SlideShare a Scribd company logo
Multi-objective Wind Farm Design
Exploring the Trade-off between Capacity Factor and Land Use
Weiyang Tong, Souma Chowdhury, Ali Mehmani, and Achille Messac
Syracuse University, Department of Mechanical and Aerospace Engineering
10th World Congress on Structural and Multidisciplinary Optimization
May 19-24, 2013, Orlando, Florida
Wind Farm Development
2
 Wind farm development is an extremely complex process that is affected by
several performance objectives (energy production and cost, etc.)
 Most of these factors are strongly coupled in the influence on the performance
objectives
Factors affecting wind
farm performance
Natural factors
(uncontrollable)
Wind shear
Wind speed
& direction
Mean speed Intermittency
Ambient
turbulence …
Design factors
(controllable)
Land
configuration
Land area Farm layout
Turbine
selection
Grid
connection
Energy
storage
…
Early Stage
(up to 3 mon. ~ 3 yr.)
• Wind resource
assessment
• Site selection
• Preliminary feasibility
analysis
Mid Stage
(2 ~ 5 yr.)
• Economics analysis
• Transmission capacity
analysis
• Regulatory framework
• Environmental studies
Late Stage
(up to 25 yr)
• Financing
• Construction
• Operation & Maintenance
Research Motivation
3
 Owing to the lack of early stage conceptual design
frameworks, wind farm planning is an undesirably time-
consuming process.
 Transparency and efficiency are compromised in
conventional wind farm planning due to typical
independent decision making of different factors (e.g.,
wind farm layouts are generally designed for prescribed
land area and nameplate capacity)
 Quantitative exploration of the balance between the key
objectives is mostly missing in the state of the art (e.g.,
balance between energy production and land use)
Research Objective
4
Develop a Bi-level Wind Farm Trade-off Visualization
framework
Explore the trade-off between the concerned design
objectives: capacity factor – land use
Visualize the trade-off by parametrically translating the
Pareto
Outline
5
• Design Objectives
• Wind farm Energy Production (Capacity Factor)
• Land Use (Land Area per MW Installed)
• Bi-level Wind Farm Trade-off Visualization Framework
• Lower-level: Trade-off exploration
• Upper-level: Trade-off visualization
• Numerical Experiment
• Concluding Remarks
Wind Farm Energy Production
6
• Wind farm Capacity Factor
𝐶𝐹 =
𝐸𝑛𝑒𝑟𝑔𝑦 𝑝𝑟𝑜𝑑𝑢𝑐𝑡𝑖𝑜𝑛 𝑜𝑣𝑒𝑟 𝑎 𝑡𝑖𝑚𝑒 𝑝𝑒𝑟𝑖𝑜𝑑
𝑃𝑜𝑡𝑒𝑛𝑡𝑖𝑎𝑙 𝑒𝑛𝑒𝑟𝑔𝑦 𝑜𝑢𝑡𝑝𝑢𝑡
• Power Generational model in Unrestricted Wind Farm Layout
Optimization (UWFLO) framework
• Quantify the power generation as a function of incoming wind conditions,
farm layout, and turbine features
Denmark's Horns Rev 1 wind farm
The Wake Effect
Land Area per MW Installed (LAMI)
7
• Based on the farm layout, the land use is determined by the Smallest Bounding
Rectangle (SBR) enclosing all turbines
• The actual land area is represented as the buffer zone created by making a 2D
distance away from the SBR
• Turbines are not placed on the boundary of a wind farm
• Avoid “zero” area when minimizing the land area
Wind Farm Layout Optimization
8
wind farm layout optimization flowchart
Stop criterion
Reach the best performance?
Evaluate design
objective functions
Trade-off between
design objectives
Adjust the
location of
turbines
Prescribed
conditions
Yes
No
-4000
-3000
-2000
-1000
0
1000
2000
3000
4000
-4000 -3000 -2000 -1000 0 1000 2000 3000 4000
optimal layout of 20 turbines optimal layout of 40 turbines
How many turbines should we install?
Bi-level Wind Farm Visualization Framework
9
wind farm layout optimization flowchart
Stop criterion
Reach the best performance?
Evaluate design
objective functions
Trade-off between
design objectives
Adjust the
location of
turbines
Sample
design
factors
Wind
distribution
Initial
boundary
Yes
No
Bi-level Wind Farm Visualization Framework
10
Capital
investment
Nameplate
capacity
Turbine
features
Numerical Experiment
• Two design objectives:
• Maximize the wind farm capacity factor
• Minimize the Land Area per MW Installed (LAMI)
• Identical turbines are used (GE-1.5 xle)
• Wind data from a site at North Dakota is used
Upper-level: the trade-off between capacity factor and LAMI is parametrically
represented by Nameplate Capacity
Lower-level: multi-objective wind farm layout optimization is performed as a
constrained single objective optimization using Mixed-Discrete Particle Swarm
Optimization (MDPSO) algorithm*
11*: Chowdhury et al., 2013 Struct Multidisc Optim
Lower-level: CF-LAMI Trade-off Exploration
12
 A set of sample nameplate capacities are generated within the 20 MW – 100 MW range
 A square initial region is pre-defined with a size less than 120 hectares per MW installed
 The bi-objective optimization is formulated as
Sample #
Nameplate
Capacity
No. of turbines
1 20 13
2 30 20
3 60 40
4 90 60
5 100 67
max 𝐶𝐹, min 𝐴
subject to
𝑔 𝑉 ≤ 0
𝑉 𝑚𝑖𝑛 ≤ 𝑉 ≤ 𝑉𝑚𝑎𝑥
𝑉 = {𝑋1, 𝑋2, ⋯ , 𝑋 𝑁, 𝑌1, 𝑌2, ⋯ , 𝑌𝑁}
Applying the Smallest Bounding Rectangle
enclosing all turbines
max 𝑓(𝑉) =
𝐸𝑓𝑎𝑟𝑚
365 × 24 𝑁𝐶
subject to
𝑔1 𝑉 ≤ 0
𝑔2 𝑉 ≤ 0
𝑉 𝑚𝑖𝑛 ≤ 𝑉 ≤ 𝑉𝑚𝑎𝑥
𝑉 = {𝑋1, 𝑋2, ⋯ , 𝑋 𝑁, 𝑌1, 𝑌2, ⋯ , 𝑌𝑁}
Lower-level: CF-LAMI Trade-off Exploration
 Solved by: Mixed-Discrete Particle Swarm Optimization 13
Estimated using the power generation model
in UWFLO framework
 N is determined by the sample nameplate
capacity
 𝑉𝑚𝑎𝑥 and 𝑉 𝑚𝑖𝑛 are set based on the initial
boundary regulated by the allowable land area
𝐸𝑓𝑎𝑟𝑚 = (365 × 24)
𝑗=1
𝑁 𝑝
𝑃𝑓𝑎𝑟𝑚 𝑝∆𝑈∆𝜃
Inter-Turbine Spacing
Land Area Constraint
Lower-level: CF-LAMI Trade-off Exploration
14
-4000
-3000
-2000
-1000
0
1000
2000
3000
4000
