SlideShare a Scribd company logo
Steel Compliance –
The Consulting
Engineers’
Perspective
Mark Sheldon
Technical Director
October 2015
2
The Compliance of Steelwork in Buildings
from the Design Engineer’s viewpoint
What does a consulting engineer do
What doesn’t a consulting engineer do
3 Case Studies
3
Offices: 87
Countries: 28
Employees: 7,000+
4
Mark Sheldon – Technical Director, Structural Engineer
• Melbourne Park - Project Director for Margaret Court Arena
• Project Director for Simonds Stadium (35,000 seats) – stages 1,2,3 & 4
• Cebu Seaside Arena (Concept design for 10,000 seat arena in the
Philippines)
• Melbourne Park – Technical Advisor role for National Tennis Centre
• Structural Design Leader for Perth Arena (14,000 seats)
• MCG Redevelopment (101,000 seats) Design Team Leader
• Etihad Stadium (54,000 seats) Structural Design Team Leader
• Roof Structure Design Team Leader for 10,000 seat Hisense Arena (incl
retractable roof)
• Design Team Leader for concept of 34,000 seat TEDA Soccer Stadium,
Tianjin
• Eden Park redevelopment (NZ) concepts and peer review
• Team Leader for Delhi 2010 Commonwealth Games Siri Fort and Yamuna
Sports Complexes
• MSAC Design Team Leader (Approx 300m x 80m sports indoor complex)
• Peer Reviewer for Wembley National Stadium, UK
• Designer for 44,000 seat Great Southern Stand, MCG
• Specialist input on dynamics - Kuala Lumpur Convention Centre
5
Analysis
• Spacegass
What Does a Structural Engineer do ?
6
Analysis
• Spacegass
• ETABS
What Does a Structural Engineer do ?
7
Analysis
• Spacegass
• ETABS
• Rhino/Grasshopper
What Does a Structural Engineer do ?
8
Analysis
• Spacegass
• ETABS
• Rhino/Grasshopper
• Strand 7
What Does a Structural Engineer do ?
9
Analysis
• Spacegass
• ETABS
• Rhino/G’hopper
• Strand 7
• Dynamo
• RAPT
• RAM Concept
• Robot
• GSA
• etc
What Does a Structural Engineer do ?
10
What Does a Structural Engineer do ?
Design and Detailing
• Determine stresses in members
• Select reo size or steel section
11
AS4100 states that members and connections shall be
proportioned so that:
∗		
Where:
S* is the design action effect
Ø is the capacity factor
Ru is the nominal section or member capacity
Limit state design philosophy
What Does a Structural Engineer do ?
12
Capacity factor () accounts for:
 Variations in material properties
 Section and member dimensional tolerances
 Fabrication and construction tolerances
 Structural modelling inaccuracies
 Ductility and reliability requirements
Load factors account for variability of load effects
What Does a Structural Engineer do ?
13
ProbabilityProbabilityProbability
Design load effect = Nominal (characteristic) load effect x load factor
Nominal load effect Design load effect
Load effect
Capacity
Design capacity = Nominal (characteristic) capacity x capacity factor
Design capacity Nominal (characteristic) capacity
Probability of failure (shaded area) ~ 0.001
95thPercentile
5thPercentile
What Does a Structural Engineer do ?
14
What Does a Structural Engineer do ?
15
What Does a Structural Engineer do ?
16
Analysis
• Spacegass
• ETABS
• Rhino/Grasshopper
• Strand 7
• Dynamo
• RAPT
• RAM Concept
• Robot
• GSA
• etc
• Revit
What Does a Structural Engineer do ?
17
2D documentation and detailing
What Does a Structural Engineer do ?
18
What Doesn’t a Structural Engineer do ?
Metallurgy
Chemistry
Forensics
19
Procurement of Construction Products
20
Procurement of Construction Products
21
AS4100
 ≤ 0.9
Erection
AS 4100
Welding
AS 1554
Fabrication
AS 4100
Testing
AS 1391
AS 1554
AS 3678
Material supply
AS 1163 – Hollow Sections
AS 3678 – Plate
AS 3679 – Open Sections
Australian Standards for steel design have been calibrated for Australian
manufactured steels using a suite of Australian Standards. The designer
assumes that the material being used on site meets these standards.
What Doesn’t a Structural Engineer do ?
22
What Doesn’t a Structural Engineer do ?
The fine print: -
23
What Doesn’t a Structural Engineer do ?
The fine print: -
24
What Doesn’t a Structural Engineer do ?
The fine print: -
25
What Doesn’t a Structural Engineer do ?
The fine print: -
26
What Doesn’t a Structural Engineer do ?
The fine print: -
27
What Doesn’t a Structural Engineer do ?
The fine print: -
28
What Doesn’t a Structural Engineer do ?
The fine print: -
29
What Doesn’t a Structural Engineer do ?
The fine print: -
30
Project details
 Australian steel specified
The problem
 Large hollow sections sourced from offshore
 Mill certificates provided in Chinese, but incomplete
 Chemical limit exceeded (apparently)
The outcome
 NATA certified testing performed in Australia
 Metallurgist consulted
 Chemical composition compliant (typo on sheets)
 Mechanical properties compliant
 Steelwork accepted
Project A – Large Building Structure
31
Project details
 Australian steel specified
The problem
 Non-compliant steel plate identified after site erection completed
 Plate sourced from overseas had yield strength less than specified
 Lack of traceability – could not establish which connections were affected
The outcome
 NATA certified testing performed in Australia
 Actual yield strength determined
 Weldability was deemed to be acceptable
 Risk based assessment – connections involving affected plate were not utilised 100%
 Plate accepted (slight increase risk of failure)
Project B – Large Building Structure
32
Project details
 ~$2 billion port expansion project
 20,000t marine steelwork / 10,000t structural steelwork
 Steel procured and fabricated in China
The problem
 Potential steel non-compliance
 Preliminary design completed to Australian Standards
The outcome
 Gap analysis between Australian and Chinese standards
 Compliance testing performed in Australia
 Design capacity adjustment
Project C – Port expansion
33
Pros
 Potential cost savings ~$50m:
o Local fabrication ~ $5,000-$7,000/t
o Chinese fabrication ~ $2,000/t
o Fabrication only (excludes transport)
 Potential schedule gains due to
increased production rates
Project C – Port expansion
Cons
 Procurement issues: currency
variation, greater transport and logistic
considerations and costs
 Quality concerns and subsequent
increased QA requirements
 Increased schedule risk due to
additional QA and/or rejected material
 Increased technical/ design
considerations
 Increased steel tonnage due to
member substitution after preliminary
design (~8% total)
Pros and cons of using foreign steel
34
Project C – Port expansion
Chemical composition
Mechanical properties
Dimensional tolerances
Manufacturing process
Material Supply
AS/NZS 1163  Structural steel hollow sections
AS/NZS 1594 Hot‐rolled steel flat products
AS/NZS 3678 Structural steel – hot rolled plates…
AS/NZS 3679  Structural Steel:
Part 1 – Hot‐rolled bars and sections
Part 2 ‐ Welded sections




