SlideShare a Scribd company logo
1 of 30
MALAYSIA ETHICAL ISSUE:




MRR2
     NUR ASYRAF BIN ABDUL RAHIM (K)
     MUHAMMAD FAIZAL BIN ABDULLAH
     NUR HASANAH BINTI SHAFEI
OBJECTIVES


      • To give a better insight of the unethical issues that
        occurred in Malaysia
  1

      • To educate people about the importance of adopting
  2     ethical conducts to prevent disastrous consequences




                                             GROUP 4            2
OVERVIEW OF MRR2 [1]

  Built by Malaysian Public Works   Department
  (JKR)




   To connect neighborhoods near Kuala Lumpur
   boundary



    Cost RM238.8 million



    Completed in 34 months (May 1999 to March
    2002)




                                                 GROUP 4   3
OVERVIEW OF MRR2

   • Construction of MRR2 was divided by 3
     phase : [1]

                      Gombak-      Ampang-
     Kepong-Gombak
                      Ampang      Sri Petaling
CONTROVERSIAL
                      ISSUES


  First closure
 8 August 2004



Second closure
4 February 2006



 Third closure
3 August 2008

                       GROUP 4    5
CONTROVERSIAL
                          ISSUES


           Fear about the safety on
           the faulty Kepong Flyover




31 out of 33 pillars               More than 7000
have obvious cracks                cracks detected

Investigations were carried out by government
Anti-Corruption Agency investigated possible fraud [2]

                                                 GROUP 4   6
CONTROVERSIAL ISSUES
                        Works Minister,
                        Dato' Seri S Samy Vellu



                     10th August 2004
         “Nobody can simply open their mouth and
           suggest it is design flaw. The question
              of design failure doesn't arise."



         PWD's consultant (Kohler & Seith) findings
                      was dismissed




                                              GROUP 4   7
CONTROVERSIAL ISSUES
  12 August, 2004  The government of
  Malaysia then appointed British Halcrow
  Consultancy Ltd to study the cracks that
  have appeared on 31 of the 32
  crossbeams since 2000.

  findings from Halcrow Consultants Ltd
  suggested design deficiencies and the
  improper anchoring were responsible for
  cracks and were finally accepted by the
  ministry

  The flyover  closed in August 2004
  >>waterproofed the bridge to prevent
  further cracks
  >>reopened in December 2004 [2]




                                             GROUP 4   8
CONTROVERSIAL ISSUES



      • On 4th Feb 2006, the Kepong Flyover was closed again
        after serious damages was confirmed
I

      • Many complaints arrived about the damages on MRR2
II

      • Traffic jam has rose due to incompletion of MRR2
III

      • On 8 December 2006, the Kepong Flyover was reopened
        to light traffic [3]
IV
                                                               GROUP 4   9
HIGHLIGHTS

                 RM20mil to repair within 3 months


 18/8/2004      Yet to determine the cause of cracks


                 Deny the possibility of design fault



 22/2/2006     Repair cost more than RM 40 milllion



                Repairs cost RM 40 mil  RM70mil

  1/2/2007
             Work Minister called to explain expenditure


                                            GROUP 4        10
3 August 2008




                GROUP 4   11
ETHICAL THEORY

 “Up to now, Malaysians still do not have a full and proper picture about
 the MRR2 flyover cracks. As two consultants, one from Australia by the
 contractor and a consultant from Germany appointed by the Public Works
 Department, have come out with different findings about the MRR2
 flyover cracks, how could there be public confidence about the repair work
 undertaken in the past five days? “
 Media Statement
 by Lim Kit Siang (14/8/2004)




                                                         GROUP 4              12
Utilitarianism
  Definition: Balance between good and bad
   consequences of an action [4]

                         GOOD: MRR2
                        brought travel
                       within easy reach



          BAD:
       Controversial
         Issues.

                                   GROUP 4    13
Right Ethics
 • Definition: People have the fundamental
   rights that other people have a duty to
   respect [4]




                                GROUP 4      14
Right Ethics


               The right to use the flyover safely


            Do not want to keep stuck in traffic
          jam as a result from the closure of the
                           MRR2


        Do not want to see the few well-
       connected companies or individuals
           profit at the public expense


                                               GROUP 4   15
Duty Ethics

               • People have duties to protect
  Definition     the rights of others

               • the duty to keep promises
   Fidelity


               - Contractors and engineers have
                 failed to design and build the
                flyover in compliance with the
                            contract

                                       GROUP 4    16
Duty Ethics
          • the duty to recognize merit work minister
            does not take any action against the
Justice     irresponsible contractors and consultant



     – “Samy Vellu is acting as if he is the
     Minister for Bumi Hiway, the contractor
     for the MRR2, instead of being Minister
           for 25 million Malaysians.”




                                        GROUP 4         17
Duty Ethics

               • the duty to improve
 Beneficence     the conditions

                                         This expenses could be
                                         reduced if he appointed
                                         a reliable contractor to
                                         build the flyover

   Repairs cost    Cause by improper planning
   RM40 mil to      and poor cost estimation
   RM70mil         and poor administrative of
                       the Work Minister



                                            GROUP 4           18
Virtue Ethics
   Irresponsibility

   Engineers did not fully supervise
   the project


       Minister did not give explanation
       of the RM70 million bill


           No actions taken towards original
           contractors


                                           GROUP 4   19
Virtue Ethics
     Dishonestly

          Denied cracks were due to
          design flaw


     Did not build according
     to right specifications
     and designs




                                      GROUP 4   20
Safety And Risk
 Definition: Ensure safety of public




                                       GROUP 4   21
Safety And Risk
                    • “ ‘space-age carbon-fibre pre-stressed
                      trusses’ would be used to repair the
       Safety         pillars, beams and girders of the
       design         flyover: a tensile strength five times
       criteria       stronger than that of steel” [5]




                     • “Samy Vellu is giving the impression
                       the repair work for the MRR2 flyover
     Risk-Benefit      is very simple and
       Analysis        straightforward, would not even
                       require the three months mentioned
                       by him.” [5]


                                               GROUP 4         22
WHISTLE BLOWING
                                         MEANING:
         An act by an employee of informing the public or higher management of
                unethical or illegal behavior by an employer or supervisor
OCCURS

     Need = There must be a clear and important harm that can be
            avoided by blowing the whistle

     Proximity = The whistleblower must be in a very clear position to
                 report on the problem

     Capability = The whistleblower must have a reasonable chance of
                  success in stopping the harmful activity

     Last Resort = Should be attempted only if there is no one else more
                   capable and all other lines of action within the
                   organization have been shut off

                                                             GROUP 4             23
ANALYSIS OF THE MRR2 CASE

1) AUTHORITYS INVOLVEMENT
                               KKR
                      (Kementerian Kerja Raya)
                             Agency

                                                 BOA (Lembaga Arkitek
           JKR (Jabatan Kerja Raya)
                                                       Malaysia)



               CIDB (Lembaga
                                                 BEM (Lembaga Jurutera
            Pembangunan Industri
                                                       Malaysia)
             Pembinaan Malaysia)


              BQSM (Lembaga
               Juruukur Bahan                       MHA (Lembaga
                  Malaysia)                       Lebuhraya Malaysia)


                                                   GROUP 4              24
ANALYSIS OF THE MRR2 CASE
2) PERSONAL VS BUSINESS CONFLICT

         MINISTERY                                    MEDIA
       (strong parties)                               (news)


 HIGH COUNCIL BOARD                                      ENGINEER
      (reputation)             CONFLICT                (responsibility)


       CONTRACTOR                                     CITIZEN
          (work)                                    (daily usage)


                          Right and wrong ethics,
                           Profitable and Loses,
                          Rules and Regulations,
                           Cost-Benefit Analysis


                                                        GROUP 4           25
ANALYSIS OF THE MRR2 CASE
3) AMONG RULES AND REGULATIONS
                                         1) Design Standard
                                         2) Maintenance Manual and
      1) Engineers Act 1967 (Rev 2007)
                                             Guideline
      2) Regulations 1990 (Rev 2003)
                                             (civil, electrical and
      3) Code of Professional Conduct
                                             mechanical)
                                         3) Guideline
      1) Architect Act 1967
      2) Architect Rules 1996
                                         1) Contractor Code of Ethics

      1) Standard Specifications for
      Building Works 2005


      1) QS Act Revised 2002
      2) QS Rule Amendment 2004


                                               GROUP 4              26
CONCLUSION
1) CORE CODE OF ETHICS REFERRED FROM VARIES CODE OF ETHICS
       A Professional shall at all times hold paramount the safety, health and
                                  welfare of the public

        A Professional shall undertake assignments only if he is qualified by
       education and experience in the specific technical fields in which he is
                                     involved

         A Professional shall issue public statements only in an objective and
                                    truthful manner


       A Professional shall act for each employer or clients as faithful agent or
                                        trustee


      A Professional shall conduct himself honourably, responsibly, ethically and
        lawfully so as to enhance the honour, reputation and usefulness of the
                                      profession

                                                              GROUP 4               27
CONCLUSION
2) ACTION WHICH SUPPOSE TO BE AVOIDED

                         Bribery taken
                        Miscalculation
                            Tragedy
                      Breach of contract
                  Doesn’t follow specification
                   Lack communication link
                      Bad construction
                       Lack team work
                    Unethical action taken
                     Bad media coverage
                     Burden the country
                      Burden the citizen
                       Fired employee
                    Accusing responsibility



                                                 GROUP 4   28
REFERENCES
   [1] Maverick, SM., Project Report Middle Ring Road 2.
       February, 2006 was retrieved from
       http://mavrkyprojectphoto.blogspot.com/2006/02/middle-ring-
       road-2.html
   [2] Brandon, H., Controversial Issues Middle Ring Road 2, was
       retrieved from
       http://en.wikipedia.org/wiki/Kuala_Lumpur_Middle_Ring_Road_2
   [3] Maverick, SM., Risk, Health & Safety. 2006 was retrieved from
       http://constructionrisk.blogspot.com/
   [4] Charles B. Fleddermann., Engineering Ethics (3rd Edition), Pearson
       Practice Hall , University of New Mexico, 2008
   [5] Lim Kit Siang, Media Statement. August, 2004 was retrieved from
       http://www.dapmalaysia.org/all-
       archive/English/2004/aug04/lks/lks3158.htm
   [6] Main Portal for Kementerian Kerja Raya
       http://www.kkr.gov.my/


                                                      GROUP 4           29
The End

Q &A

          GROUP 4   30

More Related Content

What's hot

Estimating calculation
Estimating calculationEstimating calculation
Estimating calculationZIyeeTan
 
Road Safety Audit Malaysian
Road Safety Audit Malaysian Road Safety Audit Malaysian
Road Safety Audit Malaysian uitm pulau pinang
 
Sarawak building ordinance 1994
Sarawak building ordinance 1994Sarawak building ordinance 1994
Sarawak building ordinance 1994hafizanazis
 
Malaysian Property Development
Malaysian Property DevelopmentMalaysian Property Development
Malaysian Property DevelopmentDebbie Loh
 
Chapter 4 deep foundation
Chapter 4 deep foundationChapter 4 deep foundation
Chapter 4 deep foundationAmiRul AFiq
 
Micro trenching services by t.t ehsan sdn bhd
Micro trenching services by t.t ehsan sdn bhdMicro trenching services by t.t ehsan sdn bhd
Micro trenching services by t.t ehsan sdn bhdT.T EHSAN SDN BHD
 
Numerical problem and solution on pile capacity (usefulsearch.org) ( usefuls...
Numerical problem and solution on pile capacity (usefulsearch.org) ( usefuls...Numerical problem and solution on pile capacity (usefulsearch.org) ( usefuls...
Numerical problem and solution on pile capacity (usefulsearch.org) ( usefuls...Make Mannan
 
DIFFERENCE BETWEEN CONTRACT FORM JKR 203A & PAM
DIFFERENCE BETWEEN CONTRACT FORM JKR 203A & PAMDIFFERENCE BETWEEN CONTRACT FORM JKR 203A & PAM
DIFFERENCE BETWEEN CONTRACT FORM JKR 203A & PAMAnep Botak
 
Unconsolidated Undrained Test
Unconsolidated Undrained TestUnconsolidated Undrained Test
Unconsolidated Undrained TestPsyful Bappi
 
Slope Protection works
Slope Protection worksSlope Protection works
Slope Protection worksRaj Shah
 
Tempoh tanggungan kecacatan (Defects Liability Period (DLP))
Tempoh tanggungan kecacatan (Defects Liability Period (DLP))Tempoh tanggungan kecacatan (Defects Liability Period (DLP))
Tempoh tanggungan kecacatan (Defects Liability Period (DLP))sofyan fatimi
 
Analysis & design of T-Beam bridge
Analysis & design of T-Beam bridgeAnalysis & design of T-Beam bridge
Analysis & design of T-Beam bridgeElamathy Murugan
 
construction equipment and agreegate production equipment
construction equipment and agreegate production equipmentconstruction equipment and agreegate production equipment
construction equipment and agreegate production equipmentkonagallasrivardhan
 
CONSTRUCTION [soil treatment, foundation backfill, Damp Proof Membrane[DPM] a...
CONSTRUCTION [soil treatment, foundation backfill, Damp Proof Membrane[DPM] a...CONSTRUCTION [soil treatment, foundation backfill, Damp Proof Membrane[DPM] a...
CONSTRUCTION [soil treatment, foundation backfill, Damp Proof Membrane[DPM] a...musadoto
 

What's hot (20)

Estimating calculation
Estimating calculationEstimating calculation
Estimating calculation
 
