SlideShare a Scribd company logo
Strategic Air Planning:
Is the time for a PAL here?
                        John Egan
                          All4 Inc.
       NCASI 2011 Northern Regional
                        Wausau, WI

                       May 19, 2011
Agenda
       Mounting air pressures
       Mill needs and expectations
       Major new source review struggles
       Importance of strategic planning
       Considerations for an advantage




2
Air Pressure
       NAAQS
       Boiler MACT/CISWI/NHSM
       Pulp & Paper MACT/Residual Risk
       GHG Regulation
       BART/Regional Haze
       Utility MACT/NSPS
       Multi-pollutant Rules
       Black Carbon
       More…

3
Air Pressure
       Common theme:
         For most facilities future emissions
         will decrease from historic actual
         levels as a result of new and
         developing air regulations and
         standards, regardless of growth in
         productivity.




4
Mill Needs
       Ability to change operations/equipment
        quickly and as needed
       Long range targets for planning:
         • Internal - production/energy/economics
         • External - rule driven costs to comply
       Clarity in regulatory requirements
        particularly for permitting



5
New Source Review
       NSR reminder:
        • Attainment Area = Prevention of
          Significant Deterioration (PSD), allowed
          to increase actual emissions but always
          a challenge
        • Non-attainment Area = Non-attainment
          New Source Review (NNSR), project
          has to improve area air quality



6
PSD Implementation
       Quick PSD implementation history for mill
        changes:
         • Old/old way (pre-reform)
         • Old/new way (post-reform)
         • New/new way (current & post 1-hr
           NAAQS)




7
Old/Old PSD
       Pre-NSR reform:
        • Actual-to-potential test
        • New limits to reduce PTE and avoid PSD
        • BACT main driver if PSD triggered
        • Air modeling a challenge for some
          pollutants but manageable
        • Implementation evolved over 25 years



8
Old/New PSD
       Post-NSR reform:
        • Actual-to-projected actual test
        • Better baseline/no new limits
          (supposedly)
        • Required to track relative to projections
        • Formal guidance evolved but limited
        • If PSD - BACT still a driver and air
          modeling still a challenge for some


9
New/New PSD
        Current & post 1-hr NAAQS:
         • Still actual-to-projected actual test
         • Concern w/excluded emissions
         • How to handle project on project
         • Watch out for netting
         • If PSD - air modeling more critical than
           BACT and can alter project design



10
Future Planning
        Strategic planning for facility future must
         consider implications of both new air rule
         applicability and air permitting implications:
          • New rules likely require facility changes
          • No exemption for pollution control
            projects
          • Permitting issues can impact project
            design


11
Future Planning
        Air issues must be integrated into facility
         operations planning
        Result will be same old push/pull for mill
         projects whether needed or required:
          • PSD applicability analysis
          • Potential impacts to project design, cost,
            schedule
          • Confusion and frustration


12
PAL Option
        “Plantwide Applicability Limitation” (PAL) is
         an available regulatory option that can
         potentially ease air permitting PSD cycle
        Federal PSD rule provides for PALs based
         on historic actual emissions
        PALs are pollutant specific and could be a
         critical part of a Mill strategic plan




13
PAL Advantages
        For a facility with a PAL permit that
         maintains emissions below PAL, physical
         changes and changes in method of
         operation are not major modifications and
         do not require approval under PSD




14
Why a PAL Now?
        PALs historically worked for relatively
         simple industries with limited sources and
         where technology was driving emissions
         lower per unit of production
        New air quality world we are in is forcing
         mills to realization that future emissions will
         be lower per unit of production driven by
         rules, standards, permitting, technology…



15
Why a PAL Now?
        Must be able to track and report emissions
         against PAL
        Historically mills saw too many sources
         and not enough data to justify a PAL
        Data and tools now available for
         demonstrating compliance due to other
         rule activities (e.g., ICR work)




16
Establishing a PAL
        Same baseline actual emissions used in
         PSD applicability assessment:
         • Adjust for current applicable
           requirements
         • Add PSD significance threshold
         • Justify PAL and provide method of
           compliance




17
PAL Concerns
        PAL established for 10 year period
        PAL can be adjusted down to account for
         new applicable requirements
        Getting out of a PAL can have serious
         ramifications
        State/local air construction permits may
         still be required




18
PAL Planning Approach
        Develop historic mill-wide baseline
         emission rates and potential PAL levels
        Address potential NAAQS issues
        Consider new rules, mill operations plans,
         potential energy efficiency improvements,
         new technologies, low hanging fruit for
         emissions reductions
        Weigh value of PAL for each pollutant


