SlideShare a Scribd company logo
Slide 1
10/02/2012 Slide 1
Transformer Rated
Metering
Prepared by Tom Lawton,TESCO
Mississippi Meter School
Wednesday, September 27, 2017
11:00 a.m. to 12:00 p.m.
Slide 2
Topics we will be covering
• The Basics- Differences Between Self
Contained and Transformer or Instrument
Rated Meter Sites
• Transformer Rated Meter Forms
• Test Switches and CT’s
• Blondel’s Theorem and why this matters to
us in metering
• Meter Accuracy Testing in the Field
• Checking the Health of your CT’s and PT’s
• Site Verification and not just meter testing
Slide 3
Self Contained Metering
•Typically found in residential
metering
•Meters are capable of handling
the direct incoming amperage
•Meter is connected directly to
the load being measured
•Meter is part of the circuit
•When the meter is removed
from the socket, power to the
customer is interrupted
Slide 4
Transformer Rated Metering
• Meter measures scaled down
representation of the load.
• Scaling is accomplished by the use
of external current transformers
(CTs) and sometimes voltage
transformers or PTs).
• The meter is NOT part of the circuit
• When the meter is removed from
the socket, power to the customer
is not effected.
Slide 5
9S Meter Installation with 400:5 CT’s
400A
400A
400A
LOAD
5A 5A 5A
SOURCE
PHASE A
PHASE B
PHASE C
The Basic Components
Slide 6
Typical Connections
Typical Connections for Common
Transformer (Instrument)
Rated Meter Forms
Slide 7
TESCO/Georgia Power 2017 Caribbean Meter School
Fundamentals of Polyphase Field Meter Testing and Site Verification
 Full Load
 Light Load
 Power Factor
Meter Accuracy Testing
Meter Accuracy
Testing in a Nutshell
Slide 8
The Importance of CT Testing in the Field
• One transformer in three wired
backwards will give the customer a
bill of 1/3rd
the actual bill.
• One broken wire to a single
transformer will give the customer a
bill of 2/3rd
the actual bill
• One dual ratio transformer
inappropriately marked in the billing
system as 400:5 instead of 800:5
provides a bill that is ½ of the actual
bill. And the inverse will give a bill
double of what should have been
sent. Both are lose-lose situations
for the utility.
Slide 9
The Importance of CT Testing in the Field
(cont)
•Cross Phasing (wiring errors)
•Loose or Corroded Connections
•CT Mounted Backwards
•CT’s with Shorted Turns
•Wrong Selection of Dual Ratio CT
•Detect Magnetized CT’s
•Burden Failure in Secondary Circuit
•Open or Shorted Secondary
•Mislabeled CT’s
•Ensures all Shorting Blocks have been Removed
Slide 10
Testing at Transformer Rated Sites
Meter Accuracy
Full Load
Light Load
Power Factor
CT Health
Burden Testing
Ratio Testing
Admittance Testing
Site Verification
Slide 11
Fundamentals of Polyphase Field Meter
Testing and Site Verification
Functionality with Burden Present on the Secondary Loop
PHASE A
• Some burden will always be
present – junctions, meter
coils, test switches, cables,
etc.
• CT’s must be able to
maintain an accurate ratio
with burden on the
secondary.
Slide 12
Fundamentals of Polyphase Field Meter
Testing and Site Verification
Functionality with Burden Present on the Secondary Loop
Example Burden Spec:
0.3% @ B0.1, B0.2, B0.5
or
There should be less than the 0.3%
change in secondary current from initial
(“0” burden) reading, when up to 0.5Ohms
of burden is applied
Slide 13
Fundamentals of Polyphase Field Meter
Testing and Site Verification
Functionality with Burden Present on the Secondary Loop
0.3% @ B0.1, B0.2, B0.5
0.0000
1.0000
2.0000
3.0000
4.0000
5.0000
6.0000
0 2 4 6 8
Initial Reading = 5Amps
0.3% x 5A = 0.015A
5A – 0.015 = 4.985A
Burden Reading
0 5.0000
0.1 4.9999
0.2 4.9950
0.5 4.9900
1 4.9800
2 4.9500
4 4.0000
8 0.8000
Slide 14
Ratio of Primary Current to Secondary Current
PHASE A
SOURCE LOAD
400A
400A
400A
5A5A
Calculate Ratio
Fundamentals of Polyphase Field Meter
Testing and Site Verification
Slide 15
Three Phase Power
Blondel’s Theorem
If energy be supplied to any system of conductors
through N wires, the total power in the system is given
by the algebraic sum of the readings of N wattmeters,
so arranged that each of the N wires contains one
current coil, the corresponding voltage coil being
connected between that wire and some common point.
If this common point is on one of the N wires, the
measurement may be made by the use of N-1
wattmeters.
Slide 16
Three Phase Power
Blondel’s Theorem
• Simply – We can measure the power in a
N wire system by measuring the power in
N-1 conductors.
• For example, in a 4-wire, 3-phase system
we need to measure the power in 3
circuits.
Slide 17
Three Phase Power
Blondel’s Theorem
• If a meter installation meets Blondel’s
Theorem then we will get accurate power
measurements under all circumstances.
• If a metering system does not meet
Blondel’s Theorem then we will only get
accurate measurements if certain
assumptions are met.
Slide 18
Blondel’s Theorem
• Three wires
• Two voltage measurements with
one side common to Line 2
• Current measurements on lines
1 & 3.
This satisfies Blondel’s
Theorem.
Slide 19
Blondel’s Theorem
• Four wires
• Two voltage measurements to
neutral
• Current measurements on lines 1 &
3. How about line 2?
This DOES NOT satisfy Blondel’s
Theorem.
Slide 20
Blondel’s Theorem
• In the previous example:
– What are the “ASSUMPTIONS”?
– When do we get errors?
• What would the “Right Answer” be?
• What did we measure?
)cos()cos()cos( cccbbbaaasys IVIVIVP θθθ ++=
)]cos()cos([)]cos()cos([ bbcccbbaaasys IIVIIVP θθθθ −+−=
Slide 21
Blondel’s Theorem
• Phase B power would be:
– P = Vb Ib cosθ
• But we aren’t measuring Vb
• What we are measuring is:
– IbVacos(60- θ) + IbVccos(60+ θ)
• cos(α + β) = cos(α)cos(β) - sin(α)sin(β)
• cos(α - β) = cos(α)cos(β) + sin(α)sin(β)
• So
Slide 22
Blondel’s Theorem
• Pb = Ib Va cos(60- θ) + Ib Vc cos(60+ θ)
• Applying the trig identity
– IbVa(cos(60)cos(θ) + sin(60)sin(θ))
IbVc (cos(60)cos(θ) - sin(60)sin(θ))
– Ib(Va+Vc)0.5cos(θ) + Ib(Vc-Va) 0.866sin(θ)
• Assuming
– Assume Vb = Va = Vc
– And, they are exactly 120° apart
• Pb = Ib(2Vb)(0.5cosθ) = IbVbcosθ
Slide 23
Blondel’s Theorem
• If Va ≠ Vb ≠ Vc then the error is
• %Error =
-Ib{(Va+Vc)/(2Vb) - (Va-Vc) 0.866sin(θ)/(Vbcos(θ))
How big is this in reality? If
Va=117, Vb=120, Vc=119, PF=1 then E=-1.67%
Va=117, Vb=116, Vc=119, PF=.866 then E=-1.67%
Slide 24
Blondel’s Theorem
Condition % V % I Phase A Phase B
non-
Blondel
Imb Imb V φvan I φian V φvbn I φibn
% Err
All balanced 0 0 120 0 100 0 120 180 100 180 0.00%
Unbalanced voltages PF=1 18% 0% 108 0 100 0 132 180 100 180 0.00%
