CAREER SUMMARY:
Having 6+ years of experience as a Sr. Engineer / Engineer in EPC power industry.
• Preparation of Technical Specifications related to Electrical System, Single Line Diagrams, Control schemes,
Layouts, and developing drawings as per Site requirement using AUTOCAD.
• Basic Design, Detailed Engineering, Project Co-ordination and commissioning of Power & Distribution
Transformers, 132KV Switchyard equipment, 6.6KV HT Panels, 415V PMCC & MCC Panels, AC & DC Distribution
Boards, LDB’s, Batteries & Battery Charger, UPS, HT & LT Cables, Earthing and Lightening Protection system,
Illumination system etc.
• Preparation of Bill of Quantities (BOQ) & Costing for Electrical System.
• Preparation of Material indents as per the Site requirement in SAP.
• Review of drawing and documents submitted by Vendors and approving the same.
• Releasing of Approved Drawings to site for Erection and commissioning activities.
• Tendering for Electrical system of Power plants ranging from 10MW to 250MW and Sub-stations upto 132KV
voltage level.
• Knowledge on Power Trading through open access.
PROFESSIONAL EXPERIENCE: (Total Work Experience ≈ 6 years 5 months)
Working as Sr. Engineer in M/s Lake Cement Limited, Dar Es Salaam, Tanzania from Jan-2014 to June-2015.
WORK PROFILE:-
Erection, Commissioning, Operation and Maintenance of 1x10MW Coal Based Power Plant at Kimbiji, Dar es salaam,
Tanzania.
• Involved in Testing and Commissioning of 12.5MVA Power Transformer and 2MVA Auxiliary Transformers.
• Involved in Testing and Commissioning Activities of HT Panel And LT MCC Panels.
• Testing, Commissioning, Operation and Maintenance of 3X 2MVA Cummins make DG Sets and its 6.6KV HT
Panels.
• Operation and Maintenance of all BOP Equipments like HT Panels (6.6KV), LT PCC and other MCC’s.
• Operation and Maintenance of all LT Motors.
• Preparation of Preventive maintenance Schedule and Shutdown jobs.
• Preparation of Daily and Monthly Generation Reports for both Power Plant and Cement Plant.
Worked as Engineer in My Home Industries Limited, Hyderabad from June-2013 to Dec-13.
WORK PROFILE:-
Operation and Maintenance of 1x60 MW Coal Based Power Plant at Melacheruvu, Nalgonda District, Andhra
Pradesh, India.
• Operation and Maintenance of 132 KV Switchyard equipment’s ie., Circuit Breakers, Current Transformers,
Potential Transformers, Isolators, LA, Control & Relay Panels.
• Operation and Maintenance of BOP Electrical equipment’s ie., HT Panels (6.6KV), LT MCC panels, VFD Panels,
Distribution Boards etc.
• Operation and Maintenance of HT and LT Motors.
• Erection, Testing and Commissioning of new equipment for the improvement of the Plant Performance ie.,
Capacitor Bank Panels, Auto Synchronization panels, EDS, Remote tripping system based on load shedding
etc.
• Erection, Testing and Commissioning of RTU system and OLTE as per the APTRANSCO guide lines.
• Participating in Plant Performance Review meetings conducted at Site.
• Preparation of Material indents as per the Site requirement in SAP.
Worked as Engineer in My Home Power Consultancy Services Limited, Hyderabad from April 2011 to May
2013.
WORK PROFILE:-
Project Co-ordination for 1x60MW Coal Based Power Plant at Melacheruvu, Nalgonda District, Andhra Pradesh,
India.
• Engineering and Project Co-ordination, Erection,Testing and Commissioning of Power & Distribution
Transformers, 132KV Switchyard equipment i.e., Circuit Breakers, Isolators, Current Transformers, Voltage
Transformers, Lightening Arrestors, Control and Relay panels.
• Engineering and Project Co-ordination, Testing and Commissioning of Electrical system related to BHEL make
60MW Turbine Generator (TG) set and TG set related auxiliary panels like IPBD, LAVT Panel, NGT, Generator
Control desk, Protection and Relay panels, AVR.
• Engineering and Project Co-ordination, Erection,Testing and Commissioning of 6.6KV HT Panels, 415V PMCC
& MCC Panels, AC & DC Distribution Boards, LDB’s, Batteries & Battery Charger, UPS, HT & LT Cables,
Earthing and Lightening Protection system, Illumination system etc.