Australian Standards
35
Following the gap analysis, supply tolerances remained non-
compliant (including angle leg thickness, depth of section).
Options considered:
 Relax tolerances to Chinese limits and reduce capacity factor; or
 Reject all steel that does not comply
Reduction in capacity factors chosen as preferred method to mitigate
procurement issues and schedule delays, and maintain similar
probability of failure.
Project C – Port expansion
Dealing with non-compliance
36
Capacities found for:
− Smallest geometry permissible by
Australian Standards
− Smallest geometry permissible by
Chinese Standards
% decrease in capacity calculated
Used as % decrease in Capacity Factor
Assessment undertaken for various
sections and lengths
Project C – Port expansion
Reduction of capacity factors
37
Project C – Port expansion
Steel section Capacity factor ()
RHS / SHS 0.85
TFC 0.88
EA / UA 0.80
CHS 0.81
All other sections 0.90
New capacity reduction factors
38
Project C – Port expansion
Probability
Design load effect
Load effect and capacity
Design capacity (Australian steel)
Probability of failure (Australian steel)
Probability of failure (Chinese steel)
Design capacity (Chinese steel)
Probability of load effect and capacity
39
What Does this all mean ?
Non-compliant steelwork can cause real problems such as:
 Material rejection and rework
 Project delays
 Redesign
 Increased risk of structural failure
 Insurance claims and litigation
Design documents state that materials must comply with Australian
Standards, and the onus is on the Supplier/Contractor to satisfy this
requirement.
The design engineer won’t spend hours checking the validity and traceability
of the certificates. Structural engineers are not metallurgists.
Third-party certification by a reputable organisation is a wise investment

More Related Content

What's hot

Tracy Brooks - Aerospace Manufacturing Engineer
Tracy Brooks - Aerospace Manufacturing EngineerTracy Brooks - Aerospace Manufacturing Engineer
Tracy Brooks - Aerospace Manufacturing Engineer
Tracy Brooks
 
Software Application for Analysis Design-Drawing with Case Studies- vadalkar
Software Application for Analysis Design-Drawing with Case Studies- vadalkarSoftware Application for Analysis Design-Drawing with Case Studies- vadalkar
Software Application for Analysis Design-Drawing with Case Studies- vadalkar
Ajit Sabnis
 
BIM Gets a Boost
BIM Gets a BoostBIM Gets a Boost
BIM Gets a Boost
Don Talend
 
Justin Perron Resume 2015.docx
Justin Perron Resume 2015.docxJustin Perron Resume 2015.docx
Justin Perron Resume 2015.docx
Justin Perron
 
Tracy Brooks - Manufacturing Engineer
Tracy Brooks - Manufacturing EngineerTracy Brooks - Manufacturing Engineer
Tracy Brooks - Manufacturing Engineer
Tracy Brooks
 
Jason.Haraway, PE
Jason.Haraway, PEJason.Haraway, PE
Jason.Haraway, PE
Jason Haraway
 
CV_AKSHAY RAJPUT
CV_AKSHAY RAJPUTCV_AKSHAY RAJPUT
CV_AKSHAY RAJPUT
Akshay Rajput
 
LF Lanza Resume 2016
LF Lanza Resume 2016LF Lanza Resume 2016
LF Lanza Resume 2016
Lou Lanza
 
RAJA K RAJA - RESUME
RAJA K RAJA - RESUMERAJA K RAJA - RESUME
RAJA K RAJA - RESUME
RAJA K
 
Garrett_Duncan
Garrett_DuncanGarrett_Duncan
Garrett_Duncan
Garrett Duncan
 
Cary Resume 2016
Cary Resume 2016Cary Resume 2016
Cary Resume 2016
Cary Nix
 
Hafiz A Waheed Portfolio
Hafiz A Waheed Portfolio Hafiz A Waheed Portfolio
Hafiz A Waheed Portfolio
Hafiz Waheed
 
GT STRUDL
GT STRUDLGT STRUDL
GT STRUDL
N.A. Tecnologia
 
OSAS-CV5
OSAS-CV5OSAS-CV5
OSAS-CV5
osas asemota
 
STEVEN J
STEVEN JSTEVEN J
STEVEN J
Steven Holder
 
Scbj 070618-cv
Scbj 070618-cvScbj 070618-cv
Tracy Brooks - Plant Maintenance Engineer
Tracy Brooks - Plant Maintenance EngineerTracy Brooks - Plant Maintenance Engineer
Tracy Brooks - Plant Maintenance Engineer
Tracy Brooks
 

