Project Management
PRINCE2®
in 30 mins
P R I N C E 2 I N 3 0 M I N U T E S
Introduction
2
Karen Swanston
A very enthusiastic and experienced trainer,
specialising in PRINCE2 and M_o_R
(Management of Risk) training for more than
nine years.
Along with her experience, Karen has a
passion for designing and delivering training
in a fun and easy manner. Because of this,
she consistently receives above average
feedback and exam results from her
students. Her blend of experience and
enthusiasm is what makes her the ideal
speaker for this session
P R I N C E 2 I N 3 0 M I N U T E S
This session will take you through how easy
PRINCE2 can be to learn.
We’ll look at the basics of the framework without
overcomplicating it, and provide you with some
quick and easy-to-use hints and tips.
Easy to learn
P R I N C E 2 I N 3 0 M I N U T E S
Definition of a PRINCE2 Project
A project is a temporary organisation
that is created for the purpose of delivering
one or more business products,
according to an agreed business case.
© Copyright 2013. Reproduced under Licence from AXELOS Limited.
P R I N C E 2 I N 3 0 M I N U T E S
Product
Project
Business
as
usual
Output
Change
Outcome
Users
Benefit Dis-benefit
Stuff
Specialist Product
P R I N C E 2 I N 3 0 M I N U T E S
OutPut
Change
OutCome
Users
Stuff
Specialist Product
Project
Business
as
usual
Benefit Dis-benefit
P R I N C E 2 I N 3 0 M I N U T E S
PRINCE2 four integrated elements
7 Principles (guiding obligations and good practices)
Washing your hands
7 Themes (Addressed continually throughout the project)
Ingredients to be used
7 Processes (step-wise progression through a project)
Recipe to follow
Tailoring to the environment (flexibility)
Cottage Pie for one? Including Carrots?
P R I N C E 2 I N 3 0 M I N U T E S
Principles
• Continued business justification
• Learn from experience
• Defined roles & responsibilities
• Manage by stages
• Manage by exception
• Focus on products
• Tailor to suit the project environment
P R I N C E 2 I N 3 0 M I N U T E S
Themes
• Business case
• Organization
• Quality
• Plans
• Risk
• Change
• Progress
P R I N C E 2 I N 3 0 M I N U T E S
PRINCE2 processes
Authorize
the project
M A N D A T E C O R P O R A T E O R P R O G R A M M E M A N A G E M E N T
Authorize a stage
or exception plan
Authorize
project closure
Authorize
initiation
MANAGING
A STAGE
BOUNDARY
CLOSING A
PROJECT
CONTROLLING
A STAGE
MANAGING
PRODUCT
DELIVERY
STARTING
UP A
PROJECT
INITIATING
A PROJECT
DIRECTING A PROJECT
P R I N C E 2 I N 3 0 M I N U T E S
PRINCE2 processes
Authorize
the project
M A N D A T E C O R P O R A T E O R P R O G R A M M E M A N A G E M E N T
Authorize a stage
or exception plan
Authorize
project closure
Authorize
initiation
MANAGING
A STAGE
BOUNDARY
CLOSING A
PROJECT
CONTROLLING
A STAGE
MANAGING
PRODUCT
DELIVERY
STARTING
UP A
PROJECT
INITIATING
A PROJECT
DIRECTING A PROJECT
P R I N C E 2 I N 3 0 M I N U T E S
Starting up a project
© Copyright 2013. Reproduced under Licence from AXELOS Limited.
P R I N C E 2 I N 3 0 M I N U T E S
Organization
PROJECT
MANAGEMENT
TEAM
© Copyright 2013. Reproduced under Licence from AXELOS Limited.
Corporate or programme management
Directing – Project Board
Managing – Project Manager
Delivering – Team Manager
Project
Management
Team
P R I N C E 2 I N 3 0 M I N U T E S
Business case
Confirm
benefit
Verify
updated
Business Case
Verify
outline
Business Case
Verify
detailed
Business Case
Develop
Business Case
Maintain
Business Case
Pre-
project
Initiation
stage
Subsequent delivery
stage(s)
Final delivery
stage
Post-
project
Confirm
benefit
Confirm
benefit
© Copyright 2013. Reproduced under Licence from AXELOS Limited.
P R I N C E 2 I N 3 0 M I N U T E S
Authorize
the project
M A N D A T E C O R P O R A T E O R P R O G R A M M E M A N A G E M E N T
Authorize a stage
or exception plan
Authorize
project closure
Authorize
Initiation
MANAGING
A STAGE
BOUNDARY
CLOSING A
PROJECT
CONTROLLING
A STAGE
MANAGING
PRODUCT
DELIVERY
STARTING
UP A
PROJECT
Executive &
PM
Outline
business
case
PMT
Project
approach
Project brief
Initiation
stage plan
DIRECTING A PROJECT
INITIATING
A PROJECT
PRINCE2 processes
P R I N C E 2 I N 3 0 M I N U T E S
Authorize
the project
M A N D A T E C O R P O R A T E O R P R O G R A M M E M A N A G E M E N T
Authorize a stage
or exception plan
Authorize
project closure
MANAGING
A STAGE
BOUNDARY
CLOSING A
PROJECT
CONTROLLING
A STAGE
MANAGING
PRODUCT
DELIVERY
STARTING
UP A
PROJECT
Executive &
PM
Outline
business
case
PMT
Project
approach
Project brief
Initiation
stage plan
DIRECTING A PROJECT
Authorize
Initiation
PRINCE2 processes
INITIATING
A PROJECT
P R I N C E 2 I N 3 0 M I N U T E S
Initiating a project
© Copyright 2013.
Reproduced under
Licence from
AXELOS Limited.
P R I N C E 2 I N 3 0 M I N U T E S
Risk definition
A risk is: an uncertain event or set of
events that, should it occur, will have an
effect on the achievement of objectives
MAY
MIGHT
COULD
P R I N C E 2 I N 3 0 M I N U T E S
Issue definition
A issue is: something that has happened
or it will happen that was not planned.
WILL
HAS
NO UNCERTAINTY
P R I N C E 2 I N 3 0 M I N U T E S
Quality
PRODUCT
DESCRIPTION
Engine: petrol,
3.5L
PROJECT PRODUCT DESCRIPTION
PRODUCT
DESCRIPTION
Cream leather
seats
PRODUCT
DESCRIPTION
Tyres: Dunlop
245/40 R19
ACCEPTANCE
CRITERIA
1. 0-60 mph in 3 seconds
2. Up to 2 years old
3. ‘What Car’ top 10 most
desirable cars
CUSTOMER
QUALITY
EXPECTATIONS
1.Fast Car
2.New Car
3.Flashy Car
P R I N C E 2 I N 3 0 M I N U T E S
Plans
TIME & COST
PROJECT PLAN
e e e e
P R I N C E 2 I N 3 0 M I N U T E S
Authorize
the project
M A N D A T E C O R P O R A T E O R P R O G R A M M E M A N A G E M E N T
Authorize a stage
or exception plan
Authorize
project closure
Authorize
initiation
MANAGING
A STAGE
BOUNDARY
CLOSING A
PROJECT
CONTROLLING
A STAGE
MANAGING
PRODUCT
DELIVERY
STARTING
UP A
PROJECT
Executive &
PM
Outline
business
case
PMT
Project
approach
Project brief
Initiation
stage plan
INITIATING
A PROJECT
Strategies &
registers
Project plan
Business case
Project
Initiation
Documentation
(PID)
DIRECTING A PROJECT
PRINCE2 processes
P R I N C E 2 I N 3 0 M I N U T E S
Plans
TIME & COST
STAGE PLAN
TIME & COST
PROJECT PLAN
e e e e
e e e e
P R I N C E 2 I N 3 0 M I N U T E S
Authorize
the project
M A N D A T E C O R P O R A T E O R P R O G R A M M E M A N A G E M E N T
Authorize a stage
or exception plan
Authorize
project closure
Authorize
initiation
Workpackage
PM
TM
Checkpoint
report
PRINCE2 processes
MANAGING
A STAGE
BOUNDARY
Stage plan
CLOSING A
PROJECT
CONTROLLING
A STAGE
MANAGING
PRODUCT
DELIVERY
STARTING
UP A
PROJECT
Executive &
PM
Outline
business
case
PMT
Project
approach
Project brief
Initiation
stage plan
DIRECTING A PROJECT
INITIATING
A PROJECT
Strategies &
registers
Project plan
Business case
Project
Initiation
Documentation
(PID)
P R I N C E 2 I N 3 0 M I N U T E S
Authorize
the project
M A N D A T E C O R P O R A T E O R P R O G R A M M E M A N A G E M E N T
Authorize a stage
or exception plan
Authorize
project closure
Authorize
initiation
Workpackage
PM
PRINCE2 processes
MANAGING
A STAGE
BOUNDARY
Stage plan
CLOSING A
PROJECT
CONTROLLING
A STAGE
MANAGING
PRODUCT
DELIVERY
STARTING
UP A
PROJECT
Executive &
PM
Outline
business
case
PMT
Project
approach
Project brief
