SlideShare a Scribd company logo
1 
SOLVAY BRUSSELS SCHOOL OF ECONOMICS & MANAGEMENT 
ADVANCED ACCOUNTING COURSE - ACADEMIC YEAR 2013-2014 
CASE STUDY n°1 – A - REVENUE RECOGNITION 
IAS 11 – Construction Contracts – Company ABC 
As at January 1st, 2007, Company ABC obtained a fixed price contract for 90.606 to build 2 boilers. The initial amount of revenue agreed in the contract is 90.606. 
Company ABC’s initial estimate of total costs amounts to 70.532, which can be summarized as follows: 
- Material and subcontracting: 58.767; 
- Labour: 4.533; 
- External success agent fees: 2.809; 
- Internal commercial costs: 130; 
- Standard contingencies: 2.481; 
- Warranty costs (as per Company ABC’s rule): 1.812. 
It will take 3 years to build the 2 boilers. 
By the end of year 1, Company ABC's estimate of costs has changed as follows: 
- Material and subcontracting increased by 300; 
- Labour increased by 93. 
Costs incurred at the end of year 1 can be summarized as follows: 
- Material and subcontracting: 5.928; 
- Labour: 979; 
- External success agent fees: 1.404; 
- Internal commercial costs: 130. 
By the end of year 1, part of the initial provision for standard contingencies (1,981) is considered as not meeting IAS 37 conditions. The remaining balance (500) does actually correspond to a tax risk and does actually meet the IAS 37 recognition criteria. At the end of year 1, boilers are still in a fabrication process. 
In year 2, the customer approves a variation resulting in an increase in contract revenue of 200, which corresponds to estimated additional contract costs for Company ABC of 150. The warranty provision is not updated to the extent that this contract revenue’s variation is not significant. At the end of year 2, costs invoiced include 100 for standard materials stored at the site to be used in year 3 to complete the project. 
In year 3, an amount of 250 has finally to be paid to the tax administration. 
Company ABC determines the stage of completion of the contract by calculating the proportion that contract costs incurred for work performed to date bear to the latest estimated total contract costs.
2 
Below the detail of contract costs incurred during years 2008 and 2009 (excl tax risk) : 
2008 
2009 
Material and subcontracting 
30,143 
23,096 
Labour 
2,988 
709 
External success agent fees 
1,405 
0 
Total 
34,536 
23,805 
2007 
2008 
2009 
2010 
Progress billings in each year 
8.500 
45.500 
28.900 
7.906 
Required: 
Please calculate: 
- Total contract costs and estimated gross margin of the contract at the end of each year; 
- The stage of completion of the contract at the end of each year and the amounts of revenue, expenses and profits to be recognised in financial statements; 
Please show the relevant amounts to be disclosed in financial statements of the contractor for years 2007, 2008 and 2009. 
The template for the solution is presented below. 
2007 
2008 
2009 
Initial amount of revenue agreed in contract 
Variation 
Total contract revenue 
Contract costs incurred to date 
Contract costs to complete 
Total estimated contract costs (excl. provisions) 
Provision for tax risk 
Warranty provision 
Total estimated contract costs (incl. provisions) 
Estimated profit 
Stage of completion
3 
Budget at beginning of year 2007: 
Budgeted contract revenue: 
Budgeted contract costs: 
Budgeted gross margin: 
Forecast at the end of year 2007: 
Budgeted contract revenue: 
Budgeted contract costs: 
Budgeted gross margin: 
Forecast at the end of year 2008: 
Budgeted contract revenue: 
Budgeted contract costs: 
Budgeted gross margin: 
Forecast at the end of year 2009: 
Budgeted contract revenue: 
Budgeted contract costs: 
Budgeted gross margin: 
Year 2007: 
Costs incurred: 
Cos ts Invoiced 
Down 
payments 
current year 
Down 
payments 
previous year 
Invoices to 
receive 
Invoices related 
to previous year Incurred 
Material and subcontracting 
Labour 
External agent fees 
Warranty cos ts 
Total : 
Total estimated costs to determine the POC (Percentage Of Completion) : 
POC : 
Gross margin to be recognised:
4 
Year 2008: 
Costs incurred during the year: 
Cos ts Invoiced 
Down 
payments 
current year 
Down 
payments 
previous year 
Invoices to 
receive 
Invoices related 
to prev years Incurred 
Material and subcontracting 
Labour 
External agent fees 
Warranty cos ts 
Total : 
Total estimated costs to determine the POC : 
Cumulative POC : 
Cumulative gross margin to be recognised: 
Gross margin of the year: 
Year 2009: 
Costs incurred during the year: 
Cos ts Invoiced 
Down 
payments 
current year 
Down 
payments 
previous year 
Invoices to 
receive 
Invoices related 
to prev years Incurred 
Material and subcontracting 
Labour 
External agent fees 
Tax ri sk 
Warranty cos ts 
Total : 
Total estimated costs to determine the POC : 
Cumulative POC : 
Cumulative gross margin to be recognised: 
Gross margin of the year :
5 
The amounts of revenue, expenses and profit recognised in the income statement in the three years are as follows: 
To Date 
Recognised in prior years 
Recognised in current year 
Year 1 
Revenue 
Contract costs 
Warranty provision 
Cost of sales 
Selling expenses 
Profit 
Year 2 
Revenue 
Contract costs 
Warranty provision 
Cost of sales 
Selling expenses 
Profit 
Year 3 
Revenue 
Contract costs 
Warranty provision 
Cost of sales 
Selling expenses 
Profit

More Related Content

What's hot

3bhk wef new
3bhk wef new3bhk wef new
3bhk wef new
HomePoint
 
Acc week 5 a
Acc week 5 aAcc week 5 a
Acc week 5 a
Shu Shin
 
Bba ii cost and management accounting u 3.3 contract costing
Bba ii cost and management accounting u 3.3 contract costingBba ii cost and management accounting u 3.3 contract costing
Bba ii cost and management accounting u 3.3 contract costing
Rai University
 
Sums on profits and gains from business or profession
Sums on profits and gains from business or professionSums on profits and gains from business or profession
Sums on profits and gains from business or profession
sumit235
 
Recent+changes+by+ca+nimesh+dedhia
Recent+changes+by+ca+nimesh+dedhiaRecent+changes+by+ca+nimesh+dedhia
Recent+changes+by+ca+nimesh+dedhia
PSPCL
 

What's hot (20)

Conditions of CPWD contract in INDIA
Conditions of CPWD contract in INDIAConditions of CPWD contract in INDIA
Conditions of CPWD contract in INDIA
 
3bhk wef new
3bhk wef new3bhk wef new
3bhk wef new
 
Acc week 5 a
Acc week 5 aAcc week 5 a
Acc week 5 a
 
metering-march-2015
metering-march-2015metering-march-2015
metering-march-2015
 
Contract costing, BCOM (HONS)
Contract costing, BCOM (HONS)Contract costing, BCOM (HONS)
Contract costing, BCOM (HONS)
 
Price list 2999 tower p1 block b
Price list 2999 tower p1 block bPrice list 2999 tower p1 block b
Price list 2999 tower p1 block b
 
Contract costing
Contract costingContract costing
Contract costing
 
Bba 504 & taxation management
Bba 504 & taxation managementBba 504 & taxation management
Bba 504 & taxation management
 
Bba 504 & taxation management
Bba 504 & taxation managementBba 504 & taxation management
Bba 504 & taxation management
 
Accounting 970641 paper 4 problem solving (supplementary topics) october nove...
Accounting 970641 paper 4 problem solving (supplementary topics) october nove...Accounting 970641 paper 4 problem solving (supplementary topics) october nove...
Accounting 970641 paper 4 problem solving (supplementary topics) october nove...
 
Bba ii cost and management accounting u 3.3 contract costing
Bba ii cost and management accounting u 3.3 contract costingBba ii cost and management accounting u 3.3 contract costing
Bba ii cost and management accounting u 3.3 contract costing
 
City of Salina Brochure-Tax Rebate Neighborhood Revitalization Plan
City of Salina Brochure-Tax Rebate Neighborhood Revitalization PlanCity of Salina Brochure-Tax Rebate Neighborhood Revitalization Plan
City of Salina Brochure-Tax Rebate Neighborhood Revitalization Plan
 
Ifc contract 0002
Ifc contract 0002Ifc contract 0002
Ifc contract 0002
 
Sums on profits and gains from business or profession
Sums on profits and gains from business or professionSums on profits and gains from business or profession
Sums on profits and gains from business or profession
 
