IBS1 - Group H
Nadine Bleienheuft | Horacio Fernandez | Luca Fornasier |Verena Riedhart | Lakshay Suri | Pascal Rehder
Project Management
Professor Sharada Kumaran Ravindran

18.06.2015
Project Boomerang - Project Plan
SCOPE DEFINITION
2IBS1 Group H
• Boomerang Application selected to
process end user requirements
18.06.15
BOOMERANG
• Components impacted
1. Validator
2. Order Request Module
3. Order Status Module
• Boomerang Objective
• enhance AT&T’s webpage
• provide additional functionality
• quality online service to clients
BOOMERANG ASSUMPTIONS
3IBS1 Group H 18.06.15
Existing application
1
2
Requirement identified during the
Requirements Phase need to be
implemented in line with Scope
Definition
CONSTRAINTS
4IBS1 Group H 18.06.15
1
2
3
Total budget
4
5
Resource availability
Project deadline
Client decision on final
result
Software compatibility 

w/ client infrastructure
EXCLUSIONS
5IBS1 Group H 18.06.15
No additional
requirements are
added after the
Requirement Phase
No training to the
end user about
usability of the
enhanced software
1 2
KEY DELIVERABLES
6IBS1 Group H 18.06.15
Enhance AT&T system to incorporate…
1
2
3
Order Acceptance
Order Processing
Order Validator
KEY STAKEHOLDERS
7IBS1 Group H 18.06.157
AT&T customers who…
• live in California region
• have right to access
application
• have an active user account
AT&T clients
AT&T vendors
MILESTONES
8IBS1 Group H 18.06.15
No. Task Milestone Date
1 Project Start Date 01/06/2015
2 Project Plan Document Check in 01/06/2015
3 Requirements Document Check in 24/07/2015
4 Development Package Check in 26/09/2015
5 Test Package Check in 15/10/2015
6 Production Deployment (Go-Live) 26/10/2015
WORK BREAKDOWN STRUCTURE
9IBS1 Group H 18.06.15
a
b
c
a
b
c
a
b
c
a
b
c
d
e
a
PROJECT RESOURCES
10IBS1 Group H 18.06.15
Requirement 

Gathering

Phase
Development 

Phase
System
Testing 

Phase
Production

Deployment
Resources

(People)
Pascal

Lakshay
Nadine

Horacio

Luca
Verena
Pascal
Lakshay
Pascal
Lakshay
Prof. S. Ravindran
Group Lead
Resources

(Technology)
Servers: Webspace Server
Batch Server
Database: SQL Server 2000
Development: RAD
Operating System: MS Windows
Client

Verification
Code

Deployment
Mark

Nadine

Pascal
Maintenance

Phase
SCHEDULE
11IBS1 Group H 18.06.15
BUDGET
12IBS1 Group H 18.06.15
ACCEPTANCE CRITERIA
13IBS1 Group H 18.06.15
PERFORMANCE

MEASUREMENT
A. receive the orders of specific status
which the current functionality
doesn’t allow

B. process the order of specific status
and move it to the next processing
status unless there is some other
issue
System should be able to…
RISK IDENTIFICATION
14IBS1 Group H 18.06.15
• Occurring from interfacing applications
APPLICATION

DOWNTIME OUTAGES
ERRORS
• Functional Errors

• System Errors
RISK STRATEGY
15IBS1 Group H 18.06.15
APPLICATION REBOOT
Disaster

Recovery 

Strategy
APPROVERS
16IBS1 Group H 18.06.15
Emp Role Group
Mark Thomson Project Manager AT&T, Boomerang
Sharada Ravindran Group Lead IE Business School
Nadine Bleienheuft Software Developer IE Business School
Horacio Fernández del
Castillo
Software Developer IE Business School
Luca Fornasier Software Developer IE Business School
Verena Riedhart
Software 

Tester
IE Business School
Pascal Rehder
Software 

Tester
IE Business School
Lakshay Suri
Software 

Tester
IE Business School
Q&A
17IBS1 Group H 18.06.15
PROJECT BOOMERANG

More Related Content

What's hot

PlacemakAR Application - Software Engineering Discussion
PlacemakAR Application - Software Engineering DiscussionPlacemakAR Application - Software Engineering Discussion
PlacemakAR Application - Software Engineering DiscussionKanishk Karanawat
 
Maximize Your Enterprise DevOps Efforts and Outcomes with Value Streams
Maximize Your Enterprise DevOps Efforts and Outcomes with Value StreamsMaximize Your Enterprise DevOps Efforts and Outcomes with Value Streams
Maximize Your Enterprise DevOps Efforts and Outcomes with Value StreamsDevOps.com
 
Continuous Delivery Pipelines: Metrics, Myths, and Milestones
Continuous Delivery Pipelines:  Metrics, Myths, and MilestonesContinuous Delivery Pipelines:  Metrics, Myths, and Milestones
Continuous Delivery Pipelines: Metrics, Myths, and MilestonesDevOps.com
 