-4000 -3000 -2000 -1000 0 1000 2000 3000 4000
optimal layout with land area of 180 ha
optimal layout with land area of 900 ha
optimal layout with land area of 3000 ha
Optimal layouts of 20 turbines with different land area constraints
Upper-level: CF-LAMI Trade-off Visualization
15
𝐶𝐹 = 𝑎𝐴 𝑏 + 𝑐
Pareto solutions of 13 turbines
Pareto solutions of 20 turbines
Pareto solutions of 40 turbines
Pareto solutions of 60 turbines
Pareto solutions of 67 turbines
Fitted curve for case of 13 turbines
Fitted curve for case of 20 turbines
Fitted curve for case of 40 turbines
Fitted curve for case of 60 turbines
Fitted curve for case of 67 turbines
22.4ha/MW 22.4ha/MW
US Average Land Use:
34ha/MW
Concluding Remarks
• A Bi-level Wind Farm Trade-off Visualization framework was proposed for
conceptual design of wind farms.
• The CF-LAMI trade-off was parametrically represented as a function of
nameplate capacity.
• This proposed framework can streamline the wind farm development process,
especially for large-scale wind farm projects, and help wind farm developers to
make efficient and effective decisions.
• Future work
• Use both turbine features (turbine rated power) and nameplate capacity to
parameterize the trade-off curve
• Explore the trade-off, such as Capacity Factor vs. Net Impact on
Surroundings
16
Acknowledgement
 I would like to acknowledge my research adviser
Prof. Achille Messac, and my co-adviser Prof.
Souma Chowdhury for their immense help and
support in this research.
 I would also like to thank my friend and colleague
Ali Mehmani for his valuable contributions to this
paper.
 Support from the NSF Awards is also
acknowledged.
17
Questions
and
Comments
18
Thank you
CF Response Surface Obtained
 Even if turbines are allowed the same land area per MW installed, a
greater number of turbines (higher nameplate capacity) would lead to
greater wake losses, leading to lower energy production.
 A contour plot of the function can provide the “LAMI vs. nameplate
capacity” cutoff curve that corresponds to the threshold CF.
LandAreaperMWinstalled(m2/MW)
Nameplate Capacity (MW)
19
20
Single Wake Test: Comparing Wake Growth
 Frandsen model and Larsen model predict
greater wake diameters
 Jensen model has a linear expansion
 The difference between wake diameters
predicted by each model can be as large as
3D, and it can be larger as the downstream
distance increases
3D
21
Single Wake Test: Comparing Wake Speed
 Frandsen model predicts the highest
wake speed
 Ishihara model predicts a relatively
low wake speed; however, as the
downstream distance increases, the
wake recovers fast owing to the
consideration of turbine induced
turbulence in this model
wind
direction
Numerical Experiments
22
 An array-like wind farm with 9 GE 2.5 MW – 100m turbines is considered.
 A fixed aspect ratio is selected; the streamwise spacing is ranged from 5D to 20D,
while the lateral spacing is no less than 2D.
 The farm capacity factor is given by
Prj: Rated capacity, Pfarm: Farm output
23
Layout-based Power Generation Model
 In this power generation model, the induction factor is treated as a
function of the incoming wind speed and turbine features:
U: incoming wind speed; P: power generated, given by the power curve
kg, kb: mechanical and electrical efficiencies, Dj: Rotor Diameter, 𝜌: Air density
 A generalized power curve is used to represent the approximate power
response of a particular turbine
𝑈𝑖𝑛, 𝑈 𝑜𝑢𝑡, and 𝑈𝑟: cut-in speed, cut-out speed, and rated speed
𝑃𝑟: Rated capacity, 𝑃𝑛: Polynomial fit for the generalized power curve*
*: Chowdhury et al , 2011
24
Layout-based Power Generation Model
 Turbine-j is in the influence of the wake of Turbine-i, if and only if
Considers turbines with differing rotor-diameters and hub-heights
 The Katic model* is used to account for wake merging and partial wake
overlap
𝑢𝑗: Effective velocity deficit
𝐴 𝑘𝑗: Overlapping area between Turbine-j
and Turbine-k
Partial wake-rotor overlap *: Katic et al , 1987
Mixed-Discrete Particle Swarm Optimization (PSO)
 This algorithm has the ability to
deal with both discrete and
continuous design variables, and
 The mixed-discrete PSO presents
an explicit diversity preservation
capability to prevent premature
stagnation of particles.
 PSO can appropriately address the
non-linearity and the multi-
modality of the wind farm model.
25
Lower-level: multi-objective wind farm layout optimization
26
 A set of sample nameplate capacity factors is generated
within the 20 MW – 100 MW range
 A square initial region is pre-defined, f which size is
less than 110 hectares per MW installed
 The bi-objective optimization was solved as a
Constrained single objective optimization
Sample #
Nameplate
Capacity
No. of
turbines
1 20 13
2 30 20
3 60 40
4 90 60
5 100 67
max 𝑓(𝑉) =
𝐸𝑓𝑎𝑟𝑚
365 × 24 𝑁𝐶
subject to
𝑔1 𝑉 ≤ 0
𝑔2 𝑉 ≤ 0
𝑉 𝑚𝑖𝑛 ≤ 𝑉 ≤ 𝑉𝑚𝑎𝑥
𝑉 = {𝑋1, 𝑋2, ⋯ , 𝑋 𝑁, 𝑌1, 𝑌2, ⋯ , 𝑌𝑁}
Mid-level: Quantification of Trade-offs between Design Objectives
27
• The wind distribution is unique
• A group of Pareto curves can be obtained from the multi-objective wind farm
layout optimization at the bottom-level
• Based on observation, use an appropriate form of function to fit all the Pareto
curves, for example, a form of power function with 3 coefficients
• Once the global design factors are specified, a trade-off curve between two
objectives can be generated
𝑜𝑏𝑗2
𝑛
= 𝑎(𝑝1, 𝑝2, ⋯ , 𝑝 𝐾)𝑜𝑏𝑗1
𝑛 𝑏(𝑝1,𝑝2,⋯,𝑝 𝑁)
+ 𝑐(𝑝1, 𝑝2, ⋯ , 𝑝 𝐾)
where 𝑛 = 1,2, ⋯ , 𝑁 representing 𝑁 sets of samples of global design factors; and 𝐾 is the total
number of global design factors accounted for
28

More Related Content

What's hot

WFO_MAO_2012_Souma
WFO_MAO_2012_SoumaWFO_MAO_2012_Souma
WFO_MAO_2012_Souma
MDO_Lab
 
Lcoe offshore
Lcoe offshoreLcoe offshore
Lcoe offshore
inesgs
 
Impact of Different Wake Models on the Estimation of Wind Farm Power Generation
Impact of Different Wake Models on the Estimation of Wind Farm Power GenerationImpact of Different Wake Models on the Estimation of Wind Farm Power Generation
Impact of Different Wake Models on the Estimation of Wind Farm Power Generation
Weiyang Tong
 
Control Scheme for an IPM Synchronous Generator Based-Variable Speed Wind Tur...
Control Scheme for an IPM Synchronous Generator Based-Variable Speed Wind Tur...Control Scheme for an IPM Synchronous Generator Based-Variable Speed Wind Tur...
Control Scheme for an IPM Synchronous Generator Based-Variable Speed Wind Tur...
IJMTST Journal
 
OM_MAO_2012_Jun
OM_MAO_2012_JunOM_MAO_2012_Jun
OM_MAO_2012_Jun
MDO_Lab
 
Caes gen presentation
Caes gen presentationCaes gen presentation
Caes gen presentationLukeBatten
 
Advanced Rotating Machines - Mike Werst
Advanced Rotating Machines - Mike WerstAdvanced Rotating Machines - Mike Werst
Advanced Rotating Machines - Mike Werstcahouser
 
Caes projects worldwide
Caes projects worldwideCaes projects worldwide
Caes projects worldwideLukeBatten
 
P1302029097
P1302029097P1302029097
P1302029097
IOSR Journals
 
Q13020298106
Q13020298106Q13020298106
Q13020298106
IOSR Journals
 
IRJET- Rankine Cycle Coupled with Heliostat Solar Receiver; A Review
IRJET- Rankine Cycle Coupled with Heliostat Solar Receiver; A ReviewIRJET- Rankine Cycle Coupled with Heliostat Solar Receiver; A Review
IRJET- Rankine Cycle Coupled with Heliostat Solar Receiver; A Review
IRJET Journal
 
A computer Model of Fuel Consumption Estimation for Different Agricultural Fa...
A computer Model of Fuel Consumption Estimation for Different Agricultural Fa...A computer Model of Fuel Consumption Estimation for Different Agricultural Fa...
A computer Model of Fuel Consumption Estimation for Different Agricultural Fa...
Agriculture Journal IJOEAR
 
(CCGT - Final) Preliminary FS
(CCGT - Final) Preliminary FS(CCGT - Final) Preliminary FS
(CCGT - Final) Preliminary FSAiman Ali
 
Simulating combined cycle gas turbine power plants in aspen hysys
Simulating combined cycle gas turbine power plants in aspen hysysSimulating combined cycle gas turbine power plants in aspen hysys
Simulating combined cycle gas turbine power plants in aspen hysys
YilberMndez
 
A stand-alone, solar powered commercial bank with EV for public transport
A stand-alone, solar powered commercial bank with EV for public transportA stand-alone, solar powered commercial bank with EV for public transport
A stand-alone, solar powered commercial bank with EV for public transport
alatop007
 
JESTEC - Malek Fuad
JESTEC - Malek FuadJESTEC - Malek Fuad
JESTEC - Malek FuadMalek Amin
 
Economics of power plant
Economics of power plantEconomics of power plant
Economics of power plant
Dr. Rohit Singh Lather, Ph.D.
 

What's hot (20)

WFO_MAO_2012_Souma
WFO_MAO_2012_SoumaWFO_MAO_2012_Souma
WFO_MAO_2012_Souma
 
Lcoe offshore
Lcoe offshoreLcoe offshore
Lcoe offshore
 
Impact of Different Wake Models on the Estimation of Wind Farm Power Generation
Impact of Different Wake Models on the Estimation of Wind Farm Power GenerationImpact of Different Wake Models on the Estimation of Wind Farm Power Generation
Impact of Different Wake Models on the Estimation of Wind Farm Power Generation
 
Control Scheme for an IPM Synchronous Generator Based-Variable Speed Wind Tur...
Control Scheme for an IPM Synchronous Generator Based-Variable Speed Wind Tur...Control Scheme for an IPM Synchronous Generator Based-Variable Speed Wind Tur...
Control Scheme for an IPM Synchronous Generator Based-Variable Speed Wind Tur...
 
OM_MAO_2012_Jun
OM_MAO_2012_JunOM_MAO_2012_Jun
OM_MAO_2012_Jun
 
20320130406013
2032013040601320320130406013
20320130406013
 
Caes gen presentation
Caes gen presentationCaes gen presentation
Caes gen presentation
 
Advanced Rotating Machines - Mike Werst
Advanced Rotating Machines - Mike WerstAdvanced Rotating Machines - Mike Werst
Advanced Rotating Machines - Mike Werst
 
Caes projects worldwide
Caes projects worldwideCaes projects worldwide
Caes projects worldwide
 
P1302029097
P1302029097P1302029097
P1302029097
 
Q13020298106
Q13020298106Q13020298106
Q13020298106
 
IRJET- Rankine Cycle Coupled with Heliostat Solar Receiver; A Review
IRJET- Rankine Cycle Coupled with Heliostat Solar Receiver; A ReviewIRJET- Rankine Cycle Coupled with Heliostat Solar Receiver; A Review
IRJET- Rankine Cycle Coupled with Heliostat Solar Receiver; A Review
 
A computer Model of Fuel Consumption Estimation for Different Agricultural Fa...
A computer Model of Fuel Consumption Estimation for Different Agricultural Fa...A computer Model of Fuel Consumption Estimation for Different Agricultural Fa...
A computer Model of Fuel Consumption Estimation for Different Agricultural Fa...
 
(CCGT - Final) Preliminary FS
(CCGT - Final) Preliminary FS(CCGT - Final) Preliminary FS
(CCGT - Final) Preliminary FS
 
Simulating combined cycle gas turbine power plants in aspen hysys
Simulating combined cycle gas turbine power plants in aspen hysysSimulating combined cycle gas turbine power plants in aspen hysys
Simulating combined cycle gas turbine power plants in aspen hysys
 
A stand-alone, solar powered commercial bank with EV for public transport
A stand-alone, solar powered commercial bank with EV for public transportA stand-alone, solar powered commercial bank with EV for public transport
A stand-alone, solar powered commercial bank with EV for public transport
 
Brochure rwe ag
Brochure rwe agBrochure rwe ag
Brochure rwe ag
 
JESTEC - Malek Fuad
JESTEC - Malek FuadJESTEC - Malek Fuad
JESTEC - Malek Fuad
 
Poster
PosterPoster
Poster
 
Economics of power plant
Economics of power plantEconomics of power plant
Economics of power plant
 

Similar to Multi-Objective Wind Farm Design: Exploring the Trade-off between Capacity Factor and Land Use

WCSMO-Wind-2013-Tong
WCSMO-Wind-2013-TongWCSMO-Wind-2013-Tong
WCSMO-Wind-2013-Tong
OptiModel
 
WFO_MAO_2010_Souma
WFO_MAO_2010_SoumaWFO_MAO_2010_Souma
WFO_MAO_2010_Souma
MDO_Lab
 
AIAA-SDM-WFLO-2012
AIAA-SDM-WFLO-2012AIAA-SDM-WFLO-2012
AIAA-SDM-WFLO-2012
OptiModel
 
WFO_ES_2011_Souma
WFO_ES_2011_SoumaWFO_ES_2011_Souma
WFO_ES_2011_Souma
MDO_Lab
 
ASME-IDETC-Sensitivity-2013
ASME-IDETC-Sensitivity-2013ASME-IDETC-Sensitivity-2013
ASME-IDETC-Sensitivity-2013OptiModel
 
WFSA_IDETC_2013_Weiyang
WFSA_IDETC_2013_WeiyangWFSA_IDETC_2013_Weiyang
WFSA_IDETC_2013_Weiyang
MDO_Lab
 
SA_SciTech_2014_Weiyang
SA_SciTech_2014_WeiyangSA_SciTech_2014_Weiyang
SA_SciTech_2014_Weiyang
MDO_Lab
 
AIAA-MAO-WFLO-2012
AIAA-MAO-WFLO-2012AIAA-MAO-WFLO-2012
AIAA-MAO-WFLO-2012
OptiModel
 
WFO_IDETC_2011_Souma
WFO_IDETC_2011_SoumaWFO_IDETC_2011_Souma
WFO_IDETC_2011_Souma
MDO_Lab
 
WFO_ES2011_Souma
WFO_ES2011_SoumaWFO_ES2011_Souma
WFO_ES2011_Souma
Souma Chowdhury
 
WM_MAO_2012_Weiyang
WM_MAO_2012_WeiyangWM_MAO_2012_Weiyang
WM_MAO_2012_Weiyang
MDO_Lab
 
WCSMO-WFLO-2015-mehmani
WCSMO-WFLO-2015-mehmaniWCSMO-WFLO-2015-mehmani
WCSMO-WFLO-2015-mehmani
OptiModel
 
Sensitivity of Array-like and Optimized Wind Farm Output to Key Factors and C...
Sensitivity of Array-like and Optimized Wind Farm Output to Key Factors and C...Sensitivity of Array-like and Optimized Wind Farm Output to Key Factors and C...
Sensitivity of Array-like and Optimized Wind Farm Output to Key Factors and C...
Weiyang Tong
 
VIDMAP_Aviation_2014_Souma
VIDMAP_Aviation_2014_SoumaVIDMAP_Aviation_2014_Souma
VIDMAP_Aviation_2014_Souma
MDO_Lab
 
Wind farm re-powering, life extension and decommissioning
Wind farm re-powering, life extension and decommissioningWind farm re-powering, life extension and decommissioning
Wind farm re-powering, life extension and decommissioning
Advisian
 
MAE 586 Report of Wind Tunnel VAWT Simulations
MAE 586 Report of Wind Tunnel VAWT SimulationsMAE 586 Report of Wind Tunnel VAWT Simulations
MAE 586 Report of Wind Tunnel VAWT SimulationsObaida Mohammad
 
DG SYSTEM SELECTION IN URBAN AREA
DG SYSTEM SELECTION IN URBAN AREADG SYSTEM SELECTION IN URBAN AREA
DG SYSTEM SELECTION IN URBAN AREA
Haryo Agung Wibowo
 
PSSE_2nd_generation_Wind_Models_final_Jay.ppsx
PSSE_2nd_generation_Wind_Models_final_Jay.ppsxPSSE_2nd_generation_Wind_Models_final_Jay.ppsx
PSSE_2nd_generation_Wind_Models_final_Jay.ppsx
fellahriyadh
 
Integration of a Wind Turbine Based Doubly Fed Induction Generator Using STAT...
Integration of a Wind Turbine Based Doubly Fed Induction Generator Using STAT...Integration of a Wind Turbine Based Doubly Fed Induction Generator Using STAT...
Integration of a Wind Turbine Based Doubly Fed Induction Generator Using STAT...
IJERA Editor
 
spv wind and cell calculation analysis.pptx
spv wind and cell calculation analysis.pptxspv wind and cell calculation analysis.pptx
spv wind and cell calculation analysis.pptx
ssuser5120b3
 

Similar to Multi-Objective Wind Farm Design: Exploring the Trade-off between Capacity Factor and Land Use (20)

WCSMO-Wind-2013-Tong
WCSMO-Wind-2013-TongWCSMO-Wind-2013-Tong
WCSMO-Wind-2013-Tong
 
WFO_MAO_2010_Souma
WFO_MAO_2010_SoumaWFO_MAO_2010_Souma
WFO_MAO_2010_Souma
 
AIAA-SDM-WFLO-2012
AIAA-SDM-WFLO-2012AIAA-SDM-WFLO-2012
AIAA-SDM-WFLO-2012
 
WFO_ES_2011_Souma
WFO_ES_2011_SoumaWFO_ES_2011_Souma
WFO_ES_2011_Souma
 
ASME-IDETC-Sensitivity-2013
ASME-IDETC-Sensitivity-2013ASME-IDETC-Sensitivity-2013
ASME-IDETC-Sensitivity-2013
 
WFSA_IDETC_2013_Weiyang
WFSA_IDETC_2013_WeiyangWFSA_IDETC_2013_Weiyang
WFSA_IDETC_2013_Weiyang
 
SA_SciTech_2014_Weiyang
SA_SciTech_2014_WeiyangSA_SciTech_2014_Weiyang
SA_SciTech_2014_Weiyang
 
AIAA-MAO-WFLO-2012
AIAA-MAO-WFLO-2012AIAA-MAO-WFLO-2012
AIAA-MAO-WFLO-2012
 
WFO_IDETC_2011_Souma
WFO_IDETC_2011_SoumaWFO_IDETC_2011_Souma
WFO_IDETC_2011_Souma
 
WFO_ES2011_Souma
WFO_ES2011_SoumaWFO_ES2011_Souma
WFO_ES2011_Souma
 
WM_MAO_2012_Weiyang
WM_MAO_2012_WeiyangWM_MAO_2012_Weiyang
WM_MAO_2012_Weiyang
 
WCSMO-WFLO-2015-mehmani
WCSMO-WFLO-2015-mehmaniWCSMO-WFLO-2015-mehmani
WCSMO-WFLO-2015-mehmani
 
Sensitivity of Array-like and Optimized Wind Farm Output to Key Factors and C...
Sensitivity of Array-like and Optimized Wind Farm Output to Key Factors and C...Sensitivity of Array-like and Optimized Wind Farm Output to Key Factors and C...
Sensitivity of Array-like and Optimized Wind Farm Output to Key Factors and C...
 
VIDMAP_Aviation_2014_Souma
VIDMAP_Aviation_2014_SoumaVIDMAP_Aviation_2014_Souma
VIDMAP_Aviation_2014_Souma
 
Wind farm re-powering, life extension and decommissioning
Wind farm re-powering, life extension and decommissioningWind farm re-powering, life extension and decommissioning
Wind farm re-powering, life extension and decommissioning
 
MAE 586 Report of Wind Tunnel VAWT Simulations
MAE 586 Report of Wind Tunnel VAWT SimulationsMAE 586 Report of Wind Tunnel VAWT Simulations
MAE 586 Report of Wind Tunnel VAWT Simulations
 
DG SYSTEM SELECTION IN URBAN AREA
DG SYSTEM SELECTION IN URBAN AREADG SYSTEM SELECTION IN URBAN AREA
DG SYSTEM SELECTION IN URBAN AREA
 
PSSE_2nd_generation_Wind_Models_final_Jay.ppsx
PSSE_2nd_generation_Wind_Models_final_Jay.ppsxPSSE_2nd_generation_Wind_Models_final_Jay.ppsx
PSSE_2nd_generation_Wind_Models_final_Jay.ppsx
 
Integration of a Wind Turbine Based Doubly Fed Induction Generator Using STAT...
Integration of a Wind Turbine Based Doubly Fed Induction Generator Using STAT...Integration of a Wind Turbine Based Doubly Fed Induction Generator Using STAT...
Integration of a Wind Turbine Based Doubly Fed Induction Generator Using STAT...
 
spv wind and cell calculation analysis.pptx
spv wind and cell calculation analysis.pptxspv wind and cell calculation analysis.pptx
spv wind and cell calculation analysis.pptx
 

Recently uploaded

Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdfHybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
fxintegritypublishin
 
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdfAKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
SamSarthak3
 
Automobile Management System Project Report.pdf
Automobile Management System Project Report.pdfAutomobile Management System Project Report.pdf
Automobile Management System Project Report.pdf
Kamal Acharya
 
ethical hacking in wireless-hacking1.ppt
ethical hacking in wireless-hacking1.pptethical hacking in wireless-hacking1.ppt
ethical hacking in wireless-hacking1.ppt
Jayaprasanna4
 
Forklift Classes Overview by Intella Parts
Forklift Classes Overview by Intella PartsForklift Classes Overview by Intella Parts
Forklift Classes Overview by Intella Parts
Intella Parts
 
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&BDesign and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Sreedhar Chowdam
 
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
AJAYKUMARPUND1
 
Event Management System Vb Net Project Report.pdf
Event Management System Vb Net  Project Report.pdfEvent Management System Vb Net  Project Report.pdf
Event Management System Vb Net Project Report.pdf
Kamal Acharya
 
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
obonagu
 
J.Yang, ICLR 2024, MLILAB, KAIST AI.pdf
J.Yang,  ICLR 2024, MLILAB, KAIST AI.pdfJ.Yang,  ICLR 2024, MLILAB, KAIST AI.pdf
J.Yang, ICLR 2024, MLILAB, KAIST AI.pdf
MLILAB
 
Democratizing Fuzzing at Scale by Abhishek Arya
Democratizing Fuzzing at Scale by Abhishek AryaDemocratizing Fuzzing at Scale by Abhishek Arya
Democratizing Fuzzing at Scale by Abhishek Arya
abh.arya
 
Water Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdfWater Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation & Control
 
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptxCFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
R&R Consult
 
LIGA(E)11111111111111111111111111111111111111111.ppt
LIGA(E)11111111111111111111111111111111111111111.pptLIGA(E)11111111111111111111111111111111111111111.ppt
LIGA(E)11111111111111111111111111111111111111111.ppt
ssuser9bd3ba
 
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
Amil Baba Dawood bangali
 
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
MdTanvirMahtab2
 
HYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generationHYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generation
Robbie Edward Sayers
 
Architectural Portfolio Sean Lockwood
Architectural Portfolio Sean LockwoodArchitectural Portfolio Sean Lockwood
Architectural Portfolio Sean Lockwood
seandesed
 
COLLEGE BUS MANAGEMENT SYSTEM PROJECT REPORT.pdf
COLLEGE BUS MANAGEMENT SYSTEM PROJECT REPORT.pdfCOLLEGE BUS MANAGEMENT SYSTEM PROJECT REPORT.pdf
COLLEGE BUS MANAGEMENT SYSTEM PROJECT REPORT.pdf
Kamal Acharya
 
Railway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdfRailway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdf
TeeVichai
 

Recently uploaded (20)

Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdfHybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
 
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdfAKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
 
Automobile Management System Project Report.pdf
Automobile Management System Project Report.pdfAutomobile Management System Project Report.pdf
Automobile Management System Project Report.pdf
 
ethical hacking in wireless-hacking1.ppt
ethical hacking in wireless-hacking1.pptethical hacking in wireless-hacking1.ppt
ethical hacking in wireless-hacking1.ppt
 
Forklift Classes Overview by Intella Parts
Forklift Classes Overview by Intella PartsForklift Classes Overview by Intella Parts
Forklift Classes Overview by Intella Parts
 
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&BDesign and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
 
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
 
Event Management System Vb Net Project Report.pdf
Event Management System Vb Net  Project Report.pdfEvent Management System Vb Net  Project Report.pdf
Event Management System Vb Net Project Report.pdf
 
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
 
J.Yang, ICLR 2024, MLILAB, KAIST AI.pdf
J.Yang,  ICLR 2024, MLILAB, KAIST AI.pdfJ.Yang,  ICLR 2024, MLILAB, KAIST AI.pdf
J.Yang, ICLR 2024, MLILAB, KAIST AI.pdf
 
Democratizing Fuzzing at Scale by Abhishek Arya
Democratizing Fuzzing at Scale by Abhishek AryaDemocratizing Fuzzing at Scale by Abhishek Arya
Democratizing Fuzzing at Scale by Abhishek Arya
 
Water Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdfWater Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdf
 
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptxCFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
 
LIGA(E)11111111111111111111111111111111111111111.ppt
LIGA(E)11111111111111111111111111111111111111111.pptLIGA(E)11111111111111111111111111111111111111111.ppt
LIGA(E)11111111111111111111111111111111111111111.ppt
 
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
 
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
 
HYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generationHYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generation
 
Architectural Portfolio Sean Lockwood
Architectural Portfolio Sean LockwoodArchitectural Portfolio Sean Lockwood
Architectural Portfolio Sean Lockwood
 
COLLEGE BUS MANAGEMENT SYSTEM PROJECT REPORT.pdf
COLLEGE BUS MANAGEMENT SYSTEM PROJECT REPORT.pdfCOLLEGE BUS MANAGEMENT SYSTEM PROJECT REPORT.pdf
COLLEGE BUS MANAGEMENT SYSTEM PROJECT REPORT.pdf
 
Railway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdfRailway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdf
 

Multi-Objective Wind Farm Design: Exploring the Trade-off between Capacity Factor and Land Use

  • 1. Multi-objective Wind Farm Design Exploring the Trade-off between Capacity Factor and Land Use Weiyang Tong, Souma Chowdhury, Ali Mehmani, and Achille Messac Syracuse University, Department of Mechanical and Aerospace Engineering 10th World Congress on Structural and Multidisciplinary Optimization May 19-24, 2013, Orlando, Florida
  • 2. Wind Farm Development 2  Wind farm development is an extremely complex process that is affected by several performance objectives (energy production and cost, etc.)  Most of these factors are strongly coupled in the influence on the performance objectives Factors affecting wind farm performance Natural factors (uncontrollable) Wind shear Wind speed & direction Mean speed Intermittency Ambient turbulence … Design factors (controllable) Land configuration Land area Farm layout Turbine selection Grid connection Energy storage … Early Stage (up to 3 mon. ~ 3 yr.) • Wind resource assessment • Site selection • Preliminary feasibility analysis Mid Stage (2 ~ 5 yr.) • Economics analysis • Transmission capacity analysis • Regulatory framework • Environmental studies Late Stage (up to 25 yr) • Financing • Construction • Operation & Maintenance
  • 3. Research Motivation 3  Owing to the lack of early stage conceptual design frameworks, wind farm planning is an undesirably time- consuming process.  Transparency and efficiency are compromised in conventional wind farm planning due to typical independent decision making of different factors (e.g., wind farm layouts are generally designed for prescribed land area and nameplate capacity)  Quantitative exploration of the balance between the key objectives is mostly missing in the state of the art (e.g., balance between energy production and land use)
  • 4. Research Objective 4 Develop a Bi-level Wind Farm Trade-off Visualization framework Explore the trade-off between the concerned design objectives: capacity factor – land use Visualize the trade-off by parametrically translating the Pareto
  • 5. Outline 5 • Design Objectives • Wind farm Energy Production (Capacity Factor) • Land Use (Land Area per MW Installed) • Bi-level Wind Farm Trade-off Visualization Framework • Lower-level: Trade-off exploration • Upper-level: Trade-off visualization • Numerical Experiment • Concluding Remarks
  • 6. Wind Farm Energy Production 6 • Wind farm Capacity Factor 𝐶𝐹 = 𝐸𝑛𝑒𝑟𝑔𝑦 𝑝𝑟𝑜𝑑𝑢𝑐𝑡𝑖𝑜𝑛 𝑜𝑣𝑒𝑟 𝑎 𝑡𝑖𝑚𝑒 𝑝𝑒𝑟𝑖𝑜𝑑 𝑃𝑜𝑡𝑒𝑛𝑡𝑖𝑎𝑙 𝑒𝑛𝑒𝑟𝑔𝑦 𝑜𝑢𝑡𝑝𝑢𝑡 • Power Generational model in Unrestricted Wind Farm Layout Optimization (UWFLO) framework • Quantify the power generation as a function of incoming wind conditions, farm layout, and turbine features Denmark's Horns Rev 1 wind farm The Wake Effect
  • 7. Land Area per MW Installed (LAMI) 7 • Based on the farm layout, the land use is determined by the Smallest Bounding Rectangle (SBR) enclosing all turbines • The actual land area is represented as the buffer zone created by making a 2D distance away from the SBR • Turbines are not placed on the boundary of a wind farm • Avoid “zero” area when minimizing the land area
  • 8. Wind Farm Layout Optimization 8 wind farm layout optimization flowchart Stop criterion Reach the best performance? Evaluate design objective functions Trade-off between design objectives Adjust the location of turbines Prescribed conditions Yes No -4000 -3000 -2000 -1000 0 1000 2000 3000 4000 -4000 -3000 -2000 -1000 0 1000 2000 3000 4000 optimal layout of 20 turbines optimal layout of 40 turbines How many turbines should we install?
  • 9. Bi-level Wind Farm Visualization Framework 9 wind farm layout optimization flowchart Stop criterion Reach the best performance? Evaluate design objective functions Trade-off between design objectives Adjust the location of turbines Sample design factors Wind distribution Initial boundary Yes No
  • 10. Bi-level Wind Farm Visualization Framework 10 Capital investment Nameplate capacity Turbine features
  • 11. Numerical Experiment • Two design objectives: • Maximize the wind farm capacity factor • Minimize the Land Area per MW Installed (LAMI) • Identical turbines are used (GE-1.5 xle) • Wind data from a site at North Dakota is used Upper-level: the trade-off between capacity factor and LAMI is parametrically represented by Nameplate Capacity Lower-level: multi-objective wind farm layout optimization is performed as a constrained single objective optimization using Mixed-Discrete Particle Swarm Optimization (MDPSO) algorithm* 11*: Chowdhury et al., 2013 Struct Multidisc Optim
  • 12. Lower-level: CF-LAMI Trade-off Exploration 12  A set of sample nameplate capacities are generated within the 20 MW – 100 MW range  A square initial region is pre-defined with a size less than 120 hectares per MW installed  The bi-objective optimization is formulated as Sample # Nameplate Capacity No. of turbines 1 20 13 2 30 20 3 60 40 4 90 60 5 100 67 max 𝐶𝐹, min 𝐴 subject to 𝑔 𝑉 ≤ 0 𝑉 𝑚𝑖𝑛 ≤ 𝑉 ≤ 𝑉𝑚𝑎𝑥 𝑉 = {𝑋1, 𝑋2, ⋯ , 𝑋 𝑁, 𝑌1, 𝑌2, ⋯ , 𝑌𝑁}
  • 13. Applying the Smallest Bounding Rectangle enclosing all turbines max 𝑓(𝑉) = 𝐸𝑓𝑎𝑟𝑚 365 × 24 𝑁𝐶 subject to 𝑔1 𝑉 ≤ 0 𝑔2 𝑉 ≤ 0 𝑉 𝑚𝑖𝑛 ≤ 𝑉 ≤ 𝑉𝑚𝑎𝑥 𝑉 = {𝑋1, 𝑋2, ⋯ , 𝑋 𝑁, 𝑌1, 𝑌2, ⋯ , 𝑌𝑁} Lower-level: CF-LAMI Trade-off Exploration  Solved by: Mixed-Discrete Particle Swarm Optimization 13 Estimated using the power generation model in UWFLO framework  N is determined by the sample nameplate capacity  𝑉𝑚𝑎𝑥 and 𝑉 𝑚𝑖𝑛 are set based on the initial boundary regulated by the allowable land area 𝐸𝑓𝑎𝑟𝑚 = (365 × 24) 𝑗=1 𝑁 𝑝 𝑃𝑓𝑎𝑟𝑚 𝑝∆𝑈∆𝜃 Inter-Turbine Spacing Land Area Constraint
  • 14. Lower-level: CF-LAMI Trade-off Exploration 14 -4000 -3000 -2000 -1000 0 1000 2000 3000 4000 -4000 -3000 -2000 -1000 0 1000 2000 3000 4000 optimal layout with land area of 180 ha optimal layout with land area of 900 ha optimal layout with land area of 3000 ha Optimal layouts of 20 turbines with different land area constraints
  • 15. Upper-level: CF-LAMI Trade-off Visualization 15 𝐶𝐹 = 𝑎𝐴 𝑏 + 𝑐 Pareto solutions of 13 turbines Pareto solutions of 20 turbines Pareto solutions of 40 turbines Pareto solutions of 60 turbines Pareto solutions of 67 turbines Fitted curve for case of 13 turbines Fitted curve for case of 20 turbines Fitted curve for case of 40 turbines Fitted curve for case of 60 turbines Fitted curve for case of 67 turbines 22.4ha/MW 22.4ha/MW US Average Land Use: 34ha/MW
  • 16. Concluding Remarks • A Bi-level Wind Farm Trade-off Visualization framework was proposed for conceptual design of wind farms. • The CF-LAMI trade-off was parametrically represented as a function of nameplate capacity. • This proposed framework can streamline the wind farm development process, especially for large-scale wind farm projects, and help wind farm developers to make efficient and effective decisions. • Future work • Use both turbine features (turbine rated power) and nameplate capacity to parameterize the trade-off curve • Explore the trade-off, such as Capacity Factor vs. Net Impact on Surroundings 16
  • 17. Acknowledgement  I would like to acknowledge my research adviser Prof. Achille Messac, and my co-adviser Prof. Souma Chowdhury for their immense help and support in this research.  I would also like to thank my friend and colleague Ali Mehmani for his valuable contributions to this paper.  Support from the NSF Awards is also acknowledged. 17
  • 19. CF Response Surface Obtained  Even if turbines are allowed the same land area per MW installed, a greater number of turbines (higher nameplate capacity) would lead to greater wake losses, leading to lower energy production.  A contour plot of the function can provide the “LAMI vs. nameplate capacity” cutoff curve that corresponds to the threshold CF. LandAreaperMWinstalled(m2/MW) Nameplate Capacity (MW) 19
  • 20. 20 Single Wake Test: Comparing Wake Growth  Frandsen model and Larsen model predict greater wake diameters  Jensen model has a linear expansion  The difference between wake diameters predicted by each model can be as large as 3D, and it can be larger as the downstream distance increases 3D
  • 21. 21 Single Wake Test: Comparing Wake Speed  Frandsen model predicts the highest wake speed  Ishihara model predicts a relatively low wake speed; however, as the downstream distance increases, the wake recovers fast owing to the consideration of turbine induced turbulence in this model
  • 22. wind direction Numerical Experiments 22  An array-like wind farm with 9 GE 2.5 MW – 100m turbines is considered.  A fixed aspect ratio is selected; the streamwise spacing is ranged from 5D to 20D, while the lateral spacing is no less than 2D.  The farm capacity factor is given by Prj: Rated capacity, Pfarm: Farm output
  • 23. 23 Layout-based Power Generation Model  In this power generation model, the induction factor is treated as a function of the incoming wind speed and turbine features: U: incoming wind speed; P: power generated, given by the power curve kg, kb: mechanical and electrical efficiencies, Dj: Rotor Diameter, 𝜌: Air density  A generalized power curve is used to represent the approximate power response of a particular turbine 𝑈𝑖𝑛, 𝑈 𝑜𝑢𝑡, and 𝑈𝑟: cut-in speed, cut-out speed, and rated speed 𝑃𝑟: Rated capacity, 𝑃𝑛: Polynomial fit for the generalized power curve* *: Chowdhury et al , 2011
  • 24. 24 Layout-based Power Generation Model  Turbine-j is in the influence of the wake of Turbine-i, if and only if Considers turbines with differing rotor-diameters and hub-heights  The Katic model* is used to account for wake merging and partial wake overlap 𝑢𝑗: Effective velocity deficit 𝐴 𝑘𝑗: Overlapping area between Turbine-j and Turbine-k Partial wake-rotor overlap *: Katic et al , 1987
  • 25. Mixed-Discrete Particle Swarm Optimization (PSO)  This algorithm has the ability to deal with both discrete and continuous design variables, and  The mixed-discrete PSO presents an explicit diversity preservation capability to prevent premature stagnation of particles.  PSO can appropriately address the non-linearity and the multi- modality of the wind farm model. 25
  • 26. Lower-level: multi-objective wind farm layout optimization 26  A set of sample nameplate capacity factors is generated within the 20 MW – 100 MW range  A square initial region is pre-defined, f which size is less than 110 hectares per MW installed  The bi-objective optimization was solved as a Constrained single objective optimization Sample # Nameplate Capacity No. of turbines 1 20 13 2 30 20 3 60 40 4 90 60 5 100 67 max 𝑓(𝑉) = 𝐸𝑓𝑎𝑟𝑚 365 × 24 𝑁𝐶 subject to 𝑔1 𝑉 ≤ 0 𝑔2 𝑉 ≤ 0 𝑉 𝑚𝑖𝑛 ≤ 𝑉 ≤ 𝑉𝑚𝑎𝑥 𝑉 = {𝑋1, 𝑋2, ⋯ , 𝑋 𝑁, 𝑌1, 𝑌2, ⋯ , 𝑌𝑁}
  • 27. Mid-level: Quantification of Trade-offs between Design Objectives 27 • The wind distribution is unique • A group of Pareto curves can be obtained from the multi-objective wind farm layout optimization at the bottom-level • Based on observation, use an appropriate form of function to fit all the Pareto curves, for example, a form of power function with 3 coefficients • Once the global design factors are specified, a trade-off curve between two objectives can be generated 𝑜𝑏𝑗2 𝑛 = 𝑎(𝑝1, 𝑝2, ⋯ , 𝑝 𝐾)𝑜𝑏𝑗1 𝑛 𝑏(𝑝1,𝑝2,⋯,𝑝 𝑁) + 𝑐(𝑝1, 𝑝2, ⋯ , 𝑝 𝐾) where 𝑛 = 1,2, ⋯ , 𝑁 representing 𝑁 sets of samples of global design factors; and 𝐾 is the total number of global design factors accounted for
  • 28. 28