Recent+changes+by+ca+nimesh+dedhia
Recent+changes+by+ca+nimesh+dedhiaRecent+changes+by+ca+nimesh+dedhia
Recent+changes+by+ca+nimesh+dedhia
 
Measures of national income
Measures of national incomeMeasures of national income
Measures of national income
 
Assignment 4
Assignment 4Assignment 4
Assignment 4
 
Financial plan template
Financial plan templateFinancial plan template
Financial plan template
 
Contract Costing
Contract CostingContract Costing
Contract Costing
 
Corporate hights 5599 tower 4 (1)
Corporate hights 5599 tower 4 (1)Corporate hights 5599 tower 4 (1)
Corporate hights 5599 tower 4 (1)
 

Viewers also liked (6)

Context is King! Communicate & Collaborate When and Where it Matters
Context is King! Communicate & Collaborate When and Where it MattersContext is King! Communicate & Collaborate When and Where it Matters
Context is King! Communicate & Collaborate When and Where it Matters
 
Ann ackaert - handle with ecare: 5 years of ict research in the homecare envi...
Ann ackaert - handle with ecare: 5 years of ict research in the homecare envi...Ann ackaert - handle with ecare: 5 years of ict research in the homecare envi...
Ann ackaert - handle with ecare: 5 years of ict research in the homecare envi...
 
Botanoo norwegian
Botanoo   norwegianBotanoo   norwegian
Botanoo norwegian
 
How to Succeed in Mrs. Benjamin's English Class Without Really Trying
How to Succeed in Mrs. Benjamin's English Class Without Really TryingHow to Succeed in Mrs. Benjamin's English Class Without Really Trying
How to Succeed in Mrs. Benjamin's English Class Without Really Trying
 
Understanding hdfs
Understanding hdfsUnderstanding hdfs
Understanding hdfs
 
Lipe e Mariana
Lipe e MarianaLipe e Mariana
Lipe e Mariana
 

Similar to Solvay adv acc.case 1 a. l.t. contract.company abc

Construction Training Program LFUCG, Bluegrass Airport January 25 2011
Construction Training Program LFUCG, Bluegrass Airport January 25 2011Construction Training Program LFUCG, Bluegrass Airport January 25 2011
Construction Training Program LFUCG, Bluegrass Airport January 25 2011
Irma_Miller_11344
 
Bearing Point REV RECOGNITION Project
Bearing Point REV RECOGNITION ProjectBearing Point REV RECOGNITION Project
Bearing Point REV RECOGNITION Project
Jim Gremillion Jr
 
Module 5 - Long-term Construction Contracts
Module 5 - Long-term Construction ContractsModule 5 - Long-term Construction Contracts
Module 5 - Long-term Construction Contracts
Mikee Bylss
 

Similar to Solvay adv acc.case 1 a. l.t. contract.company abc (20)

Deutsche EuroShop | Quarterly Statement 9M 2022
Deutsche EuroShop | Quarterly Statement 9M 2022Deutsche EuroShop | Quarterly Statement 9M 2022
Deutsche EuroShop | Quarterly Statement 9M 2022
 
Construction contract
Construction contractConstruction contract
Construction contract
 
Construction - Accounting and Tax Aspects
Construction - Accounting and Tax AspectsConstruction - Accounting and Tax Aspects
Construction - Accounting and Tax Aspects
 
Contract costing
Contract costingContract costing
Contract costing
 
Contract costing
Contract costingContract costing
Contract costing
 
AS-7 Construction Contracts and AS-18 Related Party Transactions
AS-7 Construction Contracts and AS-18 Related Party TransactionsAS-7 Construction Contracts and AS-18 Related Party Transactions
AS-7 Construction Contracts and AS-18 Related Party Transactions
 
Job and batch costing
Job and batch costingJob and batch costing
Job and batch costing
 
Accounting standard 7
Accounting standard 7Accounting standard 7
Accounting standard 7
 
nes.pptx
nes.pptxnes.pptx
nes.pptx
 
Contract Costing.pptx
Contract Costing.pptxContract Costing.pptx
Contract Costing.pptx
 
Commercial aspects of civil construction
Commercial aspects of civil constructionCommercial aspects of civil construction
Commercial aspects of civil construction
 
Contract account
Contract accountContract account
Contract account
 
Chap 8.2 income taxes
Chap 8.2 income taxesChap 8.2 income taxes
Chap 8.2 income taxes
 
Construction Training Program LFUCG, Bluegrass Airport January 25 2011
Construction Training Program LFUCG, Bluegrass Airport January 25 2011Construction Training Program LFUCG, Bluegrass Airport January 25 2011
Construction Training Program LFUCG, Bluegrass Airport January 25 2011
 
Master Budget of Pak Fan Gujrat.
Master Budget of Pak Fan Gujrat.Master Budget of Pak Fan Gujrat.
Master Budget of Pak Fan Gujrat.
 
