Histories
 Power car are needed to proved power supply to End
On Generation type coaches in Indian railway.
 There was Single Engine power car of Rolls Royce
make diesel Engine with Lancashire make
Alternator.320BHP/300KVA
 Before 1992 There was twin Engine Power car of
Kirloskar Cummins Make Engine Rated for 235 BHP at
415Volt.
 After 1992 High capacity power car were introdused in
IR of Caterpillar and Cummins make rated 425 BHP at
750 volts.
FEEDER EARTH FAULT PROTECTED BY FEL
EXISTING SUPPLY ARRANGEMENT OF POWER CAR
Power supply arrangement
Two 500KVA Alternator feed power supply to EOG
coaches at 750 Volt independently.
200VA Instrument transformer are provided to supply
instrument like frequency meter , AEL , KW meter ect.
Alternator Earth leakage relay are provided to shut down
Engine in case of fault.
The ACB are provided to control Alternator out put supply.
Separate 60 KVA Transformer are provided to step down
750 volt to 415 volt for Radiator motor / Ventilation motor
operation .
Feeder contactor are provided to control out put from
power car, which is protected with Feeder Earth leakage
relay.
21.6 LTR,640BHP, RAIL USE 490BHP
GREAVES
ENGINE
CUMMINS ENGINE
19 LTR,600BHP, RAIL USE 490BHP
ENGINE
ACCESSORIES
AND
PARTS
OIL COOLER
GREAVES ENGINE CUMMINS ENGINE
COOLENT PUMP
GREAVES ENGINE CUMMINS ENGINE
TURBO CHARGER
GREAVES ENGINE CUMMINS ENGINE
AFTER COOLER
CUMMINS ENGINE
GREAVES ENGINE
FUEL PUMP
CUMMINS ENGINE
Greaves Engine Injector Pump
SPEED G0VERNOR
GREAVES ENGINE CUMMINS ENGINE
INJECTOR
CUMMINS ENGINE
GREAVES ENGINE
(Cracking of welding Pipe
line)
ECPG GEVERNOR
CUMMINS ENGINE
ELECTRONIC GEVERNER
SYSTEM
CYLINDER HEAD
CUMMINS ENGINE
GREAVES ENGINE
PISTON LINER
BY PASS FILTER
CUMMINS ENGINE
GREAVES ENGINE
SAFETY CUT OUTS
OVER SPEED CUT OUT
(CUNMMINS ENGINE)
SELECT MAKE MMR WITH
FEQUECY TRIPPING
LOP CUT OUT LOW COOLENT
LEVEL
1.5 BAR TRIPPING
ACB / UVR / ELR
1. Short circuit
2. IDMT and Overload
3. Earth Fault
400/380 VOIL 1.5 TO 2.5AMP
ALT ACB
CBCT
200 mA TRIPPING
CURRENT
ALTERNATER EARTH LEAKAGE RELAY
Earth leakage relay
S. No. Name of firms Settings
Secondary
Setting
Primary
1 M/s Design &
Prototype
600 µA 300mA
2 M/s Navago 20mA 1Amp
ALT ACB
CBCT
200mA TRIPPING
CURRENT
FEEDER EARTH LEAKAGE RELAY
FEEDER
CBCT
BUS COUPLER
SAFETY LOOP
Relay used for safety loop instead of
Darlington pair as used in conventional
Coaches (Micro switch problem)
SMOKE DETECTOR
PROVIDED OVER GREAVES ENGINE WITH FIRE BALL
Diesel oil consumption
Load Kw Lt /min Lt/ Hr
50 0.33 19.8
100 0.51 30.6
150 0.77 46.2
213 0.901 54.06
270 1.182 70.92
301 1.264 75.84
358 1.48 88.8
384 1.62 97.2
Lub oil Consumption
 Cummins Engine ,1 lt /72 Hrs working of Engine
 Greaves Engine , 1 lt /48 Hrs working of Engine
Problem to concentrate
 Ventilation Fan centre bolt, replacement of vent fan motor
Assy. WR modified end cover motor to give more strength.
 Greaves Radiator Base Frame.
 Greaves Engine monitoring gauges. Engine Monitoring
System(EMS).
 Exhaust Flexible bellow for greaves Engine.
 Over heating of Cables terminal.
 Lub oil consumption Greaves Engine.
 Fire prevention in Greaves Engine Compartment.
 Breakage of Crank shaft of Greaves Engine.
 Breakage of coupling of Greaves Engine.
