SlideShare a Scribd company logo
1 of 31
Download to read offline
1
University of Tehran, Project Management Information System (PMIS), Dr. Sasan Hosseyni, xwir@yahoo.com, 2018
University of Tehran
College of Engineering
School of Industrial Engineering
“Master of Science in Engineering” Program
Project Management Information System
PART 3 – Earned Value Management
2018 Fall Semester
Dr. Sasan Hosseyni
XWIR@yahoo.com
2
University of Tehran, Project Management Information System (PMIS), Dr. Sasan Hosseyni, xwir@yahoo.com, 2018
Outlines:
• PART 1 Definitions (IS, PMBOK, PMIS)
• PART 2 PMIS in Practice
• PART 3 Earned Value Management
• PART 4 Business Process Management
• PART 5 Enterprise Resource Planning
• PART 6 Enterprise Architecture (for a Project Based Org.)
• PART 7 Implementation Methodologies
• PART 8 Organizational Change Management
• PART 9 Implementation Critical Success Factors
• PART 10 Academic Researches
3
University of Tehran, Project Management Information System (PMIS), Dr. Sasan Hosseyni, xwir@yahoo.com, 2018
Earned Value Management (EVM) helps project managers to measure
project performance. It is a systematic project management process used to
find variances in projects based on the comparison of worked performed
and work planned.
EVM is used on the cost and schedule control and can be very useful in
project forecasting. The project baseline is an essential component of EVM
and serves as a reference point for all EVM related activities. EVM provides
quantitative data for project decision making. (projectsmart.co.uk, Dwivedi)
Earned Value Management Definition
4
University of Tehran, Project Management Information System (PMIS), Dr. Sasan Hosseyni, xwir@yahoo.com, 2018
Some of the most well known organizations practicing EVM are:
• NASA
• Project Management Institute (PMI)
• Society of Cost Estimating and Analysis
• Defense Acquisition University
• Federal Acquisition Institute
• Acquisition Management (UK)
Earned Value Management Definition
5
University of Tehran, Project Management Information System (PMIS), Dr. Sasan Hosseyni, xwir@yahoo.com, 2018
Schedule % Complete (S%):
Formula: (Data Date – Planned Start Date) / (Planned End Date - Planned Start Date)
If Data date (Time Now)= 3,
then S% = (3-1)/(6-1) = 2/5 = 40%
Day 1 Day 2 Day 3 Day 4 Day 5
1 2 3 4 5 6
Percent Complete
6
University of Tehran, Project Management Information System (PMIS), Dr. Sasan Hosseyni, xwir@yahoo.com, 2018
Activity % Complete (A%): (ACTUAL % Complete)
Duration based:
Formula: (Original Duration – Remaining Duration) / Original Duration
If Data date = 3
If (You estimate that) the remaining duration to complete the work = 4 days
then A% = (5-4)/5 = 1/5 = 20%
For Calculation A% you don’t need to know:
• Activity Actual start date
Percent Complete
7
University of Tehran, Project Management Information System (PMIS), Dr. Sasan Hosseyni, xwir@yahoo.com, 2018
Activity % Complete (A%):
Unit based:
Formula: Actual Units / (Actual Units + Remaining Units)
If Data date = 3
If Actual units (e.g. an earthwork m3) = 100
If (you estimate that) the remaining units to complete the work (e.g. an earthwork m3) = 900
then A% = 100 /(100+900) = 10%
For Calculation A% you don’t need to know:
• Activity Actual start date
• Remaining duration (needs to complete the remaining work)
Percent Complete
8
University of Tehran, Project Management Information System (PMIS), Dr. Sasan Hosseyni, xwir@yahoo.com, 2018
Activity % Complete (A%):
Physical evidence based:
Based on a mutual agreement between client and contractor:
An example: For preparing a Drawing:
A% = First Issue: 70%, Second Issue: 90%, Final Issue: 100%
For Calculation A% you don’t need to know:
• Activity Actual start date
• Remaining duration (needs to complete the remaining work)
• Remaining units (need to complete the remaining work) and/or Actual units
Percent Complete
9
University of Tehran, Project Management Information System (PMIS), Dr. Sasan Hosseyni, xwir@yahoo.com, 2018
Main Parameters
WORK
SCHEDULED PERFORMED
COSTS
BUDGETTED
PV
Budgeted Cost for Work
Scheduled (BCWS)
EV
Budgeted Cost for Work
Performed (BCWP)
ACTUAL X
AC
Actual Cost of Work
Performed (ACWP)
10
University of Tehran, Project Management Information System (PMIS), Dr. Sasan Hosseyni, xwir@yahoo.com, 2018
Budget At Completion (BAC)
How much money will need to be spent to complete the project
Planned Value (PV)
OR Budgeted Cost for Work Scheduled (BCWS)
Formula: S% X BAC
The amount expressed in dollar of work to be performed as per the
schedule plan
If BAC = 500,
If Data date = 3
then S% = 40%
then PV = 40% X 500 = 200
Main Parameters
11
University of Tehran, Project Management Information System (PMIS), Dr. Sasan Hosseyni, xwir@yahoo.com, 2018
Earned Value (EV)
OR Budgeted Cost for Work Performed (BCWP)
Formula: A% X BAC
The amount expressed in dollar on the actual worked performed
If BAC = 500
If A% = 20%
then EV = 20% X 500 = 100
Main Parameters
12
University of Tehran, Project Management Information System (PMIS), Dr. Sasan Hosseyni, xwir@yahoo.com, 2018
Actual Cost (AC)
OR Actual Cost of Work Performed (ACWP)
No formula!
The sum of all costs actually accrued for an activity to date
AC = 300
Estimate to Complete (ETC)
Is a forecast of how much more money will need to be spent to complete
the project
Estimate At Completion (EAC)
EAC = AC + ETC (most common way)
Main Parameters
13
University of Tehran, Project Management Information System (PMIS), Dr. Sasan Hosseyni, xwir@yahoo.com, 2018
An s-curve is a mathematical graph or illustration that properly illustrates
the appropriate cumulative data for a project or task. This data can cost, or
man-hours plotted against time.
EXAMPLE:
If Data Date = 9
Project S-Curve
Activity  A B
If BAC 100 700
If Duration 10 14
If Planned Start Date 1 5
If Actual Start Date 3 4
If Activity Percent Complete 90 20
If Actual Cost 120 250
14
University of Tehran, Project Management Information System (PMIS), Dr. Sasan Hosseyni, xwir@yahoo.com, 2018
e.g. for Activity A:
S% = (Data Date – Planned Start Date) / (Planned End Date - Planned Start Date)
= (9-1)/(11-1) = 8/10 = 80%
Also assume that the A% , AC and Activity “Actual Start Date”
are stated by the activity’s work performer
Activity “A” Actual Start Date = 3
Data Date = 9
15
University of Tehran, Project Management Information System (PMIS), Dr. Sasan Hosseyni, xwir@yahoo.com, 2018
For Activity A+ Activity B ?
16
University of Tehran, Project Management Information System (PMIS), Dr. Sasan Hosseyni, xwir@yahoo.com, 2018
Cumulative
e.g. for Activity A:
Activity Duration = 10 Months AND BAC = 100
then PV for each month = 100/10 = 10
(Data Date – Actual Start Date) = (9-3) = 6 Months AND EV = 90
then EV for each month = 90/6 = 15
(Data Date – Actual Start Date) = (9-3) = 6 Months AND AC = 120
then AC for each month = 120/6 = 20
Cumulative
Cumulative
17
University of Tehran, Project Management Information System (PMIS), Dr. Sasan Hosseyni, xwir@yahoo.com, 2018
Cumulative
Next Slide
Cumulative
Cumulative
18
University of Tehran, Project Management Information System (PMIS), Dr. Sasan Hosseyni, xwir@yahoo.com, 2018
S-Curve for Activity A + Activity B
19
University of Tehran, Project Management Information System (PMIS), Dr. Sasan Hosseyni, xwir@yahoo.com, 2018
20
University of Tehran, Project Management Information System (PMIS), Dr. Sasan Hosseyni, xwir@yahoo.com, 2018
Interpretation of Results
21
University of Tehran, Project Management Information System (PMIS), Dr. Sasan Hosseyni, xwir@yahoo.com, 2018
Behind schedule
Over Planned Cost
Which means:
Behind schedule
Over Planned Cost
Activities
22
University of Tehran, Project Management Information System (PMIS), Dr. Sasan Hosseyni, xwir@yahoo.com, 2018
23
University of Tehran, Project Management Information System (PMIS), Dr. Sasan Hosseyni, xwir@yahoo.com, 2018
Data Date
(Time Now)
AC
PV
EV
Time
Value
EAC
BAC