19
Final Thoughts
        For typical mill projects PSD is no longer a
         consideration under a PAL
        For planning mill now has a clear bright
         line it can manage operations to
        Project timing may result in competitive
         advantage
        Future second guessing by agency of PSD
         applicability decisions and potential
         enforcement issues off the table

20
Questions?


       jegan@all4inc.com

             All4 Inc.
       2393 Kimberton Road
           P.O. Box 299
       Kimberton, PA 19442
     610.933.5246 x14 and x20

         www.all4inc.com




21

More Related Content

What's hot

Plant Changes That Trigger Air Permitting; Sturm, Eric; NAQS; 2014 Mid-Americ...
Plant Changes That Trigger Air Permitting; Sturm, Eric; NAQS; 2014 Mid-Americ...Plant Changes That Trigger Air Permitting; Sturm, Eric; NAQS; 2014 Mid-Americ...
Plant Changes That Trigger Air Permitting; Sturm, Eric; NAQS; 2014 Mid-Americ...MECConference
 
Case studies: Predictive maintenance in the petrochemical industry
Case studies: Predictive maintenance in the petrochemical industryCase studies: Predictive maintenance in the petrochemical industry
Case studies: Predictive maintenance in the petrochemical industry
Advisian
 
Decommissioning your offshore assets
Decommissioning your offshore assetsDecommissioning your offshore assets
Decommissioning your offshore assets
Advisian
 
BlueScape and Cooper White - BAAQMD Air Toxics Risk Reduction Rule 11-18 Webi...
BlueScape and Cooper White - BAAQMD Air Toxics Risk Reduction Rule 11-18 Webi...BlueScape and Cooper White - BAAQMD Air Toxics Risk Reduction Rule 11-18 Webi...
BlueScape and Cooper White - BAAQMD Air Toxics Risk Reduction Rule 11-18 Webi...
BlueScape
 
Concepts for Proposed General Permit for Well Pads and Proposed GP-5 Modifica...
Concepts for Proposed General Permit for Well Pads and Proposed GP-5 Modifica...Concepts for Proposed General Permit for Well Pads and Proposed GP-5 Modifica...
Concepts for Proposed General Permit for Well Pads and Proposed GP-5 Modifica...
Marcellus Drilling News
 
Remedial Process Optimization - Moffett RAB
Remedial Process Optimization - Moffett RABRemedial Process Optimization - Moffett RAB
Remedial Process Optimization - Moffett RAB
Steve Williams
 
Navy Moffett Environmental Restoration Program 2008 Review/2009 Goals
Navy Moffett Environmental Restoration Program 2008 Review/2009 GoalsNavy Moffett Environmental Restoration Program 2008 Review/2009 Goals
Navy Moffett Environmental Restoration Program 2008 Review/2009 Goals
Steve Williams
 
American Institute of Architects Committee on the Envrinment
American Institute of Architects Committee on the EnvrinmentAmerican Institute of Architects Committee on the Envrinment
American Institute of Architects Committee on the Envrinment
Center for Energy and Environment
 
Generating Cash From Your Backup Generator
Generating Cash From Your Backup GeneratorGenerating Cash From Your Backup Generator
Generating Cash From Your Backup Generator
Sergio A. Guerra
 
BlueScape How to Create a CEQA Air Quality Analysis for Development Projects ...
BlueScape How to Create a CEQA Air Quality Analysis for Development Projects ...BlueScape How to Create a CEQA Air Quality Analysis for Development Projects ...
BlueScape How to Create a CEQA Air Quality Analysis for Development Projects ...
BlueScape
 
Prodml Production Reporting | Hydrocarbon Allocation Forum | 2014 09-30
Prodml Production Reporting | Hydrocarbon Allocation Forum | 2014 09-30Prodml Production Reporting | Hydrocarbon Allocation Forum | 2014 09-30
Prodml Production Reporting | Hydrocarbon Allocation Forum | 2014 09-30
EnergySys Limited
 
Skills development for the new Oil & Gas industry
Skills development for the new Oil & Gas industrySkills development for the new Oil & Gas industry
Skills development for the new Oil & Gas industry
Advisian
 
Smart Integrated Infrastructure and Controlling Water Loss
Smart Integrated Infrastructure and Controlling Water LossSmart Integrated Infrastructure and Controlling Water Loss
Smart Integrated Infrastructure and Controlling Water Loss
Black & Veatch
 
MDE's Stormwater Permitting Requirements
MDE's Stormwater Permitting RequirementsMDE's Stormwater Permitting Requirements
MDE's Stormwater Permitting Requirements
Triumvirate Environmental
 
Item no
Item noItem no
Item norehant
 

What's hot (16)

Plant Changes That Trigger Air Permitting; Sturm, Eric; NAQS; 2014 Mid-Americ...
Plant Changes That Trigger Air Permitting; Sturm, Eric; NAQS; 2014 Mid-Americ...Plant Changes That Trigger Air Permitting; Sturm, Eric; NAQS; 2014 Mid-Americ...
Plant Changes That Trigger Air Permitting; Sturm, Eric; NAQS; 2014 Mid-Americ...
 