Ventilation Fan assembly
Replaced End cover with flange
Alternator Crompton Greaves
Replacement of Greaves Coupling
with Cummins
Thermograph of Electrical system
Alternator supply incoming current
transformer terminal lug normal temperature is 30.80
˚ C ,Y phase temperature was 62.90 ˚ C of Y phase
,lug was loose –tighten the lug. (delta t=32.10 ˚ C)
NEUTRAL CURRENT
REACTOR
Block 3rd harmonic component
17.Excessive neutral current in power car
Trials were conducted and it was observed that about
100 Amp full load current was flowing in the neutral
feeder.
This was attributed to third harmonics generated by the
alternators as the loads are fully balanced.
A reactor was designed by KEL and placed in the
alternator circuit. The neutral current was reduced to 1.4
Amps only.
With this it was now possible to make the earth leakage
protection system fully functional. Earth faults were
created and the protection scheme was found to be fully
functional.
M/s KEL will supply these reactors to W Rly to be
provided on all power cars.
LIVE INSULATION MONITOR
INSULATION MONITORING DEVICE
•Insulation Monitoring Device is being provided in the Imported LHB Coaches, which
gives indication in case the insulation of the system is less than the preset value of the
device.
•Insulation measuring device monitors the insulation resistance of unearthed AC three
phase four wire AC .
•A measuring Special Hi frequency-low voltage is created in the device. One pole of
measuring device connected to the Star point and the other pole is connected to earth
through an electronic measuring circuit.
•These terminals are permanently monitored and in case of failure (when ohmic
insulation between mains and earth falls below the set value and closes the measuring
circuits) a signal LED flashes and a luminous display on the switch cabinet door is
activated.
Ensure Thermo Imaging of Power Panel on
Load
Check and ensure proper
cleaning of
radiators. Clean by water jet
machine 4.9-5.6
kg/cm2 (70-80 psi) with OGR
and ID-27 or
any other suitable cleaning agent
MAINTENANCE
SCHEDULE
Modifications :
Problem The Engine was not stopping when radiator motor
gets failed.
Solution The control Circuit was suitably modified to ensure
the engine tripping in the event of radiator motor
failure.
15.Isolation valve for diesel tank in power car
Diesel tank consists of two halves connected through a
pipe.
There has been a case were entire diesel has been
wasted due to damage to tank due to cattle run over.
Now a isolation valve has been provided in between the
two halves to avoid this waste of diesel in cases of
exigencies.
Now a days RCF providing Metal flexible pipe line in
place of rigid steel pipe line, which get chocked within
year as it is meant for water.
3 Interlocking of fire alarm with the trip circuit of
the breaker of DG sets
Two smoke detectors have been provided in the
power car. One in the engine portion and other in the
switch board cabinet. At present, on detection of
smoke, an alarm gets activated. It has not been
interlocked with the trip circuit of the breakers to shut
down the DG set.
POWER CAR.pptx
POWER CAR.pptx
POWER CAR.pptx
POWER CAR.pptx
POWER CAR.pptx
POWER CAR.pptx

