A motivated Mechanical Engineer with 7.5 years of expertise in Construction of various Oil and Gas projects
in Middle East having team player mindset and a strong academic background, Possess the technical and
communication skills needed to assist the organization in achieving its goals and objectives. Being a hard
working individual, my aim is to maximize my potential and set of skills while contributing towards the
greater success of the organization.
 Graduation (B.Tech) in “Mechanical Engineering” from Calicut University, India
 PGDM in Environmental Management
 CSWIP 3.1 CWI
 Experienced in middle management and in Lead positions in Owner as well as in EPC organizations
 Familiar in Field Construction of civil and piping/pipeline/Mech activities.
 Well experienced in both Greenfield and Brownfield projects
 Highly skilled in managing contractors in such a way that the Company’s interests are not
compromised.
 A planner with competency in devising significant solutions, and in ensuring implementation of
health & safety management systems.
 Best performance recognitions from Shell GTL and Qatargas.
 Good Communication and inter-personal skills with all levels of organization with English, Hindi,
Malayalam and Tamil language capacity.
 Organizational readiness to learn, adapt and respond to changing business directions/priorities.
1. Current Employer CH2M HILL Energy Canada Ltd.
(PMC for ADCO South East Projects)
Designation Project Coordinator (As-built and data)
Projects Various projects in ADCO SE fields
Period Feb ’2015-till date
Location Abu Dhabi, UAE
Duties & Responsibilities:
 Close coordination and interaction with ADCO Engineering & Construction Management, ADCO
Corporate Design & Applications department and the main Contractor.
 Responsible to review/comment the Project As-built Procedure, based on the ADCO contractual
requirements and the Contractor’s Scope of Work.
 Responsible for review/approval all the Civil and Mechanical As-built red-line markup drawings and
documents.
 Organize and attend weekly as-built Coordination meetings with the Construction Contractors.
 Prepare plan for project close out drawings & documents submission as per contract & follow up
with the contractors.
Objective:
Educational Qualification:
Summary of skills:
Employment Profile:
Page 2 of 4
 Coordination with all the disciplines (Process, Mechanical, Piping, Pipeline & Civil) within the
company to ensure that the contractors have completed the construction activities in line with the
project approved drawings and ADCO specifications.
 Organize and attend clarification meetings with the ADCO Corporate Design & Application team and
the Construction Contractor.
 Analyzing Technical Queries (TQ) and Field Change Requests (FCR) whenever there are Technical
Design difference between the Issued for Construction (IFC) drawings and actual conditions on site.
 Communicate and guide the Contractor’s As-built Coordinator, advise and clarify any Technical
Queries related to As-built activities, enforce the As-built Procedure, ensure the quality is maintained
for all the As-built documentation activities.
 Prepare Weekly Progress Reports, review and approve the MOMs prepared by the Contractor and
distribute the same.
 Reviews the work forecasts and plans for remaining activities, comments and forecasts future
performance
 Closely interact with the PMC Engineers for As-built mark-clarification, refer to the Design Change
Notifications / Field Change Request Sheets for the authenticity of the mark-up, and confirm the
changes by verifying on site in case of any ambiguity.
 Responsible to make sure that the changes in one document is propagated to all the related
documents and the changes are captured.
 Prepare plan for project close out drawings & documents submission as per contract & follow up
with the contractors.
 Review and approve the As-built mark-plan submitted by the Construction Contractor.
 Analyzing Technical Queries (TQ) and Field Change Requests (FCR) whenever there are Technical
Design difference between the Issued for Construction (IFC) drawings and actual conditions on site.
 P&ID walk down during Mechanical Completion, Pre-Commissioning and Commissioning phases to
ensure that all the documents are updated to As-built status.
2. Employer Petrofac International Ltd
Designation Construction Engineer (Piping / Pipeline)
Project Asab Full Field Development Project
Client ADCO
Period March ’2011- Jan ‘2015
Location Abu Dhabi, UAE
Duties & Responsibilities:
 Ensure the quality of information meets Company’s E&P procedures.
 Plans and strategize for work plan for the Piping and civil department based on the overall
project execution plan and strategy.
 Preparation and review of red line markup drawings.
 Consolidating the modifications with regard to TQ and TD with QA/QC or Engineering
department and incorporates the observations in the As-built drawings.
