period 4.0 3 2.4
Scenarios analysis (IRR%):
Optimistic 35%
Most likely 25.5
Pessimistic 15.2%
Sensitivity analysis:
Deviation -10%
0%
Base
10%
Annual revenue 5.4 6 6.6
IRR% 21.9 30.72 39.2
Payback Period 3.3 2.67 2.22
Scenarios analysis (IRR%):
Optimistic 39.2%
Most likely 30.72%
Pessimistic 21.9%
PM 117
Cost Management Best Practice - Dr. Attia Gomaa - 2018
Project (B)
Project (A)
Item
5
4
Initial Investment; M$
2
1
Annual Running Cost; M$/year
5
3
Annual Revenue; M$/year
1
1
Salvage Value; M$
4
4
Project Life; years
Based on this information, discuss the following:
1. Cash Flow Diagram
2. Payback Period
3. Internal Rate of Return (IRR)
4. Which offer should you accept and why?
5. Sensitivity analysis for market price change (±10%)
Loan 15%
MARR = 20%
A manager is trying to decide between two projects (A or B):
Example:
PM 118
Cost Management Best Practice - Dr. Attia Gomaa - 2018
Scenario Analysis
Item
Best
Base
Worst
25%
50%
25%
Probability; %
4
5
5.1
Initial Investment; M$
3
4
4.1
Annual Running Cost; M$/year
6
5
4.9
Annual Revenue; M$/year
3
2
1.9
Salvage Value; M$
4
4
4
Project Life; years
Example:
Based on this information, discuss the following:
1. Cash Flow Diagram
2. Payback Period
3. Internal Rate of Return (IRR)
Risk Analysis
PM 119
Cost Management Best Practice - Dr. Attia Gomaa - 2018
Scenario Analysis
Item
Best
Base
Worst
25%
50%
25%
Probability; %
4
5
5.1
Initial Investment; M$
3
4
4.1
Annual Running Cost; M$/year
6
5
4.9
Annual Revenue; M$/year
3
2
1.9
Salvage Value; M$
4
4
4
Project Life; years
2
4
4
Payback Period (years)
72.7
6.4
0
Internal Rate of Return (IRR)
Risk Analysis
E (Payback Period) = 4 * 0.25 + 4 * 0.50 + 2 * 0.25= 3.5 years
E (IRR) = 0 * 0.25 + 6.4 * 0.50 + 72.7 * 0.25 = 21.4 %
Estimation:
PM 120
Cost Management Best Practice - Dr. Attia Gomaa - 2018
Scenario Analysis
Item
Best
Base
Worst
25%
50%
25%
Probability; % (by default)
4
5
6
Initial Investment; M$
3
4
5
Annual Running Cost; M$/year
6
5
4
Annual Revenue; M$/year
3
2
1
Salvage Value; M$
4
4
4
Project Life; years
Example:
Based on this information, discuss the following:
1. Cash Flow Diagram
2. Payback Period
3. Internal Rate of Return (IRR)
Risk Analysis
PM 121
Cost Management Best Practice - Dr. Attia Gomaa - 2018
Scenario Analysis
Item
Best
Base
Worst
25%
50%
25%
Probability; %
4
5
6
Initial Investment; M$
3
4
5
Annual Running Cost; M$/year
6
5
4
Annual Revenue; M$/year
3
2
1
Salvage Value; M$
4
4
4
Project Life; years
2
4
N/A
Payback Period (years)
72.7
6.4
N/A
Internal Rate of Return (IRR)
Infeasible
Risk Analysis
E (Payback Period) =
E (IRR) =
Estimation:
PM 122
Cost Management Best Practice - Dr. Attia Gomaa - 2018
Project (B)
Project (A)
Item
One year
One year
Construction Period
5
4
Initial Investment; M$
2
1
Annual Running Cost; M$/year
5
3
Annual Revenue; M$/year
1
1
Salvage Value; M$
4
4
Life after construction; years
Based on this information, discuss the following:
1. Cash Flow Diagram
2. Payback Period
3. Internal Rate of Return (IRR)
4. Which offer should you accept and why?
5. Sensitivity analysis for market price change (±10%)
Loan 15%
MARR = 20%
(Construction Period)
A manager is trying to decide between two projects (A or B):
Example:
PM 123
Cost Management Best Practice - Dr. Attia Gomaa - 2018
Project (B)
Project (A)
Item
One year
Six months
Construction Period
6
5
Initial Investment; M$
3
2
Annual Running Cost; M$/year
6
4
Annual Revenue; M$/year
2
2
Salvage Value; M$
6
5
Life after construction; years
Based on this information, discuss the following:
1. Cash Flow Diagram
2. Payback Period
3. Internal Rate of Return (IRR)
4. Which offer should you accept and why?
5. Sensitivity analysis for market price change (±10%)
MARR = 20%
(Construction Period)
A manager is trying to decide between two projects (A or B):
Example:
PM 124
Cost Management Best Practice - Dr. Attia Gomaa - 2018
Project (A) Project (B)
Payback Period = 3 years
IRR = 27.7% > MARR 20%
Payback Period = 3 years
IRR = 32.3% > MARR 20%
Sensitivity analysis:
Deviation -10%
0%
Base
10%
Annual revenue 3.6 4 4.4
IRR% 20.4 27.7 34.7
Payback Period 3.63 3.0 2.58
Scenarios analysis (IRR%):
Optimistic 34.7
Most likely 27.7
Pessimistic 20.4
Sensitivity analysis:
Deviation -10%
0%
Base
10%
Annual revenue 5.4 6 6.6
IRR% 25.4 32.3 38.5
Payback Period 3.5 3.0 2.67
Scenarios analysis (IRR%):
Optimistic 38.5
Most likely 32.3
Pessimistic 25.4
PM 125
Cost Management Best Practice - Dr. Attia Gomaa - 2018
Project (B)
Project (A)
Item
Two years
One year
Construction Period
$ 100,000 Down payment (t=0)
200,000 after one year
100,000 after two years
$ 100,000 Down payment (t=0)
$ 300,000 Final payment
Construction
investment
50,000 first year
100,000 second year
150,000 third year
200,000 forth year
$ 100,000 / year
Running cost after
construction
150,000 first year
300,000 second year
500,000 third year
400,000 forth year
$ 250,000 / year
Revenue after
construction
Four years
Four years
Life after construction
$ 100,000
$ 100,000
Salvage value
Based on this information, discuss & select the best alternative.
Minimum Attractive Rate of Return (MARR) 25%
Bank Interest Rate 10% Annual
A manager is trying to decide between two projects (A or B):
Example: (Construction Period)
PM 126
Cost Management Best Practice - Dr. Attia Gomaa - 2018
Project (A)
Item
One year
Construction
Period
$ 100,000 Down payment (t=0)
$ 300,000 Final payment
Construction
investment
$ 100,000 / year
Running cost
after
construction
$ 250,000 / year
Revenue after
construction
Four years
Life after
construction
$ 100,000
Salvage value
Minimum Attractive Rate of Return (MARR) 25%
100 100
100
250
300
0 1
100
100
150
300
0 1
IRR = 21.7 < 25%
(Rejected)
PM 127
Cost Management Best Practice - Dr. Attia Gomaa - 2018
Project (B)
Item
Two years
Construction
Period
$ 100,000 Down payment (t=0)
200,000 after one year
100,000 after two years
Construction
investment
50,000 first year
100,000 second year
150,000 third year
200,000 forth year
Running cost
after
construction
150,000 first year
300,000 second year
500,000 third year
400,000 forth year
Revenue after
construction
Four years
Life after
construction
$ 100,000
Salvage value
350
100
200
100
100
200
300
IRR = 25.25% > 25%
(Accepted)
0
PM 128
Cost Management Best Practice - Dr. Attia Gomaa - 2018
PM 129
Cost Management Best Practice - Dr. Attia Gomaa - 2018
Lake Lake
x
x
5 km
5 km
5 km
5 km
There are two ways (A and B) to construct a power line:
Standard Information
Example:
Project (B)
Project (A)
Item
Around lake
Under lake
Method
15 km
5 km
Length
PM 130
Cost Management Best Practice - Dr. Attia Gomaa - 2018
There are two ways (A and B) to construct a power line:
Project (B)
Project (A)
Item
Around lake
Under lake
Method
15 km
5 km
Length
$ 5,000/km
$ 25,000/km
First Cost
$ 200/km
$ 400/km
Annual Maintenance Cost
15 year
15 year
Expected Life
$ 3000/km
$ 5000/km
Salvage Value
$ 400/km
$ 500/km
Annual Power Losses
Based on this information, discuss & select the best alternative.
Sensitivity analysis for first cost change (±20%) and line length (±10%).
Interest rate 12% (Loan)
Standard Information
Example:
PM 131
Cost Management Best Practice - Dr. Attia Gomaa - 2018
Project (A)
Time
First
Cost
Annual
Maintenance
Power
Losses
Salvage
Value
Net
0 125 -125
1 2 2.5 -4.5
2 2 2.5 -4.5
3 2 2.5 -4.5
4 2 2.5 -4.5
5 2 2.5 -4.5
6 2 2.5 -4.5
7 2 2.5 -4.5
8 2 2.5 -4.5
…… …… …… …… ……
15 2 2.5 25 +20.5
Interest rate 12% (Loan)
NPV (12%) = 151.08 “Cost”
PM 132
Cost Management Best Practice - Dr. Attia Gomaa - 2018
Project (B)
Time
First
Cost
Annual
Maintenance
Power
Losses
Salvage
Value
Net
0 75 -75
1 3 6 -9
2 3 6 -9
3 3 6 -9
4 3 6 -9
5 3 6 -9
6 3 6 -9
7 3 6 -9
8 3 6 -9
…… …… …… …… ……
15 3 6 45 +36
Interest rate 12% (Loan)
NPV (12%) = 128.08 “Cost”
PM 133
Cost Management Best Practice - Dr. Attia Gomaa - 2018
Project (B)
Project (A)
Item
Around lake
Under lake
Method
16 km
8 km
Length
$ 5,000/km
$ 25,000/km
First Cost
$ 200/km
$ 400/km
Annual Maintenance Cost
10 year
10 year
Expected Life
$ 3000/km
$ 5000/km
Salvage Value
$ 400/km
$ 500/km
Annual Power Losses
NPV(A) = 227,803 NPV(B) = 126,515
For this non-profitable project, we should select project (B),
because it has lower NPV and also lower first cost.
Interest rate 12% (Loan)
Standard Information
Example:
There are two ways (A and B) to construct a power line:
PM 134
Cost Management Best Practice - Dr. Attia Gomaa - 2018
There are two ways (A and B) to construct a power line:
Project (B)
Project (A)
Item
Around lake
Under lake
Method
15 km
5 km
Length
$ 5,000/km
$ 25,000/km
First Cost
$ 200/km
$ 400/km
Annual Maintenance Cost
15 year
15 year
Expected Life
$ 3000/km
$ 5000/km
Salvage Value
$ 400/km
$ 500/km
Annual Power Losses
$ 25,000
$ 25,000
Annual Revenue
Based on this information, discuss & select the best alternative.
Sensitivity analysis for first cost change (±20%) and line length (±10%).
Interest rate 12% (Loan)
Standard Information
Example:
PM 135
Cost Management Best Practice - Dr. Attia Gomaa - 2018
PM 136
Cost Management Best Practice - Dr. Attia Gomaa - 2018
Capitalization Rate (Cap Rate)
is an indirect measurement of how an investment pays
for itself Average national cap rates for limited-service
hotels over the past decade ranged between 9-13%.
PM 137
Cost Management Best Practice - Dr. Attia Gomaa - 2018
Project (B)
Project (A)
Item
5.0
4.5
Initial Investment; M$
1.2
1.1
Annual Running Cost; M$/year
3.0
2.5
Annual Revenue; M$/year
-
-
Salvage Value; M$
4
4
Project Life; years
Based on this information, discuss the following:
1. Cash Flow Diagram
2. Profitability Index
3. Capitalization Rate
4. Which offer should you accept and why?
Bank interest rate 12%
A manager is trying to decide between two projects (A or B):
Example:
PM 138
Cost Management Best Practice - Dr. Attia Gomaa - 2018
Project (A) Project (B)
5.0
1 2
0 3 4
1.2
3.0
5.0
0 1 2 3 4
1.8
4.5
1 2
0 3 4
1.1
2.5
4.5
0 1 2 3 4
1.4
PI(B) > PI(A) & CR(B)>CR(A)
Project B is better than project A
Capitalization Rate =
Annual Net Income / Initial Capital Cost
= 1.4 / 4.5 = 0.311 = 31.1%
Capitalization Rate =
Annual Net Income / Initial Capital Cost
= 1.8/5.0 = 0.36 = 36%
NPV (cash inflow) =
= 1.4/(1.12) + 1.4/(1.12)^2
+ 1.4/(1.12)^3 + 1.4/(1.2)^4 = 4.25
Profitability Index =
NPV (cash inflow) / Initial Capital Cost
= 4.25 /4.5 = 0.94
Profitability Index =
= 5.47 /5.0 = 1.094
NPV (cash inflow) =
1.8/(1.12) + 1.8/(1.12)^2
+ 1.8/(1.12)^3 + 1.8/(1.12)^4 = 5.47
PM 139
Cost Management Best Practice - Dr. Attia Gomaa - 2018
Hotel Cap Rate
Net Operating Income $1,953,930
Total Development Cost $12,192,731
Cap Rate 16%
PM 140
Cost Management Best Practice - Dr. Attia Gomaa - 2018
Project (B)
Project (A)
Item
5.0
4.5
Initial Investment; M$
1.2
1.1
Annual Running Cost; M$/year
3.0
2.5
Annual Revenue; M$/year
-
-
Salvage Value; M$
4
4
Project Life; years
Based on this information, discuss the following:
1. Cash Flow Diagram
2. Profitability Index
3. Capitalization Rate
4. Which offer should you accept and why?
Bank interest rate 12%
A manager is trying to decide between two projects (A or B):
Example:
PM 141
Cost Management Best Practice - Dr. Attia Gomaa - 2018
Project (A) Project (B)
5.0
1 2
0 3 4
1.2
3.0
5.0
0 1 2 3 4
1.8
4.5
1 2
0 3 4
1.1
2.5
4.5
0 1 2 3 4
1.4
PI(B) > PI(A) & CR(B)>CR(A)
Project B is better than project A
Capitalization Rate =
Annual Net Income / Initial Capital Cost
= 1.4 / 4.5 = 0.311 = 31.1%
Capitalization Rate =
Annual Net Income / Initial Capital Cost
= 1.8/5.0 = 0.36 = 36%
NPV (cash inflow) =
= 1.4/(1.12) + 1.4/(1.12)^2
+ 1.4/(1.12)^3 + 1.4/(1.12)^4 = 4.25
Profitability Index =
NPV (cash inflow) / Initial Capital Cost
= 4.25 /4.5 = 0.94
Profitability Index =
= 5.47 /5.0 = 1.094
NPV (cash inflow) =
1.8/(1.12) + 1.8/(1.12)^2
+ 1.8/(1.12)^3 + 1.8/(1.12)^4 = 5.47
PM 142
Cost Management Best Practice - Dr. Attia Gomaa - 2018
Project (B)
Project (A)
Item
5.0
4.5
Initial Investment; M$
1.2
1.1
Annual Running Cost; M$/year
3.0
2.5
Annual Revenue; M$/year
1.2
1.1
Salvage Value; M$
4
4
Project Life; years
Based on this information, discuss the following:
1. Cash Flow Diagram
2. Profitability Index
3. Capitalization Rate
4. Which offer should you accept and why?
Bank interest rate 12%
A manager is trying to decide between two projects (A or B):
Example:
PM 143
Cost Management Best Practice - Dr. Attia Gomaa - 2018
Project (A)
Cash Flow Diagram:
Project (B)
NPV (cash inflow) =
= 1.4/(1.12) + 1.4/(1.12)^2
+ 1.4/(1.12)^3 + 2.5/(1.2)^4 = 4.95
Profitability Index =
NPV (cash inflow) / Initial Capital Cost
= 4.95/4.5 = 1.10
Profitability Index =
= 6.23/5.0 = 1.25
5.0
1 2
0 3 4
1.2
3.0
1.2
5.0
0 1 2 3 4
1.8 1.2
4.5
1 2
0 3 4
1.1
2.5
1.1
4.5
0 1 2 3 4
1.4 1.1
PI(B) > PI(A)
Project B is better than project A
NPV (cash inflow) =
1.8/(1.12) + 1.8/(1.12)^2
+ 1.8/(1.12)^3 + 3.0/(1.12)^4 = 6.23
PM 144
Cost Management Best Practice - Dr. Attia Gomaa - 2018
Project (A)
Cash Flow Diagram:
Project (B)
NPV (cash inflow) = 4.95
Annual Net Income = (A/P, i, n)
= {i (1+i)n } / {(1+i)n -1}
= 4.95 *0.12*(1.12)^4 / (1.12^4-1) = 1.63
5.0
1 2
0 3 4
1.2
3.0
1.2
5.0
0 1 2 3 4
1.8 1.2
4.5
1 2
0 3 4
1.1
2.5
1.1
4.5
0 1 2 3 4
1.4 1.1
CR(B) > CR(A)
Project B is better than project A
NPV (cash inflow) = 6.23
= 6.23 *0.12*(1.12)^4 / (1.12^4-1)
= 2.05
Capitalization Rate =
Annual Net Income / Initial Capital Cost
= 1.63 / 4.5 = 0.36 = 36%
Capitalization Rate =
= 2.05 / 5.0 = 0.41 = 41%
PM 145
Cost Management Best Practice - Dr. Attia Gomaa - 2018
Economic Service Life for a Lift Truck
Element
Life; Year
0 1 2 3 4 5 6 7
Initial Cost; $ 20000
O&M; $ 1000 + 15% Annual
Capital Maintenance; $ 2000
Book Value; $ 15000 11000 8000 6000 5000 4000 2000
Interest rate 15%
Replacement Analysis:
Based on this information; What is the economic life of a lift truck?
Example:
Annual Equivalent Cost (AEC)
PM 146
Cost Management Best Practice - Dr. Attia Gomaa - 2018
AEC1 = x (A/P,15%,1)
20,000
- 14,000 (P/F,15%,1)
i = 15%
0
20
1
1
15
Annual Equivalent Cost (AEC)
PM 147
Cost Management Best Practice - Dr. Attia Gomaa - 2018
AEC2 = x (A/P,15%,2)
20,000
+ 1,000 (P/F,15%,1)
- 9,850 (P/F,15%,2)
i = 15%
0
20
1
1
2
1.15
11
PM 148
Cost Management Best Practice - Dr. Attia Gomaa - 2018
AEC3 = x (A/P,15%,3)
20,000
+ 1,000 (P/F,15%,1)
+ 1,150 (P/F,15%,2)
- 6,700 (P/F,15%,3)
i = 15%
0
20
1
1
2
1.15
3
8
1.3
PM 149
Cost Management Best Practice - Dr. Attia Gomaa - 2018
AEC4 = x (A/P,15%,4)
20,000
+ 1,000 (P/F,15%,1)
+ 1,150 (P/F,15%,2)
+ 1,300 (P/F,15%,3)
- 4,550 (P/F,15%,4)
0
20
1
1
2
1.15
3 4
1.3
6
1.45
i = 15%
PM 150
Cost Management Best Practice - Dr. Attia Gomaa - 2018
AEC5 = x (A/P,15%,5)
20,000
+ 1,000 (P/F,15%,1)
+ 1,150 (P/F,15%,2)
+ 1,300 (P/F,15%,3)
+ 1,450 (P/F,15%,4)
- 1,400 (P/F,15%,5)
0
20
1
1
2
1.15
3 4 5
1.3
1.45
1.6
2
5
i = 15%
PM 151
Cost Management Best Practice - Dr. Attia Gomaa - 2018
AEC6 = x (A/P,15%,6)
20,000
+ 1,000 (P/F,15%,1)
+ 1,150 (P/F,15%,2)
+ 1,300 (P/F,15%,3)
+ 1,450 (P/F,15%,4)
+ 3,600 (P/F,15%,5)
- 2,250 (P/F,15%,6)
0
20
1
1
2
1.15
3 4 5
1.3
1.45
1.6
1.75
2
4
i = 15%
PM 152
Cost Management Best Practice - Dr. Attia Gomaa - 2018
AEC7 = x (A/P,15%,7)
20,000
+ 1,000 (P/F,15%,1)
+ 1,150 (P/F,15%,2)
+ 1,300 (P/F,15%,3)
+ 1,450 (P/F,15%,4)
+ 3,600 (P/F,15%,5)
+ 1,750 (P/F,15%,6)
- 100 (P/F,15%,7)
0
20
1
1
2
1.15
3 4 5 6
1.3
1.45
1.6
1.75
7
2 1.9
2
i = 15%
PM 153
Cost Management Best Practice - Dr. Attia Gomaa - 2018
Economic Life for truck 6 Years
AEC
Year
9000
1
8225
2
7592
3
7003
4
6780
5
6405
6
6852
7
Year
AEC
Summary:
PM 154
Cost Management Best Practice - Dr. Attia Gomaa - 2018
Economic Service Life for a compressor
Life; Year
0 1 2 3 4 5 6 7
Initial Cost; $ 18000
O&M; $ 1000 + 15% Annual
Capital Maint.; $ 3000 4500
Book Value; $ 10000 7500 5625 1780
Interest rate 15%
Based on this information; What is the economic life of this
compressor?
Example:
PM 155
Cost Management Best Practice - Dr. Attia Gomaa - 2018
Economic Service Life
• N = 1
AEC1 = $18,000(A/P, 15%, 1) + $1,000 - $10,000
= $11,700
PM 156
Cost Management Best Practice - Dr. Attia Gomaa - 2018
• N = 2
AEC2 = [$18,000 + $1,000(P/A,15%, 15%, 2)](A/P, 15%, 2)
- $7,500 (A/F, 15%, 2)
= $8,653
PM 157
Cost Management Best Practice - Dr. Attia Gomaa - 2018
N = 3, AEC3 = $7,406
N = 4, AEC4 = $6,678
N = 5, AEC5 = $6,642
N = 6, AEC6 = $6,258
N = 7, AEC7 = $6,394
Minimum cost
Economic Service Life
PM 158
Cost Management Best Practice - Dr. Attia Gomaa - 2018
Economic Service Life for a car
Element
Life; Year
0 1 2 3 4 5 6
Initial Cost 150000
O&M 2000 first year (+500 Annual)
Capital Maintenance 10000
Book Value 120000 100000 80000 60000 80000 60000
Interest rate 15%
Based on this information; What is the economic life of this car?
Replacement Analysis:
Example :
Annual Equivalent Cost (AEC)
PM 159
Cost Management Best Practice - Dr. Attia Gomaa - 2018
ID Activity Length (m)
A Line A 400
B Line B 300
C Line C 1000
D Line D 1200
E Line E 1600
F Line F 400
G Line G 800
Resources: Crew productivity = 200 m/day Average material cost = 10 $/m
Item : Water Pipeline Network
A B
C
D
E
F
G
Source
Source
Source
Process
Process
Project Sketch
Constraints: Maximum duration = 17 day Maximum number of crew = 4
Cost : Average crew cost rate= 100 $/day Margin factor= 30% from direct cost
(Predecessor, Duration, Resources)?
(Target Schedule)?
(Target Resource Plan)?
Based on this information, discuss the following:
Project Cost Analysis
PM 160
Cost Management Best Practice - Dr. Attia Gomaa - 2018
Day
Crews
Day
Pre.
ID
17
16
15
14
13
12
11
10
9
8
7
6
5
4
3
2
1
A
B
C
D
E
F
G
Number of
Crews
(Target Schedule)
Project Constraints:
Maximum duration = 17 day Maximum number of crew = 4
PM 161
Cost Management Best Practice - Dr. Attia Gomaa - 2018
ID Name Pred.
Duration
(Day)
Number
of Crews
Material
Cost, $
A Line A - 2 2 4000
B Line B - 3 1 3000
C Line C - 5 2 10000
D Line D A,B 6 2 12000
E Line E C 8 2 16000
F Line F C 2 2 4000
G Line G D,E 4 2 8000
Item : Water Pipeline Network
Constraints: Maximum duration = 17 day Maximum number of crew = 4
Based on this information, discuss & analysis
the following:
1) Network (Logic & Risk)
2) Gantt Chart (Target Schedule)
3) Workers Profile (Target Resource Plan)
4) Cost Analysis (Target Cost Plan)
5) Cash In/ Out Analysis (Payment / Cost)
A B
C
D
E
F
G
Source
Source
Source
Process
Process
Payment Plan:
1) 25% Down Payment
2) 25% After One Week
3) 25% After Two Weeks
4) 25% Final Payment
Project Sketch
Cost : Average crew cost rate= 100 $/day Margin factor= 30% from direct cost
PM 162
Cost Management Best Practice - Dr. Attia Gomaa - 2018
Day
Crews
Day
Pre.
ID
17
16
15
14
13
12
11
10
9
8
7
6
5
4
3
2
1
2
2
2
2
-
A
1
1
1
1
3
-
B
2
2
2
2
2
2
5
-
C
2
2
2
2
2
2
2
6
A,B
D
2
2
2
2
2
2
2
2
2
8
C
E
2
2
2
2
C
F
2
2
2
2
2
4
D,E
G
2
2
2
2
4
4
4
4
4
4
4
4
3
3
3
4
4
Number of
Crews
(Target Schedule)
Project Constraints:
Maximum duration = 17 day Maximum number of crew = 4
PM 163
