SlideShare a Scribd company logo
1 of 299
Download to read offline
Dr. Karim El-Dash
1
	
TRAINING	PROGRAM	
MANAGING	
MULTIPLE	PROJECTS	
PRESENTED	BY:	
KARIM	EL‐DASH;	PHD;	PMP;	CCE;	AVS;	ACIArb	
March 2012 
Dr. Karim El-Dash
2
Contents	
PROJECT MANAGEMENT .................................................................................................................................... 5 
PROJECT MANAGEMENT OFFICE ........................................................................................................................ 6 
ROLE OF A PROJECT MANAGER .......................................................................................................................... 6 
PROJECT LIFE‐CYCLE ........................................................................................................................................... 8 
PROJECT SELECTION .......................................................................................................................................... 10 
ESTIMATE CLASSIFICATIONS .............................................................................................................................. 10 
PHYSICAL DIMENSIONS METHOD ................................................................................................................................... 11 
COMPOUND‐AMOUNT FACTOR ..................................................................................................................................... 12 
COMPOUND‐AMOUNT FACTOR: .................................................................................................................................... 13 
INTERNAL RATE OF RETURN .......................................................................................................................................... 15 
THREE‐POINT ESTIMATES ............................................................................................................................................. 18 
ORGANIZATIONAL PROJECT MANAGEMENT MATURITY MODEL ........................................................................... 20 
CAPABILITY MATURITY MODEL INTEGRATED ......................................................................................................... 22 
PROJECT CHARTER ............................................................................................................................................ 24 
COLLECT PROJECT REQUIREMENTS .................................................................................................................................. 24 
DEFINE PROJECT SCOPE ................................................................................................................................................ 24 
CREATE PROJECT WBS ................................................................................................................................................. 25 
DEFINE ACTIVITIES ....................................................................................................................................................... 26 
SEQUENCE ACTIVITIES .................................................................................................................................................. 29 
ESTIMATE ACTIVITY RESOURCES ..................................................................................................................................... 31 
ESTIMATE ACTIVITY DURATION ...................................................................................................................................... 32 
DEVELOP SCHEDULE .................................................................................................................................................... 35 
ESTIMATE COST .......................................................................................................................................................... 42 
CONTROL COST ................................................................................................................................................. 47 
PROJECT QUALITY MANAGEMENT ..................................................................................................................... 57 
COST‐BENEFIT ANALYSIS ............................................................................................................................................... 59 
COST OF QUALITY ........................................................................................................................................................ 59 
OPTIMUM QUALITY COST MODEL .................................................................................................................................. 65 
CONTROL CHARTS ....................................................................................................................................................... 67 
BENCHMARKING ......................................................................................................................................................... 72 
DESIGN OF EXPERIMENTS .............................................................................................................................................. 75 
STATISTICAL SAMPLING ................................................................................................................................................ 77 
FLOWCHARTING .......................................................................................................................................................... 78 
PROPRIETARY QUALITY MANAGEMENT METHODOLOGIES ..................................................................................................... 81 
SIX SIGMA ................................................................................................................................................................. 81 
LEAN SIX SIGMA ......................................................................................................................................................... 83 
TOTAL QUALITY MANAGEMENT ..................................................................................................................................... 84 
QUALITY FUNCTION DEPLOYMENT ........................................................................................................................ 88 
PROCESS IMPROVEMENT PLAN ...................................................................................................................................... 91 
Dr. Karim El-Dash
3
QUALITY ASSURANCE ................................................................................................................................................... 93 
QUALITY AUDITS ......................................................................................................................................................... 94 
QUALITY CONTROL ...................................................................................................................................................... 96 
HISTOGRAM ............................................................................................................................................................... 98 
CREATING A HISTOGRAM .............................................................................................................................................. 98 
RUN CHART ............................................................................................................................................................. 105 
SCATTER DIAGRAM .................................................................................................................................................... 109 
INSPECTION.............................................................................................................................................................. 113 
PROJECT HUMAN RESOURCE MANAGEMENT .................................................................................................. 115 
DEVELOP HR PLAN .................................................................................................................................................... 115 
ACQUIRE PROJECT TEAM ............................................................................................................................................ 129 
DEVELOP PROJECT TEAM ............................................................................................................................................ 129 
LEADERS AGAINST MANAGERS ..................................................................................................................................... 133 
MANAGE PROJECT TEAM ............................................................................................................................................ 141 
PROJECT COMMUNICATION MANAGEMENT ................................................................................................... 148 
IDENTIFY STAKEHOLDERS ............................................................................................................................................ 148 
PLAN COMMUNICATION ............................................................................................................................................. 151 
COMMUNICATION TECHNOLOGY .................................................................................................................................. 154 
COMMUNICATION MODELS ......................................................................................................................................... 155 
COMMUNICATION METHODS ....................................................................................................................................... 156 
MANAGE STAKEHOLDER EXPECTATIONS ........................................................................................................................ 161 
PROJECT RISK MANAGEMENT ......................................................................................................................... 166 
PLAN RISK MANAGEMENT .......................................................................................................................................... 166 
IDENTIFY RISK ........................................................................................................................................................... 172 
PERFORM QUALITATIVE RISK MANAGEMENT .................................................................................................................. 180 
PERFORM QUANTITATIVE RISK MANAGEMENT ............................................................................................................... 185 
PLAN RISK RESPONSES ............................................................................................................................................... 190 
MONITOR & CONTROL RISKS ...................................................................................................................................... 197 
PROJECT PROCUREMENT MANAGEMENT ........................................................................................................ 198 
PLAN PROCUREMENTS ................................................................................................................................................ 198 
CONTRACT PROCUREMENTS ........................................................................................................................................ 212 
CLOSE PROCUREMENTS .............................................................................................................................................. 219 
MANAGING MULTIPLE PROJECTS .................................................................................................................... 220 
OVERVIEW ............................................................................................................................................................ 220 
PMO AND ORGANIZATIONAL STRUCTURE ........................................................................................................... 238 
CUSTOMER MANAGEMENT ................................................................................................................................. 252 
COMMUNICATION MANAGEMENT ...................................................................................................................... 253 
PROJECT OFFICE MANAGEMENT .......................................................................................................................... 256 
KNOWLEDGE MANAGEMENT ............................................................................................................................... 262 
PROJECT MANAGEMENT TRAINING ..................................................................................................................... 269 
PROJECT RESOURCE MANAGEMENT .................................................................................................................... 271 
Dr. Karim El-Dash
4
PROJECT SELECTION ............................................................................................................................................. 275 
PROGRAM MONITORING AND CONTROL ............................................................................................................. 287 
PROJECT AUDIT .................................................................................................................................................... 296 
Dr. Karim El-Dash
5
PROJECT MANAGEMENT
 Project management is the discipline of planning, organizing, and
managing resources to bring about the successful completion of
specific project goals and objectives.
 It is often closely related to and sometimes adjunct with program
management.
 A project is a temporary endeavor, having a defined beginning and
end (usually constrained by date, but can be by funding or
deliverables), undertaken to meet particular goals and objectives,
usually to bring about beneficial change or added value.
 The primary challenge of project management is to achieve all of the
project goals and objectives while honoring the predetermined project
constraints.
 Typical constraints are scope, time, and budget. The secondary—and
more striving —challenge is to optimize the allocation and integration
of inputs necessary to meet pre-defined objectives.
Dr. Karim El-Dash
6
Project Management Office
 The Project Management Office (PMO) in a business or professional
enterprise is the department or group that defines and maintains the
standards of process, generally related to project management, within
the organization.
 The PMO is the source of documentation, guidance and metrics on
the practice of project management and execution.
 A PMO can be one of three types from an organizational exposure
perspective:
1. enterprise PMO,
2. organizational (departmental) PMO, or
3. special–purpose PMO.
Role of a Project Manager
These three main responsibilities of a project manager are:
1. planning,
2. organizing, and
3. controlling.
Performing these responsibilities requires many skills. Some of these
necessary skills will be outlined.
1. Planning
 The planning function includes defining the project objective and
developing a plan to accomplish the objective.
 Working with the sponsor is beneficial in many ways. For example,
the sponsor is the person responsible for the resultant project and
thus has a stake in the success of the project.
 The project manager must also develop a plan to accomplish the
objective.
 The project manager should include project team members in this
phase.
Dr. Karim El-Dash
7
2. Organizing
 The organizing function involves identifying and securing necessary
resources, determining tasks that must be completed, assigning the
tasks, delegating authority, and motivating team members to work
together on the project.
 The project manager must then determine what tasks must be
completed.
 Once this has been done, the tasks should be assigned to project
team members or subcontractors.
 The project manager may also delegate authority to certain team
members to oversee task completion via supervision of those
assigned the tasks.
 Finally, the project manager must motivate members of the project
team to work together in order to complete the goal.
 Conflicts may arise and often will occur when individuals working
together come from departments with different goals.
3. Controlling
 The controlling function involves tracking progress and comparing it
with planned progress.
 Progress reports should be used to measure performance, as well as
identify areas for improvement.
Skills
Effective project managers must possess a variety of skills in addition to
general management skills. These skills include, but are not limited to:
 Analytical thinking: the ability to understand overall visions, as well as
minute details
 Leadership: the ability to inspire team members to execute the
plan and successfully complete the project
 Communication: the ability to communicate clearly, effectively, and
regularly
Dr. Karim El-Dash
8
 Interpersonal: the ability to develop a relationship with each team
member in order to know what motivates them, how
they think things are going, what concerns they have,
and how they feel about things
 Problem-Solving: the ability to anticipate problems, recognize them
when they arise, and solve them quickly and
efficiently
 Human resources: the ability to interview and choose team members
with the proper skills and knowledge
Project Life-Cycle
 A collection of generally sequential, non-
overlapping product phases whose
names and numbers are determined by
the executing and control needs of the
organization. The last product life cycle
phase for a product is generally the
product’s deterioration and death.
Generally, a project life cycle is contained
within one or more product life cycles.
 The project life cycle defines the
beginning and the end of a project and
various milestones within it.
 During the life cycle of a project there will be accomplishments made
at each phase. The completion of these accomplishments results in
the creation of a ‘‘deliverable,’’ a tangible, verifiable product of the
work being done on the project.
 These may be products that are delivered external to the project or
something needed for other project work to take place, which are
considered to be ‘‘internal deliverables.’’
Dr. Karim El-Dash
9
 In a project’s initial phase, cost and staffing levels are low. At this
phase there is the greatest chance that the project will never be
completed.
Project life-cycle
Influence-time relationship in projects
Dr. Karim El-Dash
10
PROJECT SELECTION
ESTIMATE CLASSIFICATIONS
Estimate classifications are commonly used to indicate the overall maturity
and quality for the various types of estimates that may be prepared; and
most organizations will use some form of classification system to identify
and categorize the various types of project estimates that they may prepare
during the life cycle of a project. Unfortunately, there is often a lack of
consistency and understanding of the terminology used to classify
estimates, both across industries as well as within single companies or
organizations.
AACE identifies five classes of estimates. A Class 5 Estimate is associated
with the lowest level of project definition, and a Class 1 Estimate is
associated with the highest level of project definition. The following table
shows the five classes of estimate.
Cost estimate classification
Dr. Karim El-Dash
11
PHYSICAL DIMENSIONS METHOD
The method uses the physical dimensions (length, area, volume, etc.) of
the item being estimated as the driving factor. For example, a building
estimate may be based on square meters or cubic meters of the building;
whereas pipelines, roadways, or railroads may be based on a linear basis.
This method depends on historical information from comparable facilities.
Consider the need to estimate the cost of a 3,600-m2
warehouse. A recently
completed warehouse of 2,900 m2
in a nearby location was recently
completed for KD 623,500, thus costing KD 215/m2
. The completed
warehouse utilized a 4.25-m wall height, thus containing 12,325 m3
and
resulting in a cost of $50.59/m3
on a volume basis ($623,500/12,325 m3
).
In determining the cost for the new warehouse, we can estimate the new
3,600 m2
warehouse using the m2
basis at $774,000 ($215/m2
x 3,600m2
).
However, the new warehouse will differ from the one just completed by
having 5.5-m-high walls; so we may decide that estimating on a volume
basis may provide a better indication of costs. The volume of the new
warehouse will be 19,800 m3
(3,600 m2
x 5.5m), and the new estimate will
be $1,002,000 (rounded to the nearest $1,000).
Pricing also includes adjustments to costs for specific project conditions.
Depending on the specific cost information used in preparing the estimate,
material costs may need to be adjusted for location, materials of
construction, or to account for differences between the item being installed
and the item you may have an available cost for. Labor hours may require
productivity adjustments for a variety of conditions such as weather,
amount of overtime, interferences from production, material logistics,
congestion, the experience of the labor crews, the level of contamination
control, etc. Labor rates may also need to be adjusted for location, crew
mix, open shop versus union issues, and specific benefit and burden
requirements.
Dr. Karim El-Dash
12
Example 1: Use the provided time index table to estimate the cost of a
building that contains 4,500 m2
of floor area. The
building is to be built two years from now. A building
that contains 6,800 m2
of floor area in a similar
location had a cost of KD 1,321,800 two years ago.
Solution:
Cost = Historical cost X size adjustment factor X Time
adjustment factor
Historical cost = KD 1,321,800
Size adjustment factor = 4,500/6,800 = 0.662
Time adjustment factor = (1+i)n
where;
i = inflation annual rate
n = number of years in difference
From historical data in table:
Time factor = 126/110 = (1+i)3
i = 0.046 = 4.6%
Time adjustment factor = (1+0.046)4
= 1.198
Estimated cost = KD 1,321,800 X 0.662 X 1.198 = KD 1,048,287
COMPOUND-AMOUNT FACTOR
Given a present sum P invested for N interest periods at interest rate i,
what sum will have accumulated at the end of the N periods? You probably
noticed right away that this description matches the case we first
encountered in describing compound interest. To solve for F (the future
sum); we use:
F = P (1 + i)N
Based on this equation a present value of $20,000 at interest rate of 12%
may be evaluated after 15 years by substitution in the equation as follows:
Year Index
3 years ago 110
2 years ago 120
1 year ago 128
Current year 126
Dr. Karim El-Dash
13
F = 20,000 (1 + 0.12)15
= $ 109,471
Because of its origin in the compound-interest calculation, the factor (1 +
i)
N
is known as the compound-amount factor. Like the concept of
equivalence, this factor is one of the foundations of engineering economic
analysis. Given this factor, all other important interest formulas can be
derived.
To specify how the interest tables are to be used, we may also express that
factor in a functional notation as (F/P, i, N), which is read as "Find F, given
P, i, and N." This factor is known as the single-payment compound-
amount factor. When we incorporate the table factor into the formula, the
formula is expressed as follows:
F = P (1+i)N
= P(F/P, i, N)
Thus, where we had F = $20,000(1.12)15
, we can now write F =
$20,000(F/P, 12%, 15). The table factor tells us to use the 12%-interest
table and find the factor in the F/P column for N = 15. Because using the
interest tables is often the easiest way to solve an equation, this factor
notation is included for each of the formulas derived in the upcoming
sections.
COMPOUND-AMOUNT FACTOR:
Find F, Given A, i, and W
Suppose we are interested in the future amount F of a fund to which we
contribute A dollars each period and on which we earn interest at a rate of i
per period. The contributions are made at the end of each of the N periods.
If an amount A is invested at the end of each period for N periods, the total
amount F that can be withdrawn at the end of N periods will be the sum of
the compound amounts of the individual deposits. This could be calculated
as per:
),,/(
1)1(
NiAFA
i
i
AF
N





 

Dr. Karim El-Dash
14
The following table shows the different statuses for discrete compounding
formulas with discrete payments.
Dr. Karim El-Dash
15
Example 2:
A feasibility study is being prepared for a project with KD 2,400,000 initial
cost and KD 360,000 equivalent uniform annual running cost. What is the
required net annual income to satisfy MARR of 15% return, assuming the
life-cycle of the project is 20 years?
Solution:
Assume the required annual income is Y:
Present value of accumulated annual income at discount rate 15% =
Present value of accumulated expenses at discount rate 15%
Y(P/A, 15%, 20) = 2,400,000 + 360,000 ((P/A, 15%, 20)
6.2593 Y = 2,400,000 + 360,000 * 6.2593
6.2593 Y = 4,653,348
Y = 743,429 KD/year
INTERNAL RATE OF RETURN
The internal rate of return (IRR) is the most difficult equation to calculate all
the cash flow techniques. It is a complicated formula and should be
performed on a financial calculator or computer. IRR can be figured
manually, but it’s a trial-and-error approach to get to the answer.
Technically speaking, IRR is the discount rate when the present value of
the cash inflows equals the original investment. When choosing between
projects or when choosing alternative methods of doing the project,
projects with higher IRR values are generally considered better than
projects with low IRR values.
Dr. Karim El-Dash
16
Example 3:
Compare the IRR for the shown data of projects A and B. Using PW
values. Assume that all expenses are incurred at the end of the year.
Assume discount rate; i=5%.
Project A Project B
Cash Flow Cash Flow
Year 1 (20,000) (10,000)
Year 2 (1,000) (4,000)
Year 3 5,000 3,000
Year 4 20,000 15,000
Solution:
Assume IRR=5% for both projects:
Project A Project B
PV@5% PV@5%
Year 1 (20,000) (10,000)
Year 2 (952) (3,810)
Year 3 4,535 2,721
Year 4 17,277 12,958
860 1,869
IRR > 5% for both projects
Dr. Karim El-Dash
17
Try IRR = 8%
Project A Project B
PV@8% PV@8%
Year 1 (20,000) (10,000)
Year 2 (926) (3,704)
Year 3 4,287 2,572
Year 4 15,877 11,907
(763) 776
IRR for Project A is less than 8%
IRR for Project B is more than 8%
By several trials it is found to have IRR for project A 6.5% and IRR for project B is
10.4%.
Dr. Karim El-Dash
18
THREE-POINT ESTIMATES
Three-point estimates, use three estimates that are averaged to come up
with a final estimate. The three estimates are the most likely, optimistic,
and pessimistic.
You’ll want to rely on experienced people to give you these estimates. The
most likely estimate assumes there are no disasters and the activity can be
completed as planned. The optimistic estimate is the fastest time frame in
which your resource can complete the activity. And the pessimistic estimate
assumes the worst happens and it takes much longer than planned to get
the activity completed. You’d average these three estimates to come up
with an overall estimate.
In this approach the mean and standard deviation are calculated as per the
following equations:
6
4 cpessimistilikelymostXoptimistic
Mean


6
deviationStandard
optimisticcpessimisti 

Dr. Karim El-Dash
19
Example 4:
It is required to estimate the cost of a parking deck with capacity of 550
cars. The following table shows the cost of eight decks with different
capacities adjusted for time and location. Using the three-point-estimate
method, find the expected cost of the parking deck.
Deck
Cost
KD
No. of
cars
Unit cost
KD/car
1 141,200 150
2 372,250 250
3 266,500 260
4 476,480 320
5 474,600 350
6 804,080 460
Solution:
Calculate unit cost/car for each deck:
Deck
Cost
KD
No. of cars
Unit cost
KD/car
1 141,200 150 1,358
2 372,250 250 1,489
3 266,500 260 1,025
4 476,480 320 1,489
5 474,600 350 1,356
6 804,080 460 1,748
Average unit cost /car =
6
748,1356,1489,1025,1489,1358,1 
=1410.8 KD/car
Minimum (optimistic) unit cost /car = 1,025 KD/car
Maximum (pessimistic) unit cost/car = 1,748 KD/car
Expected mean value =
6
748,18.410,1*4025,1 
= 1,402.7 KD/car
Total estimated cost of the deck = 1402 * 550 = 771,100 KD
Dr. Karim El-Dash
20
ORGANIZATIONAL PROJECT MANAGEMENT MATURITY
MODEL
The Organizational Project Management Maturity Model or OPM3 is a
globally recognized best-practice standard for assessing and developing
capabilities in Portfolio Management, Program Management, and Project
Management. It was published by the company Project Management
Institute Incorporated (PMI). OPM3 provides a method for organizations to
understand their Organizational Project Management processes and
measure their capabilities in preparation for improvement. OPM3 then
helps organizations develop the roadmap that the company will follow to
improve performance.
OPM3 covers the domains of Organizational Project Management, the
systematic management of projects, programs, and portfolios in alignment
with the achievement of strategic goals. Organizational Project
Management; the three domains are Project Management, Program
Dr. Karim El-Dash
21
Management and Portfolio Management. OPM3 uniquely integrates these
domains into one maturity model.
OPM3 offers the key to Organizational Project Management (OPM) with
three interlocking elements:
 Knowledge - Learn about hundreds of Organizational Project
Management (OPM) best practices.
 Assessment - Evaluate an organization’s current capabilities and
identify areas in need of improvement.
 Improvement - Use the completed assessment to map out the steps
needed to achieve performance improvement goals.
As with other PMI Inc. standards, OPM3’s intent is not to be prescriptive by
telling the user what improvements to make or how to make them. Rather,
OPM3 provides guidelines regarding the kinds of things an organization
may do in order to achieve excellence in Organizational Project
Management.
Dr. Karim El-Dash
22
CAPABILITY MATURITY MODEL INTEGRATED
Capability Maturity Model Integration (CMMI) is a process improvement
approach that helps organizations improve their performance. CMMI can
be used to guide process improvement across a project, a division, or an
entire organization.
CMMI in software engineering and organizational development is a
trademarked process improvement approach that provides organizations
with the essential elements for effective process improvement.
According to the Software Engineering Institute (SEI, 2008), CMMI helps
"integrate traditionally separate organizational functions, set process
improvement goals and priorities, provide guidance for quality processes,
and provide a point of reference for appraising current processes."
Dr. Karim El-Dash
23
CMMI currently addresses three areas of interest:
 Product and service development — CMMI for Development (CMMI-
DEV),
 Service establishment, management, and delivery — CMMI for
Services (CMMI-SVC), and
 Product and service acquisition — CMMI for Acquisition (CMMI-
ACQ).
CMMI was developed by a group of experts from industry, government, and
the Software Engineering Institute (SEI) at Carnegie Mellon University.
CMMI models provide guidance for developing or improving processes that
meet the business goals of an organization. A CMMI model may also be
used as a framework for appraising the process maturity of the
organization.
CMMI originated in software engineering but has been highly generalized
over the years to embrace other areas of interest, such as the development
of hardware products, the delivery of all kinds of services, and the
acquisition of products and services. The word "software" does not appear
in definitions of CMMI. This generalization of improvement concepts makes
CMMI extremely abstract.
Dr. Karim El-Dash
24
PROJECT CHARTER
The project charter is the written acknowledgment that the project exists.
The project charter names the project manager and gives that person the
authority to assign organizational resources to the project.
COLLECT PROJECT REQUIREMENTS
Requirements describe the characteristics of the project deliverables. They
might also describe functionality that the deliverable must have or specific
conditions the deliverable must meet in order to satisfy the objective of the
project. According to the PMBOK Guide, requirements are conditions that
must be met or criteria that the product or service of the project must
possess in order to satisfy the project documents, a contract, a standard, or
a specification. Requirements quantify and prioritize the wants, needs, and
expectations of the project sponsor and stakeholders. Requirements might
include elements such as dimensions, ease of use, color, specific
ingredients, and so on.
DEFINE PROJECT SCOPE
Project Scope Management encompasses both product scope and project
scope. Product scope concerns the characteristics of the product, service, or
result of the project. It’s measured against the product requirements to
determine successful completion or fulfillment. The application area usually
dictates the process tools and techniques you’ll use to define and manage
product scope. Project scope involves managing the work of the project and
only the work of the project. Project scope is measured against the project
management plan, the project scope statement, the work breakdown
structure (WBS), and the WBS dictionary.
Dr. Karim El-Dash
25
To ensure a successful project, both product and project scope must be
well integrated. This implies that Project Scope Management is well
integrated with the other Knowledge Area processes.
Scope Planning, Scope Definition, Create WBS, Scope Verification, and
Scope Control involve the following:
 Detailing the requirements of the product of the project
 Verifying those details using measurement techniques
 Creating a project scope management plan
 Creating a WBS
 Controlling changes to these processes
CREATE PROJECT WBS
The PMBOK Guide describes a WBS as “a deliverable-oriented hierarchical
decomposition of the work to be executed by the project team, to
accomplish the project objectives and create the required deliverables. The
Dr. Karim El-Dash
26
WBS defines the total scope of the project.” Simply put, a WBS is a
deliverable-oriented hierarchy that defines and organizes the work of the
project and only the work of the project. Like the scope statement, the WBS
serves as a foundational agreement among the stakeholders and project
team members regarding project scope.
The WBS will be used throughout many of the remaining Planning
processes and is an important part of project planning. The project charter
and project scope statement outline the project goals and major
deliverables. The project scope statement further refines these deliverables
into an exhaustive list and documents the requirements of the deliverables.
Project management team uses that comprehensive list of deliverables
produced in the project scope statement to build the framework of the
WBS.
DEFINE ACTIVITIES
Activity Definition and Activity Sequencing are separate processes, each
with their own inputs, tools and techniques, and outputs. In practice,
especially for small- to medium-sized projects, the planner can combine
these processes into one process or step. The Activity Definition process is
a further breakdown of the work package elements of the WBS. It
documents the specific activities needed to fulfill the deliverables detailed
on the WBS. This process might be performed by the project manager, or
when the WBS is broken down to the subproject level, this process (and all
the Activity-related processes that follow) might be assigned to a subproject
manager.
 Decomposition
Decomposition is the process of breaking the work packages into
smaller, more manageable units of work called schedule activities.
These are not deliverables but the individual units of work that must
be completed to fulfill the deliverables. Activity lists (which are one of
Dr. Karim El-Dash
27
the outputs of this process) from prior projects can be used as
templates in this process.
 Rolling Wave Planning
Rolling wave planning is the process of planning for a project in
waves as the project becomes clearer and unfolds. It is important in
such projects to at least highlight in the initial plan the key milestones
for the project.
Rolling Wave Planning acknowledges the fact that we can see more
clearly what is in close proximity, but looking further ahead our vision
becomes less clear. Rolling Wave Planning is a multi-step,
intermittent process like waves - because we cannot provide the
details very far out in our planning. Depending upon the project - its
length and complexity - we may be able to plan as much as a few
weeks or even a few months in advance with a fair amount of clarity.
This involves creating a detailed, well-defined Work Breakdown
Structure (WBS) for that period of clarity, but just highlighting the
milestone for the rest of the project.
Dr. Karim El-Dash
28
 Activity Attributes
Activity attributes typically refers to the specific components that
make up an activity. These can include descriptive factors of the
activity at the onset, or can also refer specific characteristics that may
become relevant at a later phase of an activity. Activity attributes can
be sorted, organized, and/or summarized according to some specific
categories. Some types of activity attributes can include those related
to time needed to complete specific components, costs related to
completion of an activity or of some specific components, activity
codes, responsible persons and/or persons involved in the activity,
specific locations in which the activity may be taking place, and/or
other miscellaneous categories into which these attributes can be
conveniently and appropriately organized. Activity attributes can also
include discussion of specific constraints that may make completion
more difficult.
 Milestones
A milestone is the end of a stage that marks the completion of a work
package or phase, typically marked by a high level event such as
completion, endorsement or signing of a deliverable, document or a
high level review meeting. In addition to signaling the completion of a
key deliverable, a milestone may also signify an important decision or
the derivation of a critical piece of information, which outlines or
affects the future of a project. In this sense, a milestone not only
signifies distance traveled (key stages in a project) but also indicates
direction of travel since key decisions made at milestones may alter
the route through the project plan.
Dr. Karim El-Dash
29
SEQUENCE ACTIVITIES
 Logical Relationships
Each activity has a start and a finish. A single logic relationship
describes the interdependency of starts and finishes between two
activities. There are four possible relationships between an activity’s
start and finish, and those of other activities.
The most commonly used relationship between two activities is finish-
to-start (FS), wherein the first activity must finish before the second
activity can start. A second type is finish-to-finish (FF), where two
activities must complete at the same time. The third type is start-to-
start (SS), where two activities start at the same time (regardless of
their finish dates). The fourth is start-to-finish (SF), where an activity
must start before a second activity can finish.
Activities can be linked with hard logic (i.e., sequence of each activity
is predetermined, such as footing A before footing B), or soft logic
wherein related activities may be combined and accomplished in a
different order as determined at the time of execution. There are also
physical hard logic relationships where soft logic does not normally
apply, such as footing formwork must be in place before concrete can
be placed.
 Leads and Lags
Lag time can be applied to all four relationship types. Lags are timing
applied to logic; they consume time, but are not activities per se. For
example, lags can be used to define that footing formwork needs to
remain in place until concrete is properly cured. Lead time is overlap
between tasks that have a dependency. For example, if a task can
start when its predecessor is half finished, you can specify a finish-to-
start dependency with a lead time of 50 percent for the successor
task. You enter lead time as a negative value.
Dr. Karim El-Dash
30
 Schedule Network
The project schedule is a fairly broad and all encompassing concept
that while seemingly easy to grasp, must truly be mastered in order
for all members of the project staff, from the project management
team all the way up to the project management team leader to
effectively manage the project in a capable manner from start to
finish. The project schedule typically will include all elements of the
project from the pre-planning stages of the project through all ongoing
project processes that may take place during the active project
period, to any and all project related process that may occur at the
c
o
n
c
l
u
s
i
on and or closing stages of the project. The project schedule network
diagram typically refers to a particular input/output mechanism that
represents a particular schematic display of any and all logical
relationships that may exist between the existing project schedule
activities. The project schedule network diagram when properly laid
out is always laid in a left to right display to properly reflect the
chronology of all project work.
Dr. Karim El-Dash
31
ESTIMATE ACTIVITY RESOURCES
 Resource breakdown structure
Resource Breakdown Structure (RBS) is a standardized list of
personnel, material, equipment resources related by function and
arranged in a hierarchical structure. The Resource Breakdown
Structure standardizes the departments resources to facilitate
planning and controlling of project work. It defines assignable
resources such as personnel, from a functional point of view; it
identifies "who" is doing the work. The total resources define the Top
Level, and each subsequent level is a subset of the resource
category (or level) above it. Each descending (lower) level represents
an increasingly detailed description of the resource until small enough
to be used in conjunction with the Work Breakdown Structure (WBS)
to allow the work to be planned, monitored and controlled.
 Bottom-up Estimate
Bottom-up estimating is an extremely helpful technique in project
management as it allows for the ability to get a more refined estimate
of a particular component of work. In bottom-up estimating, each task
is broken down into smaller components. Then, individual estimates
are developed to determine what specifically is needed to meet the
requirements of each of these smaller components of the work. The
Project
Materials Equipments Manpower Subcontracto
Concrete Steel Wood Ceramic
Foundation
Second floor
First floor
Dr. Karim El-Dash
32
estimates for the smaller individual components are then aggregated
to develop a larger estimate for the entire task as a whole. In doing
this, the estimate for the task as a whole is typically far more
accurate, as it allows for careful consideration of each of the smaller
parts of the task and then combining these carefully considered
estimates rather than merely making one large estimate which
typically will not as thoroughly consider all of the individual
components of a task.
ESTIMATE ACTIVITY DURATION
 Analogous Estimating
Analogous Estimating is an estimating technique with the following
characteristics:
o Estimates are based on past projects (historical information).
o It is less accurate when compared to bottom-up estimation.
o It is a top-down approach.
o It takes less time when compared to bottom-up estimation.
o It is a form of an expert judgment.
 Parametric Estimating
A parametric cost model is an extremely useful tool for preparing
early conceptual estimates when there is little technical data or
engineering deliverables to provide a basis for using more detailed
estimating methods. A parametric model is a mathematical
representation of cost relationships that provide a logical and
predictable correlation between the physical or functional
characteristics of a plant (or process system) and its resultant cost. A
parametric estimate comprises cost estimating relationships and
other parametric estimating functions that provide logical and
repeatable relationships between independent variables, such as
Dr. Karim El-Dash
33
design parameters or physical characteristics and the dependent
variable, cost.
Capacity factor and equipment factor estimates are simple examples
of parametric estimates; however sophisticated parametric models
typically involve several independent variables or cost drivers. Yet
similar to those estimating methods, parametric estimating is reliant
on the collection and analysis of previous project cost data in order to
develop the cost estimating relationships (CER’s).
 Three-Point-Estimating
The Three Point Estimation technique is based on statistical
methods, and in particular, the Normal distribution. In Three Point
Estimation we produce three figures for every estimate:
a = the best case estimate
m = the most likely estimate
b = the worst case estimate
These values are used to calculate an E value for the estimate and a
Standard Deviation (SD) where:
6
4 bma
E


6
ab
SD


E is a weighted average which takes into account both the most
optimistic and pessimistic estimates provided and SD measures the
variability or uncertainty in the estimate.
Dr. Karim El-Dash
34
To produce projects estimate the Project Manager:
1. Decomposes the project into a list of estimable tasks, i.e. a Work
Breakdown Structure
2. Estimates each the E value and SD for each task.
3. Calculates the E value for the total project work as:
 E(Tasks)E(Project)
4. Calculates the SD value for the total project work as:
 2
SD(Tasks))SD(Project
We then use the E and SD values to convert the project estimates to
Confidence Levels as follows:
 Confidence Level in E value is approximately 50%
 Confidence Level in E value + SD is approximately 68%
 Confidence Level in E value + 2 * SD is approximately 95%
 Confidence Level in E value + 3 * SD is approximately 99.7%
Dr. Karim El-Dash
35
 Reserve Analysis
In terms of the project management scope of work and work flow, the
concept of reserve analysis actually refers to a specific technique that
of often implemented by the project management team and or the
project management team leader or leaders for the purposes of
helping to better maintain and manage the projects that they may
have under their guise at that respective time. Specifically, the
technique of reserve analysis is a particular analytical technique that
is used by the project management team and or the project
management team leader for the purposes of making a complete and
thorough determination of what the entirety of the specific and exact
features and or in many cases relationships of all of the individual
project related components that currently exist as part of the
previously determined project management plan. The purpose of the
execution and implementation of a reserve analysis is for the purpose
of establishing and determining an estimated reserve that can be
used for the purposes of establishing schedule duration, any and all
estimated costs, the budget, as well as the complete funds assigned
or allocated to the project.
DEVELOP SCHEDULE
 Critical Path Method
The critical path method (CPM) is a scheduling technique using
arrow, precedence, or PERT diagramming methods to determine the
length of a project and to identify the activities and constraints on the
critical path.
The critical path method enables a scheduler to do the following:
• Determine the shortest time in which a program or project can be
completed.
• Identify those activities that are critical and that cannot be slipped
or delayed.
• Show the potential slippage or delay (known as float) available
for activities that are not critical.
Dr. Karim El-Dash
36
The critical path method (CPM) was designed for, and is useful on,
projects where the duration of each activity can be estimated with
reasonable certainty; it predicts how long an endeavor will take to
complete. It also identifies the activities that control the overall length
of the project. CPM is widely used in the process industries,
construction, single industrial projects, prototype development, and
for controlling plant outages and shutdowns.
 Critical Chain Method
Critical Chain Method (CCM) is a method of planning and managing
projects that puts the main emphasis on the resources required to
execute project tasks. It was developed by Eliyahu M. Goldratt. This
is in contrast to the more traditional Critical Path and PERT methods,
which emphasize task order and rigid scheduling. A Critical Chain
project network will tend to keep the resources levelly loaded, but will
require them to be flexible in their start times and to quickly switch
between tasks and task chains to keep the whole project on
schedule.
The critical chain is the sequence of both precedence and resource
dependent terminal elements that prevents a project from being
completed in a shorter time, given finite resources. If resources are
always available in unlimited quantities, then a project's critical chain
is identical to its critical path.
Critical chain is used as an alternative to critical path analysis. The
main features that distinguish the critical chain from the critical path
are:
1. The use of (often implicit) resource dependencies. Implicit means
that they are not included in the project network but have to be
identified by looking at the resource requirements.
2. Lack of search for an optimum solution. This means that a "good
enough" solution is enough because:
Dr. Karim El-Dash
37
a) As far as is known, there is no analytical method of finding an
absolute optimum (i.e. having the overall shortest critical chain).
b) The inherent uncertainty in estimates is much greater than the
difference between the optimum and near-optimum ("good
enough" solutions).
3. The identification and insertion of buffers:
o project buffer
o feeding buffers
o resource buffers. (Most of time it is observed that companies
are reluctant to give more resources)
Monitoring project progress and health by monitoring the
consumption rate of the buffers rather than individual task
performance to schedule.
CCM aggregates the large amounts of safety time added to many
subprojects in project buffers to protect due-date performance, and to
avoid wasting this safety time through bad multitasking, student
syndrome, Parkinson's Law and poorly synchronized integration.
Critical chain method uses buffer management instead of earned
value management to assess the performance of a project. Some
project managers feel that the earned value management technique
is misleading, because it does not distinguish progress on the project
constraint (i.e. on the critical chain) from progress on non-constraints
(i.e. on other paths). Event chain methodology can be used to
determine a size of project, feeding, and resource buffers.
 Resource Leveling
Resource leveling is a project management process used to examine
a project for an unbalanced use of resources over time, and for
resolving over-allocations or conflicts.
When performing project planning activities, the manager will attempt
to schedule certain tasks simultaneously. When more resources such
as machines or people are needed than are available, or perhaps a
specific person is needed in both tasks, the tasks will have to be
Dr. Karim El-Dash
38
rescheduled concurrently or even sequentially to manage the
constraint. Project planning resource leveling is the process of
resolving these conflicts. It can also be used to balance the workload
of primary resources over the course of the project, usually at the
expense of one of the traditional triple constraints (time, cost, scope).
When using specially designed project software, leveling typically
means resolving conflicts or over allocations in the project plan by
allowing the software to calculate delays and update tasks
automatically. Project management software leveling requires
delaying tasks until resources are available.
In either definition, leveling could result in a later project finish date if
the tasks affected are in the critical path.
Resource Leveling is also useful in the world of maintenance
management. Many organizations have maintenance backlogs.
These backlogs consist of work orders. In a "planned state" these
work orders have estimates such as 2 electricians for 8 hours. These
work orders have other attributes such as report date, priority, asset
operational requirements, and safety concerns. These same
organizations have a need to create weekly schedules. Resource-
leveling can take the "work demand" and balance it against the
resource pool availability for the given week. The goal is to create this
weekly schedule in advance of performing the work. Without
resource-leveling the organization (planner, scheduler, supervisor) is
most likely performing subjective selection. For the most part, when it
comes to maintenance scheduling, there are very few logic ties and
therefore no need to calculate critical path and total float.
 Crashing
Crashing is a process of expediting project schedule by compressing
the total or partial project duration. It is helpful when managers want
to avoid incoming bad weather season or to compensate for prior
delay. However, the downside is that more resources are needed to
speed-up a part of a project, even if resources may be withdrawn
Dr. Karim El-Dash
39
from one facet of the project and used to speed-up the section that is
lagging behind. Moreover, that may also depend on what slack is
available in a non-critical activity, thus resources can be reassigned
to critical project activity. Hence, extreme care should be taken to
make sure that appropriate activities are being crashed and that
diverted resources are not causing needless risk and project scope
integrity.
 Fast Tracking
Fast tracking is a technique that is often implemented in crisis and/or
crunch times so to speak as it involves in taking a specific schedule
activity and/or work breakdown event that has been previously
scheduled and/or is underway and expediting it in some way or
another. Fast tracking is referred to as a project schedule
compression technique of sorts in that its intent is to take an entire
schedule of a project and attempting to compress it into a smaller
period of time by conducting some events either quicker or by doing
some events that were intended to be done in a more spaced out
manner but rather doing some of them simultaneously. The network
logic has essentially been changed allowing for some items that
would otherwise have been done in a sequence are instead
overlapped as such.
 Bar Chart (Gantt Chart)
A Gantt chart is a type of bar chart that illustrates a project schedule.
Gantt charts illustrate the start and finish dates of the terminal activity
and summary elements of a project. Terminal activity and summary
activities comprise the work breakdown structure of the project. Some
Gantt charts also show the dependency (i.e. precedence network)
relationships between activities.
Gantt charts can be used to show current schedule status using
percent-complete shadings and a vertical "TODAY" line.
Dr. Karim El-Dash
40
Although now regarded as a common charting technique, Gantt
charts were considered revolutionary when they were introduced. In
recognition of Henry Gantt's contributions, the Henry Laurence Gantt
Medal is awarded for distinguished achievement in management and
in community service.
Schedule Baseline
The schedule baseline is the final approved version of the project schedule
with baseline start and baseline finish dates and resource assignments.
The PMBOK Guide notes that this baseline is derived from a schedule
network analysis of the schedule model.
In practice, for small- to medium-sized projects, you can easily complete
Activity Definition, Activity Sequencing, Activity Resource Estimating,
Activity Duration Estimating, and Schedule Development at the same time
with the aid of good project management software.
It is easy to produce Gantt charts, critical path, resource allocation, activity
dependencies, what-if analysis, and various reports after plugging your
scheduling information in to most project management software tools.
Regardless of the methods, be certain to obtain sign-off of the project
schedule and provide stakeholders and project sponsor with regular
updates.
And keep the schedule handy—there will likely be changes and
modifications as you go. Also, make certain to save a schedule baseline for
comparative purposes. Once you get into the Executing and Monitoring and
Dr. Karim El-Dash
41
Controlling processes, you’ll be able to compare what you planned to do
against what actually happened.
Schedule Baseline
Dr. Karim El-Dash
42
ESTIMATE COST
 Analogous Estimating
Analogous Estimating, is one form of expert judgment and it also
known as Top-down Estimating. This technique is used to determine
the duration of the project. After finalizing the high level
scope/requirement, the PM will refer & compare the previously
completed project’s similar activities with the current activities and
determine the duration.
This estimation technique will be applied to determine the duration
when the detailed information about the project is not available,
usually during the early stages of the project. This technique will look
the scope/requirement as a whole single unit to estimate. This
estimate will give a ball-park idea about the estimation and will have
bigger variance.
Eg : To estimate the time required to complete the project of
upgrading XYZ application’s database version to a higher version, is
to compare similar past projects and estimate the duration. This is
done irrespective of the complexity, size and other factors.
 Parametric Estimating
Parametric estimating is one of the tools and technique of processes
like Activity Duration Estimating, Cost Estimating, Cost Budgeting.
Parametric estimating is a quantitatively based estimating method
that multiplies the quantity of work by the rate.
This estimate is by multiplying a known element like the quantity of
materials needed by the time it takes to install or complete one unit
of materials. The result is a total estimate for the activity. In this
case, 10 servers multiplied by 16 hours per server gives you a 160-
hour total duration estimate.
Dr. Karim El-Dash
43
 Three-Point-Estimating
The three-point estimation technique is based on statistical methods,
and in particular, the normal distribution. Three-point estimation is
the preferred estimation technique for information systems (IS)
projects. In the three-point estimation there are three figures
produced for every estimate:
a = the best-case estimate
m = the most likely estimate
b = the worst-case estimate
These values are used to calculate an E value for the estimate and a
standard deviation (SD) where:
E = (a + 4m + b) / 6
SD = (b − a)/6
E is a weighted average which takes into account both the most
optimistic and most pessimistic estimates provided. SD measures
the variability or uncertainty in the estimate. In Project Evaluation
and Review Techniques (PERT) the three values are used to fit a
Beta distribution for Monte Carlo simulations.
To produce a project estimate the project manager:
 Decomposes the project into a list of estimable tasks, i.e. a work
breakdown structure
 Estimates each the E value and SD for each task.
 Calculates the E value for the total project work as E (Project Work) =
Σ E (Task)
 Calculates the SD value for the total project work as SD (Project
Work) = √Σ SD (Task)2
The E and SD values are then used to convert the project estimates
to confidence levels as follows:
 Confidence level in E value is approximately 50%
 Confidence level in E value + SD is approximately 85%
Dr. Karim El-Dash
44
 Confidence level in E value + 1.645 × SD is approximately
95%
 Confidence level in E value + 2 × SD is approximately 98%
 Confidence level in E value + 3 × SD is approximately 99.9%
Information Systems uses the 95% confidence level, i.e. E Value +
1.645 × SD, for all project and task estimates.
These confidence level estimates assume that the data from all of
the tasks combine to be approximately normal. Typically, there
would need to be 20–30 tasks for this to be reasonable, and each of
the estimates E for the individual tasks would have to be unbiased.
 Reserve Analysis
Reserves or Contingency allowances are used to deal with
uncertainty or “known-unknowns” and these are added to the cost
estimates, thus sometimes overstating project costs.
Options vary between grouping similar activities and assigning a
single contingency reserve for that group to a zero duration activity.
This activity may be placed across the network path for that group of
schedule activities. As the schedule progresses, the reserve can be
adjusted.
Creating a buffer activity in the critical chain method at the end of the
network path as the schedule progresses, allows the reserve to be
adjusted.
Reserve or contingency means adding a portion of cost/time to the
activity to account for cost/time risk. You might choose to add a
percentage of cost/time or a set number of work to the activity or the
overall budget/schedule.
For example, you know it will take $1000 to run new cable based on
the quantitative estimate you came up with earlier. You also know
that sometimes you hit problem areas when running the cable. To
make sure you don’t impact the project budget, you build in a
reserve of 10 percent of your original estimate to account for the
Dr. Karim El-Dash
45
problems you might encounter. This brings your activity duration
estimate to $1100 hours for this activity.
 Cost of Quality
Cost of Quality (COQ) is a measurement used for assessing the
waste or losses from some defined process (eg. machine, production
line, plant, department, company, etc.).
Recognizing the power and universal applicability of Cost of Quality
(COQ), PQA has developed numerous proprietary Cost of Quality
(COQ) systems for ensuring the effectiveness of Cost of Quality
(COQ) implementations.
The Cost of Quality (COQ) measurement can track changes over
time for one particular process, or be used as a benchmark for
comparison of two or more different processes (eg. two machines,
different production lines, sister plants, two competitor companies,
etc.).
Dr. Karim El-Dash
46
Most COQ systems are defined by use of 4 categories of costs:
COQ
Category
Typical Descriptions (may vary
between different Organizations)
Examples
Internal
Costs associated with internal losses (ie.
within the process being analyzed)
off-cuts, equipment
breakdowns, spills,
scrap, yield, productivity
External
Costs external the process being
analyzed (ie. occur outside, not within).
These costs are usually discovered by,
or affect third parties (eg. customers).
Some External costs may have
originated from within, or been caused,
created by, or made worse by the
process being analyzed. They are
defined as External because of where
they were discovered, or who is primarily
or initially affected.
customer complaints,
latent defects found by
the customer, warranty
Preventive
Costs associated with the prevention of
future losses: (eg. unplanned or
undesired problems, losses, lost
opportunities, breakdowns, work
stoppages, waste, etc.)
planning, mistake-
proofing, scheduled
maintenance, quality
assurance
Assessment
Costs associated with measurement and
assessment of the process.
KPI's, inspection,
quality check, dock
audits, third party
audits, measuring
devices, reporting
systems, data collection
systems, forms
 Vendor-Bid-Analysis
In a competitive bid process, you can apply vendor bid analysis to
determine how much a project should cost. Comparing bids can help
you determine the most likely cost for each deliverable, which will
allow for a more accurate project cost estimate.
Dr. Karim El-Dash
47
Control Cost
Earned Value management
Earned value management (EVM) is a project management technique for
measuring project progress in an objective manner. EVM has the ability to
combine measurements of scope, schedule, and cost in a single integrated
system. When properly applied, EVM provides an early warning of
performance problems. Additionally, EVM promises to improve the
definition of project scope, prevent scope creep, communicate objective
progress to stakeholders, and keep the project team focused on achieving
progress.
Essential features of any EVM implementation include
1. a project plan that identifies work to be accomplished,
2. a valuation of planned work, called Planned Value (PV) or Budgeted
Cost of Work Scheduled (BCWS), and
3. pre-defined “earning rules” (also called metrics) to quantify the
accomplishment of work, called Earned Value (EV) or Budgeted Cost
of Work Performed (BCWP).
EVM implementations for large or complex projects include many more
features, such as indicators and forecasts of cost performance (over
budget or under budget) and schedule performance (behind schedule or
ahead of schedule). However, the most basic requirement of an EVM
system is that it quantifies progress using PV and EV.
Project tracking without EVM
It is helpful to see an example of project tracking that does not include
earned value performance management. Consider a project that has been
planned in detail, including a time-phased spend plan for all elements of
work. Figure 1 shows the cumulative budget for this project as a function of
time (the blue line, labeled PV). It also shows the cumulative actual cost of
the project (red line) through week 8. To those unfamiliar with EVM, it might
appear that this project was over budget through week 4 and then under
budget from week 6 through week 8. However, what is missing from this
Dr. Karim El-Dash
48
chart is any understanding of how much work has been accomplished
during the project. If the project were actually completed at week 8, then
the project would actually be well under budget and well ahead of
schedule. If, on the other hand, the project is only 10% complete at week 8,
the project is significantly over the budget and behind schedule. A method
is needed to measure technical performance objectively and quantitatively,
and that is what EVM accomplishes.
Project tracking with EVM
Consider the same project, except this time the project plan includes pre-
defined methods of quantifying the accomplishment of work. At the end of
each week, the project manager identifies every detailed element of work
that has been completed, and sums the PV for each of these completed
elements. Earned value may be accumulated monthly, weekly, or as
progress is made.
Earned value (EV)
Figure 2 shows the EV curve (in green) along with the PV curve from
Figure 1. The chart indicates that technical performance (i.e., progress)
started more rapidly than planned, but slowed significantly and fell behind
Dr. Karim El-Dash
49
schedule at week 7 and 8. This chart illustrates the schedule performance
aspect of EVM. It is complementary to critical path or critical chain schedule
management.
Figure 3 shows the same EV curve (green) with the actual cost data from
Figure 1 (in red). It can be seen that the project was actually under budget,
relative to the amount of work accomplished, since the start of the project.
This is a much better conclusion than might be derived from Figure 1.
Figure 4 shows all three curves together – which is a typical EVM line
chart. The best way to read these three-line charts is to identify the EV
curve first, then compare it to PV (for schedule performance) and AC (for
Dr. Karim El-Dash
50
cost performance). It can be seen from this illustration that a true
understanding of cost performance and schedule performance relies first
on measuring technical performance objectively. This is the foundational
principle of EVM.
Earned Value Management Principle
The foundational principle of EVM, mentioned above, does not depend
on the size or complexity of the project. However, the implementations of
EVM can vary significantly depending on the circumstances. In many
cases, organizations establish an all-or-nothing threshold; projects above
the threshold require a full-featured (complex) EVM system and projects
below the threshold are exempted. Another approach that is gaining favor
is to scale EVM implementation according to the project at hand and skill
level of the project team.
Simple implementations
There are many more small and simple projects than there are large and
complex ones, yet historically only the largest and most complex have
enjoyed the benefits of EVM. Still, lightweight implementations of EVM are
achievable by any person who has basic spreadsheet skills. In fact,
spreadsheet implementations are an excellent way to learn basic EVM
skills.
Dr. Karim El-Dash
51
The first step is to define the work. This is typically done in a hierarchical
arrangement called a work breakdown structure (WBS) although the
simplest projects may use a simple list of tasks. In either case, it is
important that the WBS or list be comprehensive. It is also important that
the elements be mutually exclusive, so that work is easily categorized in
one and only one element of work. The most detailed elements of a WBS
hierarchy (or the items in a list) are called activities (or tasks).
The second step is to assign a value, called planned value (PV), to each
activity. For large projects, PV is almost always an allocation of the total
project budget, and may be in units of currency (e.g., dollars or euros) or in
labor hours, or both. However, in very simple projects, each activity may be
assigned a weighted “point value" which might not be a budget number.
Assigning weighted values and achieving consensus on all PV quantities
yields an important benefit of EVM, because it exposes misunderstandings
and miscommunications about the scope of the project, and resolving these
differences should always occur as early as possible. Some terminal
elements cannot be known (planned) in great detail in advance, and that is
expected, because they can be further refined at a later time.
The third step is to define “earning rules” for each activity. The simplest
method is to apply just one earning rule, such as the 0/100 rule, to all
activities. Using the 0/100 rule, no credit is earned for an element of work
until it is finished. A related rule is called the 50/50 rule, which means 50%
credit is earned when an element of work is started, and the remaining 50%
is earned upon completion. Other fixed earning rules such as a 25/75 rule
or 20/80 rule are gaining favor, because they assign more weight to
finishing work than for starting it, but they also motivate the project team to
identify when an element of work is started, which can improve awareness
of work-in-progress. These simple earning rules work well for small or
simple projects because generally each activity tends to be fairly short in
duration.
These initial three steps define the minimal amount of planning for
simplified EVM. The final step is to execute the project according to the
plan and measure progress. When activities are started or finished, EV is
accumulated according to the earning rule. This is typically done at regular
Dr. Karim El-Dash
52
intervals (e.g., weekly or monthly), but there is no reason why EV cannot
be accumulated in near real-time, when work elements are
started/completed. In fact, waiting to update EV only once per month
(simply because that is when cost data are available) only detracts from a
primary benefit of using EVM, which is to create a technical performance
scoreboard for the project team.
In a lightweight implementation such as described here, the project
manager has not accumulated cost nor defined a detailed project schedule
network (i.e., using a critical path or critical chain methodology). While such
omissions are inappropriate for managing large projects, they are a
common and reasonable occurrence in many very small or simple projects.
Any project can benefit from using EV alone as a real-time score of
progress. One useful result of this very simple approach (without schedule
models and actual cost accumulation) is to compare EV curves of similar
projects, as illustrated in Figure 5. In this example, the progress of three
residential construction projects are compared by aligning the starting
dates. If these three home construction projects were measured with the
same PV valuations, the relative schedule performance of the projects can
be easily compared.
Dr. Karim El-Dash
53
Intermediate implementations
In many projects, schedule performance (completing the work on time) is
equal in importance to technical performance. For example, some new
product development projects place a high premium on finishing quickly. It
is not that cost is unimportant, but finishing the work later than a competitor
may cost a great deal more in lost market share. It is likely that these kinds
of projects will not use the lightweight version of EVM described in the
previous section, because there is no planned timescale for measuring
schedule performance. A second layer of EVM skill can be very helpful in
managing the schedule performance of these “intermediate” projects. The
project manager may employ a critical path or critical chain to build a
project schedule model. As in the lightweight implementation, the project
manager must define the work comprehensively, typically in a WBS
hierarchy. He/she will construct a project schedule model that describes the
precedence links between elements of work. This schedule model can then
be used to develop the PV curve (or baseline), as shown in Figure 2'.
It should be noted that measuring schedule performance using EVM does
not replace the need to understand schedule performance versus the
project's schedule model (precedence network). However, EVM schedule
performance, as illustrated in Figure 2 provides an additional indicator —
one that can be communicated in a single chart. Although it is theoretically
possible that detailed schedule analysis will yield different conclusions than
broad schedule analysis, in practice there tends to be a high correlation
between the two. Although EVM schedule measurements are not
necessarily conclusive, they provide useful diagnostic information.
Although such intermediate implementations do not require units of
currency (e.g., dollars), it is common practice to use budgeted dollars as
the scale for PV and EV. It is also common practice to track labor hours in
parallel with currency. The following EVM formulas are for schedule
management, and do not require accumulation of actual cost (AC). This is
important because it is common in small and intermediate size projects for
true costs to be unknown or unavailable.
Dr. Karim El-Dash
54
 Schedule variance (SV)
EV-PV greater than 0 is good (ahead of schedule)
 Schedule performance index (SPI)
EV/PV greater than 1 is good (ahead of schedule)
See also earned schedule for a description of known limitations in SV and
SPI formulas and an emerging practice for correcting these limitations.
Advanced implementations
In addition to managing technical and schedule performance, large and
complex projects require that cost performance be monitored and reviewed
at regular intervals. To measure cost performance, planned value (or
BCWS - Budgeted Cost of Work Scheduled) and earned value (or BCWP -
Budgeted Cost of Work Performed) must be in units of currency (the same
units that actual costs are measured.) In large implementations, the
planned value curve is commonly called a Performance Measurement
Baseline (PMB) and may be arranged in control accounts, summary-level
planning packages, planning packages and work packages. In large
projects, establishing control accounts is the primary method of delegating
responsibility and authority to various parts of the performing organization.
Control accounts are cells of a responsibility assignment (RACI) matrix,
which is intersection of the project WBS and the organizational breakdown
structure (OBS). Control accounts are assigned to Control Account
Managers (CAMs). Large projects require more elaborate processes for
controlling baseline revisions, more thorough integration with subcontractor
EVM systems, and more elaborate management of procured materials.
Additional acronyms and formulas include:
Budget at completion (BAC): The total planned value (PV or BCWS) at
the end of the project. If a project has a Management Reserve (MR), it is
typically in addition to the BAC.
Dr. Karim El-Dash
55
 Cost variance (CV)
EV - AC, greater than 0 is good (under budget)
 Cost Performance Index (CPI)
EV/AC, greater than 1 is good (under budget)
< 1 means that the cost of completing the work is higher than planned
(bad)
= 1 means that the cost of completing the work is right on plan (good)
> 1 means that the cost of completing the work is less than planned (good
or sometimes bad).
Having a CPI that is very high (in some cases, very high is only 1.2) may
mean that the plan was too conservative, and thus a very high number may
in fact not be good, as the CPI is being measured against a poor baseline.
Management or the customer may be upset with the planners as an overly
conservative baseline ties up available funds for other purposes, and the
baseline is also used for manpower planning.
Estimate at completion (EAC)
EAC is the manager's projection of total cost of the project at completion.
ETC is the estimate to complete the project.
To-complete performance index (TCPI)
The To Complete Performance Index (TCPI) provides a projection of the
anticipated performance required to achieve either the BAC or the EAC.
TCPI indicates the future required cost efficiency needed to achieve a
target BAC (Budget At Complete) or EAC (Estimate At Complete). Any
Dr. Karim El-Dash
56
significant difference between CPI, the cost performance to date, and the
TCPI, the cost performance needed to meet the BAC or the EAC, should
be accounted for by management in their forecast of the final cost.
For the TCPI based on BAC (describing the performance required to meet
the original BAC budgeted total):
or for the TCPI based on EAC (describing the performance required to
meet a new, revised budget total EAC):
Independent estimate at completion (IEAC)
The IEAC is a metric to project total cost using the performance to date to
project overall performance. This can be compared to the EAC, which is
the manager's projection.
Dr. Karim El-Dash
57
Project Quality Management
Quality can be defined as meeting the customer's expectations or
exceeding the customer expectations achieved by way of deliverables
and/or activities performed to produce those deliverables.
Project Quality Plan can be defined as a set of activities planned at the
beginning of the project that helps achieve Quality in the Project being
executed. The Purpose of the Project Quality Plan is to define these
activities/tasks that intend to deliver products while focusing on achieving
customer's quality expectations. These activities / tasks are defined on the
basis of the quality standards set by the organization delivering the product.
Project Quality Plan identifies which Quality Standards are relevant to the
project and determines how they can be satisfied. It includes the
implementation of Quality Events (peer reviews, checklist execution) by
using various Quality Materials (templates, standards, checklists) available
within the organization. The holding of the Quality Event is termed as
Quality Control. As an output of the various activities, Quality Metrics or
Measurements are captured which assist in continuous improvement of
Quality thus adding to the inventory of Lessons Learned. Quality Assurance
deals in preparation of the Quality Plan and formation of organization wide
standards.
Guidelines to write the Project Quality Plan
Project Quality Plan should be written with the objective to provide project
management with easy access to quality requirements and should have
ready availability of the procedures and standards thus mentioned.
The following list provides you the various Quality Elements that should be
included in a detailed Project Quality Plan:
Management Responsibility. Describes the quality responsibilities of all
stakeholders.
Dr. Karim El-Dash
58
Documented Quality Management System. This refers to the existing
Quality Procedures that have been standardized and used within the
organization.
Design Control. This specifies the procedures for Design Review, Sign-
Off, Design Changes and Design Waivers of requirements.
Document Control. This defines the process to control Project Documents
at each Project Phase.
Purchasing. This defines Quality Control and Quality Requirements for
sub-contracting any part / whole part of the project.
Inspection Testing. This details the plans for Acceptance Testing and
Integration Testing.
Nonconformance. This defines the procedures to handle any type of
nonconformance work. The procedures include defining responsibilities,
defining conditions and availability of required documentation in such
cases.
Corrective Actions. This describes the procedures for taking Corrective
Actions for the problems encountered during project execution.
Quality Records. This describes the procedures for maintaining the
Quality Records (metrices, variance reports, executed checklists etc)
during project execution as well as after the project completion.
Quality Audits. An internal audit should be planned and implemented
during each phase of the project.
Training. This should specify any training requirements for the project
team.
Dr. Karim El-Dash
59
COST-BENEFIT ANALYSIS
In the case of quality management, cost of quality trade-offs should be
considered from within cost-benefit analysis. The benefits of meeting
quality requirements are as follows:
 Stakeholder satisfaction is increased.
 Costs are lower.
 Productivity is higher.
 There is less rework.
COST OF QUALITY
CATEGORIES	OF	QUALITY	COSTS	
Many companies summarize these costs into four categories. Some
practitioners also call these categories the “cost of quality.” These
categories and examples of typical subcategories are discussed below.
	
Internal	Failure	Costs.
These are costs of deficiencies discovered before delivery which are
associated with the failure (nonconformities) to meet explicit requirements
or implicit needs of external or internal customers. Also included are
avoidable process losses and inefficiencies that occur even when
requirements and needs are met. These are costs that would disappear if
no deficiencies existed.
Dr. Karim El-Dash
60
Failure	to	Meet	Customer	Requirements	and	Needs.		
Examples of subcategories are costs associated with:
 Scrap: The labor, material, and (usually) overhead on defective product
that cannot economically be repaired. The titles are numerous—scrap,
spoilage, defectives, etc.
 Rework: Correcting defectives in physical products or errors in service
products.
 Lost or missing information: Retrieving information that should have
been supplied.
 Failure analysis: Analyzing nonconforming goods or services to
determine causes.
 Scrap and rework—supplier: Scrap and rework due to nonconforming
product received from suppliers. This also includes the costs to the
buyer of resolving supplier quality problems.
 One hundred percent sorting inspection: Finding defective units in
product lots which c unacceptably high levels of defectives.
 Reinspection, retest: Reinspection and retest of products that have
undergone rework or other revision.
 Changing processes: Modifying manufacturing or service processes to
correct deficiencies.
 Redesign: Changing designs to correct deficiencies.
 Scrapping of obsolete product: Disposing of products that have been
superseded.
 Scrap in support operations: Defective items in indirect operations.
 Rework in internal support operations: Correcting defective items in
indirect operations.
 Downgrading: The difference between the normal selling price and the
reduced price due to quality reasons.
Dr. Karim El-Dash
61
Cost	of	Inefficient	Processes.		
Examples of subcategories are
 Variability of product characteristics: Losses that occur even with
conforming product (e.g., overfill of packages due to variability of filling
and measuring equipment).
 Unplanned downtime of equipment: Loss of capacity of equipment due
to failures.
 Inventory shrinkage: Loss due to the difference between actual and
recorded inventory amounts.
 Variation of process characteristics from “best practice”: Losses due to
cycle time and costs of processes as compared to best practices in
providing the same output. The best-practice process may be internal or
external to the organization.
 Non-value-added activities: Redundant operations, sorting inspections,
and other non-valueadded activities. A value-added activity increases
the usefulness of a product to the customer; a non-value-added activity
does not. (The concept is similar to the 1950s concept of value
engineering and value analysis.)
	
External	Failure	Costs	
These are costs associated with deficiencies that are found after product is
received by the customer. Also included are lost opportunities for sales
revenue. These costs also would disappear if there were no deficiencies.
	
Failure	to	Meet	Customer	Requirements	and	Needs	
Examples of subcategories are:
 Warranty charges: The costs involved in replacing or making repairs to
products that are still within the warranty period.
 Complaint adjustment: The costs of investigation and adjustment of
justified complaints attributable to defective product or installation.
Dr. Karim El-Dash
62
 Returned material: The costs associated with receipt and replacement
of defective product received from the field.
 Allowances: The costs of concessions made to customers due to
substandard products accepted by the customer as is or to conforming
product that does not meet customer needs.
 Penalties due to poor quality: This applies to goods or services
delivered or to internal processes such as late payment of an invoice
resulting in a lost discount for paying on time.
 Rework on support operations: Correcting errors on billing and other
external processes.
 Revenue losses in support operations: An example is the failure to
collect on receivables from some customers.
Appraisal	Costs	
These are the costs incurred to determine the degree of conformance to
quality requirements. Examples are
 Incoming inspection and test: Determining the quality of purchased
product, whether by inspection on receipt, by inspection at the source,
or by surveillance.
 In-process inspection and test: In-process evaluation of conformance to
requirements.
 Final inspection and test: Evaluation of conformance to requirements for
product acceptance.
 Document review: Examination of paperwork to be sent to customer.
 Balancing: Examination of various accounts to assure internal
consistency.
 Product quality audits: Performing quality audits on in-process or
finished products.
 Maintaining accuracy of test equipment: Keeping measuring
instruments and equipment in calibration.
 Inspection and test materials and services: Materials and supplies in
inspection and test work (e.g., x-ray film) and services (e.g., electric
power) where significant.
Dr. Karim El-Dash
63
 Evaluation of stocks: Testing products in field storage or in stock to
evaluate degradation.
In collecting appraisal costs, what is decisive is the kind of work done and
not the department name (the work may be done by chemists in the
laboratory, by sorters in Operations, by testers in Inspection, or by an
external firm engaged for the purpose of testing). Also note that industries
use a variety of terms for “appraisal,” e.g., checking, balancing,
reconciliation, review.
	
Prevention	Costs	
These are costs incurred to keep failure and appraisal costs to a minimum.
Examples are:
 Quality planning: This includes the broad array of activities which
collectively create the overall quality plan and the numerous specialized
plans. It includes also the preparation of procedures needed to
communicate these plans to all concerned.
 New-products review: Reliability engineering and other quality-related
activities associated with the launching of new design.
 Process planning: Process capability studies, inspection planning, and
other activities associated with the manufacturing and service
processes.
 Process control: In-process inspection and test to determine the status
of the process (rather than for product acceptance).
 Quality audits: Evaluating the execution of activities in the overall quality
plan.
 Supplier quality evaluation: Evaluating supplier quality activities prior to
supplier selection, auditing the activities during the contract, and
associated effort with suppliers.
 Training: Preparing and conducting quality-related training programs. As
in the case of appraisal costs, some of this work may be done by
personnel who are not on the payroll of the Quality department. The
Dr. Karim El-Dash
64
decisive criterion is again the type of work, not the name of the
department performing the work.
Note that prevention costs are costs of special planning, review, and
analysis activities for quality.
Prevention costs do not include basic activities such as product design,
process design, process maintenance, and customer service.
Dr. Karim El-Dash
65
OPTIMUM QUALITY COST MODEL
The model shows three curves:
1. The failure costs: These equal zero when the product is 100 percent
good, and rise to infinity when the product is 100 percent defective.
(Note that the vertical scale is cost per good unit of product. At 100
percent defective, the number of good units is zero, and hence the cost
per good unit is infinity.)
2. The costs of appraisal plus prevention: These costs are zero at 100
percent defective, and rise as perfection is approached.
3. The sum of curves 1 and 2: This third curve is marked “total quality
costs” and represents the total cost of quality per good unit of product.
Cost of quality
The previous figure suggests that the minimum level of total quality costs
occurs when the quality of conformance is 100 percent, i.e., perfection.
This has not always been the case. During most of the twentieth century
the predominant role of (fallible) human beings limited the efforts to attain
perfection at finite costs. Also, the inability to quantify the impact of quality
Dr. Karim El-Dash
66
failures on sales revenue resulted in underestimating the failure costs. The
result was to view the optimum value of quality of conformance as less than
100 percent.
Effect of identifying cost of quality
 
Dr. Karim El-Dash
67
CONTROL CHARTS
A control chart represents a picture of a process over time. To effectively
use control charts, one must be able to interpret the picture. What is this
control chart telling me about my process? Is this picture telling me that
everything is all right and I can relax? Is this picture telling me that
something is wrong and I should get up and find out what has happened? A
control chart tells you if your process is in statistical control. The chart
above is an example of a stable (in statistical control) process.
This pattern is typical of processes that are stable. Three characteristics of
a process that is in control are:
 Most points are near the average
 A few points are near the control limits
 No points are beyond the control limits
If a control chart does not look similar to the one above, there is probably a
special cause present. Various tests for determining if a special cause is
present are given below.
	
Points	Beyond	the	Control	Limits	
A special cause is present in the
process if any points fall above the
upper control limit or below the
lower control limit. Action should be
taken to find the special cause and
permanently remove it from the
process. If there is a point beyond
the control limits, there is no need
Dr. Karim El-Dash
68
to apply the other tests for out of control situations. Points on the control
limits are not considered to be out of statistical control.
	
Zone	Tests:	Setting	the	Zones	and	Zone	A	
The zone tests are valuable tests
for enhancing the ability of control
charts to detect small shifts
quickly. The first step in using
these tests is to divide the control
chart into zones. This is done by
dividing the area between the
average and the upper control
limit into three equally spaced areas. This is then repeated for the area
between the average and the lower control limit.
The zones are called zones A, B,
and C. There is a zone A for the top
half of the chart and a zone A for the
bottom half of the chart. The same is
true for zones B and C. Control
charts are based on 3 sigma limits
of the variable being plotted. Thus,
each zone is one standard deviation
in width. For example, considering
the top half of the chart, zone C is the region from the average to the
average plus one standard deviation. Zone B is the region between the
average plus one standard deviation and the average plus two standard
deviations. Zone A is the region between the average plus two standard
deviations and the average plus three standard deviations
A special cause exists if two out of three consecutive points fall in zone A
or beyond. The figure below shows an example of this test. The test is
applied for the zone A above the average and then for the zone A below
the average.
Dr. Karim El-Dash
69
This test, like those below, is applied to both halves of the chart. However,
only one half is considered at a time. For example, if one point falls in the
zone A above the average and the next point falls in zone A below the
average, this is not two out of three consecutive points in zone A or
beyond. The two points in zone A must be on the same side of the
average.
	
	Zone	Tests:	Zones	B	and	C	
A special cause exists if
four out five consecutive
points fall in zone B or
beyond. The figure to the
left shows an example of
this test. This test is
applied for zone B above
the average and then for
zone B below the
average.
A special cause exists if
seven consecutive points
fall in zone C or beyond. An
example of this test is
shown below. The test
should be applied for the
zone C above the average
and then for the zone C
below the average.
Dr. Karim El-Dash
70
Test	for	Stratification	
Stratification occurs if two or more
processes (distributions) are being
sampled systematically. For
example, stratification can occur if
samples are taken once a shift and
a subgroup size of 3 is formed
based on the results from three
shifts. It is possible that the shifts
are operating at a different average
or variability. Stratification (a special cause) exists if fifteen or more
consecutive points fall in zone C either above or below the average. Note
that the points tend to hug the centerline. This test involves the use of the
zones but is applied to the entire chart and not one-half of the chart at a
time.
Test	for	Mixtures	
A mixture exists when there is
more than one process present but
sampling is done for each process
separately. For example, suppose
you take three samples per shift
and form a subgroup based on
these three samples. If different
shifts are operating at different
averages, a mixture can occur. A
mixture (a special cause) is present if eight or more consecutive points lie
on both sides of the average with none of the points in zone C. The figure
shows an example of this test. Note the absence of points in zone C. This
test is applied to the entire chart.
Rule	of	Seven	Tests	
These tests are often taught initially to employees as the method for
interpreting control charts (along with points beyond the limits). The tests
Dr. Karim El-Dash
71
state that an out of control situation is present if one of the following
conditions is true:
1) Seven points in a row above the average,
2) Seven points in a row below the average,
3) Seven points in a row trending up, or
4) Seven points in a row trending down.
These four conditions are shown in the
figure above.
Dr. Karim El-Dash
72
BENCHMARKING
A benchmark is a defined measure of productivity in comparison to
something else. We can benchmark internally, seeking to maintain or
improve performance, or we can try to find industry benchmarks, and
compare ourselves to our competitors.
Sometimes, industry associations can provide information in support of
benchmarks that we should achieve. We should always evaluate them
closely to be sure that the benchmark is appropriate and realistic in our
work environment. For example, if we are using older equipment, we might
not be able to achieve an industry average rate of production. Also, we
should make sure that achieving that benchmark increases or at least
maintains customer quality while lowering cost. There is no point achieving
a benchmark if it means losing customers or losing dollars.
	
Best	Practices	
Information about solid, measurable benchmarks is hard to obtain and
harder to fit into unique situation. Developing and using best practices is a
powerful improvement method. A best practice is simply the best way to do
a repeating process at your organization. Best practices:
Managing multiple projects
Managing multiple projects
Managing multiple projects
Managing multiple projects
Managing multiple projects
Managing multiple projects
Managing multiple projects
Managing multiple projects
Managing multiple projects
Managing multiple projects
Managing multiple projects
Managing multiple projects
Managing multiple projects
Managing multiple projects
Managing multiple projects
Managing multiple projects
Managing multiple projects
Managing multiple projects
Managing multiple projects
Managing multiple projects
Managing multiple projects
Managing multiple projects
Managing multiple projects
Managing multiple projects
Managing multiple projects
Managing multiple projects
Managing multiple projects
Managing multiple projects
Managing multiple projects
Managing multiple projects
Managing multiple projects
Managing multiple projects
Managing multiple projects
Managing multiple projects
Managing multiple projects
Managing multiple projects
Managing multiple projects
Managing multiple projects
Managing multiple projects
Managing multiple projects
Managing multiple projects
Managing multiple projects
Managing multiple projects
Managing multiple projects
Managing multiple projects
Managing multiple projects
Managing multiple projects
Managing multiple projects
Managing multiple projects
Managing multiple projects
Managing multiple projects
Managing multiple projects
Managing multiple projects
Managing multiple projects
Managing multiple projects
Managing multiple projects
Managing multiple projects
Managing multiple projects
Managing multiple projects
Managing multiple projects
Managing multiple projects
Managing multiple projects
Managing multiple projects
Managing multiple projects
Managing multiple projects
Managing multiple projects
Managing multiple projects
Managing multiple projects
Managing multiple projects
Managing multiple projects
Managing multiple projects
Managing multiple projects
Managing multiple projects
Managing multiple projects
Managing multiple projects
Managing multiple projects
Managing multiple projects
Managing multiple projects
Managing multiple projects
Managing multiple projects
Managing multiple projects
Managing multiple projects
Managing multiple projects
Managing multiple projects
Managing multiple projects
Managing multiple projects
Managing multiple projects
Managing multiple projects
Managing multiple projects
Managing multiple projects
Managing multiple projects
Managing multiple projects
Managing multiple projects
Managing multiple projects
Managing multiple projects
Managing multiple projects
Managing multiple projects
Managing multiple projects
Managing multiple projects
Managing multiple projects
Managing multiple projects
Managing multiple projects
Managing multiple projects
Managing multiple projects
Managing multiple projects
Managing multiple projects
Managing multiple projects
Managing multiple projects
Managing multiple projects
Managing multiple projects
Managing multiple projects
Managing multiple projects
Managing multiple projects
Managing multiple projects
Managing multiple projects
Managing multiple projects
Managing multiple projects
Managing multiple projects
Managing multiple projects
Managing multiple projects
Managing multiple projects
Managing multiple projects
Managing multiple projects
Managing multiple projects
Managing multiple projects
Managing multiple projects
Managing multiple projects
Managing multiple projects
Managing multiple projects
Managing multiple projects
Managing multiple projects
Managing multiple projects
Managing multiple projects
Managing multiple projects
Managing multiple projects
Managing multiple projects
Managing multiple projects
Managing multiple projects
Managing multiple projects
Managing multiple projects
Managing multiple projects
Managing multiple projects
Managing multiple projects
Managing multiple projects
Managing multiple projects
Managing multiple projects
Managing multiple projects
Managing multiple projects
Managing multiple projects
Managing multiple projects
Managing multiple projects
Managing multiple projects
Managing multiple projects
Managing multiple projects
Managing multiple projects
Managing multiple projects
Managing multiple projects
Managing multiple projects
Managing multiple projects
Managing multiple projects
Managing multiple projects
Managing multiple projects
Managing multiple projects
Managing multiple projects
Managing multiple projects
Managing multiple projects
Managing multiple projects
Managing multiple projects
Managing multiple projects
Managing multiple projects
Managing multiple projects
Managing multiple projects
Managing multiple projects
Managing multiple projects
Managing multiple projects
Managing multiple projects
Managing multiple projects
Managing multiple projects
Managing multiple projects
Managing multiple projects
Managing multiple projects
Managing multiple projects
Managing multiple projects
Managing multiple projects
Managing multiple projects
Managing multiple projects
Managing multiple projects
Managing multiple projects
Managing multiple projects
Managing multiple projects
Managing multiple projects
Managing multiple projects
Managing multiple projects
Managing multiple projects
Managing multiple projects
Managing multiple projects
Managing multiple projects
Managing multiple projects
Managing multiple projects
Managing multiple projects
Managing multiple projects
Managing multiple projects
Managing multiple projects
Managing multiple projects
Managing multiple projects
Managing multiple projects
Managing multiple projects
Managing multiple projects
Managing multiple projects
Managing multiple projects
Managing multiple projects
Managing multiple projects
Managing multiple projects
Managing multiple projects
Managing multiple projects
Managing multiple projects
Managing multiple projects
Managing multiple projects
Managing multiple projects
Managing multiple projects
Managing multiple projects
Managing multiple projects
Managing multiple projects
Managing multiple projects
Managing multiple projects
Managing multiple projects
Managing multiple projects

More Related Content

What's hot

Project management
Project managementProject management
Project managementJay Raval
 
Project Management Principles and Process
Project Management Principles and ProcessProject Management Principles and Process
Project Management Principles and ProcessCharles Cotter, PhD
 
Project management
Project managementProject management
Project managementSimran Kaur
 
Discover the right tools for your Project Management Office (PMO)
Discover the right tools for your Project Management Office (PMO)Discover the right tools for your Project Management Office (PMO)
Discover the right tools for your Project Management Office (PMO)Hussain Bandukwala
 
Introduction to Project Management by Javid Hamdard
Introduction to Project Management by Javid HamdardIntroduction to Project Management by Javid Hamdard
Introduction to Project Management by Javid HamdardJavid Hamdard
 
Brief introduction to project management and project management tools
Brief introduction to project management and project management toolsBrief introduction to project management and project management tools
Brief introduction to project management and project management toolsNathan Petralia
 
Smart project management - Best Practices to Manage Project effectively
Smart project management - Best Practices to Manage Project effectivelySmart project management - Best Practices to Manage Project effectively
Smart project management - Best Practices to Manage Project effectivelyChetan Khanzode
 
Program governance Structure
Program governance StructureProgram governance Structure
Program governance StructureSaurabh Sardesai
 
Project Management Fundamentals
Project Management FundamentalsProject Management Fundamentals
Project Management FundamentalsOxfordCambridge
 
PMP Lecture 3: Project Management Processes
PMP Lecture 3: Project Management ProcessesPMP Lecture 3: Project Management Processes
PMP Lecture 3: Project Management ProcessesMohamed Loey
 
Construction Project management
Construction Project management Construction Project management
Construction Project management Anupama holla
 
Establishing an Effective PMO
Establishing an Effective PMOEstablishing an Effective PMO
Establishing an Effective PMOBusiness Beam
 
Project Management
Project ManagementProject Management
Project ManagementMark Roman
 
Project Management Summary 2012
Project Management Summary 2012Project Management Summary 2012
Project Management Summary 2012CPA Australia
 

What's hot (20)

Project Management
Project ManagementProject Management
Project Management
 
Project management
Project managementProject management
Project management
 
Project Management Principles and Process
Project Management Principles and ProcessProject Management Principles and Process
Project Management Principles and Process
 
Project management
Project managementProject management
Project management
 
Discover the right tools for your Project Management Office (PMO)
Discover the right tools for your Project Management Office (PMO)Discover the right tools for your Project Management Office (PMO)
Discover the right tools for your Project Management Office (PMO)
 
Introduction to Project Management by Javid Hamdard
Introduction to Project Management by Javid HamdardIntroduction to Project Management by Javid Hamdard
Introduction to Project Management by Javid Hamdard
 
Brief introduction to project management and project management tools
Brief introduction to project management and project management toolsBrief introduction to project management and project management tools
Brief introduction to project management and project management tools
 
Project management
Project managementProject management
Project management
 
Smart project management - Best Practices to Manage Project effectively
Smart project management - Best Practices to Manage Project effectivelySmart project management - Best Practices to Manage Project effectively
Smart project management - Best Practices to Manage Project effectively
 
project management
project managementproject management
project management
 
Program governance Structure
Program governance StructureProgram governance Structure
Program governance Structure
 
Project Management Fundamentals
Project Management FundamentalsProject Management Fundamentals
Project Management Fundamentals
 
PMP Lecture 3: Project Management Processes
PMP Lecture 3: Project Management ProcessesPMP Lecture 3: Project Management Processes
PMP Lecture 3: Project Management Processes
 
Construction Project management
Construction Project management Construction Project management
Construction Project management
 
Project Management
Project ManagementProject Management
Project Management
 
Establishing an Effective PMO
Establishing an Effective PMOEstablishing an Effective PMO
Establishing an Effective PMO
 
Project Management
Project ManagementProject Management
Project Management
 
Project Management Steps
Project Management StepsProject Management Steps
Project Management Steps
 
Project Management Tools and Techniques
Project Management Tools and TechniquesProject Management Tools and Techniques
Project Management Tools and Techniques
 
Project Management Summary 2012
Project Management Summary 2012Project Management Summary 2012
Project Management Summary 2012
 

Similar to Managing multiple projects

Project Management Methodology Guidelines
Project Management Methodology GuidelinesProject Management Methodology Guidelines
Project Management Methodology Guidelinesboetabrad
 
Project Management Methodology Guidelines
Project Management Methodology GuidelinesProject Management Methodology Guidelines
Project Management Methodology GuidelinesSyed Umair Javed
 
IT Project Planning Standards V 1.2
IT Project Planning Standards V 1.2IT Project Planning Standards V 1.2
IT Project Planning Standards V 1.2Ahmed303
 
BiometricAccessControlProjectPlanFlat
BiometricAccessControlProjectPlanFlatBiometricAccessControlProjectPlanFlat
BiometricAccessControlProjectPlanFlatKevin Swenson
 
Green Computing Research: Project management report
Green Computing Research: Project management reportGreen Computing Research: Project management report
Green Computing Research: Project management reportMohammad Balgoname, MSc
 
Internal Control & Risk
Internal Control & RiskInternal Control & Risk
Internal Control & RiskEzat Dandashi
 
Reinforced Concrete Project calculation sheet
Reinforced Concrete Project calculation sheetReinforced Concrete Project calculation sheet
Reinforced Concrete Project calculation sheetAbdallah Shaheen
 
organizational transformation research ver. 4
organizational transformation research ver. 4organizational transformation research ver. 4
organizational transformation research ver. 4Irwin Archer
 
Thèse professionnelle sur les indicateurs de performance RSE et le management...
Thèse professionnelle sur les indicateurs de performance RSE et le management...Thèse professionnelle sur les indicateurs de performance RSE et le management...
Thèse professionnelle sur les indicateurs de performance RSE et le management...Chris Delepierre
 
Cementa Ab Applied Process Management Group Iv Report Process Blue Printing
Cementa Ab Applied Process Management Group Iv Report Process Blue PrintingCementa Ab Applied Process Management Group Iv Report Process Blue Printing
Cementa Ab Applied Process Management Group Iv Report Process Blue Printingdzikothunde
 
McGill Project Team Proposal for Bombardier Aviation_20150226
McGill Project Team Proposal for Bombardier Aviation_20150226McGill Project Team Proposal for Bombardier Aviation_20150226
McGill Project Team Proposal for Bombardier Aviation_20150226Leandro Eduardo Cantelli
 
IMechE Report Final_Fixed
IMechE Report Final_FixedIMechE Report Final_Fixed
IMechE Report Final_FixedAmit Ramji ✈
 
IMechE Report Final_Fixed
IMechE Report Final_FixedIMechE Report Final_Fixed
IMechE Report Final_FixedAmit Ramji ✈
 
Islamic banking in Kazakhstan
Islamic banking in KazakhstanIslamic banking in Kazakhstan
Islamic banking in KazakhstanMadi Akmambet
 
Project-Charter-Otolaryngology
Project-Charter-OtolaryngologyProject-Charter-Otolaryngology
Project-Charter-OtolaryngologyChristian Agwumaro
 

Similar to Managing multiple projects (20)

Project Management Methodology Guidelines
Project Management Methodology GuidelinesProject Management Methodology Guidelines
Project Management Methodology Guidelines
 
Project Management Methodology Guidelines
Project Management Methodology GuidelinesProject Management Methodology Guidelines
Project Management Methodology Guidelines
 
IT Project Planning Standards V 1.2
IT Project Planning Standards V 1.2IT Project Planning Standards V 1.2
IT Project Planning Standards V 1.2
 
KAIA Project Management Plan[1]
KAIA Project Management Plan[1]KAIA Project Management Plan[1]
KAIA Project Management Plan[1]
 
Unilever_PM_Hndbk
Unilever_PM_HndbkUnilever_PM_Hndbk
Unilever_PM_Hndbk
 
BiometricAccessControlProjectPlanFlat
BiometricAccessControlProjectPlanFlatBiometricAccessControlProjectPlanFlat
BiometricAccessControlProjectPlanFlat
 
Green Computing Research: Project management report
Green Computing Research: Project management reportGreen Computing Research: Project management report
Green Computing Research: Project management report
 
Internal Control & Risk
Internal Control & RiskInternal Control & Risk
Internal Control & Risk
 
Rtp mod 2.4
Rtp mod 2.4Rtp mod 2.4
Rtp mod 2.4
 
Reinforced Concrete Project calculation sheet
Reinforced Concrete Project calculation sheetReinforced Concrete Project calculation sheet
Reinforced Concrete Project calculation sheet
 
organizational transformation research ver. 4
organizational transformation research ver. 4organizational transformation research ver. 4
organizational transformation research ver. 4
 
Thèse professionnelle sur les indicateurs de performance RSE et le management...
Thèse professionnelle sur les indicateurs de performance RSE et le management...Thèse professionnelle sur les indicateurs de performance RSE et le management...
Thèse professionnelle sur les indicateurs de performance RSE et le management...
 
Cementa Ab Applied Process Management Group Iv Report Process Blue Printing
Cementa Ab Applied Process Management Group Iv Report Process Blue PrintingCementa Ab Applied Process Management Group Iv Report Process Blue Printing
Cementa Ab Applied Process Management Group Iv Report Process Blue Printing
 
McGill Project Team Proposal for Bombardier Aviation_20150226
McGill Project Team Proposal for Bombardier Aviation_20150226McGill Project Team Proposal for Bombardier Aviation_20150226
McGill Project Team Proposal for Bombardier Aviation_20150226
 
IMechE Report Final_Fixed
IMechE Report Final_FixedIMechE Report Final_Fixed
IMechE Report Final_Fixed
 
IMechE Report Final_Fixed
IMechE Report Final_FixedIMechE Report Final_Fixed
IMechE Report Final_Fixed
 
Islamic banking in Kazakhstan
Islamic banking in KazakhstanIslamic banking in Kazakhstan
Islamic banking in Kazakhstan
 
Project Daedalus Final Report
Project Daedalus Final ReportProject Daedalus Final Report
Project Daedalus Final Report
 
Project Daedalus Final Report
Project Daedalus Final Report Project Daedalus Final Report
Project Daedalus Final Report
 
Project-Charter-Otolaryngology
Project-Charter-OtolaryngologyProject-Charter-Otolaryngology
Project-Charter-Otolaryngology
 

Recently uploaded

Introduction to LPC - Facility Design And Re-Engineering
Introduction to LPC - Facility Design And Re-EngineeringIntroduction to LPC - Facility Design And Re-Engineering
Introduction to LPC - Facility Design And Re-Engineeringthomas851723
 
LPC Warehouse Management System For Clients In The Business Sector
LPC Warehouse Management System For Clients In The Business SectorLPC Warehouse Management System For Clients In The Business Sector
LPC Warehouse Management System For Clients In The Business Sectorthomas851723
 
Fifteenth Finance Commission Presentation
Fifteenth Finance Commission PresentationFifteenth Finance Commission Presentation
Fifteenth Finance Commission Presentationmintusiprd
 
Board Diversity Initiaive Launch Presentation
Board Diversity Initiaive Launch PresentationBoard Diversity Initiaive Launch Presentation
Board Diversity Initiaive Launch Presentationcraig524401
 
Reflecting, turning experience into insight
Reflecting, turning experience into insightReflecting, turning experience into insight
Reflecting, turning experience into insightWayne Abrahams
 
LPC Operations Review PowerPoint | Operations Review
LPC Operations Review PowerPoint | Operations ReviewLPC Operations Review PowerPoint | Operations Review
LPC Operations Review PowerPoint | Operations Reviewthomas851723
 
ANIn Gurugram April 2024 |Can Agile and AI work together? by Pramodkumar Shri...
ANIn Gurugram April 2024 |Can Agile and AI work together? by Pramodkumar Shri...ANIn Gurugram April 2024 |Can Agile and AI work together? by Pramodkumar Shri...
ANIn Gurugram April 2024 |Can Agile and AI work together? by Pramodkumar Shri...AgileNetwork
 
Unlocking Productivity and Personal Growth through the Importance-Urgency Matrix
Unlocking Productivity and Personal Growth through the Importance-Urgency MatrixUnlocking Productivity and Personal Growth through the Importance-Urgency Matrix
Unlocking Productivity and Personal Growth through the Importance-Urgency MatrixCIToolkit
 
VIP Kolkata Call Girl Rajarhat 👉 8250192130 Available With Room
VIP Kolkata Call Girl Rajarhat 👉 8250192130  Available With RoomVIP Kolkata Call Girl Rajarhat 👉 8250192130  Available With Room
VIP Kolkata Call Girl Rajarhat 👉 8250192130 Available With Roomdivyansh0kumar0
 
Simplifying Complexity: How the Four-Field Matrix Reshapes Thinking
Simplifying Complexity: How the Four-Field Matrix Reshapes ThinkingSimplifying Complexity: How the Four-Field Matrix Reshapes Thinking
Simplifying Complexity: How the Four-Field Matrix Reshapes ThinkingCIToolkit
 
Pooja Mehta 9167673311, Trusted Call Girls In NAVI MUMBAI Cash On Payment , V...
Pooja Mehta 9167673311, Trusted Call Girls In NAVI MUMBAI Cash On Payment , V...Pooja Mehta 9167673311, Trusted Call Girls In NAVI MUMBAI Cash On Payment , V...
Pooja Mehta 9167673311, Trusted Call Girls In NAVI MUMBAI Cash On Payment , V...Pooja Nehwal
 

Recently uploaded (13)

Introduction to LPC - Facility Design And Re-Engineering
Introduction to LPC - Facility Design And Re-EngineeringIntroduction to LPC - Facility Design And Re-Engineering
Introduction to LPC - Facility Design And Re-Engineering
 
LPC Warehouse Management System For Clients In The Business Sector
LPC Warehouse Management System For Clients In The Business SectorLPC Warehouse Management System For Clients In The Business Sector
LPC Warehouse Management System For Clients In The Business Sector
 
Fifteenth Finance Commission Presentation
Fifteenth Finance Commission PresentationFifteenth Finance Commission Presentation
Fifteenth Finance Commission Presentation
 
Board Diversity Initiaive Launch Presentation
Board Diversity Initiaive Launch PresentationBoard Diversity Initiaive Launch Presentation
Board Diversity Initiaive Launch Presentation
 
Call Girls Service Tilak Nagar @9999965857 Delhi 🫦 No Advance VVIP 🍎 SERVICE
Call Girls Service Tilak Nagar @9999965857 Delhi 🫦 No Advance  VVIP 🍎 SERVICECall Girls Service Tilak Nagar @9999965857 Delhi 🫦 No Advance  VVIP 🍎 SERVICE
Call Girls Service Tilak Nagar @9999965857 Delhi 🫦 No Advance VVIP 🍎 SERVICE
 
Reflecting, turning experience into insight
Reflecting, turning experience into insightReflecting, turning experience into insight
Reflecting, turning experience into insight
 
LPC Operations Review PowerPoint | Operations Review
LPC Operations Review PowerPoint | Operations ReviewLPC Operations Review PowerPoint | Operations Review
LPC Operations Review PowerPoint | Operations Review
 
ANIn Gurugram April 2024 |Can Agile and AI work together? by Pramodkumar Shri...
ANIn Gurugram April 2024 |Can Agile and AI work together? by Pramodkumar Shri...ANIn Gurugram April 2024 |Can Agile and AI work together? by Pramodkumar Shri...
ANIn Gurugram April 2024 |Can Agile and AI work together? by Pramodkumar Shri...
 
Unlocking Productivity and Personal Growth through the Importance-Urgency Matrix
Unlocking Productivity and Personal Growth through the Importance-Urgency MatrixUnlocking Productivity and Personal Growth through the Importance-Urgency Matrix
Unlocking Productivity and Personal Growth through the Importance-Urgency Matrix
 
VIP Kolkata Call Girl Rajarhat 👉 8250192130 Available With Room
VIP Kolkata Call Girl Rajarhat 👉 8250192130  Available With RoomVIP Kolkata Call Girl Rajarhat 👉 8250192130  Available With Room
VIP Kolkata Call Girl Rajarhat 👉 8250192130 Available With Room
 
Simplifying Complexity: How the Four-Field Matrix Reshapes Thinking
Simplifying Complexity: How the Four-Field Matrix Reshapes ThinkingSimplifying Complexity: How the Four-Field Matrix Reshapes Thinking
Simplifying Complexity: How the Four-Field Matrix Reshapes Thinking
 
Pooja Mehta 9167673311, Trusted Call Girls In NAVI MUMBAI Cash On Payment , V...
Pooja Mehta 9167673311, Trusted Call Girls In NAVI MUMBAI Cash On Payment , V...Pooja Mehta 9167673311, Trusted Call Girls In NAVI MUMBAI Cash On Payment , V...
Pooja Mehta 9167673311, Trusted Call Girls In NAVI MUMBAI Cash On Payment , V...
 
sauth delhi call girls in Defence Colony🔝 9953056974 🔝 escort Service
sauth delhi call girls in Defence Colony🔝 9953056974 🔝 escort Servicesauth delhi call girls in Defence Colony🔝 9953056974 🔝 escort Service
sauth delhi call girls in Defence Colony🔝 9953056974 🔝 escort Service
 

Managing multiple projects

  • 2. Dr. Karim El-Dash 2 Contents PROJECT MANAGEMENT .................................................................................................................................... 5  PROJECT MANAGEMENT OFFICE ........................................................................................................................ 6  ROLE OF A PROJECT MANAGER .......................................................................................................................... 6  PROJECT LIFE‐CYCLE ........................................................................................................................................... 8  PROJECT SELECTION .......................................................................................................................................... 10  ESTIMATE CLASSIFICATIONS .............................................................................................................................. 10  PHYSICAL DIMENSIONS METHOD ................................................................................................................................... 11  COMPOUND‐AMOUNT FACTOR ..................................................................................................................................... 12  COMPOUND‐AMOUNT FACTOR: .................................................................................................................................... 13  INTERNAL RATE OF RETURN .......................................................................................................................................... 15  THREE‐POINT ESTIMATES ............................................................................................................................................. 18  ORGANIZATIONAL PROJECT MANAGEMENT MATURITY MODEL ........................................................................... 20  CAPABILITY MATURITY MODEL INTEGRATED ......................................................................................................... 22  PROJECT CHARTER ............................................................................................................................................ 24  COLLECT PROJECT REQUIREMENTS .................................................................................................................................. 24  DEFINE PROJECT SCOPE ................................................................................................................................................ 24  CREATE PROJECT WBS ................................................................................................................................................. 25  DEFINE ACTIVITIES ....................................................................................................................................................... 26  SEQUENCE ACTIVITIES .................................................................................................................................................. 29  ESTIMATE ACTIVITY RESOURCES ..................................................................................................................................... 31  ESTIMATE ACTIVITY DURATION ...................................................................................................................................... 32  DEVELOP SCHEDULE .................................................................................................................................................... 35  ESTIMATE COST .......................................................................................................................................................... 42  CONTROL COST ................................................................................................................................................. 47  PROJECT QUALITY MANAGEMENT ..................................................................................................................... 57  COST‐BENEFIT ANALYSIS ............................................................................................................................................... 59  COST OF QUALITY ........................................................................................................................................................ 59  OPTIMUM QUALITY COST MODEL .................................................................................................................................. 65  CONTROL CHARTS ....................................................................................................................................................... 67  BENCHMARKING ......................................................................................................................................................... 72  DESIGN OF EXPERIMENTS .............................................................................................................................................. 75  STATISTICAL SAMPLING ................................................................................................................................................ 77  FLOWCHARTING .......................................................................................................................................................... 78  PROPRIETARY QUALITY MANAGEMENT METHODOLOGIES ..................................................................................................... 81  SIX SIGMA ................................................................................................................................................................. 81  LEAN SIX SIGMA ......................................................................................................................................................... 83  TOTAL QUALITY MANAGEMENT ..................................................................................................................................... 84  QUALITY FUNCTION DEPLOYMENT ........................................................................................................................ 88  PROCESS IMPROVEMENT PLAN ...................................................................................................................................... 91 
  • 3. Dr. Karim El-Dash 3 QUALITY ASSURANCE ................................................................................................................................................... 93  QUALITY AUDITS ......................................................................................................................................................... 94  QUALITY CONTROL ...................................................................................................................................................... 96  HISTOGRAM ............................................................................................................................................................... 98  CREATING A HISTOGRAM .............................................................................................................................................. 98  RUN CHART ............................................................................................................................................................. 105  SCATTER DIAGRAM .................................................................................................................................................... 109  INSPECTION.............................................................................................................................................................. 113  PROJECT HUMAN RESOURCE MANAGEMENT .................................................................................................. 115  DEVELOP HR PLAN .................................................................................................................................................... 115  ACQUIRE PROJECT TEAM ............................................................................................................................................ 129  DEVELOP PROJECT TEAM ............................................................................................................................................ 129  LEADERS AGAINST MANAGERS ..................................................................................................................................... 133  MANAGE PROJECT TEAM ............................................................................................................................................ 141  PROJECT COMMUNICATION MANAGEMENT ................................................................................................... 148  IDENTIFY STAKEHOLDERS ............................................................................................................................................ 148  PLAN COMMUNICATION ............................................................................................................................................. 151  COMMUNICATION TECHNOLOGY .................................................................................................................................. 154  COMMUNICATION MODELS ......................................................................................................................................... 155  COMMUNICATION METHODS ....................................................................................................................................... 156  MANAGE STAKEHOLDER EXPECTATIONS ........................................................................................................................ 161  PROJECT RISK MANAGEMENT ......................................................................................................................... 166  PLAN RISK MANAGEMENT .......................................................................................................................................... 166  IDENTIFY RISK ........................................................................................................................................................... 172  PERFORM QUALITATIVE RISK MANAGEMENT .................................................................................................................. 180  PERFORM QUANTITATIVE RISK MANAGEMENT ............................................................................................................... 185  PLAN RISK RESPONSES ............................................................................................................................................... 190  MONITOR & CONTROL RISKS ...................................................................................................................................... 197  PROJECT PROCUREMENT MANAGEMENT ........................................................................................................ 198  PLAN PROCUREMENTS ................................................................................................................................................ 198  CONTRACT PROCUREMENTS ........................................................................................................................................ 212  CLOSE PROCUREMENTS .............................................................................................................................................. 219  MANAGING MULTIPLE PROJECTS .................................................................................................................... 220  OVERVIEW ............................................................................................................................................................ 220  PMO AND ORGANIZATIONAL STRUCTURE ........................................................................................................... 238  CUSTOMER MANAGEMENT ................................................................................................................................. 252  COMMUNICATION MANAGEMENT ...................................................................................................................... 253  PROJECT OFFICE MANAGEMENT .......................................................................................................................... 256  KNOWLEDGE MANAGEMENT ............................................................................................................................... 262  PROJECT MANAGEMENT TRAINING ..................................................................................................................... 269  PROJECT RESOURCE MANAGEMENT .................................................................................................................... 271 
  • 5. Dr. Karim El-Dash 5 PROJECT MANAGEMENT  Project management is the discipline of planning, organizing, and managing resources to bring about the successful completion of specific project goals and objectives.  It is often closely related to and sometimes adjunct with program management.  A project is a temporary endeavor, having a defined beginning and end (usually constrained by date, but can be by funding or deliverables), undertaken to meet particular goals and objectives, usually to bring about beneficial change or added value.  The primary challenge of project management is to achieve all of the project goals and objectives while honoring the predetermined project constraints.  Typical constraints are scope, time, and budget. The secondary—and more striving —challenge is to optimize the allocation and integration of inputs necessary to meet pre-defined objectives.
  • 6. Dr. Karim El-Dash 6 Project Management Office  The Project Management Office (PMO) in a business or professional enterprise is the department or group that defines and maintains the standards of process, generally related to project management, within the organization.  The PMO is the source of documentation, guidance and metrics on the practice of project management and execution.  A PMO can be one of three types from an organizational exposure perspective: 1. enterprise PMO, 2. organizational (departmental) PMO, or 3. special–purpose PMO. Role of a Project Manager These three main responsibilities of a project manager are: 1. planning, 2. organizing, and 3. controlling. Performing these responsibilities requires many skills. Some of these necessary skills will be outlined. 1. Planning  The planning function includes defining the project objective and developing a plan to accomplish the objective.  Working with the sponsor is beneficial in many ways. For example, the sponsor is the person responsible for the resultant project and thus has a stake in the success of the project.  The project manager must also develop a plan to accomplish the objective.  The project manager should include project team members in this phase.
  • 7. Dr. Karim El-Dash 7 2. Organizing  The organizing function involves identifying and securing necessary resources, determining tasks that must be completed, assigning the tasks, delegating authority, and motivating team members to work together on the project.  The project manager must then determine what tasks must be completed.  Once this has been done, the tasks should be assigned to project team members or subcontractors.  The project manager may also delegate authority to certain team members to oversee task completion via supervision of those assigned the tasks.  Finally, the project manager must motivate members of the project team to work together in order to complete the goal.  Conflicts may arise and often will occur when individuals working together come from departments with different goals. 3. Controlling  The controlling function involves tracking progress and comparing it with planned progress.  Progress reports should be used to measure performance, as well as identify areas for improvement. Skills Effective project managers must possess a variety of skills in addition to general management skills. These skills include, but are not limited to:  Analytical thinking: the ability to understand overall visions, as well as minute details  Leadership: the ability to inspire team members to execute the plan and successfully complete the project  Communication: the ability to communicate clearly, effectively, and regularly
  • 8. Dr. Karim El-Dash 8  Interpersonal: the ability to develop a relationship with each team member in order to know what motivates them, how they think things are going, what concerns they have, and how they feel about things  Problem-Solving: the ability to anticipate problems, recognize them when they arise, and solve them quickly and efficiently  Human resources: the ability to interview and choose team members with the proper skills and knowledge Project Life-Cycle  A collection of generally sequential, non- overlapping product phases whose names and numbers are determined by the executing and control needs of the organization. The last product life cycle phase for a product is generally the product’s deterioration and death. Generally, a project life cycle is contained within one or more product life cycles.  The project life cycle defines the beginning and the end of a project and various milestones within it.  During the life cycle of a project there will be accomplishments made at each phase. The completion of these accomplishments results in the creation of a ‘‘deliverable,’’ a tangible, verifiable product of the work being done on the project.  These may be products that are delivered external to the project or something needed for other project work to take place, which are considered to be ‘‘internal deliverables.’’
  • 9. Dr. Karim El-Dash 9  In a project’s initial phase, cost and staffing levels are low. At this phase there is the greatest chance that the project will never be completed. Project life-cycle Influence-time relationship in projects
  • 10. Dr. Karim El-Dash 10 PROJECT SELECTION ESTIMATE CLASSIFICATIONS Estimate classifications are commonly used to indicate the overall maturity and quality for the various types of estimates that may be prepared; and most organizations will use some form of classification system to identify and categorize the various types of project estimates that they may prepare during the life cycle of a project. Unfortunately, there is often a lack of consistency and understanding of the terminology used to classify estimates, both across industries as well as within single companies or organizations. AACE identifies five classes of estimates. A Class 5 Estimate is associated with the lowest level of project definition, and a Class 1 Estimate is associated with the highest level of project definition. The following table shows the five classes of estimate. Cost estimate classification
  • 11. Dr. Karim El-Dash 11 PHYSICAL DIMENSIONS METHOD The method uses the physical dimensions (length, area, volume, etc.) of the item being estimated as the driving factor. For example, a building estimate may be based on square meters or cubic meters of the building; whereas pipelines, roadways, or railroads may be based on a linear basis. This method depends on historical information from comparable facilities. Consider the need to estimate the cost of a 3,600-m2 warehouse. A recently completed warehouse of 2,900 m2 in a nearby location was recently completed for KD 623,500, thus costing KD 215/m2 . The completed warehouse utilized a 4.25-m wall height, thus containing 12,325 m3 and resulting in a cost of $50.59/m3 on a volume basis ($623,500/12,325 m3 ). In determining the cost for the new warehouse, we can estimate the new 3,600 m2 warehouse using the m2 basis at $774,000 ($215/m2 x 3,600m2 ). However, the new warehouse will differ from the one just completed by having 5.5-m-high walls; so we may decide that estimating on a volume basis may provide a better indication of costs. The volume of the new warehouse will be 19,800 m3 (3,600 m2 x 5.5m), and the new estimate will be $1,002,000 (rounded to the nearest $1,000). Pricing also includes adjustments to costs for specific project conditions. Depending on the specific cost information used in preparing the estimate, material costs may need to be adjusted for location, materials of construction, or to account for differences between the item being installed and the item you may have an available cost for. Labor hours may require productivity adjustments for a variety of conditions such as weather, amount of overtime, interferences from production, material logistics, congestion, the experience of the labor crews, the level of contamination control, etc. Labor rates may also need to be adjusted for location, crew mix, open shop versus union issues, and specific benefit and burden requirements.
  • 12. Dr. Karim El-Dash 12 Example 1: Use the provided time index table to estimate the cost of a building that contains 4,500 m2 of floor area. The building is to be built two years from now. A building that contains 6,800 m2 of floor area in a similar location had a cost of KD 1,321,800 two years ago. Solution: Cost = Historical cost X size adjustment factor X Time adjustment factor Historical cost = KD 1,321,800 Size adjustment factor = 4,500/6,800 = 0.662 Time adjustment factor = (1+i)n where; i = inflation annual rate n = number of years in difference From historical data in table: Time factor = 126/110 = (1+i)3 i = 0.046 = 4.6% Time adjustment factor = (1+0.046)4 = 1.198 Estimated cost = KD 1,321,800 X 0.662 X 1.198 = KD 1,048,287 COMPOUND-AMOUNT FACTOR Given a present sum P invested for N interest periods at interest rate i, what sum will have accumulated at the end of the N periods? You probably noticed right away that this description matches the case we first encountered in describing compound interest. To solve for F (the future sum); we use: F = P (1 + i)N Based on this equation a present value of $20,000 at interest rate of 12% may be evaluated after 15 years by substitution in the equation as follows: Year Index 3 years ago 110 2 years ago 120 1 year ago 128 Current year 126
  • 13. Dr. Karim El-Dash 13 F = 20,000 (1 + 0.12)15 = $ 109,471 Because of its origin in the compound-interest calculation, the factor (1 + i) N is known as the compound-amount factor. Like the concept of equivalence, this factor is one of the foundations of engineering economic analysis. Given this factor, all other important interest formulas can be derived. To specify how the interest tables are to be used, we may also express that factor in a functional notation as (F/P, i, N), which is read as "Find F, given P, i, and N." This factor is known as the single-payment compound- amount factor. When we incorporate the table factor into the formula, the formula is expressed as follows: F = P (1+i)N = P(F/P, i, N) Thus, where we had F = $20,000(1.12)15 , we can now write F = $20,000(F/P, 12%, 15). The table factor tells us to use the 12%-interest table and find the factor in the F/P column for N = 15. Because using the interest tables is often the easiest way to solve an equation, this factor notation is included for each of the formulas derived in the upcoming sections. COMPOUND-AMOUNT FACTOR: Find F, Given A, i, and W Suppose we are interested in the future amount F of a fund to which we contribute A dollars each period and on which we earn interest at a rate of i per period. The contributions are made at the end of each of the N periods. If an amount A is invested at the end of each period for N periods, the total amount F that can be withdrawn at the end of N periods will be the sum of the compound amounts of the individual deposits. This could be calculated as per: ),,/( 1)1( NiAFA i i AF N        
  • 14. Dr. Karim El-Dash 14 The following table shows the different statuses for discrete compounding formulas with discrete payments.
  • 15. Dr. Karim El-Dash 15 Example 2: A feasibility study is being prepared for a project with KD 2,400,000 initial cost and KD 360,000 equivalent uniform annual running cost. What is the required net annual income to satisfy MARR of 15% return, assuming the life-cycle of the project is 20 years? Solution: Assume the required annual income is Y: Present value of accumulated annual income at discount rate 15% = Present value of accumulated expenses at discount rate 15% Y(P/A, 15%, 20) = 2,400,000 + 360,000 ((P/A, 15%, 20) 6.2593 Y = 2,400,000 + 360,000 * 6.2593 6.2593 Y = 4,653,348 Y = 743,429 KD/year INTERNAL RATE OF RETURN The internal rate of return (IRR) is the most difficult equation to calculate all the cash flow techniques. It is a complicated formula and should be performed on a financial calculator or computer. IRR can be figured manually, but it’s a trial-and-error approach to get to the answer. Technically speaking, IRR is the discount rate when the present value of the cash inflows equals the original investment. When choosing between projects or when choosing alternative methods of doing the project, projects with higher IRR values are generally considered better than projects with low IRR values.
  • 16. Dr. Karim El-Dash 16 Example 3: Compare the IRR for the shown data of projects A and B. Using PW values. Assume that all expenses are incurred at the end of the year. Assume discount rate; i=5%. Project A Project B Cash Flow Cash Flow Year 1 (20,000) (10,000) Year 2 (1,000) (4,000) Year 3 5,000 3,000 Year 4 20,000 15,000 Solution: Assume IRR=5% for both projects: Project A Project B PV@5% PV@5% Year 1 (20,000) (10,000) Year 2 (952) (3,810) Year 3 4,535 2,721 Year 4 17,277 12,958 860 1,869 IRR > 5% for both projects
  • 17. Dr. Karim El-Dash 17 Try IRR = 8% Project A Project B PV@8% PV@8% Year 1 (20,000) (10,000) Year 2 (926) (3,704) Year 3 4,287 2,572 Year 4 15,877 11,907 (763) 776 IRR for Project A is less than 8% IRR for Project B is more than 8% By several trials it is found to have IRR for project A 6.5% and IRR for project B is 10.4%.
  • 18. Dr. Karim El-Dash 18 THREE-POINT ESTIMATES Three-point estimates, use three estimates that are averaged to come up with a final estimate. The three estimates are the most likely, optimistic, and pessimistic. You’ll want to rely on experienced people to give you these estimates. The most likely estimate assumes there are no disasters and the activity can be completed as planned. The optimistic estimate is the fastest time frame in which your resource can complete the activity. And the pessimistic estimate assumes the worst happens and it takes much longer than planned to get the activity completed. You’d average these three estimates to come up with an overall estimate. In this approach the mean and standard deviation are calculated as per the following equations: 6 4 cpessimistilikelymostXoptimistic Mean   6 deviationStandard optimisticcpessimisti  
  • 19. Dr. Karim El-Dash 19 Example 4: It is required to estimate the cost of a parking deck with capacity of 550 cars. The following table shows the cost of eight decks with different capacities adjusted for time and location. Using the three-point-estimate method, find the expected cost of the parking deck. Deck Cost KD No. of cars Unit cost KD/car 1 141,200 150 2 372,250 250 3 266,500 260 4 476,480 320 5 474,600 350 6 804,080 460 Solution: Calculate unit cost/car for each deck: Deck Cost KD No. of cars Unit cost KD/car 1 141,200 150 1,358 2 372,250 250 1,489 3 266,500 260 1,025 4 476,480 320 1,489 5 474,600 350 1,356 6 804,080 460 1,748 Average unit cost /car = 6 748,1356,1489,1025,1489,1358,1  =1410.8 KD/car Minimum (optimistic) unit cost /car = 1,025 KD/car Maximum (pessimistic) unit cost/car = 1,748 KD/car Expected mean value = 6 748,18.410,1*4025,1  = 1,402.7 KD/car Total estimated cost of the deck = 1402 * 550 = 771,100 KD
  • 20. Dr. Karim El-Dash 20 ORGANIZATIONAL PROJECT MANAGEMENT MATURITY MODEL The Organizational Project Management Maturity Model or OPM3 is a globally recognized best-practice standard for assessing and developing capabilities in Portfolio Management, Program Management, and Project Management. It was published by the company Project Management Institute Incorporated (PMI). OPM3 provides a method for organizations to understand their Organizational Project Management processes and measure their capabilities in preparation for improvement. OPM3 then helps organizations develop the roadmap that the company will follow to improve performance. OPM3 covers the domains of Organizational Project Management, the systematic management of projects, programs, and portfolios in alignment with the achievement of strategic goals. Organizational Project Management; the three domains are Project Management, Program
  • 21. Dr. Karim El-Dash 21 Management and Portfolio Management. OPM3 uniquely integrates these domains into one maturity model. OPM3 offers the key to Organizational Project Management (OPM) with three interlocking elements:  Knowledge - Learn about hundreds of Organizational Project Management (OPM) best practices.  Assessment - Evaluate an organization’s current capabilities and identify areas in need of improvement.  Improvement - Use the completed assessment to map out the steps needed to achieve performance improvement goals. As with other PMI Inc. standards, OPM3’s intent is not to be prescriptive by telling the user what improvements to make or how to make them. Rather, OPM3 provides guidelines regarding the kinds of things an organization may do in order to achieve excellence in Organizational Project Management.
  • 22. Dr. Karim El-Dash 22 CAPABILITY MATURITY MODEL INTEGRATED Capability Maturity Model Integration (CMMI) is a process improvement approach that helps organizations improve their performance. CMMI can be used to guide process improvement across a project, a division, or an entire organization. CMMI in software engineering and organizational development is a trademarked process improvement approach that provides organizations with the essential elements for effective process improvement. According to the Software Engineering Institute (SEI, 2008), CMMI helps "integrate traditionally separate organizational functions, set process improvement goals and priorities, provide guidance for quality processes, and provide a point of reference for appraising current processes."
  • 23. Dr. Karim El-Dash 23 CMMI currently addresses three areas of interest:  Product and service development — CMMI for Development (CMMI- DEV),  Service establishment, management, and delivery — CMMI for Services (CMMI-SVC), and  Product and service acquisition — CMMI for Acquisition (CMMI- ACQ). CMMI was developed by a group of experts from industry, government, and the Software Engineering Institute (SEI) at Carnegie Mellon University. CMMI models provide guidance for developing or improving processes that meet the business goals of an organization. A CMMI model may also be used as a framework for appraising the process maturity of the organization. CMMI originated in software engineering but has been highly generalized over the years to embrace other areas of interest, such as the development of hardware products, the delivery of all kinds of services, and the acquisition of products and services. The word "software" does not appear in definitions of CMMI. This generalization of improvement concepts makes CMMI extremely abstract.
  • 24. Dr. Karim El-Dash 24 PROJECT CHARTER The project charter is the written acknowledgment that the project exists. The project charter names the project manager and gives that person the authority to assign organizational resources to the project. COLLECT PROJECT REQUIREMENTS Requirements describe the characteristics of the project deliverables. They might also describe functionality that the deliverable must have or specific conditions the deliverable must meet in order to satisfy the objective of the project. According to the PMBOK Guide, requirements are conditions that must be met or criteria that the product or service of the project must possess in order to satisfy the project documents, a contract, a standard, or a specification. Requirements quantify and prioritize the wants, needs, and expectations of the project sponsor and stakeholders. Requirements might include elements such as dimensions, ease of use, color, specific ingredients, and so on. DEFINE PROJECT SCOPE Project Scope Management encompasses both product scope and project scope. Product scope concerns the characteristics of the product, service, or result of the project. It’s measured against the product requirements to determine successful completion or fulfillment. The application area usually dictates the process tools and techniques you’ll use to define and manage product scope. Project scope involves managing the work of the project and only the work of the project. Project scope is measured against the project management plan, the project scope statement, the work breakdown structure (WBS), and the WBS dictionary.
  • 25. Dr. Karim El-Dash 25 To ensure a successful project, both product and project scope must be well integrated. This implies that Project Scope Management is well integrated with the other Knowledge Area processes. Scope Planning, Scope Definition, Create WBS, Scope Verification, and Scope Control involve the following:  Detailing the requirements of the product of the project  Verifying those details using measurement techniques  Creating a project scope management plan  Creating a WBS  Controlling changes to these processes CREATE PROJECT WBS The PMBOK Guide describes a WBS as “a deliverable-oriented hierarchical decomposition of the work to be executed by the project team, to accomplish the project objectives and create the required deliverables. The
  • 26. Dr. Karim El-Dash 26 WBS defines the total scope of the project.” Simply put, a WBS is a deliverable-oriented hierarchy that defines and organizes the work of the project and only the work of the project. Like the scope statement, the WBS serves as a foundational agreement among the stakeholders and project team members regarding project scope. The WBS will be used throughout many of the remaining Planning processes and is an important part of project planning. The project charter and project scope statement outline the project goals and major deliverables. The project scope statement further refines these deliverables into an exhaustive list and documents the requirements of the deliverables. Project management team uses that comprehensive list of deliverables produced in the project scope statement to build the framework of the WBS. DEFINE ACTIVITIES Activity Definition and Activity Sequencing are separate processes, each with their own inputs, tools and techniques, and outputs. In practice, especially for small- to medium-sized projects, the planner can combine these processes into one process or step. The Activity Definition process is a further breakdown of the work package elements of the WBS. It documents the specific activities needed to fulfill the deliverables detailed on the WBS. This process might be performed by the project manager, or when the WBS is broken down to the subproject level, this process (and all the Activity-related processes that follow) might be assigned to a subproject manager.  Decomposition Decomposition is the process of breaking the work packages into smaller, more manageable units of work called schedule activities. These are not deliverables but the individual units of work that must be completed to fulfill the deliverables. Activity lists (which are one of
  • 27. Dr. Karim El-Dash 27 the outputs of this process) from prior projects can be used as templates in this process.  Rolling Wave Planning Rolling wave planning is the process of planning for a project in waves as the project becomes clearer and unfolds. It is important in such projects to at least highlight in the initial plan the key milestones for the project. Rolling Wave Planning acknowledges the fact that we can see more clearly what is in close proximity, but looking further ahead our vision becomes less clear. Rolling Wave Planning is a multi-step, intermittent process like waves - because we cannot provide the details very far out in our planning. Depending upon the project - its length and complexity - we may be able to plan as much as a few weeks or even a few months in advance with a fair amount of clarity. This involves creating a detailed, well-defined Work Breakdown Structure (WBS) for that period of clarity, but just highlighting the milestone for the rest of the project.
  • 28. Dr. Karim El-Dash 28  Activity Attributes Activity attributes typically refers to the specific components that make up an activity. These can include descriptive factors of the activity at the onset, or can also refer specific characteristics that may become relevant at a later phase of an activity. Activity attributes can be sorted, organized, and/or summarized according to some specific categories. Some types of activity attributes can include those related to time needed to complete specific components, costs related to completion of an activity or of some specific components, activity codes, responsible persons and/or persons involved in the activity, specific locations in which the activity may be taking place, and/or other miscellaneous categories into which these attributes can be conveniently and appropriately organized. Activity attributes can also include discussion of specific constraints that may make completion more difficult.  Milestones A milestone is the end of a stage that marks the completion of a work package or phase, typically marked by a high level event such as completion, endorsement or signing of a deliverable, document or a high level review meeting. In addition to signaling the completion of a key deliverable, a milestone may also signify an important decision or the derivation of a critical piece of information, which outlines or affects the future of a project. In this sense, a milestone not only signifies distance traveled (key stages in a project) but also indicates direction of travel since key decisions made at milestones may alter the route through the project plan.
  • 29. Dr. Karim El-Dash 29 SEQUENCE ACTIVITIES  Logical Relationships Each activity has a start and a finish. A single logic relationship describes the interdependency of starts and finishes between two activities. There are four possible relationships between an activity’s start and finish, and those of other activities. The most commonly used relationship between two activities is finish- to-start (FS), wherein the first activity must finish before the second activity can start. A second type is finish-to-finish (FF), where two activities must complete at the same time. The third type is start-to- start (SS), where two activities start at the same time (regardless of their finish dates). The fourth is start-to-finish (SF), where an activity must start before a second activity can finish. Activities can be linked with hard logic (i.e., sequence of each activity is predetermined, such as footing A before footing B), or soft logic wherein related activities may be combined and accomplished in a different order as determined at the time of execution. There are also physical hard logic relationships where soft logic does not normally apply, such as footing formwork must be in place before concrete can be placed.  Leads and Lags Lag time can be applied to all four relationship types. Lags are timing applied to logic; they consume time, but are not activities per se. For example, lags can be used to define that footing formwork needs to remain in place until concrete is properly cured. Lead time is overlap between tasks that have a dependency. For example, if a task can start when its predecessor is half finished, you can specify a finish-to- start dependency with a lead time of 50 percent for the successor task. You enter lead time as a negative value.
  • 30. Dr. Karim El-Dash 30  Schedule Network The project schedule is a fairly broad and all encompassing concept that while seemingly easy to grasp, must truly be mastered in order for all members of the project staff, from the project management team all the way up to the project management team leader to effectively manage the project in a capable manner from start to finish. The project schedule typically will include all elements of the project from the pre-planning stages of the project through all ongoing project processes that may take place during the active project period, to any and all project related process that may occur at the c o n c l u s i on and or closing stages of the project. The project schedule network diagram typically refers to a particular input/output mechanism that represents a particular schematic display of any and all logical relationships that may exist between the existing project schedule activities. The project schedule network diagram when properly laid out is always laid in a left to right display to properly reflect the chronology of all project work.
  • 31. Dr. Karim El-Dash 31 ESTIMATE ACTIVITY RESOURCES  Resource breakdown structure Resource Breakdown Structure (RBS) is a standardized list of personnel, material, equipment resources related by function and arranged in a hierarchical structure. The Resource Breakdown Structure standardizes the departments resources to facilitate planning and controlling of project work. It defines assignable resources such as personnel, from a functional point of view; it identifies "who" is doing the work. The total resources define the Top Level, and each subsequent level is a subset of the resource category (or level) above it. Each descending (lower) level represents an increasingly detailed description of the resource until small enough to be used in conjunction with the Work Breakdown Structure (WBS) to allow the work to be planned, monitored and controlled.  Bottom-up Estimate Bottom-up estimating is an extremely helpful technique in project management as it allows for the ability to get a more refined estimate of a particular component of work. In bottom-up estimating, each task is broken down into smaller components. Then, individual estimates are developed to determine what specifically is needed to meet the requirements of each of these smaller components of the work. The Project Materials Equipments Manpower Subcontracto Concrete Steel Wood Ceramic Foundation Second floor First floor
  • 32. Dr. Karim El-Dash 32 estimates for the smaller individual components are then aggregated to develop a larger estimate for the entire task as a whole. In doing this, the estimate for the task as a whole is typically far more accurate, as it allows for careful consideration of each of the smaller parts of the task and then combining these carefully considered estimates rather than merely making one large estimate which typically will not as thoroughly consider all of the individual components of a task. ESTIMATE ACTIVITY DURATION  Analogous Estimating Analogous Estimating is an estimating technique with the following characteristics: o Estimates are based on past projects (historical information). o It is less accurate when compared to bottom-up estimation. o It is a top-down approach. o It takes less time when compared to bottom-up estimation. o It is a form of an expert judgment.  Parametric Estimating A parametric cost model is an extremely useful tool for preparing early conceptual estimates when there is little technical data or engineering deliverables to provide a basis for using more detailed estimating methods. A parametric model is a mathematical representation of cost relationships that provide a logical and predictable correlation between the physical or functional characteristics of a plant (or process system) and its resultant cost. A parametric estimate comprises cost estimating relationships and other parametric estimating functions that provide logical and repeatable relationships between independent variables, such as
  • 33. Dr. Karim El-Dash 33 design parameters or physical characteristics and the dependent variable, cost. Capacity factor and equipment factor estimates are simple examples of parametric estimates; however sophisticated parametric models typically involve several independent variables or cost drivers. Yet similar to those estimating methods, parametric estimating is reliant on the collection and analysis of previous project cost data in order to develop the cost estimating relationships (CER’s).  Three-Point-Estimating The Three Point Estimation technique is based on statistical methods, and in particular, the Normal distribution. In Three Point Estimation we produce three figures for every estimate: a = the best case estimate m = the most likely estimate b = the worst case estimate These values are used to calculate an E value for the estimate and a Standard Deviation (SD) where: 6 4 bma E   6 ab SD   E is a weighted average which takes into account both the most optimistic and pessimistic estimates provided and SD measures the variability or uncertainty in the estimate.
  • 34. Dr. Karim El-Dash 34 To produce projects estimate the Project Manager: 1. Decomposes the project into a list of estimable tasks, i.e. a Work Breakdown Structure 2. Estimates each the E value and SD for each task. 3. Calculates the E value for the total project work as:  E(Tasks)E(Project) 4. Calculates the SD value for the total project work as:  2 SD(Tasks))SD(Project We then use the E and SD values to convert the project estimates to Confidence Levels as follows:  Confidence Level in E value is approximately 50%  Confidence Level in E value + SD is approximately 68%  Confidence Level in E value + 2 * SD is approximately 95%  Confidence Level in E value + 3 * SD is approximately 99.7%
  • 35. Dr. Karim El-Dash 35  Reserve Analysis In terms of the project management scope of work and work flow, the concept of reserve analysis actually refers to a specific technique that of often implemented by the project management team and or the project management team leader or leaders for the purposes of helping to better maintain and manage the projects that they may have under their guise at that respective time. Specifically, the technique of reserve analysis is a particular analytical technique that is used by the project management team and or the project management team leader for the purposes of making a complete and thorough determination of what the entirety of the specific and exact features and or in many cases relationships of all of the individual project related components that currently exist as part of the previously determined project management plan. The purpose of the execution and implementation of a reserve analysis is for the purpose of establishing and determining an estimated reserve that can be used for the purposes of establishing schedule duration, any and all estimated costs, the budget, as well as the complete funds assigned or allocated to the project. DEVELOP SCHEDULE  Critical Path Method The critical path method (CPM) is a scheduling technique using arrow, precedence, or PERT diagramming methods to determine the length of a project and to identify the activities and constraints on the critical path. The critical path method enables a scheduler to do the following: • Determine the shortest time in which a program or project can be completed. • Identify those activities that are critical and that cannot be slipped or delayed. • Show the potential slippage or delay (known as float) available for activities that are not critical.
  • 36. Dr. Karim El-Dash 36 The critical path method (CPM) was designed for, and is useful on, projects where the duration of each activity can be estimated with reasonable certainty; it predicts how long an endeavor will take to complete. It also identifies the activities that control the overall length of the project. CPM is widely used in the process industries, construction, single industrial projects, prototype development, and for controlling plant outages and shutdowns.  Critical Chain Method Critical Chain Method (CCM) is a method of planning and managing projects that puts the main emphasis on the resources required to execute project tasks. It was developed by Eliyahu M. Goldratt. This is in contrast to the more traditional Critical Path and PERT methods, which emphasize task order and rigid scheduling. A Critical Chain project network will tend to keep the resources levelly loaded, but will require them to be flexible in their start times and to quickly switch between tasks and task chains to keep the whole project on schedule. The critical chain is the sequence of both precedence and resource dependent terminal elements that prevents a project from being completed in a shorter time, given finite resources. If resources are always available in unlimited quantities, then a project's critical chain is identical to its critical path. Critical chain is used as an alternative to critical path analysis. The main features that distinguish the critical chain from the critical path are: 1. The use of (often implicit) resource dependencies. Implicit means that they are not included in the project network but have to be identified by looking at the resource requirements. 2. Lack of search for an optimum solution. This means that a "good enough" solution is enough because:
  • 37. Dr. Karim El-Dash 37 a) As far as is known, there is no analytical method of finding an absolute optimum (i.e. having the overall shortest critical chain). b) The inherent uncertainty in estimates is much greater than the difference between the optimum and near-optimum ("good enough" solutions). 3. The identification and insertion of buffers: o project buffer o feeding buffers o resource buffers. (Most of time it is observed that companies are reluctant to give more resources) Monitoring project progress and health by monitoring the consumption rate of the buffers rather than individual task performance to schedule. CCM aggregates the large amounts of safety time added to many subprojects in project buffers to protect due-date performance, and to avoid wasting this safety time through bad multitasking, student syndrome, Parkinson's Law and poorly synchronized integration. Critical chain method uses buffer management instead of earned value management to assess the performance of a project. Some project managers feel that the earned value management technique is misleading, because it does not distinguish progress on the project constraint (i.e. on the critical chain) from progress on non-constraints (i.e. on other paths). Event chain methodology can be used to determine a size of project, feeding, and resource buffers.  Resource Leveling Resource leveling is a project management process used to examine a project for an unbalanced use of resources over time, and for resolving over-allocations or conflicts. When performing project planning activities, the manager will attempt to schedule certain tasks simultaneously. When more resources such as machines or people are needed than are available, or perhaps a specific person is needed in both tasks, the tasks will have to be
  • 38. Dr. Karim El-Dash 38 rescheduled concurrently or even sequentially to manage the constraint. Project planning resource leveling is the process of resolving these conflicts. It can also be used to balance the workload of primary resources over the course of the project, usually at the expense of one of the traditional triple constraints (time, cost, scope). When using specially designed project software, leveling typically means resolving conflicts or over allocations in the project plan by allowing the software to calculate delays and update tasks automatically. Project management software leveling requires delaying tasks until resources are available. In either definition, leveling could result in a later project finish date if the tasks affected are in the critical path. Resource Leveling is also useful in the world of maintenance management. Many organizations have maintenance backlogs. These backlogs consist of work orders. In a "planned state" these work orders have estimates such as 2 electricians for 8 hours. These work orders have other attributes such as report date, priority, asset operational requirements, and safety concerns. These same organizations have a need to create weekly schedules. Resource- leveling can take the "work demand" and balance it against the resource pool availability for the given week. The goal is to create this weekly schedule in advance of performing the work. Without resource-leveling the organization (planner, scheduler, supervisor) is most likely performing subjective selection. For the most part, when it comes to maintenance scheduling, there are very few logic ties and therefore no need to calculate critical path and total float.  Crashing Crashing is a process of expediting project schedule by compressing the total or partial project duration. It is helpful when managers want to avoid incoming bad weather season or to compensate for prior delay. However, the downside is that more resources are needed to speed-up a part of a project, even if resources may be withdrawn
  • 39. Dr. Karim El-Dash 39 from one facet of the project and used to speed-up the section that is lagging behind. Moreover, that may also depend on what slack is available in a non-critical activity, thus resources can be reassigned to critical project activity. Hence, extreme care should be taken to make sure that appropriate activities are being crashed and that diverted resources are not causing needless risk and project scope integrity.  Fast Tracking Fast tracking is a technique that is often implemented in crisis and/or crunch times so to speak as it involves in taking a specific schedule activity and/or work breakdown event that has been previously scheduled and/or is underway and expediting it in some way or another. Fast tracking is referred to as a project schedule compression technique of sorts in that its intent is to take an entire schedule of a project and attempting to compress it into a smaller period of time by conducting some events either quicker or by doing some events that were intended to be done in a more spaced out manner but rather doing some of them simultaneously. The network logic has essentially been changed allowing for some items that would otherwise have been done in a sequence are instead overlapped as such.  Bar Chart (Gantt Chart) A Gantt chart is a type of bar chart that illustrates a project schedule. Gantt charts illustrate the start and finish dates of the terminal activity and summary elements of a project. Terminal activity and summary activities comprise the work breakdown structure of the project. Some Gantt charts also show the dependency (i.e. precedence network) relationships between activities. Gantt charts can be used to show current schedule status using percent-complete shadings and a vertical "TODAY" line.
  • 40. Dr. Karim El-Dash 40 Although now regarded as a common charting technique, Gantt charts were considered revolutionary when they were introduced. In recognition of Henry Gantt's contributions, the Henry Laurence Gantt Medal is awarded for distinguished achievement in management and in community service. Schedule Baseline The schedule baseline is the final approved version of the project schedule with baseline start and baseline finish dates and resource assignments. The PMBOK Guide notes that this baseline is derived from a schedule network analysis of the schedule model. In practice, for small- to medium-sized projects, you can easily complete Activity Definition, Activity Sequencing, Activity Resource Estimating, Activity Duration Estimating, and Schedule Development at the same time with the aid of good project management software. It is easy to produce Gantt charts, critical path, resource allocation, activity dependencies, what-if analysis, and various reports after plugging your scheduling information in to most project management software tools. Regardless of the methods, be certain to obtain sign-off of the project schedule and provide stakeholders and project sponsor with regular updates. And keep the schedule handy—there will likely be changes and modifications as you go. Also, make certain to save a schedule baseline for comparative purposes. Once you get into the Executing and Monitoring and
  • 41. Dr. Karim El-Dash 41 Controlling processes, you’ll be able to compare what you planned to do against what actually happened. Schedule Baseline
  • 42. Dr. Karim El-Dash 42 ESTIMATE COST  Analogous Estimating Analogous Estimating, is one form of expert judgment and it also known as Top-down Estimating. This technique is used to determine the duration of the project. After finalizing the high level scope/requirement, the PM will refer & compare the previously completed project’s similar activities with the current activities and determine the duration. This estimation technique will be applied to determine the duration when the detailed information about the project is not available, usually during the early stages of the project. This technique will look the scope/requirement as a whole single unit to estimate. This estimate will give a ball-park idea about the estimation and will have bigger variance. Eg : To estimate the time required to complete the project of upgrading XYZ application’s database version to a higher version, is to compare similar past projects and estimate the duration. This is done irrespective of the complexity, size and other factors.  Parametric Estimating Parametric estimating is one of the tools and technique of processes like Activity Duration Estimating, Cost Estimating, Cost Budgeting. Parametric estimating is a quantitatively based estimating method that multiplies the quantity of work by the rate. This estimate is by multiplying a known element like the quantity of materials needed by the time it takes to install or complete one unit of materials. The result is a total estimate for the activity. In this case, 10 servers multiplied by 16 hours per server gives you a 160- hour total duration estimate.
  • 43. Dr. Karim El-Dash 43  Three-Point-Estimating The three-point estimation technique is based on statistical methods, and in particular, the normal distribution. Three-point estimation is the preferred estimation technique for information systems (IS) projects. In the three-point estimation there are three figures produced for every estimate: a = the best-case estimate m = the most likely estimate b = the worst-case estimate These values are used to calculate an E value for the estimate and a standard deviation (SD) where: E = (a + 4m + b) / 6 SD = (b − a)/6 E is a weighted average which takes into account both the most optimistic and most pessimistic estimates provided. SD measures the variability or uncertainty in the estimate. In Project Evaluation and Review Techniques (PERT) the three values are used to fit a Beta distribution for Monte Carlo simulations. To produce a project estimate the project manager:  Decomposes the project into a list of estimable tasks, i.e. a work breakdown structure  Estimates each the E value and SD for each task.  Calculates the E value for the total project work as E (Project Work) = Σ E (Task)  Calculates the SD value for the total project work as SD (Project Work) = √Σ SD (Task)2 The E and SD values are then used to convert the project estimates to confidence levels as follows:  Confidence level in E value is approximately 50%  Confidence level in E value + SD is approximately 85%
  • 44. Dr. Karim El-Dash 44  Confidence level in E value + 1.645 × SD is approximately 95%  Confidence level in E value + 2 × SD is approximately 98%  Confidence level in E value + 3 × SD is approximately 99.9% Information Systems uses the 95% confidence level, i.e. E Value + 1.645 × SD, for all project and task estimates. These confidence level estimates assume that the data from all of the tasks combine to be approximately normal. Typically, there would need to be 20–30 tasks for this to be reasonable, and each of the estimates E for the individual tasks would have to be unbiased.  Reserve Analysis Reserves or Contingency allowances are used to deal with uncertainty or “known-unknowns” and these are added to the cost estimates, thus sometimes overstating project costs. Options vary between grouping similar activities and assigning a single contingency reserve for that group to a zero duration activity. This activity may be placed across the network path for that group of schedule activities. As the schedule progresses, the reserve can be adjusted. Creating a buffer activity in the critical chain method at the end of the network path as the schedule progresses, allows the reserve to be adjusted. Reserve or contingency means adding a portion of cost/time to the activity to account for cost/time risk. You might choose to add a percentage of cost/time or a set number of work to the activity or the overall budget/schedule. For example, you know it will take $1000 to run new cable based on the quantitative estimate you came up with earlier. You also know that sometimes you hit problem areas when running the cable. To make sure you don’t impact the project budget, you build in a reserve of 10 percent of your original estimate to account for the
  • 45. Dr. Karim El-Dash 45 problems you might encounter. This brings your activity duration estimate to $1100 hours for this activity.  Cost of Quality Cost of Quality (COQ) is a measurement used for assessing the waste or losses from some defined process (eg. machine, production line, plant, department, company, etc.). Recognizing the power and universal applicability of Cost of Quality (COQ), PQA has developed numerous proprietary Cost of Quality (COQ) systems for ensuring the effectiveness of Cost of Quality (COQ) implementations. The Cost of Quality (COQ) measurement can track changes over time for one particular process, or be used as a benchmark for comparison of two or more different processes (eg. two machines, different production lines, sister plants, two competitor companies, etc.).
  • 46. Dr. Karim El-Dash 46 Most COQ systems are defined by use of 4 categories of costs: COQ Category Typical Descriptions (may vary between different Organizations) Examples Internal Costs associated with internal losses (ie. within the process being analyzed) off-cuts, equipment breakdowns, spills, scrap, yield, productivity External Costs external the process being analyzed (ie. occur outside, not within). These costs are usually discovered by, or affect third parties (eg. customers). Some External costs may have originated from within, or been caused, created by, or made worse by the process being analyzed. They are defined as External because of where they were discovered, or who is primarily or initially affected. customer complaints, latent defects found by the customer, warranty Preventive Costs associated with the prevention of future losses: (eg. unplanned or undesired problems, losses, lost opportunities, breakdowns, work stoppages, waste, etc.) planning, mistake- proofing, scheduled maintenance, quality assurance Assessment Costs associated with measurement and assessment of the process. KPI's, inspection, quality check, dock audits, third party audits, measuring devices, reporting systems, data collection systems, forms  Vendor-Bid-Analysis In a competitive bid process, you can apply vendor bid analysis to determine how much a project should cost. Comparing bids can help you determine the most likely cost for each deliverable, which will allow for a more accurate project cost estimate.
  • 47. Dr. Karim El-Dash 47 Control Cost Earned Value management Earned value management (EVM) is a project management technique for measuring project progress in an objective manner. EVM has the ability to combine measurements of scope, schedule, and cost in a single integrated system. When properly applied, EVM provides an early warning of performance problems. Additionally, EVM promises to improve the definition of project scope, prevent scope creep, communicate objective progress to stakeholders, and keep the project team focused on achieving progress. Essential features of any EVM implementation include 1. a project plan that identifies work to be accomplished, 2. a valuation of planned work, called Planned Value (PV) or Budgeted Cost of Work Scheduled (BCWS), and 3. pre-defined “earning rules” (also called metrics) to quantify the accomplishment of work, called Earned Value (EV) or Budgeted Cost of Work Performed (BCWP). EVM implementations for large or complex projects include many more features, such as indicators and forecasts of cost performance (over budget or under budget) and schedule performance (behind schedule or ahead of schedule). However, the most basic requirement of an EVM system is that it quantifies progress using PV and EV. Project tracking without EVM It is helpful to see an example of project tracking that does not include earned value performance management. Consider a project that has been planned in detail, including a time-phased spend plan for all elements of work. Figure 1 shows the cumulative budget for this project as a function of time (the blue line, labeled PV). It also shows the cumulative actual cost of the project (red line) through week 8. To those unfamiliar with EVM, it might appear that this project was over budget through week 4 and then under budget from week 6 through week 8. However, what is missing from this
  • 48. Dr. Karim El-Dash 48 chart is any understanding of how much work has been accomplished during the project. If the project were actually completed at week 8, then the project would actually be well under budget and well ahead of schedule. If, on the other hand, the project is only 10% complete at week 8, the project is significantly over the budget and behind schedule. A method is needed to measure technical performance objectively and quantitatively, and that is what EVM accomplishes. Project tracking with EVM Consider the same project, except this time the project plan includes pre- defined methods of quantifying the accomplishment of work. At the end of each week, the project manager identifies every detailed element of work that has been completed, and sums the PV for each of these completed elements. Earned value may be accumulated monthly, weekly, or as progress is made. Earned value (EV) Figure 2 shows the EV curve (in green) along with the PV curve from Figure 1. The chart indicates that technical performance (i.e., progress) started more rapidly than planned, but slowed significantly and fell behind
  • 49. Dr. Karim El-Dash 49 schedule at week 7 and 8. This chart illustrates the schedule performance aspect of EVM. It is complementary to critical path or critical chain schedule management. Figure 3 shows the same EV curve (green) with the actual cost data from Figure 1 (in red). It can be seen that the project was actually under budget, relative to the amount of work accomplished, since the start of the project. This is a much better conclusion than might be derived from Figure 1. Figure 4 shows all three curves together – which is a typical EVM line chart. The best way to read these three-line charts is to identify the EV curve first, then compare it to PV (for schedule performance) and AC (for
  • 50. Dr. Karim El-Dash 50 cost performance). It can be seen from this illustration that a true understanding of cost performance and schedule performance relies first on measuring technical performance objectively. This is the foundational principle of EVM. Earned Value Management Principle The foundational principle of EVM, mentioned above, does not depend on the size or complexity of the project. However, the implementations of EVM can vary significantly depending on the circumstances. In many cases, organizations establish an all-or-nothing threshold; projects above the threshold require a full-featured (complex) EVM system and projects below the threshold are exempted. Another approach that is gaining favor is to scale EVM implementation according to the project at hand and skill level of the project team. Simple implementations There are many more small and simple projects than there are large and complex ones, yet historically only the largest and most complex have enjoyed the benefits of EVM. Still, lightweight implementations of EVM are achievable by any person who has basic spreadsheet skills. In fact, spreadsheet implementations are an excellent way to learn basic EVM skills.
  • 51. Dr. Karim El-Dash 51 The first step is to define the work. This is typically done in a hierarchical arrangement called a work breakdown structure (WBS) although the simplest projects may use a simple list of tasks. In either case, it is important that the WBS or list be comprehensive. It is also important that the elements be mutually exclusive, so that work is easily categorized in one and only one element of work. The most detailed elements of a WBS hierarchy (or the items in a list) are called activities (or tasks). The second step is to assign a value, called planned value (PV), to each activity. For large projects, PV is almost always an allocation of the total project budget, and may be in units of currency (e.g., dollars or euros) or in labor hours, or both. However, in very simple projects, each activity may be assigned a weighted “point value" which might not be a budget number. Assigning weighted values and achieving consensus on all PV quantities yields an important benefit of EVM, because it exposes misunderstandings and miscommunications about the scope of the project, and resolving these differences should always occur as early as possible. Some terminal elements cannot be known (planned) in great detail in advance, and that is expected, because they can be further refined at a later time. The third step is to define “earning rules” for each activity. The simplest method is to apply just one earning rule, such as the 0/100 rule, to all activities. Using the 0/100 rule, no credit is earned for an element of work until it is finished. A related rule is called the 50/50 rule, which means 50% credit is earned when an element of work is started, and the remaining 50% is earned upon completion. Other fixed earning rules such as a 25/75 rule or 20/80 rule are gaining favor, because they assign more weight to finishing work than for starting it, but they also motivate the project team to identify when an element of work is started, which can improve awareness of work-in-progress. These simple earning rules work well for small or simple projects because generally each activity tends to be fairly short in duration. These initial three steps define the minimal amount of planning for simplified EVM. The final step is to execute the project according to the plan and measure progress. When activities are started or finished, EV is accumulated according to the earning rule. This is typically done at regular
  • 52. Dr. Karim El-Dash 52 intervals (e.g., weekly or monthly), but there is no reason why EV cannot be accumulated in near real-time, when work elements are started/completed. In fact, waiting to update EV only once per month (simply because that is when cost data are available) only detracts from a primary benefit of using EVM, which is to create a technical performance scoreboard for the project team. In a lightweight implementation such as described here, the project manager has not accumulated cost nor defined a detailed project schedule network (i.e., using a critical path or critical chain methodology). While such omissions are inappropriate for managing large projects, they are a common and reasonable occurrence in many very small or simple projects. Any project can benefit from using EV alone as a real-time score of progress. One useful result of this very simple approach (without schedule models and actual cost accumulation) is to compare EV curves of similar projects, as illustrated in Figure 5. In this example, the progress of three residential construction projects are compared by aligning the starting dates. If these three home construction projects were measured with the same PV valuations, the relative schedule performance of the projects can be easily compared.
  • 53. Dr. Karim El-Dash 53 Intermediate implementations In many projects, schedule performance (completing the work on time) is equal in importance to technical performance. For example, some new product development projects place a high premium on finishing quickly. It is not that cost is unimportant, but finishing the work later than a competitor may cost a great deal more in lost market share. It is likely that these kinds of projects will not use the lightweight version of EVM described in the previous section, because there is no planned timescale for measuring schedule performance. A second layer of EVM skill can be very helpful in managing the schedule performance of these “intermediate” projects. The project manager may employ a critical path or critical chain to build a project schedule model. As in the lightweight implementation, the project manager must define the work comprehensively, typically in a WBS hierarchy. He/she will construct a project schedule model that describes the precedence links between elements of work. This schedule model can then be used to develop the PV curve (or baseline), as shown in Figure 2'. It should be noted that measuring schedule performance using EVM does not replace the need to understand schedule performance versus the project's schedule model (precedence network). However, EVM schedule performance, as illustrated in Figure 2 provides an additional indicator — one that can be communicated in a single chart. Although it is theoretically possible that detailed schedule analysis will yield different conclusions than broad schedule analysis, in practice there tends to be a high correlation between the two. Although EVM schedule measurements are not necessarily conclusive, they provide useful diagnostic information. Although such intermediate implementations do not require units of currency (e.g., dollars), it is common practice to use budgeted dollars as the scale for PV and EV. It is also common practice to track labor hours in parallel with currency. The following EVM formulas are for schedule management, and do not require accumulation of actual cost (AC). This is important because it is common in small and intermediate size projects for true costs to be unknown or unavailable.
  • 54. Dr. Karim El-Dash 54  Schedule variance (SV) EV-PV greater than 0 is good (ahead of schedule)  Schedule performance index (SPI) EV/PV greater than 1 is good (ahead of schedule) See also earned schedule for a description of known limitations in SV and SPI formulas and an emerging practice for correcting these limitations. Advanced implementations In addition to managing technical and schedule performance, large and complex projects require that cost performance be monitored and reviewed at regular intervals. To measure cost performance, planned value (or BCWS - Budgeted Cost of Work Scheduled) and earned value (or BCWP - Budgeted Cost of Work Performed) must be in units of currency (the same units that actual costs are measured.) In large implementations, the planned value curve is commonly called a Performance Measurement Baseline (PMB) and may be arranged in control accounts, summary-level planning packages, planning packages and work packages. In large projects, establishing control accounts is the primary method of delegating responsibility and authority to various parts of the performing organization. Control accounts are cells of a responsibility assignment (RACI) matrix, which is intersection of the project WBS and the organizational breakdown structure (OBS). Control accounts are assigned to Control Account Managers (CAMs). Large projects require more elaborate processes for controlling baseline revisions, more thorough integration with subcontractor EVM systems, and more elaborate management of procured materials. Additional acronyms and formulas include: Budget at completion (BAC): The total planned value (PV or BCWS) at the end of the project. If a project has a Management Reserve (MR), it is typically in addition to the BAC.
  • 55. Dr. Karim El-Dash 55  Cost variance (CV) EV - AC, greater than 0 is good (under budget)  Cost Performance Index (CPI) EV/AC, greater than 1 is good (under budget) < 1 means that the cost of completing the work is higher than planned (bad) = 1 means that the cost of completing the work is right on plan (good) > 1 means that the cost of completing the work is less than planned (good or sometimes bad). Having a CPI that is very high (in some cases, very high is only 1.2) may mean that the plan was too conservative, and thus a very high number may in fact not be good, as the CPI is being measured against a poor baseline. Management or the customer may be upset with the planners as an overly conservative baseline ties up available funds for other purposes, and the baseline is also used for manpower planning. Estimate at completion (EAC) EAC is the manager's projection of total cost of the project at completion. ETC is the estimate to complete the project. To-complete performance index (TCPI) The To Complete Performance Index (TCPI) provides a projection of the anticipated performance required to achieve either the BAC or the EAC. TCPI indicates the future required cost efficiency needed to achieve a target BAC (Budget At Complete) or EAC (Estimate At Complete). Any
  • 56. Dr. Karim El-Dash 56 significant difference between CPI, the cost performance to date, and the TCPI, the cost performance needed to meet the BAC or the EAC, should be accounted for by management in their forecast of the final cost. For the TCPI based on BAC (describing the performance required to meet the original BAC budgeted total): or for the TCPI based on EAC (describing the performance required to meet a new, revised budget total EAC): Independent estimate at completion (IEAC) The IEAC is a metric to project total cost using the performance to date to project overall performance. This can be compared to the EAC, which is the manager's projection.
  • 57. Dr. Karim El-Dash 57 Project Quality Management Quality can be defined as meeting the customer's expectations or exceeding the customer expectations achieved by way of deliverables and/or activities performed to produce those deliverables. Project Quality Plan can be defined as a set of activities planned at the beginning of the project that helps achieve Quality in the Project being executed. The Purpose of the Project Quality Plan is to define these activities/tasks that intend to deliver products while focusing on achieving customer's quality expectations. These activities / tasks are defined on the basis of the quality standards set by the organization delivering the product. Project Quality Plan identifies which Quality Standards are relevant to the project and determines how they can be satisfied. It includes the implementation of Quality Events (peer reviews, checklist execution) by using various Quality Materials (templates, standards, checklists) available within the organization. The holding of the Quality Event is termed as Quality Control. As an output of the various activities, Quality Metrics or Measurements are captured which assist in continuous improvement of Quality thus adding to the inventory of Lessons Learned. Quality Assurance deals in preparation of the Quality Plan and formation of organization wide standards. Guidelines to write the Project Quality Plan Project Quality Plan should be written with the objective to provide project management with easy access to quality requirements and should have ready availability of the procedures and standards thus mentioned. The following list provides you the various Quality Elements that should be included in a detailed Project Quality Plan: Management Responsibility. Describes the quality responsibilities of all stakeholders.
  • 58. Dr. Karim El-Dash 58 Documented Quality Management System. This refers to the existing Quality Procedures that have been standardized and used within the organization. Design Control. This specifies the procedures for Design Review, Sign- Off, Design Changes and Design Waivers of requirements. Document Control. This defines the process to control Project Documents at each Project Phase. Purchasing. This defines Quality Control and Quality Requirements for sub-contracting any part / whole part of the project. Inspection Testing. This details the plans for Acceptance Testing and Integration Testing. Nonconformance. This defines the procedures to handle any type of nonconformance work. The procedures include defining responsibilities, defining conditions and availability of required documentation in such cases. Corrective Actions. This describes the procedures for taking Corrective Actions for the problems encountered during project execution. Quality Records. This describes the procedures for maintaining the Quality Records (metrices, variance reports, executed checklists etc) during project execution as well as after the project completion. Quality Audits. An internal audit should be planned and implemented during each phase of the project. Training. This should specify any training requirements for the project team.
  • 59. Dr. Karim El-Dash 59 COST-BENEFIT ANALYSIS In the case of quality management, cost of quality trade-offs should be considered from within cost-benefit analysis. The benefits of meeting quality requirements are as follows:  Stakeholder satisfaction is increased.  Costs are lower.  Productivity is higher.  There is less rework. COST OF QUALITY CATEGORIES OF QUALITY COSTS Many companies summarize these costs into four categories. Some practitioners also call these categories the “cost of quality.” These categories and examples of typical subcategories are discussed below. Internal Failure Costs. These are costs of deficiencies discovered before delivery which are associated with the failure (nonconformities) to meet explicit requirements or implicit needs of external or internal customers. Also included are avoidable process losses and inefficiencies that occur even when requirements and needs are met. These are costs that would disappear if no deficiencies existed.
  • 60. Dr. Karim El-Dash 60 Failure to Meet Customer Requirements and Needs. Examples of subcategories are costs associated with:  Scrap: The labor, material, and (usually) overhead on defective product that cannot economically be repaired. The titles are numerous—scrap, spoilage, defectives, etc.  Rework: Correcting defectives in physical products or errors in service products.  Lost or missing information: Retrieving information that should have been supplied.  Failure analysis: Analyzing nonconforming goods or services to determine causes.  Scrap and rework—supplier: Scrap and rework due to nonconforming product received from suppliers. This also includes the costs to the buyer of resolving supplier quality problems.  One hundred percent sorting inspection: Finding defective units in product lots which c unacceptably high levels of defectives.  Reinspection, retest: Reinspection and retest of products that have undergone rework or other revision.  Changing processes: Modifying manufacturing or service processes to correct deficiencies.  Redesign: Changing designs to correct deficiencies.  Scrapping of obsolete product: Disposing of products that have been superseded.  Scrap in support operations: Defective items in indirect operations.  Rework in internal support operations: Correcting defective items in indirect operations.  Downgrading: The difference between the normal selling price and the reduced price due to quality reasons.
  • 61. Dr. Karim El-Dash 61 Cost of Inefficient Processes. Examples of subcategories are  Variability of product characteristics: Losses that occur even with conforming product (e.g., overfill of packages due to variability of filling and measuring equipment).  Unplanned downtime of equipment: Loss of capacity of equipment due to failures.  Inventory shrinkage: Loss due to the difference between actual and recorded inventory amounts.  Variation of process characteristics from “best practice”: Losses due to cycle time and costs of processes as compared to best practices in providing the same output. The best-practice process may be internal or external to the organization.  Non-value-added activities: Redundant operations, sorting inspections, and other non-valueadded activities. A value-added activity increases the usefulness of a product to the customer; a non-value-added activity does not. (The concept is similar to the 1950s concept of value engineering and value analysis.) External Failure Costs These are costs associated with deficiencies that are found after product is received by the customer. Also included are lost opportunities for sales revenue. These costs also would disappear if there were no deficiencies. Failure to Meet Customer Requirements and Needs Examples of subcategories are:  Warranty charges: The costs involved in replacing or making repairs to products that are still within the warranty period.  Complaint adjustment: The costs of investigation and adjustment of justified complaints attributable to defective product or installation.
  • 62. Dr. Karim El-Dash 62  Returned material: The costs associated with receipt and replacement of defective product received from the field.  Allowances: The costs of concessions made to customers due to substandard products accepted by the customer as is or to conforming product that does not meet customer needs.  Penalties due to poor quality: This applies to goods or services delivered or to internal processes such as late payment of an invoice resulting in a lost discount for paying on time.  Rework on support operations: Correcting errors on billing and other external processes.  Revenue losses in support operations: An example is the failure to collect on receivables from some customers. Appraisal Costs These are the costs incurred to determine the degree of conformance to quality requirements. Examples are  Incoming inspection and test: Determining the quality of purchased product, whether by inspection on receipt, by inspection at the source, or by surveillance.  In-process inspection and test: In-process evaluation of conformance to requirements.  Final inspection and test: Evaluation of conformance to requirements for product acceptance.  Document review: Examination of paperwork to be sent to customer.  Balancing: Examination of various accounts to assure internal consistency.  Product quality audits: Performing quality audits on in-process or finished products.  Maintaining accuracy of test equipment: Keeping measuring instruments and equipment in calibration.  Inspection and test materials and services: Materials and supplies in inspection and test work (e.g., x-ray film) and services (e.g., electric power) where significant.
  • 63. Dr. Karim El-Dash 63  Evaluation of stocks: Testing products in field storage or in stock to evaluate degradation. In collecting appraisal costs, what is decisive is the kind of work done and not the department name (the work may be done by chemists in the laboratory, by sorters in Operations, by testers in Inspection, or by an external firm engaged for the purpose of testing). Also note that industries use a variety of terms for “appraisal,” e.g., checking, balancing, reconciliation, review. Prevention Costs These are costs incurred to keep failure and appraisal costs to a minimum. Examples are:  Quality planning: This includes the broad array of activities which collectively create the overall quality plan and the numerous specialized plans. It includes also the preparation of procedures needed to communicate these plans to all concerned.  New-products review: Reliability engineering and other quality-related activities associated with the launching of new design.  Process planning: Process capability studies, inspection planning, and other activities associated with the manufacturing and service processes.  Process control: In-process inspection and test to determine the status of the process (rather than for product acceptance).  Quality audits: Evaluating the execution of activities in the overall quality plan.  Supplier quality evaluation: Evaluating supplier quality activities prior to supplier selection, auditing the activities during the contract, and associated effort with suppliers.  Training: Preparing and conducting quality-related training programs. As in the case of appraisal costs, some of this work may be done by personnel who are not on the payroll of the Quality department. The
  • 64. Dr. Karim El-Dash 64 decisive criterion is again the type of work, not the name of the department performing the work. Note that prevention costs are costs of special planning, review, and analysis activities for quality. Prevention costs do not include basic activities such as product design, process design, process maintenance, and customer service.
  • 65. Dr. Karim El-Dash 65 OPTIMUM QUALITY COST MODEL The model shows three curves: 1. The failure costs: These equal zero when the product is 100 percent good, and rise to infinity when the product is 100 percent defective. (Note that the vertical scale is cost per good unit of product. At 100 percent defective, the number of good units is zero, and hence the cost per good unit is infinity.) 2. The costs of appraisal plus prevention: These costs are zero at 100 percent defective, and rise as perfection is approached. 3. The sum of curves 1 and 2: This third curve is marked “total quality costs” and represents the total cost of quality per good unit of product. Cost of quality The previous figure suggests that the minimum level of total quality costs occurs when the quality of conformance is 100 percent, i.e., perfection. This has not always been the case. During most of the twentieth century the predominant role of (fallible) human beings limited the efforts to attain perfection at finite costs. Also, the inability to quantify the impact of quality
  • 66. Dr. Karim El-Dash 66 failures on sales revenue resulted in underestimating the failure costs. The result was to view the optimum value of quality of conformance as less than 100 percent. Effect of identifying cost of quality  
  • 67. Dr. Karim El-Dash 67 CONTROL CHARTS A control chart represents a picture of a process over time. To effectively use control charts, one must be able to interpret the picture. What is this control chart telling me about my process? Is this picture telling me that everything is all right and I can relax? Is this picture telling me that something is wrong and I should get up and find out what has happened? A control chart tells you if your process is in statistical control. The chart above is an example of a stable (in statistical control) process. This pattern is typical of processes that are stable. Three characteristics of a process that is in control are:  Most points are near the average  A few points are near the control limits  No points are beyond the control limits If a control chart does not look similar to the one above, there is probably a special cause present. Various tests for determining if a special cause is present are given below. Points Beyond the Control Limits A special cause is present in the process if any points fall above the upper control limit or below the lower control limit. Action should be taken to find the special cause and permanently remove it from the process. If there is a point beyond the control limits, there is no need
  • 68. Dr. Karim El-Dash 68 to apply the other tests for out of control situations. Points on the control limits are not considered to be out of statistical control. Zone Tests: Setting the Zones and Zone A The zone tests are valuable tests for enhancing the ability of control charts to detect small shifts quickly. The first step in using these tests is to divide the control chart into zones. This is done by dividing the area between the average and the upper control limit into three equally spaced areas. This is then repeated for the area between the average and the lower control limit. The zones are called zones A, B, and C. There is a zone A for the top half of the chart and a zone A for the bottom half of the chart. The same is true for zones B and C. Control charts are based on 3 sigma limits of the variable being plotted. Thus, each zone is one standard deviation in width. For example, considering the top half of the chart, zone C is the region from the average to the average plus one standard deviation. Zone B is the region between the average plus one standard deviation and the average plus two standard deviations. Zone A is the region between the average plus two standard deviations and the average plus three standard deviations A special cause exists if two out of three consecutive points fall in zone A or beyond. The figure below shows an example of this test. The test is applied for the zone A above the average and then for the zone A below the average.
  • 69. Dr. Karim El-Dash 69 This test, like those below, is applied to both halves of the chart. However, only one half is considered at a time. For example, if one point falls in the zone A above the average and the next point falls in zone A below the average, this is not two out of three consecutive points in zone A or beyond. The two points in zone A must be on the same side of the average. Zone Tests: Zones B and C A special cause exists if four out five consecutive points fall in zone B or beyond. The figure to the left shows an example of this test. This test is applied for zone B above the average and then for zone B below the average. A special cause exists if seven consecutive points fall in zone C or beyond. An example of this test is shown below. The test should be applied for the zone C above the average and then for the zone C below the average.
  • 70. Dr. Karim El-Dash 70 Test for Stratification Stratification occurs if two or more processes (distributions) are being sampled systematically. For example, stratification can occur if samples are taken once a shift and a subgroup size of 3 is formed based on the results from three shifts. It is possible that the shifts are operating at a different average or variability. Stratification (a special cause) exists if fifteen or more consecutive points fall in zone C either above or below the average. Note that the points tend to hug the centerline. This test involves the use of the zones but is applied to the entire chart and not one-half of the chart at a time. Test for Mixtures A mixture exists when there is more than one process present but sampling is done for each process separately. For example, suppose you take three samples per shift and form a subgroup based on these three samples. If different shifts are operating at different averages, a mixture can occur. A mixture (a special cause) is present if eight or more consecutive points lie on both sides of the average with none of the points in zone C. The figure shows an example of this test. Note the absence of points in zone C. This test is applied to the entire chart. Rule of Seven Tests These tests are often taught initially to employees as the method for interpreting control charts (along with points beyond the limits). The tests
  • 71. Dr. Karim El-Dash 71 state that an out of control situation is present if one of the following conditions is true: 1) Seven points in a row above the average, 2) Seven points in a row below the average, 3) Seven points in a row trending up, or 4) Seven points in a row trending down. These four conditions are shown in the figure above.
  • 72. Dr. Karim El-Dash 72 BENCHMARKING A benchmark is a defined measure of productivity in comparison to something else. We can benchmark internally, seeking to maintain or improve performance, or we can try to find industry benchmarks, and compare ourselves to our competitors. Sometimes, industry associations can provide information in support of benchmarks that we should achieve. We should always evaluate them closely to be sure that the benchmark is appropriate and realistic in our work environment. For example, if we are using older equipment, we might not be able to achieve an industry average rate of production. Also, we should make sure that achieving that benchmark increases or at least maintains customer quality while lowering cost. There is no point achieving a benchmark if it means losing customers or losing dollars. Best Practices Information about solid, measurable benchmarks is hard to obtain and harder to fit into unique situation. Developing and using best practices is a powerful improvement method. A best practice is simply the best way to do a repeating process at your organization. Best practices: