SlideShare a Scribd company logo
Project Management & Technical
Consultancy Services

Domain of application: Transportation, Railways




                               By Gabriel Nistorescu
Executive Summary
This presentation intends to gives an overview of the
  ‘Project Management and Technical Consultancy’
  services offered during the project lifecycle:
1. Project Management (PMBOK, PRINCE2, ITIL V3);
2. Pre-feasibility and Feasibility studies;
3. Contract Requirements;
4. Design review and approval;
5. Installation supervision;
6. FAT, IFAT;
7. Site and System based T&C
8. System Validation, Acceptance, Homologation;
9. Post-completion supporting activities.
1. Project Management
i.      Integration Management
ii.     Scope Management;
iii.    Time Management;
iv.     Cost Management;
v.      Quality Management;
vi.     Communication Management;
vii.    HR Management;
viii.   Risk Management;
ix.     Procurement Management;
1.1 – Integration Management
   Project Management Plan and subsidiaries;
   Project Procedures: Change Control, Material approval, Minutes of
    meeting, Non-conformities, Audit, Quality Plan and Manual, Review
    Contractor Project Documentation, Mission, Time Management etc.
   Configuration Management System;
   Change Control Committee (Dispute Adjudication Board);
   Contract Dispute Resolution;
   Project Management Information Systems e.g. Aconex, Sharepoint;
   Health & Safety Plan;
   Issue Register;
   Management Meetings;
   Project Database and Document Control;
1.2 – Scope Management
   Work Breakdown Structure;          Variation Instruction
   WBS Dictionary;
   Monitor and Control the
    implementation of the contract
    ‘Technical’ and ‘General’
    specifications;
   Prepare ‘Variation instruction’
    to instruct the ‘Contractor’ for
    additional works after obtaining
    the ‘Employer’ approval;
   Produce and maintain ‘Variation
    Instruction Registry’ and forms;
   Reduce the ‘Contractor’ scope
    of works via ‘Notice To Claim’
    to eliminate unnecessary or
    out-of-date project
    deliverables;
1.3 – Time Management
   Prepare/Evaluate the             Schedule of works
    ‘Consultant’ / ‘Contractor’
    schedule of works;
   Resource calendars;
   Integrate new activities
    generated by ‘Variation
    instructions’ onto schedule of
    works;
   Control of delays,
    acceleration program;
   Software for planning:
    Microsoft Project, Primavera
    P6 (ongoing);
1.4 – Cost Management
   Independent cost evaluation;    Cost Estimation
   Cost control;
   Validate ‘Monthly Payment
    Certificates’. Keep accurate
    evidence of spending;
   Invoice for procurement of
    equipment and external
    services;
   Commercial evaluation of
    additional works, ‘Notice to
    Claim’, ‘Extension of Time’;
   Deduction of contractor costs
    for unnecessary works via
    NTC;
   Budget for own project works;
   Cost Benefit Analysis;
   Commercial meetings;
1.5 – Quality Management
   Quality Plan;                 Non-Conformity
   Quality Manual;
   Quality Assurance;
   Quality Control;
   Audits;
   Clarification meetings;
   Equipment certification
    testing;
   Implement ‘Quality
    Management System’ using
    dedicated software: Minitab
    15 etc.
1.6 – Communication Management
   Communication Management      Project Monthly Report
    Plan;
   Monthly, Trimestrial,
    Semestrial and Annual
    Reports;
   Minutes of Meeting, Meeting
    Agenda, Attendance List;
   Presentations in ‘Power
    Point’;
   Procedure for project
    communication;
1.7 – HR Management
   Evaluation of the ‘Consultant’    Project Chart
    and ‘Contractor’ resources;
   Analyze of optimal organization
    chart. Change of organization
    structure: Functional, Matrix,
    Projectized;
   Organization Chart;
   Post Description;
   Responsibility Matrix;
   Staff recruitment;
   Resource allocation plan;
   Key Performance Indicators;
   Team Building & Motivation;
   HR Procedures;
1.8 – Risk Management
   Risk Management Procedure;     Risk Register
   Risk Register;
   Risk Management Meetings;
   Brainstorming;
   Impact of the identified
    project risks onto schedule,
    cost, quality;
   Risk minimization;
   Internal and External Risks;
   Stakeholder Management;
   Risk management software
    tools: Risk Matrix (MITRE).
1.9 – Procurement Management
   Subcontractor ‘Contract        Tender Evaluation
    Requirements’, RFP;
   Seller conference, Q&A
    session;
   Tender evaluation, selection
    of subcontractor services;
   Supplier approval/appraisal;
   Equipment approval, Railway
    Asset Register;
   Subcontractor management
    during the project works;
   Performance monitoring;
   Contract disputes and close;
   Procurement schedule;
2 – Pre-feasibility and Feasibility Studies
    ‘Transport Master Plan’, traffic   Investment Methodology
     simulation studies;
    Route alignment and profile;
    Investment methodology:
     GRIP, PMBOK/EN 50126 etc.
    Scheme requirements,
     Options identification and
     selection;
    Project Design Specification;
    Project Cost Estimation;
Option selection     Structure of the system




