SlideShare a Scribd company logo
1 of 16
Liquidated Damages Contracts & Specifications| 1
Contracts & Specifications
Liquidated Damages Contracts & Specifications| 2
Contracts & Specifications
• Generally, LDs are an agreed upon sum of money to which the government
/ Owner will be entitled in the event the contractor fails to perform as
directed in the contract.
• Most large contracts contain this provision
• This provision explicitly states that for each calendar day the work remains
uncompleted after the final completion date stated in the contract, the
contractor shall pay a certain amount to the owner
• These specified payments are intended as reimbursement for owner’s
monetary loss due to delay
• They are called liquidated damages because they are stated as fixed rupee
amounts per day
What are Liquidated Damages ?
Liquidated Damages Contracts & Specifications| 3
Contracts & Specifications
• In many cases, the actual damages that owner will suffer in event of late
completion is difficult to determine
• The owner & Contractor agree on a fixed daily rupee amount that is
considered reasonable measure of the extent of damage in the event of
late completion
• In public sector and in much private work, determination of rupee
amount-unilaterally made by owner-bid advertisement on a “take-it-or-
leave-it” basis
Conceptual Basis Of Liquidated Damages
Liquidated Damages Contracts & Specifications| 4
Contracts & Specifications
In supply, service, research and development, and construction
contracts:
(1) The time of delivery or performance is such an important factor in the
award of the contract that the owner may reasonably expect to suffer
damage if the delivery or performance is delinquent.
(2) The extent or amount of such damage would be difficult or impossible to
ascertain or prove.
(3) The liquidated damages rate must be a reasonable forecast of just
compensation for the harm that is caused by late delivery or untimely
performance.
(4) Applicable LDs clause and rates should be identified in the solicitation.
Rates should include an amount for other expected expenses associated
with delayed completion. After award, LDs can be incorporated into the
contract as a supplemental agreement, though it would be difficult to have
a contractor to agree without objection.
When can they be used?
Liquidated Damages Contracts & Specifications| 5
Contracts & Specifications
1. FAILURE TO COMPLETE :
Failure to complete by a specified date is the most
common breach of contract for which LD clauses are used in the construction
industry. The damages are usually expressed in Standard Forms as an
amount per day or per week of delay to completion to be paid by the
Contractor to the Purchaser.
2. FAILURE TO PAY :
Failure to pay by a certain date is a breach of contract not
usually associated with liquidated damages clauses, but such a clause could
provide for payment of interest at an increased rate for the period of delay.
Types of Liquidated Damages Clauses
Liquidated Damages Contracts & Specifications| 6
Contracts & Specifications
3. FAILURE TO MEET PERFORMANCE CRITERIA :
Failure to provide a plant which gives
the required throughput is the breach of contract for which LD clauses are
used in contracts for industrial and/or mechanical plant. A measurable
performance target is required. It may be necessary to stipulate a minimum
level of performance required. If performance falls below this level the Plant
may be considered and agreed no longer to be a viable plant, the LD
provision no longer an adequate remedy and the contractor’s performance
not to be performance at all.
Types of Liquidated Damages Clauses
Liquidated Damages Contracts & Specifications| 7
Contracts & Specifications
Liquidated Damages:
It is a sum fixed or ascertained by the parties to the contract, which is a
fair and genuine per-estimate of the probable loss that might occur as a result of breach
of contract. Thus, liquidated damages are an assessment of loss which in the opinion of
the parties will occur due to breach. Such damages are effective and recoverable by the
aggrieved party from the other.
Penalty:
On the other hand, penalty is the sum mentioned in the contract at the time of its
formation which is disproportionate to the damages likely to occur as a result of the
breach of the contract. Penalty is fixed with a view to getting the contract performed, but
it has no concern with the probable loss likely to occur to the parties due to the breach
of the contract.
Difference Between LD & Penalty
Liquidated Damages Contracts & Specifications| 8
Contracts & Specifications
• Penalty is something which is used in a contract to secure the performance of the
contract whose main purpose is to ensure the payment of money which is specified to
terrorise the offending party.
• Also where the loss which has to be recovered is greater than the pre-estimated loss
then it amounts to penalty. Whereas liquidated damages are compensatory in nature
at the same time are pre-estimated damages. The purpose liquidated damages is to
promote certainty especially in commercial field.
• Liquidated damages are based on the genuine pre-estimate of the loss, whereas
penalty is based on the doctrine of reasonable compensation
• Hence, liquidated damages are easy to impose when compared with penalty.
Difference Between LD & Penalty
Liquidated Damages Contracts & Specifications| 9
Contracts & Specifications
• Unexcused failure of contractor to meet specified date is a breach of
contract
• If liquidated damages provision is not present and if contractor failed to
perform, owners recourse would be to withhold money or sue, prove the
extent of damages and obtain judgment compelling the contractor to pay
• Liquidated damages provision relieves the owner from above burden
• Their effect is to substitute a contract remedy for a common law breach
remedy
Liquidated damages provisions are a contract remedy
Liquidated Damages Contracts & Specifications| 10
Contracts & Specifications
• Both parties to contract must realize that liquidated damages are a
contractually specified remedy to make owner whole in event of late
completion
• Liquidated damages cannot be properly assessed as a penalty to punish
contractor for any displeasing act or, when not properly due, as pressure
to coerce the contractor into action favorable to owner
• In case of disputed liquidated damages assessments, courts will not
support purely punitive or coercive actions on owner’s part
Liquidated damages are not a penalty
Liquidated Damages Contracts & Specifications| 11
Contracts & Specifications
• Current Judicial attitude toward liquidated damages is to enforce such
provisions in event of unexcused delay
• Courts usually consider liquidated damages if daily amount stated in
contract is not reasonable
• Standard of reasonableness is based on whether daily amount is
reasonable estimate, in light of level of knowledge possessed by owner &
contractor when contract was signed
Judicial attitude towards liquidated damages provisions
Liquidated Damages Contracts & Specifications| 12
Contracts & Specifications
• Liquidated damages provisions can’t be applied in reverse if contractor
finishes early
• There need not be benefits from every day’s early completion because
owner may not have planned to occupy in the event of early delivery or
due to other reasons as well
• Occasionally bonus/penalty clause provides monetary benefit for early
completion
• Daily rate for early completion is usually less than the rate for late
completion
• Bonus/Penalty clauses - more commonly found in private sector contracts
Bonus/Penalty clauses
Liquidated Damages Contracts & Specifications| 13
Contracts & Specifications
(1) acts of God or of the public enemy,
(2) acts of the government in either its sovereign or contractual capacity, (Ex.
Untimely responses to contractor’s requests, improper inspections)
(3) fires,
(4) floods,
(5) epidemics,
(6) quarantine restrictions,
(7) strikes, (contractor must show it acted reasonably)
(8) freight embargoes, and
(9) unusually severe weather.
Excusable Delays
Liquidated Damages Contracts & Specifications| 14
Contracts & Specifications
A contractor must also demonstrate that:
(1) the event was beyond the contractor's control (including that it was not
foreseeable at the time of contract signing);
(2) the contractor could not have prevented the event;
(3) the contractor could not overcome the effects of the event;
(4) no contractor fault or negligence contributed to the event; and
(5) the event caused a delay to the overall completion of the contract.
Excusable Delays
Liquidated Damages Contracts & Specifications| 15
Contracts & Specifications
• Charles L. Knapp ,and Nathan M.Crystal 1987 ,Problems in Contract Law, Cases
and Materials ,Second Edition , professor of Law New York University & South
Carolina, p 967-971
• Lindsey, Susan 2005 , Business, international . 0003-8466 Architects' Journal.
EMAP Architecture.
• Brian M. Samuels , Construction Law.
• FIDIC,1999 , Condition of Contract for CONSTRUCTION.
• INTERNET WEBSITES.
• William G. Morris , an attorney , at 247 North Collier Boulevard on Marco
Island.
• Greenburg Traurig , January ,2008,Construction Law Litigation.
• CHARLES S PHELLIPS,P.E.,1999 ,Construction Contract Administration, Society
for Minning, Metallurgy, and Exploration, inc.(SME),p 63.
• Hinze, Jimmie, University of Florida, 2nd ED. P 214, 215
References
Liquidated Damages Contracts & Specifications| 16
Contracts & Specifications