Road Safety Audit Malaysian
Road Safety Audit Malaysian Road Safety Audit Malaysian
Road Safety Audit Malaysian
 
Spun pile
Spun pileSpun pile
Spun pile
 
Sarawak building ordinance 1994
Sarawak building ordinance 1994Sarawak building ordinance 1994
Sarawak building ordinance 1994
 
Malaysian Property Development
Malaysian Property DevelopmentMalaysian Property Development
Malaysian Property Development
 
Chapter 4 deep foundation
Chapter 4 deep foundationChapter 4 deep foundation
Chapter 4 deep foundation
 
Ch 7 design of rcc footing
Ch 7 design of rcc footingCh 7 design of rcc footing
Ch 7 design of rcc footing
 
Micro trenching services by t.t ehsan sdn bhd
Micro trenching services by t.t ehsan sdn bhdMicro trenching services by t.t ehsan sdn bhd
Micro trenching services by t.t ehsan sdn bhd
 
Numerical problem and solution on pile capacity (usefulsearch.org) ( usefuls...
Numerical problem and solution on pile capacity (usefulsearch.org) ( usefuls...Numerical problem and solution on pile capacity (usefulsearch.org) ( usefuls...
Numerical problem and solution on pile capacity (usefulsearch.org) ( usefuls...
 
Refurbishment
RefurbishmentRefurbishment
Refurbishment
 
DIFFERENCE BETWEEN CONTRACT FORM JKR 203A & PAM
DIFFERENCE BETWEEN CONTRACT FORM JKR 203A & PAMDIFFERENCE BETWEEN CONTRACT FORM JKR 203A & PAM
DIFFERENCE BETWEEN CONTRACT FORM JKR 203A & PAM
 
cerucuk piling
cerucuk pilingcerucuk piling
cerucuk piling
 
Unconsolidated Undrained Test
Unconsolidated Undrained TestUnconsolidated Undrained Test
Unconsolidated Undrained Test
 
Jenis kontraktor
Jenis kontraktorJenis kontraktor
Jenis kontraktor
 
Slope Protection works
Slope Protection worksSlope Protection works
Slope Protection works
 
Tempoh tanggungan kecacatan (Defects Liability Period (DLP))
Tempoh tanggungan kecacatan (Defects Liability Period (DLP))Tempoh tanggungan kecacatan (Defects Liability Period (DLP))
Tempoh tanggungan kecacatan (Defects Liability Period (DLP))
 
Analysis & design of T-Beam bridge
Analysis & design of T-Beam bridgeAnalysis & design of T-Beam bridge
Analysis & design of T-Beam bridge
 
Reinforced column design
Reinforced column design Reinforced column design
Reinforced column design
 
construction equipment and agreegate production equipment
construction equipment and agreegate production equipmentconstruction equipment and agreegate production equipment
construction equipment and agreegate production equipment
 
CONSTRUCTION [soil treatment, foundation backfill, Damp Proof Membrane[DPM] a...
CONSTRUCTION [soil treatment, foundation backfill, Damp Proof Membrane[DPM] a...CONSTRUCTION [soil treatment, foundation backfill, Damp Proof Membrane[DPM] a...
CONSTRUCTION [soil treatment, foundation backfill, Damp Proof Membrane[DPM] a...
 

Viewers also liked

highland tower case study
highland tower case studyhighland tower case study
highland tower case studyamira688
 
Nota 2 Kajian Kes
Nota 2 Kajian KesNota 2 Kajian Kes
Nota 2 Kajian Kessyahums
 
Ikea Case Study Powerpoint
Ikea Case Study PowerpointIkea Case Study Powerpoint
Ikea Case Study PowerpointTom_Adams
 
McDonalds Case on Ethics
McDonalds Case on EthicsMcDonalds Case on Ethics
McDonalds Case on EthicsB U DEEPANKAR
 
Mcdonald case-study & analysis
Mcdonald case-study & analysisMcdonald case-study & analysis
Mcdonald case-study & analysisiipmff2
 
BP's Deepwater Oil Spill Case Study Analysis - Business Ethics
BP's Deepwater Oil Spill Case Study Analysis - Business EthicsBP's Deepwater Oil Spill Case Study Analysis - Business Ethics
BP's Deepwater Oil Spill Case Study Analysis - Business EthicsÔn Thi
 
Mc donald case study 1
Mc donald case study 1Mc donald case study 1
Mc donald case study 1umarshk
 

Viewers also liked (12)

Bukit Antarabangsa Landslide
Bukit Antarabangsa LandslideBukit Antarabangsa Landslide
Bukit Antarabangsa Landslide
 
Highland tower
Highland towerHighland tower
Highland tower
 
highland tower case study
highland tower case studyhighland tower case study
highland tower case study
 
Nota 2 Kajian Kes
Nota 2 Kajian KesNota 2 Kajian Kes
Nota 2 Kajian Kes
 
Ikea Case Study Powerpoint
Ikea Case Study PowerpointIkea Case Study Powerpoint
Ikea Case Study Powerpoint
 
Mazda Perodua V Proton
Mazda Perodua V ProtonMazda Perodua V Proton
Mazda Perodua V Proton
 
Malaysian airlines power point
Malaysian airlines power pointMalaysian airlines power point
Malaysian airlines power point
 
McDonalds Case on Ethics
McDonalds Case on EthicsMcDonalds Case on Ethics
McDonalds Case on Ethics
 
Mcdonald case-study & analysis
Mcdonald case-study & analysisMcdonald case-study & analysis
Mcdonald case-study & analysis
 
Malaysia Airlines Strategic Management (Case Study)
Malaysia Airlines Strategic Management (Case Study)Malaysia Airlines Strategic Management (Case Study)
Malaysia Airlines Strategic Management (Case Study)
 
BP's Deepwater Oil Spill Case Study Analysis - Business Ethics
BP's Deepwater Oil Spill Case Study Analysis - Business EthicsBP's Deepwater Oil Spill Case Study Analysis - Business Ethics
BP's Deepwater Oil Spill Case Study Analysis - Business Ethics
 
Mc donald case study 1
Mc donald case study 1Mc donald case study 1
Mc donald case study 1
 

Similar to MALAYSIA ETHICAL ISSUE: MRR2 FLYOVER CRACKS

Transparency and Acountability in Project Delivery
Transparency and Acountability in Project DeliveryTransparency and Acountability in Project Delivery
Transparency and Acountability in Project DeliveryRajesh Prasad
 
COMPREHENSIVE PROBLEM SUPPLEMENT P2Preparation of a Worksheet,.docx
COMPREHENSIVE PROBLEM SUPPLEMENT P2Preparation of a Worksheet,.docxCOMPREHENSIVE PROBLEM SUPPLEMENT P2Preparation of a Worksheet,.docx
COMPREHENSIVE PROBLEM SUPPLEMENT P2Preparation of a Worksheet,.docxdonnajames55
 
