SlideShare a Scribd company logo
……………………………………………………………. 
……………………………………. 
……………………………… 
,,,,,,,,,,,,,,,,,,, 
,,,,,,,,,,
REPORT ON 
DAMODAR VALLEY CORPORATION 
AT C.T.P.S
1
Dvc at c.t.p.s was started in 1964 as the only power 
plant with three bus bar.it consists of six 
units(presentely only three are in working). 
The plant is situated on the banks of the damodar 
river which is about 3kms away from hindustan 
steels dugda washery. 
Total Installed capacity of ctps is 780MW. 
Three working units are each of 140MW rating and 
the other are of 120MW.
Mission:- 
Flood control and irrigation. 
Generation,transmission and distribution. 
Eco-conservation and a forestation. 
Water supply for industrial and domestic use. 
Vision:- 
To establish DVC as a mega pithead power producer and 
distributor in eastern region.
Coal and ash handling plant 
Coal and ash handling plant 
Boiler 
Super heater 
Economize 
Airpreheater 
Steam Turbine 
Condenser 
Cooling tower 
Feed water heater 
Alternator 
Exciter 
ElEelcetcrotr sot asttiact picr epcriepcaitpoartor 
Boiler 
Super heater 
Economize 
Airpreheater 
Steam Turbine 
Condenser 
Cooling tower 
Feed water heater 
Alternator 
Exciter
No.of the 
units 
Installed 
capacity 
De rated 
Capacity 
Unit No.1 140 MW 130 MW 
Unit No.2 140 MW 130 MW 
Unit No.3 140 MW 130 MW 
Unit No.4 120 MW 120 MW 
Unit No.5 120 MW 120 MW 
Unit No.6 120 MW 120 MW 
TOTAL 780 MW 750 MW 
Capacity 
(MW) 
rated 
First 
synchroni 
sing dates 
Make of 
Boiler 
Make of 
turbo 
Generator 
140 10-10-1964 Combustion 
engg,USA 
GE,USA 
140 01-05-1965 Combustion 
engg,USA 
GE,USA 
140 10-07-1968 Combustion 
engg,USA 
GE,USA 
120 02-03-1974 ACC 
Backcock Ltd 
,India 
BHEL, India 
120 28-03-1975 ACC 
backcock 
Ltd,India 
BHEL, India 
120 29-03-1979 ACC 
backcock 
Ltd,India 
BHEL, 
India
GENERATOR NOS. 1,2 and 3; 
Rating : 165000 KVA Power factor : 0.85 
Excitation : 375 Volts Frequency : 50 Hz 
ATP : 2 poles Gas pressure : 30 PSI 
Seal oil pressure : 2.3 kg/cm2 Diff.pressure : 0.35 kg/cm2 
Starter Amp : 6351 Field Amp : 1220 
Short circuit ratio : 0.7 Coolant :hydrogen 
Connection : (Y) for 15000 and165 KVA Maker :general electric co. (U.S.A) 
GENERATOR NOS.4,5 and 6; 
Rating : 141176 KVA Power factor : 0.85 
Excitation : 433 Volts,1730amps Frequency : 50 Hz 
Revolution : 3000 RPM Gas pressure : 2.1 kg/cm2 
Startor rating : 138 kv Stator amps : 5906 
Connection : (Y) for138000volts and 141176 KVA Phase : 3 
Coolant :hydrogen Maker 
:BHEL,(BHOPAL),INDIA
TURBINE NOS. 1,2 and 3 : 
Rating : 140000 Kw RPM : 3000 
Steam condition pressure : 1800 Stage : 26 
PSIG Temperature : 1000 degree F Rheat temperature : 1000 degree F 
Exhaust pressure : 25 degree Hg 
Phase : 3 
ABS 
Frequency : 50 Hz Power factor : 0.85 
Turbine No. : 170*124 Maker :general electric co. (U.S.A) 
TURBINE NOS. 4 ,5 and 6 : 
Rating : 120000 Kw Power factor : 0.85 
KVA :141176 Excitation : 433 volts and 1730amps 
Stator :138000 volts and 5906 amps Connection and RPM : Y and 3000 
Phase : 3 Frequency : 50 Hz 
Type : Turbo Coolant :hydrogen 
Gas pressure :2.1 kg/cm3 Maker :BHEL,(BHOPAL),INDIA
1 
1.COAL HANDLING PLANT 
Coal is required in the power house to generate heat so that steam can be generated in 
the power house . to generate from row coal boulders into powered form coal handling 
plant is required. 
ROUTE 
1.By road 
2.Rail 
•Size of coal is 20mm
1 
Crusher house 
Wagon tippler and 
Coal bunker Coal mill 
Coal handling plant 
weigh bridge 
Coal (thru rake) 
furnance
BOILER 
AUXILIARY 
TURBINE 
AUXILIARY 
GENERATOR 
AUXILIARY 
F.D FANS DEAERATOR SEAL OIL SYSTEM 
I.D FANS HOTWELL HYDROGEN COOLING 
SYSTEM 
BOILER DRUM BOILER FEED PUMP GENERATOR 
TRANSFORMER 
COAL MILLS CONDENSATE PUMP 
COAL FEEDERS LOW PRESSURE AND 
HIGH PRESSURE HEATER
switching equipment used in the transmission of electricity. 
Apart from main bus bar two duplicate buses are provided in 
the switchyard . They are used when there is some fault in the 
