SlideShare a Scribd company logo
Cook Legacy College
Training Module M-200:
Fundamentals of Small
Hydro
Goals of This 15-Minute Module


Know what small hydro is.



Understand major features,
components, and selection criteria



Understand technical and financial
considerations when assessing a
site
Fundamentals of Small Hydro

SH 101:
Overview and
Background

SH 102:
Fundamentals

SH 103:
Review and
Quiz

3
What is Small Hydro
Small Hydro (also called small hydroelectric or small hydro) refers to the generation of
electrical power by using diverted water to rotate a turbine.
The major components include:
• An intake
• A penstock
• A turbine & generator
• A switchyard for connection to the power pole

4
What is Small Hydro
The most commonly used form in intake structure design is the “Discharge Equation.”
Different forms are used for flow over the spillway, Coanda accelerator, measurement
weirs, and various secondary spills.
Generally the value of C, the discharge coefficient, will adjust based on some empirical
test.
The basic discharge equation is Q=Clh^3/2
Where:
Q=Flow
C=Discharge coefficient
l=Length of the weir
h=head above the crest

The most important thing when selecting and implementing a discharge equation is
ensuring it matches in all respects the condition it was intended for.

5
Calculating Power Potential
Power is given as:
P=HQkG
Where:
P=Power in watts
H=Head (the difference in elevation between the intake and the powerhouse
Q=Flow in m^3/s
G=Gravity (9.8 m/s^2)
k=Turbine efficiency
A quick estimate is to take 7 * Q* H

Head (m)

Flow (m3/s)

Power in kW
6

7 x Head x Flow
What is Small Hydro
What counts as small hydro?

Typical Power
Micro
Mini

100 to 1,000 kW

Small

7

< 100 kW

1 to 50 MW
What is Small Hydro


Type of grid
– Central-grid: Generated power is sold back
to a power grid such as a utility.
– Isolated-grid or off-grid: Generated power is
used locally near the point of generation.



Type of civil works
– Run-of-river
• No water storage
• Power varies with flow available from river:
lower firm capacity

– Reservoir
• Higher firm capacity year-round
8

• Significant damming usually required
Process for Sizing Site

9
Process for Sizing Site
• Estimate flow duration curve based on


Measurements of flow over time



Size of drainage above site, specific run-off, and shape of flow
duration curve



The easiest way to mess up a high head site is to overestimate the
flow (as this is the only variable)
Flow-Duration Curve

Flow (m³/s)

50.0
40.0
30.0
20.0
10.0
0.0
0

10 20 30 40 50 60 70 80 90 100
Percent Time Flow Equalled or Exceeded (% )

10
Process for Sizing Site
Picking the Turbine

at various points on the FDC

Flow-Duration Curve

40.0

• Estimate the cost of
equipment cost associated
with those. This includes
questions such as the size of
the equipment and how many
nozzles will be used.

• Integrate the area under the
curve with various scenarios
and pick the best payback.
Sometimes this can be
approximated by simply slicing
the FDC into a few scenarios.

11

Flow (m³/s)

• Estimate the installed capacity

50.0

30.0
20.0
10.0
0.0
0 10 20 30 40 50 60 70 80 90 100
Percent Time Flow Equalled or Exceeded (% )

For example:
The green line has high
capacity to “catch” high flow
events, but may not run
enough to be worth the cost.
The blue line will be cheaper,
but may leave power on the
table. The red line may be the
best return.
Small Hydro Major Components
The most expensive cost component for a small hydro plant is the Civil Cost.
Much of our approach is in lowering the civil cap-ex.
Small Hydro Cost Estimate

Other
10%

Electrical
10%

Mechanical & Controls
25%

12

Civil Cost
55%
Small Hydro Major Components
The major components for the site are:
• Intake structure
• Penstock
• Powerhouse – the primary components of the powerhouse are:
o Turbine-generator
o Switchyard

13
Intake Structure
The intake structure needs to deliver clean water to the penstock
Traditional intakes include a coarse screen
with secondary screening and settling
basins to remove sand.
Coanda screens eliminate secondary
screening need & use overflowing water to
stay clean.

14
Turbine Types

15
Pelton Turbine Details
As Coanda Screens are most suitable for medium and high head sites they
are commonly paired with Pelton Machines
Peltons have a series of nozzles controlled by actuated needle valves, that
spray water onto the runners.

16
Turbine Types

17
Turbine Types

18
Low Head Hydro: Natel HydoEngine
In the low head space,
we offer
complementary
process equipment to
a range of turbine
designs.

19
Low Head Hydro: Cleanpower
Turbinator

20
Other Powerhouse Components
The generator is connected to the turbine.
A generator can be either synchronous (i.e. designed to work with an existing
load) or asynchronous.
For very small sites an induction motor can be used in place of the generator.
Additional components are the plant controls and basic facility requirements
like lighting, fire protection, personnel protection, and monitoring equipment.

