SlideShare a Scribd company logo
1 of 19
Download to read offline
KOLKATA
METRO
PROJECT,
NOAPARA,
DUMDUM
By
Mayukh Bhattacharjee
1221010041, 3rd year
Civil Infrastructure
• I sincerely thank SENBO CONSTRUCTIONS for giving me a the
opportunity to do my training in their esteemed firm.
• Mr. Partha Chakrabharty, Vice- President ( SENBO CONSTRUCTIONS)
for assigning me into the training.
• Mr. Prantik Bhowmick, Project Manager ( Metro rail
constructions,Noapara) for guiding and helping me out with every
aspect during my training.
• Mr. S. Nanda for his support in making of the project report.
INTRODUCTIONS-
BASIC BRIDGE TERMS
SUPERSTRUCTURE: The superstructure consists of the components that actually span the
obstacle the bridge is intended to cross and includes the following:
1) Bridge deck
2) Structural members
3) Parapets (bridge railings), handrails, sidewalk, lighting and some drainage features
The deck is the roadway portion of a bridge, including shoulders. Most bridge decks are
constructed as reinforced concrete slabs, but timber decks are occasionally used in rural areas
and open-grid steel decks are used in some movable bridge designs (bascule bridge).
Secondary members called diaphragms are used as cross-braces between
the main structural members and are also part of the superstructure.
A bridge deck is usually supported by structural members. The most common types are-
1) Steel I-beams and girders
2) Precast, prestressed, reinforced concrete bulb T beams
3) Precast, prestressed, reinforced concrete I beams
4) Precast, prestressed, concrete box beams
5) Reinforced concrete slabs
SUBSTRUCTURE: The substructure consists of all of the parts that support the superstructure.
The main components are abutments or end-bents, piers or interior bents, footings, and
piling.
PIERS
Piers are of: ➢Solid pier ➢Single column pie ➢Cellular pier ➢Trestle piers
➢Hammer head piers
Pier consist of three parts- 1) Pier shaft 2) Pier head 3) Pier cap
In this project hammerhead piers are used. The piers are casted over pile cap.
As from metro rail order M45 grade of concrete is used.
Load on piers- live load of metro, wind forces, longitudinal forces owing to
braking effect, seismic effect, forces owing to collision.
In this project 2 metres diameter in each pier are used. On top having
hammerhead, above that pedestal which is needed a minimum curing &
setting time after constructing. Above the pedestal bearing plate are placed,
on which girders are fix.
GIRDER
The determination of the forces becomes simple since each track is carried by
a pair of girders, spanned by the deck slab as they are assumed to act only as
stiffeners to the girders. End diaphragms are designed to take up secondary forces
that will be induced due to differential prestressing in girders.
The shorter due concrete spans are provided with one pair of girders per track or
a number of T beam and slabs placed side by side. In the matter case, the
distribution of load between the girders is decided by using one of the standard
methods evolved and mentioned subsection
MAYUKH PRESENTATION
MAYUKH PRESENTATION
MAYUKH PRESENTATION
MAYUKH PRESENTATION
MAYUKH PRESENTATION
MAYUKH PRESENTATION
MAYUKH PRESENTATION
MAYUKH PRESENTATION
MAYUKH PRESENTATION
MAYUKH PRESENTATION

More Related Content

What's hot

Samuel beckett bridge
Samuel beckett bridge Samuel beckett bridge
Samuel beckett bridge
Dhruv Seth
 
Updated_Work_Profile_29-09-15
Updated_Work_Profile_29-09-15Updated_Work_Profile_29-09-15
Updated_Work_Profile_29-09-15
Chandan Singh
 
SSRC Presentation of Telmo Andres Sanchez
SSRC Presentation of Telmo Andres SanchezSSRC Presentation of Telmo Andres Sanchez
SSRC Presentation of Telmo Andres Sanchez
Eva Lantsoght
 
