On September 28, 2015, Lake Ontario Waterkeeper submitted a request to the Canadian Nuclear Safety Committee to intervene during the Day 2 Relicensing Hearing for the Darlington Nuclear Generating Station.
Waterkeeper's PNGS hearing remarks - June 29, 2018LOWaterkeeper
On June 29, 2018 Pippa Feinstein delivered these remarks on behalf of Lake Ontario Waterkeeper and Swim Drink Fish to the CNSC hearing on the Pickering Nuclear Generating Station licence renewal application. Check against return.
Presentation entitled ‘Sustainable Wastewater Management in Rural Housing Developments’ given on the 28th January, 2008 at the ESAI run Environ Colloquium 2008. For rural developments, it is frequently the responsibility of private developers to identify a suitable wastewater treatment system to treat the effluent. Frequently, the capacity of adjacent streams and rivers to accept further treated effluent is reached and a discharge of treated effluent to groundwater is the only viable option necessitating the processing of a Discharge Licence Application and the carrying out of a groundwater assessment to assess the assimilative capacity of the underlying aquifer. Under the Nitrates Directive, the quality of treated wastewater being discharged to ground is of paramount importance in conjunction with the background nitrate concentration. This presentation was 0.3 hours in duration and hosted approximately 200 delegates
Los Angeles Water Keepers - Draft Environmental Impact Report Comments - Herm...StopHermosaBeachOil
The document is a letter from Los Angeles Waterkeeper commenting on the Draft Environmental Impact Report for the E & B Oil Drilling & Production Project in Hermosa Beach, California. The letter identifies several deficiencies in the DEIR's analysis of potential impacts to water quality and resources. Specifically, it argues the DEIR fails to adequately assess impacts from discharges, oil spills, use of hazardous chemicals, well stimulation techniques, and re-drilling. The letter maintains these omissions prevent fully informed decision-making under the California Environmental Quality Act. Extensive revisions are requested to address the shortcomings.
This document announces upcoming regulatory outreach meetings to discuss California's proposed low-threat closure policy for petroleum underground storage tanks. Meetings will be held in August, September, and October 2011 in several California cities. The meetings aim to discuss technical and practical aspects of the recommended policy, which was presented to the State Water Resources Control Board in July 2011 by a task force. Interested parties are invited to attend one of the outreach sessions.
The following documents were submitted by the Republic of Ecuador to the international arbitration hearing the case between Chevron/Texaco and the Republic. These documents further show the impact of Chevron/Texaco’s decades’ long oil pollution on the people of Ecuador.
Environmental Issues Affecting Real Estate Smu Cox Real Estate Law Classslongroy
This document summarizes several key environmental issues that can affect real estate transactions and development projects. It discusses regulations pertaining to waste management (RCRA/Texas SWDA), hazardous substance cleanup (CERCLA/Texas SWDA), and brownfield redevelopment. It also covers stormwater management and permitting requirements, protections for floodplains and wetlands, asbestos and lead regulations, the Endangered Species Act, and emerging trends around greenhouse gas regulation and sustainable development.
Special Protections And Areas Of Special Biological Significance Casqa Powerp...awaltner
The document discusses the ongoing controversy around regulating stormwater discharges to Areas of Special Biological Significance (ASBS) in California. It provides background on the designation of ASBSs in the 1970s, the history of prohibiting "waste" discharges to them, a 2003 inventory that found over 1,600 direct discharges, and recent efforts to issue exceptions allowing certain discharges if special conditions are met. Stakeholders disagree on how to balance protecting natural water quality in ASBSs with the technical and economic feasibility of completely prohibiting stormwater discharges.
Waterkeeper's PNGS hearing remarks - June 29, 2018LOWaterkeeper
On June 29, 2018 Pippa Feinstein delivered these remarks on behalf of Lake Ontario Waterkeeper and Swim Drink Fish to the CNSC hearing on the Pickering Nuclear Generating Station licence renewal application. Check against return.
Presentation entitled ‘Sustainable Wastewater Management in Rural Housing Developments’ given on the 28th January, 2008 at the ESAI run Environ Colloquium 2008. For rural developments, it is frequently the responsibility of private developers to identify a suitable wastewater treatment system to treat the effluent. Frequently, the capacity of adjacent streams and rivers to accept further treated effluent is reached and a discharge of treated effluent to groundwater is the only viable option necessitating the processing of a Discharge Licence Application and the carrying out of a groundwater assessment to assess the assimilative capacity of the underlying aquifer. Under the Nitrates Directive, the quality of treated wastewater being discharged to ground is of paramount importance in conjunction with the background nitrate concentration. This presentation was 0.3 hours in duration and hosted approximately 200 delegates
Los Angeles Water Keepers - Draft Environmental Impact Report Comments - Herm...StopHermosaBeachOil
The document is a letter from Los Angeles Waterkeeper commenting on the Draft Environmental Impact Report for the E & B Oil Drilling & Production Project in Hermosa Beach, California. The letter identifies several deficiencies in the DEIR's analysis of potential impacts to water quality and resources. Specifically, it argues the DEIR fails to adequately assess impacts from discharges, oil spills, use of hazardous chemicals, well stimulation techniques, and re-drilling. The letter maintains these omissions prevent fully informed decision-making under the California Environmental Quality Act. Extensive revisions are requested to address the shortcomings.
This document announces upcoming regulatory outreach meetings to discuss California's proposed low-threat closure policy for petroleum underground storage tanks. Meetings will be held in August, September, and October 2011 in several California cities. The meetings aim to discuss technical and practical aspects of the recommended policy, which was presented to the State Water Resources Control Board in July 2011 by a task force. Interested parties are invited to attend one of the outreach sessions.
The following documents were submitted by the Republic of Ecuador to the international arbitration hearing the case between Chevron/Texaco and the Republic. These documents further show the impact of Chevron/Texaco’s decades’ long oil pollution on the people of Ecuador.
Environmental Issues Affecting Real Estate Smu Cox Real Estate Law Classslongroy
This document summarizes several key environmental issues that can affect real estate transactions and development projects. It discusses regulations pertaining to waste management (RCRA/Texas SWDA), hazardous substance cleanup (CERCLA/Texas SWDA), and brownfield redevelopment. It also covers stormwater management and permitting requirements, protections for floodplains and wetlands, asbestos and lead regulations, the Endangered Species Act, and emerging trends around greenhouse gas regulation and sustainable development.
Special Protections And Areas Of Special Biological Significance Casqa Powerp...awaltner
The document discusses the ongoing controversy around regulating stormwater discharges to Areas of Special Biological Significance (ASBS) in California. It provides background on the designation of ASBSs in the 1970s, the history of prohibiting "waste" discharges to them, a 2003 inventory that found over 1,600 direct discharges, and recent efforts to issue exceptions allowing certain discharges if special conditions are met. Stakeholders disagree on how to balance protecting natural water quality in ASBSs with the technical and economic feasibility of completely prohibiting stormwater discharges.
Enbridge provides a summary of its liability insurance coverage for environmental damage from pipeline releases. The coverage amounts are consistent with industry standards but are not disclosed. Enbridge reviews its pipelines for risks from factors like erosion but does not detail its mitigation strategies. In the event of a spill contaminating aquifers, Enbridge would develop a remediation plan with regulators, but the potential spill size depends on many incident-specific variables.
Environmental code of practice for aboveground storage tank containing petrol...Jin Chen
The document introduces the Environmental Code of Practice for Aboveground Storage Tank Systems Containing Petroleum Products published by the Canadian Council of Ministers of the Environment (CCME) to establish minimum technical requirements to prevent releases from aboveground storage tanks and piping in order to protect the environment; the Code provides recommendations for registration, design, installation, upgrading, operation, maintenance, and withdrawal from service of aboveground storage tank systems.
Secondary containment for above ground storage tanks is important to control leaks and spills, protect water resources, and comply with EPA regulations. The SPCC rule requires facilities with above ground oil storage tanks to develop a spill prevention plan that is certified by a professional engineer. The plan must address secondary containment through dikes or barriers sufficient to contain the volume of the largest tank. Proper maintenance and inspection of containment structures is also critical to prevent environmental incidents like the 2014 chemical spill in West Virginia that contaminated local water supplies.
The document discusses water use and regulation associated with unconventional gas wells, noting that fracturing requires millions of gallons of water on average and produces wastewater containing dissolved solids, metals, and organics. It outlines the various federal and state regulatory requirements and permits for water withdrawals, wastewater treatment and discharge. While environmental impacts have included spills and contamination, the health effects are controversial with little information but concerns raised about respiratory, neurological and other issues in nearby communities.
The document discusses the environmental impacts of high volume hydraulic fracturing, or fracking, for natural gas in Pennsylvania. It notes that HVHF uses much larger volumes of water and chemical additives compared to traditional fracking methods. Regulatory loopholes and inadequate oversight of water withdrawals, wastewater disposal, and facility siting have led to concerns about impacts to water resources, habitat fragmentation, and threats to public water supplies and aquatic ecosystems. The organization discussed, Stewards of the Lower Susquehanna, is working to educate the public and advocate for stronger regulations and enforcement to better protect the environment.
A new brief guide for homeowners who live near oil and gas drilling activity, to help them know when and how they should test their water wells. The guide is written by the National Ground Water Association and the Ground Water Protection Council.
This presentation describes the current status of vapor intrusion regulation in Texas under existng rules and guidance documents, and points out the ambiguity and case-by-case nature of vapor intrustion regualtion in the State at this time.
This document provides a climate change risk assessment for the municipal assets of the Town of Hartland, NB. It identifies vulnerabilities and ranks key assets for further analysis. It assesses the storm water and wastewater systems, developing mitigation strategies. For stormwater, it proposes a management system and use of low-impact designs. For wastewater, it recommends a removable floodwall or berm/wall for the lagoon and separating storm and wastewater lines. It provides cost-benefit analysis and recommends phased implementation of stormwater management, protective barriers, line separation and continued low-impact designs.
The TCE Revolution and Its Permanent Impact on Environmental Due DiligenceEDR
EDR INSIGHT WEBINAR: THE TCE REVOLUTION AND ITS PERMANENT IMPACT ON ENVIRONMENTAL DUE DILIGENCE
June 24, 2015
Presented by:
-David Gillay, Partner and Chair of Brownfields & Environmental Transactional Diligence Practice Areas, Barnes & Thornburg LLP
-Dr. Michael Dourson, Ph.D., Alliance for Risk Assessment
Following decades of studies, scrutiny and debate, the U.S. EPA updated its TCE’s toxicity profile in the IRIS database, dramatically lowering the toxicity value. For transactional due diligence, this more stringent limit has important implications, including markedly more extensive and expensive cleanup processes. Given the focus on vapor migration in the new ASTM Phase I ESA standard, environmental professionals need to be increasingly cautious when making REC determinations and recommendations to clients.
Adding to the confusion is the significant variability in how regulators are using the updated TCE toxicity profile when making closure decisions at contaminated properties. For instance, U.S. EPA Regions 9, 10 and states like Minnesota, Indiana and Massachusetts (among others) have implemented profoundly different approaches to address TCE risk at contaminated sites. Thus, it is critical for environmental professionals to stay abreast of the how TCE guidance is being interpreted and applied across the country. In the latest development, the Agency for Toxic Substances & Disease Registry is proposing a dramatic change to its TCE toxicity profile for the first time in 18 years. The comment period ended on March 16, 2015, and if the update is finalized in its current form, there will be more intense scrutiny on exposure risks which will further complicate transactional due diligence.
This timely webinar will bring together an attorney and a national subject matter expert to address the various impacts of TCE’s toxicity update on transactional due diligence. This panel will help EPs answer the following questions:
-Does TCE in groundwater constitute a VEC and/or a REC?
-How should an EP manage variability in TCE standards in multi-state transactions?
-How can an EP take steps to minimize exposure to potential liability?
-How can an EP make sense of the science and available guidance?
-How should an EP communicate potential risks associated with TCE to clients?
This document summarizes a workshop on understanding, monitoring, and mitigating potential environmental effects of CO2 leakage from carbon capture and storage (CCS) projects in marine and terrestrial environments.
The workshop aimed to identify current research gaps on CO2 leakage effects, issues in current research, and further areas of investigation needed before large-scale CCS deployment. Workshop attendees discussed requirements and barriers for detecting CO2 leaks in marine environments, and knowledge gaps regarding potential onshore and offshore leakage scenarios. Key gaps identified included regional geological knowledge, fault behavior, improved CO2 sensors, and modeling various leakage scenarios. The social aspects of public engagement with CCS were also discussed.
The webinar covered recent regulatory developments in construction and post-construction stormwater management. It discussed changes to the EPA's Construction General Permit including new buffer requirements and timelines for stabilization. It also summarized EPA's proposed rulemaking to strengthen post-construction stormwater requirements and establish national performance standards for new development. Finally, it reviewed federal requirements for stormwater management on federal facilities.
The document discusses the history and present status of the Clean Water Act. It began as the Federal Water Pollution Control Act in 1948 and was amended and expanded in 1972 following highly polluted incidents like the Cuyahoga River catching fire. The Act established the EPA, water quality standards, and the National Pollutant Discharge Elimination System. Recent Supreme Court cases have created uncertainty around the definition of "navigable waters," weakening the Act's protections. The future effectiveness of the Act depends on clarifying these definitions and addressing challenges like infrastructure funding and pollution.
A survey conducted in fall 2013 of members of the Marcellus Shale Safe Drilling Advisory Commission members on their reaction to the draft "best practices" document produced by the commission. The survey was meant to pinpoint areas of disagreement for future discussion at Commission meetings. The responses show members to be careful, considerate, and deliberative about shale drilling. It also shows they are in favor of it and believe it can move forward with certain safeguards in place.
The document summarizes a meeting between the Blue Grass Chemical Agent-Destruction Pilot Plant team and the Secondary Waste Working Group. The meeting provided updates on cyanide mitigation treatment and worker protection. Presentations were given on hazard assessments, cyanide challenges, and safety protocols. Questions were asked about spill response procedures, facility air flows, and monitoring worker stress. The group also discussed potential recycling of secondary waste metals and an upcoming National Research Council study on off-site hydrolysate shipment.
ESI has over 15 years of experience providing environmental consulting services in Southeast England. They opened a new office in Reading in 2011 to increase their support to clients in the region. ESI specializes in water management, land quality, landfill/waste management, and ground source energy. This document highlights some of ESI's key service areas and provides case studies of projects they have completed in Southeast England.
The document discusses the requirements for Oil Spill Prevention Control and Countermeasure (SPCC) Plans under the Clean Water Act. It provides an overview of the regulations and outlines what facilities need to include in their SPCC Plans, such as inventory of oil storage containers and equipment, procedures for oil spill response, inspection schedules, and training for employees. It emphasizes that the goal of SPCC Plans is to minimize the potential for oil releases to waters of the United States such as rivers, lakes, and wetlands.
05 shoemaker us german workshop presentationleann_mays
Sandia National Laboratories manages and operates the Waste Isolation Pilot Plant (WIPP) for the US Department of Energy. WIPP is located in salt deposits near Carlsbad, New Mexico and is intended for permanent disposal of defense-related transuranic radioactive waste. WIPP's safety case demonstrates that over 10,000 years, cumulative radioactive releases from WIPP will remain below regulatory limits through multiple conservative performance assessment scenarios and the inherent stability of the salt repository. While some modeling assumptions may become less conservative over time, WIPP's compliance is ensured by its host geology and rigorous safety analysis process.