24
University of Tehran, Project Management Information System (PMIS), Dr. Sasan Hosseyni, xwir@yahoo.com, 2018
Data Date
(Time Now)
AC
PV
EV
Time
Value
EAC
BAC
ETC 
Duration
Slippage 
VAC 
25
University of Tehran, Project Management Information System (PMIS), Dr. Sasan Hosseyni, xwir@yahoo.com, 2018
Data Date
(Time Now)
AC
PV
EV
Time
Value
EAC
BAC
Time Behind 
Pro-Active Approach
Time Behind! 
(Needs a calculation for trend)
This one is my suggestion ;)
26
University of Tehran, Project Management Information System (PMIS), Dr. Sasan Hosseyni, xwir@yahoo.com, 2018
Data Date
(Time Now)
AC
PV
EV
Time
Value
Late PV!
On as late as
possible path!
Schedule Variance (SV)
On Late Path!
Cost Variance
(CV)
27
University of Tehran, Project Management Information System (PMIS), Dr. Sasan Hosseyni, xwir@yahoo.com, 2018
We are not allowed to use the “Late PV” as a base to calculate the delays!
Usually approved baseline will be developed based on Early dates not Late dates
PV includes the Duration Contingency Reserves (not Mgmt Reserves)
The best way to calculate the ETC : Reestimating!
The best way to calculate the EAC : AC + (ETC calculated by reestimating)
The only way to calculate the Duration Slippage of project: Rescheduling!
Do not use some unapproved formulas such as “Remaining time / SPI”! (this formula is one of
the several ways to forecast the completion date of an activity not whole of the project or even
a work package!)
The only way to calculate the Time Behind :
Data Date - The date that (S% = to-date A%)
OR my suggestion: The date that (A% = to-date S%) – Data Date
Attention!
28
University of Tehran, Project Management Information System (PMIS), Dr. Sasan Hosseyni, xwir@yahoo.com, 2018
Data Date
(Time Now)
AC
PV
EV
Time
Value
Replan
(New PV)
Forecast for AC
(rough estimate)
Duration
Slippage
Forecasted
Completion Date
(Accepted by
Project Client)
29
University of Tehran, Project Management Information System (PMIS), Dr. Sasan Hosseyni, xwir@yahoo.com, 2018
Data Date
(Time Now)
AC
PV
EV
Time
Value
Catch up Plan
(New PV on
Catch up path)
Forecast for AC
(rough estimate)
30
University of Tehran, Project Management Information System (PMIS), Dr. Sasan Hosseyni, xwir@yahoo.com, 2018
Reschedule: Scheduling the project on a new Data Date
• Usually every month  to report the project status
Replan: Planning the project again! (to create a new baseline)
• After rescheduling, if Schedule Variance > 25% and/or
project plan is not realistic/applicable anymore
• After replan, the new baseline (New PV) and “forecasted completion date”
should be approved by project client
Catch-up Plan: Replan without change in “Completion Date”
• After replan, the new baseline (New PV) should be approved by project
client
Reschedule Vs. Replan
31
University of Tehran, Project Management Information System (PMIS), Dr. Sasan Hosseyni, xwir@yahoo.com, 2018
SPI Trend
Data Date
0%
100% PV
EV
Alert! - descending for 4 periods
0.6
0.8
1.0
SPI = EV / PV
Safe
Warning
Danger