What's hot (17)

Tracy Brooks - Aerospace Manufacturing Engineer
Tracy Brooks - Aerospace Manufacturing EngineerTracy Brooks - Aerospace Manufacturing Engineer
Tracy Brooks - Aerospace Manufacturing Engineer
 
Software Application for Analysis Design-Drawing with Case Studies- vadalkar
Software Application for Analysis Design-Drawing with Case Studies- vadalkarSoftware Application for Analysis Design-Drawing with Case Studies- vadalkar
Software Application for Analysis Design-Drawing with Case Studies- vadalkar
 
BIM Gets a Boost
BIM Gets a BoostBIM Gets a Boost
BIM Gets a Boost
 
Justin Perron Resume 2015.docx
Justin Perron Resume 2015.docxJustin Perron Resume 2015.docx
Justin Perron Resume 2015.docx
 
Tracy Brooks - Manufacturing Engineer
Tracy Brooks - Manufacturing EngineerTracy Brooks - Manufacturing Engineer
Tracy Brooks - Manufacturing Engineer
 
Jason.Haraway, PE
Jason.Haraway, PEJason.Haraway, PE
Jason.Haraway, PE
 
CV_AKSHAY RAJPUT
CV_AKSHAY RAJPUTCV_AKSHAY RAJPUT
CV_AKSHAY RAJPUT
 
LF Lanza Resume 2016
LF Lanza Resume 2016LF Lanza Resume 2016
LF Lanza Resume 2016
 
RAJA K RAJA - RESUME
RAJA K RAJA - RESUMERAJA K RAJA - RESUME
RAJA K RAJA - RESUME
 
Garrett_Duncan
Garrett_DuncanGarrett_Duncan
Garrett_Duncan
 
Cary Resume 2016
Cary Resume 2016Cary Resume 2016
Cary Resume 2016
 
Hafiz A Waheed Portfolio
Hafiz A Waheed Portfolio Hafiz A Waheed Portfolio
Hafiz A Waheed Portfolio
 
GT STRUDL
GT STRUDLGT STRUDL
GT STRUDL
 
OSAS-CV5
OSAS-CV5OSAS-CV5
OSAS-CV5
 
STEVEN J
STEVEN JSTEVEN J
STEVEN J
 
Scbj 070618-cv
Scbj 070618-cvScbj 070618-cv
Scbj 070618-cv
 
Tracy Brooks - Plant Maintenance Engineer
Tracy Brooks - Plant Maintenance EngineerTracy Brooks - Plant Maintenance Engineer
Tracy Brooks - Plant Maintenance Engineer
 

Similar to Steel Compliance from the Consulting Engineer's Perspective

Reliability Based Design Optimization of Primary Shield Structure Under Seism...
Reliability Based Design Optimization of Primary Shield Structure Under Seism...Reliability Based Design Optimization of Primary Shield Structure Under Seism...
Reliability Based Design Optimization of Primary Shield Structure Under Seism...
Arindam Chakraborty, Ph.D., P.E. (CA, TX)
 
Armtec - Introduction to Soil Steel Structures & End Treatments
Armtec - Introduction to Soil Steel Structures & End TreatmentsArmtec - Introduction to Soil Steel Structures & End Treatments
Armtec - Introduction to Soil Steel Structures & End Treatments
Communications Branding
 
CSA S478 Guideline on Durability in Buildings
CSA S478 Guideline on Durability in BuildingsCSA S478 Guideline on Durability in Buildings
CSA S478 Guideline on Durability in Buildings
Morrison Hershfield
 
Design of earth-retaining structures - Lecture 6
Design of earth-retaining structures - Lecture 6Design of earth-retaining structures - Lecture 6
Design of earth-retaining structures - Lecture 6
Chris Bridges
 
Lect1
Lect1Lect1
joblayoutmobequipcoord-jan-2014.ppt
joblayoutmobequipcoord-jan-2014.pptjoblayoutmobequipcoord-jan-2014.ppt
joblayoutmobequipcoord-jan-2014.ppt
yokeceg852
 
Steel structure presentation for students
Steel structure presentation for studentsSteel structure presentation for students
Steel structure presentation for students
someoneslife167
 
Dbr kashmiri gate
Dbr kashmiri gateDbr kashmiri gate
Dbr kashmiri gate
Vishal Bagla
 
Company profile
Company profileCompany profile
Company profile
Dr Kari Thangaratnam
 
Keep it Flowing! Culvert Design 20: Design, Durability & Applications
Keep it Flowing! Culvert Design 20: Design, Durability & ApplicationsKeep it Flowing! Culvert Design 20: Design, Durability & Applications
Keep it Flowing! Culvert Design 20: Design, Durability & Applications
Communications Branding
 
Lecture 1_CIE 552.pdf
Lecture 1_CIE 552.pdfLecture 1_CIE 552.pdf
Lecture 1_CIE 552.pdf
EmmanuelMwaba8
 
Engineering and Design Webinar - September
Engineering and Design Webinar - SeptemberEngineering and Design Webinar - September
Engineering and Design Webinar - September
Piping Technology & Products, Inc.
 