Initiation
stage plan
DIRECTING A PROJECT
INITIATING
A PROJECT
Strategies &
registers
Project plan
Business case
Project
Initiation
Documentation
(PID)
P R I N C E 2 I N 3 0 M I N U T E S
Authorize
the project
M A N D A T E C O R P O R A T E O R P R O G R A M M E M A N A G E M E N T
Authorize a stage
or exception plan
Authorize
project closure
Authorize
initiation
Workpackage
PM
TM
PRINCE2 processes
MANAGING
A STAGE
BOUNDARY
Stage plan
CLOSING A
PROJECT
CONTROLLING
A STAGE
MANAGING
PRODUCT
DELIVERY
STARTING
UP A
PROJECT
Executive &
PM
Outline
business
case
PMT
Project
approach
Project brief
Initiation
stage plan
DIRECTING A PROJECT
INITIATING
A PROJECT
Strategies &
registers
Project plan
Business case
Project
Initiation
Documentation
(PID)
P R I N C E 2 I N 3 0 M I N U T E S
Plans
TEAM
PLAN
WORKPACKAGE
TIME & COST
STAGE PLAN
TIME & COST
PROJECT PLAN
e e e e
e e e e
P R I N C E 2 I N 3 0 M I N U T E S
PRINCE2 processes
Authorize
the project
M A N D A T E C O R P O R A T E O R P R O G R A M M E M A N A G E M E N T
Authorize a stage
or exception plan
Authorize
project closure
Authorize
initiation
Workpackage
PM
TM
MANAGING
A STAGE
BOUNDARY
Stage plan
CLOSING A
PROJECT
CONTROLLING
A STAGE
MANAGING
PRODUCT
DELIVERY
STARTING
UP A
PROJECT
Executive &
PM
Outline
business
case
PMT
Project
approach
Project brief
Initiation
stage plan
DIRECTING A PROJECT
Checkpoint
report
INITIATING
A PROJECT
Strategies &
registers
Project plan
Business case
Project
Initiation
Documentation
(PID)
P R I N C E 2 I N 3 0 M I N U T E S
Progress – reporting
P R O J E C T B O A R D
S e n i o r u s e r E x e c u t i v e S e n i o r s u p p l i e r
C O R P O R AT E O R P R O G R AM M E M AN A G E M E N T
P R O J E C T M A N A G E R
T E A M M A N A G E R
H I G H L I G H T R E P O R T
C H E C K P O I N T R E P O R T
H I G H L I G H T R E P O R T
P R I N C E 2 I N 3 0 M I N U T E S
Progress – tolerances
P R I N C E 2 I N 3 0 M I N U T E S
Authorize
the project
C O R P O R A T E O R P R O G R A M M E M A N A G E M E N T
Authorize a stage
or exception plan
Authorize
project closure
Authorize
initiation
Workpackage
PM
TM
Checkpoint
report
MANAGING
A STAGE
BOUNDARY
Stage plan
Update:
project plan
business
case
End-stage
report
CLOSING A
PROJECT
CONTROLLING
A STAGE
Update
Stage Plan
MANAGING
PRODUCT
DELIVERY
STARTING
UP A
PROJECT
Executive &
PM
Outline
business
case
PMT
Project
approach
Project brief
Initiation
stage plan
DIRECTING A PROJECT
M A N D A T E
PRINCE2 processes
INITIATING
A PROJECT
Strategies &
registers
Project plan
Business case
Project
Initiation
Documentation
(PID)
P R I N C E 2 I N 3 0 M I N U T E S
Authorize
the project
C O R P O R A T E O R P R O G R A M M E M A N A G E M E N T
Authorize a stage
or exception plan
Authorize
project closure
Authorize
initiation
Workpackage
PM
TM
Checkpoint
report
MANAGING
A STAGE
BOUNDARY
Stage plan
Update:
project plan
business
case
End-stage
report
CLOSING A
PROJECT
CONTROLLING
A STAGE
Update
Stage Plan
MANAGING
PRODUCT
DELIVERY
STARTING
UP A
PROJECT
Executive &
PM
Outline
business
case
PMT
Project
approach
Project brief
Initiation
stage plan
DIRECTING A PROJECT
M A N D A T E
PRINCE2 processes
INITIATING
A PROJECT
Strategies &
registers
Project plan
Business case
Project
Initiation
Documentation
(PID)
P R I N C E 2 I N 3 0 M I N U T E S
Authorize
the project
C O R P O R A T E O R P R O G R A M M E M A N A G E M E N T
Authorize a stage
or exception plan
Authorize
project closure
Authorize
initiation
Workpackage
PM
TM
Checkpoint
report
MANAGING
A STAGE
BOUNDARY
Stage plan
Update:
project plan
business
case
End-stage
report
CLOSING A
PROJECT
CONTROLLING
A STAGE
Update
Stage Plan
MANAGING
PRODUCT
DELIVERY
STARTING
UP A
PROJECT
Executive &
PM
Outline
business
case
PMT
Project
approach
Project brief
Initiation
stage plan
DIRECTING A PROJECT
M A N D A T E
PRINCE2 processes
INITIATING
A PROJECT
Strategies &
registers
Project plan
Business case
Project
Initiation
Documentation
(PID)
P R I N C E 2 I N 3 0 M I N U T E S
Authorize
the project
C O R P O R A T E O R P R O G R A M M E M A N A G E M E N T
Authorize a stage
or exception plan
Authorize
project closure
Authorize
initiation
Workpackage
PM
TM
Checkpoint
report
MANAGING
A STAGE
BOUNDARY
Stage plan
Update:
project plan
business
case
End-stage
report
CLOSING A
PROJECT
CONTROLLING
A STAGE
Update
Stage Plan
MANAGING
PRODUCT
DELIVERY
STARTING
UP A
PROJECT
Executive &
PM
Outline
business
case
PMT
Project
approach
Project brief
Initiation
stage plan
DIRECTING A PROJECT
M A N D A T E
PRINCE2 processes
INITIATING
A PROJECT
Strategies &
registers
Project plan
Business case
Project
Initiation
Documentation
(PID)
P R I N C E 2 I N 3 0 M I N U T E S
Authorize
the project
M A N D A T E C O R P O R A T E O R P R O G R A M M E M A N A G E M E N T
Authorize a stage
or exception plan
Authorize
project closure
Authorize
initiation
Workpackage
PM
TM
Checkpoint
report
MANAGING
A STAGE
BOUNDARY
Stage plan
Update:
project plan
business
case
End-stage
report
CLOSING A
PROJECT
CONTROLLING
A STAGE
Update
Stage Plan
MANAGING
PRODUCT
DELIVERY
STARTING
UP A
PROJECT
Executive &
PM
Outline
business
case
PMT
Project
approach
Project brief
Initiation
stage plan
Confirm all
products are
completed
Evaluate the
project
Communication
Archive project
documentation
PRINCE2 processes
DIRECTING A PROJECT
INITIATING
A PROJECT
Strategies &
registers
Project plan
Business case
Project
Initiation
Documentation
(PID)
P R I N C E 2 I N 3 0 M I N U T E S
Authorize
the project
C O R P O R A T E O R P R O G R A M M E M A N A G E M E N T
Authorize a stage
or exception plan
Authorize
project closure
Authorize
initiation
Workpackage
Checkpoint
report
MANAGING
A STAGE
BOUNDARY
Stage plan
Update:
project plan
business
case
End-stage
report
CLOSING A
PROJECT
Confirm all
products are
completed
Evaluate the
project
Communication
Archive project
documentation
CONTROLLING
A STAGE
Update
Stage Plan
MANAGING
PRODUCT
DELIVERY
STARTING
UP A
PROJECT
Executive &
PM
Outline
business
case
PMT
Project
approach
Project brief
Initiation
stage plan
PRINCE2 processes
M A N D A T E
DIRECTING A PROJECT
INITIATING
A PROJECT
Strategies &
registers
Project plan
Business case
Project
Initiation
Documentation
(PID)
P R I N C E 2 I N 3 0 M I N U T E S
During this session we
have stepped through some of the
basic concepts of PRINCE2
without overcomplicating it,
and provided you with some quick,
easy-to-use hints and tips.
Easy to learn
P R I N C E 2 I N 3 0 M I N U T E S
Questions?
P R I N C E 2 I N 3 0 M I N U T E S
Why ILX?
For more information about our courses,
visit our website ilxgroup.com,
give us a call on +44 (0) 1270 611 600 or send an email to:
Individuals enquiries suzanne.bailey@ilxgroup.com
Corporate enquiries paula.gower@ilxgroup.com
P R I N C E 2 I N 3 0 M I N U T E S
Recommended courses
PRINCE2
Programme
& Project
Sponsorship
APM Project
Management
Qualification
Change
Management
P R I N C E 2 I N 3 0 M I N U T E S
I L X G R O U P, U n i t e d K i n g d o m
7 t h F l o o r
9 5 A l d w y c h
L o n d o n W C 2 B 4 J F - U K
T: + 4 4 ( 0 ) 2 0 7 3 7 1 4 4 4 4
Thank you for listening
I L X G R O U P, Au s t r a l i a
7 3 0 S p r i n g v a l e R d
M u l g r a v e , V I C 3 1 7 0
A u s t r a l i a
T: + 6 1 1 3 0 0 4 5 9 4 5 9
www.ilxgroup.com