Unbalanced current PF=1 0% 18% 120 0 90 0 120 180 110 180 0.00%
Unbalanced V&I PF=1 5% 18% 117 0 90 0 123 180 110 180 -0.25%
Unbalanced V&I PF=1 8% 18% 110 0 90 0 120 180 110 180 -0.43%
Unbalanced V&I PF=1 8% 50% 110 0 50 0 120 180 100 180 -1.43%
Unbalanced V&I PF=1 18% 40% 108 0 75 0 132 180 125 180 -2.44%
Unbalanced voltages
PF≠1 PFa = PFb
18% 0% 108 0 100 30 132 180 100 210 0.00%
Unbalanced current
PF≠1 PFa = PFb
0% 18% 120 0 90 30 120 180 110 210 0.00%
Unbalanced V&I
PF≠1 PFa = PFb
18% 18% 108 0 90 30 132 180 110 210 -0.99%
Unbalanced V&I
PF≠1 PFa = PFb
18% 40% 108 0 75 30 132 180 125 210 -2.44%
Unbalanced voltages
PF≠1 PFa ≠ PFb
18% 0% 108 0 100 60 132 180 100 210 -2.61%
Unbalanced current
PF≠1 PFa ≠ PFb
0% 18% 120 0 90 60 120 180 110 210 0.00%
Unbalanced V&I
PF≠1 PFa ≠ PFb
18% 18% 108 0 90 60 132 180 110 210 -3.46%
Unbalanced V&I
PF≠1 PFa ≠ PFb
18% 40% 108 0 75 60 132 180 125 210 -4.63%
Power Measurements Handbook
Slide 25
Site Verification: Why should we invest our
limited meter service resources here
• These customers represent a
disproportionately large amount of the overall
revenue for every utility in North America.
• For some utilities the ten percent of their
customers who have transformer rated
metering services can represent over 70% of
their overall revenue.
• While these numbers will vary from utility to
utility the basic premise should be the same
for all utilities regarding where Meter Services
should focus their efforts
• This is perhaps one of the larger benefits that
AMI can provide for our Utilities – more time
to spend on C&I metering and less on
residential
Easy Answer: Money.
Slide 26
Potential list of tasks to be completed during a Site
Veriification of a Transformer Rated Metering SIte
• Double check the meter number, the location the test result and the meter record
• Perform a visual safety inspection of the site. This includes utility and customer equipment. Things
to look for include intact down ground on pole, properly attached enclosure, unwanted voltage on
enclosure, proper trimming and site tidiness (absence of discarded seals, etc.)
• Visually inspect for energy diversions (intentional and not). This includes broken or missing wires,
jumpers, open test switch, unconnected wires and foreign objects on meters or other metering
equipment. Broken or missing wires can seriously cause the under measurement of energy. A
simple broken wire on a CT or VT can cause the loss of 1/3 to 1/2 of the registration on either 3
element or 2 element metering, respectively.
• Visually check lightning arrestors and transformers for damage or leaks.
• Check for proper grounding and bonding of metering equipment. Poor grounding and bonding
practices may result in inaccurate measurements that go undetected for long periods of time.
Implementing a single point ground policy and practice can reduce or eliminate this type of issue.
• Burden test CTs and voltage check PTs.
Slide 27
Site Verification Checklist (cont)
• Verify service voltage. Stuck regulator or seasonal capacitor can impact service voltage.
• Verify condition of metering control wire. This includes looking for cracks in insulation, broken wires,
loose connections, etc.
• Confirm we have a Blondel compliant metering set up
• Compare the test switch wiring with the wiring at the CTs and VTs. Verify CTs and VTs not cross
wired. Be sure CTs are grounded in one location (test switch) only.
• Check for bad test switch by examining voltage at the top and bottom of the switch. Also verify amps
using amp probe on both sides of the test switch. Verify neutral connection to cabinet (voltage).
• Check rotation by closing in one phase at a time at the test switch and observing the phase meter for
forward rotation. If forward rotation is not observed measurements may be significantly impacted as
the phases are most likely cancelling each other out.
• Test meter for accuracy. Verify demand if applicable with observed load. If meter is performing
compensation (line and/or transformer losses) the compensation should be verified either through
direct testing at the site or by examining recorded pulse data.
• Loss compensation is generally a very small percentage of the overall measurement and would not
be caught under utilities normal high/low checks. However, the small percentages when applied to
large loads or generation can really add up overtime. Billing adjustments can easily be in the $million
range if not caught early.
Slide 28
Site Verification Checklist (cont)
• Verify metering vectors. Traditionally this has been done using instruments such as a circuit
analyzer. Many solid state meters today can provide vector diagrams along with volt/amp/pf and
values using meter manufacturer software or meter displays. Many of these desired values are
programmed into the meters Alternate/Utility display. Examining these values can provide much
information about the metering integrity. It may also assist in determining if unbalanced loads are
present and if CTs are sized properly. The vendor software generally has the ability to capture both
diagnostic and vector information electronically. These electronic records should be kept in the
meter shop for future comparisons.
• If metering is providing pulses/EOI pulse to customers, SCADA systems or other meters for
totalization they also should be verified vs. the known load on the meter. If present test/inspect
isolation relays/pulse splitters for things like blown fuses to ensure they are operating properly.
• Verify meter information including meter multiplier, serial number, dials/decimals, Mp, Ke, Primary
Kh, Kr and Rate. Errors in this type of information can also cause a adverse impact on
measured/reported values.
• Verify CT shunts are all opened.
• Look for signs of excessive heat on the meter base e.g.
melted plastic or discoloration related to heat
Slide 29
Periodic Site Inspections…..
….Can Discover or Prevent:
•Billing Errors
•Bad Metering set-up
•Detect Current Diversion
•Identify Potential Safety Issues
•Metering Issues (issues not
related to meter accuracy)
•AMR/AMI Communications Issues
•The need for Unscheduled Truck Rolls
due to Undetected Field Related Issues
•Discrepancies between what is believed to
be at a given site versus the actual setup
and equipment at the site
Slide 30
Questions and Discussion
Tom Lawton
TESCO – The Eastern Specialty Company
Bristol, PA
Tom.Lawton@tescometering.com
Cell: 215-688-0298
This presentation can also be found under Meter Conferences
and Schools on the TESCO web site: www.tesco-advent.com