21
Design Considerations
Technical

Financial
Plant

Environmental

22

Regulatory
Design Considerations
Intake Design

Turbine Selection

• Side intake
• Coanda

• Head
• Flow
• Fish

Technical
Penstock Design
• Distance
• Pressure

23

T&D Design
• Distance
• Connection Type
Design Considerations
Cap-Ex

Funding Sources

• Civil
• Mechanical
• Consultancy

• NGO
• Private Funding
• Equipment

Financial
Cost of Capital

Payback of
Components
• Cheap & swap
• Long term value

24
Design Considerations
Water

Grid Connection

Regulatory

Permitting Agency

25

Construction
Permits
Design Considerations
Social

Fisheries

• Build projects good for
people
• Don’t screw landowners.
Be fair.

• Improve diversion
• Improve survival

Environmental

Land Use
• Intake
• T&D

26

Proper O&M
Review Questions




27

What are the components of calculating
power capacity?
What are the balance of plant benefits of a
Coanda intake

More Related Content

What's hot

Fiberglass tank solutions rev a
Fiberglass tank solutions   rev aFiberglass tank solutions   rev a
Fiberglass tank solutions rev a
fts14
 
Compactsolutionforcso
CompactsolutionforcsoCompactsolutionforcso
Compactsolutionforcso
Scott Henderson, PE ENV-SP
 
Produced Water | Session VI - Tyler Algeo
Produced Water | Session VI - Tyler AlgeoProduced Water | Session VI - Tyler Algeo
Produced Water | Session VI - Tyler Algeo
atlanticcouncil
 
Innovative Secondary Containment Installations: Creating a Smaller Carbon Foo...
Innovative Secondary Containment Installations: Creating a Smaller Carbon Foo...Innovative Secondary Containment Installations: Creating a Smaller Carbon Foo...
Innovative Secondary Containment Installations: Creating a Smaller Carbon Foo...
C.I.Agent Solutions
 
Produced Water Treatment to Enhance Oil Recovery
Produced Water Treatment to Enhance Oil RecoveryProduced Water Treatment to Enhance Oil Recovery
Produced Water Treatment to Enhance Oil Recovery
gusgon
 
Island Water Treatment Plant Capacity Increase Study
Island Water Treatment Plant Capacity Increase StudyIsland Water Treatment Plant Capacity Increase Study
Island Water Treatment Plant Capacity Increase Study
Toronto Public Consultation Unit
 
Controlling Post-Completion Flow in Steam-Assisted Gravity Drainage Wells
Controlling Post-Completion Flow  in Steam-Assisted Gravity Drainage WellsControlling Post-Completion Flow  in Steam-Assisted Gravity Drainage Wells
Controlling Post-Completion Flow in Steam-Assisted Gravity Drainage Wells
Baker Hughes
 
Produced Water | Session III - John Veil
Produced Water | Session III - John VeilProduced Water | Session III - John Veil
Produced Water | Session III - John Veil
atlanticcouncil
 
Oil Sands Water Management Initiative Notes
Oil Sands Water Management Initiative NotesOil Sands Water Management Initiative Notes
Oil Sands Water Management Initiative Notes
williampatricklaw
 
Prototype Development of an Integrated Mars Atmosphere and Soil Processing Sy...
Prototype Development of an Integrated Mars Atmosphere and Soil Processing Sy...Prototype Development of an Integrated Mars Atmosphere and Soil Processing Sy...
Prototype Development of an Integrated Mars Atmosphere and Soil Processing Sy...
Michael Interbartolo
 
Produced Water | Session X - Steve Jester
Produced Water | Session X - Steve JesterProduced Water | Session X - Steve Jester
Produced Water | Session X - Steve Jester
atlanticcouncil
 
Gersetenmaier.william l
Gersetenmaier.william lGersetenmaier.william l
Gersetenmaier.william lNASAPMC
 
Aqua-Barrier Water Inflated Dams Literature
Aqua-Barrier Water Inflated Dams LiteratureAqua-Barrier Water Inflated Dams Literature
Aqua-Barrier Water Inflated Dams LiteratureDarren Miller
 
Severn_Trent_Wanlip_Sludge_2014
Severn_Trent_Wanlip_Sludge_2014Severn_Trent_Wanlip_Sludge_2014
Severn_Trent_Wanlip_Sludge_2014Iain McGregor
 
Longer, deeper, colder - Technology to cross energy frontiers
Longer, deeper, colder - Technology to cross energy frontiersLonger, deeper, colder - Technology to cross energy frontiers
Longer, deeper, colder - Technology to cross energy frontiersStatoil
 
Island Water Treatment Plant Capacity Expansion - Project File Report
Island Water Treatment Plant Capacity Expansion - Project File ReportIsland Water Treatment Plant Capacity Expansion - Project File Report
Island Water Treatment Plant Capacity Expansion - Project File Report
Toronto Public Consultation Unit
 