 Ensuring the work is based on regulatory, contract, design and manufacturer’s requirements.
 Bringing together any NCR issues to reflect in as-built drawings from beginning to disposition.
 Plan for the deployment and redeployment of resources for timely completion of work as has
been planned for the Piping department.
 Represent the discipline for frequent review and update meetings with the client to attend to
any concerns and also to give an update on the development of work as scheduled.
 Coordinate with other engineering discipline heads at the project site to review the overall
progress in work and coordinate with them to assess any hold points.
Page 3 of 4
 Frequently assess the subcontractors for their work and quality standards for them meeting the
project specifications.
 Monitor progress of work related to As-built and dossiers, reporting delays to Construction
Manager and discuss with contractors for recovery measures.
 Supervise the team for timely and accurate work execution. Ensure that all the work activities
get completed as per the quality norms and as per project specifications.
 Responsible for investigating, collating and analyzing information to assist in the audits
facilitated by the clients.
 Review of piping pressure test packages.
 Coordinate with the Client Engineers/Inspectors for Mechanical Completion Walk Down
inspection of construction and generate punch lists that need to be cleared.
 Interact with the commissioning team ensure any pending issues with regards to construction
department are resolved.
3. Employer Nasser S Al Hajri Co Ltd.
Designation Project Engineer (Piping / Pipeline)
Project (i) Qatar Shell Pearl GTL Project
Client Shell
Period Oct’2008- Oct’2009
Project (ii) Qatar Gas QCS 3 & 4 Onshore Facility Project
Client Qatar Gas
Period Nov’2009-Oct’2010
Location Ras Laffan, Qatar
Duties & Responsibilities:
 Study and understand the project plan and the client requirements including equipment to be
used, specifications and procurement plan.
 Plan the construction activities along with the Construction Superintendent/Manager as well as
the various discipline engineers in line with the project plan.
 On completion of each phase of the construction, inspect and ensure its progress in line with
client’s requirements.
 Develop punch lists of incomplete work.
 Generate reports on a daily and weekly basis on the status of the project with regards to
construction.
 Manpower controlling and distributing the work in the site.
 Coordinate with the client on the project construction requirements and provide feedback on the
status and seeks inputs wherever required.
4. Employer Venus Gas Products & Services Pvt. Ltd
Designation Mechanical Engineer
Period July’08-Oct’08
Location Bangalore, India
Duties & Responsibilities:
 Plan the construction activities along with the Construction Superintendent/Manager as well as
the various discipline engineers in line with the project plan.
 Develop punch lists of incomplete work.
 Generate reports on a daily and weekly basis on the status of the project with regards to
construction.
 On completion of each phase of the construction, inspect and ensure its progress in line with
client’s requirements.
 Manpower controlling and distributing the work in the site.
Page 4 of 4
 Health Safety Security Environment & Leadership Training from Shell.
 Incident and Injury Free (IIF) Supervisor skills from Shell.
 Permit to Work (PTW),Flawless Startup & Total Safety Task Instruction from Shell
 Computer based trainings in all the safety life protection rules from SHELL.
 Permit to Work (PTW) from CTJV [Chiyoda Technip Joint Venture] & Qatar Gas.
 Shell recognized “Commitment to Quality” award.
 Safety & Commitment appreciation certificate holder in QSGTL Project by JGC-KBR.
 Job Performer /Permit to work from ADCO, Abu Dhabi
 Life Protection Rules (LPR) training from ADCO, Abu Dhabi.
Operating System : Windows (all), MS Dos.
Software : Iron Cad. Navisworks (3D Model) & WinPCS
Office Skills : MS Office
Gender : Male
Date of Birth : 30th
December 1986
Marital Status : Single
Nationality : Indian
Father’s name : K J George
Mother’s name : Annie George
Languages known : English, Hindi, Malayalam & Tamil
Driving License : Holding UAE and Indian Driving license
Passport Number : L 7535106
Place of issue : Cochin.
Date of Issue : 10/03/2014
Valid up to : 09/03/2024
Permanent Address : Kidanganezhath (H), Edakochi P.O,
Kochi, Kerala, India- 682010
I hereby declare that the above-mentioned information is correct up to my knowledge and I bear
the responsibility for the correctness of the above-mentioned particulars.