Contract costing
Contract costingContract costing
Contract costing
 
Cfr ias 11 construction contract presentation by MOHSIN MUMTAZ
Cfr  ias 11 construction contract presentation by MOHSIN MUMTAZCfr  ias 11 construction contract presentation by MOHSIN MUMTAZ
Cfr ias 11 construction contract presentation by MOHSIN MUMTAZ
 
Bearing Point REV RECOGNITION Project
Bearing Point REV RECOGNITION ProjectBearing Point REV RECOGNITION Project
Bearing Point REV RECOGNITION Project
 
Contract Costing NOtes.docx
Contract Costing NOtes.docxContract Costing NOtes.docx
Contract Costing NOtes.docx
 
Module 5 - Long-term Construction Contracts
Module 5 - Long-term Construction ContractsModule 5 - Long-term Construction Contracts
Module 5 - Long-term Construction Contracts
 

Recently uploaded

NewBase 24 May 2024 Energy News issue - 1727 by Khaled Al Awadi_compresse...
NewBase   24 May  2024  Energy News issue - 1727 by Khaled Al Awadi_compresse...NewBase   24 May  2024  Energy News issue - 1727 by Khaled Al Awadi_compresse...
NewBase 24 May 2024 Energy News issue - 1727 by Khaled Al Awadi_compresse...
Khaled Al Awadi
 
Sustainability: Balancing the Environment, Equity & Economy
Sustainability: Balancing the Environment, Equity & EconomySustainability: Balancing the Environment, Equity & Economy
Sustainability: Balancing the Environment, Equity & Economy
Operational Excellence Consulting
 
anas about venice for grade 6f about venice
anas about venice for grade 6f about veniceanas about venice for grade 6f about venice
anas about venice for grade 6f about venice
anasabutalha2013
 
FINAL PRESENTATION.pptx12143241324134134
FINAL PRESENTATION.pptx12143241324134134FINAL PRESENTATION.pptx12143241324134134
FINAL PRESENTATION.pptx12143241324134134
LR1709MUSIC
 
chapter 10 - excise tax of transfer and business taxation
chapter 10 - excise tax of transfer and business taxationchapter 10 - excise tax of transfer and business taxation
chapter 10 - excise tax of transfer and business taxation
AUDIJEAngelo
 
Cree_Rey_BrandIdentityKit.PDF_PersonalBd
Cree_Rey_BrandIdentityKit.PDF_PersonalBdCree_Rey_BrandIdentityKit.PDF_PersonalBd
Cree_Rey_BrandIdentityKit.PDF_PersonalBd
creerey
 

Recently uploaded (20)

RMD24 | Retail media: hoe zet je dit in als je geen AH of Unilever bent? Heid...
RMD24 | Retail media: hoe zet je dit in als je geen AH of Unilever bent? Heid...RMD24 | Retail media: hoe zet je dit in als je geen AH of Unilever bent? Heid...
RMD24 | Retail media: hoe zet je dit in als je geen AH of Unilever bent? Heid...
 
HR and Employment law update: May 2024.
HR and Employment law update:  May 2024.HR and Employment law update:  May 2024.
HR and Employment law update: May 2024.
 
New Product Development.kjiy7ggbfdsddggo9lo
New Product Development.kjiy7ggbfdsddggo9loNew Product Development.kjiy7ggbfdsddggo9lo
New Product Development.kjiy7ggbfdsddggo9lo
 
Maximizing Efficiency Migrating AccountEdge Data to QuickBooks.pdf
Maximizing Efficiency Migrating AccountEdge Data to QuickBooks.pdfMaximizing Efficiency Migrating AccountEdge Data to QuickBooks.pdf
Maximizing Efficiency Migrating AccountEdge Data to QuickBooks.pdf
 
NewBase 24 May 2024 Energy News issue - 1727 by Khaled Al Awadi_compresse...
NewBase   24 May  2024  Energy News issue - 1727 by Khaled Al Awadi_compresse...NewBase   24 May  2024  Energy News issue - 1727 by Khaled Al Awadi_compresse...
NewBase 24 May 2024 Energy News issue - 1727 by Khaled Al Awadi_compresse...
 
