Project Management National Conference 2011                                  PMI India




  Program Management Approach
  for a Complex Business
  Transformation



      Sachdeepak S Arora
      Delivery Project Executive, IBM India Pvt. Ltd.




2|P a g e
 Application of Select Tools of Psychology for Effective Project Management
Project Management National Conference 2011                                                                          PMI India




                                                                                                            Contents



  1 Abstract ............................................................................................................................4
  2 Keywords...........................................................................................................................5
  3 Introduction.......................................................................................................................5
  4 The Case Study...................................................................................................................6
  5 Key Challenges / Risks Managed.....................................................................................16
  6 Critical success factor.......................................................................................................18
  7 Best Practices...................................................................................................................19
  8 Business Benefits Realization .........................................................................................21
  9 Lessons learnt...................................................................................................................22
  10 Conclusion......................................................................................................................23
  11 Author’s Profile..............................................................................................................24




3|P a g e
 Application of Select Tools of Psychology for Effective Project Management
Project Management National Conference 2011                                        PMI India




                 1     Abstract

                 This case study showcases successful application of Project Management
                 Methodology for a large scale Business Transformation program being
                 implemented by one of the top ten global business organizations.


                 The client decided in 2006 to transform itself to a Globally Integrated Enterprise
                 by 2015, in order to meet the following objectives


                     a. Leverage global resources through common processes


                     b. Adopt standards for seamless intra and Inter-organization operations


                     c. Provide adequate controls through compliance and governance


                     d. Improve productivity and efficiency to expand margin and increase EPS


                 To meet the above business goals, client embarked on a program which involves


                     a. Transformation of Business Processes to be globally consistent.


                     b. Implementation of single ERP instance to support business processes.


                     c. Integration of business operations management


                     d. Deployment of shared services model to support functions like HR,
                        procurement, finance etc.


                     e. A major Organization Change Management initiative to ensure smooth
                        transition to future organization design


                 The key elements of PM approach include


                     a. Key stake holders’ identification and a business case approval


                     b. Logical distribution of the initiative to Project Portfolios, Programs and
                        Projects


                     c. Setting up of team/s
4|P a g e
 Application of Select Tools of Psychology for Effective Project Management
Project Management National Conference 2011                                      PMI India



                     d. Establishing a governance model and communication cadence


                     e. Program plan preparation, which includes Proof of concepts / prototypes
                        for new technologies and processes, large scale Business Process
                        transformation activities, Systems Integration and Organization Change
                        Management activities.


                     f.   High level release / roll out strategy


                     g. Execution and control process


                     h. Focused risk management


                     i.   Creation of reusable assets


                 The ‘business benefits measurements’ have confirmed that the program is on
                 track.


                 This paper highlights the effectiveness of PM Methodology in meeting challenges
                 in such large business transformation program.


                 2        Keywords

                 Business Process Transformation, Program Management, Complex system
                 integration Project Management


                 3        Introduction

                 This paper is a case study of successful application of program management
                 methodology for executing a large scale business transformation program.


                 The client is one of the top ten global business enterprises in electronics and
                 service industry with revenue of approx. 100 billion USD and is present in 170
                 countries with 4,00,000 employees.


                 The client embarked on a large scale business transformation program in 2006 in
                 order to achieve the following business objectives.


                 •   Simplify and standardize business processes across business units and
                     geographies.

5|P a g e
 Application of Select Tools of Psychology for Effective Project Management
Project Management National Conference 2011                                          PMI India



                 •   Achieve speed to the marketplace.


                 •   Integrate across the business units to enable solutions and bundled offerings
                     to the clients


                 •   Deliver products and services globally


                 •   Increase integration with back office to leverage cost competitiveness and
                     productivity


                 •   Provide additional flexibility to adapt to changing business needs


                 •   Increase spend on strategic projects and reduce on tactical projects


                 •   Cut down on cost of operations


                 •   Increase ability to leverage scale to improve efficiencies thru initiatives like
                     shared services, back office operations etc.


                 •   Reduce revenue “leakage”


                 •   Improve forecast accuracy


                 •   Ensure improved quality and availability of information across Geos and BUs


                 •   Improves business controls / audit posture


                 •   Provides real time data


                 4       The Case Study

                 The client assigned the task of this transformation to a top business exec.


                 The Client selected SAP as technology platform


                     •       Scope


                 The scope for the first wave covered business processes from Opportunity to
                 order, Order to cash, Finance and Human resource. The processes in scope are
                 listed in the table below
6|P a g e
 Application of Select Tools of Psychology for Effective Project Management
Project Management National Conference 2011                                         PMI India



 Opportunity to Order   Order to Cash                Finance                     Human Resource
 - Quotation/Proposal   - Sales Contract         -    General Ledger             - HR
    Management          Management                    Processing                    Administration
 - Pricing and          - Contract and           -    Currency / Statutory       - Compensation
    Contracts           Project Registration     -    Inter-company                 Management
 - Price and Margin     - Service Contracts           Processing                 - Org Mgt
    Management          Management               -    Project Systems            - Time and
 - Partner Channel      - Sales Order            -    Profitability Analysis        Attendance
    Management          Management               -    Profit Centre              - Payroll
 - Product              - Service Order          -    Cost Centres / Internal    - Employee Self
    Configuration       Management                                                  Service
                                                      Orders
 - Lead Management      - Billing                                                - Manager’s
 - Opportunity          - Contract and           -    Financial Closing
                                                                                    Self service
    Management          Project Close            -    Manage Banking
                        - Invoicing                   Functions
                        - Cost Recognition       -    Tax Accounting &
                        - Revenue                     Settings
                        Recognition              -    Account Payable
                        - Logistics Execution    -    Manage Accounts
                        - Complaints And              Receivable
                        Returns                  -    Collections Management
                        - Installed Base         -    Dispute Management
                        Management               -    Credit Management
                        - Product                -    Account for Fixed Assets
                        Configuration            -    Support Capital Tracking
                        Services
                                                 -    Support Property Control
                        - Project Based Cost
                                                 -    Business Controls &
                        - Revenue
                                                      Reporting
                        Forecasting
                                                 -    Perform Supplier
                                                      enablement
                                                 -    Execute Procurement
                                                      opportunities
                                                 -    Purchase Order Logistics
                                                 -    Financial Master Data


                 •   Global Template Approach:


                 Development of one common global template was of strategic importance in
                 order to achieve business requirement of common business processes across
                 the organization.


                 In addition, the global template serves the following requirements of the program.


                 •   Minimize retrofitting, rework, regression testing


                 •   Provide 95% of configuration before deployments begin




7|P a g e
 Application of Select Tools of Psychology for Effective Project Management
Project Management National Conference 2011                                              PMI India



                      •    Promote buy-in and ownership through collaborative blueprint workshops
                           involving representatives from all geographies, business units and global
                           process owners


                      •    Develop a foundation for standardization controls to better manage the
                           systems landscape to maintain an integrated design


                      •    Develop a framework for a repeatable structure used for operations support
                           across enterprise.


 Global Common
 Standards
 Defines all globally applicable
 system structures and data
 standards, such as: global
 Chart of Accounts, SAP
 hierarchies, master data.




