SlideShare a Scribd company logo
1 of 8
Site Instruction ProvisionSite Instruction Provision
WCR / CO / CCNWCR / CO / CCN
Prepared by:Prepared by:
R.A. RetitaR.A. Retita
Site Instruction ProvisionsSite Instruction Provisions
1. Procedure Details :1. Procedure Details :
AbstractAbstract
This document provides information on procedure for measuring and quantifying of materials based on plan andThis document provides information on procedure for measuring and quantifying of materials based on plan and
actual site changes constructed or implemented on all outside plant facilities, completed civil and cable works.actual site changes constructed or implemented on all outside plant facilities, completed civil and cable works.
PurposePurpose
Site changes documentation is very essential for verification of revised actual measurement and quantity of allSite changes documentation is very essential for verification of revised actual measurement and quantity of all
materials installed. Result of all the changes on plan, specification, activity, site condition and measurement willmaterials installed. Result of all the changes on plan, specification, activity, site condition and measurement will
be the basis for the checking of quantity survey plan or as-built plan and bill of quantity.be the basis for the checking of quantity survey plan or as-built plan and bill of quantity.
Scope of workScope of work
Ensure correct Quantity Survey measurement of all completed civil, cable installation and aerial permanent works.Ensure correct Quantity Survey measurement of all completed civil, cable installation and aerial permanent works.
Manpower requirementManpower requirement
For the purpose of pre-project acceptance requiring for additional manpower. This is to recommend theFor the purpose of pre-project acceptance requiring for additional manpower. This is to recommend the
immediate manpower requirement in order to facilitate the need for Northeast and portion of FOBN2. This willimmediate manpower requirement in order to facilitate the need for Northeast and portion of FOBN2. This will
provide advance project cost probability emanating from the actual completed works recorded as to date.provide advance project cost probability emanating from the actual completed works recorded as to date.
 1 Clerical Assistance1 Clerical Assistance
ContentsContents
1. Procedure Details1. Procedure Details
2. Integrated Flow Chart for SI Documentation2. Integrated Flow Chart for SI Documentation
3. Process Flow3. Process Flow
4. SI Documentation4. SI Documentation
Site Instruction DocumentationSite Instruction Documentation
EnclosuresEnclosures
Site Instruction form towards Client/CustomerSite Instruction form towards Client/Customer
Site Instruction form towards Sub-contractorSite Instruction form towards Sub-contractor
AbstractAbstract
This description gives guidelines how to prepare and get an approval of a Site Instruction.This description gives guidelines how to prepare and get an approval of a Site Instruction.
ApplicationApplication
This document is applicable for Globe NLTN Projects for Northwest, Northeast and FOBN2 areas.This document is applicable for Globe NLTN Projects for Northwest, Northeast and FOBN2 areas.
This description is also to be used by any sub-contractors engaged for cable network installation work.This description is also to be used by any sub-contractors engaged for cable network installation work.
ContentsContents
11 ResponsibilitiesResponsibilities 33
1.11.1 Installation ManagerInstallation Manager 33
1.21.2 Project Control functionProject Control function 44
1.31.3 Installation SupervisorInstallation Supervisor 44
1.41.4 Site SupervisorSite Supervisor 44
1.51.5 Site Engineer from OSP Engineering 5Site Engineer from OSP Engineering 5
22 DescriptionDescription 55
33 Site Instruction Form 7Site Instruction Form 7
ResponsibilitiesResponsibilities
1.1 Installation Manager1.1 Installation Manager
Installation Manager is responsible to:Installation Manager is responsible to:
 Establish the Site Instruction procedure together with the customer and Project Control functionEstablish the Site Instruction procedure together with the customer and Project Control function
 Inform and make sure that concerned installation staff understand the Site Instruction procedureInform and make sure that concerned installation staff understand the Site Instruction procedure
 Receive information from Installation Supervisor that a Site Instruction involving cost and/or time extensionReceive information from Installation Supervisor that a Site Instruction involving cost and/or time extension
has been sent to Project Control function for action.has been sent to Project Control function for action.
ResponsibilitiesResponsibilities
1.1 Installation Manager1.1 Installation Manager
Installation Manager is responsible to:Installation Manager is responsible to:
 Receiving information from Project Control function that Client/ Customer has approved offered price and/orReceiving information from Project Control function that Client/ Customer has approved offered price and/or
time extensions.time extensions.
1.2 Project Control function1.2 Project Control function
The Project Control function is responsible to:The Project Control function is responsible to:
 When a Site Instruction is received, from Installation Supervisor, involving cost and/or time extension an offerWhen a Site Instruction is received, from Installation Supervisor, involving cost and/or time extension an offer
shall be prepared and formally submitted for approvalshall be prepared and formally submitted for approval
 After written approval from Client/Customer instruct Installation Supervisor when the Site Instruction involvingAfter written approval from Client/Customer instruct Installation Supervisor when the Site Instruction involving
cost and/or time extension can re-start.cost and/or time extension can re-start.
1.3 Installation Supervisor1.3 Installation Supervisor