Strategy Analysis and Selecting ( Space Matrix)
Strategy Analysis and Selecting ( Space Matrix)Strategy Analysis and Selecting ( Space Matrix)
Strategy Analysis and Selecting ( Space Matrix)
 
Using Generative AI for Content Marketing
Using Generative AI for Content MarketingUsing Generative AI for Content Marketing
Using Generative AI for Content Marketing
 
The-McKinsey-7S-Framework. strategic management
The-McKinsey-7S-Framework. strategic managementThe-McKinsey-7S-Framework. strategic management
The-McKinsey-7S-Framework. strategic management
 
Unveiling the Secrets How Does Generative AI Work.pdf
Unveiling the Secrets How Does Generative AI Work.pdfUnveiling the Secrets How Does Generative AI Work.pdf
Unveiling the Secrets How Does Generative AI Work.pdf
 
Sustainability: Balancing the Environment, Equity & Economy
Sustainability: Balancing the Environment, Equity & EconomySustainability: Balancing the Environment, Equity & Economy
Sustainability: Balancing the Environment, Equity & Economy
 
IPTV Subscription in Ireland: Elevating Your Entertainment Experience
IPTV Subscription in Ireland: Elevating Your Entertainment ExperienceIPTV Subscription in Ireland: Elevating Your Entertainment Experience
IPTV Subscription in Ireland: Elevating Your Entertainment Experience
 
Pitch Deck Teardown: RAW Dating App's $3M Angel deck
Pitch Deck Teardown: RAW Dating App's $3M Angel deckPitch Deck Teardown: RAW Dating App's $3M Angel deck
Pitch Deck Teardown: RAW Dating App's $3M Angel deck
 
G-Mica Wood Chip Particle board Table Design
G-Mica Wood Chip Particle board Table DesignG-Mica Wood Chip Particle board Table Design
G-Mica Wood Chip Particle board Table Design
 
anas about venice for grade 6f about venice
anas about venice for grade 6f about veniceanas about venice for grade 6f about venice
anas about venice for grade 6f about venice
 
What are the main advantages of using HR recruiter services.pdf
What are the main advantages of using HR recruiter services.pdfWhat are the main advantages of using HR recruiter services.pdf
What are the main advantages of using HR recruiter services.pdf
 
FINAL PRESENTATION.pptx12143241324134134
FINAL PRESENTATION.pptx12143241324134134FINAL PRESENTATION.pptx12143241324134134
FINAL PRESENTATION.pptx12143241324134134
 
chapter 10 - excise tax of transfer and business taxation
chapter 10 - excise tax of transfer and business taxationchapter 10 - excise tax of transfer and business taxation
chapter 10 - excise tax of transfer and business taxation
 
Cree_Rey_BrandIdentityKit.PDF_PersonalBd
Cree_Rey_BrandIdentityKit.PDF_PersonalBdCree_Rey_BrandIdentityKit.PDF_PersonalBd
Cree_Rey_BrandIdentityKit.PDF_PersonalBd
 
Matt Conway - Attorney - A Knowledgeable Professional - Kentucky.pdf
Matt Conway - Attorney - A Knowledgeable Professional - Kentucky.pdfMatt Conway - Attorney - A Knowledgeable Professional - Kentucky.pdf
Matt Conway - Attorney - A Knowledgeable Professional - Kentucky.pdf
 
April 2024 Nostalgia Products Newsletter
April 2024 Nostalgia Products NewsletterApril 2024 Nostalgia Products Newsletter
April 2024 Nostalgia Products Newsletter
 