PMBOK® Guide Processes Flow – 6th Edition
PMBOK® Guide Processes Flow – 6th EditionPMBOK® Guide Processes Flow – 6th Edition
PMBOK® Guide Processes Flow – 6th EditionRicardo Viana Vargas
 
Principal Financial Group: Stretching CRM Capabilities with Pivotal 6.0
Principal Financial Group: Stretching CRM Capabilities with Pivotal 6.0Principal Financial Group: Stretching CRM Capabilities with Pivotal 6.0
Principal Financial Group: Stretching CRM Capabilities with Pivotal 6.0Aptean
 
#ATAGTR2020 Presentation - GraphQL for CICD integration
#ATAGTR2020 Presentation - GraphQL for CICD integration#ATAGTR2020 Presentation - GraphQL for CICD integration
#ATAGTR2020 Presentation - GraphQL for CICD integrationAgile Testing Alliance
 
Nhif erp progress report
Nhif erp progress reportNhif erp progress report
Nhif erp progress reportfarougnoor
 
Introducing CollabNet TeamForge® 8.0
Introducing CollabNet TeamForge® 8.0Introducing CollabNet TeamForge® 8.0
Introducing CollabNet TeamForge® 8.0CollabNet
 
Agile Gurugram 2016 | Conference | Scaling Agile to Enterprises : Experience ...
Agile Gurugram 2016 | Conference | Scaling Agile to Enterprises : Experience ...Agile Gurugram 2016 | Conference | Scaling Agile to Enterprises : Experience ...
Agile Gurugram 2016 | Conference | Scaling Agile to Enterprises : Experience ...AgileNetwork
 
The evolution of project controls at csx transportation wp - Oracle Primavera...
The evolution of project controls at csx transportation wp - Oracle Primavera...The evolution of project controls at csx transportation wp - Oracle Primavera...
The evolution of project controls at csx transportation wp - Oracle Primavera...p6academy
 
Project Management in Agile Organizations - Stage Gate and Agile
Project Management in Agile Organizations - Stage Gate and AgileProject Management in Agile Organizations - Stage Gate and Agile
Project Management in Agile Organizations - Stage Gate and AgileKnowit_TM
 
CollabNet TeamForge 8.1 Webinar
CollabNet TeamForge 8.1 WebinarCollabNet TeamForge 8.1 Webinar
CollabNet TeamForge 8.1 WebinarCollabNet
 
How to Measure Agility Project Success in Business Terms
How to Measure Agility Project Success in Business TermsHow to Measure Agility Project Success in Business Terms
How to Measure Agility Project Success in Business TermsEthan Ram
 
Agile Enterprise Adoption And Enterprise Agile Enterprise Adoption And Enterp...
Agile Enterprise Adoption And Enterprise Agile Enterprise Adoption And Enterp...Agile Enterprise Adoption And Enterprise Agile Enterprise Adoption And Enterp...
Agile Enterprise Adoption And Enterprise Agile Enterprise Adoption And Enterp...Rally Software
 
K dev-slides(7)land dev seminar+demo -chuan[2]-200511
K dev-slides(7)land dev seminar+demo -chuan[2]-200511K dev-slides(7)land dev seminar+demo -chuan[2]-200511
K dev-slides(7)land dev seminar+demo -chuan[2]-200511REDceo.net
 
Creating High Performance teams by using a DevOps culture (FUG presentation)
Creating High Performance teams by using a DevOps culture (FUG presentation)Creating High Performance teams by using a DevOps culture (FUG presentation)
Creating High Performance teams by using a DevOps culture (FUG presentation)Serena Software
 
How to Uplevel Your Pipeline with Release Orchestration and Deployment Automa...
How to Uplevel Your Pipeline with Release Orchestration and Deployment Automa...How to Uplevel Your Pipeline with Release Orchestration and Deployment Automa...
How to Uplevel Your Pipeline with Release Orchestration and Deployment Automa...DevOps.com
 
Hybrid and Multi-Cloud Strategies for Kubernetes with GitOps
Hybrid and Multi-Cloud Strategies for Kubernetes with GitOpsHybrid and Multi-Cloud Strategies for Kubernetes with GitOps
Hybrid and Multi-Cloud Strategies for Kubernetes with GitOpsSonja Schweigert
 
Wealth Technology Strategy
Wealth Technology StrategyWealth Technology Strategy
Wealth Technology StrategyAlison Rooney
 
Top Down and Bottom Up Planning at Breakthru Beverage Group
Top Down and Bottom Up Planning at Breakthru Beverage GroupTop Down and Bottom Up Planning at Breakthru Beverage Group
Top Down and Bottom Up Planning at Breakthru Beverage GroupKyle Goodfriend
 

What's hot (20)

PlacemakAR Application - Software Engineering Discussion
PlacemakAR Application - Software Engineering DiscussionPlacemakAR Application - Software Engineering Discussion
PlacemakAR Application - Software Engineering Discussion
 
Maximize Your Enterprise DevOps Efforts and Outcomes with Value Streams
Maximize Your Enterprise DevOps Efforts and Outcomes with Value StreamsMaximize Your Enterprise DevOps Efforts and Outcomes with Value Streams
Maximize Your Enterprise DevOps Efforts and Outcomes with Value Streams
 
Continuous Delivery Pipelines: Metrics, Myths, and Milestones
Continuous Delivery Pipelines:  Metrics, Myths, and MilestonesContinuous Delivery Pipelines:  Metrics, Myths, and Milestones
Continuous Delivery Pipelines: Metrics, Myths, and Milestones
 
PMBOK® Guide Processes Flow – 6th Edition
PMBOK® Guide Processes Flow – 6th EditionPMBOK® Guide Processes Flow – 6th Edition
PMBOK® Guide Processes Flow – 6th Edition
 
Principal Financial Group: Stretching CRM Capabilities with Pivotal 6.0
Principal Financial Group: Stretching CRM Capabilities with Pivotal 6.0Principal Financial Group: Stretching CRM Capabilities with Pivotal 6.0
Principal Financial Group: Stretching CRM Capabilities with Pivotal 6.0
 
#ATAGTR2020 Presentation - GraphQL for CICD integration
#ATAGTR2020 Presentation - GraphQL for CICD integration#ATAGTR2020 Presentation - GraphQL for CICD integration
#ATAGTR2020 Presentation - GraphQL for CICD integration
 
Nhif erp progress report
Nhif erp progress reportNhif erp progress report
Nhif erp progress report
 
Introducing CollabNet TeamForge® 8.0
Introducing CollabNet TeamForge® 8.0Introducing CollabNet TeamForge® 8.0
Introducing CollabNet TeamForge® 8.0
 
Agile Gurugram 2016 | Conference | Scaling Agile to Enterprises : Experience ...
Agile Gurugram 2016 | Conference | Scaling Agile to Enterprises : Experience ...Agile Gurugram 2016 | Conference | Scaling Agile to Enterprises : Experience ...
Agile Gurugram 2016 | Conference | Scaling Agile to Enterprises : Experience ...
 
The evolution of project controls at csx transportation wp - Oracle Primavera...
The evolution of project controls at csx transportation wp - Oracle Primavera...The evolution of project controls at csx transportation wp - Oracle Primavera...
The evolution of project controls at csx transportation wp - Oracle Primavera...
 
Project Management in Agile Organizations - Stage Gate and Agile
Project Management in Agile Organizations - Stage Gate and AgileProject Management in Agile Organizations - Stage Gate and Agile
Project Management in Agile Organizations - Stage Gate and Agile
 
CollabNet TeamForge 8.1 Webinar
CollabNet TeamForge 8.1 WebinarCollabNet TeamForge 8.1 Webinar
CollabNet TeamForge 8.1 Webinar
 
How to Measure Agility Project Success in Business Terms
How to Measure Agility Project Success in Business TermsHow to Measure Agility Project Success in Business Terms
How to Measure Agility Project Success in Business Terms
 
Agile Enterprise Adoption And Enterprise Agile Enterprise Adoption And Enterp...
Agile Enterprise Adoption And Enterprise Agile Enterprise Adoption And Enterp...Agile Enterprise Adoption And Enterprise Agile Enterprise Adoption And Enterp...
Agile Enterprise Adoption And Enterprise Agile Enterprise Adoption And Enterp...
 
K dev-slides(7)land dev seminar+demo -chuan[2]-200511
K dev-slides(7)land dev seminar+demo -chuan[2]-200511K dev-slides(7)land dev seminar+demo -chuan[2]-200511
K dev-slides(7)land dev seminar+demo -chuan[2]-200511
 
Creating High Performance teams by using a DevOps culture (FUG presentation)
Creating High Performance teams by using a DevOps culture (FUG presentation)Creating High Performance teams by using a DevOps culture (FUG presentation)
Creating High Performance teams by using a DevOps culture (FUG presentation)
 
How to Uplevel Your Pipeline with Release Orchestration and Deployment Automa...
How to Uplevel Your Pipeline with Release Orchestration and Deployment Automa...How to Uplevel Your Pipeline with Release Orchestration and Deployment Automa...
How to Uplevel Your Pipeline with Release Orchestration and Deployment Automa...
 