Ethics in Engineering
Ethics in EngineeringEthics in Engineering
Ethics in EngineeringSunjaayhDev
 
Engineers in society
Engineers in societyEngineers in society
Engineers in societyAzlin lolin
 
project Mangement
project Mangementproject Mangement
project MangementAlex Jensen
 
Iain Cameron CV presentation jun13
Iain Cameron CV presentation jun13Iain Cameron CV presentation jun13
Iain Cameron CV presentation jun13iain_cameron
 
CV Presentation May16
CV Presentation May16CV Presentation May16
CV Presentation May16Iain Cameron
 
Challenges and Opportunities for King County to Successfully Complete the Sta...
Challenges and Opportunities for King County to Successfully Complete the Sta...Challenges and Opportunities for King County to Successfully Complete the Sta...
Challenges and Opportunities for King County to Successfully Complete the Sta...marcus evans Network
 
NEC FIDIC JBCC Contracts Workshop 2012
NEC FIDIC JBCC Contracts Workshop 2012NEC FIDIC JBCC Contracts Workshop 2012
NEC FIDIC JBCC Contracts Workshop 2012Ola Odejayi
 
ANGELA LOPEZ - CV - Civil, Environmental & Sustainability Engineer
ANGELA LOPEZ - CV - Civil, Environmental  & Sustainability EngineerANGELA LOPEZ - CV - Civil, Environmental  & Sustainability Engineer
ANGELA LOPEZ - CV - Civil, Environmental & Sustainability EngineerAngela Lopez
 
JIPMER Phase II Project
JIPMER Phase II ProjectJIPMER Phase II Project
JIPMER Phase II ProjectSupraja Mohan
 
20080129024931.contract checklists
20080129024931.contract checklists20080129024931.contract checklists
20080129024931.contract checklistsAshraf Javed
 
Summer Training Report at Simplex Infrastructures and Salarpuria Joint Ventur...
Summer Training Report at Simplex Infrastructures and Salarpuria Joint Ventur...Summer Training Report at Simplex Infrastructures and Salarpuria Joint Ventur...
Summer Training Report at Simplex Infrastructures and Salarpuria Joint Ventur...Arijit Acharya
 
ATT_lotfy farouk CV25-10-2014
ATT_lotfy farouk  CV25-10-2014ATT_lotfy farouk  CV25-10-2014
ATT_lotfy farouk CV25-10-2014LOTFY FAROUK
 

Similar to MALAYSIA ETHICAL ISSUE: MRR2 FLYOVER CRACKS (20)

Transparency and Acountability in Project Delivery
Transparency and Acountability in Project DeliveryTransparency and Acountability in Project Delivery
Transparency and Acountability in Project Delivery
 
CRNM - CARICOM Construction & Installation Services Sector
CRNM - CARICOM Construction & Installation Services SectorCRNM - CARICOM Construction & Installation Services Sector
CRNM - CARICOM Construction & Installation Services Sector
 
COMPREHENSIVE PROBLEM SUPPLEMENT P2Preparation of a Worksheet,.docx
COMPREHENSIVE PROBLEM SUPPLEMENT P2Preparation of a Worksheet,.docxCOMPREHENSIVE PROBLEM SUPPLEMENT P2Preparation of a Worksheet,.docx
COMPREHENSIVE PROBLEM SUPPLEMENT P2Preparation of a Worksheet,.docx
 
Ethics in Engineering
Ethics in EngineeringEthics in Engineering
Ethics in Engineering
 
Engineers in society
Engineers in societyEngineers in society
Engineers in society
 
Raz training report
Raz training reportRaz training report
Raz training report
 
project Mangement
project Mangementproject Mangement
project Mangement
 
Iain Cameron CV presentation jun13
Iain Cameron CV presentation jun13Iain Cameron CV presentation jun13
Iain Cameron CV presentation jun13
 
TABLE OF CONTENTS
TABLE OF CONTENTSTABLE OF CONTENTS
TABLE OF CONTENTS
 
CV Presentation May16
CV Presentation May16CV Presentation May16
CV Presentation May16
 
Construction Oil and Gas Forum Jan 2015 Abu Dhabi Brochure
Construction Oil and Gas Forum Jan 2015 Abu Dhabi BrochureConstruction Oil and Gas Forum Jan 2015 Abu Dhabi Brochure
Construction Oil and Gas Forum Jan 2015 Abu Dhabi Brochure
 
Challenges and Opportunities for King County to Successfully Complete the Sta...
Challenges and Opportunities for King County to Successfully Complete the Sta...Challenges and Opportunities for King County to Successfully Complete the Sta...
Challenges and Opportunities for King County to Successfully Complete the Sta...
 
Cv Presentation
Cv PresentationCv Presentation
Cv Presentation
 
NEC FIDIC JBCC Contracts Workshop 2012
NEC FIDIC JBCC Contracts Workshop 2012NEC FIDIC JBCC Contracts Workshop 2012
NEC FIDIC JBCC Contracts Workshop 2012
 
ANGELA LOPEZ - CV - Civil, Environmental & Sustainability Engineer
ANGELA LOPEZ - CV - Civil, Environmental  & Sustainability EngineerANGELA LOPEZ - CV - Civil, Environmental  & Sustainability Engineer
ANGELA LOPEZ - CV - Civil, Environmental & Sustainability Engineer
 
JIPMER Phase II Project
JIPMER Phase II ProjectJIPMER Phase II Project
JIPMER Phase II Project
 
20080129024931.contract checklists
20080129024931.contract checklists20080129024931.contract checklists
20080129024931.contract checklists
 
Summer Training Report at Simplex Infrastructures and Salarpuria Joint Ventur...
Summer Training Report at Simplex Infrastructures and Salarpuria Joint Ventur...Summer Training Report at Simplex Infrastructures and Salarpuria Joint Ventur...
Summer Training Report at Simplex Infrastructures and Salarpuria Joint Ventur...
 
Bs bab 4
Bs bab 4Bs bab 4
Bs bab 4
 
ATT_lotfy farouk CV25-10-2014
ATT_lotfy farouk  CV25-10-2014ATT_lotfy farouk  CV25-10-2014
ATT_lotfy farouk CV25-10-2014
 

More from Nurhasanah Shafei

Test 1 february 2010 page 3 answer
Test 1 february 2010 page 3  answerTest 1 february 2010 page 3  answer
Test 1 february 2010 page 3 answerNurhasanah Shafei
 
Test 1 february 2010 page 2 answer
Test 1 february 2010 page 2  answerTest 1 february 2010 page 2  answer
Test 1 february 2010 page 2 answerNurhasanah Shafei
 
Electrotherapy supplied rectangular current waveform generation type fm
Electrotherapy   supplied rectangular current waveform generation type fmElectrotherapy   supplied rectangular current waveform generation type fm
Electrotherapy supplied rectangular current waveform generation type fmNurhasanah Shafei
 
Dsp lab report- Analysis and classification of EMG signal using MATLAB.
Dsp lab report- Analysis and classification of EMG signal using MATLAB.Dsp lab report- Analysis and classification of EMG signal using MATLAB.
Dsp lab report- Analysis and classification of EMG signal using MATLAB.Nurhasanah Shafei
 
PRESENTATION LAB DSP.Analysis & classification of EMG signal - DSP LAB
PRESENTATION LAB DSP.Analysis & classification of EMG signal - DSP LABPRESENTATION LAB DSP.Analysis & classification of EMG signal - DSP LAB
PRESENTATION LAB DSP.Analysis & classification of EMG signal - DSP LABNurhasanah Shafei
 

More from Nurhasanah Shafei (7)

Test 1 november 2011 page 1
Test 1 november 2011 page 1Test 1 november 2011 page 1
Test 1 november 2011 page 1
 
Test 1 february 2010 page 3 answer
Test 1 february 2010 page 3  answerTest 1 february 2010 page 3  answer
Test 1 february 2010 page 3 answer
 
Test 1 february 2010 page 2 answer
Test 1 february 2010 page 2  answerTest 1 february 2010 page 2  answer
Test 1 february 2010 page 2 answer
 
Test 1 november 2011 page 2
Test 1 november 2011 page 2Test 1 november 2011 page 2
Test 1 november 2011 page 2
 
Electrotherapy supplied rectangular current waveform generation type fm
Electrotherapy   supplied rectangular current waveform generation type fmElectrotherapy   supplied rectangular current waveform generation type fm
Electrotherapy supplied rectangular current waveform generation type fm
 
Dsp lab report- Analysis and classification of EMG signal using MATLAB.
Dsp lab report- Analysis and classification of EMG signal using MATLAB.Dsp lab report- Analysis and classification of EMG signal using MATLAB.
Dsp lab report- Analysis and classification of EMG signal using MATLAB.
 
PRESENTATION LAB DSP.Analysis & classification of EMG signal - DSP LAB
PRESENTATION LAB DSP.Analysis & classification of EMG signal - DSP LABPRESENTATION LAB DSP.Analysis & classification of EMG signal - DSP LAB
PRESENTATION LAB DSP.Analysis & classification of EMG signal - DSP LAB
 

Recently uploaded

Understanding the Laravel MVC Architecture
Understanding the Laravel MVC ArchitectureUnderstanding the Laravel MVC Architecture
Understanding the Laravel MVC ArchitecturePixlogix Infotech
 
Pigging Solutions in Pet Food Manufacturing
Pigging Solutions in Pet Food ManufacturingPigging Solutions in Pet Food Manufacturing
Pigging Solutions in Pet Food ManufacturingPigging Solutions
 
Swan(sea) Song – personal research during my six years at Swansea ... and bey...
Swan(sea) Song – personal research during my six years at Swansea ... and bey...Swan(sea) Song – personal research during my six years at Swansea ... and bey...
Swan(sea) Song – personal research during my six years at Swansea ... and bey...Alan Dix
 
Neo4j - How KGs are shaping the future of Generative AI at AWS Summit London ...
Neo4j - How KGs are shaping the future of Generative AI at AWS Summit London ...Neo4j - How KGs are shaping the future of Generative AI at AWS Summit London ...
Neo4j - How KGs are shaping the future of Generative AI at AWS Summit London ...Neo4j
 
Hyderabad Call Girls Khairatabad ✨ 7001305949 ✨ Cheap Price Your Budget
Hyderabad Call Girls Khairatabad ✨ 7001305949 ✨ Cheap Price Your BudgetHyderabad Call Girls Khairatabad ✨ 7001305949 ✨ Cheap Price Your Budget
Hyderabad Call Girls Khairatabad ✨ 7001305949 ✨ Cheap Price Your BudgetEnjoy Anytime
 
Beyond Boundaries: Leveraging No-Code Solutions for Industry Innovation
Beyond Boundaries: Leveraging No-Code Solutions for Industry InnovationBeyond Boundaries: Leveraging No-Code Solutions for Industry Innovation
Beyond Boundaries: Leveraging No-Code Solutions for Industry InnovationSafe Software
 
#StandardsGoals for 2024: What’s new for BISAC - Tech Forum 2024
#StandardsGoals for 2024: What’s new for BISAC - Tech Forum 2024#StandardsGoals for 2024: What’s new for BISAC - Tech Forum 2024
#StandardsGoals for 2024: What’s new for BISAC - Tech Forum 2024BookNet Canada
 
08448380779 Call Girls In Civil Lines Women Seeking Men
08448380779 Call Girls In Civil Lines Women Seeking Men08448380779 Call Girls In Civil Lines Women Seeking Men
08448380779 Call Girls In Civil Lines Women Seeking MenDelhi Call girls
 
My Hashitalk Indonesia April 2024 Presentation
My Hashitalk Indonesia April 2024 PresentationMy Hashitalk Indonesia April 2024 Presentation
My Hashitalk Indonesia April 2024 PresentationRidwan Fadjar
 
Key Features Of Token Development (1).pptx
Key  Features Of Token  Development (1).pptxKey  Features Of Token  Development (1).pptx
Key Features Of Token Development (1).pptxLBM Solutions
 
Injustice - Developers Among Us (SciFiDevCon 2024)
Injustice - Developers Among Us (SciFiDevCon 2024)Injustice - Developers Among Us (SciFiDevCon 2024)
Injustice - Developers Among Us (SciFiDevCon 2024)Allon Mureinik
 
Automating Business Process via MuleSoft Composer | Bangalore MuleSoft Meetup...
Automating Business Process via MuleSoft Composer | Bangalore MuleSoft Meetup...Automating Business Process via MuleSoft Composer | Bangalore MuleSoft Meetup...
Automating Business Process via MuleSoft Composer | Bangalore MuleSoft Meetup...shyamraj55
 
Enhancing Worker Digital Experience: A Hands-on Workshop for Partners
Enhancing Worker Digital Experience: A Hands-on Workshop for PartnersEnhancing Worker Digital Experience: A Hands-on Workshop for Partners
Enhancing Worker Digital Experience: A Hands-on Workshop for PartnersThousandEyes
 
The Codex of Business Writing Software for Real-World Solutions 2.pptx
The Codex of Business Writing Software for Real-World Solutions 2.pptxThe Codex of Business Writing Software for Real-World Solutions 2.pptx
The Codex of Business Writing Software for Real-World Solutions 2.pptxMalak Abu Hammad
 
Transforming Data Streams with Kafka Connect: An Introduction to Single Messa...
Transforming Data Streams with Kafka Connect: An Introduction to Single Messa...Transforming Data Streams with Kafka Connect: An Introduction to Single Messa...
Transforming Data Streams with Kafka Connect: An Introduction to Single Messa...HostedbyConfluent
 
Tech-Forward - Achieving Business Readiness For Copilot in Microsoft 365
Tech-Forward - Achieving Business Readiness For Copilot in Microsoft 365Tech-Forward - Achieving Business Readiness For Copilot in Microsoft 365
Tech-Forward - Achieving Business Readiness For Copilot in Microsoft 3652toLead Limited
 
Benefits Of Flutter Compared To Other Frameworks
Benefits Of Flutter Compared To Other FrameworksBenefits Of Flutter Compared To Other Frameworks
Benefits Of Flutter Compared To Other FrameworksSoftradix Technologies
 
Azure Monitor & Application Insight to monitor Infrastructure & Application
Azure Monitor & Application Insight to monitor Infrastructure & ApplicationAzure Monitor & Application Insight to monitor Infrastructure & Application
Azure Monitor & Application Insight to monitor Infrastructure & ApplicationAndikSusilo4
 
08448380779 Call Girls In Greater Kailash - I Women Seeking Men
08448380779 Call Girls In Greater Kailash - I Women Seeking Men08448380779 Call Girls In Greater Kailash - I Women Seeking Men
08448380779 Call Girls In Greater Kailash - I Women Seeking MenDelhi Call girls
 
IAC 2024 - IA Fast Track to Search Focused AI Solutions
IAC 2024 - IA Fast Track to Search Focused AI SolutionsIAC 2024 - IA Fast Track to Search Focused AI Solutions
IAC 2024 - IA Fast Track to Search Focused AI SolutionsEnterprise Knowledge
 

Recently uploaded (20)

Understanding the Laravel MVC Architecture
Understanding the Laravel MVC ArchitectureUnderstanding the Laravel MVC Architecture
Understanding the Laravel MVC Architecture
 
Pigging Solutions in Pet Food Manufacturing
Pigging Solutions in Pet Food ManufacturingPigging Solutions in Pet Food Manufacturing
Pigging Solutions in Pet Food Manufacturing
 
Swan(sea) Song – personal research during my six years at Swansea ... and bey...
Swan(sea) Song – personal research during my six years at Swansea ... and bey...Swan(sea) Song – personal research during my six years at Swansea ... and bey...
Swan(sea) Song – personal research during my six years at Swansea ... and bey...
 
Neo4j - How KGs are shaping the future of Generative AI at AWS Summit London ...
Neo4j - How KGs are shaping the future of Generative AI at AWS Summit London ...Neo4j - How KGs are shaping the future of Generative AI at AWS Summit London ...
Neo4j - How KGs are shaping the future of Generative AI at AWS Summit London ...
 
Hyderabad Call Girls Khairatabad ✨ 7001305949 ✨ Cheap Price Your Budget
Hyderabad Call Girls Khairatabad ✨ 7001305949 ✨ Cheap Price Your BudgetHyderabad Call Girls Khairatabad ✨ 7001305949 ✨ Cheap Price Your Budget
Hyderabad Call Girls Khairatabad ✨ 7001305949 ✨ Cheap Price Your Budget
 
Beyond Boundaries: Leveraging No-Code Solutions for Industry Innovation
Beyond Boundaries: Leveraging No-Code Solutions for Industry InnovationBeyond Boundaries: Leveraging No-Code Solutions for Industry Innovation
Beyond Boundaries: Leveraging No-Code Solutions for Industry Innovation
 
#StandardsGoals for 2024: What’s new for BISAC - Tech Forum 2024
#StandardsGoals for 2024: What’s new for BISAC - Tech Forum 2024#StandardsGoals for 2024: What’s new for BISAC - Tech Forum 2024
#StandardsGoals for 2024: What’s new for BISAC - Tech Forum 2024
 
08448380779 Call Girls In Civil Lines Women Seeking Men
08448380779 Call Girls In Civil Lines Women Seeking Men08448380779 Call Girls In Civil Lines Women Seeking Men
08448380779 Call Girls In Civil Lines Women Seeking Men
 
My Hashitalk Indonesia April 2024 Presentation
My Hashitalk Indonesia April 2024 PresentationMy Hashitalk Indonesia April 2024 Presentation
My Hashitalk Indonesia April 2024 Presentation
 
Key Features Of Token Development (1).pptx
Key  Features Of Token  Development (1).pptxKey  Features Of Token  Development (1).pptx
Key Features Of Token Development (1).pptx
 
Injustice - Developers Among Us (SciFiDevCon 2024)
Injustice - Developers Among Us (SciFiDevCon 2024)Injustice - Developers Among Us (SciFiDevCon 2024)
Injustice - Developers Among Us (SciFiDevCon 2024)
 
Automating Business Process via MuleSoft Composer | Bangalore MuleSoft Meetup...
Automating Business Process via MuleSoft Composer | Bangalore MuleSoft Meetup...Automating Business Process via MuleSoft Composer | Bangalore MuleSoft Meetup...
Automating Business Process via MuleSoft Composer | Bangalore MuleSoft Meetup...
 
Enhancing Worker Digital Experience: A Hands-on Workshop for Partners
Enhancing Worker Digital Experience: A Hands-on Workshop for PartnersEnhancing Worker Digital Experience: A Hands-on Workshop for Partners
Enhancing Worker Digital Experience: A Hands-on Workshop for Partners
 
The Codex of Business Writing Software for Real-World Solutions 2.pptx
The Codex of Business Writing Software for Real-World Solutions 2.pptxThe Codex of Business Writing Software for Real-World Solutions 2.pptx
The Codex of Business Writing Software for Real-World Solutions 2.pptx
 
Transforming Data Streams with Kafka Connect: An Introduction to Single Messa...
Transforming Data Streams with Kafka Connect: An Introduction to Single Messa...Transforming Data Streams with Kafka Connect: An Introduction to Single Messa...
Transforming Data Streams with Kafka Connect: An Introduction to Single Messa...
 
