Reliability Assessment of Power
Distribution System
Haramaya University, HiT, SECE
2/16/2024
M.Sc. Thesis Defense Presentation
By: Abdulaziz Adem
Program: Electrical Power Engineering
Major Advisor: Dr. Ramesh Kumar
Co-Advisor: Mr. Wehib Abubeker
Outline
2/16/2024
2
 Introduction
 Literature Review
 Materials and Methods
 Results and Discussions
 Conclusion and Recommendation
 References
1. Introduction
2/16/2024
3
 The purpose of power systems is to provide an
economic and reliable network for electricity.
 The role of electric utility is to provide reliable electric
power to the customers.
 However, reliability problems in power systems usually
occurs at DS.
 Historical and predictive assessment two methods of RA.
 SAIFI,SAIDI,,CAIDI, ASAI, ASUI, EENS are commonly used
standard reliability metrics.
Statement of the problem
2/16/2024
4
 In Ethiopia, delivering reliable electric power is the role of
EEU, however, power interruptions are becoming a critical
problems.
 Particularly, HU DS usually experiences power interruption.
 The university is using the diesel generators as a backup
supply.
 However, due to high price of fuel, the operating cost of
diesel generator is more.
 Considering the problem an assessment of HU DS reliability
was conducted.
Objectives
2/16/2024
5
General objective
 To assess the reliability of HU DS and propose improvement
technique.
Specific Objectives
 To identify the major causes of power interruptions
 To model and simulate existing and under construction HU
DS
 To compare existing and under construction DS
 To propose improvement technique
 To perform cost analysis
2. Literature Review
6
Power System Reliability
 Reliability
 The probability a system/component performing its
function adequately for a given period time.
 Adequacy
 Sufficient facilities within the power system to satisfy
customer demand.
 Security
 The ability of the system to respond to disturbances
arising within the system.
 RA :- Generation, composite generation&transmission,
Distribution system ,substation
Component Model
7
• Failure rate (λ)
• 𝑀𝑇𝑇𝑅 =
total repair time
total no.of int.s
(2.1)
• µ =
8760
𝑀𝑇𝑇𝑅
(2.2)
• MTTF =
1
λ
(2.3)
• MTBF= MTTF +
MTTR
8760
(2.4)
• U =
MTTR
MTTF×8760
(2.5)
Fig.2.12 :Two-state space
diagram
Fig.2.13 : Mean time
Two-state model
Series & Parallel Systems
 For n components in series
 λs = i
n
λi (2.6)
 Us = i
n
λi ri (2.7)
 rs =
Us
λs
(2.8)
 For 3 components in parallel
 λp = λ1 λ2λ3 r1r2 + r2r3 +
2/16/2024
8
Reliability Indices
 SAIFI = i λiNi
i Nt
f/yr (2.12)
 SAIDI= i riNi
i Nt
hr/yr (2.13)
 CAIDI =
SAIDI
SAIFI
hr/int (2.14)
 CAIFI = i λiNi
Cn
f/yr (2.15)
 ASAI =
Nt∗8760)− i riNi
Nt∗8760)
(2.16)
 ASUI= 1−𝐴𝑆𝐴𝐼
(2.17)
 EENS = i La i Ui (2.18)
 AENS = i La i)Ui
i Nt
(2.20)
9
Reliability Improvement Methods
2/16/2024
10
 Electrical method
 Protective and switching devices
 Network reconfiguration
 Distributed generation
 Non-electrical method
 Vegetation management
 Installation of lightning arrester
 Animal protection guards
3. Materials and Methods
2/16/2024
11
Haramaya substation
Fig.3.1: One-line diagram of Haramaya distribution
substation
Calculation of Reliability Indices
2/16/2024
12
 The load point reliability indices have been calculated
using equation (2.6) to (2.8).
 The overall system reliability indices have been
calculated using equations (2.11) to (2.20).
Table 3.11: Calculated system reliability indices of HU DS
SAIFI SAIDI CAIDI ASAI ASUI EENS AENS
198.15 275.39 1.4 0.968
6
0.031
4
2167.4
3
103.21
Comparison Reliability Indices
2/16/2024
13
Table 3.12: Comparison of HU DS reliability indices with
benchmarks
Countries SAIFI
(int./cust.yr)
SAIDI
(hrs./cust.yr)
CAIDI
(hrs./int)
ASAI
(%)
USA 1.5 4 2.05 99.91
Denmark 0.5 0.4 1.67 99.981
France 1 1.03 0.97 99.97
Spain 2.2 1.73 1.9 99.968
Germany 0.5 0.38 0.83 99.999
UK 0.8 1.5 1.67 99.964
Canada 3.4 6.9 2.03 99.95
Netherland 0.3 0.55 1.25 99.97
Italy 2.2 0.97 1.77 99.999
Australia 0.9 1.2 1.87 99.97
Ethiopia 20 25 2.23 99.71
HU 198.15 275.39 1.4 96.86
Power Interruption Cost
2/16/2024
14
 The outage costs have seen by the utility and the
customers.
 Utility side
 Loss of revenue
 Customer side
 Cost of alternative supply
Sizing of Solar DG for HU
2/16/2024
15
 PV Syst 7.2 software has been used to size the system.
 Data required:-
 Load data
 Meteorological data
4. Results and Discussions
2/16/2024
16
 The simulation was performed for the following cases.
Reliability
indices
Base
case
Case 1 Case
2
Case
3
Case 4 Case 5
SAIFI 196.38 196.50 1.18 176.8
0
168.53 80.57
SAIDI 277.78 191.98 20.77 123.5
7
118.64 78.44
CAIDI 1.41 0.98 17.60 0.69 0.70 0.97
ASAI (%) 96.83 97.81 99.76 98.59 98.65 99.1
ASUI (%) 3.17 2.19 0.24 1.41 1.35 0.9
EENS 2186.5
7
1509.2
0
290.1
9
981.4
2
958.81 671.33
AENS 104.12 71.87 13.82 46.73 45.66 31.97
Cost Analysis
2/16/2024
17
 The reliability of a system can be increased by increasing
investment cost.
 Payback Period =
Investment Cost
Annual Revenue Saved
(4.1)
…Cost Analysis
18
Table 4.8: Summary of cost analysis for all cases
 Case (3)and (4) are profitable for both utility and HU.
 Case 5 and 2 are profitable only for HU.
Study
Utility side HU side
Revenue
saved (ETB/yr)
Payback
period
(yr)
Money
saved
(ETB/yr)
Payback
period
(yr)
Case 3 1,414,909.93 1.11 3,297,306 0.48
Case 4 1,141,883.66 2.05 3,423,349.
3
0.7
Case 5 1,784,847.3 34.38 4,328,113.
6
14.17
Case 2 2,239,549.9 77.7 5,762,746.
4
30.2
5. Summary and Conclusion
19
Conclusion:
 HU DS is out of service due to unplanned and planned
interruptions.
 There are serious reliability problems in HU DS.
 The reliability problem in existing system has a negative
impact on economy of utility and customers.
 Fuses, reclosers, solar DG, and UG ring network can all
improve DS reliability.
 UG ring HU DS has improved system reliability indices.
 HU can save 5,762,746.38ETB/yr by constructing an UG
ring DS and the payback period will be 30.2 yr.
Recommendations/Future Work
2/16/2024
20
 The next researcher will work on power quality issues
raised when DG is connected to grid.
 Case 3&4 are recommended for the utility to implement
(in terms cost).
 UG ring DS is recommended for HU to get improved
reliability performance.
 Preventive maintenance of existing distribution line are
required on a regular basis.
 I recommend Haramaya substation and EEU to enhance
data record experiences.
References
2/16/2024
21
Abrha H. and Teshome G. 2020. Reliability Assessment of Electrical Distribution Network
using Analytical Method: A Case Study of Maychew City Distribution System.
International Journal of Engineering Research & Technology (IJERT), 9(08): 977-985.
 Akhikpemelo A., Eyibo N. R and Adeyi A.,2016. Reliability Analysis of Power Distribution
Network. Wilolud Journals of Continental J. Engineering Sciences, 11 (2): 53 - 63
 Amache Jara, 2016. Reliability Assessment of Radial Distribution System with Distributed
Generation: A Case Study of Cottebe Substations. Master’s Thesis, Addis Ababa University,
Addis Ababa, Ethiopia.
