Marine Corps
                      Seabasing
               “Assured Access for the 21st Century”
                        February 2013
                    (Excerpts focused on
                    Prepositioning Ships)




                                                          Jim Strock
                             Director, Seabasing Integration Division
                                    Headquarters, U.S. Marine Corps
                                  Combat Development & Integration
                                            Quantico, Virginia 22134
                                                        703-784-6094
UNCLASSIFIED                                james.strock@usmc.mil
Maritime Prepositioning Ships
 T- AKE                 LMSR




                                T- AK
             MLP




                                        2
MPF Enhancement Strategy

• Roll-on roll-off cargo ships, coupled with mobile landing
  platforms, provide key enabling capabilities to fully leverage
  existing MPS capabilities
   – Selective offload
       • Increased ship stowage capacity allows for reconfigured loads across
         MPSRON for selective offload
   – In-stream offload of Large, Medium Speed RO/RO (LMSR) with
     Mobile Landing Platform (MLP)
   – Increased connector lift capacity with MLP
   – Increased ship-to-shore throughput



        T-AKE                         LMSR                        MLP




                                                                                3
Mobile Landing Platform (MLP)

34 berths                                                              • LMSR skin-skin moored
                                      Skin-to-skin ramp                  alongside MLP
                                         and fenders
                                                                       • Vehicles transfer from LMSR to
                                                                         MLP via side port ramp and
                                                                         onto LCACs
                                                                       • LCACs maneuver forces ashore




Utility Services
  (limited) for
accommodation                                             FLO/FLO
barges/modules

                  25,000 ft2
               elevated vehicle
            stowage deck module                                                 Tankage capacities
                                                                             100,000 gal Potable Water/
                                  3 LCAC lanes                                    380,000 gal JP5
                                  with services            15 knots,
                                                           9,500 nm


                                                                                                          4
MPF Mobile Landing Platform
                                                                 (MLP)
                                                              Date Updated: 1-24-13


                             Platform                                                                Capability/Capacities
                                                                             Speed / Range / Life                15 Kts @ 85% MCR / 9,500 nm / 40 yrs
                                                                             Draft (Full)                        30.11 ft
                                                                             Crew                                34 MSC
                               LMSR                                          Embarked Landing Force / C2         - DSN, VOIP, SIPR, NIPR
                                                                             Surge                               - N/A
                                                                             Medical Capability                  - 258 ft2 (Isolation only)
                                                                             Mass Casualty/Receiving             - N/A
                                                                             Potable Water                       100,000 gal; 25,000 gal production per day
                                                                             Surface Interface Point             3
                                                                             Well Deck Capacity                  3 (limited service) LCAC spots / skin to skin fendering
                                                                             Flight Deck (Spots; Level, Class)   - (1) Operating Spot, USCG NCIV 9-81 Certified
                                                                             Elevators (Aircraft/Cargo)          - N/A
                                                                             Aircraft Parking (Hangar, etc)      - N/A
             MLP                                                             Ramp                                1 LMSR Veh side port; 1 Portable Veh access
                                                                                                                 25,000 ft2 exposed (Ro/Ro)
                                                                             Vehicle Square (Net) / Pre-boat
                                                                             Cargo Cube (Net)                    - N/A
                                                                             Lifting Capability (lbs)            (1) 11 ston mission crane, (2) 5.5 ston stores cranes
                                                                             Cargo Fuel (JP5)                    380,000 gal (LCAC Ops/Cargo fuel)
                                                                             Motor Gasoline                      - N/A
                                                                             Sea State Operations                Vehicle Transfer Sea State 3 (skin to skin)

                        Program Status                                                                   Planning Factors
• Employment of Forces: Will provide enhanced throughput capability           • PMS 385 Program Manager: CAPT Henry Stevens
  for the MPF. Will facilitate delivery of vehicles, equipment, personnel       henry.stevens@navy.mil Comm. # (202)781-1187
  and supplies between Sea base and restricted access location
  ashore.                                                                     • Develop a modified repeat design using the Alaska Class BP
• Compressed Acquisition planning:                                              tanker as parent.
  – Modify Capabilities Development Document (CDD) Increment 1                • Complete System Design in 5 months.
    • R3B MLP Flight 0 Program Strategy/Schedule/Funding (3 Dec 09)           • Maintain existing MLP contract with NASSCO to provide
    • CDD development/requirements finalization (4Dec09 – 20Jan10)              solution.
    • CDD Navy Staffing (5 Feb 10): plan for a single pass at 1-Star level    • Execute FY10 ($120M) to provide Long-lead material.
      with final comments submitted 21 days.
    • Gate 3 R3B late in (Apr 10).                                            • Three vessels are budgeted for in the PR-11 budget funding in
    • MLP OA (8-10 Aug 11, )                                                    FY11, and FY12. With the disestablishment of MPSRON 1, MLP
  – JROC approval of Inc 1 CDD revision by (Jun 10) to support FY10             3 will transition to an AFSB variant.
    AP and subsequent MLP construction award.                                 • MLP 1 and 2 contract award May 2011.
  – Milestone B (FY11) Production Readiness Review May 2011                   • MLP 1 currently 95% complete
• MLP 1 & MLP 2 are scheduled-available for tasking in FY15.                  • MLP 2 currently 37% complete
USNS Montford Point (MLP 1)




  Power Point: August 2009, Under Contract: May 2011
  Keel Laying: January 2012, Launch: November 2012     6
MPF T-AKE: Selective Offload
  Plus Operational Reach




                               7
Maritime Prepositioning
                           Capability
           MPSRON 2                                        MPSRON 3 GUAM
         DIEGO GARCIA                                         / SAIPAN


      LMSR                       LMSR                   LMSR                      LMSR
      SISLER                      SEAY                 DAHL                     PILILAAU

      LMSR                         T-AKE                                           T-AKE
                                                         T-AK
    STOCKHAM               LEWIS & CLARK              LUMMUS                   SACAGAWEA


       T-AK                        T-AK                  T-AK                      T-AK
     BUTTON                     LOPEZ                 WILLIAMS                   BOBO
                     % of MEB 30-day requirement                      % of MEB 30-day requirement
              MLP
                     Square feet            71%                 MLP
                                                                      Square feet            67%
                     20-foot containers     61%                       20-foot containers     67%
MONTFORD POINT       Fuel                   37%    GLENN (ROS)        Fuel                   50%
                     Water                  13%                       Water                  15%



  Average squadron capacity is 69% of MEB square-foot lift requirement

                                            UNCLASS                                                 8
Seabasing….So What’s Next?

                                   JLOTS




?                                  ?
            Integration of
        Joint, TRANSCOM &
      Multinational Capabilities

                                           9
                                           9

Prepositioning ships

  • 1.
    Marine Corps Seabasing “Assured Access for the 21st Century” February 2013 (Excerpts focused on Prepositioning Ships) Jim Strock Director, Seabasing Integration Division Headquarters, U.S. Marine Corps Combat Development & Integration Quantico, Virginia 22134 703-784-6094 UNCLASSIFIED james.strock@usmc.mil
  • 2.
    Maritime Prepositioning Ships T- AKE LMSR T- AK MLP 2
  • 3.
    MPF Enhancement Strategy •Roll-on roll-off cargo ships, coupled with mobile landing platforms, provide key enabling capabilities to fully leverage existing MPS capabilities – Selective offload • Increased ship stowage capacity allows for reconfigured loads across MPSRON for selective offload – In-stream offload of Large, Medium Speed RO/RO (LMSR) with Mobile Landing Platform (MLP) – Increased connector lift capacity with MLP – Increased ship-to-shore throughput T-AKE LMSR MLP 3
  • 4.
    Mobile Landing Platform(MLP) 34 berths • LMSR skin-skin moored Skin-to-skin ramp alongside MLP and fenders • Vehicles transfer from LMSR to MLP via side port ramp and onto LCACs • LCACs maneuver forces ashore Utility Services (limited) for accommodation FLO/FLO barges/modules 25,000 ft2 elevated vehicle stowage deck module Tankage capacities 100,000 gal Potable Water/ 3 LCAC lanes 380,000 gal JP5 with services 15 knots, 9,500 nm 4
  • 5.
    MPF Mobile LandingPlatform (MLP) Date Updated: 1-24-13 Platform Capability/Capacities Speed / Range / Life 15 Kts @ 85% MCR / 9,500 nm / 40 yrs Draft (Full) 30.11 ft Crew 34 MSC LMSR Embarked Landing Force / C2 - DSN, VOIP, SIPR, NIPR Surge - N/A Medical Capability - 258 ft2 (Isolation only) Mass Casualty/Receiving - N/A Potable Water 100,000 gal; 25,000 gal production per day Surface Interface Point 3 Well Deck Capacity 3 (limited service) LCAC spots / skin to skin fendering Flight Deck (Spots; Level, Class) - (1) Operating Spot, USCG NCIV 9-81 Certified Elevators (Aircraft/Cargo) - N/A Aircraft Parking (Hangar, etc) - N/A MLP Ramp 1 LMSR Veh side port; 1 Portable Veh access 25,000 ft2 exposed (Ro/Ro) Vehicle Square (Net) / Pre-boat Cargo Cube (Net) - N/A Lifting Capability (lbs) (1) 11 ston mission crane, (2) 5.5 ston stores cranes Cargo Fuel (JP5) 380,000 gal (LCAC Ops/Cargo fuel) Motor Gasoline - N/A Sea State Operations Vehicle Transfer Sea State 3 (skin to skin) Program Status Planning Factors • Employment of Forces: Will provide enhanced throughput capability • PMS 385 Program Manager: CAPT Henry Stevens for the MPF. Will facilitate delivery of vehicles, equipment, personnel henry.stevens@navy.mil Comm. # (202)781-1187 and supplies between Sea base and restricted access location ashore. • Develop a modified repeat design using the Alaska Class BP • Compressed Acquisition planning: tanker as parent. – Modify Capabilities Development Document (CDD) Increment 1 • Complete System Design in 5 months. • R3B MLP Flight 0 Program Strategy/Schedule/Funding (3 Dec 09) • Maintain existing MLP contract with NASSCO to provide • CDD development/requirements finalization (4Dec09 – 20Jan10) solution. • CDD Navy Staffing (5 Feb 10): plan for a single pass at 1-Star level • Execute FY10 ($120M) to provide Long-lead material. with final comments submitted 21 days. • Gate 3 R3B late in (Apr 10). • Three vessels are budgeted for in the PR-11 budget funding in • MLP OA (8-10 Aug 11, ) FY11, and FY12. With the disestablishment of MPSRON 1, MLP – JROC approval of Inc 1 CDD revision by (Jun 10) to support FY10 3 will transition to an AFSB variant. AP and subsequent MLP construction award. • MLP 1 and 2 contract award May 2011. – Milestone B (FY11) Production Readiness Review May 2011 • MLP 1 currently 95% complete • MLP 1 & MLP 2 are scheduled-available for tasking in FY15. • MLP 2 currently 37% complete
  • 6.
    USNS Montford Point(MLP 1) Power Point: August 2009, Under Contract: May 2011 Keel Laying: January 2012, Launch: November 2012 6
  • 7.
    MPF T-AKE: SelectiveOffload Plus Operational Reach 7
  • 8.
    Maritime Prepositioning Capability MPSRON 2 MPSRON 3 GUAM DIEGO GARCIA / SAIPAN LMSR LMSR LMSR LMSR SISLER SEAY DAHL PILILAAU LMSR T-AKE T-AKE T-AK STOCKHAM LEWIS & CLARK LUMMUS SACAGAWEA T-AK T-AK T-AK T-AK BUTTON LOPEZ WILLIAMS BOBO % of MEB 30-day requirement % of MEB 30-day requirement MLP Square feet 71% MLP Square feet 67% 20-foot containers 61% 20-foot containers 67% MONTFORD POINT Fuel 37% GLENN (ROS) Fuel 50% Water 13% Water 15% Average squadron capacity is 69% of MEB square-foot lift requirement UNCLASS 8
  • 9.
    Seabasing….So What’s Next? JLOTS ? ? Integration of Joint, TRANSCOM & Multinational Capabilities 9 9

Editor's Notes

  • #9 Achieving 80% of a MEB set on each MPSRONRequires more ships