More Related Content

What's hot

Construction contracts docuements_08092008
Construction contracts docuements_08092008Construction contracts docuements_08092008
Construction contracts docuements_08092008AYM1979
 
#Liquidated Damages vs Penalty# By SN Panigrahi,
#Liquidated Damages vs Penalty# By SN Panigrahi,#Liquidated Damages vs Penalty# By SN Panigrahi,
#Liquidated Damages vs Penalty# By SN Panigrahi,SN Panigrahi, PMP
 
Specifications, reports and tenders
Specifications, reports and tendersSpecifications, reports and tenders
Specifications, reports and tendersgayu pandian
 
Tenders and procedure of tendering
Tenders and procedure of tenderingTenders and procedure of tendering
Tenders and procedure of tenderingvvsasane
 
Conditions Of Contract
Conditions Of ContractConditions Of Contract
Conditions Of Contractguestdb5e498
 
Arbitration Of Construction Disputes
Arbitration Of Construction DisputesArbitration Of Construction Disputes
Arbitration Of Construction Disputeslouchang
 
civil engineering-Contracts
civil engineering-Contractscivil engineering-Contracts
civil engineering-ContractsNikhil Kumar
 
Tendering in construction introduction
Tendering in construction introductionTendering in construction introduction
Tendering in construction introductionDaniel Ross
 
Suspensions and Delays in Construction Contract
Suspensions and Delays in Construction ContractSuspensions and Delays in Construction Contract
Suspensions and Delays in Construction ContractAvinash Kumar Gupta
 
Estimating, administrative approval, technical sanction, budget provision
Estimating, administrative approval, technical sanction, budget provisionEstimating, administrative approval, technical sanction, budget provision
Estimating, administrative approval, technical sanction, budget provisionAshwiniChaudhari13
 