Abu Dhabi, UAE
March 16, 2016. Nidhin George
Trainings & Awards:
IT Credentials:
Personal Details:
Declaration:

Nidhin George_CV

  • 1.
    Page 1 of4 NIDHIN GEORGE Project Coordinator/Construction Engineer Email: nidhin14@gmail.com Mob: +971-50-9373314 (UAE) / +91-8891467291 (India) A motivated Mechanical Engineer with 7.5 years of expertise in Construction of various Oil and Gas projects in Middle East having team player mindset and a strong academic background, Possess the technical and communication skills needed to assist the organization in achieving its goals and objectives. Being a hard working individual, my aim is to maximize my potential and set of skills while contributing towards the greater success of the organization.  Graduation (B.Tech) in “Mechanical Engineering” from Calicut University, India  PGDM in Environmental Management  CSWIP 3.1 CWI  Experienced in middle management and in Lead positions in Owner as well as in EPC organizations  Familiar in Field Construction of civil and piping/pipeline/Mech activities.  Well experienced in both Greenfield and Brownfield projects  Highly skilled in managing contractors in such a way that the Company’s interests are not compromised.  A planner with competency in devising significant solutions, and in ensuring implementation of health & safety management systems.  Best performance recognitions from Shell GTL and Qatargas.  Good Communication and inter-personal skills with all levels of organization with English, Hindi, Malayalam and Tamil language capacity.  Organizational readiness to learn, adapt and respond to changing business directions/priorities. 1. Current Employer CH2M HILL Energy Canada Ltd. (PMC for ADCO South East Projects) Designation Project Coordinator (As-built and data) Projects Various projects in ADCO SE fields Period Feb ’2015-till date Location Abu Dhabi, UAE Duties & Responsibilities:  Close coordination and interaction with ADCO Engineering & Construction Management, ADCO Corporate Design & Applications department and the main Contractor.  Responsible to review/comment the Project As-built Procedure, based on the ADCO contractual requirements and the Contractor’s Scope of Work.  Responsible for review/approval all the Civil and Mechanical As-built red-line markup drawings and documents.  Organize and attend weekly as-built Coordination meetings with the Construction Contractors.  Prepare plan for project close out drawings & documents submission as per contract & follow up with the contractors. Objective: Educational Qualification: Summary of skills: Employment Profile:
  • 2.
    Page 2 of4  Coordination with all the disciplines (Process, Mechanical, Piping, Pipeline & Civil) within the company to ensure that the contractors have completed the construction activities in line with the project approved drawings and ADCO specifications.  Organize and attend clarification meetings with the ADCO Corporate Design & Application team and the Construction Contractor.  Analyzing Technical Queries (TQ) and Field Change Requests (FCR) whenever there are Technical Design difference between the Issued for Construction (IFC) drawings and actual conditions on site.  Communicate and guide the Contractor’s As-built Coordinator, advise and clarify any Technical Queries related to As-built activities, enforce the As-built Procedure, ensure the quality is maintained for all the As-built documentation activities.  Prepare Weekly Progress Reports, review and approve the MOMs prepared by the Contractor and distribute the same.  Reviews the work forecasts and plans for remaining activities, comments and forecasts future performance  Closely interact with the PMC Engineers for As-built mark-clarification, refer to the Design Change Notifications / Field Change Request Sheets for the authenticity of the mark-up, and confirm the changes by verifying on site in case of any ambiguity.  Responsible to make sure that the changes in one document is propagated to all the related documents and the changes are captured.  Prepare plan for project close out drawings & documents submission as per contract & follow up with the contractors.  Review and approve the As-built mark-plan submitted by the Construction Contractor.  Analyzing Technical Queries (TQ) and Field Change Requests (FCR) whenever there are Technical Design difference between the Issued for Construction (IFC) drawings and actual conditions on site.  P&ID walk down during Mechanical Completion, Pre-Commissioning and Commissioning phases to ensure that all the documents are updated to As-built status. 2. Employer Petrofac International Ltd Designation Construction Engineer (Piping / Pipeline) Project Asab Full Field Development Project Client ADCO Period March ’2011- Jan ‘2015 Location Abu Dhabi, UAE Duties & Responsibilities:  Ensure the quality of information meets Company’s E&P procedures.  Plans and strategize for work plan for the Piping and civil department based on the overall project execution plan and strategy.  Preparation and review of red line markup drawings.  Consolidating the modifications with regard to TQ and TD with QA/QC or Engineering department and incorporates the observations in the As-built drawings.  Ensuring the work is based on regulatory, contract, design and manufacturer’s requirements.  Bringing together any NCR issues to reflect in as-built drawings from beginning to disposition.  Plan for the deployment and redeployment of resources for timely completion of work as has been planned for the Piping department.  Represent the discipline for frequent review and update meetings with the client to attend to any concerns and also to give an update on the development of work as scheduled.  Coordinate with other engineering discipline heads at the project site to review the overall progress in work and coordinate with them to assess any hold points.
