SlideShare a Scribd company logo
Project Management
    Case Study
  USPS Mail Processing Infrastructure
       Project (AKA-MPI Project)
        Project segment name:
Palantine distribution processing plant –
            Palantine, Illinois
Concept
   High speed data network to connect all
    aspects of all types of mail sorting and
    processing equipment networked together.
SOW
This statement of work defines the requirements
  for upgrading the existing base band local area
  network (LAN) wiring at mail processing plants
  to meet current wiring standards for “USPS
  structured wiring”. It includes pre-installation,
  installation, and post installation activities
  necessary for successful structured wiring
  implementation. The USPS has named this
  wiring effort the “Mail Processing Infrastructure
  (MPI) program.
In a nutshell
   The project consisted of :
     Building  out a new Data Center
     Multiple IDF’s (Intermediate Distribution
      Cabinets)
     Installing the cabling infrastructure including
      laser optimized 50/1.25 MM fiber optic
      backbones
     Cat. 6 copper for horizontal distribution.
Design
The design was to be a zone wiring
 topology. This was a “Davis Bacon”
 project using CLIN coding for all cost
 tracking and billing.
Design (continued)
• Fiber optic backbones would be run in conduit to
  the distribution cabinets which had to be
  elevated at 9 ft above the work floor so as to be
  out of harms way of the flow of vehicles and
  carts.
• Twelve Cat. 6 cables would then be run in
  conduit from the IDF cabinets to zone boxes
  located 18 ft AFF near the 2 lines of equipment
  that it would be supporting.
• Six Cat. 6 cables would be run in conduit from
  the zone box to the head end of the equipment
  line.
Planning

 The complexity of the project required that
  a detail site survey needed to be
  conducted as drawings could not verify
  pathways around the many mechanical
  systems in the plant.
Planning

 A boom lift was rented and my foreman
   and I spent more than a week scouring
   the 32 foot high ceiling superstructure
   documenting every conduit bend and
   transition. We also had to come up with
   very creative ways to hang the IDF
   cabinets from the ceiling structure to the
   specified 9 ft AFF height.
Planning

 Analysis had to be made for every part and
  piece of hardware to be installed. Each
  part had to match a CLIN code as
  specified by the USPS or payment for
  that item would not be made. Careful
  documentation had to be maintained.
Planning
  Storage was limited at this site so careful planning for
   delivery of product had to be considered
  Contractor parking was also limited so transporting the
   technicians to the site had to be accounted for.
  The plant operations were 24/7 so scheduling of work
   around moving machinery needed to be defined.
  Travel expenses had to be calculated and accounted
   for.
  Coordination of efforts with on site IT staff and facilities
   maintenance dept.
Implementation
Deployment tasks:
• Materials had to be ordered.
• Equipment needed to be delivered to
  site
• Technicians had to be recruited.
• Training of techs to USPS standards
  and scope of work
• USPS safety standards had to be
  adhered to.
Implementation
Management tasks:
• Track all progress
• Requests for information or
  clarification.
• Schedule progress meetings
• Define milestones
• Prepare for USPS bi-weekly
  inspections
• Execute work on punch list
Implementation
Labor:
• All technicians had to pass government
  security clearances.
• 4 ten hour shifts were worked to reduce
  travel expenses
• 90% of work was on lift equipment, safety
  harnesses needed for each technician.

Sharing of equipment became problematic
Project starts to turn south

• Failing inspections or delay
• Rework causes more delay
• Poor communication channel between
 USPS facilities personnel and contractors.
It gets worse

• Foreman tries to push techs
• Crew finds a way to skew progress
• Foreman reports skewed progress to
  Project Manager
• PM didn’t verify work.
• Crew morale drops, production slows
• Foreman gets in over his head and tries to
  give up.
Resolution

   Kick in overtime
   Recruit more technicians
   PM on site every day
   Start a second shift crew
   Deploy more equipment
Project wrap up
► Project   was inspected on scheduled due
  date
► Inspections failed
► Punch list and rework was completed within
  two weeks
► Cost overruns were substantially beyond
  budget
Conclusion
 Profit went out the window
 Company took a loss
 Disgruntled technicians left company
 Company morale is down on other
  projects

More Related Content

What's hot

Using Real-time Smoothness Equipment to Achieve Smoother Pavements
Using Real-time Smoothness Equipment to Achieve Smoother PavementsUsing Real-time Smoothness Equipment to Achieve Smoother Pavements
Using Real-time Smoothness Equipment to Achieve Smoother Pavements
Jill Reeves
 