Cost Management Best Practice - Dr. Attia Gomaa - 2018
Day
Crews
Day
Pre.
ID
17
16
15
14
13
12
11
10
9
8
7
6
5
4
3
2
1
2
2
2
2
-
A
1
1
1
1
3
-
B
2
2
2
2
2
2
5
-
C
2
2
2
2
2
2
2
6
A,B
D
2
2
2
2
2
2
2
2
2
8
C
E
2
2
2
2
C
F
2
2
2
2
2
4
D,E
G
2
2
2
2
4
4
4
4
4
4
4
4
4
4
3
3
3
Number of
Crews
(Target Schedule)
Project Constraints:
Maximum duration = 17 day Maximum number of crew = 4
PM 164
Cost Management Best Practice - Dr. Attia Gomaa - 2018
Network Analysis: A
B
C
D
G
E
F
Start
Finish
Day
Pred.
(FS=0)
ID
2
-
A
3
-
B
5
-
C
6
A,B
D
8
C
E
2
C
F
4
D,E
G
EF
d
ES
Activity ID
LF
TF
LS
3
B
6
D
2
A
5
C
8
E
2
F
4
G
0
Start
0
Finish
PM 165
Cost Management Best Practice - Dr. Attia Gomaa - 2018
Network Analysis:
0 3 3
B
4 4 7
3 6 9
D
7 4 13
0 2 2
A
5 5 7
0 5 5
C
0 0 5
5 8 13
E
5 0 13
5 2 7
F
15 10 17
13 4 17
G
13 0 17
Planned Duration = 17 Critical Path: C-E-G
It is recommended that “Delay risk analysis” be considered for critical and near-
critical path work in the schedule because such work carries the greatest
likelihood of affecting timely completion
EF
d
ES
Activity ID
LF
TF
LS
0
Start
0
17
Finish
17
PM 166
Cost Management Best Practice - Dr. Attia Gomaa - 2018
Project Constraints:
Maximum duration = 17 day Maximum number of crew = 4
PM 167
Cost Management Best Practice - Dr. Attia Gomaa - 2018
PM 168
Cost Management Best Practice - Dr. Attia Gomaa - 2018
PM 169
Cost Management Best Practice - Dr. Attia Gomaa - 2018
Cash In/ Out Analysis
PM 170
Cost Management Best Practice - Dr. Attia Gomaa - 2018
ID Activity Pred.
Normal Crashing
Material
Cost, $
Duration
(Day)
Number of
Crews
Duration
(Day)
Number of
Crews
A Line A - 2 2 1 4 4000
B Line B - 3 1 2 2 3000
C Line C - 5 2 - - 10000
D Line D A,B 6 2 4 4 12000
E Line E C 8 2 6 3 16000
F Line F C 2 2 - - 4000
G Line G D,E 4 2 3 3 8000
Item : Water Pipeline Network
Constraints: Maximum duration = 17 day Maximum number of crew = 4
Cost : Average Crew Cost Rate = 100 $/day Margin Factor = 30% direct cost
PM 171
Cost Management Best Practice - Dr. Attia Gomaa - 2018
Day
Crews
Day
Pre.
ID
17
16
15
14
13
12
11
10
9
8
7
6
5
4
3
2
1
2
2
2
2
-
A
1
1
1
1
3
-
B
2
2
2
2
2
2
5
-
C
2
2
2
2
2
2
2
6
A,B
D
2
2
2
2
2
2
2
2
2
8
C
E
2
2
2
2
C
F
2
2
2
2
2
4
D,E
G
2
2
2
2
4
4
4
4
4
4
4
4
4
4
3
3
3
Number of
Crews
(Target Schedule)
Normal : 17 day & 57 crew-day
Project Constraints:
Maximum duration = 17 day Maximum number of crew = 4
PM 172
Cost Management Best Practice - Dr. Attia Gomaa - 2018
Day
Crews
Day
Pre.
ID
17
16
15
14
13
12
11
10
9
8
7
6
5
4
3
2
1
2
2
2
2
-
A
1
1
1
1
3
-
B
2
2
2
2
2
2
5
-
C
2
2
2
2
2
2
2
6
A,B
D
2
2
2
2
2
2
2
2
2
8
C
E
2
2
2
2
C
F
3
3
3
2
4
D,E
G
3
3
3
4
4
4
4
4
4
4
4
4
4
3
3
3
Number of
Crews
(Target Schedule)
#2 : 16 day & 58 crew-day
Project Constraints:
Maximum duration = 17 day Maximum number of crew = 4
PM 173
Cost Management Best Practice - Dr. Attia Gomaa - 2018
ID Activity Pred.
Normal Crashing
Material
Cost, $
Duration
(Day)
Number of
Crews
Duration
(Day)
Number of
Crews
A Line A - 2 2 1 4 4000
B Line B - 3 1 2 2 3000
C Line C - 5 2 - - 10000
D Line D A,B 6 2 4 4 12000
E Line E C 8 2 6 3 16000
F Line F C 2 2 - - 4000
G Line G D,E 4 2 3 3 8000
Item : Water Pipeline Network
Constraints: Maximum duration = 17 day Number of crew = Open
Cost : Average Crew Cost Rate = 100 $/day Margin Factor = 30% direct cost
PM 174
Cost Management Best Practice - Dr. Attia Gomaa - 2018
Day
Crews
Day
Pre.
ID
17
16
15
14
13
12
11
10
9
8
7
6
5
4
3
2
1
2
2
2
2
-
A
1
1
1
1
3
-
B
2
2
2
2
2
2
5
-
C
2
2
2
2
2
2
2
6
A,B
D
3
3
3
3
3
3
2
8
C
E
2
2
2
2
C
F
3
3
3
2
4
D,E
G
3
5
5
5
5
5
5
5
5
4
4
3
3
3
Number of
Crews
(Target Schedule)
#3 : 14 day & 60 crew-day
Project Constraints:
Maximum duration = 17 day Maximum number of crew = Open
PM 175
Cost Management Best Practice - Dr. Attia Gomaa - 2018
Day
Crews
Day
Pre.
ID
17
16
15
14
13
12
11
10
9
8
7
6
5
4
3
2
1
2
2
2
2
-
A
1
1
1
1
3
-
B
2
2
2
2
2
2
5
-
C
2
2
2
2
2
2
2
6
A,B
D
3
3
3
3
3
3
2
8
C
E
2
2
2
2
C
F
3
3
3
2
4
D,E
G
3
5
5
5
5
5
5
5
5
2
2
5
5
3
Number of
Crews
(Target Schedule)
#4 : 14 day & 60 crew-day
Project Constraints:
Maximum duration = 17 day Maximum number of crew = Open
PM 176
Cost Management Best Practice - Dr. Attia Gomaa - 2018
Day
Crews
Day
Pre.
ID
17
16
15
14
13
12
11
10
9
8
7
6
5
4
3
2
1
2
2
2
2
-
A
1
1
1
1
3
-
B
2
2
2
2
2
2
5
-
C
2
2
2
2
2
2
2
6
A,B
D
3
3
3
3
3
3
2
8
C
E
2
2
2
2
C
F
3
3
3
2
4
D,E
G
3
5
5
5
5
5
5
5
5
5
5
3
2
2
Number of
Crews
(Target Schedule)
#3 : 14 day & 60 crew-day
Project Constraints:
Maximum duration = 17 day Maximum number of crew = Open
PM 177
Cost Management Best Practice - Dr. Attia Gomaa - 2018
Example; Building
Direct Cost $
Predecessor
Duration (weeks)
ID
15,000
-
5
A
30,000
-
3
B
33,000
A
8
C
42,000
A
7
D
57,000
-
7
E
61,000
C, E
4
F
72,000
F
5
G
Based on this information, discuss &
analysis the following:
1) Network
2) Gantt Chart
3) Cost Analysis
4) Cost Smoothing
5) Cash Flow (In/ Out) Analysis
Payment Conditions:
1) 25% Down Payment
2) 25% After 8 Weeks
3) 25% After 16 Weeks
4) 25% Final Payment
Project Cost Analysis
Planned Duration = 22 weeks Margin Factor = 30% from direct cost
PM 178
Cost Management Best Practice - Dr. Attia Gomaa - 2018
Logic Diagram:
E
Start
Finish
A
B
D
C
F G
PM 179
Cost Management Best Practice - Dr. Attia Gomaa - 2018
Network Analysis:
5
A
0
Start
Finish
8
C
7
E
4
F
7
D
5
G
3
B
PM 180
Cost Management Best Practice - Dr. Attia Gomaa - 2018
Weeks
Pred
Day
ID
22
21
20
19
18
17
16
15
14
13
12
11
10
9
8
7
6
5
4
3
2
1
-
5
A
-
3
B
A
8
C
A
7
D
-
7
E
C, E
4
F
F
5
G
PM 181
Cost Management Best Practice - Dr. Attia Gomaa - 2018
Project Co$t Control
Cost
Control
Actual
Performance
Planned
Performance
KPIs report
(Earned Value Analysis)
PM 182
Cost Management Best Practice - Dr. Attia Gomaa - 2018
Project: Office Building
Item (main activity): Excavation works
Brainstorming: Project Control
Actual Performance (Status Report after 6 days):
Actual Quantity = 320 m3
Actual Cost = 3300 $
Planned Performance (Baseline):
Bill of Quantity (BOQ) = 500 m3
Unit Price = 10 $/m3
Duration = 10 day
Control
PM 183
Cost Management Best Practice - Dr. Attia Gomaa - 2018
Project: Office Building
Item (main activity): Excavation works
Brainstorming: Project Control
Actual Performance (Status Report after 6 days):
Actual Quantity = 320 m3
Actual Cost = 3300 $
Planned Performance (Baseline):
Bill of Quantity (BOQ) = 500 m3
Unit Cost = 10 $/m3
Duration = 10 day
Daily Performance = 500 / 10 = 50 m3/day
Control
Planned Performance after 6 days:
Panned Quantity = 50*6 = 300 m3
Planned Cost = 10*300 = 3000 $
Analysis:
Quantity Variance = 320 – 300 = + 20 Ahead
Cost Variance = 320*10 – 3300 = - 100 Over budget
PM 184
Cost Management Best Practice - Dr. Attia Gomaa - 2018
Project Cost Control
Cost control is a Part of Cost Management.
70% of projects are
over budget and/or
behind schedule
52% of all projects
finish at 189% of their
initial budget
30% of completed
projects have a cost
variance of >10%
50% of completed
projects have a
schedule variance
of >10%
(Earned Value Analysis)
(1)
(2)
(3)
(4)
PM 185
Cost Management Best Practice - Dr. Attia Gomaa - 2018
Earned Value Management (EVM)
EVM is a cost management technique where the value of completed
work is compared to actual costs and the scheduled costs
EVM is a project management tool that integrates
the project performance with schedule and cost elements.
Earned Value Management Systems measure progress
PM 186
Cost Management Best Practice - Dr. Attia Gomaa - 2018
Schedule
Variance
Cost
Variance
Schedule
Performance
Index
Cost
Performance
Index
Planned Value = PV = BCWS
(Budget Cost for the Work Schedule)  Base line
Actual Cost = AV = ACWP
(Actual Cost for the Work Performed)  Actual
Earned Value = EV = BCWP
(Budget Cost for the Work Performed)  Invoice
Earned Value Analysis
PM 187
Cost Management Best Practice - Dr. Attia Gomaa - 2018
• Schedule Variance SV = BCWP – BCWS
(>0 is ahead, 0 is on target, <0 is behind)
• Schedule Performance Index SPI = BCWP/BCWS
(>1 is ahead, 1 is on target, <1 is behind)
• Cost Variance CV = BCWP – ACWP
(>0 is under-run, 0 is on target, <0 is overrun)
• Cost Performance Index CPI = BCWP/ACWP
(>1 is under-run, 1 is on target, <1 is over-run)
Earned Value Analysis
PM 188
Cost Management Best Practice - Dr. Attia Gomaa - 2018
Project: Office Building
Item (main activity): Excavation works
Brainstorming: Project Control
Actual Performance (Status Report after 6 days):
Actual Quantity = 320 m3
Actual Cost = 3300 $
Planned Performance (Baseline):
Bill of Quantity (BOQ) = 500 m3
Unit Price = 10 $/m3
Duration = 10 day
Control
PM 189
Cost Management Best Practice - Dr. Attia Gomaa - 2018
Project: Office Building
Item (main activity): Excavation works
Brainstorming: Project Control
Actual Performance (Status Report after 6 days):
Actual Quantity = 320 m3 WP
Actual Cost = 3300 $ ACWP
Actual Cost Rate (AC) = 10.3 $/m3 AC
Planned Performance (Baseline):
Bill of Quantity (BOQ) = 500 m3 WS
Unit Price = 10 $/m3 BC
Duration = 10 day
Control
Actual Value (ACWP) = 3300 $
Planned Value (BCWS) = 3000 $
Earned Value (BCWP) = 3200 $
After 6 days:
PM 190
Cost Management Best Practice - Dr. Attia Gomaa - 2018
Project: Office Building Item: Excavation works
Brainstorming: Project Control
Actual Value (ACWP) = 3300 $
Planned Value (BCWS) = 3000 $ Control
Earned Value (BCWP) = 3200 $
• Cost variance:
• BCWP – ACWP =3200 – 3300 = -100 $ (Overrun)
• Cost Performance Index:
CPI = BCWP/ACWP = 3200/3300 =0.97 = 97%
• Schedule variance:
• BCWP – BCWS = 3200 – 3000 = +200 $ (ahead)
• Schedule Performance Index:
SPI = BCWP/BCWS = 3200/3000 =1.07 = 107%
PM 191
Cost Management Best Practice - Dr. Attia Gomaa - 2018
Project: Gas Pipeline Activity: Excavation
Bill of Quantity (BOQ) = 500 m3 Unit Price = 10 LE/m3 Duration= 10 day
Status Report after 6 day:
Actual Quantity = 320 m3 Actual Cost = 3300 LE
Example:
6 day
$
BAC = 5000
CV =
- 100
SV =
+ 200
10 day
Ahead of
schedule
•Over –run cost
•Ahead of schedule
PM 192
Cost Management Best Practice - Dr. Attia Gomaa - 2018
Project: Office Building
Item (main activity): Excavation works
Planned Performance (Baseline):
Bill of Quantity (BOQ) = 600 m3
Unit Price = 10 $/m3
Duration = 10 day
Actual Performance (Status Report after 6 days):
Actual Quantity = 300 m3
Actual Cost = 3300 $
Brainstorming: Earned Value Analysis
Based on this information, calculate and analyze the following:
a) What is the cost variance?
b) What is the Schedule variance?
c) What is the Cost Performance Index?
d) What is the Schedule Performance Index?
e) How would you describe this project?
PM 193
Cost Management Best Practice - Dr. Attia Gomaa - 2018
Project: Office Building Item: Excavation works
Brainstorming: Project Control
Actual Value (ACWP) = 3300
Planned Value (BCWS) = 3600
Earned Value (BCWP) = 3000
• Cost variance:
• BCWP – ACWP = 3000 – 3300 = -300
• Cost Performance Index:
CPI = BCWP/ACWP = 3000 / 3300 = 91% (Overrun)
• Schedule variance:
• BCWP – BCWS = 3000 – 3600 = - 600
• Schedule Performance Index:
SPI = BCWP/BCWS = 3000 / 3600 = 83% (Behind)
After 6 days:
PM 194
Cost Management Best Practice - Dr. Attia Gomaa - 2018
Project: Office Building
Item (main activity): Excavation works
Planned Performance (Baseline):
Bill of Quantity (BOQ) = 600 m3
Unit Price = 10 $/m3
Duration = 10 day
Actual Performance (Status Report after 6 days):
Actual Quantity = 300 m3
Actual Cost = 3300 $
Brainstorming: Earned Value Analysis
Based on this information, calculate and analyze the following:
a) What is the cost variance?
b) What is the Schedule variance?
c) What is the Cost Performance Index?
d) What is the Schedule Performance Index?
e) How would you describe this project?
PM 195
Cost Management Best Practice - Dr. Attia Gomaa - 2018
A construction project has a total budget (BAC) of $300,000 and the
total duration of 12 months. After 4 months, the cost control revealed
the following figures:
• Actual Cost of Work Performed (ACWP) = $ 110,000
• Budgeted Cost of Work Scheduled (BCWS) = $ 100,000
• Budgeted Cost of Work Performed (BCWP) = $ 90,000
a) Calculate the CPI and SPI
b) Calculate the Estimate At Completion (EAC) if the project will
continue to perform in the same way
c) Calculate the EAC if the project cost performance improved in the
remaining period by 10%
Example:
PM 196
Cost Management Best Practice - Dr. Attia Gomaa - 2018
A construction project has a total budget of $300,000 and the total duration of
12 months. After 4 months, the cost control revealed the following figures:
• Actual Cost of Work Performed (ACWP) = $ 110,000
• Budgeted Cost of Work Scheduled (BCWS) = $ 100,000
• Budgeted Cost of Work Performed (BCWP) = $ 90,000
a) Calculate the CPI and SPI
b) Calculate the EAC if the project will continue to perform in the same way
c) Calculate the EAC if the project cost performance improved in the
remaining period by 10%
CPI = BCWP / ACWP = 90,000 / 110,000 = 0.818 < 1 Over budget
SPI = BCWP / BCWS = 90,000 / 100,000 = 0.90 < 1 Behind schedule
Estimate At Completion (EAC) = BAC/CPI = 300000/0.818= 366,748
Improve  Corrective Actions  Improve CPI by 10%
Improve CPI by 10%  New CPI = 0.818 *1.1 = 0.8998 (Expected)
New (EAC) = AC + {(BAC – EV) / CPI}
=110,000 + (300,000 – 90,000) / 0.8998 = $ 343,385
PM 197
Cost Management Best Practice - Dr. Attia Gomaa - 2018
PM 198
Cost Management Best Practice - Dr. Attia Gomaa - 2018
A construction project has a total budget (BAC) of $300,000 and the
total duration of 12 months. After 8 months, the cost control revealed
the following figures:
• Actual Cost of Work Performed (ACWP) = $ 215,000
• Budgeted Cost of Work Scheduled (BCWS) = $ 200,000
• Budgeted Cost of Work Performed (BCWP) = $ 190,000
a) Calculate the CPI and SPI
b) Calculate the Estimate At Completion (EAC) if the project will
continue to perform in the same way
c) Calculate the EAC if the project cost performance improved in the
remaining period by 10%
Next:
PM 199
Cost Management Best Practice - Dr. Attia Gomaa - 2018
PM 200
Cost Management Best Practice - Dr. Attia Gomaa - 2018
A construction project has a total budget (BAC) of $300,000 and the
total duration of 12 months. After 8 months, the cost control revealed
the following figures:
• Actual Cost of Work Performed (ACWP) = $ 215,000
• Budgeted Cost of Work Scheduled (BCWS) = $ 200,000
• Budgeted Cost of Work Performed (BCWP) = $ 190,000
a) Calculate the CPI and SPI
b) Calculate the EAC if the project will continue to perform in the same way
c) Calculate the EAC if the project cost performance improved in the
remaining period by 10%
CPI = BCWP / ACWP = 190,000 / 215,000 = 0.884 < 1 (Overrun)
SPI = BCWP / BCWS = 190,000 / 200,000 = 0.95 < 1 (Behind)
Estimate At Completion (EAC) = BAC/CPI = 300,000/0.884 = 340,909
 Corrective Actions  Improve CPI by 10%
New CPI = 0.884 *1.1 = 0.968
New (EAC) = AC + {(BAC – EV) / CPI}
= 215,000 + (300,000 – 190,000)/0.968 = 335,743
PM 201
Cost Management Best Practice - Dr. Attia Gomaa - 2018
A construction project has a total budget (BAC) of $300,000 and the
total duration of 12 months. After 13 months (closeout), the cost control
revealed the following figures:
• Actual Cost of Work Performed (ACWP) = $ 340,000
• Budgeted Cost of Work Scheduled (BCWS) = $ 300,000
• Budgeted Cost of Work Performed (BCWP) = $ 310,000
a) Calculate the CPI and SPI
CPI = BCWP / ACWP = 310,000 / 340,000 = 0.912 < 1 (overrun by 8.8%)
SPI = BCWP / BCWS = 310,000 / 300,000 = 1.03 > 1 (Ahead by 3%)
Closing:
PM 202
Cost Management Best Practice - Dr. Attia Gomaa - 2018
Summary Report:
A construction project has a total budget (BAC) of $300,000 and the
total duration of 12 months.
Period (months) 4 8 13
Planned Value (PV = BCWS) 100,000 200,000 300,000
Actual Value (AV = ACWP) 110,000 215,000 340,000
Earned Value (EV =BCWP) 90,000 190,000 310,000
CPI = BCWP / ACWP
SPI = BCWP / BCWS
Estimate At Completion (EAC)
= BAC/CPI
PM 203
Cost Management Best Practice - Dr. Attia Gomaa - 2018
Period #1 #2 #3 #4 #5 #6 #7 #8 #9 #10
BAC $1,230 $1,230 $1,230 $1,230 $1,400 $1,400 $1,400 $1,400 $1,400 $1,400
EV $100 $200 $300 $450 $750 $800 $1,125 $1,200 $1,400 $1,400
AC $100 $205 $315 $600 $800 $1,000 $1,200 $1,350 $1,475 $1,525
PV $100 $220 $325 $550 $725 $925 $1,175 $1,275 $1,450 $1,500
Period #1 #2 #3 #4 #5 #6 #7 #8 #9 #10
CV $0 ($5) ($15) ($150) ($50) ($200) ($75) ($150) ($75) ($125)
SV $0 ($20) ($25) ($100) $25 ($125) ($50) ($75) ($50) ($100)
CPI 1.00 0.98 0.95 0.75 0.94 0.80 0.94 0.89 0.95 0.92
SPI 1.00 0.91 0.92 0.82 1.03 0.86 0.96 0.94 0.97 0.93
ETC $1,130 $1,056 $977 $1,040 $693 $750 $293 $225 $0 $0
EAC $1,230 $1,261 $1,292 $1,640 $1,493 $1,750 $1,493 $1,575 $1,475 $1,525
VAC $0 ($31) ($62) ($410) ($93) ($350) ($93) ($175) ($75) ($125)
Excel File:
($1000)
Analysis:
PM 204
Cost Management Best Practice - Dr. Attia Gomaa - 2018
PM 205
Cost Management Best Practice - Dr. Attia Gomaa - 2018
PM 206
Cost Management Best Practice - Dr. Attia Gomaa - 2018
PM 207
Cost Management Best Practice - Dr. Attia Gomaa - 2018
PM 208
Cost Management Best Practice - Dr. Attia Gomaa - 2018
BCWS
ACWP
BCWP
Late
Item
Planned
Value
(BCWS)
Actual
Cost
(ACWP)
Earned
Value
(BCWP)
#1 3000000 3080000 2800000
#2 250000 210000 175000
#3 500000 468000 520000
#4 100000 88000 80000
Item BCWS ACWP BCWP SV SPI CV CPI
Comments
Schedule Cost
#1 3000000 3080000 2800000 -200000 0.93 -280000 0.91 Behind 7% Over run 9%
#2 250000 210000 175000 -75000 0.70 -35000 0.83 Behind 30% Over run 17%
#3 500000 468000 520000 20000 1.04 52000 1.11 Ahead 4% Under run 11%
#4 100000 88000 80000 -20000 0.80 -8000 0.91 Behind 20% Over run 9%
Total 3850000 3846000 3575000 -275000 0.93 -271000 0.93 Behind 7% Over run 7%
EVM Report:
Project: A Construction Project
PM 209
Cost Management Best Practice - Dr. Attia Gomaa - 2018
PM 210
Cost Management Best Practice - Dr. Attia Gomaa - 2018
√
X
PM 211
Cost Management Best Practice - Dr. Attia Gomaa - 2018
PM 212
Cost Management Best Practice - Dr. Attia Gomaa - 2018
Activity
ID
Planned
Cost
Planned Date Actual
Performance at
period #10
Start Finish
A 4000 1 4 Completed
B 10000 3 6 Completed
C 12000 6 9 In Progress
D 4000 9 12 In Progress
G 6000 9 12 Not Started
H 6000 11 14 Not Started
I 10000 14 17 Not Started
Project Status Report:
Case Study:
Based on this information; discuss the earned value analysis using the
50-50 rule?
_VIP_Cost Management -20-10-2018.pdf
_VIP_Cost Management -20-10-2018.pdf
_VIP_Cost Management -20-10-2018.pdf
_VIP_Cost Management -20-10-2018.pdf
_VIP_Cost Management -20-10-2018.pdf
_VIP_Cost Management -20-10-2018.pdf
_VIP_Cost Management -20-10-2018.pdf
_VIP_Cost Management -20-10-2018.pdf
_VIP_Cost Management -20-10-2018.pdf
_VIP_Cost Management -20-10-2018.pdf
_VIP_Cost Management -20-10-2018.pdf
_VIP_Cost Management -20-10-2018.pdf
_VIP_Cost Management -20-10-2018.pdf
_VIP_Cost Management -20-10-2018.pdf
_VIP_Cost Management -20-10-2018.pdf
_VIP_Cost Management -20-10-2018.pdf

