SlideShare a Scribd company logo
CCROATANROATAN SSOUNDOUND BBRIDGERIDGE
Predesign and Construction
Phase Load Test Programs
Geotechnical Engineering Unit
NCDOT
By: John Fargher
5.2 Mile Bridge
Water Depth is 10 Feet (typical)
Scour Ranges from 12 to 30 Feet
Bridge Types
Conventional (267 Interior Bents)
Segmental (174 Interior Bents)
Trestle Bents and Footing on Pile Bents
Pile Types
24 inch Square PPC Piles
30 inch Square PPC Piles
54 inch Diameter PPC Cylinder Piles
AASHTO and Vessel Impact Loadings
Project Details and
Design Parameters
Project Location
and Alignment
Predesign Load Test Program (1997)Predesign Load Test Program (1997)
StrategyStrategy
Obtain soil design parameters for modeling lateral stability,Obtain soil design parameters for modeling lateral stability,
bearing capacity, and pile driveability. During construction,bearing capacity, and pile driveability. During construction,
pile order lengths and driving criteria would be set bypile order lengths and driving criteria would be set by
performing dynamic load tests (PDA’s) on production piles.performing dynamic load tests (PDA’s) on production piles.
Load TestsLoad Tests
Pile Driving Analyzer (PDA)Pile Driving Analyzer (PDA)
Axial Static Load Test (Conventional)Axial Static Load Test (Conventional)
Lateral Load Test (Conventional)Lateral Load Test (Conventional)
Test PilesTest Piles
Pile #1 - 95 Feet - 30 inch Square PPC PilePile #1 - 95 Feet - 30 inch Square PPC Pile
Pile #2 - 125 Feet - 30 inch Square PPC PilePile #2 - 125 Feet - 30 inch Square PPC Pile
Pile #3 - 144 Feet - 54 inch Cylinder PPC PilePile #3 - 144 Feet - 54 inch Cylinder PPC Pile
Pile #4 - 144 Feet - 54 inch Cylinder PPC PilePile #4 - 144 Feet - 54 inch Cylinder PPC Pile
CostCost - $998,000 (Bid)- $998,000 (Bid)
SavingsSavings - $1,800,000 (Estimated)- $1,800,000 (Estimated)
Cylinder Pile Installation
Purpose - Evaluate Pile Driveability, Jetting, and
Set-up of Large Cylinder Piles at the Project Site
30 inch Square Pile Alternate was Selected by Bid 54 inch Square Pile
Pile Plunged at 250 tons (FS=1)…No Good
Virtually No Set-up or Pile “Freeze”
30 inch Square Pile
Axial Static Load Test
Unique Reaction Frame
Structurally Failed
54 Inch Cylinder Pile
Design Capacities
(Allowable)
24 inch Square Piles - 150 Tons
30 inch Square Piles - 250 Tons
54 inch Cylinder Piles - 500 Tons
Pile Broke at 1500 Tons…FS=3
WOW!!!
30 inch Square Piles
Lateral Test Load - 19.5 Tons
Deflection - 13 inches
Purpose - Determine Lateral Soil Parameters of “Muck” Layer
Lateral Load Test
Florida Pier Model -Transverse Vessel
Impact Loading of 60 Pile Bent
Outcome of Lateral Load Test
 “Muck” Layer was an Order of Magnitude Stiffer Laterally than Predicted
 Reduction in Pile Embedment Required for Fixity
 Reduced the Number of Piles
Model Used to Determine:
Pile Group is Fixed
Minimum Tip Elevation
Inputs:
Loads
Structural Parameters
Soil Parameters
Check:
Stability
Moments, Shears, Deflections
Bearing and Pull-out
Construction Phase Load Test ProgramConstruction Phase Load Test Program
(1998 to 2000)(1998 to 2000)
25 - Dynamic Load Tests (PDA’s)25 - Dynamic Load Tests (PDA’s)
Tip Elevation Must Be Greater than Min. Tip El. Required For FixityTip Elevation Must Be Greater than Min. Tip El. Required For Fixity
No Pile Splicing of Concrete Piles AllowedNo Pile Splicing of Concrete Piles Allowed
3 foot Maximum Build-ups3 foot Maximum Build-ups
Cut-Offs Greater than 6 feet Require Drilling for DowelsCut-Offs Greater than 6 feet Require Drilling for Dowels
Fuel Setting and Stroke AdjustmentsFuel Setting and Stroke Adjustments
Tensile Stress Problems EncounteredTensile Stress Problems Encountered
1 - Axial Static Load Test (Conventional)1 - Axial Static Load Test (Conventional)
To insure that pile lengths are reduced in these regionsTo insure that pile lengths are reduced in these regions
To be performed prior to giving Order Lengths for 57 bentsTo be performed prior to giving Order Lengths for 57 bents
To Determine Pile Order Lengths for 2368 PilesTo Determine Pile Order Lengths for 2368 Piles
To Control Pile Driving (Quality Control)To Control Pile Driving (Quality Control)
For Each Blow it Records:
Compressive and Tensile Stresses
Energy in the Pile
Damage to the Pile
Computer that is
Attached to the Pile by
means of Strain Gages
and Accelerometers.
It Predicts:
Capacity (Skin and Total)
Hammer Stroke
Pile Driving Analyzer (PDA)
The PDA is Used to
Monitor and Control
Pile Driving
Determined Based on a PDA Test PileDetermined Based on a PDA Test Pile
To Reduce Pile Lengths andTo Reduce Pile Lengths and
Achieve Minimum Tip Elevation and BearingAchieve Minimum Tip Elevation and Bearing
PDA’s Performed Adjacent to BoringsPDA’s Performed Adjacent to Borings
Each PDA May Represent between 36 to 258 PilesEach PDA May Represent between 36 to 258 Piles
PDA Sequence is Contractors’ OptionPDA Sequence is Contractors’ Option
With Each Successive PDA there is a Learning CurveWith Each Successive PDA there is a Learning Curve
The 2 Curves have 3 feet of Super ElevationThe 2 Curves have 3 feet of Super Elevation
Trestle Bents have Battered Leading and Trailing PilesTrestle Bents have Battered Leading and Trailing Piles
PDA Test PilesPDA Test Piles
Pile Order Lengths
Considerations:Considerations:
Goal -Goal -
Axial Static Load Test
30 inch Square Pile
Purpose - Shorten 410 piles 10 meters each
Cost $170,000
Savings $643,864
Construction Load Test Savings
Estimated Savings = $1.4 Million (from Pile Length Reduction Only)
# Piles Order Lengths Reduction # Piles Order Lengths Reduction
PDA #1 66 32 to 35 m 0 m PDA #14 258 40 to 41 m 0 m
PDA #2 36 35 m 0 m PDA #15 52 36 m 4 m
PDA #3 42 41 m 6 m PDA #16 84 36 m 4 m
PDA #4 77 41 m 2 to 5 m PDA #17 130 34 to 32 m 10 m *
PDA #5 91 40 to 41 m 7 to 10 m PDA #18 84 31 to 32 m 10 m *
PDA #6 119 39 m 4 to 10 m PDA #19 119 32 to 34 m 10 m *
PDA #7 112 39 m 0 to 2 m PDA #20 77 34 m 10 m *
PDA #8 49 38 m 1 to 2 m PDA #21 77 43 m 0 to 3 m
PDA #9 63 42 to 44 m 0 m PDA #22 154 43 to 44 m 0 to 1 m
PDA #10 70 39 m 5 m PDA #23 91 39 to 41 m 0 to 3 m
PDA #11 108 35 m 4 to 6 m PDA #24 85 40 to 41 m 0 m
PDA #12 70 35 m 7 m PDA #25 42 36 m 1 m
PDA #13 216 41 to 42 m 0 m * Based on Static Load Test
Hammer
Adjustments
Delmag D100-13 (Diesel)
4 Fuel Settings
Conmaco 300E5 (Air)
2 Stroke Settings
Hammers Currently in Use
Proposed Hammers
Delmag D80-13 (Diesel)
4 Fuel Settings
ICE 205S (Diesel)
Variable Stroke Settings
NCDOT’s Experience with Predesign Load Testing
TR NEWS Sept/Oct 1999 Issue
Research Pays Off Article
Condensed Version
By: John Fargher, Nariman Abar, Jamey Batts, Brian Keaney, and Sean Byrne
Transportation Research
Record No. 1663
For additional information contact: jfargher@dot.state.nc.us