More Related Content

Similar to prince2in30mins-170503124814.pdf

ePMO & Enterprise Implementations
ePMO & Enterprise ImplementationsePMO & Enterprise Implementations
ePMO & Enterprise Implementations
Plexlane+
 
Project management intro from prince2 foundation
Project management intro from prince2  foundationProject management intro from prince2  foundation
Project management intro from prince2 foundation
bhprabhu
 
pmiprojectmanagementprinciples20141006-141006181426-conversion-gate01-convert...
pmiprojectmanagementprinciples20141006-141006181426-conversion-gate01-convert...pmiprojectmanagementprinciples20141006-141006181426-conversion-gate01-convert...
pmiprojectmanagementprinciples20141006-141006181426-conversion-gate01-convert...
Chandrasen Sharma
 
PRINCE2 Executive Briefing
PRINCE2 Executive BriefingPRINCE2 Executive Briefing
PRINCE2 Executive Briefing
Russ McDowell, PMP, OPM3, PRINCE2, MoP
 
your-prince2-processes-and-products-roadmap-projex-academy_compress.pdf
your-prince2-processes-and-products-roadmap-projex-academy_compress.pdfyour-prince2-processes-and-products-roadmap-projex-academy_compress.pdf
your-prince2-processes-and-products-roadmap-projex-academy_compress.pdf
hiwotmengistu3
 
Project Management Slides Powerpoint Template.pptx
Project Management Slides Powerpoint Template.pptxProject Management Slides Powerpoint Template.pptx
Project Management Slides Powerpoint Template.pptx
Fabio Miranda
 
Guidelines for Managing Projects
Guidelines for Managing ProjectsGuidelines for Managing Projects
Guidelines for Managing Projects
Preston Healthcare Consulting
 
Pmi Pmbok Vs Prince2
Pmi Pmbok Vs Prince2Pmi Pmbok Vs Prince2
Pmi Pmbok Vs Prince2
sundong
 
PMBOK® Vs PRINCE2®
PMBOK®  Vs PRINCE2®PMBOK®  Vs PRINCE2®
PMBOK® Vs PRINCE2®
Rajiv Sharma
 
PRINCE 2 foundation & practitioner certification training
PRINCE 2   foundation & practitioner certification trainingPRINCE 2   foundation & practitioner certification training
PRINCE 2 foundation & practitioner certification training
Celtem Learning
 
Operational Excellence-CPOE-Unichrone
Operational Excellence-CPOE-UnichroneOperational Excellence-CPOE-Unichrone
Operational Excellence-CPOE-Unichrone
SantoshK55
 
Prince2009
Prince2009Prince2009
Prince2009
Perry Wheeler
 
Similarities and differences between PMBOK® Guide and PRINCE2® method
Similarities and differences between PMBOK® Guide and PRINCE2® methodSimilarities and differences between PMBOK® Guide and PRINCE2® method
Similarities and differences between PMBOK® Guide and PRINCE2® method
Svetlana Sidenko
 
Tell us what to do, not how to do it, APM North West Network Conference, Syne...
Tell us what to do, not how to do it, APM North West Network Conference, Syne...Tell us what to do, not how to do it, APM North West Network Conference, Syne...
Tell us what to do, not how to do it, APM North West Network Conference, Syne...
Association for Project Management
 
Northern Finishing School: IT Project Managment
Northern Finishing School: IT Project ManagmentNorthern Finishing School: IT Project Managment
Northern Finishing School: IT Project Managment
Siwawong Wuttipongprasert
 
Project management - Basics for all
Project management - Basics for allProject management - Basics for all
Project management - Basics for all
Surgyy Design
 
Project Management
Project ManagementProject Management
Project Management
Acend Corporate Learning
 
Demystifying Prince2 : Why does it matter?
Demystifying Prince2 : Why does it matter?Demystifying Prince2 : Why does it matter?
Demystifying Prince2 : Why does it matter?
Edureka!
 
Prince 2 F+P Course Preview
Prince 2 F+P Course PreviewPrince 2 F+P Course Preview
Prince 2 F+P Course Preview
Invensis Learning
 
2-0 PROJECT STARTUP
2-0 PROJECT STARTUP2-0 PROJECT STARTUP
2-0 PROJECT STARTUP
pmSPECFramework
 

Similar to prince2in30mins-170503124814.pdf (20)

ePMO & Enterprise Implementations
ePMO & Enterprise ImplementationsePMO & Enterprise Implementations
ePMO & Enterprise Implementations
 
Project management intro from prince2 foundation
Project management intro from prince2  foundationProject management intro from prince2  foundation
Project management intro from prince2 foundation
 
pmiprojectmanagementprinciples20141006-141006181426-conversion-gate01-convert...
pmiprojectmanagementprinciples20141006-141006181426-conversion-gate01-convert...pmiprojectmanagementprinciples20141006-141006181426-conversion-gate01-convert...
pmiprojectmanagementprinciples20141006-141006181426-conversion-gate01-convert...
 
PRINCE2 Executive Briefing
PRINCE2 Executive BriefingPRINCE2 Executive Briefing
PRINCE2 Executive Briefing
 
your-prince2-processes-and-products-roadmap-projex-academy_compress.pdf
your-prince2-processes-and-products-roadmap-projex-academy_compress.pdfyour-prince2-processes-and-products-roadmap-projex-academy_compress.pdf
your-prince2-processes-and-products-roadmap-projex-academy_compress.pdf
 
Project Management Slides Powerpoint Template.pptx
Project Management Slides Powerpoint Template.pptxProject Management Slides Powerpoint Template.pptx
Project Management Slides Powerpoint Template.pptx
 
Guidelines for Managing Projects
Guidelines for Managing ProjectsGuidelines for Managing Projects
Guidelines for Managing Projects
 
Pmi Pmbok Vs Prince2
Pmi Pmbok Vs Prince2Pmi Pmbok Vs Prince2
Pmi Pmbok Vs Prince2
 
PMBOK® Vs PRINCE2®
PMBOK®  Vs PRINCE2®PMBOK®  Vs PRINCE2®
PMBOK® Vs PRINCE2®
 
PRINCE 2 foundation & practitioner certification training
PRINCE 2   foundation & practitioner certification trainingPRINCE 2   foundation & practitioner certification training
PRINCE 2 foundation & practitioner certification training
 
Operational Excellence-CPOE-Unichrone
Operational Excellence-CPOE-UnichroneOperational Excellence-CPOE-Unichrone
Operational Excellence-CPOE-Unichrone
 
Prince2009
Prince2009Prince2009
Prince2009
 
Similarities and differences between PMBOK® Guide and PRINCE2® method
Similarities and differences between PMBOK® Guide and PRINCE2® methodSimilarities and differences between PMBOK® Guide and PRINCE2® method
Similarities and differences between PMBOK® Guide and PRINCE2® method
 
Tell us what to do, not how to do it, APM North West Network Conference, Syne...
Tell us what to do, not how to do it, APM North West Network Conference, Syne...Tell us what to do, not how to do it, APM North West Network Conference, Syne...
Tell us what to do, not how to do it, APM North West Network Conference, Syne...
 
Northern Finishing School: IT Project Managment
Northern Finishing School: IT Project ManagmentNorthern Finishing School: IT Project Managment
Northern Finishing School: IT Project Managment
 
Project management - Basics for all
Project management - Basics for allProject management - Basics for all
Project management - Basics for all
 
Project Management
Project ManagementProject Management
Project Management
 
Demystifying Prince2 : Why does it matter?
Demystifying Prince2 : Why does it matter?Demystifying Prince2 : Why does it matter?
Demystifying Prince2 : Why does it matter?
 