mai bus bar or some maintenace work is to be done in the main 
bus bar. 
The three bus used in DVC are: 
1. 33kv 
2. 132kv 
3. 220kv 
All the generating eguiptments- transformer,generator etc. 
are connected to the main bus bar under normal conditions 
But when fault occurs the supply is transferred to the 
transfer bus with the help of isolators. 
Two bus are connected to each other by the bus coupler. 
Jumpers are provided in the switch yard to move the wires 
either up or down in the yard.
DVC suplies bulk power at 33kv,132kv,220kv through a network covering 
more than 5500 circuit kilometers. 
The dvc grid is interconnected with the state electricity boardof jharkhand 
(JSEB),west bengal(WBSEB) and grid corporation of orissa and power grid 
corporation of India Ltd. 
Existing Links(Ckt kms) 
state 33kv 132kv 220kv 
Jharkhand 690 2175 898 
West Bengal 380 1240 560 
Orissa 42 
TOTAL 1070 3415 1500 
Existing Sub-stations(Nos.) 
State 33kv 132kv 220kv 
Jharkhand 9 21 7 
West Bengal 7 12 4 
TOTAL 16 33 11
Circuit Breakers 
1. SF6 type circuit breaker (132) 
2. Minimum oil circuit breaker(132) 
•Circuit Breakers 
1. SF6 type circuit breaker (132) 
2. Minimum oil circuit breaker(132) 
3. Vaccum circuit breaker(33kv) 
Lightning arresters 
Fuse 
Load interrupter 
Line isolator 
relays 
3. Vaccum circuit breaker(33kv) 
Lightning arresters 
Fuse 
Load interrupter 
Line isolator 
relays
. 
INTERLOCKING SYSTEM 
Interlocking system is such type of system by which 
the machine is shut down automatically for 
preventing any loss when the process is not running 
properly or under any abnormal condition .inter lock 
is used in 
many system present in the power house . 
The interlocking system is mainly used in three 
portion of the plant ; 
1.Boiler feed pump 
2.Generator seal oil pump interlock 
3.Turbine bearing oil pump
coal 
storage 
Coal 
hand 
ling 
Plant 
Boile 
r 
Ash 
Storage 
Ash 
Handli 
ng 
plant 
Air pre-heater 
Flue gases 
Econo 
miser 
Super 
heater 
turb 
ine 
R 
Y 
B 
exciter 
condenser 
Colling 
tower 
+ 
Alternator 
Induced 
draught fan chimney 
Force draught fan 
Feed water heater 
Water treatment 
chamber 
Feed water pump 
Flue gases 
Transformer 
Exhaust steam 
Valve 
Circulating water 
pump 
Hot air 
Flue gases 
Bus Bar 
C.B
. 
TRANSFORMERS IN POWER SYSTEM 
1.Generating Transformer(GT) 
It is transformer on which generating terminal voltage is given. It is a set-up 
transformer responsible for stepping up the generated voltage to the required 
voltage in the switchyard which may be either 132kv or 220 k v .after stepping 
up the voltage the power is given to the main bus bar which runs horizontally 
in centre throughout a switchyard now from this main bus the electricity is 
now ready to distributed to different sub station or direct consumer. 
2.Unit Auxiliary Transformer (UAT) 
UAT is a step down transformer which is connected to G.T so it step down the 
voltage from 132 or 22okv to the required voltage near about 3.5kv.It is used for 
providing the require power for the auxiliary unit like coal handling plant , 
coal mil, boiler feedback pump e tc. generally two UAT are connected to on 
G.T
1 
3.Reserve transformer 
In power house there is probability that the G.T can develop some fault or has to be 
closed for maintenance in that case the auxiliary unit supply is to be pulled off which 
is connected to G.T .this will interrupt in the working of the plant .R.T are present in 
the power house to supply power to auxiliary unit .R.T has two teminals; 
1.Common auxiliary board (CAB) 
2.Startup emergency board (SEB) 
( responsible for providing the power ) 
Apart from these three transformer there are two other types of transformer ; 
Potential transformer 
Current transformer
Ajay binay institute                                  of technology,/ondvc
Ajay binay institute                                  of technology,/ondvc

More Related Content

What's hot

J D J
J D JJ D J
J D J
jjinesh
 
The Excitation system by SAI
The Excitation system by SAIThe Excitation system by SAI
The Excitation system by SAI
Sai Divvela
 
Vocational Training Report (Rajdhani Express)
Vocational Training Report (Rajdhani Express)Vocational Training Report (Rajdhani Express)
Vocational Training Report (Rajdhani Express)
shovandey07
 
Effects of Reversing Generator Armature Reaction in Electric Power Generation
Effects of Reversing Generator Armature Reaction in Electric Power GenerationEffects of Reversing Generator Armature Reaction in Electric Power Generation
Effects of Reversing Generator Armature Reaction in Electric Power Generation
Thane Heins Regenerative Acceleration Generator Technology
 
trisuli hydropower nepal
trisuli hydropower nepaltrisuli hydropower nepal
trisuli hydropower nepal
surendra purbey
 
A PPT ON 220 KV GSS HINDAUN CITY
A PPT ON 220 KV GSS HINDAUN CITYA PPT ON 220 KV GSS HINDAUN CITY
A PPT ON 220 KV GSS HINDAUN CITY
Rohitashav Goyal
 
UET Power House Internship Report
UET Power House Internship ReportUET Power House Internship Report
UET Power House Internship ReportMudasSir Rahim
 
220 kV GSS Mansarovar Jaipur (RVPNL) Training Report SM54
220 kV GSS Mansarovar Jaipur (RVPNL) Training Report SM54220 kV GSS Mansarovar Jaipur (RVPNL) Training Report SM54
220 kV GSS Mansarovar Jaipur (RVPNL) Training Report SM54
Subhash Mahla
 
power transformer and its usage
power transformer and its usage power transformer and its usage
power transformer and its usage
gourav1245
 
Vocational Training Report ( Sealdah Power House)
Vocational Training Report ( Sealdah Power House)Vocational Training Report ( Sealdah Power House)
Vocational Training Report ( Sealdah Power House)
shovandey07
 
220 66 kv nrs sub report
220 66 kv nrs sub report220 66 kv nrs sub report
220 66 kv nrs sub report
Mayur Dhanaji Rane
 
Seminar report theory
Seminar report theorySeminar report theory
Seminar report theory
Ranjan kumar
 
Lhb ac buffet car
Lhb ac buffet carLhb ac buffet car
Lhb ac buffet car
Ankur Mahajan
 
Alternator excitation systems
Alternator excitation systemsAlternator excitation systems
Alternator excitation systems
MD AlBeruni
 
J DJ
J DJJ DJ
J DJ
jjinesh
 
Internship Report
Internship Report Internship Report
Internship Report
Muhammad Usman Rafiq
 
KBUNL - NTPC KANTI MUZAFFARPUR BIHAR
KBUNL - NTPC KANTI MUZAFFARPUR BIHARKBUNL - NTPC KANTI MUZAFFARPUR BIHAR
KBUNL - NTPC KANTI MUZAFFARPUR BIHAR
VIMAL VAIBHAV
 
3 Prototype #3 EV Regenerative Acceleration (ReGenX) eBike Integration Protot...
3 Prototype #3 EV Regenerative Acceleration (ReGenX) eBike Integration Protot...3 Prototype #3 EV Regenerative Acceleration (ReGenX) eBike Integration Protot...
3 Prototype #3 EV Regenerative Acceleration (ReGenX) eBike Integration Protot...
Thane Heins Regenerative Acceleration Generator Technology
 
Ranjan NTPC KAHALGAON ppt
Ranjan  NTPC KAHALGAON pptRanjan  NTPC KAHALGAON ppt
Ranjan NTPC KAHALGAON ppt
Ranjan kumar
 

What's hot (20)

J D J
J D JJ D J
J D J
 
The Excitation system by SAI
The Excitation system by SAIThe Excitation system by SAI
The Excitation system by SAI
 
Vocational Training Report (Rajdhani Express)
Vocational Training Report (Rajdhani Express)Vocational Training Report (Rajdhani Express)
Vocational Training Report (Rajdhani Express)
 
Effects of Reversing Generator Armature Reaction in Electric Power Generation
Effects of Reversing Generator Armature Reaction in Electric Power GenerationEffects of Reversing Generator Armature Reaction in Electric Power Generation
Effects of Reversing Generator Armature Reaction in Electric Power Generation
 
trisuli hydropower nepal
trisuli hydropower nepaltrisuli hydropower nepal
trisuli hydropower nepal
 
A PPT ON 220 KV GSS HINDAUN CITY
A PPT ON 220 KV GSS HINDAUN CITYA PPT ON 220 KV GSS HINDAUN CITY
A PPT ON 220 KV GSS HINDAUN CITY
 
ntpc
ntpcntpc
ntpc
 
UET Power House Internship Report
UET Power House Internship ReportUET Power House Internship Report
UET Power House Internship Report
 
