SlideShare a Scribd company logo
Six-Sigma Project Report




Hospital Surgical
Case Cart Completion
Six-Sigma Project


By Dan Johnson

Final Report
January 2011




   Six Sigma Project Final Report Jan. 2011.doc   1
Six-Sigma Project Report



                               TABLE OF CONTENTS

    Executive Review……………………………………………………………...3
1. Overview; Project Selection
    1.1 Background Information…………………………………….…………..4
    1.2 Problems and Symptoms………………………………………………...5
2. Define
    2.1 Goals and Expected Results……………………………………………...6
    2.2 Framework………………………………………………………………10
    2.3 Assumptions ……………………………………………………….……17
3. Measurement
    3.1 Study, Late Case Carts, Missing Items, Case Delays……………….…18
    3.2 Statistical Results and Sigma Level Calculation……………..………..23
4. Analysis
    4.1 Cause and Effect…………………………………………….…………..24
    4.2 Pareto………………………………………………………………...…..24
    4.3 Action Item List……………………………..…………………………..26
5. Improvement…………………………………………………………………27
6. Control
    6.1 Process, Standardized Work…………………………...……………….30
    6.1 Metrics…………………………………………………………………....30
7. Conclusion and Outlook
    7.1 Sigma Calculation……………………………………………….………33
    7.2 Savings Summary………………………………………….……………34
Appendix: Process Flow




   Six Sigma Project Final Report Jan. 2011.doc                         2
Six-Sigma Project Report


       Executive Review

       This hospital‟s Surgical Services and associated Operating Room (OR) and Sterile
       Processing and Distribution (SPD) are faced with many strategic growth decisions that
       provide both challenges and rewards. While there are many positive attributes within the
       Sterile Processing Department, surgical staff, hospital administration and the surgeon‟s
       committees have made keenly known their concern and dissatisfaction with the delays
       and time wasted due to lack of complete and ready surgical case carts, or case supplies.
       The hospital hasn‟t established a Lean or 6-sigma based process improvement
       methodology, however C-level executives are aware of the power of the approaches in
       facilitating improvement and therefore sanctioned a process improvement project focused
       on these concerns. For purposes of external publication, the facilities name and location
       is omitted and will simply be referred to as “the hospital” or similar designation.

       A team was assembled under my direction and consisted of eight individuals,
       participating as necessary over the course of the project. One of the team members is
       concurrently pursuing a green belt certification, although not through Aveta. The team
       applied the DMAIC methodology to the process of supplying the Operating Room (OR)
       with supplies and equipment required in the performance of surgical procedures (cases)
       with the intent of improving the number of cases for which all supplies are available at
       the time of need. The team drew upon some Lean knowledge, as well during the
       implementation phase. The project report is presented in alignment with the DMAIC 6-
       sigma phases.

       In the Define phase, we drew up a project charter, specified and quantified our goals and
       determined a method to track savings. We continued with a project plan and high-level
       task list outlining each team member‟s responsibilities. A rough process map was
       developed to ensure our understanding of the process and to provide a framework for
       improvement activities.

       An early discovery during the Measurement phase showed that the reporting capability in
       the OR limited the use of historical information for measurement or performance
       analysis, therefore the team was required to conduct detailed observations to understand
       the true nature of the delays being reported by the OR. During this phase we also began
       soliciting suggestions from SPD and OR personnel. A SIPOC and a HOQ were
       developed to assist the team in better understanding the relationships of the inputs and
       outputs to the process, its vendors and customers.

       During the Analyze phase Ishakawa charting was used to understand cause and affect
       relationships. This lead to brainstorming of the possible root-causes and ultimately was
       used to populate an Action Item List that is still in use to facilitate and monitor the
       ongoing process changes. A significant change brought about by the team involved
       completing a spaghetti diagram of the supply pick process; the results which included the
       implementation of a 2-bin kanban system and reorganization of the supplies storage area
       to align with the pick ticket sequence. During this phase the team reviewed the data
       collected during the observation period and quantified the scope of the incomplete case



   Six Sigma Project Final Report Jan. 2011.doc                                                    3
Six-Sigma Project Report


       cart issues. Note: case carts refer to the system of picking and delivering all supplies and
       instruments needed for the performance of a surgical case.

       The Improvement phase allowed the team the opportunity to implement a large number
       of the process improvement items detailed in their Action Item List and to begin
       measuring their impact. Detailed process flows were developed to help in the change
       process and to enlist buy-in from the technicians responsible. While many items remain
       to be accomplished the team focused on those that would have the greatest or most
       immediate impact to the process with the intent of quickly improving the satisfaction
       levels of the OR surgical personnel. A series of metrics closely aligned with the key data
       from the Measurement phase was installed at the same time, so impact could be
       quantified from the onset.

       The series of metrics mentioned before is now used daily to track and trend performance
       against an established baseline. This provides the Control element for the processes and
       allows for the quantification of impact as well as ensuring that the gains made will be
       sustained.

   1. Overview; Project Selection

       1.1. Background Information

       The hospital is one of a network of hospitals located in the southern US. The hospital
       offers general healthcare and wide variety surgical services including reconstructive,
       cardiovascular, urology, etc, utilizing 29 OR suites. Approximately 22% of its surgical
       caseload is in the fields of orthopedics and spine, both heavily supply and instrument
       intensive. The case volume for 12 calendar months ending July 2010 was about 33,000,
       split nearly equal in-patient to out-patient, although the trend for the past few years has
       been increasing the out-patient percentage. The OR conducts business typically from 7:30
       am to 5:00 pm Monday through Friday, but often extends late into the evening. Saturday
       cases are not considered scheduled, but several routinely occur each weekend.

       A key support service to the OR caseload is the reprocessing of surgical instrumentation
       and the assembly and distribution of Case Carts (customized kitting of supplies and
       instruments) by the Sterile Processing Department (SPD). The SPD is responsible for the
       cleaning, reassembly and sterilization of surgical instruments following a case and in
       preparation for those instruments to be reused. The SPD is also tasked with
       supply/inventory control and preparing case carts for use in the OR. The SPD operation
       runs 24-7.

       Quality is thought of in the relative terms of Clean and Sterile, Complete and On-time
       and is quickly becoming a focus within hospitals as accrediting agencies begin to look
       more closely at this part of the operation than ever before. Recently the noise level from
       surgeons and the hospital‟s surgical staff about the state of affairs regarding incomplete
       case carts and instruments sets had increased to the point of administrative concern. It
       was generally felt that something needed to be done, but efforts internal to the SPD had



   Six Sigma Project Final Report Jan. 2011.doc                                                       4
Six-Sigma Project Report


       proved fruitless and the department was taking a serious rap for its poor quality and
       delivery reliability, though no supporting numbers were presented.

       The hospital doesn‟t have an established process improvement methodology, but
       executives are acutely aware of improvements made in other hospitals using Lean or 6-
       Sigma methodologies, or a combination and believe that the 6-sigma approach may be a
       powerful tool to detect and reduce errors in the process. While not setting themselves up
       with a process improvement department they did agree to support the team approach to
       addressing these issues. That the process involved here is more service than production
       oriented it seems a challenge to utilize many of the 6-sigma statistical tools. However, it
       is their hope that the DMAIC provides the blueprint for solving and eliminating the
       problems they now face.

       1.2. Problems and Symptoms

       It is important to separate the noise from the real issues. Many of the same stories of case
       delays (late starts) are heard time and again throughout the hospital hallways. Weekly
       review after weekly review raised many of the same concerns. The OR record keeping
       system contains some information related to reasons for delays. However the system is
       inconclusive as it allows only a single reason code to be entered for case delay and while
       this is considered to be the primary reason there may be multiple factors and reality is
       that input often serves the person recording the code. The team initially created a Pareto
       from the OR data to begin to understand the opportunities rough order of magnitude. See
       Figure 1.

       Figure 1. OR Case Delay by Reason Code
                                                                OR Recorded Case Delay by Reason Code
                                                                             Percentage
                        PREVIOUS CASE OVER SCHEDULED TIME
                                              SURGEON LATE
                                                      OTHER
                                                      OTHER
                             PREFERENCE CARD DISCREPANCY
                                                      OTHER
                                             ANESTHESIA LATE
                                  PATIENT LATE TO HOSPITAL
                                  INSTRUMENTS NOT STERILE
          EQUIPMENT/INSTS NOT REQUESTED WHEN SCHEDULED
                     H&P NOT DICTATED-WRITTEN IN HOLDING
                                                      OTHER
                          SURGEON DELAYED IN OTHER ROOM
                                        LABS NOT AVAILABLE
                                    TRANSPORT TEAM DELAY
                                   IMPLANTS NOT AVAILABLE
                                ROOM NOT SET UP PROPERLY
                                 EQUIPMENT NOT AVAILABLE
                       PHYSICIAN REQUEST CHANGE IN LINE UP
                              PATIENT DELAYED IN ADMITTING
                                  EKG NOT DONE/AVAILABLE
                                              NO MD ORDERS
                                      DIFFICULT INTUBATION
                                           EMERGENCY BUMP
                                INSTRUMENTS NOT ORDERED
                                      SCHEDULING CONFLICT
                                           BLOOD BANK DELAY
                                   PHARMACY MEDS NEEDED
                          CONSENT INCOMPLETE/INACCURA TE
                            H&P DICTATED    NOT TRANSCRIBED
                                   PATIENT DELAYED IN OPSU
                                             C SECTION BUMP
                              XRAYS NOT DONE/UNAVAILABLE
                                 ANESTHESIA NOT AVAILABLE
         ADDITIONAL TESTS REQUESTED BY SURGEON/ANESTHESIA
                                           DIFFICULT IV START
                        PATIENT DIRECT ON A VENT/ISOLATION
                         PATIENT REQUESTED TO SPEAK TO MD
                               PATIENT WAITING FOR FAMILY
                                            PACU SATURATED
                           NOT ENOUGH STAFF TO START CASE
                        CONSENT DOES NOT MATCH SCHEDULE
                             UNANTICIPATED MULTIPLE LINES
                                   PROCTOR NOT AVAILABLE
                                  ASSISTANT NOT AVAILABLE
                         ADDITIONAL MD CONSULT REQUESTED
                                            PATIENT NOT NPO
                                           NEEDS TRANSLATOR
                                               TRAUMA BUM
                                  BED NOT AVAILABLE ON ICU
                               BED NOT AVAILABLE ON FLOOR
                                  SCRUB PERSON NOT READY
                      BIOMED DELAY IN CHECKING EQUIPMENT
                                  EQUIPMENT MALFUNCTION
                            OUTSIDE SERVICE PROVIDER DELAY
        SURGICAL CHECKLIST NOT COMPLETE FROM SENDING UNIT
                              XRAY TECH/CARM UNAVAILABLE

                                                            0.00%            5.00%        10.00%        15.00%   20.00%   25.00%




   Six Sigma Project Final Report Jan. 2011.doc                                                                                    5
Six-Sigma Project Report



       Note that the highlighted reasons are each related to the proper availability of supplies or
       instruments needed for the case. While no single reason recorded would lead a team to
       tackle it as the top offender, the aggregate of all related to supplies supports the concern
       of the hospital administration. This chart indicates that approximately 13% of delayed
       cases are so by virtue of missing supplies or instruments. The story is compelling enough
       to move forward with a project and ultimately drove the project more than adequate ROI
       analysis and comparison to other opportunities.

2. Define

   2.1. Goals and Expected Results

       Prior to assemblage of a 6-sigma team the Green Belt candidate and I developed a charter
       and had it approved and sponsored by the Sr. VP Perioperative Service. See Figure 2.1.
       The primary goal of the team is to decrease the number of surgical case carts that are
       delivered to the OR incomplete. The goal is further broken down into 1st and 2nd Cases
       and all other cases. The thought behind this is two-fold. First, getting a good start to the
       day helps ensure surgeon satisfaction. Second, the availability of some instrument sets is
       impacted by the timing of their use in cases earlier in the day. The lack of adequate
       instrumentation may be a focal point of the team during the project. The business case for
       this improvement is that improved service and delivery of complete case carts reduces the
       hours spent by both OR and SPD personnel in later searching for the missing items and
       may result in the recapture of enough OR time to provide availability for additional
       revenue generation.

       As well as the OR Pareto shown in Figure 1, a Project Evaluation and Cash Flow
       projection is developed along with a set of base data and savings projection. The base
       and savings projection are compiled through the course of the Define and Measurement
       phases and is finalized upon completion of the base data analysis. See Figures 2.2, 2.3
       and 2.4.

       The cash flow projection is predicated on the estimated FTE weeks that specific team
       members will be utilized across the course of the project. Salary considerations are
       expected to be about $76,900 over 3 months and we plan to have a couple of team
       dinners and minor project expenses. The sponsor wasn‟t concerned about capturing costs
       associated with hospital conference rooms as some are nearly always available for the
       team meetings and working sessions. Overall ROI is anticipated to be 4.4 to 1, assuming
       all hard and soft-savings targets are hit.




   Six Sigma Project Final Report Jan. 2011.doc                                                       6
Six-Sigma Project Report


Figure 2.1 6-Sigma Project Charter
                          Six-Sigma Project Charter / Client Hospital
 Product or Service         Case Cart OR Delivery                   Expected Project Savings ($)              $           350,000
 Impacted
 Facilitator                Dan Johnson                             Business Unit                            CSP/OR
 Champion                   Ms. Jackson                             Phone Number for Facilitator             602-448-5704
 Start Date                 8/10/10                                 Target Completion Date                   11/30/10
         Element                              Description                                           Team Charter
 1. Process:               Case Cart Assembly and Delivery                    Need to reduce the overall number of case carts
                                                                              delivered incomplete to less than 25% and 1st and 2nd
                                                                              cases to less than 5% by end of November 2010
 2. Project Description:   Problem and goal statement (project‟s purpose)     Eliminate the causes of case carts being delivered
    what is the             Case Cart delivered to the ORs missing trays      incomplete and wet.
    “Practical Problem”    and supplies. Wet case carts
 3. Objective:             Improvement is sought in 1) ensuring that all      Project
                           „available” items are picked to the case cart,       Y’s      Baseline      GOAL        Unit of       units
                                                                                                                   Measure
                           2) “items unavailable‟ at time of pick are         1st and       82           95        # Case         %
                           recorded and follow-up accomplished,               2nd case                              Carts
                                                                              comple
                                                                                tion
                           3) Reasons for “items unavailable” documented      Overall       60           75           # Case      %
                           and used for next steps.                             case                                  Carts
                                                                              comple
                                                                                tion

                                                                                 OR     194; 1st 2nd       54       # Delay        #
                                                                               Delay        cases                    Mins
                                                                              (Mins /      274 all        171
                                                                                Day)       others
                           Savings Metrics will include OR Delay minutes         OR     324; 1st 2nd       90       # Staff        #
                           per case resulting in increased OR utilization       Staff       cases                    mins
                           and OR Staff minutes used tracking the missing       Time       456 all        285
                           items.                                             (Mins /      others
                                                                                Day)
 4. Business Cases:        Expected financial improvement, or other           Improved service to the OR and decreased OR Starts
                           justification.                                     delayed due to incomplete cases carts. Will decrease
                                                                              labor hours spent on location and recovery.
 5. Stakeholder Team       Names and roles of team members?                   CSP Case Cart Tech(X2) – M. Hendersen, J. Maliford
    members:                                                                  OR Staff – J. Rodriguez, C. Nestman (Greenbelt)
                                                                              CSP Leadership – R. Sanchez
 6. Project Scope:         Which part of the process will be investigated     Case Cart Assembly, Transport and Staging.
                           and excluded.                                      Storage Location Control
                                                                              Completeness of reporting
 7. Benefit to External    Who are the final customers, what are their key    Patients, OR Staff and Surgeons; Improved delivery
    Customers:             measures, and what benefits will they see?         performance, improved OR Start Times

 8. Schedule:              Give the key milestones/dates.                     Project Kick-off,      August 10, 2010
                                                                              Define, Set Goals,
                                                                              Proc Map & AIL
                                                                              Review
                           M- Measurement, Metrics validation, Success        “M” Completion         August 25,2010
                           Metrics
                           A- Analysis                                        “A” Completion         September 18, 2010
                           I- Improvement                                     “I” Completion         September 25, 2010
                           C- Control                                         “C” Completion         October 10,2010
                           Note: Schedule appropriate Safety Reviews.         Safety Reviews         October 10, 2010
                                                                              Project Completion     November 30,2010
 9. Support Required:      Will any special capabilities, hardware, trials,   Meeting room, LCD Overhead, Flip Charts
                           etc be needed?




    Six Sigma Project Final Report Jan. 2011.doc                                                                                         7
Six-Sigma Project Report


Figure 2.2 Project Evaluation

     Score     Interpretation

      10       Sponsorship

      10       External Customer
       3       Shareholder
       3       Employee or Internal Customer
       3       Other (supplier, environment, etc.)
     4.75      - Total Benefit

       3       Availabilty of resources other than team

       3       Scope in terms of Black Belt effort

      10       Deliverable

       3       Time to Complete

       3       Team

      10       Project Charter

      10       Value of Six Sigma Approach

    59.225     Total




     Six Sigma Project Final Report Jan. 2011.doc         8
Base Data and Savings Projection Summary
                                                                                                                                             Baseline                                                                                         Goal Delay          Goal
                                                                                                                                Delay Delay OR                   OR Staff         Cost per                                                      Minutes                    Goal OR
                                                                                                            Incomplete         OR Lost  Lost Cost per Cost Daily Minutes OR Staff   Staff            Total Delay                              Saved Daily       Cost         Staff      Cost     Goal Total
                                                                                                             Resulting Delayed Minutes Minutes OR     Delay Lost   per    Minutes  Minute Cost Daily Cost per                                 (50% Delay       Saving      Minutes     Saving   Savings per
                                                                   # Cases      Complete        Incomplete in OR Delay Cases per Case per Day Minute   OR Min     Case per Day (Burdened) Staff Min     Day                   Complete        Minutes Per       Goal        Saved       Goal       Day

                                                                   Daily Avg.   %      #            #         %         #         Min         Min          $          $        Min    Min        $        $           $       %      #            Min            $           Min         $           $

                                               1st & 2nd Cases            60    82%        49            11       15%       1.6         18          29 $       40 $    1,166     30      324 $   0.63 $       205 $   1,372   95%        57          14.58 $         583       234 $         148 $       731
                                                                                                                                                                                                                                                                                                                                             Six-Sigma Project Report




                                               Remaining Cases            38    60%        23            15       10%       1.5         18          27 $       40 $    1,094     30      456 $   0.63 $       289 $   1,383   75%        29          13.68 $         547       171 $         108 $       656

                                               Total Daily                98    73%        72            26                 3.1                56.52              $    2,261             780          $       494 $   2,755              86          28.26 $ 1,130             405 $         257 $   1,387
                                               Average Annual @
                                               260 surgical days      25480           18720          6760                816                  14695               $ 587,808           202800          $ 128,440 $ 716,248           22230            7348 $293,904          105300 $ 66,690 $ 360,594
                                                                                                                                                                                                                                                                                                               Figure 2.3 Base and Savings




                                               27 Day Month            2646            1944             702             84.78                1526.04              $   61,042           21060              13338       74380          2309          763.02 $ 30,521           10935 $ 6,925.5 $ 37,446.3

                                                                                                                                                                                                                                              Estmated % case delays resulting in a lost case = 20%
                                                                                                                                                                                                                                              Plan to recover 50% of that potential
                                                                                                                                                                                                                                                                                                   Total




Six Sigma Project Final Report Jan. 2011.doc
                                                                                                                                                                                                                                              Recoverable                                         project
                                                                                                                                                                                                                                              OR Minutes Daily Cast Savings
                                                                                                                                                                                                                                                                        Annually                   worth
                                                                                                                                                                                                                                                         28 $ 1,130 $293,904                     $ 360,594




9
Six-Sigma Project Report


       Figure 2.4 Cash Flow Projections

                                      Project Cash Flow Projection
                                      Case Cart Completion Project
         $400,000   Approximate Annual Savings: $350,000
         $350,000   Project Cost: $78, 781
         $300,000   ROI: 4.4 to 1
         $250,000
         $200,000
         $150,000
         $100,000
          $50,000
              $0
                    1   3    5   7   9 11 13 15 17 19 21 23 25 27 29 31 33 35 37 39 41 43 45 47 49 51

                                                          Project Week

                            Cum Projected Savings     Cum Project Cost     Planned Out-of-Pocket


   2.2. Project Framework

       A high-level task plan (fig. 2.5) laid out the team members primary responsibilities and
       tasks for the project and was later detailed in the Project Gantt Chart for schedule
       adherence and reporting (fig. 2.6)




   Six Sigma Project Final Report Jan. 2011.doc                                                         10
Six-Sigma Project Report


       Figure 2.5 Task Plan
       High Level Task and Responsibility
       TASK                                       Responsibility                            Date Due Complete
       Charter
       ___ Indentify Opportunity                  Dan Johnson                                           25-Jul
       ___ Identify Sponsor                       Dan Johnson                                           25-Jul
       ___ Estimate Savings                       Dan Johnson                                           29-Jul
       ___ Draft Charter                          Dan / Ms. Jackson                                     2-Aug
       ___ Sponsor project review (weekly)        Dan / Ms. Jackson                                     2-Aug
       Define
       ___ Team selection                         Dan / Ms. Jackson                                     3-Aug
       ___ Complete Charter                       Dan Johnson                                           4-Aug
       ___ Team Training                          Dan Johnson, Green belt ( Cory Nestman)              12-Aug
       ___ Review existing documentation          Dan Johnson, Cory nestman                            15-Aug
           Define objectives and develop
       ___ plan                                   Team                                                  8-Aug
       ___ Develop Plan Gannt Chart               Cory Nestman                                         10-Aug
           Present objectives and plan to
       ___ management                             Cory Nestman                                         10-Aug
       ___ Map As-Is process                      Team                                                 15-Aug
           Review and redefine
       ___ problem/opportunity                    Team                                                 20-Aug
       ___ Sponsor sign-off                       Ms. Jackson                                          22-Aug
       Measure
       ___ Identify CTQs                          Cory Nestman                                         15-Aug
           Collect data on event tasks and
       ___ cycle time                             Team                                                 22-Aug
           Determine and validate
       ___ measurement system                     Dan Johnson, Cory Nestman                            25-Aug
       Analyze
           Prepare baseline graphs on event
       ___ tasks and cycle time                   Dan Johnson, Cory Nestman                            25-Aug
           Analyze impacts on tasks and cycle
       ___ times                                  Dan Johnson, Cory Nestman                             5-Sep
           Evaluate time and value, risk
       ___ management                             Team                                                  5-Sep
       ___ Benchmark other companies              Malik                                                10-Sep

        ___ Discuss team's preliminary findings   Team                                                 12-Sep
            Consolidate team's findings and
        ___ analysis (additional brainstorming)   Team                                                 16-Sep
       Improve
            Present recommendations to
        ___ process owners and operators          Team                                                 18-Sep
            Review recommendations and
        ___ formulate beta                        Team                                                 18-Sep
        ___ Prepare Beta                          Dan Johnson, Cory Nestman                            21-Sep
        ___ Run beta (test improved process)      Team                                                 24-Sep
        ___ Analyze beta and results              Dan Johnson, Cory Nestman                            24-Sep
        ___ Present final presentation            Team                                                 25-Sep
            Present final recommendations to
        ___ management team                       Team                                                 28-Sep
       Control
        ___ Develop Control Metrics               Dan Johnson, Cory Nestman                            21-Sep
        ___ Develop metrics collection tool       Cory Nestman                                         21-Sep
        ___ Roll out improved process             Team                                                 29-Sep
        ___ Roll out metrics                      Team                                                 29-Sep
            Monitor process monthly, using
        ___ control metrics                       Team                                                 10-Oct



   Six Sigma Project Final Report Jan. 2011.doc                                                                  11
Six-Sigma Project Report


       Figure 2.6 Project Gantt Chart




   Six Sigma Project Final Report Jan. 2011.doc   12
Six-Sigma Project Report


                         The SIPOC is used to focus the team‟s scope of work. Figure 2.7 illustrates this project‟s
                         SIPOC ensuring that the team doesn‟t try to resolve issues with the entire instrument and
                         supply flow from between the SPD and the OR. For example, while purchasing and
                         warehouse distribution certainly have an impact on the availability of supplies, it is
                         considered outside the scope of this project. The focus will be on the interrelationship
                         between the SPD and the OR and the staff‟s ability to accomplish the task of completing
                         case carts and delivering them on time to the OR.

                         Figure 2.7 Case Cart SIPOC
                                                                        SIPOC DIAGRAM
                                                        Case Cart Completion Improvement Project
            SIPOC Help

           Supplier           ►             Input                  ►         Process         ►             Output                  ►          Customer


Surgeon's offices                 Call to OR Planners                                            Surgical Schedule                     OR Planners and Team Leaders
                                                                          Print Surgery
OR Planners                       OR Surgery Scheduling System                                   Or Schedule for Reference             Case Pick Technicians
                                                                            Schedule



Surgeon's offices
                                  Surgery Equipment, Instruments        Print Preference         Pick Lists                            OR Planners
                                  and Supplies req'd                    Cards / Pick Lists       Priority / Conflict Management        Case Pick Technicians




                                  Case Pick Technicians Schedule          Assign CSP
CSP Management                                                                                   Pick assignments to technicians       OR Staff
                                  and assignment
                                                                        Resources to Pick


                                                                                                 Case Carts clean and staged
OR; Post use                      Decontamination cart wash             Obtain Clean, Dry        ready for use
                                                                                                                                       Case Pick Technicians
                                                                           Case Carts


                                                                                                 Complete Case Carts; Ready for
Cardinal                          HSS Warehouse / distribution         Pick Soft Goods and                                             OR Staff
                                                                                                 surgical use
                                                                          Document on
                                                                         Preference Card


                                                                        Pick Instrumemts
                                                                                                 Complete Case Carts; Ready for
OR and Vendors (Loaners)          CSP                                   and Document on          surgical use
                                                                                                                                       OR Staff
                                                                         Preference Card         Priority Needs List                   CSP Staff


                                                                        Sign Pick List and       Completeness acknowledged and
Case Pick Techs                   Completed and signed pick list        Surgery Schedule                                               OR Staff
                                                                                                 accounted for by tech


                                                                                                 On time case starts, satisfied
Case Pick Techs                   Complete Case Carts                   Deliver to the OR        customers                             OR, Doctors, Patients

                                              Metrics                                                        Metrics
                                   -Surgeon's scheduling                                         -Surgery Schedule
                                  Timeliness                                                     Timeliness and accuracy
                                   -Surgeon's Need's                                             -Needs List Percentage
                                  accuracy
                                   -CSP Absentee rate                                            -Case Cart Completion
                                                                                                 Rate
                                   -CSP case Pick Technician                                     -OR On-time Starts
                                  skills set
                                   -Cardinal and HSS
                                  distribution Fill Rates
                                   -Vendor delivery
                                  performance (Timeliness
                                  and accuracy)
                                   -Case Cart Completion
                                  Percentage




                    Six Sigma Project Final Report Jan. 2011.doc                                                                                                      13
Six-Sigma Project Report


       Along with the SIPOC a House of Quality was used to correlate and weight the various
       customer requirements with the functional “Hows” of the process. This tool with the
       later used fishbone helped the team to identify and quantify specific issues and eventually
       determine the tasks required to address the problems. Figure 2.8 is the HOQ developed
       and being two layers is spread over the next several pages.

       Figure 2.8 House of Quality




   Six Sigma Project Final Report Jan. 2011.doc                                                      14
Six-Sigma Project Report




   Six Sigma Project Final Report Jan. 2011.doc   15
Six-Sigma Project Report




       The team assembled and produced an initial Process Flow to ensure that they understood
       the process and breakdowns that occurred. This was built and displayed as a working
       model on a roll of kraft brown paper, a portion of which is shown in figure. 2.8. This
       methodology kept the team involved since the flow continued to be a work in process and
       didn‟t feel like an end product.

       Critical to Quality was assessed and the following was determined to be the key metrics.

           Quality
              Sets missing Instruments
              Case Carts Missing Supplies / Instruments

           Schedule
              Case Carts Missing Supplies / Instruments

           Cost
              Missing Item Recovery Time
              Revenue Potential
              Case Pick Time




   Six Sigma Project Final Report Jan. 2011.doc                                                   16
Six-Sigma Project Report


       Figure 2.8 Process Flow




   2.3. Assumptions

       The Pareto of case delay cause codes reviewed in section 1.2 is inherently flawed due to
       its subjective nature. The system that the OR staff uses to capture delay reasons is first
       limited to a single input, while there may be numerous contributing factors to the delay,
       or additional reasons that as stand-alone would have caused a delay. This puts the staff
       member in the position of need to identify a „primary‟ reason for the delay. The
       subjective nature is also heightened by the perception that a staff member may wish to
       use a delay reason to “protect or incriminate” individuals. For this, the team determined
       that it must conduct an in-depth study of the delay reasons.

       While there have been threats from surgeons to leave the hospital and take their business
       elsewhere and while their patience is limited, none have taken this option, but do make
       life miserable for the staffs.

       Case Cart assembly begins at about 5:00 pm the afternoon prior to the scheduled cases,
       after the schedule has been finalized by the OR office staff. The case carts are assembled



   Six Sigma Project Final Report Jan. 2011.doc                                                     17
Six-Sigma Project Report


       in accordance with the surgery schedule, but the schedule is subject to change for a wide
       variety of reasons.

       The perception of what is late seems to be in constant debate. The OR staff will record
       late case carts depending on whom and when the pre-case audit is done. This varies from
       the time that the case is ready to commence to hours prior to case start. For purposes of
       the team‟s study, late is defined as “1/2 hour prior to need in the room, potentially
       prompting a case delay”

       The amount of instrumentation is not unlimited. This is true and impacts the availability
       of instruments for cases later in the day, as those same sets may be in use in earlier cases.
       The ability to see that need and prioritize the “quick turn‟ of those sets is an important
       step in the process. Standard supplies should never be an issue, if the replenishment
       system is used and working correctly. Special order supplies may be a cause of delay,
       but doesn‟t impact this study as they are outside the norm and out of the control of the
       SPD staff.

       Case carts delivered complete and on time remain complete. This is not a true
       assumption as OR staff is known to cannibalize other case carts for supplies and
       instruments when they feel a need or want to have extra “just in case”.

       For purposes of savings calculation a standard value of $40 per OR minute is used. This
       is based on the financial office‟s input that an hour of surgery in the OR puts $2,400 to
       the bottom line.


   3. Measurement

       3.1. Study; Late Case Carts, Missing Items, Case Delays

       Based on the initial process flow developed the team set out to quantify the process and
       the effects of incomplete and late case carts to the OR. Part of the reason for the
       approach taken was to fill the void of case delay reasons contained within the OR data.

       The team observed and documented the timing and completeness of case carts for a
       period of 27 days and conducted interviews with the surgery staff to determine the actual
       reasons for case delay. Figure 3.1 contains the summary data from the study.




   Six Sigma Project Final Report Jan. 2011.doc                                                        18
Case Minutes Delayed Summary Data
                                                                                                                                                                                                             Missing Item Count /
                                                             Minutes Delayed                                          Case Carts Incomplete                            Delay Count / # Samples                  subgroup units                    Case Delay
                                                    Case #                                                                                                  Percent Delay                                   Daily           Items per
                                                                                               Sigma                                                            Cases                                       Missing            Case               Mins per     Mins per
                                               Subgroup      X-Bar (Avg)          Range        (StdDev)      Sample Size        # Delay         % Delay           p              Mean        UCL   LCL      Items               u     # Minutes    Delay         Item

                                                                                                                       2648               704       26.6%              0.266                  0.400 0.132         2129          0.804     12048         17.1         5.7
                                                  16-Aug                   6.16           25          8.71              105               37        35.2%              0.352            0.266 0.400 0.132             128       1.219       647         17.5         5.1
                                                                                                                                                                                                                                                                                                              Six-Sigma Project Report




                                                  17-Aug                   4.94           33          8.64                 97             26        26.8%              0.268            0.266 0.400 0.132             71        0.732       479         18.4         6.7
                                                  18-Aug                   7.51           33          9.59              103               42        40.8%              0.408            0.266 0.400 0.132             123       1.194       774         18.4         6.3
                                                  19-Aug                   4.79           32          8.88                 97             24        24.7%              0.247            0.266 0.400 0.132             65        0.670       465         19.4         7.2
                                                  20-Aug                   4.30           33          8.51                 99             22        22.2%              0.222            0.266 0.400 0.132             68        0.687       426         19.4         6.3
                                                  21-Aug                   4.73           31          8.29              101               27        26.7%              0.267            0.266 0.400 0.132             84        0.832       478         17.7         5.7
                                                  23-Aug                   3.65           28          7.58              100               20        20.0%              0.200            0.266 0.400 0.132             64        0.640       365         18.3         5.7
                                                  24-Aug                   4.96           35          8.85                 97             25        25.8%              0.258            0.266 0.400 0.132             77        0.794       481         19.2         6.2
                                                  25-Aug                   6.88           33          9.39              101               38        37.6%              0.376            0.266 0.400 0.132             125       1.238       695         18.3         5.6
                                                                                                                                                                                                                                                                           Figure 3.1 Base Data Development




                                                  26-Aug                   5.78           33          9.16                 94             29        30.9%              0.309            0.266 0.400 0.132             86        0.915       543         18.7         6.3
                                                  27-Aug                   4.30           23          7.75              105               26        24.8%              0.248            0.266 0.400 0.132             83        0.790       451         17.3         5.4
                                                  28-Aug                   3.23           22          6.89              100               19        19.0%              0.190            0.266 0.400 0.132             43        0.430       323         17.0         7.5




Six Sigma Project Final Report Jan. 2011.doc
                                                  30-Aug                   5.29           33          8.88                 95             27        28.4%              0.284            0.266 0.400 0.132             78        0.821       503         18.6         6.4
                                                  31-Aug                   4.31           31          8.09                 97             23        23.7%              0.237            0.266 0.400 0.132             61        0.629       418         18.2         6.9
                                                   1-Sep                   3.04           25          6.75              101               18        17.8%              0.178            0.266 0.400 0.132             61        0.604       307         17.1         5.0
                                                   2-Sep                   3.75           23          7.30                 91             20        22.0%              0.220            0.266 0.400 0.132             68        0.747       341         17.1         5.0
                                                   3-Sep                   5.11           33          8.62                 99             28        28.3%              0.283            0.266 0.400 0.132             90        0.909       506         18.1         5.6
                                                   4-Sep                   4.49           25          7.85                 96             25        26.0%              0.260            0.266 0.400 0.132             69        0.719       431         17.2         6.2
                                                   6-Sep                   2.65           29          6.49                 89             14        15.7%              0.157            0.266 0.400 0.132             39        0.438       236         16.9         6.1
                                                   7-Sep                   4.31           33          8.04                 99             24        24.2%              0.242            0.266 0.400 0.132             73        0.737       427         17.8         5.8
                                                   8-Sep                   5.86           26          8.69                 96             32        33.3%              0.333            0.266 0.400 0.132             105       1.094       563         17.6         5.4
                                                   9-Sep                   4.84           25          8.43                 95             25        26.3%              0.263            0.266 0.400 0.132             80        0.842       460         18.4         5.8
                                                  10-Sep                   6.36           29          9.09                 99             35        35.4%              0.354            0.266 0.400 0.132             113       1.141       630         18.0         5.6
                                                  11-Sep                   4.72           29          8.20                 99             26        26.3%              0.263            0.266 0.400 0.132             69        0.697       467         18.0         6.8
                                                  13-Sep                   3.24           23          6.84                 98             19        19.4%              0.194            0.266 0.400 0.132             51        0.520       318         16.7         6.2
                                                  14-Sep                   5.84           28          8.80              102               33        32.4%              0.324            0.266 0.400 0.132             94        0.922       596         18.1         6.3
                                                  15-Sep                   3.92           31          7.86               93              20         21.5%              0.215            0.266 0.400 0.132           61          0.656       365         18.3         6.0
                                                                                                  Average              98.1            26.1         26.6%       pbar                                              78.9        ubar
                                                                                                   StdDev              3.82            6.66          6.2%            0.266                                                      0.804
                                                                             Sum of Ranges             759 Sum of Subgroup Averages                                 122.83
                                                                               # Subgroups              27 Control Limits for Averages Chart                         4.549
                                                                                                   28.111




19
Six-Sigma Project Report


From the data collected we tracked daily a number of key defect measurables including:
       number of case carts incomplete
       # Items missing from case carts
       # Items missing per Case
       Total Delay Minutes
       # / % Instrument Sets missing instruments

Use of Attribute Control Charts:
       Since all existing data points were used and the subgroups contained data from each
       scheduled surgery for the day the sample size was inconsistent, varying from 90 to 105
       across 27 subgroups. In the control charts (p) average sample size of 98 was used. NP
       and C charts were not used due to sample size variance.
       Used a false LCL to show methodology. In reality, there is no LCL as any item not
       delivered could cause an unacceptable case delay.
       U chart was used to show the number of items missing
       There is a mix both in terms of types of cases being and 8 different technicians
       responsible for the assembly of Case Carts. Note that in nearly all samples the technician
       responsible isn‟t documented.
       The p chart indicates a process out of control as it alternates data points up and down,
       although over the center line.



The charts below contain the daily results the team found significant.




Incomplete case carts ranged between 15.7% and 40.8% daily with a mean of 26.6%. Each of
these incomplete case carts represents a potential case delay. Actual case delay is a function of


   Six Sigma Project Final Report Jan. 2011.doc                                                     20
Six-Sigma Project Report


many other variables, including the critical nature of the specific item missing from the case. For
purposes of this study, that detail was not factored. Actual number of cases delayed due to
incomplete case carts was 85. This chart and data was later used to set up the first control chart
and the upper and lower control limits were calculated and included on this chart. During the
improvement phase this data was correlated to the individual tech and deficiencies in standard
process, training and motivation were addressed.




Items missing per ranged from .43 to 1.238 (.8) per total daily case count with a mean of .804
items per case. Factored against only those cases missing items the mean is 3.003 items per case
with a range of 1.19 (2.26 to 3.45). This correlation caused the team to consider that once a case
has a missing item, the technician picking the case failed to focus on completing as much of the
case as possible.




   Six Sigma Project Final Report Jan. 2011.doc                                                       21
Six-Sigma Project Report




The two charts correlating the number of items missing to the delay time demonstrated that the
average case delay was 18.1 minutes and 6 minutes per missing item. There was a noticeable
increase following Labor Day that we attributed to unusual staff shortages and a delay in the
receipt of a supply shipment. A phenomenon noted was that contrary to expectation, days with
more items missing didn‟t necessarily result in longer case delays. This, presumably, is due to
an „all hands on deck‟ approach when items are missing. It did, of course, result in more staff
time to locate the multiple items.




   Six Sigma Project Final Report Jan. 2011.doc                                                   22
Six-Sigma Project Report




As mentioned earlier, during the observation process the team noted the high number of
instrument sets not included in the case carts because the sets themselves were incomplete. Data
was collected from the SPD‟s instrument management system to get a picture of how prevelent
this issue was. The Missing instrument chart shows that over the course of 4 months an average
of 18% of all instruments sets assembled were incomplete. This became a major focus for
improvement.

Incomplete Case Carts Statistical Results
             Over 27 days, between August 16 and September 15 there were 2648 surgery
             cases conducted
                 o Daily case volumes ranged from 90 to 105
             Of these 1620 (61.1%) were 1st or 2nd cases for the room for the day
             704 (26.6%) cases were picked incomplete
                 o 292 of these impacting 1st or 2nd cases (11.3% of total cases)
             85 (3.2%) cases were actually delayed due to incomplete case picks
             Average OR case delay due to incomplete cases carts; 18.1 minutes
                 o Results in an mean delay to all cases of 4.8 minutes
             Given $40 per OR minute lost the opportunity is $61.042 per month
             66424 Items were required for the cases
             2129 (3.2%) Items were missing

       3.2 Sigma Calculation
       Opportunities for Defect: 66424
       Defects:                          2129
       DPMO:                         32052
       Failure Rate:                      .321
       Accuracy Rate:                    .968
       --------------------------------------
       Sigma Level:                     3.35


   Six Sigma Project Final Report Jan. 2011.doc                                                    23
Six-Sigma Project Report



         4. Analysis

                   4.1 Cause and Effect
                   Upon completion of the observations and base development, the team conducted a
                   brainstorming session utilizing the Ishakawa Cause and Effect diagram to detail the
                   variety of reasons for the incomplete case carts. Each entry was then weighted, after
                   lengthy discussion, to determine which had the highest likelihood of impact. See Figure
                   4.1.

                   Figure 4.1

                 Case Cart Completion Brainstorming Session Fishbone Diagram (the 6 M's)

                                                                                   E                                                             E                                                              U


                            Priority 1,2,3                                   N                                                            R                                                             E


                                                                 2I          Lack of priority / Conflict management                 3U    Audit vs. OR Feedback                                2 I      Block scheduling


                                                         1H          Picklists incomplete, inaccurate, extra items          1 S      Individual Measurement                              3 L     Existing Carts not adequate


                                                 3C          Implants not listed on Count sheet                      3 A      Method of Accurate Measure                        3 I         Late reprocessing
Problem Description:
                                                                                                                                                                                       Interruptions to Pick (Phone & Delivery)
                                         1A          Soft-goods need to be in T-Doc?                        2E           No Consistent Definition of"Complete"             1M         Impacts focus accuracy


   Case Carts sent                   M                                                                  M

                                     Sets "Called For"
   to OR Incomplete         3   M    in other Rooms                              3M        Out-of-Service Sets                    1M      Different methods of documenting pick

                                             "Called for" Sets, not used, not
                                2    A       returned to CSP                              2A    Carry-Over Sets                          1E      Lack of Job Expectation


                                         1N          Lack of Knowledge - Location              1T       Loaners not available on time          1T       Quick Reference needed?


                                                 2           Lack of Knowledge - Material            1E         Soft goods not available at pick time   1H    Lack of follow-up
                                                                                                                                                                    Use of Priority List,
                                                                                                                      "Called-For"sets not                          Inconsistent
                                                         1           Sets not put-away in right location    2R        returned to CSP                         1O    Management follow-up


                                                                 1           Staff indifference to assignment       3I        Instruments not available at pick time 1 D    Lack of standardized process


                                                                         2         Staff inexperience                       1A      Loaners not available in time for processing


                                                                                                                                  1L      Incomplete / Inaccurate Pref. Cards




                   4.2 Pareto Revised

                   The reason code results from the team‟s observations were then entered into a new
                   pareto, figure 4.2 and compared to the initial results from the OR data system. While the
                   numbers were greater, the rating of the items didn‟t differ significantly.




         Six Sigma Project Final Report Jan. 2011.doc                                                                                                                                                                             24
Six-Sigma Project Report


                           Figure 4.2
                                                                                       Case Cart Incomplete
                                                                                  # Times Reason Code Assigned

                         Instruments not available at pick time


                    Loaners not available in time for processing


Interruptions to Pick (Phone & Delivery) Impacts focus accuracy


                   Picklists incomplete, inaccurate, extra items


                             Sets not put-away in right location


                               Staff indifference to assignment


                                  Method of Accurate Measure


                      Individual Measurement (Accountability)


                                  Lack of Knowledge - Location


                                  Lack of Knowledge - Material


                                   Lack of standardized process


                                      Quick Reference needed?


                        No Consistent Definition of"Complete"


                                            Use of Priority List,


                               Sets "Called For" in other Rooms


                                            Out-of-Service Sets


                                              Late reprocessing


                        Lack of priority / Conflict management


                                        Lack of Job Expectation


                             Implants not listed on Count sheet


                                                Carry-Over Sets


                                         Audit vs. OR Feedback


                        Different methods of documenting pick


                "Called for" Sets, not used, not returned to CSP


                                               Block scheduling


                           Inconsistent Management follow-up


                                             Staff inexperience


                           Soft goods not available at pick time


                                    Existing Carts not adequate
                                                                                                                      Source: Case cart Incomplete, 6-Sigma Tracker. Dates August 15, 2010 - Sept 14, 2010

                                                                    0   10   20            30         40         50   60                   70                   80                  90                   100




                           These breakouts were then further defined into actionable steps and were entered into the
                           team‟s Action Item Log. The log eventually contained over 160 entries and remains in
                           use at the time of this writing. A portion of the Action Item Log is shown in figure 4.4.
                           Key actions taken by the team will be reviewed in the upcoming Improvement section.




                  Six Sigma Project Final Report Jan. 2011.doc                                                                                                                                                 25
Six-Sigma Project Report


        Figure 4.4 Project Action Item List – Sample Page
                      Effect: Case carts are not 100% complete, accurate and available on time


   Category    Cause                                         Subcause                             Recommendation

                                         Not a value alignment                              Use dedicated staff for case
    Staffing   Staff indifferent
                                                                                            picking
                                         No feeling that they are being measured,
                                                                                            Use dedicated staff for case
    Staffing   Staff indifferent         watched or held accountable for case cart
                                                                                            picking
                                         defects
                                         No negative impact to them while working in
                                         case (by the time they do relief everything is     Use dedicated staff for case
    Staffing   Staff indifferent
                                         fixed)                                             picking

                                         Not all staff has scrubbed all cases therefore      Use dedicated staff for case
    Staffing   Staff inexperienced
                                         they are not familiar with all supplies & trays     picking
                                         Descriptions on work sheets are not always          Have existing staff highlight
    Staffing   Staff inexperienced       clear & user friendly                               routine problem items &
                                                                                             allocate staff to fix daily
                                         No place for staff to reference locations for items Pick cases using pick lists &
    Staffing   Staff inexperienced                                                           ensure all items have location
                                                                                             list
                                         No place for staff to reference where locations
    Staffing   Staff inexperienced                                                           Post master list of locations
                                         are in relation to the core (master location list)
                                         No existing process diagram or work instructions
                                                                                             Make work instruction & share
    Staffing   Staff inexperienced       for how cases are to be picked.
                                                                                             process flow with staff

                                         Staff for case picking not dedicated. PM staff
                                                                                            Use dedicated staff for case
    Staffing   Staff inadequate          used prior to 2:30pm when they get pulled to do
                                                                                            picking
                                         lunch relief
                                         Cases are booked after 5pm when staff is more      Use dedicated staff for case
    Staffing   Staff inadequate          limited and/or in rooms                            picking
                                         Staff picks the cases they are familiar with and   Use dedicated staff for case
    Staffing   Staff inadequate          can do fast                                        picking
                                         Items for case are placed on open carts (with 3
 Case Carts & Existing case carts not    procedures per shelf) due to lack of availability of Use dedicated closed case
 environment adequate                    carts                                                carts on each case

                                         Case carts are not numbered or identified as     Label each cart with SHJC ID
 Case Carts & Existing case carts not
                                         SJHC with numbering system                       number and reference back to
 environment adequate
                                                                                          manufacture's SR #
                                         Case carts have gotten lost or removed over the Label each cart with SHJC ID
 Case Carts & Existing case carts not
                                         years see above reason.                          number and reference back to
 environment adequate
                                                                                          manufacture's SR #
                                         Case carts are not being cleaned between each
 Case Carts & Existing case carts not                                                     Use dedicated closed case
                                         use unless they are used for soiled transport to
 environment adequate                                                                     carts on each case
                                         SPD
                                         No other system (totes or bins) available to     Use dedicated closed case
 Case Carts & Existing case carts not    contain smaller cases such as eye cases.         carts on each case but make
 environment adequate                                                                     an exception for eyes and put
                                                                                          three per cart.
 Case Carts & Existing case carts not    Case carts are not closed therefore present      Use dedicated closed case
 environment adequate                    challenge with separation of clean and dirty     carts on each case
                                         Case carts are not being maintained wheels
                                                                                          Using SJHC cart ID number, set
                                         need lubricant
 Case Carts & Existing case carts not                                                     up PM system with Biomed to
 environment adequate                                                                     have carts inspected annually.
                                                                                          Monitor and report.




   Six Sigma Project Final Report Jan. 2011.doc                                                                               26
Six-Sigma Project Report


       The opportunity to observe the Case Cart process caused us to revise the process flow a
       number of times. The end result was a cleaner, streamlined version of the process and it
       is included in the appendix. This exercise prompted the team to recognize that the case
       cart process is highly variable and statistically out of control and generated a need for not
       only improved processes but also standardized practices, which they developed in the
       way of Work Instructions for each of the key components.

       One of the top reasons for case carts not being completed was the SPD‟s inability to
       complete instruments sets on time. While staffing appropriately across the day to handle
       the incoming workload was an issue to be addressed, a significant factor was that the staff
       had developed the habit of not putting up incomplete sets, making them unavailable and
       not adequately communicating this to the OR. During the observation period a second
       set of metrics and trending was initiated to begin to understand the magnitude of this
       problem. A review of several months‟ data of sets missing instruments was captured
       from the SPD‟s instrument tracking system. It was determined that for the period
       extracted 18% of the sets put up were incomplete. The OR staff had complained often
       enough that the SPD staff determined not to send the incomplete sets with the case cart,
       further extenuating the problem. This became the focus of a major improvement
       initiative which we will cover shortly.

       While the availability of supplies would not have seemed to a major issue, it was
       discovered that some case cart assemblers were not addressing all the supply needs.
       Reasons ranged from:
                     They thought the supplies were actual stored in the OR
                     Were unfamiliar with the supply layout to
                     Supplies not listed with locations on the pick tickets
                     If one item is missing, less focus came to picking all the remaining items.

       This then lead to another major improvement initiative by the team and began with a
       spaghetti diagram detailing the typical paths taken by the case assemblers to pick all
       supplies.


   5. Improvement

       This is where the proverbial rubber meets the road. Beginning with the brainstorming,
       process flow review and Paretos used in the measurement and analyze phases of the
       project the team constructed an action plan that eventually grew to over 160 separate
       items covering the following areas:
                      Staff experience , skills, training, motivation
                      Case Cart condition and size
                      Space for storage, picking and staging
                      Standardized procedures and work instructions
                      Pick sequence and flow
                      Pick list updates
                      Completion of instrument sets


   Six Sigma Project Final Report Jan. 2011.doc                                                        27
Six-Sigma Project Report


                      Availability of loaner and consignment sets

       It‟s important to the team to set and follow a structured approach or risk losing
       themselves in the myriad possibilities and tasks. Many of the improvement tasks
       identified are beyond the team‟s scope and will remain for the SPD leadership to continue
       to facilitate or move to another improvement initiative.

       A Test of Change approach was used to introduce process changes. The team determined
       the change, its method of measurement to see whether the change resulted in
       improvement, then communicated to the SPD and OR staffs the change and how it would
       be implemented. Critical to the team‟s thinking was to over communicate in order to
       gain buy-in.

       Using the tools the team set to determine a priority for the solutions, establish the
       improvement method, define the implementation steps and communicate.

        It is clear that standardization of process and practice is key to any sustainable
       improvement. First steps included cleaning up the process flow and using it to
       demonstrate the opportunities and the revised or new elements to the SPD staff,
       developing a set of Standard Work Instructions detailing the „hows and whys‟ of each
       associated task. For the Case Cart Technicians these include instrument set put-away,
       pick sequence and documentation. Standard Work Instructions were also developed for
       the SPD Instrument Set Assembly process. The document took the form of a step-by-
       step manual with photos correlated to each step. The process steps were reviewed with
       each staff member during training sessions and are visibly posted in the work space for
       quick reference. The simplified process flow is included in the appendix.

       As part of the effort to complete instrument sets it was deemed necessary to identify the
       critical instruments in each set. This information is then entered into the SPD‟s
       instrument management system and guides the assembly technician to not complete the
       assembly if a critical instrument is missing, but to complete it if a non-critical instrument
       is missing. This should result in fewer sets being left unavailable for use in a case. An
       additional step added to this work sequence is a required supervisor sign-off for any set
       assembled incomplete. While this is contrary to Lean thinking, it was determined to be
       pragmatic and necessary in the short-term to ensure awareness and adherence to the
       process. The identification of critical instruments is a painstaking chore, accomplished by
       OR personnel, so it will be a work-in progress for some time.

       A result of the focus on instrument set completion highlighted the negligence of the SPD
       management to effectively replace instrument that were lost or damaged. A significant
       expenditure needed to be made in order to elevate the inventories to the point that a daily
       impact could be made. The team sponsor agreed that the expenditure had been needed for
       some time and measures were put in place to monitor the needs going forward, so the
       cost associated are not included in the cost-benefit analysis or savings projections for the
       project.




   Six Sigma Project Final Report Jan. 2011.doc                                                        28
Six-Sigma Project Report


       Process changes in the Case Cart Assembly process includes re-layout of the supplies
       inventory from a product-family based to alignment with the pick ticket sequence and the
       addition of stores location on the pick ticket printout. A Quick Reference Locator was
       also produced and made available in various supply areas. This later change addresses
       needs that occur more often after the case carts have been picked, for add-on or
       emergency cases or when unforeseen needs arise.

       In addition to the change in the stores layout a 2-bin Kanban was installed. In this system
       each item‟s inventory is evenly split between two compartments. The items are picked
       from the „active‟ compartment. Once this is empty, pickers select from the second or
       backup compartment. Empty compartments or containers are replenished. For small
       items, bins are used as the kanban signal. For larger items cards are used.

       The realignment of the stores, integration of the kanban system and inclusion of item pick
       locations has resulted in a pick time reduction of an average of two minutes, from 18 to
       16 per case. At 98 cases per day the savings equates to 196 minutes each day.

       Kanban Pictures




                                                   Swinging Compartment Door


       With the above key process changes the team still needed to address the control and
       compliance issues within the Case Cart assembly process itself. Consistency is important,
       but it comes at a cost. Introduced were the requirements that the picking technician
       record each pick ticket they assemble. While not a fix, it was hoped that the requirement
       would raise awareness. Case carts required, by timing, to be sent to the OR incomplete


   Six Sigma Project Final Report Jan. 2011.doc                                                      29
Six-Sigma Project Report


       required a supervisor‟s sign-off and a communication call to the OR control desk. This
       helped preemptively set in motion any schedule change or recovery action needed.

       Highlighted in the brainstorming session was the need for cross-training. The department
       suffered when primary Case Cart Assemblers were absent, especially if more than one.
       Other areas within the SPD had similar issues. It was determined to begin a cross-
       training program and soon to begin a position rotation that would allow for staff to gain
       competency in all areas. It is beyond the scope of this team to provide the train or set up
       the schedules and this will be left to the department management. They are documented
       on the project action item list for future follow-up.

       Daily controls and metrics were introduced to track case cart and instrument set
       completion rates. These are displayed daily at a department level and fed into a Quality
       Dashboard at an individual as well as department level. Note: The dashboard is now
       expanding to track quality, productivity and service across the entire SPD.

   6. Control

       Controls are integral to the success of any implementation ensuring compliance to
       practices and standards, monitoring improvement progress and sustaining the gains. First
       and foremost are the Standard Work Instructions highlighted before and training provided
       to gain understanding and compliance.

       Among the controls implemented was the Case Cart Audit mentioned in the prior section.
       This audit provided near real-time feedback from the OR to the SPD. The results were
       posted daily in the Incomplete Case Carts Daily-Monthly Control Chart. Figure 6.1
       shows the actual charts for the months of October and November.

       For purposes of this exercise, both Upper and Lower Control Limits were calculated, but
       the team and staff recognizes that the target for incomplete case carts is zero. In the two
       months since initiating the project steady progress has been made. The last two weeks of
       November shows the incomplete carts steady at about 16.4 % versus 26.6 during the
       observation period. Still work to do, but showing a 38% improvement.




   Six Sigma Project Final Report Jan. 2011.doc                                                      30
Six-Sigma Project Report


       Figure 6.1 Incomplete Case Carts Control Chart




       The second control chart installed is a daily tracker of instrument sets assembled
       incomplete. Figure 6.2 contains the charts from October and November and demonstrates
       significant improvement. November versus the base period shows an improvement from
       18% to 9.9% of Instruments Sets assembled incomplete for a 45% improvement. This
       trend is expected to continue as many eyes are focused, now, on the problem.




   Six Sigma Project Final Report Jan. 2011.doc                                                31
Six-Sigma Project Report


       Figure 6.2 Incomplete Instrument Sets Control Chart




       Additionally, a daily report was established to actively monitor case delays recorded to
       incomplete case carts. While the OR recording methodology hasn‟t changed and
       therefore the inherent inconsistencies still exist, the renewed awareness and diligence by
       the OR staff, coupled with improved review from OR management may provide better
       insight. For the month of November the OR statistics reported versus the base period:

       OR Stats                Base                     November                   Imp %
       Total Cases                 2648                    2725
       # Incomplete Case Carts      702           26.5%     447            16.4%            38%
       # Caused Delayed Cases        85            3.2%      68             2.5%            22%



   Six Sigma Project Final Report Jan. 2011.doc                                                     32
Six-Sigma Project Report


7. Conclusion and Outlook

       The 6-sigma methodology proved a useful approach to identifying, quantifying and
       providing a framework to address the many issues related to incomplete case carts at this
       hospital. Using the DMAIC roadmap the SPD can increase its accuracy and therefore
       dependability in customer service.

       While we have not yet met our goals, it is believed that with continuing perseverance that
       they may be over the next 4 to 8 months. We‟ve seen our metrics improve:
              Incomplete Case Carts down from 26.6% to 16.4 %, a 38% improvement
              Incomplete Instruments Sets, while not an initial goal, became a significant factor
              in incomplete case carts: down from 18% to 9.9%, a 45% improvement.
              Sigma level

          Sigma Calculation                       Base         November
          Opportunities for Defect:                66424          69387
          Defects:                                  2129            1370
          DPMO:                                    32052          20625
          Failure Rate:                              .321           .197
          Accuracy Rate:                             .968           .980
          ---------------------------------------------------------
          Sigma Level:                            3.35          3.56




   Six Sigma Project Final Report Jan. 2011.doc                                                     33
Six-Sigma Project Report

Base Data Normalized to November Actuals and Savings Projection Summary
                                                                                                          Baseline
                                                                                           Delay Delay OR                                                         Cost per
                                                                       Incomplete         OR Lost  Lost Cost per Cost Daily                 OR Staff     OR Staff   Staff              Total Delay
                                                                        Resulting Delayed Minutes Minutes OR     Delay Lost                  Minutes     Minutes   Minute   Cost Daily Cost per
                            # Cases       Complete         Incomplete in OR Delay Cases per Case per Day Minute   OR Min                    per Case     per Day (Burdened) Staff Min     Day

                           Daily Avg.     %       #            #         %         #          Min          Min          $          $          Min          Min        $            $           $

1st & 2nd Cases                    60      82%        49            11       15%       1.6          18           29 $       40 $    1,166           30        324 $    0.63 $          205 $   1,372

Remaining Cases                    38      60%        23            15       10%       1.5          18           27 $       40 $    1,094           30        456 $    0.63 $          289 $   1,383

Total Daily                        98      73%        72            26                 3.1                  56.52              $    2,261                     780             $        494 $   2,755
Average Annual @ 260
    surgical days              25480             18720          6760                816                    14695               $ 587,808                  202800              $ 128,440 $ 716,248

Base 27 Day Month         2648                    1944             702                 85                 1526.04              $   61,042                  21060                   13338 $ 74,380
November                  2725                                     447                 68
Impact at Base                                                     722                 87
Improvement and Savings Impact                                     275                 19           18     346.42 $         40 $   13,857           30       8262         0.63 $   5,205 $ 19,062
Direct Project Savings Annualized                                                                                              $ 166,279                                      $ 62,464 $ 228,743

Addition Soft Savings
                                        # Case   Base                                        Saved Std Prod          Mean FTE
                                         Carts   Assm. Nov. Assm.                            Mins /  FTE     Equiv.    Payroll
SPD Case Cart Pick Time                  Daily    Mins   Mins     Improvement                 Day   Min/Day FTEs      (Annual) Savings
Subtotal                                      98      18       16           2                   196      390     0.5 $ 32,000 $ 16,082                                                     $ 16,082
                                                                        11.1%
                                                                                   SPD     Saved         Std Prod         Mean FTE
SPD/OR Time recovered due to            # Sets  Base         Nov.                Mins per Mins /           FTE    Equiv.    Payroll
improved set completion                  Daily Missing      Missing Improvement     set     Day          Min/Day FTEs      (Annual) Savings
                                            910    164            121         43        25   1075             390     2.8 $ 32,000 $ 88,205
                                                  18%            13%      26.2%
                                                                                           Saved         Std Prod         Mean FTE
                                                                                 OR Mins Mins /            FTE    Equiv.    Payroll
                                                                                  per set   Day          Min/Day FTEs      (Annual)  Savings
Subtotal                                                                                12    516             390     1.3     43,000 $ 56,892                                              $ 145,097
Subtotal Soft Savings (not verified)                                                                                                                                                       $ 161,179
Potential Total Project Savings                                                                                                                                                            $ 389,922


           Using the base data for comparison to the results in November we can ascertain that we are on
           track to save $228,743 annually. While the impact on staff minutes spent searching for missing
           items is nearly on track, it‟s difficult to tell if the lost OR time will be sufficiently recovered.
           Shown also are soft savings calculated based on the reduction in time to pick and assemble case
           carts and reduction in the time SPD uses search for instruments from incomplete sets. These lines
           are excluded from the Direct Project savings for two reasons; first they are difficult to verify on a
           consistent basis and no labor has actually been reallocated from the department and second, they
           were not part of the original savings projections. However it is important to recognize the
           impact that the 6-sigma team had relative to the entire process. It is too early to definitively state
           that the project will result in the savings projected, however at the time of this writing all
           indicators are moving in the right direction and the gains made are being sustained.




                  Six Sigma Project Final Report Jan. 2011.doc                                                                                                                                         34
Six-Sigma Project Report


Appendix




           Six Sigma Project Final Report Jan. 2011.doc   35

More Related Content

What's hot

Introduction.pdf
Introduction.pdfIntroduction.pdf
Introduction.pdf
ssuser66b932
 
Basic Six Sigma Presentation
Basic Six Sigma PresentationBasic Six Sigma Presentation
Basic Six Sigma Presentationvivekissar
 
Presentation introduction to six sigma
Presentation   introduction to six sigmaPresentation   introduction to six sigma
Presentation introduction to six sigmajpanchpor
 
RMS Six Sigma Training 2010 Final
RMS Six Sigma Training 2010 FinalRMS Six Sigma Training 2010 Final
RMS Six Sigma Training 2010 FinalMichael Camp
 
Joint Commission International (JCI)
Joint Commission International (JCI)Joint Commission International (JCI)
Joint Commission International (JCI)
RadhaDeosthalee
 
Six Sigma DMAIC Case Study
Six Sigma DMAIC Case StudySix Sigma DMAIC Case Study
Six Sigma DMAIC Case Study
Body of Knowledge
 
Six Sigma
Six SigmaSix Sigma
Six Sigma
princegeet17
 
Clinical Governance
Clinical GovernanceClinical Governance
Clinical Governance
Dr. Shruti Aggarwal
 
Improving Emergency Room Efficiency & Service
Improving Emergency Room Efficiency & ServiceImproving Emergency Room Efficiency & Service
Improving Emergency Room Efficiency & Servicegtaylortpm
 
Six Sigma
Six SigmaSix Sigma
Six Sigmauzukhan
 
Fish bone diagram a problem solving tool
Fish bone diagram a problem solving toolFish bone diagram a problem solving tool
Fish bone diagram a problem solving tool
Dr.Hemant Kumar
 
QUALITY MANAGEMENT AND PATIENT SAFETY DIPLOMA BY JCI
QUALITY MANAGEMENT AND PATIENT SAFETY DIPLOMA BY JCI QUALITY MANAGEMENT AND PATIENT SAFETY DIPLOMA BY JCI
QUALITY MANAGEMENT AND PATIENT SAFETY DIPLOMA BY JCI
Healthcare consultant
 
Six sigma
Six sigma Six sigma
Six sigma
Chaitanya Chenna
 
ppt on patient satisfaction
 ppt on patient satisfaction ppt on patient satisfaction
ppt on patient satisfaction
AnkurAnkit3
 
Quality improvement healthcare final
Quality improvement healthcare finalQuality improvement healthcare final
Quality improvement healthcare finalEvanvs
 
5s-CQI-TQM For Hospital Quality Improvement
5s-CQI-TQM For Hospital Quality Improvement5s-CQI-TQM For Hospital Quality Improvement
5s-CQI-TQM For Hospital Quality Improvement
Zulfiquer Ahmed Amin
 
Lean six sigma tools and techniques
Lean six sigma tools and techniquesLean six sigma tools and techniques
Lean six sigma tools and techniques
Nikunj Rana
 

What's hot (20)

Introduction.pdf
Introduction.pdfIntroduction.pdf
Introduction.pdf
 
Basic Six Sigma Presentation
Basic Six Sigma PresentationBasic Six Sigma Presentation
Basic Six Sigma Presentation
 
Presentation introduction to six sigma
Presentation   introduction to six sigmaPresentation   introduction to six sigma
Presentation introduction to six sigma
 
RMS Six Sigma Training 2010 Final
RMS Six Sigma Training 2010 FinalRMS Six Sigma Training 2010 Final
RMS Six Sigma Training 2010 Final
 
Six sigma
Six sigmaSix sigma
Six sigma
 
Joint Commission International (JCI)
Joint Commission International (JCI)Joint Commission International (JCI)
Joint Commission International (JCI)
 
Six Sigma DMAIC Case Study
Six Sigma DMAIC Case StudySix Sigma DMAIC Case Study
Six Sigma DMAIC Case Study
 
Six Sigma
Six SigmaSix Sigma
Six Sigma
 
Clinical Governance
Clinical GovernanceClinical Governance
Clinical Governance
 
Quality improvement
Quality improvementQuality improvement
Quality improvement
 
Improving Emergency Room Efficiency & Service
Improving Emergency Room Efficiency & ServiceImproving Emergency Room Efficiency & Service
Improving Emergency Room Efficiency & Service
 
Six sigma ppt
Six sigma pptSix sigma ppt
Six sigma ppt
 
Six Sigma
Six SigmaSix Sigma
Six Sigma
 
Fish bone diagram a problem solving tool
Fish bone diagram a problem solving toolFish bone diagram a problem solving tool
Fish bone diagram a problem solving tool
 
QUALITY MANAGEMENT AND PATIENT SAFETY DIPLOMA BY JCI
QUALITY MANAGEMENT AND PATIENT SAFETY DIPLOMA BY JCI QUALITY MANAGEMENT AND PATIENT SAFETY DIPLOMA BY JCI
QUALITY MANAGEMENT AND PATIENT SAFETY DIPLOMA BY JCI
 
Six sigma
Six sigma Six sigma
Six sigma
 
ppt on patient satisfaction
 ppt on patient satisfaction ppt on patient satisfaction
ppt on patient satisfaction
 
Quality improvement healthcare final
Quality improvement healthcare finalQuality improvement healthcare final
Quality improvement healthcare final
 
5s-CQI-TQM For Hospital Quality Improvement
5s-CQI-TQM For Hospital Quality Improvement5s-CQI-TQM For Hospital Quality Improvement
5s-CQI-TQM For Hospital Quality Improvement
 
Lean six sigma tools and techniques
Lean six sigma tools and techniquesLean six sigma tools and techniques
Lean six sigma tools and techniques
 

Viewers also liked

Six sigma project report
Six sigma project reportSix sigma project report
Six sigma project report
mahtabsiddiqui
 
Six sigma full report
Six sigma full reportSix sigma full report
Six sigma full report
tapan27591
 
Optimizing Sterile Processing Workflow
Optimizing Sterile Processing WorkflowOptimizing Sterile Processing Workflow
Optimizing Sterile Processing Workflowdpjphx
 
new FINAL REPORT -A STUDY OF SIX SIGMA METHODOLOGY
new FINAL REPORT -A STUDY OF SIX SIGMA METHODOLOGYnew FINAL REPORT -A STUDY OF SIX SIGMA METHODOLOGY
new FINAL REPORT -A STUDY OF SIX SIGMA METHODOLOGYAlan Kurien Punnoose
 
Internship Report on Material Handling and Machinery
Internship Report on Material Handling and MachineryInternship Report on Material Handling and Machinery
Internship Report on Material Handling and Machinery
Akshay Mistri
 
PROJECT-HOSPITAL MANAGEMENT SYSTEM CHAP. 1 TO 4
PROJECT-HOSPITAL MANAGEMENT SYSTEM CHAP. 1 TO 4PROJECT-HOSPITAL MANAGEMENT SYSTEM CHAP. 1 TO 4
PROJECT-HOSPITAL MANAGEMENT SYSTEM CHAP. 1 TO 4
NICHOLAS RATEMO
 
Hospital management system project
Hospital management system projectHospital management system project
Hospital management system projectHimani Chopra
 
Hospital management system
Hospital management systemHospital management system
Hospital management system
Mohammad Safiullah
 
Hosptial information management system,hyderabad,india
Hosptial information management system,hyderabad,indiaHosptial information management system,hyderabad,india
Hosptial information management system,hyderabad,india
RADHAKRISHNA PUTREVU
 
Overview of Agile Team Facilitation
Overview of Agile Team FacilitationOverview of Agile Team Facilitation
Overview of Agile Team Facilitation
LuxoftAgilePractice
 
BANK MANAGEMENT SYSTEM report
BANK MANAGEMENT SYSTEM reportBANK MANAGEMENT SYSTEM report
BANK MANAGEMENT SYSTEM report
Nandana Priyanka Eluri
 
Improvement of Hospital Project Cost and Schedule Mgmt Final Rpt
Improvement of Hospital Project Cost and Schedule Mgmt  Final RptImprovement of Hospital Project Cost and Schedule Mgmt  Final Rpt
Improvement of Hospital Project Cost and Schedule Mgmt Final Rpt
Ed Kozak
 
Pc Shipping Improvement Six Sigma Case Study
Pc Shipping Improvement Six Sigma Case StudyPc Shipping Improvement Six Sigma Case Study
Pc Shipping Improvement Six Sigma Case Study
Steven Bonacorsi
 
ICG 6 sigma transformation
ICG 6 sigma transformationICG 6 sigma transformation
ICG 6 sigma transformation
Innovation Centric Group
 
Six sigma
Six sigmaSix sigma
Six sigma
mayureshhets1234
 
Six sigma implementation in it software product industry – a case study
Six sigma implementation in it software product industry – a case studySix sigma implementation in it software product industry – a case study
Six sigma implementation in it software product industry – a case studyIAEME Publication
 
Case study quality improvement in steel making plant using six sigma dmaic ...
Case study   quality improvement in steel making plant using six sigma dmaic ...Case study   quality improvement in steel making plant using six sigma dmaic ...
Case study quality improvement in steel making plant using six sigma dmaic ...Ganesh Chouhan
 
Project on pharmaceutical industry
Project on pharmaceutical industryProject on pharmaceutical industry
Project on pharmaceutical industry
Vamsi bodavula
 

Viewers also liked (20)

Six sigma project report
Six sigma project reportSix sigma project report
Six sigma project report
 
Six sigma full report
Six sigma full reportSix sigma full report
Six sigma full report
 
Optimizing Sterile Processing Workflow
Optimizing Sterile Processing WorkflowOptimizing Sterile Processing Workflow
Optimizing Sterile Processing Workflow
 
new FINAL REPORT -A STUDY OF SIX SIGMA METHODOLOGY
new FINAL REPORT -A STUDY OF SIX SIGMA METHODOLOGYnew FINAL REPORT -A STUDY OF SIX SIGMA METHODOLOGY
new FINAL REPORT -A STUDY OF SIX SIGMA METHODOLOGY
 
Internship Report on Material Handling and Machinery
Internship Report on Material Handling and MachineryInternship Report on Material Handling and Machinery
Internship Report on Material Handling and Machinery
 
PROJECT-HOSPITAL MANAGEMENT SYSTEM CHAP. 1 TO 4
PROJECT-HOSPITAL MANAGEMENT SYSTEM CHAP. 1 TO 4PROJECT-HOSPITAL MANAGEMENT SYSTEM CHAP. 1 TO 4
PROJECT-HOSPITAL MANAGEMENT SYSTEM CHAP. 1 TO 4
 
Hospital management system project
Hospital management system projectHospital management system project
Hospital management system project
 
Hospital management system
Hospital management systemHospital management system
Hospital management system
 
Hosptial information management system,hyderabad,india
Hosptial information management system,hyderabad,indiaHosptial information management system,hyderabad,india
Hosptial information management system,hyderabad,india
 
Overview of Agile Team Facilitation
Overview of Agile Team FacilitationOverview of Agile Team Facilitation
Overview of Agile Team Facilitation
 
BANK MANAGEMENT SYSTEM report
BANK MANAGEMENT SYSTEM reportBANK MANAGEMENT SYSTEM report
BANK MANAGEMENT SYSTEM report
 
Improvement of Hospital Project Cost and Schedule Mgmt Final Rpt
Improvement of Hospital Project Cost and Schedule Mgmt  Final RptImprovement of Hospital Project Cost and Schedule Mgmt  Final Rpt
Improvement of Hospital Project Cost and Schedule Mgmt Final Rpt
 
Group project report
Group project reportGroup project report
Group project report
 
Pc Shipping Improvement Six Sigma Case Study
Pc Shipping Improvement Six Sigma Case StudyPc Shipping Improvement Six Sigma Case Study
Pc Shipping Improvement Six Sigma Case Study
 
Ab1
Ab1Ab1
Ab1
 
ICG 6 sigma transformation
ICG 6 sigma transformationICG 6 sigma transformation
ICG 6 sigma transformation
 
Six sigma
Six sigmaSix sigma
Six sigma
 
Six sigma implementation in it software product industry – a case study
Six sigma implementation in it software product industry – a case studySix sigma implementation in it software product industry – a case study
Six sigma implementation in it software product industry – a case study
 
Case study quality improvement in steel making plant using six sigma dmaic ...
Case study   quality improvement in steel making plant using six sigma dmaic ...Case study   quality improvement in steel making plant using six sigma dmaic ...
Case study quality improvement in steel making plant using six sigma dmaic ...
 
Project on pharmaceutical industry
Project on pharmaceutical industryProject on pharmaceutical industry
Project on pharmaceutical industry
 

Similar to Six Sigma Case Cart Project Final Report Jan. 2011

A LEAN SIX SIGMA APPROACH TO REDUCE WAITING AND REPORTING TIME IN THE RADIOLO...
A LEAN SIX SIGMA APPROACH TO REDUCE WAITING AND REPORTING TIME IN THE RADIOLO...A LEAN SIX SIGMA APPROACH TO REDUCE WAITING AND REPORTING TIME IN THE RADIOLO...
A LEAN SIX SIGMA APPROACH TO REDUCE WAITING AND REPORTING TIME IN THE RADIOLO...
Joe Andelija
 
Workflow Continuity—Moving Beyond Business Continuityin a Mu.docx
Workflow Continuity—Moving Beyond Business Continuityin a Mu.docxWorkflow Continuity—Moving Beyond Business Continuityin a Mu.docx
Workflow Continuity—Moving Beyond Business Continuityin a Mu.docx
ambersalomon88660
 
This is a study case in all the photosthe SIPOC diagram bel.pdf
 This is a study case in all the photosthe SIPOC diagram bel.pdf This is a study case in all the photosthe SIPOC diagram bel.pdf
This is a study case in all the photosthe SIPOC diagram bel.pdf
jkcs20004
 
2 Brian Hudson Lean 6 Sigma
2 Brian Hudson Lean 6 Sigma2 Brian Hudson Lean 6 Sigma
2 Brian Hudson Lean 6 Sigmagueste681ce
 
Center for the Future of Surgery Intake Process Problem
Center for the Future of Surgery Intake Process ProblemCenter for the Future of Surgery Intake Process Problem
Center for the Future of Surgery Intake Process ProblemAwonti etoo
 
1.  Patient Safety is a health care professionals’ duty. A sur.docx
1.    Patient Safety is a health care professionals’ duty. A sur.docx1.    Patient Safety is a health care professionals’ duty. A sur.docx
1.  Patient Safety is a health care professionals’ duty. A sur.docx
SONU61709
 
Lean Scheduling in Operating Rooms
Lean Scheduling in Operating RoomsLean Scheduling in Operating Rooms
Lean Scheduling in Operating RoomsWilliam Reau
 
Healthcare Six Sigma Project
Healthcare Six Sigma ProjectHealthcare Six Sigma Project
Healthcare Six Sigma Project
Michael Floriani
 
Develop a schedule for a healthcare website redesign project. Where .pdf
Develop a schedule for a healthcare website redesign project. Where .pdfDevelop a schedule for a healthcare website redesign project. Where .pdf
Develop a schedule for a healthcare website redesign project. Where .pdf
SALES97
 
Stellar Performer Seattle Childrens Hospital and Regional Medica.docx
Stellar Performer Seattle Childrens Hospital and Regional Medica.docxStellar Performer Seattle Childrens Hospital and Regional Medica.docx
Stellar Performer Seattle Childrens Hospital and Regional Medica.docx
whitneyleman54422
 
Dataimage9 45.png dataimage7-31.pngdataimage4-47.png
Dataimage9 45.png dataimage7-31.pngdataimage4-47.pngDataimage9 45.png dataimage7-31.pngdataimage4-47.png
Dataimage9 45.png dataimage7-31.pngdataimage4-47.png
nand15
 
Dataimage9-45.pngDataimage7-31.pngDataimage4-47.png
Dataimage9-45.pngDataimage7-31.pngDataimage4-47.pngDataimage9-45.pngDataimage7-31.pngDataimage4-47.png
Dataimage9-45.pngDataimage7-31.pngDataimage4-47.png
OllieShoresna
 
Requirements Workshop Agenda eGrants ProjectDa.docx
Requirements Workshop Agenda        eGrants ProjectDa.docxRequirements Workshop Agenda        eGrants ProjectDa.docx
Requirements Workshop Agenda eGrants ProjectDa.docx
adkinspaige22
 
Organize a ProjectTop of FormBottom of FormAssignment Conten.docx
Organize a ProjectTop of FormBottom of FormAssignment Conten.docxOrganize a ProjectTop of FormBottom of FormAssignment Conten.docx
Organize a ProjectTop of FormBottom of FormAssignment Conten.docx
LacieKlineeb
 
Six Sigma Improves Healthcare Operations
Six Sigma Improves Healthcare OperationsSix Sigma Improves Healthcare Operations
Six Sigma Improves Healthcare OperationsWilliam LaFollette
 
OPS574 v1Process Improvement FlowchartOPS574 v1Page 2 of 2.docx
OPS574 v1Process Improvement FlowchartOPS574 v1Page 2 of 2.docxOPS574 v1Process Improvement FlowchartOPS574 v1Page 2 of 2.docx
OPS574 v1Process Improvement FlowchartOPS574 v1Page 2 of 2.docx
LacieKlineeb
 
U Of I Slides 11 09
U Of I Slides 11 09U Of I Slides 11 09
U Of I Slides 11 09
rblackwell46
 
Case Study Stellar Performer Seattle Children’s Hospital and Regi.docx
Case Study Stellar Performer Seattle Children’s Hospital and Regi.docxCase Study Stellar Performer Seattle Children’s Hospital and Regi.docx
Case Study Stellar Performer Seattle Children’s Hospital and Regi.docx
wendolynhalbert
 
Reducing Inefficency on the Obstetric Service
Reducing Inefficency on the Obstetric ServiceReducing Inefficency on the Obstetric Service
Reducing Inefficency on the Obstetric ServiceRobert Knuppel
 

Similar to Six Sigma Case Cart Project Final Report Jan. 2011 (20)

A LEAN SIX SIGMA APPROACH TO REDUCE WAITING AND REPORTING TIME IN THE RADIOLO...
A LEAN SIX SIGMA APPROACH TO REDUCE WAITING AND REPORTING TIME IN THE RADIOLO...A LEAN SIX SIGMA APPROACH TO REDUCE WAITING AND REPORTING TIME IN THE RADIOLO...
A LEAN SIX SIGMA APPROACH TO REDUCE WAITING AND REPORTING TIME IN THE RADIOLO...
 
Workflow Continuity—Moving Beyond Business Continuityin a Mu.docx
Workflow Continuity—Moving Beyond Business Continuityin a Mu.docxWorkflow Continuity—Moving Beyond Business Continuityin a Mu.docx
Workflow Continuity—Moving Beyond Business Continuityin a Mu.docx
 
This is a study case in all the photosthe SIPOC diagram bel.pdf
 This is a study case in all the photosthe SIPOC diagram bel.pdf This is a study case in all the photosthe SIPOC diagram bel.pdf
This is a study case in all the photosthe SIPOC diagram bel.pdf
 
2 Brian Hudson Lean 6 Sigma
2 Brian Hudson Lean 6 Sigma2 Brian Hudson Lean 6 Sigma
2 Brian Hudson Lean 6 Sigma
 
Center for the Future of Surgery Intake Process Problem
Center for the Future of Surgery Intake Process ProblemCenter for the Future of Surgery Intake Process Problem
Center for the Future of Surgery Intake Process Problem
 
1.  Patient Safety is a health care professionals’ duty. A sur.docx
1.    Patient Safety is a health care professionals’ duty. A sur.docx1.    Patient Safety is a health care professionals’ duty. A sur.docx
1.  Patient Safety is a health care professionals’ duty. A sur.docx
 
Lean Scheduling in Operating Rooms
Lean Scheduling in Operating RoomsLean Scheduling in Operating Rooms
Lean Scheduling in Operating Rooms
 
Healthcare Six Sigma Project
Healthcare Six Sigma ProjectHealthcare Six Sigma Project
Healthcare Six Sigma Project
 
Develop a schedule for a healthcare website redesign project. Where .pdf
Develop a schedule for a healthcare website redesign project. Where .pdfDevelop a schedule for a healthcare website redesign project. Where .pdf
Develop a schedule for a healthcare website redesign project. Where .pdf
 
Stellar Performer Seattle Childrens Hospital and Regional Medica.docx
Stellar Performer Seattle Childrens Hospital and Regional Medica.docxStellar Performer Seattle Childrens Hospital and Regional Medica.docx
Stellar Performer Seattle Childrens Hospital and Regional Medica.docx
 
Dataimage9 45.png dataimage7-31.pngdataimage4-47.png
Dataimage9 45.png dataimage7-31.pngdataimage4-47.pngDataimage9 45.png dataimage7-31.pngdataimage4-47.png
Dataimage9 45.png dataimage7-31.pngdataimage4-47.png
 
Dataimage9-45.pngDataimage7-31.pngDataimage4-47.png
Dataimage9-45.pngDataimage7-31.pngDataimage4-47.pngDataimage9-45.pngDataimage7-31.pngDataimage4-47.png
Dataimage9-45.pngDataimage7-31.pngDataimage4-47.png
 
Requirements Workshop Agenda eGrants ProjectDa.docx
Requirements Workshop Agenda        eGrants ProjectDa.docxRequirements Workshop Agenda        eGrants ProjectDa.docx
Requirements Workshop Agenda eGrants ProjectDa.docx
 
Organize a ProjectTop of FormBottom of FormAssignment Conten.docx
Organize a ProjectTop of FormBottom of FormAssignment Conten.docxOrganize a ProjectTop of FormBottom of FormAssignment Conten.docx
Organize a ProjectTop of FormBottom of FormAssignment Conten.docx
 
Six Sigma Improves Healthcare Operations
Six Sigma Improves Healthcare OperationsSix Sigma Improves Healthcare Operations
Six Sigma Improves Healthcare Operations
 
Craft_2013-1
Craft_2013-1Craft_2013-1
Craft_2013-1
 
OPS574 v1Process Improvement FlowchartOPS574 v1Page 2 of 2.docx
OPS574 v1Process Improvement FlowchartOPS574 v1Page 2 of 2.docxOPS574 v1Process Improvement FlowchartOPS574 v1Page 2 of 2.docx
OPS574 v1Process Improvement FlowchartOPS574 v1Page 2 of 2.docx
 
U Of I Slides 11 09
U Of I Slides 11 09U Of I Slides 11 09
U Of I Slides 11 09
 
Case Study Stellar Performer Seattle Children’s Hospital and Regi.docx
Case Study Stellar Performer Seattle Children’s Hospital and Regi.docxCase Study Stellar Performer Seattle Children’s Hospital and Regi.docx
Case Study Stellar Performer Seattle Children’s Hospital and Regi.docx
 
Reducing Inefficency on the Obstetric Service
Reducing Inefficency on the Obstetric ServiceReducing Inefficency on the Obstetric Service
Reducing Inefficency on the Obstetric Service
 

Six Sigma Case Cart Project Final Report Jan. 2011

  • 1. Six-Sigma Project Report Hospital Surgical Case Cart Completion Six-Sigma Project By Dan Johnson Final Report January 2011 Six Sigma Project Final Report Jan. 2011.doc 1
  • 2. Six-Sigma Project Report TABLE OF CONTENTS Executive Review……………………………………………………………...3 1. Overview; Project Selection 1.1 Background Information…………………………………….…………..4 1.2 Problems and Symptoms………………………………………………...5 2. Define 2.1 Goals and Expected Results……………………………………………...6 2.2 Framework………………………………………………………………10 2.3 Assumptions ……………………………………………………….……17 3. Measurement 3.1 Study, Late Case Carts, Missing Items, Case Delays……………….…18 3.2 Statistical Results and Sigma Level Calculation……………..………..23 4. Analysis 4.1 Cause and Effect…………………………………………….…………..24 4.2 Pareto………………………………………………………………...…..24 4.3 Action Item List……………………………..…………………………..26 5. Improvement…………………………………………………………………27 6. Control 6.1 Process, Standardized Work…………………………...……………….30 6.1 Metrics…………………………………………………………………....30 7. Conclusion and Outlook 7.1 Sigma Calculation……………………………………………….………33 7.2 Savings Summary………………………………………….……………34 Appendix: Process Flow Six Sigma Project Final Report Jan. 2011.doc 2
  • 3. Six-Sigma Project Report Executive Review This hospital‟s Surgical Services and associated Operating Room (OR) and Sterile Processing and Distribution (SPD) are faced with many strategic growth decisions that provide both challenges and rewards. While there are many positive attributes within the Sterile Processing Department, surgical staff, hospital administration and the surgeon‟s committees have made keenly known their concern and dissatisfaction with the delays and time wasted due to lack of complete and ready surgical case carts, or case supplies. The hospital hasn‟t established a Lean or 6-sigma based process improvement methodology, however C-level executives are aware of the power of the approaches in facilitating improvement and therefore sanctioned a process improvement project focused on these concerns. For purposes of external publication, the facilities name and location is omitted and will simply be referred to as “the hospital” or similar designation. A team was assembled under my direction and consisted of eight individuals, participating as necessary over the course of the project. One of the team members is concurrently pursuing a green belt certification, although not through Aveta. The team applied the DMAIC methodology to the process of supplying the Operating Room (OR) with supplies and equipment required in the performance of surgical procedures (cases) with the intent of improving the number of cases for which all supplies are available at the time of need. The team drew upon some Lean knowledge, as well during the implementation phase. The project report is presented in alignment with the DMAIC 6- sigma phases. In the Define phase, we drew up a project charter, specified and quantified our goals and determined a method to track savings. We continued with a project plan and high-level task list outlining each team member‟s responsibilities. A rough process map was developed to ensure our understanding of the process and to provide a framework for improvement activities. An early discovery during the Measurement phase showed that the reporting capability in the OR limited the use of historical information for measurement or performance analysis, therefore the team was required to conduct detailed observations to understand the true nature of the delays being reported by the OR. During this phase we also began soliciting suggestions from SPD and OR personnel. A SIPOC and a HOQ were developed to assist the team in better understanding the relationships of the inputs and outputs to the process, its vendors and customers. During the Analyze phase Ishakawa charting was used to understand cause and affect relationships. This lead to brainstorming of the possible root-causes and ultimately was used to populate an Action Item List that is still in use to facilitate and monitor the ongoing process changes. A significant change brought about by the team involved completing a spaghetti diagram of the supply pick process; the results which included the implementation of a 2-bin kanban system and reorganization of the supplies storage area to align with the pick ticket sequence. During this phase the team reviewed the data collected during the observation period and quantified the scope of the incomplete case Six Sigma Project Final Report Jan. 2011.doc 3
  • 4. Six-Sigma Project Report cart issues. Note: case carts refer to the system of picking and delivering all supplies and instruments needed for the performance of a surgical case. The Improvement phase allowed the team the opportunity to implement a large number of the process improvement items detailed in their Action Item List and to begin measuring their impact. Detailed process flows were developed to help in the change process and to enlist buy-in from the technicians responsible. While many items remain to be accomplished the team focused on those that would have the greatest or most immediate impact to the process with the intent of quickly improving the satisfaction levels of the OR surgical personnel. A series of metrics closely aligned with the key data from the Measurement phase was installed at the same time, so impact could be quantified from the onset. The series of metrics mentioned before is now used daily to track and trend performance against an established baseline. This provides the Control element for the processes and allows for the quantification of impact as well as ensuring that the gains made will be sustained. 1. Overview; Project Selection 1.1. Background Information The hospital is one of a network of hospitals located in the southern US. The hospital offers general healthcare and wide variety surgical services including reconstructive, cardiovascular, urology, etc, utilizing 29 OR suites. Approximately 22% of its surgical caseload is in the fields of orthopedics and spine, both heavily supply and instrument intensive. The case volume for 12 calendar months ending July 2010 was about 33,000, split nearly equal in-patient to out-patient, although the trend for the past few years has been increasing the out-patient percentage. The OR conducts business typically from 7:30 am to 5:00 pm Monday through Friday, but often extends late into the evening. Saturday cases are not considered scheduled, but several routinely occur each weekend. A key support service to the OR caseload is the reprocessing of surgical instrumentation and the assembly and distribution of Case Carts (customized kitting of supplies and instruments) by the Sterile Processing Department (SPD). The SPD is responsible for the cleaning, reassembly and sterilization of surgical instruments following a case and in preparation for those instruments to be reused. The SPD is also tasked with supply/inventory control and preparing case carts for use in the OR. The SPD operation runs 24-7. Quality is thought of in the relative terms of Clean and Sterile, Complete and On-time and is quickly becoming a focus within hospitals as accrediting agencies begin to look more closely at this part of the operation than ever before. Recently the noise level from surgeons and the hospital‟s surgical staff about the state of affairs regarding incomplete case carts and instruments sets had increased to the point of administrative concern. It was generally felt that something needed to be done, but efforts internal to the SPD had Six Sigma Project Final Report Jan. 2011.doc 4
  • 5. Six-Sigma Project Report proved fruitless and the department was taking a serious rap for its poor quality and delivery reliability, though no supporting numbers were presented. The hospital doesn‟t have an established process improvement methodology, but executives are acutely aware of improvements made in other hospitals using Lean or 6- Sigma methodologies, or a combination and believe that the 6-sigma approach may be a powerful tool to detect and reduce errors in the process. While not setting themselves up with a process improvement department they did agree to support the team approach to addressing these issues. That the process involved here is more service than production oriented it seems a challenge to utilize many of the 6-sigma statistical tools. However, it is their hope that the DMAIC provides the blueprint for solving and eliminating the problems they now face. 1.2. Problems and Symptoms It is important to separate the noise from the real issues. Many of the same stories of case delays (late starts) are heard time and again throughout the hospital hallways. Weekly review after weekly review raised many of the same concerns. The OR record keeping system contains some information related to reasons for delays. However the system is inconclusive as it allows only a single reason code to be entered for case delay and while this is considered to be the primary reason there may be multiple factors and reality is that input often serves the person recording the code. The team initially created a Pareto from the OR data to begin to understand the opportunities rough order of magnitude. See Figure 1. Figure 1. OR Case Delay by Reason Code OR Recorded Case Delay by Reason Code Percentage PREVIOUS CASE OVER SCHEDULED TIME SURGEON LATE OTHER OTHER PREFERENCE CARD DISCREPANCY OTHER ANESTHESIA LATE PATIENT LATE TO HOSPITAL INSTRUMENTS NOT STERILE EQUIPMENT/INSTS NOT REQUESTED WHEN SCHEDULED H&P NOT DICTATED-WRITTEN IN HOLDING OTHER SURGEON DELAYED IN OTHER ROOM LABS NOT AVAILABLE TRANSPORT TEAM DELAY IMPLANTS NOT AVAILABLE ROOM NOT SET UP PROPERLY EQUIPMENT NOT AVAILABLE PHYSICIAN REQUEST CHANGE IN LINE UP PATIENT DELAYED IN ADMITTING EKG NOT DONE/AVAILABLE NO MD ORDERS DIFFICULT INTUBATION EMERGENCY BUMP INSTRUMENTS NOT ORDERED SCHEDULING CONFLICT BLOOD BANK DELAY PHARMACY MEDS NEEDED CONSENT INCOMPLETE/INACCURA TE H&P DICTATED NOT TRANSCRIBED PATIENT DELAYED IN OPSU C SECTION BUMP XRAYS NOT DONE/UNAVAILABLE ANESTHESIA NOT AVAILABLE ADDITIONAL TESTS REQUESTED BY SURGEON/ANESTHESIA DIFFICULT IV START PATIENT DIRECT ON A VENT/ISOLATION PATIENT REQUESTED TO SPEAK TO MD PATIENT WAITING FOR FAMILY PACU SATURATED NOT ENOUGH STAFF TO START CASE CONSENT DOES NOT MATCH SCHEDULE UNANTICIPATED MULTIPLE LINES PROCTOR NOT AVAILABLE ASSISTANT NOT AVAILABLE ADDITIONAL MD CONSULT REQUESTED PATIENT NOT NPO NEEDS TRANSLATOR TRAUMA BUM BED NOT AVAILABLE ON ICU BED NOT AVAILABLE ON FLOOR SCRUB PERSON NOT READY BIOMED DELAY IN CHECKING EQUIPMENT EQUIPMENT MALFUNCTION OUTSIDE SERVICE PROVIDER DELAY SURGICAL CHECKLIST NOT COMPLETE FROM SENDING UNIT XRAY TECH/CARM UNAVAILABLE 0.00% 5.00% 10.00% 15.00% 20.00% 25.00% Six Sigma Project Final Report Jan. 2011.doc 5
  • 6. Six-Sigma Project Report Note that the highlighted reasons are each related to the proper availability of supplies or instruments needed for the case. While no single reason recorded would lead a team to tackle it as the top offender, the aggregate of all related to supplies supports the concern of the hospital administration. This chart indicates that approximately 13% of delayed cases are so by virtue of missing supplies or instruments. The story is compelling enough to move forward with a project and ultimately drove the project more than adequate ROI analysis and comparison to other opportunities. 2. Define 2.1. Goals and Expected Results Prior to assemblage of a 6-sigma team the Green Belt candidate and I developed a charter and had it approved and sponsored by the Sr. VP Perioperative Service. See Figure 2.1. The primary goal of the team is to decrease the number of surgical case carts that are delivered to the OR incomplete. The goal is further broken down into 1st and 2nd Cases and all other cases. The thought behind this is two-fold. First, getting a good start to the day helps ensure surgeon satisfaction. Second, the availability of some instrument sets is impacted by the timing of their use in cases earlier in the day. The lack of adequate instrumentation may be a focal point of the team during the project. The business case for this improvement is that improved service and delivery of complete case carts reduces the hours spent by both OR and SPD personnel in later searching for the missing items and may result in the recapture of enough OR time to provide availability for additional revenue generation. As well as the OR Pareto shown in Figure 1, a Project Evaluation and Cash Flow projection is developed along with a set of base data and savings projection. The base and savings projection are compiled through the course of the Define and Measurement phases and is finalized upon completion of the base data analysis. See Figures 2.2, 2.3 and 2.4. The cash flow projection is predicated on the estimated FTE weeks that specific team members will be utilized across the course of the project. Salary considerations are expected to be about $76,900 over 3 months and we plan to have a couple of team dinners and minor project expenses. The sponsor wasn‟t concerned about capturing costs associated with hospital conference rooms as some are nearly always available for the team meetings and working sessions. Overall ROI is anticipated to be 4.4 to 1, assuming all hard and soft-savings targets are hit. Six Sigma Project Final Report Jan. 2011.doc 6
  • 7. Six-Sigma Project Report Figure 2.1 6-Sigma Project Charter Six-Sigma Project Charter / Client Hospital Product or Service Case Cart OR Delivery Expected Project Savings ($) $ 350,000 Impacted Facilitator Dan Johnson Business Unit CSP/OR Champion Ms. Jackson Phone Number for Facilitator 602-448-5704 Start Date 8/10/10 Target Completion Date 11/30/10 Element Description Team Charter 1. Process: Case Cart Assembly and Delivery Need to reduce the overall number of case carts delivered incomplete to less than 25% and 1st and 2nd cases to less than 5% by end of November 2010 2. Project Description: Problem and goal statement (project‟s purpose) Eliminate the causes of case carts being delivered what is the Case Cart delivered to the ORs missing trays incomplete and wet. “Practical Problem” and supplies. Wet case carts 3. Objective: Improvement is sought in 1) ensuring that all Project „available” items are picked to the case cart, Y’s Baseline GOAL Unit of units Measure 2) “items unavailable‟ at time of pick are 1st and 82 95 # Case % recorded and follow-up accomplished, 2nd case Carts comple tion 3) Reasons for “items unavailable” documented Overall 60 75 # Case % and used for next steps. case Carts comple tion OR 194; 1st 2nd 54 # Delay # Delay cases Mins (Mins / 274 all 171 Day) others Savings Metrics will include OR Delay minutes OR 324; 1st 2nd 90 # Staff # per case resulting in increased OR utilization Staff cases mins and OR Staff minutes used tracking the missing Time 456 all 285 items. (Mins / others Day) 4. Business Cases: Expected financial improvement, or other Improved service to the OR and decreased OR Starts justification. delayed due to incomplete cases carts. Will decrease labor hours spent on location and recovery. 5. Stakeholder Team Names and roles of team members? CSP Case Cart Tech(X2) – M. Hendersen, J. Maliford members: OR Staff – J. Rodriguez, C. Nestman (Greenbelt) CSP Leadership – R. Sanchez 6. Project Scope: Which part of the process will be investigated Case Cart Assembly, Transport and Staging. and excluded. Storage Location Control Completeness of reporting 7. Benefit to External Who are the final customers, what are their key Patients, OR Staff and Surgeons; Improved delivery Customers: measures, and what benefits will they see? performance, improved OR Start Times 8. Schedule: Give the key milestones/dates. Project Kick-off, August 10, 2010 Define, Set Goals, Proc Map & AIL Review M- Measurement, Metrics validation, Success “M” Completion August 25,2010 Metrics A- Analysis “A” Completion September 18, 2010 I- Improvement “I” Completion September 25, 2010 C- Control “C” Completion October 10,2010 Note: Schedule appropriate Safety Reviews. Safety Reviews October 10, 2010 Project Completion November 30,2010 9. Support Required: Will any special capabilities, hardware, trials, Meeting room, LCD Overhead, Flip Charts etc be needed? Six Sigma Project Final Report Jan. 2011.doc 7
  • 8. Six-Sigma Project Report Figure 2.2 Project Evaluation Score Interpretation 10 Sponsorship 10 External Customer 3 Shareholder 3 Employee or Internal Customer 3 Other (supplier, environment, etc.) 4.75 - Total Benefit 3 Availabilty of resources other than team 3 Scope in terms of Black Belt effort 10 Deliverable 3 Time to Complete 3 Team 10 Project Charter 10 Value of Six Sigma Approach 59.225 Total Six Sigma Project Final Report Jan. 2011.doc 8
  • 9. Base Data and Savings Projection Summary Baseline Goal Delay Goal Delay Delay OR OR Staff Cost per Minutes Goal OR Incomplete OR Lost Lost Cost per Cost Daily Minutes OR Staff Staff Total Delay Saved Daily Cost Staff Cost Goal Total Resulting Delayed Minutes Minutes OR Delay Lost per Minutes Minute Cost Daily Cost per (50% Delay Saving Minutes Saving Savings per # Cases Complete Incomplete in OR Delay Cases per Case per Day Minute OR Min Case per Day (Burdened) Staff Min Day Complete Minutes Per Goal Saved Goal Day Daily Avg. % # # % # Min Min $ $ Min Min $ $ $ % # Min $ Min $ $ 1st & 2nd Cases 60 82% 49 11 15% 1.6 18 29 $ 40 $ 1,166 30 324 $ 0.63 $ 205 $ 1,372 95% 57 14.58 $ 583 234 $ 148 $ 731 Six-Sigma Project Report Remaining Cases 38 60% 23 15 10% 1.5 18 27 $ 40 $ 1,094 30 456 $ 0.63 $ 289 $ 1,383 75% 29 13.68 $ 547 171 $ 108 $ 656 Total Daily 98 73% 72 26 3.1 56.52 $ 2,261 780 $ 494 $ 2,755 86 28.26 $ 1,130 405 $ 257 $ 1,387 Average Annual @ 260 surgical days 25480 18720 6760 816 14695 $ 587,808 202800 $ 128,440 $ 716,248 22230 7348 $293,904 105300 $ 66,690 $ 360,594 Figure 2.3 Base and Savings 27 Day Month 2646 1944 702 84.78 1526.04 $ 61,042 21060 13338 74380 2309 763.02 $ 30,521 10935 $ 6,925.5 $ 37,446.3 Estmated % case delays resulting in a lost case = 20% Plan to recover 50% of that potential Total Six Sigma Project Final Report Jan. 2011.doc Recoverable project OR Minutes Daily Cast Savings Annually worth 28 $ 1,130 $293,904 $ 360,594 9
  • 10. Six-Sigma Project Report Figure 2.4 Cash Flow Projections Project Cash Flow Projection Case Cart Completion Project $400,000 Approximate Annual Savings: $350,000 $350,000 Project Cost: $78, 781 $300,000 ROI: 4.4 to 1 $250,000 $200,000 $150,000 $100,000 $50,000 $0 1 3 5 7 9 11 13 15 17 19 21 23 25 27 29 31 33 35 37 39 41 43 45 47 49 51 Project Week Cum Projected Savings Cum Project Cost Planned Out-of-Pocket 2.2. Project Framework A high-level task plan (fig. 2.5) laid out the team members primary responsibilities and tasks for the project and was later detailed in the Project Gantt Chart for schedule adherence and reporting (fig. 2.6) Six Sigma Project Final Report Jan. 2011.doc 10
  • 11. Six-Sigma Project Report Figure 2.5 Task Plan High Level Task and Responsibility TASK Responsibility Date Due Complete Charter ___ Indentify Opportunity Dan Johnson 25-Jul ___ Identify Sponsor Dan Johnson 25-Jul ___ Estimate Savings Dan Johnson 29-Jul ___ Draft Charter Dan / Ms. Jackson 2-Aug ___ Sponsor project review (weekly) Dan / Ms. Jackson 2-Aug Define ___ Team selection Dan / Ms. Jackson 3-Aug ___ Complete Charter Dan Johnson 4-Aug ___ Team Training Dan Johnson, Green belt ( Cory Nestman) 12-Aug ___ Review existing documentation Dan Johnson, Cory nestman 15-Aug Define objectives and develop ___ plan Team 8-Aug ___ Develop Plan Gannt Chart Cory Nestman 10-Aug Present objectives and plan to ___ management Cory Nestman 10-Aug ___ Map As-Is process Team 15-Aug Review and redefine ___ problem/opportunity Team 20-Aug ___ Sponsor sign-off Ms. Jackson 22-Aug Measure ___ Identify CTQs Cory Nestman 15-Aug Collect data on event tasks and ___ cycle time Team 22-Aug Determine and validate ___ measurement system Dan Johnson, Cory Nestman 25-Aug Analyze Prepare baseline graphs on event ___ tasks and cycle time Dan Johnson, Cory Nestman 25-Aug Analyze impacts on tasks and cycle ___ times Dan Johnson, Cory Nestman 5-Sep Evaluate time and value, risk ___ management Team 5-Sep ___ Benchmark other companies Malik 10-Sep ___ Discuss team's preliminary findings Team 12-Sep Consolidate team's findings and ___ analysis (additional brainstorming) Team 16-Sep Improve Present recommendations to ___ process owners and operators Team 18-Sep Review recommendations and ___ formulate beta Team 18-Sep ___ Prepare Beta Dan Johnson, Cory Nestman 21-Sep ___ Run beta (test improved process) Team 24-Sep ___ Analyze beta and results Dan Johnson, Cory Nestman 24-Sep ___ Present final presentation Team 25-Sep Present final recommendations to ___ management team Team 28-Sep Control ___ Develop Control Metrics Dan Johnson, Cory Nestman 21-Sep ___ Develop metrics collection tool Cory Nestman 21-Sep ___ Roll out improved process Team 29-Sep ___ Roll out metrics Team 29-Sep Monitor process monthly, using ___ control metrics Team 10-Oct Six Sigma Project Final Report Jan. 2011.doc 11
  • 12. Six-Sigma Project Report Figure 2.6 Project Gantt Chart Six Sigma Project Final Report Jan. 2011.doc 12
  • 13. Six-Sigma Project Report The SIPOC is used to focus the team‟s scope of work. Figure 2.7 illustrates this project‟s SIPOC ensuring that the team doesn‟t try to resolve issues with the entire instrument and supply flow from between the SPD and the OR. For example, while purchasing and warehouse distribution certainly have an impact on the availability of supplies, it is considered outside the scope of this project. The focus will be on the interrelationship between the SPD and the OR and the staff‟s ability to accomplish the task of completing case carts and delivering them on time to the OR. Figure 2.7 Case Cart SIPOC SIPOC DIAGRAM Case Cart Completion Improvement Project SIPOC Help Supplier ► Input ► Process ► Output ► Customer Surgeon's offices Call to OR Planners Surgical Schedule OR Planners and Team Leaders Print Surgery OR Planners OR Surgery Scheduling System Or Schedule for Reference Case Pick Technicians Schedule Surgeon's offices Surgery Equipment, Instruments Print Preference Pick Lists OR Planners and Supplies req'd Cards / Pick Lists Priority / Conflict Management Case Pick Technicians Case Pick Technicians Schedule Assign CSP CSP Management Pick assignments to technicians OR Staff and assignment Resources to Pick Case Carts clean and staged OR; Post use Decontamination cart wash Obtain Clean, Dry ready for use Case Pick Technicians Case Carts Complete Case Carts; Ready for Cardinal HSS Warehouse / distribution Pick Soft Goods and OR Staff surgical use Document on Preference Card Pick Instrumemts Complete Case Carts; Ready for OR and Vendors (Loaners) CSP and Document on surgical use OR Staff Preference Card Priority Needs List CSP Staff Sign Pick List and Completeness acknowledged and Case Pick Techs Completed and signed pick list Surgery Schedule OR Staff accounted for by tech On time case starts, satisfied Case Pick Techs Complete Case Carts Deliver to the OR customers OR, Doctors, Patients Metrics Metrics -Surgeon's scheduling -Surgery Schedule Timeliness Timeliness and accuracy -Surgeon's Need's -Needs List Percentage accuracy -CSP Absentee rate -Case Cart Completion Rate -CSP case Pick Technician -OR On-time Starts skills set -Cardinal and HSS distribution Fill Rates -Vendor delivery performance (Timeliness and accuracy) -Case Cart Completion Percentage Six Sigma Project Final Report Jan. 2011.doc 13
  • 14. Six-Sigma Project Report Along with the SIPOC a House of Quality was used to correlate and weight the various customer requirements with the functional “Hows” of the process. This tool with the later used fishbone helped the team to identify and quantify specific issues and eventually determine the tasks required to address the problems. Figure 2.8 is the HOQ developed and being two layers is spread over the next several pages. Figure 2.8 House of Quality Six Sigma Project Final Report Jan. 2011.doc 14
  • 15. Six-Sigma Project Report Six Sigma Project Final Report Jan. 2011.doc 15
  • 16. Six-Sigma Project Report The team assembled and produced an initial Process Flow to ensure that they understood the process and breakdowns that occurred. This was built and displayed as a working model on a roll of kraft brown paper, a portion of which is shown in figure. 2.8. This methodology kept the team involved since the flow continued to be a work in process and didn‟t feel like an end product. Critical to Quality was assessed and the following was determined to be the key metrics. Quality Sets missing Instruments Case Carts Missing Supplies / Instruments Schedule Case Carts Missing Supplies / Instruments Cost Missing Item Recovery Time Revenue Potential Case Pick Time Six Sigma Project Final Report Jan. 2011.doc 16
  • 17. Six-Sigma Project Report Figure 2.8 Process Flow 2.3. Assumptions The Pareto of case delay cause codes reviewed in section 1.2 is inherently flawed due to its subjective nature. The system that the OR staff uses to capture delay reasons is first limited to a single input, while there may be numerous contributing factors to the delay, or additional reasons that as stand-alone would have caused a delay. This puts the staff member in the position of need to identify a „primary‟ reason for the delay. The subjective nature is also heightened by the perception that a staff member may wish to use a delay reason to “protect or incriminate” individuals. For this, the team determined that it must conduct an in-depth study of the delay reasons. While there have been threats from surgeons to leave the hospital and take their business elsewhere and while their patience is limited, none have taken this option, but do make life miserable for the staffs. Case Cart assembly begins at about 5:00 pm the afternoon prior to the scheduled cases, after the schedule has been finalized by the OR office staff. The case carts are assembled Six Sigma Project Final Report Jan. 2011.doc 17
  • 18. Six-Sigma Project Report in accordance with the surgery schedule, but the schedule is subject to change for a wide variety of reasons. The perception of what is late seems to be in constant debate. The OR staff will record late case carts depending on whom and when the pre-case audit is done. This varies from the time that the case is ready to commence to hours prior to case start. For purposes of the team‟s study, late is defined as “1/2 hour prior to need in the room, potentially prompting a case delay” The amount of instrumentation is not unlimited. This is true and impacts the availability of instruments for cases later in the day, as those same sets may be in use in earlier cases. The ability to see that need and prioritize the “quick turn‟ of those sets is an important step in the process. Standard supplies should never be an issue, if the replenishment system is used and working correctly. Special order supplies may be a cause of delay, but doesn‟t impact this study as they are outside the norm and out of the control of the SPD staff. Case carts delivered complete and on time remain complete. This is not a true assumption as OR staff is known to cannibalize other case carts for supplies and instruments when they feel a need or want to have extra “just in case”. For purposes of savings calculation a standard value of $40 per OR minute is used. This is based on the financial office‟s input that an hour of surgery in the OR puts $2,400 to the bottom line. 3. Measurement 3.1. Study; Late Case Carts, Missing Items, Case Delays Based on the initial process flow developed the team set out to quantify the process and the effects of incomplete and late case carts to the OR. Part of the reason for the approach taken was to fill the void of case delay reasons contained within the OR data. The team observed and documented the timing and completeness of case carts for a period of 27 days and conducted interviews with the surgery staff to determine the actual reasons for case delay. Figure 3.1 contains the summary data from the study. Six Sigma Project Final Report Jan. 2011.doc 18
  • 19. Case Minutes Delayed Summary Data Missing Item Count / Minutes Delayed Case Carts Incomplete Delay Count / # Samples subgroup units Case Delay Case # Percent Delay Daily Items per Sigma Cases Missing Case Mins per Mins per Subgroup X-Bar (Avg) Range (StdDev) Sample Size # Delay % Delay p Mean UCL LCL Items u # Minutes Delay Item 2648 704 26.6% 0.266 0.400 0.132 2129 0.804 12048 17.1 5.7 16-Aug 6.16 25 8.71 105 37 35.2% 0.352 0.266 0.400 0.132 128 1.219 647 17.5 5.1 Six-Sigma Project Report 17-Aug 4.94 33 8.64 97 26 26.8% 0.268 0.266 0.400 0.132 71 0.732 479 18.4 6.7 18-Aug 7.51 33 9.59 103 42 40.8% 0.408 0.266 0.400 0.132 123 1.194 774 18.4 6.3 19-Aug 4.79 32 8.88 97 24 24.7% 0.247 0.266 0.400 0.132 65 0.670 465 19.4 7.2 20-Aug 4.30 33 8.51 99 22 22.2% 0.222 0.266 0.400 0.132 68 0.687 426 19.4 6.3 21-Aug 4.73 31 8.29 101 27 26.7% 0.267 0.266 0.400 0.132 84 0.832 478 17.7 5.7 23-Aug 3.65 28 7.58 100 20 20.0% 0.200 0.266 0.400 0.132 64 0.640 365 18.3 5.7 24-Aug 4.96 35 8.85 97 25 25.8% 0.258 0.266 0.400 0.132 77 0.794 481 19.2 6.2 25-Aug 6.88 33 9.39 101 38 37.6% 0.376 0.266 0.400 0.132 125 1.238 695 18.3 5.6 Figure 3.1 Base Data Development 26-Aug 5.78 33 9.16 94 29 30.9% 0.309 0.266 0.400 0.132 86 0.915 543 18.7 6.3 27-Aug 4.30 23 7.75 105 26 24.8% 0.248 0.266 0.400 0.132 83 0.790 451 17.3 5.4 28-Aug 3.23 22 6.89 100 19 19.0% 0.190 0.266 0.400 0.132 43 0.430 323 17.0 7.5 Six Sigma Project Final Report Jan. 2011.doc 30-Aug 5.29 33 8.88 95 27 28.4% 0.284 0.266 0.400 0.132 78 0.821 503 18.6 6.4 31-Aug 4.31 31 8.09 97 23 23.7% 0.237 0.266 0.400 0.132 61 0.629 418 18.2 6.9 1-Sep 3.04 25 6.75 101 18 17.8% 0.178 0.266 0.400 0.132 61 0.604 307 17.1 5.0 2-Sep 3.75 23 7.30 91 20 22.0% 0.220 0.266 0.400 0.132 68 0.747 341 17.1 5.0 3-Sep 5.11 33 8.62 99 28 28.3% 0.283 0.266 0.400 0.132 90 0.909 506 18.1 5.6 4-Sep 4.49 25 7.85 96 25 26.0% 0.260 0.266 0.400 0.132 69 0.719 431 17.2 6.2 6-Sep 2.65 29 6.49 89 14 15.7% 0.157 0.266 0.400 0.132 39 0.438 236 16.9 6.1 7-Sep 4.31 33 8.04 99 24 24.2% 0.242 0.266 0.400 0.132 73 0.737 427 17.8 5.8 8-Sep 5.86 26 8.69 96 32 33.3% 0.333 0.266 0.400 0.132 105 1.094 563 17.6 5.4 9-Sep 4.84 25 8.43 95 25 26.3% 0.263 0.266 0.400 0.132 80 0.842 460 18.4 5.8 10-Sep 6.36 29 9.09 99 35 35.4% 0.354 0.266 0.400 0.132 113 1.141 630 18.0 5.6 11-Sep 4.72 29 8.20 99 26 26.3% 0.263 0.266 0.400 0.132 69 0.697 467 18.0 6.8 13-Sep 3.24 23 6.84 98 19 19.4% 0.194 0.266 0.400 0.132 51 0.520 318 16.7 6.2 14-Sep 5.84 28 8.80 102 33 32.4% 0.324 0.266 0.400 0.132 94 0.922 596 18.1 6.3 15-Sep 3.92 31 7.86 93 20 21.5% 0.215 0.266 0.400 0.132 61 0.656 365 18.3 6.0 Average 98.1 26.1 26.6% pbar 78.9 ubar StdDev 3.82 6.66 6.2% 0.266 0.804 Sum of Ranges 759 Sum of Subgroup Averages 122.83 # Subgroups 27 Control Limits for Averages Chart 4.549 28.111 19
  • 20. Six-Sigma Project Report From the data collected we tracked daily a number of key defect measurables including: number of case carts incomplete # Items missing from case carts # Items missing per Case Total Delay Minutes # / % Instrument Sets missing instruments Use of Attribute Control Charts: Since all existing data points were used and the subgroups contained data from each scheduled surgery for the day the sample size was inconsistent, varying from 90 to 105 across 27 subgroups. In the control charts (p) average sample size of 98 was used. NP and C charts were not used due to sample size variance. Used a false LCL to show methodology. In reality, there is no LCL as any item not delivered could cause an unacceptable case delay. U chart was used to show the number of items missing There is a mix both in terms of types of cases being and 8 different technicians responsible for the assembly of Case Carts. Note that in nearly all samples the technician responsible isn‟t documented. The p chart indicates a process out of control as it alternates data points up and down, although over the center line. The charts below contain the daily results the team found significant. Incomplete case carts ranged between 15.7% and 40.8% daily with a mean of 26.6%. Each of these incomplete case carts represents a potential case delay. Actual case delay is a function of Six Sigma Project Final Report Jan. 2011.doc 20
  • 21. Six-Sigma Project Report many other variables, including the critical nature of the specific item missing from the case. For purposes of this study, that detail was not factored. Actual number of cases delayed due to incomplete case carts was 85. This chart and data was later used to set up the first control chart and the upper and lower control limits were calculated and included on this chart. During the improvement phase this data was correlated to the individual tech and deficiencies in standard process, training and motivation were addressed. Items missing per ranged from .43 to 1.238 (.8) per total daily case count with a mean of .804 items per case. Factored against only those cases missing items the mean is 3.003 items per case with a range of 1.19 (2.26 to 3.45). This correlation caused the team to consider that once a case has a missing item, the technician picking the case failed to focus on completing as much of the case as possible. Six Sigma Project Final Report Jan. 2011.doc 21
  • 22. Six-Sigma Project Report The two charts correlating the number of items missing to the delay time demonstrated that the average case delay was 18.1 minutes and 6 minutes per missing item. There was a noticeable increase following Labor Day that we attributed to unusual staff shortages and a delay in the receipt of a supply shipment. A phenomenon noted was that contrary to expectation, days with more items missing didn‟t necessarily result in longer case delays. This, presumably, is due to an „all hands on deck‟ approach when items are missing. It did, of course, result in more staff time to locate the multiple items. Six Sigma Project Final Report Jan. 2011.doc 22
  • 23. Six-Sigma Project Report As mentioned earlier, during the observation process the team noted the high number of instrument sets not included in the case carts because the sets themselves were incomplete. Data was collected from the SPD‟s instrument management system to get a picture of how prevelent this issue was. The Missing instrument chart shows that over the course of 4 months an average of 18% of all instruments sets assembled were incomplete. This became a major focus for improvement. Incomplete Case Carts Statistical Results Over 27 days, between August 16 and September 15 there were 2648 surgery cases conducted o Daily case volumes ranged from 90 to 105 Of these 1620 (61.1%) were 1st or 2nd cases for the room for the day 704 (26.6%) cases were picked incomplete o 292 of these impacting 1st or 2nd cases (11.3% of total cases) 85 (3.2%) cases were actually delayed due to incomplete case picks Average OR case delay due to incomplete cases carts; 18.1 minutes o Results in an mean delay to all cases of 4.8 minutes Given $40 per OR minute lost the opportunity is $61.042 per month 66424 Items were required for the cases 2129 (3.2%) Items were missing 3.2 Sigma Calculation Opportunities for Defect: 66424 Defects: 2129 DPMO: 32052 Failure Rate: .321 Accuracy Rate: .968 -------------------------------------- Sigma Level: 3.35 Six Sigma Project Final Report Jan. 2011.doc 23
  • 24. Six-Sigma Project Report 4. Analysis 4.1 Cause and Effect Upon completion of the observations and base development, the team conducted a brainstorming session utilizing the Ishakawa Cause and Effect diagram to detail the variety of reasons for the incomplete case carts. Each entry was then weighted, after lengthy discussion, to determine which had the highest likelihood of impact. See Figure 4.1. Figure 4.1 Case Cart Completion Brainstorming Session Fishbone Diagram (the 6 M's) E E U Priority 1,2,3 N R E 2I Lack of priority / Conflict management 3U Audit vs. OR Feedback 2 I Block scheduling 1H Picklists incomplete, inaccurate, extra items 1 S Individual Measurement 3 L Existing Carts not adequate 3C Implants not listed on Count sheet 3 A Method of Accurate Measure 3 I Late reprocessing Problem Description: Interruptions to Pick (Phone & Delivery) 1A Soft-goods need to be in T-Doc? 2E No Consistent Definition of"Complete" 1M Impacts focus accuracy Case Carts sent M M Sets "Called For" to OR Incomplete 3 M in other Rooms 3M Out-of-Service Sets 1M Different methods of documenting pick "Called for" Sets, not used, not 2 A returned to CSP 2A Carry-Over Sets 1E Lack of Job Expectation 1N Lack of Knowledge - Location 1T Loaners not available on time 1T Quick Reference needed? 2 Lack of Knowledge - Material 1E Soft goods not available at pick time 1H Lack of follow-up Use of Priority List, "Called-For"sets not Inconsistent 1 Sets not put-away in right location 2R returned to CSP 1O Management follow-up 1 Staff indifference to assignment 3I Instruments not available at pick time 1 D Lack of standardized process 2 Staff inexperience 1A Loaners not available in time for processing 1L Incomplete / Inaccurate Pref. Cards 4.2 Pareto Revised The reason code results from the team‟s observations were then entered into a new pareto, figure 4.2 and compared to the initial results from the OR data system. While the numbers were greater, the rating of the items didn‟t differ significantly. Six Sigma Project Final Report Jan. 2011.doc 24