More Related Content

What's hot

Introduction to Transformer Rated Metering
Introduction to Transformer Rated Metering Introduction to Transformer Rated Metering
Introduction to Transformer Rated Metering
TESCO - The Eastern Specialty Company
 
TESCO Tuesday: Ratio, Burden and Admittance
TESCO Tuesday: Ratio, Burden and AdmittanceTESCO Tuesday: Ratio, Burden and Admittance
TESCO Tuesday: Ratio, Burden and Admittance
TESCO - The Eastern Specialty Company
 
Introduction to CTs and PTs
Introduction to CTs and PTsIntroduction to CTs and PTs
Introduction to CTs and PTs
TESCO - The Eastern Specialty Company
 
TESCO Tuesday: Harmonics
TESCO Tuesday: HarmonicsTESCO Tuesday: Harmonics
TESCO Tuesday: Harmonics
TESCO - The Eastern Specialty Company
 
Advanced Polyphase Metering
Advanced Polyphase MeteringAdvanced Polyphase Metering
Advanced Polyphase Metering
TESCO - The Eastern Specialty Company
 
CT Testing: Theory and Practice
CT Testing: Theory and PracticeCT Testing: Theory and Practice
CT Testing: Theory and Practice
TESCO - The Eastern Specialty Company
 
Complete Site Testing
Complete Site TestingComplete Site Testing
Ratio, Burden, Admittance Testing
Ratio, Burden, Admittance TestingRatio, Burden, Admittance Testing
Ratio, Burden, Admittance Testing
TESCO - The Eastern Specialty Company
 
How to conduct the test on the linearity of impulse voltage divider? (www.him...
How to conduct the test on the linearity of impulse voltage divider? (www.him...How to conduct the test on the linearity of impulse voltage divider? (www.him...
How to conduct the test on the linearity of impulse voltage divider? (www.him...
Fang Sam
 
Ratio, Burden, and Admittance Testing
Ratio, Burden, and Admittance TestingRatio, Burden, and Admittance Testing
Ratio, Burden, and Admittance Testing
TESCO - The Eastern Specialty Company
 
Electronics measurements and instrumentation basics
Electronics measurements and instrumentation basicsElectronics measurements and instrumentation basics
Electronics measurements and instrumentation basics
Abhishek Thakkar
 
2 dc meter
2 dc meter 2 dc meter
2 dc meter
LOHYINNEE
 
3059
30593059
Av335 instrumentation lab report
Av335 instrumentation lab reportAv335 instrumentation lab report
Av335 instrumentation lab report
Gaurav Vaibhav
 
LAB report basic dc meter design
LAB report basic dc meter designLAB report basic dc meter design
LAB report basic dc meter design
Tyler Maisonneuve
 
Stability test of transformer
Stability test of transformerStability test of transformer
Stability test of transformer
Santu Mondal
 
Theory of AC and DC Meter Testing
Theory of AC and DC Meter TestingTheory of AC and DC Meter Testing
Theory of AC and DC Meter Testing
TESCO - The Eastern Specialty Company
 
Verifying Transformer Rated Service Installations
Verifying Transformer Rated Service InstallationsVerifying Transformer Rated Service Installations
Verifying Transformer Rated Service Installations
TESCO - The Eastern Specialty Company
 
Measurement of 3 phase power by two watt-meter method
Measurement of 3 phase power by two watt-meter methodMeasurement of 3 phase power by two watt-meter method
Measurement of 3 phase power by two watt-meter method
Mohammed Waris Senan
 
Instrumentation Lab. Experiment #4 Report: Op-Amps: Integrator, Differentiato...
Instrumentation Lab. Experiment #4 Report: Op-Amps: Integrator, Differentiato...Instrumentation Lab. Experiment #4 Report: Op-Amps: Integrator, Differentiato...
Instrumentation Lab. Experiment #4 Report: Op-Amps: Integrator, Differentiato...
mohammad zeyad
 

What's hot (20)

Introduction to Transformer Rated Metering
Introduction to Transformer Rated Metering Introduction to Transformer Rated Metering
Introduction to Transformer Rated Metering
 
TESCO Tuesday: Ratio, Burden and Admittance
TESCO Tuesday: Ratio, Burden and AdmittanceTESCO Tuesday: Ratio, Burden and Admittance
TESCO Tuesday: Ratio, Burden and Admittance
 
Introduction to CTs and PTs
Introduction to CTs and PTsIntroduction to CTs and PTs
Introduction to CTs and PTs
 
TESCO Tuesday: Harmonics
TESCO Tuesday: HarmonicsTESCO Tuesday: Harmonics
TESCO Tuesday: Harmonics
 
Advanced Polyphase Metering
Advanced Polyphase MeteringAdvanced Polyphase Metering
Advanced Polyphase Metering
 
CT Testing: Theory and Practice
CT Testing: Theory and PracticeCT Testing: Theory and Practice
CT Testing: Theory and Practice
 
Complete Site Testing
Complete Site TestingComplete Site Testing
Complete Site Testing
 
Ratio, Burden, Admittance Testing
Ratio, Burden, Admittance TestingRatio, Burden, Admittance Testing
Ratio, Burden, Admittance Testing
 
How to conduct the test on the linearity of impulse voltage divider? (www.him...
How to conduct the test on the linearity of impulse voltage divider? (www.him...How to conduct the test on the linearity of impulse voltage divider? (www.him...
How to conduct the test on the linearity of impulse voltage divider? (www.him...
 
Ratio, Burden, and Admittance Testing
Ratio, Burden, and Admittance TestingRatio, Burden, and Admittance Testing
Ratio, Burden, and Admittance Testing
 
Electronics measurements and instrumentation basics
Electronics measurements and instrumentation basicsElectronics measurements and instrumentation basics
Electronics measurements and instrumentation basics
 
2 dc meter
2 dc meter 2 dc meter
2 dc meter
 
3059
30593059
3059
 
Av335 instrumentation lab report
Av335 instrumentation lab reportAv335 instrumentation lab report
Av335 instrumentation lab report
 
LAB report basic dc meter design
LAB report basic dc meter designLAB report basic dc meter design
LAB report basic dc meter design
 
Stability test of transformer
Stability test of transformerStability test of transformer
Stability test of transformer
 
Theory of AC and DC Meter Testing
Theory of AC and DC Meter TestingTheory of AC and DC Meter Testing
Theory of AC and DC Meter Testing
 
Verifying Transformer Rated Service Installations
Verifying Transformer Rated Service InstallationsVerifying Transformer Rated Service Installations
Verifying Transformer Rated Service Installations
 
Measurement of 3 phase power by two watt-meter method
Measurement of 3 phase power by two watt-meter methodMeasurement of 3 phase power by two watt-meter method
Measurement of 3 phase power by two watt-meter method
 
Instrumentation Lab. Experiment #4 Report: Op-Amps: Integrator, Differentiato...
Instrumentation Lab. Experiment #4 Report: Op-Amps: Integrator, Differentiato...Instrumentation Lab. Experiment #4 Report: Op-Amps: Integrator, Differentiato...
Instrumentation Lab. Experiment #4 Report: Op-Amps: Integrator, Differentiato...
 

