Task Planned
Start Date
Planned
End Date
Actual Start
Date
Actual End
Date
Comments
Risk Assessment 19/10/15 19/10/15
Contingency 20/10/15 22/10/15
Permissions 23/10/15 23/10/15
Layout Plans 24/10/15 27/10/15
Stories Plan 28/10/15 30/10/15
Copyright 02/11/15 02/11/15
Shooting Script 03/11/15 05/11/15
Create Drafts 09/11/15 15/11/15
Editingof Images
and Texts
16/11/15 23/11/15
Produce Final
Pages
24/11/15 05/12/15

regional NewspaperProduction schedule

  • 1.
    Task Planned Start Date Planned EndDate Actual Start Date Actual End Date Comments Risk Assessment 19/10/15 19/10/15 Contingency 20/10/15 22/10/15 Permissions 23/10/15 23/10/15 Layout Plans 24/10/15 27/10/15 Stories Plan 28/10/15 30/10/15 Copyright 02/11/15 02/11/15 Shooting Script 03/11/15 05/11/15 Create Drafts 09/11/15 15/11/15 Editingof Images and Texts 16/11/15 23/11/15 Produce Final Pages 24/11/15 05/12/15