Calculation note suez canal cable stayed bridge
Calculation note suez canal cable stayed bridgeCalculation note suez canal cable stayed bridge
Calculation note suez canal cable stayed bridge
Mohammed Abdelkawy
 
STUDY ON VARIATION OF JOINT FORCES IN STIFFENING TRUSS OF CABLE-STAYED BRIDGE
STUDY ON VARIATION OF JOINT FORCES IN STIFFENING TRUSS OF CABLE-STAYED BRIDGESTUDY ON VARIATION OF JOINT FORCES IN STIFFENING TRUSS OF CABLE-STAYED BRIDGE
STUDY ON VARIATION OF JOINT FORCES IN STIFFENING TRUSS OF CABLE-STAYED BRIDGE
AELC
 

What's hot (20)

Samuel beckett bridge
Samuel beckett bridge Samuel beckett bridge
Samuel beckett bridge
 
Updated_Work_Profile_29-09-15
Updated_Work_Profile_29-09-15Updated_Work_Profile_29-09-15
Updated_Work_Profile_29-09-15
 
SSRC Presentation of Telmo Andres Sanchez
SSRC Presentation of Telmo Andres SanchezSSRC Presentation of Telmo Andres Sanchez
SSRC Presentation of Telmo Andres Sanchez
 
Bridges
Bridges Bridges
Bridges
 
BALANCED CANTILEVER BRIDGE
BALANCED CANTILEVER BRIDGEBALANCED CANTILEVER BRIDGE
BALANCED CANTILEVER BRIDGE
 
Bridge construction atlas
Bridge construction atlasBridge construction atlas
Bridge construction atlas
 
Calculation note suez canal cable stayed bridge
Calculation note suez canal cable stayed bridgeCalculation note suez canal cable stayed bridge
Calculation note suez canal cable stayed bridge
 
Training Report on Bridge Construction
Training Report on Bridge ConstructionTraining Report on Bridge Construction
Training Report on Bridge Construction
 
Bridge construction methods aug 2007
Bridge construction methods aug 2007Bridge construction methods aug 2007
Bridge construction methods aug 2007
 
Segmental bridge
Segmental bridgeSegmental bridge
Segmental bridge
 
Cable and suspension bridge
Cable and suspension bridge Cable and suspension bridge
Cable and suspension bridge
 
Cable stayed bridges of prestressed concrete.
Cable stayed bridges of prestressed concrete.Cable stayed bridges of prestressed concrete.
Cable stayed bridges of prestressed concrete.
 
BOGIBEEL BRIDGE
BOGIBEEL BRIDGEBOGIBEEL BRIDGE
BOGIBEEL BRIDGE
 
Cable Stay Bridge construction at Bardhman using LARSA and LUSAS four dimensi...
Cable Stay Bridge construction at Bardhman using LARSA and LUSAS four dimensi...Cable Stay Bridge construction at Bardhman using LARSA and LUSAS four dimensi...
Cable Stay Bridge construction at Bardhman using LARSA and LUSAS four dimensi...
 
STUDY ON VARIATION OF JOINT FORCES IN STIFFENING TRUSS OF CABLE-STAYED BRIDGE
STUDY ON VARIATION OF JOINT FORCES IN STIFFENING TRUSS OF CABLE-STAYED BRIDGESTUDY ON VARIATION OF JOINT FORCES IN STIFFENING TRUSS OF CABLE-STAYED BRIDGE
STUDY ON VARIATION OF JOINT FORCES IN STIFFENING TRUSS OF CABLE-STAYED BRIDGE
 
Segmental bridge construction
Segmental bridge constructionSegmental bridge construction
Segmental bridge construction
 
Viaduct
Viaduct Viaduct
Viaduct
 
Presentation on construction of cable stay bridge - a modern technique for su...
Presentation on construction of cable stay bridge - a modern technique for su...Presentation on construction of cable stay bridge - a modern technique for su...
Presentation on construction of cable stay bridge - a modern technique for su...
 