More Related Content

What's hot

Train lighting system
Train lighting systemTrain lighting system
Train lighting system
siddhartha shukla
 
Lhb ac buffet car
Lhb ac buffet carLhb ac buffet car
Lhb ac buffet car
Ankur Mahajan
 
Northern western raiways ppt
Northern western raiways pptNorthern western raiways ppt
Northern western raiways ppt
Deepak singh Chauhan
 
Train lighting
Train lightingTrain lighting
Train lighting
Ankur Mahajan
 
Comparison and analysis of electrical motor used in Electric Vehicles..
Comparison and analysis of electrical motor used in Electric Vehicles..Comparison and analysis of electrical motor used in Electric Vehicles..
Comparison and analysis of electrical motor used in Electric Vehicles..
MANAS GILDER
 
Hybrid Electric Vehicle
Hybrid Electric VehicleHybrid Electric Vehicle
Hybrid Electric Vehicle
Om Prakash
 
Hybrid Electric Vehicle
Hybrid Electric VehicleHybrid Electric Vehicle
Hybrid Electric Vehicle
Neeraj Muralidharan
 
Train Lighting System Seminor Presentation
Train Lighting System Seminor PresentationTrain Lighting System Seminor Presentation
Train Lighting System Seminor Presentation
Akhil S
 
Presentation1.pptx
Presentation1.pptxPresentation1.pptx
Presentation1.pptx
Ankur Mahajan
 
SEMINAR ON HYBRID VEHICLE / ELECTRICVEHICLE TECHNOLOGY
SEMINAR ON HYBRID VEHICLE / ELECTRICVEHICLE TECHNOLOGY SEMINAR ON HYBRID VEHICLE / ELECTRICVEHICLE TECHNOLOGY
SEMINAR ON HYBRID VEHICLE / ELECTRICVEHICLE TECHNOLOGY
Avinash Repale
 
Parts of an Ev
Parts of an EvParts of an Ev
Parts of an Ev
Šâûřãv Vêřmâ
 
Presentaion on BHEL- Diesel Locomotive
Presentaion on BHEL- Diesel LocomotivePresentaion on BHEL- Diesel Locomotive
Presentaion on BHEL- Diesel LocomotiveAbhishek Agarwal
 
Northern railway
Northern railwayNorthern railway
Northern railway
sometech
 
Introduction to energy storage requirements in Hybrid and.pptx
Introduction to energy storage requirements in Hybrid and.pptxIntroduction to energy storage requirements in Hybrid and.pptx
Introduction to energy storage requirements in Hybrid and.pptx
AdwaithDinesh2
 
Electric Vehicle Concept and Power Management Strategies
Electric Vehicle Concept and Power Management StrategiesElectric Vehicle Concept and Power Management Strategies
Electric Vehicle Concept and Power Management Strategies
countoot
 
Railay internship report
Railay internship reportRailay internship report
Railay internship report
subham gahir
 
Hybrid Electric Vehicle Powertrain
Hybrid Electric Vehicle Powertrain Hybrid Electric Vehicle Powertrain
Hybrid Electric Vehicle Powertrain
Somraj Dasgupta
 
Hybrid Electric Vehicles
Hybrid Electric VehiclesHybrid Electric Vehicles
Hybrid Electric Vehicles
Colloquium
 
Railway summer training report electrical engineering
Railway summer training report electrical engineeringRailway summer training report electrical engineering
Railway summer training report electrical engineering
Yogesh Jadoun
 

What's hot (20)

Train lighting system
Train lighting systemTrain lighting system
Train lighting system
 
Lhb ac buffet car
Lhb ac buffet carLhb ac buffet car
Lhb ac buffet car
 
Northern western raiways ppt
Northern western raiways pptNorthern western raiways ppt
Northern western raiways ppt
 
Train lighting
Train lightingTrain lighting
Train lighting
 
Comparison and analysis of electrical motor used in Electric Vehicles..
Comparison and analysis of electrical motor used in Electric Vehicles..Comparison and analysis of electrical motor used in Electric Vehicles..
Comparison and analysis of electrical motor used in Electric Vehicles..
 
Hybrid Electric Vehicle
Hybrid Electric VehicleHybrid Electric Vehicle
Hybrid Electric Vehicle
 
Traction motor
Traction motorTraction motor
Traction motor
 
Hybrid Electric Vehicle
Hybrid Electric VehicleHybrid Electric Vehicle
Hybrid Electric Vehicle
 
Train Lighting System Seminor Presentation
Train Lighting System Seminor PresentationTrain Lighting System Seminor Presentation
Train Lighting System Seminor Presentation
 