Tech-Forward - Achieving Business Readiness For Copilot in Microsoft 365
Tech-Forward - Achieving Business Readiness For Copilot in Microsoft 365Tech-Forward - Achieving Business Readiness For Copilot in Microsoft 365
Tech-Forward - Achieving Business Readiness For Copilot in Microsoft 365
 
Benefits Of Flutter Compared To Other Frameworks
Benefits Of Flutter Compared To Other FrameworksBenefits Of Flutter Compared To Other Frameworks
Benefits Of Flutter Compared To Other Frameworks
 
Azure Monitor & Application Insight to monitor Infrastructure & Application
Azure Monitor & Application Insight to monitor Infrastructure & ApplicationAzure Monitor & Application Insight to monitor Infrastructure & Application
Azure Monitor & Application Insight to monitor Infrastructure & Application
 
08448380779 Call Girls In Greater Kailash - I Women Seeking Men
08448380779 Call Girls In Greater Kailash - I Women Seeking Men08448380779 Call Girls In Greater Kailash - I Women Seeking Men
08448380779 Call Girls In Greater Kailash - I Women Seeking Men
 
IAC 2024 - IA Fast Track to Search Focused AI Solutions
IAC 2024 - IA Fast Track to Search Focused AI SolutionsIAC 2024 - IA Fast Track to Search Focused AI Solutions
IAC 2024 - IA Fast Track to Search Focused AI Solutions
 

MALAYSIA ETHICAL ISSUE: MRR2 FLYOVER CRACKS

  • 1. MALAYSIA ETHICAL ISSUE: MRR2 NUR ASYRAF BIN ABDUL RAHIM (K) MUHAMMAD FAIZAL BIN ABDULLAH NUR HASANAH BINTI SHAFEI
  • 2. OBJECTIVES • To give a better insight of the unethical issues that occurred in Malaysia 1 • To educate people about the importance of adopting 2 ethical conducts to prevent disastrous consequences GROUP 4 2
  • 3. OVERVIEW OF MRR2 [1] Built by Malaysian Public Works Department (JKR) To connect neighborhoods near Kuala Lumpur boundary Cost RM238.8 million Completed in 34 months (May 1999 to March 2002) GROUP 4 3
  • 4. OVERVIEW OF MRR2 • Construction of MRR2 was divided by 3 phase : [1] Gombak- Ampang- Kepong-Gombak Ampang Sri Petaling
  • 5. CONTROVERSIAL ISSUES First closure 8 August 2004 Second closure 4 February 2006 Third closure 3 August 2008 GROUP 4 5
  • 6. CONTROVERSIAL ISSUES Fear about the safety on the faulty Kepong Flyover 31 out of 33 pillars More than 7000 have obvious cracks cracks detected Investigations were carried out by government Anti-Corruption Agency investigated possible fraud [2] GROUP 4 6
  • 7. CONTROVERSIAL ISSUES Works Minister, Dato' Seri S Samy Vellu 10th August 2004 “Nobody can simply open their mouth and suggest it is design flaw. The question of design failure doesn't arise." PWD's consultant (Kohler & Seith) findings was dismissed GROUP 4 7
  • 8. CONTROVERSIAL ISSUES 12 August, 2004  The government of Malaysia then appointed British Halcrow Consultancy Ltd to study the cracks that have appeared on 31 of the 32 crossbeams since 2000. findings from Halcrow Consultants Ltd suggested design deficiencies and the improper anchoring were responsible for cracks and were finally accepted by the ministry The flyover  closed in August 2004 >>waterproofed the bridge to prevent further cracks >>reopened in December 2004 [2] GROUP 4 8
  • 9. CONTROVERSIAL ISSUES • On 4th Feb 2006, the Kepong Flyover was closed again after serious damages was confirmed I • Many complaints arrived about the damages on MRR2 II • Traffic jam has rose due to incompletion of MRR2 III • On 8 December 2006, the Kepong Flyover was reopened to light traffic [3] IV GROUP 4 9
  • 10. HIGHLIGHTS RM20mil to repair within 3 months 18/8/2004 Yet to determine the cause of cracks Deny the possibility of design fault 22/2/2006 Repair cost more than RM 40 milllion Repairs cost RM 40 mil  RM70mil 1/2/2007 Work Minister called to explain expenditure GROUP 4 10
  • 11. 3 August 2008 GROUP 4 11
  • 12. ETHICAL THEORY “Up to now, Malaysians still do not have a full and proper picture about the MRR2 flyover cracks. As two consultants, one from Australia by the contractor and a consultant from Germany appointed by the Public Works Department, have come out with different findings about the MRR2 flyover cracks, how could there be public confidence about the repair work undertaken in the past five days? “ Media Statement by Lim Kit Siang (14/8/2004) GROUP 4 12
  • 13. Utilitarianism  Definition: Balance between good and bad consequences of an action [4] GOOD: MRR2 brought travel within easy reach BAD: Controversial Issues. GROUP 4 13
  • 14. Right Ethics • Definition: People have the fundamental rights that other people have a duty to respect [4] GROUP 4 14
  • 15. Right Ethics The right to use the flyover safely Do not want to keep stuck in traffic jam as a result from the closure of the MRR2 Do not want to see the few well- connected companies or individuals profit at the public expense GROUP 4 15
  • 16. Duty Ethics • People have duties to protect Definition the rights of others • the duty to keep promises Fidelity - Contractors and engineers have failed to design and build the flyover in compliance with the contract GROUP 4 16
  • 17. Duty Ethics • the duty to recognize merit work minister does not take any action against the Justice irresponsible contractors and consultant – “Samy Vellu is acting as if he is the Minister for Bumi Hiway, the contractor for the MRR2, instead of being Minister for 25 million Malaysians.” GROUP 4 17
  • 18. Duty Ethics • the duty to improve Beneficence the conditions This expenses could be reduced if he appointed a reliable contractor to build the flyover Repairs cost Cause by improper planning RM40 mil to and poor cost estimation RM70mil and poor administrative of the Work Minister GROUP 4 18
  • 19. Virtue Ethics Irresponsibility Engineers did not fully supervise the project Minister did not give explanation of the RM70 million bill No actions taken towards original contractors GROUP 4 19
  • 20. Virtue Ethics Dishonestly Denied cracks were due to design flaw Did not build according to right specifications and designs GROUP 4 20
  • 21. Safety And Risk Definition: Ensure safety of public GROUP 4 21
  • 22. Safety And Risk • “ ‘space-age carbon-fibre pre-stressed trusses’ would be used to repair the Safety pillars, beams and girders of the design flyover: a tensile strength five times criteria stronger than that of steel” [5] • “Samy Vellu is giving the impression the repair work for the MRR2 flyover Risk-Benefit is very simple and Analysis straightforward, would not even require the three months mentioned by him.” [5] GROUP 4 22
  • 23. WHISTLE BLOWING MEANING: An act by an employee of informing the public or higher management of unethical or illegal behavior by an employer or supervisor OCCURS Need = There must be a clear and important harm that can be avoided by blowing the whistle Proximity = The whistleblower must be in a very clear position to report on the problem Capability = The whistleblower must have a reasonable chance of success in stopping the harmful activity Last Resort = Should be attempted only if there is no one else more capable and all other lines of action within the organization have been shut off GROUP 4 23
  • 24. ANALYSIS OF THE MRR2 CASE 1) AUTHORITYS INVOLVEMENT KKR (Kementerian Kerja Raya) Agency BOA (Lembaga Arkitek JKR (Jabatan Kerja Raya) Malaysia) CIDB (Lembaga BEM (Lembaga Jurutera Pembangunan Industri Malaysia) Pembinaan Malaysia) BQSM (Lembaga Juruukur Bahan MHA (Lembaga Malaysia) Lebuhraya Malaysia) GROUP 4 24
  • 25. ANALYSIS OF THE MRR2 CASE 2) PERSONAL VS BUSINESS CONFLICT MINISTERY MEDIA (strong parties) (news) HIGH COUNCIL BOARD ENGINEER (reputation) CONFLICT (responsibility) CONTRACTOR CITIZEN (work) (daily usage) Right and wrong ethics, Profitable and Loses, Rules and Regulations, Cost-Benefit Analysis GROUP 4 25
  • 26. ANALYSIS OF THE MRR2 CASE 3) AMONG RULES AND REGULATIONS 1) Design Standard 2) Maintenance Manual and 1) Engineers Act 1967 (Rev 2007) Guideline 2) Regulations 1990 (Rev 2003) (civil, electrical and 3) Code of Professional Conduct mechanical) 3) Guideline 1) Architect Act 1967 2) Architect Rules 1996 1) Contractor Code of Ethics 1) Standard Specifications for Building Works 2005 1) QS Act Revised 2002 2) QS Rule Amendment 2004 GROUP 4 26
  • 27. CONCLUSION 1) CORE CODE OF ETHICS REFERRED FROM VARIES CODE OF ETHICS A Professional shall at all times hold paramount the safety, health and welfare of the public A Professional shall undertake assignments only if he is qualified by education and experience in the specific technical fields in which he is involved A Professional shall issue public statements only in an objective and truthful manner A Professional shall act for each employer or clients as faithful agent or trustee A Professional shall conduct himself honourably, responsibly, ethically and lawfully so as to enhance the honour, reputation and usefulness of the profession GROUP 4 27
  • 28. CONCLUSION 2) ACTION WHICH SUPPOSE TO BE AVOIDED Bribery taken Miscalculation Tragedy Breach of contract Doesn’t follow specification Lack communication link Bad construction Lack team work Unethical action taken Bad media coverage Burden the country Burden the citizen Fired employee Accusing responsibility GROUP 4 28
  • 29. REFERENCES [1] Maverick, SM., Project Report Middle Ring Road 2. February, 2006 was retrieved from http://mavrkyprojectphoto.blogspot.com/2006/02/middle-ring- road-2.html [2] Brandon, H., Controversial Issues Middle Ring Road 2, was retrieved from http://en.wikipedia.org/wiki/Kuala_Lumpur_Middle_Ring_Road_2 [3] Maverick, SM., Risk, Health & Safety. 2006 was retrieved from http://constructionrisk.blogspot.com/ [4] Charles B. Fleddermann., Engineering Ethics (3rd Edition), Pearson Practice Hall , University of New Mexico, 2008 [5] Lim Kit Siang, Media Statement. August, 2004 was retrieved from http://www.dapmalaysia.org/all- archive/English/2004/aug04/lks/lks3158.htm [6] Main Portal for Kementerian Kerja Raya http://www.kkr.gov.my/ GROUP 4 29
  • 30. The End Q &A GROUP 4 30

