2. Liquidated Damages Contracts & Specifications| 2
Contracts & Specifications
• Generally, LDs are an agreed upon sum of money to which the government
/ Owner will be entitled in the event the contractor fails to perform as
directed in the contract.
• Most large contracts contain this provision
• This provision explicitly states that for each calendar day the work remains
uncompleted after the final completion date stated in the contract, the
contractor shall pay a certain amount to the owner
• These specified payments are intended as reimbursement for owner’s
monetary loss due to delay
• They are called liquidated damages because they are stated as fixed rupee
amounts per day
What are Liquidated Damages ?
3. Liquidated Damages Contracts & Specifications| 3
Contracts & Specifications
• In many cases, the actual damages that owner will suffer in event of late
completion is difficult to determine
• The owner & Contractor agree on a fixed daily rupee amount that is
considered reasonable measure of the extent of damage in the event of
late completion
• In public sector and in much private work, determination of rupee
amount-unilaterally made by owner-bid advertisement on a “take-it-or-
leave-it” basis
Conceptual Basis Of Liquidated Damages
4. Liquidated Damages Contracts & Specifications| 4
Contracts & Specifications
In supply, service, research and development, and construction
contracts:
(1) The time of delivery or performance is such an important factor in the
award of the contract that the owner may reasonably expect to suffer
damage if the delivery or performance is delinquent.
(2) The extent or amount of such damage would be difficult or impossible to
ascertain or prove.
(3) The liquidated damages rate must be a reasonable forecast of just
compensation for the harm that is caused by late delivery or untimely
performance.
(4) Applicable LDs clause and rates should be identified in the solicitation.
Rates should include an amount for other expected expenses associated
with delayed completion. After award, LDs can be incorporated into the
contract as a supplemental agreement, though it would be difficult to have
a contractor to agree without objection.
When can they be used?
5. Liquidated Damages Contracts & Specifications| 5
Contracts & Specifications
1. FAILURE TO COMPLETE :
Failure to complete by a specified date is the most
common breach of contract for which LD clauses are used in the construction
industry. The damages are usually expressed in Standard Forms as an
amount per day or per week of delay to completion to be paid by the
Contractor to the Purchaser.
2. FAILURE TO PAY :
Failure to pay by a certain date is a breach of contract not
usually associated with liquidated damages clauses, but such a clause could
provide for payment of interest at an increased rate for the period of delay.
Types of Liquidated Damages Clauses
6. Liquidated Damages Contracts & Specifications| 6
Contracts & Specifications
3. FAILURE TO MEET PERFORMANCE CRITERIA :
Failure to provide a plant which gives
the required throughput is the breach of contract for which LD clauses are
used in contracts for industrial and/or mechanical plant. A measurable
performance target is required. It may be necessary to stipulate a minimum
level of performance required. If performance falls below this level the Plant
may be considered and agreed no longer to be a viable plant, the LD
provision no longer an adequate remedy and the contractor’s performance
not to be performance at all.
Types of Liquidated Damages Clauses
7. Liquidated Damages Contracts & Specifications| 7
Contracts & Specifications
Liquidated Damages:
It is a sum fixed or ascertained by the parties to the contract, which is a
fair and genuine per-estimate of the probable loss that might occur as a result of breach
of contract. Thus, liquidated damages are an assessment of loss which in the opinion of
the parties will occur due to breach. Such damages are effective and recoverable by the
aggrieved party from the other.
Penalty:
On the other hand, penalty is the sum mentioned in the contract at the time of its
formation which is disproportionate to the damages likely to occur as a result of the
breach of the contract. Penalty is fixed with a view to getting the contract performed, but
it has no concern with the probable loss likely to occur to the parties due to the breach
of the contract.
Difference Between LD & Penalty
8. Liquidated Damages Contracts & Specifications| 8
Contracts & Specifications
• Penalty is something which is used in a contract to secure the performance of the
contract whose main purpose is to ensure the payment of money which is specified to
terrorise the offending party.
• Also where the loss which has to be recovered is greater than the pre-estimated loss
then it amounts to penalty. Whereas liquidated damages are compensatory in nature
at the same time are pre-estimated damages. The purpose liquidated damages is to
promote certainty especially in commercial field.
• Liquidated damages are based on the genuine pre-estimate of the loss, whereas
penalty is based on the doctrine of reasonable compensation
• Hence, liquidated damages are easy to impose when compared with penalty.
Difference Between LD & Penalty
9. Liquidated Damages Contracts & Specifications| 9
Contracts & Specifications
• Unexcused failure of contractor to meet specified date is a breach of
contract
• If liquidated damages provision is not present and if contractor failed to
perform, owners recourse would be to withhold money or sue, prove the
extent of damages and obtain judgment compelling the contractor to pay
• Liquidated damages provision relieves the owner from above burden
• Their effect is to substitute a contract remedy for a common law breach
remedy
Liquidated damages provisions are a contract remedy
10. Liquidated Damages Contracts & Specifications| 10
Contracts & Specifications
• Both parties to contract must realize that liquidated damages are a
contractually specified remedy to make owner whole in event of late
completion
• Liquidated damages cannot be properly assessed as a penalty to punish
contractor for any displeasing act or, when not properly due, as pressure
to coerce the contractor into action favorable to owner
• In case of disputed liquidated damages assessments, courts will not
support purely punitive or coercive actions on owner’s part
Liquidated damages are not a penalty
11. Liquidated Damages Contracts & Specifications| 11
Contracts & Specifications
• Current Judicial attitude toward liquidated damages is to enforce such
provisions in event of unexcused delay
• Courts usually consider liquidated damages if daily amount stated in
contract is not reasonable
• Standard of reasonableness is based on whether daily amount is
reasonable estimate, in light of level of knowledge possessed by owner &
contractor when contract was signed
Judicial attitude towards liquidated damages provisions
12. Liquidated Damages Contracts & Specifications| 12
Contracts & Specifications
• Liquidated damages provisions can’t be applied in reverse if contractor
finishes early
• There need not be benefits from every day’s early completion because
owner may not have planned to occupy in the event of early delivery or
due to other reasons as well
• Occasionally bonus/penalty clause provides monetary benefit for early
completion
• Daily rate for early completion is usually less than the rate for late
completion
• Bonus/Penalty clauses - more commonly found in private sector contracts
Bonus/Penalty clauses
13. Liquidated Damages Contracts & Specifications| 13
Contracts & Specifications
(1) acts of God or of the public enemy,
(2) acts of the government in either its sovereign or contractual capacity, (Ex.
Untimely responses to contractor’s requests, improper inspections)
(3) fires,
(4) floods,
(5) epidemics,
(6) quarantine restrictions,
(7) strikes, (contractor must show it acted reasonably)
(8) freight embargoes, and
(9) unusually severe weather.
Excusable Delays
14. Liquidated Damages Contracts & Specifications| 14
Contracts & Specifications
A contractor must also demonstrate that:
(1) the event was beyond the contractor's control (including that it was not
foreseeable at the time of contract signing);
(2) the contractor could not have prevented the event;
(3) the contractor could not overcome the effects of the event;
(4) no contractor fault or negligence contributed to the event; and
(5) the event caused a delay to the overall completion of the contract.
Excusable Delays
15. Liquidated Damages Contracts & Specifications| 15
Contracts & Specifications
• Charles L. Knapp ,and Nathan M.Crystal 1987 ,Problems in Contract Law, Cases
and Materials ,Second Edition , professor of Law New York University & South
Carolina, p 967-971
• Lindsey, Susan 2005 , Business, international . 0003-8466 Architects' Journal.
EMAP Architecture.
• Brian M. Samuels , Construction Law.
• FIDIC,1999 , Condition of Contract for CONSTRUCTION.
• INTERNET WEBSITES.
• William G. Morris , an attorney , at 247 North Collier Boulevard on Marco
Island.
• Greenburg Traurig , January ,2008,Construction Law Litigation.
• CHARLES S PHELLIPS,P.E.,1999 ,Construction Contract Administration, Society
for Minning, Metallurgy, and Exploration, inc.(SME),p 63.
• Hinze, Jimmie, University of Florida, 2nd ED. P 214, 215
References