220 kV GSS Mansarovar Jaipur (RVPNL) Training Report SM54
220 kV GSS Mansarovar Jaipur (RVPNL) Training Report SM54220 kV GSS Mansarovar Jaipur (RVPNL) Training Report SM54
220 kV GSS Mansarovar Jaipur (RVPNL) Training Report SM54
 
power transformer and its usage
power transformer and its usage power transformer and its usage
power transformer and its usage
 
Vocational Training Report ( Sealdah Power House)
Vocational Training Report ( Sealdah Power House)Vocational Training Report ( Sealdah Power House)
Vocational Training Report ( Sealdah Power House)
 
220 66 kv nrs sub report
220 66 kv nrs sub report220 66 kv nrs sub report
220 66 kv nrs sub report
 
Seminar report theory
Seminar report theorySeminar report theory
Seminar report theory
 
Lhb ac buffet car
Lhb ac buffet carLhb ac buffet car
Lhb ac buffet car
 
Alternator excitation systems
Alternator excitation systemsAlternator excitation systems
Alternator excitation systems
 
J DJ
J DJJ DJ
J DJ
 
Internship Report
Internship Report Internship Report
Internship Report
 
KBUNL - NTPC KANTI MUZAFFARPUR BIHAR
KBUNL - NTPC KANTI MUZAFFARPUR BIHARKBUNL - NTPC KANTI MUZAFFARPUR BIHAR
KBUNL - NTPC KANTI MUZAFFARPUR BIHAR
 
3 Prototype #3 EV Regenerative Acceleration (ReGenX) eBike Integration Protot...
3 Prototype #3 EV Regenerative Acceleration (ReGenX) eBike Integration Protot...3 Prototype #3 EV Regenerative Acceleration (ReGenX) eBike Integration Protot...
3 Prototype #3 EV Regenerative Acceleration (ReGenX) eBike Integration Protot...
 
Ranjan NTPC KAHALGAON ppt
Ranjan  NTPC KAHALGAON pptRanjan  NTPC KAHALGAON ppt
Ranjan NTPC KAHALGAON ppt
 

Similar to Ajay binay institute of technology,/ondvc

2x600MW Kalishindh Super Thermal Jhalawar (Rajasthan)
2x600MW Kalishindh Super Thermal Jhalawar (Rajasthan) 2x600MW Kalishindh Super Thermal Jhalawar (Rajasthan)
2x600MW Kalishindh Super Thermal Jhalawar (Rajasthan)
Ministry of New & Renewable Energy, Govt of India
 
Ramendra summer training presentation
Ramendra summer training presentationRamendra summer training presentation
Ramendra summer training presentationRamendra Dhiman
 
Durgapur Projects Limited: Vocational training presentation
Durgapur Projects Limited: Vocational training presentationDurgapur Projects Limited: Vocational training presentation
Durgapur Projects Limited: Vocational training presentation
Saumyadip Moitra
 
Ntpc barh (bstpp)
Ntpc barh (bstpp)Ntpc barh (bstpp)
Ntpc barh (bstpp)
Dheeraj Kashyap
 
NTPC faridabad nd badarpur
NTPC faridabad nd badarpurNTPC faridabad nd badarpur
NTPC faridabad nd badarpurShrey Dhasmana
 
Summer Training Report Ntpc barh (ajeet)
Summer Training Report Ntpc barh (ajeet)Summer Training Report Ntpc barh (ajeet)
Summer Training Report Ntpc barh (ajeet)
Ajeet Chaurasia
 
POWER CAR.pptx
POWER CAR.pptxPOWER CAR.pptx
POWER CAR.pptx
AnkitKumar339958
 
IPGCL/PPCL Training presentation
IPGCL/PPCL Training presentationIPGCL/PPCL Training presentation
IPGCL/PPCL Training presentation
Shubhra Dhyani
 
DPL Training .doc file
DPL Training .doc file DPL Training .doc file
DPL Training .doc file
Subhojeet Sinha ☁
 
Summer training presentation on thermal plant in jindal steel and power limit...
Summer training presentation on thermal plant in jindal steel and power limit...Summer training presentation on thermal plant in jindal steel and power limit...
Summer training presentation on thermal plant in jindal steel and power limit...
Amit Bansal
 
Study of generator and switchgear Vizag steel plant report
Study of generator and switchgear Vizag steel plant reportStudy of generator and switchgear Vizag steel plant report
Study of generator and switchgear Vizag steel plant report
sushi roy
 
Ntpc badarpur summer training
Ntpc badarpur summer trainingNtpc badarpur summer training
Ntpc badarpur summer trainingAnubhav Ghosh
 
Internship PPT final.pptx on ukai thermal power station
Internship PPT final.pptx on ukai thermal power stationInternship PPT final.pptx on ukai thermal power station
Internship PPT final.pptx on ukai thermal power station
malikavita731
 
Internship PPT ukai thermal power station .pptx
Internship PPT ukai thermal power station .pptxInternship PPT ukai thermal power station .pptx
Internship PPT ukai thermal power station .pptx
malikavita731
 
Internship PPT final ukai thermal power station
Internship PPT final ukai thermal power stationInternship PPT final ukai thermal power station
Internship PPT final ukai thermal power station
malikavita731
 
internship report final.DOC
internship report final.DOCinternship report final.DOC
internship report final.DOCqazi faisal
 
A summer training presentation on national thermal power
A summer training presentation on national thermal powerA summer training presentation on national thermal power
A summer training presentation on national thermal power
Shishupal03012015
 
Power plants in bangladesh
Power plants in bangladeshPower plants in bangladesh
Power plants in bangladesh
Imran Hossain
 
Ppt on power generation(thermal), transmission & distribution
Ppt on power generation(thermal), transmission & distributionPpt on power generation(thermal), transmission & distribution
Ppt on power generation(thermal), transmission & distribution
SuvamSahu2
 

Similar to Ajay binay institute of technology,/ondvc (20)

V.T ppt
V.T pptV.T ppt
V.T ppt
 
2x600MW Kalishindh Super Thermal Jhalawar (Rajasthan)
2x600MW Kalishindh Super Thermal Jhalawar (Rajasthan) 2x600MW Kalishindh Super Thermal Jhalawar (Rajasthan)
2x600MW Kalishindh Super Thermal Jhalawar (Rajasthan)
 
Ramendra summer training presentation
Ramendra summer training presentationRamendra summer training presentation
Ramendra summer training presentation
 
Durgapur Projects Limited: Vocational training presentation
Durgapur Projects Limited: Vocational training presentationDurgapur Projects Limited: Vocational training presentation
Durgapur Projects Limited: Vocational training presentation
 
Ntpc barh (bstpp)
Ntpc barh (bstpp)Ntpc barh (bstpp)
Ntpc barh (bstpp)
 
NTPC faridabad nd badarpur
NTPC faridabad nd badarpurNTPC faridabad nd badarpur
NTPC faridabad nd badarpur
 
Summer Training Report Ntpc barh (ajeet)
Summer Training Report Ntpc barh (ajeet)Summer Training Report Ntpc barh (ajeet)
Summer Training Report Ntpc barh (ajeet)
 
POWER CAR.pptx
POWER CAR.pptxPOWER CAR.pptx
POWER CAR.pptx
 
IPGCL/PPCL Training presentation
IPGCL/PPCL Training presentationIPGCL/PPCL Training presentation
IPGCL/PPCL Training presentation
 
DPL Training .doc file
DPL Training .doc file DPL Training .doc file
DPL Training .doc file
 
Summer training presentation on thermal plant in jindal steel and power limit...
Summer training presentation on thermal plant in jindal steel and power limit...Summer training presentation on thermal plant in jindal steel and power limit...
Summer training presentation on thermal plant in jindal steel and power limit...
 
Study of generator and switchgear Vizag steel plant report
Study of generator and switchgear Vizag steel plant reportStudy of generator and switchgear Vizag steel plant report
Study of generator and switchgear Vizag steel plant report
 
Ntpc badarpur summer training
Ntpc badarpur summer trainingNtpc badarpur summer training
Ntpc badarpur summer training
 
Internship PPT final.pptx on ukai thermal power station
Internship PPT final.pptx on ukai thermal power stationInternship PPT final.pptx on ukai thermal power station
Internship PPT final.pptx on ukai thermal power station
 
Internship PPT ukai thermal power station .pptx
Internship PPT ukai thermal power station .pptxInternship PPT ukai thermal power station .pptx
Internship PPT ukai thermal power station .pptx
 
Internship PPT final ukai thermal power station
Internship PPT final ukai thermal power stationInternship PPT final ukai thermal power station
Internship PPT final ukai thermal power station
 
internship report final.DOC
internship report final.DOCinternship report final.DOC
internship report final.DOC
 
A summer training presentation on national thermal power
A summer training presentation on national thermal powerA summer training presentation on national thermal power
A summer training presentation on national thermal power
 
Power plants in bangladesh
Power plants in bangladeshPower plants in bangladesh
Power plants in bangladesh
 
Ppt on power generation(thermal), transmission & distribution
Ppt on power generation(thermal), transmission & distributionPpt on power generation(thermal), transmission & distribution
Ppt on power generation(thermal), transmission & distribution
 

Recently uploaded

English lab ppt no titlespecENG PPTt.pdf
English lab ppt no titlespecENG PPTt.pdfEnglish lab ppt no titlespecENG PPTt.pdf
English lab ppt no titlespecENG PPTt.pdf
BrazilAccount1
 
Fundamentals of Electric Drives and its applications.pptx
Fundamentals of Electric Drives and its applications.pptxFundamentals of Electric Drives and its applications.pptx
Fundamentals of Electric Drives and its applications.pptx
manasideore6
 
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Dr.Costas Sachpazis
 
Investor-Presentation-Q1FY2024 investor presentation document.pptx
Investor-Presentation-Q1FY2024 investor presentation document.pptxInvestor-Presentation-Q1FY2024 investor presentation document.pptx
Investor-Presentation-Q1FY2024 investor presentation document.pptx
AmarGB2
 
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdfHybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
fxintegritypublishin
 
Architectural Portfolio Sean Lockwood
Architectural Portfolio Sean LockwoodArchitectural Portfolio Sean Lockwood
Architectural Portfolio Sean Lockwood
seandesed
 
The role of big data in decision making.
The role of big data in decision making.The role of big data in decision making.
The role of big data in decision making.
ankuprajapati0525
 
CME397 Surface Engineering- Professional Elective
CME397 Surface Engineering- Professional ElectiveCME397 Surface Engineering- Professional Elective
CME397 Surface Engineering- Professional Elective
karthi keyan
 
weather web application report.pdf
weather web application report.pdfweather web application report.pdf
weather web application report.pdf
Pratik Pawar
 
DESIGN A COTTON SEED SEPARATION MACHINE.docx
DESIGN A COTTON SEED SEPARATION MACHINE.docxDESIGN A COTTON SEED SEPARATION MACHINE.docx
DESIGN A COTTON SEED SEPARATION MACHINE.docx
FluxPrime1
 
Student information management system project report ii.pdf
Student information management system project report ii.pdfStudent information management system project report ii.pdf
Student information management system project report ii.pdf
Kamal Acharya
 
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdfTop 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Teleport Manpower Consultant
 
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&BDesign and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Sreedhar Chowdam
 
power quality voltage fluctuation UNIT - I.pptx
power quality voltage fluctuation UNIT - I.pptxpower quality voltage fluctuation UNIT - I.pptx
power quality voltage fluctuation UNIT - I.pptx
ViniHema
 
ethical hacking in wireless-hacking1.ppt
ethical hacking in wireless-hacking1.pptethical hacking in wireless-hacking1.ppt
ethical hacking in wireless-hacking1.ppt
Jayaprasanna4
 
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
thanhdowork
 
Runway Orientation Based on the Wind Rose Diagram.pptx
Runway Orientation Based on the Wind Rose Diagram.pptxRunway Orientation Based on the Wind Rose Diagram.pptx
Runway Orientation Based on the Wind Rose Diagram.pptx
SupreethSP4
 
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
ydteq
 
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
MdTanvirMahtab2
 
WATER CRISIS and its solutions-pptx 1234
WATER CRISIS and its solutions-pptx 1234WATER CRISIS and its solutions-pptx 1234
WATER CRISIS and its solutions-pptx 1234
AafreenAbuthahir2
 

Recently uploaded (20)

English lab ppt no titlespecENG PPTt.pdf
English lab ppt no titlespecENG PPTt.pdfEnglish lab ppt no titlespecENG PPTt.pdf
English lab ppt no titlespecENG PPTt.pdf
 
Fundamentals of Electric Drives and its applications.pptx
Fundamentals of Electric Drives and its applications.pptxFundamentals of Electric Drives and its applications.pptx
Fundamentals of Electric Drives and its applications.pptx
 
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
 
Investor-Presentation-Q1FY2024 investor presentation document.pptx
Investor-Presentation-Q1FY2024 investor presentation document.pptxInvestor-Presentation-Q1FY2024 investor presentation document.pptx
Investor-Presentation-Q1FY2024 investor presentation document.pptx
 
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdfHybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
 
Architectural Portfolio Sean Lockwood
Architectural Portfolio Sean LockwoodArchitectural Portfolio Sean Lockwood
Architectural Portfolio Sean Lockwood
 
The role of big data in decision making.
The role of big data in decision making.The role of big data in decision making.
The role of big data in decision making.
 
CME397 Surface Engineering- Professional Elective
CME397 Surface Engineering- Professional ElectiveCME397 Surface Engineering- Professional Elective
CME397 Surface Engineering- Professional Elective
 
weather web application report.pdf
weather web application report.pdfweather web application report.pdf
weather web application report.pdf
 
DESIGN A COTTON SEED SEPARATION MACHINE.docx
DESIGN A COTTON SEED SEPARATION MACHINE.docxDESIGN A COTTON SEED SEPARATION MACHINE.docx
DESIGN A COTTON SEED SEPARATION MACHINE.docx
 
Student information management system project report ii.pdf
Student information management system project report ii.pdfStudent information management system project report ii.pdf
Student information management system project report ii.pdf
 
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdfTop 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
 
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&BDesign and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
 
power quality voltage fluctuation UNIT - I.pptx
power quality voltage fluctuation UNIT - I.pptxpower quality voltage fluctuation UNIT - I.pptx
power quality voltage fluctuation UNIT - I.pptx
 
ethical hacking in wireless-hacking1.ppt
ethical hacking in wireless-hacking1.pptethical hacking in wireless-hacking1.ppt
ethical hacking in wireless-hacking1.ppt
 
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
 
Runway Orientation Based on the Wind Rose Diagram.pptx
Runway Orientation Based on the Wind Rose Diagram.pptxRunway Orientation Based on the Wind Rose Diagram.pptx
Runway Orientation Based on the Wind Rose Diagram.pptx
 
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
 
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
 
WATER CRISIS and its solutions-pptx 1234
WATER CRISIS and its solutions-pptx 1234WATER CRISIS and its solutions-pptx 1234
WATER CRISIS and its solutions-pptx 1234
 

Ajay binay institute of technology,/ondvc

  • 2. REPORT ON DAMODAR VALLEY CORPORATION AT C.T.P.S
  • 3. 1
  • 4. Dvc at c.t.p.s was started in 1964 as the only power plant with three bus bar.it consists of six units(presentely only three are in working). The plant is situated on the banks of the damodar river which is about 3kms away from hindustan steels dugda washery. Total Installed capacity of ctps is 780MW. Three working units are each of 140MW rating and the other are of 120MW.
  • 5. Mission:- Flood control and irrigation. Generation,transmission and distribution. Eco-conservation and a forestation. Water supply for industrial and domestic use. Vision:- To establish DVC as a mega pithead power producer and distributor in eastern region.
  • 6.
  • 7. Coal and ash handling plant Coal and ash handling plant Boiler Super heater Economize Airpreheater Steam Turbine Condenser Cooling tower Feed water heater Alternator Exciter ElEelcetcrotr sot asttiact picr epcriepcaitpoartor Boiler Super heater Economize Airpreheater Steam Turbine Condenser Cooling tower Feed water heater Alternator Exciter
  • 8. No.of the units Installed capacity De rated Capacity Unit No.1 140 MW 130 MW Unit No.2 140 MW 130 MW Unit No.3 140 MW 130 MW Unit No.4 120 MW 120 MW Unit No.5 120 MW 120 MW Unit No.6 120 MW 120 MW TOTAL 780 MW 750 MW Capacity (MW) rated First synchroni sing dates Make of Boiler Make of turbo Generator 140 10-10-1964 Combustion engg,USA GE,USA 140 01-05-1965 Combustion engg,USA GE,USA 140 10-07-1968 Combustion engg,USA GE,USA 120 02-03-1974 ACC Backcock Ltd ,India BHEL, India 120 28-03-1975 ACC backcock Ltd,India BHEL, India 120 29-03-1979 ACC backcock Ltd,India BHEL, India
  • 9. GENERATOR NOS. 1,2 and 3; Rating : 165000 KVA Power factor : 0.85 Excitation : 375 Volts Frequency : 50 Hz ATP : 2 poles Gas pressure : 30 PSI Seal oil pressure : 2.3 kg/cm2 Diff.pressure : 0.35 kg/cm2 Starter Amp : 6351 Field Amp : 1220 Short circuit ratio : 0.7 Coolant :hydrogen Connection : (Y) for 15000 and165 KVA Maker :general electric co. (U.S.A) GENERATOR NOS.4,5 and 6; Rating : 141176 KVA Power factor : 0.85 Excitation : 433 Volts,1730amps Frequency : 50 Hz Revolution : 3000 RPM Gas pressure : 2.1 kg/cm2 Startor rating : 138 kv Stator amps : 5906 Connection : (Y) for138000volts and 141176 KVA Phase : 3 Coolant :hydrogen Maker :BHEL,(BHOPAL),INDIA
  • 10. TURBINE NOS. 1,2 and 3 : Rating : 140000 Kw RPM : 3000 Steam condition pressure : 1800 Stage : 26 PSIG Temperature : 1000 degree F Rheat temperature : 1000 degree F Exhaust pressure : 25 degree Hg Phase : 3 ABS Frequency : 50 Hz Power factor : 0.85 Turbine No. : 170*124 Maker :general electric co. (U.S.A) TURBINE NOS. 4 ,5 and 6 : Rating : 120000 Kw Power factor : 0.85 KVA :141176 Excitation : 433 volts and 1730amps Stator :138000 volts and 5906 amps Connection and RPM : Y and 3000 Phase : 3 Frequency : 50 Hz Type : Turbo Coolant :hydrogen Gas pressure :2.1 kg/cm3 Maker :BHEL,(BHOPAL),INDIA
  • 11. 1 1.COAL HANDLING PLANT Coal is required in the power house to generate heat so that steam can be generated in the power house . to generate from row coal boulders into powered form coal handling plant is required. ROUTE 1.By road 2.Rail •Size of coal is 20mm
  • 12. 1 Crusher house Wagon tippler and Coal bunker Coal mill Coal handling plant weigh bridge Coal (thru rake) furnance
  • 13.
  • 14. BOILER AUXILIARY TURBINE AUXILIARY GENERATOR AUXILIARY F.D FANS DEAERATOR SEAL OIL SYSTEM I.D FANS HOTWELL HYDROGEN COOLING SYSTEM BOILER DRUM BOILER FEED PUMP GENERATOR TRANSFORMER COAL MILLS CONDENSATE PUMP COAL FEEDERS LOW PRESSURE AND HIGH PRESSURE HEATER
  • 15. switching equipment used in the transmission of electricity. Apart from main bus bar two duplicate buses are provided in the switchyard . They are used when there is some fault in the mai bus bar or some maintenace work is to be done in the main bus bar. The three bus used in DVC are: 1. 33kv 2. 132kv 3. 220kv All the generating eguiptments- transformer,generator etc. are connected to the main bus bar under normal conditions But when fault occurs the supply is transferred to the transfer bus with the help of isolators. Two bus are connected to each other by the bus coupler. Jumpers are provided in the switch yard to move the wires either up or down in the yard.
  • 16. DVC suplies bulk power at 33kv,132kv,220kv through a network covering more than 5500 circuit kilometers. The dvc grid is interconnected with the state electricity boardof jharkhand (JSEB),west bengal(WBSEB) and grid corporation of orissa and power grid corporation of India Ltd. Existing Links(Ckt kms) state 33kv 132kv 220kv Jharkhand 690 2175 898 West Bengal 380 1240 560 Orissa 42 TOTAL 1070 3415 1500 Existing Sub-stations(Nos.) State 33kv 132kv 220kv Jharkhand 9 21 7 West Bengal 7 12 4 TOTAL 16 33 11
  • 17. Circuit Breakers 1. SF6 type circuit breaker (132) 2. Minimum oil circuit breaker(132) •Circuit Breakers 1. SF6 type circuit breaker (132) 2. Minimum oil circuit breaker(132) 3. Vaccum circuit breaker(33kv) Lightning arresters Fuse Load interrupter Line isolator relays 3. Vaccum circuit breaker(33kv) Lightning arresters Fuse Load interrupter Line isolator relays
  • 18. . INTERLOCKING SYSTEM Interlocking system is such type of system by which the machine is shut down automatically for preventing any loss when the process is not running properly or under any abnormal condition .inter lock is used in many system present in the power house . The interlocking system is mainly used in three portion of the plant ; 1.Boiler feed pump 2.Generator seal oil pump interlock 3.Turbine bearing oil pump
  • 19. coal storage Coal hand ling Plant Boile r Ash Storage Ash Handli ng plant Air pre-heater Flue gases Econo miser Super heater turb ine R Y B exciter condenser Colling tower + Alternator Induced draught fan chimney Force draught fan Feed water heater Water treatment chamber Feed water pump Flue gases Transformer Exhaust steam Valve Circulating water pump Hot air Flue gases Bus Bar C.B
  • 20. . TRANSFORMERS IN POWER SYSTEM 1.Generating Transformer(GT) It is transformer on which generating terminal voltage is given. It is a set-up transformer responsible for stepping up the generated voltage to the required voltage in the switchyard which may be either 132kv or 220 k v .after stepping up the voltage the power is given to the main bus bar which runs horizontally in centre throughout a switchyard now from this main bus the electricity is now ready to distributed to different sub station or direct consumer. 2.Unit Auxiliary Transformer (UAT) UAT is a step down transformer which is connected to G.T so it step down the voltage from 132 or 22okv to the required voltage near about 3.5kv.It is used for providing the require power for the auxiliary unit like coal handling plant , coal mil, boiler feedback pump e tc. generally two UAT are connected to on G.T
  • 21. 1 3.Reserve transformer In power house there is probability that the G.T can develop some fault or has to be closed for maintenance in that case the auxiliary unit supply is to be pulled off which is connected to G.T .this will interrupt in the working of the plant .R.T are present in the power house to supply power to auxiliary unit .R.T has two teminals; 1.Common auxiliary board (CAB) 2.Startup emergency board (SEB) ( responsible for providing the power ) Apart from these three transformer there are two other types of transformer ; Potential transformer Current transformer