More Related Content

Similar to PMIS Course Part 3 – Earned Value Management

Chapter ThirteenProgress and Performance Measurement and Evalu
Chapter ThirteenProgress and Performance Measurement and EvaluChapter ThirteenProgress and Performance Measurement and Evalu
Chapter ThirteenProgress and Performance Measurement and EvaluJinElias52
 
Finance management in construction site
Finance management in construction siteFinance management in construction site
Finance management in construction siteSHAHIDBASHIRMALIK
 
Project Scheduling: Survey and Research Potentials
Project Scheduling: Survey and Research PotentialsProject Scheduling: Survey and Research Potentials
Project Scheduling: Survey and Research PotentialsEditor IJCATR
 
Data Analytics of Strategic Information Technology Asset Reviews
Data Analytics of Strategic Information Technology Asset ReviewsData Analytics of Strategic Information Technology Asset Reviews
Data Analytics of Strategic Information Technology Asset ReviewsBrian Bissett
 
IRJET- Evaluation Technique of Student Performance in various Courses
IRJET- Evaluation Technique of Student Performance in various CoursesIRJET- Evaluation Technique of Student Performance in various Courses
IRJET- Evaluation Technique of Student Performance in various CoursesIRJET Journal
 
Business intelligence: making more informed decisions - Jisc Digifest 2016
Business intelligence: making more informed decisions - Jisc Digifest 2016Business intelligence: making more informed decisions - Jisc Digifest 2016
Business intelligence: making more informed decisions - Jisc Digifest 2016Jisc
 
DLandry Resume 4-12-2015 Consulting focus healthcare.docx without header details
DLandry Resume 4-12-2015 Consulting focus healthcare.docx without header detailsDLandry Resume 4-12-2015 Consulting focus healthcare.docx without header details
DLandry Resume 4-12-2015 Consulting focus healthcare.docx without header detailsDonald R Landry CPM MCTS PMP
 
school billing system report
school billing system reportschool billing system report
school billing system reportaki_shu
 
Training and Placement Portal
Training and Placement PortalTraining and Placement Portal
Training and Placement PortalIRJET Journal
 
Planning techniques, budgeting, linear programming, scheduling
Planning techniques, budgeting, linear programming, schedulingPlanning techniques, budgeting, linear programming, scheduling
Planning techniques, budgeting, linear programming, schedulingPriyanka Roy
 
Integration of Principal Component Analysis and Support Vector Regression fo...
 Integration of Principal Component Analysis and Support Vector Regression fo... Integration of Principal Component Analysis and Support Vector Regression fo...
Integration of Principal Component Analysis and Support Vector Regression fo...IJCSIS Research Publications
 
Forecasting cost and schedule performance
Forecasting cost and schedule performanceForecasting cost and schedule performance
Forecasting cost and schedule performanceGlen Alleman
 
FACTORS AFFECTING ACCEPTANCE OF WEB-BASED TRAINING SYSTEM: USING EXTENDED UTA...
FACTORS AFFECTING ACCEPTANCE OF WEB-BASED TRAINING SYSTEM: USING EXTENDED UTA...FACTORS AFFECTING ACCEPTANCE OF WEB-BASED TRAINING SYSTEM: USING EXTENDED UTA...
FACTORS AFFECTING ACCEPTANCE OF WEB-BASED TRAINING SYSTEM: USING EXTENDED UTA...IJCSEIT Journal
 
Running Head STUDENT RECORD KEEPING SYSTEM DATABASE PROJECT 1.docx
Running Head STUDENT RECORD KEEPING SYSTEM DATABASE PROJECT  1.docxRunning Head STUDENT RECORD KEEPING SYSTEM DATABASE PROJECT  1.docx
Running Head STUDENT RECORD KEEPING SYSTEM DATABASE PROJECT 1.docxjeanettehully
 
Project quality management system
Project quality management systemProject quality management system
Project quality management systemselinasimpson351
 

Similar to PMIS Course Part 3 – Earned Value Management (20)

Chapter ThirteenProgress and Performance Measurement and Evalu
Chapter ThirteenProgress and Performance Measurement and EvaluChapter ThirteenProgress and Performance Measurement and Evalu
Chapter ThirteenProgress and Performance Measurement and Evalu
 
Finance management in construction site
Finance management in construction siteFinance management in construction site
Finance management in construction site
 
Project Scheduling: Survey and Research Potentials
Project Scheduling: Survey and Research PotentialsProject Scheduling: Survey and Research Potentials
Project Scheduling: Survey and Research Potentials
 
Data Analytics of Strategic Information Technology Asset Reviews
Data Analytics of Strategic Information Technology Asset ReviewsData Analytics of Strategic Information Technology Asset Reviews
Data Analytics of Strategic Information Technology Asset Reviews
 
IRJET- Evaluation Technique of Student Performance in various Courses
IRJET- Evaluation Technique of Student Performance in various CoursesIRJET- Evaluation Technique of Student Performance in various Courses
IRJET- Evaluation Technique of Student Performance in various Courses
 
Business intelligence: making more informed decisions - Jisc Digifest 2016
Business intelligence: making more informed decisions - Jisc Digifest 2016Business intelligence: making more informed decisions - Jisc Digifest 2016
Business intelligence: making more informed decisions - Jisc Digifest 2016
 
DLandry Resume 4-12-2015 Consulting focus healthcare.docx without header details
DLandry Resume 4-12-2015 Consulting focus healthcare.docx without header detailsDLandry Resume 4-12-2015 Consulting focus healthcare.docx without header details
DLandry Resume 4-12-2015 Consulting focus healthcare.docx without header details
 
school billing system report
school billing system reportschool billing system report
school billing system report
 
INSTITUTION -WEBSITE
INSTITUTION -WEBSITEINSTITUTION -WEBSITE
INSTITUTION -WEBSITE
 
Training and Placement Portal
Training and Placement PortalTraining and Placement Portal
Training and Placement Portal
 
Planning techniques, budgeting, linear programming, scheduling
Planning techniques, budgeting, linear programming, schedulingPlanning techniques, budgeting, linear programming, scheduling
Planning techniques, budgeting, linear programming, scheduling
 
Integration of Principal Component Analysis and Support Vector Regression fo...
 Integration of Principal Component Analysis and Support Vector Regression fo... Integration of Principal Component Analysis and Support Vector Regression fo...
Integration of Principal Component Analysis and Support Vector Regression fo...
 
Forecasting cost and schedule performance
Forecasting cost and schedule performanceForecasting cost and schedule performance
Forecasting cost and schedule performance
 
CAPM study session 4
CAPM study session 4CAPM study session 4
CAPM study session 4
 
sreeparvathi Resume
sreeparvathi Resumesreeparvathi Resume
sreeparvathi Resume
 
Dynamic Schedule Management
Dynamic Schedule ManagementDynamic Schedule Management
Dynamic Schedule Management
 
FACTORS AFFECTING ACCEPTANCE OF WEB-BASED TRAINING SYSTEM: USING EXTENDED UTA...
FACTORS AFFECTING ACCEPTANCE OF WEB-BASED TRAINING SYSTEM: USING EXTENDED UTA...FACTORS AFFECTING ACCEPTANCE OF WEB-BASED TRAINING SYSTEM: USING EXTENDED UTA...
FACTORS AFFECTING ACCEPTANCE OF WEB-BASED TRAINING SYSTEM: USING EXTENDED UTA...
 
Running Head STUDENT RECORD KEEPING SYSTEM DATABASE PROJECT 1.docx
Running Head STUDENT RECORD KEEPING SYSTEM DATABASE PROJECT  1.docxRunning Head STUDENT RECORD KEEPING SYSTEM DATABASE PROJECT  1.docx
Running Head STUDENT RECORD KEEPING SYSTEM DATABASE PROJECT 1.docx
 
Project quality management system
Project quality management systemProject quality management system
Project quality management system
 
Resume
ResumeResume
Resume
 

Recently uploaded

Advanced Views - Calendar View in Odoo 17
Advanced Views - Calendar View in Odoo 17Advanced Views - Calendar View in Odoo 17
Advanced Views - Calendar View in Odoo 17Celine George
 
Accessible design: Minimum effort, maximum impact
Accessible design: Minimum effort, maximum impactAccessible design: Minimum effort, maximum impact
Accessible design: Minimum effort, maximum impactdawncurless
 
Interactive Powerpoint_How to Master effective communication
Interactive Powerpoint_How to Master effective communicationInteractive Powerpoint_How to Master effective communication
Interactive Powerpoint_How to Master effective communicationnomboosow
 
Software Engineering Methodologies (overview)
Software Engineering Methodologies (overview)Software Engineering Methodologies (overview)
Software Engineering Methodologies (overview)eniolaolutunde
 
CARE OF CHILD IN INCUBATOR..........pptx
CARE OF CHILD IN INCUBATOR..........pptxCARE OF CHILD IN INCUBATOR..........pptx
CARE OF CHILD IN INCUBATOR..........pptxGaneshChakor2
 
Measures of Central Tendency: Mean, Median and Mode
Measures of Central Tendency: Mean, Median and ModeMeasures of Central Tendency: Mean, Median and Mode
Measures of Central Tendency: Mean, Median and ModeThiyagu K
 
Arihant handbook biology for class 11 .pdf
Arihant handbook biology for class 11 .pdfArihant handbook biology for class 11 .pdf
Arihant handbook biology for class 11 .pdfchloefrazer622
 
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptxSOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptxiammrhaywood
 
Web & Social Media Analytics Previous Year Question Paper.pdf
Web & Social Media Analytics Previous Year Question Paper.pdfWeb & Social Media Analytics Previous Year Question Paper.pdf
Web & Social Media Analytics Previous Year Question Paper.pdfJayanti Pande
 
Introduction to AI in Higher Education_draft.pptx
Introduction to AI in Higher Education_draft.pptxIntroduction to AI in Higher Education_draft.pptx
Introduction to AI in Higher Education_draft.pptxpboyjonauth
 
Paris 2024 Olympic Geographies - an activity
Paris 2024 Olympic Geographies - an activityParis 2024 Olympic Geographies - an activity
Paris 2024 Olympic Geographies - an activityGeoBlogs
 
Beyond the EU: DORA and NIS 2 Directive's Global Impact
Beyond the EU: DORA and NIS 2 Directive's Global ImpactBeyond the EU: DORA and NIS 2 Directive's Global Impact
Beyond the EU: DORA and NIS 2 Directive's Global ImpactPECB
 
Mastering the Unannounced Regulatory Inspection
Mastering the Unannounced Regulatory InspectionMastering the Unannounced Regulatory Inspection
Mastering the Unannounced Regulatory InspectionSafetyChain Software
 
Employee wellbeing at the workplace.pptx
Employee wellbeing at the workplace.pptxEmployee wellbeing at the workplace.pptx
Employee wellbeing at the workplace.pptxNirmalaLoungPoorunde1
 
Nutritional Needs Presentation - HLTH 104
Nutritional Needs Presentation - HLTH 104Nutritional Needs Presentation - HLTH 104
Nutritional Needs Presentation - HLTH 104misteraugie
 
Q4-W6-Restating Informational Text Grade 3
Q4-W6-Restating Informational Text Grade 3Q4-W6-Restating Informational Text Grade 3
Q4-W6-Restating Informational Text Grade 3JemimahLaneBuaron
 

Recently uploaded (20)

Advanced Views - Calendar View in Odoo 17
Advanced Views - Calendar View in Odoo 17Advanced Views - Calendar View in Odoo 17
Advanced Views - Calendar View in Odoo 17
 
Accessible design: Minimum effort, maximum impact
Accessible design: Minimum effort, maximum impactAccessible design: Minimum effort, maximum impact
Accessible design: Minimum effort, maximum impact
 
Interactive Powerpoint_How to Master effective communication
Interactive Powerpoint_How to Master effective communicationInteractive Powerpoint_How to Master effective communication
Interactive Powerpoint_How to Master effective communication
 
Software Engineering Methodologies (overview)
Software Engineering Methodologies (overview)Software Engineering Methodologies (overview)
Software Engineering Methodologies (overview)
 
Staff of Color (SOC) Retention Efforts DDSD
Staff of Color (SOC) Retention Efforts DDSDStaff of Color (SOC) Retention Efforts DDSD
Staff of Color (SOC) Retention Efforts DDSD
 
CARE OF CHILD IN INCUBATOR..........pptx
CARE OF CHILD IN INCUBATOR..........pptxCARE OF CHILD IN INCUBATOR..........pptx
CARE OF CHILD IN INCUBATOR..........pptx
 
Measures of Central Tendency: Mean, Median and Mode
Measures of Central Tendency: Mean, Median and ModeMeasures of Central Tendency: Mean, Median and Mode
Measures of Central Tendency: Mean, Median and Mode
 
Arihant handbook biology for class 11 .pdf
Arihant handbook biology for class 11 .pdfArihant handbook biology for class 11 .pdf
Arihant handbook biology for class 11 .pdf
 
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptxSOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
 
Web & Social Media Analytics Previous Year Question Paper.pdf
Web & Social Media Analytics Previous Year Question Paper.pdfWeb & Social Media Analytics Previous Year Question Paper.pdf
Web & Social Media Analytics Previous Year Question Paper.pdf
 
Código Creativo y Arte de Software | Unidad 1
Código Creativo y Arte de Software | Unidad 1Código Creativo y Arte de Software | Unidad 1
Código Creativo y Arte de Software | Unidad 1
 
Introduction to AI in Higher Education_draft.pptx
Introduction to AI in Higher Education_draft.pptxIntroduction to AI in Higher Education_draft.pptx
Introduction to AI in Higher Education_draft.pptx
 
Paris 2024 Olympic Geographies - an activity
Paris 2024 Olympic Geographies - an activityParis 2024 Olympic Geographies - an activity
Paris 2024 Olympic Geographies - an activity
 
INDIA QUIZ 2024 RLAC DELHI UNIVERSITY.pptx
INDIA QUIZ 2024 RLAC DELHI UNIVERSITY.pptxINDIA QUIZ 2024 RLAC DELHI UNIVERSITY.pptx
INDIA QUIZ 2024 RLAC DELHI UNIVERSITY.pptx
 
Beyond the EU: DORA and NIS 2 Directive's Global Impact
Beyond the EU: DORA and NIS 2 Directive's Global ImpactBeyond the EU: DORA and NIS 2 Directive's Global Impact
Beyond the EU: DORA and NIS 2 Directive's Global Impact
 
Mastering the Unannounced Regulatory Inspection
Mastering the Unannounced Regulatory InspectionMastering the Unannounced Regulatory Inspection
Mastering the Unannounced Regulatory Inspection
 
Employee wellbeing at the workplace.pptx
Employee wellbeing at the workplace.pptxEmployee wellbeing at the workplace.pptx
Employee wellbeing at the workplace.pptx
 
Nutritional Needs Presentation - HLTH 104
Nutritional Needs Presentation - HLTH 104Nutritional Needs Presentation - HLTH 104
Nutritional Needs Presentation - HLTH 104
 
Q4-W6-Restating Informational Text Grade 3
Q4-W6-Restating Informational Text Grade 3Q4-W6-Restating Informational Text Grade 3
Q4-W6-Restating Informational Text Grade 3
 
Mattingly "AI & Prompt Design: Structured Data, Assistants, & RAG"
Mattingly "AI & Prompt Design: Structured Data, Assistants, & RAG"Mattingly "AI & Prompt Design: Structured Data, Assistants, & RAG"
Mattingly "AI & Prompt Design: Structured Data, Assistants, & RAG"
 

PMIS Course Part 3 – Earned Value Management

  • 1. 1 University of Tehran, Project Management Information System (PMIS), Dr. Sasan Hosseyni, xwir@yahoo.com, 2018 University of Tehran College of Engineering School of Industrial Engineering “Master of Science in Engineering” Program Project Management Information System PART 3 – Earned Value Management 2018 Fall Semester Dr. Sasan Hosseyni XWIR@yahoo.com
  • 2. 2 University of Tehran, Project Management Information System (PMIS), Dr. Sasan Hosseyni, xwir@yahoo.com, 2018 Outlines: • PART 1 Definitions (IS, PMBOK, PMIS) • PART 2 PMIS in Practice • PART 3 Earned Value Management • PART 4 Business Process Management • PART 5 Enterprise Resource Planning • PART 6 Enterprise Architecture (for a Project Based Org.) • PART 7 Implementation Methodologies • PART 8 Organizational Change Management • PART 9 Implementation Critical Success Factors • PART 10 Academic Researches
  • 3. 3 University of Tehran, Project Management Information System (PMIS), Dr. Sasan Hosseyni, xwir@yahoo.com, 2018 Earned Value Management (EVM) helps project managers to measure project performance. It is a systematic project management process used to find variances in projects based on the comparison of worked performed and work planned. EVM is used on the cost and schedule control and can be very useful in project forecasting. The project baseline is an essential component of EVM and serves as a reference point for all EVM related activities. EVM provides quantitative data for project decision making. (projectsmart.co.uk, Dwivedi) Earned Value Management Definition
  • 4. 4 University of Tehran, Project Management Information System (PMIS), Dr. Sasan Hosseyni, xwir@yahoo.com, 2018 Some of the most well known organizations practicing EVM are: • NASA • Project Management Institute (PMI) • Society of Cost Estimating and Analysis • Defense Acquisition University • Federal Acquisition Institute • Acquisition Management (UK) Earned Value Management Definition
  • 5. 5 University of Tehran, Project Management Information System (PMIS), Dr. Sasan Hosseyni, xwir@yahoo.com, 2018 Schedule % Complete (S%): Formula: (Data Date – Planned Start Date) / (Planned End Date - Planned Start Date) If Data date (Time Now)= 3, then S% = (3-1)/(6-1) = 2/5 = 40% Day 1 Day 2 Day 3 Day 4 Day 5 1 2 3 4 5 6 Percent Complete
  • 6. 6 University of Tehran, Project Management Information System (PMIS), Dr. Sasan Hosseyni, xwir@yahoo.com, 2018 Activity % Complete (A%): (ACTUAL % Complete) Duration based: Formula: (Original Duration – Remaining Duration) / Original Duration If Data date = 3 If (You estimate that) the remaining duration to complete the work = 4 days then A% = (5-4)/5 = 1/5 = 20% For Calculation A% you don’t need to know: • Activity Actual start date Percent Complete
  • 7. 7 University of Tehran, Project Management Information System (PMIS), Dr. Sasan Hosseyni, xwir@yahoo.com, 2018 Activity % Complete (A%): Unit based: Formula: Actual Units / (Actual Units + Remaining Units) If Data date = 3 If Actual units (e.g. an earthwork m3) = 100 If (you estimate that) the remaining units to complete the work (e.g. an earthwork m3) = 900 then A% = 100 /(100+900) = 10% For Calculation A% you don’t need to know: • Activity Actual start date • Remaining duration (needs to complete the remaining work) Percent Complete
  • 8. 8 University of Tehran, Project Management Information System (PMIS), Dr. Sasan Hosseyni, xwir@yahoo.com, 2018 Activity % Complete (A%): Physical evidence based: Based on a mutual agreement between client and contractor: An example: For preparing a Drawing: A% = First Issue: 70%, Second Issue: 90%, Final Issue: 100% For Calculation A% you don’t need to know: • Activity Actual start date • Remaining duration (needs to complete the remaining work) • Remaining units (need to complete the remaining work) and/or Actual units Percent Complete
  • 9. 9 University of Tehran, Project Management Information System (PMIS), Dr. Sasan Hosseyni, xwir@yahoo.com, 2018 Main Parameters WORK SCHEDULED PERFORMED COSTS BUDGETTED PV Budgeted Cost for Work Scheduled (BCWS) EV Budgeted Cost for Work Performed (BCWP) ACTUAL X AC Actual Cost of Work Performed (ACWP)
  • 10. 10 University of Tehran, Project Management Information System (PMIS), Dr. Sasan Hosseyni, xwir@yahoo.com, 2018 Budget At Completion (BAC) How much money will need to be spent to complete the project Planned Value (PV) OR Budgeted Cost for Work Scheduled (BCWS) Formula: S% X BAC The amount expressed in dollar of work to be performed as per the schedule plan If BAC = 500, If Data date = 3 then S% = 40% then PV = 40% X 500 = 200 Main Parameters
  • 11. 11 University of Tehran, Project Management Information System (PMIS), Dr. Sasan Hosseyni, xwir@yahoo.com, 2018 Earned Value (EV) OR Budgeted Cost for Work Performed (BCWP) Formula: A% X BAC The amount expressed in dollar on the actual worked performed If BAC = 500 If A% = 20% then EV = 20% X 500 = 100 Main Parameters
  • 12. 12 University of Tehran, Project Management Information System (PMIS), Dr. Sasan Hosseyni, xwir@yahoo.com, 2018 Actual Cost (AC) OR Actual Cost of Work Performed (ACWP) No formula! The sum of all costs actually accrued for an activity to date AC = 300 Estimate to Complete (ETC) Is a forecast of how much more money will need to be spent to complete the project Estimate At Completion (EAC) EAC = AC + ETC (most common way) Main Parameters
  • 13. 13 University of Tehran, Project Management Information System (PMIS), Dr. Sasan Hosseyni, xwir@yahoo.com, 2018 An s-curve is a mathematical graph or illustration that properly illustrates the appropriate cumulative data for a project or task. This data can cost, or man-hours plotted against time. EXAMPLE: If Data Date = 9 Project S-Curve Activity  A B If BAC 100 700 If Duration 10 14 If Planned Start Date 1 5 If Actual Start Date 3 4 If Activity Percent Complete 90 20 If Actual Cost 120 250
  • 14. 14 University of Tehran, Project Management Information System (PMIS), Dr. Sasan Hosseyni, xwir@yahoo.com, 2018 e.g. for Activity A: S% = (Data Date – Planned Start Date) / (Planned End Date - Planned Start Date) = (9-1)/(11-1) = 8/10 = 80% Also assume that the A% , AC and Activity “Actual Start Date” are stated by the activity’s work performer Activity “A” Actual Start Date = 3 Data Date = 9
  • 15. 15 University of Tehran, Project Management Information System (PMIS), Dr. Sasan Hosseyni, xwir@yahoo.com, 2018 For Activity A+ Activity B ?
  • 16. 16 University of Tehran, Project Management Information System (PMIS), Dr. Sasan Hosseyni, xwir@yahoo.com, 2018 Cumulative e.g. for Activity A: Activity Duration = 10 Months AND BAC = 100 then PV for each month = 100/10 = 10 (Data Date – Actual Start Date) = (9-3) = 6 Months AND EV = 90 then EV for each month = 90/6 = 15 (Data Date – Actual Start Date) = (9-3) = 6 Months AND AC = 120 then AC for each month = 120/6 = 20 Cumulative Cumulative
  • 17. 17 University of Tehran, Project Management Information System (PMIS), Dr. Sasan Hosseyni, xwir@yahoo.com, 2018 Cumulative Next Slide Cumulative Cumulative
  • 18. 18 University of Tehran, Project Management Information System (PMIS), Dr. Sasan Hosseyni, xwir@yahoo.com, 2018 S-Curve for Activity A + Activity B
  • 19. 19 University of Tehran, Project Management Information System (PMIS), Dr. Sasan Hosseyni, xwir@yahoo.com, 2018
  • 20. 20 University of Tehran, Project Management Information System (PMIS), Dr. Sasan Hosseyni, xwir@yahoo.com, 2018 Interpretation of Results
  • 21. 21 University of Tehran, Project Management Information System (PMIS), Dr. Sasan Hosseyni, xwir@yahoo.com, 2018 Behind schedule Over Planned Cost Which means: Behind schedule Over Planned Cost Activities
  • 22. 22 University of Tehran, Project Management Information System (PMIS), Dr. Sasan Hosseyni, xwir@yahoo.com, 2018
  • 23. 23 University of Tehran, Project Management Information System (PMIS), Dr. Sasan Hosseyni, xwir@yahoo.com, 2018 Data Date (Time Now) AC PV EV Time Value EAC BAC  
  • 24. 24 University of Tehran, Project Management Information System (PMIS), Dr. Sasan Hosseyni, xwir@yahoo.com, 2018 Data Date (Time Now) AC PV EV Time Value EAC BAC ETC  Duration Slippage  VAC 
  • 25. 25 University of Tehran, Project Management Information System (PMIS), Dr. Sasan Hosseyni, xwir@yahoo.com, 2018 Data Date (Time Now) AC PV EV Time Value EAC BAC Time Behind  Pro-Active Approach Time Behind!  (Needs a calculation for trend) This one is my suggestion ;)
  • 26. 26 University of Tehran, Project Management Information System (PMIS), Dr. Sasan Hosseyni, xwir@yahoo.com, 2018 Data Date (Time Now) AC PV EV Time Value Late PV! On as late as possible path! Schedule Variance (SV) On Late Path! Cost Variance (CV)
  • 27. 27 University of Tehran, Project Management Information System (PMIS), Dr. Sasan Hosseyni, xwir@yahoo.com, 2018 We are not allowed to use the “Late PV” as a base to calculate the delays! Usually approved baseline will be developed based on Early dates not Late dates PV includes the Duration Contingency Reserves (not Mgmt Reserves) The best way to calculate the ETC : Reestimating! The best way to calculate the EAC : AC + (ETC calculated by reestimating) The only way to calculate the Duration Slippage of project: Rescheduling! Do not use some unapproved formulas such as “Remaining time / SPI”! (this formula is one of the several ways to forecast the completion date of an activity not whole of the project or even a work package!) The only way to calculate the Time Behind : Data Date - The date that (S% = to-date A%) OR my suggestion: The date that (A% = to-date S%) – Data Date Attention!
  • 28. 28 University of Tehran, Project Management Information System (PMIS), Dr. Sasan Hosseyni, xwir@yahoo.com, 2018 Data Date (Time Now) AC PV EV Time Value Replan (New PV) Forecast for AC (rough estimate) Duration Slippage Forecasted Completion Date (Accepted by Project Client)
  • 29. 29 University of Tehran, Project Management Information System (PMIS), Dr. Sasan Hosseyni, xwir@yahoo.com, 2018 Data Date (Time Now) AC PV EV Time Value Catch up Plan (New PV on Catch up path) Forecast for AC (rough estimate)
  • 30. 30 University of Tehran, Project Management Information System (PMIS), Dr. Sasan Hosseyni, xwir@yahoo.com, 2018 Reschedule: Scheduling the project on a new Data Date • Usually every month  to report the project status Replan: Planning the project again! (to create a new baseline) • After rescheduling, if Schedule Variance > 25% and/or project plan is not realistic/applicable anymore • After replan, the new baseline (New PV) and “forecasted completion date” should be approved by project client Catch-up Plan: Replan without change in “Completion Date” • After replan, the new baseline (New PV) should be approved by project client Reschedule Vs. Replan
  • 31. 31 University of Tehran, Project Management Information System (PMIS), Dr. Sasan Hosseyni, xwir@yahoo.com, 2018 SPI Trend Data Date 0% 100% PV EV Alert! - descending for 4 periods 0.6 0.8 1.0 SPI = EV / PV Safe Warning Danger