SlideShare a Scribd company logo
Everything You Should Know About
PMP® & CAPM® Certifications
Seshne Govender
vCare Project Management Session - 4
www.vcareprojectmanagement.com
I am the Founder and Director of Fundamental Project Management, having over 15 years of
experience as a Program and Project Manager managing numerous large successful deliveries
with complex IT components in the Financial Services, Telecommunications, and Retail Sectors
of South Africa. This journey has provided me with invaluable experience in the Project
Management career path.
Started my career as an Engineer, studied Chemical Engineering in South Africa. Within a short
time, found my passion in projects in the Banking Industry. I have worked in diverse roles such
as Process Engineer, Business Analyst, Project Manager, and finally, Program Manager: A
career that provided joy to me for many years.
A certified Program Management Professional (PgMP)® and Project Management Professional
(PMP)®, which were invaluable in my Project Management Journey.
I am passionate about training, coaching, and mentoring people along the Project Management
career path.
Successful Program Manager, Project Manager & Trainer
Seshne Govender
Project Management Expert
PMP® & C
APM® Certifications
Waterfall, Agile, Hybrid, Benefits, Principles
Session - 4
Key Takeaways
Upcoming Session Roadmap
Session - 3 Recap Refresher
Waterfall vs. Agile vs. Hybrid
Benefits of Agile in Project Management
Benefits of PMP® in International Market
Four Principles of Project Management Training
Emotional Stability - Balance
Sample Exam Like Questions
Frequently Asked Questions
PMP® & C
APM® Certifications
Domains, Tasks, Understanding PMBOK®
Session - 3 Recap
The CAPM® examination is comprised of 150 multiple-choice questions
Of the 150 questions, 15 are considered pretest questions
Pretest questions do not affect the score and are used in examinations
as an effective and legitimate way to test the validity of future
examination questions
CAPM® EXAMINATION QUESTIONS
135 No. of Scored
Questions 15
No. of Pretest
(Unscored)
Questions
150
Total
Examination
Questions
3 hrs
Allotted
Examination
Time
The PMP® examination is comprised of 180 multiple-choice questions
Of the 180 questions, 5 are considered pretest questions
Pretest questions do not affect the score and are used in examinations as
an effective and legitimate way to test the validity of future examination
questions
PMP® EXAMINATION QUESTIONS
175 No. of Scored
Questions 5
No. of Pretest
(Unscored)
Questions
180
Total
Examination
Questions
230
Allotted
Examination
Time
CAPM® NEW EXAM REFERENCE LIST
PMBOK® Seventh
Edition
Business Analysis for
Practitioners: A Practice
Guide PMI
Effective Project Management:
Traditional, Agile, Extreme, Hybrid
Robert K. Wysocki
The Agile Practice
Guide
Project Management
Answer Book, 2nd Edition
Jeff Furman
The PMI Guide to
Business Analysis
(December 2017) PMI
STUDY MATERIALS & BOOKS TO BE REFERRED - PMP®
Effective Project
Management: Traditional,
Agile, Extreme, Hybrid
Information Technology
Project Management –
Seventh Edition
Project Managers Portable
Handbook – Third Edition
Project Management: A
Systems Approach to Planning,
Scheduling, and Controlling
Project Management: The
Managerial Process
The Project Management Tool
Kit: 100 Tips and Techniques for
Getting the Job Done Right
The Agile
Practice Guide
Fundamentals of technology
Project Management – Second
Edition
Essential Scrum: A Practical
Guide to the most popular
Agile Process
Process Groups
A Practical Guide
PMBOK®
Seventh Edition
Demonstrate an understanding of the various
project life cycles and processes.
Demonstrate an understanding of project
management planning.
Demonstrate an understanding of project roles
and responsibilities.
Determine how to follow and execute planned
strategies or frameworks (e.g., communication,
risks, etc.).
Demonstrate an understanding of common
problem-solving tools and techniques.
Explain when it is appropriate to use a
predictive, plan-based approach.
Demonstrate an understanding of a project
management plan schedule.
Determine how to document project controls of
predictive, plan-based projects.
Explain when it is appropriate to use
an adaptive approach.
Determine how to plan project
iterations.
Determine how to document project
controls for an adaptive project.
Explain the components of an
adaptive plan.
Determine how to prepare and execute
task management steps.
Project Management Fundamentals and Core Concepts
(5 Tasks)
(3 Tasks)
(5 Tasks)
36% 17% 20%
Predictive, Plan-Based Methodologies Agile Frameworks / Methodologies
Demonstrate an understanding of business
analysis (BA) roles and responsibilities.
Determine how to conduct stakeholder
communication.
Determine how to gather requirements.
Demonstrate an understanding of product
roadmaps.
Determine how project methodologies influence
business analysis processes.
Validate requirements through product delivery.
27%
Business Analysis Frameworks
(6 Tasks)
CAPM®
DOMAINS
Build a team
Define team ground rules
Build a shared understanding of the project
Negotiate project agreements
Empower team members and stakeholders
Ensure team members/stakeholders are adequately trained
Engage and support virtual teams
Collaborate with stakeholders
Lead a team
Address and get rid of team barriers, obstacles, and blockers
Support team performance
Manage conflict
Mentoring appropriate stakeholders
Enhance group success by utilizing emotional intelligence
Plan and manage the scope
Plan and manage budget and resources
Plan and manage the schedule
Plan and manage the quality of products and deliverables
Integrate project planning activities
Plan and manage procurement
Determine appropriate project methodology / methods and practices
Establish project governance structure
Plan and manage project / phase closure
Execute projects to deliver business value
Manage communications
Assess and manage risks
Engage stakeholders
Manage project artifacts
Manage project changes
Manage project issues
Ensure knowledge transfer for project continuity
Plan and manage project compliance.
Evaluate and deliver project benefits
and value
Evaluate and address external business
environment changes for impact on the
scope
Support organizational change
People Domain Process Domain Business Environment Domain
(14 Tasks)
(17 Tasks)
(4 Tasks)
42% 50% 8%
PMP®DOMAINS
Waterfall vs. Agile
"This project has got so big,
I'm not sure I'll be able to
deliver it!"
"It's so much better
delivering this project in
bite-sized sections"
Release Release
Waterfall
Define
Build
Release
Risk
Define
Build
Release
Define
Build
Define
Build
Risk
Agile
Hybrid
Benefits of PMP® in International Market
YOU WILL ENHANCE
YOUR CAREER
OPPORTUNITIES
YOU WILL BE RECOGNIZED
AS AN EXPERIENCED
PROFESSIONAL
YOU WILL SPEAK THE
RIGHT LANGUAGE
YOU WILL LEARN
NEW SKILLS
YOU WILL (PROBABLY)
EARN MORE MONEY
YOU WILL
DEMONSTRATE YOUR
DEDICATION
Four Principles of Project Management Training
Customization
Learning
Style
Experiential
Learning
Continuous
Improvement
Benefits of Agile in Project Management
Agile is also a mindset that influences how we choose to think and act. As agilists, we choose to:
Accelerate our value
realization by embracing
worthwhile changes.
Delight customers by
taking a customer-centric
view to our work.
Improve group capability by proactively
collaborating instead of working in
functional silos.
Improve predictably by refining our
understanding of what is needed through
regularly showing our work and acting on
feedback.
Optimize flow by working on small
items instead of big items. Big things
are accomplished incrementally as a
series of small things.
Limiting the amount of work in
progress makes it easier to
identify inefficiency in a
team's workflow.
Improve continuously by frequently
learning from our experience and
evolving our practices based on what
we learned.
Source: PMI
1
2
3
4
5
6
7
Emotional Stability - Balance
Emotional Intelligence refers to our ability to
