SlideShare a Scribd company logo
1 of 21
Download to read offline
OILANDGASDOCS.COM
MECHANICAL COMPLETION &
COMMISSIONING
SCOPE
This PowerPoint defines the principles and structure of
Mechanical Completion & Commissioning.
SYSTEMS
An Operational System or a Non Operational System.
Operational Systems are Dynamic Process, Utility or
Facility Systems such as Seawater, Diesel, HVAC,
Telecom, Main Power & Control system.
Non-Operational Systems are Surface Protection,
Insulation, Civil, Structural Steel, Markings & Signs,
Cable & Tubing trays.
www.oilandgasdocs.com
MECHANICAL COMPLETION & COMMISSIONING
MECHANICAL COMPLETION STATUS INDEX (MCSI)
This is a listing of all items/tags with associated check records status for each MC (or commissioning) Package. The MCSI should be produced
based on the Project Completion system.
SUBSYSTEM
A system broken down into functional subsystems.
COMMISSIONING PACKAGE
A practical scope of work unit within a system or subsystem for commissioning, constituting a functional unit which can be tested by
commissioning to confirm its suitability for operation.
MC PACKAGE
A practical unit of the scope of work for one discipline within a commissioning package.
COMMISSIONING (C)
Is the functional verification of equipment and facilities that are grouped together in systems.
MECHANICAL COMPLETION (MC)
The checking and testing of equipment and construction to confirm that the installation is in accordance with drawings and specifications and
ready for commissioning in a safe manner and in compliance with project requirements.
STATUS "PA"
This means that this check item is not completed, and that remaining work is category 'A', i.e., must be completed prior to commissioning.
1
MECHANICAL COMPLETION & COMMISSIONING
STATUS "PB“
This means that this check item is not completed and that remaining work is category 'B’.
PUNCH LIST REGISTER (PLR)
A punch list register is a listing of all punch list items, prepared at a time when installation, functions or activities should have been completed.
CARRY OVER WORK REGISTER (COWR)
A register where incomplete items are documented sufficiently for work preparation and completion. The COWR is based on the Punch Lists
Register and describes punch listed work to be transferred to the next project executor.
MC DOSSIER
MC documentation compiled in MC package.
COMMISSIONING DOSSIER
Commissioning documentation compiled in Commissioning Dossier.
EXECUTOR
An organisation, supplier, contractor that performs a predefined scope of work.
2
MECHANICAL COMPLETION & COMMISSIONING
COMPLETION PRINCIPLES
1. OVERALL GOAL
The overall goal of Mechanical Completion & Commissioning is to verify that the system is designed and built to fulfil its purpose and specified
requirements.
Life cycle cost principles and safety should govern all decisions and actions.
Early establishment of commissioning packages is essential for an orderly and effective project completion. The commissioning plan shall have
maximum priority to enable reversed planning in all project phases. All fabrication and installation planning shall be system oriented.
Mechanical Completion, Commissioning, FAT, Preservation and suppliers assistance requirements shall be specified in the purchase orders.
Repeating of MC/C checks performed at suppliers and assembly sites should be avoided, wherever possible.
2. COMPLETION PHASES
2.1 DEFINITION PHASE
In this phase the following is carried out:
• Completion philosophy.
• Coding structure and system breakdown.
• Completion requirements to suppliers and contractors.
3
3. ENGINEERING PHASE
In this phase the following is carried out:
• Commissioning package & MC package definition.
• Define commissioning network.
• Produce commissioning procedures.
4. SUPPLIERS COMPLETION PHASE
Equipment suppliers shall execute MC, FAT, commissioning and preservation as specified in the purchase
order. The completion shall be documented as part of the completion system which leads up to handover to the
company/client.
5. CONSTRUCTION/ASSEMBLY PHASE
The Executor shall perform MC and commissioning and preservation as specified in the purchase
order/contract documents. The completion is documented as part of the completion system which leads up to
handover to the company.
4
MECHANICAL COMPLETION & COMMISSIONING
5
6. RESPONSIBILITIES
Responsibilities are defined in the contract. MC execution and registration/documentation shall be performed by
anyone who has a scope of work to be performed such as equipment suppliers, fabrication contractors,
installation contractor and hook-up contractors.
Commissioning registration and documentation shall be performed by anyone who has this responsibility
implemented in their scope of work.
7. DOCUMENTATION
Mechanical completion documentation shall be completed/executed per item/MC package.
Commissioning documentation shall be documented on a commissioning package level. All check/test records
shall end up in a status.
8. PROJECT COMPLETION SYSTEM (PCS)
An electronic based system for administration of Mechanical Completion, Commissioning and Punch List
Register should be used.
9. PLANNING
All Mechanical Completion activities shall be planned on fully integrated fabrication, Mechanical Completion and
Commissioning schedules on system prioritised basis in order to meet the optimal sequence of completion.
MECHANICAL COMPLETION & COMMISSIONING
6
10. MECHANICAL COMPLETION
This chapter forms the basis for the execution and documentation of mechanical activities. Mechanical completion takes
place through all phases of the project, starting at equipment supplier and continuing through fabrication up to
commissioning phase.
• Mechanical completion encompasses all disciplines.
• The detailed responsibilities are described in the contract.
• Executor of MC activities is responsible for establishing and compiling the MC dossiers and report status into the PCS.
10.1 DOCUMENTATION FOR A MC PACKAGE
The MC package shall consist of an MC Certificate, a MC Status Index and a Punch List Register printout as described
below.
A Mechanical Completion Certificate (MCC) is a form completed by the Executor after all MC,s are carried out. The
MCC is the cover sheet for each MC package. A MC package shall when signed be ready for start of commissioning.
The Check Records (CR) are the forms on which the Executors record the results of all checks, inspections and tests
carried out for each individual item.
A Punch List Register (PLR) shall be prepared by the Executor along with the MC activity. In each MC package a
printout from the PLR shall be included to document the incomplete work.
A MC Status Index (MCSI) lists the status of all CRs for the completed MC package shall be included in the MC
documentation dossier.
MECHANICAL COMPLETION & COMMISSIONING
7
10.2 HANDOVER AT MECHANICAL COMPLETION
Handover at Mechanical completion to commissioning shall be at commissioning package level, documented by the
Ready for Commissioning Certificate (RFCC).
10.3 CARRY OVER WORK REGISTER (COWR)
The Carry Over Work Register lists all punch items that the Project accepts as cannot be completed during present
phase. The COWR is used for the release of the work from the Executor and will as such be an input to the scheduling
and planning of outstanding work to be performed during later phases.
The COWR Item Number and cross reference to the Punch List Register/Check Records shall be given. COWR work
shall be marked up on drawings or sketches and be included in the records. COWR Material Status List (MSL) and
marked up drawings/instruction shall contain sufficient information for job setting in a later phase.
10.4 TYPICAL MECHANICAL COMPLETION ACTIVITIES
Mechanical completion activities includes checking of fabrication and installation work. The Executor shall complete
packages related to listed disciplines and as required by the MCSI. The Executor shall complete the check list items as
per the MCCR's.
MECHANICAL COMPLETION & COMMISSIONING
8
10.4.1 MECHANICAL ACTIVITIES
• Visual inspection for complete and correct installation.
• Flushing and cleanliness of equipment.
• Alignment.
• Bolt tensioning.
• Pressure test.
• Load test.
• Operation and mechanical handling.
• First fill consumables.
• Preservation.
• Completion of relevant verification certification. These are to be added on request by the reader.
MECHANICAL COMPLETION & COMMISSIONING
9
10.4.2 STRUCTURAL ACTIVITIES
• Visual inspection for complete and correct installation.
• QC documentation.
• NDE carried out.
• Welding.
• Load testing of lifting lugs and monorails.
10.4.3 SURFACE PROTECTION, INSULATION AND FIRE PROOFING ACTIVITIES
• Visual inspection for complete and correct application.
• Thickness checks carried out.
• Adhesion checks carried out.
• Preservation.
• Insulation.
• Painting.
• Fire proofing.
10.4.4 ARCHITECTURAL ACTIVITIES
• Visual inspection for complete and correct installation.
• Preservation & Doors.
MECHANICAL COMPLETION & COMMISSIONING
10
10.4.5 SURFACE PROTECTION, INSULATION, FIRE PROOFING & ARCHITECTURAL ACTIVITIES
• Visual inspection for complete and correct installation.
• Thickness checks completed.
• Adhesion checks completed.
• Preservation.
• Insulation.
• Painting.
• Fire proofing.
• Completion of relevant verification certification. These are to be added on request by the reader.
MECHANICAL COMPLETION & COMMISSIONING
11
10.4.6 ELECTRICAL ACTIVITIES
• Visual inspection for complete and correct installation.
• Insulation and continuity testing of cables.
• Ex enclosure checks.
• Insulation testing of generator, transformers and motors, panels, distribution board etc.
• Earthing checks.
• Static check of switches and control devices.
• Battery preparation.
• Lighting and socket outlet checks.
• Area classification checks.
• Function check of switch gear and controls.
• Heat tracing.
• Preservation.
• Completion of relevant verification certification. These are to be added on request by the reader.
MECHANICAL COMPLETION & COMMISSIONING
12
10.4.7 INSTRUMENT/TELECOMMUNICATION/FIRE & GAS ACTIVITIES
• Line walk, punch and as-build.
• Calibration and testing of instruments prior to installation.
• Visual inspection for complete and correct installation.
• Insulation and continuity testing of cables.
• Cleaning, flushing, pressure and leak testing of pneumatic and hydraulic tubing.
• Adjustment and verification of control, alarm and shutdown settings.
• Cold Loop testing.
• Installation of control system software
• Earthing checks.
• Function testing of control systems.
• Function testing of field instruments.
• Area classification checks.
• Preservation.
• Completion of relevant verification certification. These are to be added at the request by the reader.
MECHANICAL COMPLETION & COMMISSIONING
13
10.4.8 PIPING ACTIVITIES
• NDE carried out.
• Welding procedures.
• Removal of all items subject to damage during flushing, cleaning and pressure testing.
• Flushing of pipework.
• Chemical cleaning and testing of pipework.
• Drying of tested pipework.
• Preservation of tested pipework.
• Bolt torquing/Tensioning.
• Pipe supports completed.
• Thermal and protective insulation.
• Flow coding.
• Earthing.
• Correct piping penetrations (fire/explosive ratings).
• Line walk, punch & as-build.
• Reinstatement of all items after testing & Final inspection of pipework.
• Correct piping penetrations (fire/explosive ratings).
• Completion of relevant verification certification. These are to be added on request by the reader.
MECHANICAL COMPLETION & COMMISSIONING
14
10.4.9 HVAC ACTIVITIES
• Visual inspection for complete and correct installation.
• Cleaning of ductwork.
• Leak testing of ductwork.
• Alignment checks.
• Mechanical functions checks of equipment.
• Verification of settings.
• Correct penetrations (Fire/explosive ratings).
• Preservation.
• Flow.
• Punch and as-build.
10.4.10 SAFETY ACTIVITIES
• Visual inspection for complete and correct installation.
• Preservation.
• Area completion.
• Completion of relevant verification certification. These are to be added at the request by the reader.
MECHANICAL COMPLETION & COMMISSIONING
15
11. COMMISSIONING
This chapter forms the basis for preparation and execution of commissioning. Commissioning take place when
Mechanical completion is completed for a system or part of a system.
Commissioning can be divided into three main activities:
• Commissioning preparation.
• Commissioning execution.
• Commissioning documentation and handover to operation.
Establish a commissioning network and definition of commissioning packages early in a project in order to establish
fabrication/installation priorities and milestones.
Definition of commissioning of part systems is essential in order to achieve an early commissioning completion.
11.1 TYPICAL COMMISSIONING PREPARATION ACTIVITIES
The preparatory work shall consist of activities such as:
• Development of commissioning organisation & system breakdown (part system).
• Commissioning packages definition.
• Commissioning schedules.
• Commissioning budget including spare parts for commissioning.
MECHANICAL COMPLETION & COMMISSIONING
16
11.2 COMMISSIONING PROCEDURE CONTENTS
Commissioning shall be executed by guidance of a detailed procedure describing:
11.2.1 OBJECTIVE
Details the operating parameters to be achieved.
11.2.2 DESCRIPTION
Shall contain a brief description of the system/part systems to be commissioned, including marked up P&ID as a basis
for all functions to be tested.
11.2.3 LISTS OF TEMPORARY EQUIPMENT AND CONSUMABLES
Lists all consumables, temporary equipment tools and requirements for suppliers assistance.
11.2.4 HEALTH/ENVIRONMENT/SAFETY
A list of all toxic and polluting fluids and materials shall be made, describing their handling and disposal. A check list of
all required safety precautions including requirements for work permit shall be made. Prior to energization of electrical
equipment a livening up notice shall be issued in order to inform all involved parties of forthcoming energising.
11.2.5 PRESERVATION
Requirements for removal of existing preservatives/protection shall be made and subsequent new preservation of the
system if the system shall be out of operation for a period of time.
MECHANICAL COMPLETION & COMMISSIONING
17
12 EXAMPLES OF COMMISSIONING ACTIVITES
12.1 PIPING
• System Leak test.
• Sensitive leak test.
12.2 INSTRUMENT/TELECOMMUNICATION/FIRE & GAS
• Loop testing.
• Function testing of field instruments.
• Check of the installation, by line walking the installation verifying the correctness of key drawings.
• Function testing of control systems.
• Adjustment of control, alarm and shutdown settings.
• Verification of settings on equipment.
• Function test of equipment.
MECHANICAL COMPLETION & COMMISSIONING
16
12.3 FUNCTION TEST OF NEW FACILITIES
• Equipment test in accordance with vendor procedures.
• HMI to SCADA test.
• Signal I/O functionality.
• Local and remote indicator testing.
• Local and remote start stop function.
• Testing of emergency stops both local and remote.
• Opening/closure times on actuated valves.
• Start stop of rotational equipment, check rotation direction, check performance and product quality.
• Duty and standby function tests.
• Fill tanks/vessels and check instruments local and remote.
• Gas and UV detection tests.
• Illumination tests.
• HVAC testing (Functionality, flow, control and F&G).
• Firewater coverage testing.
MECHANICAL COMPLETION & COMMISSIONING
18
16
13 TYPICAL MECHANICAL COMPLETION DOCUMENTS
13.1 SCOPE
The scope shall detail the work to be done step by step including the commissioning preparation.
Irregularities and/or faults shall be logged.
Equipment suppliers start-up procedures shall be incorporated.
Performance parameters shall be included for comparison of results with actual result achieved during commissioning.
13.2 PLANNING
Detailed commissioning plans for system/part system shall be worked out and shall include manhours per discipline, including supplier assistance
man-hours.
13.3 HANDOVER
The handover shall contain a certificate and other documents agreed with operations.
13.4 HANDOVER DOCUMENTATION TO OPERATIONS
Handover of systems from Executor to Project/Operations shall be according to a formal procedure which as a minimum should consist of:
• Completion acceptance certificate (signed by both parties).
• Commissioning P&ID showing the extent of the completed system.
• Authority certificates (if any).
• Operational procedures and handbooks.
MECHANICAL COMPLETION & COMMISSIONING
19
6
IF YOU WOULD LIKE MORE INFORMATION
REGARDING MECHANICAL COMPLETION,
COMMISSIONING AND CERTIFICATION, VISIT:
oilandgasdocs.com
Or contact
tatjana@oilangasdocs.com
enquiries@oilandgasdocs.com
MECHANICAL COMPLETION & COMMISSIONING

More Related Content

What's hot

Commissioning & Interface With Engineering
Commissioning & Interface With EngineeringCommissioning & Interface With Engineering
Commissioning & Interface With Engineeringasim569
 
Oil & Gas Plant Construction, Project Execution Plan
Oil & Gas Plant Construction, Project Execution PlanOil & Gas Plant Construction, Project Execution Plan
Oil & Gas Plant Construction, Project Execution PlanDavid H Moloney
 
Presentation API 570 -510-653.pptx
Presentation API 570 -510-653.pptxPresentation API 570 -510-653.pptx
Presentation API 570 -510-653.pptxhesham ismail
 
7) hydro test 3
7) hydro test 37) hydro test 3
7) hydro test 3ALISAB123
 
Chris brooks storage tanks inspection, maintenance and failure
Chris brooks   storage tanks inspection, maintenance and failureChris brooks   storage tanks inspection, maintenance and failure
Chris brooks storage tanks inspection, maintenance and failureSreekumar K S
 
World Class Manufacturing:Plant Start Up and Commissioning Procedure
World  Class Manufacturing:Plant Start Up and Commissioning Procedure World  Class Manufacturing:Plant Start Up and Commissioning Procedure
World Class Manufacturing:Plant Start Up and Commissioning Procedure HIMADRI BANERJI
 
Method statement piping works
Method statement piping worksMethod statement piping works
Method statement piping worksSurya Kant
 
QC INSPECTOR E&I
QC INSPECTOR E&IQC INSPECTOR E&I
QC INSPECTOR E&INASIM NEZAM
 
Aramco inspection handbook
Aramco inspection handbookAramco inspection handbook
Aramco inspection handbookram111eg
 
Offshore qc welding inspection versi 1
Offshore qc welding inspection versi 1Offshore qc welding inspection versi 1
Offshore qc welding inspection versi 1Ramdani Diningrat
 
Hydrotest REPORT FOR 4'' 158m Line.
Hydrotest REPORT FOR 4'' 158m Line.Hydrotest REPORT FOR 4'' 158m Line.
Hydrotest REPORT FOR 4'' 158m Line.Emeka Ngwobia
 
Process Plant Start Up and Commissioning
Process Plant Start Up and CommissioningProcess Plant Start Up and Commissioning
Process Plant Start Up and CommissioningpetroEDGE
 
Process piping b31.3 detailed
Process piping b31.3 detailedProcess piping b31.3 detailed
Process piping b31.3 detailedAdeel Mazhar
 
Resume of jaison varkey, QA/QC inspector welding,coating offshore Oil & Gas
Resume of jaison varkey, QA/QC  inspector welding,coating offshore Oil & GasResume of jaison varkey, QA/QC  inspector welding,coating offshore Oil & Gas
Resume of jaison varkey, QA/QC inspector welding,coating offshore Oil & Gasjaison varkey
 
110921 commissioning of offshore installations
110921 commissioning of offshore installations110921 commissioning of offshore installations
110921 commissioning of offshore installationslaithu2908
 
Saudi aramco standards
Saudi aramco standardsSaudi aramco standards
Saudi aramco standardsJithu John
 

What's hot (20)

Asme b31,pressure piping code
Asme b31,pressure piping codeAsme b31,pressure piping code
Asme b31,pressure piping code
 
Commissioning & Interface With Engineering
Commissioning & Interface With EngineeringCommissioning & Interface With Engineering
Commissioning & Interface With Engineering
 
Jacket
JacketJacket
Jacket
 
Oil & Gas Plant Construction, Project Execution Plan
Oil & Gas Plant Construction, Project Execution PlanOil & Gas Plant Construction, Project Execution Plan
Oil & Gas Plant Construction, Project Execution Plan
 
Presentation API 570 -510-653.pptx
Presentation API 570 -510-653.pptxPresentation API 570 -510-653.pptx
Presentation API 570 -510-653.pptx
 
7) hydro test 3
7) hydro test 37) hydro test 3
7) hydro test 3
 
Chris brooks storage tanks inspection, maintenance and failure
Chris brooks   storage tanks inspection, maintenance and failureChris brooks   storage tanks inspection, maintenance and failure
Chris brooks storage tanks inspection, maintenance and failure
 
World Class Manufacturing:Plant Start Up and Commissioning Procedure
World  Class Manufacturing:Plant Start Up and Commissioning Procedure World  Class Manufacturing:Plant Start Up and Commissioning Procedure
World Class Manufacturing:Plant Start Up and Commissioning Procedure
 
presentation
presentationpresentation
presentation
 
Method statement piping works
Method statement piping worksMethod statement piping works
Method statement piping works
 
QC INSPECTOR E&I
QC INSPECTOR E&IQC INSPECTOR E&I
QC INSPECTOR E&I
 
Aramco inspection handbook
Aramco inspection handbookAramco inspection handbook
Aramco inspection handbook
 
Offshore qc welding inspection versi 1
Offshore qc welding inspection versi 1Offshore qc welding inspection versi 1
Offshore qc welding inspection versi 1
 
Hydrotest REPORT FOR 4'' 158m Line.
Hydrotest REPORT FOR 4'' 158m Line.Hydrotest REPORT FOR 4'' 158m Line.
Hydrotest REPORT FOR 4'' 158m Line.
 
Process Plant Start Up and Commissioning
Process Plant Start Up and CommissioningProcess Plant Start Up and Commissioning
Process Plant Start Up and Commissioning
 
Process piping b31.3 detailed
Process piping b31.3 detailedProcess piping b31.3 detailed
Process piping b31.3 detailed
 
Project Schedule - Level IV Schedule
Project Schedule - Level IV ScheduleProject Schedule - Level IV Schedule
Project Schedule - Level IV Schedule
 
Resume of jaison varkey, QA/QC inspector welding,coating offshore Oil & Gas
Resume of jaison varkey, QA/QC  inspector welding,coating offshore Oil & GasResume of jaison varkey, QA/QC  inspector welding,coating offshore Oil & Gas
Resume of jaison varkey, QA/QC inspector welding,coating offshore Oil & Gas
 
110921 commissioning of offshore installations
110921 commissioning of offshore installations110921 commissioning of offshore installations
110921 commissioning of offshore installations
 
Saudi aramco standards
Saudi aramco standardsSaudi aramco standards
Saudi aramco standards
 

Similar to Mechanical completion

Presentacion asme seccion viii division 2 2013
Presentacion asme seccion viii division 2 2013Presentacion asme seccion viii division 2 2013
Presentacion asme seccion viii division 2 2013leo040490
 
Pre commissioning Instrument Engineer
Pre commissioning Instrument EngineerPre commissioning Instrument Engineer
Pre commissioning Instrument EngineerKamran Saeed
 
commissioning guideline
commissioning guidelinecommissioning guideline
commissioning guidelineMahmoud Ezz
 
Episode 33 : Project Execution Part (4)
Episode 33 :  Project Execution Part (4)Episode 33 :  Project Execution Part (4)
Episode 33 : Project Execution Part (4)SAJJAD KHUDHUR ABBAS
 
APTRANSCO-Technical-reference-book-2011-vol-ii.pdf
APTRANSCO-Technical-reference-book-2011-vol-ii.pdfAPTRANSCO-Technical-reference-book-2011-vol-ii.pdf
APTRANSCO-Technical-reference-book-2011-vol-ii.pdfssuser1fc1f0
 
Updated Umang resume
Updated Umang resumeUpdated Umang resume
Updated Umang resumeUmang Tailor
 
instrument engineer shuaibah power plant cems turbine
instrument engineer shuaibah power plant cems turbineinstrument engineer shuaibah power plant cems turbine
instrument engineer shuaibah power plant cems turbineKsPuri
 
Project Quality Management PPT.pptx
Project Quality Management PPT.pptxProject Quality Management PPT.pptx
Project Quality Management PPT.pptxZiyad Zaidi
 
ICS ENGINEER CV WITH IMAGE (doc)
ICS ENGINEER CV WITH IMAGE (doc)ICS ENGINEER CV WITH IMAGE (doc)
ICS ENGINEER CV WITH IMAGE (doc)Vijayakumar Kumar
 
Egyps 2017 technical conference power point template
Egyps 2017 technical conference power point template Egyps 2017 technical conference power point template
Egyps 2017 technical conference power point template Dr. Mohamed A. El-Reedy
 
Integrating BIM and LEAN for Project Delivery - Construction of a Major Hospi...
Integrating BIM and LEAN for Project Delivery - Construction of a Major Hospi...Integrating BIM and LEAN for Project Delivery - Construction of a Major Hospi...
Integrating BIM and LEAN for Project Delivery - Construction of a Major Hospi...CCT International
 
Job Desciption Completions Engineer
Job Desciption Completions EngineerJob Desciption Completions Engineer
Job Desciption Completions EngineerDenis Utebaliev
 
UON-Project-Handover-Guideline-v1.2-010920.pdf
UON-Project-Handover-Guideline-v1.2-010920.pdfUON-Project-Handover-Guideline-v1.2-010920.pdf
UON-Project-Handover-Guideline-v1.2-010920.pdfHabtamuGaroma3
 
cable testing and intallation
cable testing and intallationcable testing and intallation
cable testing and intallationmanishgoswami66
 
VA Cx Presentation_SRE Training 2013 Final_v2
VA Cx Presentation_SRE Training 2013 Final_v2VA Cx Presentation_SRE Training 2013 Final_v2
VA Cx Presentation_SRE Training 2013 Final_v2Jerry Bauers
 
INTEGRATION OF CMMS, EDMS AND WMS
INTEGRATION OF CMMS, EDMS AND WMSINTEGRATION OF CMMS, EDMS AND WMS
INTEGRATION OF CMMS, EDMS AND WMSBehnam Rahimi
 

Similar to Mechanical completion (20)

Presentacion asme seccion viii division 2 2013
Presentacion asme seccion viii division 2 2013Presentacion asme seccion viii division 2 2013
Presentacion asme seccion viii division 2 2013
 
019113
019113019113
019113
 
Pre commissioning Instrument Engineer
Pre commissioning Instrument EngineerPre commissioning Instrument Engineer
Pre commissioning Instrument Engineer
 
commissioning guideline
commissioning guidelinecommissioning guideline
commissioning guideline
 
Episode 33 : Project Execution Part (4)
Episode 33 :  Project Execution Part (4)Episode 33 :  Project Execution Part (4)
Episode 33 : Project Execution Part (4)
 
APTRANSCO-Technical-reference-book-2011-vol-ii.pdf
APTRANSCO-Technical-reference-book-2011-vol-ii.pdfAPTRANSCO-Technical-reference-book-2011-vol-ii.pdf
APTRANSCO-Technical-reference-book-2011-vol-ii.pdf
 
Updated Umang resume
Updated Umang resumeUpdated Umang resume
Updated Umang resume
 
instrument engineer shuaibah power plant cems turbine
instrument engineer shuaibah power plant cems turbineinstrument engineer shuaibah power plant cems turbine
instrument engineer shuaibah power plant cems turbine
 
Project Quality Management PPT.pptx
Project Quality Management PPT.pptxProject Quality Management PPT.pptx
Project Quality Management PPT.pptx
 
CV
CVCV
CV
 
ICS ENGINEER CV WITH IMAGE (doc)
ICS ENGINEER CV WITH IMAGE (doc)ICS ENGINEER CV WITH IMAGE (doc)
ICS ENGINEER CV WITH IMAGE (doc)
 
Egyps 2017 technical conference power point template
Egyps 2017 technical conference power point template Egyps 2017 technical conference power point template
Egyps 2017 technical conference power point template
 
Validation master plan
Validation master planValidation master plan
Validation master plan
 
Integrating BIM and LEAN for Project Delivery - Construction of a Major Hospi...
Integrating BIM and LEAN for Project Delivery - Construction of a Major Hospi...Integrating BIM and LEAN for Project Delivery - Construction of a Major Hospi...
Integrating BIM and LEAN for Project Delivery - Construction of a Major Hospi...
 
Job Desciption Completions Engineer
Job Desciption Completions EngineerJob Desciption Completions Engineer
Job Desciption Completions Engineer
 
UON-Project-Handover-Guideline-v1.2-010920.pdf
UON-Project-Handover-Guideline-v1.2-010920.pdfUON-Project-Handover-Guideline-v1.2-010920.pdf
UON-Project-Handover-Guideline-v1.2-010920.pdf
 
cable testing and intallation
cable testing and intallationcable testing and intallation
cable testing and intallation
 
Pre commissioning
Pre commissioningPre commissioning
Pre commissioning
 
VA Cx Presentation_SRE Training 2013 Final_v2
VA Cx Presentation_SRE Training 2013 Final_v2VA Cx Presentation_SRE Training 2013 Final_v2
VA Cx Presentation_SRE Training 2013 Final_v2
 
INTEGRATION OF CMMS, EDMS AND WMS
INTEGRATION OF CMMS, EDMS AND WMSINTEGRATION OF CMMS, EDMS AND WMS
INTEGRATION OF CMMS, EDMS AND WMS
 

Recently uploaded

Call Girls Miyapur 7001305949 all area service COD available Any Time
Call Girls Miyapur 7001305949 all area service COD available Any TimeCall Girls Miyapur 7001305949 all area service COD available Any Time
Call Girls Miyapur 7001305949 all area service COD available Any Timedelhimodelshub1
 
India Consumer 2024 Redacted Sample Report
India Consumer 2024 Redacted Sample ReportIndia Consumer 2024 Redacted Sample Report
India Consumer 2024 Redacted Sample ReportMintel Group
 
Future Of Sample Report 2024 | Redacted Version
Future Of Sample Report 2024 | Redacted VersionFuture Of Sample Report 2024 | Redacted Version
Future Of Sample Report 2024 | Redacted VersionMintel Group
 
8447779800, Low rate Call girls in Saket Delhi NCR
8447779800, Low rate Call girls in Saket Delhi NCR8447779800, Low rate Call girls in Saket Delhi NCR
8447779800, Low rate Call girls in Saket Delhi NCRashishs7044
 
Youth Involvement in an Innovative Coconut Value Chain by Mwalimu Menza
Youth Involvement in an Innovative Coconut Value Chain by Mwalimu MenzaYouth Involvement in an Innovative Coconut Value Chain by Mwalimu Menza
Youth Involvement in an Innovative Coconut Value Chain by Mwalimu Menzaictsugar
 
Lowrate Call Girls In Sector 18 Noida ❤️8860477959 Escorts 100% Genuine Servi...
Lowrate Call Girls In Sector 18 Noida ❤️8860477959 Escorts 100% Genuine Servi...Lowrate Call Girls In Sector 18 Noida ❤️8860477959 Escorts 100% Genuine Servi...
Lowrate Call Girls In Sector 18 Noida ❤️8860477959 Escorts 100% Genuine Servi...lizamodels9
 
Call Girls In Connaught Place Delhi ❤️88604**77959_Russian 100% Genuine Escor...
Call Girls In Connaught Place Delhi ❤️88604**77959_Russian 100% Genuine Escor...Call Girls In Connaught Place Delhi ❤️88604**77959_Russian 100% Genuine Escor...
Call Girls In Connaught Place Delhi ❤️88604**77959_Russian 100% Genuine Escor...lizamodels9
 
Ten Organizational Design Models to align structure and operations to busines...
Ten Organizational Design Models to align structure and operations to busines...Ten Organizational Design Models to align structure and operations to busines...
Ten Organizational Design Models to align structure and operations to busines...Seta Wicaksana
 
Digital Transformation in the PLM domain - distrib.pdf
Digital Transformation in the PLM domain - distrib.pdfDigital Transformation in the PLM domain - distrib.pdf
Digital Transformation in the PLM domain - distrib.pdfJos Voskuil
 
Marketplace and Quality Assurance Presentation - Vincent Chirchir
Marketplace and Quality Assurance Presentation - Vincent ChirchirMarketplace and Quality Assurance Presentation - Vincent Chirchir
Marketplace and Quality Assurance Presentation - Vincent Chirchirictsugar
 
Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...
Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...
Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...lizamodels9
 
Lean: From Theory to Practice — One City’s (and Library’s) Lean Story… Abridged
Lean: From Theory to Practice — One City’s (and Library’s) Lean Story… AbridgedLean: From Theory to Practice — One City’s (and Library’s) Lean Story… Abridged
Lean: From Theory to Practice — One City’s (and Library’s) Lean Story… AbridgedKaiNexus
 
Islamabad Escorts | Call 03274100048 | Escort Service in Islamabad
Islamabad Escorts | Call 03274100048 | Escort Service in IslamabadIslamabad Escorts | Call 03274100048 | Escort Service in Islamabad
Islamabad Escorts | Call 03274100048 | Escort Service in IslamabadAyesha Khan
 
Contemporary Economic Issues Facing the Filipino Entrepreneur (1).pptx
Contemporary Economic Issues Facing the Filipino Entrepreneur (1).pptxContemporary Economic Issues Facing the Filipino Entrepreneur (1).pptx
Contemporary Economic Issues Facing the Filipino Entrepreneur (1).pptxMarkAnthonyAurellano
 
Marketing Management Business Plan_My Sweet Creations
Marketing Management Business Plan_My Sweet CreationsMarketing Management Business Plan_My Sweet Creations
Marketing Management Business Plan_My Sweet Creationsnakalysalcedo61
 
8447779800, Low rate Call girls in New Ashok Nagar Delhi NCR
8447779800, Low rate Call girls in New Ashok Nagar Delhi NCR8447779800, Low rate Call girls in New Ashok Nagar Delhi NCR
8447779800, Low rate Call girls in New Ashok Nagar Delhi NCRashishs7044
 
Organizational Structure Running A Successful Business
Organizational Structure Running A Successful BusinessOrganizational Structure Running A Successful Business
Organizational Structure Running A Successful BusinessSeta Wicaksana
 
Kenya Coconut Production Presentation by Dr. Lalith Perera
Kenya Coconut Production Presentation by Dr. Lalith PereraKenya Coconut Production Presentation by Dr. Lalith Perera
Kenya Coconut Production Presentation by Dr. Lalith Pereraictsugar
 
Global Scenario On Sustainable and Resilient Coconut Industry by Dr. Jelfina...
Global Scenario On Sustainable  and Resilient Coconut Industry by Dr. Jelfina...Global Scenario On Sustainable  and Resilient Coconut Industry by Dr. Jelfina...
Global Scenario On Sustainable and Resilient Coconut Industry by Dr. Jelfina...ictsugar
 
Annual General Meeting Presentation Slides
Annual General Meeting Presentation SlidesAnnual General Meeting Presentation Slides
Annual General Meeting Presentation SlidesKeppelCorporation
 

Recently uploaded (20)

Call Girls Miyapur 7001305949 all area service COD available Any Time
Call Girls Miyapur 7001305949 all area service COD available Any TimeCall Girls Miyapur 7001305949 all area service COD available Any Time
Call Girls Miyapur 7001305949 all area service COD available Any Time
 
India Consumer 2024 Redacted Sample Report
India Consumer 2024 Redacted Sample ReportIndia Consumer 2024 Redacted Sample Report
India Consumer 2024 Redacted Sample Report
 
Future Of Sample Report 2024 | Redacted Version
Future Of Sample Report 2024 | Redacted VersionFuture Of Sample Report 2024 | Redacted Version
Future Of Sample Report 2024 | Redacted Version
 
8447779800, Low rate Call girls in Saket Delhi NCR
8447779800, Low rate Call girls in Saket Delhi NCR8447779800, Low rate Call girls in Saket Delhi NCR
8447779800, Low rate Call girls in Saket Delhi NCR
 
Youth Involvement in an Innovative Coconut Value Chain by Mwalimu Menza
Youth Involvement in an Innovative Coconut Value Chain by Mwalimu MenzaYouth Involvement in an Innovative Coconut Value Chain by Mwalimu Menza
Youth Involvement in an Innovative Coconut Value Chain by Mwalimu Menza
 
Lowrate Call Girls In Sector 18 Noida ❤️8860477959 Escorts 100% Genuine Servi...
Lowrate Call Girls In Sector 18 Noida ❤️8860477959 Escorts 100% Genuine Servi...Lowrate Call Girls In Sector 18 Noida ❤️8860477959 Escorts 100% Genuine Servi...
Lowrate Call Girls In Sector 18 Noida ❤️8860477959 Escorts 100% Genuine Servi...
 
Call Girls In Connaught Place Delhi ❤️88604**77959_Russian 100% Genuine Escor...
Call Girls In Connaught Place Delhi ❤️88604**77959_Russian 100% Genuine Escor...Call Girls In Connaught Place Delhi ❤️88604**77959_Russian 100% Genuine Escor...
Call Girls In Connaught Place Delhi ❤️88604**77959_Russian 100% Genuine Escor...
 
Ten Organizational Design Models to align structure and operations to busines...
Ten Organizational Design Models to align structure and operations to busines...Ten Organizational Design Models to align structure and operations to busines...
Ten Organizational Design Models to align structure and operations to busines...
 
Digital Transformation in the PLM domain - distrib.pdf
Digital Transformation in the PLM domain - distrib.pdfDigital Transformation in the PLM domain - distrib.pdf
Digital Transformation in the PLM domain - distrib.pdf
 
Marketplace and Quality Assurance Presentation - Vincent Chirchir
Marketplace and Quality Assurance Presentation - Vincent ChirchirMarketplace and Quality Assurance Presentation - Vincent Chirchir
Marketplace and Quality Assurance Presentation - Vincent Chirchir
 
Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...
Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...
Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...
 
Lean: From Theory to Practice — One City’s (and Library’s) Lean Story… Abridged
Lean: From Theory to Practice — One City’s (and Library’s) Lean Story… AbridgedLean: From Theory to Practice — One City’s (and Library’s) Lean Story… Abridged
Lean: From Theory to Practice — One City’s (and Library’s) Lean Story… Abridged
 
Islamabad Escorts | Call 03274100048 | Escort Service in Islamabad
Islamabad Escorts | Call 03274100048 | Escort Service in IslamabadIslamabad Escorts | Call 03274100048 | Escort Service in Islamabad
Islamabad Escorts | Call 03274100048 | Escort Service in Islamabad
 
Contemporary Economic Issues Facing the Filipino Entrepreneur (1).pptx
Contemporary Economic Issues Facing the Filipino Entrepreneur (1).pptxContemporary Economic Issues Facing the Filipino Entrepreneur (1).pptx
Contemporary Economic Issues Facing the Filipino Entrepreneur (1).pptx
 
Marketing Management Business Plan_My Sweet Creations
Marketing Management Business Plan_My Sweet CreationsMarketing Management Business Plan_My Sweet Creations
Marketing Management Business Plan_My Sweet Creations
 
8447779800, Low rate Call girls in New Ashok Nagar Delhi NCR
8447779800, Low rate Call girls in New Ashok Nagar Delhi NCR8447779800, Low rate Call girls in New Ashok Nagar Delhi NCR
8447779800, Low rate Call girls in New Ashok Nagar Delhi NCR
 
Organizational Structure Running A Successful Business
Organizational Structure Running A Successful BusinessOrganizational Structure Running A Successful Business
Organizational Structure Running A Successful Business
 
Kenya Coconut Production Presentation by Dr. Lalith Perera
Kenya Coconut Production Presentation by Dr. Lalith PereraKenya Coconut Production Presentation by Dr. Lalith Perera
Kenya Coconut Production Presentation by Dr. Lalith Perera
 
Global Scenario On Sustainable and Resilient Coconut Industry by Dr. Jelfina...
Global Scenario On Sustainable  and Resilient Coconut Industry by Dr. Jelfina...Global Scenario On Sustainable  and Resilient Coconut Industry by Dr. Jelfina...
Global Scenario On Sustainable and Resilient Coconut Industry by Dr. Jelfina...
 
Annual General Meeting Presentation Slides
Annual General Meeting Presentation SlidesAnnual General Meeting Presentation Slides
Annual General Meeting Presentation Slides
 

Mechanical completion

  • 1. OILANDGASDOCS.COM MECHANICAL COMPLETION & COMMISSIONING SCOPE This PowerPoint defines the principles and structure of Mechanical Completion & Commissioning. SYSTEMS An Operational System or a Non Operational System. Operational Systems are Dynamic Process, Utility or Facility Systems such as Seawater, Diesel, HVAC, Telecom, Main Power & Control system. Non-Operational Systems are Surface Protection, Insulation, Civil, Structural Steel, Markings & Signs, Cable & Tubing trays. www.oilandgasdocs.com
  • 2. MECHANICAL COMPLETION & COMMISSIONING MECHANICAL COMPLETION STATUS INDEX (MCSI) This is a listing of all items/tags with associated check records status for each MC (or commissioning) Package. The MCSI should be produced based on the Project Completion system. SUBSYSTEM A system broken down into functional subsystems. COMMISSIONING PACKAGE A practical scope of work unit within a system or subsystem for commissioning, constituting a functional unit which can be tested by commissioning to confirm its suitability for operation. MC PACKAGE A practical unit of the scope of work for one discipline within a commissioning package. COMMISSIONING (C) Is the functional verification of equipment and facilities that are grouped together in systems. MECHANICAL COMPLETION (MC) The checking and testing of equipment and construction to confirm that the installation is in accordance with drawings and specifications and ready for commissioning in a safe manner and in compliance with project requirements. STATUS "PA" This means that this check item is not completed, and that remaining work is category 'A', i.e., must be completed prior to commissioning. 1
  • 3. MECHANICAL COMPLETION & COMMISSIONING STATUS "PB“ This means that this check item is not completed and that remaining work is category 'B’. PUNCH LIST REGISTER (PLR) A punch list register is a listing of all punch list items, prepared at a time when installation, functions or activities should have been completed. CARRY OVER WORK REGISTER (COWR) A register where incomplete items are documented sufficiently for work preparation and completion. The COWR is based on the Punch Lists Register and describes punch listed work to be transferred to the next project executor. MC DOSSIER MC documentation compiled in MC package. COMMISSIONING DOSSIER Commissioning documentation compiled in Commissioning Dossier. EXECUTOR An organisation, supplier, contractor that performs a predefined scope of work. 2
  • 4. MECHANICAL COMPLETION & COMMISSIONING COMPLETION PRINCIPLES 1. OVERALL GOAL The overall goal of Mechanical Completion & Commissioning is to verify that the system is designed and built to fulfil its purpose and specified requirements. Life cycle cost principles and safety should govern all decisions and actions. Early establishment of commissioning packages is essential for an orderly and effective project completion. The commissioning plan shall have maximum priority to enable reversed planning in all project phases. All fabrication and installation planning shall be system oriented. Mechanical Completion, Commissioning, FAT, Preservation and suppliers assistance requirements shall be specified in the purchase orders. Repeating of MC/C checks performed at suppliers and assembly sites should be avoided, wherever possible. 2. COMPLETION PHASES 2.1 DEFINITION PHASE In this phase the following is carried out: • Completion philosophy. • Coding structure and system breakdown. • Completion requirements to suppliers and contractors. 3
  • 5. 3. ENGINEERING PHASE In this phase the following is carried out: • Commissioning package & MC package definition. • Define commissioning network. • Produce commissioning procedures. 4. SUPPLIERS COMPLETION PHASE Equipment suppliers shall execute MC, FAT, commissioning and preservation as specified in the purchase order. The completion shall be documented as part of the completion system which leads up to handover to the company/client. 5. CONSTRUCTION/ASSEMBLY PHASE The Executor shall perform MC and commissioning and preservation as specified in the purchase order/contract documents. The completion is documented as part of the completion system which leads up to handover to the company. 4 MECHANICAL COMPLETION & COMMISSIONING
  • 6. 5 6. RESPONSIBILITIES Responsibilities are defined in the contract. MC execution and registration/documentation shall be performed by anyone who has a scope of work to be performed such as equipment suppliers, fabrication contractors, installation contractor and hook-up contractors. Commissioning registration and documentation shall be performed by anyone who has this responsibility implemented in their scope of work. 7. DOCUMENTATION Mechanical completion documentation shall be completed/executed per item/MC package. Commissioning documentation shall be documented on a commissioning package level. All check/test records shall end up in a status. 8. PROJECT COMPLETION SYSTEM (PCS) An electronic based system for administration of Mechanical Completion, Commissioning and Punch List Register should be used. 9. PLANNING All Mechanical Completion activities shall be planned on fully integrated fabrication, Mechanical Completion and Commissioning schedules on system prioritised basis in order to meet the optimal sequence of completion. MECHANICAL COMPLETION & COMMISSIONING
  • 7. 6 10. MECHANICAL COMPLETION This chapter forms the basis for the execution and documentation of mechanical activities. Mechanical completion takes place through all phases of the project, starting at equipment supplier and continuing through fabrication up to commissioning phase. • Mechanical completion encompasses all disciplines. • The detailed responsibilities are described in the contract. • Executor of MC activities is responsible for establishing and compiling the MC dossiers and report status into the PCS. 10.1 DOCUMENTATION FOR A MC PACKAGE The MC package shall consist of an MC Certificate, a MC Status Index and a Punch List Register printout as described below. A Mechanical Completion Certificate (MCC) is a form completed by the Executor after all MC,s are carried out. The MCC is the cover sheet for each MC package. A MC package shall when signed be ready for start of commissioning. The Check Records (CR) are the forms on which the Executors record the results of all checks, inspections and tests carried out for each individual item. A Punch List Register (PLR) shall be prepared by the Executor along with the MC activity. In each MC package a printout from the PLR shall be included to document the incomplete work. A MC Status Index (MCSI) lists the status of all CRs for the completed MC package shall be included in the MC documentation dossier. MECHANICAL COMPLETION & COMMISSIONING
  • 8. 7 10.2 HANDOVER AT MECHANICAL COMPLETION Handover at Mechanical completion to commissioning shall be at commissioning package level, documented by the Ready for Commissioning Certificate (RFCC). 10.3 CARRY OVER WORK REGISTER (COWR) The Carry Over Work Register lists all punch items that the Project accepts as cannot be completed during present phase. The COWR is used for the release of the work from the Executor and will as such be an input to the scheduling and planning of outstanding work to be performed during later phases. The COWR Item Number and cross reference to the Punch List Register/Check Records shall be given. COWR work shall be marked up on drawings or sketches and be included in the records. COWR Material Status List (MSL) and marked up drawings/instruction shall contain sufficient information for job setting in a later phase. 10.4 TYPICAL MECHANICAL COMPLETION ACTIVITIES Mechanical completion activities includes checking of fabrication and installation work. The Executor shall complete packages related to listed disciplines and as required by the MCSI. The Executor shall complete the check list items as per the MCCR's. MECHANICAL COMPLETION & COMMISSIONING
  • 9. 8 10.4.1 MECHANICAL ACTIVITIES • Visual inspection for complete and correct installation. • Flushing and cleanliness of equipment. • Alignment. • Bolt tensioning. • Pressure test. • Load test. • Operation and mechanical handling. • First fill consumables. • Preservation. • Completion of relevant verification certification. These are to be added on request by the reader. MECHANICAL COMPLETION & COMMISSIONING
  • 10. 9 10.4.2 STRUCTURAL ACTIVITIES • Visual inspection for complete and correct installation. • QC documentation. • NDE carried out. • Welding. • Load testing of lifting lugs and monorails. 10.4.3 SURFACE PROTECTION, INSULATION AND FIRE PROOFING ACTIVITIES • Visual inspection for complete and correct application. • Thickness checks carried out. • Adhesion checks carried out. • Preservation. • Insulation. • Painting. • Fire proofing. 10.4.4 ARCHITECTURAL ACTIVITIES • Visual inspection for complete and correct installation. • Preservation & Doors. MECHANICAL COMPLETION & COMMISSIONING
  • 11. 10 10.4.5 SURFACE PROTECTION, INSULATION, FIRE PROOFING & ARCHITECTURAL ACTIVITIES • Visual inspection for complete and correct installation. • Thickness checks completed. • Adhesion checks completed. • Preservation. • Insulation. • Painting. • Fire proofing. • Completion of relevant verification certification. These are to be added on request by the reader. MECHANICAL COMPLETION & COMMISSIONING
  • 12. 11 10.4.6 ELECTRICAL ACTIVITIES • Visual inspection for complete and correct installation. • Insulation and continuity testing of cables. • Ex enclosure checks. • Insulation testing of generator, transformers and motors, panels, distribution board etc. • Earthing checks. • Static check of switches and control devices. • Battery preparation. • Lighting and socket outlet checks. • Area classification checks. • Function check of switch gear and controls. • Heat tracing. • Preservation. • Completion of relevant verification certification. These are to be added on request by the reader. MECHANICAL COMPLETION & COMMISSIONING
  • 13. 12 10.4.7 INSTRUMENT/TELECOMMUNICATION/FIRE & GAS ACTIVITIES • Line walk, punch and as-build. • Calibration and testing of instruments prior to installation. • Visual inspection for complete and correct installation. • Insulation and continuity testing of cables. • Cleaning, flushing, pressure and leak testing of pneumatic and hydraulic tubing. • Adjustment and verification of control, alarm and shutdown settings. • Cold Loop testing. • Installation of control system software • Earthing checks. • Function testing of control systems. • Function testing of field instruments. • Area classification checks. • Preservation. • Completion of relevant verification certification. These are to be added at the request by the reader. MECHANICAL COMPLETION & COMMISSIONING
  • 14. 13 10.4.8 PIPING ACTIVITIES • NDE carried out. • Welding procedures. • Removal of all items subject to damage during flushing, cleaning and pressure testing. • Flushing of pipework. • Chemical cleaning and testing of pipework. • Drying of tested pipework. • Preservation of tested pipework. • Bolt torquing/Tensioning. • Pipe supports completed. • Thermal and protective insulation. • Flow coding. • Earthing. • Correct piping penetrations (fire/explosive ratings). • Line walk, punch & as-build. • Reinstatement of all items after testing & Final inspection of pipework. • Correct piping penetrations (fire/explosive ratings). • Completion of relevant verification certification. These are to be added on request by the reader. MECHANICAL COMPLETION & COMMISSIONING
  • 15. 14 10.4.9 HVAC ACTIVITIES • Visual inspection for complete and correct installation. • Cleaning of ductwork. • Leak testing of ductwork. • Alignment checks. • Mechanical functions checks of equipment. • Verification of settings. • Correct penetrations (Fire/explosive ratings). • Preservation. • Flow. • Punch and as-build. 10.4.10 SAFETY ACTIVITIES • Visual inspection for complete and correct installation. • Preservation. • Area completion. • Completion of relevant verification certification. These are to be added at the request by the reader. MECHANICAL COMPLETION & COMMISSIONING
  • 16. 15 11. COMMISSIONING This chapter forms the basis for preparation and execution of commissioning. Commissioning take place when Mechanical completion is completed for a system or part of a system. Commissioning can be divided into three main activities: • Commissioning preparation. • Commissioning execution. • Commissioning documentation and handover to operation. Establish a commissioning network and definition of commissioning packages early in a project in order to establish fabrication/installation priorities and milestones. Definition of commissioning of part systems is essential in order to achieve an early commissioning completion. 11.1 TYPICAL COMMISSIONING PREPARATION ACTIVITIES The preparatory work shall consist of activities such as: • Development of commissioning organisation & system breakdown (part system). • Commissioning packages definition. • Commissioning schedules. • Commissioning budget including spare parts for commissioning. MECHANICAL COMPLETION & COMMISSIONING
  • 17. 16 11.2 COMMISSIONING PROCEDURE CONTENTS Commissioning shall be executed by guidance of a detailed procedure describing: 11.2.1 OBJECTIVE Details the operating parameters to be achieved. 11.2.2 DESCRIPTION Shall contain a brief description of the system/part systems to be commissioned, including marked up P&ID as a basis for all functions to be tested. 11.2.3 LISTS OF TEMPORARY EQUIPMENT AND CONSUMABLES Lists all consumables, temporary equipment tools and requirements for suppliers assistance. 11.2.4 HEALTH/ENVIRONMENT/SAFETY A list of all toxic and polluting fluids and materials shall be made, describing their handling and disposal. A check list of all required safety precautions including requirements for work permit shall be made. Prior to energization of electrical equipment a livening up notice shall be issued in order to inform all involved parties of forthcoming energising. 11.2.5 PRESERVATION Requirements for removal of existing preservatives/protection shall be made and subsequent new preservation of the system if the system shall be out of operation for a period of time. MECHANICAL COMPLETION & COMMISSIONING
  • 18. 17 12 EXAMPLES OF COMMISSIONING ACTIVITES 12.1 PIPING • System Leak test. • Sensitive leak test. 12.2 INSTRUMENT/TELECOMMUNICATION/FIRE & GAS • Loop testing. • Function testing of field instruments. • Check of the installation, by line walking the installation verifying the correctness of key drawings. • Function testing of control systems. • Adjustment of control, alarm and shutdown settings. • Verification of settings on equipment. • Function test of equipment. MECHANICAL COMPLETION & COMMISSIONING
  • 19. 16 12.3 FUNCTION TEST OF NEW FACILITIES • Equipment test in accordance with vendor procedures. • HMI to SCADA test. • Signal I/O functionality. • Local and remote indicator testing. • Local and remote start stop function. • Testing of emergency stops both local and remote. • Opening/closure times on actuated valves. • Start stop of rotational equipment, check rotation direction, check performance and product quality. • Duty and standby function tests. • Fill tanks/vessels and check instruments local and remote. • Gas and UV detection tests. • Illumination tests. • HVAC testing (Functionality, flow, control and F&G). • Firewater coverage testing. MECHANICAL COMPLETION & COMMISSIONING 18
  • 20. 16 13 TYPICAL MECHANICAL COMPLETION DOCUMENTS 13.1 SCOPE The scope shall detail the work to be done step by step including the commissioning preparation. Irregularities and/or faults shall be logged. Equipment suppliers start-up procedures shall be incorporated. Performance parameters shall be included for comparison of results with actual result achieved during commissioning. 13.2 PLANNING Detailed commissioning plans for system/part system shall be worked out and shall include manhours per discipline, including supplier assistance man-hours. 13.3 HANDOVER The handover shall contain a certificate and other documents agreed with operations. 13.4 HANDOVER DOCUMENTATION TO OPERATIONS Handover of systems from Executor to Project/Operations shall be according to a formal procedure which as a minimum should consist of: • Completion acceptance certificate (signed by both parties). • Commissioning P&ID showing the extent of the completed system. • Authority certificates (if any). • Operational procedures and handbooks. MECHANICAL COMPLETION & COMMISSIONING 19
  • 21. 6 IF YOU WOULD LIKE MORE INFORMATION REGARDING MECHANICAL COMPLETION, COMMISSIONING AND CERTIFICATION, VISIT: oilandgasdocs.com Or contact tatjana@oilangasdocs.com enquiries@oilandgasdocs.com MECHANICAL COMPLETION & COMMISSIONING