CONSTRUCTION UPDATE – February 2015
Dr. Prem Reddy Health & Science
Perimeter wall framing
in SIM Labs
Metal Framing of west wall of
cadaver room / cat storage
Looking at wall framing for
cadaver room/cat storage
rooms from anatomy lab
Student restroom area,
overhead fire sprinkler
piping, perimeter wall
framing
Overhead ductwork in
beds/equipment room
Templates for medical
headwalls in Nursing
Fundamentals
Front entry, shot of
overhead work
Perimeter wall framing in
nursing fundamentals and
corridor 127. Fire
sprinkler piping and duct
overhead
Install of columns for
shade structures has
started in courtyard
South west side exterior.
Metal deck installed at
sloped roof
Wall Framing of
observation, control, and
SIM labs
Posts for shade structure,
outside deans office
Framing at faculty
offices area.
Looking in from
exterior door on west
side
Looking up at rotunda
framing
Rotunda steel being
welded.
CMU block being installed
for main covered walkway
to existing bldg
Looking down upon
covered walkway columns
in progress.
Mechanical unit set on
mezzanine level
South side flat metal
decking, sloped roof
metal decking
Penetrations in deck for
solatubes (skylights)
Air handler unit on
mezzanine (AHU 2)
Emergency eyewash
installed at chemistry lab
Wall framing at chemical
balance room, exit foyer
Overhead duct & walls
framed in nursing
fundamental
Installing overhead duct in
corridor 127.
Medical supplies and
utility rooms framed up.
Overhead duct installed
Deans office, and meeting
room to the right.
Bottom side of metal
deck, with cut outs for
solatube. Anatomy lab.
Concrete just poured at
north covered walkway
Emergency eyewash
installed at anatomy lab
SIM lab, control room,
observation room wall
framing. Overhead duct.
In wall plumbing at
patient toilet rm 150
Aluminum frames for
glass along corridor 127
Window in digital nurse
proctor room, looking into
digital nurse test lab
Piping ran to medical
headwall template,
nursing fundamentals lab
Overhead ducts in nursing
fundamentals
Looking at south covered
walkway, from roof.
North side roofing install
South roof
Mezzanine level.
Mechanical unit & piping
Looking from south, to north.
Rotunda and mechanical attic to the
right
Mock up of medical
headwall in nursing
fundamentals
Plumbing for washer &
dryer in utility room

Construction Update - February 2015 - VVCCD Dr. Prem Reddy Health Sciences Building Project