recognize, control, and communicate emotions.
EMOTIONAL INTELLIGENCE
Benefits of Increasing EI for Project Managers
Use emotions to
improve and guide
your thinking
Be able to
persuade and
influence others
Remove barriers
to working with
others
Quickly transform change,
problems and conflict into
opportunities
Assist your team in
producing project
success
01
02 04
03 05
Source: Casper, C. M. (2002). Using emotional intelligence to improve project performance. Paper presented at Project Management Institute Annual
Seminars & Symposium, San Antonio, TX. Newtown Square, PA: Project Management Institute.
Practice Makes Perfect - The Balancing Act
Feel
Think
Act
1
2
3
Be aware of emotions. Understand what
you feel and try to understand what others
feel.
Think why you feel the emotions. Analyze
them carefully. Think about the way
forward. Take control of emotions.
Only act when you understand the situation
clearly. Until then you are not in the best
position to make decisions.
Source: Fernando, M. (2003). Strong feelings. PM Network, 17(9), 64–66.
Sample Exam Like Questions
What prototyping technique shows the
sequence or navigation through a series
of images or illustrations?
Storyboarding
Wireframes
Evolutionary
Interactive
a.
b.
c.
d.
What prototyping technique shows the
sequence or navigation through a series
of images or illustrations?
Storyboarding
Wireframes
Evolutionary
Interactive
a.
b.
c.
d.
What is the purpose of a
Requirements Traceability Matrix
(RTM) in project management?
To track the progress of project deliverables.
To document and manage project risks.
To link product requirements to the deliverables
that satisfy them.
To measure and assess project performance.
a.
b.
c.
d.
What is the purpose of a
Requirements Traceability Matrix
(RTM) in project management?
To track the progress of project deliverables.
To document and manage project risks.
To link product requirements to the deliverables
that satisfy them.
To measure and assess project performance.
a.
b.
c.
d.
Which component of a business
case assesses the financial viability
of a project?
Strategic alignment
Economic feasibility study
Assessment of risk exposure
Expected key performance measures
a.
b.
c.
d.
Which component of a business
case assesses the financial viability
of a project?
Strategic alignment
Economic feasibility study
Assessment of risk exposure
Expected key performance measures
a.
b.
c.
d.
A project team lead has challenged the team to minimize
defects and waste in project teamwork. As an initial
step, the team proposes to assess the relevant quality
standards and framework. How can the team do this?
Review the requirements management plan.
Check the ISO.org website.
Investigate the project quality metrics.
Interview the person who manages quality compliance.
a.
b.
c.
d.
A project team lead has challenged the team to minimize
defects and waste in project teamwork. As an initial
step, the team proposes to assess the relevant quality
standards and framework. How can the team do this?
Review the requirements management plan.
Check the ISO.org website.
Investigate the project quality metrics.
Interview the person who manages quality compliance.
a.
b.
c.
d.
A project team member is having an extremely difficult and
busy personal life. The team is NOT aware. They only see
mistakes and missed deadlines. The team is in the middle of an
iteration and this team member’s latest mistake has caused a
major issue. How should the team lead respond in this
situation?
Coach the team member.
Replace the team member.
Discipline the team member.
Consult the team member’s functional manager.
a.
b.
c.
d.
A project team member is having an extremely difficult and
busy personal life. The team is NOT aware. They only see
mistakes and missed deadlines. The team is in the middle of an
iteration and this team member’s latest mistake has caused a
major issue. How should the team lead respond in this
situation?
Coach the team member.
Replace the team member.
Discipline the team member.
Consult the team member’s functional manager.
a.
b.
c.
d.
A project manager is working on a data center migration
project and is developing the schedule management plan. The
project was planned to last 40 days and the project sponsor
wants it done in 35. Which action should the project manager
take to amend this schedule for the new requirement?
Crash activities that are NOT on the critical path.
Increase duration of the critical path.
Use leads.
Use lags.
a.
b.
c.
d.
A project manager is working on a data center migration
project and is developing the schedule management plan. The
project was planned to last 40 days and the project sponsor
wants it done in 35. Which action should the project manager
take to amend this schedule for the new requirement?
Crash activities that are NOT on the critical path.
Increase duration of the critical path.
Use leads.
Use lags.
a.
b.
c.
d.
What is reserve analysis in
PMP®?
Reserve analysis is a technique the project manager
and project team use to determine the total project
budget for long-running projects.
Total Project Budget = Cost Baseline + Management reserve
Cost Baseline = Cost Estimate + Contingency Reserve
Is PMP® certification worth it
for an experienced project
manager?
Networking
opportunities
that can help
you grow your
career.
Greater
opportunities for
managing larger
scale projects.
Earn 16% higher
with a PMP
certification.
®
What are the benefits of PMP®
certification?
Improves career opportunities that can lead to career growth.
Adds value to your CV, proving necessary experience and skills.
Makes it easier to access opportunities in the market.
Earn more than those without certification.
What are the benefits of
joining PMI local chapters
after getting a PMP®
certification?
Connect with other
project managers.
Develop project
management skills by
staying up-to-date.
Give back to your community
by volunteering your skills,
expertise, and time.
What is your toughest
topic for PMP®?
PMP® Domains
42% 50% 8%
People Process
Business
Environment
Start with the Process
Domain and ensure
thorough understanding of
the content before moving
on to the People and
Business Environment.
How can I qualify for PMP®
hours if all of my project
management experience is
from being self-employed?
1
3
2
4
PMI will accept professional
working experience.
Self-employed work must follow
PMI definition of project.
A project is temporary because
it has a defined beginning &
end in time & therefore defined
scope & resources.
Creating a unique product,
service, or result is a temporary
endeavour.
A project is unique because it
is not a routine operation but
a specific set of operations
designed to accomplish a
singular goal.
Audience
Questions
I have MSc in Project Management,
is it mandatory to take 35 hrs
training before PMP® exam?
PMP® & C
APM® Certifications
How to clear CAPM® & PMP® Exam in First Attempt?
Session - 5
Frequently Asked Questions
Upcoming Session Roadmap
Session - 4 Recap Refresher
CAPM® Knowledge Bytes - Key Terms & Definitions
PMP® Knowledge Bytes - Key Terms & Definitions
How to clear CAPM® & PMP® Exam in First Attempt?
Tips & Secrets to Solve Exam Questions
Time Management & Exam Preparation Planner
Sample Exam Like Questions
Session - 5
Agenda
18 October'23
th
UPCOMING
SESSIONS
09:30 AM - 10:30 AM (BST)
10:30 AM - 11:30 AM (CEST/SAST)
11:30 AM - 12:30 PM (EAT/AST)
12:30 PM - 01:30 PM (GST)
02:00 PM - 03:00 PM (IST)
03:30 PM - 04:30 PM (ICT/WIB)
04:30 PM - 05:30 PM (SGT/PHST)
07:30 PM - 08:30 PM (AEDT)
Time:
Session 5: 18 October'23
Session 6: 15 November'23
Session 7: 20 December'23
Session 8: 17 January'24
th
th
th
th
C vCare Project Management
seshne@vcareprojectmanagement.com
+27 722997173
Registered Address:
325 N. Saint Paul St, Suite 3100, Dallas, TX 75201, USA
www.vcareprojectmanagement.com
EIN: 35-2657414
Disclaimer
• PMP, PMI, PMBOK, CAPM, PgMP, PfMP, PBA, RMP, ACP, SP, DA, DASM, DASSM, ATP and OPM3 are registered marks of the Project Management Institute, Inc.