Rockwell Automation TechED 2017 - AP14 - MRWPCA
Rockwell Automation TechED 2017 - AP14 - MRWPCARockwell Automation TechED 2017 - AP14 - MRWPCA
Rockwell Automation TechED 2017 - AP14 - MRWPCA
Rockwell Automation
 
Stringless Paving: Preparing & Handling Models
Stringless Paving: Preparing & Handling ModelsStringless Paving: Preparing & Handling Models
Stringless Paving: Preparing & Handling Models
Jill Reeves
 
Service revamp lean six sigma black belt project
Service revamp lean six sigma black belt projectService revamp lean six sigma black belt project
Service revamp lean six sigma black belt project
Sumit K Jha
 
CV of Tahir Mahmood
CV of Tahir MahmoodCV of Tahir Mahmood
CV of Tahir Mahmood
Tahir Mahmood
 
Updated Umang resume
Updated Umang resumeUpdated Umang resume
Updated Umang resumeUmang Tailor
 
ENGINEER MUHAMMED ZAFAR SHAH 2
ENGINEER MUHAMMED ZAFAR SHAH 2ENGINEER MUHAMMED ZAFAR SHAH 2
ENGINEER MUHAMMED ZAFAR SHAH 2Zafar Bokhari
 
FC VSM Presentation Future State Aug 5 -7 2013
FC VSM Presentation Future State Aug 5 -7  2013FC VSM Presentation Future State Aug 5 -7  2013
FC VSM Presentation Future State Aug 5 -7 2013Donna Skala
 
DavidReid Revised Resume 2
DavidReid Revised Resume 2DavidReid Revised Resume 2
DavidReid Revised Resume 2DAVID REID
 
Karl j gabel resume
Karl j gabel resumeKarl j gabel resume
Karl j gabel resume
KarlGabel
 

What's hot (20)

E&I QAQC Rajakumar Velayuthan
E&I QAQC  Rajakumar VelayuthanE&I QAQC  Rajakumar Velayuthan
E&I QAQC Rajakumar Velayuthan
 
Using Real-time Smoothness Equipment to Achieve Smoother Pavements
Using Real-time Smoothness Equipment to Achieve Smoother PavementsUsing Real-time Smoothness Equipment to Achieve Smoother Pavements
Using Real-time Smoothness Equipment to Achieve Smoother Pavements
 
Rockwell Automation TechED 2017 - AP14 - MRWPCA
Rockwell Automation TechED 2017 - AP14 - MRWPCARockwell Automation TechED 2017 - AP14 - MRWPCA
Rockwell Automation TechED 2017 - AP14 - MRWPCA
 
Stringless Paving: Preparing & Handling Models
Stringless Paving: Preparing & Handling ModelsStringless Paving: Preparing & Handling Models
Stringless Paving: Preparing & Handling Models
 
D. Medina's CV (01)
D. Medina's CV (01)D. Medina's CV (01)
D. Medina's CV (01)
 
maurice pie eslao
maurice pie eslaomaurice pie eslao
maurice pie eslao
 
Resume-Bill_2016
Resume-Bill_2016Resume-Bill_2016
Resume-Bill_2016
 
Service revamp lean six sigma black belt project
Service revamp lean six sigma black belt projectService revamp lean six sigma black belt project
Service revamp lean six sigma black belt project
 
C.Rajesh-ICE
C.Rajesh-ICEC.Rajesh-ICE
C.Rajesh-ICE
 
SteveResumeLinked
SteveResumeLinkedSteveResumeLinked
SteveResumeLinked
 
CV of Tahir Mahmood
CV of Tahir MahmoodCV of Tahir Mahmood
CV of Tahir Mahmood
 
Updated Umang resume
Updated Umang resumeUpdated Umang resume
Updated Umang resume
 
ENGINEER MUHAMMED ZAFAR SHAH 2
ENGINEER MUHAMMED ZAFAR SHAH 2ENGINEER MUHAMMED ZAFAR SHAH 2
ENGINEER MUHAMMED ZAFAR SHAH 2
 
FC VSM Presentation Future State Aug 5 -7 2013
FC VSM Presentation Future State Aug 5 -7  2013FC VSM Presentation Future State Aug 5 -7  2013
FC VSM Presentation Future State Aug 5 -7 2013
 