 Common Processes
 This repository for the key
 integrated business process
 scenarios, including common
 interfaces, reports and bolt-ons.


  Leverage able Content
  Broadly applicable content across
  business units and geographies
  offering reduced total
  implementation and long-term
  support costs


 Regional / Business
 Unit Variations
 Market specific customizations


 Differentiation
 SOA will be used to maintain those processes
 that differentiate IBM in the marketplace         Figure – 1: Global template approach



                      •    Planning


                       The initiative was spilt logically into various programs, project portfolios and
                       projects.


                       A full cycle implementation was carried out at a small business entity as a proof
                       of concept. The scope for POC was carefully chosen to represent the entirety of

8|P a g e
 Application of Select Tools of Psychology for Effective Project Management
Project Management National Conference 2011                                             PMI India



                    process design in a smaller version. Similarly, prototypes for new technologies
                    were prepared


                    Deployment plan to roll out the template across the enterprise in a release model
                    was prepared. The roll out plan is based on business priorities like emerging
                    markets , requirement of applications in the geographies where the existing
                    system are not able to take the growth load , geographies where cost of
                    maintaining existing systems are very high. Figure 2 lays out life cycle the
                    program and specifies the dependencies in the lifecycle.


                    Figure – 2: A large scale business transformation program lifecycle



                                                                             First release
                  Business Case                   Prototype / Pilot /
                  App.                            Proof of concept



                        Establish
                                                Business benefits               Set Up operations
                        Centers of
                                                measurement                     Management
                        Competency &
                        Excellence


                                                                                Achievement
                                             Subsequent                         of Business
            Global
                                             releases                           Goals
            Templates                                     We
                                                          are
                                                          her
                                                          e


                   •     Methodology


                    IBM Ascendant method is being used for the implementation. The project life
                    cycle has seven phases and six domains.


                    Deliverables of each domain in each phase are well defined in the method




9|P a g e
 Application of Select Tools of Psychology for Effective Project Management
Project Management National Conference 2011                                         PMI India



                                          Fig -3: IBM Ascendant Method


                 The Ascendant SAP Methods offer guidance, like a map or a recipe, and can be
                 altered to meet the specific needs of a project.


                 The methodology provides a consistent, structured, and practical approach to


                     1.      What needs to be done


                     2.      How it should be done


                     3.      How it should be controlled


                     4.      Who should do it


                 •   Establishing the key leadership team


                 Establishing key leadership team was the first step. In addition to the regular Job
                 description process to on board the team, the following additional factors were
                 considered keeping in view the complexity and the volume of the program.


                 •   Org structure is generally dynamic, since the technical and leadership skills
                     required at beginning of the life cycle are very different and of the highest
                     quality than the skills required for steady state operations and roll outs.


                 •   The steady state operations and rollouts to be achieved through centers of
                     competency or excellence functioning effectively.


                 •   The desired key resources may not be available at the outset, as they may
                     be involved in other programs and will require to be brought in, at different
                     stages in the program life cycle.


                 •   The requirement of type of leadership may change depending upon the
                     program situation and phase of the program lifecycle.


                 •   Strategy program planning team is different from the routine project
                     management team and focuses on the long term business benefits
                     realization




10|P a g e
 Application of Select Tools of Psychology for Effective Project Management
Project Management National Conference 2011                                         PMI India



                 •   The teams engaged at early stages of program are likely to require support
                     from their leadership since some of the deliverables may not meet the
                     expectations as anticipated.


                 •   The number of resources required is likely to increase / decrease significantly
                     to meet peaks and turfs of the requirements.


                 •   Development of Technical Applications & Systems


                 •   Design & Build


                       Best of class resources were chosen to work on solution and design. ‘As
                       is’ design was converted to a ‘To be’ design document. Solution design
                       team worked closely with business. After the business blue print was
                       signed off, a ‘Requirement Traceability and Verification Matrix’ was
                       prepared as per SEA guidelines. Solution design team configured the
                       system and developed functional as well as technical specifications.


                       More than 1500 objects and 400 interfaces were developed in the first
                       phase itself.


                       A large number of reports, data conversion programs, enhancements,
                       workflows and forms were developed.


                 •   Data Migration


                       Millions of data elements were migrated from various legacy systems in to
                       SAP. A process assigning data element ownership to the right business
                       owner was established. The global data standards were followed.


                       The data migration cycle included a seven step approach. They were data
                       extraction, mapping, cleansing, a scrambling (to ensure data privacy
                       compliance), development of conversion programs, conversion and data
                       verification & validation.


                       The data element owners assumed the responsibility of confirmation that
                       the data loaded is correct and meets the business logic as part of exit
                       criteria


                 •   Testing




11|P a g e
 Application of Select Tools of Psychology for Effective Project Management
Project Management National Conference 2011                                          PMI India



                     The following cycles of testing were carried out. A total of 1800 test scripts
                     were executed during system integration testing phase


                          • Functional / Unit Testing        was owned by the developers /
                          configuration team


                          • Integration Testing was owned by the development team. However,
                          during the later cycles, after majority of the defects were taken care of,
                          members from business and sustenance team joined the development
                          team. This helped reducing time for users’ acceptance testing and also
                          transition to sustain. The test scripts were prepared based on the
                          functionality captured in the ‘requirement traceability and verification
                          matrix’


                          • User Acceptance Testing involved multiple users and also testing of
                          global template elements .Users were trained in SAP prior to taking up
                          users’ acceptance tests.


                          • Regression Testing, wherever applicable , was carried out


                          • Performance / Stress Testing for validating network and system load
                          capacity were carried out . The test results met the defined exit criteria.


                 •   Scope Change Management Process


                     A scope change management process was set up. Each change request had
                     to go through a change board approval. Despite strict control, about 500 CRs
                     were required for the first release. The change board met more frequently
                     closer to ‘ Go Live ‘ .


                     All domain leads were required to carry out impact assessment on every
                     change request. Closer to go live only those domains which were considered
                     relevant were asked to submit impact analysis and others were informed to
                     respond in case they believed there is an impact. This expedited the process
                     for CR approvals.


                 •   Stake Holders’ Management


                     There are many stake holders in this complex program including the business
                     users, top management, steering committee, business process leaders, the
                     teams who were redeployed as part of future org design and the project team
                     members.


12|P a g e
 Application of Select Tools of Psychology for Effective Project Management
Project Management National Conference 2011                                          PMI India



                      The following    factors   increased   the   complexity   in   stake   holders’
                      management.


                         • Diversity of stake holders: local, regional, global business leaders,
                         unions etc.


                         •   Enterprise-wise impact of every important decision


                         •   Higher costs of delivery


                         •   Higher opportunity costs


                  •   Tracking & Controlling


                      A project communication plan based on project tracking, controlling and
                      communication needs was developed.


                      Processes like on boarding and off boarding were developed. Artifacts like
                      project charter, team charter and communication plan were created. Team
                      rooms, program Wikis and other virtual tools for sharing and storing project
                      the artifacts were made available.


                      Entry and exit criteria for each major deliverable and key milestone were
                      defined.


                      Communication cadence thru status calls, face to face workshops, milestone
                      check point meetings, executive and steering committee reviews, quality and
                      audit reviews were put in place


                      Conference calls involving resources from Europe, US, Australia and India
                      required time rotation so that disadvantage of working at odd hours could be
                      shared by all teams


                      IBM Seven Keys to success process was used for reporting at senior
                      management level.


                                            IBM Seven Keys to Success
                                1. Stake holders are committed
                                2. Business benefits are being realized
                                3. Work and Schedule are predictable
                                4. Scope is realistic and manageable
                                5. Team is high performing
13|P a g e
                                6. Risks are being mitigated
 Application of Select Tools of Psychology for Effective Project Management
                                7. Delivery organization benefits are being realized
Project Management National Conference 2011                                        PMI India




                     The program is on schedule; however the costs overshot by approx 13 %.
                     The main reasons for costs to increase were


                            •        The additional effort and travel for face to face workshops on
                            getting the business requirements articulated to the level of
                            granularity.


                            •        Procurement of high / niche skilled expensive resources for
                            solution and design.


                 •   Organization change management activities


                     Organization readiness to accept such a large change required significant
                     amount of OCM activity. The change agents were identified as sponsors in
                     top management, advocates in senior execs & business heads, change
                     process owners and coaches in the middle management


                     The program has engaged specialist services for carrying out OCM activities.
                     The change was mainly occurring from


                            •       Large scale business process transformation (from local to
                            global)


                            •        New organization design and changes in roles


                            •        Skill gaps for managing future organization


                     The main deliverables were


                            •        Future Org design


                     A five step approach for developing future org design was adopted


                        •   Document and assess ‘As Is’ org.



14|P a g e
 Application of Select Tools of Psychology for Effective Project Management
Project Management National Conference 2011                                      PMI India



                        •   Envision ‘To Be’ org.


                        •   Design ‘To Be’ org. and Job roles


                        •   Define Skills and Competencies to close Gaps in ‘As Is’ – ‘To Be ‘ ,
                            map roles


                        •   Create plans to resolve gaps



                                               Business Strategy
                                                                                  Future
                                           Organization & Process                  State
                     Current                  People
                      State        Organizational Change Management
                                                    Information
                                                    Technology




                                    Fig -4: Factors impacting Future Org design


                 •   Communication


                     A communication plan was developed based on communication need
                     analysis for the organization. The plan detailed what needs to be
                     communicated by whom and when. It also listed the medium of
                     communication. Various types of communication material were developed.
                     Communication was routed through key stake holders /change agents for
                     appropriate impact.


                 •   Training


                     Training need analysis was carried out. Based on requirement for various
                     user groups, multiple types of training materials were developed and
                     delivered. The super users were also sent for SAP training, prior to
                     involvement in users’ acceptance testing. Learning Labs and Classroom
                     trainings were organized. Computer based simulations were prepared for
                     complex transactions. Web lectures and web pages providing information
                     about new processes and tools were prepared and made available to the
                     users to be accessed at their own time .



15|P a g e
 Application of Select Tools of Psychology for Effective Project Management
Project Management National Conference 2011                                           PMI India



                     An organization readiness check point included completion of trainings to
                     various user groups prior to go live


                 5     Key Challenges / Risks Managed

                 The following were a few of the key risks experienced and managed in this
                 engagement


                 •   Business process owners experienced difficulty in articulating requirements,
                     since the processes were getting globally aligned for the first time in the
                     organization. The processes owners were familiar with the local business
                     requirements.


                     Use of agile methodology was of some help to address this issue.
                     Requirement Traceability Verification Matrix was of help in articulating
                     requirements.


                 •   Where the process definition was incomplete or flawed, it created issues of
                     acceptance by the users at the exit point. Program management tried
                     defining Exit and Entry criteria with as much clarity as possible.


                 •   SAP solutions being implemented did not address all the requirements from
                     the business. Additional budget and time were required for unplanned
                     development work. The following are the reasons for the additional
                     development work


                         o There were business scenarios / requirements where the SAP
                         solutions did not meet the business need and required customization.


                         o There were SAP solutions which were not tried earlier and required
                         some amount of customization. SAP time lines of delivering these
                         changes did not support the project time lines and project had to bear
                         the expenses for developing the solution


                         o The right expertise to implement a few desired solutions was not
                         accessible as required to meet the project time lines.


                 •   Low data quality created issues for migration and reconciliation in production
                     since it was the first time the globally distributed (multiple applications) data
                     was migrated in a single database and global data standards were
                     implemented.



16|P a g e
 Application of Select Tools of Psychology for Effective Project Management
Project Management National Conference 2011                                          PMI India



                 •   A few weak configurable controls / access controls and/or Separation of
                     Duties allowed errors and audit exposure. New roles at different levels were
                     getting created for the first time as per the future org design scenario.


                 •   Very high volumes of users caused system to be unstable. This was
                     especially true immediately after the roll outs / releases since more number
                     of users (out of curiosity than normally as planned ) logged in and users
                     spent more than required time (since they were learning to use the new
                     application ) on the application .


                 •   System exited (went live) with some known or unknown problems due to
                     oversight in testing and/or decisions made around Exit criteria. The users
                     signing exit criteria found it difficult to understand process & technology
                     transformation from local to global. The stay of hyper-care team was
                     extended from planned 30 days to 45 days. Additional costs were picked up
                     by the project


                 •   Multiple regulatory compliances brought in additional challenges for program
                     management team since this transformation involved multiple countries,
                     business units and applications. These compliance included


                         o   Data Privacy laws


                         o   Visa and work permits


                         o   Union agreements


                         o   Global trade practices and restrictions


                         o   Audits like SOX, Client specific , Service provider specific


                         o   Intellectual property protection


                 •   Management of diverse global delivery teams in virtual environments threw
                     up additional challenges. A global and virtual team was best suited to this
                     program since the complexity and diversity of the required skill sets dictated
                     to bring on board variety of resources. Best in class resources were required
                     for design and solution and could be picked up from any where and the most
                     cost effective for routine operations.


                     The team scaled up to approx 1000 resources during peak period.


17|P a g e
 Application of Select Tools of Psychology for Effective Project Management
Project Management National Conference 2011                                         PMI India



                     The program spent additional money for


                         o Additional communication time and infrastructure for virtual working.

                         o   Travel costs for face to face meetings and workshops


                         o   Cultural sensitivity trainings


                 6     Critical success factor

                 In order to achieve the envisaged business benefits and make program
                 successful, the following are considered as Critical Success Factors


                 •   Strong, active executive committee that demonstrates visible sponsorship of
                     the project


                 •   Visible organizational commitment to make significant process and
                     organizational changes, resulting in targeted benefits realization.


                 •   Dedicated, empowered project team able to make rapid decisions on behalf
                     of business units


                 •   Country buy-in and accountability for results, especially for such large global
                     implementation involving multiple countries.