Example: Pre-Feasibility/Feasibility
EXAMPLE
System Architecture
3 – Contract Requirements
   Contract Management e.g. FIDIC Yellow/Red/White Books, French
    system (CPS-CA, CPS-STG) etc.
   Technical contract requirements (separate books) for rail systems
    (signaling, telecom, traffic management, electrification, power supply,
    rolling stock, depot, permanent way, AFC, SCADA etc) and Civil/E&M
    disciplines;
   General Contract Specification, Administrative Clauses;
   Directive drawings;
   Operation and Maintenance Plan;
   RAMS Plan;
   Technical assistance during the tender process;
   Q&A Session, Presentations;
   Evaluation of tender response;
   Project Management, HSQE;
4 – Design review & approval
   Review & approve the contractor design versus contract specification,
    approved variation instructions; applicable standards;
   Design review comments;
   Organize clarification meetings;
   Close out of the open points. Agree the way forward;
   Organize technical presentation at different design stages;
   Check design progression against the project milestones;
   Co-ordination inter railway system discipline, E&M, external
    interfaces;
   Elements to be checked: functional requirements, performance
    specifications, operation and maintenance, standards and norms,
    technical specification, technology imposed, strategy, interfaces, Health
    & Safety, Environment etc;
   Communicate after each submission the status of design
    documentation: approved, approved with comments, rejected, resubmit
Procedure for review & approve the
Review Comment Sheet   Contractor’s project documentation




 Example: Design Review & Approval
5 – Installation Supervision
   Review and approve all contractor’s documentation necessary to
    support installation stage: EIP, Site/Intra-site installation documentation,
    Combined Service Drawings etc;
   Review & approve ‘General Installation Documentation’: ‘Equipment
    naming & tagging, Power distribution, Equipment earthing etc;
   Review and approve ‘Method Statement’, QESH Documentation;
   Review and approve sub-contractors for installation;
   Evaluate and monitor Contractor’s performances, program of works,
    monthly reports, resource allocation plan and utilization;
   On-site supervision, Witnessing, Notification for witnessing;
   Organize progression on-site/in-house meetings, remedial works;
   Keep an accurate information on ‘Registry of Defects’, ‘Issue Register’,
    prepare ‘Notice To Non-Conformance’;
   Assist for the handover of infrastructure, sign/approve ‘Site Inspection
    Check-Out’ forms;
   Equipment approval, supplier appraisal;
   Prepare ‘Variation Instruction’, unforeseen works;
Subcontractor review (Monthly
Report)                         Issue Register




   Example: Installation Supervision
6 – FAT, IFAT
   T&C are to be carried out according ‘V-lifecycle’, EN 50126;
   The EN 50126 reveals 2 level of T&C: FAT/IFAT, Field T&C;
   FAT aims to test basic equipment functionalities in accordance with
    the product datasheet. IFAT replicates the network architecture
    (low level, pilot test in factory), basically includes all subsystem
    components and test the integration between them;
   FAT/IFAT are organized at the manufacturer premises, dedicated
    laboratories and replicates minimal architecture of the system;
   IFAT is designed as three step test: internal integration between the
    backbone elements, integration between rail system components
    (signaling, telecom, system integrator, AFC, RSK etc) and integration
    with external subsystem: FPS, TVS, Lift & Elevators, External Units;
   The ‘Consultant’ role consist on: review & approve test procedures;
    organize clarification meetings, witnessing of the test, review &
    approve test report, validate the equipment & system proposed;
Test Structure (Procedure)   Test Report: Acceptance




                   Example: IFAT
7.1 – Site based T&C
   Review and approve of documentation that supports management
    of T&C:VTA Plan,VTA Program;
   Review and approve site specific test procedures: SAT, SIT;
   SAT: designated to test basic functionality of the stand alone
    equipment on site (e.g. Signalling Interlocking,VDU, Fire Protection
    System, Telecom backbone and components);
   SIT: designated to test integration between subsystem components
    on site (e.g. Signalling Interlocking to outdoor equipment, Signalling
    Interlocking to Automated Block, Signaling to Telecom, Telecom
    system etc);
   Witness T&C activities based on the program of works;
   Record of defects and agree corrective measures to be put in
    place;
   Bi-weekly progression meetings, on-site clarification meetings;
7.2 – System specific T&C
   Comprises both Static and Dynamic Tests;
   E2ET: test of integration between the site equipment and traffic
    management centre/ERTMS/Network Management Centre;
   System Integration Test: test the system wide integration between
    rail system components, other subsystems to rail systems, external
    interfaces;
   Review and approve system specific test procedures: E2ET, System
    Integration;
   Witness the tests, record defects, agrees corrective procedures;
   Validate test results, approve test reports;
   Commissioning of the infrastructure in accordance with manuals;
   Dynamic tests structure comprises: On-board signaling to fixed
    infrastructure, TCMS(rolling stock maintenance), ETCS N1/2 etc;
8 – System validation, acceptance,
homologation
   Review and approve of the ‘Maintenance Plan and Manuals’, ‘Operation
    Plan’, ‘As-Built’;
   Review and approve the procedure for ‘System Validation’;
   System Validation & Acceptance are ‘Operational’ type tests which are
    to be performed by ‘Operational’ experts. The Discipline Experts has
    to support the ‘Operational’ experts and perform corrective actions;
   System Validation is performed by the ‘Principal Contractor’ under the
    assistance of the ‘Operator’, ‘Employer’ and ‘Consultant’;
   System Acceptance Tests are performed by nominated ‘Operator’
    under supervision (witness) of ‘Principal Contractor’ and ‘Consultant’;
   If the system fulfills operational conditions and the number of defects
    is less than expected, the system is homologated and ‘Taken-In Over’
    certificate issued;
   Transfer of the infrastructure to the ‘Operator’, handover of
    equipment spares;
9 – Post-completion supporting
activities
   Administrative Close of the Contract;
   Technical audits, network capacities and performances;
   Re-design of the network, increase capacities;
   Defect statistics and records;
   Monitor of maintenance activity;
   Technical support;
   Training;

More Related Content

What's hot

The Commissioning Process
The Commissioning ProcessThe Commissioning Process
The Commissioning Process
d_mackay
 
Governance - Project Management Office Professional Services
Governance - Project Management Office Professional ServicesGovernance - Project Management Office Professional Services
Governance - Project Management Office Professional Services
Mark S. Mahre
 
Example BHP QCP Revision 3
Example BHP QCP Revision 3 Example BHP QCP Revision 3
Example BHP QCP Revision 3 Dennis J Morgan
 
Program management-steps
Program management-stepsProgram management-steps
Program management-steps
Bhawani N Prasad
 
CDS Construction Execution Process ^0 Strategy
CDS Construction Execution Process ^0 StrategyCDS Construction Execution Process ^0 Strategy
CDS Construction Execution Process ^0 StrategyRobert Doig
 
Leak d Detection feasibility study iFluids Engineering
Leak d Detection feasibility study iFluids EngineeringLeak d Detection feasibility study iFluids Engineering
Leak d Detection feasibility study iFluids Engineering
John Kingsley
 
Manu Mohan_resume
Manu Mohan_resumeManu Mohan_resume
Manu Mohan_resumeManu Mohan
 
Mechanical Completions
Mechanical CompletionsMechanical Completions
Mechanical Completions
Andy Lang
 
Kpi Development Slide
Kpi  Development SlideKpi  Development Slide
Kpi Development Slideguestfcf8f1
 
Pmicos 2011 Review And Analysis Of Mitigation Schedules
Pmicos 2011 Review And Analysis Of Mitigation SchedulesPmicos 2011 Review And Analysis Of Mitigation Schedules
Pmicos 2011 Review And Analysis Of Mitigation Schedules
Chris Carson
 
Recovery Scheduling
Recovery SchedulingRecovery Scheduling
Recovery Scheduling
Chris Carson
 
Presentation1
Presentation1Presentation1
Presentation1
Arun Kumar
 
Planning For Adverse Weather
Planning For Adverse WeatherPlanning For Adverse Weather
Planning For Adverse Weather
Chris Carson
 
Data Migrations Framework V33
Data Migrations Framework V33Data Migrations Framework V33
Data Migrations Framework V33Mark S. Mahre
 
Define Tollgate
Define TollgateDefine Tollgate
Define Tollgate
donhhenry
 

What's hot (20)

The Commissioning Process
The Commissioning ProcessThe Commissioning Process
The Commissioning Process
 
Tollgate Presentation
Tollgate PresentationTollgate Presentation
Tollgate Presentation
 
Qa plan1
Qa plan1Qa plan1
Qa plan1
 
CV
CVCV
CV
 
ACH 216 Lecture 06 (Pre Construction Planning)
ACH 216 Lecture 06 (Pre Construction Planning)ACH 216 Lecture 06 (Pre Construction Planning)
ACH 216 Lecture 06 (Pre Construction Planning)
 
Governance - Project Management Office Professional Services
Governance - Project Management Office Professional ServicesGovernance - Project Management Office Professional Services
Governance - Project Management Office Professional Services
 
