SlideShare a Scribd company logo
Presentation on
Land Acquisition
Act
• Land acquisition is the process by which
the government acquires private property
for public purpose.
• Till 2013, land acquisition in India was
governed by Land Acquisition Act of 1894 .
LAND ACQUISITION ACT
1894
• Under the 1894 Act, the government could
acquire any land as it wishes to, in the name
of "public purpose“. The term “public
purpose” was ambiguous and open to
executive-discretion. So, poor peoples’ land
was acquired at throwaway prices in pretext
of development projects.
• Sometimes such projects never started, and the
same cheap land was resold at higher price to
real estate developers, without building
anything for “public purpose”.
• Urgency clause: This is the most criticized section of
the Law. The clause never truly defines what
constitutes an urgent need and leaves it to the
discretion of the acquiring authority.
• No safeguards: There is no real appeal mechanism to
stop the process of the acquisition. A hearing (under
section 5A) is prescribed but this is not a discussion or
negotiation. The views expressed are not required to be
taken on board by the officer conducting the hearing.
• Silent on resettlement and rehabilitation of those
displaced: There are absolutely no provisions in the
1894 law relating to the resettlement and rehabilitation of
those displaced by the acquisition.
• Low rates of compensation: The rates paid for
the land acquired are the prevailing circle rates in
the area which are notorious for being outdated
and hence not even remotely indicative of the
actual rates prevailing in the area.
• Litigation: Even where acquisition has been carried
out the same has been challenged in litigations on
the grounds mentioned above. This results in the
stalling of legitimate infrastructure projects.
LAND ACQUISITION,
REHABILITATION AND
RESETTLEMENT ACT,2013
• The Right to Fair Compensation and Transparency in Land
Acquisition, Rehabilitation and Resettlement Act, 2013, which
came into force from 1 January 2014.
• The title of the old law conveyed that its primary purpose
was to expedite the acquisition of land. However, the
principle objective of the new Bill is fair compensation,
thorough resettlement and rehabilitation of those affected,
adequate safeguards for their well-being and complete
transparency in the process of land acquisition. The title
has been amended to reflect this.
• Retrospective operation: To address historical injustice
it applies retrospectively to cases where no land
acquisition award has been made. Also in cases where
the land was acquired five years ago but no compensation
has been paid land acquisition process will be started
afresh
Social Impact Assessment
Consent of Families (70-80%)
>Market rate Price (2x-4x)
Additional Relief to SC/ST
Restriction on Fertile Land
Dispute Settlement Mechanism
Accountability of HOD
1. COMPENSATION : COMPENSATION IN RURAL AREAS WOULD BE CALCULATED
BY
MULTIPLYING MARKET VALUE BY TWO AND ADDING ASSETS ATTACHED TO THE
LAND OR
BUILDING AND ADDING A SOLATIUM. IN URBAN AREAS IT WOULD BE MARKET
VALUE
PLUS ASSETS ATTACHED TO THE LAND AND SOLATIUM.
ILLUSTRATION
Suppose the market value of a piece of land in rural area is 10,00,000.
Multiplying it by 2 ----- 10,00,000 x 2 = 20,00,000
Adding value of assets (2,00,000) attached to land ------ = 22,00,000
Adding 100% solatium, the final compensation = 44,00,000
A piece of land of market value 10,00,000 in urban area ----- Adding
value of asset (2,00,000) attached to land ------ = 12,00,000 Adding 100%
solatium , the final compensation = 24,00,000
• Compensation for livelihood losers: In addition to those
losing land, the Bill provides compensation to those who
are dependent on the land being acquired for their
livelihood. To qualify for benefits under this Act the time
period has been reduced to three years of dependence (on
the acquired land) from five
• Fishing rights: In the case of irrigation or hydel projects,
affected families may be allowed fishing rights in the
reservoirs.
• Share in appreciated land value: Where the acquired land
is sold to a third party for a higher price, 40% of the
appreciated land value (or profit) will be shared with the
original owners.
•CONSENT: Consent of up to 80 per cent of people
required for private projects. For PPP projects, the
approval of 70 per cent of the same is mandatory
•Multi-cropped, irrigated land cannot be acquired unless it
is for defence or emergency caused by natural calamity
•Land should be returned to original owner or the State
Land Bank if not used in five years for the purpose for
which it is acquired
• The government will not acquire land for private
companies for private purpose
• Exemption from income tax and stamp duty: No
income tax shall be levied and no stamp duty shall be
charged on any amount that accrues to an individual as a
result of the provisions of the new law.
• The Bill also proposes amenities like schools, health
centres and civic infrastructure in places where project-
affected people are resettled
The urgency clause should be exercised in the rarest of
rare cases like national defense or for resettlement
purposes.
The Social Impact Assessment (SIA) has to be carried out in
consultation with the representatives of the Panchayati Raj
Institutions (PRIs) Reports prepared under the Social Impact
Assessment are to be shared with these representatives
1.INVESTIGATION PROCESS
• When a local authority or a company requires a land, an
application is required to be made by it to the revenue
authority,accompanied with a copy of the plan showing
survey nos., purpose of acquisition and the reason for the
particular site to be chosen and the provision made for the
cost of the acquisition.
• After the government has been fully satisfied about the
purpose, the least area needed, and other relevant facts
as provided under land acquisition rules, it will issue a
notification under Section 4 of the act that the particular
land is required for public purpose.
PROCEDURE FOR THE LAND ACQUISITION
2. OBJECTION AND CONFIRMATION
• Objections are invited from all persons interested in
land within thirty days from the date of
notification.
• The objections will be valid on one or more of the
following grounds:
i. That the purpose for which the land is proposed
for acquisition is not a public purpose.
ii. That the land is not or less suitable than another
piece of land for the said purpose.
iii. That the area under acquisition is excessive.
iv. That the acquisition will destroy or impair