  • 3.
    Page 3 of4  Frequently assess the subcontractors for their work and quality standards for them meeting the project specifications.  Monitor progress of work related to As-built and dossiers, reporting delays to Construction Manager and discuss with contractors for recovery measures.  Supervise the team for timely and accurate work execution. Ensure that all the work activities get completed as per the quality norms and as per project specifications.  Responsible for investigating, collating and analyzing information to assist in the audits facilitated by the clients.  Review of piping pressure test packages.  Coordinate with the Client Engineers/Inspectors for Mechanical Completion Walk Down inspection of construction and generate punch lists that need to be cleared.  Interact with the commissioning team ensure any pending issues with regards to construction department are resolved. 3. Employer Nasser S Al Hajri Co Ltd. Designation Project Engineer (Piping / Pipeline) Project (i) Qatar Shell Pearl GTL Project Client Shell Period Oct’2008- Oct’2009 Project (ii) Qatar Gas QCS 3 & 4 Onshore Facility Project Client Qatar Gas Period Nov’2009-Oct’2010 Location Ras Laffan, Qatar Duties & Responsibilities:  Study and understand the project plan and the client requirements including equipment to be used, specifications and procurement plan.  Plan the construction activities along with the Construction Superintendent/Manager as well as the various discipline engineers in line with the project plan.  On completion of each phase of the construction, inspect and ensure its progress in line with client’s requirements.  Develop punch lists of incomplete work.  Generate reports on a daily and weekly basis on the status of the project with regards to construction.  Manpower controlling and distributing the work in the site.  Coordinate with the client on the project construction requirements and provide feedback on the status and seeks inputs wherever required. 4. Employer Venus Gas Products & Services Pvt. Ltd Designation Mechanical Engineer Period July’08-Oct’08 Location Bangalore, India Duties & Responsibilities:  Plan the construction activities along with the Construction Superintendent/Manager as well as the various discipline engineers in line with the project plan.  Develop punch lists of incomplete work.  Generate reports on a daily and weekly basis on the status of the project with regards to construction.  On completion of each phase of the construction, inspect and ensure its progress in line with client’s requirements.  Manpower controlling and distributing the work in the site.
  • 4.
    Page 4 of4  Health Safety Security Environment & Leadership Training from Shell.  Incident and Injury Free (IIF) Supervisor skills from Shell.  Permit to Work (PTW),Flawless Startup & Total Safety Task Instruction from Shell  Computer based trainings in all the safety life protection rules from SHELL.  Permit to Work (PTW) from CTJV [Chiyoda Technip Joint Venture] & Qatar Gas.  Shell recognized “Commitment to Quality” award.  Safety & Commitment appreciation certificate holder in QSGTL Project by JGC-KBR.  Job Performer /Permit to work from ADCO, Abu Dhabi  Life Protection Rules (LPR) training from ADCO, Abu Dhabi. Operating System : Windows (all), MS Dos. Software : Iron Cad. Navisworks (3D Model) & WinPCS Office Skills : MS Office Gender : Male Date of Birth : 30th December 1986 Marital Status : Single Nationality : Indian Father’s name : K J George Mother’s name : Annie George Languages known : English, Hindi, Malayalam & Tamil Driving License : Holding UAE and Indian Driving license Passport Number : L 7535106 Place of issue : Cochin. Date of Issue : 10/03/2014 Valid up to : 09/03/2024 Permanent Address : Kidanganezhath (H), Edakochi P.O, Kochi, Kerala, India- 682010 I hereby declare that the above-mentioned information is correct up to my knowledge and I bear the responsibility for the correctness of the above-mentioned particulars. Abu Dhabi, UAE March 16, 2016. Nidhin George Trainings & Awards: IT Credentials: Personal Details: Declaration: