by
Introduction Importance & Relevance of Solar Energy in India Objectives & Targets Mission Strategy (Phase I & II)  Proposed Roadmap Policy & Regulatory Framework Research & Development 11/24/09
Human Resource Development Institutional Arrangements for Mission International Collaboration Financing Mission Activities 11/24/09
Major initiative by GOI & State Governments Aims at promoting ecologically sustainable growth  Also addresses energy security challenge Will contribute to the global effort to meet the challenges of climate change 11/24/09
Cost Solar is high on absolute cost as compared with other power such as coal Objective of Solar Mission is to drive down the cost by Rapid scale-up of capacity Technological innovation Mission anticipates to achieve Grid parity by 2022 Parity with coal-based thermal power by 2030 11/24/09
Cost trajectory depends on  Scale of global deployment Technological development & transfer Cost projections vary - from 22% for every doubling of capacity to a reduction of only 60% with global deployment increasing 16 times the current level Mission recognizes a number of off-grid applications for meeting rural needs which are cost-effective & requires rapid expansion 11/24/09
Scalability About 5000 Trillion Kwh energy potential is incident over India’s land area with most parts receiving 4-7 Kwh/Sq.mt/Day Technologies that can be used to harness the resource & provide huge scalability of solar in India– Solar Photovoltaics & Solar Thermal Advantages of Solar technology Ability to provide power in a distributed basis Enable rapid capacity addition with short lead times. Apt solution for rural electrification Can work in diffused radiating conditions as well 11/24/09
Environmental Impact Zero emissions while generating heat and emissions Security of source Available abundantly Small fraction of total incident solar energy can meet the entire country’s power requirements 11/24/09
Objective is to establish India as a global leader in solar energy Mission adopts 3-phase approach Phase I (up to 2012/2013) – remaining period of 11 th  five yr plan & first yr of 12 th  yr plan Phase II (2013-2017) – remaining 4 yrs of 12 th  five yr plan Phase III (2017-2022) – 13 th  five yr plan 11/24/09
End of each plan there will be Evaluation of progress Review of capacity Targets for subsequent phases  Above evaluations will be based on emerging cost and technology trends, both domestic and global Aims to protect government from subsidy exposure & expects cost reduction does not materialize or is  more rapid than expected 11/24/09
Mission Targets Create an enabling policy framework for the deployment of 20,000 MW of solar power by 2022 Ramp up capacity of grid-connected solar power generation  2013 – 1000 MW 2017 Additional 3000 MW  (mandatory use of renewable purchase obligation by utilities backed with preferential tariff) Capacity could increase to 10,000 MW installed power by 2017 or more, based on enhanced & enabled international finance & technology transfer 11/24/09
2022 – 20,000 MW or more – will be dependent on “ learning ” of first two phases Create favorable conditions for solar manufacturing capability (solar thermal for indigenous production & market leadership) Promote programmes for off grid applications (1000 MW – 2017 & 2000 MW – 2022) Achieve 15 million sq. meters – 2017 & 20 million sq. meters -2022  of solar thermal collector area 2022 - deploy 20 million solar lighting systems for rural areas  11/24/09
Phase I Will provide broad framework to achieve objectives  Will create necessary environment to attract industry & project developers to invest in research, domestic manufacturing & development of solar power generation Hence will help in creating the critical mass for a domestic solar industry Mission to work closely with State Govts., Regulators, Power utilities & Local self govt. bodies to ensure activities & policy framework being laid out can be implemented effectively 11/24/09
Utility connected applications: constructing the solar grid Promoting solar power through Renewable Purchase Obligation (RPO) mandated for power utilities, with specific solar component RPO will drive utility scale power generation  (solar PV or solar thermal) RPO will gradually increase where as the tariff fixed for solar power purchase will decline over time The below 80°C challenge – solar collectors Mission sets an ambitious target for ensuring that applications, domestic & industrial, below 80°C are solarised 11/24/09
Key strategy to make necessary policy changes to meet this objective Making solar heaters mandatory, through building byelaws and incorporation in the National Building Code Ensure the introduction of effective mechanisms for certification and rating of manufacturers of solar thermal applications Facilitate measurement and promotion of these individual devices through local agencies and power utilities Support the upgrading of technologies and manufacturing capacities through soft loans, to achieve higher efficiencies and further cost reduction 11/24/09
The off-grid opportunity – lighting homes of the power- deprived poor Key problem to find optimum financial strategy to pay for the high-end initial costs in these applications through appropriate Government support Government has promoted the use of decentralized applications through financial incentives and promotional schemes Solar Mission has set a target of 1000 MW by 2017, which may appear small, but its reach will add up to bringing changes in millions of households  30 % capital subsidy for promoting innovative applications of solar energy 11/24/09
Mission plans to Provide solar lighting system under the ongoing remote village electrification programme of MNRE to cover about 10,000 villages & hamlets Set up stand alone rural solar power plants in special category States and remote and difficult areas such as Lakshadweep, Andaman & Nicobar Islands, Ladakh region of J&K. Border areas would also be included  Promotion of other off grid solar power applications would also be encouraged (includes hybrid systems to meet power, heating & cooling energy requirements currently being met by use of diesel & other fossil fuels) 11/24/09
Solar energy to power computers to assist learning in schools & hostels would Consider  up to 30 per cent capital subsidy for promoting such innovative applications Also structure a non-distorting framework to support entrepreneurship, up-scaling and innovation  Manufacturing capabilities: innovate, expand and disseminate  Requires India’s leadership role in low-cost  High cost solar manufacturing, including balance of system components Proactive implementation of Special Incentive Package policy to promote PV manufacturing plants SME sector forms the backbone for manufacture of various components and systems for solar systems 11/24/09
R&D for Solar India: creating conditions for research and application  Focus on  Improvement of efficiencies in existing materials, devices and applications and  Reducing costs of balance of systems,  Establishing new applications by addressing issues related to integration and optimization Developing cost-effective storage technologies which would address both variability & storage constraints Targeting space-intensity through the use of better concentrators Application of nano-technology & use of better & improved materials 11/24/09
Solar Research Council to be set up to oversee the strategy Human resource development programme to be established  In phase I – 1000 young scientists & engineers would be incentivized to get trained on different solar energy technology as mission’s long-term R&D & HRD plan Pilot demonstration projects would be closely aligned with the Mission’s R & D priorities and designed to promote technology development and cost reduction  In Phase I - mission envisages setting up of the following demonstration projects which are already initiated by MNRE & those which may be set up by corporate investors 11/24/09
50-100 MW Solar thermal plant with 4-6 hours’ storage (which can meet both morning and evening peak loads and double plant load factor up to 40%) A 100-MW capacity parabolic trough technology based solar thermal plant A 100-150 MW Solar hybrid plant with coal, gas or bio-mass to address variability and space-constraints 20-50 MW solar plants with/without storage, based on central receiver technology with molten salt/steam as the working fluid and other emerging technologies. Grid-connected rooftops PV systems on selected government buildings and installations, with net metering. Solar-based space-cooling and refrigeration systems to meet daytime and summer season peak load. These could be installed on selected government buildings and installations 11/24/09
Bidding process will be adopted for better price discovery of determining tariff for solar power It is expected that the plants will be commissioned in the 12 th  plan period 11/24/09
To ensure large-scale deployment of solar generated power for grid-connected as well as distributed and decentralized off-grid provision of commercial energy services 11/24/09 Sl. No.  Application Segment Target for Phase I (2010-2013) Target for Phase II (2013-2017) Target for Phase III (2017-2022) 1 Solar Collectors  7 million sq meters 15 million sq meters 20 million sq meters 2 Off grid solar applications 200 MW 1000 MW 2000 MW 3 Utility grid power, including roof top 1,000-2000 MW 4000-10,000 MW 20000 MW
