(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
PM Project group 4.pptx
1. PROJECT MANAGEMENT GROUP ASSIGNMENT
ON
KOCHI METRO RAIL CORPORATION
Presented by (Group 4)
Ankit Kumar – 140006
Kumar Anand – 140019
Ruby Ruchi – 140031
Supriya Jaiswal – 140042
2.
3. ABOUT PROJECT
Kochi Metro is a proposed rapid transit system for the
city of Kochi in Kerala, India. The 25.65km metro line
will run from Aluva to Petta and will include 22
stations.
The $950m project will be operated by Kochi Metro
Rail Ltd. (KMRL), a joint venture between the Central
and State governments of India.
4. COST OF PROJECT
• The total cost of Kochi metro project is Rs. 5,181.79 crore (US$
943.09 million)
• Central government – Rs. 1,002.23 crore (US$ 182.41 million)
• State government – Rs. 1,772.23 crore (US$ 322.55 million)
• Japan international cooperation agency (JICA) – Rs. 2,174 crore
(US$ 395.67 million)
• JICA has agreed to offer loan at 1.50% interest rate
• Cost Allocated For Construction of Stations Is 220Cr. ( way side
civil A )
5. PROJECT TIMELINES
Sr No. Items of work Completion date
1 Obtain central government clearance 30/11/2011
2 Finalization of major contracts 29/02/2012
3 Execution of works and procurement of
equipment's, coaches and installations
01/04/2012 – 31/12/2015
4 Testing and Commissioning 01/01/2016 – 31/03/2016
5 Revenue Operation 31/03/2016
6.
7. WORK BREAKDOWN STRUCTURE
• Main steps involves in station construction project are
• 1. Road winding, barricading and temporary street lighting.
• 2. Piling
• 3. Pile caps
• 4. Construction of main column (stage1)
• 5. Longitudinal and precast beam
• 6. Construction of main column (stage2)
• 7. Construction of Transvers Beam
• 8. RCC work for Track Slab
• 9. Construction of Outer Column up to Platform Beam
• 10. Erection of Roof
• 11. Finishing.
9. Risk associated with project
• Timing delays
• Weather risk
• Grid connection delays
• Staff and equipment availability
• Transportation
• Ground conditions
• Environmental or health and safety incidents
• Public protests
• Covid-19 Pandemic
• Political Agenda – Due to differences between the ruling party of
state and Centre there is an obvious delay in the project.
• Unavailability of Fund – The project requires very high funding of RS
63000 cr. and due to the delays, the investors are getting cold feet
some have even withdrawn from the project.
10. Recommendations
• It is recommended to construct Metro Stations Near
Beaches so it would be benefitted for tourist also.
• A series of meetings/discussions/presentations
happened with Railways and GOK authorities.
• Government should keep in check regarding
environmental effect.
• The concerned department must speed up the work
of as the more delay will cost more.
11. Conclusion
• According to the DPR and our study, the building of the
25.65 km long Metro Rail corridor is technically and
economically viable.
• This plan is a cost-effective transportation option for the
state of Kerala that would provide significant advantages
to the people.
• This Project will result in overall rapid development of
the State's economy due to the synergistic development
of all communities en-route.
• All of this, however, is only possible if the phase 2 and 3
is finished within the projected time and cost.