SlideShare a Scribd company logo
1 of 13
Download to read offline
FSRU: Risks and Opportunities
Karthik Sathyamoorthy
President
Sudhanshu Haldar
Manager
Galway Group
8 Temasek Blvd, #22–04,
Suntec Tower 3
Singapore 038988
www.galwaygroup.com
ABSTRACT
In the context of rising global energy demand and abundant shale gas reserves, governments
and developers across the world are considering natural gas as a viable fuel for augmenting their
energy portfolios. Increasingly, gas buyers are exploring floating regasification solutions for their
perceived speed of deployment, cost advantages, and redeployment flexibility.
FSRU solution comes in different configurations. For example, Brazil has two out of three FSRUs
converted from LNGC, whereas Uruguay is going forward with world’s biggest new-built FSRU.
However, the FSRU market is in early stages and there is an increasing need for understanding the
opportunities and risks associated with potential FSRU solutions.
This paper outlines and explores FSRU as a regasification solution, as compared to an onshore
terminal, and discusses some major risks and key drivers for FSRUs from a developer’s perspective.
These risks and opportunities have been discussed from investment, commercial and technology
aspects. This paper also points out some major considerations that a project developer should
weigh to gain a clear understanding of whether FSRU is the right solution for the project under
consideration.
Page 2 of 13
Introduction and Background
With increasing gas demand across the world, new and innovative LNG terminal solutions have
surfaced the industry. These innovations spread across both the technological and commercial
fronts. A unique combination of these innovations has resulted in the emergence of floating
regasification solutions as an alternate to the onshore regasification terminals.
Gulf Gateway Deepwater port, installed offshore Louisiana in March 2005, was the earliest
design of floating regasification solutions. This facility utilized a submerged turret-loading buoy that
allowed connection to multiple downstream pipelines. However, the shale boom was unforeseen at
the time of this development. As a result of this significant development in gas production in the
US, Gulf Gateway was decommissioned in 2012.
Gulf Gateway’s era may be over, but its proven technology opened the doors for a new age of
innovative floating regasification solutions. This technology has largely been derived from either
the offshore oil industry (e.g., mooring systems, unloading systems), the LNG shipping industry
(e.g., LNG containment systems), or land-based LNG regasification (e.g., vaporizers). Therefore,
the technology risks are well understood and can be managed effectively on a project-by-project
basis, leading to as increased acceptance of floating regasification solutions.
Figure 1. Start-Ups of LNG Receiving Terminals, 1980-20161
Today, FSRUs not only provide an alternate option to onshore regasification solution, but
also offer a better economic fit in many cases. In the current market, FSRUs are challenging the
traditional onshore regasification solution and with more than 20 speculative projects2
, are one of
the primary contenders for future regasification capacity. A decade of FSRU operations have built
confidence in the industry about their reliability and safety of operations. However, in certain
instances, FSRUs grapple with some technological and commercial challenges, putting them at a
disadvantage as compared to onshore terminals.
Page 3 of 13
How are FSRUs different from an Onshore Facility?
An FSRU is a ship or barge that is built (or retrofitted from an LNG carrier) to be able to perform
regasification operations onboard. The vessel requires little or no site preparation (except
associated facilities) and is equipped with an onboard LNG storage facility. In some instances, it
can also connect to the existing offshore gas pipeline grid. This is unlike an onshore development,
which requires on-land site preparation and development, constructing cryogenic storage tanks,
integrating LNG regasification units and developing a berthing facility for LNG carriers.
An FSRU can be built either by retrofitting an existing LNG ship (“Retrofit”) or a by building an
entirely new LNG ship fitted onboard regasification equipment (“Newbuild”). A retrofitted FSRU is
one that is adapted from an LNG carrier. Retrofitting includes making modifications and adding a
regasification unit onboard. Many factors come into the equation when determining which type of
LNG carrier would make the best FSRU – availability and costs being the leading factors.
The two most prominent drivers that have made the FSRU option attractive to the developers
are (i) shorter project development timeline as compared to an onshore terminal with a similar gas
send-out rate, and; (ii) lower upfront project development capital costs as compared to a similar
sized onshore terminal. FSRUs have proven to be a better alternative for locations where either
space for development or additional infrastructure is a constraint. FSRUs can also be employed for
the use of offshore gas grids, which are no longer in use. Shorter permitting timelines are also
often pronounced as one of the benefits, however, this can vary case by case basis.
Current FSRU market and outlook
The floating LNG terminal market is a relatively new one. However, FSRUs have been gaining
a market share, especially among the new and proposed regasification terminals. The share of
FSRU as an import terminal option among the LNG importing countries is increasing swiftly and
FSRUs continue to gain popularity, especially in countries that are looking to enter the LNG import
market with lower capital investment and within a short timeframe. Since the inception of the
floating LNG solutions in 2005, more than 20 FSRUs have been constructed and deployed.
Over the last decade, the highest activity in the FSRU segment has been observed in Middle-
east and South America. Recently European and Asian economies have started deploying FSRUs to
meet their natural gas needs. By end of 2014, Brazil’s Bahia/TRBA, Indonesia’s Lampung, and
Lithuania’s Klaipeda LNG began their operations. In 2015, three additional FSRUs came online,
including one in Pakistan chartered from Excelerate Energy, one in Egypt chartered from Hoegh
LNG and one in Jordan chartered from Golar LNG1
.
The following chart (Figure 2) maps the existing terminals across the globe.
Page 4 of 13
Figure 2. Status of existing and under construction FSRUs globally [Galway Database]
The market for FSRUs can be classified into two categories: Vessel Owners and
Operators/Charterers. The current FSRU market players can be categorized as (i) Pure Play FSRU
vessel/owner companies: Excelerate, Golar and Hoegh, who have been the leaders in supply of
FSRUs, primarily because they were first movers and have successfully developed, built and
operated floating LNG vessels. (ii) Shipping Companies: Primarily existing shipping companies who
are starting to focus on floating LNG vessels, e.g., Mitsui OSK Lines (MOL), BW Offshore, Teekay,
NYK, and MISC. (iii) NOCs and government agencies: In certain cases, the NOCs and government
entities are also increasingly participating in FSRU projects to gain experience and independently
operate FSRUs in the domestic market.
Based on the current trend and popularity, it is reasonable to infer that the FSRU market is on
an upswing, undeterred by the weak commodity markets. In addition to the planned and proposed
projects, there are at least ten other speculative projects in South America, the Middle east and
Europe. These projects are expected to take FID by the end of the decade. The FSRU market is
further expected to grow. This growth will be fueled by the following factors:
 The recent dispute between Ukraine and Russia raised energy security concerns among
countries in the European Union, who import majority of their gas from Russia. FSRUs
can connect these countries to global gas supplies while offering diversification in the
European Union’s gas portfolio.
 Importers have an opportunity to capitalize on the current low LNG prices, which are
traditionally linked to oil prices (projected to remain low). Additionally, further downward
pricing pressure is expected on account of the surplus future supplies from the US and
Australian LNG projects.
 Increased development of gas fired power generation and lowering of nuclear power
dependence in Japan and Europe
Page 5 of 13
 Bridging solution for countries transitioning from being natural gas exporters to importers
and countries that need temporary intermediate energy solutions while development of
large onshore terminals is underway
 Bridging solution until cleaner and renewable fuels can be scalable and commercialized
 Small scale opportunities for FSRUs in areas with scattered demand e.g. Indonesia
On the back of the current situation and the expected developments in this space, it is
reasonable to assume that FSRUs have the potential to develop into a highly preferred regasification
option in the future. However, there are numerous complexities – technological, commercial and
operational – which can undermine the prospects of FSRU project development. These potential
challenges need to be overcome for the industry’s full potential to be achieved.
FSRUS: Opportunities and Risks - A developer’s dilemma
Although, natural gas is increasingly expected to play a pivotal role in the energy mix for a
large number of countries, the availability of the natural gas resources are not shared equally. A
growing number of countries are turning to LNG imports to meet their growing gas demand. This
presents the developers with an opportunity to come up with an economically sound and a safe
natural gas import strategy. There are multiple decisions to be made when strategizing a
regasification project. The primary decision is on the type of import terminal to be developed –
onshore or offshore.
Further, there are hybrid solutions such as a Floating Storage Unit (FSU) with regasification
units located onshore that can be considered. Such a solution might be required depending on site
considerations and may be more appropriate if:
 There are exclusion zone limitations with siting of LNG storage tanks onshore e.g.,
adherence to thermal radiation and vapor dispersion regulations;
 An LNG import facility is being fast-tracked and operations have to start before
completion of the onshore storage tanks.
A developer must clearly understand various pros and cons of onshore and offshore solutions
before embarking on a development plan. The following section offers some insights on these risks
and opportunities associated with offshore regasification solutions when compared with onshore
solutions.
Key Drivers in favor of an FSRU
FSRUs are becoming increasingly popular among the new LNG regasification project developers
because of following perceived benefits
A. Lower upfront development cost as compared to an onshore regasification
facility
One of the primary drivers in favor of the FSRU option is the low upfront capital investment
requirement. A typical FSRU can cost in the range of US $250 million to US $350 million (additional
US $200 to US $400 million for associated facilities) as compared to a similar sized (gas send-out)
onshore facility, which can cost in the range of US $1.0 billion to US $1.5 billion. FSRU capital costs
are typically lower onshore regasification terminals because of following reasons:
Page 6 of 13
 FSRUs do not require expensive site development and the construction of stand-alone
LNG storage tanks (each tank can costs in excess of US $150 million)
 FSRUs are built in a shipyard, so there can be a better control over costs as compared to
an onshore terminal
 FSRUs and associated facilities have a lower footprint as compared to onshore terminals,
thus reducing land procurement costs
Depending on the project developer’s needs, a further reduction in upfront cost can also be
attained by retrofitting an existing LNG carrier, or leasing an existing FSRU vessel. The latter option,
however, will result in loss of ship deck customization and can turn expensive if employed on a
long term basis.
B. Faster project development timeline as compared to an onshore facility
The development timeline of an FSRU based project can vary between 12 to 36 months. If an
FSRU is already available, the delivery time is even shorter. However, if an existing vessel is
converted, it could be take anywhere in the range of 12 to 18 months. In the case of a newbuild
FSRU, the construction and delivery time could be up to 3 years. This is considerably shorter as
compared to an onshore development, which requires 48 to 56 months for development. Reasons
for faster delivery time of an FSRU solutions include:
 FSRUs are built in shipyards that have years of experience in ship design and have a
better understanding of construction bottlenecks and resources at hand
 In most cases FSRU projects enjoy the advantage of shorter permitting timelines on
account of fewer participants and affected entities involved. However, it is important to
note that such permitting timelines can be site specific
 Speculation based inventory management by leading FSRU developers, long lasting
relationship with the shipyards and, in certain cases, standardized design.
Project delivery in such a relatively shorter time frame makes FSRU a very lucrative option for
developers who are running against the clock to meet acute supply shortages.
An onshore terminal project development is usually exposed to various potential bottlenecks
including site preparation, temporary material handling, labor shortages, equipment transportation,
and schedule mismatch among the various participants. These factors can significantly delay the
construction timeline and result in unexpected cost overruns.
C. Inherent flexibility offered by FSRU solution
Traditionally, there has been a lack of infrastructure to meet the needs of scattered energy
demand centers in archipelago countries like Indonesia or vast countries like Brazil and Argentina
with long coastlines. In such cases, distribution of natural gas (post LNG regasification) received at
an onshore facility through cross-country pipelines becomes cumbersome, expensive and
infeasible. In such cases, an FSRU presents the most optimal solution providing flexibility in location
(can be located as close to the demand centre as possible) and regasification capacity at a lower
cost of delivered gas. Some of the mentionable flexibility options provided by this solution are as
follows:
Page 7 of 13
 Unlike a fixed onshore facility, an FSRU can be relocated and deployed according to the
need of downstream market. A good example of this can be seen in Brazil where a Golar
FSRU located in Guanabara Bay was relocated to Bahia, Salvador. The Guanabara Bay
FSRU was replaced by an Excelerate FSRU3
.
 In case of a seasonal gas demand profile, an FSRU can be used to supply gas during
periods when there is gas demand and during the remainder of the year it can be used
as an LNG carrier. This model has been adopted by the Kuwait National Petroleum
Company (KNPC), where the vessel is deployed as an FSRU for nine months and is free
to pursue other spot LNG opportunities for three months4
.
 An FSRU can act as a base-load solution for smaller demand centers or peak-shaving
solution for larger center.
 FSRUs can be moved away to safety in case of a tsunami or similar natural or man-made
disasters.
D. Economic Options and Financial Incentives of an FSRU
During the early years, offshore regasification solutions were conventional, long-term and rigid,
which was likely a lender’s requirement for the unestablished market. However, over the years,
this rigidity in FSRU chartering has diminished significantly to less than five years of contract. Such
short-term chartering option facilitates the use of FSRU as a bridging solution during the
development of a land based regasification solution at the location. Such development strategies
have been seen in Chile (FSU), Egypt and Kuwait.
From an investor perspective, FSRUs have been drawing attention because of a faster return
on capital invested and a better residual value. The former depends on the utilization rate of the
FSRU (a higher utilization will result in a faster capital recovery) and the value of latter lies in the
option of re-deployment of the vessel as an LNG carrier.
Key challenges for an FSRU
As we discussed in the previous section, the opportunities that FSRUs bring to the table are
numerous and multifold. However, there are some challenges that the FSRU industry is currently
grappling with and these are discussed in the following section.
A. Metocean conditions threaten the availability of an FSRU
Meteorological and oceanic condition pose some serious challenges for the FSRU industry.
Depending on the severity of ocean conditions, LNG unloading could become one of the most
difficult tasks in FSRU operations. For side by side cargo unloading, a calm to mild sea state is
paramount, in absence of which an LNG carrier may have to wait for the ocean to return to normal
conditions before commencing safe operations. It is the same case when the FSRU is loaded with
LNG. Metocean factors can affect the send-out operations of an FSRU by disrupting the mooring
and regasified LNG connections. These factors can severely hurt the reliability and availability of an
FSRU.
An onshore plant, on the other hand, uses hard arms for unloading LNG and further onshore
operations usually escape the risk of uncertain open ocean behavior. LNG stored in onshore tanks
remains safe from the uncertain ocean and the regasification unit can meet the downstream gas
demand with more certainty and reliability.
Page 8 of 13
B. Technological challenges may limit the availability of an FSRU
In the process of ship-to-ship transfer (STS), an LNG carrier moors along-side the FSRU and
discharges LNG into the FSRU using flexible cryogenic hoses. This is still an evolving technology
and the long-term reliability of flexible cryogenic hoses in a marine environment is unproven and
is being evaluated for long life.
STS operations require benign conditions to ensure high regasification and berthing/unloading
availability.
Additionally, many of the deep-water unloading concepts such as Submerged Single/Double
Moored Buoy and Above Water Single Point Mooring – which can operate in deep water – still
remain theoretical because of the supplier’s and operator’s discomfort with implementing such a
system in deep water.
On the other hand, with years of successful operations all over the world, onshore regasification
terminals have significantly overcome most of the technological challenges. Also, industry practices
are well defined and -accepted by LNG suppliers and standards are well established and risks are
known and tested. These advantages may tend to make the onshore terminal option as the most
preferred one amongst suppliers.
C. Challenges attributed to limited deck and storage space
Another challenge faced by FSRUs is the limited deck and storage space. Unlike an onshore
facility, where future expansions can be a part of the original plan, an offshore solution suffers
from the lack of available footprint. The cheaper and relatively flexible open rack vaporizers (ORV)
used in a majority of onshore terminals may not be appropriate for an FSRU because of space
constraints. Also, Expansion of storage capacity is not straight forward once the FSRU has been
put in place.
The space constraints in an FSRU result in a much stricter firewater regulation as compared to
onshore facilities. Some other constraints which increase the design complexity of an FSRU pertain
to the storage of LNG and onboard fuel, sloshing of LNG stored in the FSRU, high pressure
regasification equipment installed onboard, mooring arrangement and transfer of LNG.
An onshore regasification facility, as compared to FSRUs, enjoys sufficient footprint – in most of
the cases – and can have flexible regasification options, warehouses, fuel storage tanks and
firewater operations. The terminal can also pre-plan expansion options and construct the necessary
expansion interface in advance to speed up such future plans. Such expansions can result in major
economies of scale for the onshore regasification plant, a feature that is unavailable in FSRUs.
Page 9 of 13
D. Challenges related to operation and maintenance
The typical cost of operation (variable cost) of an FSRU is higher than that of an onshore
terminal. The costs include the labor, crew costs, consumables, fuel and spare inventory. As
compared to an onshore terminal, the crew in an FSRU terminal is more specialized and requires
both LNG and ship operations experience. Such personnel are usually in high demand, leading to
a further escalation in operational costs. There also are additional costs associated with storage of
fuel, inventory management and disposal of processed waste – which pushes the operating costs
higher.
From the maintenance perspective, unlike in an onshore terminal, the spare parts in an offshore
terminal could be highly FSRU specific. Consequently, in case of an equipment fault in an FSRU,
the operations can suffer severe delays or send-out interruptions because the customized spare
parts may have a longer lead time.
These costs, if supplemented with limited availability of the FSRU on account of uncertain
metocean conditions, can result in higher per unit cost of operations and tends to eliminate the
advantage of low initial capital costs. For an onshore regasification plant, the processes are rather
standardized, thus resulting in significantly lower operational costs. Additionally, operational risks
are well understood and the reliability of equipment is well known.
An objective approach to assess the viability of a regasification solution
As compared to an onshore terminal, FSRU’s enjoy an inherent set of advantages. However,
the potential challenges of operating an FSRU cannot be ignored altogether. This makes it
imperative to lay-down a methodology to assess the optimum solution which aligns with the
developer’s objective while ensuring that the solution meets the current industry standards.
The decision of suitability of a development (onshore vs offshore) opportunity rests on the
fulfilment of the questions related to stakeholders’ risk appetite and return expectations, the
projects’ ability to meet the development and demand objectives, the required timeline to deliver
the development and capital requirement for the development. These considerations are explained
as below.
What is the type of demand under question?
For a project developer, it is important to understand the type of market and the demand
profile a project is expected to service. Demand of a market can have a mixture of following three
characters:
 Short-term demand vs. Long term demand: Short-term demand to bridge until an
alternate solution is reached; long-term demand to develop a permanent solution.
 Baseload demand vs. Peak-shaving demand: Baseload demand to meet a large
consistent gap; a peak-shaving demand to meeting acute changes in demand profile.
 Yearlong demand vs. Seasonal demand: the profile of demand can be seasonal to
meet the requirements in a few high demand seasons; continuous demand profile to
meet demand in all seasons.
Page 10 of 13
Strength of an onshore terminal lies in meeting constant downstream demand and providing
continuous reliable operations, which makes it the most suitable candidate for a baseload facility.
The onshore facility also have possibility of large storage space and possibility of expansion, and
therefore, can the meet daily fluctuation of demand easily. However, an onshore facility might not
be an appropriate solution if the demand profile is not continuous or a facility requirement is short-
term or demand is scattered in the region where transporting natural gas through available
infrastructure is not feasible. Partial utilization of these onshore terminals will yield the investment
uneconomical and un-optimized.
An FSRU successfully bridges the drawbacks of an onshore facility in this regard. The inherent
flexibility of an FSRU – can be used as a regasification vessel or an LNG carrier – successfully meets
the utilization requirement if demand is seasonal. Alternatively, an FSRU can encompass the
capacity range from baseload to small scale requirement. The chartering option of an FSRU makes
the solution lucrative in case of a bridging solution. Historically there have been a few examples
where FSRUs are chartered for a short-term (under 5 years), like in Kuwait, till the permanent
regasification solutions can be developed. These advantages, however, shall be weighted properly
against the possible risks – including send-out rates and availability – that an FSRU solution can
face as discussed in the previous sections.
How fast the development has to be up and running?
An LNG project is an intricate web of agencies and participants connected with individual
timeline commitments. The supplier, the terminal developer, the aggregator, and the downstream
customer must understand the implications of project development timelines. The factors which
affect the timeline of a project are duration required to get permits, requirement of new and existing
infrastructure, and downstream gas commitments.
The project development timeline is one of the primary factors to narrow down the choice of
regasification development. A typical onshore project takes around three to five years from
permitting to starts operations, and delays in such construction timelines are rather frequent. The
reasons for such delays may include issues such as remote location, labor shortages, permitting
delays, and inspection and testing schedule mismatches.
The implications of such uncertainty in construction timelines might not be acceptable to many
participants as the bottlenecks may push the construction timelines of an onshore terminal further.
In such cases, where meeting the construction timeline at the earliest is a necessity, an onshore
regasification terminal might not be the best solution to meet the downstream demand.
On the other hand, an FSRU meets the criteria of fast and on-time implementation well. The
permitting and construction goes in parallel and it usually take a shorter timeframe for solution to
be ready (12 to 36 months). The key to faster delivery of an FSRU lies in clarity of operational
requirement. An FSRU construction happens in the shipyards in a controlled environment, and is
less likely to face a delay. However, a project developer must scrutinize the permitting timelines
and regulations well in advance to avoid roadblocks or change in design requirements.
Page 11 of 13
Whether the FSRU fits the investment strategy of the developer?
Projects in the LNG industry are capital intensive and, usually, form a part of long-term energy
strategy. Therefore, from a project developer perspective, it is important to understand the
developer’s risk appetite. The development must be scrutinized from the both country and project
risk perspective. Understanding of country risk will help the developer get comfortable with the
security of the investment, whereas the understanding of project risk will help the developer get a
feel for the investment as compared to the other projects.
An onshore regasification development, for example, is usually a part of a long-term
development strategy of a country. A high upfront investment is required in the case of such
development and the return is tied to the long-term viability and operations of the plant. The project
also faces a significant country risk because the assets developed will be immovable and, in case
of an unrest or change in demand pattern of the country, will get stranded with no residual value.
An offshore FSRU development, however, faces some relief from the above mentioned risks.
The upfront investment required, in most of the cases, is low and the vessel is mobile. This brings
the country risk down significantly as the asset will not get stranded. Another aspect of such
investment is low project risk as in case demand dries up, the vessel can be redeployed as an LNG
Carrier. However, the FSRU availability and technology risks are much higher for an FSRU as
compared to an onshore vessel.
The above mentioned risk gets morphed in a different dimension with type of project structure.
A build, own, operate and transfer (BOOT) structure for example will have different set of risk than
a build operate and transfer (BOT) structure. The perceived confidence in country’s credit will affect
the financing of these projects and eventually the expected return and investment security.
A comparative thorough assessment of the above mentioned risks between an onshore
development and an offshore development options is of utmost importance for a project developer
to ensure the security of the investment.
Conclusion
FSRUs are the new players, in the world dominated by onshore terminals, and they offer a
unique solution in the LNG regasification industry – low cost, faster delivery, location flexibility and
scale of operations – that fits the need of many countries. With the world moving towards the
cleaner hydrocarbon, FSRU presents an attractive set of opportunities which makes the option
lucrative, but the technological and commercial challenges are yet to completely overcome.
A project developer must follow a structured investigation to understand how these risks and
opportunities are applicable to the development in question, and ensure such developments are
proposed based on objective rationale and mutual benefit of all the stakeholders.
Page 12 of 13
References:
[1] International Gas Union (June 2015).
[2] Galway Regasification database and World LNG Factbook 2015.
[3] http://www.gastechnews.com/lng/petrobras-starts-up-brazils-third-fsru-import-facility/
[4] http://gcaptain.com/golar-lng-fsru-igloo-kuwait/ Kuwait Petroleum Signs Charter Contract for
Golar LNG’s Newbuild FSRU, ‘gCaptain’, 5 August 2013.
Page 13 of 13

More Related Content

What's hot

Small scale lng
Small scale lngSmall scale lng
Small scale lngfeikojager
 
Seagas LNG Bunkering Viking Grace
Seagas LNG Bunkering Viking GraceSeagas LNG Bunkering Viking Grace
Seagas LNG Bunkering Viking GraceJohn Hatley PE
 
LNG Controversy
LNG ControversyLNG Controversy
LNG Controversymimariner
 
Global LNG bunkering infrastructure
Global LNG bunkering infrastructureGlobal LNG bunkering infrastructure
Global LNG bunkering infrastructureGeorge Teriakidis
 
Asia Days 2013 - Market opportunities for small LNG distribution
Asia Days 2013 - Market opportunities for small LNG distributionAsia Days 2013 - Market opportunities for small LNG distribution
Asia Days 2013 - Market opportunities for small LNG distributionInnovation Norway
 
Risk assessments of harbour operations involving lng carriers
Risk assessments of harbour operations involving lng carriersRisk assessments of harbour operations involving lng carriers
Risk assessments of harbour operations involving lng carriersLars Petter Blikom
 
LNG Marine Fuel Adoption, How Soon, Which Routes, and Vessel Types
LNG Marine Fuel Adoption, How Soon, Which Routes, and Vessel TypesLNG Marine Fuel Adoption, How Soon, Which Routes, and Vessel Types
LNG Marine Fuel Adoption, How Soon, Which Routes, and Vessel TypesJohn Hatley PE
 
Supporting an lng fuelled marine industry future across the entire gas value ...
Supporting an lng fuelled marine industry future across the entire gas value ...Supporting an lng fuelled marine industry future across the entire gas value ...
Supporting an lng fuelled marine industry future across the entire gas value ...Wärtsilä Marine Solutions
 
LNG Gas Supply System for Submarine
 LNG Gas Supply System for Submarine LNG Gas Supply System for Submarine
LNG Gas Supply System for SubmarineCunico Corp
 
World FLNG Market Forecast 2015-2021 Leaflet + Contents
World FLNG Market Forecast 2015-2021 Leaflet + ContentsWorld FLNG Market Forecast 2015-2021 Leaflet + Contents
World FLNG Market Forecast 2015-2021 Leaflet + ContentsDouglas-Westwood
 
Small and medium scale LNG for power generation
Small and medium scale LNG for power generationSmall and medium scale LNG for power generation
Small and medium scale LNG for power generationSmart Power Generation
 
Gas entec ppt for_gis 2016_distribution
Gas entec ppt for_gis 2016_distributionGas entec ppt for_gis 2016_distribution
Gas entec ppt for_gis 2016_distributionBrandon Shin
 
Will the shipbuilding industry flourish again? (Eun-Chang Lee)
Will the shipbuilding industry flourish again? (Eun-Chang Lee)Will the shipbuilding industry flourish again? (Eun-Chang Lee)
Will the shipbuilding industry flourish again? (Eun-Chang Lee)POSCO Research Institute
 
LNG fuelled container feeder ship
LNG fuelled container feeder shipLNG fuelled container feeder ship
LNG fuelled container feeder shipNitin Sharma
 
Determining the Viability of a Small Scale LNG Project
Determining the Viability of a Small Scale LNG ProjectDetermining the Viability of a Small Scale LNG Project
Determining the Viability of a Small Scale LNG ProjectSampo Suvisaari
 
Wärtsilä: Ensuring sustainable electricity supply in Myanmar
Wärtsilä: Ensuring sustainable electricity supply in Myanmar Wärtsilä: Ensuring sustainable electricity supply in Myanmar
Wärtsilä: Ensuring sustainable electricity supply in Myanmar Wärtsilä Marine Solutions
 

What's hot (20)

Small scale lng
Small scale lngSmall scale lng
Small scale lng
 
Seagas LNG Bunkering Viking Grace
Seagas LNG Bunkering Viking GraceSeagas LNG Bunkering Viking Grace
Seagas LNG Bunkering Viking Grace
 
LNG Controversy
LNG ControversyLNG Controversy
LNG Controversy
 
Global LNG bunkering infrastructure
Global LNG bunkering infrastructureGlobal LNG bunkering infrastructure
Global LNG bunkering infrastructure
 
Tanker Update 01 2015
Tanker Update 01 2015Tanker Update 01 2015
Tanker Update 01 2015
 
Seca seminar 2013 rolls royce - stein ruben larsen
Seca seminar 2013   rolls royce - stein ruben larsenSeca seminar 2013   rolls royce - stein ruben larsen
Seca seminar 2013 rolls royce - stein ruben larsen
 
Asia Days 2013 - Market opportunities for small LNG distribution
Asia Days 2013 - Market opportunities for small LNG distributionAsia Days 2013 - Market opportunities for small LNG distribution
Asia Days 2013 - Market opportunities for small LNG distribution
 
Risk assessments of harbour operations involving lng carriers
Risk assessments of harbour operations involving lng carriersRisk assessments of harbour operations involving lng carriers
Risk assessments of harbour operations involving lng carriers
 
LNG Marine Fuel Adoption, How Soon, Which Routes, and Vessel Types
LNG Marine Fuel Adoption, How Soon, Which Routes, and Vessel TypesLNG Marine Fuel Adoption, How Soon, Which Routes, and Vessel Types
LNG Marine Fuel Adoption, How Soon, Which Routes, and Vessel Types
 
Supporting an lng fuelled marine industry future across the entire gas value ...
Supporting an lng fuelled marine industry future across the entire gas value ...Supporting an lng fuelled marine industry future across the entire gas value ...
Supporting an lng fuelled marine industry future across the entire gas value ...
 
LNG Gas Supply System for Submarine
 LNG Gas Supply System for Submarine LNG Gas Supply System for Submarine
LNG Gas Supply System for Submarine
 
World FLNG Market Forecast 2015-2021 Leaflet + Contents
World FLNG Market Forecast 2015-2021 Leaflet + ContentsWorld FLNG Market Forecast 2015-2021 Leaflet + Contents
World FLNG Market Forecast 2015-2021 Leaflet + Contents
 
Small and medium scale LNG for power generation
Small and medium scale LNG for power generationSmall and medium scale LNG for power generation
Small and medium scale LNG for power generation
 
Gas entec ppt for_gis 2016_distribution
Gas entec ppt for_gis 2016_distributionGas entec ppt for_gis 2016_distribution
Gas entec ppt for_gis 2016_distribution
 
Will the shipbuilding industry flourish again? (Eun-Chang Lee)
Will the shipbuilding industry flourish again? (Eun-Chang Lee)Will the shipbuilding industry flourish again? (Eun-Chang Lee)
Will the shipbuilding industry flourish again? (Eun-Chang Lee)
 
LNG fuelled container feeder ship
LNG fuelled container feeder shipLNG fuelled container feeder ship
LNG fuelled container feeder ship
 
Determining the Viability of a Small Scale LNG Project
Determining the Viability of a Small Scale LNG ProjectDetermining the Viability of a Small Scale LNG Project
Determining the Viability of a Small Scale LNG Project
 
Poten and partners
Poten and partnersPoten and partners
Poten and partners
 
Wärtsilä: Ensuring sustainable electricity supply in Myanmar
Wärtsilä: Ensuring sustainable electricity supply in Myanmar Wärtsilä: Ensuring sustainable electricity supply in Myanmar
Wärtsilä: Ensuring sustainable electricity supply in Myanmar
 
LNG Fuel Marine Adoption
LNG Fuel Marine AdoptionLNG Fuel Marine Adoption
LNG Fuel Marine Adoption
 

Viewers also liked

FSRU Technology & Project Development
FSRU Technology & Project DevelopmentFSRU Technology & Project Development
FSRU Technology & Project DevelopmentWalter Lee
 
Introduction to Floating Storage & Regasification Unit (FSRU)
Introduction to Floating Storage & Regasification Unit (FSRU)Introduction to Floating Storage & Regasification Unit (FSRU)
Introduction to Floating Storage & Regasification Unit (FSRU)petroEDGE
 
Compatibility Study of FSRU Exemplar for STS Transfer with LNGC
Compatibility Study of FSRU Exemplar for STS Transfer with LNGCCompatibility Study of FSRU Exemplar for STS Transfer with LNGC
Compatibility Study of FSRU Exemplar for STS Transfer with LNGCAchmad Agung P
 
Presentataion Oil&Gas Telecommunications Conference - Radio LInk Project
Presentataion  Oil&Gas Telecommunications Conference - Radio LInk Project Presentataion  Oil&Gas Telecommunications Conference - Radio LInk Project
Presentataion Oil&Gas Telecommunications Conference - Radio LInk Project Andrea Vallavanti
 
Curriculum vitae 2015
Curriculum vitae 2015Curriculum vitae 2015
Curriculum vitae 2015Alex Pogacini
 
Presentazione OIL and GAS Telecommunications Conference rev 6 marzo_va
Presentazione OIL and GAS Telecommunications Conference rev 6 marzo_vaPresentazione OIL and GAS Telecommunications Conference rev 6 marzo_va
Presentazione OIL and GAS Telecommunications Conference rev 6 marzo_vaAndrea Vallavanti
 
628 ocg lng special investigation report part 1
628 ocg lng special investigation report part 1628 ocg lng special investigation report part 1
628 ocg lng special investigation report part 1Agustinus Cahyo Wibowo
 
Abstract recent developments in offshore gas technology –fsru, flng, fcng
Abstract   recent developments in offshore gas technology –fsru, flng, fcngAbstract   recent developments in offshore gas technology –fsru, flng, fcng
Abstract recent developments in offshore gas technology –fsru, flng, fcngAnoop Rajendran Nair
 
Fsru conference fsru dam 21 nov 12
Fsru conference fsru dam 21 nov 12Fsru conference fsru dam 21 nov 12
Fsru conference fsru dam 21 nov 12swoolway
 
Risk management during start up and commissioning of super critical once thro...
Risk management during start up and commissioning of super critical once thro...Risk management during start up and commissioning of super critical once thro...
Risk management during start up and commissioning of super critical once thro...HIMADRI BANERJI
 
Floating Liquefaction: An Alternative Solution for Alaska
Floating Liquefaction: An Alternative Solution for AlaskaFloating Liquefaction: An Alternative Solution for Alaska
Floating Liquefaction: An Alternative Solution for Alaskaalaskalng
 
Hoegh LNG Q1 2014 results presentation
Hoegh LNG Q1 2014 results presentationHoegh LNG Q1 2014 results presentation
Hoegh LNG Q1 2014 results presentationTradeWindsnews
 
Lng project risk and appraisal 2012 final 03092012
Lng project risk and appraisal 2012 final 03092012Lng project risk and appraisal 2012 final 03092012
Lng project risk and appraisal 2012 final 03092012HIMADRI BANERJI
 
Developing a Successful FLNG Project
Developing a Successful FLNG ProjectDeveloping a Successful FLNG Project
Developing a Successful FLNG ProjectDale Butler
 
Wärtsilä Mobile LNG - Your Shorter Route to Gas
Wärtsilä Mobile LNG - Your Shorter Route to GasWärtsilä Mobile LNG - Your Shorter Route to Gas
Wärtsilä Mobile LNG - Your Shorter Route to GasWärtsilä Marine Solutions
 
FPSO Redeployment
FPSO RedeploymentFPSO Redeployment
FPSO RedeploymentDan Benson
 
En indonesian energyupdates_oct13
En indonesian energyupdates_oct13En indonesian energyupdates_oct13
En indonesian energyupdates_oct13Hafid Alwan
 

Viewers also liked (20)

FSRU Technology & Project Development
FSRU Technology & Project DevelopmentFSRU Technology & Project Development
FSRU Technology & Project Development
 
Introduction to Floating Storage & Regasification Unit (FSRU)
Introduction to Floating Storage & Regasification Unit (FSRU)Introduction to Floating Storage & Regasification Unit (FSRU)
Introduction to Floating Storage & Regasification Unit (FSRU)
 
Compatibility Study of FSRU Exemplar for STS Transfer with LNGC
Compatibility Study of FSRU Exemplar for STS Transfer with LNGCCompatibility Study of FSRU Exemplar for STS Transfer with LNGC
Compatibility Study of FSRU Exemplar for STS Transfer with LNGC
 
FSRU_projects
FSRU_projectsFSRU_projects
FSRU_projects
 
Presentataion Oil&Gas Telecommunications Conference - Radio LInk Project
Presentataion  Oil&Gas Telecommunications Conference - Radio LInk Project Presentataion  Oil&Gas Telecommunications Conference - Radio LInk Project
Presentataion Oil&Gas Telecommunications Conference - Radio LInk Project
 
Curriculum vitae 2015
Curriculum vitae 2015Curriculum vitae 2015
Curriculum vitae 2015
 
Presentazione OIL and GAS Telecommunications Conference rev 6 marzo_va
Presentazione OIL and GAS Telecommunications Conference rev 6 marzo_vaPresentazione OIL and GAS Telecommunications Conference rev 6 marzo_va
Presentazione OIL and GAS Telecommunications Conference rev 6 marzo_va
 
628 ocg lng special investigation report part 1
628 ocg lng special investigation report part 1628 ocg lng special investigation report part 1
628 ocg lng special investigation report part 1
 
Abstract recent developments in offshore gas technology –fsru, flng, fcng
Abstract   recent developments in offshore gas technology –fsru, flng, fcngAbstract   recent developments in offshore gas technology –fsru, flng, fcng
Abstract recent developments in offshore gas technology –fsru, flng, fcng
 
Broadwater Powerpoint
Broadwater PowerpointBroadwater Powerpoint
Broadwater Powerpoint
 
Fsru conference fsru dam 21 nov 12
Fsru conference fsru dam 21 nov 12Fsru conference fsru dam 21 nov 12
Fsru conference fsru dam 21 nov 12
 
Risk management during start up and commissioning of super critical once thro...
Risk management during start up and commissioning of super critical once thro...Risk management during start up and commissioning of super critical once thro...
Risk management during start up and commissioning of super critical once thro...
 
Floating Liquefaction: An Alternative Solution for Alaska
Floating Liquefaction: An Alternative Solution for AlaskaFloating Liquefaction: An Alternative Solution for Alaska
Floating Liquefaction: An Alternative Solution for Alaska
 
Hoegh LNG Q1 2014 results presentation
Hoegh LNG Q1 2014 results presentationHoegh LNG Q1 2014 results presentation
Hoegh LNG Q1 2014 results presentation
 
Lng project risk and appraisal 2012 final 03092012
Lng project risk and appraisal 2012 final 03092012Lng project risk and appraisal 2012 final 03092012
Lng project risk and appraisal 2012 final 03092012
 
Developing a Successful FLNG Project
Developing a Successful FLNG ProjectDeveloping a Successful FLNG Project
Developing a Successful FLNG Project
 
D mfor lng
D mfor lngD mfor lng
D mfor lng
 
Wärtsilä Mobile LNG - Your Shorter Route to Gas
Wärtsilä Mobile LNG - Your Shorter Route to GasWärtsilä Mobile LNG - Your Shorter Route to Gas
Wärtsilä Mobile LNG - Your Shorter Route to Gas
 
FPSO Redeployment
FPSO RedeploymentFPSO Redeployment
FPSO Redeployment
 
En indonesian energyupdates_oct13
En indonesian energyupdates_oct13En indonesian energyupdates_oct13
En indonesian energyupdates_oct13
 

Similar to LNG18_FSRU Risk and Opportunities

FloatingLNGRevolutionEvolution
FloatingLNGRevolutionEvolutionFloatingLNGRevolutionEvolution
FloatingLNGRevolutionEvolutionAndy Varoshiotis
 
August Newsletter - Affinity Small Scale LNG.pdf
August Newsletter  - Affinity Small Scale LNG.pdfAugust Newsletter  - Affinity Small Scale LNG.pdf
August Newsletter - Affinity Small Scale LNG.pdfAbrorieABE
 
Brookings Speech.03.03.15
Brookings Speech.03.03.15Brookings Speech.03.03.15
Brookings Speech.03.03.15John Graykowski
 
2011 LNG AS PROPULSION FUEL
2011 LNG AS PROPULSION FUEL2011 LNG AS PROPULSION FUEL
2011 LNG AS PROPULSION FUELMEC Intelligence
 
Basic technology & solutions of LNG
Basic technology & solutions of LNGBasic technology & solutions of LNG
Basic technology & solutions of LNGAbu Bakar Siddiqui
 
MARKET ANALYSIS OF LIQUEFIED GAS INDUSTRY UPTO 2030
MARKET ANALYSIS OF LIQUEFIED GAS INDUSTRY UPTO 2030MARKET ANALYSIS OF LIQUEFIED GAS INDUSTRY UPTO 2030
MARKET ANALYSIS OF LIQUEFIED GAS INDUSTRY UPTO 2030Capt. Ayan Banerjee
 
Global LNG Navigating Risks in a Dynamic Market
Global LNG Navigating Risks in a Dynamic MarketGlobal LNG Navigating Risks in a Dynamic Market
Global LNG Navigating Risks in a Dynamic MarketCTRM Center
 
APAC LNG PDF
APAC LNG PDFAPAC LNG PDF
APAC LNG PDFPaul Lim
 
11th FLNG APAC 2013 brochure_website 4 July 2013
11th FLNG APAC 2013 brochure_website 4 July 201311th FLNG APAC 2013 brochure_website 4 July 2013
11th FLNG APAC 2013 brochure_website 4 July 2013Connie Kirk
 
Hydrogen_Valley_Feasibility_Study_Report_Final_Version.pdf
Hydrogen_Valley_Feasibility_Study_Report_Final_Version.pdfHydrogen_Valley_Feasibility_Study_Report_Final_Version.pdf
Hydrogen_Valley_Feasibility_Study_Report_Final_Version.pdfkyaq0011
 
Cogliolo Andrea - Innovation & Research - RINA
Cogliolo Andrea - Innovation & Research - RINACogliolo Andrea - Innovation & Research - RINA
Cogliolo Andrea - Innovation & Research - RINAWEC Italia
 
Future Trends in LNG Project Finance (2011)
Future Trends in LNG Project Finance (2011)Future Trends in LNG Project Finance (2011)
Future Trends in LNG Project Finance (2011)Michael Filippich
 
Global lng market assessment
Global lng market assessmentGlobal lng market assessment
Global lng market assessmentJulie Dubrovskaya
 
global lng fleet market
global lng fleet marketglobal lng fleet market
global lng fleet marketPreeti Singh
 
LNG Bunkering Market.pptx
LNG Bunkering Market.pptxLNG Bunkering Market.pptx
LNG Bunkering Market.pptxRahulcmi
 
Oivin inversen's presentation slides from the 2010 World National Oil Compani...
Oivin inversen's presentation slides from the 2010 World National Oil Compani...Oivin inversen's presentation slides from the 2010 World National Oil Compani...
Oivin inversen's presentation slides from the 2010 World National Oil Compani...oilandgas
 
The rising demand of offshore wind vessels and its impact on the industry
The rising demand of offshore wind vessels and its impact on the industryThe rising demand of offshore wind vessels and its impact on the industry
The rising demand of offshore wind vessels and its impact on the industryTorben Haagh
 

Similar to LNG18_FSRU Risk and Opportunities (20)

FloatingLNGRevolutionEvolution
FloatingLNGRevolutionEvolutionFloatingLNGRevolutionEvolution
FloatingLNGRevolutionEvolution
 
August Newsletter - Affinity Small Scale LNG.pdf
August Newsletter  - Affinity Small Scale LNG.pdfAugust Newsletter  - Affinity Small Scale LNG.pdf
August Newsletter - Affinity Small Scale LNG.pdf
 
Brookings Speech.03.03.15
Brookings Speech.03.03.15Brookings Speech.03.03.15
Brookings Speech.03.03.15
 
2011 LNG AS PROPULSION FUEL
2011 LNG AS PROPULSION FUEL2011 LNG AS PROPULSION FUEL
2011 LNG AS PROPULSION FUEL
 
Basic technology & solutions of LNG
Basic technology & solutions of LNGBasic technology & solutions of LNG
Basic technology & solutions of LNG
 
MARKET ANALYSIS OF LIQUEFIED GAS INDUSTRY UPTO 2030
MARKET ANALYSIS OF LIQUEFIED GAS INDUSTRY UPTO 2030MARKET ANALYSIS OF LIQUEFIED GAS INDUSTRY UPTO 2030
MARKET ANALYSIS OF LIQUEFIED GAS INDUSTRY UPTO 2030
 
Global LNG Navigating Risks in a Dynamic Market
Global LNG Navigating Risks in a Dynamic MarketGlobal LNG Navigating Risks in a Dynamic Market
Global LNG Navigating Risks in a Dynamic Market
 
IGU_WorldLNG_2021.pdf
IGU_WorldLNG_2021.pdfIGU_WorldLNG_2021.pdf
IGU_WorldLNG_2021.pdf
 
APAC LNG PDF
APAC LNG PDFAPAC LNG PDF
APAC LNG PDF
 
11th FLNG APAC 2013 brochure_website 4 July 2013
11th FLNG APAC 2013 brochure_website 4 July 201311th FLNG APAC 2013 brochure_website 4 July 2013
11th FLNG APAC 2013 brochure_website 4 July 2013
 
Hydrogen_Valley_Feasibility_Study_Report_Final_Version.pdf
Hydrogen_Valley_Feasibility_Study_Report_Final_Version.pdfHydrogen_Valley_Feasibility_Study_Report_Final_Version.pdf
Hydrogen_Valley_Feasibility_Study_Report_Final_Version.pdf
 
CCS learnings from the LNG sector
CCS learnings from the LNG sectorCCS learnings from the LNG sector
CCS learnings from the LNG sector
 
Cogliolo Andrea - Innovation & Research - RINA
Cogliolo Andrea - Innovation & Research - RINACogliolo Andrea - Innovation & Research - RINA
Cogliolo Andrea - Innovation & Research - RINA
 
Future Trends in LNG Project Finance (2011)
Future Trends in LNG Project Finance (2011)Future Trends in LNG Project Finance (2011)
Future Trends in LNG Project Finance (2011)
 
Global lng market assessment
Global lng market assessmentGlobal lng market assessment
Global lng market assessment
 
global lng fleet market
global lng fleet marketglobal lng fleet market
global lng fleet market
 
LNG Bunkering Market.pptx
LNG Bunkering Market.pptxLNG Bunkering Market.pptx
LNG Bunkering Market.pptx
 
Oivin inversen's presentation slides from the 2010 World National Oil Compani...
Oivin inversen's presentation slides from the 2010 World National Oil Compani...Oivin inversen's presentation slides from the 2010 World National Oil Compani...
Oivin inversen's presentation slides from the 2010 World National Oil Compani...
 
The rising demand of offshore wind vessels and its impact on the industry
The rising demand of offshore wind vessels and its impact on the industryThe rising demand of offshore wind vessels and its impact on the industry
The rising demand of offshore wind vessels and its impact on the industry
 
2021 Is the floating LNG moment?
2021 Is the floating LNG moment?2021 Is the floating LNG moment?
2021 Is the floating LNG moment?
 

LNG18_FSRU Risk and Opportunities

  • 1. FSRU: Risks and Opportunities Karthik Sathyamoorthy President Sudhanshu Haldar Manager Galway Group 8 Temasek Blvd, #22–04, Suntec Tower 3 Singapore 038988 www.galwaygroup.com ABSTRACT In the context of rising global energy demand and abundant shale gas reserves, governments and developers across the world are considering natural gas as a viable fuel for augmenting their energy portfolios. Increasingly, gas buyers are exploring floating regasification solutions for their perceived speed of deployment, cost advantages, and redeployment flexibility. FSRU solution comes in different configurations. For example, Brazil has two out of three FSRUs converted from LNGC, whereas Uruguay is going forward with world’s biggest new-built FSRU. However, the FSRU market is in early stages and there is an increasing need for understanding the opportunities and risks associated with potential FSRU solutions. This paper outlines and explores FSRU as a regasification solution, as compared to an onshore terminal, and discusses some major risks and key drivers for FSRUs from a developer’s perspective. These risks and opportunities have been discussed from investment, commercial and technology aspects. This paper also points out some major considerations that a project developer should weigh to gain a clear understanding of whether FSRU is the right solution for the project under consideration.
  • 2. Page 2 of 13 Introduction and Background With increasing gas demand across the world, new and innovative LNG terminal solutions have surfaced the industry. These innovations spread across both the technological and commercial fronts. A unique combination of these innovations has resulted in the emergence of floating regasification solutions as an alternate to the onshore regasification terminals. Gulf Gateway Deepwater port, installed offshore Louisiana in March 2005, was the earliest design of floating regasification solutions. This facility utilized a submerged turret-loading buoy that allowed connection to multiple downstream pipelines. However, the shale boom was unforeseen at the time of this development. As a result of this significant development in gas production in the US, Gulf Gateway was decommissioned in 2012. Gulf Gateway’s era may be over, but its proven technology opened the doors for a new age of innovative floating regasification solutions. This technology has largely been derived from either the offshore oil industry (e.g., mooring systems, unloading systems), the LNG shipping industry (e.g., LNG containment systems), or land-based LNG regasification (e.g., vaporizers). Therefore, the technology risks are well understood and can be managed effectively on a project-by-project basis, leading to as increased acceptance of floating regasification solutions. Figure 1. Start-Ups of LNG Receiving Terminals, 1980-20161 Today, FSRUs not only provide an alternate option to onshore regasification solution, but also offer a better economic fit in many cases. In the current market, FSRUs are challenging the traditional onshore regasification solution and with more than 20 speculative projects2 , are one of the primary contenders for future regasification capacity. A decade of FSRU operations have built confidence in the industry about their reliability and safety of operations. However, in certain instances, FSRUs grapple with some technological and commercial challenges, putting them at a disadvantage as compared to onshore terminals.
  • 3. Page 3 of 13 How are FSRUs different from an Onshore Facility? An FSRU is a ship or barge that is built (or retrofitted from an LNG carrier) to be able to perform regasification operations onboard. The vessel requires little or no site preparation (except associated facilities) and is equipped with an onboard LNG storage facility. In some instances, it can also connect to the existing offshore gas pipeline grid. This is unlike an onshore development, which requires on-land site preparation and development, constructing cryogenic storage tanks, integrating LNG regasification units and developing a berthing facility for LNG carriers. An FSRU can be built either by retrofitting an existing LNG ship (“Retrofit”) or a by building an entirely new LNG ship fitted onboard regasification equipment (“Newbuild”). A retrofitted FSRU is one that is adapted from an LNG carrier. Retrofitting includes making modifications and adding a regasification unit onboard. Many factors come into the equation when determining which type of LNG carrier would make the best FSRU – availability and costs being the leading factors. The two most prominent drivers that have made the FSRU option attractive to the developers are (i) shorter project development timeline as compared to an onshore terminal with a similar gas send-out rate, and; (ii) lower upfront project development capital costs as compared to a similar sized onshore terminal. FSRUs have proven to be a better alternative for locations where either space for development or additional infrastructure is a constraint. FSRUs can also be employed for the use of offshore gas grids, which are no longer in use. Shorter permitting timelines are also often pronounced as one of the benefits, however, this can vary case by case basis. Current FSRU market and outlook The floating LNG terminal market is a relatively new one. However, FSRUs have been gaining a market share, especially among the new and proposed regasification terminals. The share of FSRU as an import terminal option among the LNG importing countries is increasing swiftly and FSRUs continue to gain popularity, especially in countries that are looking to enter the LNG import market with lower capital investment and within a short timeframe. Since the inception of the floating LNG solutions in 2005, more than 20 FSRUs have been constructed and deployed. Over the last decade, the highest activity in the FSRU segment has been observed in Middle- east and South America. Recently European and Asian economies have started deploying FSRUs to meet their natural gas needs. By end of 2014, Brazil’s Bahia/TRBA, Indonesia’s Lampung, and Lithuania’s Klaipeda LNG began their operations. In 2015, three additional FSRUs came online, including one in Pakistan chartered from Excelerate Energy, one in Egypt chartered from Hoegh LNG and one in Jordan chartered from Golar LNG1 . The following chart (Figure 2) maps the existing terminals across the globe.
  • 4. Page 4 of 13 Figure 2. Status of existing and under construction FSRUs globally [Galway Database] The market for FSRUs can be classified into two categories: Vessel Owners and Operators/Charterers. The current FSRU market players can be categorized as (i) Pure Play FSRU vessel/owner companies: Excelerate, Golar and Hoegh, who have been the leaders in supply of FSRUs, primarily because they were first movers and have successfully developed, built and operated floating LNG vessels. (ii) Shipping Companies: Primarily existing shipping companies who are starting to focus on floating LNG vessels, e.g., Mitsui OSK Lines (MOL), BW Offshore, Teekay, NYK, and MISC. (iii) NOCs and government agencies: In certain cases, the NOCs and government entities are also increasingly participating in FSRU projects to gain experience and independently operate FSRUs in the domestic market. Based on the current trend and popularity, it is reasonable to infer that the FSRU market is on an upswing, undeterred by the weak commodity markets. In addition to the planned and proposed projects, there are at least ten other speculative projects in South America, the Middle east and Europe. These projects are expected to take FID by the end of the decade. The FSRU market is further expected to grow. This growth will be fueled by the following factors:  The recent dispute between Ukraine and Russia raised energy security concerns among countries in the European Union, who import majority of their gas from Russia. FSRUs can connect these countries to global gas supplies while offering diversification in the European Union’s gas portfolio.  Importers have an opportunity to capitalize on the current low LNG prices, which are traditionally linked to oil prices (projected to remain low). Additionally, further downward pricing pressure is expected on account of the surplus future supplies from the US and Australian LNG projects.  Increased development of gas fired power generation and lowering of nuclear power dependence in Japan and Europe
  • 5. Page 5 of 13  Bridging solution for countries transitioning from being natural gas exporters to importers and countries that need temporary intermediate energy solutions while development of large onshore terminals is underway  Bridging solution until cleaner and renewable fuels can be scalable and commercialized  Small scale opportunities for FSRUs in areas with scattered demand e.g. Indonesia On the back of the current situation and the expected developments in this space, it is reasonable to assume that FSRUs have the potential to develop into a highly preferred regasification option in the future. However, there are numerous complexities – technological, commercial and operational – which can undermine the prospects of FSRU project development. These potential challenges need to be overcome for the industry’s full potential to be achieved. FSRUS: Opportunities and Risks - A developer’s dilemma Although, natural gas is increasingly expected to play a pivotal role in the energy mix for a large number of countries, the availability of the natural gas resources are not shared equally. A growing number of countries are turning to LNG imports to meet their growing gas demand. This presents the developers with an opportunity to come up with an economically sound and a safe natural gas import strategy. There are multiple decisions to be made when strategizing a regasification project. The primary decision is on the type of import terminal to be developed – onshore or offshore. Further, there are hybrid solutions such as a Floating Storage Unit (FSU) with regasification units located onshore that can be considered. Such a solution might be required depending on site considerations and may be more appropriate if:  There are exclusion zone limitations with siting of LNG storage tanks onshore e.g., adherence to thermal radiation and vapor dispersion regulations;  An LNG import facility is being fast-tracked and operations have to start before completion of the onshore storage tanks. A developer must clearly understand various pros and cons of onshore and offshore solutions before embarking on a development plan. The following section offers some insights on these risks and opportunities associated with offshore regasification solutions when compared with onshore solutions. Key Drivers in favor of an FSRU FSRUs are becoming increasingly popular among the new LNG regasification project developers because of following perceived benefits A. Lower upfront development cost as compared to an onshore regasification facility One of the primary drivers in favor of the FSRU option is the low upfront capital investment requirement. A typical FSRU can cost in the range of US $250 million to US $350 million (additional US $200 to US $400 million for associated facilities) as compared to a similar sized (gas send-out) onshore facility, which can cost in the range of US $1.0 billion to US $1.5 billion. FSRU capital costs are typically lower onshore regasification terminals because of following reasons:
  • 6. Page 6 of 13  FSRUs do not require expensive site development and the construction of stand-alone LNG storage tanks (each tank can costs in excess of US $150 million)  FSRUs are built in a shipyard, so there can be a better control over costs as compared to an onshore terminal  FSRUs and associated facilities have a lower footprint as compared to onshore terminals, thus reducing land procurement costs Depending on the project developer’s needs, a further reduction in upfront cost can also be attained by retrofitting an existing LNG carrier, or leasing an existing FSRU vessel. The latter option, however, will result in loss of ship deck customization and can turn expensive if employed on a long term basis. B. Faster project development timeline as compared to an onshore facility The development timeline of an FSRU based project can vary between 12 to 36 months. If an FSRU is already available, the delivery time is even shorter. However, if an existing vessel is converted, it could be take anywhere in the range of 12 to 18 months. In the case of a newbuild FSRU, the construction and delivery time could be up to 3 years. This is considerably shorter as compared to an onshore development, which requires 48 to 56 months for development. Reasons for faster delivery time of an FSRU solutions include:  FSRUs are built in shipyards that have years of experience in ship design and have a better understanding of construction bottlenecks and resources at hand  In most cases FSRU projects enjoy the advantage of shorter permitting timelines on account of fewer participants and affected entities involved. However, it is important to note that such permitting timelines can be site specific  Speculation based inventory management by leading FSRU developers, long lasting relationship with the shipyards and, in certain cases, standardized design. Project delivery in such a relatively shorter time frame makes FSRU a very lucrative option for developers who are running against the clock to meet acute supply shortages. An onshore terminal project development is usually exposed to various potential bottlenecks including site preparation, temporary material handling, labor shortages, equipment transportation, and schedule mismatch among the various participants. These factors can significantly delay the construction timeline and result in unexpected cost overruns. C. Inherent flexibility offered by FSRU solution Traditionally, there has been a lack of infrastructure to meet the needs of scattered energy demand centers in archipelago countries like Indonesia or vast countries like Brazil and Argentina with long coastlines. In such cases, distribution of natural gas (post LNG regasification) received at an onshore facility through cross-country pipelines becomes cumbersome, expensive and infeasible. In such cases, an FSRU presents the most optimal solution providing flexibility in location (can be located as close to the demand centre as possible) and regasification capacity at a lower cost of delivered gas. Some of the mentionable flexibility options provided by this solution are as follows:
  • 7. Page 7 of 13  Unlike a fixed onshore facility, an FSRU can be relocated and deployed according to the need of downstream market. A good example of this can be seen in Brazil where a Golar FSRU located in Guanabara Bay was relocated to Bahia, Salvador. The Guanabara Bay FSRU was replaced by an Excelerate FSRU3 .  In case of a seasonal gas demand profile, an FSRU can be used to supply gas during periods when there is gas demand and during the remainder of the year it can be used as an LNG carrier. This model has been adopted by the Kuwait National Petroleum Company (KNPC), where the vessel is deployed as an FSRU for nine months and is free to pursue other spot LNG opportunities for three months4 .  An FSRU can act as a base-load solution for smaller demand centers or peak-shaving solution for larger center.  FSRUs can be moved away to safety in case of a tsunami or similar natural or man-made disasters. D. Economic Options and Financial Incentives of an FSRU During the early years, offshore regasification solutions were conventional, long-term and rigid, which was likely a lender’s requirement for the unestablished market. However, over the years, this rigidity in FSRU chartering has diminished significantly to less than five years of contract. Such short-term chartering option facilitates the use of FSRU as a bridging solution during the development of a land based regasification solution at the location. Such development strategies have been seen in Chile (FSU), Egypt and Kuwait. From an investor perspective, FSRUs have been drawing attention because of a faster return on capital invested and a better residual value. The former depends on the utilization rate of the FSRU (a higher utilization will result in a faster capital recovery) and the value of latter lies in the option of re-deployment of the vessel as an LNG carrier. Key challenges for an FSRU As we discussed in the previous section, the opportunities that FSRUs bring to the table are numerous and multifold. However, there are some challenges that the FSRU industry is currently grappling with and these are discussed in the following section. A. Metocean conditions threaten the availability of an FSRU Meteorological and oceanic condition pose some serious challenges for the FSRU industry. Depending on the severity of ocean conditions, LNG unloading could become one of the most difficult tasks in FSRU operations. For side by side cargo unloading, a calm to mild sea state is paramount, in absence of which an LNG carrier may have to wait for the ocean to return to normal conditions before commencing safe operations. It is the same case when the FSRU is loaded with LNG. Metocean factors can affect the send-out operations of an FSRU by disrupting the mooring and regasified LNG connections. These factors can severely hurt the reliability and availability of an FSRU. An onshore plant, on the other hand, uses hard arms for unloading LNG and further onshore operations usually escape the risk of uncertain open ocean behavior. LNG stored in onshore tanks remains safe from the uncertain ocean and the regasification unit can meet the downstream gas demand with more certainty and reliability.
  • 8. Page 8 of 13 B. Technological challenges may limit the availability of an FSRU In the process of ship-to-ship transfer (STS), an LNG carrier moors along-side the FSRU and discharges LNG into the FSRU using flexible cryogenic hoses. This is still an evolving technology and the long-term reliability of flexible cryogenic hoses in a marine environment is unproven and is being evaluated for long life. STS operations require benign conditions to ensure high regasification and berthing/unloading availability. Additionally, many of the deep-water unloading concepts such as Submerged Single/Double Moored Buoy and Above Water Single Point Mooring – which can operate in deep water – still remain theoretical because of the supplier’s and operator’s discomfort with implementing such a system in deep water. On the other hand, with years of successful operations all over the world, onshore regasification terminals have significantly overcome most of the technological challenges. Also, industry practices are well defined and -accepted by LNG suppliers and standards are well established and risks are known and tested. These advantages may tend to make the onshore terminal option as the most preferred one amongst suppliers. C. Challenges attributed to limited deck and storage space Another challenge faced by FSRUs is the limited deck and storage space. Unlike an onshore facility, where future expansions can be a part of the original plan, an offshore solution suffers from the lack of available footprint. The cheaper and relatively flexible open rack vaporizers (ORV) used in a majority of onshore terminals may not be appropriate for an FSRU because of space constraints. Also, Expansion of storage capacity is not straight forward once the FSRU has been put in place. The space constraints in an FSRU result in a much stricter firewater regulation as compared to onshore facilities. Some other constraints which increase the design complexity of an FSRU pertain to the storage of LNG and onboard fuel, sloshing of LNG stored in the FSRU, high pressure regasification equipment installed onboard, mooring arrangement and transfer of LNG. An onshore regasification facility, as compared to FSRUs, enjoys sufficient footprint – in most of the cases – and can have flexible regasification options, warehouses, fuel storage tanks and firewater operations. The terminal can also pre-plan expansion options and construct the necessary expansion interface in advance to speed up such future plans. Such expansions can result in major economies of scale for the onshore regasification plant, a feature that is unavailable in FSRUs.
  • 9. Page 9 of 13 D. Challenges related to operation and maintenance The typical cost of operation (variable cost) of an FSRU is higher than that of an onshore terminal. The costs include the labor, crew costs, consumables, fuel and spare inventory. As compared to an onshore terminal, the crew in an FSRU terminal is more specialized and requires both LNG and ship operations experience. Such personnel are usually in high demand, leading to a further escalation in operational costs. There also are additional costs associated with storage of fuel, inventory management and disposal of processed waste – which pushes the operating costs higher. From the maintenance perspective, unlike in an onshore terminal, the spare parts in an offshore terminal could be highly FSRU specific. Consequently, in case of an equipment fault in an FSRU, the operations can suffer severe delays or send-out interruptions because the customized spare parts may have a longer lead time. These costs, if supplemented with limited availability of the FSRU on account of uncertain metocean conditions, can result in higher per unit cost of operations and tends to eliminate the advantage of low initial capital costs. For an onshore regasification plant, the processes are rather standardized, thus resulting in significantly lower operational costs. Additionally, operational risks are well understood and the reliability of equipment is well known. An objective approach to assess the viability of a regasification solution As compared to an onshore terminal, FSRU’s enjoy an inherent set of advantages. However, the potential challenges of operating an FSRU cannot be ignored altogether. This makes it imperative to lay-down a methodology to assess the optimum solution which aligns with the developer’s objective while ensuring that the solution meets the current industry standards. The decision of suitability of a development (onshore vs offshore) opportunity rests on the fulfilment of the questions related to stakeholders’ risk appetite and return expectations, the projects’ ability to meet the development and demand objectives, the required timeline to deliver the development and capital requirement for the development. These considerations are explained as below. What is the type of demand under question? For a project developer, it is important to understand the type of market and the demand profile a project is expected to service. Demand of a market can have a mixture of following three characters:  Short-term demand vs. Long term demand: Short-term demand to bridge until an alternate solution is reached; long-term demand to develop a permanent solution.  Baseload demand vs. Peak-shaving demand: Baseload demand to meet a large consistent gap; a peak-shaving demand to meeting acute changes in demand profile.  Yearlong demand vs. Seasonal demand: the profile of demand can be seasonal to meet the requirements in a few high demand seasons; continuous demand profile to meet demand in all seasons.
  • 10. Page 10 of 13 Strength of an onshore terminal lies in meeting constant downstream demand and providing continuous reliable operations, which makes it the most suitable candidate for a baseload facility. The onshore facility also have possibility of large storage space and possibility of expansion, and therefore, can the meet daily fluctuation of demand easily. However, an onshore facility might not be an appropriate solution if the demand profile is not continuous or a facility requirement is short- term or demand is scattered in the region where transporting natural gas through available infrastructure is not feasible. Partial utilization of these onshore terminals will yield the investment uneconomical and un-optimized. An FSRU successfully bridges the drawbacks of an onshore facility in this regard. The inherent flexibility of an FSRU – can be used as a regasification vessel or an LNG carrier – successfully meets the utilization requirement if demand is seasonal. Alternatively, an FSRU can encompass the capacity range from baseload to small scale requirement. The chartering option of an FSRU makes the solution lucrative in case of a bridging solution. Historically there have been a few examples where FSRUs are chartered for a short-term (under 5 years), like in Kuwait, till the permanent regasification solutions can be developed. These advantages, however, shall be weighted properly against the possible risks – including send-out rates and availability – that an FSRU solution can face as discussed in the previous sections. How fast the development has to be up and running? An LNG project is an intricate web of agencies and participants connected with individual timeline commitments. The supplier, the terminal developer, the aggregator, and the downstream customer must understand the implications of project development timelines. The factors which affect the timeline of a project are duration required to get permits, requirement of new and existing infrastructure, and downstream gas commitments. The project development timeline is one of the primary factors to narrow down the choice of regasification development. A typical onshore project takes around three to five years from permitting to starts operations, and delays in such construction timelines are rather frequent. The reasons for such delays may include issues such as remote location, labor shortages, permitting delays, and inspection and testing schedule mismatches. The implications of such uncertainty in construction timelines might not be acceptable to many participants as the bottlenecks may push the construction timelines of an onshore terminal further. In such cases, where meeting the construction timeline at the earliest is a necessity, an onshore regasification terminal might not be the best solution to meet the downstream demand. On the other hand, an FSRU meets the criteria of fast and on-time implementation well. The permitting and construction goes in parallel and it usually take a shorter timeframe for solution to be ready (12 to 36 months). The key to faster delivery of an FSRU lies in clarity of operational requirement. An FSRU construction happens in the shipyards in a controlled environment, and is less likely to face a delay. However, a project developer must scrutinize the permitting timelines and regulations well in advance to avoid roadblocks or change in design requirements.
  • 11. Page 11 of 13 Whether the FSRU fits the investment strategy of the developer? Projects in the LNG industry are capital intensive and, usually, form a part of long-term energy strategy. Therefore, from a project developer perspective, it is important to understand the developer’s risk appetite. The development must be scrutinized from the both country and project risk perspective. Understanding of country risk will help the developer get comfortable with the security of the investment, whereas the understanding of project risk will help the developer get a feel for the investment as compared to the other projects. An onshore regasification development, for example, is usually a part of a long-term development strategy of a country. A high upfront investment is required in the case of such development and the return is tied to the long-term viability and operations of the plant. The project also faces a significant country risk because the assets developed will be immovable and, in case of an unrest or change in demand pattern of the country, will get stranded with no residual value. An offshore FSRU development, however, faces some relief from the above mentioned risks. The upfront investment required, in most of the cases, is low and the vessel is mobile. This brings the country risk down significantly as the asset will not get stranded. Another aspect of such investment is low project risk as in case demand dries up, the vessel can be redeployed as an LNG Carrier. However, the FSRU availability and technology risks are much higher for an FSRU as compared to an onshore vessel. The above mentioned risk gets morphed in a different dimension with type of project structure. A build, own, operate and transfer (BOOT) structure for example will have different set of risk than a build operate and transfer (BOT) structure. The perceived confidence in country’s credit will affect the financing of these projects and eventually the expected return and investment security. A comparative thorough assessment of the above mentioned risks between an onshore development and an offshore development options is of utmost importance for a project developer to ensure the security of the investment. Conclusion FSRUs are the new players, in the world dominated by onshore terminals, and they offer a unique solution in the LNG regasification industry – low cost, faster delivery, location flexibility and scale of operations – that fits the need of many countries. With the world moving towards the cleaner hydrocarbon, FSRU presents an attractive set of opportunities which makes the option lucrative, but the technological and commercial challenges are yet to completely overcome. A project developer must follow a structured investigation to understand how these risks and opportunities are applicable to the development in question, and ensure such developments are proposed based on objective rationale and mutual benefit of all the stakeholders.
  • 12. Page 12 of 13 References: [1] International Gas Union (June 2015). [2] Galway Regasification database and World LNG Factbook 2015. [3] http://www.gastechnews.com/lng/petrobras-starts-up-brazils-third-fsru-import-facility/ [4] http://gcaptain.com/golar-lng-fsru-igloo-kuwait/ Kuwait Petroleum Signs Charter Contract for Golar LNG’s Newbuild FSRU, ‘gCaptain’, 5 August 2013.