The Installation Supervisor is responsible to:The Installation Supervisor is responsible to:
 When receiving the Site Instruction decide if there is cost and/or time extension involvedWhen receiving the Site Instruction decide if there is cost and/or time extension involved
 Instruct Site Supervisor to start the suggested Site Instruction work if cost and/or time extension are notInstruct Site Supervisor to start the suggested Site Instruction work if cost and/or time extension are not
involvedinvolved
 Make sure that a cost estimate is prepared as soon as possible by him/herself or other appointed functionMake sure that a cost estimate is prepared as soon as possible by him/herself or other appointed function
within the Project if cost and/or time extension are involvedwithin the Project if cost and/or time extension are involved
 Send the cost and time extension estimate to Project Administration function for action and InstallationSend the cost and time extension estimate to Project Administration function for action and Installation
Manager for informationManager for information..
Site Instruction DocumentationSite Instruction Documentation
Site Instruction DocumentationSite Instruction Documentation
ResponsibilitiesResponsibilities
1.4 Site Supervisor1.4 Site Supervisor
Site Supervisor is responsible to:Site Supervisor is responsible to:
 Discuss and agree with Customer Site Representative including client and Sun-contractor with technicalDiscuss and agree with Customer Site Representative including client and Sun-contractor with technical
solution suggested and prepare a Site Instruction in accordance to the agreed solution.solution suggested and prepare a Site Instruction in accordance to the agreed solution.
 Make proper recommendation to the solution and ensure that Client/Customer, Ericsson Site Supervisor andMake proper recommendation to the solution and ensure that Client/Customer, Ericsson Site Supervisor and
Site Representatives are always affix signature to the Site Instruction as well as the Sub-contractorSite Representatives are always affix signature to the Site Instruction as well as the Sub-contractor
Representative, if applicableRepresentative, if applicable
 Send the Site Instruction to Installation Supervisor for the immediate revision and implementation of approvedSend the Site Instruction to Installation Supervisor for the immediate revision and implementation of approved
construction works. Site Supervisor must check the recommended solution and revision prior start of theconstruction works. Site Supervisor must check the recommended solution and revision prior start of the
required workrequired work
 Make sure that no work starts before such instruction is received.Make sure that no work starts before such instruction is received.
1.5 Site Engineer from OSP Engineering1.5 Site Engineer from OSP Engineering
Site Engineer is responsible to:Site Engineer is responsible to:
 Suggest to Site Supervisor a new plan when approved drawing(s) require a change.Suggest to Site Supervisor a new plan when approved drawing(s) require a change.
 Site Engineer can only agree on the approved plan based from revision but will not authorize to sign in theSite Engineer can only agree on the approved plan based from revision but will not authorize to sign in the
Site Instruction Form.Site Instruction Form.
 He/she may conduct random inspection, if applicable.He/she may conduct random inspection, if applicable.
 He/ She can suggest a suitable solution.He/ She can suggest a suitable solution.
Site Instruction DocumentationSite Instruction Documentation
2. Description :2. Description :
The Site Instruction procedure is required in all cases when an approved design is changed, see Attachment 1.The Site Instruction procedure is required in all cases when an approved design is changed, see Attachment 1.
 There will be no work included in the Site Instruction unless all signature are affixed.There will be no work included in the Site Instruction unless all signature are affixed.
 Preparation of new Site Instruction is recommended for the additional work order from the previous SitePreparation of new Site Instruction is recommended for the additional work order from the previous Site
Instruction.Instruction.
 The work shall be started upon clearing all Site Instruction and approved by Client/Customer, Ericsson SiteThe work shall be started upon clearing all Site Instruction and approved by Client/Customer, Ericsson Site
Supervisor, Sub-contractor.Supervisor, Sub-contractor.
 In some cases, when cost and/or time extension affect the start of the construction, another clearance isIn some cases, when cost and/or time extension affect the start of the construction, another clearance is
required from Client/Customer, Ericsson Site Supervisor, Sub-contractor prior the start of the suggested work.required from Client/Customer, Ericsson Site Supervisor, Sub-contractor prior the start of the suggested work.
3. Site Instruction Form :3. Site Instruction Form :
See Attachment 3See Attachment 3
GLOBE Representative
Approved as corrected
Disapproved
Approved for Implementation
DeleteDirectional Boring
Extend
PROPOSAL:
Handhole
S. I. No. Date:
Relocate
RerouteCulvert Attachment Pulling
BlowingBridge Attachment
Description
Modify / Demolish
Change Type / Size /
Height
Remark:
contract price only no change in contract time and price
The instructions appearing above shall have effect on:
contract time only both contract price and time
GLOBE COMMENTS
ERICSSON Representative
As-built
Prepared by:Remark:
Non-Chargeable Chargeable to GLOBE
ERICSSON COMMENTS
REASON:
Original route:
REMARKS PROPOSAL
Others (specify): Ploughing
Change Material Use
Additional
Client's request Trenching
Revision Trial Pit
JointingDesign Excavation
R. O. W.
Obstruction
OF CHANGE CIVIL CABLE of works
REASON TYPE OF INSTALLATION
Scheme No.
Scheme CWS
GLOBE OSP NW_NLTN PROJECT
SITE INSTRUCTION FORM
Segment No. :
Cable