Case studies: Predictive maintenance in the petrochemical industry
Case studies: Predictive maintenance in the petrochemical industryCase studies: Predictive maintenance in the petrochemical industry
Case studies: Predictive maintenance in the petrochemical industry
 
Decommissioning your offshore assets
Decommissioning your offshore assetsDecommissioning your offshore assets
Decommissioning your offshore assets
 
BlueScape and Cooper White - BAAQMD Air Toxics Risk Reduction Rule 11-18 Webi...
BlueScape and Cooper White - BAAQMD Air Toxics Risk Reduction Rule 11-18 Webi...BlueScape and Cooper White - BAAQMD Air Toxics Risk Reduction Rule 11-18 Webi...
BlueScape and Cooper White - BAAQMD Air Toxics Risk Reduction Rule 11-18 Webi...
 
Concepts for Proposed General Permit for Well Pads and Proposed GP-5 Modifica...
Concepts for Proposed General Permit for Well Pads and Proposed GP-5 Modifica...Concepts for Proposed General Permit for Well Pads and Proposed GP-5 Modifica...
Concepts for Proposed General Permit for Well Pads and Proposed GP-5 Modifica...
 
Remedial Process Optimization - Moffett RAB
Remedial Process Optimization - Moffett RABRemedial Process Optimization - Moffett RAB
Remedial Process Optimization - Moffett RAB
 
Navy Moffett Environmental Restoration Program 2008 Review/2009 Goals
Navy Moffett Environmental Restoration Program 2008 Review/2009 GoalsNavy Moffett Environmental Restoration Program 2008 Review/2009 Goals
Navy Moffett Environmental Restoration Program 2008 Review/2009 Goals
 
American Institute of Architects Committee on the Envrinment
American Institute of Architects Committee on the EnvrinmentAmerican Institute of Architects Committee on the Envrinment
American Institute of Architects Committee on the Envrinment
 
Generating Cash From Your Backup Generator
Generating Cash From Your Backup GeneratorGenerating Cash From Your Backup Generator
Generating Cash From Your Backup Generator
 
BlueScape How to Create a CEQA Air Quality Analysis for Development Projects ...
BlueScape How to Create a CEQA Air Quality Analysis for Development Projects ...BlueScape How to Create a CEQA Air Quality Analysis for Development Projects ...
BlueScape How to Create a CEQA Air Quality Analysis for Development Projects ...
 
Prodml Production Reporting | Hydrocarbon Allocation Forum | 2014 09-30
Prodml Production Reporting | Hydrocarbon Allocation Forum | 2014 09-30Prodml Production Reporting | Hydrocarbon Allocation Forum | 2014 09-30
Prodml Production Reporting | Hydrocarbon Allocation Forum | 2014 09-30
 
Skills development for the new Oil & Gas industry
Skills development for the new Oil & Gas industrySkills development for the new Oil & Gas industry
Skills development for the new Oil & Gas industry
 
Smart Integrated Infrastructure and Controlling Water Loss
Smart Integrated Infrastructure and Controlling Water LossSmart Integrated Infrastructure and Controlling Water Loss
Smart Integrated Infrastructure and Controlling Water Loss
 
MDE's Stormwater Permitting Requirements
MDE's Stormwater Permitting RequirementsMDE's Stormwater Permitting Requirements
MDE's Stormwater Permitting Requirements
 
CV-ZTUFAIL2016
CV-ZTUFAIL2016CV-ZTUFAIL2016
CV-ZTUFAIL2016
 
Item no
Item noItem no
Item no
 

Similar to Strategic Air Planning: Is the time for a PAL here?

Implications of Greenhouse Gas (GHG), Volatile Organic Compounds (VOC), and F...
Implications of Greenhouse Gas (GHG), Volatile Organic Compounds (VOC), and F...Implications of Greenhouse Gas (GHG), Volatile Organic Compounds (VOC), and F...
Implications of Greenhouse Gas (GHG), Volatile Organic Compounds (VOC), and F...
All4 Inc.
 
Project Planning and Air Permit Issues
Project Planning and Air Permit IssuesProject Planning and Air Permit Issues
Project Planning and Air Permit IssuesAll4 Inc.
 
Potential PM2.5 and CPM Pitfalls in Permitting, Testing, and Compliance
Potential PM2.5 and CPM Pitfalls in Permitting, Testing, and CompliancePotential PM2.5 and CPM Pitfalls in Permitting, Testing, and Compliance
Potential PM2.5 and CPM Pitfalls in Permitting, Testing, and Compliance
All4 Inc.
 
The complexities of nsr permitting ddix
The complexities of nsr permitting ddixThe complexities of nsr permitting ddix
The complexities of nsr permitting ddix
All4 Inc.
 
Introduction to Carbon Capture and Storage
Introduction to Carbon Capture and Storage Introduction to Carbon Capture and Storage
Introduction to Carbon Capture and Storage
The Climate Institute
 
Project Management Track: Lean Projects, Cost Controls, Price Forecasts, & Re...
Project Management Track: Lean Projects, Cost Controls, Price Forecasts, & Re...Project Management Track: Lean Projects, Cost Controls, Price Forecasts, & Re...
Project Management Track: Lean Projects, Cost Controls, Price Forecasts, & Re...
Energy Construction Forum
 
Energy Optimization with Pinch Analysis McMullan
Energy Optimization with Pinch Analysis McMullanEnergy Optimization with Pinch Analysis McMullan
Energy Optimization with Pinch Analysis McMullan
KBC (A Yokogawa Company)
 
Compressed Timelines for Breakthrough Therapies: Impact on Process Characteri...
Compressed Timelines for Breakthrough Therapies: Impact on Process Characteri...Compressed Timelines for Breakthrough Therapies: Impact on Process Characteri...
Compressed Timelines for Breakthrough Therapies: Impact on Process Characteri...
KBI Biopharma
 
Boiler MACT and Strategic Air Permitting
Boiler MACT and Strategic Air PermittingBoiler MACT and Strategic Air Permitting
Boiler MACT and Strategic Air Permitting
All4 Inc.
 
The Status of CCS 2011 Report - Victor Der - Global CCS Institute – Nov 2011 ...
The Status of CCS 2011 Report - Victor Der - Global CCS Institute – Nov 2011 ...The Status of CCS 2011 Report - Victor Der - Global CCS Institute – Nov 2011 ...
The Status of CCS 2011 Report - Victor Der - Global CCS Institute – Nov 2011 ...
Global CCS Institute
 
Ppx
PpxPpx
Ppx
yn_raja
 
Richard clark cv
Richard clark cvRichard clark cv
Richard clark cv
Richard Clark
 
Advantages of a modern DCS in coal handling
Advantages of a modern DCS in coal handlingAdvantages of a modern DCS in coal handling
Advantages of a modern DCS in coal handling
Schneider Electric
 
Integrated Delivery of Supply Chain Solutions_5C Contracts_02-Nov-15
Integrated Delivery of Supply Chain Solutions_5C Contracts_02-Nov-15Integrated Delivery of Supply Chain Solutions_5C Contracts_02-Nov-15
Integrated Delivery of Supply Chain Solutions_5C Contracts_02-Nov-15Ian Carr SCMP, MCIPS
 
PHMSA Final Rule (part 1) for Gas Transmission Pipelines
PHMSA Final Rule (part 1) for Gas Transmission Pipelines PHMSA Final Rule (part 1) for Gas Transmission Pipelines
PHMSA Final Rule (part 1) for Gas Transmission Pipelines
Audubon Engineering Company
 
Design, Permitting and Construction Considerations for Marcellus Shale Gas Co...
Design, Permitting and Construction Considerations for Marcellus Shale Gas Co...Design, Permitting and Construction Considerations for Marcellus Shale Gas Co...
Design, Permitting and Construction Considerations for Marcellus Shale Gas Co...All4 Inc.
 
TChapman ENNU808I Assignment Final
TChapman ENNU808I Assignment FinalTChapman ENNU808I Assignment Final
TChapman ENNU808I Assignment FinalTravis Chapman
 
Barry Jones - Global Status of CCS – Presentation at the Global CCS Institute...
Barry Jones - Global Status of CCS – Presentation at the Global CCS Institute...Barry Jones - Global Status of CCS – Presentation at the Global CCS Institute...
Barry Jones - Global Status of CCS – Presentation at the Global CCS Institute...Global CCS Institute
 
2 co making the business case for ccs
2 co   making the business case for ccs2 co   making the business case for ccs
2 co making the business case for ccsGlobal CCS Institute
 

Similar to Strategic Air Planning: Is the time for a PAL here? (20)

Implications of Greenhouse Gas (GHG), Volatile Organic Compounds (VOC), and F...
Implications of Greenhouse Gas (GHG), Volatile Organic Compounds (VOC), and F...Implications of Greenhouse Gas (GHG), Volatile Organic Compounds (VOC), and F...
Implications of Greenhouse Gas (GHG), Volatile Organic Compounds (VOC), and F...
 