JSW Summer Internship Report 2017
JSW Summer Internship Report  2017JSW Summer Internship Report  2017
JSW Summer Internship Report 2017
ASHISH JAISWAL
 
Peb structures (1)
Peb structures (1)Peb structures (1)
Peb structures (1)
hlksd
 
IRJET- Composite Floors using Profiled Deck Sheet in Steel Structure
IRJET- Composite Floors using Profiled Deck Sheet in Steel StructureIRJET- Composite Floors using Profiled Deck Sheet in Steel Structure
IRJET- Composite Floors using Profiled Deck Sheet in Steel Structure
IRJET Journal
 
Design structural steel_design_and_construction
Design structural steel_design_and_constructionDesign structural steel_design_and_construction
Design structural steel_design_and_construction
Durim Bajrami
 
Harlem Park Building Design Project
Harlem Park Building Design ProjectHarlem Park Building Design Project
Harlem Park Building Design Project
Ed Guerra, P.E.
 
Taming The Wind with Engineered Tall Walls
Taming The Wind with Engineered Tall WallsTaming The Wind with Engineered Tall Walls
Taming The Wind with Engineered Tall Walls
donaldsimon
 
Lincoln arc welding article183
Lincoln arc welding article183Lincoln arc welding article183
Lincoln arc welding article183
Miklos Peller, Sr.
 
STEVEN cv
STEVEN cvSTEVEN cv
STEVEN cv
steven french
 

Similar to Steel Compliance from the Consulting Engineer's Perspective (20)

Reliability Based Design Optimization of Primary Shield Structure Under Seism...
Reliability Based Design Optimization of Primary Shield Structure Under Seism...Reliability Based Design Optimization of Primary Shield Structure Under Seism...
Reliability Based Design Optimization of Primary Shield Structure Under Seism...
 
Armtec - Introduction to Soil Steel Structures & End Treatments
Armtec - Introduction to Soil Steel Structures & End TreatmentsArmtec - Introduction to Soil Steel Structures & End Treatments
Armtec - Introduction to Soil Steel Structures & End Treatments
 
CSA S478 Guideline on Durability in Buildings
CSA S478 Guideline on Durability in BuildingsCSA S478 Guideline on Durability in Buildings
CSA S478 Guideline on Durability in Buildings
 
Design of earth-retaining structures - Lecture 6
Design of earth-retaining structures - Lecture 6Design of earth-retaining structures - Lecture 6
Design of earth-retaining structures - Lecture 6
 
Lect1
Lect1Lect1
Lect1
 
joblayoutmobequipcoord-jan-2014.ppt
joblayoutmobequipcoord-jan-2014.pptjoblayoutmobequipcoord-jan-2014.ppt
joblayoutmobequipcoord-jan-2014.ppt
 
Steel structure presentation for students
Steel structure presentation for studentsSteel structure presentation for students
Steel structure presentation for students
 
Dbr kashmiri gate
Dbr kashmiri gateDbr kashmiri gate
Dbr kashmiri gate
 
Company profile
Company profileCompany profile
Company profile
 
Keep it Flowing! Culvert Design 20: Design, Durability & Applications
Keep it Flowing! Culvert Design 20: Design, Durability & ApplicationsKeep it Flowing! Culvert Design 20: Design, Durability & Applications
Keep it Flowing! Culvert Design 20: Design, Durability & Applications
 
Lecture 1_CIE 552.pdf
Lecture 1_CIE 552.pdfLecture 1_CIE 552.pdf
Lecture 1_CIE 552.pdf
 
Engineering and Design Webinar - September
Engineering and Design Webinar - SeptemberEngineering and Design Webinar - September
Engineering and Design Webinar - September
 
JSW Summer Internship Report 2017
JSW Summer Internship Report  2017JSW Summer Internship Report  2017
JSW Summer Internship Report 2017
 
Peb structures (1)
Peb structures (1)Peb structures (1)
Peb structures (1)
 
IRJET- Composite Floors using Profiled Deck Sheet in Steel Structure
IRJET- Composite Floors using Profiled Deck Sheet in Steel StructureIRJET- Composite Floors using Profiled Deck Sheet in Steel Structure
IRJET- Composite Floors using Profiled Deck Sheet in Steel Structure
 
Design structural steel_design_and_construction
Design structural steel_design_and_constructionDesign structural steel_design_and_construction
Design structural steel_design_and_construction
 
Harlem Park Building Design Project
Harlem Park Building Design ProjectHarlem Park Building Design Project
Harlem Park Building Design Project
 
Taming The Wind with Engineered Tall Walls
Taming The Wind with Engineered Tall WallsTaming The Wind with Engineered Tall Walls
Taming The Wind with Engineered Tall Walls
 
Lincoln arc welding article183
Lincoln arc welding article183Lincoln arc welding article183
Lincoln arc welding article183
 
STEVEN cv
STEVEN cvSTEVEN cv
STEVEN cv
 

More from Mark Sheldon

Structural Dynamics in Tennis Courts
Structural Dynamics in Tennis CourtsStructural Dynamics in Tennis Courts
Structural Dynamics in Tennis Courts
Mark Sheldon
 
Presentation to Interior Designers
Presentation to Interior DesignersPresentation to Interior Designers
Presentation to Interior Designers
Mark Sheldon
 
Concrete 2015 - Dynamics at Tennis Centre- Sheldon Delaney
Concrete 2015 - Dynamics at Tennis Centre- Sheldon DelaneyConcrete 2015 - Dynamics at Tennis Centre- Sheldon Delaney
Concrete 2015 - Dynamics at Tennis Centre- Sheldon Delaney
Mark Sheldon
 
Onesteel MCourt Arena_0314
Onesteel MCourt Arena_0314Onesteel MCourt Arena_0314
Onesteel MCourt Arena_0314
Mark Sheldon
 
Civil Engineers Aust - Margaret Court Arena April 2014
Civil Engineers Aust - Margaret Court Arena April 2014Civil Engineers Aust - Margaret Court Arena April 2014
Civil Engineers Aust - Margaret Court Arena April 2014Mark Sheldon
 