More Related Content

Similar to _VIP_Cost Management -20-10-2018.pdf

Chapter 3 JIT, Value Added and Waste .docx
Chapter 3 JIT, Value Added and Waste            .docxChapter 3 JIT, Value Added and Waste            .docx
Chapter 3 JIT, Value Added and Waste .docx
adkinspaige22
 
Telecom product cost models development approach
Telecom product cost models development approachTelecom product cost models development approach
Telecom product cost models development approach
Parcus Group
 
Project Management C8 -cost_estimation_and_budgeting
Project Management C8  -cost_estimation_and_budgetingProject Management C8  -cost_estimation_and_budgeting
Project Management C8 -cost_estimation_and_budgeting
Izah Asmadi
 
IRJET- Value Analysis Aimed at Cost Reduction in Wooden Bed Manufacturing
IRJET- Value Analysis Aimed at Cost Reduction in Wooden Bed ManufacturingIRJET- Value Analysis Aimed at Cost Reduction in Wooden Bed Manufacturing
IRJET- Value Analysis Aimed at Cost Reduction in Wooden Bed Manufacturing
IRJET Journal
 
Byron Pang (LinkedIn- Oct 2014)
Byron Pang (LinkedIn- Oct 2014)Byron Pang (LinkedIn- Oct 2014)
Byron Pang (LinkedIn- Oct 2014)
Byron Pang
 
5 costestimation-110716160453-phpapp01
5 costestimation-110716160453-phpapp015 costestimation-110716160453-phpapp01
5 costestimation-110716160453-phpapp01
hlksd
 
Project cost stimating
Project cost stimatingProject cost stimating
Project cost stimating
hatim ahmed
 
Concept of Value Engineering with Case Study
Concept of Value Engineering with Case StudyConcept of Value Engineering with Case Study
Concept of Value Engineering with Case Study
Aditya Deshpande
 
Introduction to Engineering Economics Unit I MG6863
Introduction to Engineering Economics  Unit I MG6863Introduction to Engineering Economics  Unit I MG6863
Introduction to Engineering Economics Unit I MG6863
Balamurugan Subburaj
 
CV_Pooranpr
CV_PooranprCV_Pooranpr
CV_Pooranpr
Pooran Shahani
 
Lean Six Sigma project Caponera
Lean Six Sigma project CaponeraLean Six Sigma project Caponera
Lean Six Sigma project Caponera
Annalisa Caponera
 
IIRJET-Cost Control Techniques for Construction Project
IIRJET-Cost Control Techniques for Construction ProjectIIRJET-Cost Control Techniques for Construction Project
IIRJET-Cost Control Techniques for Construction Project
IRJET Journal
 
CV_Pooranpr
CV_PooranprCV_Pooranpr
CV_Pooranpr
Pooran Shahani
 
IFPRI - PME Manual - Indicators and Processes- Mruthyunjaya
IFPRI - PME Manual - Indicators and Processes- MruthyunjayaIFPRI - PME Manual - Indicators and Processes- Mruthyunjaya
IFPRI - PME Manual - Indicators and Processes- Mruthyunjaya
International Food Policy Research Institute- South Asia Office
 
Eng econ lecture
Eng econ lectureEng econ lecture
Eng econ lecture
Arul Kumar
 
IRJET- Evaluation of Rework Factors Affecting Cost and Schedule Performance i...
IRJET- Evaluation of Rework Factors Affecting Cost and Schedule Performance i...IRJET- Evaluation of Rework Factors Affecting Cost and Schedule Performance i...
IRJET- Evaluation of Rework Factors Affecting Cost and Schedule Performance i...
IRJET Journal
 
Asia NOC Bridges Business-wide Performance Objectives and KPIs through an Adv...
Asia NOC Bridges Business-wide Performance Objectives and KPIs through an Adv...Asia NOC Bridges Business-wide Performance Objectives and KPIs through an Adv...
Asia NOC Bridges Business-wide Performance Objectives and KPIs through an Adv...
Yokogawa1
 
Cost managment
Cost managmentCost managment
Cost managment
Hassan Sardar
 
Damon 2016 nov 15
Damon 2016 nov 15Damon 2016 nov 15
Damon 2016 nov 15
Damon Chan
 
Triple/S Dynamics Presentation - Belt Conveyor vs. Horizontal Motion Conveyor
Triple/S Dynamics Presentation - Belt Conveyor vs. Horizontal Motion ConveyorTriple/S Dynamics Presentation - Belt Conveyor vs. Horizontal Motion Conveyor
Triple/S Dynamics Presentation - Belt Conveyor vs. Horizontal Motion Conveyor
Grand View Media
 

Similar to _VIP_Cost Management -20-10-2018.pdf (20)

Chapter 3 JIT, Value Added and Waste .docx
Chapter 3 JIT, Value Added and Waste            .docxChapter 3 JIT, Value Added and Waste            .docx
Chapter 3 JIT, Value Added and Waste .docx
 
Telecom product cost models development approach
Telecom product cost models development approachTelecom product cost models development approach
Telecom product cost models development approach
 
Project Management C8 -cost_estimation_and_budgeting
Project Management C8  -cost_estimation_and_budgetingProject Management C8  -cost_estimation_and_budgeting
Project Management C8 -cost_estimation_and_budgeting
 
IRJET- Value Analysis Aimed at Cost Reduction in Wooden Bed Manufacturing
IRJET- Value Analysis Aimed at Cost Reduction in Wooden Bed ManufacturingIRJET- Value Analysis Aimed at Cost Reduction in Wooden Bed Manufacturing
IRJET- Value Analysis Aimed at Cost Reduction in Wooden Bed Manufacturing
 
Byron Pang (LinkedIn- Oct 2014)
Byron Pang (LinkedIn- Oct 2014)Byron Pang (LinkedIn- Oct 2014)
Byron Pang (LinkedIn- Oct 2014)
 
5 costestimation-110716160453-phpapp01
5 costestimation-110716160453-phpapp015 costestimation-110716160453-phpapp01
5 costestimation-110716160453-phpapp01
 
Project cost stimating
Project cost stimatingProject cost stimating
Project cost stimating
 
Concept of Value Engineering with Case Study
Concept of Value Engineering with Case StudyConcept of Value Engineering with Case Study
Concept of Value Engineering with Case Study
 
Introduction to Engineering Economics Unit I MG6863
Introduction to Engineering Economics  Unit I MG6863Introduction to Engineering Economics  Unit I MG6863
Introduction to Engineering Economics Unit I MG6863
 
CV_Pooranpr
CV_PooranprCV_Pooranpr
CV_Pooranpr
 
Lean Six Sigma project Caponera
Lean Six Sigma project CaponeraLean Six Sigma project Caponera
Lean Six Sigma project Caponera
 
IIRJET-Cost Control Techniques for Construction Project
IIRJET-Cost Control Techniques for Construction ProjectIIRJET-Cost Control Techniques for Construction Project
IIRJET-Cost Control Techniques for Construction Project
 
CV_Pooranpr
CV_PooranprCV_Pooranpr
CV_Pooranpr
 
IFPRI - PME Manual - Indicators and Processes- Mruthyunjaya
IFPRI - PME Manual - Indicators and Processes- MruthyunjayaIFPRI - PME Manual - Indicators and Processes- Mruthyunjaya
IFPRI - PME Manual - Indicators and Processes- Mruthyunjaya
 
Eng econ lecture
Eng econ lectureEng econ lecture
Eng econ lecture
 
IRJET- Evaluation of Rework Factors Affecting Cost and Schedule Performance i...
IRJET- Evaluation of Rework Factors Affecting Cost and Schedule Performance i...IRJET- Evaluation of Rework Factors Affecting Cost and Schedule Performance i...
IRJET- Evaluation of Rework Factors Affecting Cost and Schedule Performance i...
 
Asia NOC Bridges Business-wide Performance Objectives and KPIs through an Adv...
Asia NOC Bridges Business-wide Performance Objectives and KPIs through an Adv...Asia NOC Bridges Business-wide Performance Objectives and KPIs through an Adv...
Asia NOC Bridges Business-wide Performance Objectives and KPIs through an Adv...
 
Cost managment
Cost managmentCost managment
Cost managment
 
Damon 2016 nov 15
Damon 2016 nov 15Damon 2016 nov 15
Damon 2016 nov 15
 
Triple/S Dynamics Presentation - Belt Conveyor vs. Horizontal Motion Conveyor
Triple/S Dynamics Presentation - Belt Conveyor vs. Horizontal Motion ConveyorTriple/S Dynamics Presentation - Belt Conveyor vs. Horizontal Motion Conveyor
Triple/S Dynamics Presentation - Belt Conveyor vs. Horizontal Motion Conveyor
 

Recently uploaded

原版制作(Humboldt毕业证书)柏林大学毕业证学位证一模一样
原版制作(Humboldt毕业证书)柏林大学毕业证学位证一模一样原版制作(Humboldt毕业证书)柏林大学毕业证学位证一模一样
原版制作(Humboldt毕业证书)柏林大学毕业证学位证一模一样
ydzowc
 
Applications of artificial Intelligence in Mechanical Engineering.pdf
Applications of artificial Intelligence in Mechanical Engineering.pdfApplications of artificial Intelligence in Mechanical Engineering.pdf
Applications of artificial Intelligence in Mechanical Engineering.pdf
Atif Razi
 
An Introduction to the Compiler Designss
An Introduction to the Compiler DesignssAn Introduction to the Compiler Designss
An Introduction to the Compiler Designss
ElakkiaU
 
一比一原版(uoft毕业证书)加拿大多伦多大学毕业证如何办理
一比一原版(uoft毕业证书)加拿大多伦多大学毕业证如何办理一比一原版(uoft毕业证书)加拿大多伦多大学毕业证如何办理
一比一原版(uoft毕业证书)加拿大多伦多大学毕业证如何办理
sydezfe
 
OOPS_Lab_Manual - programs using C++ programming language
OOPS_Lab_Manual - programs using C++ programming languageOOPS_Lab_Manual - programs using C++ programming language
OOPS_Lab_Manual - programs using C++ programming language
PreethaV16
 
Open Channel Flow: fluid flow with a free surface
Open Channel Flow: fluid flow with a free surfaceOpen Channel Flow: fluid flow with a free surface
Open Channel Flow: fluid flow with a free surface
Indrajeet sahu
 
SCALING OF MOS CIRCUITS m .pptx
SCALING OF MOS CIRCUITS m                 .pptxSCALING OF MOS CIRCUITS m                 .pptx
SCALING OF MOS CIRCUITS m .pptx
harshapolam10
 
一比一原版(爱大毕业证书)爱荷华大学毕业证如何办理
一比一原版(爱大毕业证书)爱荷华大学毕业证如何办理一比一原版(爱大毕业证书)爱荷华大学毕业证如何办理
一比一原版(爱大毕业证书)爱荷华大学毕业证如何办理
nedcocy
 
Mechatronics material . Mechanical engineering
Mechatronics material . Mechanical engineeringMechatronics material . Mechanical engineering
Mechatronics material . Mechanical engineering
sachin chaurasia
 
Mechanical Engineering on AAI Summer Training Report-003.pdf
Mechanical Engineering on AAI Summer Training Report-003.pdfMechanical Engineering on AAI Summer Training Report-003.pdf
Mechanical Engineering on AAI Summer Training Report-003.pdf
21UME003TUSHARDEB
 
TIME TABLE MANAGEMENT SYSTEM testing.pptx
TIME TABLE MANAGEMENT SYSTEM testing.pptxTIME TABLE MANAGEMENT SYSTEM testing.pptx
TIME TABLE MANAGEMENT SYSTEM testing.pptx
CVCSOfficial
 
Software Engineering and Project Management - Software Testing + Agile Method...
Software Engineering and Project Management - Software Testing + Agile Method...Software Engineering and Project Management - Software Testing + Agile Method...
Software Engineering and Project Management - Software Testing + Agile Method...
Prakhyath Rai
 
Object Oriented Analysis and Design - OOAD
Object Oriented Analysis and Design - OOADObject Oriented Analysis and Design - OOAD
Object Oriented Analysis and Design - OOAD
PreethaV16
 
Transformers design and coooling methods
Transformers design and coooling methodsTransformers design and coooling methods
Transformers design and coooling methods
Roger Rozario
 
Height and depth gauge linear metrology.pdf
Height and depth gauge linear metrology.pdfHeight and depth gauge linear metrology.pdf
Height and depth gauge linear metrology.pdf
q30122000
 
Data Driven Maintenance | UReason Webinar
Data Driven Maintenance | UReason WebinarData Driven Maintenance | UReason Webinar
Data Driven Maintenance | UReason Webinar
UReason
 
一比一原版(USF毕业证)旧金山大学毕业证如何办理
一比一原版(USF毕业证)旧金山大学毕业证如何办理一比一原版(USF毕业证)旧金山大学毕业证如何办理
一比一原版(USF毕业证)旧金山大学毕业证如何办理
uqyfuc
 
Call For Paper -3rd International Conference on Artificial Intelligence Advan...
Call For Paper -3rd International Conference on Artificial Intelligence Advan...Call For Paper -3rd International Conference on Artificial Intelligence Advan...
Call For Paper -3rd International Conference on Artificial Intelligence Advan...
ijseajournal
 
Supermarket Management System Project Report.pdf
Supermarket Management System Project Report.pdfSupermarket Management System Project Report.pdf
Supermarket Management System Project Report.pdf
Kamal Acharya
 
4. Mosca vol I -Fisica-Tipler-5ta-Edicion-Vol-1.pdf
4. Mosca vol I -Fisica-Tipler-5ta-Edicion-Vol-1.pdf4. Mosca vol I -Fisica-Tipler-5ta-Edicion-Vol-1.pdf
4. Mosca vol I -Fisica-Tipler-5ta-Edicion-Vol-1.pdf
Gino153088
 

Recently uploaded (20)

原版制作(Humboldt毕业证书)柏林大学毕业证学位证一模一样
原版制作(Humboldt毕业证书)柏林大学毕业证学位证一模一样原版制作(Humboldt毕业证书)柏林大学毕业证学位证一模一样
原版制作(Humboldt毕业证书)柏林大学毕业证学位证一模一样
 
Applications of artificial Intelligence in Mechanical Engineering.pdf
Applications of artificial Intelligence in Mechanical Engineering.pdfApplications of artificial Intelligence in Mechanical Engineering.pdf
Applications of artificial Intelligence in Mechanical Engineering.pdf
 
An Introduction to the Compiler Designss
An Introduction to the Compiler DesignssAn Introduction to the Compiler Designss
An Introduction to the Compiler Designss
 
一比一原版(uoft毕业证书)加拿大多伦多大学毕业证如何办理
一比一原版(uoft毕业证书)加拿大多伦多大学毕业证如何办理一比一原版(uoft毕业证书)加拿大多伦多大学毕业证如何办理
一比一原版(uoft毕业证书)加拿大多伦多大学毕业证如何办理
 
OOPS_Lab_Manual - programs using C++ programming language
OOPS_Lab_Manual - programs using C++ programming languageOOPS_Lab_Manual - programs using C++ programming language
OOPS_Lab_Manual - programs using C++ programming language
 
Open Channel Flow: fluid flow with a free surface
Open Channel Flow: fluid flow with a free surfaceOpen Channel Flow: fluid flow with a free surface
Open Channel Flow: fluid flow with a free surface
 
SCALING OF MOS CIRCUITS m .pptx
SCALING OF MOS CIRCUITS m                 .pptxSCALING OF MOS CIRCUITS m                 .pptx
SCALING OF MOS CIRCUITS m .pptx
 
一比一原版(爱大毕业证书)爱荷华大学毕业证如何办理
一比一原版(爱大毕业证书)爱荷华大学毕业证如何办理一比一原版(爱大毕业证书)爱荷华大学毕业证如何办理
一比一原版(爱大毕业证书)爱荷华大学毕业证如何办理
 
Mechatronics material . Mechanical engineering
Mechatronics material . Mechanical engineeringMechatronics material . Mechanical engineering
Mechatronics material . Mechanical engineering
 
Mechanical Engineering on AAI Summer Training Report-003.pdf
Mechanical Engineering on AAI Summer Training Report-003.pdfMechanical Engineering on AAI Summer Training Report-003.pdf
Mechanical Engineering on AAI Summer Training Report-003.pdf
 
TIME TABLE MANAGEMENT SYSTEM testing.pptx
TIME TABLE MANAGEMENT SYSTEM testing.pptxTIME TABLE MANAGEMENT SYSTEM testing.pptx
TIME TABLE MANAGEMENT SYSTEM testing.pptx
 
Software Engineering and Project Management - Software Testing + Agile Method...
Software Engineering and Project Management - Software Testing + Agile Method...Software Engineering and Project Management - Software Testing + Agile Method...
Software Engineering and Project Management - Software Testing + Agile Method...
 
Object Oriented Analysis and Design - OOAD
Object Oriented Analysis and Design - OOADObject Oriented Analysis and Design - OOAD
Object Oriented Analysis and Design - OOAD
 
Transformers design and coooling methods
Transformers design and coooling methodsTransformers design and coooling methods
Transformers design and coooling methods
 
Height and depth gauge linear metrology.pdf
Height and depth gauge linear metrology.pdfHeight and depth gauge linear metrology.pdf
Height and depth gauge linear metrology.pdf
 
Data Driven Maintenance | UReason Webinar
Data Driven Maintenance | UReason WebinarData Driven Maintenance | UReason Webinar
Data Driven Maintenance | UReason Webinar
 
一比一原版(USF毕业证)旧金山大学毕业证如何办理
一比一原版(USF毕业证)旧金山大学毕业证如何办理一比一原版(USF毕业证)旧金山大学毕业证如何办理
一比一原版(USF毕业证)旧金山大学毕业证如何办理
 
Call For Paper -3rd International Conference on Artificial Intelligence Advan...
Call For Paper -3rd International Conference on Artificial Intelligence Advan...Call For Paper -3rd International Conference on Artificial Intelligence Advan...
Call For Paper -3rd International Conference on Artificial Intelligence Advan...
 
