SlideShare a Scribd company logo
Construction Failure
Case study : Skyline Plaza Collapse
Center for Environmental Planning & Technology
Prepared By :
Janak Shah
(PT401914)
Guided By :
Prof. R. J. Shah
Contents
• Literature Review
• Detailed Case Study
• Summary
• Lessons Learnt
2
JANAK SHAH (PT-401914)
Skyline Plaza Failure
Literature Review
• Formwork
• Shoring
• Reshoring
• Flat Plate
• Punching Shear Failure
• Progressive collapse
3
JANAK SHAH (PT-401914)
Skyline Plaza Failure
Formwork
• Formwork is the temporary structure which moulds concrete
into the desired shape, and holds it in the correct position
until it is able to support the loads imposed upon it.
• Formwork and its supports (falsework) is a structural system
and must be designed and built accordingly. The actions
(loads) on it may be temporary but they can be extremely
large.
• It is a temporary structure that supports its own weight and
that of freshly placed concrete as well as construction live
loads including material, equipment and workmen.
4
JANAK SHAH (PT-401914)
Skyline Plaza Failure
Requirements for formwork
Property Purpose
Strength Carry imposed loads.
Stiffness Maintain specified shape and avoid
distortion of concrete elements.
Accuracy •Ensure shape and size of concrete
elements.
•Ensure specified cover to reinforcement.
Watertightness Avoid grout loss and subsequent
honeycombing of the concrete.
Robustness Enable re-use.
Ease of stripping Avoid damage to concrete surfaces.
Standardisation Promote economy.
Safety Ensure a safe working environment.
5
JANAK SHAH (PT-401914)
Skyline Plaza Failure
Shores
Mudsill
Wedges
Bracing
Joist
Sheathing
Stringer
Fig 1 Typical elevated flat-slab formwork elements. (From Hurd, M.K., Formwork for Concrete, 7th ed., SP-4,
American Concrete Institute, Farmington Hills, MI, 2005.) 6
JANAK SHAH (PT-401914)
Skyline Plaza Failure
Fig 3 Beam form and supports
Fig 2 Column forms
7
JANAK SHAH (PT-401914)
Skyline Plaza Failure
Shoring
• Vertical or inclined support members designed to carry the
weight of the formwork, concrete, and construction loads
above.
8
JANAK SHAH (PT-401914)
Skyline Plaza Failure
Shoring
Fig 4
9
JANAK SHAH (PT-401914)
Skyline Plaza Failure
Reshoring
• Reshoring systems involve the removal of a section of the
formwork and support structure. With proper control and
good supervision, these systems can give acceptable results.
Props must be replaced in the original pattern and not
overtightened to avoid causing undesirable stresses in the
concrete.
10
JANAK SHAH (PT-401914)
Skyline Plaza Failure
Reshoring
Fig 5 PHASE 1: PLACEMENT OF CONCRETE Fig 6 PHASE 2: REMOVAL OF SHORES
11
JANAK SHAH (PT-401914)
Skyline Plaza Failure
Reshoring
Fig 7 PHASE 3: REMOVAL OF LOWER LEVEL OF SHORES Fig 8 PHASE 4: INSTALLATION OF RESHORES
12
JANAK SHAH (PT-401914)
Skyline Plaza Failure
Flat plates
• Flat plates are of uniform thickness throughout without drop
panels or column capitals.
• Flatplate floors are widely used in apartments because the
underside of the slab is flat and hence can be used as the
ceiling of the room below.
13
JANAK SHAH (PT-401914)
Skyline Plaza Failure
• Of equal importance, the forming for a flat plate is generally
cheaper than that for flat slabs with drop panels .
Fig 9
14
JANAK SHAH (PT-401914)
Skyline Plaza Failure
Fig 10 Reinforced concrete flat plate system, Eugene, USA
15
JANAK SHAH (PT-401914)
Skyline Plaza Failure
Fig 11 A reinforced concrete building with flat plate system under construction, Kenya
16
JANAK SHAH (PT-401914)
Skyline Plaza Failure
Punching Shear
• Punching shear failure is caused by the vertical shear and
unbalanced moment borne by the slab-column connection,
which makes the flat-slab connections a weak link in the
whole flat-slab structure, and then leading to serious damage
or even collapse.
17
JANAK SHAH (PT-401914)
Skyline Plaza Failure
• In a slab system with a concentrated load or at a slab column
connection, the loaded area is not actually pushed through
the slab as shown in Fig 12.
• Punching shear failures arise from the formation of diagonal
tension cracks around the loaded area, which result in a
conical failure surface as illustrated in Fig 13.
Fig 12 Misconception of Punching Shear Failure Fig 13Correct Representation of Punching Shear Failure
18
JANAK SHAH (PT-401914)
Skyline Plaza Failure
Laboratory Studies
Fig 14 Exterior connection Fig 15 Interior connection
Photo: Hwang and Moehle, ACI SJ, March-April 2000 19
JANAK SHAH (PT-401914)
Skyline Plaza Failure
Fig 16 Building Collapsed due to punching failure
20
JANAK SHAH (PT-401914)
Skyline Plaza Failure
Progressive collapse
• ‘Progressive collapse denotes an extensive structural failure
initiated by local structural damage, or a chain reaction of
failures following damage to a relatively small portion of a
structure. This can be also characterized by the loss of load-
carrying capacity of a relatively small portion of a structure
due to an abnormal load which, in turn, triggers a cascade of
failures affecting a major portion of the structure.’
21
JANAK SHAH (PT-401914)
Skyline Plaza Failure
Chain of Events
• Progressive collapse occurs when an initiating event leads to
damage to part of the structure by which this part looses its
load bearing capacity.
• As a consequence the loading pattern of the structure is
changed leading to an overloading of other structural
elements which are thereby also damaged.
• This process continues until the whole structure collapses or a
greater part of it.
22
JANAK SHAH (PT-401914)
Skyline Plaza Failure
Historical Perspective to Progressive
Collapse
Fig 17 A time line of cases associated with progressive collapse.
23
JANAK SHAH (PT-401914)
Skyline Plaza Failure
Progressive collapse ,
Skyline Plaza at Bailey's Crossroads,
National Archives
Fig 18
24
JANAK SHAH (PT-401914)
Skyline Plaza Failure
Skyline Plaza Collapse in
Fairfax County, Virginia
Date of Collapse : March 2, 1973
25
JANAK SHAH (PT-401914)
Skyline Plaza Failure
Background
• The Skyline center complex located near Bailey’s Crossroad, Fairfax
County, Virginia.
• It was planned to contain
1. Eight apartment buildings (namely A-1 to A-8),
2. Six office buildings,
3. A hotel, and
4. A shopping center.
Two apartment buildings which had been completed are shown in
figure 19 .
A pair of apartment buildings and adjoining parking and lobby
structure were under construction
26
JANAK SHAH (PT-401914)
Skyline Plaza Failure
Fig 19 Appearance of completed apartment
27
JANAK SHAH (PT-401914)
Skyline Plaza Failure
Description of the Structure
• The three structures under construction were designed under
the Fairfax County Building Code Ordinance which
incorporates by reference the provision of ACI 318-63.
Building A-4
• Reinforced concrete flat plat construction
• Supported on 4-ft thick foundation mat
• Completed structure was to have 26 stories of apartments, a
penthouse and a four story basement(B-1, B-2, B-3, B-4)
28
JANAK SHAH (PT-401914)
Skyline Plaza Failure
• The typical story height from the from the first story up was 9
ft 0 in from top of slab to top of slab. Floor slab were 8 inches
thick.
• Total basement height of about 40 ft as measured from top of
the foundation mat(level B-4) to the top of the first floor slab.
• The plan view without parking garage plan shown in fig. is
that of 22nd storey and is typical for the 1st through 26th stories
in the column layout.
• There are eight shear walls in the structure. These are
designated as A through H shown in fig 20.
• A ½ inch expansion joint separated the building into two parts
at grid line H.
29
JANAK SHAH (PT-401914)
Skyline Plaza Failure
Fig 20
30
JANAK SHAH (PT-401914)
Skyline Plaza Failure
N
Fig 21 Aerial View of Construction at 11 am, March 2, 1973 (Before Collapse)
31
JANAK SHAH (PT-401914)
Skyline Plaza Failure
Design Strength of Concrete
Concrete Design Strength (psi)
Floor Base - 7 7 - 17 17 - Top
Columns 5000 (34.5MPa) 4000 (27.6MPa) 3000 (20.7 MPa)
Slabs 3000 (20.7 MPa) 3000 (20.7 MPa) 3000 (20.7 MPa)
Table 1
32
JANAK SHAH (PT-401914)
Skyline Plaza Failure
The Collapse
• The collapse occurred at around 2:30 pm on March 2, 1973,
while under construction while the 24th floor slab was being
casted.
• Shortly after lunch, some workers observed slab deflections of
approximately 150–600 mm (6 in. to 2 ft) for both the 23rd
floor slab and the freshly placed 24th floor slab.
• The freshly placed section of the 24th floor slab then fell onto
the 23rd floor slab, starting a collapse that continued all the
way to the foundation.
• The building’s collapse removed the edge support from the
parking garage, and falling debris triggered the failure of the
garage.
33
JANAK SHAH (PT-401914)
Skyline Plaza Failure
General appearance of
building A-4 as
viewed from the southeast.
Fig 22
34
JANAK SHAH (PT-401914)
Skyline Plaza Failure
•A partial view of the north face of
building A-4 is shown in figure.
•A number of columns and floors are
identified. The collapse extended
between shear wall H and column 33
on the south face a distance of about
65 ft (refer to building plan).
•On the north face the collapse
extended between columns 12 and
17, a distance of about 104 ft.
Fig 23
35
JANAK SHAH (PT-401914)
Skyline Plaza Failure
Closeup view of the top of the east end
of the failure zone, looking south.
Fig 24
36
JANAK SHAH (PT-401914)
Skyline Plaza Failure
Closeup view near the midheight
of the east end of the failure zone,
looking south
Fig 25 37
JANAK SHAH (PT-401914)
Skyline Plaza Failure
General view of building A-4 as seen
looking southwest
Fig 26
38
JANAK SHAH (PT-401914)
Skyline Plaza Failure
The Collapse
• Once the section of the apartment building collapsed, the
failure propagated horizontally through the attached parking
garage.
• It resulted in the death of 14 construction workers and the
injury to 34 others.
• Of the workers killed, ten were in the tower and four in the
garage.
39
JANAK SHAH (PT-401914)
Skyline Plaza Failure
Investigation of failure
• The collapse of the Skyline Plaza apartment building A-4 has
been studied by using information contained in case records
of the Occupational Safety and Health administration (OSHA),
U.S. Department of Labor and obtained from on-site
inspections by investigators from the National Bureau of
Standards(NBS)
40
JANAK SHAH (PT-401914)
Skyline Plaza Failure
Formwork
Fig 27 General appearance of building A-4 as viewed from the southeast.
41
JANAK SHAH (PT-401914)
Skyline Plaza Failure
Formwork
• Figure 27 shows the locations of the formwork on March 2,
shortly after the collapse. Full formwork was in place on the
24th and 23rd stories in sections 1 and 2. Some formwork may
be seen on the 22nd story in sections 2 and 3.
• Full formwork was also in place under section 4 on the 22nd
and 23rd stories. No reshoring can be seen under section 4
below the 22nd floor in figure 27 .
42
JANAK SHAH (PT-401914)
Skyline Plaza Failure
Formwork, Shoring and Reshoring
• Formwork sheets submitted to Fairfax County contained no
mention of lateral bracing for the form system. However, a limited
amount of bracing may be seen in figure 28.
• OSHA, regulations (ANSI-A10.9, Sections 6.3.2 and 8.1.5) require a
lateral bracing system capable of resisting a lateral force of at least
2 percent of the dead load of the slab.
• Stringers were erected with a shore under each end wherein
stringer were inserted in a basket like socket connected to the
shore.
• Diagonal lateral bracing was installed after every fourth shore at
about 16 ft intervals.
• Joists were placed over stringers at 16 inch intervals over which
plywood sheathing was provided.
• Stringers and Joists were usually 16 ft long although some were as
short as 6 to 8 ft.
43
JANAK SHAH (PT-401914)
Skyline Plaza Failure
The formwork on the 24th story is shown in figure. Several columns
have been identified for reference.
Fig 28
44
JANAK SHAH (PT-401914)
Skyline Plaza Failure
Fig 29 A schematic of formwork is shown in figure as derived from OSHA case records
45
JANAK SHAH (PT-401914)
Skyline Plaza Failure
Formwork, Shoring and Reshoring
• During the NBS site inspection. a considerable portion of the
lumber use for the remaining forms in the 24th story was
found to be in poor condition or out of plumb.
The photograph illustrates a shore
which is out of plumb and has a
vertical crack near the top. OSHA
regulations (ANSI-A10.9, sections
8.1.24 and 8.1.25) require
correction of this condition prior to
placing concrete (which was not yet
placed on these forms).
Fig 30
46
JANAK SHAH (PT-401914)
Skyline Plaza Failure
• One concrete finisher working near the stair well (around
columns 65 and 66) indicated that a large deflection was seen
in the middle of section 3.
• However. the middle of section 3 is about midway between
columns 67 and 85.
47
JANAK SHAH (PT-401914)
Skyline Plaza Failure
•The formwork on the 23rd story is shown in figure 2.20. These forms supported the
24th floor which had been cast on February 28 (section 1) and March 1(section 2).
•Note the number of shores out of plumb.
Fig 31
48
JANAK SHAH (PT-401914)
Skyline Plaza Failure
Fig 32 The method of attaching the brace to the floor is shown in figure
49
JANAK SHAH (PT-401914)
Skyline Plaza Failure
• As in the case of the 24th story. the 23rd story lumber which
was apparently damaged was reused.
• As in the case of the 24th story. OSHA regulations (ANSI-A10.9,
sections 8.1.24 and 8.1.25) required correction of these
conditions prior to placing concrete.
Fig 33 50
JANAK SHAH (PT-401914)
Skyline Plaza Failure
•Reshoring in section 2 of the 22nd story as of March 6 is shown in figure.
•There is conflict in their statements, a number of workmen that escaped the
building by way of the stairs in section 4 have indicated that the 22nd story was
either partially or entirely stripped in section 3.
Fig 34
51
JANAK SHAH (PT-401914)
Skyline Plaza Failure
• Photographs taken right after the collapse showed that while
full shoring remained on the 23rd and 24th stories, it had
nearly all been removed from the 22nd story in sections 1 and
2 but remained in section 4.
• According to OSHA regulations, forms are required to be in
place for a minimum of 10 days with temperatures greater
than 50 degrees F for spans longer than 20'-0“ (ANSI A10.9,
Section 6.4.8).
• The engineer’s structural drawings required two full stories of
shoring and one story of reshoring while a concrete slab was
being cast.
52
JANAK SHAH (PT-401914)
Skyline Plaza Failure
Fig 35 Estimated location of forms and reshores at the time of the collapse.
53
JANAK SHAH (PT-401914)
Skyline Plaza Failure
• The statements of one worker gave the investigators a good
idea of the state of the forms at the time of the collapse.
• “One workman indicated that, at the time of the incident, he
was placing reshores in section 3 of the 21st story and that
some reshores were present when he started working. Prior
to the incident, all the reshores fell out (except those in the
balcony areas). This is consistent with what could occur if the
forms had been removed in the story above.”
• If the shoring had been removed in the 22nd floor, the 22nd
floor slab would have been relieved of its previous loads. With
less loading, the deflection would have decreased in the slab
causing the reshores on the 21st floor to fall out.
54
JANAK SHAH (PT-401914)
Skyline Plaza Failure
Concrete Strength
• Results of standard ASTM C39 concrete cylinder tests showed
adequate strength at 7 and 28 days.
• However, these were laboratory tests, with cylinders stored at
a controlled temperature. Particularly in cold weather,
laboratory tests do not correspond to the strength of the
concrete in place in a structure.
• OSHA regulations required field cured cylinders, stored at the
same temperature as the structure, to verify the strength of
the structure before removing shores and formwork
55
JANAK SHAH (PT-401914)
Skyline Plaza Failure
Structural investigation of Failure
• The evaluation of the capacity of structural elements was
based on the Provisions of the ACI 318-71 Code and on
procedures from published analytical and experimental
research.
• The three dimensional elastic analysis was performed using
the finite element analysis program known by the acronym
SAP.
56
JANAK SHAH (PT-401914)
Skyline Plaza Failure
• Each of the three finite element analyses had a particular
purpose:
• Case 1: Some of the employee statements indicated that the
22nd story forms were entirely removed at the time of
collapse. (Complete removal of shoring)
• Case 2: The concrete to have attained its full 28-day design
strength of 3000 psi.
• Case 3: Some of the employee statements indicated that
removal of shoring under the 23rd-floor slab in the central
corridor area of the building was in progress on the day of the
collapse.(Partial removal of shoring)
57
JANAK SHAH (PT-401914)
Skyline Plaza Failure
• Investigation to flexure failure:
• Upon Examination of all the probable conditions prior to the
collapse, It is concluded that the initial mode of failure of
either the 22nd or the 23rd floor slab was not flexural.
58
JANAK SHAH (PT-401914)
Skyline Plaza Failure
Investigation to Shear Failure
Fig 36 Summary of shear stresses in the 23rd story floor slab.
59
JANAK SHAH (PT-401914)
Skyline Plaza Failure
Investigation to Shear Failure
• Upon examination of all the probable conditions prior to the
collapse, it is concluded that the initial shear mode of failure
of the 23rd story floor slab resulting from partial or complete
removal of shoring prior to the incident was a major
contributing factor to the collapse.
60
JANAK SHAH (PT-401914)
Skyline Plaza Failure
Probable mode of failure
• The most likely mode of collapse has been determined to be a
shear failure around columns 67, 68, 83, or 84.
• The premature removal of forms supporting the 23rd story slab
when the concrete of that slab had a relatively low strength
produced shear stresses that were in excess of the concrete
capacity at the time of the incident.
• The collapse is believed to have started with shear around columns
67,68, 83, or 84. The loss of support from anyone of these columns
would lead to overstressing of the remaining columns.
• The accumulation and impact of debris from the 23rd and 24th
floor slab would have overloaded the 22nd floor slab and induced
progressive collapse of successive floors to the ground.
61
JANAK SHAH (PT-401914)
Skyline Plaza Failure
Contribution of Crane
• There is no indication that the crane was a contributing factor
to the beginning of collapse in building A-4. No witness
statements indicated that the crane moved prior to or during
the initial sagging of the 23rd and 24th floors. The crane
supports on the 14th and 16th floors are far enough away
from the initiation of failure to preclude the crane as a cause.
However, the crane probably became a driving force in the
collapse once its support was lost.
62
JANAK SHAH (PT-401914)
Skyline Plaza Failure
Summary
• An analysis of the 23rd-floor slab indicates that its most likely
mode of failure was in shear around one or more columns in
section 3 of the floor slab. The strength of the 23rd-floor slab
on the day of collapse has been found to be of a magnitude
that complete or partial removal of shoring underneath the
slab would have produced a shear failure in the slab. The
weight of debris resulted in failure in the slabs below and
carried through the height of the building.
63
JANAK SHAH (PT-401914)
Skyline Plaza Failure
Non-Compliance with OSHA
Regulation
• Shoring in section 3 of 22nd story:
The architect‘s specification required "In all cases two floors
shall be fully shored."The removal of the 23rd story forms left
only one story of formwork in place under the recently
poured 24th floor.
• Premature removal of 22nd story form:
The forms removed on the 22nd story were in an area with
spans exceeding 20 ft and therefore, should have been in
place for 10 days of temperatures exceeding 50°F.
64
JANAK SHAH (PT-401914)
Skyline Plaza Failure
Non-Compliance with OSHA
Regulation
• Lateral bracing:
Minimum values of 100 pounds per foot of floor edge or 2
percent of the total dead load of the floor, whichever is
greater, is required. No evidence has been found which
indicates that lateral load was considered in the design of
forms. The lateral bracing provided would not provide this
resistance.
• Shoring out of plumb
• Damaged Shoring
• Inspection
65
JANAK SHAH (PT-401914)
Skyline Plaza Failure
Lessons Learnt
• The contractor should be responsible for preparing formwork
drawings, including shores and reshores;
• The contractor should prepare a detailed concrete testing plan for
stripping forms, including cylinder tests;
• Inspectors and other quality control agencies should verify that the
contractor performs the previous two items;
• The Engineer of Record (EOR) should make sure he/she provides
the contractor with all necessary design load data and other unique
project information;
• Uncontrolled acceleration of formwork removal may cause a total
or partial collapse; and
• Continuous top and bottom slab reinforcement is necessary around
the columns. Continuous reinforcement provides overall ductility.
66
JANAK SHAH (PT-401914)
Skyline Plaza Failure
References
• Edgar V. L. and S. George Fattal, “Investigation of the Skyline Plaza Collapse
in Fairfax County, Virginia”, U.S.Department of Commerce, NBS, February
1977.
• Jeffrey S., Norbert D. and Paul A. Bosela, “Another Look at the Collapse of
Skyline Plaza at Bailey’s Crossroads, Virginia”, Cleveland State University,
June 2013.
• N.subramanian, “Alternative punching Shear reinforcement for RC flat
slabs”,The Indian concrete Journal, January 2014.
• K. Micallef, J. Sagaseta, M. Fernández Ruiz, A. Muttoni, “Assessing
punching shear failure in reinforced concrete flat slabs subjected to
localised impact loading”, International Journal of Impact Engineering,27-
February 2014.
• Devin K. Harris, “Characterization of punching shear capacity of thin UHPC
PLATES”, December 2004.
67
JANAK SHAH (PT-401914)
Skyline Plaza Failure
References
• M. Smith, “Progressive collapse assessment , non-linear behaviour of
concrete structures in damaged state”, January 26th, 2007.
• Alkarani, Ravindra. R, “Evaluation of punching shear in flat slabs”,
International Journal of Research in Engineering and Technology,
November 2013.
• Prof. Kamran M. , “Temporary Structures : Shoring, scaffolding, and
underpinning”.
• David W. Johnston, P.E., Ph.D. , “Design and Construction of Concrete
Formwork”, Concrete Construction Engineering Handbook.
• “Guide to Concrete Construction”, Cement & Concrete Association of New
Zealand (CCANZ).
• Basher Alamin, “Analysis of Construction Loads on Concrete Formwork”,
August 1999.
68
JANAK SHAH (PT-401914)
Skyline Plaza Failure
69
JANAK SHAH (PT-401914)
Skyline Plaza Failure

