The project manager needs to understand the availability of team members required to complete project work. She should look at the resource calendars, which identify the working days, shifts, and availability of each resource. The resource calendars serve as an input to the Acquire Resources process, showing when resources are available during planned activity periods. Reviewing the calendars will provide the project manager with the information about team member availability to perform the project work.