Supermarket Management System Project Report.pdf
Supermarket Management System Project Report.pdfSupermarket Management System Project Report.pdf
Supermarket Management System Project Report.pdf
 
4. Mosca vol I -Fisica-Tipler-5ta-Edicion-Vol-1.pdf
4. Mosca vol I -Fisica-Tipler-5ta-Edicion-Vol-1.pdf4. Mosca vol I -Fisica-Tipler-5ta-Edicion-Vol-1.pdf
4. Mosca vol I -Fisica-Tipler-5ta-Edicion-Vol-1.pdf
 

_VIP_Cost Management -20-10-2018.pdf

  • 1. PM ‫باهلل‬ ‫إال‬ ‫توفيقي‬ ‫وما‬ Cost Management (Planning , Control & Improvements) Dr. Attia Gomaa Industrial Engineering Professor & Consultant Mechanical Eng. Department – Shoubra Faculty of Eng. - Benha University & Engineering and Science Services - American University in Cairo Facebook: Attia Gomaa & Group: Project Management - Dr Attia Gomaa October 2018
  • 2. PM 2 Cost Management Best Practice - Dr. Attia Gomaa - 2018 Course Contents: 1. Cost Management 2. Cost Estimation 3. Cost Analysis 4. Cash Flow Analysis 5. Financial Analysis 6. Project Cost Analysis 7. Project Cost Control 8. Case Studies Cost Management (Planning , Control & Improvements)
  • 3. PM 3 Cost Management Best Practice - Dr. Attia Gomaa - 2018 Rules of the Course This is an Open Discussion Course: Team Approach Remember … You can’t do it alone! Let us be a teamwork. – Share Knowledge – Share Experiences – Share Best Practices – Share Questions – ‫المعرفة‬ ‫تبادل‬ – ‫الخبرات‬ ‫تبادل‬ – ‫الجيدة‬ ‫التجارب‬ ‫تبادل‬ – ‫األسئلة‬ ‫تبادل‬
  • 4. PM 4 Cost Management Best Practice - Dr. Attia Gomaa - 2018 Project Triple Constraints:
  • 5. PM 5 Cost Management Best Practice - Dr. Attia Gomaa - 2018 1) Material 2) Machine 3) Manpower 4) Method 5) Money (Cost) Resources Analysis (5 M’s): Project Constraints: 1. Scope of Work (Specs) 2. Quality (Service Quality) 3. Time (Schedule) 4. Cost (Budget)
  • 6. PM 6 Cost Management Best Practice - Dr. Attia Gomaa - 2018 Cost Management (1) Resource Planning (2) Cost Estimation (3) Cost Budgeting (4) Cost Control Cost Planning (5) Cost Forecasting 2017 2018 2019
  • 7. PM 7 Cost Management Best Practice - Dr. Attia Gomaa - 2018 • Resource planning: determining what resources and quantities of them should be used. • Cost estimating: developing an estimate of the costs and resources needed to complete a project. • Cost budgeting: allocating the overall cost estimate to individual work items to establish a baseline for measuring performance. • Cost control: controlling changes to the project budget. COST MANAGEMENT - Definitions
  • 8. PM 8 Cost Management Best Practice - Dr. Attia Gomaa - 2018 (1) Resource Planning (2) Cost Estimating 1. Work breakdown structure (WBS) 2. Main activities 3. Resource allocation 4. Resource limits (constraints) 5. Resource requirements 6. Cost rates 7. Cost estimation 8. Cost analysis (3) Cost Budgeting (4) Cost Control 9. Cost baseline 10.Cash in / cash out 11.Budget plan 12.Budget limits (constraints) 13.Planned performance 14.Actual performance 15.Change requests 16.Performance reports Source: PMBOK Standard Cost Management
  • 9. PM 9 Cost Management Best Practice - Dr. Attia Gomaa - 2018 Discuss briefly the resource estimation sheet for the following item: • Project scope of Work: Office Building (250 m2 * 5 floors) • Main Item: Plain Concerete • Activity: Concrete Casting For Foundation (250 kg/cm2) • BOQ: 300 m3 Duration: 3 day Resource Estimation: • Resource Allocation (Standard Information): Materials Rates:  Cement = 0.4 ton/m3 700 LE/ton  Sand = 0.5 m3/m3 30 LE/m3  Gravel = 0.8 m3/m3 90 LE/m3  Water = 160 liter/m3 0.1 LE/liter Labor Rates:  Concrete Crew = 5 man/day 80 LE/man-day  Carpenter Crew = 3 man/day 90 LE/man-day Equipment Rates:  Mixer =1 Eq./day 250 LE/day  Loader =1 Eq./day 200 LE/day Margin Factor = Overhead + Profit = 50% Direct Cost
  • 10. PM 10 Cost Management Best Practice - Dr. Attia Gomaa - 2018 Activity ID Activity Description BOQ (units) Dur. Day Resource Type Resource Name Resource Units Resource Quantity Resource Price/unit Item Cost LE C250 Concrete Casting For Foundation (strength 250 kg/cm2) by Concrete Mixer 300 m3 3 day Materials Cement 0.4 ton/m3 120 ton 700 LE/ton 84000 114900 Sand 0.5 m3/m3 150 m3 30 LE/m3 4500 Gravel 0.8 m3/m3 240 m3 90 LE/m3 21600 Water 160 liter/m3 48000 liter 0.1 LE/liter 4800 Labor Concrete Crew 5 man/day 15 man-day 80 LE/man-d 1200 2010 Carpenter Crew 3 man/day 9 man-day 90 LE/man-d 810 Equipment Mixer 1 Eq./day 3 Eq.-day 250 LE/day 750 1350 Loader 1 Eq./day 3 Eq.-day 200 LE/day 600 Total Direct Cost = 118,260 Margin Factor = Overhead + Profit = 50% Direct Cost 59,130 Total Income (LE) 177,390 Unit Price (LE/m3) 591 Project scope of Work: Office Building (250 m2 * 5 floors) Main Item: Foundation Activity Resource Estimation Sheet:
  • 11. PM 11 Cost Management Best Practice - Dr. Attia Gomaa - 2018 Activity ID Activity Description BOQ (units) Dur. Day Resource Type Resource Name Resource Units Resource Quantity Resource Price/unit Item Cost LE C250 Concrete Casting For Foundation (strength 250 kg/cm2) by Concrete Mixer 300 m3 3 day Materials Cement 0.4 ton/m3 120 ton 700 LE/ton 84000 114900 Sand 0.5 m3/m3 150 m3 30 LE/m3 4500 Gravel 0.8 m3/m3 240 m3 90 LE/m3 21600 Water 160 liter/m3 48000 liter 0.1 LE/liter 4800 Labor Concrete Crew 5 man/day 15 man-day 80 LE/man-d 1200 2010 Carpenter Crew 3 man/day 9 man-day 90 LE/man-d 810 Equipment Mixer 1 Eq./day 3 Eq.-day 250 LE/day 750 1350 Loader 1 Eq./day 3 Eq.-day 200 LE/day 600 Total Direct Cost = 118,260 Margin Factor = Overhead + Profit = 50% Direct Cost 59,130 Total Income (LE) 177,390 Unit Price (LE/m3) 591 Project scope of Work: Office Building (250 m2 * 5 floors) Main Item: Foundation Activity Resource Estimation Sheet: ID Item Name Cost Duration Responsibility C250 Plain Concrete 118260 LE 3 Days Eng. Attia Gomaa
  • 12. PM 12 Cost Management Best Practice - Dr. Attia Gomaa - 2018 Cost Tracking Schedule Responsibility Quality QA/QC WBS Work Breakdown Structure (WBS) For example; MIS Project for Resource Planning 20% 27% 53% 100% 37% 100% 41% 22% Project Main Items
  • 13. PM 13 Cost Management Best Practice - Dr. Attia Gomaa - 2018 Work Breakdown Structure (WBS) Requirements Design Resource Module Cost Module Resource Module Cost Module For example; MIS Project for Resource Planning
  • 14. PM 14 Cost Management Best Practice - Dr. Attia Gomaa - 2018 Project: Computer Lab 30 Users Work Breakdown Structure (WBS) Client: AUC WBS - LAB Electrical Works Mechanical Works Civil Works IT Works Finishing
  • 15. PM 15 Cost Management Best Practice - Dr. Attia Gomaa - 2018 Cost Breakdown Structure Unit Profit - (-%) Labour Cost - (-%) Machine Cost - (- %) Office Overhead - (-%) Overhead - (-%) Technical Cost - (-%) Unit Price - $/unit Unit Cost - (100%) Critical Resources Technical Direct Cost - (-%) Materials Cost - (- %) Technical Overhead - (-%) Base
  • 16. PM 16 Cost Management Best Practice - Dr. Attia Gomaa - 2018 The cost classification matrix for a project (First year 2016) is as follows: Unit Price = 300 $/unit (Market Price) Planned Capacity = 100,000 units/year Case Study: Cost Elements Total Cost 1,000,000 $ Direct Costs Raw Materials 10 Technical labors 5 Equipment & Tools 10 Overheads Technical Overhead 2 Office Overhead 1 Total 1,000,000 $ 28 Based on this information, discuss briefly the Cost Breakdown Structure
  • 17. PM 17 Cost Management Best Practice - Dr. Attia Gomaa - 2018 Cost Breakdown Structure Total Profit 2 (7.1 %) Labour Cost 10 (35.7%) Machine Cost 5 (17.8 %) Office Overhead 1 (3.5%) Overhead 3 (10.7%) Factory Cost 27 (96.4%) Total Price 30 M$ Total Cost 28 (100%) Critical Resources Technical Direct Cost 25 (89.2%) Materials Cost 10 (35.7 %) Technical Overhead 2 (7.1 %) Base Annual Level Planned Capacity = 100,000 units/year
  • 18. PM 18 Cost Management Best Practice - Dr. Attia Gomaa - 2018 Cost Breakdown Structure Unit Profit 20 (7.1 %) Labour Cost 100 (35.7%) Machine Cost 50 (17.8 %) Office Overhead 10 (3.5%) Overhead 30 (10.7%) Factory Cost 270 (96.4%) Unit Price 300 $/unit Unit Cost 280 (100%) Critical Resources Technical Direct Cost 250 (89.2%) Materials Cost 100 (35.7 %) Technical Overhead 20 (7.1 %) Base Unit Level Planned Capacity = 100,000 units/year Price Policy: Target Price = 300 $/unit Worst Price = 270 $/unit
  • 19. PM 19 Cost Management Best Practice - Dr. Attia Gomaa - 2018 • Planned Cost • Actual Cost • Variance Analysis Each Indicator: • Value ($) • Ratio (%) • Factor Profit Ratio Value Added Margin Factor Markup Factor Breakeven Point Cost Analysis Main Indicators: - Profit = Price - Cost  Total Productivity - Value Added Factor = Price / Mat. Cost  Material Productivity - Margin Factor = Price / Direct Cost  Direct Resource Productivity - Markup Factor = Price /Factory Cost  Factory Productivity - Breakeven Point = F / (p-v)  Margin of Safety
  • 20. PM 20 Cost Management Best Practice - Dr. Attia Gomaa - 2018 Price TC Profit Total Cost Value Added 1.5 to 2.5  2.0 External Resource Cost Margin Factor 1.3 to 1.7  1.5 Direct Cost Markup Factor 1.2 to 1.3  1.25 Factory Cost Or Site Cost Contribution Margin 1.4 to 1.6  1.5 Variable Cost Cost Analysis
  • 21. PM 21 Cost Management Best Practice - Dr. Attia Gomaa - 2018 Price Structure Analysis: (Cost KPIs - Objectives) Contract Price Margin = Price - Direct Direct Cost Total Cost = Direct Cost + Overhead Profit Value Added = Price - Outsource Outsource Cost or rough cut estimation by using the value added or rough cut estimation by using the margin factor or rough cut estimation by using the markup factor Markup (Cost Plus) = Office O/h + Profit Labor Mat. Jobsite OH Subs Equip Factory Cost = Direct + Tech. O/h For same scope of work For different scope of work For Cost Plus Contract
  • 22. PM 22 Cost Management Best Practice - Dr. Attia Gomaa - 2018 The project cost information is as follows: • Project : Office Building 10 Floors • Bill of Quantity (BOQ): 6000 m2 ---------------- • Direct Material Cost: 18,000,000 LE • Direct Machine Cost: 6,000,000 LE • Direct Labor Cost: 6,000,000 LE ---------------- • Site Overhead 3,000,000 LE • Office Overhead: 1,500,000 LE • Unit Price: 7,000 LE/m2 Based on this information, discuss briefly the Cost Breakdown Structure Case Study: Actual Cost (2018) Inflation Rate 15% Annually Cost Estimation (2019 , 2020)
  • 23. PM 23 Cost Management Best Practice - Dr. Attia Gomaa - 2018 Cost Breakdown Structure Total Profit 7.5 (21.7%) Labour Cost 6 (17.4%) Machine Cost 6 (17.4 %) Office Overhead 1.5 (4.3%) Overhead 4.5 (13.0%) Site Cost 33 (95.6%) Total Price 42 M.LE Total Cost 34.5 (100%) Critical Resources Technical Direct Cost 30 (86.9%) Materials Cost 18 (52.2 %) Site Overhead 3 (8.6%) Base Project Level Actual Cost (2018)
  • 24. PM 24 Cost Management Best Practice - Dr. Attia Gomaa - 2018 Cost Breakdown Structure Unit Profit 1250 (21.7%) Labour Cost 1000 (17.4%) Machine Cost 1000 (17.4 %) Office Overhead 250 (4.3%) Overhead 750 (13.0%) Site Cost 5500 (95.6%) Unit Price 7000 LE/unit Unit Cost 5750 (100%) Critical Resources Technical Direct Cost 5000 (86.9%) Materials Cost 3000(52.2 %) Site Overhead 500 (8.6%) Base Unit Level Actual Cost (2018) Inflation Rate 15%
  • 25. PM 25 Cost Management Best Practice - Dr. Attia Gomaa - 2018 Cost Breakdown Structure Unit Profit 1437 (21.7%) Labour Cost 1150 (17.4%) Machine Cost 1150 (17.4 %) Office Overhead 287 (4.3%) Overhead 862 (13.0%) Site Cost 6325 (95.6%) Unit Price 8050 LE/unit Unit Cost 6613 (100%) Critical Resources Technical Direct Cost 5750 (86.9%) Materials Cost 3450 (52.2 %) Site Overhead 575 (8.6%) Base Unit Level Cost Estimation (2019) Inflation Rate 15%
  • 26. PM 26 Cost Management Best Practice - Dr. Attia Gomaa - 2018 Price Structure Analysis: (Cost KPIs - Objectives) Contract Price = 7000 LE/m2 Margin =7000-5000= 2000 LE Direct Cost =5000 Total Cost = Direct Cost + Overhead = 5750 Profit 1250 LE Value Added = 7000-3000= 4000 LE Outsource Cost 3000 or rough cut estimation by using the value added or rough cut estimation by using the margin factor or rough cut estimation by using the markup factor Markup (Cost Plus) =7000-5500= 1500 LE Labor Mat. Jobsite OH Subs Equip Site Cost = Direct + Tech. O/h = 5500 For same scope of work For different scope of work For Cost Plus Contract Actual Cost (2018)
  • 27. PM 27 Cost Management Best Practice - Dr. Attia Gomaa - 2018 Price Structure Analysis: (Cost KPIs - Objectives) Contract Price = 7000 LE/m2 Margin Factor =7000/5000= 1.4 (1 Direct : 1.4 Income) Direct Cost =5000 Total Cost = Direct Cost + Overhead = 5750 Profit 21.7% Value Added Factor = 7000/3000= 2.33 Material Productivity = (1 Material : 2.33 Income) Outsource Cost 3000 or rough cut estimation by using the value added or rough cut estimation by using the margin factor or rough cut estimation by using the markup factor Markup Factor =7000/5500= 1.27 (Cost Plus) Labor Mat. Jobsite OH Subs Equip Site Cost = Direct + Tech. O/h = 5500 For same scope of work For different scope of work For Cost Plus Contract Actual Cost (2018)
  • 28. PM 28 Cost Management Best Practice - Dr. Attia Gomaa - 2018 Unit Profit -- (21.7%) Labour Cost --- (17.4%) Machine Cost -- (17.4 %) Office Overhead -- (4.3%) Overhead -- (13.0%) Site Cost -- (95.6%) Unit Price --- LE/unit Unit Cost --- (100%) Critical Resources Technical Direct Cost -- (86.9%) Materials Cost -- (52.2 %) Site Overhead -- (8.6%) Base Given: Raw Material Cost = 4000 LE/unit Cost Estimation #1:
  • 29. PM 29 Cost Management Best Practice - Dr. Attia Gomaa - 2018 The project cost information is as follows: • Project : Office Building 10 Floors • Bill of Quantity (BOQ): 6000 m2 • Direct Material Cost: 18 M.LE • Direct Machine Cost: 6 M.LE • Direct Labor Cost: 6 M.LE ---------------- • Technical Overhead 10% Direct Cost • Office Overhead: 5% Direct Cost • Profit Ratio 22% Cost Total Cost = Direct + Overhead = 30*1.15 = 34.5 M.LE Price = Total Cost + Profit = 34.5 * 1.22 = 42 M.LE Cost Estimation #2:
  • 30. PM 30 Cost Management Best Practice - Dr. Attia Gomaa - 2018 The project cost information is as follows: • Project : Office Building 10 Floors • Bill of Quantity (BOQ): 600*10 = 6000 m2 ---------------- • Direct Material Cost: 18 M.LE • Direct Machine Cost: 6 M.LE • Direct Labor Cost: 6 M.LE ---------------- • Margin Factor 40 % Direct (Margin Factor = Overhead + Profit = Price - Direct) Price = Direct Cost * Margin Factor = 30 * 1.4 = 42 M.LE Cost Estimation #3:
  • 31. PM 31 Cost Management Best Practice - Dr. Attia Gomaa - 2018 The project cost information is as follows: • Project : Office Building 10 Floors • Bill of Quantity (BOQ): 6000 m2 ---------------- • Direct Material Cost: 18 M.LE ---------------- • Value Added Factor 2.333 (Value Added Factor = Price / Material) Price = Material Cost * Value Added Factor = 18*2.333 = 42 M.LE Cost Estimation #4:
  • 32. PM 32 Cost Management Best Practice - Dr. Attia Gomaa - 2018 The project cost information is as follows: • Project : Office Building One Floor • Bill of Quantity (BOQ): 300 m2 ---------------- • Direct Material Cost: 600,000 LE • Direct Machine Cost: 100,000 LE • Direct Labor Cost: 300,000 LE ---------------- • Site Overhead 100,000 LE • Office Overhead: 50,000 LE • Unit Price: 5,000 LE/m2 Based on this information, discuss briefly the Cost Breakdown Structure Example: Actual Cost
  • 33. PM 33 Cost Management Best Practice - Dr. Attia Gomaa - 2018 The project cost information is as follows: • Item (Main Activity): Plain Concrete • Bill of Quantity (BOQ) 300 m3 • Direct Material Cost 120,000 LE • Direct Machine Cost 54,000 LE • Direct Labor Cost 24,000 LE • Factory Overhead 33,000 LE • Office Overhead 16,500 LE • Unit Price 1,100 LE/m3 Based on this information, discuss briefly the Cost Breakdown Structure Example:
  • 34. PM 34 Cost Management Best Practice - Dr. Attia Gomaa - 2018 The project cost information is as follows: • Item (Main Activity): Power Cable • Bill of Quantity (BOQ) 1000 m • Direct Material Cost 1,500,000 • Direct Machines 500,000 • Direct Labors 400,000 • Tech. Overhead 15% Direct Cost • Office Overhead 5% Direct Cost • Profit 20% Total Cost Brainstorming: Based on this information, discuss briefly the Cost Breakdown Structure
  • 35. PM 35 Cost Management Best Practice - Dr. Attia Gomaa - 2018 The project cost information is as follows: (Main Contractor) • Project : Gas Pipe Line • Bill of Quantity (BOQ) 100 Km • Direct Material Cost 1,000,000 $ • Direct Sub-Contactor $ 400,000 • Direct Engineers $ 100,000 ----------- • Tech. Overhead 7% Total Cost • Office Overhead 3% Total Cost • Profit 20% Total Cost Brainstorming: Based on this information, discuss briefly the Cost Breakdown Structure
  • 36. PM 36 Cost Management Best Practice - Dr. Attia Gomaa - 2018 Cost Breakdown Structure Total Profit 0.333 (20%) Engineers Cost 0.1 (6 %) Subcontractor Cost 0.4 (24 %) Office Overhead 0.050 (3%) Overhead 0.167 (10%) Site Cost 1.617(97%) Total Price 2.0 M.$ Total Cost 1.667 (100%) Critical Resources Technical Direct Cost 1.5 (90%) Materials Cost 1.0 (60 %) Site Overhead 0.117(7%) Base Project Level
  • 37. PM 37 Cost Management Best Practice - Dr. Attia Gomaa - 2018 Cost Breakdown Structure Total Profit 333 (20%) Engineers Cost 100 (6%) Subcontractor Cost 400 (24 %) Office Overhead 50 (3%) Overhead 167 (10%) Site Cost 1,617(97%) Total Price 20,000 $/km Total Cost 1,667 (100%) Critical Resources Technical Direct Cost 1,500 (90%) Materials Cost 1,000 (60 %) Site Overhead 117 (7%) Base Unit Level
  • 38. PM 38 Cost Management Best Practice - Dr. Attia Gomaa - 2018 Break-Even Analysis
  • 39. PM 39 Cost Management Best Practice - Dr. Attia Gomaa - 2018 Total costs = fixed costs + variable costs – Total fixed cost (TFC) is the cost of fixed inputs, inputs that do not vary with output (e.g., rent) – Total variable cost (TVC) is the cost of all inputs that vary with output (e.g., wages, raw materials) Breakeven Quantity of Sales: BE Total Fixed Costs Q = Price Var.Cost per unit 
  • 40. PM 40 Cost Management Best Practice - Dr. Attia Gomaa - 2018 • Determines at what level cost and revenue are in equilibrium • Break-even point – Obtained directly by mathematical calculations – Usually presented in graphic form known as break-even chart Break-Even Analysis: Breakeven quantity = (Total Fixed Cost) / (unit price – unit variable cost) Fixed cost Variable cost Total cost line Total revenue line Profit Breakeven point Total cost = Total revenue Profit = 0 Production Volume (units/period) Cost Loss Cost-Volume-Profit Chart
  • 41. PM 41 Cost Management Best Practice - Dr. Attia Gomaa - 2018 Breakeven - Margin of Safety