More Related Content

Similar to Skylineplazacollapse.pptx

TECHNOLOGY RESEARCH FOR MAIN ARCH ON STONE ARCH BRIDGE REINFORCEMENT ENGINEER...
TECHNOLOGY RESEARCH FOR MAIN ARCH ON STONE ARCH BRIDGE REINFORCEMENT ENGINEER...TECHNOLOGY RESEARCH FOR MAIN ARCH ON STONE ARCH BRIDGE REINFORCEMENT ENGINEER...
TECHNOLOGY RESEARCH FOR MAIN ARCH ON STONE ARCH BRIDGE REINFORCEMENT ENGINEER...
International Journal of Technical Research & Application
 
IRJET- Progressive Collapse Resistance of Flat Slab Building
IRJET- Progressive Collapse Resistance of Flat Slab BuildingIRJET- Progressive Collapse Resistance of Flat Slab Building
IRJET- Progressive Collapse Resistance of Flat Slab Building
IRJET Journal
 
Site visit
Site visitSite visit
Site visit
kohwenqi
 
Progressive Collapse Analysis of RC Structures
Progressive Collapse Analysis of RC StructuresProgressive Collapse Analysis of RC Structures
Progressive Collapse Analysis of RC Structures
IRJET Journal
 
Dynamic Performance Analysis of Outrigger and Outrigger with Belt Truss Syste...
Dynamic Performance Analysis of Outrigger and Outrigger with Belt Truss Syste...Dynamic Performance Analysis of Outrigger and Outrigger with Belt Truss Syste...
Dynamic Performance Analysis of Outrigger and Outrigger with Belt Truss Syste...
IRJET Journal
 
An analysis of multi-storey building with floating and non-floating column un...
An analysis of multi-storey building with floating and non-floating column un...An analysis of multi-storey building with floating and non-floating column un...
An analysis of multi-storey building with floating and non-floating column un...
IRJET Journal
 
Elfejji Final Paper
Elfejji Final PaperElfejji Final Paper
Elfejji Final Paper
Jalila Elfejji
 
v3 FINAL FINAL PDF SOLAR PANEL PROJECT BY MYLES MARCUS
v3 FINAL FINAL PDF SOLAR PANEL PROJECT BY MYLES MARCUSv3 FINAL FINAL PDF SOLAR PANEL PROJECT BY MYLES MARCUS
v3 FINAL FINAL PDF SOLAR PANEL PROJECT BY MYLES MARCUS
Myles Marcus
 
IRJET- Seismic Analysis of G+6 Frame Building using ETABS
IRJET-  	  Seismic Analysis of G+6 Frame Building using ETABSIRJET-  	  Seismic Analysis of G+6 Frame Building using ETABS
IRJET- Seismic Analysis of G+6 Frame Building using ETABS
IRJET Journal
 
Building Structure Project 1
Building Structure Project 1Building Structure Project 1
Building Structure Project 1
AlexSiv03
 
civil_engg_thesis_F inal presentation_mirzaShasan
civil_engg_thesis_F inal presentation_mirzaShasancivil_engg_thesis_F inal presentation_mirzaShasan
civil_engg_thesis_F inal presentation_mirzaShasan
Engr Mirza S Hasan
 

Similar to Skylineplazacollapse.pptx (11)

TECHNOLOGY RESEARCH FOR MAIN ARCH ON STONE ARCH BRIDGE REINFORCEMENT ENGINEER...
TECHNOLOGY RESEARCH FOR MAIN ARCH ON STONE ARCH BRIDGE REINFORCEMENT ENGINEER...TECHNOLOGY RESEARCH FOR MAIN ARCH ON STONE ARCH BRIDGE REINFORCEMENT ENGINEER...
TECHNOLOGY RESEARCH FOR MAIN ARCH ON STONE ARCH BRIDGE REINFORCEMENT ENGINEER...
 
IRJET- Progressive Collapse Resistance of Flat Slab Building
IRJET- Progressive Collapse Resistance of Flat Slab BuildingIRJET- Progressive Collapse Resistance of Flat Slab Building
IRJET- Progressive Collapse Resistance of Flat Slab Building
 
Site visit
Site visitSite visit
Site visit
 
Progressive Collapse Analysis of RC Structures
Progressive Collapse Analysis of RC StructuresProgressive Collapse Analysis of RC Structures
Progressive Collapse Analysis of RC Structures
 
Dynamic Performance Analysis of Outrigger and Outrigger with Belt Truss Syste...
Dynamic Performance Analysis of Outrigger and Outrigger with Belt Truss Syste...Dynamic Performance Analysis of Outrigger and Outrigger with Belt Truss Syste...
Dynamic Performance Analysis of Outrigger and Outrigger with Belt Truss Syste...
 
An analysis of multi-storey building with floating and non-floating column un...
An analysis of multi-storey building with floating and non-floating column un...An analysis of multi-storey building with floating and non-floating column un...
An analysis of multi-storey building with floating and non-floating column un...
 
Elfejji Final Paper
Elfejji Final PaperElfejji Final Paper
Elfejji Final Paper
 
v3 FINAL FINAL PDF SOLAR PANEL PROJECT BY MYLES MARCUS
v3 FINAL FINAL PDF SOLAR PANEL PROJECT BY MYLES MARCUSv3 FINAL FINAL PDF SOLAR PANEL PROJECT BY MYLES MARCUS
v3 FINAL FINAL PDF SOLAR PANEL PROJECT BY MYLES MARCUS
 
IRJET- Seismic Analysis of G+6 Frame Building using ETABS
IRJET-  	  Seismic Analysis of G+6 Frame Building using ETABSIRJET-  	  Seismic Analysis of G+6 Frame Building using ETABS
IRJET- Seismic Analysis of G+6 Frame Building using ETABS
 
Building Structure Project 1
Building Structure Project 1Building Structure Project 1
Building Structure Project 1
 
civil_engg_thesis_F inal presentation_mirzaShasan
civil_engg_thesis_F inal presentation_mirzaShasancivil_engg_thesis_F inal presentation_mirzaShasan
civil_engg_thesis_F inal presentation_mirzaShasan
 

Recently uploaded

LLM Fine Tuning with QLoRA Cassandra Lunch 4, presented by Anant
LLM Fine Tuning with QLoRA Cassandra Lunch 4, presented by AnantLLM Fine Tuning with QLoRA Cassandra Lunch 4, presented by Anant
LLM Fine Tuning with QLoRA Cassandra Lunch 4, presented by Anant
Anant Corporation
 
Seminar on Distillation study-mafia.pptx
Seminar on Distillation study-mafia.pptxSeminar on Distillation study-mafia.pptx
Seminar on Distillation study-mafia.pptx
Madan Karki
 
官方认证美国密歇根州立大学毕业证学位证书原版一模一样
官方认证美国密歇根州立大学毕业证学位证书原版一模一样官方认证美国密歇根州立大学毕业证学位证书原版一模一样
官方认证美国密歇根州立大学毕业证学位证书原版一模一样
171ticu
 
Null Bangalore | Pentesters Approach to AWS IAM
Null Bangalore | Pentesters Approach to AWS IAMNull Bangalore | Pentesters Approach to AWS IAM
Null Bangalore | Pentesters Approach to AWS IAM
Divyanshu
 
Generative AI leverages algorithms to create various forms of content
Generative AI leverages algorithms to create various forms of contentGenerative AI leverages algorithms to create various forms of content
Generative AI leverages algorithms to create various forms of content
Hitesh Mohapatra
 
An improved modulation technique suitable for a three level flying capacitor ...
An improved modulation technique suitable for a three level flying capacitor ...An improved modulation technique suitable for a three level flying capacitor ...
An improved modulation technique suitable for a three level flying capacitor ...
IJECEIAES
 
哪里办理(csu毕业证书)查尔斯特大学毕业证硕士学历原版一模一样
哪里办理(csu毕业证书)查尔斯特大学毕业证硕士学历原版一模一样哪里办理(csu毕业证书)查尔斯特大学毕业证硕士学历原版一模一样
哪里办理(csu毕业证书)查尔斯特大学毕业证硕士学历原版一模一样
insn4465
 
