Open BIM Learning Xchange




        Dr. Howard Jeffrey
          BIM Specialist
            Skanska




1
Presentation content

- Approach to BIM
- Interpretation of BIM
- Challenges
- Opportunities
- Implementation of BIM
- Benefits on Projects
- Open BIM



2
BIM at Skanska
Building Information Modelling
BIM – The Skanska AB Definition:
Building Information Modelling is a method to describe
the building and its spaces, structures, components and
materials with their essential information and properties.
The model is a container for the information.

BIM can also be described as a collaborative approach
making sure the right people get the right project
information at the right time.




“From January 1st 2009 all new Design and Build
projects where design has not yet started – shall adopt
Building Information Modelling”
BIM Plan based upon 16 Areas
          Intelligent                                                                                         Visualizations
                                                                                       Records
         Modelling      Safety Planning         Green BIM
                                                                Facilities Mgt.
                                                                                      Management
          Design

15
                                                                                     As Constructed
                                                                                        Records
                                                                                     Asset Register
                                                                                     O&M Manuals




                           Quantity take-
                            Off, costing
                                                 Clash      Simulations, energy,
                                                                                   Production
                                                                 Fire etc.                                 Procurement
                                                Detection                             BIM




         Supply Chain Management

                                            4D-Scheduling           Quality                           Commercial




17




     4
UK BIM Implementation Structure
                                            Strategic decision
Mandate                                        to adopt BIM
                             AB              across all BU’s
President & CEO

                                          UKBU requires BIM on
Policy                     UKBU           all appropriate projects
UK President                                   going forward

                                           Individual strategies
Strategy                 OU’s / EF’s      formed, respecting the
BIM Rep’s                                    different markets

                                            Detailed plans for
Plan                     PROJECTS           those elements of
Project Directors                           BIM to be adopted

            5
Some relative proportions in BIM delivery



    3.
Technology      2. Process                  1. People




                                             1. Strategic         2. Detailed process   3. Tech
                                             Process Monitoring   Monitoring             Coord




             Coordination of BIM Delivery
BIM During Design and Construction

                                               CAFM
           CAD
        Intelligent      Databases
            2D
                                                                 Excel
                                                   Word
                                                                Spread
                                                 Documents
                                                                Sheets
    Co-ordinated
                        BIM MODEL               Electronic data management
     3D Models
    Architectural                                                PDF
                              Electronic             2D          Text
     Structural          Production Methods       Drawings       Docs
                         eg Tablet PC’s, GPS
       MEP                 Machine control
                           Laser scanning

                 ‘Foundation’: Created by the application of
                 BIM standards, Design Agreement clauses,
                 Project BIM Plan and BIM Guidance Notes




7
BIM within Broad Information Management


WEB
 .




                                Client
                      Information Management




                                                        CAFM

          Services Provision                     BIM
       Information Management      Building Information Modelling




                  INFORMATION MANAGEMENT



 8
Challenges

- Timing in relation to projects
- Common understanding of BIM
- How much BIM to Implement
- Levels of Details within the models
- Articulation of what is required
- Investment in the process
- Management of the process



9
Proportion and Hierarchy of BIM Understanding



                                                                                               Mandate BIM Concept

 Strategy                                          1%

Government

                                                                                                 Edict to adopt BIM
Clients                                            4%                               What is BIM, What Extent, Articulation of
                                                                                                  Requirements
Public and private


                                                                                              Management Philosophy and
                                                   5%                                       protocols, Defining requirements
Contractors

                                                                                               Implementation Policy
Large

                                                                                           Practical Application on projects
Supply Chain
                                                90%                                           What do I have to do?
SME’s, subs etc.

Bulk of people not interested in BIM wedges, Protocols, Standards Process and Flowcharts    They want TO DO LISTS
              10
Opportunities

- Not having to wait for perfect BIM for Benefits
- Better understanding of other’s needs/perspectives
- Enhanced Collaboration
- Un-envisaged advantages and usages
- Increasing benefits on subsequent projects
- Vehicle for lessons learned
- Potential Differentiator
- Client Engagement

11
Legacy                   Case Studies       Feedback Lessons
                         capture ongoing                                       Implementation
 Hospitals               Implementation                                         Onto Legacy
                             Benefits
                                                                                 Hospitals
                       Challenges/Lessons         Interrogate
                           Quantifiable                                            Derby
Other legacy                                      Rationalise
    projects                Evidence                                             Mansfield
                                                and Implement
                                                  Outcomes
                                                      BIM
                         Case Study          (Building Information
Walsall Hospital          Lessons           Modelling) provides a
                                                                                      Lessons
                          Learned               ‘vehicle’ to help
                                                                                      Learned
                                            Articulate and transfer
                                               The Benefits for:
                          Case Study                 Clients
 Barts & The Royal
                           Lessons                User groups
  London Hospital
                           Learned          Estates Management
                                                 Supply Chain
                                                   Designers                    New Project
 Post Occupancy Evaluation                          Skanska
    (POE) of the design

  Review Initiatives/Protocols
  Processes/Existing practices
                                                                      OTHER NEW
                                                   Lessons
                                                                       PROJECTS
Academic/University engagement                     Learned
  For Research and Innovation                                         Including NKS
Formulating BIM Plan
  Deliberation and articulation                                                  Agreement of
 Of BIM requirements for Client                                                 Project BIM Plan
                                                                           Incorporates the agreed
                                                                         requirements of stakeholders
                                                                         For the Design, Construction,
                                                                         Operational and Maintenance
  Deliberation and articulation                                              Periods of the project
   Of BIM requirements for
           Designers
                                            Dialogue and
                                             Interactive
                                           Engagement of
  Deliberation and articulation             Participants to
    Of BIM requirements for
Facilities Services Hard and Soft          Understand and
                                           Accommodate                          Project
                                             Each others’
                                             Practical and                       BIM
   Deliberation and articulation
    Of BIM requirements for                    Also BIM                          Plan
           Contractor                       Requirements



   Deliberation and articulation                                                             BIM Plan Route Plan
   Of BIM requirements for SPV
                                                                                          To manage Implementation,
                                                     Inputs to the BIM                       Compliance Auditing,
                                                       Plan as project                          Development
                                                       Progresses eg.                           And Updating
    Deliberation and articulation                     Subcontractors
     Of BIM requirements for                              Suppliers
        Other stakeholders
                                                      Commissioners

                          Confidential
Project BIM Plan Example
                                                            Required by            Lead
 Application                Benefits Expected                                               Comments/requirements
                                                          Client   ID   CJV   FM   CJV FM
                        •   Accurate and visual                                              • Required under Skanska
      Intelligent           design, no shortcuts
                            (completed design in all                                           Group BIM Strategy
     3D-Modelling
                            details)                                                         • Must support requirements of
                        •   Standardized components
                                                                                               the BIM applications detailed
                            in use, libraries and
                            catalogs                                                           below
                        •   Information on materials                                         • CJV to determine optimum
                            and components available
                            from model to meet                                                 technical solutions
                            O&M/FM & Investor’s                                              • Must agree and adopt an
                            needs
                                                                                               object/asset coding system
                                                                                               at the commencement of
                                                                                               design to be used throughout
                                                                                               the life of the project
                        •   Analyze alternative                                              • Required under ID BIM
                            design/construction/mainten
                            ance options                                                       Strategy
                        •   Select options on basis of                                       • BIM to facilitate rapid re-
                            optimized capital and                                              assessment of implications
                            ownership costs
                        •   Ensures most attractive /                                          and quantities of design
                            affordable whole life cost                                         options
                            solution
                                                                                             • Suggested that a member of
                        •   Accurate life cycle cost
                            estimation                                                         the BIM team should attend
                        •   Reduced risk in life cycle                                         all optioneering workshops in
                            fund management
                                                                                               order to facilitate BIM
                                                                                               support




14                  Confidential
Steps in Creating and Managing Project BIM Plan

                     RFQ                         Project        Commercial                       BID                   Financial    Construction            Operational
      PreORA                                                                                                ORA
                     PQQ                         Launch           Review                        Review                  Close         Phase                   Phase

Project Timeline
                      1             2                                            5              6             7                                    9            10
                                                    3              4                                                            8
                     Draf t      BIM Plan                                     Technical      Training      BIM Plan                           Criticality     Model
                                                 Approve        Resource                                                      Monitor
                   BIM Plan      Stage 1                                       Needs          Needs        Stage 2                             Assess        Operating
                                                 BIM Plan         Plan                                                        Comply