                 •   Rigorous scope management process to limit modifications to standard SAP
                     functionality and to keep scope within original estimates


                 •   Common enterprise level design, with limited process and configuration
                     changes during the rollout/ releases of the project


                 •   Rapid decision making and issue resolution procedures, coupled with prompt
                     escalation and resolution of critical business issue


                 •   Benefits Realization as an integral part of the Project, not a follow-on or
                     collateral activity


                 •   Change management and organizational alignment processes in place to
                     make the organization ready to accept change.



18|P a g e
 Application of Select Tools of Psychology for Effective Project Management
Project Management National Conference 2011                                          PMI India



                 •   Clear, concise, relevant, and actionable performance measures directly
                     linked to each element of the business case and visible to all levels of the
                     organization


                 •   One integrated team with clearly defined program objectives, goals, and
                     timeline.


                 7     Best Practices

                 The following are some of the best Practices implemented in the program


                 •   Establishment of the CoE / CoC .- A CoE was set up with the following
                     objectives


                        o CoE enables development of the required skills, development and
                        upkeep of reusable assets thus bringing down the costs for the program


                        o The location of the CoE was carefully selected considering costs
                        and availability of required skills


                        o    The CoE charter includes that


                        •   All key resources are strategically part of the center.


                        •   The key deliverables of the program are owned by the center.


                        •   Implement best practices


                 •   Established ‘Core and Flexi team’ model


                        o In order to optimize costs and delivery capabilities, a core and flexi
                        team model has been adopted. This addresses resource requirements to
                        meet ‘peaks and troughs’


                        o The critical skills are retained in the program as core team. These
                        resources are usually on the leadership roles or posses niche skills. The
                        flexi team is brought in on ‘as required basis ’.


                        o The core team is highly skilled and is well versed in client specific
                        business requirements. This team can guide / lead the flexi team. The
                        flexi team is brought up to required skill levels by the core team through
19|P a g e
 Application of Select Tools of Psychology for Effective Project Management
Project Management National Conference 2011                                          PMI India



                         an ‘on boarding’ process which include training in client specific
                         processes and methods


                 •   Created reusable assets and assigned asset ownership A large number
                     of reusable assets were created / being created. A process to continuously
                     improve upon the existing reusable assets and skills based on the lessons
                     learnt has been established. This process helps to meet the planned
                     productivity improvement in the business case. The program management
                     assets are


                         o   Templates - development, configuration, testing, communication etc.


                         o Processes – engagement, change management, issues and risk
                         management, decision making,


                         o   Physical assets - testing rooms, virtual Private networks, severs .


                         o Soft ware Programs – configuration documentation , RICEFW
                         programs (Reports , Interfaces, Conversions, Enhancements , Forms and
                         workflows )


                         o Project Plans – Engagement & delivery, development, testing,
                         cutover.


                         o   Test scripts , Data migration processes


                         o Business Process Procedures – Global processes, desk top
                         procedures.


                         o   Technical architect diagrams.


                 •   Prepared business continuity / Disaster Recovery. The client servers are
                     hosted in a data center which has built up geographically dispersed back up
                     to ensure continuity in case of any disaster / eventuality like earth quake
                     /floods or damage due war / terrorist strikes.


                 •   Assigned data elements ownership – Each data element was assigned an
                     owner. The owner was normally a business process owner, who dealt with
                     the specific data element as part of his normal duties. He was responsible of
                     ensuring that the clean data is provided for upload and after conversion,
                     validate that data is correctly reflected in the new SAP system.


20|P a g e
 Application of Select Tools of Psychology for Effective Project Management
Project Management National Conference 2011                                             PMI India



                    •    Preparation of Check lists - Check lists defining entry & exit criteria for all
                         major milestones were prepared. A check list for meeting Go Live criteria is
                         listed below as an example.




                      Go Live Check List


Completion of all major test activities SIT: Signoff complete
                                        UAT: Signoff complete
                                        Performance Test: Test complete
Data Cleanup and Data Migration       Data verification signoff complete
Activities                            Data validation and correction Complete
Execution of users’ transition plan   OCM roadmap execution in progress as per plan
                                      Bubble staff in place
Completion of LCM Preparedness        LCM staff in place
Plan                                  Knowledge transfer Complete
                                      Sustain Readiness Exit criteria met
Execution of Cutover Plan             Production verification Confirmed
                                      Dry run Complete
                                      Failover plan in place
Operational Readiness                 Documentation in place
                                      Hypercare support in place
Technical Readiness                   Hardware in place; System build Complete
                                      Network upgrade complete
                                      Interface batch Scheduling/monitoring/performance complete
Other Criteria Required for Go Live   Disaster recovery plan confirmed
                                      Audit certification received


                    8       Business Benefits Realization

                      The realized business benefits were measured in line with business case
                      commitments. In addition to the global process alignment, there were tangible as
                      well as intangible benefits.


                      All tangible benefits were measured and reflected in quantities. Assessment
                      about intangible benefits like increased employee morale, company branding etc.
                      was also made.


                      This exercise confirmed that the program was meeting the business case
                      objectives and is in line with business leadership’s strategic vision


                      Key benefits achieved are mentioned below

21|P a g e
 Application of Select Tools of Psychology for Effective Project Management
Project Management National Conference 2011                                                 PMI India




       Benefit                            Source                                      Metrics
System Sunset            Number of systems / interfaces sunset /       Number of Systems / interfaces
                         partly sunset                                 sunset

Resource Savings         Resource Costs                                Number of FTEs redeployed

Contract Savings         Number of external support vendors            Number of external venders’
                                                                       reduced / activities curtailed
Control Points saving    Redundant Control Points                      Number of control points reduced
                         Automated Control Points

Staff Efficiency &       Transaction Time                              Reduction in Transaction process
Productivity             Iterations                                    time
                                                                       Reduction in Iteration
Cost savings             The amount spent on the system to             The difference between the
                         support business                              amounts spent prior and post
                                                                       transformation with details of
                                                                       contributing factors.


                     9      Lessons learnt

                     •   Requirement of right skills - The requirement of right skills is critical for such a
                         large transformation program. These skills are required across the domains
                         like engagement, business, application, architect and organization change
                         management. Right service provider, where these skills are available needs
                         to be brought in to steer such programs right at the outset


                     •   The business finds very difficult to provide the requirements in the
                         requirement gathering phase. Despite trainings, some gaps do remain with
                         business teams to provide end to end process information and also
                         understand 'to be' processes. Hence changes in business requirements do
                         come up during testing and even later part of the project. Methodologies like
                         Agile and artifacts like ‘Requirement Traceability and Verification matrix’ are
                         of help.


                     •   Program managers need to effectively monitor changes in the scope. A few
                         slippages could result in additional work for months. On the other hand,
                         missing on a few critical business requirements could make the developed



22|P a g e
 Application of Select Tools of Psychology for Effective Project Management
Project Management National Conference 2011                                          PMI India



                     application inadequate for business to accept or may require an expensive
                     work-around.


                 •   The change management process followed at the project involved mandatory
                     assessment by all domains. The response from all domains delays
                     processing of CRs .To expedite the approval process , CRs should be taken
                     for approval after preliminary assessment by relevant domains and should be
                     send to all domains for concurrence after approval.


                 •   Early involvement of users’ and sustain team members help reduce overall
                     users’ acceptance testing and transition to sustain time


                 •   Data quality and application of global data standards to multiple local
                     systems can create major data consistency issues. Assignment of data
                     ownership to the right business process owner to validate the data is of help
                     to get the right quality of data in to the system.


                 10 Conclusion

                 Many multinationals are integrated businesses across geographies and business
                 units to realize their strategic business objectives of rapidly responding to global
                 marketplace and significantly reducing operations costs. The ERP packages
                 provide technology platform to support such initiatives.


                 Program managing such complex transformation initiatives throw multiple
                 additional challenges. The Program Managers require high levels of skills of
                 effectively communicating to virtual teams across diverse cultures, negotiating
                 successfully , solving complex issues, providing leadership , managing
                 relationship across multiple levels, managing ambiguity, demonstrating sound
                 business Judgment and technical acumen             to successfully deliver these
                 envisaged business benefits to the clients, on time and with in budget




23|P a g e
 Application of Select Tools of Psychology for Effective Project Management
Project Management National Conference 2011                                  PMI India




                 11 Author’s Profile




                 Sachdeepak is IBM certified Senior Project Manager and Certified SAP
                 Consultant

                 He has successfully managed complex and high valued IT /SAP
                 business transformation Projects like Global SAP Implementation &
                 Support and business transformation on SAP for one of the largest
                 global IT Companies .

                 He set up operations support and development of interfaces in WBI suite,
                 managed Siebel implementation & support and Implementation of SAP in
                 Uniliver Ltd.

                 He managed ECC 5.0 upgrade, SAP releases and rollouts for Ericsson,
                 while working in Stockholm.

                 He led Implementation of SAP HR for Rohm & Haas, 3Com (while
                 working in the US) & for L & T group of companies.

                 He spearheaded automation of Airmen and Officers’ recruitment and
                 selection processes for Indian Air Force

                 In addition, to his delivery roles, Sachdeepak is a trainer and a certified
                 instructor for Project Management and Project Financial and also a
                 reviewer and mentor for PMs seeking Senior PM Certifications in IBM.
24|P a g e
 Application of Select Tools of Psychology for Effective Project Management
Project Management National Conference 2011                                  PMI India



                 He holds MBA and M. Phil. (Org Mgt ) degrees and have published and
                 presented papers on Project Management in system integration &
                 application development at various forums like SAP Tech Ed, Society of
                 PM Japan and PMI Chapter, Bangalore.


                 sacarora@in.ibm.com , sdsarora@hotmail.com




25|P a g e
 Application of Select Tools of Psychology for Effective Project Management

MCP4

  • 2.
    Project Management NationalConference 2011 PMI India Program Management Approach for a Complex Business Transformation Sachdeepak S Arora Delivery Project Executive, IBM India Pvt. Ltd. 2|P a g e Application of Select Tools of Psychology for Effective Project Management
  • 3.
    Project Management NationalConference 2011 PMI India Contents 1 Abstract ............................................................................................................................4 2 Keywords...........................................................................................................................5 3 Introduction.......................................................................................................................5 4 The Case Study...................................................................................................................6 5 Key Challenges / Risks Managed.....................................................................................16 6 Critical success factor.......................................................................................................18 7 Best Practices...................................................................................................................19 8 Business Benefits Realization .........................................................................................21 9 Lessons learnt...................................................................................................................22 10 Conclusion......................................................................................................................23 11 Author’s Profile..............................................................................................................24 3|P a g e Application of Select Tools of Psychology for Effective Project Management
  • 4.
    Project Management NationalConference 2011 PMI India 1 Abstract This case study showcases successful application of Project Management Methodology for a large scale Business Transformation program being implemented by one of the top ten global business organizations. The client decided in 2006 to transform itself to a Globally Integrated Enterprise by 2015, in order to meet the following objectives a. Leverage global resources through common processes b. Adopt standards for seamless intra and Inter-organization operations c. Provide adequate controls through compliance and governance d. Improve productivity and efficiency to expand margin and increase EPS To meet the above business goals, client embarked on a program which involves a. Transformation of Business Processes to be globally consistent. b. Implementation of single ERP instance to support business processes. c. Integration of business operations management d. Deployment of shared services model to support functions like HR, procurement, finance etc. e. A major Organization Change Management initiative to ensure smooth transition to future organization design The key elements of PM approach include a. Key stake holders’ identification and a business case approval b. Logical distribution of the initiative to Project Portfolios, Programs and Projects c. Setting up of team/s 4|P a g e Application of Select Tools of Psychology for Effective Project Management
  • 5.
    Project Management NationalConference 2011 PMI India d. Establishing a governance model and communication cadence e. Program plan preparation, which includes Proof of concepts / prototypes for new technologies and processes, large scale Business Process transformation activities, Systems Integration and Organization Change Management activities. f. High level release / roll out strategy g. Execution and control process h. Focused risk management i. Creation of reusable assets The ‘business benefits measurements’ have confirmed that the program is on track. This paper highlights the effectiveness of PM Methodology in meeting challenges in such large business transformation program. 2 Keywords Business Process Transformation, Program Management, Complex system integration Project Management 3 Introduction This paper is a case study of successful application of program management methodology for executing a large scale business transformation program. The client is one of the top ten global business enterprises in electronics and service industry with revenue of approx. 100 billion USD and is present in 170 countries with 4,00,000 employees. The client embarked on a large scale business transformation program in 2006 in order to achieve the following business objectives. • Simplify and standardize business processes across business units and geographies. 5|P a g e Application of Select Tools of Psychology for Effective Project Management
  • 6.
    Project Management NationalConference 2011 PMI India • Achieve speed to the marketplace. • Integrate across the business units to enable solutions and bundled offerings to the clients • Deliver products and services globally • Increase integration with back office to leverage cost competitiveness and productivity • Provide additional flexibility to adapt to changing business needs • Increase spend on strategic projects and reduce on tactical projects • Cut down on cost of operations • Increase ability to leverage scale to improve efficiencies thru initiatives like shared services, back office operations etc. • Reduce revenue “leakage” • Improve forecast accuracy • Ensure improved quality and availability of information across Geos and BUs • Improves business controls / audit posture • Provides real time data 4 The Case Study The client assigned the task of this transformation to a top business exec. The Client selected SAP as technology platform • Scope The scope for the first wave covered business processes from Opportunity to order, Order to cash, Finance and Human resource. The processes in scope are listed in the table below 6|P a g e Application of Select Tools of Psychology for Effective Project Management
  • 7.
    Project Management NationalConference 2011 PMI India Opportunity to Order Order to Cash Finance Human Resource - Quotation/Proposal - Sales Contract - General Ledger - HR Management Management Processing Administration - Pricing and - Contract and - Currency / Statutory - Compensation Contracts Project Registration - Inter-company Management - Price and Margin - Service Contracts Processing - Org Mgt Management Management - Project Systems - Time and - Partner Channel - Sales Order - Profitability Analysis Attendance Management Management - Profit Centre - Payroll - Product - Service Order - Cost Centres / Internal - Employee Self Configuration Management Service Orders - Lead Management - Billing - Manager’s - Opportunity - Contract and - Financial Closing Self service Management Project Close - Manage Banking - Invoicing Functions - Cost Recognition - Tax Accounting & - Revenue Settings Recognition - Account Payable - Logistics Execution - Manage Accounts - Complaints And Receivable Returns - Collections Management - Installed Base - Dispute Management Management - Credit Management - Product - Account for Fixed Assets Configuration - Support Capital Tracking Services - Support Property Control - Project Based Cost - Business Controls & - Revenue Reporting Forecasting - Perform Supplier enablement - Execute Procurement opportunities - Purchase Order Logistics - Financial Master Data • Global Template Approach: Development of one common global template was of strategic importance in order to achieve business requirement of common business processes across the organization. In addition, the global template serves the following requirements of the program. • Minimize retrofitting, rework, regression testing • Provide 95% of configuration before deployments begin 7|P a g e Application of Select Tools of Psychology for Effective Project Management
  • 8.
    Project Management NationalConference 2011 PMI India • Promote buy-in and ownership through collaborative blueprint workshops involving representatives from all geographies, business units and global process owners • Develop a foundation for standardization controls to better manage the systems landscape to maintain an integrated design • Develop a framework for a repeatable structure used for operations support across enterprise. Global Common Standards Defines all globally applicable system structures and data standards, such as: global Chart of Accounts, SAP hierarchies, master data. Common Processes This repository for the key integrated business process scenarios, including common interfaces, reports and bolt-ons. Leverage able Content Broadly applicable content across business units and geographies offering reduced total implementation and long-term support costs Regional / Business Unit Variations Market specific customizations Differentiation SOA will be used to maintain those processes that differentiate IBM in the marketplace Figure – 1: Global template approach • Planning The initiative was spilt logically into various programs, project portfolios and projects. A full cycle implementation was carried out at a small business entity as a proof of concept. The scope for POC was carefully chosen to represent the entirety of 8|P a g e Application of Select Tools of Psychology for Effective Project Management
  • 9.
    Project Management NationalConference 2011 PMI India process design in a smaller version. Similarly, prototypes for new technologies were prepared Deployment plan to roll out the template across the enterprise in a release model was prepared. The roll out plan is based on business priorities like emerging markets , requirement of applications in the geographies where the existing system are not able to take the growth load , geographies where cost of maintaining existing systems are very high. Figure 2 lays out life cycle the program and specifies the dependencies in the lifecycle. Figure – 2: A large scale business transformation program lifecycle First release Business Case Prototype / Pilot / App. Proof of concept Establish Business benefits Set Up operations Centers of measurement Management Competency & Excellence Achievement Subsequent of Business Global releases Goals Templates We are her e • Methodology IBM Ascendant method is being used for the implementation. The project life cycle has seven phases and six domains. Deliverables of each domain in each phase are well defined in the method 9|P a g e Application of Select Tools of Psychology for Effective Project Management
  • 10.
    Project Management NationalConference 2011 PMI India Fig -3: IBM Ascendant Method The Ascendant SAP Methods offer guidance, like a map or a recipe, and can be altered to meet the specific needs of a project. The methodology provides a consistent, structured, and practical approach to 1. What needs to be done 2. How it should be done 3. How it should be controlled 4. Who should do it • Establishing the key leadership team Establishing key leadership team was the first step. In addition to the regular Job description process to on board the team, the following additional factors were considered keeping in view the complexity and the volume of the program. • Org structure is generally dynamic, since the technical and leadership skills required at beginning of the life cycle are very different and of the highest quality than the skills required for steady state operations and roll outs. • The steady state operations and rollouts to be achieved through centers of competency or excellence functioning effectively. • The desired key resources may not be available at the outset, as they may be involved in other programs and will require to be brought in, at different stages in the program life cycle. • The requirement of type of leadership may change depending upon the program situation and phase of the program lifecycle. • Strategy program planning team is different from the routine project management team and focuses on the long term business benefits realization 10|P a g e Application of Select Tools of Psychology for Effective Project Management
  • 11.
    Project Management NationalConference 2011 PMI India • The teams engaged at early stages of program are likely to require support from their leadership since some of the deliverables may not meet the expectations as anticipated. • The number of resources required is likely to increase / decrease significantly to meet peaks and turfs of the requirements. • Development of Technical Applications & Systems • Design & Build Best of class resources were chosen to work on solution and design. ‘As is’ design was converted to a ‘To be’ design document. Solution design team worked closely with business. After the business blue print was signed off, a ‘Requirement Traceability and Verification Matrix’ was prepared as per SEA guidelines. Solution design team configured the system and developed functional as well as technical specifications. More than 1500 objects and 400 interfaces were developed in the first phase itself. A large number of reports, data conversion programs, enhancements, workflows and forms were developed. • Data Migration Millions of data elements were migrated from various legacy systems in to SAP. A process assigning data element ownership to the right business owner was established. The global data standards were followed. The data migration cycle included a seven step approach. They were data extraction, mapping, cleansing, a scrambling (to ensure data privacy compliance), development of conversion programs, conversion and data verification & validation. The data element owners assumed the responsibility of confirmation that the data loaded is correct and meets the business logic as part of exit criteria • Testing 11|P a g e Application of Select Tools of Psychology for Effective Project Management
  • 12.
    Project Management NationalConference 2011 PMI India The following cycles of testing were carried out. A total of 1800 test scripts were executed during system integration testing phase • Functional / Unit Testing was owned by the developers / configuration team • Integration Testing was owned by the development team. However, during the later cycles, after majority of the defects were taken care of, members from business and sustenance team joined the development team. This helped reducing time for users’ acceptance testing and also transition to sustain. The test scripts were prepared based on the functionality captured in the ‘requirement traceability and verification matrix’ • User Acceptance Testing involved multiple users and also testing of global template elements .Users were trained in SAP prior to taking up users’ acceptance tests. • Regression Testing, wherever applicable , was carried out • Performance / Stress Testing for validating network and system load capacity were carried out . The test results met the defined exit criteria. • Scope Change Management Process A scope change management process was set up. Each change request had to go through a change board approval. Despite strict control, about 500 CRs were required for the first release. The change board met more frequently closer to ‘ Go Live ‘ . All domain leads were required to carry out impact assessment on every change request. Closer to go live only those domains which were considered relevant were asked to submit impact analysis and others were informed to respond in case they believed there is an impact. This expedited the process for CR approvals. • Stake Holders’ Management There are many stake holders in this complex program including the business users, top management, steering committee, business process leaders, the teams who were redeployed as part of future org design and the project team members. 12|P a g e Application of Select Tools of Psychology for Effective Project Management
  • 13.
    Project Management NationalConference 2011 PMI India The following factors increased the complexity in stake holders’ management. • Diversity of stake holders: local, regional, global business leaders, unions etc. • Enterprise-wise impact of every important decision • Higher costs of delivery • Higher opportunity costs • Tracking & Controlling A project communication plan based on project tracking, controlling and communication needs was developed. Processes like on boarding and off boarding were developed. Artifacts like project charter, team charter and communication plan were created. Team rooms, program Wikis and other virtual tools for sharing and storing project the artifacts were made available. Entry and exit criteria for each major deliverable and key milestone were defined. Communication cadence thru status calls, face to face workshops, milestone check point meetings, executive and steering committee reviews, quality and audit reviews were put in place Conference calls involving resources from Europe, US, Australia and India required time rotation so that disadvantage of working at odd hours could be shared by all teams IBM Seven Keys to success process was used for reporting at senior management level. IBM Seven Keys to Success 1. Stake holders are committed 2. Business benefits are being realized 3. Work and Schedule are predictable 4. Scope is realistic and manageable 5. Team is high performing 13|P a g e 6. Risks are being mitigated Application of Select Tools of Psychology for Effective Project Management 7. Delivery organization benefits are being realized
  • 14.
    Project Management NationalConference 2011 PMI India The program is on schedule; however the costs overshot by approx 13 %. The main reasons for costs to increase were • The additional effort and travel for face to face workshops on getting the business requirements articulated to the level of granularity. • Procurement of high / niche skilled expensive resources for solution and design. • Organization change management activities Organization readiness to accept such a large change required significant amount of OCM activity. The change agents were identified as sponsors in top management, advocates in senior execs & business heads, change process owners and coaches in the middle management The program has engaged specialist services for carrying out OCM activities. The change was mainly occurring from • Large scale business process transformation (from local to global) • New organization design and changes in roles • Skill gaps for managing future organization The main deliverables were • Future Org design A five step approach for developing future org design was adopted • Document and assess ‘As Is’ org. 14|P a g e Application of Select Tools of Psychology for Effective Project Management
  • 15.
    Project Management NationalConference 2011 PMI India • Envision ‘To Be’ org. • Design ‘To Be’ org. and Job roles • Define Skills and Competencies to close Gaps in ‘As Is’ – ‘To Be ‘ , map roles • Create plans to resolve gaps Business Strategy Future Organization & Process State Current People State Organizational Change Management Information Technology Fig -4: Factors impacting Future Org design • Communication A communication plan was developed based on communication need analysis for the organization. The plan detailed what needs to be communicated by whom and when. It also listed the medium of communication. Various types of communication material were developed. Communication was routed through key stake holders /change agents for appropriate impact. • Training Training need analysis was carried out. Based on requirement for various user groups, multiple types of training materials were developed and delivered. The super users were also sent for SAP training, prior to involvement in users’ acceptance testing. Learning Labs and Classroom trainings were organized. Computer based simulations were prepared for complex transactions. Web lectures and web pages providing information about new processes and tools were prepared and made available to the users to be accessed at their own time . 15|P a g e Application of Select Tools of Psychology for Effective Project Management
  • 16.
    Project Management NationalConference 2011 PMI India An organization readiness check point included completion of trainings to various user groups prior to go live 5 Key Challenges / Risks Managed The following were a few of the key risks experienced and managed in this engagement • Business process owners experienced difficulty in articulating requirements, since the processes were getting globally aligned for the first time in the organization. The processes owners were familiar with the local business requirements. Use of agile methodology was of some help to address this issue. Requirement Traceability Verification Matrix was of help in articulating requirements. • Where the process definition was incomplete or flawed, it created issues of acceptance by the users at the exit point. Program management tried defining Exit and Entry criteria with as much clarity as possible. • SAP solutions being implemented did not address all the requirements from the business. Additional budget and time were required for unplanned development work. The following are the reasons for the additional development work o There were business scenarios / requirements where the SAP solutions did not meet the business need and required customization. o There were SAP solutions which were not tried earlier and required some amount of customization. SAP time lines of delivering these changes did not support the project time lines and project had to bear the expenses for developing the solution o The right expertise to implement a few desired solutions was not accessible as required to meet the project time lines. • Low data quality created issues for migration and reconciliation in production since it was the first time the globally distributed (multiple applications) data was migrated in a single database and global data standards were implemented. 16|P a g e Application of Select Tools of Psychology for Effective Project Management
  • 17.
    Project Management NationalConference 2011 PMI India • A few weak configurable controls / access controls and/or Separation of Duties allowed errors and audit exposure. New roles at different levels were getting created for the first time as per the future org design scenario. • Very high volumes of users caused system to be unstable. This was especially true immediately after the roll outs / releases since more number of users (out of curiosity than normally as planned ) logged in and users spent more than required time (since they were learning to use the new application ) on the application . • System exited (went live) with some known or unknown problems due to oversight in testing and/or decisions made around Exit criteria. The users signing exit criteria found it difficult to understand process & technology transformation from local to global. The stay of hyper-care team was extended from planned 30 days to 45 days. Additional costs were picked up by the project • Multiple regulatory compliances brought in additional challenges for program management team since this transformation involved multiple countries, business units and applications. These compliance included o Data Privacy laws o Visa and work permits o Union agreements o Global trade practices and restrictions o Audits like SOX, Client specific , Service provider specific o Intellectual property protection • Management of diverse global delivery teams in virtual environments threw up additional challenges. A global and virtual team was best suited to this program since the complexity and diversity of the required skill sets dictated to bring on board variety of resources. Best in class resources were required for design and solution and could be picked up from any where and the most cost effective for routine operations. The team scaled up to approx 1000 resources during peak period. 17|P a g e Application of Select Tools of Psychology for Effective Project Management
  • 18.