Similar to Transformer Rated Metering 09.27.17

Introduction to Transformer Rated Metering
Introduction to Transformer Rated MeteringIntroduction to Transformer Rated Metering
Introduction to Transformer Rated Metering
TESCO - The Eastern Specialty Company
 
Site Verification for Self-Contained Hot Socket Detection
Site Verification for Self-Contained Hot Socket DetectionSite Verification for Self-Contained Hot Socket Detection
Site Verification for Self-Contained Hot Socket Detection
TESCO - The Eastern Specialty Company
 
Hands-On Transformer Rated Polyphase Meter Testing
Hands-On Transformer Rated Polyphase Meter TestingHands-On Transformer Rated Polyphase Meter Testing
Hands-On Transformer Rated Polyphase Meter Testing
TESCO - The Eastern Specialty Company
 
Fundamentals of Transformer Rated Field Meter Testing and Site Verification
Fundamentals of Transformer Rated Field Meter Testing and Site VerificationFundamentals of Transformer Rated Field Meter Testing and Site Verification
Fundamentals of Transformer Rated Field Meter Testing and Site Verification
TESCO - The Eastern Specialty Company
 
Complete Site Testing
Complete Site TestingComplete Site Testing
Ratio Burden Admittance Testing
Ratio Burden Admittance TestingRatio Burden Admittance Testing
Ratio Burden Admittance Testing
TESCO - The Eastern Specialty Company
 
Electric Meter and Transformer Testing in an AMI World - AclaraConnect 2018
Electric Meter and Transformer Testing in an AMI World - AclaraConnect 2018Electric Meter and Transformer Testing in an AMI World - AclaraConnect 2018
Electric Meter and Transformer Testing in an AMI World - AclaraConnect 2018
TESCO - The Eastern Specialty Company
 
Instrument Transformer Testing in them Shop and Field_Tom Lawton 2023
Instrument Transformer Testing in them Shop and Field_Tom Lawton 2023Instrument Transformer Testing in them Shop and Field_Tom Lawton 2023
Instrument Transformer Testing in them Shop and Field_Tom Lawton 2023
TESCO - The Eastern Specialty Company
 
TESCO Tuesday: Meter Testing in the Field
TESCO Tuesday: Meter Testing in the FieldTESCO Tuesday: Meter Testing in the Field
TESCO Tuesday: Meter Testing in the Field
TESCO - The Eastern Specialty Company
 
Instrument Transformer Testing in the Shop and Field
Instrument Transformer Testing in the Shop and FieldInstrument Transformer Testing in the Shop and Field
Instrument Transformer Testing in the Shop and Field
TESCO - The Eastern Specialty Company
 
Instrument Transformer Testing
Instrument Transformer TestingInstrument Transformer Testing
Instrument Transformer Testing
TESCO - The Eastern Specialty Company
 
Site Verification: Tools and Best Practices to Accurately Meter Complex, High...
Site Verification: Tools and Best Practices to Accurately Meter Complex, High...Site Verification: Tools and Best Practices to Accurately Meter Complex, High...
Site Verification: Tools and Best Practices to Accurately Meter Complex, High...
TESCO - The Eastern Specialty Company
 
Simulating Real World Metering Conditions
Simulating Real World Metering ConditionsSimulating Real World Metering Conditions
Simulating Real World Metering Conditions
TESCO - The Eastern Specialty Company
 
TESCO Tuesday: Traditional Ratio, Burden, Admittance and Demag Testing – Part II
TESCO Tuesday: Traditional Ratio, Burden, Admittance and Demag Testing – Part IITESCO Tuesday: Traditional Ratio, Burden, Admittance and Demag Testing – Part II
TESCO Tuesday: Traditional Ratio, Burden, Admittance and Demag Testing – Part II
TESCO - The Eastern Specialty Company
 
Instrument Transformers - Following the Money: Best Practices in a Post AMI W...
Instrument Transformers - Following the Money: Best Practices in a Post AMI W...Instrument Transformers - Following the Money: Best Practices in a Post AMI W...
Instrument Transformers - Following the Money: Best Practices in a Post AMI W...
TESCO - The Eastern Specialty Company
 
TESCO Tuesday: Metering Testing by Form
TESCO Tuesday: Metering Testing by FormTESCO Tuesday: Metering Testing by Form
TESCO Tuesday: Metering Testing by Form
TESCO - The Eastern Specialty Company
 
Fundamentals of Field Testing Meters
Fundamentals of Field Testing MetersFundamentals of Field Testing Meters
Fundamentals of Field Testing Meters
TESCO - The Eastern Specialty Company
 
Site Verification - Protocols & Tools for Complex Metering Installations
Site Verification - Protocols & Tools for Complex Metering InstallationsSite Verification - Protocols & Tools for Complex Metering Installations
Site Verification - Protocols & Tools for Complex Metering Installations
TESCO - The Eastern Specialty Company
 
The art of meter testing on site 2019
The art of meter testing on site 2019The art of meter testing on site 2019
The art of meter testing on site 2019
Christopher Urbanski Calmet
 
The art of meter testing on site 2019
The art of meter testing on site 2019The art of meter testing on site 2019
The art of meter testing on site 2019
Christopher Urbanski Calmet
 

Similar to Transformer Rated Metering 09.27.17 (20)

Introduction to Transformer Rated Metering
Introduction to Transformer Rated MeteringIntroduction to Transformer Rated Metering
Introduction to Transformer Rated Metering
 
Site Verification for Self-Contained Hot Socket Detection
Site Verification for Self-Contained Hot Socket DetectionSite Verification for Self-Contained Hot Socket Detection
Site Verification for Self-Contained Hot Socket Detection
 
Hands-On Transformer Rated Polyphase Meter Testing
Hands-On Transformer Rated Polyphase Meter TestingHands-On Transformer Rated Polyphase Meter Testing
Hands-On Transformer Rated Polyphase Meter Testing
 
Fundamentals of Transformer Rated Field Meter Testing and Site Verification
Fundamentals of Transformer Rated Field Meter Testing and Site VerificationFundamentals of Transformer Rated Field Meter Testing and Site Verification
Fundamentals of Transformer Rated Field Meter Testing and Site Verification
 
Complete Site Testing
Complete Site TestingComplete Site Testing
Complete Site Testing
 
Ratio Burden Admittance Testing
Ratio Burden Admittance TestingRatio Burden Admittance Testing
Ratio Burden Admittance Testing
 
Electric Meter and Transformer Testing in an AMI World - AclaraConnect 2018
Electric Meter and Transformer Testing in an AMI World - AclaraConnect 2018Electric Meter and Transformer Testing in an AMI World - AclaraConnect 2018
Electric Meter and Transformer Testing in an AMI World - AclaraConnect 2018
 
Instrument Transformer Testing in them Shop and Field_Tom Lawton 2023
Instrument Transformer Testing in them Shop and Field_Tom Lawton 2023Instrument Transformer Testing in them Shop and Field_Tom Lawton 2023
Instrument Transformer Testing in them Shop and Field_Tom Lawton 2023
 
TESCO Tuesday: Meter Testing in the Field
TESCO Tuesday: Meter Testing in the FieldTESCO Tuesday: Meter Testing in the Field
TESCO Tuesday: Meter Testing in the Field
 
Instrument Transformer Testing in the Shop and Field
Instrument Transformer Testing in the Shop and FieldInstrument Transformer Testing in the Shop and Field
Instrument Transformer Testing in the Shop and Field
 
Instrument Transformer Testing
Instrument Transformer TestingInstrument Transformer Testing
Instrument Transformer Testing
 
Site Verification: Tools and Best Practices to Accurately Meter Complex, High...
Site Verification: Tools and Best Practices to Accurately Meter Complex, High...Site Verification: Tools and Best Practices to Accurately Meter Complex, High...
Site Verification: Tools and Best Practices to Accurately Meter Complex, High...
 
Simulating Real World Metering Conditions
Simulating Real World Metering ConditionsSimulating Real World Metering Conditions
Simulating Real World Metering Conditions
 
TESCO Tuesday: Traditional Ratio, Burden, Admittance and Demag Testing – Part II
TESCO Tuesday: Traditional Ratio, Burden, Admittance and Demag Testing – Part IITESCO Tuesday: Traditional Ratio, Burden, Admittance and Demag Testing – Part II
TESCO Tuesday: Traditional Ratio, Burden, Admittance and Demag Testing – Part II
 
Instrument Transformers - Following the Money: Best Practices in a Post AMI W...
Instrument Transformers - Following the Money: Best Practices in a Post AMI W...Instrument Transformers - Following the Money: Best Practices in a Post AMI W...
Instrument Transformers - Following the Money: Best Practices in a Post AMI W...
 
TESCO Tuesday: Metering Testing by Form
TESCO Tuesday: Metering Testing by FormTESCO Tuesday: Metering Testing by Form
TESCO Tuesday: Metering Testing by Form
 
Fundamentals of Field Testing Meters
Fundamentals of Field Testing MetersFundamentals of Field Testing Meters
Fundamentals of Field Testing Meters
 
Site Verification - Protocols & Tools for Complex Metering Installations
Site Verification - Protocols & Tools for Complex Metering InstallationsSite Verification - Protocols & Tools for Complex Metering Installations
Site Verification - Protocols & Tools for Complex Metering Installations
 
The art of meter testing on site 2019
The art of meter testing on site 2019The art of meter testing on site 2019
The art of meter testing on site 2019
 
The art of meter testing on site 2019
The art of meter testing on site 2019The art of meter testing on site 2019
The art of meter testing on site 2019
 

Recently uploaded

UiPath Test Automation using UiPath Test Suite series, part 5
UiPath Test Automation using UiPath Test Suite series, part 5UiPath Test Automation using UiPath Test Suite series, part 5
UiPath Test Automation using UiPath Test Suite series, part 5
DianaGray10
 
TrustArc Webinar - 2024 Global Privacy Survey
TrustArc Webinar - 2024 Global Privacy SurveyTrustArc Webinar - 2024 Global Privacy Survey
TrustArc Webinar - 2024 Global Privacy Survey
TrustArc
 
GraphSummit Singapore | Enhancing Changi Airport Group's Passenger Experience...
GraphSummit Singapore | Enhancing Changi Airport Group's Passenger Experience...GraphSummit Singapore | Enhancing Changi Airport Group's Passenger Experience...
GraphSummit Singapore | Enhancing Changi Airport Group's Passenger Experience...
Neo4j
 
Generative AI Deep Dive: Advancing from Proof of Concept to Production
Generative AI Deep Dive: Advancing from Proof of Concept to ProductionGenerative AI Deep Dive: Advancing from Proof of Concept to Production
Generative AI Deep Dive: Advancing from Proof of Concept to Production
Aggregage
 
Uni Systems Copilot event_05062024_C.Vlachos.pdf
Uni Systems Copilot event_05062024_C.Vlachos.pdfUni Systems Copilot event_05062024_C.Vlachos.pdf
Uni Systems Copilot event_05062024_C.Vlachos.pdf
Uni Systems S.M.S.A.
 
GraphSummit Singapore | The Future of Agility: Supercharging Digital Transfor...
GraphSummit Singapore | The Future of Agility: Supercharging Digital Transfor...GraphSummit Singapore | The Future of Agility: Supercharging Digital Transfor...
GraphSummit Singapore | The Future of Agility: Supercharging Digital Transfor...
Neo4j
 
Large Language Model (LLM) and it’s Geospatial Applications
Large Language Model (LLM) and it’s Geospatial ApplicationsLarge Language Model (LLM) and it’s Geospatial Applications
Large Language Model (LLM) and it’s Geospatial Applications
Rohit Gautam
 
Full-RAG: A modern architecture for hyper-personalization
Full-RAG: A modern architecture for hyper-personalizationFull-RAG: A modern architecture for hyper-personalization
Full-RAG: A modern architecture for hyper-personalization
Zilliz
 
Monitoring Java Application Security with JDK Tools and JFR Events
Monitoring Java Application Security with JDK Tools and JFR EventsMonitoring Java Application Security with JDK Tools and JFR Events
Monitoring Java Application Security with JDK Tools and JFR Events
Ana-Maria Mihalceanu
 
UiPath Test Automation using UiPath Test Suite series, part 6
UiPath Test Automation using UiPath Test Suite series, part 6UiPath Test Automation using UiPath Test Suite series, part 6
UiPath Test Automation using UiPath Test Suite series, part 6
DianaGray10
 
20240607 QFM018 Elixir Reading List May 2024
20240607 QFM018 Elixir Reading List May 202420240607 QFM018 Elixir Reading List May 2024
20240607 QFM018 Elixir Reading List May 2024
Matthew Sinclair
 
Artificial Intelligence for XMLDevelopment
Artificial Intelligence for XMLDevelopmentArtificial Intelligence for XMLDevelopment
Artificial Intelligence for XMLDevelopment
Octavian Nadolu
 
Building RAG with self-deployed Milvus vector database and Snowpark Container...
Building RAG with self-deployed Milvus vector database and Snowpark Container...Building RAG with self-deployed Milvus vector database and Snowpark Container...
Building RAG with self-deployed Milvus vector database and Snowpark Container...
Zilliz
 
National Security Agency - NSA mobile device best practices
National Security Agency - NSA mobile device best practicesNational Security Agency - NSA mobile device best practices
National Security Agency - NSA mobile device best practices
Quotidiano Piemontese
 
Unlock the Future of Search with MongoDB Atlas_ Vector Search Unleashed.pdf
Unlock the Future of Search with MongoDB Atlas_ Vector Search Unleashed.pdfUnlock the Future of Search with MongoDB Atlas_ Vector Search Unleashed.pdf
Unlock the Future of Search with MongoDB Atlas_ Vector Search Unleashed.pdf
Malak Abu Hammad
 
Introduction to CHERI technology - Cybersecurity
Introduction to CHERI technology - CybersecurityIntroduction to CHERI technology - Cybersecurity
Introduction to CHERI technology - Cybersecurity
mikeeftimakis1
 
みなさんこんにちはこれ何文字まで入るの?40文字以下不可とか本当に意味わからないけどこれ限界文字数書いてないからマジでやばい文字数いけるんじゃないの?えこ...
みなさんこんにちはこれ何文字まで入るの?40文字以下不可とか本当に意味わからないけどこれ限界文字数書いてないからマジでやばい文字数いけるんじゃないの?えこ...みなさんこんにちはこれ何文字まで入るの?40文字以下不可とか本当に意味わからないけどこれ限界文字数書いてないからマジでやばい文字数いけるんじゃないの?えこ...
みなさんこんにちはこれ何文字まで入るの?40文字以下不可とか本当に意味わからないけどこれ限界文字数書いてないからマジでやばい文字数いけるんじゃないの?えこ...
名前 です男
 
Essentials of Automations: The Art of Triggers and Actions in FME
Essentials of Automations: The Art of Triggers and Actions in FMEEssentials of Automations: The Art of Triggers and Actions in FME
Essentials of Automations: The Art of Triggers and Actions in FME
Safe Software
 
GraphSummit Singapore | The Art of the Possible with Graph - Q2 2024
GraphSummit Singapore | The Art of the  Possible with Graph - Q2 2024GraphSummit Singapore | The Art of the  Possible with Graph - Q2 2024
GraphSummit Singapore | The Art of the Possible with Graph - Q2 2024
Neo4j
 
Let's Integrate MuleSoft RPA, COMPOSER, APM with AWS IDP along with Slack
Let's Integrate MuleSoft RPA, COMPOSER, APM with AWS IDP along with SlackLet's Integrate MuleSoft RPA, COMPOSER, APM with AWS IDP along with Slack
Let's Integrate MuleSoft RPA, COMPOSER, APM with AWS IDP along with Slack
shyamraj55
 

Recently uploaded (20)

UiPath Test Automation using UiPath Test Suite series, part 5
UiPath Test Automation using UiPath Test Suite series, part 5UiPath Test Automation using UiPath Test Suite series, part 5
UiPath Test Automation using UiPath Test Suite series, part 5
 
TrustArc Webinar - 2024 Global Privacy Survey
TrustArc Webinar - 2024 Global Privacy SurveyTrustArc Webinar - 2024 Global Privacy Survey
TrustArc Webinar - 2024 Global Privacy Survey
 
GraphSummit Singapore | Enhancing Changi Airport Group's Passenger Experience...
GraphSummit Singapore | Enhancing Changi Airport Group's Passenger Experience...GraphSummit Singapore | Enhancing Changi Airport Group's Passenger Experience...
GraphSummit Singapore | Enhancing Changi Airport Group's Passenger Experience...
 
Generative AI Deep Dive: Advancing from Proof of Concept to Production
Generative AI Deep Dive: Advancing from Proof of Concept to ProductionGenerative AI Deep Dive: Advancing from Proof of Concept to Production
Generative AI Deep Dive: Advancing from Proof of Concept to Production
 
Uni Systems Copilot event_05062024_C.Vlachos.pdf
Uni Systems Copilot event_05062024_C.Vlachos.pdfUni Systems Copilot event_05062024_C.Vlachos.pdf
Uni Systems Copilot event_05062024_C.Vlachos.pdf
 
GraphSummit Singapore | The Future of Agility: Supercharging Digital Transfor...
GraphSummit Singapore | The Future of Agility: Supercharging Digital Transfor...GraphSummit Singapore | The Future of Agility: Supercharging Digital Transfor...
GraphSummit Singapore | The Future of Agility: Supercharging Digital Transfor...
 
Large Language Model (LLM) and it’s Geospatial Applications
Large Language Model (LLM) and it’s Geospatial ApplicationsLarge Language Model (LLM) and it’s Geospatial Applications
Large Language Model (LLM) and it’s Geospatial Applications
 
Full-RAG: A modern architecture for hyper-personalization
Full-RAG: A modern architecture for hyper-personalizationFull-RAG: A modern architecture for hyper-personalization
Full-RAG: A modern architecture for hyper-personalization
 
Monitoring Java Application Security with JDK Tools and JFR Events
Monitoring Java Application Security with JDK Tools and JFR EventsMonitoring Java Application Security with JDK Tools and JFR Events
Monitoring Java Application Security with JDK Tools and JFR Events
 
UiPath Test Automation using UiPath Test Suite series, part 6
UiPath Test Automation using UiPath Test Suite series, part 6UiPath Test Automation using UiPath Test Suite series, part 6
UiPath Test Automation using UiPath Test Suite series, part 6
 
20240607 QFM018 Elixir Reading List May 2024
20240607 QFM018 Elixir Reading List May 202420240607 QFM018 Elixir Reading List May 2024
20240607 QFM018 Elixir Reading List May 2024
 
Artificial Intelligence for XMLDevelopment
Artificial Intelligence for XMLDevelopmentArtificial Intelligence for XMLDevelopment
Artificial Intelligence for XMLDevelopment
 
Building RAG with self-deployed Milvus vector database and Snowpark Container...
Building RAG with self-deployed Milvus vector database and Snowpark Container...Building RAG with self-deployed Milvus vector database and Snowpark Container...
Building RAG with self-deployed Milvus vector database and Snowpark Container...
 
National Security Agency - NSA mobile device best practices
National Security Agency - NSA mobile device best practicesNational Security Agency - NSA mobile device best practices
National Security Agency - NSA mobile device best practices
 
Unlock the Future of Search with MongoDB Atlas_ Vector Search Unleashed.pdf
Unlock the Future of Search with MongoDB Atlas_ Vector Search Unleashed.pdfUnlock the Future of Search with MongoDB Atlas_ Vector Search Unleashed.pdf
Unlock the Future of Search with MongoDB Atlas_ Vector Search Unleashed.pdf
 
Introduction to CHERI technology - Cybersecurity
Introduction to CHERI technology - CybersecurityIntroduction to CHERI technology - Cybersecurity
Introduction to CHERI technology - Cybersecurity
 
みなさんこんにちはこれ何文字まで入るの?40文字以下不可とか本当に意味わからないけどこれ限界文字数書いてないからマジでやばい文字数いけるんじゃないの?えこ...
みなさんこんにちはこれ何文字まで入るの?40文字以下不可とか本当に意味わからないけどこれ限界文字数書いてないからマジでやばい文字数いけるんじゃないの?えこ...みなさんこんにちはこれ何文字まで入るの?40文字以下不可とか本当に意味わからないけどこれ限界文字数書いてないからマジでやばい文字数いけるんじゃないの?えこ...
みなさんこんにちはこれ何文字まで入るの?40文字以下不可とか本当に意味わからないけどこれ限界文字数書いてないからマジでやばい文字数いけるんじゃないの?えこ...
 
Essentials of Automations: The Art of Triggers and Actions in FME
Essentials of Automations: The Art of Triggers and Actions in FMEEssentials of Automations: The Art of Triggers and Actions in FME
Essentials of Automations: The Art of Triggers and Actions in FME
 
GraphSummit Singapore | The Art of the Possible with Graph - Q2 2024
GraphSummit Singapore | The Art of the  Possible with Graph - Q2 2024GraphSummit Singapore | The Art of the  Possible with Graph - Q2 2024
GraphSummit Singapore | The Art of the Possible with Graph - Q2 2024
 
Let's Integrate MuleSoft RPA, COMPOSER, APM with AWS IDP along with Slack
Let's Integrate MuleSoft RPA, COMPOSER, APM with AWS IDP along with SlackLet's Integrate MuleSoft RPA, COMPOSER, APM with AWS IDP along with Slack
Let's Integrate MuleSoft RPA, COMPOSER, APM with AWS IDP along with Slack
 

Transformer Rated Metering 09.27.17

  • 1. Slide 1 10/02/2012 Slide 1 Transformer Rated Metering Prepared by Tom Lawton,TESCO Mississippi Meter School Wednesday, September 27, 2017 11:00 a.m. to 12:00 p.m.
  • 2. Slide 2 Topics we will be covering • The Basics- Differences Between Self Contained and Transformer or Instrument Rated Meter Sites • Transformer Rated Meter Forms • Test Switches and CT’s • Blondel’s Theorem and why this matters to us in metering • Meter Accuracy Testing in the Field • Checking the Health of your CT’s and PT’s • Site Verification and not just meter testing
  • 3. Slide 3 Self Contained Metering •Typically found in residential metering •Meters are capable of handling the direct incoming amperage •Meter is connected directly to the load being measured •Meter is part of the circuit •When the meter is removed from the socket, power to the customer is interrupted
  • 4. Slide 4 Transformer Rated Metering • Meter measures scaled down representation of the load. • Scaling is accomplished by the use of external current transformers (CTs) and sometimes voltage transformers or PTs). • The meter is NOT part of the circuit • When the meter is removed from the socket, power to the customer is not effected.
  • 5. Slide 5 9S Meter Installation with 400:5 CT’s 400A 400A 400A LOAD 5A 5A 5A SOURCE PHASE A PHASE B PHASE C The Basic Components
  • 6. Slide 6 Typical Connections Typical Connections for Common Transformer (Instrument) Rated Meter Forms
  • 7. Slide 7 TESCO/Georgia Power 2017 Caribbean Meter School Fundamentals of Polyphase Field Meter Testing and Site Verification  Full Load  Light Load  Power Factor Meter Accuracy Testing Meter Accuracy Testing in a Nutshell
  • 8. Slide 8 The Importance of CT Testing in the Field • One transformer in three wired backwards will give the customer a bill of 1/3rd the actual bill. • One broken wire to a single transformer will give the customer a bill of 2/3rd the actual bill • One dual ratio transformer inappropriately marked in the billing system as 400:5 instead of 800:5 provides a bill that is ½ of the actual bill. And the inverse will give a bill double of what should have been sent. Both are lose-lose situations for the utility.
  • 9. Slide 9 The Importance of CT Testing in the Field (cont) •Cross Phasing (wiring errors) •Loose or Corroded Connections •CT Mounted Backwards •CT’s with Shorted Turns •Wrong Selection of Dual Ratio CT •Detect Magnetized CT’s •Burden Failure in Secondary Circuit •Open or Shorted Secondary •Mislabeled CT’s •Ensures all Shorting Blocks have been Removed
  • 10. Slide 10 Testing at Transformer Rated Sites Meter Accuracy Full Load Light Load Power Factor CT Health Burden Testing Ratio Testing Admittance Testing Site Verification
  • 11. Slide 11 Fundamentals of Polyphase Field Meter Testing and Site Verification Functionality with Burden Present on the Secondary Loop PHASE A • Some burden will always be present – junctions, meter coils, test switches, cables, etc. • CT’s must be able to maintain an accurate ratio with burden on the secondary.
  • 12. Slide 12 Fundamentals of Polyphase Field Meter Testing and Site Verification Functionality with Burden Present on the Secondary Loop Example Burden Spec: 0.3% @ B0.1, B0.2, B0.5 or There should be less than the 0.3% change in secondary current from initial (“0” burden) reading, when up to 0.5Ohms of burden is applied
  • 13. Slide 13 Fundamentals of Polyphase Field Meter Testing and Site Verification Functionality with Burden Present on the Secondary Loop 0.3% @ B0.1, B0.2, B0.5 0.0000 1.0000 2.0000 3.0000 4.0000 5.0000 6.0000 0 2 4 6 8 Initial Reading = 5Amps 0.3% x 5A = 0.015A 5A – 0.015 = 4.985A Burden Reading 0 5.0000 0.1 4.9999 0.2 4.9950 0.5 4.9900 1 4.9800 2 4.9500 4 4.0000 8 0.8000
  • 14. Slide 14 Ratio of Primary Current to Secondary Current PHASE A SOURCE LOAD 400A 400A 400A 5A5A Calculate Ratio Fundamentals of Polyphase Field Meter Testing and Site Verification
  • 15. Slide 15 Three Phase Power Blondel’s Theorem If energy be supplied to any system of conductors through N wires, the total power in the system is given by the algebraic sum of the readings of N wattmeters, so arranged that each of the N wires contains one current coil, the corresponding voltage coil being connected between that wire and some common point. If this common point is on one of the N wires, the measurement may be made by the use of N-1 wattmeters.
  • 16. Slide 16 Three Phase Power Blondel’s Theorem • Simply – We can measure the power in a N wire system by measuring the power in N-1 conductors. • For example, in a 4-wire, 3-phase system we need to measure the power in 3 circuits.
  • 17. Slide 17 Three Phase Power Blondel’s Theorem • If a meter installation meets Blondel’s Theorem then we will get accurate power measurements under all circumstances. • If a metering system does not meet Blondel’s Theorem then we will only get accurate measurements if certain assumptions are met.
  • 18. Slide 18 Blondel’s Theorem • Three wires • Two voltage measurements with one side common to Line 2 • Current measurements on lines 1 & 3. This satisfies Blondel’s Theorem.
  • 19. Slide 19 Blondel’s Theorem • Four wires • Two voltage measurements to neutral • Current measurements on lines 1 & 3. How about line 2? This DOES NOT satisfy Blondel’s Theorem.
  • 20. Slide 20 Blondel’s Theorem • In the previous example: – What are the “ASSUMPTIONS”? – When do we get errors? • What would the “Right Answer” be? • What did we measure? )cos()cos()cos( cccbbbaaasys IVIVIVP θθθ ++= )]cos()cos([)]cos()cos([ bbcccbbaaasys IIVIIVP θθθθ −+−=
  • 21. Slide 21 Blondel’s Theorem • Phase B power would be: – P = Vb Ib cosθ • But we aren’t measuring Vb • What we are measuring is: – IbVacos(60- θ) + IbVccos(60+ θ) • cos(α + β) = cos(α)cos(β) - sin(α)sin(β) • cos(α - β) = cos(α)cos(β) + sin(α)sin(β) • So
  • 22. Slide 22 Blondel’s Theorem • Pb = Ib Va cos(60- θ) + Ib Vc cos(60+ θ) • Applying the trig identity – IbVa(cos(60)cos(θ) + sin(60)sin(θ)) IbVc (cos(60)cos(θ) - sin(60)sin(θ)) – Ib(Va+Vc)0.5cos(θ) + Ib(Vc-Va) 0.866sin(θ) • Assuming – Assume Vb = Va = Vc – And, they are exactly 120° apart • Pb = Ib(2Vb)(0.5cosθ) = IbVbcosθ