Hybrid and Multi-Cloud Strategies for Kubernetes with GitOps
Hybrid and Multi-Cloud Strategies for Kubernetes with GitOpsHybrid and Multi-Cloud Strategies for Kubernetes with GitOps
Hybrid and Multi-Cloud Strategies for Kubernetes with GitOps
 
Wealth Technology Strategy
Wealth Technology StrategyWealth Technology Strategy
Wealth Technology Strategy
 
Top Down and Bottom Up Planning at Breakthru Beverage Group
Top Down and Bottom Up Planning at Breakthru Beverage GroupTop Down and Bottom Up Planning at Breakthru Beverage Group
Top Down and Bottom Up Planning at Breakthru Beverage Group
 

Similar to Project Management - AT&T vs Project Boomerang

Using Q-Pulse to Manage Maintenance & Errors
Using Q-Pulse to Manage Maintenance & ErrorsUsing Q-Pulse to Manage Maintenance & Errors
Using Q-Pulse to Manage Maintenance & ErrorsFionaMacGael
 
asme_product_development_cycle.ppt
asme_product_development_cycle.pptasme_product_development_cycle.ppt
asme_product_development_cycle.pptbibhu518
 
DevOps for Big Data - Data 360 2014 Conference
DevOps for Big Data - Data 360 2014 ConferenceDevOps for Big Data - Data 360 2014 Conference
DevOps for Big Data - Data 360 2014 ConferenceGrid Dynamics
 
Projektværktøjsdagen 2014 rapid implementation of ppm tool
Projektværktøjsdagen 2014   rapid implementation of ppm toolProjektværktøjsdagen 2014   rapid implementation of ppm tool
Projektværktøjsdagen 2014 rapid implementation of ppm toolThomas Røygaard
 
CipherCloud Microservice Meetup - Managing Services in a Lean Startup
CipherCloud Microservice Meetup - Managing Services in a Lean StartupCipherCloud Microservice Meetup - Managing Services in a Lean Startup
CipherCloud Microservice Meetup - Managing Services in a Lean StartupShobana Radhakrishnan
 
Monthly Status Report - old
Monthly Status Report - oldMonthly Status Report - old
Monthly Status Report - oldMargaret D.
 
Training on ASAP Methodology_11.10.2020.ppt
Training on ASAP Methodology_11.10.2020.pptTraining on ASAP Methodology_11.10.2020.ppt
Training on ASAP Methodology_11.10.2020.pptAshwaniKumar207236
 
Road to agile: federal government case study
Road to agile: federal government case studyRoad to agile: federal government case study
Road to agile: federal government case studyDavid Marsh
 
Project Management Sample
Project Management SampleProject Management Sample
Project Management SampleRavi Nakulan
 
Fundamentals of SDLC for Business Analysts
Fundamentals of SDLC for Business AnalystsFundamentals of SDLC for Business Analysts
Fundamentals of SDLC for Business AnalystsVeneet-BA
 
Software Development Life Cycle – SDLC
Software Development Life Cycle – SDLCSoftware Development Life Cycle – SDLC
Software Development Life Cycle – SDLCSwatiS-BA
 
SDLC Training for Business Analysts
SDLC Training for Business AnalystsSDLC Training for Business Analysts
SDLC Training for Business AnalystsSwatiS-BA
 
PPM. Gør det rigtige, rigtigt, - men hurtigt - Thomas Røygaard, Maersk Oil
PPM. Gør det rigtige, rigtigt, - men hurtigt - Thomas Røygaard, Maersk Oil PPM. Gør det rigtige, rigtigt, - men hurtigt - Thomas Røygaard, Maersk Oil
PPM. Gør det rigtige, rigtigt, - men hurtigt - Thomas Røygaard, Maersk Oil Mediehuset Ingeniøren Live
 
HeartofAgile_Presentation_v3
HeartofAgile_Presentation_v3HeartofAgile_Presentation_v3
HeartofAgile_Presentation_v3Armand Spoto
 
Warehouse Operations Redefining methodology
Warehouse Operations Redefining methodologyWarehouse Operations Redefining methodology
Warehouse Operations Redefining methodologyAkhilRanjanDubey
 
How Oceanwide Accelerated its DevOps Adoption Journey with AppDynamics - AppS...
How Oceanwide Accelerated its DevOps Adoption Journey with AppDynamics - AppS...How Oceanwide Accelerated its DevOps Adoption Journey with AppDynamics - AppS...
How Oceanwide Accelerated its DevOps Adoption Journey with AppDynamics - AppS...AppDynamics
 
Training on ASAP Methodology.ppt
Training on ASAP Methodology.pptTraining on ASAP Methodology.ppt
Training on ASAP Methodology.pptAshwaniKumar207236
 
PPAP Awareness training.pptx
PPAP Awareness training.pptxPPAP Awareness training.pptx
PPAP Awareness training.pptxNeeraj Pandey
 

Similar to Project Management - AT&T vs Project Boomerang (20)

Using Q-Pulse to Manage Maintenance & Errors
Using Q-Pulse to Manage Maintenance & ErrorsUsing Q-Pulse to Manage Maintenance & Errors
Using Q-Pulse to Manage Maintenance & Errors
 
asme_product_development_cycle.ppt
asme_product_development_cycle.pptasme_product_development_cycle.ppt
asme_product_development_cycle.ppt
 
DevOps for Big Data - Data 360 2014 Conference
DevOps for Big Data - Data 360 2014 ConferenceDevOps for Big Data - Data 360 2014 Conference
DevOps for Big Data - Data 360 2014 Conference
 