Procurement Methods and their Application.
Procurement Methods and their Application.Procurement Methods and their Application.
Procurement Methods and their Application.Lilian Nwachukwu
 
Contract Conditions
Contract ConditionsContract Conditions
Contract ConditionsDr K M SONI
 
Types of tender and their processing.
Types of tender and their processing.Types of tender and their processing.
Types of tender and their processing.Abhishek kumar maurya
 

What's hot (20)

Types of contracts
Types of contractsTypes of contracts
Types of contracts
 
Construction contracts docuements_08092008
Construction contracts docuements_08092008Construction contracts docuements_08092008
Construction contracts docuements_08092008
 
Liquadated damages
Liquadated damagesLiquadated damages
Liquadated damages
 
#Liquidated Damages vs Penalty# By SN Panigrahi,
#Liquidated Damages vs Penalty# By SN Panigrahi,#Liquidated Damages vs Penalty# By SN Panigrahi,
#Liquidated Damages vs Penalty# By SN Panigrahi,
 
Liquidated damages
Liquidated damagesLiquidated damages
Liquidated damages
 
Specifications, reports and tenders
Specifications, reports and tendersSpecifications, reports and tenders
Specifications, reports and tenders
 
Contracts and-tenders
Contracts and-tendersContracts and-tenders
Contracts and-tenders
 
Valuation
ValuationValuation
Valuation
 
Tenders and procedure of tendering
Tenders and procedure of tenderingTenders and procedure of tendering
Tenders and procedure of tendering
 
Earnest Money
Earnest MoneyEarnest Money
Earnest Money
 
Conditions Of Contract
Conditions Of ContractConditions Of Contract
Conditions Of Contract
 
Arbitration Of Construction Disputes
Arbitration Of Construction DisputesArbitration Of Construction Disputes
Arbitration Of Construction Disputes
 
civil engineering-Contracts
civil engineering-Contractscivil engineering-Contracts
civil engineering-Contracts
 
Tendering in construction introduction
Tendering in construction introductionTendering in construction introduction
Tendering in construction introduction
 
Unit 10. CONTRACT CLAUSES
Unit 10. CONTRACT CLAUSESUnit 10. CONTRACT CLAUSES
Unit 10. CONTRACT CLAUSES
 
Suspensions and Delays in Construction Contract
Suspensions and Delays in Construction ContractSuspensions and Delays in Construction Contract
Suspensions and Delays in Construction Contract
 
Estimating, administrative approval, technical sanction, budget provision
Estimating, administrative approval, technical sanction, budget provisionEstimating, administrative approval, technical sanction, budget provision
Estimating, administrative approval, technical sanction, budget provision
 
Procurement Methods and their Application.
Procurement Methods and their Application.Procurement Methods and their Application.
Procurement Methods and their Application.
 
Contract Conditions
Contract ConditionsContract Conditions
Contract Conditions
 
Types of tender and their processing.
Types of tender and their processing.Types of tender and their processing.
Types of tender and their processing.
 

Viewers also liked

Contract law - Remedies
Contract law - RemediesContract law - Remedies
Contract law - RemediesMaliza Eza
 
Commercial and Legal Aspects of Liquidated Damages and Penalties
Commercial and Legal Aspects of Liquidated Damages and PenaltiesCommercial and Legal Aspects of Liquidated Damages and Penalties
Commercial and Legal Aspects of Liquidated Damages and PenaltiesAMILA GAYAN
 
Build,Operate,Own,Transfer (BOOT)
Build,Operate,Own,Transfer (BOOT)Build,Operate,Own,Transfer (BOOT)
Build,Operate,Own,Transfer (BOOT)Mohd. Ikhwan
 
Private public partnership (ppp)
Private public partnership (ppp)Private public partnership (ppp)
Private public partnership (ppp)Môhãñ Raj
 
Law remedies for breach of contract
Law  remedies for breach of contractLaw  remedies for breach of contract
Law remedies for breach of contractAdil Shaikh
 
Public Private Partnerships
Public Private PartnershipsPublic Private Partnerships
Public Private Partnershipsjamesrobinsonjnr
 
Remedies Of Breach of contract(law)
Remedies Of Breach of contract(law)Remedies Of Breach of contract(law)
Remedies Of Breach of contract(law)Kavya Rawat
 

Viewers also liked (10)

BOOT 2
BOOT 2BOOT 2
BOOT 2
 
madhu
madhumadhu
madhu
 
Contract law - Remedies
Contract law - RemediesContract law - Remedies
Contract law - Remedies
 
INJUNCTION
INJUNCTIONINJUNCTION
INJUNCTION
 
Commercial and Legal Aspects of Liquidated Damages and Penalties
Commercial and Legal Aspects of Liquidated Damages and PenaltiesCommercial and Legal Aspects of Liquidated Damages and Penalties
Commercial and Legal Aspects of Liquidated Damages and Penalties
 
Build,Operate,Own,Transfer (BOOT)
Build,Operate,Own,Transfer (BOOT)Build,Operate,Own,Transfer (BOOT)
Build,Operate,Own,Transfer (BOOT)
 
Private public partnership (ppp)
Private public partnership (ppp)Private public partnership (ppp)
Private public partnership (ppp)
 
Law remedies for breach of contract
Law  remedies for breach of contractLaw  remedies for breach of contract
Law remedies for breach of contract
 
Public Private Partnerships
Public Private PartnershipsPublic Private Partnerships
Public Private Partnerships
 
Remedies Of Breach of contract(law)
Remedies Of Breach of contract(law)Remedies Of Breach of contract(law)
Remedies Of Breach of contract(law)
 

Similar to Liquidated damages contracts

RFP and Negotiation Best Practices.pdf
RFP and Negotiation Best Practices.pdfRFP and Negotiation Best Practices.pdf
RFP and Negotiation Best Practices.pdfTaralee Zimmerman
 
The Masquerade Of Low Bids_Phillips
The Masquerade Of Low Bids_PhillipsThe Masquerade Of Low Bids_Phillips
The Masquerade Of Low Bids_PhillipsContract Cities
 
Wind_Energy_Law_2014_Amanda James_Overcoming Wind Energy Project Financing Ob...
Wind_Energy_Law_2014_Amanda James_Overcoming Wind Energy Project Financing Ob...Wind_Energy_Law_2014_Amanda James_Overcoming Wind Energy Project Financing Ob...
Wind_Energy_Law_2014_Amanda James_Overcoming Wind Energy Project Financing Ob...Amanda James
 
Subcontract Clauses.PPTX
Subcontract Clauses.PPTXSubcontract Clauses.PPTX
Subcontract Clauses.PPTXRyan Hatton
 
Master supply agreements - les régimes de responsabilité contractuelle aux usa
Master supply agreements - les régimes de responsabilité contractuelle aux usaMaster supply agreements - les régimes de responsabilité contractuelle aux usa
Master supply agreements - les régimes de responsabilité contractuelle aux usaEliot Norman
 
Top 20 Standard Contract Clauses Every Manager Should Know
Top 20 Standard Contract Clauses Every Manager Should KnowTop 20 Standard Contract Clauses Every Manager Should Know
Top 20 Standard Contract Clauses Every Manager Should KnowSHAZEBALIKHAN1
 
Adm proyek kontrak konstruksi.ppt
Adm proyek kontrak konstruksi.pptAdm proyek kontrak konstruksi.ppt
Adm proyek kontrak konstruksi.pptAdibaBaves18
 
Construction claims, disputes and project closure
Construction claims, disputes and project closureConstruction claims, disputes and project closure
Construction claims, disputes and project closuresrinivas2036
 
RICS Dilapidations Consumer Guide
RICS Dilapidations Consumer GuideRICS Dilapidations Consumer Guide
RICS Dilapidations Consumer GuideRICS
 
Contract law & Project Mangers
Contract law & Project MangersContract law & Project Mangers
Contract law & Project MangersMaryam Sanaei- PMP
 
What Was the FASB Thinking?
What Was the FASB Thinking? What Was the FASB Thinking?
What Was the FASB Thinking? DecosimoCPAs
 
Claims & disputes management
Claims & disputes managementClaims & disputes management
Claims & disputes managementMohammed Tanbouz
 
The Practical Side of Bankruptcy
The Practical Side of BankruptcyThe Practical Side of Bankruptcy
The Practical Side of BankruptcyAnthony Kelley
 
Construction Law Presentation
Construction Law PresentationConstruction Law Presentation
Construction Law Presentationelliotfus
 
Identifying & Managing Risk In Supply Chain Agreements
Identifying & Managing Risk In Supply Chain AgreementsIdentifying & Managing Risk In Supply Chain Agreements
Identifying & Managing Risk In Supply Chain AgreementsQuarles & Brady
 
Olswang Construction Law Masterclass - October 2014 - Liqudated Damages and P...
Olswang Construction Law Masterclass - October 2014 - Liqudated Damages and P...Olswang Construction Law Masterclass - October 2014 - Liqudated Damages and P...
Olswang Construction Law Masterclass - October 2014 - Liqudated Damages and P...Francis Ho
 

Similar to Liquidated damages contracts (20)

RFP and Negotiation Best Practices.pdf
RFP and Negotiation Best Practices.pdfRFP and Negotiation Best Practices.pdf
RFP and Negotiation Best Practices.pdf
 
The Masquerade Of Low Bids_Phillips
The Masquerade Of Low Bids_PhillipsThe Masquerade Of Low Bids_Phillips
The Masquerade Of Low Bids_Phillips
 
Wind_Energy_Law_2014_Amanda James_Overcoming Wind Energy Project Financing Ob...
Wind_Energy_Law_2014_Amanda James_Overcoming Wind Energy Project Financing Ob...Wind_Energy_Law_2014_Amanda James_Overcoming Wind Energy Project Financing Ob...
Wind_Energy_Law_2014_Amanda James_Overcoming Wind Energy Project Financing Ob...
 
