The 2001 foot and mouth outbreak incurred costs over £9 billion, with £3 billion borne by the public sector in direct compensation to farmers, while tourism and related industries suffered approximately £5 billion in unreimbursed losses. The document argues that government flaws in disease control policies and agriculture practices exacerbated the outbreak and that a lack of a comprehensive public inquiry has hindered the identification of lessons learned. It highlights the complexities of agricultural regulations, the impacts of EU policies, and ongoing issues with animal movement and disease prevention that remain unresolved in the aftermath of the crisis.