Provide a predictable incentive structure that enables rapid & large-scale capital investment in solar energy applications Encourage technical innovation & lower the costs In long run, mission would seek to establish a sector-specific legal & regulatory framework for solar power development In short run, it embeds the activities of the mission within the existing framework of Electricity Act of 2003 11/24/09
National Tariff Policy 2006 mandates the State Electricity Regulatory Commissions (SERC) to fix a minimum percentage of energy purchase from renewable sources of energy (availability of resources & impact on retail tariff) Solar power purchase for states  11/24/09 Phase I 0.25% By 2022 Up to 3%
In order to encourage rapid scale-up a scheme is being introduced in co-operation with the Ministry of Power, NTPC & Central Electricity Authority, to simply off-take of solar power & reduce the financial burden on govt. Also aims to bring down the gap between average cost of power and sale price of power NVVN  (wholly owned subsidiary - NTPC) ( NTPC Vidyut Vyapar Nigam Ltd  ) is chosen as the nodal agency for entering into a Power Purchase Agreement (PPA) with solar power developers 11/24/09
PPA Shall be signed with the developers who will be setting up Solar Projects within next three years and are connected to the grid at 33 KV level and above  Will be valid for a period of 25 years Mission will encourage rooftop solar PV and other small solar power plants, connected to LT/11 KV grid, to replace conventional power and diesel-based generators  Generation Based Incentive payable to the utility to cover the difference between the solar tariff determined by CERC, less the base price of Rs. 5.50/kWh with 3% p.a. escalation  11/24/09
State Governments would encourage to promote and establish solar generation Parks with dedicated infrastructure for setting up utility scale plants to ensure ease of capacity creation  Fiscal Incentives Custom duties and excise duties concessions/ exemptions be made available on specific capital equipment, critical materials , components and project imports  Solar Manufacturing in India Aims to take India on a global leadership role in Solar Manufacturing 11/24/09
Targets 4-5 GW equivalent of installed capacity by 2020 including setting up of dedicated manufacturing capacities for poly silicon material to annually make about 2 GW capacity of solar cells India’s current PV module manufacturing capacity 700 MW Some plants likely to be set in public & private sector To achieve installed target capacity, mission recommends Local Demand Creation 11/24/09
Financing & Incentives SEZ like incentives to be provided to the manufacturing parks which may include Zero import duty on capital equipment, raw materials and excise duty exemption Low interest rate loans, priority sector lending Incentives under Special Incentive Package (SIPs) policy to set up integrated manufacturing plants; from poly silicon material to solar modules; and thin film based module manufacturing plants It is also recommended that solar components be covered under the Bureau of Energy Efficiency’s star rating programmes to ensure high standards 11/24/09
Committee may be set up to formulate a policy for promotion of solar thermal manufacture in the country  Ease of Doing Business Infrastructure & ecosystem enablers 2-3 large solar manufacturing tech parks Should have 24x7 power and water supply need to be located near large urban centers with good linkages to ports and airports to ensure rapid access to imported raw materials and high quality engineering talent 11/24/09
Mission will launch a major R&D programme in Solar Energy, which will focus on improving efficiency in existing applications, reducing costs of Balance of Systems To support the R&D Strategy, the Mission may include the following Setting up a high level Research Council comprising eminent scientists, technical experts and representatives from academic and research institutions, industry, Government and Civil Society to guide the overall technology development strategy National Centre of Excellence (NCE) shall be established to implement the technology development plan formulated by the Research Council and serve as its Secretariat 11/24/09
Research Council, in coordination with the National Centre of Excellence,  inventorize existing institutional capabilities for Solar R&D and encourage the setting up of a network of Centres of Excellence, each focusing on an R&D area of its proven competence and capability These centers to be located in research institutes, academic institutions or even private sector companies NCE will provide a national platform for networking among different centers of excellence and research institutions, including foreign R&D institutions and high-tech companies NCE will serve as the funding agency to support performance-linked solar R&D programmes (funding, or co-funding of pilot demonstration projects) in areas relevant to Mission objectives 11/24/09