This document provides information and guidance on protesting a Texas Railroad Commission (RRC) injection well permit application on behalf of a Groundwater Conservation District (GCD). It outlines the 15-day deadline to request an RRC hearing after a permit application is published. It also recommends that GCDs adopt rules authorizing the general manager to seek party status in permit hearings and negotiate with applicants. Key hearing issues include whether the well will adequately protect groundwater and be confined to the permitted disposal zone. The document suggests items for potential settlement with applicants, such as enhanced containment and cement bond logs.
Complaint to Advertising Standards Canada - 2010LOWaterkeeper
Waterkeeper submitted a complaint about the Power Workers Union's claim that nuclear power is "emissions-free". This complaint documents a few of the ways nuclear power plants do release contaminants into the air. ASC upheld Waterkeeper's complaint.
Investing in wastewater infrastructure to restore the Great LakesLOWaterkeeper
On May 26, 2016 Krystyn Tully spoke at the Ontario Coalition for Sustainable Infrastructure's annual Forum. Asked to address the topic of "big things happening in Ontario" in six minutes, Krystyn told the audience that people are coming back to the Great Lakes in droves. She challenged them to think of wastewater system improvements that would ensure all Great Lakes waters are clean for every person in every community so that our urban communities can prosper.
Enbridge provides a summary of its liability insurance coverage for environmental damage from pipeline releases. The coverage amounts are consistent with industry standards but are not disclosed. Enbridge reviews its pipelines for risks from factors like erosion but does not detail its mitigation strategies. In the event of a spill contaminating aquifers, Enbridge would develop a remediation plan with regulators, but the potential spill size depends on many incident-specific variables.
Environmental code of practice for aboveground storage tank containing petrol...Jin Chen
The document introduces the Environmental Code of Practice for Aboveground Storage Tank Systems Containing Petroleum Products published by the Canadian Council of Ministers of the Environment (CCME) to establish minimum technical requirements to prevent releases from aboveground storage tanks and piping in order to protect the environment; the Code provides recommendations for registration, design, installation, upgrading, operation, maintenance, and withdrawal from service of aboveground storage tank systems.
Secondary containment for above ground storage tanks is important to control leaks and spills, protect water resources, and comply with EPA regulations. The SPCC rule requires facilities with above ground oil storage tanks to develop a spill prevention plan that is certified by a professional engineer. The plan must address secondary containment through dikes or barriers sufficient to contain the volume of the largest tank. Proper maintenance and inspection of containment structures is also critical to prevent environmental incidents like the 2014 chemical spill in West Virginia that contaminated local water supplies.
The document discusses water use and regulation associated with unconventional gas wells, noting that fracturing requires millions of gallons of water on average and produces wastewater containing dissolved solids, metals, and organics. It outlines the various federal and state regulatory requirements and permits for water withdrawals, wastewater treatment and discharge. While environmental impacts have included spills and contamination, the health effects are controversial with little information but concerns raised about respiratory, neurological and other issues in nearby communities.
The document discusses the environmental impacts of high volume hydraulic fracturing, or fracking, for natural gas in Pennsylvania. It notes that HVHF uses much larger volumes of water and chemical additives compared to traditional fracking methods. Regulatory loopholes and inadequate oversight of water withdrawals, wastewater disposal, and facility siting have led to concerns about impacts to water resources, habitat fragmentation, and threats to public water supplies and aquatic ecosystems. The organization discussed, Stewards of the Lower Susquehanna, is working to educate the public and advocate for stronger regulations and enforcement to better protect the environment.
A new brief guide for homeowners who live near oil and gas drilling activity, to help them know when and how they should test their water wells. The guide is written by the National Ground Water Association and the Ground Water Protection Council.
This presentation describes the current status of vapor intrusion regulation in Texas under existng rules and guidance documents, and points out the ambiguity and case-by-case nature of vapor intrustion regualtion in the State at this time.
This document provides a climate change risk assessment for the municipal assets of the Town of Hartland, NB. It identifies vulnerabilities and ranks key assets for further analysis. It assesses the storm water and wastewater systems, developing mitigation strategies. For stormwater, it proposes a management system and use of low-impact designs. For wastewater, it recommends a removable floodwall or berm/wall for the lagoon and separating storm and wastewater lines. It provides cost-benefit analysis and recommends phased implementation of stormwater management, protective barriers, line separation and continued low-impact designs.
The TCE Revolution and Its Permanent Impact on Environmental Due DiligenceEDR
EDR INSIGHT WEBINAR: THE TCE REVOLUTION AND ITS PERMANENT IMPACT ON ENVIRONMENTAL DUE DILIGENCE
June 24, 2015
Presented by:
-David Gillay, Partner and Chair of Brownfields & Environmental Transactional Diligence Practice Areas, Barnes & Thornburg LLP
-Dr. Michael Dourson, Ph.D., Alliance for Risk Assessment
Following decades of studies, scrutiny and debate, the U.S. EPA updated its TCE’s toxicity profile in the IRIS database, dramatically lowering the toxicity value. For transactional due diligence, this more stringent limit has important implications, including markedly more extensive and expensive cleanup processes. Given the focus on vapor migration in the new ASTM Phase I ESA standard, environmental professionals need to be increasingly cautious when making REC determinations and recommendations to clients.
Adding to the confusion is the significant variability in how regulators are using the updated TCE toxicity profile when making closure decisions at contaminated properties. For instance, U.S. EPA Regions 9, 10 and states like Minnesota, Indiana and Massachusetts (among others) have implemented profoundly different approaches to address TCE risk at contaminated sites. Thus, it is critical for environmental professionals to stay abreast of the how TCE guidance is being interpreted and applied across the country. In the latest development, the Agency for Toxic Substances & Disease Registry is proposing a dramatic change to its TCE toxicity profile for the first time in 18 years. The comment period ended on March 16, 2015, and if the update is finalized in its current form, there will be more intense scrutiny on exposure risks which will further complicate transactional due diligence.
This timely webinar will bring together an attorney and a national subject matter expert to address the various impacts of TCE’s toxicity update on transactional due diligence. This panel will help EPs answer the following questions:
-Does TCE in groundwater constitute a VEC and/or a REC?
-How should an EP manage variability in TCE standards in multi-state transactions?
-How can an EP take steps to minimize exposure to potential liability?
-How can an EP make sense of the science and available guidance?
-How should an EP communicate potential risks associated with TCE to clients?
This document summarizes a workshop on understanding, monitoring, and mitigating potential environmental effects of CO2 leakage from carbon capture and storage (CCS) projects in marine and terrestrial environments.
The workshop aimed to identify current research gaps on CO2 leakage effects, issues in current research, and further areas of investigation needed before large-scale CCS deployment. Workshop attendees discussed requirements and barriers for detecting CO2 leaks in marine environments, and knowledge gaps regarding potential onshore and offshore leakage scenarios. Key gaps identified included regional geological knowledge, fault behavior, improved CO2 sensors, and modeling various leakage scenarios. The social aspects of public engagement with CCS were also discussed.
The webinar covered recent regulatory developments in construction and post-construction stormwater management. It discussed changes to the EPA's Construction General Permit including new buffer requirements and timelines for stabilization. It also summarized EPA's proposed rulemaking to strengthen post-construction stormwater requirements and establish national performance standards for new development. Finally, it reviewed federal requirements for stormwater management on federal facilities.
The document discusses the history and present status of the Clean Water Act. It began as the Federal Water Pollution Control Act in 1948 and was amended and expanded in 1972 following highly polluted incidents like the Cuyahoga River catching fire. The Act established the EPA, water quality standards, and the National Pollutant Discharge Elimination System. Recent Supreme Court cases have created uncertainty around the definition of "navigable waters," weakening the Act's protections. The future effectiveness of the Act depends on clarifying these definitions and addressing challenges like infrastructure funding and pollution.
A survey conducted in fall 2013 of members of the Marcellus Shale Safe Drilling Advisory Commission members on their reaction to the draft "best practices" document produced by the commission. The survey was meant to pinpoint areas of disagreement for future discussion at Commission meetings. The responses show members to be careful, considerate, and deliberative about shale drilling. It also shows they are in favor of it and believe it can move forward with certain safeguards in place.
The document summarizes a meeting between the Blue Grass Chemical Agent-Destruction Pilot Plant team and the Secondary Waste Working Group. The meeting provided updates on cyanide mitigation treatment and worker protection. Presentations were given on hazard assessments, cyanide challenges, and safety protocols. Questions were asked about spill response procedures, facility air flows, and monitoring worker stress. The group also discussed potential recycling of secondary waste metals and an upcoming National Research Council study on off-site hydrolysate shipment.
ESI has over 15 years of experience providing environmental consulting services in Southeast England. They opened a new office in Reading in 2011 to increase their support to clients in the region. ESI specializes in water management, land quality, landfill/waste management, and ground source energy. This document highlights some of ESI's key service areas and provides case studies of projects they have completed in Southeast England.
The document discusses the requirements for Oil Spill Prevention Control and Countermeasure (SPCC) Plans under the Clean Water Act. It provides an overview of the regulations and outlines what facilities need to include in their SPCC Plans, such as inventory of oil storage containers and equipment, procedures for oil spill response, inspection schedules, and training for employees. It emphasizes that the goal of SPCC Plans is to minimize the potential for oil releases to waters of the United States such as rivers, lakes, and wetlands.
05 shoemaker us german workshop presentationleann_mays
Sandia National Laboratories manages and operates the Waste Isolation Pilot Plant (WIPP) for the US Department of Energy. WIPP is located in salt deposits near Carlsbad, New Mexico and is intended for permanent disposal of defense-related transuranic radioactive waste. WIPP's safety case demonstrates that over 10,000 years, cumulative radioactive releases from WIPP will remain below regulatory limits through multiple conservative performance assessment scenarios and the inherent stability of the salt repository. While some modeling assumptions may become less conservative over time, WIPP's compliance is ensured by its host geology and rigorous safety analysis process.
This document provides information and guidance on protesting a Texas Railroad Commission (RRC) injection well permit application on behalf of a Groundwater Conservation District (GCD). It outlines the 15-day deadline to request an RRC hearing after a permit application is published. It also recommends that GCDs adopt rules authorizing the general manager to seek party status in permit hearings and negotiate with applicants. Key hearing issues include whether the well will adequately protect groundwater and be confined to the permitted disposal zone. The document suggests items for potential settlement with applicants, such as enhanced containment and cement bond logs.
Complaint to Advertising Standards Canada - 2010LOWaterkeeper
Waterkeeper submitted a complaint about the Power Workers Union's claim that nuclear power is "emissions-free". This complaint documents a few of the ways nuclear power plants do release contaminants into the air. ASC upheld Waterkeeper's complaint.
Investing in wastewater infrastructure to restore the Great LakesLOWaterkeeper
On May 26, 2016 Krystyn Tully spoke at the Ontario Coalition for Sustainable Infrastructure's annual Forum. Asked to address the topic of "big things happening in Ontario" in six minutes, Krystyn told the audience that people are coming back to the Great Lakes in droves. She challenged them to think of wastewater system improvements that would ensure all Great Lakes waters are clean for every person in every community so that our urban communities can prosper.
ejercicios para mejorar condicionamiento fisico ArleyDuque
El documento describe diferentes ejercicios para fortalecer los músculos, incluyendo curl de bíceps isométrico, caminata lateral en posición de tabla, flaket por terreno, y correr en la arena y colinas. Estos ejercicios mejoran la energía, rapidez y fuerza muscular, especialmente en los glúteos, piernas y parte superior del cuerpo.
Letter: Request for a 20-year review of the Nuclear Safety and Control ActLOWaterkeeper
including Greenpeace, Waterkeeper, EcoJustice, and the Canadian Environmental Law Association are asking Prime Minister Trudeau for a full parliamentary review of the law, the Nuclear Safety and Control Act.
Lake Ontario Waterkeeper's submission on the Navigation Protection Act ReviewLOWaterkeeper
On Wednesday, November 30, 2016, Lake Ontario Waterkeeper submitted comments to the Government of Canada on changes made to the Navigation Protection Act (formerly, "Navigable Waters Protection Act") – one of Canada’s oldest laws. Until 2009, the law remained substantially unchanged, when sweeping changes to the legislation eliminated protections for the majority of navigable waters in Canada and focused the law on specific acts of navigation on waters of interest to the federal government. Waterkeeper was the only environmental organization to participate in the committee review prior to the 2009 changes, and again in 2012. Here are Waterkeeper's recommendations for the Standing Committee on Transport, Infrastructure and Communities’ consideration.
Letter: 47 groups ask Federal Government to repeal changes to the Fisheries Act.LOWaterkeeper
The letter requests that the Minister of Fisheries, Oceans and the Canadian Coast Guard initiate a two-phased approach to updating the Fisheries Act. The first phase would immediately reinstate previous habitat protections and improve enforcement. The second phase would begin consultations on incorporating modern safeguards within two years. It is signed by representatives of environmental organizations and scientists seeking stronger protections for Canada's fish habitats and populations.
Lake Ontario Waterkeeper's Darlington Relicensing Hearing presentation- Novem...LOWaterkeeper
This is Lake Ontario Waterkeeper's presentation at the Darlington Relicensing Day 2 Hearing in Courtice, Ontario. Represented by Pippa Feinstein and Lake Ontario Waterkeeper's Public Interest Articling Fellow, Tristan Willis.
Submission of Lake Ontario Waterkeeper - Relicensing hearing before the Canad...LOWaterkeeper
Cameco Corporation (Cameco) is currently applying to renew its Fuel Facility Operating Licence FFOL-3631.0/2017 (the licence) for its Port Hope Conversion Facility (PHCF). This licence was issued on February 28, 2012, (valid from March 1, 2012) and will expire February 28, 2017.
The requested licence is for a ten-year period and would permit Cameco to continue to produce nuclear fuel for reactors in Canada and abroad. Currently, the facility is permitted to process and produce up to 2,800 tonnes of uranium as UO2 which is used for CANDU reactor fuel and up to 12,500 tonnes of UF6 which is exported for processing into light water reactor fuel. The requested licence would also permit Cameco to make significant changes to its facility, renovating some buildings, decommissioning others, and building entirely new facilities on the
PHCF site. These changes collectively comprise its Vision in Motion (VIM) project. More specifically, Cameco’s proposed VIM project involves:
• Removing up to 150,000 cubic metres (m3) of radioactive contaminated waste. This includes contaminated soil excavation, “legacy” drummed waste generated at the facility before 1988, and rubble from demolished older buildings at the PHCF site and Center Pier). This waste will be taken to Canadian Nuclear Laboratories’ secure long-term waste management facility in Port Hope;
• Removing 11 older or under-utilized buildings from the PHCF site and Center Pier;
• Constructing of 4 new buildings and the refurbishment or modification of 7 other buildings at the site;
• Installing of new pump and treat wells to address the groundwater contamination that will remain under the PHCF site after VIM is completed;
• Improving the facility’s stormwater management infrastructure; and
• Moving the eastern fence-line of the PHCF away from the harbour to help facilitate greater public access to Port Hope’s waterfront.
Waterkeeper has been involved in several other past decision-making processes before the CNSC concerning this facility, including its environmental assessment (EA) under the Canadian Environmental Assessment Act, 1992, as well as its application for a Certificate of Approval from the then Ontario Ministry of Environment for its industrial sewage permit. During these processes, Waterkeeper expressed concerns regarding the facility’s poor stormwater management, the need for better cooling water technology, and the need for better environmental monitoring and public communication.
In the last five years, some progress has been made to ensure the initiative supports a more swimmable, drinkable, and fishable Lake Ontario. But more work is still needed.