OMPRAKASH_Resume
OMPRAKASH_ResumeOMPRAKASH_Resume
OMPRAKASH_Resume
 
vijins new-11-2016
vijins new-11-2016vijins new-11-2016
vijins new-11-2016
 
Ashish Resume
Ashish ResumeAshish Resume
Ashish Resume
 
DavidReid Revised Resume 2
DavidReid Revised Resume 2DavidReid Revised Resume 2
DavidReid Revised Resume 2
 
Jeff Ross Resume
Jeff Ross ResumeJeff Ross Resume
Jeff Ross Resume
 
Karl j gabel resume
Karl j gabel resumeKarl j gabel resume
Karl j gabel resume
 

Similar to PM Sase Study USPS MPI Project-Palantine

PM Case Study USPS MPI Project-Cardiss Collins P&DC-Chicago
PM Case Study USPS MPI Project-Cardiss Collins P&DC-ChicagoPM Case Study USPS MPI Project-Cardiss Collins P&DC-Chicago
PM Case Study USPS MPI Project-Cardiss Collins P&DC-ChicagoDennis Usky
 
Victor Holderby - Project Manger
Victor Holderby - Project MangerVictor Holderby - Project Manger
Victor Holderby - Project MangerVictor Holderby
 
Overview Of Major Project Efforts
Overview Of Major Project EffortsOverview Of Major Project Efforts
Overview Of Major Project Effortsskvanbibber
 
ayed cv.newest one 23.11.2011
ayed cv.newest one 23.11.2011ayed cv.newest one 23.11.2011
ayed cv.newest one 23.11.2011Iyad Hassan
 
Chris_Chambers_Facilities
Chris_Chambers_FacilitiesChris_Chambers_Facilities
Chris_Chambers_FacilitiesChris Chambers
 
Bill Rogers CV 19-01-15
Bill Rogers CV 19-01-15Bill Rogers CV 19-01-15
Bill Rogers CV 19-01-15Bill Rogers
 
Dcs capabilities
Dcs capabilitiesDcs capabilities
Dcs capabilities
Generic Logical
 
Connecting offshore platforms to a subsea cable system
Connecting offshore platforms to a subsea cable system Connecting offshore platforms to a subsea cable system
Connecting offshore platforms to a subsea cable system
Jerry Brown
 
Customer presentation
Customer presentationCustomer presentation
Customer presentation
Daniel Webb
 
Leadership TheoriesWrite a 700- to 1,050-word paper that addre.docx
Leadership TheoriesWrite a 700- to 1,050-word paper that addre.docxLeadership TheoriesWrite a 700- to 1,050-word paper that addre.docx
Leadership TheoriesWrite a 700- to 1,050-word paper that addre.docx
smile790243
 
Leak d Detection feasibility study iFluids Engineering
Leak d Detection feasibility study iFluids EngineeringLeak d Detection feasibility study iFluids Engineering
Leak d Detection feasibility study iFluids Engineering
John Kingsley
 
Baumann, Erik Resume 1
Baumann, Erik Resume 1Baumann, Erik Resume 1
Baumann, Erik Resume 1Erik Baumann
 
Baumann, Erik Resume 1
Baumann, Erik Resume 1Baumann, Erik Resume 1
Baumann, Erik Resume 1Erik Baumann
 

Similar to PM Sase Study USPS MPI Project-Palantine (20)

PM Case Study USPS MPI Project-Cardiss Collins P&DC-Chicago
PM Case Study USPS MPI Project-Cardiss Collins P&DC-ChicagoPM Case Study USPS MPI Project-Cardiss Collins P&DC-Chicago
PM Case Study USPS MPI Project-Cardiss Collins P&DC-Chicago
 
Victor Holderby - Project Manger
Victor Holderby - Project MangerVictor Holderby - Project Manger
Victor Holderby - Project Manger
 
Overview Of Major Project Efforts
Overview Of Major Project EffortsOverview Of Major Project Efforts
Overview Of Major Project Efforts
 
ayed cv.newest one 23.11.2011
ayed cv.newest one 23.11.2011ayed cv.newest one 23.11.2011
ayed cv.newest one 23.11.2011
 
GRANT DELP724
GRANT DELP724GRANT DELP724
GRANT DELP724
 
ProjectExamples
ProjectExamplesProjectExamples
ProjectExamples
 
Ariel Pantaleon - CV
Ariel Pantaleon - CVAriel Pantaleon - CV
Ariel Pantaleon - CV
 