Projektværktøjsdagen 2014 rapid implementation of ppm tool
Projektværktøjsdagen 2014   rapid implementation of ppm toolProjektværktøjsdagen 2014   rapid implementation of ppm tool
Projektværktøjsdagen 2014 rapid implementation of ppm tool
 
CipherCloud Microservice Meetup - Managing Services in a Lean Startup
CipherCloud Microservice Meetup - Managing Services in a Lean StartupCipherCloud Microservice Meetup - Managing Services in a Lean Startup
CipherCloud Microservice Meetup - Managing Services in a Lean Startup
 
Monthly Status Report - old
Monthly Status Report - oldMonthly Status Report - old
Monthly Status Report - old
 
Training on ASAP Methodology_11.10.2020.ppt
Training on ASAP Methodology_11.10.2020.pptTraining on ASAP Methodology_11.10.2020.ppt
Training on ASAP Methodology_11.10.2020.ppt
 
Scope management
Scope managementScope management
Scope management
 
Road to agile: federal government case study
Road to agile: federal government case studyRoad to agile: federal government case study
Road to agile: federal government case study
 
Project Management Sample
Project Management SampleProject Management Sample
Project Management Sample
 
Fundamentals of SDLC for Business Analysts
Fundamentals of SDLC for Business AnalystsFundamentals of SDLC for Business Analysts
Fundamentals of SDLC for Business Analysts
 
Software Development Life Cycle – SDLC
Software Development Life Cycle – SDLCSoftware Development Life Cycle – SDLC
Software Development Life Cycle – SDLC
 
SDLC Training for Business Analysts
SDLC Training for Business AnalystsSDLC Training for Business Analysts
SDLC Training for Business Analysts
 
PPM. Gør det rigtige, rigtigt, - men hurtigt - Thomas Røygaard, Maersk Oil
PPM. Gør det rigtige, rigtigt, - men hurtigt - Thomas Røygaard, Maersk Oil PPM. Gør det rigtige, rigtigt, - men hurtigt - Thomas Røygaard, Maersk Oil
PPM. Gør det rigtige, rigtigt, - men hurtigt - Thomas Røygaard, Maersk Oil
 
HeartofAgile_Presentation_v3
HeartofAgile_Presentation_v3HeartofAgile_Presentation_v3
HeartofAgile_Presentation_v3
 
Agile & Wakanda
Agile & WakandaAgile & Wakanda
Agile & Wakanda
 
Warehouse Operations Redefining methodology
Warehouse Operations Redefining methodologyWarehouse Operations Redefining methodology
Warehouse Operations Redefining methodology
 
How Oceanwide Accelerated its DevOps Adoption Journey with AppDynamics - AppS...
How Oceanwide Accelerated its DevOps Adoption Journey with AppDynamics - AppS...How Oceanwide Accelerated its DevOps Adoption Journey with AppDynamics - AppS...
How Oceanwide Accelerated its DevOps Adoption Journey with AppDynamics - AppS...
 
Training on ASAP Methodology.ppt
Training on ASAP Methodology.pptTraining on ASAP Methodology.ppt
Training on ASAP Methodology.ppt
 
PPAP Awareness training.pptx
PPAP Awareness training.pptxPPAP Awareness training.pptx
PPAP Awareness training.pptx
 

Recently uploaded

NewBase 17 May 2024 Energy News issue - 1725 by Khaled Al Awadi_compresse...
NewBase   17 May  2024  Energy News issue - 1725 by Khaled Al Awadi_compresse...NewBase   17 May  2024  Energy News issue - 1725 by Khaled Al Awadi_compresse...
NewBase 17 May 2024 Energy News issue - 1725 by Khaled Al Awadi_compresse...Khaled Al Awadi
 
The Art of Decision-Making: Navigating Complexity and Uncertainty
The Art of Decision-Making: Navigating Complexity and UncertaintyThe Art of Decision-Making: Navigating Complexity and Uncertainty
The Art of Decision-Making: Navigating Complexity and Uncertaintycapivisgroup
 
Should Law Firms Outsource their Bookkeeping
Should Law Firms Outsource their BookkeepingShould Law Firms Outsource their Bookkeeping
Should Law Firms Outsource their BookkeepingYourLegal Accounting
 
What are the differences between an international company, a global company, ...
What are the differences between an international company, a global company, ...What are the differences between an international company, a global company, ...
What are the differences between an international company, a global company, ...AbhishekSharma823325
 
10 Easiest Ways To Buy Verified TransferWise Accounts
10 Easiest Ways To Buy Verified TransferWise Accounts10 Easiest Ways To Buy Verified TransferWise Accounts
10 Easiest Ways To Buy Verified TransferWise Accountshttps://localsmmshop.com/
 
Elevate Your Online Presence with SEO Services
Elevate Your Online Presence with SEO ServicesElevate Your Online Presence with SEO Services
Elevate Your Online Presence with SEO ServicesHaseebBashir5
 