More Related Content

What's hot

Health, Safety and Environmental Management Plan
Health, Safety and Environmental Management PlanHealth, Safety and Environmental Management Plan
Health, Safety and Environmental Management PlanFlevy.com Best Practices
 
Construction safety lecture-1
Construction safety  lecture-1Construction safety  lecture-1
Construction safety lecture-1Saleem Malik
 
PROJECT HEALTH, SAFETY, AND ENVIRONMENTAL PLAN
PROJECT HEALTH, SAFETY, AND ENVIRONMENTAL PLANPROJECT HEALTH, SAFETY, AND ENVIRONMENTAL PLAN
PROJECT HEALTH, SAFETY, AND ENVIRONMENTAL PLANDwarika Bhushan Sharma
 
Cause of accident and prevention in construction industry
Cause of accident and prevention in construction industryCause of accident and prevention in construction industry
Cause of accident and prevention in construction industryYASMINE HASLAN
 
Safety health and environment
Safety health and environmentSafety health and environment
Safety health and environmentImran Amami
 
Environment at site – construction management
Environment at site – construction managementEnvironment at site – construction management
Environment at site – construction managementsrinivas2036
 
Construction Site Health & Safety
Construction Site Health & SafetyConstruction Site Health & Safety
Construction Site Health & SafetySAURABH SINGH
 
Health and safety in construction projects.pptx
Health and safety in construction projects.pptxHealth and safety in construction projects.pptx
Health and safety in construction projects.pptxTouqeer1
 
Legal issues associated with project management and consulting
Legal issues associated with project management and consultingLegal issues associated with project management and consulting
Legal issues associated with project management and consultingThis account is closed
 
Demolition Safety 2015
Demolition Safety 2015Demolition Safety 2015
Demolition Safety 2015John Newquist
 
Method statement for structure excavation
Method statement for structure excavationMethod statement for structure excavation
Method statement for structure excavationAl-Amin Ahmed Nabin
 