Solvay adv acc.case 1 a. l.t. contract.company abc

  • 1. 1 SOLVAY BRUSSELS SCHOOL OF ECONOMICS & MANAGEMENT ADVANCED ACCOUNTING COURSE - ACADEMIC YEAR 2013-2014 CASE STUDY n°1 – A - REVENUE RECOGNITION IAS 11 – Construction Contracts – Company ABC As at January 1st, 2007, Company ABC obtained a fixed price contract for 90.606 to build 2 boilers. The initial amount of revenue agreed in the contract is 90.606. Company ABC’s initial estimate of total costs amounts to 70.532, which can be summarized as follows: - Material and subcontracting: 58.767; - Labour: 4.533; - External success agent fees: 2.809; - Internal commercial costs: 130; - Standard contingencies: 2.481; - Warranty costs (as per Company ABC’s rule): 1.812. It will take 3 years to build the 2 boilers. By the end of year 1, Company ABC's estimate of costs has changed as follows: - Material and subcontracting increased by 300; - Labour increased by 93. Costs incurred at the end of year 1 can be summarized as follows: - Material and subcontracting: 5.928; - Labour: 979; - External success agent fees: 1.404; - Internal commercial costs: 130. By the end of year 1, part of the initial provision for standard contingencies (1,981) is considered as not meeting IAS 37 conditions. The remaining balance (500) does actually correspond to a tax risk and does actually meet the IAS 37 recognition criteria. At the end of year 1, boilers are still in a fabrication process. In year 2, the customer approves a variation resulting in an increase in contract revenue of 200, which corresponds to estimated additional contract costs for Company ABC of 150. The warranty provision is not updated to the extent that this contract revenue’s variation is not significant. At the end of year 2, costs invoiced include 100 for standard materials stored at the site to be used in year 3 to complete the project. In year 3, an amount of 250 has finally to be paid to the tax administration. Company ABC determines the stage of completion of the contract by calculating the proportion that contract costs incurred for work performed to date bear to the latest estimated total contract costs.
  • 2. 2 Below the detail of contract costs incurred during years 2008 and 2009 (excl tax risk) : 2008 2009 Material and subcontracting 30,143 23,096 Labour 2,988 709 External success agent fees 1,405 0 Total 34,536 23,805 2007 2008 2009 2010 Progress billings in each year 8.500 45.500 28.900 7.906 Required: Please calculate: - Total contract costs and estimated gross margin of the contract at the end of each year; - The stage of completion of the contract at the end of each year and the amounts of revenue, expenses and profits to be recognised in financial statements; Please show the relevant amounts to be disclosed in financial statements of the contractor for years 2007, 2008 and 2009. The template for the solution is presented below. 2007 2008 2009 Initial amount of revenue agreed in contract Variation Total contract revenue Contract costs incurred to date Contract costs to complete Total estimated contract costs (excl. provisions) Provision for tax risk Warranty provision Total estimated contract costs (incl. provisions) Estimated profit Stage of completion
  • 3. 3 Budget at beginning of year 2007: Budgeted contract revenue: Budgeted contract costs: Budgeted gross margin: Forecast at the end of year 2007: Budgeted contract revenue: Budgeted contract costs: Budgeted gross margin: Forecast at the end of year 2008: Budgeted contract revenue: Budgeted contract costs: Budgeted gross margin: Forecast at the end of year 2009: Budgeted contract revenue: Budgeted contract costs: Budgeted gross margin: Year 2007: Costs incurred: Cos ts Invoiced Down payments current year Down payments previous year Invoices to receive Invoices related to previous year Incurred Material and subcontracting Labour External agent fees Warranty cos ts Total : Total estimated costs to determine the POC (Percentage Of Completion) : POC : Gross margin to be recognised:
  • 4. 4 Year 2008: Costs incurred during the year: Cos ts Invoiced Down payments current year Down payments previous year Invoices to receive Invoices related to prev years Incurred Material and subcontracting Labour External agent fees Warranty cos ts Total : Total estimated costs to determine the POC : Cumulative POC : Cumulative gross margin to be recognised: Gross margin of the year: Year 2009: Costs incurred during the year: Cos ts Invoiced Down payments current year Down payments previous year Invoices to receive Invoices related to prev years Incurred Material and subcontracting Labour External agent fees Tax ri sk Warranty cos ts Total : Total estimated costs to determine the POC : Cumulative POC : Cumulative gross margin to be recognised: Gross margin of the year :
  • 5. 5 The amounts of revenue, expenses and profit recognised in the income statement in the three years are as follows: To Date Recognised in prior years Recognised in current year Year 1 Revenue Contract costs Warranty provision Cost of sales Selling expenses Profit Year 2 Revenue Contract costs Warranty provision Cost of sales Selling expenses Profit Year 3 Revenue Contract costs Warranty provision Cost of sales Selling expenses Profit