Lake Ontario Waterkeeper's comments on review of changes to the Fisheries ActLOWaterkeeper
The document is a submission from several Canadian waterkeeper organizations to the Standing Committee on Fisheries and Oceans regarding proposed changes to the Fisheries Act. It outlines 9 recommendations for improving protections for fish and fish habitat in the new Act. Key points include restoring broad protections for fish habitat, simplifying rules against pollution, embracing the precautionary principle, ensuring Fisheries and Oceans Canada remains accountable, and giving the Act an explicit purpose of protecting all fish and fish habitat in Canada.
Submission: Recovery Strategy for the American Eel in OntarioLOWaterkeeper
A final Recovery Strategy for the American Eel has been submitted to the Government of Ontario. The current public consultation opportunity seeks public input that will inform the
government’s response to this Strategy. Due to Lake Ontario Waterkeeper’s unique expertise, our organization is perfectly primed to comment on the Strategy and guide the government response.
We urge the Government of Ontario, in their response to the Strategy, to affirm the three broad principles outlined in our submission. First, that the American Eel is important to Ontario’s ecosystems, including those of Lake Ontario. Second, that the Strategy is an important step to protecting the American Eel and promoting swimmable, drinkable, fishable watersheds. Third, that coordinated action by both provincial and federal governments is required in order to achieve the Strategy’s objectives.
Comments on proposed Canadian microbeads regulationsLOWaterkeeper
The Federal Government is currently developing regulations to eliminate the use of microbeads in personal care products. In February, the government made its proposed regulations available to the public for comment. Lake Ontario Waterkeeper, Ottawa Riverkeeper, Fraser Riverkeeper and North Saskatchewan Riverkeeper submitted joint comments on the proposed regulations. Read them here.
Comments on adding microbeads to Schedule 1 of CEPA 1999 – September 30, 2015LOWaterkeeper
These are the comments by Lake Ontario Waterkeeper, Ottawa Riverkeeper, North Saskatchewan Riverkeeper, and Fraser Riverkeeper on the Order adding microbeads to Schedule 1 of CEPA 1999.
Waterkeeper submission: Review of Ontario’s Environmental Bill of Rights and ...LOWaterkeeper
Waterkeeper submitted these recommendations to the Environmental Commissioner of Ontario in response to the Ministry of the Environment and Climate Change’s call for public comments as part of its review of Ontario’s Environmental Bill of Rights (“EBR”).
The EBR is a uniquely Ontarian, powerful tool to bring citizens, government, and business together to protect the province’s environment. Over the years, issues with the EBR and its implementation have emerged. This review is a welcome opportunity to improve the EBR without undermining or compromising original protections.
One aspect of the EBR’s importance that deserves highlighting is its value to charities. Political activity by charities is limited. Partisan activities are prohibited. Tools such as those created under the EBR are often the sole means by which charities can
participate in government decision-making.
Similarly, the EBR is a safeguard for Ontario residents who may not have geographic, political, social, or professional access to government. As such, this review is an important opportunity to re-assert the authority of the EBR when it comes to decision-making in Ontario.
In addition to these comments, Lake Ontario Waterkeeper / Swim Drink Fish Canada wholly endorses the detailed comments submitted on November 4, 2016 by the Canadian Environmental Law Association (“CELA”).
Waterkeeper's Review of CNSC's Regulatory Oversight Report for Uranium and Nu...LOWaterkeeper
The CNSC asked Swim Drink Fish Canada/Lake Ontario to look into its 2016 Regulatory Oversight Report for
Uranium and Nuclear Substance Processing Facilities in Canada. CNSC provided funding for the review.
Lake Ontario Waterkeeper's submissions for Pickering Waste Management Facilit...LOWaterkeeper
Ontario Power Generation (OPG) is currently applying to renew its Waste Facility Operating Licence for its Pickering Waste Management Facility (PWMF). The current licence
will expire March 31, 2018.
OPG is currently requesting a licence term of approximately 11 years that will expire on August 31, 2028.
Waterkeeper's written submissions discuss several identified concerns with the PWMF and provide
recommendations for improving the facility’s planned expansion and routine operations.
Submission of Lake Ontario Waterkeeper - Reviewing Canadian Nuclear Safety Co...LOWaterkeeper
The Port Hope Area Initiative (PHAI) is an internationally significant undertaking. It is the biggest radioactive waste clean-up project in Canadian history, and involves one of the largest nuclear waste holding facilities in North America. The PHAI is comprised of two distinct projects: the Port Hope waste relocation project (“Port Hope Project”), and the Port Granby waste relocation project (“Port Granby Project”). Together, both projects seek to clean up a combined two-million cubic metres (m3) of low-level radioactive waste from various sites across Port Hope and Port Granby.
The Port Hope Project involves excavating 1,223,250 m3 of historic radioactive waste from several sites around the town of Port Hope to a Long-term Waste Management Facility (PH LTWMF) just north of the community. The project was subject to an environmental assessment (EA) under the Canadian Environmental Assessment Act, 1992 (CEAA, 1992) which was conducted from 2001 to 2007. In 2009, the CNSC granted a five-year Nuclear Waste Substance Licence to Atomic Energy Canada Limited (AECL) to implement the project. In 2012, AECL applied to have its licence extended for ten years. This was granted by the Canadian Nuclear Safety Commission (CNSC), making the current licence valid until December 31, 2022.
The Port Granby Project involves the removal of 450,000 m3 of historic radioactive waste from the existing and poorly contained Port Granby waste management facility to a new above ground waste management facility (the PG LTWMF) 700 metres north of the Lake Ontario shoreline. The Port Granby Project was also subject to a federal EA under CEAA, 1992 and the project was approved in 2009. After a public hearing in September 2010, the CNSC granted AECL a ten-year licence to implement this project.
In the last five years, some progress has been made to ensure the initiative supports a more swimmable, drinkable, and fishable Lake Ontario. But more work is still needed.
Swim Drink Fish's Preliminary Submission on Pickering Nuclear Generating StationLOWaterkeeper
Here is Swim Drink Fish’s preliminary submission to the CNSC Tribunal as it reviews the PNGS licence conditions. OPG withholds vital information about the PNGS’ environmental impacts needed for Swim Drink Fish’s complete submission.
1. ESI provided a conceptual model of the London Basin aquifer for the Environment Agency, advancing understanding of its hydrogeology and addressing issues like abstraction sustainability.
2. ESI served as an expert witness for a petrol retailer, advising on risks from a diesel spill and demonstrating remediation addressed contamination risks.
3. ESI assessed the impact of over 30 groundwater abstractions on key streams for Severn Trent Water, quantifying low flow issues to identify remedial options.
4. ESI minimised environmental and reputational liabilities for a company from a 40,000 liter diesel leak by rapidly investigating and containing the spill.
This document discusses cooling water options for new nuclear power stations in the UK. It provides an overview of different cooling system designs, including direct once-through systems and various cooling tower options. It evaluates the environmental impacts of water abstraction and thermal discharges for each system. While direct cooling can have impacts on aquatic life from intake and discharge, the document finds it can be considered best available technology if best practices for design, mitigation and compensation are followed. Site-specific factors will also determine the suitability of different options.
This document provides an evaluation report of Rhode Island's pump-out facilities from 2014. It discusses the background and history of no discharge areas, describes the inspections of 67 facilities, and reports the results. Key findings include: 63 of 68 facilities inspected were functional, with only 1 failing the pump test of emptying 5 gallons in under a minute. The report provides recommendations to improve the program and compliance with protecting Rhode Island waters.
The document discusses the environmental obligations and requirements for contractors conducting exploration activities for marine minerals in the international seabed area. It outlines 7 key study areas that must be addressed in baseline environmental studies to gather oceanographic and environmental data: physical oceanography, geology, chemical oceanography, sediment properties, biological communities, bioturbation, and fluxes to sediment. It also discusses the requirements for an environmental impact assessment, environmental impact statement, and environmental management and monitoring plan that must be submitted to obtain exploitation contracts and mitigate environmental impacts.
Rabbit Branch at Collingham Drive Stream Restoration Information Meeting - Ju...Fairfax County
The goal of the stream restoration project is to build an ecologically sound restoration that balances water quality benefits with riparian function and park user experience.
The Office of River Protection is working to treat over 53 million gallons of radioactive and chemical tank waste stored in underground tanks at Hanford by operating the Waste Treatment Plant to immobilize the waste in glass by 2047 and close the tank farms by 2052, while preparing the tank waste feed delivery systems and continuing tank waste retrieval efforts to support the plant once operational in 2019. The document outlines the budget request and status of ongoing projects and initiatives to transition Hanford's tank waste from storage to treatment and risk reduction.
This document provides an Environmental Management Framework (EMF) for subprojects under the Regional Disaster Vulnerability Reduction Project (RDVRP) in St. Vincent and the Grenadines. The EMF outlines screening procedures and mitigation measures to minimize environmental impacts. Subprojects include repairing infrastructure, retrofitting buildings, slope stabilization, coastal protection, and road rehabilitation. The EMF describes the local environment and identifies potential positive and negative impacts such as reduced disaster risk but also construction disturbance. It establishes a screening process to determine study and mitigation requirements for each subproject based on complexity. A generic Environmental Management Plan is also provided to guide simple civil works. The EMF is the tool to help ensure subprojects comply with
The document discusses two projects in Egypt: the Alexandria Integrated Coastal Zone Management Project and the Pollution Reduction Measures for Lake Maryute Project. It provides details on project components, objectives, status updates, and monitoring plans. The overall goal is to reduce water pollution entering the Mediterranean Sea from Lake Maryute through coastal zone planning, institutional capacity building, and small-scale pollution reduction interventions.
Do not include any personal information as all posted material on this site is considered to be part of a public record as defined by section 27 of the Municipal Freedom of Information and Protection of Privacy Act.
We reserve the right to remove inappropriate comments. Please see Terms of Use for City of Toronto Social Media Sites at http://www.toronto.ca/e-updates/termsofuse.htm.
This document proposes building an integrated ocean carbon observing system to monitor ocean carbon uptake on an annual basis. Currently, ocean observations are funded primarily through research projects rather than operations. An operational system using existing technologies like ships, floats, gliders and satellites could provide early warnings if ocean carbon uptake changes, allowing adjustments to emission reduction plans to reduce costs. The document invites stakeholders to help develop a plan and secure long-term funding to realize this "Ocean Carbon Moonshot" vision. Estimates suggest the return on investment for such a system could be 50-100 times the costs.
The document provides an environmental impact assessment for the proposed rehabilitation of the Liberia Petroleum Refinery Company. It identifies key issues raised during stakeholder consultations, including concerns about the current site location, waste management, oil spills, air quality, and community benefits. It describes the project, which involves rehabilitating storage tanks and installing new pipelines, tanks, loading racks, and other infrastructure. Specialist studies were conducted on visual impacts, air quality, waste management, water resources, flora and fauna, and socioeconomic impacts. The document recommends applying international standards to storage tanks and piping systems to improve integrity and safety. It also recommends remediation measures, installing sprinklers and firefighting equipment, and re
The document summarizes recent regulatory actions, legislation, and legal cases related to water regulation. It notes that three oil production facilities in Louisiana were fined in August 2012 for violations of SPCC regulations, including failures to conduct inspections, provide documentation of training, and ensure adequate secondary containment. It also references two bills in Congress related to water regulation and summarizes three legal cases, including one upholding imprisonment and fines for Clean Water Act violations.
The document provides information about the Office of River Protection's budget and plans for fiscal year 2013. It discusses treating and disposing of radioactive waste stored in underground tanks at Hanford, continuing construction of the Waste Treatment Plant, and meeting regulatory milestones for emptying waste tanks and processing waste by certain deadlines. The budget request supports ongoing tank farm operations, waste retrieval projects, and construction and commissioning of the Waste Treatment Plant facilities.
The document discusses a proposed sewer expansion project by the Steuben Lakes Regional Waste District and opposition to the project from a citizens group. It summarizes various studies from the 1970s concluding septic systems were effectively treating wastewater and not negatively impacting water quality. The EPA recommended a limited alternative approach rather than a large sewer system, but the District approved the larger sewer plan against the EPA's recommendation.
Similar to Submission by Lake Ontario Waterkeeper for the Darlington Nuclear Relicensing Day 2 Hearing (20)
ENVIRONMENT~ Renewable Energy Sources and their future prospects.tiwarimanvi3129
This presentation is for us to know that how our Environment need Attention for protection of our natural resources which are depleted day by day that's why we need to take time and shift our attention to renewable energy sources instead of non-renewable sources which are better and Eco-friendly for our environment. these renewable energy sources are so helpful for our planet and for every living organism which depends on environment.
Kinetic studies on malachite green dye adsorption from aqueous solutions by A...Open Access Research Paper
Water polluted by dyestuffs compounds is a global threat to health and the environment; accordingly, we prepared a green novel sorbent chemical and Physical system from an algae, chitosan and chitosan nanoparticle and impregnated with algae with chitosan nanocomposite for the sorption of Malachite green dye from water. The algae with chitosan nanocomposite by a simple method and used as a recyclable and effective adsorbent for the removal of malachite green dye from aqueous solutions. Algae, chitosan, chitosan nanoparticle and algae with chitosan nanocomposite were characterized using different physicochemical methods. The functional groups and chemical compounds found in algae, chitosan, chitosan algae, chitosan nanoparticle, and chitosan nanoparticle with algae were identified using FTIR, SEM, and TGADTA/DTG techniques. The optimal adsorption conditions, different dosages, pH and Temperature the amount of algae with chitosan nanocomposite were determined. At optimized conditions and the batch equilibrium studies more than 99% of the dye was removed. The adsorption process data matched well kinetics showed that the reaction order for dye varied with pseudo-first order and pseudo-second order. Furthermore, the maximum adsorption capacity of the algae with chitosan nanocomposite toward malachite green dye reached as high as 15.5mg/g, respectively. Finally, multiple times reusing of algae with chitosan nanocomposite and removing dye from a real wastewater has made it a promising and attractive option for further practical applications.
Microbial characterisation and identification, and potability of River Kuywa ...Open Access Research Paper
Water contamination is one of the major causes of water borne diseases worldwide. In Kenya, approximately 43% of people lack access to potable water due to human contamination. River Kuywa water is currently experiencing contamination due to human activities. Its water is widely used for domestic, agricultural, industrial and recreational purposes. This study aimed at characterizing bacteria and fungi in river Kuywa water. Water samples were randomly collected from four sites of the river: site A (Matisi), site B (Ngwelo), site C (Nzoia water pump) and site D (Chalicha), during the dry season (January-March 2018) and wet season (April-July 2018) and were transported to Maseno University Microbiology and plant pathology laboratory for analysis. The characterization and identification of bacteria and fungi were carried out using standard microbiological techniques. Nine bacterial genera and three fungi were identified from Kuywa river water. Clostridium spp., Staphylococcus spp., Enterobacter spp., Streptococcus spp., E. coli, Klebsiella spp., Shigella spp., Proteus spp. and Salmonella spp. Fungi were Fusarium oxysporum, Aspergillus flavus complex and Penicillium species. Wet season recorded highest bacterial and fungal counts (6.61-7.66 and 3.83-6.75cfu/ml) respectively. The results indicated that the river Kuywa water is polluted and therefore unsafe for human consumption before treatment. It is therefore recommended that the communities to ensure that they boil water especially for drinking.
Recycling and Disposal on SWM Raymond Einyu pptxRayLetai1
Increasing urbanization, rural–urban migration, rising standards of living, and rapid development associated with population growth have resulted in increased solid waste generation by industrial, domestic and other activities in Nairobi City. It has been noted in other contexts too that increasing population, changing consumption patterns, economic development, changing income, urbanization and industrialization all contribute to the increased generation of waste.
With the increasing urban population in Kenya, which is estimated to be growing at a rate higher than that of the country’s general population, waste generation and management is already a major challenge. The industrialization and urbanization process in the country, dominated by one major city – Nairobi, which has around four times the population of the next largest urban centre (Mombasa) – has witnessed an exponential increase in the generation of solid waste. It is projected that by 2030, about 50 per cent of the Kenyan population will be urban.
Aim:
A healthy, safe, secure and sustainable solid waste management system fit for a world – class city.
Improve and protect the public health of Nairobi residents and visitors.
Ecological health, diversity and productivity and maximize resource recovery through the participatory approach.
Goals:
Build awareness and capacity for source separation as essential components of sustainable waste management.
Build new environmentally sound infrastructure and systems for safe disposal of residual waste and replacing current dumpsites which should be commissioned.
Current solid waste management situation:
The status.
Solid waste generation rate is at 2240 tones / day
collection efficiently is at about 50%.
Actors i.e. city authorities, CBO’s , private firms and self-disposal
Current SWM Situation in Nairobi City:
Solid waste generation – collection – dumping
Good Practices:
• Separation – recycling – marketing.
• Open dumpsite dandora dump site through public education on source separation of waste, of which the situation can be reversed.
• Nairobi is one of the C40 cities in this respect , various actors in the solid waste management space have adopted a variety of technologies to reduce short lived climate pollutants including source separation , recycling , marketing of the recycled products.
• Through the network, it should expect to benefit from expertise of the different actors in the network in terms of applicable technologies and practices in reducing the short-lived climate pollutants.
Good practices:
Despite the dismal collection of solid waste in Nairobi city, there are practices and activities of informal actors (CBOs, CBO-SACCOs and yard shop operators) and other formal industrial actors on solid waste collection, recycling and waste reduction.
Practices and activities of these actor groups are viewed as innovations with the potential to change the way solid waste is handled.
CHALLENGES:
• Resource Allocation.
Improving the viability of probiotics by encapsulation methods for developmen...Open Access Research Paper
The popularity of functional foods among scientists and common people has been increasing day by day. Awareness and modernization make the consumer think better regarding food and nutrition. Now a day’s individual knows very well about the relation between food consumption and disease prevalence. Humans have a diversity of microbes in the gut that together form the gut microflora. Probiotics are the health-promoting live microbial cells improve host health through gut and brain connection and fighting against harmful bacteria. Bifidobacterium and Lactobacillus are the two bacterial genera which are considered to be probiotic. These good bacteria are facing challenges of viability. There are so many factors such as sensitivity to heat, pH, acidity, osmotic effect, mechanical shear, chemical components, freezing and storage time as well which affects the viability of probiotics in the dairy food matrix as well as in the gut. Multiple efforts have been done in the past and ongoing in present for these beneficial microbial population stability until their destination in the gut. One of a useful technique known as microencapsulation makes the probiotic effective in the diversified conditions and maintain these microbe’s community to the optimum level for achieving targeted benefits. Dairy products are found to be an ideal vehicle for probiotic incorporation. It has been seen that the encapsulated microbial cells show higher viability than the free cells in different processing and storage conditions as well as against bile salts in the gut. They make the food functional when incorporated, without affecting the product sensory characteristics.
Presented by The Global Peatlands Assessment: Mapping, Policy, and Action at GLF Peatlands 2024 - The Global Peatlands Assessment: Mapping, Policy, and Action
Optimizing Post Remediation Groundwater Performance with Enhanced Microbiolog...Joshua Orris
Results of geophysics and pneumatic injection pilot tests during 2003 – 2007 yielded significant positive results for injection delivery design and contaminant mass treatment, resulting in permanent shut-down of an existing groundwater Pump & Treat system.
Accessible source areas were subsequently removed (2011) by soil excavation and treated with the placement of Emulsified Vegetable Oil EVO and zero-valent iron ZVI to accelerate treatment of impacted groundwater in overburden and weathered fractured bedrock. Post pilot test and post remediation groundwater monitoring has included analyses of CVOCs, organic fatty acids, dissolved gases and QuantArray® -Chlor to quantify key microorganisms (e.g., Dehalococcoides, Dehalobacter, etc.) and functional genes (e.g., vinyl chloride reductase, methane monooxygenase, etc.) to assess potential for reductive dechlorination and aerobic cometabolism of CVOCs.
In 2022, the first commercial application of MetaArray™ was performed at the site. MetaArray™ utilizes statistical analysis, such as principal component analysis and multivariate analysis to provide evidence that reductive dechlorination is active or even that it is slowing. This creates actionable data allowing users to save money by making important site management decisions earlier.
The results of the MetaArray™ analysis’ support vector machine (SVM) identified groundwater monitoring wells with a 80% confidence that were characterized as either Limited for Reductive Decholorination or had a High Reductive Reduction Dechlorination potential. The results of MetaArray™ will be used to further optimize the site’s post remediation monitoring program for monitored natural attenuation.
Climate Change All over the World .pptxsairaanwer024
Climate change refers to significant and lasting changes in the average weather patterns over periods ranging from decades to millions of years. It encompasses both global warming driven by human emissions of greenhouse gases and the resulting large-scale shifts in weather patterns. While climate change is a natural phenomenon, human activities, particularly since the Industrial Revolution, have accelerated its pace and intensity
Epcon is One of the World's leading Manufacturing Companies.EpconLP
Epcon is One of the World's leading Manufacturing Companies. With over 4000 installations worldwide, EPCON has been pioneering new techniques since 1977 that have become industry standards now. Founded in 1977, Epcon has grown from a one-man operation to a global leader in developing and manufacturing innovative air pollution control technology and industrial heating equipment.
Epcon is One of the World's leading Manufacturing Companies.
Submission by Lake Ontario Waterkeeper for the Darlington Nuclear Relicensing Day 2 Hearing
1. Submissions of Lake Ontario Waterkeeper
to the
Canadian Nuclear Safety Commission
Re: Relicensing hearing for the
Darlington Nuclear Generating Station
and
Notice of Public Hearing,
Ref. 2015-H-04
September 28, 2015
Submitted to Adam Levine
via email: Adam.Levine@cnsc-ccsn.gc.ca
Cc: interventions@cnsc-ccsn.gc.ca and pfp@cnsc-ccsn.gc.ca
2. 2
EXECUTIVE SUMMARY
Ontario Power Generation (“OPG”) is seeking a 13-year licence that will allow it to
operate and refurbish the Darlington Nuclear Generating Station in Clarington, Ontario
(DNGS). The DNGS was built in the 1980s and is among the largest power plants in
North America and within the top 25 globally. If the Canadian Nuclear Safety
Commission (“the Commission”) approves OPG’s request for this 13-year licence, then
the plant’s life will be extended until 2055.
OPG formally notified the CNSC of its intention to refurbish the DNGS in 2011, and a
screening level environmental assessment process began. The “screening”
assessment was the lowest level of environmental assessment available under
Canadian law at the time, offering the least scrutiny, public participation, and expert
review. After the publication of the Draft Environmental Assessment Screening Report
– Refurbishment and Continued Operation of the Darlington Nuclear Generating
Station, Lake Ontario Waterkeeper (“Waterkeeper”) participated in the review process.
Waterkeeper raised a number of concerns, most focusing on the impacts of
Darlington’s cooling water system on the aquatic ecosystem. Based on its review of
the draft, Waterkeeper submitted that a more rigorous environmental assessment
process was warranted: a “review panel” under Canadian environmental assessment
law. This recommendation was ignored, and only minor adjustments were made to the
draft Environmental Assessment Screening Report before its release.
Waterkeeper continues to have concerns about the DNGS’s current and future impact
on Lake Ontario. Waterkeeper has carefully examined documents related to this
licensing hearing, including the Environmental Assessment Screening Report, its
supporting technical documents, and the documents relating to OPG’s Fisheries and
Oceans Canada (“DFO”) authorization. After reviewing this information, it is apparent
the current plan does not make adequate protection for the environment. The
Commission cannot issue a 13-year licence unless deficiencies in the plan are
addressed.
Waterkeeper recommends that Commission licence the DNGS for not longer than
one year. A one-year licence would give OPG sufficient time to: 1) determine how it
3. 3
will comply with its DFO authorization; 2) develop and implement programs to monitor
impingement, entrainment and stormwater runoff; and 3) develop a plan for ensuring
that water quality onsite and near-site consistently meets all water quality standards.
Specifically, Waterkeeper is concerned by the following three (3) problems and offers
the related six (6) necessary corrective measures:
PROBLEM (a): The DNGS has failed to make adequate provisions to protect
aquatic biota.
This is apparent from:
● The large numbers of fish, fish eggs, fish larvae, invertebrates and plankton that
the DNGS continues to impinge and entrain;
● The absence of a proper impingement and entrainment monitoring program that
is required to predict future trends and understand the project's impact on
endangered species;
● OPG’s failure to recognize and account for the fact that Lake Ontario’s
ecosystems are in a state of flux;
● The DNGS’s history of non-compliance with the Fisheries Act; and,
● The inability of the DNGS to comply with its current DFO authorization.
→ CORRECTIVE MEASURE (a)(i): The Commission should require OPG to
develop and implement a robust impingement and entrainment monitoring program for
the DNGS.
→ CORRECTIVE MEASURE (a)(ii): The Commission should require OPG to
immediately review available impingement and entrainment mitigation options and
determine how it will comply with its current DFO authorization.
PROBLEM (b): The DNGS has failed to make adequate provisions to minimize
surface water pollution.
4. 4
This is apparent from:
● The DNGS’s history of stormwater pollution. Existing stormwater data indicates
that stormwater running off the DNGS site routinely exceeds Provincial Water
Quality Objectives (PWQOs), and stormwater samples failed acute lethality
testing in 1996 and 2001;
● The absence of a regular stormwater monitoring program;
● Contaminant concentrations in onsite and near site water bodies that regularly
exceed PWQOs.
→ CORRECTIVE MEASURE (b)(i): The Commission should require OPG to
develop and implement a regular stormwater monitoring regime.
→ CORRECTIVE MEASURE (b)(ii): The Commission should require OPG to take
corrective actions to ensure that onsite and near site water bodies meet PWQOs.
PROBLEM (c): Flaws in the Environmental Assessment Screening Report have
deprived the Commission of the information necessary to assess whether the
DNGS has taken adequate measures to protect the environment.
→ CORRECTIVE MEASURE (c)(i): The Commission should not allow refurbishment of
the DNGS to begin until the flaws in the Environmental Assessment Screening Report
are addressed.
→ CORRECTIVE MEASURE (c)(ii): If the CNSC does issues OPG a general
operating licence, it should be for no more than one year, and it should incorporate the
recommendations outlined above.
These problems and corrective measures were identified with the assistance of two
experienced advisors who assisted Waterkeeper in considering the plant’s impact on
local aquatic biota and surface water quality:
● Dr. Richard Seaby of Pisces Conservation is a fisheries biologist with a
doctorate in freshwater ecology from the University of Liverpool. He is a
5. 5
specialist in aquatic ecology and much of his recent work has involved
examining the effects of industrial plants on aquatic ecosystems.
● Kevin Draganchuk of Carpenter Environmental Associates is an Environmental
Engineer whose areas of expertise include designing stormwater treatment and
management systems, stormwater permitting, designing site remediations and
analyzing the operation and design of sanitary sewer systems. He is a registered
Professional Engineer in New York State.
This submission also draws upon relevant findings in expert reports that Waterkeeper
commissioned for previous hearings before the CNSC concerning the proposed
refurbishment of the DNGS and the proposal to build new reactors at the DNGS. These
additional reports were authored by:
● Dr. Peter Henderson of Pisces Conservation, an experienced fisheries biologist
and a leading expert on cooling water intake structures.
● Bill Powers, a pollution control engineer with considerable experience in the
design and evaluation of cooling towers for the power industry. He has provided
engineering testimony in numerous regulatory proceedings, drafted portions of
policy notes related to cooling towers for the Edison Power Research Institute, a
leading energy-industry body, and advised on the feasibility of cooling tower
retrofits at a large number of existing industrial facilities;
6. 6
TABLE OF CONTENTS
EXECUTIVE SUMMARY……………………………………………………………….. 2
BACKGROUND…………………………………………………………………………..10
Lake Ontario Waterkeeper is a charity participating in this process in
the public interest…………………………………………………………………...10
Lake Ontario is an irreplaceable source of life, beauty and recreation…...11
Lake Ontario has a changing, severely stressed ecosystem………………. 11
Durham Region is changing……………………………………………………….13
The DNGS’s continues to kill fish and degrade water quality……………...15
DISCUSSIONS…………………………………………………………………………... 16
Does the DNGS make adequate provisions for the protection of the
Environment?....................................................................................................16
a. The DNGS, as it currently operates, does not make adequate
provisions for the protection of the environment………………....……... 16
a.1. The DNGS has not made adequate provisions to protect
aquatic biota…………………………..………………………………...........17
a.1.1. The DNGS kills large numbers of fish, invertebrates and
plankton…………………………………………………………………....17
a.1.1.1. Impingement…………………………………………………17
a.1.1.2. Entrainment…………………………………………………. 19
7. 7
a.1.2. Old impingement and entrainment data may not be
predictive of future trends………………………………………………. 20
a.1.3. The DNGS has a history of non-compliance with the
Fisheries Act……………………………………………………………… 22
a.1.4. The Commission is obliged to consider the impact that
relicensing the DNGS will have on fish populations and
whether the plant will comply with the Fisheries Act………………… 24
a.1.5. The DNGS will exceed the terms of its DFO authorization…... 26
a.1.5.1.The plant will kill more than 2,200 kilograms of
Age+1 per year………………………………..………………………26
a.1.5.2. The plant may kill species of conservation concern…….29
a.2. The timelines for future impingement and entrainment studies
are not acceptable…………………………………………………………....30
a.2.1. The current monitoring plan will make it impossible to know
whether the DNGS complies with the Fisheries Act or SARA……….31
a.2.2. The current monitoring plan will deprive the Commission
of a complete record in future relicensing hearings…………………. 31
a.2.3. The current monitoring plan will deprive the public of
information it is entitled to be provided with…………………………. 32
b. The DNGS has not made adequate provisions to minimize
surface water pollution…………………………………………………………33
b.1 Stormwater from the DNGS runs directly into Lake Ontario……….. 33
8. 8
b.2 Stormwater from the DNGS fails to comply with federal law or
provincial standards…………………………………………………………. 34
b.3 Stormwater runoff from the DNGS is not regularly monitored……...36
b.4 Contaminant concentrations in onsite and near site waterbodies
exceed Provincial Water Quality Objectives……………………………….36
What terms and conditions, if any, would be required to ensure
adequate provisions for the protection of the environment?.......................37
The following licensing conditions would help to minimize the
plant’s impact on the environment (both necessary and feasible)........ 37
a(i) The Commission should require OPG to develop and
implement a robust impingement and entrainment monitoring
program for the DNGS……………………………………………………….37
a(ii) The Commission should require OPG to immediately review
available impingement and entrainment mitigation options and
determine how it will comply with its current DFO authorization………. 38
b(i) The Commission should require OPG to develop and implement
a regular stormwater monitoring regime…………………………………...39
b(ii) The Commission should require OPG to take corrective actions
to ensure that onsite and near site water bodies meet PWQOs……...... 40
Are there any other issues with this project?................................................40
c. The Environmental Assessment Screening Report is not
sufficient to prove the project makes adequate provision for the
protection of the environment……………………………………………….. 40
9. 9
c.1. The Environmental Assessment Screening Report failed to
properly consider closed cycle cooling - the only technology
that would allow the DNGS to drastically reduce fish kills,
thermal discharge and biocide release……………………………………. 41
c.2. The Environmental Assessment Screening Report’s
methodology for assessing the CCW system’s impact on
aquatic biota was flawed…………………………………………………….42
d. The CNSC has not released the results of the DNGS
accident study conducted by the CNSC staff……………………………...44
e. DNGS has not developed a proper off site emergency plan………… 44
CONCLUSION…………………………………………………………………………… 44
LIST OF APPENDICES…………………………………………………………………. 46
WORKS CITED…………………………………………………………………………...47
10. 10
BACKGROUND
Lake Ontario Waterkeeper is a charity participating in this process in the public
interest.
Lake Ontario Waterkeeper (“Waterkeeper”) is a grassroots environmental organization
that uses research, education, and legal tools to protect and restore the public’s right
to swim, drink, and fish in Lake Ontario. Founded in 2001, Waterkeeper is a non-
political registered charity focusing on research and justice issues in the public interest.
Waterkeeper is responsible for protecting and celebrating the Lake Ontario watershed,
including the wetlands, streams, rivers, and creeks that flow into the lake. Waterkeeper
11. 11
conducts academic, legal, and field research, and shares the findings with the public.
Waterkeeper works with communities to facilitate the use of environmental laws to
protect their rights to swim, drink, and fish.
Waterkeeper participates in legal processes to help ensure that environmental
decisions are made on the basis of sound and tested scientific evidence by
independent decision-makers and in the public interest. We are participating in the
Darlington Nuclear Generating Station (DNGS) relicensing hearing to ensure the
Commission considers the public’s need for a swimmable, drinkable, fishable Lake
Ontario when rendering its decision.
Lake Ontario is an irreplaceable source of life, beauty and recreation.
Despite centuries of upheaval, the Lake Ontario watershed continues to support a
diverse range of animal and plant species. Lake Ontario’s archipelagos, beaches, bays,
tributaries, islands and wetlands provide countless opportunities for swimming,
canoeing, fishing, nature observation and other forms of recreation. For many in the
province, Lake Ontario is the closest, most familiar, waterbody.
Lake Ontario also provides essential ecosystems services to millions of people.
Currently, around 9-million Americans and Canadians depend on Lake Ontario for
drinking water, and this number is expected to grow steadily into the future. Further, as
the population in Southern Ontario continues to increase, and as communities along
Lake Ontario’s shoreline continue to urbanize, the Lake’s value as a public recreational
place will only become more significant. As such, the health of Lake Ontario will remain
essential to the ongoing health and prosperity of Ontario and the entire Great Lakes
region.
Lake Ontario has a changing, severely stressed ecosystem.
The Commission must consider the fragility of Lake Ontario’s ecosystem when making
its decision. The degraded state of the environment in Lake Ontario makes it more
important to protect and restore the lake. Greater caution is required when assessing
the continued impact of fish mortality and pollution on this stressed ecosystem.
12. 12
Lake Ontario is Severely Stressed
The lake is threatened by a number of stressors, most linked to a failure to respect and
nurture it as a finite and essential resource. Historic and ongoing abuse and pollution of
this ecosystem have drastically altered nutrient dynamics, hydrological rhythms,
coastal habitats, water quality, and biological diversity. Many of these changes have
occurred rapidly, and the lake continues to respond to these changes in unpredictable
ways.
In the report on the Darlington New Nuclear Power Plant Environmental Impact
Statement, Dr. Peter Henderson stated, “The Great Lakes are in the midst of a huge
ecological upheaval”.1
He points to the increasing populations of invasive species,
1
P. A. Henderson, “Comments on aquatic issues relating to the proposed New Nuclear Darlington (NND)
13. 13
including zebra mussels, quagga mussels, sea lamprey, and alewife. He noted the
contemporaneous decline in native populations of fish, like the slimy sculpin, and of
amphipod crustaceans, like Diporeia. Diporeia once generated more than 80% of total
benthic production of Lake Ontario and was a critical component of the diets of most
benthic fishes. It’s decline has very significant impacts on the stability of the Lake’s
food web. Further, as the lake’s water clarity changes, there is increased plant growth,
including beds of Cladophora (or green algae) along the shore by the Darlington site.
Lake Ontario’s ecological instability means that predictions about the DNGS’s future
impact must be treated with caution. In the report he prepared for the Darlington
Refurbishment Environmental Assessment process, Dr. Henderson noted that climate
change models have predicted that by 2041-2070 the maximum water temperature
could be 2.5°C above the 1970-2000 norm.2
His report also noted that entrainment and
impingement numbers at the DNGS have varied greatly over time.3
This information
indicates that neither the Lake Ontario ecosystem, nor the DNGS’s impact on it, can be
treated as static.
Durham Region is changing.
Durham Region will not look the same 13 years from now, let alone 40. Ontario’s
Growth plan for the Golden Horseshoe identifies Oshawa as an urban growth center
and the area surrounding the DNGS as a ‘Golden Horseshoe Growth Plan Area’.4
According to the Ontario government’s growth forecasts, there will be an additional
350,000 people living in Durham region by 2031.5
As the areas around Darlington urbanize, Lake Ontario’s role will change. More people
will come to depend on the shoreline near the DNGS as a source of recreation and
natural beauty. Darlington Provincial Park will be one of the largest green spaces in the
2
P. A. Henderson, “Comments on Environmental Studies Relation to the Darlington Nuclear Generating
Station Refurbishment and Continued Operation Project”, prepared for Lake Ontario Ontario
Waterkeeper with reference to the Darlington Nuclear refurbishment EA process, (July 2012) [hereinafter
“Henderson, 2012] at 10.
3
Henderson, 2012 at 6, 8.
4
Ontario Ministry of Infrastructure, “Growth Plan for the Greater Golden Horseshoe, 2006”, (June 2013,
Office Consolidation) [hereinafter “Ontario Growth Plan”] at 61.
5
Ontario Growth Plan at 63.
14. 14
area, and one of the best swimming spots in the summer. The lake will also provide
drinking water to all of Durham’s new inhabitants. The revitalization of Toronto’s
waterfront over the past two decades should serve as a reminder that a community's
connection to the lake can change quickly. As Durham grows, the importance of Lake
Ontario to the community will grow as well.
Ontario’s growth forecasts indicate the area surrounding the DNGS will continue
to grow in the coming decades.
Growth in the Durham region will place further stress on the lake. Sewage and
stormwater runoff are two of the most common sources of water pollution in Canada.
15. 15
As the population of Durham grows, the quantity of stormwater and sewage released
into Lake Ontario will increase. In Ajax, water quality has already been degraded by
massive summer blooms of Cladophora (a type of algae), which may be linked to
phosphorus in effluent from the Duffin Creek wastewater treatment plant.6
The algae is
a significant ecological problem, and already impedes the public’s enjoyment of the
Lakeshore in this area.
Paradoxically, growth will mean not only increased stress on the Lake, but also
increased dependence on a swimmable, drinkable, fishable Lake Ontario. The
Commission must take this into account when examining the impact of the DNGS on
the lake.
The DNGS continues to kill fish and degrade water quality.
The DNGS continues to use once-through cooling technology, despite the fact that it
has been demonstrated to be most detrimental to aquatic ecosystems. The DNGS
Condenser Cooling Water (CCW) system has a maximum flow rate of 155 cubic meters
of water per second7
. This is the equivalent of one Olympic-size swimming pool every
15 seconds. After passing through the reactors this water is returned directly to Lake
Ontario. This process results in the entrainment and impingement of fish and the
release of biocides and other contaminants into the lake. The water discharged into
Lake Ontario is a source of thermal pollution with the potential to degrade surrounding
fish habitat. Thermal plumes from the DNGS have been linked to lower survival rates in
round whitefish embryos.
Stormwater from the DNGS is released directly into Lake Ontario. Although stormwater
is not sampled regularly, some samples taken in 1996 and 2001 failed acute lethality
testing.8
Samples taken in 2010 revealed contaminant concentrations exceeding
6
see: Town of Ajax, “Duffin Creek Water Pollution Control Plant Outfall Environmental Assessment - Part
II Order Request”, (10 February, 2014).
7
Canadian Nuclear Safety Commission and Fisheries and Oceans Canada, “Final Environmental
Assessment Screening Report: The Refurbishment and Continued Operation of the Darlington Nuclear
Generating Station, Municipality of Clarington, Ontario”, (March 2013) [hereinafter “CNSC and DFO EA
Report”] at 19.
8
CNSC and DFO EA Report at 42.
16. 16
Ontario’s Provincial Water Quality Objectives (PWQOs).9
Sampling in 2010 also
revealed that onsite and near site waterbodies are exceeding some PWQOs on a
regular basis.10
PWQOs are target concentrations set by the Ontario government
aimed at protecting human and aquatic life. Although PWQOs are not legal guidelines
per se, the Ontario government has acknowledged that “meeting PWQOs is a minimum
requirement” for ensuring that “the surface waters of the province are of a quality
which is satisfactory for aquatic life and recreation”.11
DISCUSSIONS
Does the DNGS make adequate provisions for the protection of the Environment?
Section 24(4)(b) of the Nuclear Safety and Control Act is explicit that the Commission
shall not relicence a facility unless it “make[s] adequate provision for the protection of
the environment”. OPG bears the onus of demonstrating that the DNGS adequately
protects the environment. If the Commission does not have sufficient information to
conclude that this is the case, or if the information before the Commission does not
lead to this conclusion, the Commission cannot relicence the DNGS.
a. The DNGS, as it currently operates, does not make adequate provisions for
the protection of the environment.
The DNGS has not made adequate provisions to protect aquatic biota or to minimize
surface water pollution. Therefore, the DNGS is unable to satisfy section 24(4)(b) of the
Nuclear Safety and Control Act.
9
CNSC and DFO EA Report at 41.
10
Golder Associates, “Surface Water Environment Technical Support Document Darlington Nuclear
Generating Station Refurbishment and Continued Operation Environmental Assessment”, (December
2011) [hereinafter “Surface Water TSD”] at 56.
11
Ontario Ministry of Environment and Climate Change, “Provincial Water Quality Objectives of the
Ministry of Environment and Energy”, (July, 1994) at 3.1.
17. 17
a.1. The DNGS has not made adequate provisions to protect aquatic biota.
The DNGS’s failure to make adequate provisions to protect aquatic biota is apparent
from the impingement and entrainment data, the plant’s history of non-compliance with
the Fisheries Act, the inadequacy of the current DFO authorization, the continued
threat posed to species of conservation concern, and the lack of robust monitoring
requirements.
a.1.1. The DNGS kills large numbers of fish, invertebrates and plankton.
a.1.1.1. Impingement.
The DNGS’s once-through cooling system kills large numbers of fish, fish larvae and
fish eggs each year. While the porous veneer intake system may help reduce
impingement and entrainment rates, the available data shows that impingement and
entrainment rates are significant.
Existing impingement data suggests that impingement rates have increased at the
DNGS over the last decade. In the report he prepared for the Darlington Refurbishment
Environmental Assessment process, Dr. Henderson concluded that the “most recent
data indicate that fish are becoming impinged in high numbers and biomass”.12
In
2006/07 the weight of fish impinged was estimated to be no more than 893 kg,
whereas by 2010/2011 this number had increased to over 2300 kg, representing the
fate of an estimated 274,931 individual fish.13
The increase in impingement rates is likely due to an increase in round goby and
alewife abundance in the area surrounding the plant. The increase may also be due in
part to new screens that were installed in 2010/11. According to Dr. Henderson’s
report, the new screens may be better at washing impinged fish to the sampling point,
12
Henderson, 2012 at 8.
13
Ontario Power Generation, “Submission to DFO for an Authorization under the Fisheries Act for the
Darlington Nuclear Generating Facility”, (21 August, 2014) [hereinafter “OPG’s Submission to DFO”] at
32.
18. 18
thereby increasing the accuracy of impingement data.14
If this is part of the reason for
the reported increase in impingement rates it would mean that previous data were
underestimating the impact of the DNGS.
The high numbers of alewife and round goby impinged by the DNGS cannot be
dismissed simply because the species are non-native. In its submission to the DFO for
a section 35 authorization, OPG went so far as to claim that the “ongoing removal of
goby biomass through impingement should be regarded as positive”.15
This mindset
indicates OPG’s unacceptable failure to recognize that Lake Ontario is in a state of
ecological upheaval. While the presence of goby and alewife in Lake Ontario may be
detrimental to some native species, they have become a part of Lake Ontario’s
ecology. To ignore these species would be unwise because, as Dr. Henderson has
noted, in the future ‘an ecosystem dependent on round goby and alewife as prey for
large predatory species is quite likely’.16
The fact that Lake Ontario is changing does
not mean it is in less need of protection. Rather, minimizing disturbance will be
essential to allowing the ecosystem to stabilize.
Impingement data indicates that the number of species being impinged has also
increased over the past decade. Sampling in 2006/07 indicated that 8 different species
were impinged. In 2010/11 the impingement study identified 15 different species and
reported an additional 712 fish that were too decayed to identify.17
Although round
goby and alewife constituted over 90% of the species impinged during the 2010/11
study, the fact remains that the plant continues to kill a relatively diverse range of
native and non-native species.18
14
Henderson, 2012 at 7.
15
OPG’s Submission to DFO at 48.
16
Henderson, 2012 at 12.
17
SENES Consultants Limited, “Aquatic Environment Technical Support Document Darlington Nuclear
Generating Station Refurbishment and Continued Operation Environmental Assessment”, (December
2011) [hereinafter “Aquatic Environment TSD”] at 3-16.
18
Aquatic Environment TSD, at 4-18.
19. 19
a.1.1.2. Entrainment.
The most recent entrainment data available for the DNGS is almost 10 years old. These
data come from a 2006 study, which estimated that 605,059 eggs and 6,996,246
larvae were entrained.19
A previous 2004 study estimated that 15,631,833 fish eggs
and 1,201,943 fish larvae were entrained.20
These studies assessed the Equivalent
Adult (Age) Value (EAV) of the entrainment losses to be 1,318 and 11,548 Age-1 fish for
2004 and 2006 respectively.21
EAV is a mathematically-derived value that measures the
reproductive importance of individual fish, eggs and larvae by providing a unit (Age-1)
that is standardized across life-stages (i.e. eggs and larvae have a low Age-1 value,
since very few will survive until adulthood to reproduce, while reproductively mature
adults will have a high Age-1 value).
The limited entrainment data indicate that entrainment rates at the DNGS may be
increasing. Between 2004 and 2006 the EAV values increased by roughly 875%.22
As
with the impingement data, this may be largely due to the increased abundance of
round goby. The variability in the existing entrainment data, along with the absence of
any recent sampling, makes it difficult to comment on current entrainment rates but Dr.
Henderson’s report noted that entrainment rates may increase in the future.23
It is important to note that neither the raw entrainment data or equivalent adult age
values fully describe the impact that entrainment has on the surrounding aquatic
ecosystem. The CCW sucks in immense numbers of planktonic plants and
invertebrates along with fish eggs and larvae. Although survival rates have not been
studied at the DNGS, Dr. Henderson’s report indicates that survival rates for
invertebrates can range between 18 and 66 percent.24
By killing hundreds of
thousands of invertebrates, which have an ecologically significant position in the food
web, the CCW systems takes an additional toll on the surrounding ecosystem.
19
CNSC and DFO EA Report at 89.
20
CNSC and DFO EA Report at 89.
21
CNSC and DFO EA Report at 89.
22
This number was produced using the EAV values found on pg 89 of the CNSC and DFO EA report
(11548/1318 = 8.76*100=875%)
23
Henderson, 2012 at 10.
24
Henderson, 2012 at 9.
20. 20
The available data suggests that impingement and entrainment rates at the DNGS are increasing.
Dr. Henderson’s report also cautions that the equivalent adult age values should be
treated with caution since they are based on various assumptions that may not hold
true for the ecosystem surrounding the DNGS.25
A final problem with these values is
that they fail to account for the fact that fish eggs and larvae are an important
component of Lake Ontario’s already stressed and unstable local food web.26
a.1.2. Old impingement and entrainment data may not be predictive of future
trends.
During Day One of the current relicensing hearing on August 19th, 2015, OPG was
asked by Commission Member Harvey whether there could be any change in lake
conditions that might alter impingement or entrainment rates. OPG stated that they
25
Henderson, 2012 at 9.
26
Henderson, 2010 at 8.
21. 21
“are not anticipating changes”.27
This conclusion is simply not supported by the
entrainment and impingement data, which shows dramatic variance in impingement
and entrainment rates over the past decade. As mentioned above, between 2004 and
2006, the EAV for loss due to entrainment increased by roughly 875%. The estimated
biomass of fish impinged increased by over 200% between sampling conducted in
2006/07 and 2010/11. Given these well documented increases in impingement and
entrainment rates, it is highly problematic that OPG does not anticipate future changes.
These indications that impingement and entrainment rates are increasing cannot be
ignored. At the same time, given Lake Ontario’s ecological instability, and the limited
availability of entrainment and impingement data, it is difficult to predict future trends
with any degree of certainty. Lake Ontario is a severely stressed ecosystem in the
midst of ecological upheaval. The introduction and proliferation of invasive species
(which could potentially include asian carp), climatic warming, eutrophication and
pollution will all continue to alter Lake Ontario’s ecosystems during the refurbishment
period. In addition, growth in Durham region also has the potential to significantly
increase local stresses on the lake.
There are also positive changes occurring within Lake Ontario; concentrations of some
contaminants are decreasing, and there are initiatives underway to reintroduce
extirpated species. One example is the Lake Ontario Atlantic Salmon Restoration
project, which OPG has played an important role in supporting. To date, this initiative
has been responsible for the release of 2.5 million salmon into three target tributaries,
one of which is within 30 kilometers of the DNGS.28
A second example of a major
restoration effort is Ontario’s proposed American eel recovery strategy. The strategy
aims to restore eel access to all immediate tributaries on Lake Ontario, increase eel
habitat by 10% every five years and achieve a 50% reduction in cumulative mortality
rates by 2050.29
These two initiatives alone have the potential to bring about significant
27
Canadian Nuclear Safety Commission, “Transcript: Public Hearing on August 19 2015”, [hereinafter
“the transcript”] at 267.
28
Bring Back the Salmon, “Lake Ontario Atlantic Salmon Restoration Program”, viewed on 24
September, 2015 at: http://www.bringbackthesalmon.ca/?page_id=12
29
MacGregor et al., “Recovery Strategy for the American Eel (Anguilla rostrata) in Ontario”, Ontario
Recovery Strategy Series. Prepared for Ontario Ministry of Natural Resources, Peterborough, Ontario,
(2013) at v.
22. 22
changes in the aquatic ecosystems surrounding the DNGS. These initiatives also mean
that the ecological impacts of the DNGS could change drastically over the course of
the proposed 13-year licence period.
Atlantic salmon and American eel are two species that could become more abundant around the DNGS
due to restoration initiatives.
In sum, there are numerous changes, both challenging and beneficial, taking place in
Lake Ontario. What is clear is that predictions about future lake conditions must be
treated cautiously, especially when data are limited. This is consistent with the
precautionary principle which has been developed over decades in Canadian
environmental law. Further, it is of utmost importance that the Commission properly
consider certain data trends that may be inconsistent with OPG’s assertion that
changes in impingement and entrainment rates will not change.
a.1.3. The DNGS has a history of non-compliance with the Fisheries Act.
The DNGS’s CCW system has operated in violation of the Fisheries Act for over two
decades. When Unit 2 of the Darlington plant was brought online in 1990, sections 32
and 35 of the Fisheries Act read:
32. (1) No person shall destroy fish by any means other than fishing except as
authorized by the Minister or under regulations made by the Governor in Council
under this Act.
35. (1) No person shall carry on any work or undertaking that results in the harmful
alteration, disruption or destruction of fish habitat.
23. 23
(2) No person contravenes subsection (1) by causing the alteration, disruption or
destruction of fish habitat by any means or under any conditions authorized by the
Minister or under regulations made by the Governor in Council under this Act.
The DNGS has used the same CCW system since it began operating. Throughout the
1990s and 2000s the CCW system killed thousands of fish each year. It also released
contaminants and created thermal plumes which may have altered or destroyed fish
habitat. During this time the DNGS did not have authorization from the minister to kill
fish or to disrupt or destroy fish habitat. Nor were there any regulations exempting the
DNGS from section 32 and 35 of the Act. It is concerning that the DNGS would illegally
operate its CCW system for such an extended period of time. The scale and
complexity of the DNGS would suggest that this conduct was not merely an oversight.
In 2012 section 32 of the Fisheries Act was repealed and 35 was changed to read as
follows:
(1) No person shall carry on any work, undertaking or activity that results in the harmful
alteration or disruption, or the destruction, of fish habitat.30
(2) A person may carry on a work, undertaking or activity without contravening
subsection (1) if
(a) the work, undertaking or activity is a prescribed work, undertaking or activity,
or is carried on in or around prescribed Canadian fisheries waters, and the work,
undertaking or activity is carried on in accordance with the prescribed conditions;
(b) the carrying on of the work, undertaking or activity is authorized by the
Minister and the work, undertaking or activity is carried on in accordance with the
conditions established by the Minister;
(c) the carrying on of the work, undertaking or activity is authorized by a
prescribed person or entity and the work, undertaking or activity is carried on in
accordance with the prescribed conditions;
(d) the harmful alteration or disruption, or the destruction, of fish habitat is
produced as a result of doing anything that is authorized, otherwise permitted or
required under this Act; or
30
Note that the wording of section 32(1) was changed as of November 25th, 2013.
24. 24
(e) the work, undertaking or activity is carried on in accordance with the
regulations.
Although the new wording of section 35 provided the DNGS with additional options for
compliance, the plant continued to illegally degrade and destroy fish habitat for
another three years. OPG did not apply for a section 35 authorization from DFO until
August 21st, 2014 and the authorization was not granted until June 24th, 2015.
a.1.4. The Commission is obliged to consider the impact that relicensing the DNGS
will have on fish populations and whether the plant will comply with the Fisheries
Act.
During Day One of the relicensing hearing for this matter on August 19th, 2015, Mr.
Richardson stated, on behalf of CNSC staff, that the DNGS’s section 35 DFO
“authorization is not linked to this CNSC licence application and, therefore, it does not
impact or impede the decision for this licence application”.31
This statement is
problematic in at least two respects.
First, this statement indicates that CNSC staff have failed to appreciate that the
Commission must understand whether the DNGS complies with the Fisheries Act in
order to meet its obligation under section 24(4)(b) of the Nuclear Safety and Control
Act. Although the term ‘adequate’ is not defined in Nuclear Safety and Control Act it is
inconceivable that parliament could have intended the standard demanded by section
24(4)(b) to fall anywhere below full regulatory compliance. Therefore, the questions of
whether the DNGS has a section 35 authorization, and whether it will be able to comply
with the terms of the authorization, are highly relevant to the relicensing decision.
Second, this statement does not reflect the terms of the Memorandum of
Understanding (MOU) between CNSC and DFO that was signed on December 16th,
2013. Section 3(a)(ii) of the MOU reads:
31
Transcript at 225.
25. 25
3. PURPOSE
3(a) The Parties will work together in the development of work plans and protocols to
improve the efficiency and effectiveness of regulatory reviews of applications and
decision-making related to the roles and responsibilities of each Party for:
(i) [.....]
(ii) Ensuring that CNSC’s assessment of applications considers the intent and
requirements of the Nuclear Safety and Control Act, the Fisheries Act, and the
Species at Risk Act.
Section 4(c)(i) of the MOU reads:
4. WORK TO BE COORDINATED
(a) [.....]
(b) [.....]
(c) THE CNSC agrees to:
(i) Conduct reviews of licence applications for potential impacts to fish and fish habitats,
to ensure that the assessment process considers the intent and requirements of the
Fisheries Act, SARA, and their associated regulatory and policy frameworks;32
Section 3(a)(ii) and 4(c)(i) of the MOU make it very clear that in rendering its
relicensing decision, the Commission must consider the requirements and intent
of both the Fisheries Act and the Species at Risk Act (SARA). The clear wording
of the MOU contradicts the CNSC staff’s position that the DFO authorization
need not be considered during the relicensing process.
The MOU requires the Commission to take a holistic approach when assessing
the DNGS’s impact on fish populations and endangered species. By requiring
the Commission to consider the intent of the Fisheries Act and SARA, the MOU
makes it clear that the Commission’s obligation is more than a perfunctory
check for regulatory compliance. The Commission must look beyond the
technical requirements of these acts and ask whether there is a risk that the
DNGS will frustrate the overarching goals of either act, namely protecting the
32
Canadian Nuclear Safety Commission and Fisheries and Oceans Canada, “Memorandum of
Understanding Between Fisheries and Oceans Canada and Canadian Nuclear Safety Commission for
Cooperation and Administration of the Fisheries Act and the Species at Risk Act Related to Regulating
Nuclear Materials and Energy Development”, (16 December, 2013) s 3-4.
26. 26
health of Canada’s fish populations and protecting species of conservation
concern from further harm.
a.1.5. The DNGS will exceed the terms of its DFO authorization.
In light of the DNGS’s history of non-compliance, it is important that the Commission
seriously consider whether the DNGS will be able to comply with the terms of its
current section 35 DFO authorization. The authorization reads:
The serious harm to fish likely to result from the proposed work(s), undertaking(s), or
activity(ies), and covered by this Authorization includes.
○ Death of fish: the impingement and entrainment of approximately 1,742 kilograms
to 2,200 kilograms of Age+1 equivalent fish per year than do not include any
aquatic species at risk listed under the Species at Risk Act.33
a.1.5.1. The plant will kill more than 2,200 kilograms of Age+1 per year.
It is important to recognize that 2,200 kg of Age+1 fish is a very different metric than
2200 kg of fish. As discussed above, Age-1 is a mathematically derived metric that
attempts to standardize across life stages. Eggs, larvae and young fish have low Age-1
values, while older fish have higher Age-1 values.
The available data indicates that the DNGS impinges and entrains well over 2,200 kg of
Age+1 fish. According to OPG’s own calculations, the DNGS could be impinging and
entraining approximately 21,537 kg of Age+1 equivalents of fish per year.34
As Dr.
Seaby has noted, this number exceeds the current authorization by nearly 10 times.35
33
Fisheries and Oceans Canada, “Paragraph 35(2)(b) Fisheries Act Authorization”, issued: June 24,
2015, [hereinafter DFO authorization] s. 1.
34
OPG’s Submission to DFO at 55.
35
R. Seaby “Notes on the fishery issues relating to Darlington Nuclear Generating Facility relicensing
(Ontario Power Generation (OPG))”, prepared for Lake Ontario Ontario Waterkeeper with reference to the
DNGS relicensing process, (September, 2015) [hereinafter “Seaby, 2015”] at 6.
27. 27
In its “Submission to DFO for an Authorization under the Fisheries Act for the
Darlington Nuclear Generating Facility” (“OPG’s submission to DFO”), OPG requested
that it be permitted to ‘discount’ the contribution of round goby to impingement and
entrainment biomass.36
OPG also indicated that the entrainment contribution of carp
should be ‘reduced’ since OPG believed that there were problems with the
methodology in its own entrainment studies.37
In OPG’s submission to DFO it estimates
that after round goby is discounted and carp entrainment reduced, the plant impinges
and entrains roughly 1,742 kg of Age+1 equivalents per year.
The DFO authorization does not permit OPG to discount the contribution of round goby
impingement and entrainment, nor does it comment on OPG’s conclusion about carp
36
OPG’s Submission to DFO at 48, 55.
37
OPG’s Submission to DFO at 45-48 ,55.
28. 28
entrainment. As such, the DNGS cannot be held to comply with the terms of its current
DFO authorization.38
According to the DFO authorization:
“The failure to comply with any condition of this Authorization constitutes an offence
under Paragraph 40(3)(a) of the Fisheries Act and may result in charges being laid
under the Fisheries Act”.39
The Commission must not ignore the fact the DNGS has now operated its CCW
system in violation of the Fisheries Act for over two decades. This pattern of chronic
noncompliance indicates a failure of take adequate provisions to protect the
environment.
The DFO was correct to not allow the DNGS to discount the contribution of round goby
biomass to impingement and entrainment numbers. As noted above, round goby’s
status as an invasive species does not negate their potential to become an important
component of the food web. Dr. Seaby has explained that although goby may be
considered a ‘pest’ species, their removal represents a loss of biomass felt by the
entire aquatic community, including ‘species of value’.40
OPG’s request that of carp entrainment estimates be reduced highlights the
inadequacy of the current impingement and entrainment data. In its submission to the
DFO, OPG noted that:
“The methodology used in the 2004 and 2006 studies (OPG 2006 and 2007) is considered
standard practice but is a potential source of a great deal of uncertainty in estimates”.41
OPG cannot argue, on the one hand, that current data are sufficiently reliable to
estimate the CCW system’s future impact on aquatic biota, but on the other, that the
data are such a source of uncertainty that carp entrainment rates should be drastically
reduced. Although OPG does point to other aquatic sampling in the area to support its
38
It should be noted that even if the contribution of carp entrainment is ‘reduced’ OPG will still exceed
the current authorization by a large margin since goby entrainment alone represents 16,021 kg of Age+1
fish.
39
DFO authorization, at 7.
40
Seaby 2015 at 6.
41
OPG’s Submission to DFO, at 47.
29. 29
assertion that carp entrainment estimates in 2006 were high, it is obvious that
uncertainty in the data can cut both ways. The solution is the development of robust
sampling regime, not the selective examination of data points that OPG finds
undesirable.
a.1.5.2. The plant may kill species of conservation concern.
The EA screening report noted that four species of conservation concern have been
recorded in the vicinity of the DNGS: deepwater sculpin, atlantic salmon, lake sturgeon
and American eel.
Dr. Seaby notes that it would ‘certainly be possible’ that the DNGS entrains or
impinges young deepwater sculpin.42
A study in Lake Michigan found that some
sculpin larvae came inshore in December before moving deeper in the water column.43
Sculpin larvae were reported at all depths from 15 meters downward, suggesting that
the DNGS 10 meter intake has the potential to catch sculpin larvae in small numbers.44
In his report, Dr. Seaby notes that the DNGS currently impinges American eel and there
is no reason to expect that this will stop in the future.45
The 2010/11 impingement
study found that one American eel was impinged.46
It is important to recall that the
2010/11 annual impingement figures were derived by extrapolating the data from the
impingement study, so the actual number of eels impinged during this time frame may
have been higher.
The fact that the American eel is not listed under SARA does not relieve the
Commission from considering the impact of the CCW system on this species. The
American eel has been designated as threatened by the Committee on the Status of
Endangered Wildlife in Canada (COSEWIC) and is listed as endangered under Ontario’s
Endangered Species Act. Taking adequate provisions to protect the environment must
42
Seaby 2015 at 7.
43
Seaby 2015 at 7.
44
Seaby 2015 at 7.
45
Seaby 2015 at 7.
46
Aquatic Environment TSD, at 3-16.
30. 30
include protecting this species. It is not acceptable for the DNGS to continue impinging
this imperiled species for the next four decades.
Low impingement rates of American eel or deepwater sculpin could still translate into a
significant ecological impact. Dr. Seaby comments in his report that because species
of conservation concern are typically rare it is difficult to effectively sample for them or
to observe a project’s impact on them.47
At risk species often have small populations
and multiple stressors, meaning that chronic low level sources of mortality like the
DNGS have the potential to impede recovery or contribute to further decline.
a.2. The timelines for future impingement and entrainment studies are not
acceptable.
OPG’s proposal for future monitoring is to conduct 2 year impingement and
entrainment studies once per decade.48
The DFO authorization indicates that
entrainment monitoring will be conducted in 2015/16 and impingement monitoring will
occur in 2024/25.49
The EA follow-up report does not impose any additional
requirements.50
These timelines indicate that OPG will be allowed to follow its
proposed once-per-decade monitoring approach.
OPG’s 10 year monitoring timelines are inappropriate due to the highly dynamic nature
of Lake Ontario’s ecosystems and the changing character of the local environment
surrounding the DNGS site discussed in this submission above. The current monitoring
plan will make it impossible to know whether the DNGS complies with the Fisheries Act
or SARA.
In addition, the once per decade monitoring will deprive the Commission of a complete
factual record on this issue in future relicensing hearings. It will also deprive the public
of important information concerning the quality and ecological integrity of Lake Ontario,
their local waterbody.
47
Seaby, 2015 at 6.
48
OPG’s Submission to DFO, at 36.
49
DFO authorization, at 3.1.1.2, 3.1.1.3.
50
Ontario Power Generation, “Darlington Nuclear Refurbishment and Continued Operation
Environmental Assessment Follow-Up Program”, (September 2013) at 11-12.
31. 31
a.2.1. The current monitoring plan will make it impossible to know whether the
DNGS complies with the Fisheries Act or SARA.
Determining whether the DNGS complies with its current authorization will only be
possible if OPG adopts a regular, robust monitoring regime. This is the only approach
that will allow OPG to know if the CCW system is killing listed species or if it is
exceeding the impingement and entrainment limits set in the authorization. Given that
that the most recent data indicates that the DNGS greatly exceeds impingements and
entrainment limits it is essential that there is monitoring data to show whether the
DNGS is able to take measures to comply with the Fisheries Act.
Dr. Seaby has noted that because of their scarcity, threatened species are difficult to
sample.51
Without regular, long term monitoring, understanding a project's impact on
species that are present in low densities is difficult. The DNGS s 35 authorization
requires that OPG give DFO notice within 72 hours when a listed species is killed.52
Yet this requirement will be all but meaningless if OPG only studies impingement and
entrainment rates once per decade. It is troubling that DFO would support such an
unambitious monitoring plan.
Dr. Seaby states in his report that Lake Ontario is ‘in a state of flux’.53
The existing
impingement and entrainment data reveal that there have been major fluctuations over
short periods of time. The data also raise concerns about whether OPG will be able to
comply with its authorization. All of this indicates a pressing need for regular
monitoring. If the Commission does not require the DNGS to adopt a suitable
monitoring regime it will be very difficult for the Commission to know whether the
DNGS complies with its s 35 authorization over the next decade.
a.2.2. The current monitoring plan will deprive the Commission of a complete record
in future relicensing hearings.
Refurbishing the DNGS’s four reactors will allow the station to operate for another 40
years. Throughout this period the Commission will be responsible for relicensing the
51
Seaby, 2015 at 6.
52
DFO authorization, at 3.2.2.
53
Seaby, 2015 at 11.
32. 32
plant and ensuring that it makes adequate provisions to protect the environment. This
submission has highlighted the essential importance that reliable information plays in
allowing the Commission to understand whether there are adequate provisions in place
to protect the environment. Unless the Commission requires OPG to change its
monitoring plan, it will be forced to make future licensing decisions without a full
understanding of the DNGS’s impact on species of conservation concern, or changes
in impingement and entrainment rates.
a.2.3. The current monitoring plan will deprive the public of information it is entitled
to be provided with.
The preamble of the proposed Great Lakes Protection Act (GLPA) states that “all
Ontarians have an interest in the ecological health of the Great Lakes-St. Lawrence
River Basin”.54
The GLPA recognizes that Ontarians care deeply about Lake Ontario.
Ontario’s Environmental Bill of Rights acknowledges that Ontarians have the right to a
healthful environment.55
Because of Lake Ontario’s position as a source of drinking
water and recreation this right cannot be protected without protecting Lake Ontario.
If Ontarians are not provided with information about the impact that the DNGS has on
the surrounding environment they will not be able to assess whether it affects their
right to a healthful environment, or whether they consider its impact on Lake Ontario to
be acceptable. This information is particularly important for people living in the ever
expanding communities near the DNGS, who may fish in Lake Ontario and rely on the
health of its ecosystems for their future recreation.
OPG is a public company, wholly owned by the Government of Ontario. OPG’s basic
mandate is to provide the public with a service - the generation of electricity. How this
electricity is produced, and where it will come from in the future, are public issues. For
Ontarians to engage with these issues, they need to understand the costs associated
with different forms of electricity production. The Darlington plant produces roughly
54
Bill 66, An Act to protect and restore the Great Lakes-St. Lawrence River Basin, 1st Sess, 41st Leg,
Ontario, 2015 (passed 2nd reading 04 June 2105, currently before the Standing Committee on General
Government).
55
Environmental Bill of Rights, 1993, SO 1993, C-28.
33. 33
20% of Ontario’s electricity - Ontarians are entitled to reliable, long term data about the
impact that the DNGS has on Lake Ontario.
b. The DNGS has not made adequate provisions to minimize surface water
pollution.
b.1 Stormwater from the DNGS runs directly into Lake Ontario.
According to the Surface Water Environment Technical Supporting Document (TSD),
stormwater from the DNGS property is discharged directly into Lake Ontario. The
Surface Water TSD notes that there are 12 sub-catchments on the property and an
additional four that partially border the property.56
These sub-catchments lead to 16
outfalls that all send stormwater directly into Lake Ontario.57
Stormwater runoff from the DNGS is released directly into Lake Ontario
56
Surface Water TSD, at 35.
57
Surface Water TSD, at 35.
34. 34
b.2 Stormwater from the DNGS fails to comply with federal law or provincial
standards.
Stormwater has not been sampled consistently at the DNGS, but the three studies that
were conducted over the last two decades (in 1996, 2001/02 and 2010/11) raise a
number of concerns. Sampling in 1996 showed that several discharge points were
failing acute lethality tests for Daphnia magna and rainbow trout.58
A sample taken from
one of the discharge points in 2001/02 also failed acute lethality testing for Daphnia
magna.59
Stormwater passed acute toxicity tests in 2011, however no chronic lethality
tests were performed.60
All three stormwater studies also detected a
range of contaminants coming of the DNGS
site. In 1996 and 2001 sampling detected
petroleum hydrocarbons in runoff. Petroleum
hydrocarbons were not detected in 2011, but
toluene was found at a concentration that was
nearly double the existing interim Provincial
Water Quality Objective (PWQO).61
In 2001
concentrations of aluminum, iron, lead,
copper, zinc, cadmium and total suspended
solids all exceeded PWQOs during one or
more sampling events.62
In 2010 over 10
different contaminants exceeded PWQOs
during one or more sampling events, these
included: boron, iron, cadmium, copper,
hexavalent chromium, lead, molybdenum,
vanadium, and zinc.63
58
Surface Water TSD, at 42.
59
Surface Water TSD, at 42.
60
Surface Water TSD, at 42.
61
Surface Water TSD, from 44-45.
62
Surface Water TSD, from 45-50.
63
Surface Water TSD, from 45-50.
35. 35
A final concern with stormwater runoff is that the recent monitoring shows tritium levels
that are hundreds of times higher than background levels.64
Although concentrations
remain below the current PWQO of 7000 Bq/L it should be noted that the Ontario
Drinking Water Advisory Council (ODWAC) has recommended that Ontario adopt a
tritium drinking water standard of 20 Bq/L (Ontario’s current drinking water standard
for tritium is also 7000 Bq/L).65
Since Lake Ontario is a crucial source of drinking water
to local inhabitants, and due to the inability of water supply plants to remove tritium, it
is essential that all reasonable efforts are made to minimize tritium discharge into the
lake.
64
CNSC and DFO EA Report, at 85 (the Report notes that tritium levels in some subcatchments are up
to 5,430 Bq/L compared to background levels of 5-26.2 Bq/L in surface water and 23-61Bq/L in
precipitation).
65
Ontario Drinking Water Advisory Council, “Report and Advice on the Ontario Drinking Water Quality
Standard for Tritium”, (21 May, 2009).
36. 36
b.3 Stormwater runoff from the DNGS is not regularly monitored.
Stormwater sampling at Darlington has only been conducted during three intervals
over the past 20 years. The lack of regular stormwater monitoring at the DNGS is
troubling given that past sampling has shown a range of metal concentrations
exceedings PWQOs. Failed acute lethality in 1996 and 2001 suggests that the DNGS
was in violation of section 36 of the Fisheries Act. In light of these findings, it is difficult
to understand why the DNGS has not developed a regular storm water monitoring
program.
b.4 Contaminant concentrations in onsite and near site waterbodies exceed
Provincial Water Quality Objectives.
The surface water technical supporting document
indicates that contaminant concentrations in several
onsite and near site water bodies have exceeded
PWQOs and interim PWQOs on one or more
sampling occasions. Coot’s Pond has consistently
exceeded the PWQO for pH during the summer
months.66
Samples taken from Coot’s Pond have
also exceeded the PWQO for unionized ammonia
and iron, and the interim PWQO for phosphorus.67
Samples from SWM pond, Tree Frog Pond and
Darlington Creek have exceeded the PWQO for
cobalt and iron on one or more sampling
occasions.68
In addition, samples from SMW pond in
2007 showed chromium levels above the PWQO,
and samples from Darlington Creek and Tree Frog pond in 2007 exceeded the interim
PWQOs for boron, phosphorus and zirconium.69
A final concern is samples from 2008
that show aluminum, nitrate and nitrite levels in Darlington Creek exceeding the
66
Surface Water TSD, at 53.
67
Surface Water TSD, at D-6, D-12, D-18, D-24.
68
Surface Water TSD, at D-5, D-11, D-17, D-23
69
Surface Water TSD, at D-5, D-6, D-11, D-12, D-17, D-18, D-23, D-24.
37. 37
Canadian Council of Ministers of the Environment’s Canadian Environmental Quality
Guidelines for the Protection of Aquatic Life (CCME CEQG PALs).70
What terms and conditions, if any, would be required to ensure adequate
provisions for the protection of the environment?
Section 24(5) of the Nuclear Safety and Control Act allows the Commission to impose
any licence condition that it deems necessary for the purposes of the Act. If the
Commission decides to issue a licence, it has the authority and responsibility to
impose terms and conditions to ensure that environmental protection measures are
adopted and enforced.
The following licensing conditions would help to minimize the plant’s impact on
the environment (both necessary and feasible).
a(i) The Commission should require OPG to develop and implement a robust
impingement and entrainment monitoring program for the DNGS.
Due to the inadequacy of the available impingement and entrainment data. The
Commission should require the DNGS to develop and adopt a robust monitoring
program that can address this significant deficiency.
A robust monitoring program would require:
● ongoing impingement and entrainment sampling at monthly intervals;
● an understanding of differences between daytime and nighttime impingement
and entrainment rates, and a sampling methodology that accounts for these
differences; and
● making the monitoring data readily available to the public and the Commission
on an ongoing basis.
OPG should also monitor the impact of the DNGS on ichthyoplankton. Properly
monitoring ichthyoplankton will require a study that is attuned to seasonal variation in
70
Surface Water TSD, at D-5, D-11, D-17, D-23
38. 38
the presence of eggs and larvae in the water. The study would also need to be
intensive, since life stages for some species last only a few days. Finally, the study
would need to develop a protocol for reliably collecting ichthyoplankton samples,
which are delicate and can easily be damaged beyond the point of identification.
a(ii) The Commission should require OPG to immediately review available
impingement and entrainment mitigation options and determine how it will comply
with its current DFO authorization.
Aside from switching to a closed cycle cooling system, there are no obvious mitigation
measures for reducing impingement and entrainment rates at the DNGS. The DFO
authorization requires that OPG conduct a “review of available impingement and
entrainment avoidance and mitigation options... to determine if any may be technically
and economically feasible to further avoid or mitigate impingement and entrainment
losses”.71
The authorization requires that this review be completed and reported to
DFO by 2024.
The Commission should request that OPG begin this review immediately and release
the findings within one year. Impingement and entrainment represent a chronic source
of stress to the ecosystem surrounding the DNGS. If there are any mitigation measures
that can reduce the impact of the CCW system, they should be implemented as soon
as possible. Unless this review is conducted in a timely manner, and viable options are
implemented, the DNGS cannot be said to have taken adequate measures to protect
the environment. Furthermore, OPG is currently unable to meet the terms of its DFO
authorization. OPG must determine how it will comply with the authorization as soon as
possible, and within one year at the latest. The Commission must not permit the DNGS
to continue operating in violation of the Fisheries Act.
OPG’s review of mitigation options should include an examination of variable speed
pumps. The use of variable speed pumps could help reduce flow rates through the
CCW system at times when higher flow rates are not needed (due to low water
temperatures, or lower generation). A reduction in flow rates could translate into a
reduction in impingement and entrainment rates. However, OPG will need to consider
71
DFO authorization, at 2.1.2.
39. 39
whether variable speed pumps could create further problems with biofouling or thermal
plumes.
b(i) The Commission should require OPG to develop and implement a regular
stormwater monitoring regime.
The Commission should require the DNGS to implement a regular stormwater
monitoring regime. According to Mr. Draganchuk, monthly or quarterly stormwater
monitoring program would be feasible and in keeping with industry best practices.
Mr. Draganchuk has advised that an effective stormwater monitoring regime would
include:
● Monthly sampling initially with future reductions to a minimum of quarterly
sampling based on each stormwater outfall meeting all benchmark monitoring
requirements;
● A protocol to ensure that sampling captures the first flush. Mr. Draganchuk
suggested that first flush samples would ideally be taken within the first 30
minutes of a storm event (and no later than an hour after a storm event begins);
● A sampling regime that captures potential changes in contaminant levels over
the course of the year due to seasonal factors (e.g. salt use in the winter);
● A determination for each outfall of:
a. monthly and annual discharge volumes
b. contaminant loading discharged to Lake Ontario, and
c. an assessment of the impact of contaminant loads on water quality in the
area immediately surrounding outfall
● A proper record keeping system that includes sampling and storm event data.
Based on the current lack of stormwater data, the Commission should require the
DNGS to conduct monthly stormwater sampling to generate baseline data. The DNGS
could shift to quarterly sampling after the Commission is satisfied that it has
established adequate baseline data.
Finally, the DNGS should be prepared to take corrective measures if stormwater data
exceeds relevant benchmarks. Waterkeeper believes that two relevant benchmarks
40. 40
should be PWQOs and acute lethality testing.72
The Commission should require the
DNGS to develop a contingency plan that details what corrective measures it will take
if stormwater samples fail acute lethality testing or exceed PWQOs.
b(ii) The Commission should require OPG to take corrective actions to ensure that
onsite and near site water bodies meet PWQOs.
The Surface Water Technical Support document suggests that Coot’s Pond, SWM
Pond, Tree Frog Pond and Darlington Creek exceed certain PWQOs on a regular basis.
The Commission should require that OPG closely monitor contaminant concentrations
in these waterbodies and develop a strategy to keep all contaminant concentrations in
these waterbodies below PWQOs.
Are there any other issues with this project?
The Commission's primary tool for understanding whether the DNGS has made
adequate provisions for the environment is the Environmental Assessment Screening
Report. If there are gaps or flaws in the screening report the record before the
Commission will not be complete and the Commission will not be able to fulfill its
obligation to assess whether the DNGS has taken adequate measures to protect the
environment.
c. The Environmental Assessment Screening Report is not sufficient to prove the
project makes adequate provision for the protection of the environment.
Waterkeeper believes that the Environmental Assessment Screening Report (the
“Report”) is seriously flawed. After the release of the Draft Environmental Screening
Report (the “Draft”) Waterkeeper hired four experienced advisors in help inform the
environmental assessment process. Based on their expert advice Waterkeeper raised a
number of concerns with the Responsible Authorities about the draft. These concerns
were not addressed in the Report. A detailed discussion of these concerns can be
found in the submission we made to the Responsible Authorities during the
72
Waterkeeper stresses that acute lethality testing is already a legally binding benchmark under section
36(3) of the Fisheries Act. The DFO authorization does not alter the DNGS’s obligations vis-a-vis section
36(3).
41. 41
environmental assessment process (see Appendix 6). Below, two of our main concerns
with the Report are briefly highlighted. The Commission should be aware of these
concerns when reviewing the findings in the Report.
c.1 The Environmental Assessment Screening Report failed to properly consider
closed cycle cooling - the only technology that would allow the DNGS to drastically
reduce fish kills, thermal discharge and biocide release.
Cooling towers are a readily available technology that should be evaluated in any
environmental assessment of a thermal power plant. In the United States the
Environmental Protection Agency (EPA) considers the use of cooling towers at every
power plant that it permits directly . This is because after 40 years of studying and
regulating cooling water systems, the EPA has determined that closed cycle cooling is
the best technology available for all new power plants.73
Cooling towers would allow the DNGS to drastically reduce the quantity of water that it
draws from Lake Ontario. This would in turn allow for a major reduction in fish kills.
The EPA has estimated that “freshwater cooling towers and saltwater cooling towers
reduce impingement mortality and entrainment by 97.5 percent and 94.9 percent,
respectively”.74
In addition to saving fish from impingement and entrainment, closed-
cycle cooling would reduce thermal and chemical pollution, protect endangered
species and improve the integrity of the surrounding ecosystem. No other technology
even approaches the environmental effectiveness of closed-cycle cooling.
Closed cycle-cooling would be both technologically and economically feasible at the
DNGS. The Powers Engineering report which was attached to Waterkeeper’s
submission to the Responsible Authorities concluded that:
73
See 66 Fed. Reg., at 65,256 (Dec. 18, 2001).
74
See 76 Fed. Reg. at 22,200, at col. 1 (“Optimized cooling towers may achieve flow reductions of 97.5
percent or better and 94.9 percent or better for freshwater and saltwater sources, respectively.”).
Assuming that the same or a similarly sized intake structure is used, the reduced flow also greatly
reduces the intake velocity, which also helps to lower impingement rates.
42. 42
A closed-cycle cooling system is the most effective alternative available to minimize the adverse
environmental impact of the intake structures of DNGS Units 1-4. It would be technically feasible
and cost-effective to retrofit Units 1-4 to closed-cycle cooling.75
Despite its feasibility, and well documented benefits, closed cycle cooling is not
considered in the Report. Waterkeeper believes that this omission violated the
Canadian Environmental Assessment Act and the Scoping Information Document.
However, even if these two issues are left aside, there is a third that remains: The
Commission must determine if the DNGS has taken adequate provisions to protect the
environment, but it is being asked to do so with almost no information about the single
provision that would allow the plant to drastically reduce its environmental impact. The
Commission should not allow the DNGS to begin refurbishment until this informational
gap is addressed.
c.2 The Environmental Assessment Screening Report’s methodology for assessing
the CCW system’s impact on aquatic biota was flawed.
A major flaw in the Environmental Assessment Screening Report is its unwillingness to
consider the broader ecological context in which effects of the CCW’s system are
situated. It notes that lakewide populations of alewife and goby are large without
discussing lakewide stressors. It notes that the decrease in round whitefish embryo
survival was minor during warmer winters without considering the future impact of
climate change. It notes the difficulty in linking the low impingement rates of slimy
sculpin with population level changes, but treats this as grounds for inaction rather
than precaution.76
It assumes that survival rates for plankton and invertebrates are high
despite conflicting evidence in the literature and the absence of any information at all
about survival rates at the DNGS.77
75
B. Powers, “Declaration on Feasibility and Cost-Effectiveness of Cooling Tower Retrofits for
Darlington Nuclear Generating Station Units 1-4”, prepared for Lake Ontario Ontario Waterkeeper with
reference to the Darlington Nuclear refurbishment EA process, (16 July, 2012) at 12.
76
CNSC and DFO EA Report at 89.
77
CNSC and DFO EA Report at 89.
43. 43
The conclusions in the Screening Report contrast with the United States Environmental
Protection Agency’s (EPA) approach to understanding the impacts once-through
cooling. The EPA has explained that:
“Although it is difficult to measure, EPA believes that an aquatic population's
compensatory ability—the capacity for a species to increase survival, growth, or
reproduction rates in response to decreased population —is likely compromised by
impingement and entrainment (I&E) mortality losses and the cumulative impact of other
stressors in the environment over extended periods of time. These cumulative impacts
may lead to subtle, less-easily observed changes in aquatic communities and
ecosystem function. These secondary impacts are difficult to isolate from background
variability, partly because of the limited scope and inherent limitations of the data
available to characterize I&E mortality.”78
The EPA’s approach is more in keeping with precautionary principles. It is also
alive to the fact that the complexity of ecological systems can make drawing
causal links difficult. This is particularly for true a highly stressed waterbody the
size of Lake Ontario.
The screening report’s flawed approach to understanding the DNGS’s impact on
aquatic biota has led to a mistaken conclusion: that the impact is non-
significant. When examining once-through cooling systems in the United States,
American regulators have learned to avoid this mistake. They have recognized
that once-through cooling degrades ecosystem health regardless of whether the
impacts can be easily isolated and quantified. Accordingly, they have helped
protect overall ecosystem health by focusing directly on minimizing
impingement, entrainment and thermal discharge from power plants.
Waterkeeper urges the Commission to take a similar approach.
78
United States Environmental Protection Agency, “Environmental and Economic Benefits Analysis for
Proposed Section 316(b) Existing Facilities Rule (28 March, 2011), at 2-1.
44. 44
d. The CNSC has not released the results of the DNGS accident study conducted
by the CNSC staff.
In 2012, CNSC staff agreed to produce an accident study before the DNGS relicensing
hearing took place. Through information requests, Greenpeace has discovered that
CNSC staff have not released the portion of the study that looked at the potential
impacts of a Fukushima-scale accident at Darlington. Waterkeeper believes that this
study must be released immediately. Given the expected growth rates in Durham
region, and Lake Ontario’s importance as a source of drinking water, the public has a
right to know all the risks associated with the DNGS. Furthermore, this information is
central to the Commission’s ability to adequately assess the potential impacts of
OPG’s proposal on the community, including the natural environment.
e. DNGS has not developed a proper off-site emergency plan.
The Canadian Environmental Law Association (CELA) has spent considerable time
reviewing the DNGS’s off site emergency planning. CELA has drawn attention to a
number of issues including: 1) emergency plans are not designed to respond to serious
accidents;, 2) lengthy evacuation times;, and 3) the inadequate, arbitrary distribution
radius for KI pills. Waterkeeper believes that the DNGS must adopt CELA’s
recommendations and develop a comprehensive, evidence-based off site emergency
plan.
CONCLUSION
Lake Ontario is an irreplaceable resource. It constitutes an ecosystem of international
importance that provides significant ecological services. It is the drinking water supply
for millions of people, the site of recreation, transportation, and diverse aquatic
habitats. In light of this, it is essential that the Commission’s decision about the DNGS
be based on a thorough and reliable factual record. At this time such a record does not
exist.
Waterkeeper is deeply concerned about the DNGS’s continued non-compliance with
the Fisheries Act, the open-cycle cooling water system, and the lack of information
being collected on impingement, entrainment, and stormwater runoff. These concerns
45. 45
should lead the Commission to conclude that the DNGS does not make adequate
provision for the protection of the environment.
If the Commission decides to issue the DNGS a general operating licence, it should be
for one year at most. A one-year licence would give OPG sufficient time to: 1)
determine how it will comply with its DFO authorization; 2) develop and implement
programs to monitor impingement, entrainment and stormwater runoff; and 3) develop
a plan for ensuring that water quality onsite and near-site consistently meets all water
quality standards.
OPG’s request for a licence comes at a time when the United States and Canada have
been cooperating to restore and protect the Great Lakes. Via the work of the
International Joint Commission, and the Great Lakes Water Quality Agreement, and by
committing billions to sustain and restore the Great Lakes, both jurisdictions recognize
the value of these precious ecosystems. Furthermore, the Province of Ontario is on the
verge of passing the Great Lakes Protection Act, which would require consideration for
swimmable, drinkable, fishable Great Lakes in all major decisions.
As a community, we are just beginning to appreciate the essential link between the
health of the Great Lakes and our future prosperity. At a minimum, regulators should
ensure that facilities like the DNGS comply with the law and carefully monitor their
impact on the aquatic environment. OPG has not demonstrated that the DNGS does
either. For that reason, the Commission cannot reasonably grant its request for a 13-
year licence.
46. 46
LIST OF APPENDICES
APPENDIX 1: Biological Report of Dr. Henderson on the New Nuclear Darlington Power
Plant, Pisces Conservation Ltd.
APPENDIX 2: Biological Report of Dr. Henderson on the Continued Operation of the
Darlington Nuclear Generating Station, Pisces Conservation Ltd.
APPENDIX 3: Biological Report of Dr. Seaby on the Continued Operation of the
Darlington Nuclear Generating Station, Pisces Conservation Ltd.
APPENDIX 4: Engineering Report of Bill Powers, Powers Engineering
APPENDIX 5: Kevin Dragnanchuk CV
APPENDIX 6: Lake Ontario Waterkeeper’s submission for the DNGS EA process.
47. 47
WORKS CITED
Bill 66, An Act to protect and restore the Great Lakes-St. Lawrence River Basin, 1st
Sess, 41st Leg, Ontario, 2015 (passed 2nd reading 04 June 2105, currently before the
Standing Committee on General Government).
Bring Back the Salmon, Lake Ontario Atlantic Salmon Restoration Program, viewed on
September 24th 2015 at: http://www.bringbackthesalmon.ca/?page_id=12
Canadian Nuclear Safety Commission. (19 August, 2015). Transcript: Public Hearing on
August 19 2015.
Canadian Nuclear Safety Commission and Fisheries and Oceans Canada. (March
2013). Final Environmental Assessment Screening Report: The Refurbishment and
Continued Operation of the Darlington Nuclear Generating Station, Municipality of
Clarington, Ontario.
Canadian Nuclear Safety Commission and Fisheries and Oceans Canada. (16
December, 2013). Memorandum of Understanding Between Fisheries and Oceans
Canada and Canadian Nuclear Safety Commission for Cooperation and Administration
of the Fisheries Act and the Species at Risk Act Related to Regulating Nuclear Materials
and Energy Development.
Golder Associates. (December 2011). Surface Water Environment Technical Support
Document Darlington Nuclear Generating Station Refurbishment and Continued
Operation Environmental Assessment.
Fisheries and Oceans Canada. (June 24, 2015). Paragraph 35(2)(b) Fisheries Act
Authorization.
Henderson, P. A., Dr. (4 October, 2010) Comments on aquatic issues relating to the
proposed New Nuclear Darlington (NND) power plants, Prepared for Lake Ontario
Waterkeeper with reference to the Darlington New Nuclear Power Plant EA Process.
48. 48
Henderson, P. A., Dr. (July, 2012) “Comments on Environmental Studies Relation to the
Darlington Nuclear Generating Station Refurbishment and Continued Operation
Project”, prepared for Lake Ontario Ontario Waterkeeper with reference to the
Darlington Nuclear refurbishment EA process.
MacGregor, R. J. Casselman, L. Greig, J. Dettmers, W. A. Allen, L. McDermott, and T.
Haxton. (2013). Recovery Strategy for the American Eel (Anguilla rostrata) in Ontario.
Ontario Recovery Strategy Series. Prepared for Ontario Ministry of Natural Resources,
Peterborough, Ontario.
Ontario Drinking Water Advisory Council. (21 May, 2009). Report and Advice on the
Ontario Drinking Water Quality Standard for Tritium. Retrieved from http://ceaa-
acee.gc.ca/050/documents/49046/49046E.pdf
Ontario Ministry of Environment and Climate Change. (July, 1994). Provincial Water
Quality Objectives of the Ministry of Environment and Energy. Retrieved from:
https://dr6j45jk9xcmk.cloudfront.net/documents/3016/moeprovincialwaterqualityobject
ivesen.pdf
Ontario Ministry of Infrastructure. (June 2013, Office Consolidation). Growth Plan for
the Greater Golden Horseshoe, 2006. Retrieved from
https://www.placestogrow.ca/content/ggh/2013-06-10-Growth-Plan-for-the-GGH-
EN.pdf
Ontario Power Generation. (September 2013). Darlington Nuclear Refurbishment and
Continued Operation Environmental Assessment Follow-Up Program.
Ontario Power Generation. (21 August, 2014). Submission to DFO for an Authorization
under the Fisheries Act for the Darlington Nuclear Generating Facility.
Powers, B. (16 July, 2012). Declaration on Feasibility and Cost-Effectiveness of Cooling
Tower Retrofits for Darlington Nuclear Generating Station Units 1-4, prepared for Lake
Ontario Ontario Waterkeeper with reference to the Darlington Nuclear refurbishment EA
process.
49. 49
Seaby, R., Dr. (September, 2015). Notes on the fishery issues relating to Darlington
Nuclear Generating Facility relicensing (Ontario Power Generation (OPG)), prepared for
Lake Ontario Ontario Waterkeeper with reference to the DNGS relicensing process.
SENES Consultants Limited. (December 2011). Aquatic Environment Technical Support
Document Darlington Nuclear Generating Station Refurbishment and Continued
Operation Environmental Assessment.
Town of Ajax. (10 February, 2014). Duffin Creek Water Pollution Control Plant Outfall
Environmental Assessment - Part II Order Request.
United States Environmental Protection Agency. (28 March, 2011). Environmental and
Economic Benefits Analysis for Proposed Section 316(b) Existing Facilities Rule.