 Balogun M. O., Ahmed M. O., Ajani A. A., and Olaoye H. 2019. Reliability Assessment of
33KV Feeder: A Case Study of Transmission Company of Nigeria, Ganmo Work Centre.
World Journal of Innovative Research, 6(1): 77-83.
 Chemdi M. 2020. Reliability Analysis of 15kv Distribution System Network. (Case Study:
Addis Alem Substation Network, Master’s Thesis, Addis Ababa University, Addis Ababa,
Ethiopia.
 Degarege Anteneh. 2020. Reliability Assessment of Distribution System Using Analytical
Method: A Case Study of Debre Berhan Distribution Network. Journal of Informatics
Electrical and Electronics Engineering, 1(1): 1-9.
…References
2/16/2024
22
 Eyasu B, 2017. Studies on Power Distribution System Reliability Assessment and improvement,
Master’s thesis, Addis Ababa Science and Technology University, Addis Ababa, Ethiopia.
 G. Sengi and E. Ntagwirumugara. 2021. Improving reliability of the power distribution system
in Goma (DRC) using solar distributed generation, Journal of Energy in Southern Africa 32(4):
84–101.
 Khaidir A, Rama O, and Ramadoni S, 2017. Reliability Analysis of Power Distribution System, Journal
of Electrical Technology UMY (JET-UMY), 1(2).
 M. Wadi, M. Baysal, A. Shobole, and M.R. Tur, 2020. Historical and Monte Carlo Simulation-Based
Reliability Assessment of Power Distribution Systems, Sigma Journal of Engineering and Natural
Sciences, 38(3): 1527-1540
 S. L. Braide and E. O. Kenneth, 2018. Improved Reliability Analysis of Electricity Power Supply to
Port Harcourt Distribution Network. International Journal of Engineering Science Invention, 7(7): 2319
– 6734
 Vishalini Divaka, B. K. Keshavan and M. S. Raviprakasha. 2016. A Survey on Methods of Evaluation
of Reliability of Distribution Systems with Distributed Generation. International Journal of Engineering
Research & Technology, 5(08): 220-226.
 Z. Hoosain Khan,2015, Improving the reliability performance of medium voltage networks, Master’s
dissertation, University of Cape Town, Cape Town
Thank You!
2/16/2024
23
Haramaya University, HiT, SECE

reliability assessment of power distribution system.pptx

  • 1.
    Reliability Assessment ofPower Distribution System Haramaya University, HiT, SECE 2/16/2024 M.Sc. Thesis Defense Presentation By: Abdulaziz Adem Program: Electrical Power Engineering Major Advisor: Dr. Ramesh Kumar Co-Advisor: Mr. Wehib Abubeker
  • 2.
    Outline 2/16/2024 2  Introduction  LiteratureReview  Materials and Methods  Results and Discussions  Conclusion and Recommendation  References
  • 3.
    1. Introduction 2/16/2024 3  Thepurpose of power systems is to provide an economic and reliable network for electricity.  The role of electric utility is to provide reliable electric power to the customers.  However, reliability problems in power systems usually occurs at DS.  Historical and predictive assessment two methods of RA.  SAIFI,SAIDI,,CAIDI, ASAI, ASUI, EENS are commonly used standard reliability metrics.
  • 4.
    Statement of theproblem 2/16/2024 4  In Ethiopia, delivering reliable electric power is the role of EEU, however, power interruptions are becoming a critical problems.  Particularly, HU DS usually experiences power interruption.  The university is using the diesel generators as a backup supply.  However, due to high price of fuel, the operating cost of diesel generator is more.  Considering the problem an assessment of HU DS reliability was conducted.
  • 5.
    Objectives 2/16/2024 5 General objective  Toassess the reliability of HU DS and propose improvement technique. Specific Objectives  To identify the major causes of power interruptions  To model and simulate existing and under construction HU DS  To compare existing and under construction DS  To propose improvement technique  To perform cost analysis
  • 6.
    2. Literature Review 6 PowerSystem Reliability  Reliability  The probability a system/component performing its function adequately for a given period time.  Adequacy  Sufficient facilities within the power system to satisfy customer demand.  Security  The ability of the system to respond to disturbances arising within the system.  RA :- Generation, composite generation&transmission, Distribution system ,substation
  • 7.