Subcontract Clauses.PPTX
Subcontract Clauses.PPTXSubcontract Clauses.PPTX
Subcontract Clauses.PPTX
 
Master supply agreements - les régimes de responsabilité contractuelle aux usa
Master supply agreements - les régimes de responsabilité contractuelle aux usaMaster supply agreements - les régimes de responsabilité contractuelle aux usa
Master supply agreements - les régimes de responsabilité contractuelle aux usa
 
LSH-GUIDE-TO-DILAPIDATIONS
LSH-GUIDE-TO-DILAPIDATIONSLSH-GUIDE-TO-DILAPIDATIONS
LSH-GUIDE-TO-DILAPIDATIONS
 
Prolongation and HOOH Costs
Prolongation and HOOH CostsProlongation and HOOH Costs
Prolongation and HOOH Costs
 
Nce603 mod unit4
Nce603 mod unit4Nce603 mod unit4
Nce603 mod unit4
 
Top 20 Standard Contract Clauses Every Manager Should Know
Top 20 Standard Contract Clauses Every Manager Should KnowTop 20 Standard Contract Clauses Every Manager Should Know
Top 20 Standard Contract Clauses Every Manager Should Know
 
Adm proyek kontrak konstruksi.ppt
Adm proyek kontrak konstruksi.pptAdm proyek kontrak konstruksi.ppt
Adm proyek kontrak konstruksi.ppt
 
Construction claims, disputes and project closure
Construction claims, disputes and project closureConstruction claims, disputes and project closure
Construction claims, disputes and project closure
 
RICS Dilapidations Consumer Guide
RICS Dilapidations Consumer GuideRICS Dilapidations Consumer Guide
RICS Dilapidations Consumer Guide
 
Contract law & Project Mangers
Contract law & Project MangersContract law & Project Mangers
Contract law & Project Mangers
 
What Was the FASB Thinking?
What Was the FASB Thinking? What Was the FASB Thinking?
What Was the FASB Thinking?
 
Claims & disputes management
Claims & disputes managementClaims & disputes management
Claims & disputes management
 
Focus on Retail
Focus on RetailFocus on Retail
Focus on Retail
 
The Practical Side of Bankruptcy
The Practical Side of BankruptcyThe Practical Side of Bankruptcy
The Practical Side of Bankruptcy
 
Construction Law Presentation
Construction Law PresentationConstruction Law Presentation
Construction Law Presentation
 
Identifying & Managing Risk In Supply Chain Agreements
Identifying & Managing Risk In Supply Chain AgreementsIdentifying & Managing Risk In Supply Chain Agreements
Identifying & Managing Risk In Supply Chain Agreements
 
Olswang Construction Law Masterclass - October 2014 - Liqudated Damages and P...
Olswang Construction Law Masterclass - October 2014 - Liqudated Damages and P...Olswang Construction Law Masterclass - October 2014 - Liqudated Damages and P...
Olswang Construction Law Masterclass - October 2014 - Liqudated Damages and P...
 

Recently uploaded

Solving Puzzles Benefits Everyone (English).pptx
Solving Puzzles Benefits Everyone (English).pptxSolving Puzzles Benefits Everyone (English).pptx
Solving Puzzles Benefits Everyone (English).pptxOH TEIK BIN
 
Presiding Officer Training module 2024 lok sabha elections
Presiding Officer Training module 2024 lok sabha electionsPresiding Officer Training module 2024 lok sabha elections
Presiding Officer Training module 2024 lok sabha electionsanshu789521
 
Separation of Lanthanides/ Lanthanides and Actinides
Separation of Lanthanides/ Lanthanides and ActinidesSeparation of Lanthanides/ Lanthanides and Actinides
Separation of Lanthanides/ Lanthanides and ActinidesFatimaKhan178732
 
Accessible design: Minimum effort, maximum impact
Accessible design: Minimum effort, maximum impactAccessible design: Minimum effort, maximum impact
Accessible design: Minimum effort, maximum impactdawncurless
 
APM Welcome, APM North West Network Conference, Synergies Across Sectors
APM Welcome, APM North West Network Conference, Synergies Across SectorsAPM Welcome, APM North West Network Conference, Synergies Across Sectors
APM Welcome, APM North West Network Conference, Synergies Across SectorsAssociation for Project Management
 
18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdf
18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdf18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdf
18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdfssuser54595a
 
The Most Excellent Way | 1 Corinthians 13
The Most Excellent Way | 1 Corinthians 13The Most Excellent Way | 1 Corinthians 13
The Most Excellent Way | 1 Corinthians 13Steve Thomason
 
Concept of Vouching. B.Com(Hons) /B.Compdf
Concept of Vouching. B.Com(Hons) /B.CompdfConcept of Vouching. B.Com(Hons) /B.Compdf
Concept of Vouching. B.Com(Hons) /B.CompdfUmakantAnnand
 
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptx
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptxPOINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptx
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptxSayali Powar
 
Incoming and Outgoing Shipments in 1 STEP Using Odoo 17
Incoming and Outgoing Shipments in 1 STEP Using Odoo 17Incoming and Outgoing Shipments in 1 STEP Using Odoo 17
Incoming and Outgoing Shipments in 1 STEP Using Odoo 17Celine George
 
Arihant handbook biology for class 11 .pdf
Arihant handbook biology for class 11 .pdfArihant handbook biology for class 11 .pdf
Arihant handbook biology for class 11 .pdfchloefrazer622
 
Industrial Policy - 1948, 1956, 1973, 1977, 1980, 1991
Industrial Policy - 1948, 1956, 1973, 1977, 1980, 1991Industrial Policy - 1948, 1956, 1973, 1977, 1980, 1991
Industrial Policy - 1948, 1956, 1973, 1977, 1980, 1991RKavithamani
 
Introduction to ArtificiaI Intelligence in Higher Education
Introduction to ArtificiaI Intelligence in Higher EducationIntroduction to ArtificiaI Intelligence in Higher Education
Introduction to ArtificiaI Intelligence in Higher Educationpboyjonauth
 
Call Girls in Dwarka Mor Delhi Contact Us 9654467111
Call Girls in Dwarka Mor Delhi Contact Us 9654467111Call Girls in Dwarka Mor Delhi Contact Us 9654467111
Call Girls in Dwarka Mor Delhi Contact Us 9654467111Sapana Sha
 
microwave assisted reaction. General introduction
microwave assisted reaction. General introductionmicrowave assisted reaction. General introduction
microwave assisted reaction. General introductionMaksud Ahmed
 
Software Engineering Methodologies (overview)
Software Engineering Methodologies (overview)Software Engineering Methodologies (overview)
Software Engineering Methodologies (overview)eniolaolutunde
 
Alper Gobel In Media Res Media Component
Alper Gobel In Media Res Media ComponentAlper Gobel In Media Res Media Component
Alper Gobel In Media Res Media ComponentInMediaRes1
 
Crayon Activity Handout For the Crayon A
Crayon Activity Handout For the Crayon ACrayon Activity Handout For the Crayon A
Crayon Activity Handout For the Crayon AUnboundStockton
 
Measures of Central Tendency: Mean, Median and Mode
Measures of Central Tendency: Mean, Median and ModeMeasures of Central Tendency: Mean, Median and Mode
Measures of Central Tendency: Mean, Median and ModeThiyagu K
 

Recently uploaded (20)

Solving Puzzles Benefits Everyone (English).pptx
Solving Puzzles Benefits Everyone (English).pptxSolving Puzzles Benefits Everyone (English).pptx
Solving Puzzles Benefits Everyone (English).pptx
 
Presiding Officer Training module 2024 lok sabha elections
Presiding Officer Training module 2024 lok sabha electionsPresiding Officer Training module 2024 lok sabha elections
Presiding Officer Training module 2024 lok sabha elections
 
Separation of Lanthanides/ Lanthanides and Actinides
Separation of Lanthanides/ Lanthanides and ActinidesSeparation of Lanthanides/ Lanthanides and Actinides
Separation of Lanthanides/ Lanthanides and Actinides
 
Accessible design: Minimum effort, maximum impact
Accessible design: Minimum effort, maximum impactAccessible design: Minimum effort, maximum impact
Accessible design: Minimum effort, maximum impact
 
APM Welcome, APM North West Network Conference, Synergies Across Sectors
APM Welcome, APM North West Network Conference, Synergies Across SectorsAPM Welcome, APM North West Network Conference, Synergies Across Sectors
APM Welcome, APM North West Network Conference, Synergies Across Sectors
 
18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdf
18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdf18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdf
18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdf
 
The Most Excellent Way | 1 Corinthians 13
The Most Excellent Way | 1 Corinthians 13The Most Excellent Way | 1 Corinthians 13
The Most Excellent Way | 1 Corinthians 13
 
Concept of Vouching. B.Com(Hons) /B.Compdf
Concept of Vouching. B.Com(Hons) /B.CompdfConcept of Vouching. B.Com(Hons) /B.Compdf
Concept of Vouching. B.Com(Hons) /B.Compdf
 
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptx
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptxPOINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptx
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptx
 
Incoming and Outgoing Shipments in 1 STEP Using Odoo 17
Incoming and Outgoing Shipments in 1 STEP Using Odoo 17Incoming and Outgoing Shipments in 1 STEP Using Odoo 17
Incoming and Outgoing Shipments in 1 STEP Using Odoo 17
 
Arihant handbook biology for class 11 .pdf
Arihant handbook biology for class 11 .pdfArihant handbook biology for class 11 .pdf
Arihant handbook biology for class 11 .pdf
 
Industrial Policy - 1948, 1956, 1973, 1977, 1980, 1991
Industrial Policy - 1948, 1956, 1973, 1977, 1980, 1991Industrial Policy - 1948, 1956, 1973, 1977, 1980, 1991
Industrial Policy - 1948, 1956, 1973, 1977, 1980, 1991
 