PPI ALTA 201_b
PPI ALTA 201_bPPI ALTA 201_b
PPI ALTA 201_b
 
Ravi-apr30
Ravi-apr30Ravi-apr30
Ravi-apr30
 
James Bullen CV
James Bullen CVJames Bullen CV
James Bullen CV
 
Robert-Project Presentation
Robert-Project PresentationRobert-Project Presentation
Robert-Project Presentation
 
Chris_Chambers_Facilities
Chris_Chambers_FacilitiesChris_Chambers_Facilities
Chris_Chambers_Facilities
 
Bill Rogers CV 19-01-15
Bill Rogers CV 19-01-15Bill Rogers CV 19-01-15
Bill Rogers CV 19-01-15
 
Dcs capabilities
Dcs capabilitiesDcs capabilities
Dcs capabilities
 
Connecting offshore platforms to a subsea cable system
Connecting offshore platforms to a subsea cable system Connecting offshore platforms to a subsea cable system
Connecting offshore platforms to a subsea cable system
 
Customer presentation
Customer presentationCustomer presentation
Customer presentation
 
Leadership TheoriesWrite a 700- to 1,050-word paper that addre.docx
Leadership TheoriesWrite a 700- to 1,050-word paper that addre.docxLeadership TheoriesWrite a 700- to 1,050-word paper that addre.docx
Leadership TheoriesWrite a 700- to 1,050-word paper that addre.docx
 
Leak d Detection feasibility study iFluids Engineering
Leak d Detection feasibility study iFluids EngineeringLeak d Detection feasibility study iFluids Engineering
Leak d Detection feasibility study iFluids Engineering
 
Baumann, Erik Resume 1
Baumann, Erik Resume 1Baumann, Erik Resume 1
Baumann, Erik Resume 1
 
Baumann, Erik Resume 1
Baumann, Erik Resume 1Baumann, Erik Resume 1
Baumann, Erik Resume 1
 

Recently uploaded

Maximize Your Content with Beautiful Assets : Content & Asset for Landing Page
Maximize Your Content with Beautiful Assets : Content & Asset for Landing Page Maximize Your Content with Beautiful Assets : Content & Asset for Landing Page
Maximize Your Content with Beautiful Assets : Content & Asset for Landing Page
pmgdscunsri
 
Game Concept Presentation for Ukrainian Mythology Based Game With Designs
Game Concept Presentation for Ukrainian Mythology Based Game With DesignsGame Concept Presentation for Ukrainian Mythology Based Game With Designs
Game Concept Presentation for Ukrainian Mythology Based Game With Designs
184804
 
原版定做(penn毕业证书)美国宾夕法尼亚大学毕业证文凭学历证书原版一模一样
原版定做(penn毕业证书)美国宾夕法尼亚大学毕业证文凭学历证书原版一模一样原版定做(penn毕业证书)美国宾夕法尼亚大学毕业证文凭学历证书原版一模一样
原版定做(penn毕业证书)美国宾夕法尼亚大学毕业证文凭学历证书原版一模一样
gpffo76j
 
RTUYUIJKLDSADAGHBDJNKSMAL,D
RTUYUIJKLDSADAGHBDJNKSMAL,DRTUYUIJKLDSADAGHBDJNKSMAL,D
RTUYUIJKLDSADAGHBDJNKSMAL,D
cy0krjxt
 
Design Thinking Design thinking Design thinking
Design Thinking Design thinking Design thinkingDesign Thinking Design thinking Design thinking
Design Thinking Design thinking Design thinking
cy0krjxt
 
Can AI do good? at 'offtheCanvas' India HCI prelude
Can AI do good? at 'offtheCanvas' India HCI preludeCan AI do good? at 'offtheCanvas' India HCI prelude
Can AI do good? at 'offtheCanvas' India HCI prelude
Alan Dix
 
Portfolio.pdf
Portfolio.pdfPortfolio.pdf
Portfolio.pdf
garcese
 
Borys Sutkowski portfolio interior design
Borys Sutkowski portfolio interior designBorys Sutkowski portfolio interior design
Borys Sutkowski portfolio interior design
boryssutkowski
 