Contractor management slides #1 unit1& 2
Contractor management slides #1 unit1& 2 Contractor management slides #1 unit1& 2
Contractor management slides #1 unit1& 2 Michael Shellshear
 
Excavation method rectified 13-11-2010
Excavation method   rectified 13-11-2010Excavation method   rectified 13-11-2010
Excavation method rectified 13-11-2010Minh Bui Si
 
Health and Safety in Construction PPT
Health and Safety in Construction  PPTHealth and Safety in Construction  PPT
Health and Safety in Construction PPTLuke D'Arcy
 
Construction Documents
Construction DocumentsConstruction Documents
Construction DocumentsAllan Berry
 
17 Traffic Operations - Working on live roads Risk Assessment Templates.docx
17 Traffic Operations - Working on live roads Risk Assessment Templates.docx17 Traffic Operations - Working on live roads Risk Assessment Templates.docx
17 Traffic Operations - Working on live roads Risk Assessment Templates.docxDwarika Bhushan Sharma
 
Safety at Construction SIte
Safety at Construction SIteSafety at Construction SIte
Safety at Construction SIteAvi Gandhi
 
Construction site safety
Construction site safetyConstruction site safety
Construction site safetyDebajit Roy
 
Safety and Health During Construction
Safety and Health During ConstructionSafety and Health During Construction
Safety and Health During ConstructionDr K M SONI
 
Construction site safety
Construction site safetyConstruction site safety
Construction site safetyFroyd Dias
 

What's hot (20)

Health, Safety and Environmental Management Plan
Health, Safety and Environmental Management PlanHealth, Safety and Environmental Management Plan
Health, Safety and Environmental Management Plan
 
Construction safety lecture-1
Construction safety  lecture-1Construction safety  lecture-1
Construction safety lecture-1
 
PROJECT HEALTH, SAFETY, AND ENVIRONMENTAL PLAN
PROJECT HEALTH, SAFETY, AND ENVIRONMENTAL PLANPROJECT HEALTH, SAFETY, AND ENVIRONMENTAL PLAN
PROJECT HEALTH, SAFETY, AND ENVIRONMENTAL PLAN
 
Cause of accident and prevention in construction industry
Cause of accident and prevention in construction industryCause of accident and prevention in construction industry
Cause of accident and prevention in construction industry
 
Safety health and environment
Safety health and environmentSafety health and environment
Safety health and environment
 
Environment at site – construction management
Environment at site – construction managementEnvironment at site – construction management
Environment at site – construction management
 
Construction Site Health & Safety
Construction Site Health & SafetyConstruction Site Health & Safety
Construction Site Health & Safety
 
Health and safety in construction projects.pptx
Health and safety in construction projects.pptxHealth and safety in construction projects.pptx
Health and safety in construction projects.pptx
 
Legal issues associated with project management and consulting
Legal issues associated with project management and consultingLegal issues associated with project management and consulting
Legal issues associated with project management and consulting
 
Demolition Safety 2015
Demolition Safety 2015Demolition Safety 2015
Demolition Safety 2015
 
Method statement for structure excavation
Method statement for structure excavationMethod statement for structure excavation
Method statement for structure excavation
 
Contractor management slides #1 unit1& 2
Contractor management slides #1 unit1& 2 Contractor management slides #1 unit1& 2
Contractor management slides #1 unit1& 2
 
Excavation method rectified 13-11-2010
Excavation method   rectified 13-11-2010Excavation method   rectified 13-11-2010
Excavation method rectified 13-11-2010
 
Health and Safety in Construction PPT
Health and Safety in Construction  PPTHealth and Safety in Construction  PPT
Health and Safety in Construction PPT
 
Construction Documents
Construction DocumentsConstruction Documents
Construction Documents
 
17 Traffic Operations - Working on live roads Risk Assessment Templates.docx
17 Traffic Operations - Working on live roads Risk Assessment Templates.docx17 Traffic Operations - Working on live roads Risk Assessment Templates.docx
17 Traffic Operations - Working on live roads Risk Assessment Templates.docx
 