Model Call Girl in Bikash Puri Delhi reach out to us at 🔝9953056974🔝
Model Call Girl in Bikash Puri  Delhi reach out to us at 🔝9953056974🔝Model Call Girl in Bikash Puri  Delhi reach out to us at 🔝9953056974🔝
Model Call Girl in Bikash Puri Delhi reach out to us at 🔝9953056974🔝
 
Introduction to ArtificiaI Intelligence in Higher Education
Introduction to ArtificiaI Intelligence in Higher EducationIntroduction to ArtificiaI Intelligence in Higher Education
Introduction to ArtificiaI Intelligence in Higher Education
 
Call Girls in Dwarka Mor Delhi Contact Us 9654467111
Call Girls in Dwarka Mor Delhi Contact Us 9654467111Call Girls in Dwarka Mor Delhi Contact Us 9654467111
Call Girls in Dwarka Mor Delhi Contact Us 9654467111
 
microwave assisted reaction. General introduction
microwave assisted reaction. General introductionmicrowave assisted reaction. General introduction
microwave assisted reaction. General introduction
 
Software Engineering Methodologies (overview)
Software Engineering Methodologies (overview)Software Engineering Methodologies (overview)
Software Engineering Methodologies (overview)
 
Alper Gobel In Media Res Media Component
Alper Gobel In Media Res Media ComponentAlper Gobel In Media Res Media Component
Alper Gobel In Media Res Media Component
 
Crayon Activity Handout For the Crayon A
Crayon Activity Handout For the Crayon ACrayon Activity Handout For the Crayon A
Crayon Activity Handout For the Crayon A
 
Measures of Central Tendency: Mean, Median and Mode
Measures of Central Tendency: Mean, Median and ModeMeasures of Central Tendency: Mean, Median and Mode
Measures of Central Tendency: Mean, Median and Mode
 

Liquidated damages contracts

  • 1. Liquidated Damages Contracts & Specifications| 1 Contracts & Specifications
  • 2. Liquidated Damages Contracts & Specifications| 2 Contracts & Specifications • Generally, LDs are an agreed upon sum of money to which the government / Owner will be entitled in the event the contractor fails to perform as directed in the contract. • Most large contracts contain this provision • This provision explicitly states that for each calendar day the work remains uncompleted after the final completion date stated in the contract, the contractor shall pay a certain amount to the owner • These specified payments are intended as reimbursement for owner’s monetary loss due to delay • They are called liquidated damages because they are stated as fixed rupee amounts per day What are Liquidated Damages ?
  • 3. Liquidated Damages Contracts & Specifications| 3 Contracts & Specifications • In many cases, the actual damages that owner will suffer in event of late completion is difficult to determine • The owner & Contractor agree on a fixed daily rupee amount that is considered reasonable measure of the extent of damage in the event of late completion • In public sector and in much private work, determination of rupee amount-unilaterally made by owner-bid advertisement on a “take-it-or- leave-it” basis Conceptual Basis Of Liquidated Damages
  • 4. Liquidated Damages Contracts & Specifications| 4 Contracts & Specifications In supply, service, research and development, and construction contracts: (1) The time of delivery or performance is such an important factor in the award of the contract that the owner may reasonably expect to suffer damage if the delivery or performance is delinquent. (2) The extent or amount of such damage would be difficult or impossible to ascertain or prove. (3) The liquidated damages rate must be a reasonable forecast of just compensation for the harm that is caused by late delivery or untimely performance. (4) Applicable LDs clause and rates should be identified in the solicitation. Rates should include an amount for other expected expenses associated with delayed completion. After award, LDs can be incorporated into the contract as a supplemental agreement, though it would be difficult to have a contractor to agree without objection. When can they be used?
  • 5. Liquidated Damages Contracts & Specifications| 5 Contracts & Specifications 1. FAILURE TO COMPLETE : Failure to complete by a specified date is the most common breach of contract for which LD clauses are used in the construction industry. The damages are usually expressed in Standard Forms as an amount per day or per week of delay to completion to be paid by the Contractor to the Purchaser. 2. FAILURE TO PAY : Failure to pay by a certain date is a breach of contract not usually associated with liquidated damages clauses, but such a clause could provide for payment of interest at an increased rate for the period of delay. Types of Liquidated Damages Clauses
  • 6. Liquidated Damages Contracts & Specifications| 6 Contracts & Specifications 3. FAILURE TO MEET PERFORMANCE CRITERIA : Failure to provide a plant which gives the required throughput is the breach of contract for which LD clauses are used in contracts for industrial and/or mechanical plant. A measurable performance target is required. It may be necessary to stipulate a minimum level of performance required. If performance falls below this level the Plant may be considered and agreed no longer to be a viable plant, the LD provision no longer an adequate remedy and the contractor’s performance not to be performance at all. Types of Liquidated Damages Clauses
  • 7. Liquidated Damages Contracts & Specifications| 7 Contracts & Specifications Liquidated Damages: It is a sum fixed or ascertained by the parties to the contract, which is a fair and genuine per-estimate of the probable loss that might occur as a result of breach of contract. Thus, liquidated damages are an assessment of loss which in the opinion of the parties will occur due to breach. Such damages are effective and recoverable by the aggrieved party from the other. Penalty: On the other hand, penalty is the sum mentioned in the contract at the time of its formation which is disproportionate to the damages likely to occur as a result of the breach of the contract. Penalty is fixed with a view to getting the contract performed, but it has no concern with the probable loss likely to occur to the parties due to the breach of the contract. Difference Between LD & Penalty
  • 8. Liquidated Damages Contracts & Specifications| 8 Contracts & Specifications • Penalty is something which is used in a contract to secure the performance of the contract whose main purpose is to ensure the payment of money which is specified to terrorise the offending party. • Also where the loss which has to be recovered is greater than the pre-estimated loss then it amounts to penalty. Whereas liquidated damages are compensatory in nature at the same time are pre-estimated damages. The purpose liquidated damages is to promote certainty especially in commercial field. • Liquidated damages are based on the genuine pre-estimate of the loss, whereas penalty is based on the doctrine of reasonable compensation • Hence, liquidated damages are easy to impose when compared with penalty. Difference Between LD & Penalty
  • 9. Liquidated Damages Contracts & Specifications| 9 Contracts & Specifications • Unexcused failure of contractor to meet specified date is a breach of contract • If liquidated damages provision is not present and if contractor failed to perform, owners recourse would be to withhold money or sue, prove the extent of damages and obtain judgment compelling the contractor to pay • Liquidated damages provision relieves the owner from above burden • Their effect is to substitute a contract remedy for a common law breach remedy Liquidated damages provisions are a contract remedy
  • 10. Liquidated Damages Contracts & Specifications| 10 Contracts & Specifications • Both parties to contract must realize that liquidated damages are a contractually specified remedy to make owner whole in event of late completion • Liquidated damages cannot be properly assessed as a penalty to punish contractor for any displeasing act or, when not properly due, as pressure to coerce the contractor into action favorable to owner • In case of disputed liquidated damages assessments, courts will not support purely punitive or coercive actions on owner’s part Liquidated damages are not a penalty
  • 11. Liquidated Damages Contracts & Specifications| 11 Contracts & Specifications • Current Judicial attitude toward liquidated damages is to enforce such provisions in event of unexcused delay • Courts usually consider liquidated damages if daily amount stated in contract is not reasonable • Standard of reasonableness is based on whether daily amount is reasonable estimate, in light of level of knowledge possessed by owner & contractor when contract was signed Judicial attitude towards liquidated damages provisions
  • 12. Liquidated Damages Contracts & Specifications| 12 Contracts & Specifications • Liquidated damages provisions can’t be applied in reverse if contractor finishes early • There need not be benefits from every day’s early completion because owner may not have planned to occupy in the event of early delivery or due to other reasons as well • Occasionally bonus/penalty clause provides monetary benefit for early completion • Daily rate for early completion is usually less than the rate for late completion • Bonus/Penalty clauses - more commonly found in private sector contracts Bonus/Penalty clauses
  • 13. Liquidated Damages Contracts & Specifications| 13 Contracts & Specifications (1) acts of God or of the public enemy, (2) acts of the government in either its sovereign or contractual capacity, (Ex. Untimely responses to contractor’s requests, improper inspections) (3) fires, (4) floods, (5) epidemics, (6) quarantine restrictions, (7) strikes, (contractor must show it acted reasonably) (8) freight embargoes, and (9) unusually severe weather. Excusable Delays
  • 14. Liquidated Damages Contracts & Specifications| 14 Contracts & Specifications A contractor must also demonstrate that: (1) the event was beyond the contractor's control (including that it was not foreseeable at the time of contract signing); (2) the contractor could not have prevented the event; (3) the contractor could not overcome the effects of the event; (4) no contractor fault or negligence contributed to the event; and (5) the event caused a delay to the overall completion of the contract. Excusable Delays
  • 15. Liquidated Damages Contracts & Specifications| 15 Contracts & Specifications • Charles L. Knapp ,and Nathan M.Crystal 1987 ,Problems in Contract Law, Cases and Materials ,Second Edition , professor of Law New York University & South Carolina, p 967-971 • Lindsey, Susan 2005 , Business, international . 0003-8466 Architects' Journal. EMAP Architecture. • Brian M. Samuels , Construction Law. • FIDIC,1999 , Condition of Contract for CONSTRUCTION. • INTERNET WEBSITES. • William G. Morris , an attorney , at 247 North Collier Boulevard on Marco Island. • Greenburg Traurig , January ,2008,Construction Law Litigation. • CHARLES S PHELLIPS,P.E.,1999 ,Construction Contract Administration, Society for Minning, Metallurgy, and Exploration, inc.(SME),p 63. • Hinze, Jimmie, University of Florida, 2nd ED. P 214, 215 References
  • 16. Liquidated Damages Contracts & Specifications| 16 Contracts & Specifications