More Related Content

Viewers also liked

Pizarra digital y educación inclusiva
Pizarra digital y educación inclusivaPizarra digital y educación inclusiva
Pizarra digital y educación inclusiva
possiblelab
 
TheStateoftheEuropeanUnion2012
TheStateoftheEuropeanUnion2012TheStateoftheEuropeanUnion2012
TheStateoftheEuropeanUnion2012
Chelsea Perdue
 
LA CIENCIA VA A LA ESCUELA: INTEGRACIÓN DE DOS MUNDOS CONTRAPUESTOS
LA CIENCIA VA A LA ESCUELA: INTEGRACIÓN DE DOS MUNDOS CONTRAPUESTOSLA CIENCIA VA A LA ESCUELA: INTEGRACIÓN DE DOS MUNDOS CONTRAPUESTOS
LA CIENCIA VA A LA ESCUELA: INTEGRACIÓN DE DOS MUNDOS CONTRAPUESTOS
ProfessorPrincipiante
 
Meeting notes - Week 8
Meeting notes - Week 8Meeting notes - Week 8
Meeting notes - Week 8
Indira De Silva
 
東京物語
東京物語 東京物語
東京物語
markus liu
 
Pravapis myakkaga znaka
Pravapis myakkaga znakaPravapis myakkaga znaka
Pravapis myakkaga znaka
elenbeauti1
 
WebDevelopmentwithCSS
WebDevelopmentwithCSSWebDevelopmentwithCSS
WebDevelopmentwithCSS
Digital Systems
 
ELIZABETHS CV 2015
ELIZABETHS CV 2015ELIZABETHS CV 2015
ELIZABETHS CV 2015
elizabeth kerrigan
 
How effective is the combination of your main product and ancillary texts?
How effective is the combination of your main product and ancillary texts?How effective is the combination of your main product and ancillary texts?
How effective is the combination of your main product and ancillary texts?
IsabelWatkins
 
ENSAYO SAIA M
ENSAYO SAIA MENSAYO SAIA M
ENSAYO SAIA M
mariafernandasaia
 

Viewers also liked (11)

Pizarra digital y educación inclusiva
Pizarra digital y educación inclusivaPizarra digital y educación inclusiva
Pizarra digital y educación inclusiva
 
TheStateoftheEuropeanUnion2012
TheStateoftheEuropeanUnion2012TheStateoftheEuropeanUnion2012
TheStateoftheEuropeanUnion2012
 
Westerner Alumni Profile Article
Westerner Alumni Profile ArticleWesterner Alumni Profile Article
Westerner Alumni Profile Article
 
LA CIENCIA VA A LA ESCUELA: INTEGRACIÓN DE DOS MUNDOS CONTRAPUESTOS
LA CIENCIA VA A LA ESCUELA: INTEGRACIÓN DE DOS MUNDOS CONTRAPUESTOSLA CIENCIA VA A LA ESCUELA: INTEGRACIÓN DE DOS MUNDOS CONTRAPUESTOS
LA CIENCIA VA A LA ESCUELA: INTEGRACIÓN DE DOS MUNDOS CONTRAPUESTOS
 
Meeting notes - Week 8
Meeting notes - Week 8Meeting notes - Week 8
Meeting notes - Week 8
 
東京物語
東京物語 東京物語
東京物語
 
Pravapis myakkaga znaka
Pravapis myakkaga znakaPravapis myakkaga znaka
Pravapis myakkaga znaka
 
WebDevelopmentwithCSS
WebDevelopmentwithCSSWebDevelopmentwithCSS
WebDevelopmentwithCSS
 
ELIZABETHS CV 2015
ELIZABETHS CV 2015ELIZABETHS CV 2015
ELIZABETHS CV 2015
 
How effective is the combination of your main product and ancillary texts?
How effective is the combination of your main product and ancillary texts?How effective is the combination of your main product and ancillary texts?
How effective is the combination of your main product and ancillary texts?
 