TEDA ACSE magazine Sept 05
TEDA ACSE magazine Sept 05TEDA ACSE magazine Sept 05
TEDA ACSE magazine Sept 05Mark Sheldon
 
MCG Concrete 2005 050725
MCG Concrete 2005 050725MCG Concrete 2005 050725
MCG Concrete 2005 050725
Mark Sheldon
 
IABSE 2002
IABSE 2002IABSE 2002
IABSE 2002
Mark Sheldon
 

More from Mark Sheldon (11)

Structural Dynamics in Tennis Courts
Structural Dynamics in Tennis CourtsStructural Dynamics in Tennis Courts
Structural Dynamics in Tennis Courts
 
Presentation to Interior Designers
Presentation to Interior DesignersPresentation to Interior Designers
Presentation to Interior Designers
 
Concrete 2015 - Dynamics at Tennis Centre- Sheldon Delaney
Concrete 2015 - Dynamics at Tennis Centre- Sheldon DelaneyConcrete 2015 - Dynamics at Tennis Centre- Sheldon Delaney
Concrete 2015 - Dynamics at Tennis Centre- Sheldon Delaney
 
Onesteel MCourt Arena_0314
Onesteel MCourt Arena_0314Onesteel MCourt Arena_0314
Onesteel MCourt Arena_0314
 
Civil Engineers Aust - Margaret Court Arena April 2014
Civil Engineers Aust - Margaret Court Arena April 2014Civil Engineers Aust - Margaret Court Arena April 2014
Civil Engineers Aust - Margaret Court Arena April 2014
 
TEDA ACSE magazine Sept 05
TEDA ACSE magazine Sept 05TEDA ACSE magazine Sept 05
TEDA ACSE magazine Sept 05
 
SEI 2002
SEI 2002SEI 2002
SEI 2002
 
MCG Concrete 2005 050725
MCG Concrete 2005 050725MCG Concrete 2005 050725
MCG Concrete 2005 050725
 
IABSE 2002
IABSE 2002IABSE 2002
IABSE 2002
 
CEI 2000
CEI 2000CEI 2000
CEI 2000
 
AISC 1999
AISC 1999AISC 1999
AISC 1999
 

Recently uploaded

Recycled Concrete Aggregate in Construction Part II
Recycled Concrete Aggregate in Construction Part IIRecycled Concrete Aggregate in Construction Part II
Recycled Concrete Aggregate in Construction Part II
Aditya Rajan Patra
 
Recycled Concrete Aggregate in Construction Part III
Recycled Concrete Aggregate in Construction Part IIIRecycled Concrete Aggregate in Construction Part III
Recycled Concrete Aggregate in Construction Part III
Aditya Rajan Patra
 
官方认证美国密歇根州立大学毕业证学位证书原版一模一样
官方认证美国密歇根州立大学毕业证学位证书原版一模一样官方认证美国密歇根州立大学毕业证学位证书原版一模一样
官方认证美国密歇根州立大学毕业证学位证书原版一模一样
171ticu
 
Heat Resistant Concrete Presentation ppt
Heat Resistant Concrete Presentation pptHeat Resistant Concrete Presentation ppt
Heat Resistant Concrete Presentation ppt
mamunhossenbd75
 
ISPM 15 Heat Treated Wood Stamps and why your shipping must have one
ISPM 15 Heat Treated Wood Stamps and why your shipping must have oneISPM 15 Heat Treated Wood Stamps and why your shipping must have one
ISPM 15 Heat Treated Wood Stamps and why your shipping must have one
Las Vegas Warehouse
 
DEEP LEARNING FOR SMART GRID INTRUSION DETECTION: A HYBRID CNN-LSTM-BASED MODEL
DEEP LEARNING FOR SMART GRID INTRUSION DETECTION: A HYBRID CNN-LSTM-BASED MODELDEEP LEARNING FOR SMART GRID INTRUSION DETECTION: A HYBRID CNN-LSTM-BASED MODEL
DEEP LEARNING FOR SMART GRID INTRUSION DETECTION: A HYBRID CNN-LSTM-BASED MODEL
gerogepatton
 
学校原版美国波士顿大学毕业证学历学位证书原版一模一样
学校原版美国波士顿大学毕业证学历学位证书原版一模一样学校原版美国波士顿大学毕业证学历学位证书原版一模一样
学校原版美国波士顿大学毕业证学历学位证书原版一模一样
171ticu
 
Eric Nizeyimana's document 2006 from gicumbi to ttc nyamata handball play
Eric Nizeyimana's document 2006 from gicumbi to ttc nyamata handball playEric Nizeyimana's document 2006 from gicumbi to ttc nyamata handball play
Eric Nizeyimana's document 2006 from gicumbi to ttc nyamata handball play
enizeyimana36
 
5214-1693458878915-Unit 6 2023 to 2024 academic year assignment (AutoRecovere...
5214-1693458878915-Unit 6 2023 to 2024 academic year assignment (AutoRecovere...5214-1693458878915-Unit 6 2023 to 2024 academic year assignment (AutoRecovere...
5214-1693458878915-Unit 6 2023 to 2024 academic year assignment (AutoRecovere...
ihlasbinance2003
 
ML Based Model for NIDS MSc Updated Presentation.v2.pptx
ML Based Model for NIDS MSc Updated Presentation.v2.pptxML Based Model for NIDS MSc Updated Presentation.v2.pptx
ML Based Model for NIDS MSc Updated Presentation.v2.pptx
JamalHussainArman
 
Textile Chemical Processing and Dyeing.pdf
Textile Chemical Processing and Dyeing.pdfTextile Chemical Processing and Dyeing.pdf
Textile Chemical Processing and Dyeing.pdf
NazakatAliKhoso2
 