NCE will coordinate with the IMD, ISRO and other concerned agencies, the detailed mapping of ground insulation, particularly in high potential solar regions of the country To provide support for incubation and start ups, the Mission could tie up with institutions like Centre for Innovation, Incubation and Entrepreneurship (CIIE) based in IIM Ahmedabad to incubate solar energy start-ups and SMEs in India through mentoring, networking and financial support Fund aims to support at least 50 start ups developing & deploying solar related technologies across India over next 5 yrs & would be managed by a professional entity Initiative shall be structured ideally in a private-public partnership model, to be able to provide risky capital to the aspiring entrepreneurs It would also attract contributions from private stakeholders, amounting to, at least 10% of that of the Government 11/24/09
Requires a concomitant increase in technically qualified manpower of international standard Steps required for HRD IITs & premier Engineering Colleges will be involved in designing & developing specialized courses in Solar Energy Government Fellowship programme to train 100 selected engineers / technologies and scientists in Solar Energy in world class institutions abroad will be taken up Setting up of a National Centre for Photovoltaic Research and Education at IIT, Mumbai drawing upon its Department of Energy Science and Engineering and its Centre for Excellence in Nano-Electronics  11/24/09
Autonomous Solar Energy Authority embedded within the existing structure of the Ministry of New and Renewable Energy  To monitor technology developments, review and adjust incentives, manage funding requirements and execute pilot projects  11/24/09
Strategic international collaborations and partnerships Effective technology transfer mechanisms and strong IPR protection Co-operation through bilateral and multilateral arrangements would be facilitated  11/24/09
Budgetary support for the activities under the National Solar Mission established under the MNRE International Funds under the UNFCCC framework, which would enable up scaling of Mission targets 11/24/09

National Solar Mission India

  • 1.
  • 2.
    Introduction Importance &Relevance of Solar Energy in India Objectives & Targets Mission Strategy (Phase I & II) Proposed Roadmap Policy & Regulatory Framework Research & Development 11/24/09
  • 3.
    Human Resource DevelopmentInstitutional Arrangements for Mission International Collaboration Financing Mission Activities 11/24/09
  • 4.
    Major initiative byGOI & State Governments Aims at promoting ecologically sustainable growth Also addresses energy security challenge Will contribute to the global effort to meet the challenges of climate change 11/24/09
  • 5.
    Cost Solar ishigh on absolute cost as compared with other power such as coal Objective of Solar Mission is to drive down the cost by Rapid scale-up of capacity Technological innovation Mission anticipates to achieve Grid parity by 2022 Parity with coal-based thermal power by 2030 11/24/09
  • 6.
    Cost trajectory dependson Scale of global deployment Technological development & transfer Cost projections vary - from 22% for every doubling of capacity to a reduction of only 60% with global deployment increasing 16 times the current level Mission recognizes a number of off-grid applications for meeting rural needs which are cost-effective & requires rapid expansion 11/24/09
  • 7.
    Scalability About 5000Trillion Kwh energy potential is incident over India’s land area with most parts receiving 4-7 Kwh/Sq.mt/Day Technologies that can be used to harness the resource & provide huge scalability of solar in India– Solar Photovoltaics & Solar Thermal Advantages of Solar technology Ability to provide power in a distributed basis Enable rapid capacity addition with short lead times. Apt solution for rural electrification Can work in diffused radiating conditions as well 11/24/09
  • 8.
    Environmental Impact Zeroemissions while generating heat and emissions Security of source Available abundantly Small fraction of total incident solar energy can meet the entire country’s power requirements 11/24/09
  • 9.
    Objective is toestablish India as a global leader in solar energy Mission adopts 3-phase approach Phase I (up to 2012/2013) – remaining period of 11 th five yr plan & first yr of 12 th yr plan Phase II (2013-2017) – remaining 4 yrs of 12 th five yr plan Phase III (2017-2022) – 13 th five yr plan 11/24/09
  • 10.
    End of eachplan there will be Evaluation of progress Review of capacity Targets for subsequent phases Above evaluations will be based on emerging cost and technology trends, both domestic and global Aims to protect government from subsidy exposure & expects cost reduction does not materialize or is more rapid than expected 11/24/09
  • 11.
    Mission Targets Createan enabling policy framework for the deployment of 20,000 MW of solar power by 2022 Ramp up capacity of grid-connected solar power generation 2013 – 1000 MW 2017 Additional 3000 MW (mandatory use of renewable purchase obligation by utilities backed with preferential tariff) Capacity could increase to 10,000 MW installed power by 2017 or more, based on enhanced & enabled international finance & technology transfer 11/24/09
  • 12.
    2022 – 20,000MW or more – will be dependent on “ learning ” of first two phases Create favorable conditions for solar manufacturing capability (solar thermal for indigenous production & market leadership) Promote programmes for off grid applications (1000 MW – 2017 & 2000 MW – 2022) Achieve 15 million sq. meters – 2017 & 20 million sq. meters -2022 of solar thermal collector area 2022 - deploy 20 million solar lighting systems for rural areas 11/24/09
  • 13.
    Phase I Willprovide broad framework to achieve objectives Will create necessary environment to attract industry & project developers to invest in research, domestic manufacturing & development of solar power generation Hence will help in creating the critical mass for a domestic solar industry Mission to work closely with State Govts., Regulators, Power utilities & Local self govt. bodies to ensure activities & policy framework being laid out can be implemented effectively 11/24/09
  • 14.
    Utility connected applications:constructing the solar grid Promoting solar power through Renewable Purchase Obligation (RPO) mandated for power utilities, with specific solar component RPO will drive utility scale power generation (solar PV or solar thermal) RPO will gradually increase where as the tariff fixed for solar power purchase will decline over time The below 80°C challenge – solar collectors Mission sets an ambitious target for ensuring that applications, domestic & industrial, below 80°C are solarised 11/24/09
  • 15.
    Key strategy tomake necessary policy changes to meet this objective Making solar heaters mandatory, through building byelaws and incorporation in the National Building Code Ensure the introduction of effective mechanisms for certification and rating of manufacturers of solar thermal applications Facilitate measurement and promotion of these individual devices through local agencies and power utilities Support the upgrading of technologies and manufacturing capacities through soft loans, to achieve higher efficiencies and further cost reduction 11/24/09
  • 16.
    The off-grid opportunity– lighting homes of the power- deprived poor Key problem to find optimum financial strategy to pay for the high-end initial costs in these applications through appropriate Government support Government has promoted the use of decentralized applications through financial incentives and promotional schemes Solar Mission has set a target of 1000 MW by 2017, which may appear small, but its reach will add up to bringing changes in millions of households 30 % capital subsidy for promoting innovative applications of solar energy 11/24/09
  • 17.
    Mission plans toProvide solar lighting system under the ongoing remote village electrification programme of MNRE to cover about 10,000 villages & hamlets Set up stand alone rural solar power plants in special category States and remote and difficult areas such as Lakshadweep, Andaman & Nicobar Islands, Ladakh region of J&K. Border areas would also be included Promotion of other off grid solar power applications would also be encouraged (includes hybrid systems to meet power, heating & cooling energy requirements currently being met by use of diesel & other fossil fuels) 11/24/09
  • 18.
    Solar energy topower computers to assist learning in schools & hostels would Consider up to 30 per cent capital subsidy for promoting such innovative applications Also structure a non-distorting framework to support entrepreneurship, up-scaling and innovation Manufacturing capabilities: innovate, expand and disseminate Requires India’s leadership role in low-cost High cost solar manufacturing, including balance of system components Proactive implementation of Special Incentive Package policy to promote PV manufacturing plants SME sector forms the backbone for manufacture of various components and systems for solar systems 11/24/09
  • 19.
    R&D for SolarIndia: creating conditions for research and application Focus on Improvement of efficiencies in existing materials, devices and applications and Reducing costs of balance of systems, Establishing new applications by addressing issues related to integration and optimization Developing cost-effective storage technologies which would address both variability & storage constraints Targeting space-intensity through the use of better concentrators Application of nano-technology & use of better & improved materials 11/24/09
  • 20.
    Solar Research Councilto be set up to oversee the strategy Human resource development programme to be established In phase I – 1000 young scientists & engineers would be incentivized to get trained on different solar energy technology as mission’s long-term R&D & HRD plan Pilot demonstration projects would be closely aligned with the Mission’s R & D priorities and designed to promote technology development and cost reduction In Phase I - mission envisages setting up of the following demonstration projects which are already initiated by MNRE & those which may be set up by corporate investors 11/24/09
  • 21.
    50-100 MW Solarthermal plant with 4-6 hours’ storage (which can meet both morning and evening peak loads and double plant load factor up to 40%) A 100-MW capacity parabolic trough technology based solar thermal plant A 100-150 MW Solar hybrid plant with coal, gas or bio-mass to address variability and space-constraints 20-50 MW solar plants with/without storage, based on central receiver technology with molten salt/steam as the working fluid and other emerging technologies. Grid-connected rooftops PV systems on selected government buildings and installations, with net metering. Solar-based space-cooling and refrigeration systems to meet daytime and summer season peak load. These could be installed on selected government buildings and installations 11/24/09
  • 22.
    Bidding process willbe adopted for better price discovery of determining tariff for solar power It is expected that the plants will be commissioned in the 12 th plan period 11/24/09
  • 23.
    To ensure large-scaledeployment of solar generated power for grid-connected as well as distributed and decentralized off-grid provision of commercial energy services 11/24/09 Sl. No. Application Segment Target for Phase I (2010-2013) Target for Phase II (2013-2017) Target for Phase III (2017-2022) 1 Solar Collectors 7 million sq meters 15 million sq meters 20 million sq meters 2 Off grid solar applications 200 MW 1000 MW 2000 MW 3 Utility grid power, including roof top 1,000-2000 MW 4000-10,000 MW 20000 MW
  • 24.
    Provide a predictableincentive structure that enables rapid & large-scale capital investment in solar energy applications Encourage technical innovation & lower the costs In long run, mission would seek to establish a sector-specific legal & regulatory framework for solar power development In short run, it embeds the activities of the mission within the existing framework of Electricity Act of 2003 11/24/09
  • 25.
    National Tariff Policy2006 mandates the State Electricity Regulatory Commissions (SERC) to fix a minimum percentage of energy purchase from renewable sources of energy (availability of resources & impact on retail tariff) Solar power purchase for states 11/24/09 Phase I 0.25% By 2022 Up to 3%
  • 26.
    In order toencourage rapid scale-up a scheme is being introduced in co-operation with the Ministry of Power, NTPC & Central Electricity Authority, to simply off-take of solar power & reduce the financial burden on govt. Also aims to bring down the gap between average cost of power and sale price of power NVVN (wholly owned subsidiary - NTPC) ( NTPC Vidyut Vyapar Nigam Ltd ) is chosen as the nodal agency for entering into a Power Purchase Agreement (PPA) with solar power developers 11/24/09
  • 27.
    PPA Shall besigned with the developers who will be setting up Solar Projects within next three years and are connected to the grid at 33 KV level and above Will be valid for a period of 25 years Mission will encourage rooftop solar PV and other small solar power plants, connected to LT/11 KV grid, to replace conventional power and diesel-based generators Generation Based Incentive payable to the utility to cover the difference between the solar tariff determined by CERC, less the base price of Rs. 5.50/kWh with 3% p.a. escalation 11/24/09
  • 28.
    State Governments wouldencourage to promote and establish solar generation Parks with dedicated infrastructure for setting up utility scale plants to ensure ease of capacity creation Fiscal Incentives Custom duties and excise duties concessions/ exemptions be made available on specific capital equipment, critical materials , components and project imports Solar Manufacturing in India Aims to take India on a global leadership role in Solar Manufacturing 11/24/09
  • 29.
    Targets 4-5 GWequivalent of installed capacity by 2020 including setting up of dedicated manufacturing capacities for poly silicon material to annually make about 2 GW capacity of solar cells India’s current PV module manufacturing capacity 700 MW Some plants likely to be set in public & private sector To achieve installed target capacity, mission recommends Local Demand Creation 11/24/09
  • 30.
    Financing & IncentivesSEZ like incentives to be provided to the manufacturing parks which may include Zero import duty on capital equipment, raw materials and excise duty exemption Low interest rate loans, priority sector lending Incentives under Special Incentive Package (SIPs) policy to set up integrated manufacturing plants; from poly silicon material to solar modules; and thin film based module manufacturing plants It is also recommended that solar components be covered under the Bureau of Energy Efficiency’s star rating programmes to ensure high standards 11/24/09
  • 31.
    Committee may beset up to formulate a policy for promotion of solar thermal manufacture in the country Ease of Doing Business Infrastructure & ecosystem enablers 2-3 large solar manufacturing tech parks Should have 24x7 power and water supply need to be located near large urban centers with good linkages to ports and airports to ensure rapid access to imported raw materials and high quality engineering talent 11/24/09
  • 32.
    Mission will launcha major R&D programme in Solar Energy, which will focus on improving efficiency in existing applications, reducing costs of Balance of Systems To support the R&D Strategy, the Mission may include the following Setting up a high level Research Council comprising eminent scientists, technical experts and representatives from academic and research institutions, industry, Government and Civil Society to guide the overall technology development strategy National Centre of Excellence (NCE) shall be established to implement the technology development plan formulated by the Research Council and serve as its Secretariat 11/24/09
  • 33.
    Research Council, incoordination with the National Centre of Excellence, inventorize existing institutional capabilities for Solar R&D and encourage the setting up of a network of Centres of Excellence, each focusing on an R&D area of its proven competence and capability These centers to be located in research institutes, academic institutions or even private sector companies NCE will provide a national platform for networking among different centers of excellence and research institutions, including foreign R&D institutions and high-tech companies NCE will serve as the funding agency to support performance-linked solar R&D programmes (funding, or co-funding of pilot demonstration projects) in areas relevant to Mission objectives 11/24/09
  • 34.
    NCE will coordinatewith the IMD, ISRO and other concerned agencies, the detailed mapping of ground insulation, particularly in high potential solar regions of the country To provide support for incubation and start ups, the Mission could tie up with institutions like Centre for Innovation, Incubation and Entrepreneurship (CIIE) based in IIM Ahmedabad to incubate solar energy start-ups and SMEs in India through mentoring, networking and financial support Fund aims to support at least 50 start ups developing & deploying solar related technologies across India over next 5 yrs & would be managed by a professional entity Initiative shall be structured ideally in a private-public partnership model, to be able to provide risky capital to the aspiring entrepreneurs It would also attract contributions from private stakeholders, amounting to, at least 10% of that of the Government 11/24/09
  • 35.
    Requires a concomitantincrease in technically qualified manpower of international standard Steps required for HRD IITs & premier Engineering Colleges will be involved in designing & developing specialized courses in Solar Energy Government Fellowship programme to train 100 selected engineers / technologies and scientists in Solar Energy in world class institutions abroad will be taken up Setting up of a National Centre for Photovoltaic Research and Education at IIT, Mumbai drawing upon its Department of Energy Science and Engineering and its Centre for Excellence in Nano-Electronics 11/24/09
  • 36.
    Autonomous Solar EnergyAuthority embedded within the existing structure of the Ministry of New and Renewable Energy To monitor technology developments, review and adjust incentives, manage funding requirements and execute pilot projects 11/24/09
  • 37.
    Strategic international collaborationsand partnerships Effective technology transfer mechanisms and strong IPR protection Co-operation through bilateral and multilateral arrangements would be facilitated 11/24/09
  • 38.
    Budgetary support forthe activities under the National Solar Mission established under the MNRE International Funds under the UNFCCC framework, which would enable up scaling of Mission targets 11/24/09