Redefining brain tumor segmentation: a cutting-edge convolutional neural netw...
Redefining brain tumor segmentation: a cutting-edge convolutional neural netw...Redefining brain tumor segmentation: a cutting-edge convolutional neural netw...
Redefining brain tumor segmentation: a cutting-edge convolutional neural netw...
IJECEIAES
 
Rainfall intensity duration frequency curve statistical analysis and modeling...
Rainfall intensity duration frequency curve statistical analysis and modeling...Rainfall intensity duration frequency curve statistical analysis and modeling...
Rainfall intensity duration frequency curve statistical analysis and modeling...
bijceesjournal
 
Data Driven Maintenance | UReason Webinar
Data Driven Maintenance | UReason WebinarData Driven Maintenance | UReason Webinar
Data Driven Maintenance | UReason Webinar
UReason
 
Unit-III-ELECTROCHEMICAL STORAGE DEVICES.ppt
Unit-III-ELECTROCHEMICAL STORAGE DEVICES.pptUnit-III-ELECTROCHEMICAL STORAGE DEVICES.ppt
Unit-III-ELECTROCHEMICAL STORAGE DEVICES.ppt
KrishnaveniKrishnara1
 
Data Control Language.pptx Data Control Language.pptx
Data Control Language.pptx Data Control Language.pptxData Control Language.pptx Data Control Language.pptx
Data Control Language.pptx Data Control Language.pptx
ramrag33
 
Optimizing Gradle Builds - Gradle DPE Tour Berlin 2024
Optimizing Gradle Builds - Gradle DPE Tour Berlin 2024Optimizing Gradle Builds - Gradle DPE Tour Berlin 2024
Optimizing Gradle Builds - Gradle DPE Tour Berlin 2024
Sinan KOZAK
 
Applications of artificial Intelligence in Mechanical Engineering.pdf
Applications of artificial Intelligence in Mechanical Engineering.pdfApplications of artificial Intelligence in Mechanical Engineering.pdf
Applications of artificial Intelligence in Mechanical Engineering.pdf
Atif Razi
 
一比一原版(CalArts毕业证)加利福尼亚艺术学院毕业证如何办理
一比一原版(CalArts毕业证)加利福尼亚艺术学院毕业证如何办理一比一原版(CalArts毕业证)加利福尼亚艺术学院毕业证如何办理
一比一原版(CalArts毕业证)加利福尼亚艺术学院毕业证如何办理
ecqow
 
Mechanical Engineering on AAI Summer Training Report-003.pdf
Mechanical Engineering on AAI Summer Training Report-003.pdfMechanical Engineering on AAI Summer Training Report-003.pdf
Mechanical Engineering on AAI Summer Training Report-003.pdf
21UME003TUSHARDEB
 
Properties Railway Sleepers and Test.pptx
Properties Railway Sleepers and Test.pptxProperties Railway Sleepers and Test.pptx
Properties Railway Sleepers and Test.pptx
MDSABBIROJJAMANPAYEL
 
An Introduction to the Compiler Designss
An Introduction to the Compiler DesignssAn Introduction to the Compiler Designss
An Introduction to the Compiler Designss
ElakkiaU
 
Welding Metallurgy Ferrous Materials.pdf
Welding Metallurgy Ferrous Materials.pdfWelding Metallurgy Ferrous Materials.pdf
Welding Metallurgy Ferrous Materials.pdf
AjmalKhan50578
 
Material for memory and display system h
Material for memory and display system hMaterial for memory and display system h
Material for memory and display system h
gowrishankartb2005
 

Recently uploaded (20)

LLM Fine Tuning with QLoRA Cassandra Lunch 4, presented by Anant
LLM Fine Tuning with QLoRA Cassandra Lunch 4, presented by AnantLLM Fine Tuning with QLoRA Cassandra Lunch 4, presented by Anant
LLM Fine Tuning with QLoRA Cassandra Lunch 4, presented by Anant
 
Seminar on Distillation study-mafia.pptx
Seminar on Distillation study-mafia.pptxSeminar on Distillation study-mafia.pptx
Seminar on Distillation study-mafia.pptx
 
官方认证美国密歇根州立大学毕业证学位证书原版一模一样
官方认证美国密歇根州立大学毕业证学位证书原版一模一样官方认证美国密歇根州立大学毕业证学位证书原版一模一样
官方认证美国密歇根州立大学毕业证学位证书原版一模一样
 
Null Bangalore | Pentesters Approach to AWS IAM
Null Bangalore | Pentesters Approach to AWS IAMNull Bangalore | Pentesters Approach to AWS IAM
Null Bangalore | Pentesters Approach to AWS IAM
 
Generative AI leverages algorithms to create various forms of content
Generative AI leverages algorithms to create various forms of contentGenerative AI leverages algorithms to create various forms of content
Generative AI leverages algorithms to create various forms of content
 
An improved modulation technique suitable for a three level flying capacitor ...
An improved modulation technique suitable for a three level flying capacitor ...An improved modulation technique suitable for a three level flying capacitor ...
An improved modulation technique suitable for a three level flying capacitor ...
 
哪里办理(csu毕业证书)查尔斯特大学毕业证硕士学历原版一模一样
哪里办理(csu毕业证书)查尔斯特大学毕业证硕士学历原版一模一样哪里办理(csu毕业证书)查尔斯特大学毕业证硕士学历原版一模一样
哪里办理(csu毕业证书)查尔斯特大学毕业证硕士学历原版一模一样
 
Redefining brain tumor segmentation: a cutting-edge convolutional neural netw...
Redefining brain tumor segmentation: a cutting-edge convolutional neural netw...Redefining brain tumor segmentation: a cutting-edge convolutional neural netw...
Redefining brain tumor segmentation: a cutting-edge convolutional neural netw...
 
Rainfall intensity duration frequency curve statistical analysis and modeling...
Rainfall intensity duration frequency curve statistical analysis and modeling...Rainfall intensity duration frequency curve statistical analysis and modeling...
Rainfall intensity duration frequency curve statistical analysis and modeling...
 
Data Driven Maintenance | UReason Webinar
Data Driven Maintenance | UReason WebinarData Driven Maintenance | UReason Webinar
Data Driven Maintenance | UReason Webinar
 
Unit-III-ELECTROCHEMICAL STORAGE DEVICES.ppt
Unit-III-ELECTROCHEMICAL STORAGE DEVICES.pptUnit-III-ELECTROCHEMICAL STORAGE DEVICES.ppt
Unit-III-ELECTROCHEMICAL STORAGE DEVICES.ppt
 
Data Control Language.pptx Data Control Language.pptx
Data Control Language.pptx Data Control Language.pptxData Control Language.pptx Data Control Language.pptx
Data Control Language.pptx Data Control Language.pptx
 
Optimizing Gradle Builds - Gradle DPE Tour Berlin 2024
Optimizing Gradle Builds - Gradle DPE Tour Berlin 2024Optimizing Gradle Builds - Gradle DPE Tour Berlin 2024
Optimizing Gradle Builds - Gradle DPE Tour Berlin 2024
 
Applications of artificial Intelligence in Mechanical Engineering.pdf
Applications of artificial Intelligence in Mechanical Engineering.pdfApplications of artificial Intelligence in Mechanical Engineering.pdf
Applications of artificial Intelligence in Mechanical Engineering.pdf
 
一比一原版(CalArts毕业证)加利福尼亚艺术学院毕业证如何办理
一比一原版(CalArts毕业证)加利福尼亚艺术学院毕业证如何办理一比一原版(CalArts毕业证)加利福尼亚艺术学院毕业证如何办理
一比一原版(CalArts毕业证)加利福尼亚艺术学院毕业证如何办理
 
Mechanical Engineering on AAI Summer Training Report-003.pdf
Mechanical Engineering on AAI Summer Training Report-003.pdfMechanical Engineering on AAI Summer Training Report-003.pdf
Mechanical Engineering on AAI Summer Training Report-003.pdf
 