Presentation of IEEE Slovenia CIS (Computational Intelligence Society) Chapte...
Presentation of IEEE Slovenia CIS (Computational Intelligence Society) Chapte...Presentation of IEEE Slovenia CIS (Computational Intelligence Society) Chapte...
Presentation of IEEE Slovenia CIS (Computational Intelligence Society) Chapte...
University of Maribor
 
Properties Railway Sleepers and Test.pptx
Properties Railway Sleepers and Test.pptxProperties Railway Sleepers and Test.pptx
Properties Railway Sleepers and Test.pptx
MDSABBIROJJAMANPAYEL
 
BPV-GUI-01-Guide-for-ASME-Review-Teams-(General)-10-10-2023.pdf
BPV-GUI-01-Guide-for-ASME-Review-Teams-(General)-10-10-2023.pdfBPV-GUI-01-Guide-for-ASME-Review-Teams-(General)-10-10-2023.pdf
BPV-GUI-01-Guide-for-ASME-Review-Teams-(General)-10-10-2023.pdf
MIGUELANGEL966976
 
TIME DIVISION MULTIPLEXING TECHNIQUE FOR COMMUNICATION SYSTEM
TIME DIVISION MULTIPLEXING TECHNIQUE FOR COMMUNICATION SYSTEMTIME DIVISION MULTIPLEXING TECHNIQUE FOR COMMUNICATION SYSTEM
TIME DIVISION MULTIPLEXING TECHNIQUE FOR COMMUNICATION SYSTEM
HODECEDSIET
 
132/33KV substation case study Presentation
132/33KV substation case study Presentation132/33KV substation case study Presentation
132/33KV substation case study Presentation
kandramariana6
 
Literature Review Basics and Understanding Reference Management.pptx
Literature Review Basics and Understanding Reference Management.pptxLiterature Review Basics and Understanding Reference Management.pptx
Literature Review Basics and Understanding Reference Management.pptx
Dr Ramhari Poudyal
 
哪里办理(csu毕业证书)查尔斯特大学毕业证硕士学历原版一模一样
哪里办理(csu毕业证书)查尔斯特大学毕业证硕士学历原版一模一样哪里办理(csu毕业证书)查尔斯特大学毕业证硕士学历原版一模一样
哪里办理(csu毕业证书)查尔斯特大学毕业证硕士学历原版一模一样
insn4465
 
Computational Engineering IITH Presentation
Computational Engineering IITH PresentationComputational Engineering IITH Presentation
Computational Engineering IITH Presentation
co23btech11018
 
Question paper of renewable energy sources
Question paper of renewable energy sourcesQuestion paper of renewable energy sources
Question paper of renewable energy sources
mahammadsalmanmech
 

Recently uploaded (20)

Recycled Concrete Aggregate in Construction Part II
Recycled Concrete Aggregate in Construction Part IIRecycled Concrete Aggregate in Construction Part II
Recycled Concrete Aggregate in Construction Part II
 
Recycled Concrete Aggregate in Construction Part III
Recycled Concrete Aggregate in Construction Part IIIRecycled Concrete Aggregate in Construction Part III
Recycled Concrete Aggregate in Construction Part III
 
官方认证美国密歇根州立大学毕业证学位证书原版一模一样
官方认证美国密歇根州立大学毕业证学位证书原版一模一样官方认证美国密歇根州立大学毕业证学位证书原版一模一样
官方认证美国密歇根州立大学毕业证学位证书原版一模一样
 
Heat Resistant Concrete Presentation ppt
Heat Resistant Concrete Presentation pptHeat Resistant Concrete Presentation ppt
Heat Resistant Concrete Presentation ppt
 
ISPM 15 Heat Treated Wood Stamps and why your shipping must have one
ISPM 15 Heat Treated Wood Stamps and why your shipping must have oneISPM 15 Heat Treated Wood Stamps and why your shipping must have one
ISPM 15 Heat Treated Wood Stamps and why your shipping must have one
 
DEEP LEARNING FOR SMART GRID INTRUSION DETECTION: A HYBRID CNN-LSTM-BASED MODEL
DEEP LEARNING FOR SMART GRID INTRUSION DETECTION: A HYBRID CNN-LSTM-BASED MODELDEEP LEARNING FOR SMART GRID INTRUSION DETECTION: A HYBRID CNN-LSTM-BASED MODEL
DEEP LEARNING FOR SMART GRID INTRUSION DETECTION: A HYBRID CNN-LSTM-BASED MODEL
 
学校原版美国波士顿大学毕业证学历学位证书原版一模一样
学校原版美国波士顿大学毕业证学历学位证书原版一模一样学校原版美国波士顿大学毕业证学历学位证书原版一模一样
学校原版美国波士顿大学毕业证学历学位证书原版一模一样
 
Eric Nizeyimana's document 2006 from gicumbi to ttc nyamata handball play
Eric Nizeyimana's document 2006 from gicumbi to ttc nyamata handball playEric Nizeyimana's document 2006 from gicumbi to ttc nyamata handball play
Eric Nizeyimana's document 2006 from gicumbi to ttc nyamata handball play
 
5214-1693458878915-Unit 6 2023 to 2024 academic year assignment (AutoRecovere...
5214-1693458878915-Unit 6 2023 to 2024 academic year assignment (AutoRecovere...5214-1693458878915-Unit 6 2023 to 2024 academic year assignment (AutoRecovere...
5214-1693458878915-Unit 6 2023 to 2024 academic year assignment (AutoRecovere...
 
ML Based Model for NIDS MSc Updated Presentation.v2.pptx
ML Based Model for NIDS MSc Updated Presentation.v2.pptxML Based Model for NIDS MSc Updated Presentation.v2.pptx
ML Based Model for NIDS MSc Updated Presentation.v2.pptx
 
Textile Chemical Processing and Dyeing.pdf
Textile Chemical Processing and Dyeing.pdfTextile Chemical Processing and Dyeing.pdf
Textile Chemical Processing and Dyeing.pdf
 
Presentation of IEEE Slovenia CIS (Computational Intelligence Society) Chapte...
Presentation of IEEE Slovenia CIS (Computational Intelligence Society) Chapte...Presentation of IEEE Slovenia CIS (Computational Intelligence Society) Chapte...
Presentation of IEEE Slovenia CIS (Computational Intelligence Society) Chapte...
 
Properties Railway Sleepers and Test.pptx
Properties Railway Sleepers and Test.pptxProperties Railway Sleepers and Test.pptx
Properties Railway Sleepers and Test.pptx
 
BPV-GUI-01-Guide-for-ASME-Review-Teams-(General)-10-10-2023.pdf
BPV-GUI-01-Guide-for-ASME-Review-Teams-(General)-10-10-2023.pdfBPV-GUI-01-Guide-for-ASME-Review-Teams-(General)-10-10-2023.pdf
BPV-GUI-01-Guide-for-ASME-Review-Teams-(General)-10-10-2023.pdf
 
TIME DIVISION MULTIPLEXING TECHNIQUE FOR COMMUNICATION SYSTEM
TIME DIVISION MULTIPLEXING TECHNIQUE FOR COMMUNICATION SYSTEMTIME DIVISION MULTIPLEXING TECHNIQUE FOR COMMUNICATION SYSTEM
TIME DIVISION MULTIPLEXING TECHNIQUE FOR COMMUNICATION SYSTEM
 
132/33KV substation case study Presentation
132/33KV substation case study Presentation132/33KV substation case study Presentation
132/33KV substation case study Presentation
 
Literature Review Basics and Understanding Reference Management.pptx
Literature Review Basics and Understanding Reference Management.pptxLiterature Review Basics and Understanding Reference Management.pptx
Literature Review Basics and Understanding Reference Management.pptx
 
哪里办理(csu毕业证书)查尔斯特大学毕业证硕士学历原版一模一样
哪里办理(csu毕业证书)查尔斯特大学毕业证硕士学历原版一模一样哪里办理(csu毕业证书)查尔斯特大学毕业证硕士学历原版一模一样
哪里办理(csu毕业证书)查尔斯特大学毕业证硕士学历原版一模一样
 
Computational Engineering IITH Presentation
Computational Engineering IITH PresentationComputational Engineering IITH Presentation
Computational Engineering IITH Presentation
 
Question paper of renewable energy sources
Question paper of renewable energy sourcesQuestion paper of renewable energy sources
Question paper of renewable energy sources
 