Project Planning and Air Permit Issues
Project Planning and Air Permit IssuesProject Planning and Air Permit Issues
Project Planning and Air Permit Issues
 
Qatar petroleum presentation
Qatar petroleum presentationQatar petroleum presentation
Qatar petroleum presentation
 
Potential PM2.5 and CPM Pitfalls in Permitting, Testing, and Compliance
Potential PM2.5 and CPM Pitfalls in Permitting, Testing, and CompliancePotential PM2.5 and CPM Pitfalls in Permitting, Testing, and Compliance
Potential PM2.5 and CPM Pitfalls in Permitting, Testing, and Compliance
 
The complexities of nsr permitting ddix
The complexities of nsr permitting ddixThe complexities of nsr permitting ddix
The complexities of nsr permitting ddix
 
Introduction to Carbon Capture and Storage
Introduction to Carbon Capture and Storage Introduction to Carbon Capture and Storage
Introduction to Carbon Capture and Storage
 
Project Management Track: Lean Projects, Cost Controls, Price Forecasts, & Re...
Project Management Track: Lean Projects, Cost Controls, Price Forecasts, & Re...Project Management Track: Lean Projects, Cost Controls, Price Forecasts, & Re...
Project Management Track: Lean Projects, Cost Controls, Price Forecasts, & Re...
 
Energy Optimization with Pinch Analysis McMullan
Energy Optimization with Pinch Analysis McMullanEnergy Optimization with Pinch Analysis McMullan
Energy Optimization with Pinch Analysis McMullan
 
Compressed Timelines for Breakthrough Therapies: Impact on Process Characteri...
Compressed Timelines for Breakthrough Therapies: Impact on Process Characteri...Compressed Timelines for Breakthrough Therapies: Impact on Process Characteri...
Compressed Timelines for Breakthrough Therapies: Impact on Process Characteri...
 
Boiler MACT and Strategic Air Permitting
Boiler MACT and Strategic Air PermittingBoiler MACT and Strategic Air Permitting
Boiler MACT and Strategic Air Permitting
 
The Status of CCS 2011 Report - Victor Der - Global CCS Institute – Nov 2011 ...
The Status of CCS 2011 Report - Victor Der - Global CCS Institute – Nov 2011 ...The Status of CCS 2011 Report - Victor Der - Global CCS Institute – Nov 2011 ...
The Status of CCS 2011 Report - Victor Der - Global CCS Institute – Nov 2011 ...
 
Ppx
PpxPpx
Ppx
 
Richard clark cv
Richard clark cvRichard clark cv
Richard clark cv
 
Advantages of a modern DCS in coal handling
Advantages of a modern DCS in coal handlingAdvantages of a modern DCS in coal handling
Advantages of a modern DCS in coal handling
 
Integrated Delivery of Supply Chain Solutions_5C Contracts_02-Nov-15
Integrated Delivery of Supply Chain Solutions_5C Contracts_02-Nov-15Integrated Delivery of Supply Chain Solutions_5C Contracts_02-Nov-15
Integrated Delivery of Supply Chain Solutions_5C Contracts_02-Nov-15
 
PHMSA Final Rule (part 1) for Gas Transmission Pipelines
PHMSA Final Rule (part 1) for Gas Transmission Pipelines PHMSA Final Rule (part 1) for Gas Transmission Pipelines
PHMSA Final Rule (part 1) for Gas Transmission Pipelines
 
Design, Permitting and Construction Considerations for Marcellus Shale Gas Co...
Design, Permitting and Construction Considerations for Marcellus Shale Gas Co...Design, Permitting and Construction Considerations for Marcellus Shale Gas Co...
Design, Permitting and Construction Considerations for Marcellus Shale Gas Co...
 
TChapman ENNU808I Assignment Final
TChapman ENNU808I Assignment FinalTChapman ENNU808I Assignment Final
TChapman ENNU808I Assignment Final
 
Barry Jones - Global Status of CCS – Presentation at the Global CCS Institute...
Barry Jones - Global Status of CCS – Presentation at the Global CCS Institute...Barry Jones - Global Status of CCS – Presentation at the Global CCS Institute...
Barry Jones - Global Status of CCS – Presentation at the Global CCS Institute...
 
2 co making the business case for ccs
2 co   making the business case for ccs2 co   making the business case for ccs
2 co making the business case for ccs
 

More from All4 Inc.

Impacts of U.S. EPA Region 6 Guidance on CMS Downtime and Data Calculations
Impacts of U.S. EPA Region 6 Guidance on CMS Downtime and Data CalculationsImpacts of U.S. EPA Region 6 Guidance on CMS Downtime and Data Calculations
Impacts of U.S. EPA Region 6 Guidance on CMS Downtime and Data Calculations
All4 Inc.
 
