CONSTRUCTION UPDATE – January 2015
Dr. Prem Reddy Health & Science
Metal decking
installed at digital
nurses lab
Metal Decking being set
Metal roof deck installed
At science labs
Perimeter walls being
framed in medical
supplies & equipment
Boring for columns
for shade structure
Metal deck installed at
restrooms.
Perimeter wall framing
and structural steel set
in faculty office area.
Perimeter wall framing in
nursing fundamentals lab.
Also overhead piping
installed.
Metal decking, perimeter
wall framing in nursing
fundamentals and
corridor 127
Plywood covers holes
bored for shade
structure posts in new
courtyard area
Steel set in admin &
workroom areas.
Metal Decking installed at
faculty offices
Metal Decking at nursing
fundamentals lab.
Overhead piping installed.
Rear view of rotunda.
Looking towards faculty
offices from corridor 127
Overhead piping,
perimeter framing,
and metal decking
installed at beds &
equipment
Interior view of main
entrance
Perimeter framing at
workroom and admin areas
More perimeter framing at
anatomy labs.
Preparation for footings at
new trash enclosure
New doorway cut into
existing science bldg.
(Temporary Door)
Metal decking installed at
anatomy labs
SIM Lab area perimeter
wall framing installed.
Decking in process of
install.
Perimeter wall framing and
metal decking installed at
deans office / meeting
rooms
Holes bored for
covered walkway
pilasters.
Framing for walls along
corridor 127
Progress on metal decking
at nursing fundamentals
Top view of metal
decking installation
Another top view of metal decking.
Looking towards the second floor
mezzanine and rotunda
Stored duct waiting for
install is covered to
prevent dirt and debris
from accumulating inside.
Stored duct waiting for
install is covered to
prevent dirt and debris
from accumulating inside.
Duct being installed in
chemistry lab
Decking installed over
corridor 127
Installing in wall conduits
for power and piping for
roof drains.
Electrical room 132
Rebar laid out on metal
decking in mezzanine for
concrete topping and
equipment pad.
Looking down into
courtyard area
Opening for duct from
HVAC unit in mezzanine.
Signed steel beam set into
place
Temporary jacks set in
place in preparation of
concrete being poured on
deck above
Concrete being poured on
mezzanine deck
Footing poured for trash
enclosure
Interior walls being
framed for faculty offices
Framing of interior walls
in the admin, workroom,
deans office areas
Concrete poured out for
revolving door at main
entry
Mezzanine concrete and
equipment pad- North
side
Mezzanine concrete and
equipment pad- South
side

January 2015 Construction Update - Victor Valley Community College District - Dr. Prem Reddy Health Sciences Building