Presentation1.pptx
Presentation1.pptxPresentation1.pptx
Presentation1.pptx
 
SEMINAR ON HYBRID VEHICLE / ELECTRICVEHICLE TECHNOLOGY
SEMINAR ON HYBRID VEHICLE / ELECTRICVEHICLE TECHNOLOGY SEMINAR ON HYBRID VEHICLE / ELECTRICVEHICLE TECHNOLOGY
SEMINAR ON HYBRID VEHICLE / ELECTRICVEHICLE TECHNOLOGY
 
Parts of an Ev
Parts of an EvParts of an Ev
Parts of an Ev
 
Presentaion on BHEL- Diesel Locomotive
Presentaion on BHEL- Diesel LocomotivePresentaion on BHEL- Diesel Locomotive
Presentaion on BHEL- Diesel Locomotive
 
Northern railway
Northern railwayNorthern railway
Northern railway
 
Introduction to energy storage requirements in Hybrid and.pptx
Introduction to energy storage requirements in Hybrid and.pptxIntroduction to energy storage requirements in Hybrid and.pptx
Introduction to energy storage requirements in Hybrid and.pptx
 
Electric Vehicle Concept and Power Management Strategies
Electric Vehicle Concept and Power Management StrategiesElectric Vehicle Concept and Power Management Strategies
Electric Vehicle Concept and Power Management Strategies
 
Railay internship report
Railay internship reportRailay internship report
Railay internship report
 
Hybrid Electric Vehicle Powertrain
Hybrid Electric Vehicle Powertrain Hybrid Electric Vehicle Powertrain
Hybrid Electric Vehicle Powertrain
 
Hybrid Electric Vehicles
Hybrid Electric VehiclesHybrid Electric Vehicles
Hybrid Electric Vehicles
 
Railway summer training report electrical engineering
Railway summer training report electrical engineeringRailway summer training report electrical engineering
Railway summer training report electrical engineering
 

Similar to POWER CAR.pptx

lift ppt
lift pptlift ppt
lift ppt
smartraja1991
 
Railway workshop jodhpur
Railway workshop jodhpurRailway workshop jodhpur
Railway workshop jodhpur
MAHESH SONI
 
Ramendra summer training presentation
Ramendra summer training presentationRamendra summer training presentation
Ramendra summer training presentationRamendra Dhiman
 
C.S.P.D.C.L.AMBIKAPUR (TOWN)
C.S.P.D.C.L.AMBIKAPUR (TOWN)C.S.P.D.C.L.AMBIKAPUR (TOWN)
C.S.P.D.C.L.AMBIKAPUR (TOWN)saurabhVEC
 
Electrical loco tripshed,sawai madhopur
Electrical loco tripshed,sawai madhopurElectrical loco tripshed,sawai madhopur
Electrical loco tripshed,sawai madhopur
Akash Karol
 
Shivesh ntpc ppt
Shivesh ntpc pptShivesh ntpc ppt
Shivesh ntpc ppt
Shivesh Sourabh
 
220 KV Substation Operation & Maintenance
220 KV Substation Operation & Maintenance220 KV Substation Operation & Maintenance
220 KV Substation Operation & Maintenance
Himansu Pradhan
 
fdocuments.in_presentation-on-substation-220-kv.pptx
fdocuments.in_presentation-on-substation-220-kv.pptxfdocuments.in_presentation-on-substation-220-kv.pptx
fdocuments.in_presentation-on-substation-220-kv.pptx
AkshaiSai2
 
J DJ
J DJJ DJ
J DJ
jjinesh
 
Summer Training Report Ntpc barh (ajeet)
Summer Training Report Ntpc barh (ajeet)Summer Training Report Ntpc barh (ajeet)
Summer Training Report Ntpc barh (ajeet)
Ajeet Chaurasia
 
132 kV uppcl
132 kV uppcl132 kV uppcl
132 kV uppcl
Abrar Ahamed
 
Ajay binay institute of technology,/ondvc
Ajay binay institute                                  of technology,/ondvcAjay binay institute                                  of technology,/ondvc
Ajay binay institute of technology,/ondvc
Mukesh Kumar
 
HarmonicFilter_VFDdrives2014
HarmonicFilter_VFDdrives2014HarmonicFilter_VFDdrives2014
HarmonicFilter_VFDdrives2014Kanai Banerjee
 
132 KV Grid Station Intern ship training report
132 KV Grid Station Intern ship training report132 KV Grid Station Intern ship training report
132 KV Grid Station Intern ship training report
Muntazir Mehdi
 
Durgapur Projects Limited: Vocational training presentation
Durgapur Projects Limited: Vocational training presentationDurgapur Projects Limited: Vocational training presentation
Durgapur Projects Limited: Vocational training presentation
Saumyadip Moitra
 
A PPT ON 220 KV GSS HINDAUN CITY
A PPT ON 220 KV GSS HINDAUN CITYA PPT ON 220 KV GSS HINDAUN CITY
A PPT ON 220 KV GSS HINDAUN CITY
Rohitashav Goyal
 
ppt on summer training on uppcl
ppt on summer training on uppclppt on summer training on uppcl
ppt on summer training on uppcl
Sunny Daksh
 
ABB Price List of Capacitors 008
ABB Price List of Capacitors 008ABB Price List of Capacitors 008
ABB Price List of Capacitors 008
R Sanghavi Mercantile Pvt Ltd
 
Mitsubishi inverter freqrol-hc2 series dienhathe.vn
Mitsubishi inverter freqrol-hc2 series dienhathe.vnMitsubishi inverter freqrol-hc2 series dienhathe.vn
Mitsubishi inverter freqrol-hc2 series dienhathe.vn
Dien Ha The
 

Similar to POWER CAR.pptx (20)

lift ppt
lift pptlift ppt
lift ppt
 
Railway workshop jodhpur
Railway workshop jodhpurRailway workshop jodhpur
Railway workshop jodhpur
 
Ramendra summer training presentation
Ramendra summer training presentationRamendra summer training presentation
Ramendra summer training presentation
 
C.S.P.D.C.L.AMBIKAPUR (TOWN)
C.S.P.D.C.L.AMBIKAPUR (TOWN)C.S.P.D.C.L.AMBIKAPUR (TOWN)
C.S.P.D.C.L.AMBIKAPUR (TOWN)
 
Electrical loco tripshed,sawai madhopur
Electrical loco tripshed,sawai madhopurElectrical loco tripshed,sawai madhopur
Electrical loco tripshed,sawai madhopur
 
Shivesh ntpc ppt
Shivesh ntpc pptShivesh ntpc ppt
Shivesh ntpc ppt
 
220 KV Substation Operation & Maintenance
220 KV Substation Operation & Maintenance220 KV Substation Operation & Maintenance
220 KV Substation Operation & Maintenance
 
fdocuments.in_presentation-on-substation-220-kv.pptx
fdocuments.in_presentation-on-substation-220-kv.pptxfdocuments.in_presentation-on-substation-220-kv.pptx
fdocuments.in_presentation-on-substation-220-kv.pptx
 
J DJ
J DJJ DJ
J DJ
 
Summer Training Report Ntpc barh (ajeet)
Summer Training Report Ntpc barh (ajeet)Summer Training Report Ntpc barh (ajeet)
Summer Training Report Ntpc barh (ajeet)
 
132 kV uppcl
132 kV uppcl132 kV uppcl
132 kV uppcl
 
Ajay binay institute of technology,/ondvc
Ajay binay institute                                  of technology,/ondvcAjay binay institute                                  of technology,/ondvc
Ajay binay institute of technology,/ondvc
 
HarmonicFilter_VFDdrives2014
HarmonicFilter_VFDdrives2014HarmonicFilter_VFDdrives2014
HarmonicFilter_VFDdrives2014
 
132 KV Grid Station Intern ship training report
132 KV Grid Station Intern ship training report132 KV Grid Station Intern ship training report
132 KV Grid Station Intern ship training report
 
Durgapur Projects Limited: Vocational training presentation
Durgapur Projects Limited: Vocational training presentationDurgapur Projects Limited: Vocational training presentation
Durgapur Projects Limited: Vocational training presentation
 
A PPT ON 220 KV GSS HINDAUN CITY
A PPT ON 220 KV GSS HINDAUN CITYA PPT ON 220 KV GSS HINDAUN CITY
A PPT ON 220 KV GSS HINDAUN CITY
 
ppt on summer training on uppcl
ppt on summer training on uppclppt on summer training on uppcl
ppt on summer training on uppcl
 
V.T ppt
V.T pptV.T ppt
V.T ppt
 
ABB Price List of Capacitors 008
ABB Price List of Capacitors 008ABB Price List of Capacitors 008
ABB Price List of Capacitors 008
 
Mitsubishi inverter freqrol-hc2 series dienhathe.vn
Mitsubishi inverter freqrol-hc2 series dienhathe.vnMitsubishi inverter freqrol-hc2 series dienhathe.vn
Mitsubishi inverter freqrol-hc2 series dienhathe.vn
 

Recently uploaded

Cosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdfCosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdf
Kamal Acharya
 
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&BDesign and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Sreedhar Chowdam
 
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Dr.Costas Sachpazis
 
AP LAB PPT.pdf ap lab ppt no title specific
AP LAB PPT.pdf ap lab ppt no title specificAP LAB PPT.pdf ap lab ppt no title specific
AP LAB PPT.pdf ap lab ppt no title specific
BrazilAccount1
 
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdfTop 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Teleport Manpower Consultant
 
Standard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - NeometrixStandard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - Neometrix
Neometrix_Engineering_Pvt_Ltd
 
space technology lecture notes on satellite
space technology lecture notes on satellitespace technology lecture notes on satellite
space technology lecture notes on satellite
ongomchris
 
MCQ Soil mechanics questions (Soil shear strength).pdf
MCQ Soil mechanics questions (Soil shear strength).pdfMCQ Soil mechanics questions (Soil shear strength).pdf
MCQ Soil mechanics questions (Soil shear strength).pdf
Osamah Alsalih
 
HYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generationHYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generation
Robbie Edward Sayers
 
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdfHybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
fxintegritypublishin
 
Gen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdfGen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdf
gdsczhcet
 
J.Yang, ICLR 2024, MLILAB, KAIST AI.pdf
J.Yang,  ICLR 2024, MLILAB, KAIST AI.pdfJ.Yang,  ICLR 2024, MLILAB, KAIST AI.pdf
J.Yang, ICLR 2024, MLILAB, KAIST AI.pdf
MLILAB
 
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdfAKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
SamSarthak3
 
Hierarchical Digital Twin of a Naval Power System
Hierarchical Digital Twin of a Naval Power SystemHierarchical Digital Twin of a Naval Power System
Hierarchical Digital Twin of a Naval Power System
Kerry Sado
 
Runway Orientation Based on the Wind Rose Diagram.pptx
Runway Orientation Based on the Wind Rose Diagram.pptxRunway Orientation Based on the Wind Rose Diagram.pptx
Runway Orientation Based on the Wind Rose Diagram.pptx
SupreethSP4
 
Architectural Portfolio Sean Lockwood
Architectural Portfolio Sean LockwoodArchitectural Portfolio Sean Lockwood
Architectural Portfolio Sean Lockwood
seandesed
 
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
ydteq
 
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptxCFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
R&R Consult
 
ML for identifying fraud using open blockchain data.pptx
ML for identifying fraud using open blockchain data.pptxML for identifying fraud using open blockchain data.pptx
ML for identifying fraud using open blockchain data.pptx
Vijay Dialani, PhD
 
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
obonagu
 

Recently uploaded (20)

Cosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdfCosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdf
 
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&BDesign and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
 
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
 
AP LAB PPT.pdf ap lab ppt no title specific
AP LAB PPT.pdf ap lab ppt no title specificAP LAB PPT.pdf ap lab ppt no title specific
AP LAB PPT.pdf ap lab ppt no title specific
 
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdfTop 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
 
Standard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - NeometrixStandard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - Neometrix
 
space technology lecture notes on satellite
space technology lecture notes on satellitespace technology lecture notes on satellite
space technology lecture notes on satellite
 
MCQ Soil mechanics questions (Soil shear strength).pdf
MCQ Soil mechanics questions (Soil shear strength).pdfMCQ Soil mechanics questions (Soil shear strength).pdf
MCQ Soil mechanics questions (Soil shear strength).pdf
 
HYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generationHYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generation
 
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdfHybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
 
Gen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdfGen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdf
 
J.Yang, ICLR 2024, MLILAB, KAIST AI.pdf
J.Yang,  ICLR 2024, MLILAB, KAIST AI.pdfJ.Yang,  ICLR 2024, MLILAB, KAIST AI.pdf
J.Yang, ICLR 2024, MLILAB, KAIST AI.pdf
 
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdfAKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
 
Hierarchical Digital Twin of a Naval Power System
Hierarchical Digital Twin of a Naval Power SystemHierarchical Digital Twin of a Naval Power System
Hierarchical Digital Twin of a Naval Power System
 
Runway Orientation Based on the Wind Rose Diagram.pptx
Runway Orientation Based on the Wind Rose Diagram.pptxRunway Orientation Based on the Wind Rose Diagram.pptx
Runway Orientation Based on the Wind Rose Diagram.pptx
 
Architectural Portfolio Sean Lockwood
Architectural Portfolio Sean LockwoodArchitectural Portfolio Sean Lockwood
Architectural Portfolio Sean Lockwood
 
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
 
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptxCFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
 
ML for identifying fraud using open blockchain data.pptx
ML for identifying fraud using open blockchain data.pptxML for identifying fraud using open blockchain data.pptx
ML for identifying fraud using open blockchain data.pptx
 
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
 

POWER CAR.pptx

  • 2. Histories  Power car are needed to proved power supply to End On Generation type coaches in Indian railway.  There was Single Engine power car of Rolls Royce make diesel Engine with Lancashire make Alternator.320BHP/300KVA  Before 1992 There was twin Engine Power car of Kirloskar Cummins Make Engine Rated for 235 BHP at 415Volt.  After 1992 High capacity power car were introdused in IR of Caterpillar and Cummins make rated 425 BHP at 750 volts.
  • 3. FEEDER EARTH FAULT PROTECTED BY FEL EXISTING SUPPLY ARRANGEMENT OF POWER CAR
  • 4. Power supply arrangement Two 500KVA Alternator feed power supply to EOG coaches at 750 Volt independently. 200VA Instrument transformer are provided to supply instrument like frequency meter , AEL , KW meter ect. Alternator Earth leakage relay are provided to shut down Engine in case of fault. The ACB are provided to control Alternator out put supply. Separate 60 KVA Transformer are provided to step down 750 volt to 415 volt for Radiator motor / Ventilation motor operation . Feeder contactor are provided to control out put from power car, which is protected with Feeder Earth leakage relay.
  • 5. 21.6 LTR,640BHP, RAIL USE 490BHP GREAVES ENGINE
  • 8. OIL COOLER GREAVES ENGINE CUMMINS ENGINE
  • 12. FUEL PUMP CUMMINS ENGINE Greaves Engine Injector Pump
  • 19. BY PASS FILTER CUMMINS ENGINE GREAVES ENGINE
  • 21. OVER SPEED CUT OUT (CUNMMINS ENGINE) SELECT MAKE MMR WITH FEQUECY TRIPPING
  • 22. LOP CUT OUT LOW COOLENT LEVEL 1.5 BAR TRIPPING
  • 23. ACB / UVR / ELR 1. Short circuit 2. IDMT and Overload 3. Earth Fault 400/380 VOIL 1.5 TO 2.5AMP
  • 24. ALT ACB CBCT 200 mA TRIPPING CURRENT ALTERNATER EARTH LEAKAGE RELAY
  • 25. Earth leakage relay S. No. Name of firms Settings Secondary Setting Primary 1 M/s Design & Prototype 600 µA 300mA 2 M/s Navago 20mA 1Amp
  • 26. ALT ACB CBCT 200mA TRIPPING CURRENT FEEDER EARTH LEAKAGE RELAY FEEDER CBCT BUS COUPLER
  • 27. SAFETY LOOP Relay used for safety loop instead of Darlington pair as used in conventional Coaches (Micro switch problem)
  • 28. SMOKE DETECTOR PROVIDED OVER GREAVES ENGINE WITH FIRE BALL
  • 29.
  • 30.
  • 31. Diesel oil consumption Load Kw Lt /min Lt/ Hr 50 0.33 19.8 100 0.51 30.6 150 0.77 46.2 213 0.901 54.06 270 1.182 70.92 301 1.264 75.84 358 1.48 88.8 384 1.62 97.2
  • 32. Lub oil Consumption  Cummins Engine ,1 lt /72 Hrs working of Engine  Greaves Engine , 1 lt /48 Hrs working of Engine
  • 33. Problem to concentrate  Ventilation Fan centre bolt, replacement of vent fan motor Assy. WR modified end cover motor to give more strength.  Greaves Radiator Base Frame.  Greaves Engine monitoring gauges. Engine Monitoring System(EMS).  Exhaust Flexible bellow for greaves Engine.  Over heating of Cables terminal.  Lub oil consumption Greaves Engine.  Fire prevention in Greaves Engine Compartment.  Breakage of Crank shaft of Greaves Engine.  Breakage of coupling of Greaves Engine.
  • 34. Ventilation Fan assembly Replaced End cover with flange
  • 35. Alternator Crompton Greaves Replacement of Greaves Coupling with Cummins
  • 37. Alternator supply incoming current transformer terminal lug normal temperature is 30.80 ˚ C ,Y phase temperature was 62.90 ˚ C of Y phase ,lug was loose –tighten the lug. (delta t=32.10 ˚ C)
  • 38. NEUTRAL CURRENT REACTOR Block 3rd harmonic component
  • 39. 17.Excessive neutral current in power car Trials were conducted and it was observed that about 100 Amp full load current was flowing in the neutral feeder. This was attributed to third harmonics generated by the alternators as the loads are fully balanced. A reactor was designed by KEL and placed in the alternator circuit. The neutral current was reduced to 1.4 Amps only. With this it was now possible to make the earth leakage protection system fully functional. Earth faults were created and the protection scheme was found to be fully functional. M/s KEL will supply these reactors to W Rly to be provided on all power cars.
  • 41. INSULATION MONITORING DEVICE •Insulation Monitoring Device is being provided in the Imported LHB Coaches, which gives indication in case the insulation of the system is less than the preset value of the device. •Insulation measuring device monitors the insulation resistance of unearthed AC three phase four wire AC . •A measuring Special Hi frequency-low voltage is created in the device. One pole of measuring device connected to the Star point and the other pole is connected to earth through an electronic measuring circuit. •These terminals are permanently monitored and in case of failure (when ohmic insulation between mains and earth falls below the set value and closes the measuring circuits) a signal LED flashes and a luminous display on the switch cabinet door is activated.
  • 42. Ensure Thermo Imaging of Power Panel on Load Check and ensure proper cleaning of radiators. Clean by water jet machine 4.9-5.6 kg/cm2 (70-80 psi) with OGR and ID-27 or any other suitable cleaning agent MAINTENANCE SCHEDULE
  • 43.
  • 44.
  • 45.
  • 46.
  • 47. Modifications : Problem The Engine was not stopping when radiator motor gets failed. Solution The control Circuit was suitably modified to ensure the engine tripping in the event of radiator motor failure.
  • 48. 15.Isolation valve for diesel tank in power car Diesel tank consists of two halves connected through a pipe. There has been a case were entire diesel has been wasted due to damage to tank due to cattle run over. Now a isolation valve has been provided in between the two halves to avoid this waste of diesel in cases of exigencies. Now a days RCF providing Metal flexible pipe line in place of rigid steel pipe line, which get chocked within year as it is meant for water.
  • 49.
  • 50. 3 Interlocking of fire alarm with the trip circuit of the breaker of DG sets Two smoke detectors have been provided in the power car. One in the engine portion and other in the switch board cabinet. At present, on detection of smoke, an alarm gets activated. It has not been interlocked with the trip circuit of the breakers to shut down the DG set.