• Engineering and Project Co-ordination,Erection, Testing and Commissioning of Electrical system related to
Raw Water intake system consisting of 6.6KV Line, Transformer, LT Panels and Motors.
• Releasing of Approved Drawings to site for Erection and commissioning activities.
• Monitoring the progress of work at site and Preparation of monthly Progress Reports.
Worked as Engineer in Amreli Power Projects (P) Ltd, a SPV of Zenith Energy Ltd, Hyderabad from April
2010 to March 2011.
WORK PROFILE:-
Project Co-ordination based at Head Office for 10 MW Biomass Based Power Plant at Amreli District, Gujarat, India.
• Preparation of specification for Electrical Packages.
• Floating of enquires to Vendor for different package (Both Mechanical and Electrical)
• Reviewing the offers submitted by the vendors and preparation of comparison statements.
• Preparation of LOI, Purchase and Work orders.
• Co-ordination with vendors after finalization of the order and reviewing the Documents and Drawings
Submitted by Vendor and forwarding the approved drawings to the site for erection.
• Co-ordination with site Engineers in implementation of the project.
• Participating in technical discussion and progress review meeting with the suppliers
• Processing the invoices and RA bills submitted by Vendors and Contractors.
• Monitoring the progress of work at site with the schedule and Preparation of monthly Progress Reports.
• Visiting the site for reviewing the progress.
• Participated in the commissioning activities of the Plant and synchronizing with the grid.
Worked as a Jr.Engineer – Electrical in ALLIED ENGINEERING PVT LIMITED from June 08 to March 10
Under L&T . in VIZAG Steel Plant for the construction of Blast Furnace (BF#3).
WORK PROFILE:-
• Review of drawing released for construction
• Preparation of Bill of quantities
• Participating in Technical discussion with Owner Engineers
• Planning of daily works and assigning works to the workers
• Preparation of Daily Progress Report
• Worked on lighting protection to the buildings and machine equipments.
• 415 V line work
• Installation of Outdoor and Indoor lighting
• Earthing work using MS Flat.
• Laying of Cable trays, running cable in the tray through JB’s to the MCCDB’s. Fitting supports to lamps etc.
TECHNICAL SKILL SET:
Certification course in ELECTRICAL DESIGN ENGINEERING from Smart Brains Institute of Engineering Design and
Research, Hyderabad, India.
• Preparation of Single Line Diagrams (SLD’s), Load List.
• Transformer Sizing Calculations.
• Generator Sizing Calculations, UPS Sizing Calculations.
• Battery and Battery Charger Sizing Calculations.
• Cable Sizing.
• Lighting Calculations Using CGLUX (Indoor & Outdoor).
• Exposure to System studies e.g. - Load Flow, Short Circuit, Motor Starting on ETAP.
• Earthling Calculations.
• Power Factor Correction Equipment Sizing.
• Knowledge of Hazardous Area Classification.
• Understanding of Various Phases of Projects.
SOFTWARE SKILL SET:
• ETAP Software for System studies (load flow analysis, configuration &case study and also using for circuit
analysis)
• CGLUX Software for Plant lighting &illumination design
• AUTO CAD (2D & 3D Design) Software
• PLC, SCADA, AC DRIVES
• SAP
• Programming languages: C, Oracle
EDUCATION QUALIFICATIONS:
• B.Tech in Electrical and Electronics passed in 2008 from VRS and YRN college of Engineering and Technology,
affiliated to Jawaharlal Nehru technological University, Andhra Pradesh, India.
• Diploma in Electrical and Electronics passed in 2004. From Government polytechnic, Proddatur, Andhra
Pradesh, India.
• S.S.C passed in First divison in 2001 from St Mary’s high school, Bhimavaram, A.P, India.
PERSONAL SKILLS:
• Ability to work individually or in a team environment.
• Ability to work meticulously with careful attention to details.
• Excellent personal interactive and communication skills.
PERSONAL PROFILE:
Father’s name : P.Narasimhudu
Date of birth : 09/08/1986.
Gender : Male.
Marital status : Single.
Nationality : Indian.
Languages known : Telugu, English & Hindi
(P.D.V.Narasimha Rao)

PDV narasimha Rao 6+ (2)

  • 1.