ENSAYO SAIA M
ENSAYO SAIA MENSAYO SAIA M
ENSAYO SAIA M
 

Similar to NCDOT_Croatan_Sound

03 drilling recent development ui 17 sep 2007
03 drilling recent development   ui 17 sep 200703 drilling recent development   ui 17 sep 2007
03 drilling recent development ui 17 sep 2007
yudi05
 
d_walsh_directional.pdf
d_walsh_directional.pdfd_walsh_directional.pdf
d_walsh_directional.pdf
peter877754
 
Falling weight deflection test
Falling weight deflection testFalling weight deflection test
Falling weight deflection test
jagadish civil
 
Pump out tests in alluvial sands – a case study
Pump out tests in alluvial sands – a case studyPump out tests in alluvial sands – a case study
Pump out tests in alluvial sands – a case study
Infocengrs63
 
AT SUBSEA VESSEL OPERATIONS CONFERENCE, OSLO (YEAR 2013)
AT SUBSEA VESSEL OPERATIONS CONFERENCE, OSLO (YEAR 2013)AT SUBSEA VESSEL OPERATIONS CONFERENCE, OSLO (YEAR 2013)
AT SUBSEA VESSEL OPERATIONS CONFERENCE, OSLO (YEAR 2013)
coderweb
 
2015 CRW - Setting Up for Success
2015 CRW - Setting Up for Success2015 CRW - Setting Up for Success
2015 CRW - Setting Up for Success
Specialized Carriers & Rigging Association
 
Flight Readiness Review Presentation for Project A.R.E.S.
Flight Readiness Review Presentation for Project A.R.E.S.Flight Readiness Review Presentation for Project A.R.E.S.
Flight Readiness Review Presentation for Project A.R.E.S.
Sung (Stephen) Kim
 
Shock Control, Restraint, & Support Devices Webinar
Shock Control, Restraint, & Support Devices WebinarShock Control, Restraint, & Support Devices Webinar
Shock Control, Restraint, & Support Devices Webinar
Piping Technology & Products, Inc.
 
Sign Size and Breakaway Support Relationships
Sign Size and Breakaway Support RelationshipsSign Size and Breakaway Support Relationships
Sign Size and Breakaway Support Relationships
Texas A&M Transportation Institute
 
HDOT one of the topmost Manufacturing Units in India
HDOT one of the topmost Manufacturing Units in IndiaHDOT one of the topmost Manufacturing Units in India
HDOT one of the topmost Manufacturing Units in India
Gitanjali Singh
 
FIELD DEVELOPMENT REPORT PROJECT OF DRILLING DEPT
FIELD DEVELOPMENT REPORT PROJECT OF DRILLING DEPTFIELD DEVELOPMENT REPORT PROJECT OF DRILLING DEPT
FIELD DEVELOPMENT REPORT PROJECT OF DRILLING DEPT
MUHAMMAD NOMAN KHAN
 
INDUSTRIAL TRAINING REPORT BY ShRiDhAR KaDaM
INDUSTRIAL TRAINING REPORT BY ShRiDhAR KaDaMINDUSTRIAL TRAINING REPORT BY ShRiDhAR KaDaM
INDUSTRIAL TRAINING REPORT BY ShRiDhAR KaDaM
shridharthecyberdude
 
Transocean offshore operation 2
Transocean   offshore operation 2Transocean   offshore operation 2
Transocean offshore operation 2
Steffones K
 
Constant Springs Webinar - January
Constant Springs Webinar - JanuaryConstant Springs Webinar - January
Constant Springs Webinar - January
Piping Technology & Products, Inc.
 
Design, Fabrication and Analysis of Crank and Slotted Lever Quick Return Mech...
Design, Fabrication and Analysis of Crank and Slotted Lever Quick Return Mech...Design, Fabrication and Analysis of Crank and Slotted Lever Quick Return Mech...
Design, Fabrication and Analysis of Crank and Slotted Lever Quick Return Mech...
Mohammed Naseeruddin Shah
 
Optimum weight design of ship’s structures
Optimum weight design of ship’s structuresOptimum weight design of ship’s structures
Optimum weight design of ship’s structures
Muhammed Moanes
 
Optimum weight design of ship’s structures
Optimum weight design of ship’s structuresOptimum weight design of ship’s structures
Optimum weight design of ship’s structures
Mohamed Moanes EzzElarab
 
Modeling of Flexible and Rigid Pavements under Aircraft Loading
Modeling of Flexible and Rigid Pavements under Aircraft LoadingModeling of Flexible and Rigid Pavements under Aircraft Loading
Modeling of Flexible and Rigid Pavements under Aircraft Loading
Elise M. Mansour
 
Anderson Greenwood Pilot Operated Pressure Relief Valves
Anderson Greenwood Pilot Operated Pressure Relief ValvesAnderson Greenwood Pilot Operated Pressure Relief Valves
Anderson Greenwood Pilot Operated Pressure Relief Valves
Miller Energy, Inc.
 