  • 42. PM 42 Cost Management Best Practice - Dr. Attia Gomaa - 2018 Planned Capacity 60 units Annual Fixed Cost 300 Annual Variable Cost 360 Revenue $ 900 Example: Planned Capacity = 60 units Unit variable cost = 360/60 = 6 $/unit Unit Price = 900/60 = 15 BEP = F / (p-v) = 300 / (15-6) = 33.3 = 34 Margin of safety = 60 – 34 = 26 units
  • 43. PM 43 Cost Management Best Practice - Dr. Attia Gomaa - 2018 Example: Demand (units) 500 Unit price ($) 50 Unit Variable cost ($) 15 Fixed Cost ($) 10,000 Based on this information, discuss the profit & breakeven analysis Profit = Revenue – Total Cost = 500*50 – (10000 + 500*15) = BEP: Q = F / (p-v) = 10000 / (50-15) = 285.7 Q % = 285.7 / 500 = 57.14 % Safety Margin = 100 – 57.14 = 42.86% > 30% (Excellent)
  • 44. PM 44 Cost Management Best Practice - Dr. Attia Gomaa - 2018 Scenario Analysis Worst-Case Scenario Most-Likely- Case Scenario Best-Case Scenario Demand (units) 400 500 600 Unit price ($) 48 50 53 Unit Variable cost ($) 17 15 12 Fixed Cost ($) 11,000 10,000 8,000 Based on this information, discuss the profit & breakeven analysis Total Cost Revenue Profit ($) Profit (%) BEQ (units) BEQ (%) Safety Margin (%) Comment
  • 45. PM 45 Cost Management Best Practice - Dr. Attia Gomaa - 2018 A company is building a workshop for producing metal windows. There is a considerable degree of uncertainty in cost terms. • Annual fixed costs = $ 300,000 to 500,000 • Variable cost per unit = $ 500 to 600 • Selling price per unit = $ 1,000 to 1,200 • Annual Production = 900 to 1,100 units Based on this information, discuss the profit & breakeven analysis Worst-Case Scenario Most-Likely- Case Scenario Best-Case Scenario Demand (units) 900 1000 1100 Unit price ($) 1000 1100 1200 Unit Variable cost ($) 600 550 500 Fixed Cost ($) 500,000 400,000 300,000 Example:
  • 46. PM 46 Cost Management Best Practice - Dr. Attia Gomaa - 2018 Year 1 2 3 4 5 Income: Sales Quantity, units 4000 5000 6000 7000 8000 Unit Price; $ 3000 3250 3500 3750 4000 Variable Cost ($1000): Production Cost 1000 1250 1500 1750 2000 Technical Overhead 500 625 750 875 1000 Fixed Cost ($1000): Depreciation 5000 5000 5000 5000 5000 Maintenance (3% of investment) 900 900 900 900 900 Insurance (1% of investment) 300 300 300 300 300 Production Cost 1000 1250 1500 1750 2000 Technical Overhead 500 625 750 875 1000 Office Overhead 500 625 750 875 1000 1) Economical Analysis (Unit Cost , Profit Ratio for each period , …) 2) Risk Analysis (Breakeven Analysis for each period ) 3) Risk Analysis (Sensitivity Analysis for Market Price Change ± 10%) 4) Risk Analysis (Sensitivity Analysis for variable Cost Change ± 10%) Based on this information, discuss the following:
  • 47. PM 47 Cost Management Best Practice - Dr. Attia Gomaa - 2018 A manager is trying to decide between two machines (A or B) to produce a certain product: • Alt. 1: Machine A: – Fixed Costs: • Annual Depreciation: $120,000 • Annual Maintenance: $20,000 – Variable costs: • Material: $2.25 / unit • Labor: $6.25 / unit • Alt. 2: Machine B: – Fixed Costs: • Annual Depreciation : $165,000 • Annual Maintenance: $35,000 – Variable costs: • Material: $2.25 / unit • Labor: $2.25 / unit Based on this information, select the best machine. Example: • Alt. 1: Machine A: – Fixed Costs: 140,000 – Variable costs: 8.5 /unit – TC(A) = 140,000 + 8.5 Q • Alt. 2: Machine B: – Fixed Costs: 200,000 – Variable costs: 4.5 /unit – TC(B) = 200,000 + 4.5 Q At BEQ: TC(A) = TC(B) 140,000 + 8.5 Q = 200,000 + 4.5 Q Q = 15,000 <15000 15000 >15000 A A,B B B A 15000 BEP
  • 48. PM 48 Cost Management Best Practice - Dr. Attia Gomaa - 2018 EGR 312 - 22 48 Two alternatives exist for a machining process. Alternative 1 has an initial cost of $10,000 and a salvage value of $1000 after 5 years. Alternative 1 also has a variable cost of $1/unit of product produced and an annual maintenance of $1000. Alternative 2 has an initial cost of $15,000 and a salvage value of $2,000 after 7 years. Alternative 2 also has a variable cost of $0.80/unit of product produced and an annual maintenance cost of $1200. Example: Based on this information, select the best machine.
  • 49. PM 49 Cost Management Best Practice - Dr. Attia Gomaa - 2018 Total Cost ‫الكلية‬ ‫التكاليف‬ Capital Cost ‫اإلستثمار‬ ‫التكليف‬ ‫ية‬ Running Cost ‫التشغيل‬ ‫التكاليف‬ ‫ية‬ CAPEX and OPEX Analysis
  • 50. PM 50 Cost Management Best Practice - Dr. Attia Gomaa - 2018 Assets: The economic resources owned by a business that can be used for future operations ‫األصول‬ : Fixed Assets: ‫ثابته‬ ‫أصول‬ • Land • Building • Equipment Current Assets: ‫متداولة‬ ‫أصول‬ • Cash • Accounts Receivable • Inventories • Raw Materials • Supplies Intellectual Assets: ‫ملموسة‬ ‫غير‬ ‫أصول‬ ) ‫فكرية‬ ( • Brand , Know-how
  • 51. PM 51 Cost Management Best Practice - Dr. Attia Gomaa - 2018 CAPEX and OPEX Analysis CAPEX Ratio + OPEX Ratio = 100% Capital Expenses = CAPEX Ratio (Best CAPEX ≥ 25%) = Fixed Asset Depreciation / Annual Total cost Operating Expenses = OPEX Ratio (Best OPEX ≤ 75%) = 100 – CAPEX
  • 52. PM 52 Cost Management Best Practice - Dr. Attia Gomaa - 2018 The cost classification matrix for a project (First year 2018) is as follows: Product / Project: xxxxxxx Unit Price= -- LE/unit Planned Capacity = --- units/year Product Cost Analysis: (Information) Cost Classification Matrix Cost Elements Annual Fixed Cost Annual Variable Cost Direct Costs 1) Materials 2) Technical labors 3) Equipment & Tools 4) Sub-Contractor Overheads 5) Technical Overhead Costs 6) Office Overhead Costs Cost Analysis? Cost Account
  • 53. PM 53 Cost Management Best Practice - Dr. Attia Gomaa - 2018 The cost classification matrix for a project (First year 2016) is as follows: Unit Price= 300 $/unit (Market Price) Planned Capacity = 100,000 units/year Cost Elements Annual Fixed Cost 1,000,000 $ Annual Variable Cost 1,000,000 $ Direct Costs Raw Materials - 10 Technical labors 3 2 Equipment & Tools 9 1 Overheads Technical Overhead 1 1 Office Overhead 1 - Based on this information, discuss the following: a) Cost breakdown structure b) Break even ratio & Margin of safety c) Sensitivity analysis for material cost and unit price change (±20%) Case Study:
  • 54. PM 54 Cost Management Best Practice - Dr. Attia Gomaa - 2018 The cost classification matrix for a project (First year 2016) is as follows: Unit Price= 300 $/unit (Market Price) Planned Capacity = 100,000 units/year Cost Elements Annual Fixed Cost 1,000,000 $ Annual Variable Cost 1,000,000 $ Total Cost 1,000,000 $ Direct Costs Raw Materials - 10 10 Technical labors 3 2 5 Equipment & Tools 9 1 10 Overhe ads Technical Overhead 1 1 2 Office Overhead 1 - 1 Total 1,000,000 $ 14 14 28 Unit Cost = 28,000,000 / 100,000 = 280 $/unit Unit Profit = 300 – 280 = 20 $/unit (7.14%) << 20% “Low Profit Ratio”
  • 55. PM 55 Cost Management Best Practice - Dr. Attia Gomaa - 2018 Cost Breakdown Structure Total Profit 2 (7.1 %) Labour Cost 10 (35.7%) Machine Cost 5 (17.8 %) Office Overhead 1 (3.5%) Overhead 3 (10.7%) Factory Cost 27 (96.4%) Total Price 30 M$ Total Cost 28 (100%) Critical Resources Technical Direct Cost 25 (89.2%) Materials Cost 10 (35.7 %) Technical Overhead 2 (7.1 %) Base Annual Level Planned Capacity = 100,000 units/year
  • 56. PM 56 Cost Management Best Practice - Dr. Attia Gomaa - 2018 Cost Breakdown Structure Unit Profit 20 (7.1 %) Labour Cost 100 (35.7%) Machine Cost 50 (17.8 %) Office Overhead 10 (3.5%) Overhead 30 (10.7%) Factory Cost 270 (96.4%) Unit Price 300 $/unit Unit Cost 280 (100%) Critical Resources Technical Direct Cost 250 (89.2%) Materials Cost 100 (35.7 %) Technical Overhead 20 (7.1 %) Base Unit Level Planned Capacity = 100,000 units/year Price Policy: Target Price = 300 $/unit Worst Price = 270 $/unit
  • 57. PM 57 Cost Management Best Practice - Dr. Attia Gomaa - 2018 Total Fixed Cost = 14,000,000 $ Unit Variable Cost = 140 $/unit Unit Price= 300 $/unit Breakeven % BEP = Total Fixed Cost / (Unit Price - Unit Variable Cost) = 14,000,000 / (300 – 140) = 87,500 unit Planned Capacity = 100,000 units/year BE % = 87,500 / 100,000 = 87.5% Margin of Safety = 12.5% <<< 30 % (Very Low  High Risk) Corrective Action: Try to reduce fixed cost by 20% Fixed cost Variable cost Total cost line Total revenue line Profit Breakeven point 87,500 units Production Volume (units/period) Cost Loss Cost-Volume-Profit Chart
  • 58. PM 58 Cost Management Best Practice - Dr. Attia Gomaa - 2018 Sensitivity analysis for material cost and unit price change (±20%) Deviation -20% -10% 0% Base 10% 20% Unit price -40 -10 20 50 80 Unit Material 40 30 20 10 0 Profit Matrix ($/unit) Scenario Profit $/unit Pessimistic 80 Most Likely 20 Optimistic -40
  • 59. PM 59 Cost Management Best Practice - Dr. Attia Gomaa - 2018 The cost classification matrix for a project (First year 2016) is as follows: Unit Price= 300 $/unit (Market Price) Planned Capacity = 100,000 units/year Cost Elements Annual Fixed Cost 1,000,000 $ Annual Variable Cost 1,000,000 $ Direct Costs Raw Materials - 10 Technical labors 2 3 Equipment & Tools 6 4 Overheads Technical Overhead 1 1 Office Overhead 1 - Based on this information, discuss the following: a) Cost breakdown structure b) Break even ratio & Margin of safety c) Sensitivity analysis for material cost and unit price change (±20%) Case Study:
  • 60. PM 60 Cost Management Best Practice - Dr. Attia Gomaa - 2018 The cost classification matrix for a project (First year 2016) is as follows: Unit Price= 300 $/unit (Market Price) Planned Capacity = 100,000 units/year Cost Elements Annual Fixed Cost 1,000,000 $ Annual Variable Cost 1,000,000 $ Total Cost 1,000,000 $ Direct Costs Raw Materials - 10 10 Technical labors 2 3 5 Equipment & Tools 6 4 10 Overhe ads Technical Overhead 1 1 2 Office Overhead 1 - 1 Total 1,000,000 $ 10 18 28 Unit Cost = 28,000,000 / 100,000 = 280 $/unit Unit Profit = 300 – 280 = 20 $/unit (7.14%) << 20% “Low Profit Ratio”
  • 61. PM 61 Cost Management Best Practice - Dr. Attia Gomaa - 2018 Cost Breakdown Structure Total Profit 2 (7.1 %) Labour Cost 10 (35.7%) Machine Cost 5 (17.8 %) Office Overhead 1 (3.5%) Overhead 3 (10.7%) Factory Cost 27 (96.4%) Total Price 30 M$ Total Cost 28 (100%) Critical Resources Technical Direct Cost 25 (89.2%) Materials Cost 10 (35.7 %) Technical Overhead 2 (7.1 %) Base Annual Level Planned Capacity = 100,000 units/year
  • 62. PM 62 Cost Management Best Practice - Dr. Attia Gomaa - 2018 Cost Breakdown Structure Unit Profit 20 (7.1 %) Labour Cost 100 (35.7%) Machine Cost 50 (17.8 %) Office Overhead 10 (3.5%) Overhead 30 (10.7%) Factory Cost 270 (96.4%) Unit Price 300 $/unit Unit Cost 280 (100%) Critical Resources Technical Direct Cost 250 (89.2%) Materials Cost 100 (35.7 %) Technical Overhead 20 (7.1 %) Base Unit Level Planned Capacity = 100,000 units/year Price Policy: Target Price = 300 $/unit Worst Price = 270 $/unit
  • 63. PM 63 Cost Management Best Practice - Dr. Attia Gomaa - 2018 Total Fixed Cost = 10,000,000 $ Unit Variable Cost = 180 $/unit Unit Price= 300 $/unit Breakeven % BEP = Total Fixed Cost / (Unit Price - Unit Variable Cost) = 10,000,000 / (300 – 180) = 83,333 unit Planned Capacity = 100,000 units/year BE % = 83,333 / 100,000 = 83.3% Margin of Safety = 16.7% <<< 30 % (Very Low  High Risk) Corrective Action: Try to reduce fixed cost by 20% Fixed cost Variable cost Total cost line Total revenue line Profit Breakeven point 83,333 units Production Volume (units/period) Cost Loss Cost-Volume-Profit Chart
  • 64. PM 64 Cost Management Best Practice - Dr. Attia Gomaa - 2018 Sensitivity analysis for material cost and unit price change (±20%) Deviation -20% -10% 0% Base 10% 20% Unit price -40 -10 20 50 80 Unit Material 40 30 20 10 0 Profit Matrix ($/unit) Scenario Profit $/unit Pessimistic 80 Most Likely 20 Optimistic -40
  • 65. PM 65 Cost Management Best Practice - Dr. Attia Gomaa - 2018
  • 66. PM 66 Cost Management Best Practice - Dr. Attia Gomaa - 2018
  • 67. PM 67 Cost Management Best Practice - Dr. Attia Gomaa - 2018
  • 68. PM 68 Cost Management Best Practice - Dr. Attia Gomaa - 2018
  • 69. PM 69 Cost Management Best Practice - Dr. Attia Gomaa - 2018
  • 70. PM 70 Cost Management Best Practice - Dr. Attia Gomaa - 2018
  • 71. PM 71 Cost Management Best Practice - Dr. Attia Gomaa - 2018 The cost classification matrix for a project (First year 2018) is as follows: Product Name : Microwave Product Code: FMW-25KC-S Unit Price= 2000 LE/unit Planned Capacity = 20,000 units/year Product Cost Analysis: Cost Classification Matrix Cost Elements Fixed Cost Variable Cost Direct Cost 1) Materials 20,000,000 2) Technical labors 3,000,000 2,000,000 3) Equipment & Tools 2,000,000 1,000,000 4) Sub-Contractor - - Overhead Cost 5) Technical Overhead Costs 1,500,000 1,500,000 6) Office Overhead Costs 1,500,000 500,000 Cost Analysis?
  • 72. PM 72 Cost Management Best Practice - Dr. Attia Gomaa - 2018 Cash Flow Analysis Time is money; there is a difference between $1000 today and $1000 after 3 years. If the interest rate (i) 10% annual; then: $ 1000 today = $ 1331 after 3 years How Financial Analysis (Long Term  Project Life) F = P (1 + i)n P = F / (1 + i)n
  • 73. PM 73 Cost Management Best Practice - Dr. Attia Gomaa - 2018 Cash Flow Cash Out Initial Investment Running Cost • Equipment • Building • Know-How • … etc. • Production • Salaries • Marketing • Maintenance • … etc. Cash In Sales Revenue Salvage Value • Quantity • Price • … etc. • Equipment • Building • … etc. Cash Flow Analysis: CAPEX OPEX CAPEX
  • 74. PM 74 Cost Management Best Practice - Dr. Attia Gomaa - 2018 Year 0 1 2 3 4 … … Equipment (Assets) Building (Assets) Production Cost …… …… …… Cost Elements (1000 LE): Sales Quantities, units Unit Market Price Salvage Value 4000 Cash Out Analysis Cash In Analysis Income (1000 LE): Analysis Tools? Based on this information, discuss the following: Comments? Salvage Value ‫المصروفات‬ ‫قائمة‬ : ‫اإلرادات‬ ‫قائمة‬ : Source: Technical Study Source: Market Study Project: Feasibility Study: ‫الجدوي‬ ‫دراسة‬ :
  • 75. PM 75 Cost Management Best Practice - Dr. Attia Gomaa - 2018 Year 0 1 2 3 4 5 6 Equipment (Assets) 7000 Building (Assets) 3000 Production Cost 2000 2600 2600 2600 2600 2600 Salaries Cost 300 300 300 300 300 300 Marketing Cost 200 250 250 250 250 250 Overhead 100 100 100 100 100 100 Sales Quantities, units 400 550 600 600 600 600 Unit Market Price 10 10 10 10 10 10 Salvage Value 4000 Based on this information, discuss the following: Salvage Value 4000 Cost Elements (1000 LE): Cash Out Analysis ‫المصروفات‬ ‫قائمة‬ : Cash In Analysis Income (1000 LE): ‫اإلرادات‬ ‫قائمة‬ : Project: ABC Manufacturing Company Feasibility Study: ‫الجدوي‬ ‫دراسة‬ : 1) Cash Flow Analysis 2) Financial Analysis (Payback Period , IRR , … ) 3) Economical Analysis (Unit Cost , Profit Ratio for each period , …) 4) Risk Analysis (Sensitivity Analysis for Market Price Change ± 10%)
  • 76. PM 76 Cost Management Best Practice - Dr. Attia Gomaa - 2018 Cash Flow Analysis i = Interest rate (%) n = Life time (year) P = Present value  Value at time = 0 F= Future value  Value at time > 0 A= Annual uniform value  Equal value over time • Interest rate  Certain bank  i% given (10%) • Minimum Attractive Rate of Return (MARR) • Internal Rate return  Cash In/out for Certain project P A F Cost (Cash Out) Revenue (Cash In) (-) (+) F = P (1 + i)n 0 (F , P , i , n )
  • 77. PM 77 Cost Management Best Practice - Dr. Attia Gomaa - 2018 Analysis Tools? Financial & Economical Analysis 1) Financial Analysis (Project Life): • Net Cash Flow • Payback Period • Internal Rate of Return IRR --------------------------- • Net Present Value NPV at i % • CAPEX% & OPEX% • Return On Investment • …… 1 ) ‫المالي‬ ‫التحليل‬ ) ‫عمر‬ ‫إلجمالي‬ ‫المشروع‬ :) • ‫المالي‬ ‫التدفق‬ ‫صافي‬ • ‫فترة‬ ‫المال‬ ‫رأس‬ ‫استرداد‬ • ‫الداخلي‬ ‫المعدل‬ ‫المالي‬ ‫للعائد‬ --------------------------- • ‫للمشروع‬ ‫الحالية‬ ‫القيمة‬ ‫صافي‬ • ‫المصروفات‬ ‫نسبة‬ ‫مالية‬ ‫الرأس‬ / ‫التشغيلية‬ • ‫اإلستثمار‬ ‫علي‬ ‫العائد‬ ‫متوسط‬ • ….. ‫للمشروع‬ ‫واإلقتصادي‬ ‫المالي‬ ‫التحليل‬ 2) Economical Analysis (Annually): • Unit Cost • Annual Profit% --------------------------- • Cost Breakdown Structure • CAPEX% & OPEX% 2 ) ‫االقتصادي‬ ‫التحليل‬ ) ‫سنويا‬ :) • ‫تكلفة‬ ‫الوحدة‬ • ‫السنوي‬ ‫الربح‬ ‫نسبة‬ --------------------------- • ‫التكاليف‬ ‫عناصر‬ ‫هيكل‬ • ‫المصروفات‬ ‫نسبة‬ ‫مالية‬ ‫الرأس‬ / ‫التشغيلية‬ 3) Risk Analysis (Financial / Economical) : • Break Even Point • Sensitivity Analysis for Material Cost & Unit Price Change • 3 ) ‫المخاطر‬ ‫تحليل‬ ) ‫مالي‬ ‫المحتملة‬ / ‫إقتصادي‬ :) • ‫إنتاج‬ ‫حجم‬ ‫نقطة‬ ‫التعادل‬ • ‫الخامات‬ ‫تكلفة‬ ‫تغير‬ ‫إحتمال‬ ‫حساسية‬ ‫تحليل‬ ‫وخالفه‬ ‫الوحدة‬ ‫وسعر‬ • Feasibility Study: ‫الجدوي‬ ‫دراسة‬ :
  • 78. PM 78 Cost Management Best Practice - Dr. Attia Gomaa - 2018 Project Financial Analysis: • Payback Period (Breakeven Period); (years) • ‫المال‬ ‫رأس‬ ‫إسترداد‬ ‫فترة‬ • Net Present Value (NPV)  (i% given) • ‫للمشروع‬ ‫الحالية‬ ‫القيمة‬ • Profitability Index  (i% given) • ‫الربجية‬ ‫معامل‬ • Internal Rate of Return (IRR)  (i% Unknown) • ‫الداخلي‬ ‫العائد‬ ‫معدل‬ ) ‫االستثمار‬ ‫علي‬ ‫العائد‬ ‫معدل‬ ( • Minimum Attractive Rate of Return (MARR)  Given • ‫للمستثمر‬ ‫جاذب‬ ‫عائد‬ ‫معدل‬ ‫أقل‬ Most Common
  • 79. PM 79 Cost Management Best Practice - Dr. Attia Gomaa - 2018 Example: Payback period = 2 + 25 / 75 = 2.333 years Firm recovers its initial investment in 2.333 years Year Net Cash Flow Cumulative Cash Flow 0 –100 –100 1 25 –75 2 50 –25 3 75 50 Payback Period Definition: The length of time until the original investment has been recouped by the project • Ignore time value of money • Does not consider profitability • A shorter payback period is better
  • 80. PM 80 Cost Management Best Practice - Dr. Attia Gomaa - 2018 Example: Payback Period = (2 to 3) years = 2 + 300/350 = 2.857 years = 2 years & 11 months $1000 $350 years 1 2 3 4 $350 $350 $350 Year 0 1 2 3 4 Cost -1000 Revenue +350 +350 +350 +350 Cumulative Cash Flow -1000 - 650 - 300 + 50 +400 1400 1000 Payback Period
  • 81. PM 81 Cost Management Best Practice - Dr. Attia Gomaa - 2018 Example: Payback Period = (2 to 3) years = 2 + 300/500 = 2.6 years = 2 years & 7.2 months $1000 $300 years 1 2 3 4 $500 $400 $400 Year 0 1 2 3 4 Cost -1000 Revenue +300 +400 +500 +400 Cumulative Cash Flow -1000 - 700 - 300 + 200 +600 1600 1000 Payback Period
  • 82. PM 82 Cost Management Best Practice - Dr. Attia Gomaa - 2018 Net Present Value (NPV) Converting Cash Flows to Present Value End of project Time zero: Initial Investment = $105,000 TIME Year 1 Year 2 Year 3 $38,463 $38,463 $38,463 = ?? = ?? = ?? Annual Savings • A higher NPV is better • Higher the discount rate lower the NPV        n t t t i F P 1 0 1 NPV