Uses of Larsa 4 d and Lusas 4 D models for Implementation of Cable Stayed ...
Uses of Larsa   4 d and Lusas  4 D models for Implementation of Cable Stayed ...Uses of Larsa   4 d and Lusas  4 D models for Implementation of Cable Stayed ...
Uses of Larsa 4 d and Lusas 4 D models for Implementation of Cable Stayed ...
 
Suspension bridge
Suspension bridgeSuspension bridge
Suspension bridge
 

Similar to MAYUKH PRESENTATION

Running Head BRIDGE DESIGN1BRIDGE DESIGN31.docx
Running Head BRIDGE DESIGN1BRIDGE DESIGN31.docxRunning Head BRIDGE DESIGN1BRIDGE DESIGN31.docx
Running Head BRIDGE DESIGN1BRIDGE DESIGN31.docx
toddr4
 
4. STUDY ONVARIATION OF JOINT FORCES IN STEEL TRUSS BRIDGE
4.	STUDY ONVARIATION OF JOINT FORCES IN STEEL TRUSS BRIDGE4.	STUDY ONVARIATION OF JOINT FORCES IN STEEL TRUSS BRIDGE
4. STUDY ONVARIATION OF JOINT FORCES IN STEEL TRUSS BRIDGE
AELC
 

Similar to MAYUKH PRESENTATION (20)

Prestressed Concrete Bridge.pptx
Prestressed Concrete Bridge.pptxPrestressed Concrete Bridge.pptx
Prestressed Concrete Bridge.pptx
 
Bridge-SIT-01.pptx
Bridge-SIT-01.pptxBridge-SIT-01.pptx
Bridge-SIT-01.pptx
 
Running Head BRIDGE DESIGN1BRIDGE DESIGN31.docx
Running Head BRIDGE DESIGN1BRIDGE DESIGN31.docxRunning Head BRIDGE DESIGN1BRIDGE DESIGN31.docx
Running Head BRIDGE DESIGN1BRIDGE DESIGN31.docx
 
Bridge-SGI-01_Pranoti.pdf
Bridge-SGI-01_Pranoti.pdfBridge-SGI-01_Pranoti.pdf
Bridge-SGI-01_Pranoti.pdf
 
ANALYSIS OF PRE-STRESSED BRIDGE CONSTRUCTION
ANALYSIS OF PRE-STRESSED BRIDGE CONSTRUCTIONANALYSIS OF PRE-STRESSED BRIDGE CONSTRUCTION
ANALYSIS OF PRE-STRESSED BRIDGE CONSTRUCTION
 
Bhupen hazarika setu
Bhupen hazarika setuBhupen hazarika setu
Bhupen hazarika setu
 
stress ribbon bridge.pptx
stress ribbon bridge.pptxstress ribbon bridge.pptx
stress ribbon bridge.pptx
 
Bandra Worli sea link
Bandra Worli sea linkBandra Worli sea link
Bandra Worli sea link
 
Tony
TonyTony
Tony
 
Larsen and Toubro (Lucknow Metro Project) Summer Internship Presentation
Larsen and Toubro (Lucknow Metro Project) Summer Internship PresentationLarsen and Toubro (Lucknow Metro Project) Summer Internship Presentation
Larsen and Toubro (Lucknow Metro Project) Summer Internship Presentation
 
Cast in situ bridge superstracture
Cast in situ bridge superstractureCast in situ bridge superstracture
Cast in situ bridge superstracture
 
Ijciet 08 02_040
Ijciet 08 02_040Ijciet 08 02_040
Ijciet 08 02_040
 
Training
TrainingTraining
Training
 
Gaurav-Jhalani-Seminar-ppt.pptx
Gaurav-Jhalani-Seminar-ppt.pptxGaurav-Jhalani-Seminar-ppt.pptx
Gaurav-Jhalani-Seminar-ppt.pptx
 
suspension bridge ppt
suspension bridge pptsuspension bridge ppt
suspension bridge ppt
 
Construction Of A Viaduct/Bridge: An Overview
Construction Of A Viaduct/Bridge: An OverviewConstruction Of A Viaduct/Bridge: An Overview
Construction Of A Viaduct/Bridge: An Overview
 
AMANRAWAT 2.pptx
AMANRAWAT 2.pptxAMANRAWAT 2.pptx
AMANRAWAT 2.pptx
 
MODULE-IV INFRASTRUCTURE ENGINEERING BTCVC702
MODULE-IV INFRASTRUCTURE ENGINEERING BTCVC702MODULE-IV INFRASTRUCTURE ENGINEERING BTCVC702
MODULE-IV INFRASTRUCTURE ENGINEERING BTCVC702
 
4. STUDY ONVARIATION OF JOINT FORCES IN STEEL TRUSS BRIDGE
4.	STUDY ONVARIATION OF JOINT FORCES IN STEEL TRUSS BRIDGE4.	STUDY ONVARIATION OF JOINT FORCES IN STEEL TRUSS BRIDGE
4. STUDY ONVARIATION OF JOINT FORCES IN STEEL TRUSS BRIDGE
 
Bridges in Hilly areas seminar
Bridges in Hilly areas seminarBridges in Hilly areas seminar
Bridges in Hilly areas seminar
 

MAYUKH PRESENTATION

  • 2. • I sincerely thank SENBO CONSTRUCTIONS for giving me a the opportunity to do my training in their esteemed firm. • Mr. Partha Chakrabharty, Vice- President ( SENBO CONSTRUCTIONS) for assigning me into the training. • Mr. Prantik Bhowmick, Project Manager ( Metro rail constructions,Noapara) for guiding and helping me out with every aspect during my training. • Mr. S. Nanda for his support in making of the project report.
  • 3.
  • 4.
  • 5. INTRODUCTIONS- BASIC BRIDGE TERMS SUPERSTRUCTURE: The superstructure consists of the components that actually span the obstacle the bridge is intended to cross and includes the following: 1) Bridge deck 2) Structural members 3) Parapets (bridge railings), handrails, sidewalk, lighting and some drainage features The deck is the roadway portion of a bridge, including shoulders. Most bridge decks are constructed as reinforced concrete slabs, but timber decks are occasionally used in rural areas and open-grid steel decks are used in some movable bridge designs (bascule bridge). Secondary members called diaphragms are used as cross-braces between the main structural members and are also part of the superstructure. A bridge deck is usually supported by structural members. The most common types are- 1) Steel I-beams and girders 2) Precast, prestressed, reinforced concrete bulb T beams 3) Precast, prestressed, reinforced concrete I beams 4) Precast, prestressed, concrete box beams 5) Reinforced concrete slabs SUBSTRUCTURE: The substructure consists of all of the parts that support the superstructure. The main components are abutments or end-bents, piers or interior bents, footings, and piling.
  • 6.
  • 7. PIERS Piers are of: ➢Solid pier ➢Single column pie ➢Cellular pier ➢Trestle piers ➢Hammer head piers Pier consist of three parts- 1) Pier shaft 2) Pier head 3) Pier cap In this project hammerhead piers are used. The piers are casted over pile cap. As from metro rail order M45 grade of concrete is used. Load on piers- live load of metro, wind forces, longitudinal forces owing to braking effect, seismic effect, forces owing to collision. In this project 2 metres diameter in each pier are used. On top having hammerhead, above that pedestal which is needed a minimum curing & setting time after constructing. Above the pedestal bearing plate are placed, on which girders are fix.
  • 8.
  • 9. GIRDER The determination of the forces becomes simple since each track is carried by a pair of girders, spanned by the deck slab as they are assumed to act only as stiffeners to the girders. End diaphragms are designed to take up secondary forces that will be induced due to differential prestressing in girders. The shorter due concrete spans are provided with one pair of girders per track or a number of T beam and slabs placed side by side. In the matter case, the distribution of load between the girders is decided by using one of the standard methods evolved and mentioned subsection