   Client BIM,
  Contractual &
   Agreement       BIM Design    Principals                                                                                                     Asset
                                                                 Identify                                                     Structure                      Construction
       BIM         Assessment   Engagement         Agree                         Identify                                                     Criticality
                                                                Resources                     Identify      Finalise          Monitoring
  Requirements       Design                       Extent of                     Hardware                                                     Assessment
                                                                Required to                   Training        BIM              BIM Plan                       Operation
                   Agreements     Inform of         BIM                         Software                                                      Alignment
                                                                Implement                      needs          Plan              Status                          And
                    Links to    Standards &      Applications                 requirements                                                   With Policy
                                                                   plan                                                      On Agendas                      Maintenance
                   Documents     Templates                                                                                                   Documents


                                        Level of Detail LOD
                                           Click to link


                       Strategic Process Monitoring

                                              Detailed Process Monitoring
                                                                                 Technical Co-ordination
                   Coordination of BIM Delivery


                    Life Cycle Optioneering

                   Concept                             Design                                                 Detailed
                                 Optioneering                          Optioneering                                                Optioneering
                   Design                            Development                                              design


                                                                                                                       Joint safety reviews


   15
Benefits on Accommodation projects
−    On the Barts Hospital(383 beds) project the M&E package cost was avoided
     average scope increase of circa £1.7m by improved design co-ordination and
     clash prevention




−    Use of Tablet PC’s at the Royal London Hospital (905 beds)reduced the
     management time in office to site and back by circa 50%




−    Efficient take-off of quantities from the model saved £350,000 in QS time
16
Utilisation of BIM at NKS
            −    Beneficial way of working throughout the project, facilitating a safer, greener,
                 faster, leaner project delivery
Visualisations                                       Identify specific search sets Tracking RDD Process




Improving the design       After Review




                                                  Safety Reviews                Clash Prevention
Benefits on Highways
•        On M25 model illustrated where batter could replace proposed piling and saved £3.0m
•        GPS machine control via the model eliminated profile so saved 3 engineers for the duration
         of the project
•        Laser scanning of existing bridges provided a complete and retrievable database of
         information including dimensions in a safe manner. Saved £1000 per day in traffic
         management
•        Improved engagement/understanding with the emergency services, fire police etc. on M25
•        Efficient and accurate schedules production of drainage, barriers lighting etc. on M25 75%
         more efficient
•        Design is optimised by active modelling. Sign Location Gantries reduced from 46 to 35 on
         M25 saving £3.5m




− The Return on Investment in BIM processes at the M25 is calculated at
  10 to 1
    18
Benefits to Designers



− Able to visualise road layouts
− Checking the visibility positioning of signs and signals
− Positioning gantries efficiently
− Clash prevention of infrastructure
−    Assists with third party engagement and understanding
−    Buildability verification and construction sequences confirmed
−    Reduction of environmental impacts




19
BIM on the A1 in Poland




3D survey and control system supported
by GPS




23




                                             • Haul road on Phase 2 of the A1 in Poland was
                                             modelled and saved circa £3.5m in accurate location
                                             and construction
Benefits during bids

−     Fewer Room Layout reviews: The 3D and the live updates generally got the rooms agreed
     in principle in a single meeting ( previously 3 to 4 meeting required !)
−    The client asked us to do about 50 rooms we achieved 130 including equipment and this
     gave confidence to the 1:200 area schedules. Modelling made this easy
−    Touch screens were really liked by those who used them. Others preferred the architect to
     update and watch the items move on screen and direct.
−     A significant difference was the loading 3-D as the client understood better and the live
     updates ensured all their directions were tested then, rather than taking them away and
     finding it did not work.


−    Able to market test 26 works packages (90%) of project because of meaningful images of
     project illustrating the project and reducing risk.
−    Facilitated submission requirements
−    Permitted earlier design decisions e.g. Façade with thermal modelling based on architectural
     and frame models




21
Interactive touch screen 1:50 process
− BIM Design
  − Captures the information from
  the 3D planning, review and
  adjustment of spaces




  22
3D Room Elevations

− BIM Design
  − Captures the details
  of the 3D elevations
  including equipment
  requirements




   23
Virtual Samples/Mock-ups

     − BIM Design
       − Data collected allows for
       virtual mock-ups to be built and
       tested




24
Guide to Level of detail

                                                               LEVELS OF DETAIL RELATING TO THE PROJECT SPECIFIC BIM STRATEGY AND PLAN
                                      Tender process                                       Finalise Bid                  Final Construction                     Construction                Operation & Maintenance
Project Specific BIM       1                     2        3       4        5         6                  7           8    Price              9                                 9                          10
Plan stages              DRAFT         DEVELOP STAGE 1 Approve Resource Technical Training        DEVELOP STAGE 2 Comply                 INPUT                              INPUT                     MODEL

Levels of Detail
(Development) LOD




LOD                                   LOD 100                                         LOD 200                                  LOD 300                          LOD 400                     LOD 500

Architectural          BIM:        100 - Concept planning                             200 - Schematic                          300 - Design development         400 - Construction ready    500 - Virtual prototype
                       Assessment 150 - Space planning                                                                         350 - Fully coordinated design   documentation               600 - As built
                       Into Design                                                                                                                                                          700 - Operations documentation
RIBA Stage Plan        Agreement A, B, C                                              D,E,F,G,H                                J                                K                           L


Services               BIM:        Specifications                                     Plantrooms, risers, distribution         Spatial Co-ordination            Co-ordinated details        As Installed
                       Assessment                                                     Schematics                               Builders w ork                   Manufacturers details
                       Into Design                                                    Utilities
                       Agreement

Structural             BIM:        Foundations/frame                                  Outline Design                           Detail Design                                                As Constructed
                       Assessment                                                                                              Checking subcontract design
                       Into Design                                                                                             Co-ordinated details
                       Agreement

Sub-contractor                                                                        Component spacial dimensions             BIM into design agreement Create links to models/databases
                                                                                      Including future access space            Detail Design                    Detail Design               As Constructed
                       Note: Create                                                                                            Component attributes/spacial     Component attributes        As Installed
                       Links to                                                                                                dims inc access space            dims inc access space
                       Documents
Standards                             Room Numbering                                  Drawing numbering'                       Change Control
                       Articulating   Asset Coding (empty                             Clash Prevention                                                                                      Retrievable Legible
                       BIM: SFS       fields if necessary)                                                                                                                                  Useful Data to be available
                                      Asset Register
                                      O&M template                                                                                                                                          Handover 'Timelined' versions
                       Articulating                                                                                                                                                         of models and databases for
Optioneering           BIM: ID        Concept Options                                 Design Options                           Detail Options                                               FM usage




                25
The Model as a Graphical Route Map

                                Hosted Data

                                Within the Model
                                e.g. What, where, unique identifier


                                Linked Data

                                Local Area Network
                                e.g. Room data, spec’s, doc’s


Sample 3D Model                 Referenced Data

                                Wide Area Network / Web
                                e.g. Manufacturers data, QA / QC
OpenBIM and Skanska: (Imported Slide)

What is OPEN BIM?
OPEN BIM is a universal approach to the collaborative design, realisation and operation of buildings based on open standards and
workflows. OPEN BIM is an initiative of buildingSMART International (bSI) and several leading software vendors using the open
buildingSMART Data Model.


Why is it important?
•OPEN BIM supports a transparent, open workflow, allowing project members to participate regardless of the software tools they use.
•OPEN BIM creates a common language for widely referenced processes, allowing industry and government to procure projects in
transparent commercial engagement, comparable service evaluation and assured data quality.
•OPEN BIM provides enduring project data for use throughout the asset life-cycle, avoiding multiple input of the same data and
consequential errors.
•OPEN BIM enables small and large (platform) software vendors to participate and compete on system independent, ‘best of breed’
solutions.
•OPEN BIM energises the on-line product supply side with more exact user demand searches and delivers the product data directly into
the BIM.




Skanska
• supports these principles
• remains platform neutral
• embraces BIM in its broadest context




                                                                                                     SmartBIM Solutions
Open BIM Learning Xchange




           Thank you




28

Open BIM Benefits - Howard Jeffrey

  • 1.
    Open BIM LearningXchange Dr. Howard Jeffrey BIM Specialist Skanska 1
  • 2.
    Presentation content - Approachto BIM - Interpretation of BIM - Challenges - Opportunities - Implementation of BIM - Benefits on Projects - Open BIM 2
  • 3.
    BIM at Skanska BuildingInformation Modelling BIM – The Skanska AB Definition: Building Information Modelling is a method to describe the building and its spaces, structures, components and materials with their essential information and properties. The model is a container for the information. BIM can also be described as a collaborative approach making sure the right people get the right project information at the right time. “From January 1st 2009 all new Design and Build projects where design has not yet started – shall adopt Building Information Modelling”
  • 4.
    BIM Plan basedupon 16 Areas Intelligent Visualizations Records Modelling Safety Planning Green BIM Facilities Mgt. Management Design 15 As Constructed Records Asset Register O&M Manuals Quantity take- Off, costing Clash Simulations, energy, Production Fire etc. Procurement Detection BIM Supply Chain Management 4D-Scheduling Quality Commercial 17 4
  • 5.
    UK BIM ImplementationStructure Strategic decision Mandate to adopt BIM AB across all BU’s President & CEO UKBU requires BIM on Policy UKBU all appropriate projects UK President going forward Individual strategies Strategy OU’s / EF’s formed, respecting the BIM Rep’s different markets Detailed plans for Plan PROJECTS those elements of Project Directors BIM to be adopted 5
  • 6.
    Some relative proportionsin BIM delivery 3. Technology 2. Process 1. People 1. Strategic 2. Detailed process 3. Tech Process Monitoring Monitoring Coord Coordination of BIM Delivery
  • 7.
    BIM During Designand Construction CAFM CAD Intelligent Databases 2D Excel Word Spread Documents Sheets Co-ordinated BIM MODEL Electronic data management 3D Models Architectural PDF Electronic 2D Text Structural Production Methods Drawings Docs eg Tablet PC’s, GPS MEP Machine control Laser scanning ‘Foundation’: Created by the application of BIM standards, Design Agreement clauses, Project BIM Plan and BIM Guidance Notes 7
  • 8.
    BIM within BroadInformation Management WEB . Client Information Management CAFM Services Provision BIM Information Management Building Information Modelling INFORMATION MANAGEMENT 8
  • 9.
    Challenges - Timing inrelation to projects - Common understanding of BIM - How much BIM to Implement - Levels of Details within the models - Articulation of what is required - Investment in the process - Management of the process 9
  • 10.
    Proportion and Hierarchyof BIM Understanding Mandate BIM Concept Strategy 1% Government Edict to adopt BIM Clients 4% What is BIM, What Extent, Articulation of Requirements Public and private Management Philosophy and 5% protocols, Defining requirements Contractors Implementation Policy Large Practical Application on projects Supply Chain 90% What do I have to do? SME’s, subs etc. Bulk of people not interested in BIM wedges, Protocols, Standards Process and Flowcharts They want TO DO LISTS 10
  • 11.
    Opportunities - Not havingto wait for perfect BIM for Benefits - Better understanding of other’s needs/perspectives - Enhanced Collaboration - Un-envisaged advantages and usages - Increasing benefits on subsequent projects - Vehicle for lessons learned - Potential Differentiator - Client Engagement 11
  • 12.
    Legacy Case Studies Feedback Lessons capture ongoing Implementation Hospitals Implementation Onto Legacy Benefits Hospitals Challenges/Lessons Interrogate Quantifiable Derby Other legacy Rationalise projects Evidence Mansfield and Implement Outcomes BIM Case Study (Building Information Walsall Hospital Lessons Modelling) provides a Lessons Learned ‘vehicle’ to help Learned Articulate and transfer The Benefits for: Case Study Clients Barts & The Royal Lessons User groups London Hospital Learned Estates Management Supply Chain Designers New Project Post Occupancy Evaluation Skanska (POE) of the design Review Initiatives/Protocols Processes/Existing practices OTHER NEW Lessons PROJECTS Academic/University engagement Learned For Research and Innovation Including NKS
  • 13.
    Formulating BIM Plan Deliberation and articulation Agreement of Of BIM requirements for Client Project BIM Plan Incorporates the agreed requirements of stakeholders For the Design, Construction, Operational and Maintenance Deliberation and articulation Periods of the project Of BIM requirements for Designers Dialogue and Interactive Engagement of Deliberation and articulation Participants to Of BIM requirements for Facilities Services Hard and Soft Understand and Accommodate Project Each others’ Practical and BIM Deliberation and articulation Of BIM requirements for Also BIM Plan Contractor Requirements Deliberation and articulation BIM Plan Route Plan Of BIM requirements for SPV To manage Implementation, Inputs to the BIM Compliance Auditing, Plan as project Development Progresses eg. And Updating Deliberation and articulation Subcontractors Of BIM requirements for Suppliers Other stakeholders Commissioners Confidential
  • 14.
    Project BIM PlanExample Required by Lead Application Benefits Expected Comments/requirements Client ID CJV FM CJV FM • Accurate and visual • Required under Skanska Intelligent design, no shortcuts (completed design in all Group BIM Strategy 3D-Modelling details) • Must support requirements of • Standardized components the BIM applications detailed in use, libraries and catalogs below • Information on materials • CJV to determine optimum and components available from model to meet technical solutions O&M/FM & Investor’s • Must agree and adopt an needs object/asset coding system at the commencement of design to be used throughout the life of the project • Analyze alternative • Required under ID BIM design/construction/mainten ance options Strategy • Select options on basis of • BIM to facilitate rapid re- optimized capital and assessment of implications ownership costs • Ensures most attractive / and quantities of design affordable whole life cost options solution • Suggested that a member of • Accurate life cycle cost estimation the BIM team should attend • Reduced risk in life cycle all optioneering workshops in fund management order to facilitate BIM support 14 Confidential
  • 15.
    Steps in Creatingand Managing Project BIM Plan RFQ Project Commercial BID Financial Construction Operational PreORA ORA PQQ Launch Review Review Close Phase Phase Project Timeline 1 2 5 6 7 9 10 3 4 8 Draf t BIM Plan Technical Training BIM Plan Criticality Model Approve Resource Monitor BIM Plan Stage 1 Needs Needs Stage 2 Assess Operating BIM Plan Plan Comply Client BIM, Contractual & Agreement BIM Design Principals Asset Identify Structure Construction BIM Assessment Engagement Agree Identify Criticality Resources Identify Finalise Monitoring Requirements Design Extent of Hardware Assessment Required to Training BIM BIM Plan Operation Agreements Inform of BIM Software Alignment Implement needs Plan Status And Links to Standards & Applications requirements With Policy plan On Agendas Maintenance Documents Templates Documents Level of Detail LOD Click to link Strategic Process Monitoring Detailed Process Monitoring Technical Co-ordination Coordination of BIM Delivery Life Cycle Optioneering Concept Design Detailed Optioneering Optioneering Optioneering Design Development design Joint safety reviews 15
  • 16.
    Benefits on Accommodationprojects − On the Barts Hospital(383 beds) project the M&E package cost was avoided average scope increase of circa £1.7m by improved design co-ordination and clash prevention − Use of Tablet PC’s at the Royal London Hospital (905 beds)reduced the management time in office to site and back by circa 50% − Efficient take-off of quantities from the model saved £350,000 in QS time 16
  • 17.
    Utilisation of BIMat NKS − Beneficial way of working throughout the project, facilitating a safer, greener, faster, leaner project delivery Visualisations Identify specific search sets Tracking RDD Process Improving the design After Review Safety Reviews Clash Prevention
  • 18.
    Benefits on Highways • On M25 model illustrated where batter could replace proposed piling and saved £3.0m • GPS machine control via the model eliminated profile so saved 3 engineers for the duration of the project • Laser scanning of existing bridges provided a complete and retrievable database of information including dimensions in a safe manner. Saved £1000 per day in traffic management • Improved engagement/understanding with the emergency services, fire police etc. on M25 • Efficient and accurate schedules production of drainage, barriers lighting etc. on M25 75% more efficient • Design is optimised by active modelling. Sign Location Gantries reduced from 46 to 35 on M25 saving £3.5m − The Return on Investment in BIM processes at the M25 is calculated at 10 to 1 18
  • 19.
    Benefits to Designers −Able to visualise road layouts − Checking the visibility positioning of signs and signals − Positioning gantries efficiently − Clash prevention of infrastructure − Assists with third party engagement and understanding − Buildability verification and construction sequences confirmed − Reduction of environmental impacts 19
  • 20.
    BIM on theA1 in Poland 3D survey and control system supported by GPS 23 • Haul road on Phase 2 of the A1 in Poland was modelled and saved circa £3.5m in accurate location and construction
  • 21.
    Benefits during bids − Fewer Room Layout reviews: The 3D and the live updates generally got the rooms agreed in principle in a single meeting ( previously 3 to 4 meeting required !) − The client asked us to do about 50 rooms we achieved 130 including equipment and this gave confidence to the 1:200 area schedules. Modelling made this easy − Touch screens were really liked by those who used them. Others preferred the architect to update and watch the items move on screen and direct. − A significant difference was the loading 3-D as the client understood better and the live updates ensured all their directions were tested then, rather than taking them away and finding it did not work. − Able to market test 26 works packages (90%) of project because of meaningful images of project illustrating the project and reducing risk. − Facilitated submission requirements − Permitted earlier design decisions e.g. Façade with thermal modelling based on architectural and frame models 21
  • 22.
    Interactive touch screen1:50 process − BIM Design − Captures the information from the 3D planning, review and adjustment of spaces 22
  • 23.
    3D Room Elevations −BIM Design − Captures the details of the 3D elevations including equipment requirements 23
  • 24.
    Virtual Samples/Mock-ups − BIM Design − Data collected allows for virtual mock-ups to be built and tested 24
  • 25.
    Guide to Levelof detail LEVELS OF DETAIL RELATING TO THE PROJECT SPECIFIC BIM STRATEGY AND PLAN Tender process Finalise Bid Final Construction Construction Operation & Maintenance Project Specific BIM 1 2 3 4 5 6 7 8 Price 9 9 10 Plan stages DRAFT DEVELOP STAGE 1 Approve Resource Technical Training DEVELOP STAGE 2 Comply INPUT INPUT MODEL Levels of Detail (Development) LOD LOD LOD 100 LOD 200 LOD 300 LOD 400 LOD 500 Architectural BIM: 100 - Concept planning 200 - Schematic 300 - Design development 400 - Construction ready 500 - Virtual prototype Assessment 150 - Space planning 350 - Fully coordinated design documentation 600 - As built Into Design 700 - Operations documentation RIBA Stage Plan Agreement A, B, C D,E,F,G,H J K L Services BIM: Specifications Plantrooms, risers, distribution Spatial Co-ordination Co-ordinated details As Installed Assessment Schematics Builders w ork Manufacturers details Into Design Utilities Agreement Structural BIM: Foundations/frame Outline Design Detail Design As Constructed Assessment Checking subcontract design Into Design Co-ordinated details Agreement Sub-contractor Component spacial dimensions BIM into design agreement Create links to models/databases Including future access space Detail Design Detail Design As Constructed Note: Create Component attributes/spacial Component attributes As Installed Links to dims inc access space dims inc access space Documents Standards Room Numbering Drawing numbering' Change Control Articulating Asset Coding (empty Clash Prevention Retrievable Legible BIM: SFS fields if necessary) Useful Data to be available Asset Register O&M template Handover 'Timelined' versions Articulating of models and databases for Optioneering BIM: ID Concept Options Design Options Detail Options FM usage 25
  • 26.
    The Model asa Graphical Route Map Hosted Data Within the Model e.g. What, where, unique identifier Linked Data Local Area Network e.g. Room data, spec’s, doc’s Sample 3D Model Referenced Data Wide Area Network / Web e.g. Manufacturers data, QA / QC
  • 27.
    OpenBIM and Skanska:(Imported Slide) What is OPEN BIM? OPEN BIM is a universal approach to the collaborative design, realisation and operation of buildings based on open standards and workflows. OPEN BIM is an initiative of buildingSMART International (bSI) and several leading software vendors using the open buildingSMART Data Model. Why is it important? •OPEN BIM supports a transparent, open workflow, allowing project members to participate regardless of the software tools they use. •OPEN BIM creates a common language for widely referenced processes, allowing industry and government to procure projects in transparent commercial engagement, comparable service evaluation and assured data quality. •OPEN BIM provides enduring project data for use throughout the asset life-cycle, avoiding multiple input of the same data and consequential errors. •OPEN BIM enables small and large (platform) software vendors to participate and compete on system independent, ‘best of breed’ solutions. •OPEN BIM energises the on-line product supply side with more exact user demand searches and delivers the product data directly into the BIM. Skanska • supports these principles • remains platform neutral • embraces BIM in its broadest context SmartBIM Solutions
  • 28.
    Open BIM LearningXchange Thank you 28