    P.D.V.NARASIMHA RAO Mob No:+91 - 7799265411 Email ID: narasimha.pasupuleti@gmail.com Dr.No.3-536(45A), Ramanjaneyapuram (ST), Yerraguntla (MD), Kadapa (DT), AP. CAREER SUMMARY: Having 6+ years of experience as a Sr. Engineer / Engineer in EPC power industry. • Preparation of Technical Specifications related to Electrical System, Single Line Diagrams, Control schemes, Layouts, and developing drawings as per Site requirement using AUTOCAD. • Basic Design, Detailed Engineering, Project Co-ordination and commissioning of Power & Distribution Transformers, 132KV Switchyard equipment, 6.6KV HT Panels, 415V PMCC & MCC Panels, AC & DC Distribution Boards, LDB’s, Batteries & Battery Charger, UPS, HT & LT Cables, Earthing and Lightening Protection system, Illumination system etc. • Preparation of Bill of Quantities (BOQ) & Costing for Electrical System. • Preparation of Material indents as per the Site requirement in SAP. • Review of drawing and documents submitted by Vendors and approving the same. • Releasing of Approved Drawings to site for Erection and commissioning activities. • Tendering for Electrical system of Power plants ranging from 10MW to 250MW and Sub-stations upto 132KV voltage level. • Knowledge on Power Trading through open access. PROFESSIONAL EXPERIENCE: (Total Work Experience ≈ 6 years 5 months) Working as Sr. Engineer in M/s Lake Cement Limited, Dar Es Salaam, Tanzania from Jan-2014 to June-2015. WORK PROFILE:- Erection, Commissioning, Operation and Maintenance of 1x10MW Coal Based Power Plant at Kimbiji, Dar es salaam, Tanzania. • Involved in Testing and Commissioning of 12.5MVA Power Transformer and 2MVA Auxiliary Transformers. • Involved in Testing and Commissioning Activities of HT Panel And LT MCC Panels. • Testing, Commissioning, Operation and Maintenance of 3X 2MVA Cummins make DG Sets and its 6.6KV HT Panels. • Operation and Maintenance of all BOP Equipments like HT Panels (6.6KV), LT PCC and other MCC’s. • Operation and Maintenance of all LT Motors. • Preparation of Preventive maintenance Schedule and Shutdown jobs. • Preparation of Daily and Monthly Generation Reports for both Power Plant and Cement Plant. Worked as Engineer in My Home Industries Limited, Hyderabad from June-2013 to Dec-13. WORK PROFILE:- Operation and Maintenance of 1x60 MW Coal Based Power Plant at Melacheruvu, Nalgonda District, Andhra Pradesh, India. • Operation and Maintenance of 132 KV Switchyard equipment’s ie., Circuit Breakers, Current Transformers, Potential Transformers, Isolators, LA, Control & Relay Panels. • Operation and Maintenance of BOP Electrical equipment’s ie., HT Panels (6.6KV), LT MCC panels, VFD Panels, Distribution Boards etc. • Operation and Maintenance of HT and LT Motors. • Erection, Testing and Commissioning of new equipment for the improvement of the Plant Performance ie., Capacitor Bank Panels, Auto Synchronization panels, EDS, Remote tripping system based on load shedding etc. • Erection, Testing and Commissioning of RTU system and OLTE as per the APTRANSCO guide lines. • Participating in Plant Performance Review meetings conducted at Site. • Preparation of Material indents as per the Site requirement in SAP. Worked as Engineer in My Home Power Consultancy Services Limited, Hyderabad from April 2011 to May 2013. WORK PROFILE:-
  • 2.
