Task Name Finish Resource Names
100% XYZ Company Data Center Re-Location to CO-LO Facility Sat 5/18/13
100% Order MPLS betwwen HQ & CO-LO Facility Tue 1/1/13 XYZ Emp.#1
100% MPLS Installed & Tested Fri 3/1/13 Carrier
100% Order Router Tue 1/1/13 XYZ Emp #2
100% Router Installed, Configured & Tested at CO-LO Facility Fri 3/8/13 XYZ Emp.#1
100% Create From and To Hardware & Network Plan Sat 1/26/13 XYZ Emp.#1
100% Create RFP for Hardware Movers and send out Sun 2/3/13 TKO,Sr. MGMT
100% Project Team Kickoff Fri 2/8/13 Mover,Physical
Movers,Sr.
MGMT,XYZ Emp
#2,XYZ Emp.#1,TKO
100% Evaluate and Execute Hardware Mover Contract Wed 2/27/13 Sr. MGMT,TKO
100% Moving Company Internal Mobilization Wed 3/6/13 Physical Movers
100% Moving Company XYZ Company DC Relocation Materials Order
& Receipt
Tue 3/5/13 Physical Movers
100% Design Patch Matrix/BOM Development Complete Sat 3/9/13 Physical Movers
100% Order BOM and Delivered for Installation Complete Sun 3/10/13 Physical Movers
100% ‐Destination Site Cable Pre Deployment Complete Fri 3/15/13 Physical Movers
100% QA Patch Matrix (20%) Mon 1/14/13 XYZ Emp.#1,TKO
Task
Split
Milestone
Summary
Project Summary
External Tasks
External Milestone
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
Deadline
Progress
Page 1
Project: XYZ Company Data Cente
Date: Thu 6/9/16
%
Complete
Task Name Finish Resource Names
100% Customer 1 Operation Backup, Down/UP Processes Tue 3/5/13 XYZ Emp.#1,XYZ
Emp #2
100% Customer 2 Operation Backup, Down/UP Processes Thu 3/7/13 XYZ Emp.#1,XYZ
Emp #2
100% Customer 3 Operation Backup, Down/UP Processes Sat 3/2/13 XYZ Emp.#1,XYZ
Emp #2
100% Customer 4 Operation Backup, Down/UP Processes Sat 3/9/13 XYZ Emp.#1,XYZ
Emp #2
100% Customer 5 Operation Backup, Down/UP Processes Fri 3/8/13 XYZ Emp.#1,XYZ
Emp #2
100% Customer 6, 7, 8, 9, and 10 Homed on same system Backup,
Operation Down/UP Processes
Sun 3/17/13 XYZ Emp.#1,XYZ
Emp #2
100% Order Redundant Firewall Fri 2/8/13 XYZ Emp.#1
100% Redundant Firewall Delivered Thu 2/14/13 XYZ Emp.#1
100% Install and Configure Redundant Firewall Fri 3/15/13 XYZ Emp.#1
100% Tue 1/1/13
100%
Customer Migrations Tue 1/1/13
100% Tue 1/1/13
100% Customer 1 Migration - Also see XYZ
Migration 1 schedule at bottom of this plan
Fri 3/15/13
100% Notify Customer 1 Client of Plans Sat 1/26/13 Sr. MGMT,TKO
Task
Split
Milestone
Summary
Project Summary
External Tasks
External Milestone
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
Deadline
Progress
Page 2
Project: XYZ Company Data Cente
Date: Thu 6/9/16
%
Complete
Task Name Finish Resource Names
100% Schedule Customer 1 Client Resources Fri 3/15/13 Sr. MGMT,TKO
100% Operations : Backups, Power Down/Power Up Procedures Fri 3/15/13 XYZ Emp.#1,XYZ
Emp #2
100% Perform Syms Backup Fri 3/15/13 XYZ Emp.#1,XYZ
Emp #2
100% End all System Processes and verify all jobs are stopped prior to
shutdown
Fri 3/15/13 XYZ Emp.#1,XYZ
Emp #2
100% HMC Power Down all LPARS Fri 3/15/13 XYZ Emp.#1,XYZ
Emp #2
100% Customer 1 Physical Migration Fri 3/15/13 Physical Movers
100% Test Conectivity and OPS Consoles Fri 3/15/13 XYZ Emp.#1,XYZ
Emp #2
100% Run All "Missed" Jobs during Offline Fri 3/15/13 XYZ Emp.#1,XYZ
Emp #2
100% Run HW Test for Drives, Connect, etc. Fri 3/15/13 XYZ Emp.#1,XYZ
Emp #2
100% Verify "Stable State" Fri 3/15/13 XYZ Emp.#1,XYZ
Emp #2
100% Customer 1 Migration Window Complete Fri 3/15/13 Entire Team
100% Tue 1/1/13
100% Customer Migrations <continue> Tue 1/1/13
100% Customer 4 Migration Fri 3/22/13 Entire Team,TKO,Mon
1/14/13
Task
Split
Milestone
Summary
Project Summary
External Tasks
External Milestone
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
Deadline
Progress
Page 3
Project: XYZ Company Data Cente
Date: Thu 6/9/16
%
Complete
Task Name Finish Resource Names
100% Notify Client of Plans Sat 1/26/13 Sr. MGMT,TKO
100% Schedule Client Resources Sat 1/26/13 XYZ Emp.#1,XYZ
Emp #2
100% Operations: Backup, Power Down/Power Up Procedures Fri 3/22/13 XYZ Emp.#1,XYZ
Emp #2
100% Perform Backup Fri 3/22/13 XYZ Emp.#1,XYZ Emp #2
100% End all System Processes and verify all jobs are stopped prior to shutdownFri 3/22/13 XYZ Emp.#1,XYZ Emp #2
100% Power down Customer 4 IDEAS/GUI Server Tue 1/1/13 XYZ Emp.#1
100% HMC Power Down all LPARS Fri 3/22/13 XYZ Emp.#1,XYZ Emp #2
100% Customer 4 Physical Migration Fri 3/22/13 Physical Movers
100% Power Up Systems Fri 3/22/13 XYZ Emp.#1,XYZ Emp #2
100% Test Conectivity and OPS Consoles Fri 3/22/13 XYZ Emp.#1,XYZ Emp #2
100% Verify "Stable State" Fri 3/22/13 XYZ Emp #2,Chris H.,XYZ Emp.#1
100% Customer 4 Migration Window Complete Fri 3/22/13 Entire Team
100% Run Missed Jobs – MSGSDIMSG and EOD Process Fri 3/22/13 XYZ Emp #2
100% Qinter Up – System available to users Fri 3/22/13 XYZ Emp #2
Task
Split
Milestone
Summary
Project Summary
External Tasks
External Milestone
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
Deadline
Progress
Page 4
Project: XYZ Company Data Cente
Date: Thu 6/9/16
%
Complete
Task Name Finish Resource Names
100% Customer 2 Migration/Implementation Tue 4/2/13
100% Notify Client of Plans Sat 1/26/13 Sr. MGMT
100% Schedule Client Resources Mon 1/14/13 TKO,Sr. MGMT,XYZ
Emp.#1
100% Operations: Backup, Power Down Power Up Procedures Tue 4/9/13 XYZ Emp.#1,XYZ
Emp #2
100% Perform Full System Backup 1:00 am Monday Mon 4/1/13 XYZ Emp.#1,XYZ
Emp #2
100% Perform Intel Backups Mon 4/1/13 XYZ Emp.#1
100% End all System Processes and verify all jobs are stopped prior to
shutdown
Sat 4/27/13 XYZ Emp.#1,XYZ
Emp #2
100% Perform Incremental backup Mon 4/1/13 XYZ Emp #2
Task
Split
Milestone
Summary
Project Summary
External Tasks
External Milestone
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
Deadline
Progress
Page 5
Project: XYZ Company Data Cente
Date: Thu 6/9/16
%
Complete
Task Name Finish Resource Names
100% Power Down VMs Tue 4/2/13 XYZ Emp.#1
100% Power Down VM Host Tue 4/2/13 XYZ Emp.#1
100% Power Down AS400 System Tue 4/2/13 XYZ Emp.#1,XYZ
Emp #2
100% Power Down Network Equipment Tue 4/2/13 XYZ Emp.#1
100% Customer 2 Physical Migration Tue 4/2/13 Physical Movers
100% Power up Network Equipment Tue 4/2/13 XYZ Emp.#1
Task
Split
Milestone
Summary
Project Summary
External Tasks
External Milestone
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
Deadline
Progress
Page 6
Project: XYZ Company Data Cente
Date: Thu 6/9/16
%
Complete
Task Name Finish Resource Names
100% Power up San Device Wed 4/3/13 XYZ Emp.#1
100% Power up FD-Bckup Server (Check San is up & Check network is
up)
Wed 4/3/13 XYZ Emp.#1
100% Power UP VM Host Wed 4/3/13 XYZ Emp.#1
100% Power up VM's Wed 4/3/13 XYZ Emp.#1
100% Power on the HMC Managed Server Wed 4/3/13 XYZ Emp #2
100% Power on the Systems – FLDMMS first- Wait for *NWS – others
can go
Wed 4/3/13 XYZ Emp #2
100% Power on Tape Drives Wed 4/3/13 XYZ Emp #2
100% Test Conectivity and OPS Consoles Wed 4/3/13 XYZ Emp.#1,XYZ
Emp #2
100% Run missed schedules on FLD side (E3) Wed 4/3/13 Customer 2
Task
Split
Milestone
Summary
Project Summary
External Tasks
External Milestone
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
Deadline
Progress
Page 7
Project: XYZ Company Data Cente
Date: Thu 6/9/16
%
Complete
Task Name Finish Resource Names
100% Run All "Missed" Jobs during Offline Wed 4/3/13 XYZ Emp.#1,XYZ
Emp #2
100% Verify "Stable State" Wed 4/3/13 XYZ Emp.#1,XYZ
Emp #2
100% Custome 2 Migration/Implementation Window Complete Wed 4/3/13 Entire Team
100% Customer 5 Migration Wed 3/20/13
100% Notify Client of Plans Sat 1/26/13 Sr. MGMT,TKO
Task
Split
Milestone
Summary
Project Summary
External Tasks
External Milestone
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
Deadline
Progress
Page 8
Project: XYZ Company Data Cente
Date: Thu 6/9/16
%
Complete
Task Name Finish Resource Names
100% Schedule Client Resources Mon 1/14/13 TKO,Sr. MGMT
100% Operations: Backup, Power Down/Power Up Procedures Fri 4/5/13 XYZ Emp.#1,XYZ
Emp #2
100% Perform Backup Thu 4/4/13 XYZ Emp.#1,XYZ
Emp #2
100% End all System Processes and verify all jobs are stopped prior to
shutdown
Fri 4/5/13 XYZ Emp.#1,XYZ
Emp #2
100% HMC Power Down all LPARS Fri 4/5/13 XYZ Emp.#1,XYZ
Emp #2
100% Customer 5 Physical Migration Fri 4/5/13 Physical Movers
100% Test Conectivity and OPS Consoles Fri 4/5/13 XYZ Emp.#1,XYZ
Emp #2
100% Run All "Missed" Jobs during Offline Fri 4/5/13 XYZ Emp.#1,XYZ
Emp #2
100% Run HW Test for Drives, Connect, etc. Fri 4/5/13 XYZ Emp.#1,XYZ
Emp #2
100% Verify "Stable State" Fri 4/5/13 XYZ Emp.#1,XYZ
Emp #2
100% Customer 5 Migration Window Complete Tue 3/19/13 Entire Team
Task
Split
Milestone
Summary
Project Summary
External Tasks
External Milestone
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
Deadline
Progress
Page 9
Project: XYZ Company Data Cente
Date: Thu 6/9/16
%
Complete
Task Name Finish Resource Names
100% Customer 3 Migration Sun 4/28/13
100% Notify Client of Plans Sat 1/26/13 Sr. MGMT,TKO
100% Order Client Links Mon 1/21/13 XYZ Emp.#1,XYZ
Contact
100% Links Installed & Ready Sat 3/16/13 Carrier
100% CO-LO Cross Connect Sat 3/23/13 Data Center Co_Lo
100% Schedule Carrier for Migration Date Sat 3/2/13 TKO,XYZ Emp.#1
100% Schedule Client Resources Fri 3/15/13 TKO,Sr. MGMT
100% Operations: Backup, Power Down/Power Up Procedures Sat 4/27/13 XYZ Emp.#1,XYZ
Emp #2
100% Perform Backup Sat 4/6/13 XYZ Emp.#1,XYZ
Emp #2
100% End all System Processes and verify all jobs are stopped prior to
shutdown
Sun 4/7/13 XYZ Emp.#1,XYZ
Emp #2
100% HMC Power Down all LPARS Mon 4/8/13 XYZ Emp.#1,XYZ
Emp #2
100% Customer 3 Physical Migration Sun 4/7/13 Physical Movers
Task
Split
Milestone
Summary
Project Summary
External Tasks
External Milestone
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
Deadline
Progress
Page 10
Project: XYZ Company Data Cente
Date: Thu 6/9/16
%
Complete
Task Name Finish Resource Names
100% Test Conectivity and OPS Consoles Mon 4/8/13 XYZ Emp.#1,XYZ
Emp #2
100% Run All "Missed" Jobs during Offline Sun 4/7/13 XYZ Emp.#1,XYZ
Emp #2
100% Run HW Test for Drives, Connect, etc. Sun 4/7/13 XYZ Emp.#1,XYZ
Emp #2
100% Verify "Stable State" Sun 4/7/13 XYZ Emp.#1,XYZ
Emp #2
100% Customer 3 Migration Window Complete Sun 4/7/13 Entire Team
100% Shared Equipment (SE) Migration (Customers 6, 7, 8, 9 and
10)
Wed 5/1/13
100% Notify Client of Plans Sat 1/26/13 Sr. MGMT,TKO
100% Schedule Client Resources Tue 1/1/13 XYZ Emp.#1,XYZ
Emp #2
100% Operations: Backup, Power Down Power Up Procedures Tue 4/30/13 XYZ Emp.#1,XYZ
Emp #2
100% Perform Backup Thu 4/11/13 XYZ Emp.#1,XYZ
Emp #2
100% End all System Processes and verify all jobs are stopped prior to
shutdown
Fri 4/12/13 XYZ Emp.#1,XYZ
Emp #2
Task
Split
Milestone
Summary
Project Summary
External Tasks
External Milestone
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
Deadline
Progress
Page 11
Project: XYZ Company Data Cente