Properties Railway Sleepers and Test.pptx
Properties Railway Sleepers and Test.pptxProperties Railway Sleepers and Test.pptx
Properties Railway Sleepers and Test.pptx
 
An Introduction to the Compiler Designss
An Introduction to the Compiler DesignssAn Introduction to the Compiler Designss
An Introduction to the Compiler Designss
 
Welding Metallurgy Ferrous Materials.pdf
Welding Metallurgy Ferrous Materials.pdfWelding Metallurgy Ferrous Materials.pdf
Welding Metallurgy Ferrous Materials.pdf
 
Material for memory and display system h
Material for memory and display system hMaterial for memory and display system h
Material for memory and display system h
 

Skylineplazacollapse.pptx

  • 1. Construction Failure Case study : Skyline Plaza Collapse Center for Environmental Planning & Technology Prepared By : Janak Shah (PT401914) Guided By : Prof. R. J. Shah
  • 2. Contents • Literature Review • Detailed Case Study • Summary • Lessons Learnt 2 JANAK SHAH (PT-401914) Skyline Plaza Failure
  • 3. Literature Review • Formwork • Shoring • Reshoring • Flat Plate • Punching Shear Failure • Progressive collapse 3 JANAK SHAH (PT-401914) Skyline Plaza Failure
  • 4. Formwork • Formwork is the temporary structure which moulds concrete into the desired shape, and holds it in the correct position until it is able to support the loads imposed upon it. • Formwork and its supports (falsework) is a structural system and must be designed and built accordingly. The actions (loads) on it may be temporary but they can be extremely large. • It is a temporary structure that supports its own weight and that of freshly placed concrete as well as construction live loads including material, equipment and workmen. 4 JANAK SHAH (PT-401914) Skyline Plaza Failure
  • 5. Requirements for formwork Property Purpose Strength Carry imposed loads. Stiffness Maintain specified shape and avoid distortion of concrete elements. Accuracy •Ensure shape and size of concrete elements. •Ensure specified cover to reinforcement. Watertightness Avoid grout loss and subsequent honeycombing of the concrete. Robustness Enable re-use. Ease of stripping Avoid damage to concrete surfaces. Standardisation Promote economy. Safety Ensure a safe working environment. 5 JANAK SHAH (PT-401914) Skyline Plaza Failure
  • 6. Shores Mudsill Wedges Bracing Joist Sheathing Stringer Fig 1 Typical elevated flat-slab formwork elements. (From Hurd, M.K., Formwork for Concrete, 7th ed., SP-4, American Concrete Institute, Farmington Hills, MI, 2005.) 6 JANAK SHAH (PT-401914) Skyline Plaza Failure
  • 7. Fig 3 Beam form and supports Fig 2 Column forms 7 JANAK SHAH (PT-401914) Skyline Plaza Failure
  • 8. Shoring • Vertical or inclined support members designed to carry the weight of the formwork, concrete, and construction loads above. 8 JANAK SHAH (PT-401914) Skyline Plaza Failure
  • 9. Shoring Fig 4 9 JANAK SHAH (PT-401914) Skyline Plaza Failure
  • 10. Reshoring • Reshoring systems involve the removal of a section of the formwork and support structure. With proper control and good supervision, these systems can give acceptable results. Props must be replaced in the original pattern and not overtightened to avoid causing undesirable stresses in the concrete. 10 JANAK SHAH (PT-401914) Skyline Plaza Failure
  • 11. Reshoring Fig 5 PHASE 1: PLACEMENT OF CONCRETE Fig 6 PHASE 2: REMOVAL OF SHORES 11 JANAK SHAH (PT-401914) Skyline Plaza Failure
  • 12. Reshoring Fig 7 PHASE 3: REMOVAL OF LOWER LEVEL OF SHORES Fig 8 PHASE 4: INSTALLATION OF RESHORES 12 JANAK SHAH (PT-401914) Skyline Plaza Failure
  • 13. Flat plates • Flat plates are of uniform thickness throughout without drop panels or column capitals. • Flatplate floors are widely used in apartments because the underside of the slab is flat and hence can be used as the ceiling of the room below. 13 JANAK SHAH (PT-401914) Skyline Plaza Failure
  • 14. • Of equal importance, the forming for a flat plate is generally cheaper than that for flat slabs with drop panels . Fig 9 14 JANAK SHAH (PT-401914) Skyline Plaza Failure
  • 15. Fig 10 Reinforced concrete flat plate system, Eugene, USA 15 JANAK SHAH (PT-401914) Skyline Plaza Failure
  • 16. Fig 11 A reinforced concrete building with flat plate system under construction, Kenya 16 JANAK SHAH (PT-401914) Skyline Plaza Failure
  • 17. Punching Shear • Punching shear failure is caused by the vertical shear and unbalanced moment borne by the slab-column connection, which makes the flat-slab connections a weak link in the whole flat-slab structure, and then leading to serious damage or even collapse. 17 JANAK SHAH (PT-401914) Skyline Plaza Failure
  • 18. • In a slab system with a concentrated load or at a slab column connection, the loaded area is not actually pushed through the slab as shown in Fig 12. • Punching shear failures arise from the formation of diagonal tension cracks around the loaded area, which result in a conical failure surface as illustrated in Fig 13. Fig 12 Misconception of Punching Shear Failure Fig 13Correct Representation of Punching Shear Failure 18 JANAK SHAH (PT-401914) Skyline Plaza Failure
  • 19. Laboratory Studies Fig 14 Exterior connection Fig 15 Interior connection Photo: Hwang and Moehle, ACI SJ, March-April 2000 19 JANAK SHAH (PT-401914) Skyline Plaza Failure
  • 20. Fig 16 Building Collapsed due to punching failure 20 JANAK SHAH (PT-401914) Skyline Plaza Failure
  • 21. Progressive collapse • ‘Progressive collapse denotes an extensive structural failure initiated by local structural damage, or a chain reaction of failures following damage to a relatively small portion of a structure. This can be also characterized by the loss of load- carrying capacity of a relatively small portion of a structure due to an abnormal load which, in turn, triggers a cascade of failures affecting a major portion of the structure.’ 21 JANAK SHAH (PT-401914) Skyline Plaza Failure
  • 22. Chain of Events • Progressive collapse occurs when an initiating event leads to damage to part of the structure by which this part looses its load bearing capacity. • As a consequence the loading pattern of the structure is changed leading to an overloading of other structural elements which are thereby also damaged. • This process continues until the whole structure collapses or a greater part of it. 22 JANAK SHAH (PT-401914) Skyline Plaza Failure
  • 23. Historical Perspective to Progressive Collapse Fig 17 A time line of cases associated with progressive collapse. 23 JANAK SHAH (PT-401914) Skyline Plaza Failure
  • 24. Progressive collapse , Skyline Plaza at Bailey's Crossroads, National Archives Fig 18 24 JANAK SHAH (PT-401914) Skyline Plaza Failure
  • 25. Skyline Plaza Collapse in Fairfax County, Virginia Date of Collapse : March 2, 1973 25 JANAK SHAH (PT-401914) Skyline Plaza Failure
  • 26. Background • The Skyline center complex located near Bailey’s Crossroad, Fairfax County, Virginia. • It was planned to contain 1. Eight apartment buildings (namely A-1 to A-8), 2. Six office buildings, 3. A hotel, and 4. A shopping center. Two apartment buildings which had been completed are shown in figure 19 . A pair of apartment buildings and adjoining parking and lobby structure were under construction 26 JANAK SHAH (PT-401914) Skyline Plaza Failure
  • 27. Fig 19 Appearance of completed apartment 27 JANAK SHAH (PT-401914) Skyline Plaza Failure
  • 28. Description of the Structure • The three structures under construction were designed under the Fairfax County Building Code Ordinance which incorporates by reference the provision of ACI 318-63. Building A-4 • Reinforced concrete flat plat construction • Supported on 4-ft thick foundation mat • Completed structure was to have 26 stories of apartments, a penthouse and a four story basement(B-1, B-2, B-3, B-4) 28 JANAK SHAH (PT-401914) Skyline Plaza Failure
  • 29. • The typical story height from the from the first story up was 9 ft 0 in from top of slab to top of slab. Floor slab were 8 inches thick. • Total basement height of about 40 ft as measured from top of the foundation mat(level B-4) to the top of the first floor slab. • The plan view without parking garage plan shown in fig. is that of 22nd storey and is typical for the 1st through 26th stories in the column layout. • There are eight shear walls in the structure. These are designated as A through H shown in fig 20. • A ½ inch expansion joint separated the building into two parts at grid line H. 29 JANAK SHAH (PT-401914) Skyline Plaza Failure
  • 30. Fig 20 30 JANAK SHAH (PT-401914) Skyline Plaza Failure
  • 31. N Fig 21 Aerial View of Construction at 11 am, March 2, 1973 (Before Collapse) 31 JANAK SHAH (PT-401914) Skyline Plaza Failure
  • 32. Design Strength of Concrete Concrete Design Strength (psi) Floor Base - 7 7 - 17 17 - Top Columns 5000 (34.5MPa) 4000 (27.6MPa) 3000 (20.7 MPa) Slabs 3000 (20.7 MPa) 3000 (20.7 MPa) 3000 (20.7 MPa) Table 1 32 JANAK SHAH (PT-401914) Skyline Plaza Failure
  • 33. The Collapse • The collapse occurred at around 2:30 pm on March 2, 1973, while under construction while the 24th floor slab was being casted. • Shortly after lunch, some workers observed slab deflections of approximately 150–600 mm (6 in. to 2 ft) for both the 23rd floor slab and the freshly placed 24th floor slab. • The freshly placed section of the 24th floor slab then fell onto the 23rd floor slab, starting a collapse that continued all the way to the foundation. • The building’s collapse removed the edge support from the parking garage, and falling debris triggered the failure of the garage. 33 JANAK SHAH (PT-401914) Skyline Plaza Failure
  • 34. General appearance of building A-4 as viewed from the southeast. Fig 22 34 JANAK SHAH (PT-401914) Skyline Plaza Failure
  • 35. •A partial view of the north face of building A-4 is shown in figure. •A number of columns and floors are identified. The collapse extended between shear wall H and column 33 on the south face a distance of about 65 ft (refer to building plan). •On the north face the collapse extended between columns 12 and 17, a distance of about 104 ft. Fig 23 35 JANAK SHAH (PT-401914) Skyline Plaza Failure
  • 36. Closeup view of the top of the east end of the failure zone, looking south. Fig 24 36 JANAK SHAH (PT-401914) Skyline Plaza Failure
  • 37. Closeup view near the midheight of the east end of the failure zone, looking south Fig 25 37 JANAK SHAH (PT-401914) Skyline Plaza Failure
  • 38. General view of building A-4 as seen looking southwest Fig 26 38 JANAK SHAH (PT-401914) Skyline Plaza Failure
  • 39. The Collapse • Once the section of the apartment building collapsed, the failure propagated horizontally through the attached parking garage. • It resulted in the death of 14 construction workers and the injury to 34 others. • Of the workers killed, ten were in the tower and four in the garage. 39 JANAK SHAH (PT-401914) Skyline Plaza Failure
  • 40. Investigation of failure • The collapse of the Skyline Plaza apartment building A-4 has been studied by using information contained in case records of the Occupational Safety and Health administration (OSHA), U.S. Department of Labor and obtained from on-site inspections by investigators from the National Bureau of Standards(NBS) 40 JANAK SHAH (PT-401914) Skyline Plaza Failure
  • 41. Formwork Fig 27 General appearance of building A-4 as viewed from the southeast. 41 JANAK SHAH (PT-401914) Skyline Plaza Failure
  • 42. Formwork • Figure 27 shows the locations of the formwork on March 2, shortly after the collapse. Full formwork was in place on the 24th and 23rd stories in sections 1 and 2. Some formwork may be seen on the 22nd story in sections 2 and 3. • Full formwork was also in place under section 4 on the 22nd and 23rd stories. No reshoring can be seen under section 4 below the 22nd floor in figure 27 . 42 JANAK SHAH (PT-401914) Skyline Plaza Failure
  • 43. Formwork, Shoring and Reshoring • Formwork sheets submitted to Fairfax County contained no mention of lateral bracing for the form system. However, a limited amount of bracing may be seen in figure 28. • OSHA, regulations (ANSI-A10.9, Sections 6.3.2 and 8.1.5) require a lateral bracing system capable of resisting a lateral force of at least 2 percent of the dead load of the slab. • Stringers were erected with a shore under each end wherein stringer were inserted in a basket like socket connected to the shore. • Diagonal lateral bracing was installed after every fourth shore at about 16 ft intervals. • Joists were placed over stringers at 16 inch intervals over which plywood sheathing was provided. • Stringers and Joists were usually 16 ft long although some were as short as 6 to 8 ft. 43 JANAK SHAH (PT-401914) Skyline Plaza Failure
  • 44. The formwork on the 24th story is shown in figure. Several columns have been identified for reference. Fig 28 44 JANAK SHAH (PT-401914) Skyline Plaza Failure
  • 45. Fig 29 A schematic of formwork is shown in figure as derived from OSHA case records 45 JANAK SHAH (PT-401914) Skyline Plaza Failure
  • 46. Formwork, Shoring and Reshoring • During the NBS site inspection. a considerable portion of the lumber use for the remaining forms in the 24th story was found to be in poor condition or out of plumb. The photograph illustrates a shore which is out of plumb and has a vertical crack near the top. OSHA regulations (ANSI-A10.9, sections 8.1.24 and 8.1.25) require correction of this condition prior to placing concrete (which was not yet placed on these forms). Fig 30 46 JANAK SHAH (PT-401914) Skyline Plaza Failure
  • 47. • One concrete finisher working near the stair well (around columns 65 and 66) indicated that a large deflection was seen in the middle of section 3. • However. the middle of section 3 is about midway between columns 67 and 85. 47 JANAK SHAH (PT-401914) Skyline Plaza Failure
  • 48. •The formwork on the 23rd story is shown in figure 2.20. These forms supported the 24th floor which had been cast on February 28 (section 1) and March 1(section 2). •Note the number of shores out of plumb. Fig 31 48 JANAK SHAH (PT-401914) Skyline Plaza Failure
  • 49. Fig 32 The method of attaching the brace to the floor is shown in figure 49 JANAK SHAH (PT-401914) Skyline Plaza Failure
  • 50. • As in the case of the 24th story. the 23rd story lumber which was apparently damaged was reused. • As in the case of the 24th story. OSHA regulations (ANSI-A10.9, sections 8.1.24 and 8.1.25) required correction of these conditions prior to placing concrete. Fig 33 50 JANAK SHAH (PT-401914) Skyline Plaza Failure
  • 51. •Reshoring in section 2 of the 22nd story as of March 6 is shown in figure. •There is conflict in their statements, a number of workmen that escaped the building by way of the stairs in section 4 have indicated that the 22nd story was either partially or entirely stripped in section 3. Fig 34 51 JANAK SHAH (PT-401914) Skyline Plaza Failure
  • 52. • Photographs taken right after the collapse showed that while full shoring remained on the 23rd and 24th stories, it had nearly all been removed from the 22nd story in sections 1 and 2 but remained in section 4. • According to OSHA regulations, forms are required to be in place for a minimum of 10 days with temperatures greater than 50 degrees F for spans longer than 20'-0“ (ANSI A10.9, Section 6.4.8). • The engineer’s structural drawings required two full stories of shoring and one story of reshoring while a concrete slab was being cast. 52 JANAK SHAH (PT-401914) Skyline Plaza Failure
  • 53. Fig 35 Estimated location of forms and reshores at the time of the collapse. 53 JANAK SHAH (PT-401914) Skyline Plaza Failure
  • 54. • The statements of one worker gave the investigators a good idea of the state of the forms at the time of the collapse. • “One workman indicated that, at the time of the incident, he was placing reshores in section 3 of the 21st story and that some reshores were present when he started working. Prior to the incident, all the reshores fell out (except those in the balcony areas). This is consistent with what could occur if the forms had been removed in the story above.” • If the shoring had been removed in the 22nd floor, the 22nd floor slab would have been relieved of its previous loads. With less loading, the deflection would have decreased in the slab causing the reshores on the 21st floor to fall out. 54 JANAK SHAH (PT-401914) Skyline Plaza Failure
  • 55. Concrete Strength • Results of standard ASTM C39 concrete cylinder tests showed adequate strength at 7 and 28 days. • However, these were laboratory tests, with cylinders stored at a controlled temperature. Particularly in cold weather, laboratory tests do not correspond to the strength of the concrete in place in a structure. • OSHA regulations required field cured cylinders, stored at the same temperature as the structure, to verify the strength of the structure before removing shores and formwork 55 JANAK SHAH (PT-401914) Skyline Plaza Failure
  • 56. Structural investigation of Failure • The evaluation of the capacity of structural elements was based on the Provisions of the ACI 318-71 Code and on procedures from published analytical and experimental research. • The three dimensional elastic analysis was performed using the finite element analysis program known by the acronym SAP. 56 JANAK SHAH (PT-401914) Skyline Plaza Failure
  • 57. • Each of the three finite element analyses had a particular purpose: • Case 1: Some of the employee statements indicated that the 22nd story forms were entirely removed at the time of collapse. (Complete removal of shoring) • Case 2: The concrete to have attained its full 28-day design strength of 3000 psi. • Case 3: Some of the employee statements indicated that removal of shoring under the 23rd-floor slab in the central corridor area of the building was in progress on the day of the collapse.(Partial removal of shoring) 57 JANAK SHAH (PT-401914) Skyline Plaza Failure
  • 58. • Investigation to flexure failure: • Upon Examination of all the probable conditions prior to the collapse, It is concluded that the initial mode of failure of either the 22nd or the 23rd floor slab was not flexural. 58 JANAK SHAH (PT-401914) Skyline Plaza Failure
  • 59. Investigation to Shear Failure Fig 36 Summary of shear stresses in the 23rd story floor slab. 59 JANAK SHAH (PT-401914) Skyline Plaza Failure
  • 60. Investigation to Shear Failure • Upon examination of all the probable conditions prior to the collapse, it is concluded that the initial shear mode of failure of the 23rd story floor slab resulting from partial or complete removal of shoring prior to the incident was a major contributing factor to the collapse. 60 JANAK SHAH (PT-401914) Skyline Plaza Failure
  • 61. Probable mode of failure • The most likely mode of collapse has been determined to be a shear failure around columns 67, 68, 83, or 84. • The premature removal of forms supporting the 23rd story slab when the concrete of that slab had a relatively low strength produced shear stresses that were in excess of the concrete capacity at the time of the incident. • The collapse is believed to have started with shear around columns 67,68, 83, or 84. The loss of support from anyone of these columns would lead to overstressing of the remaining columns. • The accumulation and impact of debris from the 23rd and 24th floor slab would have overloaded the 22nd floor slab and induced progressive collapse of successive floors to the ground. 61 JANAK SHAH (PT-401914) Skyline Plaza Failure
  • 62. Contribution of Crane • There is no indication that the crane was a contributing factor to the beginning of collapse in building A-4. No witness statements indicated that the crane moved prior to or during the initial sagging of the 23rd and 24th floors. The crane supports on the 14th and 16th floors are far enough away from the initiation of failure to preclude the crane as a cause. However, the crane probably became a driving force in the collapse once its support was lost. 62 JANAK SHAH (PT-401914) Skyline Plaza Failure
  • 63. Summary • An analysis of the 23rd-floor slab indicates that its most likely mode of failure was in shear around one or more columns in section 3 of the floor slab. The strength of the 23rd-floor slab on the day of collapse has been found to be of a magnitude that complete or partial removal of shoring underneath the slab would have produced a shear failure in the slab. The weight of debris resulted in failure in the slabs below and carried through the height of the building. 63 JANAK SHAH (PT-401914) Skyline Plaza Failure
  • 64. Non-Compliance with OSHA Regulation • Shoring in section 3 of 22nd story: The architect‘s specification required "In all cases two floors shall be fully shored."The removal of the 23rd story forms left only one story of formwork in place under the recently poured 24th floor. • Premature removal of 22nd story form: The forms removed on the 22nd story were in an area with spans exceeding 20 ft and therefore, should have been in place for 10 days of temperatures exceeding 50°F. 64 JANAK SHAH (PT-401914) Skyline Plaza Failure
  • 65. Non-Compliance with OSHA Regulation • Lateral bracing: Minimum values of 100 pounds per foot of floor edge or 2 percent of the total dead load of the floor, whichever is greater, is required. No evidence has been found which indicates that lateral load was considered in the design of forms. The lateral bracing provided would not provide this resistance. • Shoring out of plumb • Damaged Shoring • Inspection 65 JANAK SHAH (PT-401914) Skyline Plaza Failure
  • 66. Lessons Learnt • The contractor should be responsible for preparing formwork drawings, including shores and reshores; • The contractor should prepare a detailed concrete testing plan for stripping forms, including cylinder tests; • Inspectors and other quality control agencies should verify that the contractor performs the previous two items; • The Engineer of Record (EOR) should make sure he/she provides the contractor with all necessary design load data and other unique project information; • Uncontrolled acceleration of formwork removal may cause a total or partial collapse; and • Continuous top and bottom slab reinforcement is necessary around the columns. Continuous reinforcement provides overall ductility. 66 JANAK SHAH (PT-401914) Skyline Plaza Failure
  • 67. References • Edgar V. L. and S. George Fattal, “Investigation of the Skyline Plaza Collapse in Fairfax County, Virginia”, U.S.Department of Commerce, NBS, February 1977. • Jeffrey S., Norbert D. and Paul A. Bosela, “Another Look at the Collapse of Skyline Plaza at Bailey’s Crossroads, Virginia”, Cleveland State University, June 2013. • N.subramanian, “Alternative punching Shear reinforcement for RC flat slabs”,The Indian concrete Journal, January 2014. • K. Micallef, J. Sagaseta, M. Fernández Ruiz, A. Muttoni, “Assessing punching shear failure in reinforced concrete flat slabs subjected to localised impact loading”, International Journal of Impact Engineering,27- February 2014. • Devin K. Harris, “Characterization of punching shear capacity of thin UHPC PLATES”, December 2004. 67 JANAK SHAH (PT-401914) Skyline Plaza Failure
  • 68. References • M. Smith, “Progressive collapse assessment , non-linear behaviour of concrete structures in damaged state”, January 26th, 2007. • Alkarani, Ravindra. R, “Evaluation of punching shear in flat slabs”, International Journal of Research in Engineering and Technology, November 2013. • Prof. Kamran M. , “Temporary Structures : Shoring, scaffolding, and underpinning”. • David W. Johnston, P.E., Ph.D. , “Design and Construction of Concrete Formwork”, Concrete Construction Engineering Handbook. • “Guide to Concrete Construction”, Cement & Concrete Association of New Zealand (CCANZ). • Basher Alamin, “Analysis of Construction Loads on Concrete Formwork”, August 1999. 68 JANAK SHAH (PT-401914) Skyline Plaza Failure

Editor's Notes

  1. Explain this portion …