Safety at Construction SIte
Safety at Construction SIteSafety at Construction SIte
Safety at Construction SIte
 
Construction site safety
Construction site safetyConstruction site safety
Construction site safety
 
Safety and Health During Construction
Safety and Health During ConstructionSafety and Health During Construction
Safety and Health During Construction
 
Construction site safety
Construction site safetyConstruction site safety
Construction site safety
 

Similar to Site Instruction Provision

Table of ContentsProject ObjectiveRationale for Projec.docx
Table of ContentsProject ObjectiveRationale for Projec.docxTable of ContentsProject ObjectiveRationale for Projec.docx
Table of ContentsProject ObjectiveRationale for Projec.docxssuserf9c51d
 
Leadership TheoriesWrite a 700- to 1,050-word paper that addre.docx
Leadership TheoriesWrite a 700- to 1,050-word paper that addre.docxLeadership TheoriesWrite a 700- to 1,050-word paper that addre.docx
Leadership TheoriesWrite a 700- to 1,050-word paper that addre.docxsmile790243
 
VA Cx Presentation_SRE Training 2013 Final_v2
VA Cx Presentation_SRE Training 2013 Final_v2VA Cx Presentation_SRE Training 2013 Final_v2
VA Cx Presentation_SRE Training 2013 Final_v2Jerry Bauers
 
Single Proprietorship JD
Single Proprietorship JDSingle Proprietorship JD
Single Proprietorship JDDean Apao
 
1. Usman Ali CV Project Engineer Electrical.pdf
1. Usman Ali CV Project Engineer Electrical.pdf1. Usman Ali CV Project Engineer Electrical.pdf
1. Usman Ali CV Project Engineer Electrical.pdfEmmanuelMatutu
 
Implementation-Plan_X_Corp
Implementation-Plan_X_CorpImplementation-Plan_X_Corp
Implementation-Plan_X_CorpJared Bourne
 
Vignesh Kumar C- TPI Coordinator
Vignesh Kumar C- TPI CoordinatorVignesh Kumar C- TPI Coordinator
Vignesh Kumar C- TPI CoordinatorVignesh Kumar C
 
Erection method statement
Erection method statementErection method statement
Erection method statementkanalbiru
 
ERECTION METHOD STATEMENT
ERECTION METHOD STATEMENTERECTION METHOD STATEMENT
ERECTION METHOD STATEMENTmustafa hussain
 
Commissioning-Team-Role-Responsibilities-1.pdf
Commissioning-Team-Role-Responsibilities-1.pdfCommissioning-Team-Role-Responsibilities-1.pdf
Commissioning-Team-Role-Responsibilities-1.pdfRommelTolentino8
 
Utility Coordination 2015 - for show
Utility Coordination 2015 - for showUtility Coordination 2015 - for show
Utility Coordination 2015 - for showLynee Russell
 
Tpqma r5 to upload in slide share
Tpqma r5 to upload in slide shareTpqma r5 to upload in slide share
Tpqma r5 to upload in slide shareRajiva Gupta
 

Similar to Site Instruction Provision (20)

Table of ContentsProject ObjectiveRationale for Projec.docx
Table of ContentsProject ObjectiveRationale for Projec.docxTable of ContentsProject ObjectiveRationale for Projec.docx
Table of ContentsProject ObjectiveRationale for Projec.docx
 
Leadership TheoriesWrite a 700- to 1,050-word paper that addre.docx
Leadership TheoriesWrite a 700- to 1,050-word paper that addre.docxLeadership TheoriesWrite a 700- to 1,050-word paper that addre.docx
Leadership TheoriesWrite a 700- to 1,050-word paper that addre.docx
 
PROJECT_STEPS
PROJECT_STEPSPROJECT_STEPS
PROJECT_STEPS
 
ptsresume[1]
ptsresume[1]ptsresume[1]
ptsresume[1]
 
VA Cx Presentation_SRE Training 2013 Final_v2
VA Cx Presentation_SRE Training 2013 Final_v2VA Cx Presentation_SRE Training 2013 Final_v2
VA Cx Presentation_SRE Training 2013 Final_v2
 