Pitch Deck Teardown: Goodcarbon's $5.5m Seed deck
Pitch Deck Teardown: Goodcarbon's $5.5m Seed deckPitch Deck Teardown: Goodcarbon's $5.5m Seed deck
Pitch Deck Teardown: Goodcarbon's $5.5m Seed deckHajeJanKamps
 
Unlocking Growth The Power of Outsourcing for CPA Firms
Unlocking Growth The Power of Outsourcing for CPA FirmsUnlocking Growth The Power of Outsourcing for CPA Firms
Unlocking Growth The Power of Outsourcing for CPA FirmsYourLegal Accounting
 
Innomantra Viewpoint - Building Moonshots : May-Jun 2024.pdf
Innomantra Viewpoint - Building Moonshots : May-Jun 2024.pdfInnomantra Viewpoint - Building Moonshots : May-Jun 2024.pdf
Innomantra Viewpoint - Building Moonshots : May-Jun 2024.pdfInnomantra
 
00971508021841 حبوب الإجهاض في دبي | أبوظبي | الشارقة | السطوة |❇ ❈ ((![© ر
00971508021841 حبوب الإجهاض في دبي | أبوظبي | الشارقة | السطوة |❇ ❈ ((![©  ر00971508021841 حبوب الإجهاض في دبي | أبوظبي | الشارقة | السطوة |❇ ❈ ((![©  ر
00971508021841 حبوب الإجهاض في دبي | أبوظبي | الشارقة | السطوة |❇ ❈ ((![© رnafizanafzal
 
Thompson_Taylor_MBBS_PB1_2024-03 (1)- Project & Portfolio 2.pptx
Thompson_Taylor_MBBS_PB1_2024-03 (1)- Project & Portfolio 2.pptxThompson_Taylor_MBBS_PB1_2024-03 (1)- Project & Portfolio 2.pptx
Thompson_Taylor_MBBS_PB1_2024-03 (1)- Project & Portfolio 2.pptxtmthompson1
 
Jual Obat Aborsi Di Sibolga wa 0851/7541/5434 Cytotec Misoprostol 200mcg Pfizer
Jual Obat Aborsi Di Sibolga wa 0851/7541/5434 Cytotec Misoprostol 200mcg PfizerJual Obat Aborsi Di Sibolga wa 0851/7541/5434 Cytotec Misoprostol 200mcg Pfizer
Jual Obat Aborsi Di Sibolga wa 0851/7541/5434 Cytotec Misoprostol 200mcg PfizerPusat Herbal Resmi BPOM
 
Shots fired Budget Presentation.pdf12312
Shots fired Budget Presentation.pdf12312Shots fired Budget Presentation.pdf12312
Shots fired Budget Presentation.pdf12312LR1709MUSIC
 
Goal Presentation_NEW EMPLOYEE_NETAPS FOUNDATION.pptx
Goal Presentation_NEW EMPLOYEE_NETAPS FOUNDATION.pptxGoal Presentation_NEW EMPLOYEE_NETAPS FOUNDATION.pptx
Goal Presentation_NEW EMPLOYEE_NETAPS FOUNDATION.pptxNetapsFoundationAdmi
 
如何办理(SUT毕业证书)斯威本科技大学毕业证成绩单本科硕士学位证留信学历认证
如何办理(SUT毕业证书)斯威本科技大学毕业证成绩单本科硕士学位证留信学历认证如何办理(SUT毕业证书)斯威本科技大学毕业证成绩单本科硕士学位证留信学历认证
如何办理(SUT毕业证书)斯威本科技大学毕业证成绩单本科硕士学位证留信学历认证ogawka
 
Pay after result spell caster (,$+27834335081)@ bring back lost lover same da...
Pay after result spell caster (,$+27834335081)@ bring back lost lover same da...Pay after result spell caster (,$+27834335081)@ bring back lost lover same da...
Pay after result spell caster (,$+27834335081)@ bring back lost lover same da...BabaJohn3
 

Recently uploaded (20)

NewBase 17 May 2024 Energy News issue - 1725 by Khaled Al Awadi_compresse...
NewBase   17 May  2024  Energy News issue - 1725 by Khaled Al Awadi_compresse...NewBase   17 May  2024  Energy News issue - 1725 by Khaled Al Awadi_compresse...
NewBase 17 May 2024 Energy News issue - 1725 by Khaled Al Awadi_compresse...
 
The Art of Decision-Making: Navigating Complexity and Uncertainty
The Art of Decision-Making: Navigating Complexity and UncertaintyThe Art of Decision-Making: Navigating Complexity and Uncertainty
The Art of Decision-Making: Navigating Complexity and Uncertainty
 
Obat Aborsi Malang 0851\7696\3835 Jual Obat Cytotec Di Malang
Obat Aborsi Malang 0851\7696\3835 Jual Obat Cytotec Di MalangObat Aborsi Malang 0851\7696\3835 Jual Obat Cytotec Di Malang
Obat Aborsi Malang 0851\7696\3835 Jual Obat Cytotec Di Malang
 
Should Law Firms Outsource their Bookkeeping
Should Law Firms Outsource their BookkeepingShould Law Firms Outsource their Bookkeeping
Should Law Firms Outsource their Bookkeeping
 
What are the differences between an international company, a global company, ...
What are the differences between an international company, a global company, ...What are the differences between an international company, a global company, ...
What are the differences between an international company, a global company, ...
 