Steel Compliance from the Consulting Engineer's Perspective

  • 1. Steel Compliance – The Consulting Engineers’ Perspective Mark Sheldon Technical Director October 2015
  • 2. 2 The Compliance of Steelwork in Buildings from the Design Engineer’s viewpoint What does a consulting engineer do What doesn’t a consulting engineer do 3 Case Studies
  • 4. 4 Mark Sheldon – Technical Director, Structural Engineer • Melbourne Park - Project Director for Margaret Court Arena • Project Director for Simonds Stadium (35,000 seats) – stages 1,2,3 & 4 • Cebu Seaside Arena (Concept design for 10,000 seat arena in the Philippines) • Melbourne Park – Technical Advisor role for National Tennis Centre • Structural Design Leader for Perth Arena (14,000 seats) • MCG Redevelopment (101,000 seats) Design Team Leader • Etihad Stadium (54,000 seats) Structural Design Team Leader • Roof Structure Design Team Leader for 10,000 seat Hisense Arena (incl retractable roof) • Design Team Leader for concept of 34,000 seat TEDA Soccer Stadium, Tianjin • Eden Park redevelopment (NZ) concepts and peer review • Team Leader for Delhi 2010 Commonwealth Games Siri Fort and Yamuna Sports Complexes • MSAC Design Team Leader (Approx 300m x 80m sports indoor complex) • Peer Reviewer for Wembley National Stadium, UK • Designer for 44,000 seat Great Southern Stand, MCG • Specialist input on dynamics - Kuala Lumpur Convention Centre
  • 5. 5 Analysis • Spacegass What Does a Structural Engineer do ?
  • 6. 6 Analysis • Spacegass • ETABS What Does a Structural Engineer do ?
  • 7. 7 Analysis • Spacegass • ETABS • Rhino/Grasshopper What Does a Structural Engineer do ?
  • 8. 8 Analysis • Spacegass • ETABS • Rhino/Grasshopper • Strand 7 What Does a Structural Engineer do ?
  • 9. 9 Analysis • Spacegass • ETABS • Rhino/G’hopper • Strand 7 • Dynamo • RAPT • RAM Concept • Robot • GSA • etc What Does a Structural Engineer do ?
  • 10. 10 What Does a Structural Engineer do ? Design and Detailing • Determine stresses in members • Select reo size or steel section
  • 11. 11 AS4100 states that members and connections shall be proportioned so that: ∗ Where: S* is the design action effect Ø is the capacity factor Ru is the nominal section or member capacity Limit state design philosophy What Does a Structural Engineer do ?
  • 12. 12 Capacity factor () accounts for:  Variations in material properties  Section and member dimensional tolerances  Fabrication and construction tolerances  Structural modelling inaccuracies  Ductility and reliability requirements Load factors account for variability of load effects What Does a Structural Engineer do ?
  • 13. 13 ProbabilityProbabilityProbability Design load effect = Nominal (characteristic) load effect x load factor Nominal load effect Design load effect Load effect Capacity Design capacity = Nominal (characteristic) capacity x capacity factor Design capacity Nominal (characteristic) capacity Probability of failure (shaded area) ~ 0.001 95thPercentile 5thPercentile What Does a Structural Engineer do ?
  • 14. 14 What Does a Structural Engineer do ?
  • 15. 15 What Does a Structural Engineer do ?
  • 16. 16 Analysis • Spacegass • ETABS • Rhino/Grasshopper • Strand 7 • Dynamo • RAPT • RAM Concept • Robot • GSA • etc • Revit What Does a Structural Engineer do ?
  • 17. 17 2D documentation and detailing What Does a Structural Engineer do ?
  • 18. 18 What Doesn’t a Structural Engineer do ? Metallurgy Chemistry Forensics
  • 21. 21 AS4100  ≤ 0.9 Erection AS 4100 Welding AS 1554 Fabrication AS 4100 Testing AS 1391 AS 1554 AS 3678 Material supply AS 1163 – Hollow Sections AS 3678 – Plate AS 3679 – Open Sections Australian Standards for steel design have been calibrated for Australian manufactured steels using a suite of Australian Standards. The designer assumes that the material being used on site meets these standards. What Doesn’t a Structural Engineer do ?
  • 22. 22 What Doesn’t a Structural Engineer do ? The fine print: -
  • 23. 23 What Doesn’t a Structural Engineer do ? The fine print: -
  • 24. 24 What Doesn’t a Structural Engineer do ? The fine print: -
  • 25. 25 What Doesn’t a Structural Engineer do ? The fine print: -
  • 26. 26 What Doesn’t a Structural Engineer do ? The fine print: -
  • 27. 27 What Doesn’t a Structural Engineer do ? The fine print: -
  • 28. 28 What Doesn’t a Structural Engineer do ? The fine print: -
  • 29. 29 What Doesn’t a Structural Engineer do ? The fine print: -
  • 30. 30 Project details  Australian steel specified The problem  Large hollow sections sourced from offshore  Mill certificates provided in Chinese, but incomplete  Chemical limit exceeded (apparently) The outcome  NATA certified testing performed in Australia  Metallurgist consulted  Chemical composition compliant (typo on sheets)  Mechanical properties compliant  Steelwork accepted Project A – Large Building Structure
  • 31. 31 Project details  Australian steel specified The problem  Non-compliant steel plate identified after site erection completed  Plate sourced from overseas had yield strength less than specified  Lack of traceability – could not establish which connections were affected The outcome  NATA certified testing performed in Australia  Actual yield strength determined  Weldability was deemed to be acceptable  Risk based assessment – connections involving affected plate were not utilised 100%  Plate accepted (slight increase risk of failure) Project B – Large Building Structure
  • 32. 32 Project details  ~$2 billion port expansion project  20,000t marine steelwork / 10,000t structural steelwork  Steel procured and fabricated in China The problem  Potential steel non-compliance  Preliminary design completed to Australian Standards The outcome  Gap analysis between Australian and Chinese standards  Compliance testing performed in Australia  Design capacity adjustment Project C – Port expansion
  • 33. 33 Pros  Potential cost savings ~$50m: o Local fabrication ~ $5,000-$7,000/t o Chinese fabrication ~ $2,000/t o Fabrication only (excludes transport)  Potential schedule gains due to increased production rates Project C – Port expansion Cons  Procurement issues: currency variation, greater transport and logistic considerations and costs  Quality concerns and subsequent increased QA requirements  Increased schedule risk due to additional QA and/or rejected material  Increased technical/ design considerations  Increased steel tonnage due to member substitution after preliminary design (~8% total) Pros and cons of using foreign steel
  • 34. 34 Project C – Port expansion Chemical composition Mechanical properties Dimensional tolerances Manufacturing process Material Supply AS/NZS 1163  Structural steel hollow sections AS/NZS 1594 Hot‐rolled steel flat products AS/NZS 3678 Structural steel – hot rolled plates… AS/NZS 3679  Structural Steel: Part 1 – Hot‐rolled bars and sections Part 2 ‐ Welded sections     Australian Standards
  • 35. 35 Following the gap analysis, supply tolerances remained non- compliant (including angle leg thickness, depth of section). Options considered:  Relax tolerances to Chinese limits and reduce capacity factor; or  Reject all steel that does not comply Reduction in capacity factors chosen as preferred method to mitigate procurement issues and schedule delays, and maintain similar probability of failure. Project C – Port expansion Dealing with non-compliance
  • 36. 36 Capacities found for: − Smallest geometry permissible by Australian Standards − Smallest geometry permissible by Chinese Standards % decrease in capacity calculated Used as % decrease in Capacity Factor Assessment undertaken for various sections and lengths Project C – Port expansion Reduction of capacity factors
  • 37. 37 Project C – Port expansion Steel section Capacity factor () RHS / SHS 0.85 TFC 0.88 EA / UA 0.80 CHS 0.81 All other sections 0.90 New capacity reduction factors
  • 38. 38 Project C – Port expansion Probability Design load effect Load effect and capacity Design capacity (Australian steel) Probability of failure (Australian steel) Probability of failure (Chinese steel) Design capacity (Chinese steel) Probability of load effect and capacity
  • 39. 39 What Does this all mean ? Non-compliant steelwork can cause real problems such as:  Material rejection and rework  Project delays  Redesign  Increased risk of structural failure  Insurance claims and litigation Design documents state that materials must comply with Australian Standards, and the onus is on the Supplier/Contractor to satisfy this requirement. The design engineer won’t spend hours checking the validity and traceability of the certificates. Structural engineers are not metallurgists. Third-party certification by a reputable organisation is a wise investment