Steve Major: Finally…an Engineer’s Perspective: 9 MBRs and Counting
Steve Major: Finally…an Engineer’s Perspective: 9 MBRs and CountingSteve Major: Finally…an Engineer’s Perspective: 9 MBRs and Counting
Steve Major: Finally…an Engineer’s Perspective: 9 MBRs and Counting
ovivombr
 
O&GFaclities_Oct2013_SandManagementMethodologies
O&GFaclities_Oct2013_SandManagementMethodologiesO&GFaclities_Oct2013_SandManagementMethodologies
O&GFaclities_Oct2013_SandManagementMethodologiesHank Rawlins
 
Blue mountains cascade dam- Horizontal direction drill
Blue mountains cascade dam- Horizontal direction drillBlue mountains cascade dam- Horizontal direction drill
Blue mountains cascade dam- Horizontal direction drill
DeanGarratt
 
Water shut off ppt
Water shut off pptWater shut off ppt
Water shut off pptAdjei Sephen
 

What's hot (20)

Fiberglass tank solutions rev a
Fiberglass tank solutions   rev aFiberglass tank solutions   rev a
Fiberglass tank solutions rev a
 
Compactsolutionforcso
CompactsolutionforcsoCompactsolutionforcso
Compactsolutionforcso
 
Produced Water | Session VI - Tyler Algeo
Produced Water | Session VI - Tyler AlgeoProduced Water | Session VI - Tyler Algeo
Produced Water | Session VI - Tyler Algeo
 
Innovative Secondary Containment Installations: Creating a Smaller Carbon Foo...
Innovative Secondary Containment Installations: Creating a Smaller Carbon Foo...Innovative Secondary Containment Installations: Creating a Smaller Carbon Foo...
Innovative Secondary Containment Installations: Creating a Smaller Carbon Foo...
 
Produced Water Treatment to Enhance Oil Recovery
Produced Water Treatment to Enhance Oil RecoveryProduced Water Treatment to Enhance Oil Recovery
Produced Water Treatment to Enhance Oil Recovery
 
Island Water Treatment Plant Capacity Increase Study
Island Water Treatment Plant Capacity Increase StudyIsland Water Treatment Plant Capacity Increase Study
Island Water Treatment Plant Capacity Increase Study
 
Controlling Post-Completion Flow in Steam-Assisted Gravity Drainage Wells
Controlling Post-Completion Flow  in Steam-Assisted Gravity Drainage WellsControlling Post-Completion Flow  in Steam-Assisted Gravity Drainage Wells
Controlling Post-Completion Flow in Steam-Assisted Gravity Drainage Wells
 
Produced Water | Session III - John Veil
Produced Water | Session III - John VeilProduced Water | Session III - John Veil
Produced Water | Session III - John Veil
 
Oil Sands Water Management Initiative Notes
Oil Sands Water Management Initiative NotesOil Sands Water Management Initiative Notes
Oil Sands Water Management Initiative Notes
 
Prototype Development of an Integrated Mars Atmosphere and Soil Processing Sy...
Prototype Development of an Integrated Mars Atmosphere and Soil Processing Sy...Prototype Development of an Integrated Mars Atmosphere and Soil Processing Sy...
Prototype Development of an Integrated Mars Atmosphere and Soil Processing Sy...
 
Produced Water | Session X - Steve Jester
Produced Water | Session X - Steve JesterProduced Water | Session X - Steve Jester
Produced Water | Session X - Steve Jester
 
Gersetenmaier.william l
Gersetenmaier.william lGersetenmaier.william l
Gersetenmaier.william l
 
Aqua-Barrier Water Inflated Dams Literature
Aqua-Barrier Water Inflated Dams LiteratureAqua-Barrier Water Inflated Dams Literature
Aqua-Barrier Water Inflated Dams Literature
 
Severn_Trent_Wanlip_Sludge_2014
Severn_Trent_Wanlip_Sludge_2014Severn_Trent_Wanlip_Sludge_2014
Severn_Trent_Wanlip_Sludge_2014
 
Longer, deeper, colder - Technology to cross energy frontiers
Longer, deeper, colder - Technology to cross energy frontiersLonger, deeper, colder - Technology to cross energy frontiers
Longer, deeper, colder - Technology to cross energy frontiers
 
Island Water Treatment Plant Capacity Expansion - Project File Report
Island Water Treatment Plant Capacity Expansion - Project File ReportIsland Water Treatment Plant Capacity Expansion - Project File Report
Island Water Treatment Plant Capacity Expansion - Project File Report
 
Steve Major: Finally…an Engineer’s Perspective: 9 MBRs and Counting
Steve Major: Finally…an Engineer’s Perspective: 9 MBRs and CountingSteve Major: Finally…an Engineer’s Perspective: 9 MBRs and Counting
Steve Major: Finally…an Engineer’s Perspective: 9 MBRs and Counting
 
O&GFaclities_Oct2013_SandManagementMethodologies
O&GFaclities_Oct2013_SandManagementMethodologiesO&GFaclities_Oct2013_SandManagementMethodologies
O&GFaclities_Oct2013_SandManagementMethodologies
 
Blue mountains cascade dam- Horizontal direction drill
Blue mountains cascade dam- Horizontal direction drillBlue mountains cascade dam- Horizontal direction drill
Blue mountains cascade dam- Horizontal direction drill
 
Water shut off ppt
Water shut off pptWater shut off ppt
Water shut off ppt
 

Similar to Small Hydro Training Module

Introduction to power plant
Introduction to power plantIntroduction to power plant
Introduction to power plant
Rahul Rathod
 
Basics of Hydro power plant
Basics of  Hydro power plant Basics of  Hydro power plant
Basics of Hydro power plant Prasad Vejendla
 
Hydraulic Ram Pump: Consumers guide - Delft University of Technology
Hydraulic Ram Pump: Consumers guide - Delft University of TechnologyHydraulic Ram Pump: Consumers guide - Delft University of Technology
Hydraulic Ram Pump: Consumers guide - Delft University of Technology
Fatin62c
 
PLANNING & DESIGN OF LIFT IRRIGATION.pptx
PLANNING & DESIGN OF LIFT IRRIGATION.pptxPLANNING & DESIGN OF LIFT IRRIGATION.pptx
PLANNING & DESIGN OF LIFT IRRIGATION.pptx
ExeEnggManchannalaDi
 
Archimedes Screw as a Low Head Hydropower Generator
Archimedes Screw as a Low Head Hydropower GeneratorArchimedes Screw as a Low Head Hydropower Generator
Archimedes Screw as a Low Head Hydropower GeneratorChristos Charisiadis
 
Hydro power plant
Hydro power plantHydro power plant
Hydro power plant
Naveed Ahmed
 
commutation failure
commutation failurecommutation failure
commutation failureShiva Kumar
 
Hydro electric power plant lecture
Hydro electric power plant lectureHydro electric power plant lecture
Hydro electric power plant lecturec3b2a1
 
Presentation1.pptx
Presentation1.pptxPresentation1.pptx
Presentation1.pptx
magedahmed44
 
New Wave Energy Services Ltd. Presentation 2016 US
New Wave Energy Services Ltd. Presentation 2016 USNew Wave Energy Services Ltd. Presentation 2016 US
New Wave Energy Services Ltd. Presentation 2016 USKristopher Vardell
 
Hydro Energy or Hydro power conversion Technology
Hydro Energy or Hydro power conversion TechnologyHydro Energy or Hydro power conversion Technology
Hydro Energy or Hydro power conversion Technology
Tesfaye Birara
 
MRE 510 ppt... 2 Hydraulic Turbines.pptx
MRE 510 ppt... 2 Hydraulic Turbines.pptxMRE 510 ppt... 2 Hydraulic Turbines.pptx
MRE 510 ppt... 2 Hydraulic Turbines.pptx
SeanTapiwaKabera1
 
Hydro power plant
Hydro power plantHydro power plant
Hydro power plant
Ripuranjan Singh
 
Water Lifts and Pumps
Water Lifts and PumpsWater Lifts and Pumps
Water Lifts and Pumps
Suyog Khose
 
Pump efficiency
Pump efficiencyPump efficiency
Pump efficiency
Ashwin Narayan
 
Proposed Design Models of Axial-Flux Permanent Magnet Synchronous Generator ...
Proposed Design Models of Axial-Flux Permanent Magnet  Synchronous Generator ...Proposed Design Models of Axial-Flux Permanent Magnet  Synchronous Generator ...
Proposed Design Models of Axial-Flux Permanent Magnet Synchronous Generator ...
abdoyakob
 
Hydel Generation and Types Of Turbines
Hydel Generation and Types Of TurbinesHydel Generation and Types Of Turbines
Hydel Generation and Types Of Turbines
Taimoor Muzaffar Gondal
 
Barangaroo South District Cooling Plant (DCP) Fact Sheet
Barangaroo South District Cooling Plant (DCP) Fact SheetBarangaroo South District Cooling Plant (DCP) Fact Sheet
Barangaroo South District Cooling Plant (DCP) Fact Sheet
DeanDallwitz
 
3: Energy Management In Water Supply Systems - Pumping Operations
3: Energy Management In Water Supply Systems - Pumping Operations3: Energy Management In Water Supply Systems - Pumping Operations
3: Energy Management In Water Supply Systems - Pumping Operations
Alliance To Save Energy
 
Artificial-Lift-System-N production engineering.pdf
Artificial-Lift-System-N production engineering.pdfArtificial-Lift-System-N production engineering.pdf
Artificial-Lift-System-N production engineering.pdf
IsmailKatun1
 

Similar to Small Hydro Training Module (20)

Introduction to power plant
Introduction to power plantIntroduction to power plant
Introduction to power plant
 
Basics of Hydro power plant
Basics of  Hydro power plant Basics of  Hydro power plant
Basics of Hydro power plant
 
Hydraulic Ram Pump: Consumers guide - Delft University of Technology
Hydraulic Ram Pump: Consumers guide - Delft University of TechnologyHydraulic Ram Pump: Consumers guide - Delft University of Technology
Hydraulic Ram Pump: Consumers guide - Delft University of Technology
 
PLANNING & DESIGN OF LIFT IRRIGATION.pptx
PLANNING & DESIGN OF LIFT IRRIGATION.pptxPLANNING & DESIGN OF LIFT IRRIGATION.pptx
PLANNING & DESIGN OF LIFT IRRIGATION.pptx
 
Archimedes Screw as a Low Head Hydropower Generator
Archimedes Screw as a Low Head Hydropower GeneratorArchimedes Screw as a Low Head Hydropower Generator
Archimedes Screw as a Low Head Hydropower Generator
 
Hydro power plant
Hydro power plantHydro power plant
Hydro power plant
 
commutation failure
commutation failurecommutation failure
commutation failure
 
Hydro electric power plant lecture
Hydro electric power plant lectureHydro electric power plant lecture
Hydro electric power plant lecture
 
Presentation1.pptx
Presentation1.pptxPresentation1.pptx
Presentation1.pptx
 
New Wave Energy Services Ltd. Presentation 2016 US
New Wave Energy Services Ltd. Presentation 2016 USNew Wave Energy Services Ltd. Presentation 2016 US
New Wave Energy Services Ltd. Presentation 2016 US
 
Hydro Energy or Hydro power conversion Technology
Hydro Energy or Hydro power conversion TechnologyHydro Energy or Hydro power conversion Technology
Hydro Energy or Hydro power conversion Technology
 
MRE 510 ppt... 2 Hydraulic Turbines.pptx
MRE 510 ppt... 2 Hydraulic Turbines.pptxMRE 510 ppt... 2 Hydraulic Turbines.pptx
MRE 510 ppt... 2 Hydraulic Turbines.pptx
 
Hydro power plant
Hydro power plantHydro power plant
Hydro power plant
 
Water Lifts and Pumps
Water Lifts and PumpsWater Lifts and Pumps
Water Lifts and Pumps
 
Pump efficiency
Pump efficiencyPump efficiency
Pump efficiency
 
Proposed Design Models of Axial-Flux Permanent Magnet Synchronous Generator ...
Proposed Design Models of Axial-Flux Permanent Magnet  Synchronous Generator ...Proposed Design Models of Axial-Flux Permanent Magnet  Synchronous Generator ...
Proposed Design Models of Axial-Flux Permanent Magnet Synchronous Generator ...
 
Hydel Generation and Types Of Turbines
Hydel Generation and Types Of TurbinesHydel Generation and Types Of Turbines
Hydel Generation and Types Of Turbines
 
Barangaroo South District Cooling Plant (DCP) Fact Sheet
Barangaroo South District Cooling Plant (DCP) Fact SheetBarangaroo South District Cooling Plant (DCP) Fact Sheet
Barangaroo South District Cooling Plant (DCP) Fact Sheet
 
3: Energy Management In Water Supply Systems - Pumping Operations
3: Energy Management In Water Supply Systems - Pumping Operations3: Energy Management In Water Supply Systems - Pumping Operations
3: Energy Management In Water Supply Systems - Pumping Operations
 
Artificial-Lift-System-N production engineering.pdf
Artificial-Lift-System-N production engineering.pdfArtificial-Lift-System-N production engineering.pdf
Artificial-Lift-System-N production engineering.pdf
 

Recently uploaded

Essentials of Automations: Optimizing FME Workflows with Parameters
Essentials of Automations: Optimizing FME Workflows with ParametersEssentials of Automations: Optimizing FME Workflows with Parameters
Essentials of Automations: Optimizing FME Workflows with Parameters
Safe Software
 
Neuro-symbolic is not enough, we need neuro-*semantic*
Neuro-symbolic is not enough, we need neuro-*semantic*Neuro-symbolic is not enough, we need neuro-*semantic*
Neuro-symbolic is not enough, we need neuro-*semantic*
Frank van Harmelen
 
JMeter webinar - integration with InfluxDB and Grafana
JMeter webinar - integration with InfluxDB and GrafanaJMeter webinar - integration with InfluxDB and Grafana
JMeter webinar - integration with InfluxDB and Grafana
RTTS
 
How world-class product teams are winning in the AI era by CEO and Founder, P...
How world-class product teams are winning in the AI era by CEO and Founder, P...How world-class product teams are winning in the AI era by CEO and Founder, P...
How world-class product teams are winning in the AI era by CEO and Founder, P...
Product School
 
Connector Corner: Automate dynamic content and events by pushing a button
Connector Corner: Automate dynamic content and events by pushing a buttonConnector Corner: Automate dynamic content and events by pushing a button
Connector Corner: Automate dynamic content and events by pushing a button
DianaGray10
 
Epistemic Interaction - tuning interfaces to provide information for AI support
Epistemic Interaction - tuning interfaces to provide information for AI supportEpistemic Interaction - tuning interfaces to provide information for AI support
Epistemic Interaction - tuning interfaces to provide information for AI support
Alan Dix
 
Knowledge engineering: from people to machines and back
Knowledge engineering: from people to machines and backKnowledge engineering: from people to machines and back
Knowledge engineering: from people to machines and back
Elena Simperl
 
Search and Society: Reimagining Information Access for Radical Futures
Search and Society: Reimagining Information Access for Radical FuturesSearch and Society: Reimagining Information Access for Radical Futures
Search and Society: Reimagining Information Access for Radical Futures
Bhaskar Mitra
 
Dev Dives: Train smarter, not harder – active learning and UiPath LLMs for do...
Dev Dives: Train smarter, not harder – active learning and UiPath LLMs for do...Dev Dives: Train smarter, not harder – active learning and UiPath LLMs for do...
Dev Dives: Train smarter, not harder – active learning and UiPath LLMs for do...
UiPathCommunity
 
Designing Great Products: The Power of Design and Leadership by Chief Designe...
Designing Great Products: The Power of Design and Leadership by Chief Designe...Designing Great Products: The Power of Design and Leadership by Chief Designe...
Designing Great Products: The Power of Design and Leadership by Chief Designe...
Product School
 
PHP Frameworks: I want to break free (IPC Berlin 2024)
PHP Frameworks: I want to break free (IPC Berlin 2024)PHP Frameworks: I want to break free (IPC Berlin 2024)
PHP Frameworks: I want to break free (IPC Berlin 2024)
Ralf Eggert
 
Key Trends Shaping the Future of Infrastructure.pdf
Key Trends Shaping the Future of Infrastructure.pdfKey Trends Shaping the Future of Infrastructure.pdf
Key Trends Shaping the Future of Infrastructure.pdf
Cheryl Hung
 
Kubernetes & AI - Beauty and the Beast !?! @KCD Istanbul 2024
Kubernetes & AI - Beauty and the Beast !?! @KCD Istanbul 2024Kubernetes & AI - Beauty and the Beast !?! @KCD Istanbul 2024
Kubernetes & AI - Beauty and the Beast !?! @KCD Istanbul 2024
Tobias Schneck
 
State of ICS and IoT Cyber Threat Landscape Report 2024 preview
State of ICS and IoT Cyber Threat Landscape Report 2024 previewState of ICS and IoT Cyber Threat Landscape Report 2024 preview
State of ICS and IoT Cyber Threat Landscape Report 2024 preview
Prayukth K V
 
Builder.ai Founder Sachin Dev Duggal's Strategic Approach to Create an Innova...
Builder.ai Founder Sachin Dev Duggal's Strategic Approach to Create an Innova...Builder.ai Founder Sachin Dev Duggal's Strategic Approach to Create an Innova...
Builder.ai Founder Sachin Dev Duggal's Strategic Approach to Create an Innova...
Ramesh Iyer
 
Transcript: Selling digital books in 2024: Insights from industry leaders - T...
Transcript: Selling digital books in 2024: Insights from industry leaders - T...Transcript: Selling digital books in 2024: Insights from industry leaders - T...
Transcript: Selling digital books in 2024: Insights from industry leaders - T...
BookNet Canada
 
Accelerate your Kubernetes clusters with Varnish Caching
Accelerate your Kubernetes clusters with Varnish CachingAccelerate your Kubernetes clusters with Varnish Caching
Accelerate your Kubernetes clusters with Varnish Caching
Thijs Feryn
 
DevOps and Testing slides at DASA Connect
DevOps and Testing slides at DASA ConnectDevOps and Testing slides at DASA Connect
DevOps and Testing slides at DASA Connect
Kari Kakkonen
 
The Art of the Pitch: WordPress Relationships and Sales
The Art of the Pitch: WordPress Relationships and SalesThe Art of the Pitch: WordPress Relationships and Sales
The Art of the Pitch: WordPress Relationships and Sales
Laura Byrne
 
Bits & Pixels using AI for Good.........
Bits & Pixels using AI for Good.........Bits & Pixels using AI for Good.........
Bits & Pixels using AI for Good.........
Alison B. Lowndes
 

Recently uploaded (20)

Essentials of Automations: Optimizing FME Workflows with Parameters
Essentials of Automations: Optimizing FME Workflows with ParametersEssentials of Automations: Optimizing FME Workflows with Parameters
Essentials of Automations: Optimizing FME Workflows with Parameters
 
Neuro-symbolic is not enough, we need neuro-*semantic*
Neuro-symbolic is not enough, we need neuro-*semantic*Neuro-symbolic is not enough, we need neuro-*semantic*
Neuro-symbolic is not enough, we need neuro-*semantic*
 
JMeter webinar - integration with InfluxDB and Grafana
JMeter webinar - integration with InfluxDB and GrafanaJMeter webinar - integration with InfluxDB and Grafana
JMeter webinar - integration with InfluxDB and Grafana
 
How world-class product teams are winning in the AI era by CEO and Founder, P...
How world-class product teams are winning in the AI era by CEO and Founder, P...How world-class product teams are winning in the AI era by CEO and Founder, P...
How world-class product teams are winning in the AI era by CEO and Founder, P...
 
Connector Corner: Automate dynamic content and events by pushing a button
Connector Corner: Automate dynamic content and events by pushing a buttonConnector Corner: Automate dynamic content and events by pushing a button
Connector Corner: Automate dynamic content and events by pushing a button
 
Epistemic Interaction - tuning interfaces to provide information for AI support
Epistemic Interaction - tuning interfaces to provide information for AI supportEpistemic Interaction - tuning interfaces to provide information for AI support
Epistemic Interaction - tuning interfaces to provide information for AI support
 
Knowledge engineering: from people to machines and back
Knowledge engineering: from people to machines and backKnowledge engineering: from people to machines and back
Knowledge engineering: from people to machines and back
 
Search and Society: Reimagining Information Access for Radical Futures
Search and Society: Reimagining Information Access for Radical FuturesSearch and Society: Reimagining Information Access for Radical Futures
Search and Society: Reimagining Information Access for Radical Futures
 
Dev Dives: Train smarter, not harder – active learning and UiPath LLMs for do...
Dev Dives: Train smarter, not harder – active learning and UiPath LLMs for do...Dev Dives: Train smarter, not harder – active learning and UiPath LLMs for do...
Dev Dives: Train smarter, not harder – active learning and UiPath LLMs for do...
 
Designing Great Products: The Power of Design and Leadership by Chief Designe...
Designing Great Products: The Power of Design and Leadership by Chief Designe...Designing Great Products: The Power of Design and Leadership by Chief Designe...
Designing Great Products: The Power of Design and Leadership by Chief Designe...
 
PHP Frameworks: I want to break free (IPC Berlin 2024)
PHP Frameworks: I want to break free (IPC Berlin 2024)PHP Frameworks: I want to break free (IPC Berlin 2024)
PHP Frameworks: I want to break free (IPC Berlin 2024)
 
Key Trends Shaping the Future of Infrastructure.pdf
Key Trends Shaping the Future of Infrastructure.pdfKey Trends Shaping the Future of Infrastructure.pdf
Key Trends Shaping the Future of Infrastructure.pdf
 
Kubernetes & AI - Beauty and the Beast !?! @KCD Istanbul 2024
Kubernetes & AI - Beauty and the Beast !?! @KCD Istanbul 2024Kubernetes & AI - Beauty and the Beast !?! @KCD Istanbul 2024
Kubernetes & AI - Beauty and the Beast !?! @KCD Istanbul 2024
 
State of ICS and IoT Cyber Threat Landscape Report 2024 preview
State of ICS and IoT Cyber Threat Landscape Report 2024 previewState of ICS and IoT Cyber Threat Landscape Report 2024 preview
State of ICS and IoT Cyber Threat Landscape Report 2024 preview
 
Builder.ai Founder Sachin Dev Duggal's Strategic Approach to Create an Innova...
Builder.ai Founder Sachin Dev Duggal's Strategic Approach to Create an Innova...Builder.ai Founder Sachin Dev Duggal's Strategic Approach to Create an Innova...
Builder.ai Founder Sachin Dev Duggal's Strategic Approach to Create an Innova...
 
Transcript: Selling digital books in 2024: Insights from industry leaders - T...
Transcript: Selling digital books in 2024: Insights from industry leaders - T...Transcript: Selling digital books in 2024: Insights from industry leaders - T...
Transcript: Selling digital books in 2024: Insights from industry leaders - T...
 
Accelerate your Kubernetes clusters with Varnish Caching
Accelerate your Kubernetes clusters with Varnish CachingAccelerate your Kubernetes clusters with Varnish Caching
Accelerate your Kubernetes clusters with Varnish Caching
 
DevOps and Testing slides at DASA Connect
DevOps and Testing slides at DASA ConnectDevOps and Testing slides at DASA Connect
DevOps and Testing slides at DASA Connect
 
The Art of the Pitch: WordPress Relationships and Sales
The Art of the Pitch: WordPress Relationships and SalesThe Art of the Pitch: WordPress Relationships and Sales
The Art of the Pitch: WordPress Relationships and Sales
 
Bits & Pixels using AI for Good.........
Bits & Pixels using AI for Good.........Bits & Pixels using AI for Good.........
Bits & Pixels using AI for Good.........
 

Small Hydro Training Module

  • 1. Cook Legacy College Training Module M-200: Fundamentals of Small Hydro
  • 2. Goals of This 15-Minute Module  Know what small hydro is.  Understand major features, components, and selection criteria  Understand technical and financial considerations when assessing a site
  • 3. Fundamentals of Small Hydro SH 101: Overview and Background SH 102: Fundamentals SH 103: Review and Quiz 3
  • 4. What is Small Hydro Small Hydro (also called small hydroelectric or small hydro) refers to the generation of electrical power by using diverted water to rotate a turbine. The major components include: • An intake • A penstock • A turbine & generator • A switchyard for connection to the power pole 4
  • 5. What is Small Hydro The most commonly used form in intake structure design is the “Discharge Equation.” Different forms are used for flow over the spillway, Coanda accelerator, measurement weirs, and various secondary spills. Generally the value of C, the discharge coefficient, will adjust based on some empirical test. The basic discharge equation is Q=Clh^3/2 Where: Q=Flow C=Discharge coefficient l=Length of the weir h=head above the crest The most important thing when selecting and implementing a discharge equation is ensuring it matches in all respects the condition it was intended for. 5
  • 6. Calculating Power Potential Power is given as: P=HQkG Where: P=Power in watts H=Head (the difference in elevation between the intake and the powerhouse Q=Flow in m^3/s G=Gravity (9.8 m/s^2) k=Turbine efficiency A quick estimate is to take 7 * Q* H Head (m) Flow (m3/s) Power in kW 6 7 x Head x Flow
  • 7. What is Small Hydro What counts as small hydro? Typical Power Micro Mini 100 to 1,000 kW Small 7 < 100 kW 1 to 50 MW
  • 8. What is Small Hydro  Type of grid – Central-grid: Generated power is sold back to a power grid such as a utility. – Isolated-grid or off-grid: Generated power is used locally near the point of generation.  Type of civil works – Run-of-river • No water storage • Power varies with flow available from river: lower firm capacity – Reservoir • Higher firm capacity year-round 8 • Significant damming usually required
  • 10. Process for Sizing Site • Estimate flow duration curve based on  Measurements of flow over time  Size of drainage above site, specific run-off, and shape of flow duration curve  The easiest way to mess up a high head site is to overestimate the flow (as this is the only variable) Flow-Duration Curve Flow (m³/s) 50.0 40.0 30.0 20.0 10.0 0.0 0 10 20 30 40 50 60 70 80 90 100 Percent Time Flow Equalled or Exceeded (% ) 10
  • 11. Process for Sizing Site Picking the Turbine at various points on the FDC Flow-Duration Curve 40.0 • Estimate the cost of equipment cost associated with those. This includes questions such as the size of the equipment and how many nozzles will be used. • Integrate the area under the curve with various scenarios and pick the best payback. Sometimes this can be approximated by simply slicing the FDC into a few scenarios. 11 Flow (m³/s) • Estimate the installed capacity 50.0 30.0 20.0 10.0 0.0 0 10 20 30 40 50 60 70 80 90 100 Percent Time Flow Equalled or Exceeded (% ) For example: The green line has high capacity to “catch” high flow events, but may not run enough to be worth the cost. The blue line will be cheaper, but may leave power on the table. The red line may be the best return.
  • 12. Small Hydro Major Components The most expensive cost component for a small hydro plant is the Civil Cost. Much of our approach is in lowering the civil cap-ex. Small Hydro Cost Estimate Other 10% Electrical 10% Mechanical & Controls 25% 12 Civil Cost 55%
  • 13. Small Hydro Major Components The major components for the site are: • Intake structure • Penstock • Powerhouse – the primary components of the powerhouse are: o Turbine-generator o Switchyard 13
  • 14. Intake Structure The intake structure needs to deliver clean water to the penstock Traditional intakes include a coarse screen with secondary screening and settling basins to remove sand. Coanda screens eliminate secondary screening need & use overflowing water to stay clean. 14
  • 16. Pelton Turbine Details As Coanda Screens are most suitable for medium and high head sites they are commonly paired with Pelton Machines Peltons have a series of nozzles controlled by actuated needle valves, that spray water onto the runners. 16
  • 19. Low Head Hydro: Natel HydoEngine In the low head space, we offer complementary process equipment to a range of turbine designs. 19
  • 20. Low Head Hydro: Cleanpower Turbinator 20
  • 21. Other Powerhouse Components The generator is connected to the turbine. A generator can be either synchronous (i.e. designed to work with an existing load) or asynchronous. For very small sites an induction motor can be used in place of the generator. Additional components are the plant controls and basic facility requirements like lighting, fire protection, personnel protection, and monitoring equipment. 21
  • 23. Design Considerations Intake Design Turbine Selection • Side intake • Coanda • Head • Flow • Fish Technical Penstock Design • Distance • Pressure 23 T&D Design • Distance • Connection Type
  • 24. Design Considerations Cap-Ex Funding Sources • Civil • Mechanical • Consultancy • NGO • Private Funding • Equipment Financial Cost of Capital Payback of Components • Cheap & swap • Long term value 24
  • 26. Design Considerations Social Fisheries • Build projects good for people • Don’t screw landowners. Be fair. • Improve diversion • Improve survival Environmental Land Use • Intake • T&D 26 Proper O&M
  • 27. Review Questions   27 What are the components of calculating power capacity? What are the balance of plant benefits of a Coanda intake