    Component Model 7 • Failurerate (λ) • 𝑀𝑇𝑇𝑅 = total repair time total no.of int.s (2.1) • µ = 8760 𝑀𝑇𝑇𝑅 (2.2) • MTTF = 1 λ (2.3) • MTBF= MTTF + MTTR 8760 (2.4) • U = MTTR MTTF×8760 (2.5) Fig.2.12 :Two-state space diagram Fig.2.13 : Mean time Two-state model
  • 8.
    Series & ParallelSystems  For n components in series  λs = i n λi (2.6)  Us = i n λi ri (2.7)  rs = Us λs (2.8)  For 3 components in parallel  λp = λ1 λ2λ3 r1r2 + r2r3 + 2/16/2024 8
  • 9.
    Reliability Indices  SAIFI= i λiNi i Nt f/yr (2.12)  SAIDI= i riNi i Nt hr/yr (2.13)  CAIDI = SAIDI SAIFI hr/int (2.14)  CAIFI = i λiNi Cn f/yr (2.15)  ASAI = Nt∗8760)− i riNi Nt∗8760) (2.16)  ASUI= 1−𝐴𝑆𝐴𝐼 (2.17)  EENS = i La i Ui (2.18)  AENS = i La i)Ui i Nt (2.20) 9
  • 10.
    Reliability Improvement Methods 2/16/2024 10 Electrical method  Protective and switching devices  Network reconfiguration  Distributed generation  Non-electrical method  Vegetation management  Installation of lightning arrester  Animal protection guards
  • 11.
    3. Materials andMethods 2/16/2024 11 Haramaya substation Fig.3.1: One-line diagram of Haramaya distribution substation
  • 12.
    Calculation of ReliabilityIndices 2/16/2024 12  The load point reliability indices have been calculated using equation (2.6) to (2.8).  The overall system reliability indices have been calculated using equations (2.11) to (2.20). Table 3.11: Calculated system reliability indices of HU DS SAIFI SAIDI CAIDI ASAI ASUI EENS AENS 198.15 275.39 1.4 0.968 6 0.031 4 2167.4 3 103.21
  • 13.
    Comparison Reliability Indices 2/16/2024 13 Table3.12: Comparison of HU DS reliability indices with benchmarks Countries SAIFI (int./cust.yr) SAIDI (hrs./cust.yr) CAIDI (hrs./int) ASAI (%) USA 1.5 4 2.05 99.91 Denmark 0.5 0.4 1.67 99.981 France 1 1.03 0.97 99.97 Spain 2.2 1.73 1.9 99.968 Germany 0.5 0.38 0.83 99.999 UK 0.8 1.5 1.67 99.964 Canada 3.4 6.9 2.03 99.95 Netherland 0.3 0.55 1.25 99.97 Italy 2.2 0.97 1.77 99.999 Australia 0.9 1.2 1.87 99.97 Ethiopia 20 25 2.23 99.71 HU 198.15 275.39 1.4 96.86
  • 14.
    Power Interruption Cost 2/16/2024 14 The outage costs have seen by the utility and the customers.  Utility side  Loss of revenue  Customer side  Cost of alternative supply
  • 15.
    Sizing of SolarDG for HU 2/16/2024 15  PV Syst 7.2 software has been used to size the system.  Data required:-  Load data  Meteorological data
  • 16.
    4. Results andDiscussions 2/16/2024 16  The simulation was performed for the following cases. Reliability indices Base case Case 1 Case 2 Case 3 Case 4 Case 5 SAIFI 196.38 196.50 1.18 176.8 0 168.53 80.57 SAIDI 277.78 191.98 20.77 123.5 7 118.64 78.44 CAIDI 1.41 0.98 17.60 0.69 0.70 0.97 ASAI (%) 96.83 97.81 99.76 98.59 98.65 99.1 ASUI (%) 3.17 2.19 0.24 1.41 1.35 0.9 EENS 2186.5 7 1509.2 0 290.1 9 981.4 2 958.81 671.33 AENS 104.12 71.87 13.82 46.73 45.66 31.97
  • 17.
    Cost Analysis 2/16/2024 17  Thereliability of a system can be increased by increasing investment cost.  Payback Period = Investment Cost Annual Revenue Saved (4.1)
  • 18.
    …Cost Analysis 18 Table 4.8:Summary of cost analysis for all cases  Case (3)and (4) are profitable for both utility and HU.  Case 5 and 2 are profitable only for HU. Study Utility side HU side Revenue saved (ETB/yr) Payback period (yr) Money saved (ETB/yr) Payback period (yr) Case 3 1,414,909.93 1.11 3,297,306 0.48 Case 4 1,141,883.66 2.05 3,423,349. 3 0.7 Case 5 1,784,847.3 34.38 4,328,113. 6 14.17 Case 2 2,239,549.9 77.7 5,762,746. 4 30.2
  • 19.
    5. Summary andConclusion 19 Conclusion:  HU DS is out of service due to unplanned and planned interruptions.  There are serious reliability problems in HU DS.  The reliability problem in existing system has a negative impact on economy of utility and customers.  Fuses, reclosers, solar DG, and UG ring network can all improve DS reliability.  UG ring HU DS has improved system reliability indices.  HU can save 5,762,746.38ETB/yr by constructing an UG ring DS and the payback period will be 30.2 yr.
  • 20.
    Recommendations/Future Work 2/16/2024 20  Thenext researcher will work on power quality issues raised when DG is connected to grid.  Case 3&4 are recommended for the utility to implement (in terms cost).  UG ring DS is recommended for HU to get improved reliability performance.  Preventive maintenance of existing distribution line are required on a regular basis.  I recommend Haramaya substation and EEU to enhance data record experiences.
  • 21.
    References 2/16/2024 21 Abrha H. andTeshome G. 2020. Reliability Assessment of Electrical Distribution Network using Analytical Method: A Case Study of Maychew City Distribution System. International Journal of Engineering Research & Technology (IJERT), 9(08): 977-985.  Akhikpemelo A., Eyibo N. R and Adeyi A.,2016. Reliability Analysis of Power Distribution Network. Wilolud Journals of Continental J. Engineering Sciences, 11 (2): 53 - 63  Amache Jara, 2016. Reliability Assessment of Radial Distribution System with Distributed Generation: A Case Study of Cottebe Substations. Master’s Thesis, Addis Ababa University, Addis Ababa, Ethiopia.  Balogun M. O., Ahmed M. O., Ajani A. A., and Olaoye H. 2019. Reliability Assessment of 33KV Feeder: A Case Study of Transmission Company of Nigeria, Ganmo Work Centre. World Journal of Innovative Research, 6(1): 77-83.  Chemdi M. 2020. Reliability Analysis of 15kv Distribution System Network. (Case Study: Addis Alem Substation Network, Master’s Thesis, Addis Ababa University, Addis Ababa, Ethiopia.  Degarege Anteneh. 2020. Reliability Assessment of Distribution System Using Analytical Method: A Case Study of Debre Berhan Distribution Network. Journal of Informatics Electrical and Electronics Engineering, 1(1): 1-9.
  • 22.
    …References 2/16/2024 22  Eyasu B,2017. Studies on Power Distribution System Reliability Assessment and improvement, Master’s thesis, Addis Ababa Science and Technology University, Addis Ababa, Ethiopia.  G. Sengi and E. Ntagwirumugara. 2021. Improving reliability of the power distribution system in Goma (DRC) using solar distributed generation, Journal of Energy in Southern Africa 32(4): 84–101.  Khaidir A, Rama O, and Ramadoni S, 2017. Reliability Analysis of Power Distribution System, Journal of Electrical Technology UMY (JET-UMY), 1(2).  M. Wadi, M. Baysal, A. Shobole, and M.R. Tur, 2020. Historical and Monte Carlo Simulation-Based Reliability Assessment of Power Distribution Systems, Sigma Journal of Engineering and Natural Sciences, 38(3): 1527-1540  S. L. Braide and E. O. Kenneth, 2018. Improved Reliability Analysis of Electricity Power Supply to Port Harcourt Distribution Network. International Journal of Engineering Science Invention, 7(7): 2319 – 6734  Vishalini Divaka, B. K. Keshavan and M. S. Raviprakasha. 2016. A Survey on Methods of Evaluation of Reliability of Distribution Systems with Distributed Generation. International Journal of Engineering Research & Technology, 5(08): 220-226.  Z. Hoosain Khan,2015, Improving the reliability performance of medium voltage networks, Master’s dissertation, University of Cape Town, Cape Town
  • 23.