More Related Content

Similar to Session 4 Everything You Should Know About PMP & CAPM Certifications

Project management in IBM EG - lecce_20140224
Project management in IBM EG - lecce_20140224Project management in IBM EG - lecce_20140224
Project management in IBM EG - lecce_20140224Antonio Caforio
 
Session - 6 Everything about PgMP & PfMP Certifications
Session - 6 Everything about PgMP & PfMP CertificationsSession - 6 Everything about PgMP & PfMP Certifications
Session - 6 Everything about PgMP & PfMP Certifications
Dharam Singh PgMP, PfMP, PMP, RMP, ACP, PBA, DASM, DASSM, PMI-ATP
 
Project Management Quick Connects
Project Management Quick ConnectsProject Management Quick Connects
Project Management Quick Connects
Mitchell Manning Sr.
 
UCISA Project and Change Management Group Toolkits
UCISA Project and Change Management Group Toolkits  UCISA Project and Change Management Group Toolkits
UCISA Project and Change Management Group Toolkits
Mark Ritchie
 
Session - 4 Everything about PgMP & PfMP Certifications
Session - 4 Everything about PgMP & PfMP CertificationsSession - 4 Everything about PgMP & PfMP Certifications
Session - 4 Everything about PgMP & PfMP Certifications
Dharam Singh PgMP, PfMP, PMP, RMP, ACP, PBA, DASM, DASSM, PMI-ATP
 
PMP Refresher Course
PMP Refresher CoursePMP Refresher Course
PMP Refresher Course
Edureka!
 
Session 5 Everything You Should Know About PMP & CAPM Certifications
Session 5 Everything You Should Know About PMP & CAPM CertificationsSession 5 Everything You Should Know About PMP & CAPM Certifications
Session 5 Everything You Should Know About PMP & CAPM Certifications
Seshne Govender
 
Top 30 Project Manager Interview Questions and Answers | PMP Certification Tr...
Top 30 Project Manager Interview Questions and Answers | PMP Certification Tr...Top 30 Project Manager Interview Questions and Answers | PMP Certification Tr...
Top 30 Project Manager Interview Questions and Answers | PMP Certification Tr...
Edureka!
 