Designing a shaft system
Designing a shaft systemDesigning a shaft system
Designing a shaft system
Safdar Ali
 

Similar to NCDOT_Croatan_Sound (20)

03 drilling recent development ui 17 sep 2007
03 drilling recent development   ui 17 sep 200703 drilling recent development   ui 17 sep 2007
03 drilling recent development ui 17 sep 2007
 
d_walsh_directional.pdf
d_walsh_directional.pdfd_walsh_directional.pdf
d_walsh_directional.pdf
 
Falling weight deflection test
Falling weight deflection testFalling weight deflection test
Falling weight deflection test
 
Pump out tests in alluvial sands – a case study
Pump out tests in alluvial sands – a case studyPump out tests in alluvial sands – a case study
Pump out tests in alluvial sands – a case study
 
AT SUBSEA VESSEL OPERATIONS CONFERENCE, OSLO (YEAR 2013)
AT SUBSEA VESSEL OPERATIONS CONFERENCE, OSLO (YEAR 2013)AT SUBSEA VESSEL OPERATIONS CONFERENCE, OSLO (YEAR 2013)
AT SUBSEA VESSEL OPERATIONS CONFERENCE, OSLO (YEAR 2013)
 
2015 CRW - Setting Up for Success
2015 CRW - Setting Up for Success2015 CRW - Setting Up for Success
2015 CRW - Setting Up for Success
 
Flight Readiness Review Presentation for Project A.R.E.S.
Flight Readiness Review Presentation for Project A.R.E.S.Flight Readiness Review Presentation for Project A.R.E.S.
Flight Readiness Review Presentation for Project A.R.E.S.
 
Shock Control, Restraint, & Support Devices Webinar
Shock Control, Restraint, & Support Devices WebinarShock Control, Restraint, & Support Devices Webinar
Shock Control, Restraint, & Support Devices Webinar
 
Sign Size and Breakaway Support Relationships
Sign Size and Breakaway Support RelationshipsSign Size and Breakaway Support Relationships
Sign Size and Breakaway Support Relationships
 
HDOT one of the topmost Manufacturing Units in India
HDOT one of the topmost Manufacturing Units in IndiaHDOT one of the topmost Manufacturing Units in India
HDOT one of the topmost Manufacturing Units in India
 
FIELD DEVELOPMENT REPORT PROJECT OF DRILLING DEPT
FIELD DEVELOPMENT REPORT PROJECT OF DRILLING DEPTFIELD DEVELOPMENT REPORT PROJECT OF DRILLING DEPT
FIELD DEVELOPMENT REPORT PROJECT OF DRILLING DEPT
 
INDUSTRIAL TRAINING REPORT BY ShRiDhAR KaDaM
INDUSTRIAL TRAINING REPORT BY ShRiDhAR KaDaMINDUSTRIAL TRAINING REPORT BY ShRiDhAR KaDaM
INDUSTRIAL TRAINING REPORT BY ShRiDhAR KaDaM
 
Transocean offshore operation 2
Transocean   offshore operation 2Transocean   offshore operation 2
Transocean offshore operation 2
 
Constant Springs Webinar - January
Constant Springs Webinar - JanuaryConstant Springs Webinar - January
Constant Springs Webinar - January
 
Design, Fabrication and Analysis of Crank and Slotted Lever Quick Return Mech...
Design, Fabrication and Analysis of Crank and Slotted Lever Quick Return Mech...Design, Fabrication and Analysis of Crank and Slotted Lever Quick Return Mech...
Design, Fabrication and Analysis of Crank and Slotted Lever Quick Return Mech...
 
Optimum weight design of ship’s structures
Optimum weight design of ship’s structuresOptimum weight design of ship’s structures
Optimum weight design of ship’s structures
 
Optimum weight design of ship’s structures
Optimum weight design of ship’s structuresOptimum weight design of ship’s structures
Optimum weight design of ship’s structures
 
Modeling of Flexible and Rigid Pavements under Aircraft Loading
Modeling of Flexible and Rigid Pavements under Aircraft LoadingModeling of Flexible and Rigid Pavements under Aircraft Loading
Modeling of Flexible and Rigid Pavements under Aircraft Loading
 
Anderson Greenwood Pilot Operated Pressure Relief Valves
Anderson Greenwood Pilot Operated Pressure Relief ValvesAnderson Greenwood Pilot Operated Pressure Relief Valves
Anderson Greenwood Pilot Operated Pressure Relief Valves
 
Designing a shaft system
Designing a shaft systemDesigning a shaft system
Designing a shaft system
 

NCDOT_Croatan_Sound

  • 1. CCROATANROATAN SSOUNDOUND BBRIDGERIDGE Predesign and Construction Phase Load Test Programs Geotechnical Engineering Unit NCDOT By: John Fargher
  • 2. 5.2 Mile Bridge Water Depth is 10 Feet (typical) Scour Ranges from 12 to 30 Feet Bridge Types Conventional (267 Interior Bents) Segmental (174 Interior Bents) Trestle Bents and Footing on Pile Bents Pile Types 24 inch Square PPC Piles 30 inch Square PPC Piles 54 inch Diameter PPC Cylinder Piles AASHTO and Vessel Impact Loadings Project Details and Design Parameters Project Location and Alignment
  • 3. Predesign Load Test Program (1997)Predesign Load Test Program (1997) StrategyStrategy Obtain soil design parameters for modeling lateral stability,Obtain soil design parameters for modeling lateral stability, bearing capacity, and pile driveability. During construction,bearing capacity, and pile driveability. During construction, pile order lengths and driving criteria would be set bypile order lengths and driving criteria would be set by performing dynamic load tests (PDA’s) on production piles.performing dynamic load tests (PDA’s) on production piles. Load TestsLoad Tests Pile Driving Analyzer (PDA)Pile Driving Analyzer (PDA) Axial Static Load Test (Conventional)Axial Static Load Test (Conventional) Lateral Load Test (Conventional)Lateral Load Test (Conventional) Test PilesTest Piles Pile #1 - 95 Feet - 30 inch Square PPC PilePile #1 - 95 Feet - 30 inch Square PPC Pile Pile #2 - 125 Feet - 30 inch Square PPC PilePile #2 - 125 Feet - 30 inch Square PPC Pile Pile #3 - 144 Feet - 54 inch Cylinder PPC PilePile #3 - 144 Feet - 54 inch Cylinder PPC Pile Pile #4 - 144 Feet - 54 inch Cylinder PPC PilePile #4 - 144 Feet - 54 inch Cylinder PPC Pile CostCost - $998,000 (Bid)- $998,000 (Bid) SavingsSavings - $1,800,000 (Estimated)- $1,800,000 (Estimated)
  • 4. Cylinder Pile Installation Purpose - Evaluate Pile Driveability, Jetting, and Set-up of Large Cylinder Piles at the Project Site 30 inch Square Pile Alternate was Selected by Bid 54 inch Square Pile
  • 5. Pile Plunged at 250 tons (FS=1)…No Good Virtually No Set-up or Pile “Freeze” 30 inch Square Pile Axial Static Load Test Unique Reaction Frame
  • 6. Structurally Failed 54 Inch Cylinder Pile Design Capacities (Allowable) 24 inch Square Piles - 150 Tons 30 inch Square Piles - 250 Tons 54 inch Cylinder Piles - 500 Tons Pile Broke at 1500 Tons…FS=3 WOW!!!
  • 7. 30 inch Square Piles Lateral Test Load - 19.5 Tons Deflection - 13 inches Purpose - Determine Lateral Soil Parameters of “Muck” Layer Lateral Load Test
  • 8. Florida Pier Model -Transverse Vessel Impact Loading of 60 Pile Bent Outcome of Lateral Load Test  “Muck” Layer was an Order of Magnitude Stiffer Laterally than Predicted  Reduction in Pile Embedment Required for Fixity  Reduced the Number of Piles Model Used to Determine: Pile Group is Fixed Minimum Tip Elevation Inputs: Loads Structural Parameters Soil Parameters Check: Stability Moments, Shears, Deflections Bearing and Pull-out
  • 9. Construction Phase Load Test ProgramConstruction Phase Load Test Program (1998 to 2000)(1998 to 2000) 25 - Dynamic Load Tests (PDA’s)25 - Dynamic Load Tests (PDA’s) Tip Elevation Must Be Greater than Min. Tip El. Required For FixityTip Elevation Must Be Greater than Min. Tip El. Required For Fixity No Pile Splicing of Concrete Piles AllowedNo Pile Splicing of Concrete Piles Allowed 3 foot Maximum Build-ups3 foot Maximum Build-ups Cut-Offs Greater than 6 feet Require Drilling for DowelsCut-Offs Greater than 6 feet Require Drilling for Dowels Fuel Setting and Stroke AdjustmentsFuel Setting and Stroke Adjustments Tensile Stress Problems EncounteredTensile Stress Problems Encountered 1 - Axial Static Load Test (Conventional)1 - Axial Static Load Test (Conventional) To insure that pile lengths are reduced in these regionsTo insure that pile lengths are reduced in these regions To be performed prior to giving Order Lengths for 57 bentsTo be performed prior to giving Order Lengths for 57 bents To Determine Pile Order Lengths for 2368 PilesTo Determine Pile Order Lengths for 2368 Piles To Control Pile Driving (Quality Control)To Control Pile Driving (Quality Control)
  • 10. For Each Blow it Records: Compressive and Tensile Stresses Energy in the Pile Damage to the Pile Computer that is Attached to the Pile by means of Strain Gages and Accelerometers. It Predicts: Capacity (Skin and Total) Hammer Stroke Pile Driving Analyzer (PDA) The PDA is Used to Monitor and Control Pile Driving
  • 11. Determined Based on a PDA Test PileDetermined Based on a PDA Test Pile To Reduce Pile Lengths andTo Reduce Pile Lengths and Achieve Minimum Tip Elevation and BearingAchieve Minimum Tip Elevation and Bearing PDA’s Performed Adjacent to BoringsPDA’s Performed Adjacent to Borings Each PDA May Represent between 36 to 258 PilesEach PDA May Represent between 36 to 258 Piles PDA Sequence is Contractors’ OptionPDA Sequence is Contractors’ Option With Each Successive PDA there is a Learning CurveWith Each Successive PDA there is a Learning Curve The 2 Curves have 3 feet of Super ElevationThe 2 Curves have 3 feet of Super Elevation Trestle Bents have Battered Leading and Trailing PilesTrestle Bents have Battered Leading and Trailing Piles PDA Test PilesPDA Test Piles Pile Order Lengths Considerations:Considerations: Goal -Goal -
  • 12. Axial Static Load Test 30 inch Square Pile Purpose - Shorten 410 piles 10 meters each Cost $170,000 Savings $643,864
  • 13. Construction Load Test Savings Estimated Savings = $1.4 Million (from Pile Length Reduction Only) # Piles Order Lengths Reduction # Piles Order Lengths Reduction PDA #1 66 32 to 35 m 0 m PDA #14 258 40 to 41 m 0 m PDA #2 36 35 m 0 m PDA #15 52 36 m 4 m PDA #3 42 41 m 6 m PDA #16 84 36 m 4 m PDA #4 77 41 m 2 to 5 m PDA #17 130 34 to 32 m 10 m * PDA #5 91 40 to 41 m 7 to 10 m PDA #18 84 31 to 32 m 10 m * PDA #6 119 39 m 4 to 10 m PDA #19 119 32 to 34 m 10 m * PDA #7 112 39 m 0 to 2 m PDA #20 77 34 m 10 m * PDA #8 49 38 m 1 to 2 m PDA #21 77 43 m 0 to 3 m PDA #9 63 42 to 44 m 0 m PDA #22 154 43 to 44 m 0 to 1 m PDA #10 70 39 m 5 m PDA #23 91 39 to 41 m 0 to 3 m PDA #11 108 35 m 4 to 6 m PDA #24 85 40 to 41 m 0 m PDA #12 70 35 m 7 m PDA #25 42 36 m 1 m PDA #13 216 41 to 42 m 0 m * Based on Static Load Test
  • 14. Hammer Adjustments Delmag D100-13 (Diesel) 4 Fuel Settings Conmaco 300E5 (Air) 2 Stroke Settings Hammers Currently in Use Proposed Hammers Delmag D80-13 (Diesel) 4 Fuel Settings ICE 205S (Diesel) Variable Stroke Settings
  • 15. NCDOT’s Experience with Predesign Load Testing TR NEWS Sept/Oct 1999 Issue Research Pays Off Article Condensed Version By: John Fargher, Nariman Abar, Jamey Batts, Brian Keaney, and Sean Byrne Transportation Research Record No. 1663
  • 16. For additional information contact: jfargher@dot.state.nc.us