Doc No: DPD074.GN
Revision: March-09
© 2009
This document has copyright, which is owned by Sonneville International Corporation (SIC) and may not be reproduced, in whole, in part, or in any form whatsoever without
prior written authority from SIC. This document has been submitted on the understanding that it will not be used in any way against the interest of SIC.
LOW VIBRATION TRACK (LVT)
Track renewal
SONNEVILLE INTERNATIONAL CORPORATION
8109 Tis Well Drive, Suite 513
Alexandria, VA 22306, USA
Tel. +1 703 619 1530
Fax +1 703 619 1534
E-mail mail@sonneville.com
www.sonneville.com
Doc No: DPD074.GN
Revision: March-09
Low Vibration Track (LVT) – Track renewal Page 2 of 7
A) Special cavity LVT
Substitution of old wooden ties or blocks embedded in
concrete with special cavity LVT supports
Track geometry re-adjustment
Doc No: DPD074.GN
Revision: March-09
Low Vibration Track (LVT) – Track renewal Page 3 of 7
Grout placement
Special cavity LVT supports, first installed on Amtrak in early 2000, were primarily designed to replace existing ties or blocks
encased in concrete. Their relatively smaller size allows them to be retrofitted in the cavities left by the removed ties or blocks,
adjusted and sealed in place with flowable cementitious grout. The trapezoidal shape of the concrete blocks, resilient pads and
rubber boots equalizes the pressure per area on the field and gauge sides under combined vertical and lateral loads and further
prevents long term migration towards the gauge side when the LVT supports are installed adjacent to an existing central trough.
Doc No: DPD074.GN
Revision: March-09
Low Vibration Track (LVT) – Track renewal Page 4 of 7
B) Renewal of ballasted track under traffic
The following procedure was successfully implemented in 1974 in Denmark to renew 6 km (3.8 miles) of ballasted track with the
earlier non-ballasted track system comprising tie bars.
The work was restricted to 4 ½ hours per night with traffic operating normally at all other times, except for a temporary 35 km/h
(22 mph) speed restriction.
The same procedure is applicable to LVT with the only addition of insulated temporary gauge bars between the rails.
Advanced ballast removal
An advance crew excavated the ballast cribs up to the ends of
the existing ties.
Doc No: DPD074.GN
Revision: March-09
Low Vibration Track (LVT) – Track renewal Page 5 of 7
Old track removal
The first trackwork crew removed three 15-metre panels
[45 metres (150 ft) of track] per night, excavated the remaining
ballast and placed roller compacted concrete on the
foundation while restoring the drainage system.
Doc No: DPD074.GN
Revision: March-09
Low Vibration Track (LVT) – Track renewal Page 6 of 7
Track restoration
New track panels were then installed directly on the roller compacted concrete, the rails connected and ramps shimmed at both
ends, the track temporarily resting slightly below its final level.
Traffic immediately resumed.
Doc No: DPD074.GN
Revision: March-09
Low Vibration Track (LVT) – Track renewal Page 7 of 7
Final adjustment and concreting
The second trackwork crew adjusted the track, verified its geometry and secured it in place with shims inserted between the rail
base and the now fully cured roller compacted concrete before placing and finishing the track concrete.
The loads generated by the traffic that resumed immediately thereafter were transferred directly from the rails to the roller
compacted concrete through the shims without any measurable relative movement between the rubber boots and the green
track concrete below.
The upper portion of the shims was later removed and recycled forwards.

Renovación de Vías

  • 1.
    Doc No: DPD074.GN Revision:March-09 © 2009 This document has copyright, which is owned by Sonneville International Corporation (SIC) and may not be reproduced, in whole, in part, or in any form whatsoever without prior written authority from SIC. This document has been submitted on the understanding that it will not be used in any way against the interest of SIC. LOW VIBRATION TRACK (LVT) Track renewal SONNEVILLE INTERNATIONAL CORPORATION 8109 Tis Well Drive, Suite 513 Alexandria, VA 22306, USA Tel. +1 703 619 1530 Fax +1 703 619 1534 E-mail mail@sonneville.com www.sonneville.com
  • 2.
    Doc No: DPD074.GN Revision:March-09 Low Vibration Track (LVT) – Track renewal Page 2 of 7 A) Special cavity LVT Substitution of old wooden ties or blocks embedded in concrete with special cavity LVT supports Track geometry re-adjustment
  • 3.
    Doc No: DPD074.GN Revision:March-09 Low Vibration Track (LVT) – Track renewal Page 3 of 7 Grout placement Special cavity LVT supports, first installed on Amtrak in early 2000, were primarily designed to replace existing ties or blocks encased in concrete. Their relatively smaller size allows them to be retrofitted in the cavities left by the removed ties or blocks, adjusted and sealed in place with flowable cementitious grout. The trapezoidal shape of the concrete blocks, resilient pads and rubber boots equalizes the pressure per area on the field and gauge sides under combined vertical and lateral loads and further prevents long term migration towards the gauge side when the LVT supports are installed adjacent to an existing central trough.
  • 4.
    Doc No: DPD074.GN Revision:March-09 Low Vibration Track (LVT) – Track renewal Page 4 of 7 B) Renewal of ballasted track under traffic The following procedure was successfully implemented in 1974 in Denmark to renew 6 km (3.8 miles) of ballasted track with the earlier non-ballasted track system comprising tie bars. The work was restricted to 4 ½ hours per night with traffic operating normally at all other times, except for a temporary 35 km/h (22 mph) speed restriction. The same procedure is applicable to LVT with the only addition of insulated temporary gauge bars between the rails. Advanced ballast removal An advance crew excavated the ballast cribs up to the ends of the existing ties.
  • 5.
    Doc No: DPD074.GN Revision:March-09 Low Vibration Track (LVT) – Track renewal Page 5 of 7 Old track removal The first trackwork crew removed three 15-metre panels [45 metres (150 ft) of track] per night, excavated the remaining ballast and placed roller compacted concrete on the foundation while restoring the drainage system.
  • 6.
    Doc No: DPD074.GN Revision:March-09 Low Vibration Track (LVT) – Track renewal Page 6 of 7 Track restoration New track panels were then installed directly on the roller compacted concrete, the rails connected and ramps shimmed at both ends, the track temporarily resting slightly below its final level. Traffic immediately resumed.
  • 7.
    Doc No: DPD074.GN Revision:March-09 Low Vibration Track (LVT) – Track renewal Page 7 of 7 Final adjustment and concreting The second trackwork crew adjusted the track, verified its geometry and secured it in place with shims inserted between the rail base and the now fully cured roller compacted concrete before placing and finishing the track concrete. The loads generated by the traffic that resumed immediately thereafter were transferred directly from the rails to the roller compacted concrete through the shims without any measurable relative movement between the rubber boots and the green track concrete below. The upper portion of the shims was later removed and recycled forwards.