10 Easiest Ways To Buy Verified TransferWise Accounts
10 Easiest Ways To Buy Verified TransferWise Accounts10 Easiest Ways To Buy Verified TransferWise Accounts
10 Easiest Ways To Buy Verified TransferWise Accounts
 
Elevate Your Online Presence with SEO Services
Elevate Your Online Presence with SEO ServicesElevate Your Online Presence with SEO Services
Elevate Your Online Presence with SEO Services
 
Obat Aborsi Surabaya 0851\7696\3835 Jual Obat Cytotec Di Surabaya
Obat Aborsi Surabaya 0851\7696\3835 Jual Obat Cytotec Di SurabayaObat Aborsi Surabaya 0851\7696\3835 Jual Obat Cytotec Di Surabaya
Obat Aborsi Surabaya 0851\7696\3835 Jual Obat Cytotec Di Surabaya
 
Pitch Deck Teardown: Goodcarbon's $5.5m Seed deck
Pitch Deck Teardown: Goodcarbon's $5.5m Seed deckPitch Deck Teardown: Goodcarbon's $5.5m Seed deck
Pitch Deck Teardown: Goodcarbon's $5.5m Seed deck
 
Unlocking Growth The Power of Outsourcing for CPA Firms
Unlocking Growth The Power of Outsourcing for CPA FirmsUnlocking Growth The Power of Outsourcing for CPA Firms
Unlocking Growth The Power of Outsourcing for CPA Firms
 
Innomantra Viewpoint - Building Moonshots : May-Jun 2024.pdf
Innomantra Viewpoint - Building Moonshots : May-Jun 2024.pdfInnomantra Viewpoint - Building Moonshots : May-Jun 2024.pdf
Innomantra Viewpoint - Building Moonshots : May-Jun 2024.pdf
 
00971508021841 حبوب الإجهاض في دبي | أبوظبي | الشارقة | السطوة |❇ ❈ ((![© ر
00971508021841 حبوب الإجهاض في دبي | أبوظبي | الشارقة | السطوة |❇ ❈ ((![©  ر00971508021841 حبوب الإجهاض في دبي | أبوظبي | الشارقة | السطوة |❇ ❈ ((![©  ر
00971508021841 حبوب الإجهاض في دبي | أبوظبي | الشارقة | السطوة |❇ ❈ ((![© ر
 
Thompson_Taylor_MBBS_PB1_2024-03 (1)- Project & Portfolio 2.pptx
Thompson_Taylor_MBBS_PB1_2024-03 (1)- Project & Portfolio 2.pptxThompson_Taylor_MBBS_PB1_2024-03 (1)- Project & Portfolio 2.pptx
Thompson_Taylor_MBBS_PB1_2024-03 (1)- Project & Portfolio 2.pptx
 
Jual Obat Aborsi Di Sibolga wa 0851/7541/5434 Cytotec Misoprostol 200mcg Pfizer
Jual Obat Aborsi Di Sibolga wa 0851/7541/5434 Cytotec Misoprostol 200mcg PfizerJual Obat Aborsi Di Sibolga wa 0851/7541/5434 Cytotec Misoprostol 200mcg Pfizer
Jual Obat Aborsi Di Sibolga wa 0851/7541/5434 Cytotec Misoprostol 200mcg Pfizer
 
Obat Aborsi Depok 0851\7696\3835 Jual Obat Cytotec Di Depok
Obat Aborsi Depok 0851\7696\3835 Jual Obat Cytotec Di DepokObat Aborsi Depok 0851\7696\3835 Jual Obat Cytotec Di Depok
Obat Aborsi Depok 0851\7696\3835 Jual Obat Cytotec Di Depok
 
Shots fired Budget Presentation.pdf12312
Shots fired Budget Presentation.pdf12312Shots fired Budget Presentation.pdf12312
Shots fired Budget Presentation.pdf12312
 
Goal Presentation_NEW EMPLOYEE_NETAPS FOUNDATION.pptx
Goal Presentation_NEW EMPLOYEE_NETAPS FOUNDATION.pptxGoal Presentation_NEW EMPLOYEE_NETAPS FOUNDATION.pptx
Goal Presentation_NEW EMPLOYEE_NETAPS FOUNDATION.pptx
 
如何办理(SUT毕业证书)斯威本科技大学毕业证成绩单本科硕士学位证留信学历认证
如何办理(SUT毕业证书)斯威本科技大学毕业证成绩单本科硕士学位证留信学历认证如何办理(SUT毕业证书)斯威本科技大学毕业证成绩单本科硕士学位证留信学历认证
如何办理(SUT毕业证书)斯威本科技大学毕业证成绩单本科硕士学位证留信学历认证
 
Pay after result spell caster (,$+27834335081)@ bring back lost lover same da...
Pay after result spell caster (,$+27834335081)@ bring back lost lover same da...Pay after result spell caster (,$+27834335081)@ bring back lost lover same da...
Pay after result spell caster (,$+27834335081)@ bring back lost lover same da...
 
Obat Aborsi Pasuruan 0851\7696\3835 Jual Obat Cytotec Di Pasuruan
Obat Aborsi Pasuruan 0851\7696\3835 Jual Obat Cytotec Di PasuruanObat Aborsi Pasuruan 0851\7696\3835 Jual Obat Cytotec Di Pasuruan
Obat Aborsi Pasuruan 0851\7696\3835 Jual Obat Cytotec Di Pasuruan
 

Project Management - AT&T vs Project Boomerang

  • 1. IBS1 - Group H Nadine Bleienheuft | Horacio Fernandez | Luca Fornasier |Verena Riedhart | Lakshay Suri | Pascal Rehder Project Management Professor Sharada Kumaran Ravindran
 18.06.2015 Project Boomerang - Project Plan
  • 2. SCOPE DEFINITION 2IBS1 Group H • Boomerang Application selected to process end user requirements 18.06.15 BOOMERANG • Components impacted 1. Validator 2. Order Request Module 3. Order Status Module • Boomerang Objective • enhance AT&T’s webpage • provide additional functionality • quality online service to clients
  • 3. BOOMERANG ASSUMPTIONS 3IBS1 Group H 18.06.15 Existing application 1 2 Requirement identified during the Requirements Phase need to be implemented in line with Scope Definition
  • 4. CONSTRAINTS 4IBS1 Group H 18.06.15 1 2 3 Total budget 4 5 Resource availability Project deadline Client decision on final result Software compatibility 
 w/ client infrastructure
  • 5. EXCLUSIONS 5IBS1 Group H 18.06.15 No additional requirements are added after the Requirement Phase No training to the end user about usability of the enhanced software 1 2
  • 6. KEY DELIVERABLES 6IBS1 Group H 18.06.15 Enhance AT&T system to incorporate… 1 2 3 Order Acceptance Order Processing Order Validator
  • 7. KEY STAKEHOLDERS 7IBS1 Group H 18.06.157 AT&T customers who… • live in California region • have right to access application • have an active user account AT&T clients AT&T vendors
  • 8. MILESTONES 8IBS1 Group H 18.06.15 No. Task Milestone Date 1 Project Start Date 01/06/2015 2 Project Plan Document Check in 01/06/2015 3 Requirements Document Check in 24/07/2015 4 Development Package Check in 26/09/2015 5 Test Package Check in 15/10/2015 6 Production Deployment (Go-Live) 26/10/2015
  • 9. WORK BREAKDOWN STRUCTURE 9IBS1 Group H 18.06.15 a b c a b c a b c a b c d e a
  • 10. PROJECT RESOURCES 10IBS1 Group H 18.06.15 Requirement 
 Gathering
 Phase Development 
 Phase System Testing 
 Phase Production
 Deployment Resources
 (People) Pascal
 Lakshay Nadine
 Horacio
 Luca Verena Pascal Lakshay Pascal Lakshay Prof. S. Ravindran Group Lead Resources
 (Technology) Servers: Webspace Server Batch Server Database: SQL Server 2000 Development: RAD Operating System: MS Windows Client
 Verification Code
 Deployment Mark
 Nadine
 Pascal Maintenance
 Phase
  • 13. ACCEPTANCE CRITERIA 13IBS1 Group H 18.06.15 PERFORMANCE
 MEASUREMENT A. receive the orders of specific status which the current functionality doesn’t allow
 B. process the order of specific status and move it to the next processing status unless there is some other issue System should be able to…
  • 14. RISK IDENTIFICATION 14IBS1 Group H 18.06.15 • Occurring from interfacing applications APPLICATION
 DOWNTIME OUTAGES ERRORS • Functional Errors
 • System Errors
  • 15. RISK STRATEGY 15IBS1 Group H 18.06.15 APPLICATION REBOOT Disaster
 Recovery 
 Strategy
  • 16. APPROVERS 16IBS1 Group H 18.06.15 Emp Role Group Mark Thomson Project Manager AT&T, Boomerang Sharada Ravindran Group Lead IE Business School Nadine Bleienheuft Software Developer IE Business School Horacio Fernández del Castillo Software Developer IE Business School Luca Fornasier Software Developer IE Business School Verena Riedhart Software 
 Tester IE Business School Pascal Rehder Software 
 Tester IE Business School Lakshay Suri Software 
 Tester IE Business School
  • 17. Q&A 17IBS1 Group H 18.06.15 PROJECT BOOMERANG