  • 83. PM 83 Cost Management Best Practice - Dr. Attia Gomaa - 2018 Net Present Value   63 64 . 0 * 350 71 . 0 * 350 80 . 0 * 350 89 . 0 * 350 000 , 1 12 . 1 350 12 . 1 350 12 . 1 350 12 . 1 350 000 , 1 4 3 2               Investment NPV Interest rate of i =12%. -$1,000 $350 years 1 2 3 4 $350 $350 $350 Example: P = F / (1 + i)n ‫؟‬ (NPV +)  IRR > 12% NPV (cash inflow) Loan or MARR - 0 + IRR < i IRR = i IRR > i NPV
  • 84. PM 84 Cost Management Best Practice - Dr. Attia Gomaa - 2018 Profitability Index: • Allows a comparison of the costs and benefits of different projects to be assessed and thus allow decision making to be carried out NPV (cash inflow) Profitability Index = --------------------------- Initial Capital Cost PI < 1.0 Losses  Rejected (or Service projects) PI = 1.0 Break even point  short term projects PI > 1.0 Profit  Accepted )Best ≥ 1.20) -$1,000 $350 years 1 2 3 4 $350 $350 $350 Profitability Index = 1063 / 1000 = 1.063 > 1.0 Accepted Cost Benefits (B/C) B C Interest rate of 12% NPV (cash inflow)
  • 85. PM 85 Cost Management Best Practice - Dr. Attia Gomaa - 2018 Internal Rate of Return (IRR) Definition: The rate of return that yields a Net Present Value of zero. (rate at which NPV=0) Example: -$1,000 $350 years 1 2 3 4 $350 $350 $350 15 . 0 0 000 , 1 ) 1 ( 350 ) 1 ( 350 ) 1 ( 350 1 350 4 3 2            IRR IRR IRR IRR IRR Example: P = F / (1 + i)n 14.96% IRR (i% Unknown)
  • 86. PM 86 Cost Management Best Practice - Dr. Attia Gomaa - 2018 Return On Investment (ROI) Year 0 1 2 3 Total to end Year 3 Cost (Outflows) 100 30 30 35 195 Income (Inflows) 0 100 95 75 265 ROI is a ratio comparing net gains to net costs. (measure of investment profitability) For example:
  • 87. PM 87 Cost Management Best Practice - Dr. Attia Gomaa - 2018 A Year 0 1 2 3 ROI = 20% IRR = 10% Cost (Outflows) 10 2 2 2 Income (Inflows) 6 6 6 Net Flows -10 4 4 4 ROI & IRR B Year 0 1 2 3 ROI = 20% IRR = 11% Cost (Outflows) 10 1 1 4 Income (Inflows) 6 6 6 Net Flows -10 5 5 2 C Year 0 1 2 3 ROI = 20% IRR = 9% Cost (Outflows) 10 4 1 1 Income (Inflows) 6 6 6 Net Flows -10 2 5 5
  • 88. PM 88 Cost Management Best Practice - Dr. Attia Gomaa - 2018 You can purchase a building for $350,000. The investment will generate $16,000 in cash flows (i.e. rent) during the first three years. At the end of three years you will sell the building for $450,000. What is the IRR on this investment? 0 350 000 16 000 1 16 000 1 466 000 1 1 2 3         , , ( ) , ( ) , ( ) IRR IRR IRR IRR = 12.96% ≥ MARR Example: 350 16 years 1 2 3 16 450 16 P = F / (1 + i)n Feasibility Study For Small Projects
  • 89. PM 89 Cost Management Best Practice - Dr. Attia Gomaa - 2018 Period Cash 2 Years 3 Years 0 200,000 75,000 60,000 1 - 75,000 60,000 2 - 75,000 60,000 3 60,000 You need to buy a new car, three alternatives are available : Based on this information, discuss the following: 1. Cash Flow Diagram 2. Internal Rate of Return (IRR) Example: Feasibility Study For Small Projects
  • 90. PM 90 Cost Management Best Practice - Dr. Attia Gomaa - 2018 2 ) 1 ( 75 1 75 75 200 i i      3 2 ) 1 ( 60 ) 1 ( 60 1 60 60 200 i i i        75 years 1 2 0 75 75 P= 200 = B P= 200 = 60 years 1 2 3 0 60 60 60 C Internal Rate of Return (IRR) i = IRR = 13.066% i = IRR = 13.7009% PV (A) < PV (B) < PV (C) & IRR (B) < IRR (C) The best choice is A then B then C
  • 91. PM 91 Cost Management Best Practice - Dr. Attia Gomaa - 2018 Initial Cost: $4000 Annual M&O Costs: $500 Salvage Value $500 1- Pump (A) Initial Cost: $4500 Annual M&O Costs: $400 Salvage Value $500 Based on this information, discuss & select the best pump. - Centrifugal Pump 1.0 HP - Interest rate is 10% - Average Annual Costs are constant - Life 10 years Assumptions / Calculations: 2- Pump (B) Example: Feasibility Study For Small Projects
  • 92. PM 92 Cost Management Best Practice - Dr. Attia Gomaa - 2018 Initial Cost: $4000 Annual M&O Costs: $500 Capital Maintenance after 6 years $3000 Salvage Value $500 1- Pump (A) Initial Cost: $5000 Annual M&O Costs: $400 Capital Maintenance after 6 years $2000 Salvage Value $500 Based on this information, discuss & select the best pump. - Centrifugal Pump 1.0 HP - Interest rate is 10% - Average Annual Costs are constant - Life 10 years Assumptions / Calculations: 2- Pump (B) PV: A= 8,572.9 B= 8,394.0 (Ranking: B < A) Example: Feasibility Study For Small Projects
  • 93. PM 93 Cost Management Best Practice - Dr. Attia Gomaa - 2018 A company needs a mobile crane for the next 10 years. Two alternatives are available to buy or to lease the crane. 1) The buy decision includes a first cost of 800,000 LE with a market value after 10 years of 100,000 LE and annual O&M cost of 30,000 LE. 2) To lease a similar crane, the annual charge will be 120,000 LE including everything. If the company earns 20% annually which alternative is to be selected. Example: Feasibility Study For Small Projects By using IRR method.
  • 94. PM 94 Cost Management Best Practice - Dr. Attia Gomaa - 2018 800 30 100 120 680 100 90 IRR = 5.1 < 20% (Rent) or NPV(20%) = - 305.9 Net 800 30 100 120 MARR 20% Cash Out Cash In 0 0 IRR
  • 95. PM 95 Cost Management Best Practice - Dr. Attia Gomaa - 2018 800 30 100 120 MARR 20% Buy Rent NPV (i=20%) = 909.6 NPV (i=20%) = 603.7 (min.) 0 0 NPV
  • 96. PM 96 Cost Management Best Practice - Dr. Attia Gomaa - 2018 Feasibility Study For Small Projects ‫المشروع‬ ‫وصف‬ ‫المكان‬ : ‫الجديدة‬ ‫القاهرة‬ / ‫األندلس‬ ‫منطقة‬ ‫األرض‬ ‫مساحة‬ : 500 ‫م‬ 2 ‫مباني‬ ‫مساحة‬ : 6000 ‫م‬ 2 ‫المواصفات‬ : ‫بدروم‬ + ‫أرضي‬ + 3 ‫أدوار‬ + ‫رووف‬ ‫األرضي‬ : ‫شقة‬ 180 ‫م‬ 2 + ‫دوبلكس‬ 330 ‫م‬ 2 ‫الدور‬ : ‫عدد‬ 2 ‫شقة‬ * 180 ‫م‬ 2 = 360 ‫م‬ 2 ‫التكاليف‬ ‫عناصر‬ ‫متوسط‬ ) 2017 ) ‫األرض‬ ‫قيمة‬ : 6000 ‫جنيه‬ / ‫م‬ 2 ‫التنفيذ‬ ‫تكاليف‬ : 6000 ‫جنيه‬ / ‫م‬ 2 ‫اإلشراف‬ ‫نسبة‬ : 10 % ‫التنفيذ‬ ‫من‬ ‫التسويق‬ ‫نسبة‬ : 5 % ‫المبيعات‬ ‫من‬ ‫الحديد‬ ‫سعر‬ : 12300 ‫جنيه‬ / ‫طن‬ ‫سعر‬ ‫األسمنت‬ : 830 ‫جنيه‬ / ‫طن‬ ‫المبيعات‬ ‫عناصر‬ ‫متوسط‬ ) 2017 ) ‫األرضي‬ : ‫شقة‬ : 7300 ‫جنيه‬ / ‫م‬ 2 ‫دوبلكس‬ : 5500 ‫جنيه‬ / ‫م‬ 2 ‫األدوار‬ : ‫شقة‬ : 7500 ‫جنيه‬ / ‫م‬ 2 ‫الجراج‬ : 50000 ‫جنيه‬ ‫التضخم‬ ‫معامل‬ 1 1 % ‫سنويا‬ ‫عقاري‬ ‫إلستثمار‬ ‫جدوي‬ ‫دراسة‬ ‫التنفيذ‬ ‫مدة‬ = 12 ‫شهر‬
  • 97. PM 97 Cost Management Best Practice - Dr. Attia Gomaa - 2018 Project: Car Rent Initial Investment = 500,000 LE Project Life = 10 years Salvage Value 100,000 Annual Running Cost = 8% Initial investment Annual Maintenance Cost = 3% Initial investment Annual Risk and Insurance = 1% Initial investment Annual Working Days = 200 day/year Daily Rent Price = 700 LE/day Feasibility Study For Small Projects
  • 98. PM 98 Cost Management Best Practice - Dr. Attia Gomaa - 2018 Year 0 1 2 3 4 5 6 Equipment (Assets) 7000 Building (Assets) 3000 Production Cost 2000 2600 2600 2600 2600 2600 Salaries Cost 300 300 300 300 300 300 Marketing Cost 200 250 250 250 250 250 Overhead 100 100 100 100 100 100 Sales Quantities, units 400 550 600 600 600 600 Unit Market Price 10 10 10 10 10 10 Salvage Value 4000 Based on this information, discuss the following: Salvage Value 4000 Cost Elements (1000 LE): Cash Out Analysis ‫المصروفات‬ ‫قائمة‬ : Cash In Analysis Income (1000 LE): ‫اإلرادات‬ ‫قائمة‬ : Project: ABC Manufacturing Company Feasibility Study: ‫الجدوي‬ ‫دراسة‬ : 1) Cash Flow Analysis 2) Financial Analysis (Payback Period , IRR , … ) 3) Economical Analysis (Unit Cost , Profit Ratio for each period , …) 4) Risk Analysis (Sensitivity Analysis for Market Price Change ± 10%)
  • 99. PM 99 Cost Management Best Practice - Dr. Attia Gomaa - 2018 (1000 LE): Year 0 1 2 3 4 5 6 Total Cost 10000 2600 3250 3250 3250 3250 3250 Salvage Value 4000 Sales Revenue 4000 5500 6000 6000 6000 6000 Net Cash Flow -10000 1400 2250 2750 2750 2750 6750 Cash Flow Analysis: Payback Period = 4 + 850 / 2750 = 4.31 years = 4 year + 4 months Accumulative Net Cash -10000 -8600 -6350 -3600 -850 +1900 +8650 1) Financial Analysis -15000 -10000 -5000 0 5000 10000 0 2 4 6 8 Manual
  • 100. PM 100 Cost Management Best Practice - Dr. Attia Gomaa - 2018 Internal Rate of Return (IRR) = 16.7% ≥ MARR (1000 LE): Year 0 1 2 3 4 5 6 Total Cost 10000 2600 3250 3250 3250 3250 3250 Salvage Value 4000 Sales Revenue 4000 5500 6000 6000 6000 6000 Net Cash Flow -10000 1400 2250 2750 2750 2750 6250 Cash Flow Analysis: P = F / (1 + i)n NPV = 0 = -10000 + {1400/(1+i)1 +2250/ (1+ i)2 +2750/ (1+ i)3 +2750/ (1+ i)4 +2750/ (1+ i)5 +6250/ (1+ i)6 } 1) Financial Analysis Or Trail & error method: i= 10%  NPV = + 2,312.13 i= 20%  NPV = - 1,154.93 i ?  NPV = 0 i = IRR = 16.7% NPV i % 0 Manual F = P (1 + i)n
  • 101. PM 101 Cost Management Best Practice - Dr. Attia Gomaa - 2018 Year 1 2 3 4 5 6 Annual Depreciation 1000 1000 1000 1000 1000 1000 Production 2000 2500 2500 2500 2500 2500 Salaries 300 300 300 300 300 300 Marketing 200 250 250 250 250 250 Overhead 100 100 100 100 100 100 Total Cost 3600 4150 4150 4150 4150 4150 Sales Quantities 400 550 600 600 600 600 Unit Price 10 10 10 10 10 10 Sales Revenue 4000 5500 6000 6000 6000 6000 Unit Cost 9.0 7.5 6.9 6.9 6.9 6.9 Unit Price 10 10 10 10 10 10 Profit % 11.1% 32.5% 44.6% 44.6% 44.6% 44.6% Annual Cost (1000 LE): Annual Revenue (1000 LE): 2) Economical Analysis: Cost Analysis (1000 LE): Annual Depreciation = (10000 – 4000)/6 = 1000 (Straight Line Method)
  • 102. PM 102 Cost Management Best Practice - Dr. Attia Gomaa - 2018 Sensitivity Analysis for Market Price Change ± 10% 3) Risk Analysis: Indicator Change in Market Price - 10% 0% + 10% Payback Period ; years 5.13 4.31 3.61 IRR 10.5% 16.7% 22.6% Financial Risk: Economical Risk (Year #1): Indicator Change in Market Price - 10% 0% + 10% Unit Cost 9.0 9.0 9.0 Unit Price 9.0 10 11 Profit % 0 % 11.1% 22.2% Year 0 1 2 3 4 5 6 Unit Market Price (Base) 10 10 10 10 10 10 +10% 11 11 11 11 11 11 -10% 9 9 9 9 9 9
  • 103. PM 103 Cost Management Best Practice - Dr. Attia Gomaa - 2018 (1000 LE): Year 0 1 2 3 4 5 6 Total Cost 10000 2600 3250 3250 3250 3250 3250 Salvage Value 4000 Sales Revenue 4400 6050 6600 6600 6600 6600 Net Cash Flow -10000 1800 2800 3350 3350 3350 7350 Cash Flow Analysis: Payback Period = 3 + 2050 / 3350 = 3.61 years = 3 year + 7 months Accumulative Net Cash -10000 -8200 -5400 -2050 1300 4650 12000 Financial Risk Change in Market Price +10% = 11 LE/unit Internal Rate of Return (IRR) = 22.6% ≥ MARR -15000 -10000 -5000 0 5000 10000 15000 0 1 2 3 4 5 6 7
  • 104. PM 104 Cost Management Best Practice - Dr. Attia Gomaa - 2018 (1000 LE): Year 0 1 2 3 4 5 6 Total Cost 10000 2600 3250 3250 3250 3250 3250 Salvage Value 4000 Sales Revenue 3600 4950 5400 5400 5400 5400 Net Cash Flow -10000 1000 1700 2150 2150 2150 6150 Cash Flow Analysis: Payback Period = 5 + 850 /6150 = 3.13 years = 3 year + 1 month Accumulative Net Cash -10000 -9000 -7300 -5150 -3000 -850 5300 Financial Risk Change in Market Price -10% = 9 LE/unit -15000 -10000 -5000 0 5000 10000 15000 0 1 2 3 4 5 6 7 8 Internal Rate of Return (IRR) = 10.5% ≥ MARR
  • 105. PM 105 Cost Management Best Practice - Dr. Attia Gomaa - 2018 Sensitivity Analysis for Operating Cost Change ± 10% 3) Risk Analysis: Indicator Change in Market Price - 10% 0% + 10% Payback Period ; years 4.31 IRR 16.7% Financial Risk: Economical Risk (Year #1): Indicator Change in Market Price - 10% 0% + 10% Unit Cost 9.0 Unit Price 10 Profit % 11.1% Year 0 1 2 3 4 5 6 Operating Cost (Base) 2600 3250 3250 3250 3250 3250 +10% 2860 3575 3575 3575 3575 3575 -10% 2340 2925 2925 2925 2925 2925
  • 106. PM 106 Cost Management Best Practice - Dr. Attia Gomaa - 2018 Year 0 1 2 3 4 …. Income: Sales Quantity, units Unit Price, $ Initial Investment ($1000): Equipment (Assets) Building (Assets) Cost Elements ($1000): Direct Production Cost Study Assumptions: Project: Manufacturing Company Feasibility Study Guidelines (Dr. Attia Gomaa) • Annual Maintenance Cost = 3% of initial investment • Annual Insurance = 1% of initial investment • Salvage Value after 5 years = 50% of initial investment • Salvage Value after 10 years = 20% of initial investment • Technical Overhead = 50% of Direct Production Cost • Office Overhead = 25% of Direct Production Cost
  • 107. PM 107 Cost Management Best Practice - Dr. Attia Gomaa - 2018 Year 0 1 2 3 4 5 Income: Sales Quantity, units 4000 5000 6000 7000 8000 Unit Price, $ 3000 3250 3500 3750 4000 Initial Investment ($1000): Equipment (Assets) 25000 Building (Assets) 5000 Cost Elements ($1000): Direct Production Cost 2000 2500 3000 3500 4000 • Annual Maintenance Cost = 3% of initial investment • Annual Insurance = 1% of initial investment • Salvage Value after 5 years = 50% of initial investment • Technical Overhead = 50% of Direct Production Cost • Office Overhead = 25% of Direct Production Cost Based on this information, discuss the following: Study Assumptions: Project: ABC Manufacturing Company 1) Financial Analysis (Cash Flow, Payback Period , IRR , … ) 2) Economical Analysis (Unit Cost , Profit Ratio for each period , …) 3) Risk Analysis (Sensitivity Analysis for Market Price & Production Cost Change ± 10%)
  • 108. PM 108 Cost Management Best Practice - Dr. Attia Gomaa - 2018 Year 0 1 2 3 4 5 Income: Sales Quantity, units 4000 5000 6000 7000 8000 Unit Price, $ 3000 3250 3500 3750 4000 Initial Investment ($1000): Equipment (Assets) 25000 Building (Assets) 5000 Salvage Value 15000 Cost Elements ($1000): Direct Production Cost 2000 2500 3000 3500 4000 Technical Overhead 1000 1250 1500 1750 2000 Office Overhead 500 625 750 875 1000 Maintenance (3% of investment) 900 900 900 900 900 Insurance (1% of investment) 300 300 300 300 300 Based on this information, discuss the following: 1) Financial Analysis (Cash Flow, Payback Period , IRR , … ) 2) Economical Analysis (Unit Cost , Profit Ratio for each period , …) 3) Risk Analysis (Sensitivity Analysis for Market Price & Production Cost Change ± 10%) Project: ABC Manufacturing Company
  • 109. PM 109 Cost Management Best Practice - Dr. Attia Gomaa - 2018 Year 0 1 2 3 4 5 6 Income: Sales Quantity, units 500 550 600 650 700 750 Unit Price, $ 10.0 10.5 11.0 11.5 12.0 12.5 Initial Investment ($1000): Equipment (Assets) 8000 Building (Assets) 3000 Cost Elements ($1000): Direct Production Cost 2000 2500 3000 3500 4000 4500 • Annual Maintenance Cost = 3% of initial investment • Annual Insurance = 1% of initial investment • Salvage Value after 6 years = 40% of initial investment • Technical Overhead = 50% of Direct Production Cost • Office Overhead = 25% of Direct Production Cost Based on this information, discuss the following: Study Assumptions: Project: ABC Manufacturing Company 1) Financial Analysis (Cash Flow, Payback Period , IRR , … ) 2) Economical Analysis (Unit Cost , Profit Ratio for each period , …) 3) Risk Analysis (Sensitivity Analysis for Market Price & Production Cost Change ± 10%)
  • 110. PM 110 Cost Management Best Practice - Dr. Attia Gomaa - 2018 Project (B) Project (A) Item 7 5 Initial Investment; M$ 2 2 Annual Running Cost; M$/year 5 4 Annual Revenue; M$/year 2 1 Salvage Value; M$ 4 4 Project Life; years A manager is trying to decide between two projects (A or B): Based on this information, discuss the following: 1. Cash Flow Diagram 2. Payback Period 3. Internal Rate of Return (IRR) 4. Which offer should you accept and why? 5. Sensitivity analysis for annual revenue , salvage value & initial investment (±10%) Minimum Attractive Rate of Return (MARR) 20% Example:
  • 111. PM 111 Cost Management Best Practice - Dr. Attia Gomaa - 2018 Project (A) Cash Flow Diagram: Project (B) Payback Period = 5/2 = 2.5 years = 2 years & 6 months IRR = 26.40 % > 20% MARR (Accepted) Payback Period = 7/3 = 2.33 years = 2 years & 4 months IRR = 31.56 % > 20% MARR (Accepted) NPV = 0 = - 5 +2/(1+i) + 2/(1+i)^2 + 2/(1+i)^3 + 3/(1+i)^4 NPV = 0 = - 7 +3/(1+i) + 3/(1+i)^2 + 3/(1+i)^3 + 5/(1+i)^4 IRR (B) > IRR (A) > MARR 20% Project B is better than project A 7 1 2 0 3 4 2 5 2 7 0 1 2 3 4 3 2 5 1 2 0 3 4 2 4 1 5 0 1 2 3 4 2 1 Net cash flow = Cash inflows - Cash outflows
  • 112. PM 112 Cost Management Best Practice - Dr. Attia Gomaa - 2018 Project (B) Payback Period = 7/2.5 = 2.8 years = 2 years & 10 months IRR = 22.96 % NPV = 0 = - 7 +2.5/(1+i) + 2.5/(1+i)^2 + 2.5/(1+i)^3 + 4.5/(1+i)^4 7 1 2 0 3 4 2 5-0.5 2 7 0 1 2 3 4 2.5 2 Project (B) Payback Period = 7/3.5 = 2 years IRR = 39.94 % NPV = 0 = - 7 +3.5/(1+i) + 3.5/(1+i)^2 + 3.5/(1+i)^3 + 5.5/(1+i)^4 7 1 2 0 3 4 2 5+0.5 2 7 0 1 2 3 4 3.5 2 Sensitivity Analysis for Project (B) Annual revenue (±10%)
  • 113. PM 113 Cost Management Best Practice - Dr. Attia Gomaa - 2018 Financial Risk Analysis: Indicator Change in Annual Revenue - 10% 0% + 10% Payback Period ; years 3 3 2 IRR 22.96 % 31.56 % 39.94 % Sensitivity Analysis for Project (B) Indicator Change in Salvage Value - 10% 0% + 10% Payback Period ; years 3 3 3 IRR 31.02 31.56 % 32.09 Indicator Change in Initial Investment - 10% 0% + 10% Payback Period ; years 3 3 3 IRR 37.70 31.56 % 26.37 Scenarios analysis (IRR%): Optimistic 39.94 Most likely 31.56 Pessimistic 22.96
  • 114. PM 114 Cost Management Best Practice - Dr. Attia Gomaa - 2018 Sensitivity Analysis Graph for Project (B) IRR% -5 5 10 20 30 40 60 80 -30 -20 -10 0 10 20 30 Base Annual revenue Initial Invest % change from base Deviation -20% -15% -10% -5% 0% Base 5% 10% 15% 20% Annual revenue 22.96 31.56 % 39.94 Salvage value 31.56 % Initial Investment 31.56 % IRR Matrix Sketch
  • 115. PM 115 Cost Management Best Practice - Dr. Attia Gomaa - 2018 Project (B) Project (A) Item 8 6 Initial Investment; M$ 3 3 Annual Running Cost; M$/year 6 5 Annual Revenue; M$/year 3 2 Salvage Value; M$ 5 5 Project Life; years Based on this information, discuss the following: 1. Cash Flow Diagram 2. Payback Period 3. Internal Rate of Return (IRR) 4. Which offer should you accept and why? 5. Sensitivity analysis for annual revenue , salvage value & initial investment (±10%) Minimum Attractive Rate of Return (MARR) 20% A manager is trying to decide between two projects (A or B): Example:
  • 116. PM 116 Cost Management Best Practice - Dr. Attia Gomaa - 2018 Project (A) Project (B) Payback Period = 3 years IRR = 25.25% > MARR 20% Payback Period = 2.67 years IRR = 30.7% > MARR 20% Sensitivity analysis: Deviation -10% 0% Base 10% Annual revenue 4.5 5 5.5 IRR% 15.12 25.2 % 35 Payback Period 4.0 3 2.4 Scenarios analysis (IRR%): Optimistic 35% Most likely 25.5 Pessimistic 15.2% Sensitivity analysis: Deviation -10% 0% Base 10% Annual revenue 5.4 6 6.6 IRR% 21.9 30.72 39.2 Payback Period 3.3 2.67 2.22 Scenarios analysis (IRR%): Optimistic 39.2% Most likely 30.72% Pessimistic 21.9%
  • 117. PM 117 Cost Management Best Practice - Dr. Attia Gomaa - 2018 Project (B) Project (A) Item 5 4 Initial Investment; M$ 2 1 Annual Running Cost; M$/year 5 3 Annual Revenue; M$/year 1 1 Salvage Value; M$ 4 4 Project Life; years Based on this information, discuss the following: 1. Cash Flow Diagram 2. Payback Period 3. Internal Rate of Return (IRR) 4. Which offer should you accept and why? 5. Sensitivity analysis for market price change (±10%) Loan 15% MARR = 20% A manager is trying to decide between two projects (A or B): Example:
  • 118. PM 118 Cost Management Best Practice - Dr. Attia Gomaa - 2018 Scenario Analysis Item Best Base Worst 25% 50% 25% Probability; % 4 5 5.1 Initial Investment; M$ 3 4 4.1 Annual Running Cost; M$/year 6 5 4.9 Annual Revenue; M$/year 3 2 1.9 Salvage Value; M$ 4 4 4 Project Life; years Example: Based on this information, discuss the following: 1. Cash Flow Diagram 2. Payback Period 3. Internal Rate of Return (IRR) Risk Analysis
  • 119. PM 119 Cost Management Best Practice - Dr. Attia Gomaa - 2018 Scenario Analysis Item Best Base Worst 25% 50% 25% Probability; % 4 5 5.1 Initial Investment; M$ 3 4 4.1 Annual Running Cost; M$/year 6 5 4.9 Annual Revenue; M$/year 3 2 1.9 Salvage Value; M$ 4 4 4 Project Life; years 2 4 4 Payback Period (years) 72.7 6.4 0 Internal Rate of Return (IRR) Risk Analysis E (Payback Period) = 4 * 0.25 + 4 * 0.50 + 2 * 0.25= 3.5 years E (IRR) = 0 * 0.25 + 6.4 * 0.50 + 72.7 * 0.25 = 21.4 % Estimation:
  • 120. PM 120 Cost Management Best Practice - Dr. Attia Gomaa - 2018 Scenario Analysis Item Best Base Worst 25% 50% 25% Probability; % (by default) 4 5 6 Initial Investment; M$ 3 4 5 Annual Running Cost; M$/year 6 5 4 Annual Revenue; M$/year 3 2 1 Salvage Value; M$ 4 4 4 Project Life; years Example: Based on this information, discuss the following: 1. Cash Flow Diagram 2. Payback Period 3. Internal Rate of Return (IRR) Risk Analysis
  • 121. PM 121 Cost Management Best Practice - Dr. Attia Gomaa - 2018 Scenario Analysis Item Best Base Worst 25% 50% 25% Probability; % 4 5 6 Initial Investment; M$ 3 4 5 Annual Running Cost; M$/year 6 5 4 Annual Revenue; M$/year 3 2 1 Salvage Value; M$ 4 4 4 Project Life; years 2 4 N/A Payback Period (years) 72.7 6.4 N/A Internal Rate of Return (IRR) Infeasible Risk Analysis E (Payback Period) = E (IRR) = Estimation:
  • 122. PM 122 Cost Management Best Practice - Dr. Attia Gomaa - 2018 Project (B) Project (A) Item One year One year Construction Period 5 4 Initial Investment; M$ 2 1 Annual Running Cost; M$/year 5 3 Annual Revenue; M$/year 1 1 Salvage Value; M$ 4 4 Life after construction; years Based on this information, discuss the following: 1. Cash Flow Diagram 2. Payback Period 3. Internal Rate of Return (IRR) 4. Which offer should you accept and why? 5. Sensitivity analysis for market price change (±10%) Loan 15% MARR = 20% (Construction Period) A manager is trying to decide between two projects (A or B): Example:
  • 123. PM 123 Cost Management Best Practice - Dr. Attia Gomaa - 2018 Project (B) Project (A) Item One year Six months Construction Period 6 5 Initial Investment; M$ 3 2 Annual Running Cost; M$/year 6 4 Annual Revenue; M$/year 2 2 Salvage Value; M$ 6 5 Life after construction; years Based on this information, discuss the following: 1. Cash Flow Diagram 2. Payback Period 3. Internal Rate of Return (IRR) 4. Which offer should you accept and why? 5. Sensitivity analysis for market price change (±10%) MARR = 20% (Construction Period) A manager is trying to decide between two projects (A or B): Example:
  • 124. PM 124 Cost Management Best Practice - Dr. Attia Gomaa - 2018 Project (A) Project (B) Payback Period = 3 years IRR = 27.7% > MARR 20% Payback Period = 3 years IRR = 32.3% > MARR 20% Sensitivity analysis: Deviation -10% 0% Base 10% Annual revenue 3.6 4 4.4 IRR% 20.4 27.7 34.7 Payback Period 3.63 3.0 2.58 Scenarios analysis (IRR%): Optimistic 34.7 Most likely 27.7 Pessimistic 20.4 Sensitivity analysis: Deviation -10% 0% Base 10% Annual revenue 5.4 6 6.6 IRR% 25.4 32.3 38.5 Payback Period 3.5 3.0 2.67 Scenarios analysis (IRR%): Optimistic 38.5 Most likely 32.3 Pessimistic 25.4
  • 125. PM 125 Cost Management Best Practice - Dr. Attia Gomaa - 2018 Project (B) Project (A) Item Two years One year Construction Period $ 100,000 Down payment (t=0) 200,000 after one year 100,000 after two years $ 100,000 Down payment (t=0) $ 300,000 Final payment Construction investment 50,000 first year 100,000 second year 150,000 third year 200,000 forth year $ 100,000 / year Running cost after construction 150,000 first year 300,000 second year 500,000 third year 400,000 forth year $ 250,000 / year Revenue after construction Four years Four years Life after construction $ 100,000 $ 100,000 Salvage value Based on this information, discuss & select the best alternative. Minimum Attractive Rate of Return (MARR) 25% Bank Interest Rate 10% Annual A manager is trying to decide between two projects (A or B): Example: (Construction Period)
  • 126. PM 126 Cost Management Best Practice - Dr. Attia Gomaa - 2018 Project (A) Item One year Construction Period $ 100,000 Down payment (t=0) $ 300,000 Final payment Construction investment $ 100,000 / year Running cost after construction $ 250,000 / year Revenue after construction Four years Life after construction $ 100,000 Salvage value Minimum Attractive Rate of Return (MARR) 25% 100 100 100 250 300 0 1 100 100 150 300 0 1 IRR = 21.7 < 25% (Rejected)
  • 127. PM 127 Cost Management Best Practice - Dr. Attia Gomaa - 2018 Project (B) Item Two years Construction Period $ 100,000 Down payment (t=0) 200,000 after one year 100,000 after two years Construction investment 50,000 first year 100,000 second year 150,000 third year 200,000 forth year Running cost after construction 150,000 first year 300,000 second year 500,000 third year 400,000 forth year Revenue after construction Four years Life after construction $ 100,000 Salvage value 350 100 200 100 100 200 300 IRR = 25.25% > 25% (Accepted) 0
  • 128. PM 128 Cost Management Best Practice - Dr. Attia Gomaa - 2018
  • 129. PM 129 Cost Management Best Practice - Dr. Attia Gomaa - 2018 Lake Lake x x 5 km 5 km 5 km 5 km There are two ways (A and B) to construct a power line: Standard Information Example: Project (B) Project (A) Item Around lake Under lake Method 15 km 5 km Length
  • 130. PM 130 Cost Management Best Practice - Dr. Attia Gomaa - 2018 There are two ways (A and B) to construct a power line: Project (B) Project (A) Item Around lake Under lake Method 15 km 5 km Length $ 5,000/km $ 25,000/km First Cost $ 200/km $ 400/km Annual Maintenance Cost 15 year 15 year Expected Life $ 3000/km $ 5000/km Salvage Value $ 400/km $ 500/km Annual Power Losses Based on this information, discuss & select the best alternative. Sensitivity analysis for first cost change (±20%) and line length (±10%). Interest rate 12% (Loan) Standard Information Example:
  • 131. PM 131 Cost Management Best Practice - Dr. Attia Gomaa - 2018 Project (A) Time First Cost Annual Maintenance Power Losses Salvage Value Net 0 125 -125 1 2 2.5 -4.5 2 2 2.5 -4.5 3 2 2.5 -4.5 4 2 2.5 -4.5 5 2 2.5 -4.5 6 2 2.5 -4.5 7 2 2.5 -4.5 8 2 2.5 -4.5 …… …… …… …… …… 15 2 2.5 25 +20.5 Interest rate 12% (Loan) NPV (12%) = 151.08 “Cost”
  • 132. PM 132 Cost Management Best Practice - Dr. Attia Gomaa - 2018 Project (B) Time First Cost Annual Maintenance Power Losses Salvage Value Net 0 75 -75 1 3 6 -9 2 3 6 -9 3 3 6 -9 4 3 6 -9 5 3 6 -9 6 3 6 -9 7 3 6 -9 8 3 6 -9 …… …… …… …… …… 15 3 6 45 +36 Interest rate 12% (Loan) NPV (12%) = 128.08 “Cost”
  • 133. PM 133 Cost Management Best Practice - Dr. Attia Gomaa - 2018 Project (B) Project (A) Item Around lake Under lake Method 16 km 8 km Length $ 5,000/km $ 25,000/km First Cost $ 200/km $ 400/km Annual Maintenance Cost 10 year 10 year Expected Life $ 3000/km $ 5000/km Salvage Value $ 400/km $ 500/km Annual Power Losses NPV(A) = 227,803 NPV(B) = 126,515 For this non-profitable project, we should select project (B), because it has lower NPV and also lower first cost. Interest rate 12% (Loan) Standard Information Example: There are two ways (A and B) to construct a power line:
  • 134. PM 134 Cost Management Best Practice - Dr. Attia Gomaa - 2018 There are two ways (A and B) to construct a power line: Project (B) Project (A) Item Around lake Under lake Method 15 km 5 km Length $ 5,000/km $ 25,000/km First Cost $ 200/km $ 400/km Annual Maintenance Cost 15 year 15 year Expected Life $ 3000/km $ 5000/km Salvage Value $ 400/km $ 500/km Annual Power Losses $ 25,000 $ 25,000 Annual Revenue Based on this information, discuss & select the best alternative. Sensitivity analysis for first cost change (±20%) and line length (±10%). Interest rate 12% (Loan) Standard Information Example:
  • 135. PM 135 Cost Management Best Practice - Dr. Attia Gomaa - 2018
  • 136. PM 136 Cost Management Best Practice - Dr. Attia Gomaa - 2018 Capitalization Rate (Cap Rate) is an indirect measurement of how an investment pays for itself Average national cap rates for limited-service hotels over the past decade ranged between 9-13%.
  • 137. PM 137 Cost Management Best Practice - Dr. Attia Gomaa - 2018 Project (B) Project (A) Item 5.0 4.5 Initial Investment; M$ 1.2 1.1 Annual Running Cost; M$/year 3.0 2.5 Annual Revenue; M$/year - - Salvage Value; M$ 4 4 Project Life; years Based on this information, discuss the following: 1. Cash Flow Diagram 2. Profitability Index 3. Capitalization Rate 4. Which offer should you accept and why? Bank interest rate 12% A manager is trying to decide between two projects (A or B): Example:
  • 138. PM 138 Cost Management Best Practice - Dr. Attia Gomaa - 2018 Project (A) Project (B) 5.0 1 2 0 3 4 1.2 3.0 5.0 0 1 2 3 4 1.8 4.5 1 2 0 3 4 1.1 2.5 4.5 0 1 2 3 4 1.4 PI(B) > PI(A) & CR(B)>CR(A) Project B is better than project A Capitalization Rate = Annual Net Income / Initial Capital Cost = 1.4 / 4.5 = 0.311 = 31.1% Capitalization Rate = Annual Net Income / Initial Capital Cost = 1.8/5.0 = 0.36 = 36% NPV (cash inflow) = = 1.4/(1.12) + 1.4/(1.12)^2 + 1.4/(1.12)^3 + 1.4/(1.2)^4 = 4.25 Profitability Index = NPV (cash inflow) / Initial Capital Cost = 4.25 /4.5 = 0.94 Profitability Index = = 5.47 /5.0 = 1.094 NPV (cash inflow) = 1.8/(1.12) + 1.8/(1.12)^2 + 1.8/(1.12)^3 + 1.8/(1.12)^4 = 5.47
  • 139. PM 139 Cost Management Best Practice - Dr. Attia Gomaa - 2018 Hotel Cap Rate Net Operating Income $1,953,930 Total Development Cost $12,192,731 Cap Rate 16%
  • 140. PM 140 Cost Management Best Practice - Dr. Attia Gomaa - 2018 Project (B) Project (A) Item 5.0 4.5 Initial Investment; M$ 1.2 1.1 Annual Running Cost; M$/year 3.0 2.5 Annual Revenue; M$/year - - Salvage Value; M$ 4 4 Project Life; years Based on this information, discuss the following: 1. Cash Flow Diagram 2. Profitability Index 3. Capitalization Rate 4. Which offer should you accept and why? Bank interest rate 12% A manager is trying to decide between two projects (A or B): Example:
  • 141. PM 141 Cost Management Best Practice - Dr. Attia Gomaa - 2018 Project (A) Project (B) 5.0 1 2 0 3 4 1.2 3.0 5.0 0 1 2 3 4 1.8 4.5 1 2 0 3 4 1.1 2.5 4.5 0 1 2 3 4 1.4 PI(B) > PI(A) & CR(B)>CR(A) Project B is better than project A Capitalization Rate = Annual Net Income / Initial Capital Cost = 1.4 / 4.5 = 0.311 = 31.1% Capitalization Rate = Annual Net Income / Initial Capital Cost = 1.8/5.0 = 0.36 = 36% NPV (cash inflow) = = 1.4/(1.12) + 1.4/(1.12)^2 + 1.4/(1.12)^3 + 1.4/(1.12)^4 = 4.25 Profitability Index = NPV (cash inflow) / Initial Capital Cost = 4.25 /4.5 = 0.94 Profitability Index = = 5.47 /5.0 = 1.094 NPV (cash inflow) = 1.8/(1.12) + 1.8/(1.12)^2 + 1.8/(1.12)^3 + 1.8/(1.12)^4 = 5.47
  • 142. PM 142 Cost Management Best Practice - Dr. Attia Gomaa - 2018 Project (B) Project (A) Item 5.0 4.5 Initial Investment; M$ 1.2 1.1 Annual Running Cost; M$/year 3.0 2.5 Annual Revenue; M$/year 1.2 1.1 Salvage Value; M$ 4 4 Project Life; years Based on this information, discuss the following: 1. Cash Flow Diagram 2. Profitability Index 3. Capitalization Rate 4. Which offer should you accept and why? Bank interest rate 12% A manager is trying to decide between two projects (A or B): Example:
  • 143. PM 143 Cost Management Best Practice - Dr. Attia Gomaa - 2018 Project (A) Cash Flow Diagram: Project (B) NPV (cash inflow) = = 1.4/(1.12) + 1.4/(1.12)^2 + 1.4/(1.12)^3 + 2.5/(1.2)^4 = 4.95 Profitability Index = NPV (cash inflow) / Initial Capital Cost = 4.95/4.5 = 1.10 Profitability Index = = 6.23/5.0 = 1.25 5.0 1 2 0 3 4 1.2 3.0 1.2 5.0 0 1 2 3 4 1.8 1.2 4.5 1 2 0 3 4 1.1 2.5 1.1 4.5 0 1 2 3 4 1.4 1.1 PI(B) > PI(A) Project B is better than project A NPV (cash inflow) = 1.8/(1.12) + 1.8/(1.12)^2 + 1.8/(1.12)^3 + 3.0/(1.12)^4 = 6.23
  • 144. PM 144 Cost Management Best Practice - Dr. Attia Gomaa - 2018 Project (A) Cash Flow Diagram: Project (B) NPV (cash inflow) = 4.95 Annual Net Income = (A/P, i, n) = {i (1+i)n } / {(1+i)n -1} = 4.95 *0.12*(1.12)^4 / (1.12^4-1) = 1.63 5.0 1 2 0 3 4 1.2 3.0 1.2 5.0 0 1 2 3 4 1.8 1.2 4.5 1 2 0 3 4 1.1 2.5 1.1 4.5 0 1 2 3 4 1.4 1.1 CR(B) > CR(A) Project B is better than project A NPV (cash inflow) = 6.23 = 6.23 *0.12*(1.12)^4 / (1.12^4-1) = 2.05 Capitalization Rate = Annual Net Income / Initial Capital Cost = 1.63 / 4.5 = 0.36 = 36% Capitalization Rate = = 2.05 / 5.0 = 0.41 = 41%
  • 145. PM 145 Cost Management Best Practice - Dr. Attia Gomaa - 2018 Economic Service Life for a Lift Truck Element Life; Year 0 1 2 3 4 5 6 7 Initial Cost; $ 20000 O&M; $ 1000 + 15% Annual Capital Maintenance; $ 2000 Book Value; $ 15000 11000 8000 6000 5000 4000 2000 Interest rate 15% Replacement Analysis: Based on this information; What is the economic life of a lift truck? Example: Annual Equivalent Cost (AEC)
  • 146. PM 146 Cost Management Best Practice - Dr. Attia Gomaa - 2018 AEC1 = x (A/P,15%,1) 20,000 - 14,000 (P/F,15%,1) i = 15% 0 20 1 1 15 Annual Equivalent Cost (AEC)
  • 147. PM 147 Cost Management Best Practice - Dr. Attia Gomaa - 2018 AEC2 = x (A/P,15%,2) 20,000 + 1,000 (P/F,15%,1) - 9,850 (P/F,15%,2) i = 15% 0 20 1 1 2 1.15 11
  • 148. PM 148 Cost Management Best Practice - Dr. Attia Gomaa - 2018 AEC3 = x (A/P,15%,3) 20,000 + 1,000 (P/F,15%,1) + 1,150 (P/F,15%,2) - 6,700 (P/F,15%,3) i = 15% 0 20 1 1 2 1.15 3 8 1.3
  • 149. PM 149 Cost Management Best Practice - Dr. Attia Gomaa - 2018 AEC4 = x (A/P,15%,4) 20,000 + 1,000 (P/F,15%,1) + 1,150 (P/F,15%,2) + 1,300 (P/F,15%,3) - 4,550 (P/F,15%,4) 0 20 1 1 2 1.15 3 4 1.3 6 1.45 i = 15%
  • 150. PM 150 Cost Management Best Practice - Dr. Attia Gomaa - 2018 AEC5 = x (A/P,15%,5) 20,000 + 1,000 (P/F,15%,1) + 1,150 (P/F,15%,2) + 1,300 (P/F,15%,3) + 1,450 (P/F,15%,4) - 1,400 (P/F,15%,5) 0 20 1 1 2 1.15 3 4 5 1.3 1.45 1.6 2 5 i = 15%
  • 151. PM 151 Cost Management Best Practice - Dr. Attia Gomaa - 2018 AEC6 = x (A/P,15%,6) 20,000 + 1,000 (P/F,15%,1) + 1,150 (P/F,15%,2) + 1,300 (P/F,15%,3) + 1,450 (P/F,15%,4) + 3,600 (P/F,15%,5) - 2,250 (P/F,15%,6) 0 20 1 1 2 1.15 3 4 5 1.3 1.45 1.6 1.75 2 4 i = 15%
  • 152. PM 152 Cost Management Best Practice - Dr. Attia Gomaa - 2018 AEC7 = x (A/P,15%,7) 20,000 + 1,000 (P/F,15%,1) + 1,150 (P/F,15%,2) + 1,300 (P/F,15%,3) + 1,450 (P/F,15%,4) + 3,600 (P/F,15%,5) + 1,750 (P/F,15%,6) - 100 (P/F,15%,7) 0 20 1 1 2 1.15 3 4 5 6 1.3 1.45 1.6 1.75 7 2 1.9 2 i = 15%
  • 153. PM 153 Cost Management Best Practice - Dr. Attia Gomaa - 2018 Economic Life for truck 6 Years AEC Year 9000 1 8225 2 7592 3 7003 4 6780 5 6405 6 6852 7 Year AEC Summary:
  • 154. PM 154 Cost Management Best Practice - Dr. Attia Gomaa - 2018 Economic Service Life for a compressor Life; Year 0 1 2 3 4 5 6 7 Initial Cost; $ 18000 O&M; $ 1000 + 15% Annual Capital Maint.; $ 3000 4500 Book Value; $ 10000 7500 5625 1780 Interest rate 15% Based on this information; What is the economic life of this compressor? Example:
  • 155. PM 155 Cost Management Best Practice - Dr. Attia Gomaa - 2018 Economic Service Life • N = 1 AEC1 = $18,000(A/P, 15%, 1) + $1,000 - $10,000 = $11,700
  • 156. PM 156 Cost Management Best Practice - Dr. Attia Gomaa - 2018 • N = 2 AEC2 = [$18,000 + $1,000(P/A,15%, 15%, 2)](A/P, 15%, 2) - $7,500 (A/F, 15%, 2) = $8,653
  • 157. PM 157 Cost Management Best Practice - Dr. Attia Gomaa - 2018 N = 3, AEC3 = $7,406 N = 4, AEC4 = $6,678 N = 5, AEC5 = $6,642 N = 6, AEC6 = $6,258 N = 7, AEC7 = $6,394 Minimum cost Economic Service Life
  • 158. PM 158 Cost Management Best Practice - Dr. Attia Gomaa - 2018 Economic Service Life for a car Element Life; Year 0 1 2 3 4 5 6 Initial Cost 150000 O&M 2000 first year (+500 Annual) Capital Maintenance 10000 Book Value 120000 100000 80000 60000 80000 60000 Interest rate 15% Based on this information; What is the economic life of this car? Replacement Analysis: Example : Annual Equivalent Cost (AEC)
  • 159. PM 159 Cost Management Best Practice - Dr. Attia Gomaa - 2018 ID Activity Length (m) A Line A 400 B Line B 300 C Line C 1000 D Line D 1200 E Line E 1600 F Line F 400 G Line G 800 Resources: Crew productivity = 200 m/day Average material cost = 10 $/m Item : Water Pipeline Network A B C D E F G Source Source Source Process Process Project Sketch Constraints: Maximum duration = 17 day Maximum number of crew = 4 Cost : Average crew cost rate= 100 $/day Margin factor= 30% from direct cost (Predecessor, Duration, Resources)? (Target Schedule)? (Target Resource Plan)? Based on this information, discuss the following: Project Cost Analysis
  • 160. PM 160 Cost Management Best Practice - Dr. Attia Gomaa - 2018 Day Crews Day Pre. ID 17 16 15 14 13 12 11 10 9 8 7 6 5 4 3 2 1 A B C D E F G Number of Crews (Target Schedule) Project Constraints: Maximum duration = 17 day Maximum number of crew = 4
  • 161. PM 161 Cost Management Best Practice - Dr. Attia Gomaa - 2018 ID Name Pred. Duration (Day) Number of Crews Material Cost, $ A Line A - 2 2 4000 B Line B - 3 1 3000 C Line C - 5 2 10000 D Line D A,B 6 2 12000 E Line E C 8 2 16000 F Line F C 2 2 4000 G Line G D,E 4 2 8000 Item : Water Pipeline Network Constraints: Maximum duration = 17 day Maximum number of crew = 4 Based on this information, discuss & analysis the following: 1) Network (Logic & Risk) 2) Gantt Chart (Target Schedule) 3) Workers Profile (Target Resource Plan) 4) Cost Analysis (Target Cost Plan) 5) Cash In/ Out Analysis (Payment / Cost) A B C D E F G Source Source Source Process Process Payment Plan: 1) 25% Down Payment 2) 25% After One Week 3) 25% After Two Weeks 4) 25% Final Payment Project Sketch Cost : Average crew cost rate= 100 $/day Margin factor= 30% from direct cost
  • 162. PM 162 Cost Management Best Practice - Dr. Attia Gomaa - 2018 Day Crews Day Pre. ID 17 16 15 14 13 12 11 10 9 8 7 6 5 4 3 2 1 2 2 2 2 - A 1 1 1 1 3 - B 2 2 2 2 2 2 5 - C 2 2 2 2 2 2 2 6 A,B D 2 2 2 2 2 2 2 2 2 8 C E 2 2 2 2 C F 2 2 2 2 2 4 D,E G 2 2 2 2 4 4 4 4 4 4 4 4 3 3 3 4 4 Number of Crews (Target Schedule) Project Constraints: Maximum duration = 17 day Maximum number of crew = 4