Enterprise Project Management
Enterprise Project ManagementEnterprise Project Management
Enterprise Project Management
Peter1020
 
Session 6 Everything You Should Know About PMP & CAPM Certifications
Session 6 Everything You Should Know About PMP & CAPM CertificationsSession 6 Everything You Should Know About PMP & CAPM Certifications
Session 6 Everything You Should Know About PMP & CAPM Certifications
Seshne Govender
 
Project Management MethodologiesPPMP20009Week 10 LectureDr.docx
Project Management MethodologiesPPMP20009Week 10 LectureDr.docxProject Management MethodologiesPPMP20009Week 10 LectureDr.docx
Project Management MethodologiesPPMP20009Week 10 LectureDr.docx
briancrawford30935
 
KickOff Session
KickOff SessionKickOff Session
KickOff Session
SupportGCI
 
Practice of PM
Practice of PMPractice of PM
How to set up a value adding PMO
How to set up a value adding PMOHow to set up a value adding PMO
How to set up a value adding PMO
Association for Project Management
 
PgMP Panel Review (3/3)
PgMP Panel Review (3/3)PgMP Panel Review (3/3)
Business Analysts Value in Today's Work Environment
Business Analysts Value in Today's Work EnvironmentBusiness Analysts Value in Today's Work Environment
Business Analysts Value in Today's Work Environment
MAX Technical Training
 
(PMP)Project Management Professional Training
(PMP)Project Management Professional Training (PMP)Project Management Professional Training
(PMP)Project Management Professional Training
Lilaynaa
 
Project Management Framework
Project Management FrameworkProject Management Framework
Project Management Framework
Wadhwani Foundation
 
Linda Dulye IABC 2010 Global Conference Presentation
Linda Dulye IABC 2010 Global Conference PresentationLinda Dulye IABC 2010 Global Conference Presentation
Linda Dulye IABC 2010 Global Conference Presentation
Dulye
 

Similar to Session 4 Everything You Should Know About PMP & CAPM Certifications (20)

Project management in IBM EG - lecce_20140224
Project management in IBM EG - lecce_20140224Project management in IBM EG - lecce_20140224
Project management in IBM EG - lecce_20140224
 
Session - 6 Everything about PgMP & PfMP Certifications
Session - 6 Everything about PgMP & PfMP CertificationsSession - 6 Everything about PgMP & PfMP Certifications
Session - 6 Everything about PgMP & PfMP Certifications
 
Project Management Quick Connects
Project Management Quick ConnectsProject Management Quick Connects
Project Management Quick Connects
 
UCISA Project and Change Management Group Toolkits
UCISA Project and Change Management Group Toolkits  UCISA Project and Change Management Group Toolkits
UCISA Project and Change Management Group Toolkits
 
Session - 4 Everything about PgMP & PfMP Certifications
Session - 4 Everything about PgMP & PfMP CertificationsSession - 4 Everything about PgMP & PfMP Certifications
Session - 4 Everything about PgMP & PfMP Certifications
 
PMP Refresher Course
PMP Refresher CoursePMP Refresher Course
PMP Refresher Course
 
Session 5 Everything You Should Know About PMP & CAPM Certifications
Session 5 Everything You Should Know About PMP & CAPM CertificationsSession 5 Everything You Should Know About PMP & CAPM Certifications
Session 5 Everything You Should Know About PMP & CAPM Certifications
 
Top 30 Project Manager Interview Questions and Answers | PMP Certification Tr...
Top 30 Project Manager Interview Questions and Answers | PMP Certification Tr...Top 30 Project Manager Interview Questions and Answers | PMP Certification Tr...
Top 30 Project Manager Interview Questions and Answers | PMP Certification Tr...
 
Enterprise Project Management
Enterprise Project ManagementEnterprise Project Management
Enterprise Project Management
 
Session 6 Everything You Should Know About PMP & CAPM Certifications
Session 6 Everything You Should Know About PMP & CAPM CertificationsSession 6 Everything You Should Know About PMP & CAPM Certifications
Session 6 Everything You Should Know About PMP & CAPM Certifications
 
Project Management MethodologiesPPMP20009Week 10 LectureDr.docx
Project Management MethodologiesPPMP20009Week 10 LectureDr.docxProject Management MethodologiesPPMP20009Week 10 LectureDr.docx
Project Management MethodologiesPPMP20009Week 10 LectureDr.docx
 
KickOff Session
KickOff SessionKickOff Session
KickOff Session
 
Practice of PM
Practice of PMPractice of PM
Practice of PM
 
How to set up a value adding PMO
How to set up a value adding PMOHow to set up a value adding PMO
How to set up a value adding PMO
 
PgMP Panel Review (3/3)
PgMP Panel Review (3/3)PgMP Panel Review (3/3)
PgMP Panel Review (3/3)
 
Hima varsha
Hima varshaHima varsha
Hima varsha
 
Business Analysts Value in Today's Work Environment
Business Analysts Value in Today's Work EnvironmentBusiness Analysts Value in Today's Work Environment
Business Analysts Value in Today's Work Environment
 
(PMP)Project Management Professional Training
(PMP)Project Management Professional Training (PMP)Project Management Professional Training
(PMP)Project Management Professional Training
 
Project Management Framework
Project Management FrameworkProject Management Framework
Project Management Framework
 
Linda Dulye IABC 2010 Global Conference Presentation
Linda Dulye IABC 2010 Global Conference PresentationLinda Dulye IABC 2010 Global Conference Presentation
Linda Dulye IABC 2010 Global Conference Presentation
 

Recently uploaded

Home assignment II on Spectroscopy 2024 Answers.pdf
Home assignment II on Spectroscopy 2024 Answers.pdfHome assignment II on Spectroscopy 2024 Answers.pdf
Home assignment II on Spectroscopy 2024 Answers.pdf
Tamralipta Mahavidyalaya
 
Sectors of the Indian Economy - Class 10 Study Notes pdf
Sectors of the Indian Economy - Class 10 Study Notes pdfSectors of the Indian Economy - Class 10 Study Notes pdf
Sectors of the Indian Economy - Class 10 Study Notes pdf
Vivekanand Anglo Vedic Academy
 
Unit 8 - Information and Communication Technology (Paper I).pdf
Unit 8 - Information and Communication Technology (Paper I).pdfUnit 8 - Information and Communication Technology (Paper I).pdf
Unit 8 - Information and Communication Technology (Paper I).pdf
Thiyagu K
 
Polish students' mobility in the Czech Republic
Polish students' mobility in the Czech RepublicPolish students' mobility in the Czech Republic
Polish students' mobility in the Czech Republic
Anna Sz.
 
2024.06.01 Introducing a competency framework for languag learning materials ...
2024.06.01 Introducing a competency framework for languag learning materials ...2024.06.01 Introducing a competency framework for languag learning materials ...
2024.06.01 Introducing a competency framework for languag learning materials ...
Sandy Millin
 
Basic phrases for greeting and assisting costumers
Basic phrases for greeting and assisting costumersBasic phrases for greeting and assisting costumers
Basic phrases for greeting and assisting costumers
PedroFerreira53928
 
The approach at University of Liverpool.pptx
The approach at University of Liverpool.pptxThe approach at University of Liverpool.pptx
The approach at University of Liverpool.pptx
Jisc
 
The Challenger.pdf DNHS Official Publication
The Challenger.pdf DNHS Official PublicationThe Challenger.pdf DNHS Official Publication
The Challenger.pdf DNHS Official Publication
Delapenabediema
 
Unit 2- Research Aptitude (UGC NET Paper I).pdf
Unit 2- Research Aptitude (UGC NET Paper I).pdfUnit 2- Research Aptitude (UGC NET Paper I).pdf
Unit 2- Research Aptitude (UGC NET Paper I).pdf
Thiyagu K
 
Welcome to TechSoup New Member Orientation and Q&A (May 2024).pdf
Welcome to TechSoup   New Member Orientation and Q&A (May 2024).pdfWelcome to TechSoup   New Member Orientation and Q&A (May 2024).pdf
Welcome to TechSoup New Member Orientation and Q&A (May 2024).pdf
TechSoup
 
Language Across the Curriculm LAC B.Ed.
Language Across the  Curriculm LAC B.Ed.Language Across the  Curriculm LAC B.Ed.
Language Across the Curriculm LAC B.Ed.
Atul Kumar Singh
 
Mule 4.6 & Java 17 Upgrade | MuleSoft Mysore Meetup #46
Mule 4.6 & Java 17 Upgrade | MuleSoft Mysore Meetup #46Mule 4.6 & Java 17 Upgrade | MuleSoft Mysore Meetup #46
Mule 4.6 & Java 17 Upgrade | MuleSoft Mysore Meetup #46
MysoreMuleSoftMeetup
 
ESC Beyond Borders _From EU to You_ InfoPack general.pdf
ESC Beyond Borders _From EU to You_ InfoPack general.pdfESC Beyond Borders _From EU to You_ InfoPack general.pdf
ESC Beyond Borders _From EU to You_ InfoPack general.pdf
Fundacja Rozwoju Społeczeństwa Przedsiębiorczego
 
Supporting (UKRI) OA monographs at Salford.pptx
Supporting (UKRI) OA monographs at Salford.pptxSupporting (UKRI) OA monographs at Salford.pptx
Supporting (UKRI) OA monographs at Salford.pptx
Jisc
 
How to Split Bills in the Odoo 17 POS Module
How to Split Bills in the Odoo 17 POS ModuleHow to Split Bills in the Odoo 17 POS Module
How to Split Bills in the Odoo 17 POS Module
Celine George
 
aaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaa
aaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaa
aaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaa
siemaillard
 
TESDA TM1 REVIEWER FOR NATIONAL ASSESSMENT WRITTEN AND ORAL QUESTIONS WITH A...
TESDA TM1 REVIEWER  FOR NATIONAL ASSESSMENT WRITTEN AND ORAL QUESTIONS WITH A...TESDA TM1 REVIEWER  FOR NATIONAL ASSESSMENT WRITTEN AND ORAL QUESTIONS WITH A...
TESDA TM1 REVIEWER FOR NATIONAL ASSESSMENT WRITTEN AND ORAL QUESTIONS WITH A...
EugeneSaldivar
 
Phrasal Verbs.XXXXXXXXXXXXXXXXXXXXXXXXXX
Phrasal Verbs.XXXXXXXXXXXXXXXXXXXXXXXXXXPhrasal Verbs.XXXXXXXXXXXXXXXXXXXXXXXXXX
Phrasal Verbs.XXXXXXXXXXXXXXXXXXXXXXXXXX
MIRIAMSALINAS13
 
Model Attribute Check Company Auto Property
Model Attribute  Check Company Auto PropertyModel Attribute  Check Company Auto Property
Model Attribute Check Company Auto Property
Celine George
 
Students, digital devices and success - Andreas Schleicher - 27 May 2024..pptx
Students, digital devices and success - Andreas Schleicher - 27 May 2024..pptxStudents, digital devices and success - Andreas Schleicher - 27 May 2024..pptx
Students, digital devices and success - Andreas Schleicher - 27 May 2024..pptx
EduSkills OECD
 

Recently uploaded (20)

Home assignment II on Spectroscopy 2024 Answers.pdf
Home assignment II on Spectroscopy 2024 Answers.pdfHome assignment II on Spectroscopy 2024 Answers.pdf
Home assignment II on Spectroscopy 2024 Answers.pdf
 
Sectors of the Indian Economy - Class 10 Study Notes pdf
Sectors of the Indian Economy - Class 10 Study Notes pdfSectors of the Indian Economy - Class 10 Study Notes pdf
Sectors of the Indian Economy - Class 10 Study Notes pdf
 
Unit 8 - Information and Communication Technology (Paper I).pdf
Unit 8 - Information and Communication Technology (Paper I).pdfUnit 8 - Information and Communication Technology (Paper I).pdf
Unit 8 - Information and Communication Technology (Paper I).pdf
 
Polish students' mobility in the Czech Republic
Polish students' mobility in the Czech RepublicPolish students' mobility in the Czech Republic
Polish students' mobility in the Czech Republic
 
2024.06.01 Introducing a competency framework for languag learning materials ...
2024.06.01 Introducing a competency framework for languag learning materials ...2024.06.01 Introducing a competency framework for languag learning materials ...
2024.06.01 Introducing a competency framework for languag learning materials ...
 
Basic phrases for greeting and assisting costumers
Basic phrases for greeting and assisting costumersBasic phrases for greeting and assisting costumers
Basic phrases for greeting and assisting costumers
 
The approach at University of Liverpool.pptx
The approach at University of Liverpool.pptxThe approach at University of Liverpool.pptx
The approach at University of Liverpool.pptx
 
The Challenger.pdf DNHS Official Publication
The Challenger.pdf DNHS Official PublicationThe Challenger.pdf DNHS Official Publication
The Challenger.pdf DNHS Official Publication
 
Unit 2- Research Aptitude (UGC NET Paper I).pdf
Unit 2- Research Aptitude (UGC NET Paper I).pdfUnit 2- Research Aptitude (UGC NET Paper I).pdf
Unit 2- Research Aptitude (UGC NET Paper I).pdf
 
Welcome to TechSoup New Member Orientation and Q&A (May 2024).pdf
Welcome to TechSoup   New Member Orientation and Q&A (May 2024).pdfWelcome to TechSoup   New Member Orientation and Q&A (May 2024).pdf
Welcome to TechSoup New Member Orientation and Q&A (May 2024).pdf
 
Language Across the Curriculm LAC B.Ed.
Language Across the  Curriculm LAC B.Ed.Language Across the  Curriculm LAC B.Ed.
Language Across the Curriculm LAC B.Ed.
 
Mule 4.6 & Java 17 Upgrade | MuleSoft Mysore Meetup #46
Mule 4.6 & Java 17 Upgrade | MuleSoft Mysore Meetup #46Mule 4.6 & Java 17 Upgrade | MuleSoft Mysore Meetup #46
Mule 4.6 & Java 17 Upgrade | MuleSoft Mysore Meetup #46
 
ESC Beyond Borders _From EU to You_ InfoPack general.pdf
ESC Beyond Borders _From EU to You_ InfoPack general.pdfESC Beyond Borders _From EU to You_ InfoPack general.pdf
ESC Beyond Borders _From EU to You_ InfoPack general.pdf
 
Supporting (UKRI) OA monographs at Salford.pptx
Supporting (UKRI) OA monographs at Salford.pptxSupporting (UKRI) OA monographs at Salford.pptx
Supporting (UKRI) OA monographs at Salford.pptx
 
How to Split Bills in the Odoo 17 POS Module
How to Split Bills in the Odoo 17 POS ModuleHow to Split Bills in the Odoo 17 POS Module
How to Split Bills in the Odoo 17 POS Module
 
aaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaa
aaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaa
aaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaa
 
TESDA TM1 REVIEWER FOR NATIONAL ASSESSMENT WRITTEN AND ORAL QUESTIONS WITH A...
TESDA TM1 REVIEWER  FOR NATIONAL ASSESSMENT WRITTEN AND ORAL QUESTIONS WITH A...TESDA TM1 REVIEWER  FOR NATIONAL ASSESSMENT WRITTEN AND ORAL QUESTIONS WITH A...
TESDA TM1 REVIEWER FOR NATIONAL ASSESSMENT WRITTEN AND ORAL QUESTIONS WITH A...
 
Phrasal Verbs.XXXXXXXXXXXXXXXXXXXXXXXXXX
Phrasal Verbs.XXXXXXXXXXXXXXXXXXXXXXXXXXPhrasal Verbs.XXXXXXXXXXXXXXXXXXXXXXXXXX
Phrasal Verbs.XXXXXXXXXXXXXXXXXXXXXXXXXX
 
Model Attribute Check Company Auto Property
Model Attribute  Check Company Auto PropertyModel Attribute  Check Company Auto Property
Model Attribute Check Company Auto Property
 
Students, digital devices and success - Andreas Schleicher - 27 May 2024..pptx
Students, digital devices and success - Andreas Schleicher - 27 May 2024..pptxStudents, digital devices and success - Andreas Schleicher - 27 May 2024..pptx
Students, digital devices and success - Andreas Schleicher - 27 May 2024..pptx
 

Session 4 Everything You Should Know About PMP & CAPM Certifications

  • 1. Everything You Should Know About PMP® & CAPM® Certifications Seshne Govender vCare Project Management Session - 4 www.vcareprojectmanagement.com
  • 2. I am the Founder and Director of Fundamental Project Management, having over 15 years of experience as a Program and Project Manager managing numerous large successful deliveries with complex IT components in the Financial Services, Telecommunications, and Retail Sectors of South Africa. This journey has provided me with invaluable experience in the Project Management career path. Started my career as an Engineer, studied Chemical Engineering in South Africa. Within a short time, found my passion in projects in the Banking Industry. I have worked in diverse roles such as Process Engineer, Business Analyst, Project Manager, and finally, Program Manager: A career that provided joy to me for many years. A certified Program Management Professional (PgMP)® and Project Management Professional (PMP)®, which were invaluable in my Project Management Journey. I am passionate about training, coaching, and mentoring people along the Project Management career path. Successful Program Manager, Project Manager & Trainer Seshne Govender Project Management Expert
  • 3. PMP® & C APM® Certifications Waterfall, Agile, Hybrid, Benefits, Principles Session - 4
  • 4. Key Takeaways Upcoming Session Roadmap Session - 3 Recap Refresher Waterfall vs. Agile vs. Hybrid Benefits of Agile in Project Management Benefits of PMP® in International Market Four Principles of Project Management Training Emotional Stability - Balance Sample Exam Like Questions Frequently Asked Questions
  • 5. PMP® & C APM® Certifications Domains, Tasks, Understanding PMBOK® Session - 3 Recap
  • 6. The CAPM® examination is comprised of 150 multiple-choice questions Of the 150 questions, 15 are considered pretest questions Pretest questions do not affect the score and are used in examinations as an effective and legitimate way to test the validity of future examination questions CAPM® EXAMINATION QUESTIONS 135 No. of Scored Questions 15 No. of Pretest (Unscored) Questions 150 Total Examination Questions 3 hrs Allotted Examination Time
  • 7. The PMP® examination is comprised of 180 multiple-choice questions Of the 180 questions, 5 are considered pretest questions Pretest questions do not affect the score and are used in examinations as an effective and legitimate way to test the validity of future examination questions PMP® EXAMINATION QUESTIONS 175 No. of Scored Questions 5 No. of Pretest (Unscored) Questions 180 Total Examination Questions 230 Allotted Examination Time
  • 8. CAPM® NEW EXAM REFERENCE LIST PMBOK® Seventh Edition Business Analysis for Practitioners: A Practice Guide PMI Effective Project Management: Traditional, Agile, Extreme, Hybrid Robert K. Wysocki The Agile Practice Guide Project Management Answer Book, 2nd Edition Jeff Furman The PMI Guide to Business Analysis (December 2017) PMI
  • 9. STUDY MATERIALS & BOOKS TO BE REFERRED - PMP® Effective Project Management: Traditional, Agile, Extreme, Hybrid Information Technology Project Management – Seventh Edition Project Managers Portable Handbook – Third Edition Project Management: A Systems Approach to Planning, Scheduling, and Controlling Project Management: The Managerial Process The Project Management Tool Kit: 100 Tips and Techniques for Getting the Job Done Right The Agile Practice Guide Fundamentals of technology Project Management – Second Edition Essential Scrum: A Practical Guide to the most popular Agile Process Process Groups A Practical Guide PMBOK® Seventh Edition
  • 10. Demonstrate an understanding of the various project life cycles and processes. Demonstrate an understanding of project management planning. Demonstrate an understanding of project roles and responsibilities. Determine how to follow and execute planned strategies or frameworks (e.g., communication, risks, etc.). Demonstrate an understanding of common problem-solving tools and techniques. Explain when it is appropriate to use a predictive, plan-based approach. Demonstrate an understanding of a project management plan schedule. Determine how to document project controls of predictive, plan-based projects. Explain when it is appropriate to use an adaptive approach. Determine how to plan project iterations. Determine how to document project controls for an adaptive project. Explain the components of an adaptive plan. Determine how to prepare and execute task management steps. Project Management Fundamentals and Core Concepts (5 Tasks) (3 Tasks) (5 Tasks) 36% 17% 20% Predictive, Plan-Based Methodologies Agile Frameworks / Methodologies Demonstrate an understanding of business analysis (BA) roles and responsibilities. Determine how to conduct stakeholder communication. Determine how to gather requirements. Demonstrate an understanding of product roadmaps. Determine how project methodologies influence business analysis processes. Validate requirements through product delivery. 27% Business Analysis Frameworks (6 Tasks) CAPM® DOMAINS
  • 11. Build a team Define team ground rules Build a shared understanding of the project Negotiate project agreements Empower team members and stakeholders Ensure team members/stakeholders are adequately trained Engage and support virtual teams Collaborate with stakeholders Lead a team Address and get rid of team barriers, obstacles, and blockers Support team performance Manage conflict Mentoring appropriate stakeholders Enhance group success by utilizing emotional intelligence Plan and manage the scope Plan and manage budget and resources Plan and manage the schedule Plan and manage the quality of products and deliverables Integrate project planning activities Plan and manage procurement Determine appropriate project methodology / methods and practices Establish project governance structure Plan and manage project / phase closure Execute projects to deliver business value Manage communications Assess and manage risks Engage stakeholders Manage project artifacts Manage project changes Manage project issues Ensure knowledge transfer for project continuity Plan and manage project compliance. Evaluate and deliver project benefits and value Evaluate and address external business environment changes for impact on the scope Support organizational change People Domain Process Domain Business Environment Domain (14 Tasks) (17 Tasks) (4 Tasks) 42% 50% 8% PMP®DOMAINS
  • 12. Waterfall vs. Agile "This project has got so big, I'm not sure I'll be able to deliver it!" "It's so much better delivering this project in bite-sized sections"
  • 14. Benefits of PMP® in International Market YOU WILL ENHANCE YOUR CAREER OPPORTUNITIES YOU WILL BE RECOGNIZED AS AN EXPERIENCED PROFESSIONAL YOU WILL SPEAK THE RIGHT LANGUAGE YOU WILL LEARN NEW SKILLS YOU WILL (PROBABLY) EARN MORE MONEY YOU WILL DEMONSTRATE YOUR DEDICATION
  • 15. Four Principles of Project Management Training Customization Learning Style Experiential Learning Continuous Improvement
  • 16. Benefits of Agile in Project Management Agile is also a mindset that influences how we choose to think and act. As agilists, we choose to: Accelerate our value realization by embracing worthwhile changes. Delight customers by taking a customer-centric view to our work. Improve group capability by proactively collaborating instead of working in functional silos. Improve predictably by refining our understanding of what is needed through regularly showing our work and acting on feedback. Optimize flow by working on small items instead of big items. Big things are accomplished incrementally as a series of small things. Limiting the amount of work in progress makes it easier to identify inefficiency in a team's workflow. Improve continuously by frequently learning from our experience and evolving our practices based on what we learned. Source: PMI 1 2 3 4 5 6 7
  • 17. Emotional Stability - Balance Emotional Intelligence refers to our ability to recognize, control, and communicate emotions. EMOTIONAL INTELLIGENCE
  • 18. Benefits of Increasing EI for Project Managers Use emotions to improve and guide your thinking Be able to persuade and influence others Remove barriers to working with others Quickly transform change, problems and conflict into opportunities Assist your team in producing project success 01 02 04 03 05 Source: Casper, C. M. (2002). Using emotional intelligence to improve project performance. Paper presented at Project Management Institute Annual Seminars & Symposium, San Antonio, TX. Newtown Square, PA: Project Management Institute.
  • 19. Practice Makes Perfect - The Balancing Act Feel Think Act 1 2 3 Be aware of emotions. Understand what you feel and try to understand what others feel. Think why you feel the emotions. Analyze them carefully. Think about the way forward. Take control of emotions. Only act when you understand the situation clearly. Until then you are not in the best position to make decisions. Source: Fernando, M. (2003). Strong feelings. PM Network, 17(9), 64–66.
  • 20. Sample Exam Like Questions
  • 21. What prototyping technique shows the sequence or navigation through a series of images or illustrations? Storyboarding Wireframes Evolutionary Interactive a. b. c. d.
  • 22. What prototyping technique shows the sequence or navigation through a series of images or illustrations? Storyboarding Wireframes Evolutionary Interactive a. b. c. d.
  • 23. What is the purpose of a Requirements Traceability Matrix (RTM) in project management? To track the progress of project deliverables. To document and manage project risks. To link product requirements to the deliverables that satisfy them. To measure and assess project performance. a. b. c. d.
  • 24. What is the purpose of a Requirements Traceability Matrix (RTM) in project management? To track the progress of project deliverables. To document and manage project risks. To link product requirements to the deliverables that satisfy them. To measure and assess project performance. a. b. c. d.
  • 25. Which component of a business case assesses the financial viability of a project? Strategic alignment Economic feasibility study Assessment of risk exposure Expected key performance measures a. b. c. d.
  • 26. Which component of a business case assesses the financial viability of a project? Strategic alignment Economic feasibility study Assessment of risk exposure Expected key performance measures a. b. c. d.
  • 27. A project team lead has challenged the team to minimize defects and waste in project teamwork. As an initial step, the team proposes to assess the relevant quality standards and framework. How can the team do this? Review the requirements management plan. Check the ISO.org website. Investigate the project quality metrics. Interview the person who manages quality compliance. a. b. c. d.
  • 28. A project team lead has challenged the team to minimize defects and waste in project teamwork. As an initial step, the team proposes to assess the relevant quality standards and framework. How can the team do this? Review the requirements management plan. Check the ISO.org website. Investigate the project quality metrics. Interview the person who manages quality compliance. a. b. c. d.
  • 29. A project team member is having an extremely difficult and busy personal life. The team is NOT aware. They only see mistakes and missed deadlines. The team is in the middle of an iteration and this team member’s latest mistake has caused a major issue. How should the team lead respond in this situation? Coach the team member. Replace the team member. Discipline the team member. Consult the team member’s functional manager. a. b. c. d.
  • 30. A project team member is having an extremely difficult and busy personal life. The team is NOT aware. They only see mistakes and missed deadlines. The team is in the middle of an iteration and this team member’s latest mistake has caused a major issue. How should the team lead respond in this situation? Coach the team member. Replace the team member. Discipline the team member. Consult the team member’s functional manager. a. b. c. d.
  • 31. A project manager is working on a data center migration project and is developing the schedule management plan. The project was planned to last 40 days and the project sponsor wants it done in 35. Which action should the project manager take to amend this schedule for the new requirement? Crash activities that are NOT on the critical path. Increase duration of the critical path. Use leads. Use lags. a. b. c. d.
  • 32. A project manager is working on a data center migration project and is developing the schedule management plan. The project was planned to last 40 days and the project sponsor wants it done in 35. Which action should the project manager take to amend this schedule for the new requirement? Crash activities that are NOT on the critical path. Increase duration of the critical path. Use leads. Use lags. a. b. c. d.
  • 33.
  • 34. What is reserve analysis in PMP®?
  • 35. Reserve analysis is a technique the project manager and project team use to determine the total project budget for long-running projects. Total Project Budget = Cost Baseline + Management reserve Cost Baseline = Cost Estimate + Contingency Reserve
  • 36. Is PMP® certification worth it for an experienced project manager?
  • 37. Networking opportunities that can help you grow your career. Greater opportunities for managing larger scale projects. Earn 16% higher with a PMP certification. ®
  • 38. What are the benefits of PMP® certification?
  • 39. Improves career opportunities that can lead to career growth. Adds value to your CV, proving necessary experience and skills. Makes it easier to access opportunities in the market. Earn more than those without certification.
  • 40. What are the benefits of joining PMI local chapters after getting a PMP® certification?
  • 41. Connect with other project managers. Develop project management skills by staying up-to-date. Give back to your community by volunteering your skills, expertise, and time.
  • 42. What is your toughest topic for PMP®?
  • 43. PMP® Domains 42% 50% 8% People Process Business Environment Start with the Process Domain and ensure thorough understanding of the content before moving on to the People and Business Environment.
  • 44. How can I qualify for PMP® hours if all of my project management experience is from being self-employed?
  • 45. 1 3 2 4 PMI will accept professional working experience. Self-employed work must follow PMI definition of project. A project is temporary because it has a defined beginning & end in time & therefore defined scope & resources. Creating a unique product, service, or result is a temporary endeavour. A project is unique because it is not a routine operation but a specific set of operations designed to accomplish a singular goal.
  • 47. I have MSc in Project Management, is it mandatory to take 35 hrs training before PMP® exam?
  • 48. PMP® & C APM® Certifications How to clear CAPM® & PMP® Exam in First Attempt? Session - 5
  • 49. Frequently Asked Questions Upcoming Session Roadmap Session - 4 Recap Refresher CAPM® Knowledge Bytes - Key Terms & Definitions PMP® Knowledge Bytes - Key Terms & Definitions How to clear CAPM® & PMP® Exam in First Attempt? Tips & Secrets to Solve Exam Questions Time Management & Exam Preparation Planner Sample Exam Like Questions Session - 5 Agenda 18 October'23 th
  • 50. UPCOMING SESSIONS 09:30 AM - 10:30 AM (BST) 10:30 AM - 11:30 AM (CEST/SAST) 11:30 AM - 12:30 PM (EAT/AST) 12:30 PM - 01:30 PM (GST) 02:00 PM - 03:00 PM (IST) 03:30 PM - 04:30 PM (ICT/WIB) 04:30 PM - 05:30 PM (SGT/PHST) 07:30 PM - 08:30 PM (AEDT) Time: Session 5: 18 October'23 Session 6: 15 November'23 Session 7: 20 December'23 Session 8: 17 January'24 th th th th
  • 51. C vCare Project Management seshne@vcareprojectmanagement.com +27 722997173 Registered Address: 325 N. Saint Paul St, Suite 3100, Dallas, TX 75201, USA www.vcareprojectmanagement.com EIN: 35-2657414 Disclaimer • PMP, PMI, PMBOK, CAPM, PgMP, PfMP, PBA, RMP, ACP, SP, DA, DASM, DASSM, ATP and OPM3 are registered marks of the Project Management Institute, Inc.