Example BHP QCP Revision 3
Example BHP QCP Revision 3 Example BHP QCP Revision 3
Example BHP QCP Revision 3
 
James L Harris CV
James L Harris CVJames L Harris CV
James L Harris CV
 
Program management-steps
Program management-stepsProgram management-steps
Program management-steps
 
CDS Construction Execution Process ^0 Strategy
CDS Construction Execution Process ^0 StrategyCDS Construction Execution Process ^0 Strategy
CDS Construction Execution Process ^0 Strategy
 
Leak d Detection feasibility study iFluids Engineering
Leak d Detection feasibility study iFluids EngineeringLeak d Detection feasibility study iFluids Engineering
Leak d Detection feasibility study iFluids Engineering
 
Manu Mohan_resume
Manu Mohan_resumeManu Mohan_resume
Manu Mohan_resume
 
Mechanical Completions
Mechanical CompletionsMechanical Completions
Mechanical Completions
 
Kpi Development Slide
Kpi  Development SlideKpi  Development Slide
Kpi Development Slide
 
Pmicos 2011 Review And Analysis Of Mitigation Schedules
Pmicos 2011 Review And Analysis Of Mitigation SchedulesPmicos 2011 Review And Analysis Of Mitigation Schedules
Pmicos 2011 Review And Analysis Of Mitigation Schedules
 
Recovery Scheduling
Recovery SchedulingRecovery Scheduling
Recovery Scheduling
 
Presentation1
Presentation1Presentation1
Presentation1
 
Planning For Adverse Weather
Planning For Adverse WeatherPlanning For Adverse Weather
Planning For Adverse Weather
 
Data Migrations Framework V33
Data Migrations Framework V33Data Migrations Framework V33
Data Migrations Framework V33
 
Define Tollgate
Define TollgateDefine Tollgate
Define Tollgate
 

Viewers also liked

Tietoturvallisuuden_kevatseminaari_2013_Timo_Lehtimaki
Tietoturvallisuuden_kevatseminaari_2013_Timo_LehtimakiTietoturvallisuuden_kevatseminaari_2013_Timo_Lehtimaki
Tietoturvallisuuden_kevatseminaari_2013_Timo_Lehtimaki
Valtiokonttori / Statskontoret / State Treasury of Finland
 
Role of Project Management Consultancy in Construction Project
Role of Project Management Consultancy in Construction ProjectRole of Project Management Consultancy in Construction Project
Role of Project Management Consultancy in Construction Project
IOSR Journals
 
Pmc singapore 2016
Pmc singapore 2016Pmc singapore 2016
Pmc singapore 2016
Anant kulkarni
 
Basel III project management services
Basel III project management servicesBasel III project management services
Basel III project management services
Philippe Meyer
 
Project Management Services Overview
Project Management Services OverviewProject Management Services Overview
Project Management Services Overview
billwoerner
 
PMC-Sierra - ERP Case Study
PMC-Sierra - ERP Case StudyPMC-Sierra - ERP Case Study
PMC-Sierra - ERP Case StudyAdhir Mattu
 
eresource nfra ERP - PMC module
eresource nfra ERP  - PMC moduleeresource nfra ERP  - PMC module
eresource nfra ERP - PMC module
nfra erp
 
Why pmc presentation
Why pmc presentationWhy pmc presentation
Why pmc presentation
Deependra Vikram
 
Overview of the Management Consultancy Services
Overview of the Management Consultancy ServicesOverview of the Management Consultancy Services
Overview of the Management Consultancy Services
Jefferson Padilla
 
MANAGEMENT CONSULTING 101 part 1
MANAGEMENT CONSULTING 101 part 1MANAGEMENT CONSULTING 101 part 1
MANAGEMENT CONSULTING 101 part 1
Ahmad Faisal
 
Top Office Etiquette Mistakes
Top Office Etiquette MistakesTop Office Etiquette Mistakes
Top Office Etiquette Mistakes
ej4video
 

Viewers also liked (11)

Tietoturvallisuuden_kevatseminaari_2013_Timo_Lehtimaki
Tietoturvallisuuden_kevatseminaari_2013_Timo_LehtimakiTietoturvallisuuden_kevatseminaari_2013_Timo_Lehtimaki
Tietoturvallisuuden_kevatseminaari_2013_Timo_Lehtimaki
 
Role of Project Management Consultancy in Construction Project
Role of Project Management Consultancy in Construction ProjectRole of Project Management Consultancy in Construction Project
Role of Project Management Consultancy in Construction Project
 
Pmc singapore 2016
Pmc singapore 2016Pmc singapore 2016
Pmc singapore 2016
 
Basel III project management services
Basel III project management servicesBasel III project management services
Basel III project management services
 
Project Management Services Overview
Project Management Services OverviewProject Management Services Overview
Project Management Services Overview
 
PMC-Sierra - ERP Case Study
PMC-Sierra - ERP Case StudyPMC-Sierra - ERP Case Study
PMC-Sierra - ERP Case Study
 
eresource nfra ERP - PMC module
eresource nfra ERP  - PMC moduleeresource nfra ERP  - PMC module
eresource nfra ERP - PMC module
 
Why pmc presentation
Why pmc presentationWhy pmc presentation
Why pmc presentation
 
Overview of the Management Consultancy Services
Overview of the Management Consultancy ServicesOverview of the Management Consultancy Services
Overview of the Management Consultancy Services
 
MANAGEMENT CONSULTING 101 part 1
MANAGEMENT CONSULTING 101 part 1MANAGEMENT CONSULTING 101 part 1
MANAGEMENT CONSULTING 101 part 1
 
Top Office Etiquette Mistakes
Top Office Etiquette MistakesTop Office Etiquette Mistakes
Top Office Etiquette Mistakes
 

Similar to Project Management & Technical Consultancy Services [Transportation, Railways]

5 project commissioning best practices for you to consider
5 project commissioning best practices for you to consider5 project commissioning best practices for you to consider
5 project commissioning best practices for you to consider
Olivia Wilson
 
CV-Sidharth Sunny- Project Engineer
CV-Sidharth Sunny- Project EngineerCV-Sidharth Sunny- Project Engineer
CV-Sidharth Sunny- Project Engineer
Sidharth Sunny
 
CV-Sidharth Sunny Project Engineer
CV-Sidharth Sunny Project EngineerCV-Sidharth Sunny Project Engineer
CV-Sidharth Sunny Project EngineerSidharth Sunny
 
professional services and value engeneering
professional services and value engeneeringprofessional services and value engeneering
professional services and value engeneeringAbdo Jamous El Jamous
 
RAJU-CV(UPDATED) on 2016 Aug 10
RAJU-CV(UPDATED) on 2016 Aug 10RAJU-CV(UPDATED) on 2016 Aug 10
RAJU-CV(UPDATED) on 2016 Aug 10Satyanarayana Raju
 
Project Control- Overview Presentation Tafseer
Project Control- Overview Presentation   TafseerProject Control- Overview Presentation   Tafseer
Project Control- Overview Presentation Tafseer
Kishan Solankimbaccepmp
 
Control procurement
Control procurement Control procurement
Control procurement
Shereef Sabri
 
Ch 2 project planning and control
Ch 2 project planning and controlCh 2 project planning and control
Ch 2 project planning and controlJanak Singh Chauhan
 
Project PlanGroup 2The Data Center Project PlanProj.docx
Project PlanGroup 2The Data Center Project PlanProj.docxProject PlanGroup 2The Data Center Project PlanProj.docx
Project PlanGroup 2The Data Center Project PlanProj.docx
briancrawford30935
 
250250902-141-ISACA-NACACS-Auditing-IT-Projects-Audit-Program.pdf
250250902-141-ISACA-NACACS-Auditing-IT-Projects-Audit-Program.pdf250250902-141-ISACA-NACACS-Auditing-IT-Projects-Audit-Program.pdf
250250902-141-ISACA-NACACS-Auditing-IT-Projects-Audit-Program.pdf
Addisu15
 
CV ISMAIL SHAIKH-31.10.2015
CV ISMAIL SHAIKH-31.10.2015CV ISMAIL SHAIKH-31.10.2015
CV ISMAIL SHAIKH-31.10.2015Ismail Shaikh
 
Vignesh Kumar C- TPI Coordinator
Vignesh Kumar C- TPI CoordinatorVignesh Kumar C- TPI Coordinator
Vignesh Kumar C- TPI CoordinatorVignesh Kumar C
 
Warehouse Operations Redefining methodology
Warehouse Operations Redefining methodologyWarehouse Operations Redefining methodology
Warehouse Operations Redefining methodology
AkhilRanjanDubey
 
Establishing An Enterprise and Project Management.pptx
Establishing An Enterprise and Project Management.pptxEstablishing An Enterprise and Project Management.pptx
Establishing An Enterprise and Project Management.pptx
shrinivas kulkarni
 
MuneerKhanResume v1
MuneerKhanResume v1MuneerKhanResume v1
MuneerKhanResume v1muneer khan
 
Resume - MOSTAFA SAYED (C.V)
Resume - MOSTAFA SAYED (C.V)Resume - MOSTAFA SAYED (C.V)
Resume - MOSTAFA SAYED (C.V)Mostafa Sayed
 

Similar to Project Management & Technical Consultancy Services [Transportation, Railways] (20)

5 project commissioning best practices for you to consider
5 project commissioning best practices for you to consider5 project commissioning best practices for you to consider
5 project commissioning best practices for you to consider
 
CV-Sidharth Sunny- Project Engineer
CV-Sidharth Sunny- Project EngineerCV-Sidharth Sunny- Project Engineer
CV-Sidharth Sunny- Project Engineer
 
CV-Sidharth Sunny Project Engineer
CV-Sidharth Sunny Project EngineerCV-Sidharth Sunny Project Engineer
CV-Sidharth Sunny Project Engineer
 
professional services and value engeneering
professional services and value engeneeringprofessional services and value engeneering
professional services and value engeneering
 
RAJU-CV(UPDATED) on 2016 Aug 10
RAJU-CV(UPDATED) on 2016 Aug 10RAJU-CV(UPDATED) on 2016 Aug 10
RAJU-CV(UPDATED) on 2016 Aug 10
 
Prashant Wani1
Prashant Wani1Prashant Wani1
Prashant Wani1
 
Project Control- Overview Presentation Tafseer
Project Control- Overview Presentation   TafseerProject Control- Overview Presentation   Tafseer
Project Control- Overview Presentation Tafseer
 
Control procurement
Control procurement Control procurement
Control procurement
 
Ch 2 project planning and control
Ch 2 project planning and controlCh 2 project planning and control
Ch 2 project planning and control
 
ALAA Y ABUGHAIDAH
ALAA Y ABUGHAIDAHALAA Y ABUGHAIDAH
ALAA Y ABUGHAIDAH
 
Project PlanGroup 2The Data Center Project PlanProj.docx
Project PlanGroup 2The Data Center Project PlanProj.docxProject PlanGroup 2The Data Center Project PlanProj.docx
Project PlanGroup 2The Data Center Project PlanProj.docx
 
250250902-141-ISACA-NACACS-Auditing-IT-Projects-Audit-Program.pdf
250250902-141-ISACA-NACACS-Auditing-IT-Projects-Audit-Program.pdf250250902-141-ISACA-NACACS-Auditing-IT-Projects-Audit-Program.pdf
250250902-141-ISACA-NACACS-Auditing-IT-Projects-Audit-Program.pdf
 
Profile_Kishore Sundar
Profile_Kishore SundarProfile_Kishore Sundar
Profile_Kishore Sundar
 
CV ISMAIL SHAIKH-31.10.2015
CV ISMAIL SHAIKH-31.10.2015CV ISMAIL SHAIKH-31.10.2015
CV ISMAIL SHAIKH-31.10.2015
 
Srinivaskumar_cv_16
Srinivaskumar_cv_16Srinivaskumar_cv_16
Srinivaskumar_cv_16
 
Vignesh Kumar C- TPI Coordinator
Vignesh Kumar C- TPI CoordinatorVignesh Kumar C- TPI Coordinator
Vignesh Kumar C- TPI Coordinator
 
Warehouse Operations Redefining methodology
Warehouse Operations Redefining methodologyWarehouse Operations Redefining methodology
Warehouse Operations Redefining methodology
 
Establishing An Enterprise and Project Management.pptx
Establishing An Enterprise and Project Management.pptxEstablishing An Enterprise and Project Management.pptx
Establishing An Enterprise and Project Management.pptx
 
MuneerKhanResume v1
MuneerKhanResume v1MuneerKhanResume v1
MuneerKhanResume v1
 
Resume - MOSTAFA SAYED (C.V)
Resume - MOSTAFA SAYED (C.V)Resume - MOSTAFA SAYED (C.V)
Resume - MOSTAFA SAYED (C.V)
 

Project Management & Technical Consultancy Services [Transportation, Railways]

  • 1. Project Management & Technical Consultancy Services Domain of application: Transportation, Railways By Gabriel Nistorescu
  • 2. Executive Summary This presentation intends to gives an overview of the ‘Project Management and Technical Consultancy’ services offered during the project lifecycle: 1. Project Management (PMBOK, PRINCE2, ITIL V3); 2. Pre-feasibility and Feasibility studies; 3. Contract Requirements; 4. Design review and approval; 5. Installation supervision; 6. FAT, IFAT; 7. Site and System based T&C 8. System Validation, Acceptance, Homologation; 9. Post-completion supporting activities.
  • 3. 1. Project Management i. Integration Management ii. Scope Management; iii. Time Management; iv. Cost Management; v. Quality Management; vi. Communication Management; vii. HR Management; viii. Risk Management; ix. Procurement Management;
  • 4. 1.1 – Integration Management  Project Management Plan and subsidiaries;  Project Procedures: Change Control, Material approval, Minutes of meeting, Non-conformities, Audit, Quality Plan and Manual, Review Contractor Project Documentation, Mission, Time Management etc.  Configuration Management System;  Change Control Committee (Dispute Adjudication Board);  Contract Dispute Resolution;  Project Management Information Systems e.g. Aconex, Sharepoint;  Health & Safety Plan;  Issue Register;  Management Meetings;  Project Database and Document Control;
  • 5. 1.2 – Scope Management  Work Breakdown Structure; Variation Instruction  WBS Dictionary;  Monitor and Control the implementation of the contract ‘Technical’ and ‘General’ specifications;  Prepare ‘Variation instruction’ to instruct the ‘Contractor’ for additional works after obtaining the ‘Employer’ approval;  Produce and maintain ‘Variation Instruction Registry’ and forms;  Reduce the ‘Contractor’ scope of works via ‘Notice To Claim’ to eliminate unnecessary or out-of-date project deliverables;
  • 6. 1.3 – Time Management  Prepare/Evaluate the Schedule of works ‘Consultant’ / ‘Contractor’ schedule of works;  Resource calendars;  Integrate new activities generated by ‘Variation instructions’ onto schedule of works;  Control of delays, acceleration program;  Software for planning: Microsoft Project, Primavera P6 (ongoing);
  • 7. 1.4 – Cost Management  Independent cost evaluation; Cost Estimation  Cost control;  Validate ‘Monthly Payment Certificates’. Keep accurate evidence of spending;  Invoice for procurement of equipment and external services;  Commercial evaluation of additional works, ‘Notice to Claim’, ‘Extension of Time’;  Deduction of contractor costs for unnecessary works via NTC;  Budget for own project works;  Cost Benefit Analysis;  Commercial meetings;
  • 8. 1.5 – Quality Management  Quality Plan; Non-Conformity  Quality Manual;  Quality Assurance;  Quality Control;  Audits;  Clarification meetings;  Equipment certification testing;  Implement ‘Quality Management System’ using dedicated software: Minitab 15 etc.
  • 9. 1.6 – Communication Management  Communication Management Project Monthly Report Plan;  Monthly, Trimestrial, Semestrial and Annual Reports;  Minutes of Meeting, Meeting Agenda, Attendance List;  Presentations in ‘Power Point’;  Procedure for project communication;
  • 10. 1.7 – HR Management  Evaluation of the ‘Consultant’ Project Chart and ‘Contractor’ resources;  Analyze of optimal organization chart. Change of organization structure: Functional, Matrix, Projectized;  Organization Chart;  Post Description;  Responsibility Matrix;  Staff recruitment;  Resource allocation plan;  Key Performance Indicators;  Team Building & Motivation;  HR Procedures;
  • 11. 1.8 – Risk Management  Risk Management Procedure; Risk Register  Risk Register;  Risk Management Meetings;  Brainstorming;  Impact of the identified project risks onto schedule, cost, quality;  Risk minimization;  Internal and External Risks;  Stakeholder Management;  Risk management software tools: Risk Matrix (MITRE).
  • 12. 1.9 – Procurement Management  Subcontractor ‘Contract Tender Evaluation Requirements’, RFP;  Seller conference, Q&A session;  Tender evaluation, selection of subcontractor services;  Supplier approval/appraisal;  Equipment approval, Railway Asset Register;  Subcontractor management during the project works;  Performance monitoring;  Contract disputes and close;  Procurement schedule;
  • 13. 2 – Pre-feasibility and Feasibility Studies  ‘Transport Master Plan’, traffic Investment Methodology simulation studies;  Route alignment and profile;  Investment methodology: GRIP, PMBOK/EN 50126 etc.  Scheme requirements, Options identification and selection;  Project Design Specification;  Project Cost Estimation;
  • 14. Option selection Structure of the system Example: Pre-Feasibility/Feasibility
  • 16. 3 – Contract Requirements  Contract Management e.g. FIDIC Yellow/Red/White Books, French system (CPS-CA, CPS-STG) etc.  Technical contract requirements (separate books) for rail systems (signaling, telecom, traffic management, electrification, power supply, rolling stock, depot, permanent way, AFC, SCADA etc) and Civil/E&M disciplines;  General Contract Specification, Administrative Clauses;  Directive drawings;  Operation and Maintenance Plan;  RAMS Plan;  Technical assistance during the tender process;  Q&A Session, Presentations;  Evaluation of tender response;  Project Management, HSQE;
  • 17. 4 – Design review & approval  Review & approve the contractor design versus contract specification, approved variation instructions; applicable standards;  Design review comments;  Organize clarification meetings;  Close out of the open points. Agree the way forward;  Organize technical presentation at different design stages;  Check design progression against the project milestones;  Co-ordination inter railway system discipline, E&M, external interfaces;  Elements to be checked: functional requirements, performance specifications, operation and maintenance, standards and norms, technical specification, technology imposed, strategy, interfaces, Health & Safety, Environment etc;  Communicate after each submission the status of design documentation: approved, approved with comments, rejected, resubmit
  • 18. Procedure for review & approve the Review Comment Sheet Contractor’s project documentation Example: Design Review & Approval
  • 19. 5 – Installation Supervision  Review and approve all contractor’s documentation necessary to support installation stage: EIP, Site/Intra-site installation documentation, Combined Service Drawings etc;  Review & approve ‘General Installation Documentation’: ‘Equipment naming & tagging, Power distribution, Equipment earthing etc;  Review and approve ‘Method Statement’, QESH Documentation;  Review and approve sub-contractors for installation;  Evaluate and monitor Contractor’s performances, program of works, monthly reports, resource allocation plan and utilization;  On-site supervision, Witnessing, Notification for witnessing;  Organize progression on-site/in-house meetings, remedial works;  Keep an accurate information on ‘Registry of Defects’, ‘Issue Register’, prepare ‘Notice To Non-Conformance’;  Assist for the handover of infrastructure, sign/approve ‘Site Inspection Check-Out’ forms;  Equipment approval, supplier appraisal;  Prepare ‘Variation Instruction’, unforeseen works;
  • 20. Subcontractor review (Monthly Report) Issue Register Example: Installation Supervision
  • 21. 6 – FAT, IFAT  T&C are to be carried out according ‘V-lifecycle’, EN 50126;  The EN 50126 reveals 2 level of T&C: FAT/IFAT, Field T&C;  FAT aims to test basic equipment functionalities in accordance with the product datasheet. IFAT replicates the network architecture (low level, pilot test in factory), basically includes all subsystem components and test the integration between them;  FAT/IFAT are organized at the manufacturer premises, dedicated laboratories and replicates minimal architecture of the system;  IFAT is designed as three step test: internal integration between the backbone elements, integration between rail system components (signaling, telecom, system integrator, AFC, RSK etc) and integration with external subsystem: FPS, TVS, Lift & Elevators, External Units;  The ‘Consultant’ role consist on: review & approve test procedures; organize clarification meetings, witnessing of the test, review & approve test report, validate the equipment & system proposed;
  • 22. Test Structure (Procedure) Test Report: Acceptance Example: IFAT
  • 23. 7.1 – Site based T&C  Review and approve of documentation that supports management of T&C:VTA Plan,VTA Program;  Review and approve site specific test procedures: SAT, SIT;  SAT: designated to test basic functionality of the stand alone equipment on site (e.g. Signalling Interlocking,VDU, Fire Protection System, Telecom backbone and components);  SIT: designated to test integration between subsystem components on site (e.g. Signalling Interlocking to outdoor equipment, Signalling Interlocking to Automated Block, Signaling to Telecom, Telecom system etc);  Witness T&C activities based on the program of works;  Record of defects and agree corrective measures to be put in place;  Bi-weekly progression meetings, on-site clarification meetings;
  • 24. 7.2 – System specific T&C  Comprises both Static and Dynamic Tests;  E2ET: test of integration between the site equipment and traffic management centre/ERTMS/Network Management Centre;  System Integration Test: test the system wide integration between rail system components, other subsystems to rail systems, external interfaces;  Review and approve system specific test procedures: E2ET, System Integration;  Witness the tests, record defects, agrees corrective procedures;  Validate test results, approve test reports;  Commissioning of the infrastructure in accordance with manuals;  Dynamic tests structure comprises: On-board signaling to fixed infrastructure, TCMS(rolling stock maintenance), ETCS N1/2 etc;
  • 25. 8 – System validation, acceptance, homologation  Review and approve of the ‘Maintenance Plan and Manuals’, ‘Operation Plan’, ‘As-Built’;  Review and approve the procedure for ‘System Validation’;  System Validation & Acceptance are ‘Operational’ type tests which are to be performed by ‘Operational’ experts. The Discipline Experts has to support the ‘Operational’ experts and perform corrective actions;  System Validation is performed by the ‘Principal Contractor’ under the assistance of the ‘Operator’, ‘Employer’ and ‘Consultant’;  System Acceptance Tests are performed by nominated ‘Operator’ under supervision (witness) of ‘Principal Contractor’ and ‘Consultant’;  If the system fulfills operational conditions and the number of defects is less than expected, the system is homologated and ‘Taken-In Over’ certificate issued;  Transfer of the infrastructure to the ‘Operator’, handover of equipment spares;
  • 26. 9 – Post-completion supporting activities  Administrative Close of the Contract;  Technical audits, network capacities and performances;  Re-design of the network, increase capacities;  Defect statistics and records;  Monitor of maintenance activity;  Technical support;  Training;