  • 163. PM 163 Cost Management Best Practice - Dr. Attia Gomaa - 2018 Day Crews Day Pre. ID 17 16 15 14 13 12 11 10 9 8 7 6 5 4 3 2 1 2 2 2 2 - A 1 1 1 1 3 - B 2 2 2 2 2 2 5 - C 2 2 2 2 2 2 2 6 A,B D 2 2 2 2 2 2 2 2 2 8 C E 2 2 2 2 C F 2 2 2 2 2 4 D,E G 2 2 2 2 4 4 4 4 4 4 4 4 4 4 3 3 3 Number of Crews (Target Schedule) Project Constraints: Maximum duration = 17 day Maximum number of crew = 4
  • 164. PM 164 Cost Management Best Practice - Dr. Attia Gomaa - 2018 Network Analysis: A B C D G E F Start Finish Day Pred. (FS=0) ID 2 - A 3 - B 5 - C 6 A,B D 8 C E 2 C F 4 D,E G EF d ES Activity ID LF TF LS 3 B 6 D 2 A 5 C 8 E 2 F 4 G 0 Start 0 Finish
  • 165. PM 165 Cost Management Best Practice - Dr. Attia Gomaa - 2018 Network Analysis: 0 3 3 B 4 4 7 3 6 9 D 7 4 13 0 2 2 A 5 5 7 0 5 5 C 0 0 5 5 8 13 E 5 0 13 5 2 7 F 15 10 17 13 4 17 G 13 0 17 Planned Duration = 17 Critical Path: C-E-G It is recommended that “Delay risk analysis” be considered for critical and near- critical path work in the schedule because such work carries the greatest likelihood of affecting timely completion EF d ES Activity ID LF TF LS 0 Start 0 17 Finish 17
  • 166. PM 166 Cost Management Best Practice - Dr. Attia Gomaa - 2018 Project Constraints: Maximum duration = 17 day Maximum number of crew = 4
  • 167. PM 167 Cost Management Best Practice - Dr. Attia Gomaa - 2018
  • 168. PM 168 Cost Management Best Practice - Dr. Attia Gomaa - 2018
  • 169. PM 169 Cost Management Best Practice - Dr. Attia Gomaa - 2018 Cash In/ Out Analysis
  • 170. PM 170 Cost Management Best Practice - Dr. Attia Gomaa - 2018 ID Activity Pred. Normal Crashing Material Cost, $ Duration (Day) Number of Crews Duration (Day) Number of Crews A Line A - 2 2 1 4 4000 B Line B - 3 1 2 2 3000 C Line C - 5 2 - - 10000 D Line D A,B 6 2 4 4 12000 E Line E C 8 2 6 3 16000 F Line F C 2 2 - - 4000 G Line G D,E 4 2 3 3 8000 Item : Water Pipeline Network Constraints: Maximum duration = 17 day Maximum number of crew = 4 Cost : Average Crew Cost Rate = 100 $/day Margin Factor = 30% direct cost
  • 171. PM 171 Cost Management Best Practice - Dr. Attia Gomaa - 2018 Day Crews Day Pre. ID 17 16 15 14 13 12 11 10 9 8 7 6 5 4 3 2 1 2 2 2 2 - A 1 1 1 1 3 - B 2 2 2 2 2 2 5 - C 2 2 2 2 2 2 2 6 A,B D 2 2 2 2 2 2 2 2 2 8 C E 2 2 2 2 C F 2 2 2 2 2 4 D,E G 2 2 2 2 4 4 4 4 4 4 4 4 4 4 3 3 3 Number of Crews (Target Schedule) Normal : 17 day & 57 crew-day Project Constraints: Maximum duration = 17 day Maximum number of crew = 4
  • 172. PM 172 Cost Management Best Practice - Dr. Attia Gomaa - 2018 Day Crews Day Pre. ID 17 16 15 14 13 12 11 10 9 8 7 6 5 4 3 2 1 2 2 2 2 - A 1 1 1 1 3 - B 2 2 2 2 2 2 5 - C 2 2 2 2 2 2 2 6 A,B D 2 2 2 2 2 2 2 2 2 8 C E 2 2 2 2 C F 3 3 3 2 4 D,E G 3 3 3 4 4 4 4 4 4 4 4 4 4 3 3 3 Number of Crews (Target Schedule) #2 : 16 day & 58 crew-day Project Constraints: Maximum duration = 17 day Maximum number of crew = 4
  • 173. PM 173 Cost Management Best Practice - Dr. Attia Gomaa - 2018 ID Activity Pred. Normal Crashing Material Cost, $ Duration (Day) Number of Crews Duration (Day) Number of Crews A Line A - 2 2 1 4 4000 B Line B - 3 1 2 2 3000 C Line C - 5 2 - - 10000 D Line D A,B 6 2 4 4 12000 E Line E C 8 2 6 3 16000 F Line F C 2 2 - - 4000 G Line G D,E 4 2 3 3 8000 Item : Water Pipeline Network Constraints: Maximum duration = 17 day Number of crew = Open Cost : Average Crew Cost Rate = 100 $/day Margin Factor = 30% direct cost
  • 174. PM 174 Cost Management Best Practice - Dr. Attia Gomaa - 2018 Day Crews Day Pre. ID 17 16 15 14 13 12 11 10 9 8 7 6 5 4 3 2 1 2 2 2 2 - A 1 1 1 1 3 - B 2 2 2 2 2 2 5 - C 2 2 2 2 2 2 2 6 A,B D 3 3 3 3 3 3 2 8 C E 2 2 2 2 C F 3 3 3 2 4 D,E G 3 5 5 5 5 5 5 5 5 4 4 3 3 3 Number of Crews (Target Schedule) #3 : 14 day & 60 crew-day Project Constraints: Maximum duration = 17 day Maximum number of crew = Open
  • 175. PM 175 Cost Management Best Practice - Dr. Attia Gomaa - 2018 Day Crews Day Pre. ID 17 16 15 14 13 12 11 10 9 8 7 6 5 4 3 2 1 2 2 2 2 - A 1 1 1 1 3 - B 2 2 2 2 2 2 5 - C 2 2 2 2 2 2 2 6 A,B D 3 3 3 3 3 3 2 8 C E 2 2 2 2 C F 3 3 3 2 4 D,E G 3 5 5 5 5 5 5 5 5 2 2 5 5 3 Number of Crews (Target Schedule) #4 : 14 day & 60 crew-day Project Constraints: Maximum duration = 17 day Maximum number of crew = Open
  • 176. PM 176 Cost Management Best Practice - Dr. Attia Gomaa - 2018 Day Crews Day Pre. ID 17 16 15 14 13 12 11 10 9 8 7 6 5 4 3 2 1 2 2 2 2 - A 1 1 1 1 3 - B 2 2 2 2 2 2 5 - C 2 2 2 2 2 2 2 6 A,B D 3 3 3 3 3 3 2 8 C E 2 2 2 2 C F 3 3 3 2 4 D,E G 3 5 5 5 5 5 5 5 5 5 5 3 2 2 Number of Crews (Target Schedule) #3 : 14 day & 60 crew-day Project Constraints: Maximum duration = 17 day Maximum number of crew = Open
  • 177. PM 177 Cost Management Best Practice - Dr. Attia Gomaa - 2018 Example; Building Direct Cost $ Predecessor Duration (weeks) ID 15,000 - 5 A 30,000 - 3 B 33,000 A 8 C 42,000 A 7 D 57,000 - 7 E 61,000 C, E 4 F 72,000 F 5 G Based on this information, discuss & analysis the following: 1) Network 2) Gantt Chart 3) Cost Analysis 4) Cost Smoothing 5) Cash Flow (In/ Out) Analysis Payment Conditions: 1) 25% Down Payment 2) 25% After 8 Weeks 3) 25% After 16 Weeks 4) 25% Final Payment Project Cost Analysis Planned Duration = 22 weeks Margin Factor = 30% from direct cost
  • 178. PM 178 Cost Management Best Practice - Dr. Attia Gomaa - 2018 Logic Diagram: E Start Finish A B D C F G
  • 179. PM 179 Cost Management Best Practice - Dr. Attia Gomaa - 2018 Network Analysis: 5 A 0 Start Finish 8 C 7 E 4 F 7 D 5 G 3 B
  • 180. PM 180 Cost Management Best Practice - Dr. Attia Gomaa - 2018 Weeks Pred Day ID 22 21 20 19 18 17 16 15 14 13 12 11 10 9 8 7 6 5 4 3 2 1 - 5 A - 3 B A 8 C A 7 D - 7 E C, E 4 F F 5 G
  • 181. PM 181 Cost Management Best Practice - Dr. Attia Gomaa - 2018 Project Co$t Control Cost Control Actual Performance Planned Performance KPIs report (Earned Value Analysis)
  • 182. PM 182 Cost Management Best Practice - Dr. Attia Gomaa - 2018 Project: Office Building Item (main activity): Excavation works Brainstorming: Project Control Actual Performance (Status Report after 6 days): Actual Quantity = 320 m3 Actual Cost = 3300 $ Planned Performance (Baseline): Bill of Quantity (BOQ) = 500 m3 Unit Price = 10 $/m3 Duration = 10 day Control
  • 183. PM 183 Cost Management Best Practice - Dr. Attia Gomaa - 2018 Project: Office Building Item (main activity): Excavation works Brainstorming: Project Control Actual Performance (Status Report after 6 days): Actual Quantity = 320 m3 Actual Cost = 3300 $ Planned Performance (Baseline): Bill of Quantity (BOQ) = 500 m3 Unit Cost = 10 $/m3 Duration = 10 day Daily Performance = 500 / 10 = 50 m3/day Control Planned Performance after 6 days: Panned Quantity = 50*6 = 300 m3 Planned Cost = 10*300 = 3000 $ Analysis: Quantity Variance = 320 – 300 = + 20 Ahead Cost Variance = 320*10 – 3300 = - 100 Over budget
  • 184. PM 184 Cost Management Best Practice - Dr. Attia Gomaa - 2018 Project Cost Control Cost control is a Part of Cost Management. 70% of projects are over budget and/or behind schedule 52% of all projects finish at 189% of their initial budget 30% of completed projects have a cost variance of >10% 50% of completed projects have a schedule variance of >10% (Earned Value Analysis) (1) (2) (3) (4)
  • 185. PM 185 Cost Management Best Practice - Dr. Attia Gomaa - 2018 Earned Value Management (EVM) EVM is a cost management technique where the value of completed work is compared to actual costs and the scheduled costs EVM is a project management tool that integrates the project performance with schedule and cost elements. Earned Value Management Systems measure progress
  • 186. PM 186 Cost Management Best Practice - Dr. Attia Gomaa - 2018 Schedule Variance Cost Variance Schedule Performance Index Cost Performance Index Planned Value = PV = BCWS (Budget Cost for the Work Schedule)  Base line Actual Cost = AV = ACWP (Actual Cost for the Work Performed)  Actual Earned Value = EV = BCWP (Budget Cost for the Work Performed)  Invoice Earned Value Analysis
  • 187. PM 187 Cost Management Best Practice - Dr. Attia Gomaa - 2018 • Schedule Variance SV = BCWP – BCWS (>0 is ahead, 0 is on target, <0 is behind) • Schedule Performance Index SPI = BCWP/BCWS (>1 is ahead, 1 is on target, <1 is behind) • Cost Variance CV = BCWP – ACWP (>0 is under-run, 0 is on target, <0 is overrun) • Cost Performance Index CPI = BCWP/ACWP (>1 is under-run, 1 is on target, <1 is over-run) Earned Value Analysis
  • 188. PM 188 Cost Management Best Practice - Dr. Attia Gomaa - 2018 Project: Office Building Item (main activity): Excavation works Brainstorming: Project Control Actual Performance (Status Report after 6 days): Actual Quantity = 320 m3 Actual Cost = 3300 $ Planned Performance (Baseline): Bill of Quantity (BOQ) = 500 m3 Unit Price = 10 $/m3 Duration = 10 day Control
  • 189. PM 189 Cost Management Best Practice - Dr. Attia Gomaa - 2018 Project: Office Building Item (main activity): Excavation works Brainstorming: Project Control Actual Performance (Status Report after 6 days): Actual Quantity = 320 m3 WP Actual Cost = 3300 $ ACWP Actual Cost Rate (AC) = 10.3 $/m3 AC Planned Performance (Baseline): Bill of Quantity (BOQ) = 500 m3 WS Unit Price = 10 $/m3 BC Duration = 10 day Control Actual Value (ACWP) = 3300 $ Planned Value (BCWS) = 3000 $ Earned Value (BCWP) = 3200 $ After 6 days:
  • 190. PM 190 Cost Management Best Practice - Dr. Attia Gomaa - 2018 Project: Office Building Item: Excavation works Brainstorming: Project Control Actual Value (ACWP) = 3300 $ Planned Value (BCWS) = 3000 $ Control Earned Value (BCWP) = 3200 $ • Cost variance: • BCWP – ACWP =3200 – 3300 = -100 $ (Overrun) • Cost Performance Index: CPI = BCWP/ACWP = 3200/3300 =0.97 = 97% • Schedule variance: • BCWP – BCWS = 3200 – 3000 = +200 $ (ahead) • Schedule Performance Index: SPI = BCWP/BCWS = 3200/3000 =1.07 = 107%
  • 191. PM 191 Cost Management Best Practice - Dr. Attia Gomaa - 2018 Project: Gas Pipeline Activity: Excavation Bill of Quantity (BOQ) = 500 m3 Unit Price = 10 LE/m3 Duration= 10 day Status Report after 6 day: Actual Quantity = 320 m3 Actual Cost = 3300 LE Example: 6 day $ BAC = 5000 CV = - 100 SV = + 200 10 day Ahead of schedule •Over –run cost •Ahead of schedule
  • 192. PM 192 Cost Management Best Practice - Dr. Attia Gomaa - 2018 Project: Office Building Item (main activity): Excavation works Planned Performance (Baseline): Bill of Quantity (BOQ) = 600 m3 Unit Price = 10 $/m3 Duration = 10 day Actual Performance (Status Report after 6 days): Actual Quantity = 300 m3 Actual Cost = 3300 $ Brainstorming: Earned Value Analysis Based on this information, calculate and analyze the following: a) What is the cost variance? b) What is the Schedule variance? c) What is the Cost Performance Index? d) What is the Schedule Performance Index? e) How would you describe this project?
  • 193. PM 193 Cost Management Best Practice - Dr. Attia Gomaa - 2018 Project: Office Building Item: Excavation works Brainstorming: Project Control Actual Value (ACWP) = 3300 Planned Value (BCWS) = 3600 Earned Value (BCWP) = 3000 • Cost variance: • BCWP – ACWP = 3000 – 3300 = -300 • Cost Performance Index: CPI = BCWP/ACWP = 3000 / 3300 = 91% (Overrun) • Schedule variance: • BCWP – BCWS = 3000 – 3600 = - 600 • Schedule Performance Index: SPI = BCWP/BCWS = 3000 / 3600 = 83% (Behind) After 6 days:
  • 194. PM 194 Cost Management Best Practice - Dr. Attia Gomaa - 2018 Project: Office Building Item (main activity): Excavation works Planned Performance (Baseline): Bill of Quantity (BOQ) = 600 m3 Unit Price = 10 $/m3 Duration = 10 day Actual Performance (Status Report after 6 days): Actual Quantity = 300 m3 Actual Cost = 3300 $ Brainstorming: Earned Value Analysis Based on this information, calculate and analyze the following: a) What is the cost variance? b) What is the Schedule variance? c) What is the Cost Performance Index? d) What is the Schedule Performance Index? e) How would you describe this project?
  • 195. PM 195 Cost Management Best Practice - Dr. Attia Gomaa - 2018 A construction project has a total budget (BAC) of $300,000 and the total duration of 12 months. After 4 months, the cost control revealed the following figures: • Actual Cost of Work Performed (ACWP) = $ 110,000 • Budgeted Cost of Work Scheduled (BCWS) = $ 100,000 • Budgeted Cost of Work Performed (BCWP) = $ 90,000 a) Calculate the CPI and SPI b) Calculate the Estimate At Completion (EAC) if the project will continue to perform in the same way c) Calculate the EAC if the project cost performance improved in the remaining period by 10% Example:
  • 196. PM 196 Cost Management Best Practice - Dr. Attia Gomaa - 2018 A construction project has a total budget of $300,000 and the total duration of 12 months. After 4 months, the cost control revealed the following figures: • Actual Cost of Work Performed (ACWP) = $ 110,000 • Budgeted Cost of Work Scheduled (BCWS) = $ 100,000 • Budgeted Cost of Work Performed (BCWP) = $ 90,000 a) Calculate the CPI and SPI b) Calculate the EAC if the project will continue to perform in the same way c) Calculate the EAC if the project cost performance improved in the remaining period by 10% CPI = BCWP / ACWP = 90,000 / 110,000 = 0.818 < 1 Over budget SPI = BCWP / BCWS = 90,000 / 100,000 = 0.90 < 1 Behind schedule Estimate At Completion (EAC) = BAC/CPI = 300000/0.818= 366,748 Improve  Corrective Actions  Improve CPI by 10% Improve CPI by 10%  New CPI = 0.818 *1.1 = 0.8998 (Expected) New (EAC) = AC + {(BAC – EV) / CPI} =110,000 + (300,000 – 90,000) / 0.8998 = $ 343,385
  • 197. PM 197 Cost Management Best Practice - Dr. Attia Gomaa - 2018
  • 198. PM 198 Cost Management Best Practice - Dr. Attia Gomaa - 2018 A construction project has a total budget (BAC) of $300,000 and the total duration of 12 months. After 8 months, the cost control revealed the following figures: • Actual Cost of Work Performed (ACWP) = $ 215,000 • Budgeted Cost of Work Scheduled (BCWS) = $ 200,000 • Budgeted Cost of Work Performed (BCWP) = $ 190,000 a) Calculate the CPI and SPI b) Calculate the Estimate At Completion (EAC) if the project will continue to perform in the same way c) Calculate the EAC if the project cost performance improved in the remaining period by 10% Next:
  • 199. PM 199 Cost Management Best Practice - Dr. Attia Gomaa - 2018
  • 200. PM 200 Cost Management Best Practice - Dr. Attia Gomaa - 2018 A construction project has a total budget (BAC) of $300,000 and the total duration of 12 months. After 8 months, the cost control revealed the following figures: • Actual Cost of Work Performed (ACWP) = $ 215,000 • Budgeted Cost of Work Scheduled (BCWS) = $ 200,000 • Budgeted Cost of Work Performed (BCWP) = $ 190,000 a) Calculate the CPI and SPI b) Calculate the EAC if the project will continue to perform in the same way c) Calculate the EAC if the project cost performance improved in the remaining period by 10% CPI = BCWP / ACWP = 190,000 / 215,000 = 0.884 < 1 (Overrun) SPI = BCWP / BCWS = 190,000 / 200,000 = 0.95 < 1 (Behind) Estimate At Completion (EAC) = BAC/CPI = 300,000/0.884 = 340,909  Corrective Actions  Improve CPI by 10% New CPI = 0.884 *1.1 = 0.968 New (EAC) = AC + {(BAC – EV) / CPI} = 215,000 + (300,000 – 190,000)/0.968 = 335,743
  • 201. PM 201 Cost Management Best Practice - Dr. Attia Gomaa - 2018 A construction project has a total budget (BAC) of $300,000 and the total duration of 12 months. After 13 months (closeout), the cost control revealed the following figures: • Actual Cost of Work Performed (ACWP) = $ 340,000 • Budgeted Cost of Work Scheduled (BCWS) = $ 300,000 • Budgeted Cost of Work Performed (BCWP) = $ 310,000 a) Calculate the CPI and SPI CPI = BCWP / ACWP = 310,000 / 340,000 = 0.912 < 1 (overrun by 8.8%) SPI = BCWP / BCWS = 310,000 / 300,000 = 1.03 > 1 (Ahead by 3%) Closing:
  • 202. PM 202 Cost Management Best Practice - Dr. Attia Gomaa - 2018 Summary Report: A construction project has a total budget (BAC) of $300,000 and the total duration of 12 months. Period (months) 4 8 13 Planned Value (PV = BCWS) 100,000 200,000 300,000 Actual Value (AV = ACWP) 110,000 215,000 340,000 Earned Value (EV =BCWP) 90,000 190,000 310,000 CPI = BCWP / ACWP SPI = BCWP / BCWS Estimate At Completion (EAC) = BAC/CPI
  • 203. PM 203 Cost Management Best Practice - Dr. Attia Gomaa - 2018 Period #1 #2 #3 #4 #5 #6 #7 #8 #9 #10 BAC $1,230 $1,230 $1,230 $1,230 $1,400 $1,400 $1,400 $1,400 $1,400 $1,400 EV $100 $200 $300 $450 $750 $800 $1,125 $1,200 $1,400 $1,400 AC $100 $205 $315 $600 $800 $1,000 $1,200 $1,350 $1,475 $1,525 PV $100 $220 $325 $550 $725 $925 $1,175 $1,275 $1,450 $1,500 Period #1 #2 #3 #4 #5 #6 #7 #8 #9 #10 CV $0 ($5) ($15) ($150) ($50) ($200) ($75) ($150) ($75) ($125) SV $0 ($20) ($25) ($100) $25 ($125) ($50) ($75) ($50) ($100) CPI 1.00 0.98 0.95 0.75 0.94 0.80 0.94 0.89 0.95 0.92 SPI 1.00 0.91 0.92 0.82 1.03 0.86 0.96 0.94 0.97 0.93 ETC $1,130 $1,056 $977 $1,040 $693 $750 $293 $225 $0 $0 EAC $1,230 $1,261 $1,292 $1,640 $1,493 $1,750 $1,493 $1,575 $1,475 $1,525 VAC $0 ($31) ($62) ($410) ($93) ($350) ($93) ($175) ($75) ($125) Excel File: ($1000) Analysis:
  • 204. PM 204 Cost Management Best Practice - Dr. Attia Gomaa - 2018
  • 205. PM 205 Cost Management Best Practice - Dr. Attia Gomaa - 2018
  • 206. PM 206 Cost Management Best Practice - Dr. Attia Gomaa - 2018
  • 207. PM 207 Cost Management Best Practice - Dr. Attia Gomaa - 2018
  • 208. PM 208 Cost Management Best Practice - Dr. Attia Gomaa - 2018 BCWS ACWP BCWP Late Item Planned Value (BCWS) Actual Cost (ACWP) Earned Value (BCWP) #1 3000000 3080000 2800000 #2 250000 210000 175000 #3 500000 468000 520000 #4 100000 88000 80000 Item BCWS ACWP BCWP SV SPI CV CPI Comments Schedule Cost #1 3000000 3080000 2800000 -200000 0.93 -280000 0.91 Behind 7% Over run 9% #2 250000 210000 175000 -75000 0.70 -35000 0.83 Behind 30% Over run 17% #3 500000 468000 520000 20000 1.04 52000 1.11 Ahead 4% Under run 11% #4 100000 88000 80000 -20000 0.80 -8000 0.91 Behind 20% Over run 9% Total 3850000 3846000 3575000 -275000 0.93 -271000 0.93 Behind 7% Over run 7% EVM Report: Project: A Construction Project
  • 209. PM 209 Cost Management Best Practice - Dr. Attia Gomaa - 2018
  • 210. PM 210 Cost Management Best Practice - Dr. Attia Gomaa - 2018 √ X
  • 211. PM 211 Cost Management Best Practice - Dr. Attia Gomaa - 2018
  • 212. PM 212 Cost Management Best Practice - Dr. Attia Gomaa - 2018 Activity ID Planned Cost Planned Date Actual Performance at period #10 Start Finish A 4000 1 4 Completed B 10000 3 6 Completed C 12000 6 9 In Progress D 4000 9 12 In Progress G 6000 9 12 Not Started H 6000 11 14 Not Started I 10000 14 17 Not Started Project Status Report: Case Study: Based on this information; discuss the earned value analysis using the 50-50 rule?