Implementing a DAHS for Compliance with the Refinery Sector Rule
Implementing a DAHS for Compliance with the Refinery Sector RuleImplementing a DAHS for Compliance with the Refinery Sector Rule
Implementing a DAHS for Compliance with the Refinery Sector Rule
All4 Inc.
 
NSR Reform Updates
NSR Reform Updates NSR Reform Updates
NSR Reform Updates
All4 Inc.
 
Tceq recent permitting changes 4 c-2019-f_dougherty (1-31-19)
Tceq recent permitting changes 4 c-2019-f_dougherty (1-31-19)Tceq recent permitting changes 4 c-2019-f_dougherty (1-31-19)
Tceq recent permitting changes 4 c-2019-f_dougherty (1-31-19)
All4 Inc.
 
All4 impacts of recent u.s. epa region 6 guidance on cms downtime and data ...
All4   impacts of recent u.s. epa region 6 guidance on cms downtime and data ...All4   impacts of recent u.s. epa region 6 guidance on cms downtime and data ...
All4 impacts of recent u.s. epa region 6 guidance on cms downtime and data ...
All4 Inc.
 
D dix awma conference air toxics evaluation requirements 062718
D dix awma conference air toxics evaluation requirements 062718D dix awma conference air toxics evaluation requirements 062718
D dix awma conference air toxics evaluation requirements 062718
All4 Inc.
 
4 c nsr presentation 032318 all4 mccall
4 c nsr presentation 032318   all4 mccall4 c nsr presentation 032318   all4 mccall
4 c nsr presentation 032318 all4 mccall
All4 Inc.
 
All4 inc awma re-entrainment
All4 inc awma re-entrainmentAll4 inc awma re-entrainment
All4 inc awma re-entrainment
All4 Inc.
 
All4 tcc acit pres ipt guidance 2017
All4 tcc acit pres ipt guidance 2017All4 tcc acit pres ipt guidance 2017
All4 tcc acit pres ipt guidance 2017
All4 Inc.
 
Air Quality Compliance Training 12-8-16
Air Quality Compliance Training 12-8-16Air Quality Compliance Training 12-8-16
Air Quality Compliance Training 12-8-16
All4 Inc.
 
CEDRI-NextGen
CEDRI-NextGenCEDRI-NextGen
CEDRI-NextGen
All4 Inc.
 
understanding the validity and increased scrutiny of data used for compliance...
understanding the validity and increased scrutiny of data used for compliance...understanding the validity and increased scrutiny of data used for compliance...
understanding the validity and increased scrutiny of data used for compliance...
All4 Inc.
 
CUHMMC Presentation
CUHMMC PresentationCUHMMC Presentation
CUHMMC Presentation
All4 Inc.
 
Preview of ALL4 Air Quality Compliance - PIOGATech
Preview of ALL4 Air Quality Compliance - PIOGATechPreview of ALL4 Air Quality Compliance - PIOGATech
Preview of ALL4 Air Quality Compliance - PIOGATech
All4 Inc.
 
Top 5 Environmental Compliance Issues for Engineers and Managers
Top 5 Environmental Compliance Issues for Engineers and ManagersTop 5 Environmental Compliance Issues for Engineers and Managers
Top 5 Environmental Compliance Issues for Engineers and Managers
All4 Inc.
 
SO2 Data Requirements Rule Modeling Strategies
SO2 Data Requirements Rule Modeling StrategiesSO2 Data Requirements Rule Modeling Strategies
SO2 Data Requirements Rule Modeling Strategies
All4 Inc.
 
The complexities of new source review air permitting – a case study ddix 020116
The complexities of new source review air permitting – a case study ddix 020116The complexities of new source review air permitting – a case study ddix 020116
The complexities of new source review air permitting – a case study ddix 020116
All4 Inc.
 
The Good vs. Bad: The Specifics for Validating CMS Data
The Good vs. Bad: The Specifics for Validating CMS DataThe Good vs. Bad: The Specifics for Validating CMS Data
The Good vs. Bad: The Specifics for Validating CMS Data
All4 Inc.
 
Benzene Fenceline Monitoring: An Introduction and What the Regulations Don’...
Benzene Fenceline Monitoring:  An Introduction and What the Regulations Don’...Benzene Fenceline Monitoring:  An Introduction and What the Regulations Don’...
Benzene Fenceline Monitoring: An Introduction and What the Regulations Don’...
All4 Inc.
 
The Petroleum Refinery Sector Rule: What’s all the fuss about and what are th...
The Petroleum Refinery Sector Rule: What’s all the fuss about and what are th...The Petroleum Refinery Sector Rule: What’s all the fuss about and what are th...
The Petroleum Refinery Sector Rule: What’s all the fuss about and what are th...
All4 Inc.
 