CV
CVCV
CV
 
Single Proprietorship JD
Single Proprietorship JDSingle Proprietorship JD
Single Proprietorship JD
 
CV.C
CV.CCV.C
CV.C
 
1. Usman Ali CV Project Engineer Electrical.pdf
1. Usman Ali CV Project Engineer Electrical.pdf1. Usman Ali CV Project Engineer Electrical.pdf
1. Usman Ali CV Project Engineer Electrical.pdf
 
Implementation-Plan_X_Corp
Implementation-Plan_X_CorpImplementation-Plan_X_Corp
Implementation-Plan_X_Corp
 
RAVI CV (1)
RAVI CV (1)RAVI CV (1)
RAVI CV (1)
 
Vignesh Kumar C- TPI Coordinator
Vignesh Kumar C- TPI CoordinatorVignesh Kumar C- TPI Coordinator
Vignesh Kumar C- TPI Coordinator
 
UPDATED RESUME 2016
UPDATED RESUME 2016UPDATED RESUME 2016
UPDATED RESUME 2016
 
Erection method statement
Erection method statementErection method statement
Erection method statement
 
ERECTION METHOD STATEMENT
ERECTION METHOD STATEMENTERECTION METHOD STATEMENT
ERECTION METHOD STATEMENT
 
PradeepKombilath
PradeepKombilathPradeepKombilath
PradeepKombilath
 
Commissioning-Team-Role-Responsibilities-1.pdf
Commissioning-Team-Role-Responsibilities-1.pdfCommissioning-Team-Role-Responsibilities-1.pdf
Commissioning-Team-Role-Responsibilities-1.pdf
 
Utility Coordination 2015 - for show
Utility Coordination 2015 - for showUtility Coordination 2015 - for show
Utility Coordination 2015 - for show
 
Tpqma r5 to upload in slide share
Tpqma r5 to upload in slide shareTpqma r5 to upload in slide share
Tpqma r5 to upload in slide share
 
Quality application
Quality applicationQuality application
Quality application
 

Site Instruction Provision

  • 1. Site Instruction ProvisionSite Instruction Provision WCR / CO / CCNWCR / CO / CCN Prepared by:Prepared by: R.A. RetitaR.A. Retita
  • 2. Site Instruction ProvisionsSite Instruction Provisions 1. Procedure Details :1. Procedure Details : AbstractAbstract This document provides information on procedure for measuring and quantifying of materials based on plan andThis document provides information on procedure for measuring and quantifying of materials based on plan and actual site changes constructed or implemented on all outside plant facilities, completed civil and cable works.actual site changes constructed or implemented on all outside plant facilities, completed civil and cable works. PurposePurpose Site changes documentation is very essential for verification of revised actual measurement and quantity of allSite changes documentation is very essential for verification of revised actual measurement and quantity of all materials installed. Result of all the changes on plan, specification, activity, site condition and measurement willmaterials installed. Result of all the changes on plan, specification, activity, site condition and measurement will be the basis for the checking of quantity survey plan or as-built plan and bill of quantity.be the basis for the checking of quantity survey plan or as-built plan and bill of quantity. Scope of workScope of work Ensure correct Quantity Survey measurement of all completed civil, cable installation and aerial permanent works.Ensure correct Quantity Survey measurement of all completed civil, cable installation and aerial permanent works. Manpower requirementManpower requirement For the purpose of pre-project acceptance requiring for additional manpower. This is to recommend theFor the purpose of pre-project acceptance requiring for additional manpower. This is to recommend the immediate manpower requirement in order to facilitate the need for Northeast and portion of FOBN2. This willimmediate manpower requirement in order to facilitate the need for Northeast and portion of FOBN2. This will provide advance project cost probability emanating from the actual completed works recorded as to date.provide advance project cost probability emanating from the actual completed works recorded as to date.  1 Clerical Assistance1 Clerical Assistance ContentsContents 1. Procedure Details1. Procedure Details 2. Integrated Flow Chart for SI Documentation2. Integrated Flow Chart for SI Documentation 3. Process Flow3. Process Flow 4. SI Documentation4. SI Documentation
  • 3.
  • 4. Site Instruction DocumentationSite Instruction Documentation EnclosuresEnclosures Site Instruction form towards Client/CustomerSite Instruction form towards Client/Customer Site Instruction form towards Sub-contractorSite Instruction form towards Sub-contractor AbstractAbstract This description gives guidelines how to prepare and get an approval of a Site Instruction.This description gives guidelines how to prepare and get an approval of a Site Instruction. ApplicationApplication This document is applicable for Globe NLTN Projects for Northwest, Northeast and FOBN2 areas.This document is applicable for Globe NLTN Projects for Northwest, Northeast and FOBN2 areas. This description is also to be used by any sub-contractors engaged for cable network installation work.This description is also to be used by any sub-contractors engaged for cable network installation work. ContentsContents 11 ResponsibilitiesResponsibilities 33 1.11.1 Installation ManagerInstallation Manager 33 1.21.2 Project Control functionProject Control function 44 1.31.3 Installation SupervisorInstallation Supervisor 44 1.41.4 Site SupervisorSite Supervisor 44 1.51.5 Site Engineer from OSP Engineering 5Site Engineer from OSP Engineering 5 22 DescriptionDescription 55 33 Site Instruction Form 7Site Instruction Form 7 ResponsibilitiesResponsibilities 1.1 Installation Manager1.1 Installation Manager Installation Manager is responsible to:Installation Manager is responsible to:  Establish the Site Instruction procedure together with the customer and Project Control functionEstablish the Site Instruction procedure together with the customer and Project Control function  Inform and make sure that concerned installation staff understand the Site Instruction procedureInform and make sure that concerned installation staff understand the Site Instruction procedure  Receive information from Installation Supervisor that a Site Instruction involving cost and/or time extensionReceive information from Installation Supervisor that a Site Instruction involving cost and/or time extension has been sent to Project Control function for action.has been sent to Project Control function for action.
  • 5. ResponsibilitiesResponsibilities 1.1 Installation Manager1.1 Installation Manager Installation Manager is responsible to:Installation Manager is responsible to:  Receiving information from Project Control function that Client/ Customer has approved offered price and/orReceiving information from Project Control function that Client/ Customer has approved offered price and/or time extensions.time extensions. 1.2 Project Control function1.2 Project Control function The Project Control function is responsible to:The Project Control function is responsible to:  When a Site Instruction is received, from Installation Supervisor, involving cost and/or time extension an offerWhen a Site Instruction is received, from Installation Supervisor, involving cost and/or time extension an offer shall be prepared and formally submitted for approvalshall be prepared and formally submitted for approval  After written approval from Client/Customer instruct Installation Supervisor when the Site Instruction involvingAfter written approval from Client/Customer instruct Installation Supervisor when the Site Instruction involving cost and/or time extension can re-start.cost and/or time extension can re-start. 1.3 Installation Supervisor1.3 Installation Supervisor The Installation Supervisor is responsible to:The Installation Supervisor is responsible to:  When receiving the Site Instruction decide if there is cost and/or time extension involvedWhen receiving the Site Instruction decide if there is cost and/or time extension involved  Instruct Site Supervisor to start the suggested Site Instruction work if cost and/or time extension are notInstruct Site Supervisor to start the suggested Site Instruction work if cost and/or time extension are not involvedinvolved  Make sure that a cost estimate is prepared as soon as possible by him/herself or other appointed functionMake sure that a cost estimate is prepared as soon as possible by him/herself or other appointed function within the Project if cost and/or time extension are involvedwithin the Project if cost and/or time extension are involved  Send the cost and time extension estimate to Project Administration function for action and InstallationSend the cost and time extension estimate to Project Administration function for action and Installation Manager for informationManager for information.. Site Instruction DocumentationSite Instruction Documentation
  • 6. Site Instruction DocumentationSite Instruction Documentation ResponsibilitiesResponsibilities 1.4 Site Supervisor1.4 Site Supervisor Site Supervisor is responsible to:Site Supervisor is responsible to:  Discuss and agree with Customer Site Representative including client and Sun-contractor with technicalDiscuss and agree with Customer Site Representative including client and Sun-contractor with technical solution suggested and prepare a Site Instruction in accordance to the agreed solution.solution suggested and prepare a Site Instruction in accordance to the agreed solution.  Make proper recommendation to the solution and ensure that Client/Customer, Ericsson Site Supervisor andMake proper recommendation to the solution and ensure that Client/Customer, Ericsson Site Supervisor and Site Representatives are always affix signature to the Site Instruction as well as the Sub-contractorSite Representatives are always affix signature to the Site Instruction as well as the Sub-contractor Representative, if applicableRepresentative, if applicable  Send the Site Instruction to Installation Supervisor for the immediate revision and implementation of approvedSend the Site Instruction to Installation Supervisor for the immediate revision and implementation of approved construction works. Site Supervisor must check the recommended solution and revision prior start of theconstruction works. Site Supervisor must check the recommended solution and revision prior start of the required workrequired work  Make sure that no work starts before such instruction is received.Make sure that no work starts before such instruction is received. 1.5 Site Engineer from OSP Engineering1.5 Site Engineer from OSP Engineering Site Engineer is responsible to:Site Engineer is responsible to:  Suggest to Site Supervisor a new plan when approved drawing(s) require a change.Suggest to Site Supervisor a new plan when approved drawing(s) require a change.  Site Engineer can only agree on the approved plan based from revision but will not authorize to sign in theSite Engineer can only agree on the approved plan based from revision but will not authorize to sign in the Site Instruction Form.Site Instruction Form.  He/she may conduct random inspection, if applicable.He/she may conduct random inspection, if applicable.  He/ She can suggest a suitable solution.He/ She can suggest a suitable solution.
  • 7. Site Instruction DocumentationSite Instruction Documentation 2. Description :2. Description : The Site Instruction procedure is required in all cases when an approved design is changed, see Attachment 1.The Site Instruction procedure is required in all cases when an approved design is changed, see Attachment 1.  There will be no work included in the Site Instruction unless all signature are affixed.There will be no work included in the Site Instruction unless all signature are affixed.  Preparation of new Site Instruction is recommended for the additional work order from the previous SitePreparation of new Site Instruction is recommended for the additional work order from the previous Site Instruction.Instruction.  The work shall be started upon clearing all Site Instruction and approved by Client/Customer, Ericsson SiteThe work shall be started upon clearing all Site Instruction and approved by Client/Customer, Ericsson Site Supervisor, Sub-contractor.Supervisor, Sub-contractor.  In some cases, when cost and/or time extension affect the start of the construction, another clearance isIn some cases, when cost and/or time extension affect the start of the construction, another clearance is required from Client/Customer, Ericsson Site Supervisor, Sub-contractor prior the start of the suggested work.required from Client/Customer, Ericsson Site Supervisor, Sub-contractor prior the start of the suggested work. 3. Site Instruction Form :3. Site Instruction Form : See Attachment 3See Attachment 3
  • 8. GLOBE Representative Approved as corrected Disapproved Approved for Implementation DeleteDirectional Boring Extend PROPOSAL: Handhole S. I. No. Date: Relocate RerouteCulvert Attachment Pulling BlowingBridge Attachment Description Modify / Demolish Change Type / Size / Height Remark: contract price only no change in contract time and price The instructions appearing above shall have effect on: contract time only both contract price and time GLOBE COMMENTS ERICSSON Representative As-built Prepared by:Remark: Non-Chargeable Chargeable to GLOBE ERICSSON COMMENTS REASON: Original route: REMARKS PROPOSAL Others (specify): Ploughing Change Material Use Additional Client's request Trenching Revision Trial Pit JointingDesign Excavation R. O. W. Obstruction OF CHANGE CIVIL CABLE of works REASON TYPE OF INSTALLATION Scheme No. Scheme CWS GLOBE OSP NW_NLTN PROJECT SITE INSTRUCTION FORM Segment No. : Cable