historical or artistic monuments or will
desecrate religious buildings, graveyards and
the like.
3. Claim and Award
•The collector will issue notices under Section 9 to all
persons interested in the acquisition
to file their claim reports.
•In determining the compensation the market value of
the land is determined at the date of notification. The
rise and fall in the value during the period of
transaction and notification is taken into consideration.
• Compensation is also payable when:
i. Part of the property is proposed for acquisition in
such a manner that the remainder depreciates in
value.
ii. When the land notified for acquisition has standing
crops or trees.
• Compensation is also payable when:
i. Part of the property is proposed for acquisition in such a manner
that the remainder depreciates in value.
ii. When the land notified for acquisition has standing crops or
trees.
iii. If the person interested has to change his place of residence or
business then the excess rent payable for the new premises is
also considered for compensation
• After necessary inquiries the collector declares his award showing
true area of the land, total amount of compensation payable and
apportionment of compensation if there are more than one owners
or claimants.
4. Reference to Court
• Any person interested to whom the award is not satisfactory can
submit a written application to the court.
• This application should be made within six weeks from the date
of declaration of the award.
The new government passed an
ordinance on Land Acquisition on
29th December 2014 introducing
major changes to the 2013 Act.
Land Acquisition Bill
• LARR Act-2013 established an extremely complex andimpractical
land acquisition process.
• Holdouts: Jholachhap NGOs would instigate 20-25% of the affected
families to stage holdout- promising them it’ll fetch them even
higher prices. and Given the 70-80% consent requirement, the
project will never kickoff.
• Litigation: because local (and therefore corruption) Patwari and
Tehsildars never maintain proper land records of who owns how
much land.
•This raised the land prices, red tapism and thus the overall project
cost.
• Neither the farmer could sell its land and move to urban areas, nor
the entrepreneur could buy the land and move towards rural areas.
The existing Act kept 13 most frequently used acts for Land
Acquisition for Central Government Projects out of the purview.
These acts are applicable for national highways, metro rail,
atomic energy projects, electricity related projects, etc. The
present amendments bring all those exempted from the 13 acts
under the purview of this Act for the purpose of compensation,
rehabilitation and resettlement. Therefore, the amendment
benefits farmers and affected families.
The proposed changes in the Land Acquisition Act would
allow a fast track process for defence and defence
production, rural infrastructure including electrification,
affordable housing, industrial corridors and infrastructure
projects including projects taken up under Public Private
Partnership mode where ownership of the land continues
to be vested with the government. As per the changes
brought in the Ordinance, multi-crop irrigated land can
also be acquired for purposes like national security,
defence, rural infrastructure including electrification,
industrial corridors and building social infrastructure.
CONS
The original Land Acquisition Act, 2013 had a
consent clause for acquiring land – industrial
corridors, Public Private Partnership projects, rural
infrastructure, affordable housing and defence. But
after the central government changed, it exempted
these five categories from the rule of acquitting
land in the Bill tabled on February 24.
Social assessment which was mandatory before
acquitting land has also been exempted in the Bill
tabled in the Lok Sabha.
As per the existing law, land will be given back to the
farmer if it remains unused for five years. The proposed
amendment says the land will be returned only if the
specified project on the land fails to complete the
deadline.
Also whether the land is fertile or not will also not be
taken into consideration while acquiring it for these five
specific sectors.
• Anti-corruption crusader Anna Hazare launched a two-day token
agitation against the new land acquisition act on February 23 and
24. His agitation has received support from thousands of activists
and farmers
• Hazare pressed for repeal of the ordinance issued by the
union government on 29 December 2014
• In a post on his blog, Hazare has criticised this amendment as anti-
farmer and pro-corporate
• He opposed the various clauses in the ordinance like removal of
SIA,Consent Requirement,multi crop land provision,Return of Land
to Farmers if unused.
Comparison between 1984
Law , 2013 Act and 2014
Ordinance
 In an attempt to placate the opposition and
some unhappy allies, government brought
nine official amendments and added two
clauses to the controversial legislation.
 The amendments have been passed in the
Lok Sabha setting the stage for its
consideration in Rajya Sabha where the
numbers are loaded against the
government.
 The social impact asssessment of land to be acquired will be the
prerogativeofthestate governments
 The amendments include dropping of exemption to "social
infrastructure" projects as there were fears that private individuals
may use this clause to open colleges and hospitals which are actually
businessmodels
 Multi-croplandswillnotbeacquired
 Land will be returned to the farmer if the project is not completed,
but the time consumed by court cases and injunctions will not be
counted.
Themostimportantclause-theConsentClause hasnotbeendealtwithyet
, this being the major reason for the widespread opposition against the
ordinance
 Government has decided to prorogue the Rajya Sabha and
repromulgate the Land Ordinance in the next session, as the
existing ordinance lapses on April 5 with the end of the Rajya
SabhaSession.
 Sources said that the government will its best to bring the
land bill in Rajya Sabha to replace the ordinance in the
second half of the Budget session after it reconvenes on
April20
 It may agree to reintroduce the provision of taking farmers'
consent for acquiring land. The earlier 80 percent consent
requirementcanbe reduced to51percent.
 Similarly, instead of the earlier social impact assessment (SIA), the
government may involve expert groups to examine the land deals
to find out whether excess landhas beenacquiredfora projectand
whether ithas affectedthe original inhabitants.
THANK YOU