  • 25. Six-Sigma Project Report Figure 4.2 Case Cart Incomplete # Times Reason Code Assigned Instruments not available at pick time Loaners not available in time for processing Interruptions to Pick (Phone & Delivery) Impacts focus accuracy Picklists incomplete, inaccurate, extra items Sets not put-away in right location Staff indifference to assignment Method of Accurate Measure Individual Measurement (Accountability) Lack of Knowledge - Location Lack of Knowledge - Material Lack of standardized process Quick Reference needed? No Consistent Definition of"Complete" Use of Priority List, Sets "Called For" in other Rooms Out-of-Service Sets Late reprocessing Lack of priority / Conflict management Lack of Job Expectation Implants not listed on Count sheet Carry-Over Sets Audit vs. OR Feedback Different methods of documenting pick "Called for" Sets, not used, not returned to CSP Block scheduling Inconsistent Management follow-up Staff inexperience Soft goods not available at pick time Existing Carts not adequate Source: Case cart Incomplete, 6-Sigma Tracker. Dates August 15, 2010 - Sept 14, 2010 0 10 20 30 40 50 60 70 80 90 100 These breakouts were then further defined into actionable steps and were entered into the team‟s Action Item Log. The log eventually contained over 160 entries and remains in use at the time of this writing. A portion of the Action Item Log is shown in figure 4.4. Key actions taken by the team will be reviewed in the upcoming Improvement section. Six Sigma Project Final Report Jan. 2011.doc 25
  • 26. Six-Sigma Project Report Figure 4.4 Project Action Item List – Sample Page Effect: Case carts are not 100% complete, accurate and available on time Category Cause Subcause Recommendation Not a value alignment Use dedicated staff for case Staffing Staff indifferent picking No feeling that they are being measured, Use dedicated staff for case Staffing Staff indifferent watched or held accountable for case cart picking defects No negative impact to them while working in case (by the time they do relief everything is Use dedicated staff for case Staffing Staff indifferent fixed) picking Not all staff has scrubbed all cases therefore Use dedicated staff for case Staffing Staff inexperienced they are not familiar with all supplies & trays picking Descriptions on work sheets are not always Have existing staff highlight Staffing Staff inexperienced clear & user friendly routine problem items & allocate staff to fix daily No place for staff to reference locations for items Pick cases using pick lists & Staffing Staff inexperienced ensure all items have location list No place for staff to reference where locations Staffing Staff inexperienced Post master list of locations are in relation to the core (master location list) No existing process diagram or work instructions Make work instruction & share Staffing Staff inexperienced for how cases are to be picked. process flow with staff Staff for case picking not dedicated. PM staff Use dedicated staff for case Staffing Staff inadequate used prior to 2:30pm when they get pulled to do picking lunch relief Cases are booked after 5pm when staff is more Use dedicated staff for case Staffing Staff inadequate limited and/or in rooms picking Staff picks the cases they are familiar with and Use dedicated staff for case Staffing Staff inadequate can do fast picking Items for case are placed on open carts (with 3 Case Carts & Existing case carts not procedures per shelf) due to lack of availability of Use dedicated closed case environment adequate carts carts on each case Case carts are not numbered or identified as Label each cart with SHJC ID Case Carts & Existing case carts not SJHC with numbering system number and reference back to environment adequate manufacture's SR # Case carts have gotten lost or removed over the Label each cart with SHJC ID Case Carts & Existing case carts not years see above reason. number and reference back to environment adequate manufacture's SR # Case carts are not being cleaned between each Case Carts & Existing case carts not Use dedicated closed case use unless they are used for soiled transport to environment adequate carts on each case SPD No other system (totes or bins) available to Use dedicated closed case Case Carts & Existing case carts not contain smaller cases such as eye cases. carts on each case but make environment adequate an exception for eyes and put three per cart. Case Carts & Existing case carts not Case carts are not closed therefore present Use dedicated closed case environment adequate challenge with separation of clean and dirty carts on each case Case carts are not being maintained wheels Using SJHC cart ID number, set need lubricant Case Carts & Existing case carts not up PM system with Biomed to environment adequate have carts inspected annually. Monitor and report. Six Sigma Project Final Report Jan. 2011.doc 26
  • 27. Six-Sigma Project Report The opportunity to observe the Case Cart process caused us to revise the process flow a number of times. The end result was a cleaner, streamlined version of the process and it is included in the appendix. This exercise prompted the team to recognize that the case cart process is highly variable and statistically out of control and generated a need for not only improved processes but also standardized practices, which they developed in the way of Work Instructions for each of the key components. One of the top reasons for case carts not being completed was the SPD‟s inability to complete instruments sets on time. While staffing appropriately across the day to handle the incoming workload was an issue to be addressed, a significant factor was that the staff had developed the habit of not putting up incomplete sets, making them unavailable and not adequately communicating this to the OR. During the observation period a second set of metrics and trending was initiated to begin to understand the magnitude of this problem. A review of several months‟ data of sets missing instruments was captured from the SPD‟s instrument tracking system. It was determined that for the period extracted 18% of the sets put up were incomplete. The OR staff had complained often enough that the SPD staff determined not to send the incomplete sets with the case cart, further extenuating the problem. This became the focus of a major improvement initiative which we will cover shortly. While the availability of supplies would not have seemed to a major issue, it was discovered that some case cart assemblers were not addressing all the supply needs. Reasons ranged from: They thought the supplies were actual stored in the OR Were unfamiliar with the supply layout to Supplies not listed with locations on the pick tickets If one item is missing, less focus came to picking all the remaining items. This then lead to another major improvement initiative by the team and began with a spaghetti diagram detailing the typical paths taken by the case assemblers to pick all supplies. 5. Improvement This is where the proverbial rubber meets the road. Beginning with the brainstorming, process flow review and Paretos used in the measurement and analyze phases of the project the team constructed an action plan that eventually grew to over 160 separate items covering the following areas: Staff experience , skills, training, motivation Case Cart condition and size Space for storage, picking and staging Standardized procedures and work instructions Pick sequence and flow Pick list updates Completion of instrument sets Six Sigma Project Final Report Jan. 2011.doc 27
  • 28. Six-Sigma Project Report Availability of loaner and consignment sets It‟s important to the team to set and follow a structured approach or risk losing themselves in the myriad possibilities and tasks. Many of the improvement tasks identified are beyond the team‟s scope and will remain for the SPD leadership to continue to facilitate or move to another improvement initiative. A Test of Change approach was used to introduce process changes. The team determined the change, its method of measurement to see whether the change resulted in improvement, then communicated to the SPD and OR staffs the change and how it would be implemented. Critical to the team‟s thinking was to over communicate in order to gain buy-in. Using the tools the team set to determine a priority for the solutions, establish the improvement method, define the implementation steps and communicate. It is clear that standardization of process and practice is key to any sustainable improvement. First steps included cleaning up the process flow and using it to demonstrate the opportunities and the revised or new elements to the SPD staff, developing a set of Standard Work Instructions detailing the „hows and whys‟ of each associated task. For the Case Cart Technicians these include instrument set put-away, pick sequence and documentation. Standard Work Instructions were also developed for the SPD Instrument Set Assembly process. The document took the form of a step-by- step manual with photos correlated to each step. The process steps were reviewed with each staff member during training sessions and are visibly posted in the work space for quick reference. The simplified process flow is included in the appendix. As part of the effort to complete instrument sets it was deemed necessary to identify the critical instruments in each set. This information is then entered into the SPD‟s instrument management system and guides the assembly technician to not complete the assembly if a critical instrument is missing, but to complete it if a non-critical instrument is missing. This should result in fewer sets being left unavailable for use in a case. An additional step added to this work sequence is a required supervisor sign-off for any set assembled incomplete. While this is contrary to Lean thinking, it was determined to be pragmatic and necessary in the short-term to ensure awareness and adherence to the process. The identification of critical instruments is a painstaking chore, accomplished by OR personnel, so it will be a work-in progress for some time. A result of the focus on instrument set completion highlighted the negligence of the SPD management to effectively replace instrument that were lost or damaged. A significant expenditure needed to be made in order to elevate the inventories to the point that a daily impact could be made. The team sponsor agreed that the expenditure had been needed for some time and measures were put in place to monitor the needs going forward, so the cost associated are not included in the cost-benefit analysis or savings projections for the project. Six Sigma Project Final Report Jan. 2011.doc 28
  • 29. Six-Sigma Project Report Process changes in the Case Cart Assembly process includes re-layout of the supplies inventory from a product-family based to alignment with the pick ticket sequence and the addition of stores location on the pick ticket printout. A Quick Reference Locator was also produced and made available in various supply areas. This later change addresses needs that occur more often after the case carts have been picked, for add-on or emergency cases or when unforeseen needs arise. In addition to the change in the stores layout a 2-bin Kanban was installed. In this system each item‟s inventory is evenly split between two compartments. The items are picked from the „active‟ compartment. Once this is empty, pickers select from the second or backup compartment. Empty compartments or containers are replenished. For small items, bins are used as the kanban signal. For larger items cards are used. The realignment of the stores, integration of the kanban system and inclusion of item pick locations has resulted in a pick time reduction of an average of two minutes, from 18 to 16 per case. At 98 cases per day the savings equates to 196 minutes each day. Kanban Pictures Swinging Compartment Door With the above key process changes the team still needed to address the control and compliance issues within the Case Cart assembly process itself. Consistency is important, but it comes at a cost. Introduced were the requirements that the picking technician record each pick ticket they assemble. While not a fix, it was hoped that the requirement would raise awareness. Case carts required, by timing, to be sent to the OR incomplete Six Sigma Project Final Report Jan. 2011.doc 29
  • 30. Six-Sigma Project Report required a supervisor‟s sign-off and a communication call to the OR control desk. This helped preemptively set in motion any schedule change or recovery action needed. Highlighted in the brainstorming session was the need for cross-training. The department suffered when primary Case Cart Assemblers were absent, especially if more than one. Other areas within the SPD had similar issues. It was determined to begin a cross- training program and soon to begin a position rotation that would allow for staff to gain competency in all areas. It is beyond the scope of this team to provide the train or set up the schedules and this will be left to the department management. They are documented on the project action item list for future follow-up. Daily controls and metrics were introduced to track case cart and instrument set completion rates. These are displayed daily at a department level and fed into a Quality Dashboard at an individual as well as department level. Note: The dashboard is now expanding to track quality, productivity and service across the entire SPD. 6. Control Controls are integral to the success of any implementation ensuring compliance to practices and standards, monitoring improvement progress and sustaining the gains. First and foremost are the Standard Work Instructions highlighted before and training provided to gain understanding and compliance. Among the controls implemented was the Case Cart Audit mentioned in the prior section. This audit provided near real-time feedback from the OR to the SPD. The results were posted daily in the Incomplete Case Carts Daily-Monthly Control Chart. Figure 6.1 shows the actual charts for the months of October and November. For purposes of this exercise, both Upper and Lower Control Limits were calculated, but the team and staff recognizes that the target for incomplete case carts is zero. In the two months since initiating the project steady progress has been made. The last two weeks of November shows the incomplete carts steady at about 16.4 % versus 26.6 during the observation period. Still work to do, but showing a 38% improvement. Six Sigma Project Final Report Jan. 2011.doc 30
  • 31. Six-Sigma Project Report Figure 6.1 Incomplete Case Carts Control Chart The second control chart installed is a daily tracker of instrument sets assembled incomplete. Figure 6.2 contains the charts from October and November and demonstrates significant improvement. November versus the base period shows an improvement from 18% to 9.9% of Instruments Sets assembled incomplete for a 45% improvement. This trend is expected to continue as many eyes are focused, now, on the problem. Six Sigma Project Final Report Jan. 2011.doc 31
  • 32. Six-Sigma Project Report Figure 6.2 Incomplete Instrument Sets Control Chart Additionally, a daily report was established to actively monitor case delays recorded to incomplete case carts. While the OR recording methodology hasn‟t changed and therefore the inherent inconsistencies still exist, the renewed awareness and diligence by the OR staff, coupled with improved review from OR management may provide better insight. For the month of November the OR statistics reported versus the base period: OR Stats Base November Imp % Total Cases 2648 2725 # Incomplete Case Carts 702 26.5% 447 16.4% 38% # Caused Delayed Cases 85 3.2% 68 2.5% 22% Six Sigma Project Final Report Jan. 2011.doc 32
  • 33. Six-Sigma Project Report 7. Conclusion and Outlook The 6-sigma methodology proved a useful approach to identifying, quantifying and providing a framework to address the many issues related to incomplete case carts at this hospital. Using the DMAIC roadmap the SPD can increase its accuracy and therefore dependability in customer service. While we have not yet met our goals, it is believed that with continuing perseverance that they may be over the next 4 to 8 months. We‟ve seen our metrics improve: Incomplete Case Carts down from 26.6% to 16.4 %, a 38% improvement Incomplete Instruments Sets, while not an initial goal, became a significant factor in incomplete case carts: down from 18% to 9.9%, a 45% improvement. Sigma level Sigma Calculation Base November Opportunities for Defect: 66424 69387 Defects: 2129 1370 DPMO: 32052 20625 Failure Rate: .321 .197 Accuracy Rate: .968 .980 --------------------------------------------------------- Sigma Level: 3.35 3.56 Six Sigma Project Final Report Jan. 2011.doc 33
  • 34. Six-Sigma Project Report Base Data Normalized to November Actuals and Savings Projection Summary Baseline Delay Delay OR Cost per Incomplete OR Lost Lost Cost per Cost Daily OR Staff OR Staff Staff Total Delay Resulting Delayed Minutes Minutes OR Delay Lost Minutes Minutes Minute Cost Daily Cost per # Cases Complete Incomplete in OR Delay Cases per Case per Day Minute OR Min per Case per Day (Burdened) Staff Min Day Daily Avg. % # # % # Min Min $ $ Min Min $ $ $ 1st & 2nd Cases 60 82% 49 11 15% 1.6 18 29 $ 40 $ 1,166 30 324 $ 0.63 $ 205 $ 1,372 Remaining Cases 38 60% 23 15 10% 1.5 18 27 $ 40 $ 1,094 30 456 $ 0.63 $ 289 $ 1,383 Total Daily 98 73% 72 26 3.1 56.52 $ 2,261 780 $ 494 $ 2,755 Average Annual @ 260 surgical days 25480 18720 6760 816 14695 $ 587,808 202800 $ 128,440 $ 716,248 Base 27 Day Month 2648 1944 702 85 1526.04 $ 61,042 21060 13338 $ 74,380 November 2725 447 68 Impact at Base 722 87 Improvement and Savings Impact 275 19 18 346.42 $ 40 $ 13,857 30 8262 0.63 $ 5,205 $ 19,062 Direct Project Savings Annualized $ 166,279 $ 62,464 $ 228,743 Addition Soft Savings # Case Base Saved Std Prod Mean FTE Carts Assm. Nov. Assm. Mins / FTE Equiv. Payroll SPD Case Cart Pick Time Daily Mins Mins Improvement Day Min/Day FTEs (Annual) Savings Subtotal 98 18 16 2 196 390 0.5 $ 32,000 $ 16,082 $ 16,082 11.1% SPD Saved Std Prod Mean FTE SPD/OR Time recovered due to # Sets Base Nov. Mins per Mins / FTE Equiv. Payroll improved set completion Daily Missing Missing Improvement set Day Min/Day FTEs (Annual) Savings 910 164 121 43 25 1075 390 2.8 $ 32,000 $ 88,205 18% 13% 26.2% Saved Std Prod Mean FTE OR Mins Mins / FTE Equiv. Payroll per set Day Min/Day FTEs (Annual) Savings Subtotal 12 516 390 1.3 43,000 $ 56,892 $ 145,097 Subtotal Soft Savings (not verified) $ 161,179 Potential Total Project Savings $ 389,922 Using the base data for comparison to the results in November we can ascertain that we are on track to save $228,743 annually. While the impact on staff minutes spent searching for missing items is nearly on track, it‟s difficult to tell if the lost OR time will be sufficiently recovered. Shown also are soft savings calculated based on the reduction in time to pick and assemble case carts and reduction in the time SPD uses search for instruments from incomplete sets. These lines are excluded from the Direct Project savings for two reasons; first they are difficult to verify on a consistent basis and no labor has actually been reallocated from the department and second, they were not part of the original savings projections. However it is important to recognize the impact that the 6-sigma team had relative to the entire process. It is too early to definitively state that the project will result in the savings projected, however at the time of this writing all indicators are moving in the right direction and the gains made are being sustained. Six Sigma Project Final Report Jan. 2011.doc 34
  • 35. Six-Sigma Project Report Appendix Six Sigma Project Final Report Jan. 2011.doc 35