    Project Co-ordination for1x60MW Coal Based Power Plant at Melacheruvu, Nalgonda District, Andhra Pradesh, India. • Engineering and Project Co-ordination, Erection,Testing and Commissioning of Power & Distribution Transformers, 132KV Switchyard equipment i.e., Circuit Breakers, Isolators, Current Transformers, Voltage Transformers, Lightening Arrestors, Control and Relay panels. • Engineering and Project Co-ordination, Testing and Commissioning of Electrical system related to BHEL make 60MW Turbine Generator (TG) set and TG set related auxiliary panels like IPBD, LAVT Panel, NGT, Generator Control desk, Protection and Relay panels, AVR. • Engineering and Project Co-ordination, Erection,Testing and Commissioning of 6.6KV HT Panels, 415V PMCC & MCC Panels, AC & DC Distribution Boards, LDB’s, Batteries & Battery Charger, UPS, HT & LT Cables, Earthing and Lightening Protection system, Illumination system etc. • Engineering and Project Co-ordination,Erection, Testing and Commissioning of Electrical system related to Raw Water intake system consisting of 6.6KV Line, Transformer, LT Panels and Motors. • Releasing of Approved Drawings to site for Erection and commissioning activities. • Monitoring the progress of work at site and Preparation of monthly Progress Reports. Worked as Engineer in Amreli Power Projects (P) Ltd, a SPV of Zenith Energy Ltd, Hyderabad from April 2010 to March 2011. WORK PROFILE:- Project Co-ordination based at Head Office for 10 MW Biomass Based Power Plant at Amreli District, Gujarat, India. • Preparation of specification for Electrical Packages. • Floating of enquires to Vendor for different package (Both Mechanical and Electrical) • Reviewing the offers submitted by the vendors and preparation of comparison statements. • Preparation of LOI, Purchase and Work orders. • Co-ordination with vendors after finalization of the order and reviewing the Documents and Drawings Submitted by Vendor and forwarding the approved drawings to the site for erection. • Co-ordination with site Engineers in implementation of the project. • Participating in technical discussion and progress review meeting with the suppliers • Processing the invoices and RA bills submitted by Vendors and Contractors. • Monitoring the progress of work at site with the schedule and Preparation of monthly Progress Reports. • Visiting the site for reviewing the progress. • Participated in the commissioning activities of the Plant and synchronizing with the grid. Worked as a Jr.Engineer – Electrical in ALLIED ENGINEERING PVT LIMITED from June 08 to March 10 Under L&T . in VIZAG Steel Plant for the construction of Blast Furnace (BF#3). WORK PROFILE:- • Review of drawing released for construction • Preparation of Bill of quantities • Participating in Technical discussion with Owner Engineers • Planning of daily works and assigning works to the workers • Preparation of Daily Progress Report • Worked on lighting protection to the buildings and machine equipments. • 415 V line work • Installation of Outdoor and Indoor lighting • Earthing work using MS Flat. • Laying of Cable trays, running cable in the tray through JB’s to the MCCDB’s. Fitting supports to lamps etc. TECHNICAL SKILL SET: Certification course in ELECTRICAL DESIGN ENGINEERING from Smart Brains Institute of Engineering Design and Research, Hyderabad, India. • Preparation of Single Line Diagrams (SLD’s), Load List. • Transformer Sizing Calculations. • Generator Sizing Calculations, UPS Sizing Calculations. • Battery and Battery Charger Sizing Calculations.
  • 3.
    • Cable Sizing. •Lighting Calculations Using CGLUX (Indoor & Outdoor). • Exposure to System studies e.g. - Load Flow, Short Circuit, Motor Starting on ETAP. • Earthling Calculations. • Power Factor Correction Equipment Sizing. • Knowledge of Hazardous Area Classification. • Understanding of Various Phases of Projects. SOFTWARE SKILL SET: • ETAP Software for System studies (load flow analysis, configuration &case study and also using for circuit analysis) • CGLUX Software for Plant lighting &illumination design • AUTO CAD (2D & 3D Design) Software • PLC, SCADA, AC DRIVES • SAP • Programming languages: C, Oracle EDUCATION QUALIFICATIONS: • B.Tech in Electrical and Electronics passed in 2008 from VRS and YRN college of Engineering and Technology, affiliated to Jawaharlal Nehru technological University, Andhra Pradesh, India. • Diploma in Electrical and Electronics passed in 2004. From Government polytechnic, Proddatur, Andhra Pradesh, India. • S.S.C passed in First divison in 2001 from St Mary’s high school, Bhimavaram, A.P, India. PERSONAL SKILLS: • Ability to work individually or in a team environment. • Ability to work meticulously with careful attention to details. • Excellent personal interactive and communication skills. PERSONAL PROFILE: Father’s name : P.Narasimhudu Date of birth : 09/08/1986. Gender : Male. Marital status : Single. Nationality : Indian. Languages known : Telugu, English & Hindi (P.D.V.Narasimha Rao)