Editor's Notes

  1. There 2 objectives of this presentation adalahuntukmemberigambaran yang lebihbaikataupnlebihjelastentangisu-isu yang tidakberetika yang berlakudi Malaysia Dan seretusnya mendidik orang ramai tentang kepentingan mengamalkan etika dalam menjalankan kerja ataupun tugas bagi mengelakkan bencana atau kesan buruk kepada sesiapa sahaja.
  2. MRR2 stands for Middle Ring Road two yang terletak di Kuala LumpurIa dibina oleh Jabatan Kerja Raya Malaysia (JKR) untuk mneghubungkan kawasan kejiranan yang berhampiran sempadan Kuala LumpuMRR2 meliputi sepanjang 4km dan kos RM238.8 jutadan Tempoh kontrak pembinaan mrr2 ialah 36 bulan dan namun pembinaan mrr2 siap lebih awal dari tempoh jangkaan iaitu dalam 34 bulan (Mei 1999 hingga Mac 2002)
  3. Controversial isumengenai MRR@ bermulaapabilaselapasduatahunia dibuka,mrr2 initerpaksaditutupkeranaberlakukeretakkan beam ataurasukpadatiang flyover dekatkepong. kali pertamaiaditutup pada-8 August 2004Kali kedua -4 February 2006Kali ketiga-3 August 2008
  4. Isu-isu kontroversi timbul apabila penduduk Kepong menyatakan kebimbangan mereka tentang keselamatan di Kepong Flyover yang dilaporkan rosak dua tahun selepas jejambat itu telah siap.31 daripada 33 tiang-tiang sokongan jejambat itu dilaporkan telah retak jelas.Manakala di sesetengah tiang itu pula jelas terdapat lebih daripada 7000 retak dikesan.Siasatan telah dijalankan oleh kerajaan untuk menyiasat perkara itu.Kontroversi ini terus berkembang apabila Badan Pencegah Rasuah (BPR) mula menyiasat penipuan yang mungkin telah berkalu dalam pembinaan MRR2 dan diperiksa sama ada MRR2 dibina mengikut spesifikasi
  5. Utilitarianismialah 1 tindakanygbaikjikabertujuanutkmemaksimumkankebajikanawam..Tidakmenekankankebajikanindividu, tetapikebajikan org ramai.Cthdlm MRR2..kewujudan MRR2 menjadikanperjalanankedestinasitertentumenjadilebihmudah.Tapidalammasa yang sama, pembinaan MRR2 initelahmenyebabkanControversial Issues.Derivation from utilitarianism: Cost benefit analysis.
  6. Right ethic- tindakan2 yang menghormatihakindividu yang baik.
  7. Rakyat mempunyaihakutkdigunakanhartamereka..sekiranyamelibatkanpengambilantanahpendudukutkpembinaan MRR2 ni, penduduk ken pikir MRR2 nibergunakepadaramai org- berkorbanuntukkepentinganpihak lain.
  8. Duty ethic- seseorang yang mempunyaitugasuntukmelindungihakorang lain
  9. Samyvellutakambiktindakanterhadap contractor dan consultant yang terbabit.
  10. The engineering codes of ethics show that engineer have a responsibility to society to produce product that are safe. Memanglatiadabenda yang 100% perfect, tapisbg engineer, should be make a products as safe as reasonable possible.
  11. Engineering design include multistep procedure, diperkenalkanoleh Wilcox [1990]: (6) Define the problem, generate several solutions, analyze each solution, test the solution, select best solution, implement the chosen solution.Risk benefit analysis- to help analyze the risk and to determine whether a project should be proceed. One must consider who take a risk and who reaps the benefits.
  12. The authority which involve in this case are (JKR), (CIDB), (BQSM), (BOA), (BEM) and (MHA)JKR- piling, concrete, structural``
  13. Private highway, government highway, faderal (jlnpersekutuan) – JKR selenggarajlnpersekutuansahaja.MRR2 – faderal highway.Private- bayartol.. (sebabkosmantainancedilakukanolehpihakswasta la, bukanpihakkerajaan).