  • 23. Slide 23 Blondel’s Theorem • If Va ≠ Vb ≠ Vc then the error is • %Error = -Ib{(Va+Vc)/(2Vb) - (Va-Vc) 0.866sin(θ)/(Vbcos(θ)) How big is this in reality? If Va=117, Vb=120, Vc=119, PF=1 then E=-1.67% Va=117, Vb=116, Vc=119, PF=.866 then E=-1.67%
  • 24. Slide 24 Blondel’s Theorem Condition % V % I Phase A Phase B non- Blondel Imb Imb V φvan I φian V φvbn I φibn % Err All balanced 0 0 120 0 100 0 120 180 100 180 0.00% Unbalanced voltages PF=1 18% 0% 108 0 100 0 132 180 100 180 0.00% Unbalanced current PF=1 0% 18% 120 0 90 0 120 180 110 180 0.00% Unbalanced V&I PF=1 5% 18% 117 0 90 0 123 180 110 180 -0.25% Unbalanced V&I PF=1 8% 18% 110 0 90 0 120 180 110 180 -0.43% Unbalanced V&I PF=1 8% 50% 110 0 50 0 120 180 100 180 -1.43% Unbalanced V&I PF=1 18% 40% 108 0 75 0 132 180 125 180 -2.44% Unbalanced voltages PF≠1 PFa = PFb 18% 0% 108 0 100 30 132 180 100 210 0.00% Unbalanced current PF≠1 PFa = PFb 0% 18% 120 0 90 30 120 180 110 210 0.00% Unbalanced V&I PF≠1 PFa = PFb 18% 18% 108 0 90 30 132 180 110 210 -0.99% Unbalanced V&I PF≠1 PFa = PFb 18% 40% 108 0 75 30 132 180 125 210 -2.44% Unbalanced voltages PF≠1 PFa ≠ PFb 18% 0% 108 0 100 60 132 180 100 210 -2.61% Unbalanced current PF≠1 PFa ≠ PFb 0% 18% 120 0 90 60 120 180 110 210 0.00% Unbalanced V&I PF≠1 PFa ≠ PFb 18% 18% 108 0 90 60 132 180 110 210 -3.46% Unbalanced V&I PF≠1 PFa ≠ PFb 18% 40% 108 0 75 60 132 180 125 210 -4.63% Power Measurements Handbook
  • 25. Slide 25 Site Verification: Why should we invest our limited meter service resources here • These customers represent a disproportionately large amount of the overall revenue for every utility in North America. • For some utilities the ten percent of their customers who have transformer rated metering services can represent over 70% of their overall revenue. • While these numbers will vary from utility to utility the basic premise should be the same for all utilities regarding where Meter Services should focus their efforts • This is perhaps one of the larger benefits that AMI can provide for our Utilities – more time to spend on C&I metering and less on residential Easy Answer: Money.
  • 26. Slide 26 Potential list of tasks to be completed during a Site Veriification of a Transformer Rated Metering SIte • Double check the meter number, the location the test result and the meter record • Perform a visual safety inspection of the site. This includes utility and customer equipment. Things to look for include intact down ground on pole, properly attached enclosure, unwanted voltage on enclosure, proper trimming and site tidiness (absence of discarded seals, etc.) • Visually inspect for energy diversions (intentional and not). This includes broken or missing wires, jumpers, open test switch, unconnected wires and foreign objects on meters or other metering equipment. Broken or missing wires can seriously cause the under measurement of energy. A simple broken wire on a CT or VT can cause the loss of 1/3 to 1/2 of the registration on either 3 element or 2 element metering, respectively. • Visually check lightning arrestors and transformers for damage or leaks. • Check for proper grounding and bonding of metering equipment. Poor grounding and bonding practices may result in inaccurate measurements that go undetected for long periods of time. Implementing a single point ground policy and practice can reduce or eliminate this type of issue. • Burden test CTs and voltage check PTs.
  • 27. Slide 27 Site Verification Checklist (cont) • Verify service voltage. Stuck regulator or seasonal capacitor can impact service voltage. • Verify condition of metering control wire. This includes looking for cracks in insulation, broken wires, loose connections, etc. • Confirm we have a Blondel compliant metering set up • Compare the test switch wiring with the wiring at the CTs and VTs. Verify CTs and VTs not cross wired. Be sure CTs are grounded in one location (test switch) only. • Check for bad test switch by examining voltage at the top and bottom of the switch. Also verify amps using amp probe on both sides of the test switch. Verify neutral connection to cabinet (voltage). • Check rotation by closing in one phase at a time at the test switch and observing the phase meter for forward rotation. If forward rotation is not observed measurements may be significantly impacted as the phases are most likely cancelling each other out. • Test meter for accuracy. Verify demand if applicable with observed load. If meter is performing compensation (line and/or transformer losses) the compensation should be verified either through direct testing at the site or by examining recorded pulse data. • Loss compensation is generally a very small percentage of the overall measurement and would not be caught under utilities normal high/low checks. However, the small percentages when applied to large loads or generation can really add up overtime. Billing adjustments can easily be in the $million range if not caught early.
  • 28. Slide 28 Site Verification Checklist (cont) • Verify metering vectors. Traditionally this has been done using instruments such as a circuit analyzer. Many solid state meters today can provide vector diagrams along with volt/amp/pf and values using meter manufacturer software or meter displays. Many of these desired values are programmed into the meters Alternate/Utility display. Examining these values can provide much information about the metering integrity. It may also assist in determining if unbalanced loads are present and if CTs are sized properly. The vendor software generally has the ability to capture both diagnostic and vector information electronically. These electronic records should be kept in the meter shop for future comparisons. • If metering is providing pulses/EOI pulse to customers, SCADA systems or other meters for totalization they also should be verified vs. the known load on the meter. If present test/inspect isolation relays/pulse splitters for things like blown fuses to ensure they are operating properly. • Verify meter information including meter multiplier, serial number, dials/decimals, Mp, Ke, Primary Kh, Kr and Rate. Errors in this type of information can also cause a adverse impact on measured/reported values. • Verify CT shunts are all opened. • Look for signs of excessive heat on the meter base e.g. melted plastic or discoloration related to heat
  • 29. Slide 29 Periodic Site Inspections….. ….Can Discover or Prevent: •Billing Errors •Bad Metering set-up •Detect Current Diversion •Identify Potential Safety Issues •Metering Issues (issues not related to meter accuracy) •AMR/AMI Communications Issues •The need for Unscheduled Truck Rolls due to Undetected Field Related Issues •Discrepancies between what is believed to be at a given site versus the actual setup and equipment at the site
  • 30. Slide 30 Questions and Discussion Tom Lawton TESCO – The Eastern Specialty Company Bristol, PA Tom.Lawton@tescometering.com Cell: 215-688-0298 This presentation can also be found under Meter Conferences and Schools on the TESCO web site: www.tesco-advent.com