More Related Content

What's hot

Land law 1 alienation 2014
Land law 1 alienation 2014Land law 1 alienation 2014
Land law 1 alienation 2014
xareejx
 
Eviction under tamilnadu rent control act
Eviction under tamilnadu rent control actEviction under tamilnadu rent control act
Eviction under tamilnadu rent control act
Altacit Global
 
Contrato Locacao Imovel De Temporada
Contrato Locacao Imovel De TemporadaContrato Locacao Imovel De Temporada
Contrato Locacao Imovel De Temporada
Rodolfo Rodrigo Acosta
 
Contrato de arrendamento para comercio
Contrato de arrendamento para comercioContrato de arrendamento para comercio
Contrato de arrendamento para comercio
qazmlo
 
The law on maintenance for children (equal responsibilities)
The law on maintenance for children (equal responsibilities)The law on maintenance for children (equal responsibilities)
The law on maintenance for children (equal responsibilities)
NurulHayyu1
 
Alienation of Land
Alienation of LandAlienation of Land
Alienation of Land
FAROUQ
 
Section 106 notice
Section 106 noticeSection 106 notice
Section 106 notice
Chenoy Ceil
 
LAND LAW 1 INDEFEASIBILITY 2014
LAND LAW 1 INDEFEASIBILITY 2014LAND LAW 1 INDEFEASIBILITY 2014
LAND LAW 1 INDEFEASIBILITY 2014
xareejx
 
Undang undang Tanah - Lesen Pendudukan Sementara atau Temporary Occupational ...
Undang undang Tanah - Lesen Pendudukan Sementara atau Temporary Occupational ...Undang undang Tanah - Lesen Pendudukan Sementara atau Temporary Occupational ...
Undang undang Tanah - Lesen Pendudukan Sementara atau Temporary Occupational ...
surrenderyourthrone
 
Difference between lease and license: Everything you need to know
Difference between lease and license: Everything you need to knowDifference between lease and license: Everything you need to know
Difference between lease and license: Everything you need to know
MyAdvo.in
 
Land law 1 alienation 2014
Land law 1 alienation 2014Land law 1 alienation 2014
Land law 1 alienation 2014
xareejx
 
National land code 1965
National land code 1965National land code 1965
National land code 1965
Hafizul Mukhlis
 
Undang undang tanah - lesen pendudukan sementara atau temporary occupational ...
Undang undang tanah - lesen pendudukan sementara atau temporary occupational ...Undang undang tanah - lesen pendudukan sementara atau temporary occupational ...
Undang undang tanah - lesen pendudukan sementara atau temporary occupational ...
surrenderyourthrone
 
Removal of rock material
Removal of rock materialRemoval of rock material
Removal of rock material
FAROUQ
 
Real Estate (Development & Regulation) Act, 2016
Real Estate (Development & Regulation) Act, 2016Real Estate (Development & Regulation) Act, 2016
Real Estate (Development & Regulation) Act, 2016
Dr. Kalpeshkumar L Gupta
 
3) lien holder caveat
3) lien holder caveat3) lien holder caveat
3) lien holder caveat
ilyana iskandar
 
Land Law 1 DEFINITION OF LAND
Land Law 1 DEFINITION OF LANDLand Law 1 DEFINITION OF LAND
Land Law 1 DEFINITION OF LAND
xareejx
 
Strata titles
Strata titlesStrata titles
Strata titles
Hafizul Mukhlis
 
restraint on dealings
restraint on dealingsrestraint on dealings
restraint on dealings
Hafizul Mukhlis
 
land-notes-all.pdf
land-notes-all.pdfland-notes-all.pdf
land-notes-all.pdf
Gobikrishna Krishnan
 

What's hot (20)

Land law 1 alienation 2014
Land law 1 alienation 2014Land law 1 alienation 2014
Land law 1 alienation 2014
 
Eviction under tamilnadu rent control act
Eviction under tamilnadu rent control actEviction under tamilnadu rent control act
Eviction under tamilnadu rent control act
 
Contrato Locacao Imovel De Temporada
Contrato Locacao Imovel De TemporadaContrato Locacao Imovel De Temporada
Contrato Locacao Imovel De Temporada
 
Contrato de arrendamento para comercio
Contrato de arrendamento para comercioContrato de arrendamento para comercio
Contrato de arrendamento para comercio
 
The law on maintenance for children (equal responsibilities)
The law on maintenance for children (equal responsibilities)The law on maintenance for children (equal responsibilities)
The law on maintenance for children (equal responsibilities)
 
Alienation of Land
Alienation of LandAlienation of Land
Alienation of Land
 
Section 106 notice
Section 106 noticeSection 106 notice
Section 106 notice
 
LAND LAW 1 INDEFEASIBILITY 2014
LAND LAW 1 INDEFEASIBILITY 2014LAND LAW 1 INDEFEASIBILITY 2014
LAND LAW 1 INDEFEASIBILITY 2014
 
Undang undang Tanah - Lesen Pendudukan Sementara atau Temporary Occupational ...
Undang undang Tanah - Lesen Pendudukan Sementara atau Temporary Occupational ...Undang undang Tanah - Lesen Pendudukan Sementara atau Temporary Occupational ...
Undang undang Tanah - Lesen Pendudukan Sementara atau Temporary Occupational ...
 
Difference between lease and license: Everything you need to know
Difference between lease and license: Everything you need to knowDifference between lease and license: Everything you need to know
Difference between lease and license: Everything you need to know
 
Land law 1 alienation 2014
Land law 1 alienation 2014Land law 1 alienation 2014
Land law 1 alienation 2014
 
National land code 1965
National land code 1965National land code 1965
National land code 1965
 
Undang undang tanah - lesen pendudukan sementara atau temporary occupational ...
Undang undang tanah - lesen pendudukan sementara atau temporary occupational ...Undang undang tanah - lesen pendudukan sementara atau temporary occupational ...
Undang undang tanah - lesen pendudukan sementara atau temporary occupational ...
 
Removal of rock material
Removal of rock materialRemoval of rock material
Removal of rock material
 
Real Estate (Development & Regulation) Act, 2016
Real Estate (Development & Regulation) Act, 2016Real Estate (Development & Regulation) Act, 2016
Real Estate (Development & Regulation) Act, 2016
 
3) lien holder caveat
3) lien holder caveat3) lien holder caveat
3) lien holder caveat
 
Land Law 1 DEFINITION OF LAND
Land Law 1 DEFINITION OF LANDLand Law 1 DEFINITION OF LAND
Land Law 1 DEFINITION OF LAND
 
Strata titles
Strata titlesStrata titles
Strata titles
 
restraint on dealings
restraint on dealingsrestraint on dealings
restraint on dealings
 
land-notes-all.pdf
land-notes-all.pdfland-notes-all.pdf
land-notes-all.pdf
 

Similar to Land Acquisition, Rehabilitation And Resettlement Act 2013

Land acquisition
Land acquisitionLand acquisition
Land acquisition
Aman Verma
 
Land Acquisition - Sem 9 .pptx
Land Acquisition - Sem 9 .pptxLand Acquisition - Sem 9 .pptx
Land Acquisition - Sem 9 .pptx
SajidPatel28
 
OVERVIEW OF LAND ACQUISITION ACT, 2013.pptx
OVERVIEW OF LAND ACQUISITION ACT, 2013.pptxOVERVIEW OF LAND ACQUISITION ACT, 2013.pptx
OVERVIEW OF LAND ACQUISITION ACT, 2013.pptx
HarshDhaka9
 
LARR act 2013
LARR act 2013LARR act 2013
LARR act 2013
Saurabh Pare
 
Land acquisition 1894 and larr 2013.pptx
Land acquisition 1894 and larr 2013.pptxLand acquisition 1894 and larr 2013.pptx
Land acquisition 1894 and larr 2013.pptx
DrVenkateswarluGogan1
 
Land acquisition (rehabilitation and resettlement) bill
Land acquisition (rehabilitation and resettlement) billLand acquisition (rehabilitation and resettlement) bill
Land acquisition (rehabilitation and resettlement) bill
Varun Vaish
 
Land acqusition-bill-pro-cons-by-prs
Land acqusition-bill-pro-cons-by-prsLand acqusition-bill-pro-cons-by-prs
Land acqusition-bill-pro-cons-by-prs
Shailesh Mishra
 
land acquisition act 2013
 land acquisition act 2013 land acquisition act 2013
land acquisition act 2013
MRS.PRITI VIVEK PATWARI
 
Slum Area Improvement & Clearance Act
Slum Area Improvement & Clearance ActSlum Area Improvement & Clearance Act
Slum Area Improvement & Clearance Act
Mitiksha Jain
 
LARR 02.10.2020 Class Lecture.pptx
LARR 02.10.2020 Class Lecture.pptxLARR 02.10.2020 Class Lecture.pptx
LARR 02.10.2020 Class Lecture.pptx
Bapul1
 
LARR act2013--.pptx
LARR act2013--.pptxLARR act2013--.pptx
LARR act2013--.pptx
rahulsen64
 
Exploring Alternatives to Land Acquisition
Exploring Alternatives to Land AcquisitionExploring Alternatives to Land Acquisition
Exploring Alternatives to Land Acquisition
Centre for Public Policy Research
 
Land law
Land lawLand law
Land Acquisition
Land AcquisitionLand Acquisition
Land Acquisition
Deepesh Seth
 
4.Land Acquisition ppt.pptx
4.Land Acquisition ppt.pptx4.Land Acquisition ppt.pptx
4.Land Acquisition ppt.pptx
rajarambharose8
 
Land acquisition act 1894- 2013
Land acquisition act 1894- 2013Land acquisition act 1894- 2013
Land acquisition act 1894- 2013
Sona Rawat
 
Land Acquisitoin Act 1894 Dr Venkateswarlu gogana.pdf
Land Acquisitoin Act 1894 Dr Venkateswarlu gogana.pdfLand Acquisitoin Act 1894 Dr Venkateswarlu gogana.pdf
Land Acquisitoin Act 1894 Dr Venkateswarlu gogana.pdf
DrVenkateswarluGogan1
 
Rttfc in larr_2013_2
Rttfc in larr_2013_2Rttfc in larr_2013_2
Rttfc in larr_2013_2
PSPCL
 
Land bill not cleared bill needs to modify again
Land bill not cleared bill needs to modify againLand bill not cleared bill needs to modify again
Land bill not cleared bill needs to modify again
kjanand
 
Planning Law Update May 2013
Planning Law Update May  2013Planning Law Update May  2013
Planning Law Update May 2013
Pat Coyle
 

Similar to Land Acquisition, Rehabilitation And Resettlement Act 2013 (20)

Land acquisition
Land acquisitionLand acquisition
Land acquisition
 
Land Acquisition - Sem 9 .pptx
Land Acquisition - Sem 9 .pptxLand Acquisition - Sem 9 .pptx
Land Acquisition - Sem 9 .pptx
 
OVERVIEW OF LAND ACQUISITION ACT, 2013.pptx
OVERVIEW OF LAND ACQUISITION ACT, 2013.pptxOVERVIEW OF LAND ACQUISITION ACT, 2013.pptx
OVERVIEW OF LAND ACQUISITION ACT, 2013.pptx
 
LARR act 2013
LARR act 2013LARR act 2013
LARR act 2013
 
Land acquisition 1894 and larr 2013.pptx
Land acquisition 1894 and larr 2013.pptxLand acquisition 1894 and larr 2013.pptx
Land acquisition 1894 and larr 2013.pptx
 
Land acquisition (rehabilitation and resettlement) bill
Land acquisition (rehabilitation and resettlement) billLand acquisition (rehabilitation and resettlement) bill
Land acquisition (rehabilitation and resettlement) bill
 
Land acqusition-bill-pro-cons-by-prs
Land acqusition-bill-pro-cons-by-prsLand acqusition-bill-pro-cons-by-prs
Land acqusition-bill-pro-cons-by-prs
 
land acquisition act 2013
 land acquisition act 2013 land acquisition act 2013
land acquisition act 2013
 
Slum Area Improvement & Clearance Act
Slum Area Improvement & Clearance ActSlum Area Improvement & Clearance Act
Slum Area Improvement & Clearance Act
 
LARR 02.10.2020 Class Lecture.pptx
LARR 02.10.2020 Class Lecture.pptxLARR 02.10.2020 Class Lecture.pptx
LARR 02.10.2020 Class Lecture.pptx
 
LARR act2013--.pptx
LARR act2013--.pptxLARR act2013--.pptx
LARR act2013--.pptx
 
Exploring Alternatives to Land Acquisition
Exploring Alternatives to Land AcquisitionExploring Alternatives to Land Acquisition
Exploring Alternatives to Land Acquisition
 
Land law
Land lawLand law
Land law
 
Land Acquisition
Land AcquisitionLand Acquisition
Land Acquisition
 
4.Land Acquisition ppt.pptx
4.Land Acquisition ppt.pptx4.Land Acquisition ppt.pptx
4.Land Acquisition ppt.pptx
 
Land acquisition act 1894- 2013
Land acquisition act 1894- 2013Land acquisition act 1894- 2013
Land acquisition act 1894- 2013
 
Land Acquisitoin Act 1894 Dr Venkateswarlu gogana.pdf
Land Acquisitoin Act 1894 Dr Venkateswarlu gogana.pdfLand Acquisitoin Act 1894 Dr Venkateswarlu gogana.pdf
Land Acquisitoin Act 1894 Dr Venkateswarlu gogana.pdf
 
Rttfc in larr_2013_2
Rttfc in larr_2013_2Rttfc in larr_2013_2
Rttfc in larr_2013_2
 
Land bill not cleared bill needs to modify again
Land bill not cleared bill needs to modify againLand bill not cleared bill needs to modify again
Land bill not cleared bill needs to modify again
 
Planning Law Update May 2013
Planning Law Update May  2013Planning Law Update May  2013
Planning Law Update May 2013
 

Recently uploaded

How to Fix [Errno 98] address already in use
How to Fix [Errno 98] address already in useHow to Fix [Errno 98] address already in use
How to Fix [Errno 98] address already in use
Celine George
 
Présentationvvvvvvvvvvvvvvvvvvvvvvvvvvvv2.pptx
Présentationvvvvvvvvvvvvvvvvvvvvvvvvvvvv2.pptxPrésentationvvvvvvvvvvvvvvvvvvvvvvvvvvvv2.pptx
Présentationvvvvvvvvvvvvvvvvvvvvvvvvvvvv2.pptx
siemaillard
 
REASIGNACION 2024 UGEL CHUPACA 2024 UGEL CHUPACA.pdf
REASIGNACION 2024 UGEL CHUPACA 2024 UGEL CHUPACA.pdfREASIGNACION 2024 UGEL CHUPACA 2024 UGEL CHUPACA.pdf
REASIGNACION 2024 UGEL CHUPACA 2024 UGEL CHUPACA.pdf
giancarloi8888
 
NIPER 2024 MEMORY BASED QUESTIONS.ANSWERS TO NIPER 2024 QUESTIONS.NIPER JEE 2...
NIPER 2024 MEMORY BASED QUESTIONS.ANSWERS TO NIPER 2024 QUESTIONS.NIPER JEE 2...NIPER 2024 MEMORY BASED QUESTIONS.ANSWERS TO NIPER 2024 QUESTIONS.NIPER JEE 2...
NIPER 2024 MEMORY BASED QUESTIONS.ANSWERS TO NIPER 2024 QUESTIONS.NIPER JEE 2...
Payaamvohra1
 
MDP on air pollution of class 8 year 2024-2025
MDP on air pollution of class 8 year 2024-2025MDP on air pollution of class 8 year 2024-2025
MDP on air pollution of class 8 year 2024-2025
khuleseema60
 
CapTechTalks Webinar Slides June 2024 Donovan Wright.pptx
CapTechTalks Webinar Slides June 2024 Donovan Wright.pptxCapTechTalks Webinar Slides June 2024 Donovan Wright.pptx
CapTechTalks Webinar Slides June 2024 Donovan Wright.pptx
CapitolTechU
 
Juneteenth Freedom Day 2024 David Douglas School District
Juneteenth Freedom Day 2024 David Douglas School DistrictJuneteenth Freedom Day 2024 David Douglas School District
Juneteenth Freedom Day 2024 David Douglas School District
David Douglas School District
 
Educational Technology in the Health Sciences
Educational Technology in the Health SciencesEducational Technology in the Health Sciences
Educational Technology in the Health Sciences
Iris Thiele Isip-Tan
 
Level 3 NCEA - NZ: A Nation In the Making 1872 - 1900 SML.ppt
Level 3 NCEA - NZ: A  Nation In the Making 1872 - 1900 SML.pptLevel 3 NCEA - NZ: A  Nation In the Making 1872 - 1900 SML.ppt
Level 3 NCEA - NZ: A Nation In the Making 1872 - 1900 SML.ppt
Henry Hollis
 
Wound healing PPT
Wound healing PPTWound healing PPT
Wound healing PPT
Jyoti Chand
 
Data Structure using C by Dr. K Adisesha .ppsx
Data Structure using C by Dr. K Adisesha .ppsxData Structure using C by Dr. K Adisesha .ppsx
Data Structure using C by Dr. K Adisesha .ppsx
Prof. Dr. K. Adisesha
 
مصحف القراءات العشر أعد أحرف الخلاف سمير بسيوني.pdf
مصحف القراءات العشر   أعد أحرف الخلاف سمير بسيوني.pdfمصحف القراءات العشر   أعد أحرف الخلاف سمير بسيوني.pdf
مصحف القراءات العشر أعد أحرف الخلاف سمير بسيوني.pdf
سمير بسيوني
 
Andreas Schleicher presents PISA 2022 Volume III - Creative Thinking - 18 Jun...
Andreas Schleicher presents PISA 2022 Volume III - Creative Thinking - 18 Jun...Andreas Schleicher presents PISA 2022 Volume III - Creative Thinking - 18 Jun...
Andreas Schleicher presents PISA 2022 Volume III - Creative Thinking - 18 Jun...
EduSkills OECD
 
A Visual Guide to 1 Samuel | A Tale of Two Hearts
A Visual Guide to 1 Samuel | A Tale of Two HeartsA Visual Guide to 1 Samuel | A Tale of Two Hearts
A Visual Guide to 1 Samuel | A Tale of Two Hearts
Steve Thomason
 
Oliver Asks for More by Charles Dickens (9)
Oliver Asks for More by Charles Dickens (9)Oliver Asks for More by Charles Dickens (9)
Oliver Asks for More by Charles Dickens (9)
nitinpv4ai
 
HYPERTENSION - SLIDE SHARE PRESENTATION.
HYPERTENSION - SLIDE SHARE PRESENTATION.HYPERTENSION - SLIDE SHARE PRESENTATION.
HYPERTENSION - SLIDE SHARE PRESENTATION.
deepaannamalai16
 
Leveraging Generative AI to Drive Nonprofit Innovation
Leveraging Generative AI to Drive Nonprofit InnovationLeveraging Generative AI to Drive Nonprofit Innovation
Leveraging Generative AI to Drive Nonprofit Innovation
TechSoup
 
Bossa N’ Roll Records by Ismael Vazquez.
Bossa N’ Roll Records by Ismael Vazquez.Bossa N’ Roll Records by Ismael Vazquez.
Bossa N’ Roll Records by Ismael Vazquez.
IsmaelVazquez38
 
Elevate Your Nonprofit's Online Presence_ A Guide to Effective SEO Strategies...
Elevate Your Nonprofit's Online Presence_ A Guide to Effective SEO Strategies...Elevate Your Nonprofit's Online Presence_ A Guide to Effective SEO Strategies...
Elevate Your Nonprofit's Online Presence_ A Guide to Effective SEO Strategies...
TechSoup
 
THE SACRIFICE HOW PRO-PALESTINE PROTESTS STUDENTS ARE SACRIFICING TO CHANGE T...
THE SACRIFICE HOW PRO-PALESTINE PROTESTS STUDENTS ARE SACRIFICING TO CHANGE T...THE SACRIFICE HOW PRO-PALESTINE PROTESTS STUDENTS ARE SACRIFICING TO CHANGE T...
THE SACRIFICE HOW PRO-PALESTINE PROTESTS STUDENTS ARE SACRIFICING TO CHANGE T...
indexPub
 

Recently uploaded (20)

How to Fix [Errno 98] address already in use
How to Fix [Errno 98] address already in useHow to Fix [Errno 98] address already in use
How to Fix [Errno 98] address already in use
 
Présentationvvvvvvvvvvvvvvvvvvvvvvvvvvvv2.pptx
Présentationvvvvvvvvvvvvvvvvvvvvvvvvvvvv2.pptxPrésentationvvvvvvvvvvvvvvvvvvvvvvvvvvvv2.pptx
Présentationvvvvvvvvvvvvvvvvvvvvvvvvvvvv2.pptx
 
REASIGNACION 2024 UGEL CHUPACA 2024 UGEL CHUPACA.pdf
REASIGNACION 2024 UGEL CHUPACA 2024 UGEL CHUPACA.pdfREASIGNACION 2024 UGEL CHUPACA 2024 UGEL CHUPACA.pdf
REASIGNACION 2024 UGEL CHUPACA 2024 UGEL CHUPACA.pdf
 
NIPER 2024 MEMORY BASED QUESTIONS.ANSWERS TO NIPER 2024 QUESTIONS.NIPER JEE 2...
NIPER 2024 MEMORY BASED QUESTIONS.ANSWERS TO NIPER 2024 QUESTIONS.NIPER JEE 2...NIPER 2024 MEMORY BASED QUESTIONS.ANSWERS TO NIPER 2024 QUESTIONS.NIPER JEE 2...
NIPER 2024 MEMORY BASED QUESTIONS.ANSWERS TO NIPER 2024 QUESTIONS.NIPER JEE 2...
 
MDP on air pollution of class 8 year 2024-2025
MDP on air pollution of class 8 year 2024-2025MDP on air pollution of class 8 year 2024-2025
MDP on air pollution of class 8 year 2024-2025
 
CapTechTalks Webinar Slides June 2024 Donovan Wright.pptx
CapTechTalks Webinar Slides June 2024 Donovan Wright.pptxCapTechTalks Webinar Slides June 2024 Donovan Wright.pptx
CapTechTalks Webinar Slides June 2024 Donovan Wright.pptx
 
Juneteenth Freedom Day 2024 David Douglas School District
Juneteenth Freedom Day 2024 David Douglas School DistrictJuneteenth Freedom Day 2024 David Douglas School District
Juneteenth Freedom Day 2024 David Douglas School District
 
Educational Technology in the Health Sciences
Educational Technology in the Health SciencesEducational Technology in the Health Sciences
Educational Technology in the Health Sciences
 
Level 3 NCEA - NZ: A Nation In the Making 1872 - 1900 SML.ppt
Level 3 NCEA - NZ: A  Nation In the Making 1872 - 1900 SML.pptLevel 3 NCEA - NZ: A  Nation In the Making 1872 - 1900 SML.ppt
Level 3 NCEA - NZ: A Nation In the Making 1872 - 1900 SML.ppt
 
Wound healing PPT
Wound healing PPTWound healing PPT
Wound healing PPT
 
Data Structure using C by Dr. K Adisesha .ppsx
Data Structure using C by Dr. K Adisesha .ppsxData Structure using C by Dr. K Adisesha .ppsx
Data Structure using C by Dr. K Adisesha .ppsx
 
مصحف القراءات العشر أعد أحرف الخلاف سمير بسيوني.pdf
مصحف القراءات العشر   أعد أحرف الخلاف سمير بسيوني.pdfمصحف القراءات العشر   أعد أحرف الخلاف سمير بسيوني.pdf
مصحف القراءات العشر أعد أحرف الخلاف سمير بسيوني.pdf
 
Andreas Schleicher presents PISA 2022 Volume III - Creative Thinking - 18 Jun...
Andreas Schleicher presents PISA 2022 Volume III - Creative Thinking - 18 Jun...Andreas Schleicher presents PISA 2022 Volume III - Creative Thinking - 18 Jun...
Andreas Schleicher presents PISA 2022 Volume III - Creative Thinking - 18 Jun...
 
A Visual Guide to 1 Samuel | A Tale of Two Hearts
A Visual Guide to 1 Samuel | A Tale of Two HeartsA Visual Guide to 1 Samuel | A Tale of Two Hearts
A Visual Guide to 1 Samuel | A Tale of Two Hearts
 
Oliver Asks for More by Charles Dickens (9)
Oliver Asks for More by Charles Dickens (9)Oliver Asks for More by Charles Dickens (9)
Oliver Asks for More by Charles Dickens (9)
 
HYPERTENSION - SLIDE SHARE PRESENTATION.
HYPERTENSION - SLIDE SHARE PRESENTATION.HYPERTENSION - SLIDE SHARE PRESENTATION.
HYPERTENSION - SLIDE SHARE PRESENTATION.
 
Leveraging Generative AI to Drive Nonprofit Innovation
Leveraging Generative AI to Drive Nonprofit InnovationLeveraging Generative AI to Drive Nonprofit Innovation
Leveraging Generative AI to Drive Nonprofit Innovation
 
Bossa N’ Roll Records by Ismael Vazquez.
Bossa N’ Roll Records by Ismael Vazquez.Bossa N’ Roll Records by Ismael Vazquez.
Bossa N’ Roll Records by Ismael Vazquez.
 
Elevate Your Nonprofit's Online Presence_ A Guide to Effective SEO Strategies...
Elevate Your Nonprofit's Online Presence_ A Guide to Effective SEO Strategies...Elevate Your Nonprofit's Online Presence_ A Guide to Effective SEO Strategies...
Elevate Your Nonprofit's Online Presence_ A Guide to Effective SEO Strategies...
 
THE SACRIFICE HOW PRO-PALESTINE PROTESTS STUDENTS ARE SACRIFICING TO CHANGE T...
THE SACRIFICE HOW PRO-PALESTINE PROTESTS STUDENTS ARE SACRIFICING TO CHANGE T...THE SACRIFICE HOW PRO-PALESTINE PROTESTS STUDENTS ARE SACRIFICING TO CHANGE T...
THE SACRIFICE HOW PRO-PALESTINE PROTESTS STUDENTS ARE SACRIFICING TO CHANGE T...
 

Land Acquisition, Rehabilitation And Resettlement Act 2013

  • 2. • Land acquisition is the process by which the government acquires private property for public purpose. • Till 2013, land acquisition in India was governed by Land Acquisition Act of 1894 .
  • 4. • Under the 1894 Act, the government could acquire any land as it wishes to, in the name of "public purpose“. The term “public purpose” was ambiguous and open to executive-discretion. So, poor peoples’ land was acquired at throwaway prices in pretext of development projects. • Sometimes such projects never started, and the same cheap land was resold at higher price to real estate developers, without building anything for “public purpose”.
  • 5. • Urgency clause: This is the most criticized section of the Law. The clause never truly defines what constitutes an urgent need and leaves it to the discretion of the acquiring authority. • No safeguards: There is no real appeal mechanism to stop the process of the acquisition. A hearing (under section 5A) is prescribed but this is not a discussion or negotiation. The views expressed are not required to be taken on board by the officer conducting the hearing. • Silent on resettlement and rehabilitation of those displaced: There are absolutely no provisions in the 1894 law relating to the resettlement and rehabilitation of those displaced by the acquisition.
  • 6. • Low rates of compensation: The rates paid for the land acquired are the prevailing circle rates in the area which are notorious for being outdated and hence not even remotely indicative of the actual rates prevailing in the area. • Litigation: Even where acquisition has been carried out the same has been challenged in litigations on the grounds mentioned above. This results in the stalling of legitimate infrastructure projects.
  • 8. • The Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013, which came into force from 1 January 2014. • The title of the old law conveyed that its primary purpose was to expedite the acquisition of land. However, the principle objective of the new Bill is fair compensation, thorough resettlement and rehabilitation of those affected, adequate safeguards for their well-being and complete transparency in the process of land acquisition. The title has been amended to reflect this. • Retrospective operation: To address historical injustice it applies retrospectively to cases where no land acquisition award has been made. Also in cases where the land was acquired five years ago but no compensation has been paid land acquisition process will be started afresh
  • 9. Social Impact Assessment Consent of Families (70-80%) >Market rate Price (2x-4x) Additional Relief to SC/ST Restriction on Fertile Land Dispute Settlement Mechanism Accountability of HOD
  • 10. 1. COMPENSATION : COMPENSATION IN RURAL AREAS WOULD BE CALCULATED BY MULTIPLYING MARKET VALUE BY TWO AND ADDING ASSETS ATTACHED TO THE LAND OR BUILDING AND ADDING A SOLATIUM. IN URBAN AREAS IT WOULD BE MARKET VALUE PLUS ASSETS ATTACHED TO THE LAND AND SOLATIUM. ILLUSTRATION Suppose the market value of a piece of land in rural area is 10,00,000. Multiplying it by 2 ----- 10,00,000 x 2 = 20,00,000 Adding value of assets (2,00,000) attached to land ------ = 22,00,000 Adding 100% solatium, the final compensation = 44,00,000 A piece of land of market value 10,00,000 in urban area ----- Adding value of asset (2,00,000) attached to land ------ = 12,00,000 Adding 100% solatium , the final compensation = 24,00,000
  • 11. • Compensation for livelihood losers: In addition to those losing land, the Bill provides compensation to those who are dependent on the land being acquired for their livelihood. To qualify for benefits under this Act the time period has been reduced to three years of dependence (on the acquired land) from five • Fishing rights: In the case of irrigation or hydel projects, affected families may be allowed fishing rights in the reservoirs. • Share in appreciated land value: Where the acquired land is sold to a third party for a higher price, 40% of the appreciated land value (or profit) will be shared with the original owners.
  • 12. •CONSENT: Consent of up to 80 per cent of people required for private projects. For PPP projects, the approval of 70 per cent of the same is mandatory •Multi-cropped, irrigated land cannot be acquired unless it is for defence or emergency caused by natural calamity •Land should be returned to original owner or the State Land Bank if not used in five years for the purpose for which it is acquired • The government will not acquire land for private companies for private purpose
  • 13. • Exemption from income tax and stamp duty: No income tax shall be levied and no stamp duty shall be charged on any amount that accrues to an individual as a result of the provisions of the new law. • The Bill also proposes amenities like schools, health centres and civic infrastructure in places where project- affected people are resettled The urgency clause should be exercised in the rarest of rare cases like national defense or for resettlement purposes. The Social Impact Assessment (SIA) has to be carried out in consultation with the representatives of the Panchayati Raj Institutions (PRIs) Reports prepared under the Social Impact Assessment are to be shared with these representatives
  • 14. 1.INVESTIGATION PROCESS • When a local authority or a company requires a land, an application is required to be made by it to the revenue authority,accompanied with a copy of the plan showing survey nos., purpose of acquisition and the reason for the particular site to be chosen and the provision made for the cost of the acquisition. • After the government has been fully satisfied about the purpose, the least area needed, and other relevant facts as provided under land acquisition rules, it will issue a notification under Section 4 of the act that the particular land is required for public purpose. PROCEDURE FOR THE LAND ACQUISITION
  • 15. 2. OBJECTION AND CONFIRMATION • Objections are invited from all persons interested in land within thirty days from the date of notification. • The objections will be valid on one or more of the following grounds: i. That the purpose for which the land is proposed for acquisition is not a public purpose. ii. That the land is not or less suitable than another piece of land for the said purpose. iii. That the area under acquisition is excessive. iv. That the acquisition will destroy or impair historical or artistic monuments or will desecrate religious buildings, graveyards and the like.
  • 16. 3. Claim and Award •The collector will issue notices under Section 9 to all persons interested in the acquisition to file their claim reports. •In determining the compensation the market value of the land is determined at the date of notification. The rise and fall in the value during the period of transaction and notification is taken into consideration. • Compensation is also payable when: i. Part of the property is proposed for acquisition in such a manner that the remainder depreciates in value. ii. When the land notified for acquisition has standing crops or trees.
  • 17. • Compensation is also payable when: i. Part of the property is proposed for acquisition in such a manner that the remainder depreciates in value. ii. When the land notified for acquisition has standing crops or trees. iii. If the person interested has to change his place of residence or business then the excess rent payable for the new premises is also considered for compensation • After necessary inquiries the collector declares his award showing true area of the land, total amount of compensation payable and apportionment of compensation if there are more than one owners or claimants. 4. Reference to Court • Any person interested to whom the award is not satisfactory can submit a written application to the court. • This application should be made within six weeks from the date of declaration of the award.
  • 18. The new government passed an ordinance on Land Acquisition on 29th December 2014 introducing major changes to the 2013 Act. Land Acquisition Bill
  • 19. • LARR Act-2013 established an extremely complex andimpractical land acquisition process. • Holdouts: Jholachhap NGOs would instigate 20-25% of the affected families to stage holdout- promising them it’ll fetch them even higher prices. and Given the 70-80% consent requirement, the project will never kickoff. • Litigation: because local (and therefore corruption) Patwari and Tehsildars never maintain proper land records of who owns how much land. •This raised the land prices, red tapism and thus the overall project cost. • Neither the farmer could sell its land and move to urban areas, nor the entrepreneur could buy the land and move towards rural areas.
  • 20. The existing Act kept 13 most frequently used acts for Land Acquisition for Central Government Projects out of the purview. These acts are applicable for national highways, metro rail, atomic energy projects, electricity related projects, etc. The present amendments bring all those exempted from the 13 acts under the purview of this Act for the purpose of compensation, rehabilitation and resettlement. Therefore, the amendment benefits farmers and affected families.
  • 21. The proposed changes in the Land Acquisition Act would allow a fast track process for defence and defence production, rural infrastructure including electrification, affordable housing, industrial corridors and infrastructure projects including projects taken up under Public Private Partnership mode where ownership of the land continues to be vested with the government. As per the changes brought in the Ordinance, multi-crop irrigated land can also be acquired for purposes like national security, defence, rural infrastructure including electrification, industrial corridors and building social infrastructure.
  • 22. CONS The original Land Acquisition Act, 2013 had a consent clause for acquiring land – industrial corridors, Public Private Partnership projects, rural infrastructure, affordable housing and defence. But after the central government changed, it exempted these five categories from the rule of acquitting land in the Bill tabled on February 24.
  • 23. Social assessment which was mandatory before acquitting land has also been exempted in the Bill tabled in the Lok Sabha. As per the existing law, land will be given back to the farmer if it remains unused for five years. The proposed amendment says the land will be returned only if the specified project on the land fails to complete the deadline. Also whether the land is fertile or not will also not be taken into consideration while acquiring it for these five specific sectors.
  • 24.
  • 25. • Anti-corruption crusader Anna Hazare launched a two-day token agitation against the new land acquisition act on February 23 and 24. His agitation has received support from thousands of activists and farmers • Hazare pressed for repeal of the ordinance issued by the union government on 29 December 2014 • In a post on his blog, Hazare has criticised this amendment as anti- farmer and pro-corporate • He opposed the various clauses in the ordinance like removal of SIA,Consent Requirement,multi crop land provision,Return of Land to Farmers if unused.
  • 26. Comparison between 1984 Law , 2013 Act and 2014 Ordinance
  • 27.
  • 28.  In an attempt to placate the opposition and some unhappy allies, government brought nine official amendments and added two clauses to the controversial legislation.  The amendments have been passed in the Lok Sabha setting the stage for its consideration in Rajya Sabha where the numbers are loaded against the government.
  • 29.  The social impact asssessment of land to be acquired will be the prerogativeofthestate governments  The amendments include dropping of exemption to "social infrastructure" projects as there were fears that private individuals may use this clause to open colleges and hospitals which are actually businessmodels  Multi-croplandswillnotbeacquired  Land will be returned to the farmer if the project is not completed, but the time consumed by court cases and injunctions will not be counted. Themostimportantclause-theConsentClause hasnotbeendealtwithyet , this being the major reason for the widespread opposition against the ordinance
  • 30.  Government has decided to prorogue the Rajya Sabha and repromulgate the Land Ordinance in the next session, as the existing ordinance lapses on April 5 with the end of the Rajya SabhaSession.  Sources said that the government will its best to bring the land bill in Rajya Sabha to replace the ordinance in the second half of the Budget session after it reconvenes on April20
  • 31.  It may agree to reintroduce the provision of taking farmers' consent for acquiring land. The earlier 80 percent consent requirementcanbe reduced to51percent.  Similarly, instead of the earlier social impact assessment (SIA), the government may involve expert groups to examine the land deals to find out whether excess landhas beenacquiredfora projectand whether ithas affectedthe original inhabitants.