More from All4 Inc. (20)

Impacts of U.S. EPA Region 6 Guidance on CMS Downtime and Data Calculations
Impacts of U.S. EPA Region 6 Guidance on CMS Downtime and Data CalculationsImpacts of U.S. EPA Region 6 Guidance on CMS Downtime and Data Calculations
Impacts of U.S. EPA Region 6 Guidance on CMS Downtime and Data Calculations
 
Implementing a DAHS for Compliance with the Refinery Sector Rule
Implementing a DAHS for Compliance with the Refinery Sector RuleImplementing a DAHS for Compliance with the Refinery Sector Rule
Implementing a DAHS for Compliance with the Refinery Sector Rule
 
NSR Reform Updates
NSR Reform Updates NSR Reform Updates
NSR Reform Updates
 
Tceq recent permitting changes 4 c-2019-f_dougherty (1-31-19)
Tceq recent permitting changes 4 c-2019-f_dougherty (1-31-19)Tceq recent permitting changes 4 c-2019-f_dougherty (1-31-19)
Tceq recent permitting changes 4 c-2019-f_dougherty (1-31-19)
 
All4 impacts of recent u.s. epa region 6 guidance on cms downtime and data ...
All4   impacts of recent u.s. epa region 6 guidance on cms downtime and data ...All4   impacts of recent u.s. epa region 6 guidance on cms downtime and data ...
All4 impacts of recent u.s. epa region 6 guidance on cms downtime and data ...
 
D dix awma conference air toxics evaluation requirements 062718
D dix awma conference air toxics evaluation requirements 062718D dix awma conference air toxics evaluation requirements 062718
D dix awma conference air toxics evaluation requirements 062718
 
4 c nsr presentation 032318 all4 mccall
4 c nsr presentation 032318   all4 mccall4 c nsr presentation 032318   all4 mccall
4 c nsr presentation 032318 all4 mccall
 
All4 inc awma re-entrainment
All4 inc awma re-entrainmentAll4 inc awma re-entrainment
All4 inc awma re-entrainment
 
All4 tcc acit pres ipt guidance 2017
All4 tcc acit pres ipt guidance 2017All4 tcc acit pres ipt guidance 2017
All4 tcc acit pres ipt guidance 2017
 
Air Quality Compliance Training 12-8-16
Air Quality Compliance Training 12-8-16Air Quality Compliance Training 12-8-16
Air Quality Compliance Training 12-8-16
 
CEDRI-NextGen
CEDRI-NextGenCEDRI-NextGen
CEDRI-NextGen
 
understanding the validity and increased scrutiny of data used for compliance...
understanding the validity and increased scrutiny of data used for compliance...understanding the validity and increased scrutiny of data used for compliance...
understanding the validity and increased scrutiny of data used for compliance...
 
CUHMMC Presentation
CUHMMC PresentationCUHMMC Presentation
CUHMMC Presentation
 
Preview of ALL4 Air Quality Compliance - PIOGATech
Preview of ALL4 Air Quality Compliance - PIOGATechPreview of ALL4 Air Quality Compliance - PIOGATech
Preview of ALL4 Air Quality Compliance - PIOGATech
 
Top 5 Environmental Compliance Issues for Engineers and Managers
Top 5 Environmental Compliance Issues for Engineers and ManagersTop 5 Environmental Compliance Issues for Engineers and Managers
Top 5 Environmental Compliance Issues for Engineers and Managers
 
SO2 Data Requirements Rule Modeling Strategies
SO2 Data Requirements Rule Modeling StrategiesSO2 Data Requirements Rule Modeling Strategies
SO2 Data Requirements Rule Modeling Strategies
 
The complexities of new source review air permitting – a case study ddix 020116
The complexities of new source review air permitting – a case study ddix 020116The complexities of new source review air permitting – a case study ddix 020116
The complexities of new source review air permitting – a case study ddix 020116
 
The Good vs. Bad: The Specifics for Validating CMS Data
The Good vs. Bad: The Specifics for Validating CMS DataThe Good vs. Bad: The Specifics for Validating CMS Data
The Good vs. Bad: The Specifics for Validating CMS Data
 
Benzene Fenceline Monitoring: An Introduction and What the Regulations Don’...
Benzene Fenceline Monitoring:  An Introduction and What the Regulations Don’...Benzene Fenceline Monitoring:  An Introduction and What the Regulations Don’...
Benzene Fenceline Monitoring: An Introduction and What the Regulations Don’...
 
The Petroleum Refinery Sector Rule: What’s all the fuss about and what are th...
The Petroleum Refinery Sector Rule: What’s all the fuss about and what are th...The Petroleum Refinery Sector Rule: What’s all the fuss about and what are th...
The Petroleum Refinery Sector Rule: What’s all the fuss about and what are th...
 

Strategic Air Planning: Is the time for a PAL here?

  • 1. Strategic Air Planning: Is the time for a PAL here? John Egan All4 Inc. NCASI 2011 Northern Regional Wausau, WI May 19, 2011
  • 2. Agenda  Mounting air pressures  Mill needs and expectations  Major new source review struggles  Importance of strategic planning  Considerations for an advantage 2
  • 3. Air Pressure  NAAQS  Boiler MACT/CISWI/NHSM  Pulp & Paper MACT/Residual Risk  GHG Regulation  BART/Regional Haze  Utility MACT/NSPS  Multi-pollutant Rules  Black Carbon  More… 3
  • 4. Air Pressure  Common theme: For most facilities future emissions will decrease from historic actual levels as a result of new and developing air regulations and standards, regardless of growth in productivity. 4
  • 5. Mill Needs  Ability to change operations/equipment quickly and as needed  Long range targets for planning: • Internal - production/energy/economics • External - rule driven costs to comply  Clarity in regulatory requirements particularly for permitting 5
  • 6. New Source Review  NSR reminder: • Attainment Area = Prevention of Significant Deterioration (PSD), allowed to increase actual emissions but always a challenge • Non-attainment Area = Non-attainment New Source Review (NNSR), project has to improve area air quality 6
  • 7. PSD Implementation  Quick PSD implementation history for mill changes: • Old/old way (pre-reform) • Old/new way (post-reform) • New/new way (current & post 1-hr NAAQS) 7
  • 8. Old/Old PSD  Pre-NSR reform: • Actual-to-potential test • New limits to reduce PTE and avoid PSD • BACT main driver if PSD triggered • Air modeling a challenge for some pollutants but manageable • Implementation evolved over 25 years 8
  • 9. Old/New PSD  Post-NSR reform: • Actual-to-projected actual test • Better baseline/no new limits (supposedly) • Required to track relative to projections • Formal guidance evolved but limited • If PSD - BACT still a driver and air modeling still a challenge for some 9
  • 10. New/New PSD  Current & post 1-hr NAAQS: • Still actual-to-projected actual test • Concern w/excluded emissions • How to handle project on project • Watch out for netting • If PSD - air modeling more critical than BACT and can alter project design 10
  • 11. Future Planning  Strategic planning for facility future must consider implications of both new air rule applicability and air permitting implications: • New rules likely require facility changes • No exemption for pollution control projects • Permitting issues can impact project design 11
  • 12. Future Planning  Air issues must be integrated into facility operations planning  Result will be same old push/pull for mill projects whether needed or required: • PSD applicability analysis • Potential impacts to project design, cost, schedule • Confusion and frustration 12
  • 13. PAL Option  “Plantwide Applicability Limitation” (PAL) is an available regulatory option that can potentially ease air permitting PSD cycle  Federal PSD rule provides for PALs based on historic actual emissions  PALs are pollutant specific and could be a critical part of a Mill strategic plan 13
  • 14. PAL Advantages  For a facility with a PAL permit that maintains emissions below PAL, physical changes and changes in method of operation are not major modifications and do not require approval under PSD 14
  • 15. Why a PAL Now?  PALs historically worked for relatively simple industries with limited sources and where technology was driving emissions lower per unit of production  New air quality world we are in is forcing mills to realization that future emissions will be lower per unit of production driven by rules, standards, permitting, technology… 15
  • 16. Why a PAL Now?  Must be able to track and report emissions against PAL  Historically mills saw too many sources and not enough data to justify a PAL  Data and tools now available for demonstrating compliance due to other rule activities (e.g., ICR work) 16
  • 17. Establishing a PAL  Same baseline actual emissions used in PSD applicability assessment: • Adjust for current applicable requirements • Add PSD significance threshold • Justify PAL and provide method of compliance 17
  • 18. PAL Concerns  PAL established for 10 year period  PAL can be adjusted down to account for new applicable requirements  Getting out of a PAL can have serious ramifications  State/local air construction permits may still be required 18
  • 19. PAL Planning Approach  Develop historic mill-wide baseline emission rates and potential PAL levels  Address potential NAAQS issues  Consider new rules, mill operations plans, potential energy efficiency improvements, new technologies, low hanging fruit for emissions reductions  Weigh value of PAL for each pollutant 19
  • 20. Final Thoughts  For typical mill projects PSD is no longer a consideration under a PAL  For planning mill now has a clear bright line it can manage operations to  Project timing may result in competitive advantage  Future second guessing by agency of PSD applicability decisions and potential enforcement issues off the table 20
  • 21. Questions? jegan@all4inc.com All4 Inc. 2393 Kimberton Road P.O. Box 299 Kimberton, PA 19442 610.933.5246 x14 and x20 www.all4inc.com 21