    Project Management NationalConference 2011 PMI India The program spent additional money for o Additional communication time and infrastructure for virtual working. o Travel costs for face to face meetings and workshops o Cultural sensitivity trainings 6 Critical success factor In order to achieve the envisaged business benefits and make program successful, the following are considered as Critical Success Factors • Strong, active executive committee that demonstrates visible sponsorship of the project • Visible organizational commitment to make significant process and organizational changes, resulting in targeted benefits realization. • Dedicated, empowered project team able to make rapid decisions on behalf of business units • Country buy-in and accountability for results, especially for such large global implementation involving multiple countries. • Rigorous scope management process to limit modifications to standard SAP functionality and to keep scope within original estimates • Common enterprise level design, with limited process and configuration changes during the rollout/ releases of the project • Rapid decision making and issue resolution procedures, coupled with prompt escalation and resolution of critical business issue • Benefits Realization as an integral part of the Project, not a follow-on or collateral activity • Change management and organizational alignment processes in place to make the organization ready to accept change. 18|P a g e Application of Select Tools of Psychology for Effective Project Management
  • 19.
    Project Management NationalConference 2011 PMI India • Clear, concise, relevant, and actionable performance measures directly linked to each element of the business case and visible to all levels of the organization • One integrated team with clearly defined program objectives, goals, and timeline. 7 Best Practices The following are some of the best Practices implemented in the program • Establishment of the CoE / CoC .- A CoE was set up with the following objectives o CoE enables development of the required skills, development and upkeep of reusable assets thus bringing down the costs for the program o The location of the CoE was carefully selected considering costs and availability of required skills o The CoE charter includes that • All key resources are strategically part of the center. • The key deliverables of the program are owned by the center. • Implement best practices • Established ‘Core and Flexi team’ model o In order to optimize costs and delivery capabilities, a core and flexi team model has been adopted. This addresses resource requirements to meet ‘peaks and troughs’ o The critical skills are retained in the program as core team. These resources are usually on the leadership roles or posses niche skills. The flexi team is brought in on ‘as required basis ’. o The core team is highly skilled and is well versed in client specific business requirements. This team can guide / lead the flexi team. The flexi team is brought up to required skill levels by the core team through 19|P a g e Application of Select Tools of Psychology for Effective Project Management
  • 20.
    Project Management NationalConference 2011 PMI India an ‘on boarding’ process which include training in client specific processes and methods • Created reusable assets and assigned asset ownership A large number of reusable assets were created / being created. A process to continuously improve upon the existing reusable assets and skills based on the lessons learnt has been established. This process helps to meet the planned productivity improvement in the business case. The program management assets are o Templates - development, configuration, testing, communication etc. o Processes – engagement, change management, issues and risk management, decision making, o Physical assets - testing rooms, virtual Private networks, severs . o Soft ware Programs – configuration documentation , RICEFW programs (Reports , Interfaces, Conversions, Enhancements , Forms and workflows ) o Project Plans – Engagement & delivery, development, testing, cutover. o Test scripts , Data migration processes o Business Process Procedures – Global processes, desk top procedures. o Technical architect diagrams. • Prepared business continuity / Disaster Recovery. The client servers are hosted in a data center which has built up geographically dispersed back up to ensure continuity in case of any disaster / eventuality like earth quake /floods or damage due war / terrorist strikes. • Assigned data elements ownership – Each data element was assigned an owner. The owner was normally a business process owner, who dealt with the specific data element as part of his normal duties. He was responsible of ensuring that the clean data is provided for upload and after conversion, validate that data is correctly reflected in the new SAP system. 20|P a g e Application of Select Tools of Psychology for Effective Project Management
  • 21.
    Project Management NationalConference 2011 PMI India • Preparation of Check lists - Check lists defining entry & exit criteria for all major milestones were prepared. A check list for meeting Go Live criteria is listed below as an example. Go Live Check List Completion of all major test activities SIT: Signoff complete UAT: Signoff complete Performance Test: Test complete Data Cleanup and Data Migration Data verification signoff complete Activities Data validation and correction Complete Execution of users’ transition plan OCM roadmap execution in progress as per plan Bubble staff in place Completion of LCM Preparedness LCM staff in place Plan Knowledge transfer Complete Sustain Readiness Exit criteria met Execution of Cutover Plan Production verification Confirmed Dry run Complete Failover plan in place Operational Readiness Documentation in place Hypercare support in place Technical Readiness Hardware in place; System build Complete Network upgrade complete Interface batch Scheduling/monitoring/performance complete Other Criteria Required for Go Live Disaster recovery plan confirmed Audit certification received 8 Business Benefits Realization The realized business benefits were measured in line with business case commitments. In addition to the global process alignment, there were tangible as well as intangible benefits. All tangible benefits were measured and reflected in quantities. Assessment about intangible benefits like increased employee morale, company branding etc. was also made. This exercise confirmed that the program was meeting the business case objectives and is in line with business leadership’s strategic vision Key benefits achieved are mentioned below 21|P a g e Application of Select Tools of Psychology for Effective Project Management
  • 22.
    Project Management NationalConference 2011 PMI India Benefit Source Metrics System Sunset Number of systems / interfaces sunset / Number of Systems / interfaces partly sunset sunset Resource Savings Resource Costs Number of FTEs redeployed Contract Savings Number of external support vendors Number of external venders’ reduced / activities curtailed Control Points saving Redundant Control Points Number of control points reduced Automated Control Points Staff Efficiency & Transaction Time Reduction in Transaction process Productivity Iterations time Reduction in Iteration Cost savings The amount spent on the system to The difference between the support business amounts spent prior and post transformation with details of contributing factors. 9 Lessons learnt • Requirement of right skills - The requirement of right skills is critical for such a large transformation program. These skills are required across the domains like engagement, business, application, architect and organization change management. Right service provider, where these skills are available needs to be brought in to steer such programs right at the outset • The business finds very difficult to provide the requirements in the requirement gathering phase. Despite trainings, some gaps do remain with business teams to provide end to end process information and also understand 'to be' processes. Hence changes in business requirements do come up during testing and even later part of the project. Methodologies like Agile and artifacts like ‘Requirement Traceability and Verification matrix’ are of help. • Program managers need to effectively monitor changes in the scope. A few slippages could result in additional work for months. On the other hand, missing on a few critical business requirements could make the developed 22|P a g e Application of Select Tools of Psychology for Effective Project Management
  • 23.
    Project Management NationalConference 2011 PMI India application inadequate for business to accept or may require an expensive work-around. • The change management process followed at the project involved mandatory assessment by all domains. The response from all domains delays processing of CRs .To expedite the approval process , CRs should be taken for approval after preliminary assessment by relevant domains and should be send to all domains for concurrence after approval. • Early involvement of users’ and sustain team members help reduce overall users’ acceptance testing and transition to sustain time • Data quality and application of global data standards to multiple local systems can create major data consistency issues. Assignment of data ownership to the right business process owner to validate the data is of help to get the right quality of data in to the system. 10 Conclusion Many multinationals are integrated businesses across geographies and business units to realize their strategic business objectives of rapidly responding to global marketplace and significantly reducing operations costs. The ERP packages provide technology platform to support such initiatives. Program managing such complex transformation initiatives throw multiple additional challenges. The Program Managers require high levels of skills of effectively communicating to virtual teams across diverse cultures, negotiating successfully , solving complex issues, providing leadership , managing relationship across multiple levels, managing ambiguity, demonstrating sound business Judgment and technical acumen to successfully deliver these envisaged business benefits to the clients, on time and with in budget 23|P a g e Application of Select Tools of Psychology for Effective Project Management
  • 24.
    Project Management NationalConference 2011 PMI India 11 Author’s Profile Sachdeepak is IBM certified Senior Project Manager and Certified SAP Consultant He has successfully managed complex and high valued IT /SAP business transformation Projects like Global SAP Implementation & Support and business transformation on SAP for one of the largest global IT Companies . He set up operations support and development of interfaces in WBI suite, managed Siebel implementation & support and Implementation of SAP in Uniliver Ltd. He managed ECC 5.0 upgrade, SAP releases and rollouts for Ericsson, while working in Stockholm. He led Implementation of SAP HR for Rohm & Haas, 3Com (while working in the US) & for L & T group of companies. He spearheaded automation of Airmen and Officers’ recruitment and selection processes for Indian Air Force In addition, to his delivery roles, Sachdeepak is a trainer and a certified instructor for Project Management and Project Financial and also a reviewer and mentor for PMs seeking Senior PM Certifications in IBM. 24|P a g e Application of Select Tools of Psychology for Effective Project Management
  • 25.
    Project Management NationalConference 2011 PMI India He holds MBA and M. Phil. (Org Mgt ) degrees and have published and presented papers on Project Management in system integration & application development at various forums like SAP Tech Ed, Society of PM Japan and PMI Chapter, Bangalore. sacarora@in.ibm.com , sdsarora@hotmail.com 25|P a g e Application of Select Tools of Psychology for Effective Project Management