Date: Thu 6/9/16
%
Complete
Task Name Finish Resource Names
100% HMC Power Down all LPARS Fri 4/12/13 XYZ Emp.#1,XYZ
Emp #2
100% SE Physical Migration Sat 4/13/13 Physical Movers
100% Test Conectivity and OPS Consoles Sat 4/13/13 XYZ Emp.#1,XYZ
Emp #2
100% Run All "Missed" Jobs during Offline Sat 4/13/13 XYZ Emp.#1,XYZ
Emp #2
100% Run HW Test for Drives, Connect, etc. Sat 4/13/13 XYZ Emp.#1,XYZ
Emp #2
100% Verify "Stable State" Sat 4/13/13 XYZ Emp.#1,XYZ
Emp #2
100% (SE) Migration Window Complete Sat 4/13/13 Entire Team
100% Customer XYZ Migration #2 Sun 4/21/13
100% Notify Client of Plans / Normal Change Management Processes
Used
Fri 1/25/13 Sr. MGMT,TKO
100% Order Client Links (Megapath 3 T1's) Mon 1/21/13 XYZ Contact,TKO
100% Schedule Carrier for Migration Date Mon 1/21/13 Jay R.
Task
Split
Milestone
Summary
Project Summary
External Tasks
External Milestone
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
Deadline
Progress
Page 12
Project: XYZ Company Data Cente
Date: Thu 6/9/16
%
Complete
Task Name Finish Resource Names
100% Schedule Client Resources Fri 2/22/13 John D.,Jay R.,Sr.
MGMT,TKO,XYZ
100% Links Installed & Ready Wed 3/20/13 Carrier
100% Co-Lo Cross Connect Wed 3/20/13 Data Center Co_Lo
100% Network Testing Complete Thu 3/21/13 John Doe
100% Perform AS400 Backup Fri 4/19/13 John Doe
100% FRMMS full backup Fri 4/19/13 XYZ
100% FRRI full backup Fri 4/19/13
100% Perform Windows Backup Fri 4/19/13 Jane May
100% Scheduled Windows Backup Fri 4/19/13 Jane May
100% End all System Processes and verify all jobs are stopped prior to
shutdown
Fri 4/19/13 John Doe,Jane May
100% Graceful Powerdown AS400 System Fri 4/19/13 Jay R.,John D.
100% Robot Jobs Identified - held Fri 4/19/13 John Doe
100% Outside Windows FTP servers Fri 4/19/13 John Doe
100% Windows Scheduled Jobs Off Fri 4/19/13 John Doe
100% Shutdown FRMMS/FRRI Fri 4/19/13 John Doe
100% Power down managed system (FRMMS) Fri 4/19/13 John Doe
100% Power down managed system (FRRI) Fri 4/19/13 John Doe
100% Power down HMC Fri 4/19/13 John Doe
100% Power down 2 Tape Libraries Fri 4/19/13 John Doe
Task
Split
Milestone
Summary
Project Summary
External Tasks
External Milestone
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
Deadline
Progress
Page 13
Project: XYZ Company Data Cente
Date: Thu 6/9/16
%
Complete
Task Name Finish Resource Names
100% Graceful Powerdown Windows System Fri 4/19/13 Jane May
100% Power down VMs (5 mins to power down each VM) a. .18 subnet = XYZCenteraldev, XYZ-DNS,XYZ-CRM, XYZ-GUI, XYZ-IDEAS, XYZ-SAFri 4/19/13 Jane May
100% Power down physical VM Server (5 mins to power down each VM Host) a. Host 1 & Host2Fri 4/19/13 Jane May
100% Power down xyzintprod.servers.xyz 192.168.X.X IBM 3850 Fri 4/19/13 Jane May
100% Power Down xyzallocation.servers.xyz 192.168.X.X System x3550Fri 4/19/13 Jane May
100% Power down xyzentralprod.servers... 192.168.X.X System x3550Fri 4/19/13 Jane May
100% Power down xyzinttest.servers.xyz 192.168.X.X System
x3550
Fri 4/19/13 XYZ Emp.#1
100% Power down xyz-emn1-bk1.servers.xyz 192.168.X.X Fri 4/19/13 XYZ Emp.#1
100% Power down SAN devices (5 mins to power down SAN devices)Fri 4/19/13 XYZ Emp.#1
100% Physical Migration to Co-Lo except Credit Auth Fri 4/19/13 Physical Movers
100% Power down xyzisd.servers.xyz 192.168.0.X System x3550 Fri 4/19/13 XYZ Emp.#1
100% Power down xyzsdhot.servers.xyz 192.168.X.X System x3550 Fri 4/19/13 XYZ Emp.#1
100% Power down xyzisdwarm.servers.xyz 192.168.X.X System x3550 Fri 4/19/13 XYZ Emp.#1
100% Power down SAN devices (5 mins to power down SAN devices) Fri 4/19/13 XYZ Emp.#1
100% Power down xyzisdbkup.servers.xyz 192.168.X.X System x3550 Fri 4/19/13 XYZ Emp.#1
100% Power Down XYZ network equipment Fri 4/19/13 XYZ Emp.#1
100% XYZ 2nd Physical Migration to Co-Lo ( Credit Auth ) Fri 4/19/13 Physical Movers
Task
Split
Milestone
Summary
Project Summary
External Tasks
External Milestone
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
Deadline
Progress
Page 14
Project: XYZ Company Data Cente
Date: Thu 6/9/16
%
Complete
Task Name Finish Resource Names
100% Power UP AS400 System Sat 4/20/13
100% Power up Tape Library Sat 4/20/13 XYZ Emp #2
100% Power up HMC Sat 4/20/13 XYZ Emp #2
100% Power up managed system (FRMMS) Sat 4/20/13 XYZ Emp #2
100% Power up managed system (FRRI) Sat 4/20/13 XYZ Emp #2
100% TCP001 job started - FRMMS Sat 4/20/13 XYZ Emp #2
100% Outside Windows FTP servers communicating Sat 4/20/13 XYZ Emp #2
100% Windows Scheduler Started Sat 4/20/13 XYZ Emp #2
100% Startup Robot Sat 4/20/13 XYZ Emp #2
100% Release Missed jobs Sat 4/20/13 XYZ Emp #2
100% Power UP Windows System Sat 4/20/13
100% Power on SAN devices (15 mins to power on SAN devices) Sat 4/20/13 XYZ Emp.#1
100% Power UP xyzisdbkup.servers.xyz 192.168.X.X System x3550 Sat 4/20/13 XYZ Emp.#1
100% Power UP 1st- xyz-emn1-bk1.servers.xyz 192.168.X.X Sat 4/20/13 XYZ Emp.#1
100% Power on physical Windows Servers (10-15 min to power on each server) Exact boot order for A-ESat 4/20/13 XYZ Emp.#1
100% Power on VMs (2 mins to power on each VM) a. XYZCenteraldev, XYZ-DNS, XYZ-CRM, XYZ-GUI, XYZ-IDEAS, XYZ-SALLOSat 4/20/13 XYZ Emp.#1
100% Power UP a. xyzintprod.servers.xyz 192.168.X.X IBM 3850 Sat 4/20/13 XYZ Emp.#1
100% Power UP b. xyzisd.servers.xyz 192.168.X.X System x3550 Sat 4/20/13 XYZ Emp.#1
100% Power UP b. xyzentralprod.servers... 192.168.X.X System x3550Sat 4/20/13 XYZ Emp.#1
100% Power UP d. xyzisdhot.servers.xyz 192.168.X.X System
x3550
Sat 4/20/13 XYZ Emp.#1
Task
Split
Milestone
Summary
Project Summary
External Tasks
External Milestone
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
Deadline
Progress
Page 15
Project: XYZ Company Data Cente
Date: Thu 6/9/16
%
Complete
Task Name Finish Resource Names
100% Power UP e. xyzisdwarm.servers.xyz 192.168.X.X System
x3550
Sat 4/20/13 XYZ Emp.#1
100% Power UP f. xyzallocation.servers.xyz 192.168.X.X System x3550Sat 4/20/13 XYZ Emp.#1
100% Power UP h. xyzinttest.servers.xyz 192.168.X.X System x3550Sat 4/20/13 XYZ Emp.#1
100% Power on physical VM Server (10-15 mins to power down each VM Host) a. Host 1 & Host2Sat 4/20/13 XYZ Emp.#1
100% Test Conectivity and OPS Consoles Sat 4/20/13 XYZ Emp.#1,XYZ
Emp #2
100% Run All "Missed" Jobs during Offline Sat 4/20/13 XYZ Emp.#1,XYZ
Emp #2
100% Run HW Test for Drives, Connect, etc. Sat 4/20/13 XYZ Emp.#1,XYZ
Emp #2
100% Operations Post-Move Checklist Sat 4/20/13 XYZ Emp.#1,XYZ
Emp #2
100% Power up system at Co-Lo Sat 4/20/13 XYZ Emp #2
100% Start the HMC Sat 4/20/13 XYZ Emp #2
100% Start the partitions Sat 4/20/13 XYZ Emp #2
100% Verify Communications to Iseries/Client Access Sat 4/20/13 XYZ Emp #2
100% Windows server/s to system verification Sat 4/20/13 XYZ Emp.#1
100% Subsystems up Sat 4/20/13 XYZ Emp #2
100% Netserver running Sat 4/20/13 XYZ Emp.#1
100% Client Checkpoint – (network and communications ok) Sat 4/20/13 XYZ Emp.#1
100% Qinter Up Sat 4/20/13 XYZ Emp #2
100% Users allowed back onto the system Sat 4/20/13 XYZ Emp #2
Task
Split
Milestone
Summary
Project Summary
External Tasks
External Milestone
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
Deadline
Progress
Page 16
Project: XYZ Company Data Cente
Date: Thu 6/9/16
%
Complete
Task Name Finish Resource Names
100% Retail Ideas – IDE210CL released and running (was initially on hold)Sat 4/20/13 XYZ Emp #2
100% Verify any Jobs/applications that need to be running – exa: Logagent, TCP001, etcSat 4/20/13 XYZ Emp #2
100% Jwalk up – if necessary Sat 4/20/13 XYZ Emp #2
100% JOBQ’s released Sat 4/20/13 XYZ Emp #2
100% Robot Started Sat 4/20/13 XYZ Emp #2
100% Robot jobs released and caught up to Current time Sat 4/20/13 XYZ Emp #2
100% Release IBM scheduler if necessary Sat 4/20/13 XYZ Emp #2
100% Release Windows scheduled jobs Sat 4/20/13 XYZ Emp.#1
100% Release Windows scheduled jobs Sat 4/20/13 XYZ Emp.#1
100% Verify "Stable State" Sat 5/18/13 XYZ Emp.#1,XYZ
Emp #2
100% XYZ Migration Window Complete Sat 4/20/13 Entire Team
100% XYZ Test Systems Sat 4/20/13 XYZ Contact
100% Run End of Day Processes Sat 4/20/13 XYZ Emp #2
100% XYZ Company Migration #1 Fri 3/15/13
100% Notify Client of Plans Tue 1/1/13 Sr. MGMT,TKO
100% Operations : Backups, Power Down/Power Up Procedures Fri 3/15/13 XYZ Emp.#1
100% Perform XYZ Company Backup Fri 3/15/13 XYZ Emp.#1
100% End all System Processes and applications prior to shutdown Fri 3/15/13 XYZ Emp.#1
100% System and Network Equipment Power Down Fri 3/15/13 XYZ Emp.#1
Task
Split
Milestone
Summary
Project Summary
External Tasks
External Milestone
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
Deadline
Progress
Page 17
Project: XYZ Company Data Cente
Date: Thu 6/9/16
%
Complete
Task Name Finish Resource Names
100% XYZ Company Physical Migration Fri 3/15/13 Physical Movers
100% Breakdown/Packing Fri 3/15/13 Physical Movers
100% Travel Fri 3/15/13 Physical Movers
100% Rack & Stack Fri 3/15/13 Physical Movers
100% Cable Services Fri 3/15/13 Physical Movers
100% Power up Network and Systems Tue 1/1/13 XYZ Emp.#1,Cisco
Engineer
100% Test Conectivity and OPS Consoles Fri 3/15/13 XYZ Emp.#1
100% Verify VMs, WEB, Blackberry back ONLINE Fri 3/15/13 XYZ Emp.#1
100% Run HW Test for Drives, Connect, etc. Fri 3/15/13 XYZ Emp.#1
100% Verify "Stable State" Fri 3/15/13 XYZ Emp.#1,XYZ
Emp #2
100% XYZ Company Migration Window Complete Fri 3/15/13 Entire Team
Task
Split
Milestone
Summary
Project Summary
External Tasks
External Milestone
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
Deadline
Progress
Page 18
Project: XYZ Company Data Cente
Date: Thu 6/9/16
Notes
Lead by TKO
Week of March 11th
Week of March 11th
Week of March 11th
1/1
Carrier
XYZ Emp #2
XYZ Emp.#1
XYZ Emp.#1
TKO,Sr. MGMT
2/8
Sr. MGMT,TKO
Physical Movers
Physical Movers
3/9
Physical Movers
Physical Movers
XYZ Emp.#1,TKO
16 23 30 6 13 20 27 3 10 17 24 3 10 17 24 31 7 14 21 28 5 12 19 26 2 9 16 23 30
Dec '12 Jan '13 Feb '13 Mar '13 Apr '13 May '13 Jun '13
Task
Split
Milestone
Summary
Project Summary
External Tasks
External Milestone
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
Deadline
Progress
Page 19
Project: XYZ Company Data Cente
Date: Thu 6/9/16
Notes
Scheduled for March 21st
Scheduled: March 15th
9:00am Est. / BOM and Cable
order dependancy
XYZ Emp.#1,XYZ Emp #2
XYZ Emp.#1,XYZ Emp #2
XYZ Emp.#1,XYZ Emp #2
XYZ Emp.#1,XYZ Emp #2
XYZ Emp.#1,XYZ Emp #2
XYZ Emp.#1,XYZ Emp #2
2/8
XYZ Emp.#1
XYZ Emp.#1
3/15
Sr. MGMT,TKO
16 23 30 6 13 20 27 3 10 17 24 3 10 17 24 31 7 14 21 28 5 12 19 26 2 9 16 23 30
Dec '12 Jan '13 Feb '13 Mar '13 Apr '13 May '13 Jun '13
Task
Split
Milestone
Summary
Project Summary
External Tasks
External Milestone
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
Deadline
Progress
Page 20
Project: XYZ Company Data Cente
Date: Thu 6/9/16
Notes
Customer 1 Power Down
Tasks...
Start of Maintenance Window
- 9:00am
3:00 pm Est.
Scheduled: March 22nd/
BOM and Cable order
dependancy
3/15
3/15
XYZ Emp.#1,XYZ Emp #2
3/15
3/15
Physical Movers
3/15
3/15
3/15
XYZ Emp.#1,XYZ Emp #2
Entire Team
Entire Team,TKO,Mon 1/14/13
16 23 30 6 13 20 27 3 10 17 24 3 10 17 24 31 7 14 21 28 5 12 19 26 2 9 16 23 30
Dec '12 Jan '13 Feb '13 Mar '13 Apr '13 May '13 Jun '13
Task
Split
Milestone
Summary
Project Summary
External Tasks
External Milestone
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
Deadline
Progress
Page 21
Project: XYZ Company Data Cente
Date: Thu 6/9/16
Notes
Power Down Tasks...
08:00 PM – 2 hours
10:00 PM
10:00PM
10:10PM (9:36pm)
10:10PM (9:36pm) - (Turn
over to Moving Company) - 7
hours to move (3:36am 6
hours)
5:10am April 2nd (3:36am)
5:10am April 2nd
5:30am April 2nd
5:30am April 2nd
3 hours
8:30am EST (6:52am EST)
Sr. MGMT,TKO
XYZ Emp.#1,XYZ Emp #2
3/22
XYZ Emp.#1,XYZ Emp #2
XYZ Emp.#1,XYZ Emp #2
XYZ Emp.#1
XYZ Emp.#1,XYZ Emp #2
Physical Movers
XYZ Emp.#1,XYZ Emp #2
XYZ Emp.#1,XYZ Emp #2
XYZ Emp #2,Chris H.,XYZ Emp.#1
Entire Team
XYZ Emp #2
XYZ Emp #2
16 23 30 6 13 20 27 3 10 17 24 3 10 17 24 31 7 14 21 28 5 12 19 26 2 9 16 23 30
Dec '12 Jan '13 Feb '13 Mar '13 Apr '13 May '13 Jun '13
Task
Split
Milestone
Summary
Project Summary
External Tasks
External Milestone
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
Deadline
Progress
Page 22
Project: XYZ Company Data Cente
Date: Thu 6/9/16
Notes
Scheduled : April 2nd
(TUESDAY) - 2:30pm Est.
Power Down Tasks...
1:30PM - 2:30PM
2:30pm
2:30pm - FLDE3 – 1hr,
FLDITG – 1hr 45min,
FLDMMS – 1hr 30min,
FLDRI – 10min ( all at the
same time so (2hrs max for
all))
4/2
Sr. MGMT
TKO,Sr. MGMT,XYZ Emp.#1
XYZ Emp.#1,XYZ Emp #2
XYZ Emp.#1,XYZ Emp #2
XYZ Emp.#1
XYZ Emp.#1,XYZ Emp #2
XYZ Emp #2
16 23 30 6 13 20 27 3 10 17 24 3 10 17 24 31 7 14 21 28 5 12 19 26 2 9 16 23 30
Dec '12 Jan '13 Feb '13 Mar '13 Apr '13 May '13 Jun '13
Task
Split
Milestone
Summary
Project Summary
External Tasks
External Milestone
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
Deadline
Progress
Page 23
Project: XYZ Company Data Cente
Date: Thu 6/9/16
Notes
FD-CentralProd – power
down 2:30pm, FD-INTProd –
power down 2:31pm,
FD-CRMDEV power down
2:33pm, FD-CRMProd Power
down 2:35pm,
FD-IDEASProd power down
2:36pm, FD-SilvonProd
power down 2:38pm
ESX Host1 power down
2:45pm, ESX Host2 power
down 2:45pm, FD-Bkup
power down 2:50pm,
FD-IBMSAN power down
2:50
4:30PM
4:30PM
5:15PM (4:31) (Turn over
to Moving Company) - 10
hours to move
3:15AM April 3rd (12:00am)
XYZ Emp.#1
XYZ Emp.#1
XYZ Emp.#1,XYZ Emp #2
XYZ Emp.#1
Physical Movers
XYZ Emp.#1
16 23 30 6 13 20 27 3 10 17 24 3 10 17 24 31 7 14 21 28 5 12 19 26 2 9 16 23 30
Dec '12 Jan '13 Feb '13 Mar '13 Apr '13 May '13 Jun '13
Task
Split
Milestone
Summary
Project Summary
External Tasks
External Milestone
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
Deadline
Progress
Page 24
Project: XYZ Company Data Cente
Date: Thu 6/9/16
Notes
3:15am April 3rd (12:03am)
3:30am April 3rd (12:03 am)
3:45AM April 3rd (12:03 am)
4:00AM April 3rd (12:03
am)
4:15am (10 min) (12:30am -
HMC Internal Drive Failure -
IBM Dispatched)
4:25am (20 min) (5:45am)
4:45am (5 min) (12:30am)
4:45AM April 3rd (6:00am)
4:45AM April 3rd (6:28am)
XYZ Emp.#1
XYZ Emp.#1
XYZ Emp.#1
XYZ Emp.#1
XYZ Emp #2
XYZ Emp #2
XYZ Emp #2
XYZ Emp.#1,XYZ Emp #2
Customer 2
16 23 30 6 13 20 27 3 10 17 24 3 10 17 24 31 7 14 21 28 5 12 19 26 2 9 16 23 30
Dec '12 Jan '13 Feb '13 Mar '13 Apr '13 May '13 Jun '13
Task
Split
Milestone
Summary
Project Summary
External Tasks
External Milestone
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
Deadline
Progress
Page 25
Project: XYZ Company Data Cente
Date: Thu 6/9/16
Notes
FLDRI – None, FLDE3
-ASR_SWAP SCD USER
DEF 05:35:00 *WEEKLY,
AWR_SKUOUT SCD USER
DEF 05:30:00 *WEEKLY ,
AWR_SWAP SCD
USER,DEF 05:35:00
*WEEKLY, RUNALLPO
SCD *ALL 21:45:00
*WEEKLY, RUNAMPO SCD
USER DEF 06:15:00
*WEEKLY , RUNASR SCD
USER DEF 05:00:00
*WEEKL
4:45AM (6:45am)
Target Completion : 5:00am
April 3rd (6:45am)
Schedule : April 5th - 9:00am
XYZ Emp.#1,XYZ Emp #2
XYZ Emp.#1,XYZ Emp #2
Entire Team
3/20
Sr. MGMT,TKO
16 23 30 6 13 20 27 3 10 17 24 3 10 17 24 31 7 14 21 28 5 12 19 26 2 9 16 23 30
Dec '12 Jan '13 Feb '13 Mar '13 Apr '13 May '13 Jun '13
Task
Split
Milestone
Summary
Project Summary
External Tasks
External Milestone
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
Deadline
Progress
Page 26
Project: XYZ Company Data Cente
Date: Thu 6/9/16
Notes
Power Down Tasks...
10:30 AM April 5th (Turn
over to Moving Company) 10
hours to move
9:00 PM April 5th
TKO,Sr. MGMT
XYZ Emp.#1,XYZ Emp #2
XYZ Emp.#1,XYZ Emp #2
XYZ Emp.#1,XYZ Emp #2
XYZ Emp.#1,XYZ Emp #2
4/5
XYZ Emp.#1,XYZ Emp #2
XYZ Emp.#1,XYZ Emp #2
XYZ Emp.#1,XYZ Emp #2
XYZ Emp.#1,XYZ Emp #2
Entire Team
16 23 30 6 13 20 27 3 10 17 24 3 10 17 24 31 7 14 21 28 5 12 19 26 2 9 16 23 30
Dec '12 Jan '13 Feb '13 Mar '13 Apr '13 May '13 Jun '13
Task
Split
Milestone
Summary
Project Summary
External Tasks
External Milestone
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
Deadline
Progress
Page 27
Project: XYZ Company Data Cente
Date: Thu 6/9/16
Notes
Scheduled April 7th 1:00 AM
Open ticket with Carrier for
Migration times
Power Down Tasks...
12:15AM April 7 (Turn over
to Moving Company) 9.5
hours to move (see Move
Plan)
Sr. MGMT,TKO
XYZ Emp.#1,XYZ Contact
Carrier
Data Center Co_Lo
3/2
TKO,Sr. MGMT
XYZ Emp.#1,XYZ Emp #2
XYZ Emp.#1,XYZ Emp #2
XYZ Emp.#1,XYZ Emp #2
XYZ Emp.#1,XYZ Emp #2
Physical Movers
16 23 30 6 13 20 27 3 10 17 24 3 10 17 24 31 7 14 21 28 5 12 19 26 2 9 16 23 30
Dec '12 Jan '13 Feb '13 Mar '13 Apr '13 May '13 Jun '13
Task
Split
Milestone
Summary
Project Summary
External Tasks
External Milestone
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
Deadline
Progress
Page 28
Project: XYZ Company Data Cente
Date: Thu 6/9/16
Notes
12:00PM April 7 (per Move
Plan)
Schedule : April 12th -
10:00pm to 6:00am
Power Down Tasks...
XYZ Emp.#1,XYZ Emp #2
XYZ Emp.#1,XYZ Emp #2
XYZ Emp.#1,XYZ Emp #2
XYZ Emp.#1,XYZ Emp #2
Entire Team
Sr. MGMT,TKO
XYZ Emp.#1,XYZ Emp #2
XYZ Emp.#1,XYZ Emp #2
XYZ Emp.#1,XYZ Emp #2
XYZ Emp.#1,XYZ Emp #2
16 23 30 6 13 20 27 3 10 17 24 3 10 17 24 31 7 14 21 28 5 12 19 26 2 9 16 23 30
Dec '12 Jan '13 Feb '13 Mar '13 Apr '13 May '13 Jun '13
Task
Split
Milestone
Summary
Project Summary
External Tasks
External Milestone
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
Deadline
Progress
Page 29
Project: XYZ Company Data Cente
Date: Thu 6/9/16
Notes
10:30PM - (Turn over to
Moving Company) - 7 hours
to move
5:30am April 13th
6:00am April 13
Open ticket with Carrier for
Migration Window
XYZ Emp.#1,XYZ Emp #2
Physical Movers
XYZ Emp.#1,XYZ Emp #2
XYZ Emp.#1,XYZ Emp #2
XYZ Emp.#1,XYZ Emp #2
XYZ Emp.#1,XYZ Emp #2
Entire Team
Sr. MGMT,TKO
XYZ Contact,TKO
1/21
16 23 30 6 13 20 27 3 10 17 24 3 10 17 24 31 7 14 21 28 5 12 19 26 2 9 16 23 30
Dec '12 Jan '13 Feb '13 Mar '13 Apr '13 May '13 Jun '13
Task
Split
Milestone
Summary
Project Summary
External Tasks
External Milestone
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
Deadline
Progress
Page 30
Project: XYZ Company Data Cente
Date: Thu 6/9/16
Notes
Date and Time Verified
Upon Formal Approval - Start
of Maintenance Window -
2:00am
Power Down Tasks...
John D.,Jay R.,Sr. MGMT,TKO,XYZ
Carrier
Data Center Co_Lo
3/21
XYZ
Jane May
John Doe,Jane May
John Doe
John Doe
John Doe
John Doe
John Doe
John Doe
John Doe
John Doe
16 23 30 6 13 20 27 3 10 17 24 3 10 17 24 31 7 14 21 28 5 12 19 26 2 9 16 23 30
Dec '12 Jan '13 Feb '13 Mar '13 Apr '13 May '13 Jun '13
Task
Split
Milestone
Summary
Project Summary
External Tasks
External Milestone
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
Deadline
Progress
Page 31
Project: XYZ Company Data Cente
Date: Thu 6/9/16
Notes
Power Down Tasks...
Except Credit Auth Servers -
Est 14 hours
Estimated 2 hours
Jane May
Jane May
Jane May
Jane May
Jane May
XYZ Emp.#1
XYZ Emp.#1
XYZ Emp.#1
Physical Movers
XYZ Emp.#1
XYZ Emp.#1
XYZ Emp.#1
XYZ Emp.#1
XYZ Emp.#1
XYZ Emp.#1
Physical Movers
16 23 30 6 13 20 27 3 10 17 24 3 10 17 24 31 7 14 21 28 5 12 19 26 2 9 16 23 30
Dec '12 Jan '13 Feb '13 Mar '13 Apr '13 May '13 Jun '13
Task
Split
Milestone
Summary
Project Summary
External Tasks
External Milestone
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
Deadline
Progress
Page 32
Project: XYZ Company Data Cente
Date: Thu 6/9/16
Notes
Power Up starts
Power Up starts
Credit Auth
Credit Auth
XYZ Emp #2
XYZ Emp #2
XYZ Emp #2
XYZ Emp #2
XYZ Emp #2
XYZ Emp #2
XYZ Emp #2
XYZ Emp #2
XYZ Emp #2
XYZ Emp.#1
XYZ Emp.#1
XYZ Emp.#1
XYZ Emp.#1
XYZ Emp.#1
XYZ Emp.#1
XYZ Emp.#1
XYZ Emp.#1
XYZ Emp.#1
16 23 30 6 13 20 27 3 10 17 24 3 10 17 24 31 7 14 21 28 5 12 19 26 2 9 16 23 30
Dec '12 Jan '13 Feb '13 Mar '13 Apr '13 May '13 Jun '13
Task
Split
Milestone
Summary
Project Summary
External Tasks
External Milestone
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
Deadline
Progress
Page 33
Project: XYZ Company Data Cente
Date: Thu 6/9/16
Notes
Credit Auth
Post Move ...
XYZ Emp.#1
XYZ Emp.#1
XYZ Emp.#1
XYZ Emp.#1
XYZ Emp.#1,XYZ Emp #2
XYZ Emp.#1,XYZ Emp #2
XYZ Emp.#1,XYZ Emp #2
XYZ Emp #2
XYZ Emp #2
XYZ Emp #2
XYZ Emp #2
XYZ Emp.#1
XYZ Emp #2
XYZ Emp.#1
XYZ Emp.#1
XYZ Emp #2
XYZ Emp #2
16 23 30 6 13 20 27 3 10 17 24 3 10 17 24 31 7 14 21 28 5 12 19 26 2 9 16 23 30
Dec '12 Jan '13 Feb '13 Mar '13 Apr '13 May '13 Jun '13
Task
Split
Milestone
Summary
Project Summary
External Tasks
External Milestone
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
Deadline
Progress
Page 34
Project: XYZ Company Data Cente
Date: Thu 6/9/16
Notes
Estimated 3.5 Hours after
Maint. Window
XYZ Company Power Down
Tasks...
Start of Maintenance Window
XYZ Emp #2
XYZ Emp #2
XYZ Emp #2
XYZ Emp #2
XYZ Emp #2
XYZ Emp #2
XYZ Emp #2
XYZ Emp.#1
XYZ Emp.#1
XYZ Emp.#1,XYZ Emp #2
Entire Team
XYZ Contact
XYZ Emp #2
3/15
Sr. MGMT,TKO
3/15
XYZ Emp.#1
3/15
3/15
16 23 30 6 13 20 27 3 10 17 24 3 10 17 24 31 7 14 21 28 5 12 19 26 2 9 16 23 30
Dec '12 Jan '13 Feb '13 Mar '13 Apr '13 May '13 Jun '13
Task
Split
Milestone
Summary
Project Summary
External Tasks
External Milestone
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
Deadline
Progress
Page 35
Project: XYZ Company Data Cente
Date: Thu 6/9/16
Notes
9.5 hour Estimate (Total)
3 hours
1 hour
2 hours
3.5 hours
Physical Movers
Physical Movers
Physical Movers
Physical Movers
XYZ Emp.#1,Cisco Engineer
3/15
3/15
3/15
Entire Team
16 23 30 6 13 20 27 3 10 17 24 3 10 17 24 31 7 14 21 28 5 12 19 26 2 9 16 23 30
Dec '12 Jan '13 Feb '13 Mar '13 Apr '13 May '13 Jun '13
Task
Split
Milestone
Summary
Project Summary
External Tasks
External Milestone
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
Deadline
Progress
Page 36
Project: XYZ Company Data Cente
Date: Thu 6/9/16

More Related Content

What's hot

Trouble Ticket Integration with Zabbix in Large Environment
Trouble Ticket Integration with Zabbix in Large EnvironmentTrouble Ticket Integration with Zabbix in Large Environment
Trouble Ticket Integration with Zabbix in Large Environment
Alain Ganuchaud
 
OVN DBs HA with scale test
OVN DBs HA with scale testOVN DBs HA with scale test
OVN DBs HA with scale test
Aliasgar Ginwala
 
Media Handling in FreeSWITCH
Media Handling in FreeSWITCHMedia Handling in FreeSWITCH
Media Handling in FreeSWITCH
Moises Silva
 
OVN operationalization at scale at eBay
OVN operationalization at scale at eBayOVN operationalization at scale at eBay
OVN operationalization at scale at eBay
Aliasgar Ginwala
 
Install and Configure NGINX Unit, the Universal Application, Web, and Proxy S...
Install and Configure NGINX Unit, the Universal Application, Web, and Proxy S...Install and Configure NGINX Unit, the Universal Application, Web, and Proxy S...
Install and Configure NGINX Unit, the Universal Application, Web, and Proxy S...
NGINX, Inc.
 
BGP and Traffic Engineering with Akamai
BGP and Traffic Engineering with AkamaiBGP and Traffic Engineering with Akamai
BGP and Traffic Engineering with Akamai
Internet Society
 
MBA GIS Solar Farm Feasibility Study
MBA GIS Solar Farm Feasibility StudyMBA GIS Solar Farm Feasibility Study
MBA GIS Solar Farm Feasibility StudyEian Ray
 
Nickel Laterite Deposit.pptx
Nickel Laterite Deposit.pptxNickel Laterite Deposit.pptx
Nickel Laterite Deposit.pptx
AndiAzisRusdi
 
영업비밀 보호 및 보안관리 관련 쟁점과 분쟁사례 연구
영업비밀 보호 및 보안관리 관련 쟁점과 분쟁사례 연구영업비밀 보호 및 보안관리 관련 쟁점과 분쟁사례 연구
영업비밀 보호 및 보안관리 관련 쟁점과 분쟁사례 연구
국현 김
 
Aaron Mildenstein - Using Logstash with Zabbix
Aaron Mildenstein - Using Logstash with ZabbixAaron Mildenstein - Using Logstash with Zabbix
Aaron Mildenstein - Using Logstash with Zabbix
Zabbix
 
VPP for Stateless SRv6/GTP-U Translation
VPP for Stateless SRv6/GTP-U TranslationVPP for Stateless SRv6/GTP-U Translation
VPP for Stateless SRv6/GTP-U Translation
Satoru Matsushima
 
ملزمة علوم للأول الإعدادى ترم أول
ملزمة علوم للأول الإعدادى ترم أولملزمة علوم للأول الإعدادى ترم أول
ملزمة علوم للأول الإعدادى ترم أول
أمنية وجدى
 
CNIT 121: 2 IR Management Handbook
CNIT 121: 2 IR Management HandbookCNIT 121: 2 IR Management Handbook
CNIT 121: 2 IR Management Handbook
Sam Bowne
 
Kamailio World 2014 - Kamailio - The Platform for Interoperable WebRTC
Kamailio World 2014 - Kamailio - The Platform for Interoperable WebRTCKamailio World 2014 - Kamailio - The Platform for Interoperable WebRTC
Kamailio World 2014 - Kamailio - The Platform for Interoperable WebRTC
Crocodile WebRTC SDK and Cloud Signalling Network
 
Tin Mine Costs - June 2013 - Greenfields Research / ITRI / Curtin University ...
Tin Mine Costs - June 2013 - Greenfields Research / ITRI / Curtin University ...Tin Mine Costs - June 2013 - Greenfields Research / ITRI / Curtin University ...
Tin Mine Costs - June 2013 - Greenfields Research / ITRI / Curtin University ...John Sykes
 
PublicadoresDeDados2.pdf
PublicadoresDeDados2.pdfPublicadoresDeDados2.pdf
PublicadoresDeDados2.pdf
ssuserb174cd
 
PostgreSQL High Availability via SLONY and PG POOL II
PostgreSQL High Availability via SLONY and PG POOL IIPostgreSQL High Availability via SLONY and PG POOL II
PostgreSQL High Availability via SLONY and PG POOL II
Command Prompt., Inc
 
Re:invent 2016 Container Scheduling, Execution and AWS Integration
Re:invent 2016 Container Scheduling, Execution and AWS IntegrationRe:invent 2016 Container Scheduling, Execution and AWS Integration
Re:invent 2016 Container Scheduling, Execution and AWS Integration
aspyker
 
SIP Attack Handling (Kamailio World 2021)
SIP Attack Handling (Kamailio World 2021)SIP Attack Handling (Kamailio World 2021)
SIP Attack Handling (Kamailio World 2021)
Fred Posner
 
Attacker's Perspective of Active Directory
Attacker's Perspective of Active DirectoryAttacker's Perspective of Active Directory
Attacker's Perspective of Active Directory
Sunny Neo
 

What's hot (20)

Trouble Ticket Integration with Zabbix in Large Environment
Trouble Ticket Integration with Zabbix in Large EnvironmentTrouble Ticket Integration with Zabbix in Large Environment
Trouble Ticket Integration with Zabbix in Large Environment
 
OVN DBs HA with scale test
OVN DBs HA with scale testOVN DBs HA with scale test
OVN DBs HA with scale test
 
Media Handling in FreeSWITCH
Media Handling in FreeSWITCHMedia Handling in FreeSWITCH
Media Handling in FreeSWITCH
 
OVN operationalization at scale at eBay
OVN operationalization at scale at eBayOVN operationalization at scale at eBay
OVN operationalization at scale at eBay
 
Install and Configure NGINX Unit, the Universal Application, Web, and Proxy S...
Install and Configure NGINX Unit, the Universal Application, Web, and Proxy S...Install and Configure NGINX Unit, the Universal Application, Web, and Proxy S...
Install and Configure NGINX Unit, the Universal Application, Web, and Proxy S...
 
BGP and Traffic Engineering with Akamai
BGP and Traffic Engineering with AkamaiBGP and Traffic Engineering with Akamai
BGP and Traffic Engineering with Akamai
 
MBA GIS Solar Farm Feasibility Study
MBA GIS Solar Farm Feasibility StudyMBA GIS Solar Farm Feasibility Study
MBA GIS Solar Farm Feasibility Study
 
Nickel Laterite Deposit.pptx
Nickel Laterite Deposit.pptxNickel Laterite Deposit.pptx
Nickel Laterite Deposit.pptx
 
영업비밀 보호 및 보안관리 관련 쟁점과 분쟁사례 연구
영업비밀 보호 및 보안관리 관련 쟁점과 분쟁사례 연구영업비밀 보호 및 보안관리 관련 쟁점과 분쟁사례 연구
영업비밀 보호 및 보안관리 관련 쟁점과 분쟁사례 연구
 
Aaron Mildenstein - Using Logstash with Zabbix
Aaron Mildenstein - Using Logstash with ZabbixAaron Mildenstein - Using Logstash with Zabbix
Aaron Mildenstein - Using Logstash with Zabbix
 
VPP for Stateless SRv6/GTP-U Translation
VPP for Stateless SRv6/GTP-U TranslationVPP for Stateless SRv6/GTP-U Translation
VPP for Stateless SRv6/GTP-U Translation
 
ملزمة علوم للأول الإعدادى ترم أول
ملزمة علوم للأول الإعدادى ترم أولملزمة علوم للأول الإعدادى ترم أول
ملزمة علوم للأول الإعدادى ترم أول
 
CNIT 121: 2 IR Management Handbook
CNIT 121: 2 IR Management HandbookCNIT 121: 2 IR Management Handbook
CNIT 121: 2 IR Management Handbook
 
Kamailio World 2014 - Kamailio - The Platform for Interoperable WebRTC
Kamailio World 2014 - Kamailio - The Platform for Interoperable WebRTCKamailio World 2014 - Kamailio - The Platform for Interoperable WebRTC
Kamailio World 2014 - Kamailio - The Platform for Interoperable WebRTC
 
Tin Mine Costs - June 2013 - Greenfields Research / ITRI / Curtin University ...
Tin Mine Costs - June 2013 - Greenfields Research / ITRI / Curtin University ...Tin Mine Costs - June 2013 - Greenfields Research / ITRI / Curtin University ...
Tin Mine Costs - June 2013 - Greenfields Research / ITRI / Curtin University ...
 
PublicadoresDeDados2.pdf
PublicadoresDeDados2.pdfPublicadoresDeDados2.pdf
PublicadoresDeDados2.pdf
 
PostgreSQL High Availability via SLONY and PG POOL II
PostgreSQL High Availability via SLONY and PG POOL IIPostgreSQL High Availability via SLONY and PG POOL II
PostgreSQL High Availability via SLONY and PG POOL II
 
Re:invent 2016 Container Scheduling, Execution and AWS Integration
Re:invent 2016 Container Scheduling, Execution and AWS IntegrationRe:invent 2016 Container Scheduling, Execution and AWS Integration
Re:invent 2016 Container Scheduling, Execution and AWS Integration
 
SIP Attack Handling (Kamailio World 2021)
SIP Attack Handling (Kamailio World 2021)SIP Attack Handling (Kamailio World 2021)
SIP Attack Handling (Kamailio World 2021)
 
Attacker's Perspective of Active Directory
Attacker's Perspective of Active DirectoryAttacker's Perspective of Active Directory
Attacker's Perspective of Active Directory
 

Similar to Keith odom sample microsoft project template data center move

Project Portfolio Francois Bourcier
Project Portfolio Francois BourcierProject Portfolio Francois Bourcier
Project Portfolio Francois Bourcier
Francois Bourcier
 
R squared weekly-status_03012010[1]
R squared  weekly-status_03012010[1]R squared  weekly-status_03012010[1]
R squared weekly-status_03012010[1]Captainsamcox
 
Project Closing Procedure PowerPoint Presentation Slides
Project Closing Procedure PowerPoint Presentation Slides Project Closing Procedure PowerPoint Presentation Slides
Project Closing Procedure PowerPoint Presentation Slides
SlideTeam
 
PLUG N’ PLAY NETWORK SOLUTIONS PRESENTATION 1
PLUG N’ PLAY NETWORK SOLUTIONS PRESENTATION 1PLUG N’ PLAY NETWORK SOLUTIONS PRESENTATION 1
PLUG N’ PLAY NETWORK SOLUTIONS PRESENTATION 1andrew stefan
 
Tenant improvement Scheduling
Tenant improvement SchedulingTenant improvement Scheduling
Tenant improvement SchedulingRonald Rhodes
 
Predictive RCM
Predictive RCMPredictive RCM
Predictive RCMJoe Soroka
 
Project Closure PowerPoint Presentation Slides
Project Closure PowerPoint Presentation Slides Project Closure PowerPoint Presentation Slides
Project Closure PowerPoint Presentation Slides
SlideTeam
 
Project Closure Powerpoint Presentation Slides
Project Closure Powerpoint Presentation SlidesProject Closure Powerpoint Presentation Slides
Project Closure Powerpoint Presentation Slides
SlideTeam
 
Recharge_report_Automation
Recharge_report_AutomationRecharge_report_Automation
Recharge_report_AutomationKIIT
 
Project Closure Process Steps PowerPoint Presentation Slides
Project Closure Process Steps PowerPoint Presentation Slides Project Closure Process Steps PowerPoint Presentation Slides
Project Closure Process Steps PowerPoint Presentation Slides
SlideTeam
 
Wa warehouse project status report
Wa warehouse project status reportWa warehouse project status report
Wa warehouse project status reportTom Evans
 
Project Closure Activities In Project Management Powerpoint Presentation Slides
Project Closure Activities In Project Management Powerpoint Presentation SlidesProject Closure Activities In Project Management Powerpoint Presentation Slides
Project Closure Activities In Project Management Powerpoint Presentation Slides
SlideTeam
 
Wa warehouse project status report
Wa warehouse project status reportWa warehouse project status report
Wa warehouse project status reportTom Evans
 
USMC Shops PM Project-Dec 3, 2008
USMC Shops PM Project-Dec 3, 2008USMC Shops PM Project-Dec 3, 2008
USMC Shops PM Project-Dec 3, 2008
tkjohns1
 
Project Plan - Risk Management & Integration
Project Plan - Risk Management & IntegrationProject Plan - Risk Management & Integration
Project Plan - Risk Management & IntegrationPrachi Dikshit
 
ID WBS Task Name Duration Start Finish Predecessors Resource N.docx
ID WBS Task Name Duration Start Finish Predecessors Resource N.docxID WBS Task Name Duration Start Finish Predecessors Resource N.docx
ID WBS Task Name Duration Start Finish Predecessors Resource N.docx
wilcockiris
 
Weekly Meeting Presentation
Weekly Meeting PresentationWeekly Meeting Presentation
Weekly Meeting Presentation
Calkee
 
Project Closure Activities In Project Management PowerPoint Presentation Slides
Project Closure Activities In Project Management PowerPoint Presentation Slides Project Closure Activities In Project Management PowerPoint Presentation Slides
Project Closure Activities In Project Management PowerPoint Presentation Slides
SlideTeam
 

Similar to Keith odom sample microsoft project template data center move (20)

Project Portfolio Francois Bourcier
Project Portfolio Francois BourcierProject Portfolio Francois Bourcier
Project Portfolio Francois Bourcier
 
R squared weekly-status_03012010[1]
R squared  weekly-status_03012010[1]R squared  weekly-status_03012010[1]
R squared weekly-status_03012010[1]
 
DRAFT LHD-2 PEMT SKED V - Portfolio Example
DRAFT LHD-2 PEMT SKED V - Portfolio ExampleDRAFT LHD-2 PEMT SKED V - Portfolio Example
DRAFT LHD-2 PEMT SKED V - Portfolio Example
 
Project Closing Procedure PowerPoint Presentation Slides
Project Closing Procedure PowerPoint Presentation Slides Project Closing Procedure PowerPoint Presentation Slides
Project Closing Procedure PowerPoint Presentation Slides
 
PLUG N’ PLAY NETWORK SOLUTIONS PRESENTATION 1
PLUG N’ PLAY NETWORK SOLUTIONS PRESENTATION 1PLUG N’ PLAY NETWORK SOLUTIONS PRESENTATION 1
PLUG N’ PLAY NETWORK SOLUTIONS PRESENTATION 1
 
Tenant improvement Scheduling
Tenant improvement SchedulingTenant improvement Scheduling
Tenant improvement Scheduling
 
Predictive RCM
Predictive RCMPredictive RCM
Predictive RCM
 
Project Closure PowerPoint Presentation Slides
Project Closure PowerPoint Presentation Slides Project Closure PowerPoint Presentation Slides
Project Closure PowerPoint Presentation Slides
 
Project Closure Powerpoint Presentation Slides
Project Closure Powerpoint Presentation SlidesProject Closure Powerpoint Presentation Slides
Project Closure Powerpoint Presentation Slides
 
Recharge_report_Automation
Recharge_report_AutomationRecharge_report_Automation
Recharge_report_Automation
 
CPM
CPMCPM
CPM
 
Project Closure Process Steps PowerPoint Presentation Slides
Project Closure Process Steps PowerPoint Presentation Slides Project Closure Process Steps PowerPoint Presentation Slides
Project Closure Process Steps PowerPoint Presentation Slides
 
Wa warehouse project status report
Wa warehouse project status reportWa warehouse project status report
Wa warehouse project status report
 
Project Closure Activities In Project Management Powerpoint Presentation Slides
Project Closure Activities In Project Management Powerpoint Presentation SlidesProject Closure Activities In Project Management Powerpoint Presentation Slides
Project Closure Activities In Project Management Powerpoint Presentation Slides
 
Wa warehouse project status report
Wa warehouse project status reportWa warehouse project status report
Wa warehouse project status report
 
USMC Shops PM Project-Dec 3, 2008
USMC Shops PM Project-Dec 3, 2008USMC Shops PM Project-Dec 3, 2008
USMC Shops PM Project-Dec 3, 2008
 
Project Plan - Risk Management & Integration
Project Plan - Risk Management & IntegrationProject Plan - Risk Management & Integration
Project Plan - Risk Management & Integration
 
ID WBS Task Name Duration Start Finish Predecessors Resource N.docx
ID WBS Task Name Duration Start Finish Predecessors Resource N.docxID WBS Task Name Duration Start Finish Predecessors Resource N.docx
ID WBS Task Name Duration Start Finish Predecessors Resource N.docx
 
Weekly Meeting Presentation
Weekly Meeting PresentationWeekly Meeting Presentation
Weekly Meeting Presentation
 
Project Closure Activities In Project Management PowerPoint Presentation Slides
Project Closure Activities In Project Management PowerPoint Presentation Slides Project Closure Activities In Project Management PowerPoint Presentation Slides
Project Closure Activities In Project Management PowerPoint Presentation Slides
 

Recently uploaded

GraphRAG is All You need? LLM & Knowledge Graph
GraphRAG is All You need? LLM & Knowledge GraphGraphRAG is All You need? LLM & Knowledge Graph
GraphRAG is All You need? LLM & Knowledge Graph
Guy Korland
 
Enchancing adoption of Open Source Libraries. A case study on Albumentations.AI
Enchancing adoption of Open Source Libraries. A case study on Albumentations.AIEnchancing adoption of Open Source Libraries. A case study on Albumentations.AI
Enchancing adoption of Open Source Libraries. A case study on Albumentations.AI
Vladimir Iglovikov, Ph.D.
 
GDG Cloud Southlake #33: Boule & Rebala: Effective AppSec in SDLC using Deplo...
GDG Cloud Southlake #33: Boule & Rebala: Effective AppSec in SDLC using Deplo...GDG Cloud Southlake #33: Boule & Rebala: Effective AppSec in SDLC using Deplo...
GDG Cloud Southlake #33: Boule & Rebala: Effective AppSec in SDLC using Deplo...
James Anderson
 
UiPath Test Automation using UiPath Test Suite series, part 6
UiPath Test Automation using UiPath Test Suite series, part 6UiPath Test Automation using UiPath Test Suite series, part 6
UiPath Test Automation using UiPath Test Suite series, part 6
DianaGray10
 
LF Energy Webinar: Electrical Grid Modelling and Simulation Through PowSyBl -...
LF Energy Webinar: Electrical Grid Modelling and Simulation Through PowSyBl -...LF Energy Webinar: Electrical Grid Modelling and Simulation Through PowSyBl -...
LF Energy Webinar: Electrical Grid Modelling and Simulation Through PowSyBl -...
DanBrown980551
 
Free Complete Python - A step towards Data Science
Free Complete Python - A step towards Data ScienceFree Complete Python - A step towards Data Science
Free Complete Python - A step towards Data Science
RinaMondal9
 
DevOps and Testing slides at DASA Connect
DevOps and Testing slides at DASA ConnectDevOps and Testing slides at DASA Connect
DevOps and Testing slides at DASA Connect
Kari Kakkonen
 
GraphSummit Singapore | The Art of the Possible with Graph - Q2 2024
GraphSummit Singapore | The Art of the  Possible with Graph - Q2 2024GraphSummit Singapore | The Art of the  Possible with Graph - Q2 2024
GraphSummit Singapore | The Art of the Possible with Graph - Q2 2024
Neo4j
 
Securing your Kubernetes cluster_ a step-by-step guide to success !
Securing your Kubernetes cluster_ a step-by-step guide to success !Securing your Kubernetes cluster_ a step-by-step guide to success !
Securing your Kubernetes cluster_ a step-by-step guide to success !
KatiaHIMEUR1
 
Large Language Model (LLM) and it’s Geospatial Applications
Large Language Model (LLM) and it’s Geospatial ApplicationsLarge Language Model (LLM) and it’s Geospatial Applications
Large Language Model (LLM) and it’s Geospatial Applications
Rohit Gautam
 
Goodbye Windows 11: Make Way for Nitrux Linux 3.5.0!
Goodbye Windows 11: Make Way for Nitrux Linux 3.5.0!Goodbye Windows 11: Make Way for Nitrux Linux 3.5.0!
Goodbye Windows 11: Make Way for Nitrux Linux 3.5.0!
SOFTTECHHUB
 
Mind map of terminologies used in context of Generative AI
Mind map of terminologies used in context of Generative AIMind map of terminologies used in context of Generative AI
Mind map of terminologies used in context of Generative AI
Kumud Singh
 
Alt. GDG Cloud Southlake #33: Boule & Rebala: Effective AppSec in SDLC using ...
Alt. GDG Cloud Southlake #33: Boule & Rebala: Effective AppSec in SDLC using ...Alt. GDG Cloud Southlake #33: Boule & Rebala: Effective AppSec in SDLC using ...
Alt. GDG Cloud Southlake #33: Boule & Rebala: Effective AppSec in SDLC using ...
James Anderson
 
A tale of scale & speed: How the US Navy is enabling software delivery from l...
A tale of scale & speed: How the US Navy is enabling software delivery from l...A tale of scale & speed: How the US Navy is enabling software delivery from l...
A tale of scale & speed: How the US Navy is enabling software delivery from l...
sonjaschweigert1
 
20240605 QFM017 Machine Intelligence Reading List May 2024
20240605 QFM017 Machine Intelligence Reading List May 202420240605 QFM017 Machine Intelligence Reading List May 2024
20240605 QFM017 Machine Intelligence Reading List May 2024
Matthew Sinclair
 
GraphSummit Singapore | Enhancing Changi Airport Group's Passenger Experience...
GraphSummit Singapore | Enhancing Changi Airport Group's Passenger Experience...GraphSummit Singapore | Enhancing Changi Airport Group's Passenger Experience...
GraphSummit Singapore | Enhancing Changi Airport Group's Passenger Experience...
Neo4j
 
Secstrike : Reverse Engineering & Pwnable tools for CTF.pptx
Secstrike : Reverse Engineering & Pwnable tools for CTF.pptxSecstrike : Reverse Engineering & Pwnable tools for CTF.pptx
Secstrike : Reverse Engineering & Pwnable tools for CTF.pptx
nkrafacyberclub
 
Video Streaming: Then, Now, and in the Future
Video Streaming: Then, Now, and in the FutureVideo Streaming: Then, Now, and in the Future
Video Streaming: Then, Now, and in the Future
Alpen-Adria-Universität
 
Encryption in Microsoft 365 - ExpertsLive Netherlands 2024
Encryption in Microsoft 365 - ExpertsLive Netherlands 2024Encryption in Microsoft 365 - ExpertsLive Netherlands 2024
Encryption in Microsoft 365 - ExpertsLive Netherlands 2024
Albert Hoitingh
 
RESUME BUILDER APPLICATION Project for students
RESUME BUILDER APPLICATION Project for studentsRESUME BUILDER APPLICATION Project for students
RESUME BUILDER APPLICATION Project for students
KAMESHS29
 

Recently uploaded (20)

GraphRAG is All You need? LLM & Knowledge Graph
GraphRAG is All You need? LLM & Knowledge GraphGraphRAG is All You need? LLM & Knowledge Graph
GraphRAG is All You need? LLM & Knowledge Graph
 
Enchancing adoption of Open Source Libraries. A case study on Albumentations.AI
Enchancing adoption of Open Source Libraries. A case study on Albumentations.AIEnchancing adoption of Open Source Libraries. A case study on Albumentations.AI
Enchancing adoption of Open Source Libraries. A case study on Albumentations.AI
 
GDG Cloud Southlake #33: Boule & Rebala: Effective AppSec in SDLC using Deplo...
GDG Cloud Southlake #33: Boule & Rebala: Effective AppSec in SDLC using Deplo...GDG Cloud Southlake #33: Boule & Rebala: Effective AppSec in SDLC using Deplo...
GDG Cloud Southlake #33: Boule & Rebala: Effective AppSec in SDLC using Deplo...
 
UiPath Test Automation using UiPath Test Suite series, part 6
UiPath Test Automation using UiPath Test Suite series, part 6UiPath Test Automation using UiPath Test Suite series, part 6
UiPath Test Automation using UiPath Test Suite series, part 6
 
LF Energy Webinar: Electrical Grid Modelling and Simulation Through PowSyBl -...
LF Energy Webinar: Electrical Grid Modelling and Simulation Through PowSyBl -...LF Energy Webinar: Electrical Grid Modelling and Simulation Through PowSyBl -...
LF Energy Webinar: Electrical Grid Modelling and Simulation Through PowSyBl -...
 
Free Complete Python - A step towards Data Science
Free Complete Python - A step towards Data ScienceFree Complete Python - A step towards Data Science
Free Complete Python - A step towards Data Science
 
DevOps and Testing slides at DASA Connect
DevOps and Testing slides at DASA ConnectDevOps and Testing slides at DASA Connect
DevOps and Testing slides at DASA Connect
 
GraphSummit Singapore | The Art of the Possible with Graph - Q2 2024
GraphSummit Singapore | The Art of the  Possible with Graph - Q2 2024GraphSummit Singapore | The Art of the  Possible with Graph - Q2 2024
GraphSummit Singapore | The Art of the Possible with Graph - Q2 2024
 
Securing your Kubernetes cluster_ a step-by-step guide to success !
Securing your Kubernetes cluster_ a step-by-step guide to success !Securing your Kubernetes cluster_ a step-by-step guide to success !
Securing your Kubernetes cluster_ a step-by-step guide to success !
 
Large Language Model (LLM) and it’s Geospatial Applications
Large Language Model (LLM) and it’s Geospatial ApplicationsLarge Language Model (LLM) and it’s Geospatial Applications
Large Language Model (LLM) and it’s Geospatial Applications
 
Goodbye Windows 11: Make Way for Nitrux Linux 3.5.0!
Goodbye Windows 11: Make Way for Nitrux Linux 3.5.0!Goodbye Windows 11: Make Way for Nitrux Linux 3.5.0!
Goodbye Windows 11: Make Way for Nitrux Linux 3.5.0!
 
Mind map of terminologies used in context of Generative AI
Mind map of terminologies used in context of Generative AIMind map of terminologies used in context of Generative AI
Mind map of terminologies used in context of Generative AI
 
Alt. GDG Cloud Southlake #33: Boule & Rebala: Effective AppSec in SDLC using ...
Alt. GDG Cloud Southlake #33: Boule & Rebala: Effective AppSec in SDLC using ...Alt. GDG Cloud Southlake #33: Boule & Rebala: Effective AppSec in SDLC using ...
Alt. GDG Cloud Southlake #33: Boule & Rebala: Effective AppSec in SDLC using ...
 
A tale of scale & speed: How the US Navy is enabling software delivery from l...
A tale of scale & speed: How the US Navy is enabling software delivery from l...A tale of scale & speed: How the US Navy is enabling software delivery from l...
A tale of scale & speed: How the US Navy is enabling software delivery from l...
 
20240605 QFM017 Machine Intelligence Reading List May 2024
20240605 QFM017 Machine Intelligence Reading List May 202420240605 QFM017 Machine Intelligence Reading List May 2024
20240605 QFM017 Machine Intelligence Reading List May 2024
 
GraphSummit Singapore | Enhancing Changi Airport Group's Passenger Experience...
GraphSummit Singapore | Enhancing Changi Airport Group's Passenger Experience...GraphSummit Singapore | Enhancing Changi Airport Group's Passenger Experience...
GraphSummit Singapore | Enhancing Changi Airport Group's Passenger Experience...
 
Secstrike : Reverse Engineering & Pwnable tools for CTF.pptx
Secstrike : Reverse Engineering & Pwnable tools for CTF.pptxSecstrike : Reverse Engineering & Pwnable tools for CTF.pptx
Secstrike : Reverse Engineering & Pwnable tools for CTF.pptx
 
Video Streaming: Then, Now, and in the Future
Video Streaming: Then, Now, and in the FutureVideo Streaming: Then, Now, and in the Future
Video Streaming: Then, Now, and in the Future
 
Encryption in Microsoft 365 - ExpertsLive Netherlands 2024
Encryption in Microsoft 365 - ExpertsLive Netherlands 2024Encryption in Microsoft 365 - ExpertsLive Netherlands 2024
Encryption in Microsoft 365 - ExpertsLive Netherlands 2024
 
RESUME BUILDER APPLICATION Project for students
RESUME BUILDER APPLICATION Project for studentsRESUME BUILDER APPLICATION Project for students
RESUME BUILDER APPLICATION Project for students
 

Keith odom sample microsoft project template data center move

  • 1. % Complete Task Name Finish Resource Names 100% XYZ Company Data Center Re-Location to CO-LO Facility Sat 5/18/13 100% Order MPLS betwwen HQ & CO-LO Facility Tue 1/1/13 XYZ Emp.#1 100% MPLS Installed & Tested Fri 3/1/13 Carrier 100% Order Router Tue 1/1/13 XYZ Emp #2 100% Router Installed, Configured & Tested at CO-LO Facility Fri 3/8/13 XYZ Emp.#1 100% Create From and To Hardware & Network Plan Sat 1/26/13 XYZ Emp.#1 100% Create RFP for Hardware Movers and send out Sun 2/3/13 TKO,Sr. MGMT 100% Project Team Kickoff Fri 2/8/13 Mover,Physical Movers,Sr. MGMT,XYZ Emp #2,XYZ Emp.#1,TKO 100% Evaluate and Execute Hardware Mover Contract Wed 2/27/13 Sr. MGMT,TKO 100% Moving Company Internal Mobilization Wed 3/6/13 Physical Movers 100% Moving Company XYZ Company DC Relocation Materials Order & Receipt Tue 3/5/13 Physical Movers 100% Design Patch Matrix/BOM Development Complete Sat 3/9/13 Physical Movers 100% Order BOM and Delivered for Installation Complete Sun 3/10/13 Physical Movers 100% ‐Destination Site Cable Pre Deployment Complete Fri 3/15/13 Physical Movers 100% QA Patch Matrix (20%) Mon 1/14/13 XYZ Emp.#1,TKO Task Split Milestone Summary Project Summary External Tasks External Milestone Inactive Task Inactive Milestone Inactive Summary Manual Task Duration-only Manual Summary Rollup Manual Summary Start-only Finish-only Deadline Progress Page 1 Project: XYZ Company Data Cente Date: Thu 6/9/16
  • 2. % Complete Task Name Finish Resource Names 100% Customer 1 Operation Backup, Down/UP Processes Tue 3/5/13 XYZ Emp.#1,XYZ Emp #2 100% Customer 2 Operation Backup, Down/UP Processes Thu 3/7/13 XYZ Emp.#1,XYZ Emp #2 100% Customer 3 Operation Backup, Down/UP Processes Sat 3/2/13 XYZ Emp.#1,XYZ Emp #2 100% Customer 4 Operation Backup, Down/UP Processes Sat 3/9/13 XYZ Emp.#1,XYZ Emp #2 100% Customer 5 Operation Backup, Down/UP Processes Fri 3/8/13 XYZ Emp.#1,XYZ Emp #2 100% Customer 6, 7, 8, 9, and 10 Homed on same system Backup, Operation Down/UP Processes Sun 3/17/13 XYZ Emp.#1,XYZ Emp #2 100% Order Redundant Firewall Fri 2/8/13 XYZ Emp.#1 100% Redundant Firewall Delivered Thu 2/14/13 XYZ Emp.#1 100% Install and Configure Redundant Firewall Fri 3/15/13 XYZ Emp.#1 100% Tue 1/1/13 100% Customer Migrations Tue 1/1/13 100% Tue 1/1/13 100% Customer 1 Migration - Also see XYZ Migration 1 schedule at bottom of this plan Fri 3/15/13 100% Notify Customer 1 Client of Plans Sat 1/26/13 Sr. MGMT,TKO Task Split Milestone Summary Project Summary External Tasks External Milestone Inactive Task Inactive Milestone Inactive Summary Manual Task Duration-only Manual Summary Rollup Manual Summary Start-only Finish-only Deadline Progress Page 2 Project: XYZ Company Data Cente Date: Thu 6/9/16
  • 3. % Complete Task Name Finish Resource Names 100% Schedule Customer 1 Client Resources Fri 3/15/13 Sr. MGMT,TKO 100% Operations : Backups, Power Down/Power Up Procedures Fri 3/15/13 XYZ Emp.#1,XYZ Emp #2 100% Perform Syms Backup Fri 3/15/13 XYZ Emp.#1,XYZ Emp #2 100% End all System Processes and verify all jobs are stopped prior to shutdown Fri 3/15/13 XYZ Emp.#1,XYZ Emp #2 100% HMC Power Down all LPARS Fri 3/15/13 XYZ Emp.#1,XYZ Emp #2 100% Customer 1 Physical Migration Fri 3/15/13 Physical Movers 100% Test Conectivity and OPS Consoles Fri 3/15/13 XYZ Emp.#1,XYZ Emp #2 100% Run All "Missed" Jobs during Offline Fri 3/15/13 XYZ Emp.#1,XYZ Emp #2 100% Run HW Test for Drives, Connect, etc. Fri 3/15/13 XYZ Emp.#1,XYZ Emp #2 100% Verify "Stable State" Fri 3/15/13 XYZ Emp.#1,XYZ Emp #2 100% Customer 1 Migration Window Complete Fri 3/15/13 Entire Team 100% Tue 1/1/13 100% Customer Migrations <continue> Tue 1/1/13 100% Customer 4 Migration Fri 3/22/13 Entire Team,TKO,Mon 1/14/13 Task Split Milestone Summary Project Summary External Tasks External Milestone Inactive Task Inactive Milestone Inactive Summary Manual Task Duration-only Manual Summary Rollup Manual Summary Start-only Finish-only Deadline Progress Page 3 Project: XYZ Company Data Cente Date: Thu 6/9/16
  • 4. % Complete Task Name Finish Resource Names 100% Notify Client of Plans Sat 1/26/13 Sr. MGMT,TKO 100% Schedule Client Resources Sat 1/26/13 XYZ Emp.#1,XYZ Emp #2 100% Operations: Backup, Power Down/Power Up Procedures Fri 3/22/13 XYZ Emp.#1,XYZ Emp #2 100% Perform Backup Fri 3/22/13 XYZ Emp.#1,XYZ Emp #2 100% End all System Processes and verify all jobs are stopped prior to shutdownFri 3/22/13 XYZ Emp.#1,XYZ Emp #2 100% Power down Customer 4 IDEAS/GUI Server Tue 1/1/13 XYZ Emp.#1 100% HMC Power Down all LPARS Fri 3/22/13 XYZ Emp.#1,XYZ Emp #2 100% Customer 4 Physical Migration Fri 3/22/13 Physical Movers 100% Power Up Systems Fri 3/22/13 XYZ Emp.#1,XYZ Emp #2 100% Test Conectivity and OPS Consoles Fri 3/22/13 XYZ Emp.#1,XYZ Emp #2 100% Verify "Stable State" Fri 3/22/13 XYZ Emp #2,Chris H.,XYZ Emp.#1 100% Customer 4 Migration Window Complete Fri 3/22/13 Entire Team 100% Run Missed Jobs – MSGSDIMSG and EOD Process Fri 3/22/13 XYZ Emp #2 100% Qinter Up – System available to users Fri 3/22/13 XYZ Emp #2 Task Split Milestone Summary Project Summary External Tasks External Milestone Inactive Task Inactive Milestone Inactive Summary Manual Task Duration-only Manual Summary Rollup Manual Summary Start-only Finish-only Deadline Progress Page 4 Project: XYZ Company Data Cente Date: Thu 6/9/16
  • 5. % Complete Task Name Finish Resource Names 100% Customer 2 Migration/Implementation Tue 4/2/13 100% Notify Client of Plans Sat 1/26/13 Sr. MGMT 100% Schedule Client Resources Mon 1/14/13 TKO,Sr. MGMT,XYZ Emp.#1 100% Operations: Backup, Power Down Power Up Procedures Tue 4/9/13 XYZ Emp.#1,XYZ Emp #2 100% Perform Full System Backup 1:00 am Monday Mon 4/1/13 XYZ Emp.#1,XYZ Emp #2 100% Perform Intel Backups Mon 4/1/13 XYZ Emp.#1 100% End all System Processes and verify all jobs are stopped prior to shutdown Sat 4/27/13 XYZ Emp.#1,XYZ Emp #2 100% Perform Incremental backup Mon 4/1/13 XYZ Emp #2 Task Split Milestone Summary Project Summary External Tasks External Milestone Inactive Task Inactive Milestone Inactive Summary Manual Task Duration-only Manual Summary Rollup Manual Summary Start-only Finish-only Deadline Progress Page 5 Project: XYZ Company Data Cente Date: Thu 6/9/16
  • 6. % Complete Task Name Finish Resource Names 100% Power Down VMs Tue 4/2/13 XYZ Emp.#1 100% Power Down VM Host Tue 4/2/13 XYZ Emp.#1 100% Power Down AS400 System Tue 4/2/13 XYZ Emp.#1,XYZ Emp #2 100% Power Down Network Equipment Tue 4/2/13 XYZ Emp.#1 100% Customer 2 Physical Migration Tue 4/2/13 Physical Movers 100% Power up Network Equipment Tue 4/2/13 XYZ Emp.#1 Task Split Milestone Summary Project Summary External Tasks External Milestone Inactive Task Inactive Milestone Inactive Summary Manual Task Duration-only Manual Summary Rollup Manual Summary Start-only Finish-only Deadline Progress Page 6 Project: XYZ Company Data Cente Date: Thu 6/9/16
  • 7. % Complete Task Name Finish Resource Names 100% Power up San Device Wed 4/3/13 XYZ Emp.#1 100% Power up FD-Bckup Server (Check San is up & Check network is up) Wed 4/3/13 XYZ Emp.#1 100% Power UP VM Host Wed 4/3/13 XYZ Emp.#1 100% Power up VM's Wed 4/3/13 XYZ Emp.#1 100% Power on the HMC Managed Server Wed 4/3/13 XYZ Emp #2 100% Power on the Systems – FLDMMS first- Wait for *NWS – others can go Wed 4/3/13 XYZ Emp #2 100% Power on Tape Drives Wed 4/3/13 XYZ Emp #2 100% Test Conectivity and OPS Consoles Wed 4/3/13 XYZ Emp.#1,XYZ Emp #2 100% Run missed schedules on FLD side (E3) Wed 4/3/13 Customer 2 Task Split Milestone Summary Project Summary External Tasks External Milestone Inactive Task Inactive Milestone Inactive Summary Manual Task Duration-only Manual Summary Rollup Manual Summary Start-only Finish-only Deadline Progress Page 7 Project: XYZ Company Data Cente Date: Thu 6/9/16
  • 8. % Complete Task Name Finish Resource Names 100% Run All "Missed" Jobs during Offline Wed 4/3/13 XYZ Emp.#1,XYZ Emp #2 100% Verify "Stable State" Wed 4/3/13 XYZ Emp.#1,XYZ Emp #2 100% Custome 2 Migration/Implementation Window Complete Wed 4/3/13 Entire Team 100% Customer 5 Migration Wed 3/20/13 100% Notify Client of Plans Sat 1/26/13 Sr. MGMT,TKO Task Split Milestone Summary Project Summary External Tasks External Milestone Inactive Task Inactive Milestone Inactive Summary Manual Task Duration-only Manual Summary Rollup Manual Summary Start-only Finish-only Deadline Progress Page 8 Project: XYZ Company Data Cente Date: Thu 6/9/16
  • 9. % Complete Task Name Finish Resource Names 100% Schedule Client Resources Mon 1/14/13 TKO,Sr. MGMT 100% Operations: Backup, Power Down/Power Up Procedures Fri 4/5/13 XYZ Emp.#1,XYZ Emp #2 100% Perform Backup Thu 4/4/13 XYZ Emp.#1,XYZ Emp #2 100% End all System Processes and verify all jobs are stopped prior to shutdown Fri 4/5/13 XYZ Emp.#1,XYZ Emp #2 100% HMC Power Down all LPARS Fri 4/5/13 XYZ Emp.#1,XYZ Emp #2 100% Customer 5 Physical Migration Fri 4/5/13 Physical Movers 100% Test Conectivity and OPS Consoles Fri 4/5/13 XYZ Emp.#1,XYZ Emp #2 100% Run All "Missed" Jobs during Offline Fri 4/5/13 XYZ Emp.#1,XYZ Emp #2 100% Run HW Test for Drives, Connect, etc. Fri 4/5/13 XYZ Emp.#1,XYZ Emp #2 100% Verify "Stable State" Fri 4/5/13 XYZ Emp.#1,XYZ Emp #2 100% Customer 5 Migration Window Complete Tue 3/19/13 Entire Team Task Split Milestone Summary Project Summary External Tasks External Milestone Inactive Task Inactive Milestone Inactive Summary Manual Task Duration-only Manual Summary Rollup Manual Summary Start-only Finish-only Deadline Progress Page 9 Project: XYZ Company Data Cente Date: Thu 6/9/16
  • 10. % Complete Task Name Finish Resource Names 100% Customer 3 Migration Sun 4/28/13 100% Notify Client of Plans Sat 1/26/13 Sr. MGMT,TKO 100% Order Client Links Mon 1/21/13 XYZ Emp.#1,XYZ Contact 100% Links Installed & Ready Sat 3/16/13 Carrier 100% CO-LO Cross Connect Sat 3/23/13 Data Center Co_Lo 100% Schedule Carrier for Migration Date Sat 3/2/13 TKO,XYZ Emp.#1 100% Schedule Client Resources Fri 3/15/13 TKO,Sr. MGMT 100% Operations: Backup, Power Down/Power Up Procedures Sat 4/27/13 XYZ Emp.#1,XYZ Emp #2 100% Perform Backup Sat 4/6/13 XYZ Emp.#1,XYZ Emp #2 100% End all System Processes and verify all jobs are stopped prior to shutdown Sun 4/7/13 XYZ Emp.#1,XYZ Emp #2 100% HMC Power Down all LPARS Mon 4/8/13 XYZ Emp.#1,XYZ Emp #2 100% Customer 3 Physical Migration Sun 4/7/13 Physical Movers Task Split Milestone Summary Project Summary External Tasks External Milestone Inactive Task Inactive Milestone Inactive Summary Manual Task Duration-only Manual Summary Rollup Manual Summary Start-only Finish-only Deadline Progress Page 10 Project: XYZ Company Data Cente Date: Thu 6/9/16
  • 11. % Complete Task Name Finish Resource Names 100% Test Conectivity and OPS Consoles Mon 4/8/13 XYZ Emp.#1,XYZ Emp #2 100% Run All "Missed" Jobs during Offline Sun 4/7/13 XYZ Emp.#1,XYZ Emp #2 100% Run HW Test for Drives, Connect, etc. Sun 4/7/13 XYZ Emp.#1,XYZ Emp #2 100% Verify "Stable State" Sun 4/7/13 XYZ Emp.#1,XYZ Emp #2 100% Customer 3 Migration Window Complete Sun 4/7/13 Entire Team 100% Shared Equipment (SE) Migration (Customers 6, 7, 8, 9 and 10) Wed 5/1/13 100% Notify Client of Plans Sat 1/26/13 Sr. MGMT,TKO 100% Schedule Client Resources Tue 1/1/13 XYZ Emp.#1,XYZ Emp #2 100% Operations: Backup, Power Down Power Up Procedures Tue 4/30/13 XYZ Emp.#1,XYZ Emp #2 100% Perform Backup Thu 4/11/13 XYZ Emp.#1,XYZ Emp #2 100% End all System Processes and verify all jobs are stopped prior to shutdown Fri 4/12/13 XYZ Emp.#1,XYZ Emp #2 Task Split Milestone Summary Project Summary External Tasks External Milestone Inactive Task Inactive Milestone Inactive Summary Manual Task Duration-only Manual Summary Rollup Manual Summary Start-only Finish-only Deadline Progress Page 11 Project: XYZ Company Data Cente Date: Thu 6/9/16
  • 12. % Complete Task Name Finish Resource Names 100% HMC Power Down all LPARS Fri 4/12/13 XYZ Emp.#1,XYZ Emp #2 100% SE Physical Migration Sat 4/13/13 Physical Movers 100% Test Conectivity and OPS Consoles Sat 4/13/13 XYZ Emp.#1,XYZ Emp #2 100% Run All "Missed" Jobs during Offline Sat 4/13/13 XYZ Emp.#1,XYZ Emp #2 100% Run HW Test for Drives, Connect, etc. Sat 4/13/13 XYZ Emp.#1,XYZ Emp #2 100% Verify "Stable State" Sat 4/13/13 XYZ Emp.#1,XYZ Emp #2 100% (SE) Migration Window Complete Sat 4/13/13 Entire Team 100% Customer XYZ Migration #2 Sun 4/21/13 100% Notify Client of Plans / Normal Change Management Processes Used Fri 1/25/13 Sr. MGMT,TKO 100% Order Client Links (Megapath 3 T1's) Mon 1/21/13 XYZ Contact,TKO 100% Schedule Carrier for Migration Date Mon 1/21/13 Jay R. Task Split Milestone Summary Project Summary External Tasks External Milestone Inactive Task Inactive Milestone Inactive Summary Manual Task Duration-only Manual Summary Rollup Manual Summary Start-only Finish-only Deadline Progress Page 12 Project: XYZ Company Data Cente Date: Thu 6/9/16
  • 13. % Complete Task Name Finish Resource Names 100% Schedule Client Resources Fri 2/22/13 John D.,Jay R.,Sr. MGMT,TKO,XYZ 100% Links Installed & Ready Wed 3/20/13 Carrier 100% Co-Lo Cross Connect Wed 3/20/13 Data Center Co_Lo 100% Network Testing Complete Thu 3/21/13 John Doe 100% Perform AS400 Backup Fri 4/19/13 John Doe 100% FRMMS full backup Fri 4/19/13 XYZ 100% FRRI full backup Fri 4/19/13 100% Perform Windows Backup Fri 4/19/13 Jane May 100% Scheduled Windows Backup Fri 4/19/13 Jane May 100% End all System Processes and verify all jobs are stopped prior to shutdown Fri 4/19/13 John Doe,Jane May 100% Graceful Powerdown AS400 System Fri 4/19/13 Jay R.,John D. 100% Robot Jobs Identified - held Fri 4/19/13 John Doe 100% Outside Windows FTP servers Fri 4/19/13 John Doe 100% Windows Scheduled Jobs Off Fri 4/19/13 John Doe 100% Shutdown FRMMS/FRRI Fri 4/19/13 John Doe 100% Power down managed system (FRMMS) Fri 4/19/13 John Doe 100% Power down managed system (FRRI) Fri 4/19/13 John Doe 100% Power down HMC Fri 4/19/13 John Doe 100% Power down 2 Tape Libraries Fri 4/19/13 John Doe Task Split Milestone Summary Project Summary External Tasks External Milestone Inactive Task Inactive Milestone Inactive Summary Manual Task Duration-only Manual Summary Rollup Manual Summary Start-only Finish-only Deadline Progress Page 13 Project: XYZ Company Data Cente Date: Thu 6/9/16
  • 14. % Complete Task Name Finish Resource Names 100% Graceful Powerdown Windows System Fri 4/19/13 Jane May 100% Power down VMs (5 mins to power down each VM) a. .18 subnet = XYZCenteraldev, XYZ-DNS,XYZ-CRM, XYZ-GUI, XYZ-IDEAS, XYZ-SAFri 4/19/13 Jane May 100% Power down physical VM Server (5 mins to power down each VM Host) a. Host 1 & Host2Fri 4/19/13 Jane May 100% Power down xyzintprod.servers.xyz 192.168.X.X IBM 3850 Fri 4/19/13 Jane May 100% Power Down xyzallocation.servers.xyz 192.168.X.X System x3550Fri 4/19/13 Jane May 100% Power down xyzentralprod.servers... 192.168.X.X System x3550Fri 4/19/13 Jane May 100% Power down xyzinttest.servers.xyz 192.168.X.X System x3550 Fri 4/19/13 XYZ Emp.#1 100% Power down xyz-emn1-bk1.servers.xyz 192.168.X.X Fri 4/19/13 XYZ Emp.#1 100% Power down SAN devices (5 mins to power down SAN devices)Fri 4/19/13 XYZ Emp.#1 100% Physical Migration to Co-Lo except Credit Auth Fri 4/19/13 Physical Movers 100% Power down xyzisd.servers.xyz 192.168.0.X System x3550 Fri 4/19/13 XYZ Emp.#1 100% Power down xyzsdhot.servers.xyz 192.168.X.X System x3550 Fri 4/19/13 XYZ Emp.#1 100% Power down xyzisdwarm.servers.xyz 192.168.X.X System x3550 Fri 4/19/13 XYZ Emp.#1 100% Power down SAN devices (5 mins to power down SAN devices) Fri 4/19/13 XYZ Emp.#1 100% Power down xyzisdbkup.servers.xyz 192.168.X.X System x3550 Fri 4/19/13 XYZ Emp.#1 100% Power Down XYZ network equipment Fri 4/19/13 XYZ Emp.#1 100% XYZ 2nd Physical Migration to Co-Lo ( Credit Auth ) Fri 4/19/13 Physical Movers Task Split Milestone Summary Project Summary External Tasks External Milestone Inactive Task Inactive Milestone Inactive Summary Manual Task Duration-only Manual Summary Rollup Manual Summary Start-only Finish-only Deadline Progress Page 14 Project: XYZ Company Data Cente Date: Thu 6/9/16
  • 15. % Complete Task Name Finish Resource Names 100% Power UP AS400 System Sat 4/20/13 100% Power up Tape Library Sat 4/20/13 XYZ Emp #2 100% Power up HMC Sat 4/20/13 XYZ Emp #2 100% Power up managed system (FRMMS) Sat 4/20/13 XYZ Emp #2 100% Power up managed system (FRRI) Sat 4/20/13 XYZ Emp #2 100% TCP001 job started - FRMMS Sat 4/20/13 XYZ Emp #2 100% Outside Windows FTP servers communicating Sat 4/20/13 XYZ Emp #2 100% Windows Scheduler Started Sat 4/20/13 XYZ Emp #2 100% Startup Robot Sat 4/20/13 XYZ Emp #2 100% Release Missed jobs Sat 4/20/13 XYZ Emp #2 100% Power UP Windows System Sat 4/20/13 100% Power on SAN devices (15 mins to power on SAN devices) Sat 4/20/13 XYZ Emp.#1 100% Power UP xyzisdbkup.servers.xyz 192.168.X.X System x3550 Sat 4/20/13 XYZ Emp.#1 100% Power UP 1st- xyz-emn1-bk1.servers.xyz 192.168.X.X Sat 4/20/13 XYZ Emp.#1 100% Power on physical Windows Servers (10-15 min to power on each server) Exact boot order for A-ESat 4/20/13 XYZ Emp.#1 100% Power on VMs (2 mins to power on each VM) a. XYZCenteraldev, XYZ-DNS, XYZ-CRM, XYZ-GUI, XYZ-IDEAS, XYZ-SALLOSat 4/20/13 XYZ Emp.#1 100% Power UP a. xyzintprod.servers.xyz 192.168.X.X IBM 3850 Sat 4/20/13 XYZ Emp.#1 100% Power UP b. xyzisd.servers.xyz 192.168.X.X System x3550 Sat 4/20/13 XYZ Emp.#1 100% Power UP b. xyzentralprod.servers... 192.168.X.X System x3550Sat 4/20/13 XYZ Emp.#1 100% Power UP d. xyzisdhot.servers.xyz 192.168.X.X System x3550 Sat 4/20/13 XYZ Emp.#1 Task Split Milestone Summary Project Summary External Tasks External Milestone Inactive Task Inactive Milestone Inactive Summary Manual Task Duration-only Manual Summary Rollup Manual Summary Start-only Finish-only Deadline Progress Page 15 Project: XYZ Company Data Cente Date: Thu 6/9/16
  • 16. % Complete Task Name Finish Resource Names 100% Power UP e. xyzisdwarm.servers.xyz 192.168.X.X System x3550 Sat 4/20/13 XYZ Emp.#1 100% Power UP f. xyzallocation.servers.xyz 192.168.X.X System x3550Sat 4/20/13 XYZ Emp.#1 100% Power UP h. xyzinttest.servers.xyz 192.168.X.X System x3550Sat 4/20/13 XYZ Emp.#1 100% Power on physical VM Server (10-15 mins to power down each VM Host) a. Host 1 & Host2Sat 4/20/13 XYZ Emp.#1 100% Test Conectivity and OPS Consoles Sat 4/20/13 XYZ Emp.#1,XYZ Emp #2 100% Run All "Missed" Jobs during Offline Sat 4/20/13 XYZ Emp.#1,XYZ Emp #2 100% Run HW Test for Drives, Connect, etc. Sat 4/20/13 XYZ Emp.#1,XYZ Emp #2 100% Operations Post-Move Checklist Sat 4/20/13 XYZ Emp.#1,XYZ Emp #2 100% Power up system at Co-Lo Sat 4/20/13 XYZ Emp #2 100% Start the HMC Sat 4/20/13 XYZ Emp #2 100% Start the partitions Sat 4/20/13 XYZ Emp #2 100% Verify Communications to Iseries/Client Access Sat 4/20/13 XYZ Emp #2 100% Windows server/s to system verification Sat 4/20/13 XYZ Emp.#1 100% Subsystems up Sat 4/20/13 XYZ Emp #2 100% Netserver running Sat 4/20/13 XYZ Emp.#1 100% Client Checkpoint – (network and communications ok) Sat 4/20/13 XYZ Emp.#1 100% Qinter Up Sat 4/20/13 XYZ Emp #2 100% Users allowed back onto the system Sat 4/20/13 XYZ Emp #2 Task Split Milestone Summary Project Summary External Tasks External Milestone Inactive Task Inactive Milestone Inactive Summary Manual Task Duration-only Manual Summary Rollup Manual Summary Start-only Finish-only Deadline Progress Page 16 Project: XYZ Company Data Cente Date: Thu 6/9/16
  • 17. % Complete Task Name Finish Resource Names 100% Retail Ideas – IDE210CL released and running (was initially on hold)Sat 4/20/13 XYZ Emp #2 100% Verify any Jobs/applications that need to be running – exa: Logagent, TCP001, etcSat 4/20/13 XYZ Emp #2 100% Jwalk up – if necessary Sat 4/20/13 XYZ Emp #2 100% JOBQ’s released Sat 4/20/13 XYZ Emp #2 100% Robot Started Sat 4/20/13 XYZ Emp #2 100% Robot jobs released and caught up to Current time Sat 4/20/13 XYZ Emp #2 100% Release IBM scheduler if necessary Sat 4/20/13 XYZ Emp #2 100% Release Windows scheduled jobs Sat 4/20/13 XYZ Emp.#1 100% Release Windows scheduled jobs Sat 4/20/13 XYZ Emp.#1 100% Verify "Stable State" Sat 5/18/13 XYZ Emp.#1,XYZ Emp #2 100% XYZ Migration Window Complete Sat 4/20/13 Entire Team 100% XYZ Test Systems Sat 4/20/13 XYZ Contact 100% Run End of Day Processes Sat 4/20/13 XYZ Emp #2 100% XYZ Company Migration #1 Fri 3/15/13 100% Notify Client of Plans Tue 1/1/13 Sr. MGMT,TKO 100% Operations : Backups, Power Down/Power Up Procedures Fri 3/15/13 XYZ Emp.#1 100% Perform XYZ Company Backup Fri 3/15/13 XYZ Emp.#1 100% End all System Processes and applications prior to shutdown Fri 3/15/13 XYZ Emp.#1 100% System and Network Equipment Power Down Fri 3/15/13 XYZ Emp.#1 Task Split Milestone Summary Project Summary External Tasks External Milestone Inactive Task Inactive Milestone Inactive Summary Manual Task Duration-only Manual Summary Rollup Manual Summary Start-only Finish-only Deadline Progress Page 17 Project: XYZ Company Data Cente Date: Thu 6/9/16
  • 18. % Complete Task Name Finish Resource Names 100% XYZ Company Physical Migration Fri 3/15/13 Physical Movers 100% Breakdown/Packing Fri 3/15/13 Physical Movers 100% Travel Fri 3/15/13 Physical Movers 100% Rack & Stack Fri 3/15/13 Physical Movers 100% Cable Services Fri 3/15/13 Physical Movers 100% Power up Network and Systems Tue 1/1/13 XYZ Emp.#1,Cisco Engineer 100% Test Conectivity and OPS Consoles Fri 3/15/13 XYZ Emp.#1 100% Verify VMs, WEB, Blackberry back ONLINE Fri 3/15/13 XYZ Emp.#1 100% Run HW Test for Drives, Connect, etc. Fri 3/15/13 XYZ Emp.#1 100% Verify "Stable State" Fri 3/15/13 XYZ Emp.#1,XYZ Emp #2 100% XYZ Company Migration Window Complete Fri 3/15/13 Entire Team Task Split Milestone Summary Project Summary External Tasks External Milestone Inactive Task Inactive Milestone Inactive Summary Manual Task Duration-only Manual Summary Rollup Manual Summary Start-only Finish-only Deadline Progress Page 18 Project: XYZ Company Data Cente Date: Thu 6/9/16
  • 19. Notes Lead by TKO Week of March 11th Week of March 11th Week of March 11th 1/1 Carrier XYZ Emp #2 XYZ Emp.#1 XYZ Emp.#1 TKO,Sr. MGMT 2/8 Sr. MGMT,TKO Physical Movers Physical Movers 3/9 Physical Movers Physical Movers XYZ Emp.#1,TKO 16 23 30 6 13 20 27 3 10 17 24 3 10 17 24 31 7 14 21 28 5 12 19 26 2 9 16 23 30 Dec '12 Jan '13 Feb '13 Mar '13 Apr '13 May '13 Jun '13 Task Split Milestone Summary Project Summary External Tasks External Milestone Inactive Task Inactive Milestone Inactive Summary Manual Task Duration-only Manual Summary Rollup Manual Summary Start-only Finish-only Deadline Progress Page 19 Project: XYZ Company Data Cente Date: Thu 6/9/16
  • 20. Notes Scheduled for March 21st Scheduled: March 15th 9:00am Est. / BOM and Cable order dependancy XYZ Emp.#1,XYZ Emp #2 XYZ Emp.#1,XYZ Emp #2 XYZ Emp.#1,XYZ Emp #2 XYZ Emp.#1,XYZ Emp #2 XYZ Emp.#1,XYZ Emp #2 XYZ Emp.#1,XYZ Emp #2 2/8 XYZ Emp.#1 XYZ Emp.#1 3/15 Sr. MGMT,TKO 16 23 30 6 13 20 27 3 10 17 24 3 10 17 24 31 7 14 21 28 5 12 19 26 2 9 16 23 30 Dec '12 Jan '13 Feb '13 Mar '13 Apr '13 May '13 Jun '13 Task Split Milestone Summary Project Summary External Tasks External Milestone Inactive Task Inactive Milestone Inactive Summary Manual Task Duration-only Manual Summary Rollup Manual Summary Start-only Finish-only Deadline Progress Page 20 Project: XYZ Company Data Cente Date: Thu 6/9/16
  • 21. Notes Customer 1 Power Down Tasks... Start of Maintenance Window - 9:00am 3:00 pm Est. Scheduled: March 22nd/ BOM and Cable order dependancy 3/15 3/15 XYZ Emp.#1,XYZ Emp #2 3/15 3/15 Physical Movers 3/15 3/15 3/15 XYZ Emp.#1,XYZ Emp #2 Entire Team Entire Team,TKO,Mon 1/14/13 16 23 30 6 13 20 27 3 10 17 24 3 10 17 24 31 7 14 21 28 5 12 19 26 2 9 16 23 30 Dec '12 Jan '13 Feb '13 Mar '13 Apr '13 May '13 Jun '13 Task Split Milestone Summary Project Summary External Tasks External Milestone Inactive Task Inactive Milestone Inactive Summary Manual Task Duration-only Manual Summary Rollup Manual Summary Start-only Finish-only Deadline Progress Page 21 Project: XYZ Company Data Cente Date: Thu 6/9/16
  • 22. Notes Power Down Tasks... 08:00 PM – 2 hours 10:00 PM 10:00PM 10:10PM (9:36pm) 10:10PM (9:36pm) - (Turn over to Moving Company) - 7 hours to move (3:36am 6 hours) 5:10am April 2nd (3:36am) 5:10am April 2nd 5:30am April 2nd 5:30am April 2nd 3 hours 8:30am EST (6:52am EST) Sr. MGMT,TKO XYZ Emp.#1,XYZ Emp #2 3/22 XYZ Emp.#1,XYZ Emp #2 XYZ Emp.#1,XYZ Emp #2 XYZ Emp.#1 XYZ Emp.#1,XYZ Emp #2 Physical Movers XYZ Emp.#1,XYZ Emp #2 XYZ Emp.#1,XYZ Emp #2 XYZ Emp #2,Chris H.,XYZ Emp.#1 Entire Team XYZ Emp #2 XYZ Emp #2 16 23 30 6 13 20 27 3 10 17 24 3 10 17 24 31 7 14 21 28 5 12 19 26 2 9 16 23 30 Dec '12 Jan '13 Feb '13 Mar '13 Apr '13 May '13 Jun '13 Task Split Milestone Summary Project Summary External Tasks External Milestone Inactive Task Inactive Milestone Inactive Summary Manual Task Duration-only Manual Summary Rollup Manual Summary Start-only Finish-only Deadline Progress Page 22 Project: XYZ Company Data Cente Date: Thu 6/9/16
  • 23. Notes Scheduled : April 2nd (TUESDAY) - 2:30pm Est. Power Down Tasks... 1:30PM - 2:30PM 2:30pm 2:30pm - FLDE3 – 1hr, FLDITG – 1hr 45min, FLDMMS – 1hr 30min, FLDRI – 10min ( all at the same time so (2hrs max for all)) 4/2 Sr. MGMT TKO,Sr. MGMT,XYZ Emp.#1 XYZ Emp.#1,XYZ Emp #2 XYZ Emp.#1,XYZ Emp #2 XYZ Emp.#1 XYZ Emp.#1,XYZ Emp #2 XYZ Emp #2 16 23 30 6 13 20 27 3 10 17 24 3 10 17 24 31 7 14 21 28 5 12 19 26 2 9 16 23 30 Dec '12 Jan '13 Feb '13 Mar '13 Apr '13 May '13 Jun '13 Task Split Milestone Summary Project Summary External Tasks External Milestone Inactive Task Inactive Milestone Inactive Summary Manual Task Duration-only Manual Summary Rollup Manual Summary Start-only Finish-only Deadline Progress Page 23 Project: XYZ Company Data Cente Date: Thu 6/9/16
  • 24. Notes FD-CentralProd – power down 2:30pm, FD-INTProd – power down 2:31pm, FD-CRMDEV power down 2:33pm, FD-CRMProd Power down 2:35pm, FD-IDEASProd power down 2:36pm, FD-SilvonProd power down 2:38pm ESX Host1 power down 2:45pm, ESX Host2 power down 2:45pm, FD-Bkup power down 2:50pm, FD-IBMSAN power down 2:50 4:30PM 4:30PM 5:15PM (4:31) (Turn over to Moving Company) - 10 hours to move 3:15AM April 3rd (12:00am) XYZ Emp.#1 XYZ Emp.#1 XYZ Emp.#1,XYZ Emp #2 XYZ Emp.#1 Physical Movers XYZ Emp.#1 16 23 30 6 13 20 27 3 10 17 24 3 10 17 24 31 7 14 21 28 5 12 19 26 2 9 16 23 30 Dec '12 Jan '13 Feb '13 Mar '13 Apr '13 May '13 Jun '13 Task Split Milestone Summary Project Summary External Tasks External Milestone Inactive Task Inactive Milestone Inactive Summary Manual Task Duration-only Manual Summary Rollup Manual Summary Start-only Finish-only Deadline Progress Page 24 Project: XYZ Company Data Cente Date: Thu 6/9/16
  • 25. Notes 3:15am April 3rd (12:03am) 3:30am April 3rd (12:03 am) 3:45AM April 3rd (12:03 am) 4:00AM April 3rd (12:03 am) 4:15am (10 min) (12:30am - HMC Internal Drive Failure - IBM Dispatched) 4:25am (20 min) (5:45am) 4:45am (5 min) (12:30am) 4:45AM April 3rd (6:00am) 4:45AM April 3rd (6:28am) XYZ Emp.#1 XYZ Emp.#1 XYZ Emp.#1 XYZ Emp.#1 XYZ Emp #2 XYZ Emp #2 XYZ Emp #2 XYZ Emp.#1,XYZ Emp #2 Customer 2 16 23 30 6 13 20 27 3 10 17 24 3 10 17 24 31 7 14 21 28 5 12 19 26 2 9 16 23 30 Dec '12 Jan '13 Feb '13 Mar '13 Apr '13 May '13 Jun '13 Task Split Milestone Summary Project Summary External Tasks External Milestone Inactive Task Inactive Milestone Inactive Summary Manual Task Duration-only Manual Summary Rollup Manual Summary Start-only Finish-only Deadline Progress Page 25 Project: XYZ Company Data Cente Date: Thu 6/9/16
  • 26. Notes FLDRI – None, FLDE3 -ASR_SWAP SCD USER DEF 05:35:00 *WEEKLY, AWR_SKUOUT SCD USER DEF 05:30:00 *WEEKLY , AWR_SWAP SCD USER,DEF 05:35:00 *WEEKLY, RUNALLPO SCD *ALL 21:45:00 *WEEKLY, RUNAMPO SCD USER DEF 06:15:00 *WEEKLY , RUNASR SCD USER DEF 05:00:00 *WEEKL 4:45AM (6:45am) Target Completion : 5:00am April 3rd (6:45am) Schedule : April 5th - 9:00am XYZ Emp.#1,XYZ Emp #2 XYZ Emp.#1,XYZ Emp #2 Entire Team 3/20 Sr. MGMT,TKO 16 23 30 6 13 20 27 3 10 17 24 3 10 17 24 31 7 14 21 28 5 12 19 26 2 9 16 23 30 Dec '12 Jan '13 Feb '13 Mar '13 Apr '13 May '13 Jun '13 Task Split Milestone Summary Project Summary External Tasks External Milestone Inactive Task Inactive Milestone Inactive Summary Manual Task Duration-only Manual Summary Rollup Manual Summary Start-only Finish-only Deadline Progress Page 26 Project: XYZ Company Data Cente Date: Thu 6/9/16
  • 27. Notes Power Down Tasks... 10:30 AM April 5th (Turn over to Moving Company) 10 hours to move 9:00 PM April 5th TKO,Sr. MGMT XYZ Emp.#1,XYZ Emp #2 XYZ Emp.#1,XYZ Emp #2 XYZ Emp.#1,XYZ Emp #2 XYZ Emp.#1,XYZ Emp #2 4/5 XYZ Emp.#1,XYZ Emp #2 XYZ Emp.#1,XYZ Emp #2 XYZ Emp.#1,XYZ Emp #2 XYZ Emp.#1,XYZ Emp #2 Entire Team 16 23 30 6 13 20 27 3 10 17 24 3 10 17 24 31 7 14 21 28 5 12 19 26 2 9 16 23 30 Dec '12 Jan '13 Feb '13 Mar '13 Apr '13 May '13 Jun '13 Task Split Milestone Summary Project Summary External Tasks External Milestone Inactive Task Inactive Milestone Inactive Summary Manual Task Duration-only Manual Summary Rollup Manual Summary Start-only Finish-only Deadline Progress Page 27 Project: XYZ Company Data Cente Date: Thu 6/9/16
  • 28. Notes Scheduled April 7th 1:00 AM Open ticket with Carrier for Migration times Power Down Tasks... 12:15AM April 7 (Turn over to Moving Company) 9.5 hours to move (see Move Plan) Sr. MGMT,TKO XYZ Emp.#1,XYZ Contact Carrier Data Center Co_Lo 3/2 TKO,Sr. MGMT XYZ Emp.#1,XYZ Emp #2 XYZ Emp.#1,XYZ Emp #2 XYZ Emp.#1,XYZ Emp #2 XYZ Emp.#1,XYZ Emp #2 Physical Movers 16 23 30 6 13 20 27 3 10 17 24 3 10 17 24 31 7 14 21 28 5 12 19 26 2 9 16 23 30 Dec '12 Jan '13 Feb '13 Mar '13 Apr '13 May '13 Jun '13 Task Split Milestone Summary Project Summary External Tasks External Milestone Inactive Task Inactive Milestone Inactive Summary Manual Task Duration-only Manual Summary Rollup Manual Summary Start-only Finish-only Deadline Progress Page 28 Project: XYZ Company Data Cente Date: Thu 6/9/16
  • 29. Notes 12:00PM April 7 (per Move Plan) Schedule : April 12th - 10:00pm to 6:00am Power Down Tasks... XYZ Emp.#1,XYZ Emp #2 XYZ Emp.#1,XYZ Emp #2 XYZ Emp.#1,XYZ Emp #2 XYZ Emp.#1,XYZ Emp #2 Entire Team Sr. MGMT,TKO XYZ Emp.#1,XYZ Emp #2 XYZ Emp.#1,XYZ Emp #2 XYZ Emp.#1,XYZ Emp #2 XYZ Emp.#1,XYZ Emp #2 16 23 30 6 13 20 27 3 10 17 24 3 10 17 24 31 7 14 21 28 5 12 19 26 2 9 16 23 30 Dec '12 Jan '13 Feb '13 Mar '13 Apr '13 May '13 Jun '13 Task Split Milestone Summary Project Summary External Tasks External Milestone Inactive Task Inactive Milestone Inactive Summary Manual Task Duration-only Manual Summary Rollup Manual Summary Start-only Finish-only Deadline Progress Page 29 Project: XYZ Company Data Cente Date: Thu 6/9/16
  • 30. Notes 10:30PM - (Turn over to Moving Company) - 7 hours to move 5:30am April 13th 6:00am April 13 Open ticket with Carrier for Migration Window XYZ Emp.#1,XYZ Emp #2 Physical Movers XYZ Emp.#1,XYZ Emp #2 XYZ Emp.#1,XYZ Emp #2 XYZ Emp.#1,XYZ Emp #2 XYZ Emp.#1,XYZ Emp #2 Entire Team Sr. MGMT,TKO XYZ Contact,TKO 1/21 16 23 30 6 13 20 27 3 10 17 24 3 10 17 24 31 7 14 21 28 5 12 19 26 2 9 16 23 30 Dec '12 Jan '13 Feb '13 Mar '13 Apr '13 May '13 Jun '13 Task Split Milestone Summary Project Summary External Tasks External Milestone Inactive Task Inactive Milestone Inactive Summary Manual Task Duration-only Manual Summary Rollup Manual Summary Start-only Finish-only Deadline Progress Page 30 Project: XYZ Company Data Cente Date: Thu 6/9/16
  • 31. Notes Date and Time Verified Upon Formal Approval - Start of Maintenance Window - 2:00am Power Down Tasks... John D.,Jay R.,Sr. MGMT,TKO,XYZ Carrier Data Center Co_Lo 3/21 XYZ Jane May John Doe,Jane May John Doe John Doe John Doe John Doe John Doe John Doe John Doe John Doe 16 23 30 6 13 20 27 3 10 17 24 3 10 17 24 31 7 14 21 28 5 12 19 26 2 9 16 23 30 Dec '12 Jan '13 Feb '13 Mar '13 Apr '13 May '13 Jun '13 Task Split Milestone Summary Project Summary External Tasks External Milestone Inactive Task Inactive Milestone Inactive Summary Manual Task Duration-only Manual Summary Rollup Manual Summary Start-only Finish-only Deadline Progress Page 31 Project: XYZ Company Data Cente Date: Thu 6/9/16
  • 32. Notes Power Down Tasks... Except Credit Auth Servers - Est 14 hours Estimated 2 hours Jane May Jane May Jane May Jane May Jane May XYZ Emp.#1 XYZ Emp.#1 XYZ Emp.#1 Physical Movers XYZ Emp.#1 XYZ Emp.#1 XYZ Emp.#1 XYZ Emp.#1 XYZ Emp.#1 XYZ Emp.#1 Physical Movers 16 23 30 6 13 20 27 3 10 17 24 3 10 17 24 31 7 14 21 28 5 12 19 26 2 9 16 23 30 Dec '12 Jan '13 Feb '13 Mar '13 Apr '13 May '13 Jun '13 Task Split Milestone Summary Project Summary External Tasks External Milestone Inactive Task Inactive Milestone Inactive Summary Manual Task Duration-only Manual Summary Rollup Manual Summary Start-only Finish-only Deadline Progress Page 32 Project: XYZ Company Data Cente Date: Thu 6/9/16
  • 33. Notes Power Up starts Power Up starts Credit Auth Credit Auth XYZ Emp #2 XYZ Emp #2 XYZ Emp #2 XYZ Emp #2 XYZ Emp #2 XYZ Emp #2 XYZ Emp #2 XYZ Emp #2 XYZ Emp #2 XYZ Emp.#1 XYZ Emp.#1 XYZ Emp.#1 XYZ Emp.#1 XYZ Emp.#1 XYZ Emp.#1 XYZ Emp.#1 XYZ Emp.#1 XYZ Emp.#1 16 23 30 6 13 20 27 3 10 17 24 3 10 17 24 31 7 14 21 28 5 12 19 26 2 9 16 23 30 Dec '12 Jan '13 Feb '13 Mar '13 Apr '13 May '13 Jun '13 Task Split Milestone Summary Project Summary External Tasks External Milestone Inactive Task Inactive Milestone Inactive Summary Manual Task Duration-only Manual Summary Rollup Manual Summary Start-only Finish-only Deadline Progress Page 33 Project: XYZ Company Data Cente Date: Thu 6/9/16
  • 34. Notes Credit Auth Post Move ... XYZ Emp.#1 XYZ Emp.#1 XYZ Emp.#1 XYZ Emp.#1 XYZ Emp.#1,XYZ Emp #2 XYZ Emp.#1,XYZ Emp #2 XYZ Emp.#1,XYZ Emp #2 XYZ Emp #2 XYZ Emp #2 XYZ Emp #2 XYZ Emp #2 XYZ Emp.#1 XYZ Emp #2 XYZ Emp.#1 XYZ Emp.#1 XYZ Emp #2 XYZ Emp #2 16 23 30 6 13 20 27 3 10 17 24 3 10 17 24 31 7 14 21 28 5 12 19 26 2 9 16 23 30 Dec '12 Jan '13 Feb '13 Mar '13 Apr '13 May '13 Jun '13 Task Split Milestone Summary Project Summary External Tasks External Milestone Inactive Task Inactive Milestone Inactive Summary Manual Task Duration-only Manual Summary Rollup Manual Summary Start-only Finish-only Deadline Progress Page 34 Project: XYZ Company Data Cente Date: Thu 6/9/16
  • 35. Notes Estimated 3.5 Hours after Maint. Window XYZ Company Power Down Tasks... Start of Maintenance Window XYZ Emp #2 XYZ Emp #2 XYZ Emp #2 XYZ Emp #2 XYZ Emp #2 XYZ Emp #2 XYZ Emp #2 XYZ Emp.#1 XYZ Emp.#1 XYZ Emp.#1,XYZ Emp #2 Entire Team XYZ Contact XYZ Emp #2 3/15 Sr. MGMT,TKO 3/15 XYZ Emp.#1 3/15 3/15 16 23 30 6 13 20 27 3 10 17 24 3 10 17 24 31 7 14 21 28 5 12 19 26 2 9 16 23 30 Dec '12 Jan '13 Feb '13 Mar '13 Apr '13 May '13 Jun '13 Task Split Milestone Summary Project Summary External Tasks External Milestone Inactive Task Inactive Milestone Inactive Summary Manual Task Duration-only Manual Summary Rollup Manual Summary Start-only Finish-only Deadline Progress Page 35 Project: XYZ Company Data Cente Date: Thu 6/9/16
  • 36. Notes 9.5 hour Estimate (Total) 3 hours 1 hour 2 hours 3.5 hours Physical Movers Physical Movers Physical Movers Physical Movers XYZ Emp.#1,Cisco Engineer 3/15 3/15 3/15 Entire Team 16 23 30 6 13 20 27 3 10 17 24 3 10 17 24 31 7 14 21 28 5 12 19 26 2 9 16 23 30 Dec '12 Jan '13 Feb '13 Mar '13 Apr '13 May '13 Jun '13 Task Split Milestone Summary Project Summary External Tasks External Milestone Inactive Task Inactive Milestone Inactive Summary Manual Task Duration-only Manual Summary Rollup Manual Summary Start-only Finish-only Deadline Progress Page 36 Project: XYZ Company Data Cente Date: Thu 6/9/16