Menaxhim i projekteve java-8
- 20. START 0 2 A 2 4 6 2 7 C 5 6 11 0 5 B 5 0 5 5 11 D 6 5 11 11 16 F 5 15 20 11 20 E 9 11 20 20 22 G 2 20 22 22 28 I 6 22 28 11 15 H 4 24 28 28 29 J 28 29 29 31 K 2 29 31 END RRUGA KOHËZGJATJA A-C-E-G-I-J-K A-C-F-G-I-J-K B-D-E-G-I-J-K B-D-F-G-I-J-K B-D-H-J-K 27 javë 23 javë 31 javë Rrugë Kritike 27 javë 18 javë