UNIT IV-VISUAL STYLE AND MOBILE INTERFACES.pptx
UNIT IV-VISUAL STYLE AND MOBILE INTERFACES.pptxUNIT IV-VISUAL STYLE AND MOBILE INTERFACES.pptx
UNIT IV-VISUAL STYLE AND MOBILE INTERFACES.pptx
GOWSIKRAJA PALANISAMY
 
一比一原版(CITY毕业证书)谢菲尔德哈勒姆大学毕业证如何办理
一比一原版(CITY毕业证书)谢菲尔德哈勒姆大学毕业证如何办理一比一原版(CITY毕业证书)谢菲尔德哈勒姆大学毕业证如何办理
一比一原版(CITY毕业证书)谢菲尔德哈勒姆大学毕业证如何办理
9a93xvy
 
Коричневый и Кремовый Деликатный Органический Копирайтер Фрилансер Марке...
Коричневый и Кремовый Деликатный Органический Копирайтер Фрилансер Марке...Коричневый и Кремовый Деликатный Органический Копирайтер Фрилансер Марке...
Коричневый и Кремовый Деликатный Органический Копирайтер Фрилансер Марке...
ameli25062005
 
Moldes de letra 3D Alfabeto completo esp
Moldes de letra 3D Alfabeto completo espMoldes de letra 3D Alfabeto completo esp
Moldes de letra 3D Alfabeto completo esp
Hess9
 
Mohannad Abdullah portfolio _ V2 _22-24
Mohannad Abdullah  portfolio _ V2 _22-24Mohannad Abdullah  portfolio _ V2 _22-24
Mohannad Abdullah portfolio _ V2 _22-24
M. A. Architect
 
Research 20 slides Amelia gavryliuks.pdf
Research 20 slides Amelia gavryliuks.pdfResearch 20 slides Amelia gavryliuks.pdf
Research 20 slides Amelia gavryliuks.pdf
ameli25062005
 
Transforming Brand Perception and Boosting Profitability
Transforming Brand Perception and Boosting ProfitabilityTransforming Brand Perception and Boosting Profitability
Transforming Brand Perception and Boosting Profitability
aaryangarg12
 
一比一原版(Brunel毕业证书)布鲁内尔大学毕业证成绩单如何办理
一比一原版(Brunel毕业证书)布鲁内尔大学毕业证成绩单如何办理一比一原版(Brunel毕业证书)布鲁内尔大学毕业证成绩单如何办理
一比一原版(Brunel毕业证书)布鲁内尔大学毕业证成绩单如何办理
smpc3nvg
 
Book Formatting: Quality Control Checks for Designers
Book Formatting: Quality Control Checks for DesignersBook Formatting: Quality Control Checks for Designers
Book Formatting: Quality Control Checks for Designers
Confidence Ago
 
20 slides of research movie and artists .pdf
20 slides of research movie and artists .pdf20 slides of research movie and artists .pdf
20 slides of research movie and artists .pdf
ameli25062005
 
一比一原版(Bristol毕业证书)布里斯托大学毕业证成绩单如何办理
一比一原版(Bristol毕业证书)布里斯托大学毕业证成绩单如何办理一比一原版(Bristol毕业证书)布里斯托大学毕业证成绩单如何办理
一比一原版(Bristol毕业证书)布里斯托大学毕业证成绩单如何办理
smpc3nvg
 
一比一原版(MMU毕业证书)曼彻斯特城市大学毕业证成绩单如何办理
一比一原版(MMU毕业证书)曼彻斯特城市大学毕业证成绩单如何办理一比一原版(MMU毕业证书)曼彻斯特城市大学毕业证成绩单如何办理
一比一原版(MMU毕业证书)曼彻斯特城市大学毕业证成绩单如何办理
7sd8fier
 

Recently uploaded (20)

Maximize Your Content with Beautiful Assets : Content & Asset for Landing Page
Maximize Your Content with Beautiful Assets : Content & Asset for Landing Page Maximize Your Content with Beautiful Assets : Content & Asset for Landing Page
Maximize Your Content with Beautiful Assets : Content & Asset for Landing Page
 
Game Concept Presentation for Ukrainian Mythology Based Game With Designs
Game Concept Presentation for Ukrainian Mythology Based Game With DesignsGame Concept Presentation for Ukrainian Mythology Based Game With Designs
Game Concept Presentation for Ukrainian Mythology Based Game With Designs
 
原版定做(penn毕业证书)美国宾夕法尼亚大学毕业证文凭学历证书原版一模一样
原版定做(penn毕业证书)美国宾夕法尼亚大学毕业证文凭学历证书原版一模一样原版定做(penn毕业证书)美国宾夕法尼亚大学毕业证文凭学历证书原版一模一样
原版定做(penn毕业证书)美国宾夕法尼亚大学毕业证文凭学历证书原版一模一样
 
RTUYUIJKLDSADAGHBDJNKSMAL,D
RTUYUIJKLDSADAGHBDJNKSMAL,DRTUYUIJKLDSADAGHBDJNKSMAL,D
RTUYUIJKLDSADAGHBDJNKSMAL,D
 
Design Thinking Design thinking Design thinking
Design Thinking Design thinking Design thinkingDesign Thinking Design thinking Design thinking
Design Thinking Design thinking Design thinking
 
Can AI do good? at 'offtheCanvas' India HCI prelude
Can AI do good? at 'offtheCanvas' India HCI preludeCan AI do good? at 'offtheCanvas' India HCI prelude
Can AI do good? at 'offtheCanvas' India HCI prelude
 
Portfolio.pdf
Portfolio.pdfPortfolio.pdf
Portfolio.pdf
 
Borys Sutkowski portfolio interior design
Borys Sutkowski portfolio interior designBorys Sutkowski portfolio interior design
Borys Sutkowski portfolio interior design
 
UNIT IV-VISUAL STYLE AND MOBILE INTERFACES.pptx
UNIT IV-VISUAL STYLE AND MOBILE INTERFACES.pptxUNIT IV-VISUAL STYLE AND MOBILE INTERFACES.pptx
UNIT IV-VISUAL STYLE AND MOBILE INTERFACES.pptx
 
一比一原版(CITY毕业证书)谢菲尔德哈勒姆大学毕业证如何办理
一比一原版(CITY毕业证书)谢菲尔德哈勒姆大学毕业证如何办理一比一原版(CITY毕业证书)谢菲尔德哈勒姆大学毕业证如何办理
一比一原版(CITY毕业证书)谢菲尔德哈勒姆大学毕业证如何办理
 
Коричневый и Кремовый Деликатный Органический Копирайтер Фрилансер Марке...
Коричневый и Кремовый Деликатный Органический Копирайтер Фрилансер Марке...Коричневый и Кремовый Деликатный Органический Копирайтер Фрилансер Марке...
Коричневый и Кремовый Деликатный Органический Копирайтер Фрилансер Марке...
 
Moldes de letra 3D Alfabeto completo esp
Moldes de letra 3D Alfabeto completo espMoldes de letra 3D Alfabeto completo esp
Moldes de letra 3D Alfabeto completo esp
 
Mohannad Abdullah portfolio _ V2 _22-24
Mohannad Abdullah  portfolio _ V2 _22-24Mohannad Abdullah  portfolio _ V2 _22-24
Mohannad Abdullah portfolio _ V2 _22-24
 
Research 20 slides Amelia gavryliuks.pdf
Research 20 slides Amelia gavryliuks.pdfResearch 20 slides Amelia gavryliuks.pdf
Research 20 slides Amelia gavryliuks.pdf
 
Transforming Brand Perception and Boosting Profitability
Transforming Brand Perception and Boosting ProfitabilityTransforming Brand Perception and Boosting Profitability
Transforming Brand Perception and Boosting Profitability
 
一比一原版(Brunel毕业证书)布鲁内尔大学毕业证成绩单如何办理
一比一原版(Brunel毕业证书)布鲁内尔大学毕业证成绩单如何办理一比一原版(Brunel毕业证书)布鲁内尔大学毕业证成绩单如何办理
一比一原版(Brunel毕业证书)布鲁内尔大学毕业证成绩单如何办理
 
Book Formatting: Quality Control Checks for Designers
Book Formatting: Quality Control Checks for DesignersBook Formatting: Quality Control Checks for Designers
Book Formatting: Quality Control Checks for Designers
 
20 slides of research movie and artists .pdf
20 slides of research movie and artists .pdf20 slides of research movie and artists .pdf
20 slides of research movie and artists .pdf
 
一比一原版(Bristol毕业证书)布里斯托大学毕业证成绩单如何办理
一比一原版(Bristol毕业证书)布里斯托大学毕业证成绩单如何办理一比一原版(Bristol毕业证书)布里斯托大学毕业证成绩单如何办理
一比一原版(Bristol毕业证书)布里斯托大学毕业证成绩单如何办理
 
一比一原版(MMU毕业证书)曼彻斯特城市大学毕业证成绩单如何办理
一比一原版(MMU毕业证书)曼彻斯特城市大学毕业证成绩单如何办理一比一原版(MMU毕业证书)曼彻斯特城市大学毕业证成绩单如何办理
一比一原版(MMU毕业证书)曼彻斯特城市大学毕业证成绩单如何办理
 

PM Sase Study USPS MPI Project-Palantine

  • 1. Project Management Case Study USPS Mail Processing Infrastructure Project (AKA-MPI Project) Project segment name: Palantine distribution processing plant – Palantine, Illinois
  • 2. Concept  High speed data network to connect all aspects of all types of mail sorting and processing equipment networked together.
  • 3. SOW This statement of work defines the requirements for upgrading the existing base band local area network (LAN) wiring at mail processing plants to meet current wiring standards for “USPS structured wiring”. It includes pre-installation, installation, and post installation activities necessary for successful structured wiring implementation. The USPS has named this wiring effort the “Mail Processing Infrastructure (MPI) program.
  • 4. In a nutshell  The project consisted of :  Building out a new Data Center  Multiple IDF’s (Intermediate Distribution Cabinets)  Installing the cabling infrastructure including laser optimized 50/1.25 MM fiber optic backbones  Cat. 6 copper for horizontal distribution.
  • 5. Design The design was to be a zone wiring topology. This was a “Davis Bacon” project using CLIN coding for all cost tracking and billing.
  • 6. Design (continued) • Fiber optic backbones would be run in conduit to the distribution cabinets which had to be elevated at 9 ft above the work floor so as to be out of harms way of the flow of vehicles and carts. • Twelve Cat. 6 cables would then be run in conduit from the IDF cabinets to zone boxes located 18 ft AFF near the 2 lines of equipment that it would be supporting. • Six Cat. 6 cables would be run in conduit from the zone box to the head end of the equipment line.
  • 7. Planning The complexity of the project required that a detail site survey needed to be conducted as drawings could not verify pathways around the many mechanical systems in the plant.
  • 8. Planning A boom lift was rented and my foreman and I spent more than a week scouring the 32 foot high ceiling superstructure documenting every conduit bend and transition. We also had to come up with very creative ways to hang the IDF cabinets from the ceiling structure to the specified 9 ft AFF height.
  • 9. Planning Analysis had to be made for every part and piece of hardware to be installed. Each part had to match a CLIN code as specified by the USPS or payment for that item would not be made. Careful documentation had to be maintained.
  • 10. Planning  Storage was limited at this site so careful planning for delivery of product had to be considered  Contractor parking was also limited so transporting the technicians to the site had to be accounted for.  The plant operations were 24/7 so scheduling of work around moving machinery needed to be defined.  Travel expenses had to be calculated and accounted for.  Coordination of efforts with on site IT staff and facilities maintenance dept.
  • 11. Implementation Deployment tasks: • Materials had to be ordered. • Equipment needed to be delivered to site • Technicians had to be recruited. • Training of techs to USPS standards and scope of work • USPS safety standards had to be adhered to.
  • 12. Implementation Management tasks: • Track all progress • Requests for information or clarification. • Schedule progress meetings • Define milestones • Prepare for USPS bi-weekly inspections • Execute work on punch list
  • 13. Implementation Labor: • All technicians had to pass government security clearances. • 4 ten hour shifts were worked to reduce travel expenses • 90% of work was on lift equipment, safety harnesses needed for each technician. Sharing of equipment became problematic
  • 14. Project starts to turn south • Failing inspections or delay • Rework causes more delay • Poor communication channel between USPS facilities personnel and contractors.
  • 15. It gets worse • Foreman tries to push techs • Crew finds a way to skew progress • Foreman reports skewed progress to Project Manager • PM didn’t verify work. • Crew morale drops, production slows • Foreman gets in over his head and tries to give up.
  • 16. Resolution  Kick in overtime  Recruit more technicians  PM on site every day  Start a second shift crew  Deploy more equipment
  • 17. Project wrap up ► Project was inspected on scheduled due date ► Inspections failed ► Punch list and rework was completed within two weeks ► Cost overruns were substantially beyond budget
  • 18. Conclusion  Profit went out the window  Company took a loss  Disgruntled technicians left company  Company morale is down on other projects