Prince 2 F+P Course Preview
Prince 2 F+P Course PreviewPrince 2 F+P Course Preview
Prince 2 F+P Course Preview
 
2-0 PROJECT STARTUP
2-0 PROJECT STARTUP2-0 PROJECT STARTUP
2-0 PROJECT STARTUP
 

Recently uploaded

一比一原版(USF毕业证)旧金山大学毕业证如何办理
一比一原版(USF毕业证)旧金山大学毕业证如何办理一比一原版(USF毕业证)旧金山大学毕业证如何办理
一比一原版(USF毕业证)旧金山大学毕业证如何办理
40fortunate
 
nurs fpx 4050 assessment 4 final care coordination plan.pdf
nurs fpx 4050 assessment 4 final care coordination plan.pdfnurs fpx 4050 assessment 4 final care coordination plan.pdf
nurs fpx 4050 assessment 4 final care coordination plan.pdf
Carolyn Harker
 
Fit to Fly PCR Covid Testing at our Clinic Near You
Fit to Fly PCR Covid Testing at our Clinic Near YouFit to Fly PCR Covid Testing at our Clinic Near You
Fit to Fly PCR Covid Testing at our Clinic Near You
NX Healthcare
 
Friendly Massage in Ajman - Malayali Kerala Spa Ajman
Friendly Massage in Ajman - Malayali Kerala Spa AjmanFriendly Massage in Ajman - Malayali Kerala Spa Ajman
Friendly Massage in Ajman - Malayali Kerala Spa Ajman
Malayali Kerala Spa Ajman
 
Hypertension and it's role of physiotherapy in it.
Hypertension and it's role of physiotherapy in it.Hypertension and it's role of physiotherapy in it.
Hypertension and it's role of physiotherapy in it.
Vishal kr Thakur
 
Pneumothorax and role of Physiotherapy in it.
Pneumothorax and role of Physiotherapy in it.Pneumothorax and role of Physiotherapy in it.
Pneumothorax and role of Physiotherapy in it.
Vishal kr Thakur
 
Mental Health and Physical Wellbeing.pdf
Mental Health and Physical Wellbeing.pdfMental Health and Physical Wellbeing.pdf
Mental Health and Physical Wellbeing.pdf
shindesupriya013
 
Data-Driven Dispensing- Rise of AI in Pharmacies.pdf
Data-Driven Dispensing- Rise of AI in Pharmacies.pdfData-Driven Dispensing- Rise of AI in Pharmacies.pdf
Data-Driven Dispensing- Rise of AI in Pharmacies.pdf
Jasper Colin
 
Research, Monitoring and Evaluation, in Public Health
Research, Monitoring and Evaluation, in Public HealthResearch, Monitoring and Evaluation, in Public Health
Research, Monitoring and Evaluation, in Public Health
aghedogodday
 
English Drug and Alcohol Commissioners June 2024.pptx
English Drug and Alcohol Commissioners June 2024.pptxEnglish Drug and Alcohol Commissioners June 2024.pptx
English Drug and Alcohol Commissioners June 2024.pptx
MatSouthwell1
 
Digital Health in India_Health Informatics Trained Manpower _DrDevTaneja_15.0...
Digital Health in India_Health Informatics Trained Manpower _DrDevTaneja_15.0...Digital Health in India_Health Informatics Trained Manpower _DrDevTaneja_15.0...
Digital Health in India_Health Informatics Trained Manpower _DrDevTaneja_15.0...
DrDevTaneja1
 
EXAMINATION OF HUMAN URINE AND FAECES.pdf
EXAMINATION OF HUMAN URINE AND FAECES.pdfEXAMINATION OF HUMAN URINE AND FAECES.pdf
EXAMINATION OF HUMAN URINE AND FAECES.pdf
Madhusmita Sahoo
 
VEDANTA AIR AMBULANCE SERVICES IN REWA AT A COST-EFFECTIVE PRICE.pdf
VEDANTA AIR AMBULANCE SERVICES IN REWA AT A COST-EFFECTIVE PRICE.pdfVEDANTA AIR AMBULANCE SERVICES IN REWA AT A COST-EFFECTIVE PRICE.pdf
VEDANTA AIR AMBULANCE SERVICES IN REWA AT A COST-EFFECTIVE PRICE.pdf
Vedanta A
 
Solution manual for managerial accounting 18th edition by ray garrison eric n...
Solution manual for managerial accounting 18th edition by ray garrison eric n...Solution manual for managerial accounting 18th edition by ray garrison eric n...
Solution manual for managerial accounting 18th edition by ray garrison eric n...
rightmanforbloodline
 
Monopoly PCD Pharma Franchise in Tripura
Monopoly PCD Pharma Franchise in TripuraMonopoly PCD Pharma Franchise in Tripura
Monopoly PCD Pharma Franchise in Tripura
SKG Internationals
 
nhs fpx 4000 assessment 4 analyzing a current health care problem or issue.pdf
nhs fpx 4000 assessment 4 analyzing a current health care problem or issue.pdfnhs fpx 4000 assessment 4 analyzing a current health care problem or issue.pdf
nhs fpx 4000 assessment 4 analyzing a current health care problem or issue.pdf
Carolyn Harker
 
muscluskeletal assessment...........pptx
muscluskeletal assessment...........pptxmuscluskeletal assessment...........pptx
muscluskeletal assessment...........pptx
RushikeshHange1
 
Management of Post Operative Pain: to make doctors conscious about the benefi...
Management of Post Operative Pain: to make doctors conscious about the benefi...Management of Post Operative Pain: to make doctors conscious about the benefi...
Management of Post Operative Pain: to make doctors conscious about the benefi...
Nilima65
 
Daughter's of Dr Ranjit Jagtap (Poulami & Aditi)
Daughter's of Dr Ranjit Jagtap (Poulami & Aditi)Daughter's of Dr Ranjit Jagtap (Poulami & Aditi)
Daughter's of Dr Ranjit Jagtap (Poulami & Aditi)
Aditi Jagtap Pune
 
FACIAL NERVE
FACIAL NERVEFACIAL NERVE
FACIAL NERVE
aditigupta1117
 

Recently uploaded (20)

一比一原版(USF毕业证)旧金山大学毕业证如何办理
一比一原版(USF毕业证)旧金山大学毕业证如何办理一比一原版(USF毕业证)旧金山大学毕业证如何办理
一比一原版(USF毕业证)旧金山大学毕业证如何办理
 
nurs fpx 4050 assessment 4 final care coordination plan.pdf
nurs fpx 4050 assessment 4 final care coordination plan.pdfnurs fpx 4050 assessment 4 final care coordination plan.pdf
nurs fpx 4050 assessment 4 final care coordination plan.pdf
 
Fit to Fly PCR Covid Testing at our Clinic Near You
Fit to Fly PCR Covid Testing at our Clinic Near YouFit to Fly PCR Covid Testing at our Clinic Near You
Fit to Fly PCR Covid Testing at our Clinic Near You
 
Friendly Massage in Ajman - Malayali Kerala Spa Ajman
Friendly Massage in Ajman - Malayali Kerala Spa AjmanFriendly Massage in Ajman - Malayali Kerala Spa Ajman
Friendly Massage in Ajman - Malayali Kerala Spa Ajman
 
Hypertension and it's role of physiotherapy in it.
Hypertension and it's role of physiotherapy in it.Hypertension and it's role of physiotherapy in it.
Hypertension and it's role of physiotherapy in it.
 
Pneumothorax and role of Physiotherapy in it.
Pneumothorax and role of Physiotherapy in it.Pneumothorax and role of Physiotherapy in it.
Pneumothorax and role of Physiotherapy in it.
 
Mental Health and Physical Wellbeing.pdf
Mental Health and Physical Wellbeing.pdfMental Health and Physical Wellbeing.pdf
Mental Health and Physical Wellbeing.pdf
 
Data-Driven Dispensing- Rise of AI in Pharmacies.pdf
Data-Driven Dispensing- Rise of AI in Pharmacies.pdfData-Driven Dispensing- Rise of AI in Pharmacies.pdf
Data-Driven Dispensing- Rise of AI in Pharmacies.pdf
 
Research, Monitoring and Evaluation, in Public Health
Research, Monitoring and Evaluation, in Public HealthResearch, Monitoring and Evaluation, in Public Health
Research, Monitoring and Evaluation, in Public Health
 
English Drug and Alcohol Commissioners June 2024.pptx
English Drug and Alcohol Commissioners June 2024.pptxEnglish Drug and Alcohol Commissioners June 2024.pptx
English Drug and Alcohol Commissioners June 2024.pptx
 
Digital Health in India_Health Informatics Trained Manpower _DrDevTaneja_15.0...
Digital Health in India_Health Informatics Trained Manpower _DrDevTaneja_15.0...Digital Health in India_Health Informatics Trained Manpower _DrDevTaneja_15.0...
Digital Health in India_Health Informatics Trained Manpower _DrDevTaneja_15.0...
 
EXAMINATION OF HUMAN URINE AND FAECES.pdf
EXAMINATION OF HUMAN URINE AND FAECES.pdfEXAMINATION OF HUMAN URINE AND FAECES.pdf
EXAMINATION OF HUMAN URINE AND FAECES.pdf
 
VEDANTA AIR AMBULANCE SERVICES IN REWA AT A COST-EFFECTIVE PRICE.pdf
VEDANTA AIR AMBULANCE SERVICES IN REWA AT A COST-EFFECTIVE PRICE.pdfVEDANTA AIR AMBULANCE SERVICES IN REWA AT A COST-EFFECTIVE PRICE.pdf
VEDANTA AIR AMBULANCE SERVICES IN REWA AT A COST-EFFECTIVE PRICE.pdf
 
Solution manual for managerial accounting 18th edition by ray garrison eric n...
Solution manual for managerial accounting 18th edition by ray garrison eric n...Solution manual for managerial accounting 18th edition by ray garrison eric n...
Solution manual for managerial accounting 18th edition by ray garrison eric n...
 
Monopoly PCD Pharma Franchise in Tripura
Monopoly PCD Pharma Franchise in TripuraMonopoly PCD Pharma Franchise in Tripura
Monopoly PCD Pharma Franchise in Tripura
 
nhs fpx 4000 assessment 4 analyzing a current health care problem or issue.pdf
nhs fpx 4000 assessment 4 analyzing a current health care problem or issue.pdfnhs fpx 4000 assessment 4 analyzing a current health care problem or issue.pdf
nhs fpx 4000 assessment 4 analyzing a current health care problem or issue.pdf
 
muscluskeletal assessment...........pptx
muscluskeletal assessment...........pptxmuscluskeletal assessment...........pptx
muscluskeletal assessment...........pptx
 
Management of Post Operative Pain: to make doctors conscious about the benefi...
Management of Post Operative Pain: to make doctors conscious about the benefi...Management of Post Operative Pain: to make doctors conscious about the benefi...
Management of Post Operative Pain: to make doctors conscious about the benefi...
 
Daughter's of Dr Ranjit Jagtap (Poulami & Aditi)
Daughter's of Dr Ranjit Jagtap (Poulami & Aditi)Daughter's of Dr Ranjit Jagtap (Poulami & Aditi)
Daughter's of Dr Ranjit Jagtap (Poulami & Aditi)
 
FACIAL NERVE
FACIAL NERVEFACIAL NERVE
FACIAL NERVE
 

prince2in30mins-170503124814.pdf

  • 1. www.ilxgroup.com by Karen Swanston Project Management PRINCE2® in 30 mins
  • 2. P R I N C E 2 I N 3 0 M I N U T E S Introduction 2 Karen Swanston A very enthusiastic and experienced trainer, specialising in PRINCE2 and M_o_R (Management of Risk) training for more than nine years. Along with her experience, Karen has a passion for designing and delivering training in a fun and easy manner. Because of this, she consistently receives above average feedback and exam results from her students. Her blend of experience and enthusiasm is what makes her the ideal speaker for this session
  • 3. P R I N C E 2 I N 3 0 M I N U T E S This session will take you through how easy PRINCE2 can be to learn. We’ll look at the basics of the framework without overcomplicating it, and provide you with some quick and easy-to-use hints and tips. Easy to learn
  • 4. P R I N C E 2 I N 3 0 M I N U T E S Definition of a PRINCE2 Project A project is a temporary organisation that is created for the purpose of delivering one or more business products, according to an agreed business case. © Copyright 2013. Reproduced under Licence from AXELOS Limited.
  • 5. P R I N C E 2 I N 3 0 M I N U T E S Product Project Business as usual Output Change Outcome Users Benefit Dis-benefit Stuff Specialist Product
  • 6. P R I N C E 2 I N 3 0 M I N U T E S OutPut Change OutCome Users Stuff Specialist Product Project Business as usual Benefit Dis-benefit
  • 7. P R I N C E 2 I N 3 0 M I N U T E S PRINCE2 four integrated elements 7 Principles (guiding obligations and good practices) Washing your hands 7 Themes (Addressed continually throughout the project) Ingredients to be used 7 Processes (step-wise progression through a project) Recipe to follow Tailoring to the environment (flexibility) Cottage Pie for one? Including Carrots?
  • 8. P R I N C E 2 I N 3 0 M I N U T E S Principles • Continued business justification • Learn from experience • Defined roles & responsibilities • Manage by stages • Manage by exception • Focus on products • Tailor to suit the project environment
  • 9. P R I N C E 2 I N 3 0 M I N U T E S Themes • Business case • Organization • Quality • Plans • Risk • Change • Progress
  • 10. P R I N C E 2 I N 3 0 M I N U T E S PRINCE2 processes Authorize the project M A N D A T E C O R P O R A T E O R P R O G R A M M E M A N A G E M E N T Authorize a stage or exception plan Authorize project closure Authorize initiation MANAGING A STAGE BOUNDARY CLOSING A PROJECT CONTROLLING A STAGE MANAGING PRODUCT DELIVERY STARTING UP A PROJECT INITIATING A PROJECT DIRECTING A PROJECT
  • 11. P R I N C E 2 I N 3 0 M I N U T E S PRINCE2 processes Authorize the project M A N D A T E C O R P O R A T E O R P R O G R A M M E M A N A G E M E N T Authorize a stage or exception plan Authorize project closure Authorize initiation MANAGING A STAGE BOUNDARY CLOSING A PROJECT CONTROLLING A STAGE MANAGING PRODUCT DELIVERY STARTING UP A PROJECT INITIATING A PROJECT DIRECTING A PROJECT
  • 12. P R I N C E 2 I N 3 0 M I N U T E S Starting up a project © Copyright 2013. Reproduced under Licence from AXELOS Limited.
  • 13. P R I N C E 2 I N 3 0 M I N U T E S Organization PROJECT MANAGEMENT TEAM © Copyright 2013. Reproduced under Licence from AXELOS Limited. Corporate or programme management Directing – Project Board Managing – Project Manager Delivering – Team Manager Project Management Team
  • 14. P R I N C E 2 I N 3 0 M I N U T E S Business case Confirm benefit Verify updated Business Case Verify outline Business Case Verify detailed Business Case Develop Business Case Maintain Business Case Pre- project Initiation stage Subsequent delivery stage(s) Final delivery stage Post- project Confirm benefit Confirm benefit © Copyright 2013. Reproduced under Licence from AXELOS Limited.
  • 15. P R I N C E 2 I N 3 0 M I N U T E S Authorize the project M A N D A T E C O R P O R A T E O R P R O G R A M M E M A N A G E M E N T Authorize a stage or exception plan Authorize project closure Authorize Initiation MANAGING A STAGE BOUNDARY CLOSING A PROJECT CONTROLLING A STAGE MANAGING PRODUCT DELIVERY STARTING UP A PROJECT Executive & PM Outline business case PMT Project approach Project brief Initiation stage plan DIRECTING A PROJECT INITIATING A PROJECT PRINCE2 processes
  • 16. P R I N C E 2 I N 3 0 M I N U T E S Authorize the project M A N D A T E C O R P O R A T E O R P R O G R A M M E M A N A G E M E N T Authorize a stage or exception plan Authorize project closure MANAGING A STAGE BOUNDARY CLOSING A PROJECT CONTROLLING A STAGE MANAGING PRODUCT DELIVERY STARTING UP A PROJECT Executive & PM Outline business case PMT Project approach Project brief Initiation stage plan DIRECTING A PROJECT Authorize Initiation PRINCE2 processes INITIATING A PROJECT
  • 17. P R I N C E 2 I N 3 0 M I N U T E S Initiating a project © Copyright 2013. Reproduced under Licence from AXELOS Limited.
  • 18. P R I N C E 2 I N 3 0 M I N U T E S Risk definition A risk is: an uncertain event or set of events that, should it occur, will have an effect on the achievement of objectives MAY MIGHT COULD
  • 19. P R I N C E 2 I N 3 0 M I N U T E S Issue definition A issue is: something that has happened or it will happen that was not planned. WILL HAS NO UNCERTAINTY
  • 20. P R I N C E 2 I N 3 0 M I N U T E S Quality PRODUCT DESCRIPTION Engine: petrol, 3.5L PROJECT PRODUCT DESCRIPTION PRODUCT DESCRIPTION Cream leather seats PRODUCT DESCRIPTION Tyres: Dunlop 245/40 R19 ACCEPTANCE CRITERIA 1. 0-60 mph in 3 seconds 2. Up to 2 years old 3. ‘What Car’ top 10 most desirable cars CUSTOMER QUALITY EXPECTATIONS 1.Fast Car 2.New Car 3.Flashy Car
  • 21. P R I N C E 2 I N 3 0 M I N U T E S Plans TIME & COST PROJECT PLAN e e e e
  • 22. P R I N C E 2 I N 3 0 M I N U T E S Authorize the project M A N D A T E C O R P O R A T E O R P R O G R A M M E M A N A G E M E N T Authorize a stage or exception plan Authorize project closure Authorize initiation MANAGING A STAGE BOUNDARY CLOSING A PROJECT CONTROLLING A STAGE MANAGING PRODUCT DELIVERY STARTING UP A PROJECT Executive & PM Outline business case PMT Project approach Project brief Initiation stage plan INITIATING A PROJECT Strategies & registers Project plan Business case Project Initiation Documentation (PID) DIRECTING A PROJECT PRINCE2 processes
  • 23. P R I N C E 2 I N 3 0 M I N U T E S Plans TIME & COST STAGE PLAN TIME & COST PROJECT PLAN e e e e e e e e
  • 24. P R I N C E 2 I N 3 0 M I N U T E S Authorize the project M A N D A T E C O R P O R A T E O R P R O G R A M M E M A N A G E M E N T Authorize a stage or exception plan Authorize project closure Authorize initiation Workpackage PM TM Checkpoint report PRINCE2 processes MANAGING A STAGE BOUNDARY Stage plan CLOSING A PROJECT CONTROLLING A STAGE MANAGING PRODUCT DELIVERY STARTING UP A PROJECT Executive & PM Outline business case PMT Project approach Project brief Initiation stage plan DIRECTING A PROJECT INITIATING A PROJECT Strategies & registers Project plan Business case Project Initiation Documentation (PID)
  • 25. P R I N C E 2 I N 3 0 M I N U T E S Authorize the project M A N D A T E C O R P O R A T E O R P R O G R A M M E M A N A G E M E N T Authorize a stage or exception plan Authorize project closure Authorize initiation Workpackage PM PRINCE2 processes MANAGING A STAGE BOUNDARY Stage plan CLOSING A PROJECT CONTROLLING A STAGE MANAGING PRODUCT DELIVERY STARTING UP A PROJECT Executive & PM Outline business case PMT Project approach Project brief Initiation stage plan DIRECTING A PROJECT INITIATING A PROJECT Strategies & registers Project plan Business case Project Initiation Documentation (PID)
  • 26. P R I N C E 2 I N 3 0 M I N U T E S Authorize the project M A N D A T E C O R P O R A T E O R P R O G R A M M E M A N A G E M E N T Authorize a stage or exception plan Authorize project closure Authorize initiation Workpackage PM TM PRINCE2 processes MANAGING A STAGE BOUNDARY Stage plan CLOSING A PROJECT CONTROLLING A STAGE MANAGING PRODUCT DELIVERY STARTING UP A PROJECT Executive & PM Outline business case PMT Project approach Project brief Initiation stage plan DIRECTING A PROJECT INITIATING A PROJECT Strategies & registers Project plan Business case Project Initiation Documentation (PID)
  • 27. P R I N C E 2 I N 3 0 M I N U T E S Plans TEAM PLAN WORKPACKAGE TIME & COST STAGE PLAN TIME & COST PROJECT PLAN e e e e e e e e
  • 28. P R I N C E 2 I N 3 0 M I N U T E S PRINCE2 processes Authorize the project M A N D A T E C O R P O R A T E O R P R O G R A M M E M A N A G E M E N T Authorize a stage or exception plan Authorize project closure Authorize initiation Workpackage PM TM MANAGING A STAGE BOUNDARY Stage plan CLOSING A PROJECT CONTROLLING A STAGE MANAGING PRODUCT DELIVERY STARTING UP A PROJECT Executive & PM Outline business case PMT Project approach Project brief Initiation stage plan DIRECTING A PROJECT Checkpoint report INITIATING A PROJECT Strategies & registers Project plan Business case Project Initiation Documentation (PID)
  • 29. P R I N C E 2 I N 3 0 M I N U T E S Progress – reporting P R O J E C T B O A R D S e n i o r u s e r E x e c u t i v e S e n i o r s u p p l i e r C O R P O R AT E O R P R O G R AM M E M AN A G E M E N T P R O J E C T M A N A G E R T E A M M A N A G E R H I G H L I G H T R E P O R T C H E C K P O I N T R E P O R T H I G H L I G H T R E P O R T
  • 30. P R I N C E 2 I N 3 0 M I N U T E S Progress – tolerances
  • 31. P R I N C E 2 I N 3 0 M I N U T E S Authorize the project C O R P O R A T E O R P R O G R A M M E M A N A G E M E N T Authorize a stage or exception plan Authorize project closure Authorize initiation Workpackage PM TM Checkpoint report MANAGING A STAGE BOUNDARY Stage plan Update: project plan business case End-stage report CLOSING A PROJECT CONTROLLING A STAGE Update Stage Plan MANAGING PRODUCT DELIVERY STARTING UP A PROJECT Executive & PM Outline business case PMT Project approach Project brief Initiation stage plan DIRECTING A PROJECT M A N D A T E PRINCE2 processes INITIATING A PROJECT Strategies & registers Project plan Business case Project Initiation Documentation (PID)
  • 32. P R I N C E 2 I N 3 0 M I N U T E S Authorize the project C O R P O R A T E O R P R O G R A M M E M A N A G E M E N T Authorize a stage or exception plan Authorize project closure Authorize initiation Workpackage PM TM Checkpoint report MANAGING A STAGE BOUNDARY Stage plan Update: project plan business case End-stage report CLOSING A PROJECT CONTROLLING A STAGE Update Stage Plan MANAGING PRODUCT DELIVERY STARTING UP A PROJECT Executive & PM Outline business case PMT Project approach Project brief Initiation stage plan DIRECTING A PROJECT M A N D A T E PRINCE2 processes INITIATING A PROJECT Strategies & registers Project plan Business case Project Initiation Documentation (PID)
  • 33. P R I N C E 2 I N 3 0 M I N U T E S Authorize the project C O R P O R A T E O R P R O G R A M M E M A N A G E M E N T Authorize a stage or exception plan Authorize project closure Authorize initiation Workpackage PM TM Checkpoint report MANAGING A STAGE BOUNDARY Stage plan Update: project plan business case End-stage report CLOSING A PROJECT CONTROLLING A STAGE Update Stage Plan MANAGING PRODUCT DELIVERY STARTING UP A PROJECT Executive & PM Outline business case PMT Project approach Project brief Initiation stage plan DIRECTING A PROJECT M A N D A T E PRINCE2 processes INITIATING A PROJECT Strategies & registers Project plan Business case Project Initiation Documentation (PID)
  • 34. P R I N C E 2 I N 3 0 M I N U T E S Authorize the project C O R P O R A T E O R P R O G R A M M E M A N A G E M E N T Authorize a stage or exception plan Authorize project closure Authorize initiation Workpackage PM TM Checkpoint report MANAGING A STAGE BOUNDARY Stage plan Update: project plan business case End-stage report CLOSING A PROJECT CONTROLLING A STAGE Update Stage Plan MANAGING PRODUCT DELIVERY STARTING UP A PROJECT Executive & PM Outline business case PMT Project approach Project brief Initiation stage plan DIRECTING A PROJECT M A N D A T E PRINCE2 processes INITIATING A PROJECT Strategies & registers Project plan Business case Project Initiation Documentation (PID)
  • 35. P R I N C E 2 I N 3 0 M I N U T E S Authorize the project M A N D A T E C O R P O R A T E O R P R O G R A M M E M A N A G E M E N T Authorize a stage or exception plan Authorize project closure Authorize initiation Workpackage PM TM Checkpoint report MANAGING A STAGE BOUNDARY Stage plan Update: project plan business case End-stage report CLOSING A PROJECT CONTROLLING A STAGE Update Stage Plan MANAGING PRODUCT DELIVERY STARTING UP A PROJECT Executive & PM Outline business case PMT Project approach Project brief Initiation stage plan Confirm all products are completed Evaluate the project Communication Archive project documentation PRINCE2 processes DIRECTING A PROJECT INITIATING A PROJECT Strategies & registers Project plan Business case Project Initiation Documentation (PID)
  • 36. P R I N C E 2 I N 3 0 M I N U T E S Authorize the project C O R P O R A T E O R P R O G R A M M E M A N A G E M E N T Authorize a stage or exception plan Authorize project closure Authorize initiation Workpackage Checkpoint report MANAGING A STAGE BOUNDARY Stage plan Update: project plan business case End-stage report CLOSING A PROJECT Confirm all products are completed Evaluate the project Communication Archive project documentation CONTROLLING A STAGE Update Stage Plan MANAGING PRODUCT DELIVERY STARTING UP A PROJECT Executive & PM Outline business case PMT Project approach Project brief Initiation stage plan PRINCE2 processes M A N D A T E DIRECTING A PROJECT INITIATING A PROJECT Strategies & registers Project plan Business case Project Initiation Documentation (PID)
  • 37. P R I N C E 2 I N 3 0 M I N U T E S During this session we have stepped through some of the basic concepts of PRINCE2 without overcomplicating it, and provided you with some quick, easy-to-use hints and tips. Easy to learn
  • 38. P R I N C E 2 I N 3 0 M I N U T E S Questions?
  • 39. P R I N C E 2 I N 3 0 M I N U T E S Why ILX? For more information about our courses, visit our website ilxgroup.com, give us a call on +44 (0) 1270 611 600 or send an email to: Individuals enquiries suzanne.bailey@ilxgroup.com Corporate enquiries paula.gower@ilxgroup.com
  • 40. P R I N C E 2 I N 3 0 M I N U T E S Recommended courses PRINCE2 Programme & Project Sponsorship APM Project Management Qualification Change Management
  • 41. P R I N C E 2 I N 3 0 M I N U T E S I L X G R O U P, U n i t e d K i n g d o m 7 t h F l o o r 9 5 A l d w y c h L o n d o n W C 2 B 4 J F - U K T: + 4 4 ( 0 ) 2 0 7 3 7 1 4 4 4 4 Thank you for listening I L X G R O U P, Au s t r a l i a 7 3 0 S p r i n g v a l e R d M u l g r a v e , V I C 3 1 7 0 A u s t r a l i a T: + 6 1 1 3 0 0 4 5 9 4 5 9 www.ilxgroup.com