SlideShare a Scribd company logo
1 of 55
Download to read offline
School of Engineering & Technology
Jain Global Campus, Kanakapura Taluk - 562112
Ramanagara District, Karnataka, INDIA
2013-2014
A Project Report on
Time and Resource Management of Construction Project
Submitted in partial fulfilment for the award of the degree of
BACHELOR OF ENGINEERING
IN
CIVIL ENGINEERING
Submitted by
Rathan Kumar N M (09BE6CV035)
Amruthesh K (09BE6CV008)
Sukesh Shetty (09BE6CV043)
Mentor
Dr. Shashishankar A
HOD,
Department of Civil Engineering
(Internal Guide)
Mr. Yashwanth
Managing Director, SYConE CPMC PVT. LTD
(External Guide)
SCHOOL OF ENGINEERING & TECHNOLOGY
Jain Global campus
Kanakapura Taluk - 562112
Ramanagara District
Karnataka, INDIA
CERTIFICATE
This is to certify that this project work titled ‗Time and Resource Management of
Construction Project’, is carried out by ‘Rathan Kumar N M (09BE6CV035)’,
‘Amrutesh K (09BE6CV008)’ and ‘Sukesh Shetty (10BE6CV043)’, bona fide students
of Bachelor of Civil Engineering at the School of Engineering & Technology, Jain
University, in partial fulfilment for the award of Bachelor of Engineering in
Civil Engineering, during the year 2013-2014
External Examiner:
1.
2.
Dr. A Shashishankar Mr. Yashwanth C B Mohan
Professor – Civil Department
SET – Jain University
Date:
Managing Director
SYConE CPMC PVT. LTD
Date:
Associate Director
SET – Jain University
Date:
(HOD) (External guide) (Associate Director)
(Internal Project Guide)
DECLARATION
We, ‗Rathan Kumar N M, Sukesh Shetty , Amrutesh K’, students of VIII semester B.E
in Civil Engineering at School of Engineering and Technology – Jain University, hereby
declare that the dissertation titled ‗Time and Resource Management of Construction
Project’ has been conducted by us at School of Engineering and Technology – Jain
University (SET-JU) and submitted in partial fulfilment for the award of Bachelor of
Engineering in Civil Engineering, during the academic year February – May 2013-2014,
under the guidance and supervision of Dr. Shashishankar A, Professor and Head,
Department of Civil Engineering. Further the matter embodied in the dissertation has not
been submitted previously by anybody for the award of any degree or diploma to any
University, to the best of my knowledge and faith.
PLACE :
DATE :
Rathan Kumar N M Amrutesh K Sukesh K
(09BE6CV035) (09BE6CV008) (10BE6CV043)
ABSTRACT
Project management is the process and activity of planning, organizing, motivating, and
controlling resources, procedure and protocols to realize completion of the project. The
primary challenge of project management is to achieve all of the project goals and
objectives while honouring the preconceived constraints. The constraints are scope, time,
quality and budget.
The purpose of this project is to utilize time and resource efficiently. The title of the
project is ―Time and Resource Management‖, in-order to manage Resources such as
labour, material, cost, so on.
Time is a very important factor to complete the work within the given deadline or even
earlier. The project is done with the use of MSP which is project management software.
The procedure for the project included understanding the project and creation of WBS,
creation of level 3 activities, master construction programme, resource scheduling and cash
flow projection, monitoring and tracking.
Detailed quantity estimation of constructing a villa is being shown in this project. Also the
time estimation and management of the villa is also included in this report.
CONTENTS
Abstract ....................................................................................................... i
Contents ......................................................................................................... ii
List of tables ................................................................................................... v
List of figures ................................................................................................ vi
1 Introduction ...................................................Error! Bookmark not defined.
1.1 History......................................................Error! Bookmark not defined.
1.1.1 The Pre 19th
century ............................Error! Bookmark not defined.
1.1.2 The 20th
century ................................................................................ 2
1.2 Approaches of project management....................................................... 2
1.3Process of project management................................................................. 2
1.3.1 initiation........................................................................................... 3
1.3.1.1 Scope of the project management company ............................. 3
1.3.2 Planning .......................................................................................... 3
1.3.3 Executing ......................................................................................... 4
1.3.4 Monitoring and controlling ............................................................... 4
1.3.5 Closing............................................................................................. 4
1.4 Constraints of a project............................................................................ 5
1.4.1 Time................................................................................................. 5
1.4.2 Cost.............................................................................................. 5
1.4.3 Scope ............................................................................................... 6
1.4.4 Quality ............................................................................................. 6
1.5 Time management ................................................................................... 6
1.5.1 The importance of time management for a construction project .......... 7
1.6 Resource management ............................................................................. 8
1.6.1 Labour productivity .......................................................................... 8
1.6.2 Material management ....................................................................... 9
1.7 Scheduling .............................................................................................10
1.7.1 Methods of scheduling.......................................................................11
2 Site Details ................................................................................................13
2.1 Companies involved in the project .........................................................13
2.2 Enterprise project structure....................................................................14
2.3 Organization breakdown structure............Error! Bookmark not defined.4
2.4 Work breakdown structures ....................................................................14
3 Drawing Details ..........................................................................................24
3.1 Groung floor ..........................................................................................24
3.2 First floor...............................................................................................25
3.3 Second floor...........................................................................................26
3.4 Terrace floor ..........................................................................................27
4 Estimation and Quantites............................................................................28
5 Reports obtained from MSP........................................................................39
5.1 S-Curve Method .....................................................................................39
5.1.1 Generating S-Curve .............................................................................39
5.1.1.1Project Benchmark ............................................................................39
5.1.1.2 Steps to generate S-Curve .................................................................39
5.2 Gantt Chart ............................................................................................41
5.3Project Summary Report..........................................................................42
5.4 Tracking Reports....................................................................................41
5.4 Cash-Flow Report ..................................................................................41
6.0 Conclusion and Discussions.....................................................................42
7.0 References ..............................................................................................43
Time and Resource Management in Construction Project
Department of Civil Engineering, SET, Jain University
1
LIST OF TABLES
Table 2.1 Details of Villa at project site
Table 4.1 Estimation and Quantities
Time and Resource Management in Construction Project
Department of Civil Engineering, SET, Jain University
2
LIST OF FIGURES
Figure.1.1 Process group flowchart
Figure 1.2 Project management triangle
Figure 2.1 Organization Breakdown Structure Flowchart
Figure 2.2 Typical Work Breakdown Structure
Figure 2.3 Activity and Event Network
Figure 3.1 Ground Floor Plan
Figure 3.2 First Floor Plan
Figure 3.3 Second Floor Plan
Figure 3.4 Terrace Floor Plan
Figure 5.1 S-Curve Graphs
Figure 5.2 Simple Gantt chart
Time and Resource Management in Construction Project
Department of Civil Engineering, SET, Jain University
3
Time and Resource Management in Construction Project
Department of Civil Engineering, SET, Jain University
1
CHAPTER 1
1. INTRODUCTION
Management is the process of getting activities completed efficiently and
effectively with and through other people. The term Management has different
meaning in different perspective.
Project management is the process and activity of planning, organizing,
motivating, and controlling resources, procedures and protocols to achieve
specific goals in scientific or daily problems. A project is a temporary endeavor
designed to produce a unique product, service or result with a defined beginning
and end (usually time-constrained, and often constrained by funding or
deliverables), undertaken to meet unique goals and objectives, typically to bring
about beneficial change or added value. The temporary nature of projects stands
in contrast with business as usual (or operations), which are repetitive,
permanent, or semi-permanent functional activities to produce products or
services. In practice, the management of these two systems is often quite
different, and as such requires the development of distinct technical skills and
management strategies.
The primary challenge of project management is to achieve all of the project
goals and objectives while honoring the preconceived constraints. The primary
constraints are scope, time, quality and budget. The secondary — and more
ambitious — challenge is to optimize the allocation of necessary inputs and
integrate them to meet pre-defined objectives.
1.1. HISTORY
1.1.1. THE PRE 19TH CENTURY
Until 1900, civil engineering projects were generally managed by creative
architects, engineers, and master builders themselves. Project management has
existed in some form for thousands of years. After all anything that requires an
approach where humans organize effectively to a plan and achieve specific
objectives can be loosely defined as a project. How else would have humans
achieved some of stunning wonders and achievements.
Time and Resource Management in Construction Project
Department of Civil Engineering, SET, Jain University
2
The forerunners of engineers, practical artists and craftsmen, proceeded mainly
by trial and error. Yet tinkering combined with imagination produced many
marvelous devices. Many ancient monuments cannot fail to incite admiration.
The admiration is embodied in the name ―engineer‖ itself. It originated in the
eleventh century from the Latin ingeniator, meaning one with ingenium, the
ingenious one.
The 18th and 19th Century and the Industrial Revolutions witnessed changes in
the Western World with industrial revolutions and with this the birth of
management principles in the business to become the backbone of project
management.
1.1.2. THE 20TH CENTURY
The 20th century witnessed colossal improvements across the world with two
industrial revolutions which required a far more structured approach to business
and management as the scale of objectives changed.
1.2. APPROACHES OF PROJECT MANAGEMENT
 The traditional approach
 PRINCE2
 Critical chain project management
 Event chain methodology
 Process-based management
 Agile project management
 Lean project management
 Extreme project management
 Benefits realization management
1.3. PROCESSES OF PROJECT MANAGEMENTS
Traditionally, project management includes a number of elements: four to five
process groups, and a control system. Regardless of the methodology or
terminology used, the same basic project management processes will be used.
Time and Resource Management in Construction Project
Department of Civil Engineering, SET, Jain University
3
Major process groups generally include:
 Initiation
 Planning
 Execution
 Monitoring and controlling
 Closing
Figure 1.1 Process groups flowchart
1.3.1. INITIATION
The Project Initiation Phase is the most crucial phase in the Project Life Cycle,
as it's the phase in which you define your scope and hire your team. With a
clearly defined scope and a suitably skilled team, you can ensure success.
If this stage is not performed well, it is unlikely that the project will be
successful in meeting the business‘ needs. The key project controls needed here
are an understanding of the business environment and making sure that all
necessary controls are incorporated into the project. Any deficiencies should be
reported and a recommendation should be made to fix them.
1.3.1.1. SCOPE OF PROJECT MANAGEMENT COMPANY (PMC)
 Planning and Co-ordination
 Construction Supervision
o Control over Master Construction Schedule (MCS)
 Quality Control
 Site co-ordination and Construction Execution
 Personnel
 PMC‘s responsibility after completion of project
 Professional Misconduct
1.3.2. PLANNING
After the initiation stage, the project is planned to an appropriate level of detail
(see example of a flow-chart). The main purpose is to plan time, cost and
Time and Resource Management in Construction Project
Department of Civil Engineering, SET, Jain University
4
resources adequately to estimate the work needed and to effectively manage risk
during project execution. As with the Initiation process group, a failure to
adequately plan greatly reduces the project's chances of successfully
accomplishing its goals. Additional processes, such as planning for
communications and for scope management, identifying roles and
responsibilities, determining what to purchase for the project and holding a kick-
off meeting are also generally advisable. For new product development projects,
conceptual design of the operation of the final product may be performed
concurrent with the project planning activities, and may help to inform the
planning team when identifying deliverables and planning activities.
1.3.3. EXECUTING
Executing consists of the processes used to complete the work defined in the
project plan to accomplish the project's requirements. Execution process involves
coordinating people and resources, as well as integrating and performing the
activities of the project in accordance with the project management plan. The
deliverables are produced as outputs from the processes performed as defined in
the project management plan and other frameworks that might be applicable to
the type of project at hand.
1.3.4. MONITORING AND CONTROLLING
Monitoring and controlling consists of those processes performed to observe
project execution so that potential problems can be identified in a timely manner
and corrective action can be taken, when necessary, to control the execution of
the project. The key benefit is that project performance is observed and measured
regularly to identify variances from the project management plan.
1.3.5. CLOSING
Closing includes the formal acceptance of the project and the ending thereof.
Administrative activities include the archiving of the files and documenting
lessons learned.
Time and Resource Management in Construction Project
Department of Civil Engineering, SET, Jain University
5
The Closing phase consists of:
Contract closure: Complete and settle each contract (including the resolution of
any open items) and close each contract applicable to the project or project
phase.
Project closure: Finalize all activities across all of the process groups to
formally close the project or a project phase.
1.4. CONSTRAINTS OF A PROJECT
The project management triangle is used by managers to analyze or understand
the difficulties that may arise due to implementing and executing a project. All
projects irrespective of their size will have many constraints.
Although there are many such project
constraints, these should not be barriers for
successful project execution and for the
effective decision making.
There are three main interdependent
constraints for every project; Time, Cost
and Scope. This is also known as Project
Management Triangle.
Fig 1.2 Project Management Triangle
1.4.1. TIME
A project's activities can either take shorter or longer amount of time to
complete. Completion of tasks depends on a number of factors such as the
number of people working on the project, experience, skills, etc.
Time is a crucial factor which is uncontrollable. On the other hand, failure to
meet the deadlines in a project can create adverse effects. Most often, the main
reason for organizations to fail in terms of time is due to lack of resources.
Time and Resource Management in Construction Project
Department of Civil Engineering, SET, Jain University
6
1.4.2. COST
It's imperative for both the project manager and the organization to have an
estimated cost when undertaking a project. Budgets will ensure that project is
developed or implemented below a certain cost.
Sometimes, project managers have to allocate additional resources in order to
meet the deadlines with a penalty of additional project costs.
1.4.3. SCOPE
Scope looks at the outcome of the project undertaken. This consists of a list of
deliverables, which need to be addressed by the project team.
A successful project manager will know to manage both the scope of the project
and any change in scope which impacts time and cost.
1.4.4. QUALITY
Quality is not a part of the project management triangle, but it is the ultimate
objective of every delivery. Hence, the project management triangle represents
implies quality.
Many project managers are under the notion that 'high quality comes with high
cost', which to some extent is true. By using low quality resources to accomplish
project deadlines does not ensure success of the overall project. Like with the
scope, quality will also be an important deliverable for the project.
1.5. TIME MANAGEMENT
Time management is the act of taking conscious control over the amount of time
spent on specific activities. One exercises time management to increase
productivity, effectiveness and efficiency, also practicing skills and using tools
and techniques to aid in accomplishing tasks, projects or working toward goals
and deadlines.
Time management is about effective scheduling of your time, goal setting,
prioritizing and choosing what to do and what not to do, delegating tasks,
Time and Resource Management in Construction Project
Department of Civil Engineering, SET, Jain University
7
analyzing and reviewing spent time, organizing workspace, keeping
concentration and focus at work, motivating to work towards a goal.
Managing time can gain extra productive hours which can lead to increased
efficiency and productivity.
Time management is the strategy of organizing and implementing conscious
regulation on the time-frame allocated to a particular activity, with the purpose
of enhancing the effectiveness, proficiency and productivity. Time management
may be assisted by an assortment of tools, devices, and techniques utilized to
manage valuable time whenever undertaking particular projects, tasks and
objectives complying with a deadline.
Implementation of time management entails a broad range of activities, which
includes preparation, allocation and delegation, evaluation, supervision,
scheduling and prioritizing.
1.5.1. THE IMPORTANCE OF TIME MANAGEMENT FOR A
CONSTRUCTION PROJECT
 Effective time management is used to assign workers attainable goals,
resources and time-frames to lower the overall cost of the project with the
efficient use of their billable hours and energy.
 Time management is important in construction because it organizes the
allotted time set for the completion of the task for the purpose of meeting
or even beating the deadline.
 Time management is important to a contractor's profitability because they
are given a legally binding contract in which failure to abide by its terms
and deadlines can result to a partial lost in monetary payment or even
cancellation of the contract.
 Proper use of time management techniques can result in the completion of
project, on time, and create a positive testimonial for the contractor.
The effective use of time management is a vital element needed by construction
companies to successfully meet the budget and allocated timeframe for the
Time and Resource Management in Construction Project
Department of Civil Engineering, SET, Jain University
8
completion of any development work. It is not just a tool used in construction
management but is a key to achieving corporate profitability and success.
1.6. RESOURCE MANAGEMENT
Resource management is the efficient and effective deployment of an
organization's resources when they are needed. Such resources may include
financial resources, inventory, human skills, production resources, or information
technology.
A dimension of resource development is included in resource management by
which investment in resources can be retained by a smaller additional investment
to develop a new capability that is demanded, at a lower investment than
disposing of the current resource and replacing it with another that has the
demanded capability.
In conservation, resource management is a set of practices pertaining to
maintaining natural systems integrity. Examples of this form of management are
resource management, soil conservation, forestry, wildlife management and water
resource management.
The broad term for this type of resource management is natural resource
management.
Good project management in construction must vigorously pursue the efficient
utilization of labor, material and equipment. Improvement of labour productivity
should be a major and continual concern of those who are responsible for cost
control of constructed facilities. Material handling, which includes procurement,
inventory, shop fabrication and field servicing, requires special attention for cost
reduction. The use of new equipment and innovative methods has made possible
wholesale changes in construction technologies in recent decades. Organizations
which do not recognize the impact of various innovations and have not adapted to
Time and Resource Management in Construction Project
Department of Civil Engineering, SET, Jain University
9
changing environments have justifiably been forced out of the mainstream of
construction activities.
1.6.1. LABOUR PRODUCTIVITY
Productivity in construction is often broadly defined as output per labour hour.
Since labour constitutes a large part of the construction cost and the quantity of
labour hours in performing a task in construction is more susceptible to the
influence of management than are materials or capital, this productivity measure
is often referred to as labour productivity. However, it is important to note that
labour productivity is a measure of the overall effectiveness of an operating
system in utilizing labour, equipment and capital to convert labour efforts into
useful output, and is not a measure of the capabilities of labour alone.
1.6.2. MATERIAL MANAGEMENT
Materials management is an important element in project planning and control.
Materials represent a major expense in construction, so minimizing procurement
or purchase costs presents important opportunities for reducing costs. Poor
materials management can also result in large and avoidable costs during
construction. First, if materials are purchased early, capital may be tied up and
interest charges incurred on the excess inventory of materials.
Even worse, materials may deteriorate during storage or be stolen unless special
care is taken. For example, electrical equipment often must be stored in
waterproof locations. Second, delays and extra expenses may be incurred if
materials required for particular activities are not available. Accordingly,
insuring a timely flow of material is an important concern of project managers.
Materials management is not just a concern during the monitoring stage in which
construction is taking place. Decisions about material procurement may also be
required during the initial planning and scheduling stages. For example, activities
can be inserted in the project schedule to represent purchasing of major items
such as elevators for buildings. The availability of materials may greatly
influence the schedule in projects with a fast track or very tight time schedule:
sufficient time for obtaining the necessary materials must be allowed. In some
case, more expensive suppliers or shippers may be employed to save time.
Time and Resource Management in Construction Project
Department of Civil Engineering, SET, Jain University
10
Materials management is also a problem at the organization level if central
purchasing and inventory control is used for standard items. In this case, the
various projects undertaken by the organization would present requests to the
central purchasing group. In turn, this group would maintain inventories of
standard items to reduce the delay in providing material or to obtain lower costs
due to bulk purchasing. This organizational materials management problem is
analogous to inventory control in any organization facing continuing demand for
particular items.
Materials ordering problems lend themselves particularly well to computer based
systems to insure the consistency and completeness of the purchasing process. In
the manufacturing realm, the use of automated materials requirements planning
systems is common. In these systems, the master production schedule, inventory
records and product component lists are merged to determine what items must be
ordered, when they should be ordered, and how much of each item should be
ordered in each time period. The heart of these calculations is simple arithmetic:
the projected demand for each material item in each period is subtracted from the
available inventory. When the inventory becomes too low, a new order is
recommended.
For items that are non-standard or not kept in inventory, the calculation is even
simpler since no inventory must be considered. With a materials requirement
system, much of the detailed record keeping is automated and project managers
are alerted to purchasing requirements.
1.7. SCHEDULING
In project management, a schedule is a listing of project's milestones, activities,
and deliverables, usually with intended start and finish dates. Those items are
often estimated in terms of resource allocation, budget and duration, linked by
dependencies and scheduled events. A schedule is commonly used in project
planning and project portfolio management parts of project management.
Elements on a schedule may be closely related to the work breakdown structure
(WBS) terminal elements, the Statement of work, or a Contract Data
Requirements List.
Time and Resource Management in Construction Project
Department of Civil Engineering, SET, Jain University
11
Planning, Scheduling (or organizing) and Control are considered to be basic
Managerial functions, and CPM/PERT has been rightfully accorded due
importance in the literature on Operations Research and Quantitative Analysis.
Far more than the technical benefits, it was found that PERT/CPM provided a
focus around which managers could brain-storm and put their ideas together. It
proved to be a great communication medium by which thinkers and planners at
one level could communicate their ideas, their doubts and fears to another level.
Most important, it became a useful tool for evaluating the performance of
individuals and teams.
There are many variations of CPM/PERT which have been useful in planning
costs, scheduling manpower and machine time.
WORK BREAKDOWN STRUCTURE
A work breakdown structure (WBS), in project management and systems
engineering, is a deliverable-oriented decomposition of a project into smaller
components.
A work breakdown structure element may be a product, data, service, or any
combination thereof. A WBS also provides the necessary framework for detailed
cost estimating and control along with providing guidance for schedule
development and control
1.7.1. METHODS OF SCHEDULING
CPM (Critical Path Method) and PERT (Program Evaluation Review Technique)
are project management techniques, which have been created out of the need of
Western industrial and military establishments to plan, schedule and control
complex projects. While CPM is easy to understand and use, it does not consider
the time variations that can have a great impact on the completion time of a
complex project.
The Program Evaluation and Review Technique (PERT) is a network model that
allows for randomness in activity completion times. PERT was developed in the
late 1950's for the U.S. Navy's Polaris project having thousands of contractors. It
has the potential to reduce both the time and cost required to complete a project.
Time and Resource Management in Construction Project
Department of Civil Engineering, SET, Jain University
12
Essentially, there are six steps which are common to both the techniques.
The procedure is listed below:
I. Define the Project and all of its significant activities or tasks. The Project
(made up of several tasks) should have only a single start activity and a single
finish activity.
II. Develop the relationships among the activities. Decide which activities
must precede and which must follow others.
III. Draw the "Network" connecting all the activities. Each Activity should
have unique event numbers. Dummy arrows are used where required to avoid
giving the same numbering to two activities.
IV. Assign time and/or cost estimates to each activity
V. Compute the longest time path through the network. This is called the
critical path.
VI. Use the Network to help plan, schedule, and monitor and control the
project.
PERT planning involves the following steps:
1. Identify the specific activities and milestones.
2. Determine the proper sequence of the activities.
3. Construct a network diagram.
4. Estimate the time required for each activity.
5. Determine the critical path.
6. Update the PERT chart.
Benefits of PERT
• Expected project completion time.
• Probability of completion before a specified date.
Time and Resource Management in Construction Project
Department of Civil Engineering, SET, Jain University
13
• The critical path activities that directly impact the completion time.
• The activities that have slack time and that can lend resources to
critical path activities.
• Activities start and end dates.
Time and Resource Management in Construction Project
Department of Civil Engineering, SET, Jain University
14
Chapter 2
2. SITE DETAILS
Project: Vaishnavi Commune
2.1. COMPANIES INVOLVED IN PROJECT
Client: M/S. VAISHNAVI GROUP
Contractor: Adharsh Group
Architects: Eccumene Habitat Solutions PVT. LTD.
PMC: SYConE CPMC PVT. LTD
Structural Consultant: SHRADHA DESIGNTECH PVT.LTD
Electrical Consultants: POORNA ENGINEERING CONSULTANTS
PHE Consultants: PRISM CONSULTANTS
Landscape Consultants: TERRA FIRMA Landscape Architecture
Project Configuration:
 6 Acres of land
 46 Villas with Villament and Club House
 3 & 4 BHK villas
 3 BHK villa measures 3508 – 3787 Sq. ft.
 4 BHK villa measures 4030 – 4309 Sq. ft.
Time and Resource Management in Construction Project
Department of Civil Engineering, SET, Jain University
15
Details of villa:
Table 2.1 Details of villa at the project site
2.2. ENTERPRISE PROJECT STRUCTURE
A Project is managed by a company which may be or may not be under its mother
company. The company who is managing the project is defined as enterprise in
project management. If a particular company having its branches and one of the
branch is managing the project. Then we have to enter the list of all the company
this list is called Enterprise Project Structure (EPS).
2.3. ORGANIZATION BREAKDOWN STRUCTURE
It is the list of people in a company who will be responsible for managing either
the work breakdown structure or activity in a project this is called as
organization breakdown structure.
2.4. WORK BREAKDOWN STRUCTURE
The functional elements of a project and their inter relationship are determined
by a technique is known as Work Breakdown Structure (WBS).
BHK Facing Type No.
3 East A 7
3 East B 6
3 West A 7
3 West B 6
4 East A 6
4 East B 5
4 West A 4
4 West B 4
3 North A 1
Total 46
Time and Resource Management in Construction Project
Department of Civil Engineering, SET, Jain University
16
Figure 2.1 Flow chart represents the OBS of the Project
Figure 2.2 Typical WBS (Work Breakdown Structure) of a Building
Time and Resource Management in Construction Project
Department of Civil Engineering, SET, Jain University
17
ACTIVITY
Performance of a specific task, operation, job or function which consumes time
and resource and has a definite beginning and end is called an Activity.
EVENT
An instantaneous point in time marking the beginning or end of one or more
activities is called an Event.
NETWORK
A Network is the diagrammatic representation of a work plan showing the
activities step by step leading to the established goal. It depicts the inter-
dependence between the various activities.
Figure 2.3 Representing Activity and Event Networks
Time and Resource Management in Construction Project
Department of Civil Engineering, SET, Jain University
18
WORK BREAKDOWN STRUCTURE OF A VILLA
1. Sub-Structure
1.1. Marking
1.2. Earthwork
1.3. ATT
1.4. PCC
1.5. Foundation
1.5.1. Reinforcement
1.5.2. Shuttering
1.5.3. Concreting
1.6. Column
1.6.1. Column Marking
1.6.2. Reinforcement (up to soffit of plinth beam)
1.6.3. Shuttering
1.6.4. Concreting
1.7. Backfilling (up to soffit of plinth beam)
1.8. Size Stone Masonry
1.8.1. Excavation
1.8.2. PCC
1.8.3. SSM Work
1.9. DPC
1.10. Backfilling
1.11. Plinth Beam
1.11.1. Reinforcement
1.11.2. Shuttering
1.11.3. Concreting
2. Super Structure
2.1. Floor 00
2.1.1. Structural work
2.1.1.1. Backfilling
2.1.1.2. ATT for floor area
2.1.1.3. Soling
2.1.1.4. Floor PCC
2.1.1.5. Column
Time and Resource Management in Construction Project
Department of Civil Engineering, SET, Jain University
19
2.1.1.5.1. Column Layout
2.1.1.5.2. Reinforcement
2.1.1.5.3. Shuttering
2.1.1.5.4. Concreting
2.1.1.6. Staircase Flights
2.1.1.6.1. Flight 1
2.1.1.6.2. Flight 2
2.1.1.7. First floor Slab
2.1.1.7.1. Beam Shuttering
2.1.1.7.2. Slab Shuttering
2.1.1.7.3. Beam Reinforcement
2.1.1.7.4. Slab Reinforcement
2.1.1.7.5. Electrical Conduting
2.1.1.7.6. Slab Concreting
2.1.2. Civil Finishes
2.1.2.1. Wet Finishes
2.1.2.1.1. Block Masonry
2.1.2.1.2. Ceiling Plastering
2.1.2.1.3. Wall Plastering
2.1.2.1.4. Granite Counters – Kitchen
2.1.2.1.5. Dadoing – Kitchen
2.1.2.1.6. Flooring
2.1.2.1.6.1. Vitrified
2.1.2.1.6.2. Marble (Laying)
2.1.2.1.7. Putty and Primer
2.1.2.1.8. First coat painting
2.1.2.1.9. Flooring – Marble - Polishing and Finishing
2.1.2.1.10. Painting Final/Polishing
2.1.2.2. Dry Finishes
2.1.2.2.1. Windows fixing
2.1.2.2.2. Staircase railing
2.1.2.2.3. Door frames and shuttering fixing
2.1.2.2.4. Fixing of Iron mongery works
2.1.3. MEP
Time and Resource Management in Construction Project
Department of Civil Engineering, SET, Jain University
20
2.1.3.1. Electrical
2.1.3.1.1. Chasing and Wall conduting
2.1.3.1.2. Wiring and switch plate fixing
2.1.3.1.3. Testing and commissioning
2.1.3.2. PHE Toilet and Kitchen
2.1.3.2.1. Pipe Laying – Waste and soil
2.1.3.2.2. Pipe Laying – Water
2.1.3.2.3. Pipe testing
2.1.3.2.4. Sanitary fixtures
2.1.3.3. Toilet
2.1.3.3.1. Chasing
2.1.3.3.2. Dadoing – Toilet
2.1.3.3.3. Granite Counters
2.2. Floor 01
2.2.1. Structural Work
2.2.1.1. Column
2.2.1.1.1. Column Layout
2.2.1.1.2. Reinforcement
2.2.1.1.3. Shuttering
2.2.1.1.4. Concreting
2.2.1.2. First flight of stairs
2.2.1.3. Beam and Slab work
2.2.1.3.1. Beam Shuttering
2.2.1.3.2. Slab Shuttering
2.2.1.3.3. Beam Reinforcement
2.2.1.3.4. Slab Reinforcement
2.2.1.3.5. Electrical Conduting
2.2.1.3.6. Slab Concreting
2.2.2. Civil Finishes
2.2.2.1. Wet Finishes
2.2.2.1.1. Block Masonry
2.2.2.1.2. Ceiling Plastering
2.2.2.1.3. Wall Plastering
2.2.2.1.4. Flooring
Time and Resource Management in Construction Project
Department of Civil Engineering, SET, Jain University
21
2.2.2.1.4.1. Vitrified
2.2.2.1.4.2. Marble (Laying)
2.2.2.1.5. Putty and Primer
2.2.2.1.6. First coat painting
2.2.2.1.7. Flooring – Marble - Polishing and Finishing
2.2.2.1.8. Painting Final/Polishing
2.2.2.2. Dry Finishes
2.2.2.2.1. Windows fixing
2.2.2.2.2. Staircase railing
2.2.2.2.3. Door frames and shuttering fixing
2.2.2.2.4. Fixing of Iron mongery works
2.2.3. MEP
2.2.3.1. Electrical
2.2.3.1.1. Chasing and Wall conduting
2.2.3.1.2. Wiring and switch plate fixing
2.2.3.1.3. Testing and commissioning
2.2.3.2. PHE Toilet
2.2.3.2.1. Pipe Laying – Waste and soil
2.2.3.2.2. Pipe Laying – Water
2.2.3.2.3. Pipe testing
2.2.3.2.4. Sanitary fixtures
2.2.3.3. Toilet
2.2.3.3.1. Rough plastering
2.2.3.3.2. Chasing
2.2.3.3.3. Waterproofing
2.2.3.3.4. Bore Packing
2.2.3.3.5. Sunken Filling
2.2.3.3.6. Dadoing – Toilet
2.2.3.3.7. Toilet Flooring
2.2.3.3.8. Granite Counters
2.3. Study Room Slab
2.3.1. Structural Work
2.3.1.1. Column
2.3.1.1.1. Column Layout
Time and Resource Management in Construction Project
Department of Civil Engineering, SET, Jain University
22
2.3.1.1.2. Reinforcement
2.3.1.1.3. Shuttering
2.3.1.1.4. Concreting
2.3.1.2. First flight of stairs
2.3.1.3. Beam and Slab work
2.3.1.3.1. Beam Shuttering
2.3.1.3.2. Slab Shuttering
2.3.1.3.3. Beam Reinforcement
2.3.1.3.4. Slab Reinforcement – Stairs (2nd Flight)
2.3.1.3.5. Electrical Conduting
2.3.1.3.6. Slab Concreting
2.3.1.4. Roof Slab
2.3.2. Civil Finishes
2.3.2.1. Wet Finishes
2.3.2.1.1. Block Masonry
2.3.2.1.2. Ceiling Plastering
2.3.2.1.3. Wall Plastering
2.3.2.1.4. Flooring
2.3.2.1.4.1. Vitrified
2.3.2.1.4.2. Marble (Laying)
2.3.2.1.5. Putty and Primer
2.3.2.1.6. Flooring – Marble - Polishing and Finishing
2.3.2.1.7. Painting Final/Polishing
2.3.2.2. Dry Finishes
2.3.2.2.1. Windows fixing
2.3.2.2.2. Staircase railing
2.3.2.2.3. Door frames and shuttering fixing
2.3.2.2.4. Fixing of Iron mongery works
2.3.3. MEP
2.3.3.1. Electrical
2.3.3.1.1. Chasing and Wall conduting
2.3.3.1.2. Wiring and switch plate fixing
2.3.3.1.3. Testing and commissioning
2.4. Terrace
Time and Resource Management in Construction Project
Department of Civil Engineering, SET, Jain University
23
2.4.1. Parapet wall and plastering
2.4.2. Weather Proofing
2.4.3. Landscaping
3. External Finishes
3.1. Civil
3.1.1. External Plastering
3.1.2. Pergola
3.1.3. External Painting
3.1.4. Car park Flooring
3.2. MEP
3.2.1. External Sewage Lines Laying
3.2.2. Chamber Construction
3.2.3. Water Supply Line
3.3. Landscaping
3.3.1. Hard scape
3.3.2. Soft scape
4. Snagging and Desnagging
4.1. Punch list and desnagging
Time and Resource Management in Construction Project
Department of Civil Engineering, SET, Jain University
24
Chapter 3
3. DRAWINGS DETAILS
3.1. GROUND FLOOR
Note: All dimensions are in mm
Time and Resource Management in Construction Project
Department of Civil Engineering, SET, Jain University
25
3.2. First FLOOR
Time and Resource Management in Construction Project
Department of Civil Engineering, SET, Jain University
26
3.3. SECOND FLOOR
Time and Resource Management in Construction Project
Department of Civil Engineering, SET, Jain University
27
3.4. TERRACE FLOOR
Time and Resource Management in Construction Project
Department of Civil Engineering, SET, Jain University
28
Chapter 4
4. ESTIMATION AND QUANTITIES
Item No.
Particulars and
Description No.s
Volume
(m3
) Percent
Density of
Steel
Quantity of
Steel (Kgs) Comments
1. Steel in RCC
Works
1.1RCC Footing
@ 0.5%
Total Footing of a
villa 1 23.854375 0.005 7850 936.2842188
Density of Steel 78.5
q/cu m
1.2 RCC
Coulmn @
1.5%
a) Total Quantity
Steel in Columns of
Ground Floor 1 3.969 0.015 7850 467.34975
Density of Steel 78.5
q/cu m
b) Total Quantity
Steel in Columns of
First Floor 1 3.73275 0.015 7850 439.5313125
Density of Steel 78.5
q/cu m
c) Total Quantity
Steel in Columns of
Second Floor 1 1.134 0.015 7850 133.5285
Density of Steel 78.5
q/cu m
1.3 RCC Roof
Slab @ 0.8%
a) Total Quantity
Steel in Ground Floor
Slab 1 22.275 0.008 7850 1398.87
Density of Steel 78.5
q/cu m
b) Total Quantity
Steel in First Floor
Slab 1 18.39 0.008 7850 1154.892
Density of Steel 78.5
q/cu m
c) Total Quantity
Steel in Second Floor
Slab 1 3.6 0.008 7850 226.08
Density of Steel 78.5
q/cu m
d) Total Quantity
Steel in Study Room
Slab 1 1.9305 0.008 7850 121.2354
Density of Steel 78.5
q/cu m
e) Total Quantity
Steel in Terrace Floor
Slab 1 5.94 0.008 7850 373.032
Density of Steel 78.5
q/cu m
1.4 RCC Beam
@ 1.0%
a) Total Quantity
Steel in Ground Floor
Beam 1 8.1855 0.01 7850 642.56175
Time and Resource Management in Construction Project
Department of Civil Engineering, SET, Jain University
29
b) Total Quantity
Steel in First Floor
Beam 1 8.1855 0.01 7850 642.56175
c) Total Quantity
Steel in Second Floor
Beam 1 1.692 0.01 7850 132.822
d) Total Quantity
Steel in Terrace Floor
Beam 1 2.0376 0.01 7850 159.9516
1.5 RCC Plinth
Beam @ 1.0%
a) PB1 + PB2 1 3.9 0.01 7850 306.15
Density of Steel 78.5
q/cu m
b) PB3 1 1.9 0.01 7851 149.169
Density of Steel 78.5
q/cu m
Item No.
Particulars and
Description No.s
Volume
(m3
) Comments
2. Earthwork
in Foundation
Quantity of
Excavation for all
footings 1 82.350625
Footing Type No.s Length (m) Bredth (m) Depth (m)
Quantity of
Excavation (m3
)
4EACF1 1 3.4 1.9 0.5 9.69
4EAF1 2 1.75 1.5 0.35 8.6625
4EAF2 5 1.9 1.7 0.4 25.84
4EAF3 3 2.2 1.95 0.45 19.9485
4EAF4 1 2.45 2.2 0.5 8.085
4EAF5 1 2.85 2.45 0.55 10.124625
Total Quantity of Excavation
(m3
) 82.350625
Item
Particulars and
Description
No.s Length (m)
Bredth
(m)
Height or
Depth (m)
Quantity (m3
) Comments
3. Block Work
a) Ground Floor
Blockwork
i) 200 mm Blocks 1 76.847 0.215 2.95 48.74020975
ii) 100 mm Blocks 1 3.35 0.1 2.95 0.98825
b) First Floor
Blockwork
i) 200 mm Blocks 1 82.072 0.215 2.95 52.054166
ii) 100 mm Blocks 1 14.55 0.1 2.95 4.29225
Time and Resource Management in Construction Project
Department of Civil Engineering, SET, Jain University
30
c) Second Floor
Blockwork
i) 200 mm Blocks
(Parapet) 1 61.472 0.215 0.6 7.929888
ii) 200 mm Blocks
(Study Room) 1 26.65 0.215 2.95 16.9027625
Total Quantity of 200 mm Blocks 125.6270263 m3
Total Quantity of 100 mm Blocks 5.2805 m3
3.1
Deductions
a) Ground
Floor
CW-01 1 2.7 0.2 1.65 0.891
DT-01 1 1.05 0.2 2.4 0.504
DT-02 1 0.9 0.1 2.4 0.216
DT-02 1 0.9 0.2 2.4 0.432
DT-03 2 0.85 0.2 2.4 0.816
DWT-01 1 1.5 0.2 2.4 0.72
SD-01 1 2.4 0.2 2.4 1.152
V-03 2 0.6 0.2 1.2 0.288
W-01 2 1.2 0.2 1.4 0.672
W-02 1 1.2 0.2 1.65 0.396
W-03 1 1 0.2 1.65 0.33
W-04 1 1.35 0.2 1.65 0.4455
W-05 1 0.6 0.2 1.65 0.198
b) First Floor
CW-01 2 2.7 0.2 1.65 1.782
DT-02 2 0.9 0.1 2.4 0.432
DT-02 2 0.9 0.2 2.4 0.864
DT-03 2 0.85 0.1 2.4 0.408
SD-01 1 2.4 0.2 2.4 1.152
V-02 1 1 0.2 1.2 0.24
V-04 1 0.85 0.2 1.2 0.204
W-02 1 1.2 0.2 1.65 0.396
W-03 1 1 0.2 1.65 0.33
W-05 1 0.6 0.2 1.65 0.198
c) Second
Floor
CW-01 1 2.7 0.2 1.65 0.891
DT-04 1 0.9 0.2 2.3 0.414
Time and Resource Management in Construction Project
Department of Civil Engineering, SET, Jain University
31
W-05 1 0.6 0.2 1.65 0.198
Deductions 200 mm
Wall 13.5135 m3
Deductions 100 mm
Wall 1.056 m3
Quantity of Blockwork After Deduction (200 mm) + 10% wastage 123.3248789 m3
Quantity of Blockwork After Deduction (100 mm) + 10% wastage 4.64695 m3
Total Number of 200 mm Block 7707.80493 Units
Total Number of 100 mm Block 580.86875 Units
Item
Particulars and
Description
No.s Length (m)
Bredth
(m)
Height or
Depth (m)
Quantity (m2
) Comments
4. Wall
Plastering
4.1 Ground
Floor
i) Interior Walls 1 98.8 2.95 291.46 468.805
ii) Exterior Walls 1 56.3 3.15 177.345
4.2 First Floor
i) Interior Walls 1 92.8 2.95 273.76 430.7875
ii) Exterior Walls 1 49.85 3.15 157.0275
4.3 Second
Floor
i) Interior Walls 1 18.2 2.95 53.69 116.69
ii) Exterior Walls 1 20 3.15 63
Total Wall Plastering 1016.2825 m2
Item
Particulars and
Description
No.s Length (m)
Bredth
(m)
Height or
Depth (m)
Quantity (m2
) Comments
4.4
Deductions
a) Ground
Floor
CW-01 1 2.7 1.65 4.455
DT-01 1 1.05 2.4 2.52
DT-02 2 0.9 2.4 4.32
DT-03 2 0.85 2.4 4.08
Time and Resource Management in Construction Project
Department of Civil Engineering, SET, Jain University
32
DWT-01 1 1.5 2.4 3.6
SD-01 1 2.4 2.4 5.76
V-03 2 0.6 1.2 1.44
W-01 2 1.2 1.4 3.36
W-02 1 1.2 1.65 1.98
W-03 1 1 1.65 1.65
W-04 1 1.35 1.65 2.2275
W-05 1 0.6 1.65 0.99
b) First Floor
CW-01 2 2.7 1.65 8.91
DT-02 2 0.9 2.4 4.32
DT-02 2 0.9 2.4 4.32
DT-03 2 0.85 2.4 4.08
SD-01 1 2.4 2.4 5.76
V-02 1 1 1.2 1.2
V-04 1 0.85 1.2 1.02
W-02 1 1.2 1.65 1.98
W-03 1 1 1.65 1.65
W-05 1 0.6 1.65 0.99
c) Second
Floor
CW-01 1 2.7 1.65 4.455
DT-04 1 0.9 2.3 2.07
W-05 1 0.6 1.65 0.99
Total Wall Plastering 78.1275 m2
Wall Plastering After Deduction + 10% extra 1031.9705 m2
Item
Particulars and
Description
No.s Length (m)
Bredth
(m)
Height or
Depth (m)
Quantity (m3
) Comments
5. RMC
5.1 RMC for
footing
4EACF1 1 3.4 1.9 0.5 3.23
4EAF1 2 1.75 1.5 0.35 1.8375
4EAF2 5 1.9 1.7 0.4 6.46
4EAF3 3 2.2 1.95 0.45 5.7915
4EAF4 1 2.45 2.2 0.5 2.695
4EAF5 1 2.85 2.45 0.55 3.840375
Total RMC required for footing 23.854375 m3
Time and Resource Management in Construction Project
Department of Civil Engineering, SET, Jain University
33
5.2 RMC for
Column
Columns of Ground
Floor
4EAC16 2 0.2 0.45 3.15 0.567
4EAC17 1 0.2 0.45 3.15 0.2835
4EAC12 1 0.2 0.45 3.15 0.2835
4EAC13 1 0.2 0.45 3.15 0.2835
4EAC11 1 0.2 0.45 3.15 0.2835
4EAC8 1 0.2 0.6 3.15 0.378
4EAC9 1 0.2 0.45 3.15 0.2835
4EAC10 1 0.2 0.375 3.15 0.23625
4EAC6 1 0.2 0.375 3.15 0.23625
4EAC7 1 0.2 0.45 3.15 0.2835
4EAC3 1 0.2 0.45 3.15 0.2835
4EAC4 1 0.2 0.45 3.15 0.2835
4EAC5 1 0.2 0.45 3.15 0.2835
Sum 3.969 m3
Columns of First
Floor
4EAC16 2 0.2 0.45 3.15 0.567
4EAC17 1 0.2 0.45 3.15 0.2835
4EAC12 1 0.2 0.45 3.15 0.2835
4EAC13 1 0.2 0.45 3.15 0.2835
4EAC11 1 0.2 0.45 3.15 0.2835
4EAC8 1 0.2 0.6 3.15 0.378
4EAC9 1 0.2 0.45 3.15 0.2835
4EAC10 1 0.2 0.375 3.15 0.23625
4EAC7 1 0.2 0.45 3.15 0.2835
4EAC3 1 0.2 0.45 3.15 0.2835
4EAC4 1 0.2 0.45 3.15 0.2835
4EAC5 1 0.2 0.45 3.15 0.2835
Sum 3.73275 m3
Columns of Second
Floor
4EAC11 2 0.2 0.45 3.15 0.567
4EAC8 1 0.2 0.6 3.15 0.378
4EAC18 1 0.2 0.3 3.15 0.189
Sum 1.134 m3
Total RMC required for Columns 8.83575 m3
Time and Resource Management in Construction Project
Department of Civil Engineering, SET, Jain University
34
Item
Particulars and
Description
No.s
Quantity
(m3
)
Comments
5.3 RMC for
Slab
a) Total Quantity of
RMC in Ground Floor
Slab 1 22.275
b) Total Quantity of
RMC in First Floor
Slab 1 18.39
c) Total Quantity of
RMC in Second Floor
Slab 1 3.6
d) Total Quantity of
RMC in Study Room
Slab 1 1.9305
e) Total Quantity of
RMC in Terrace Floor
Slab 1 5.94
Total RMC required for Slabs 52.1355 m3
Item
Particulars and
Description
No.s
Quantity
(m3
)
Comments
5.3 RMC for
Plinth Beam
a) PB1 + PB2 1 3.9
b) PB3 1 1.9
Total RMC required for Plinth Beam 5.8 m3
Item
Particulars and
Description
No.s Length (m)
Bredth
(m)
Height or
Depth (m)
Quantity (m3
) Comments
5.3 RMC for
Beam
a) First Floor Beams 90.95 0.2 0.45 8.1855
b) Second Floor
Beam 18.8 0.2 0.45 1.692
Total RMC required for Beams 9.8775 m3
Quantity of RMC required for a villa + 10%
extra=
150.7546875
m3
Item Particulars and No.s Area (m2
) Depth (m) Quantity (m3
) Comments
Time and Resource Management in Construction Project
Department of Civil Engineering, SET, Jain University
35
Description
6. PCC
6.1 Ground
Floor Flooring
a) Guest Bedroom 1 18.153 0.1 1.8153
b) Living cum Dining 1 39.767 0.1 3.9767
c) Staircase 1 11.529 0.1 1.1529
d) Kitchen 1 11.29 0.1 1.129
e) Utility Room 1 6.125 0.1 0.6125
f) Servent Room +
Path 1 8.52 0.1 0.852
g) Lobby 1 6.12 0.1 0.612
h) Verandah 1 4.002 0.1 0.4002
Total PCC required for flooring 10.5506 m3
Footing Type No.s Length (m) Bredth (m)
Quantity of
Excavation
(m3
)
Comments
6.2 PCC below
Footing
4EACF1 1 3.4 1.9 0.756
4EAF1 2 1.75 1.5 0.663
4EAF2 5 1.9 1.7 1.995
4EAF3 3 2.2 1.95 1.548
4EAF4 1 2.45 2.2 0.636
4EAF5 1 2.85 2.45 0.80825
Total PCC required for flooring 6.40625 m3
6.3 PCC @ DPC Total PCC required for Damp-Proof 1.051875 m3
6.4 PCC below Plinth (Inner Walls) Total PCC required below Plinth 1.394 m3
6.5 PCC below
SSM
Total PCC required below SSM
3.22575 m3
Quantity of PCC required for a villa = 22.628475 m3
Quantity of PCC required for a villa + 10%
extra=
24.8913225
m3
7. Size Stone
Masonry
Quantity of SSM
8.415 m3
Time and Resource Management in Construction Project
Department of Civil Engineering, SET, Jain University
36
Item
Particulars and
Description
No.s Length (m)
Bredth
(m)
Height or
Depth (m)
Quantity of
Shuttering
(m2
)
Comments
8. Shuttering
8.1 Shuttering
for footings
4EACF1 1 3.4 1.9 0.5 5.3
4EAF1 2 1.75 1.5 0.35 4.55
4EAF2 5 1.9 1.7 0.4 14.4
4EAF3 3 2.2 1.95 0.45 11.205
4EAF4 1 2.45 2.2 0.5 4.65
4EAF5 1 2.85 2.45 0.55 5.83
Quantity of Shuttering for Footings 45.935 m2
8.2 Shuttering
for Column
a) Columns of
Ground Floor
4EAC16 2 0.2 0.45 3.15 8.19
4EAC17 1 0.2 0.45 3.15 4.095
4EAC12 1 0.2 0.45 3.15 4.095
4EAC13 1 0.2 0.45 3.15 4.095
4EAC11 1 0.2 0.45 3.15 4.095
4EAC8 1 0.2 0.6 3.15 5.04
4EAC9 1 0.2 0.45 3.15 4.095
4EAC10 1 0.2 0.375 3.15 3.6225
4EAC6 1 0.2 0.375 3.15 3.6225
4EAC7 1 0.2 0.45 3.15 4.095
4EAC3 1 0.2 0.45 3.15 4.095
4EAC4 1 0.2 0.45 3.15 4.095
4EAC5 1 0.2 0.45 3.15 4.095
Sum 57.33 m2
b) Columns of First
Floor
4EAC16 2 0.2 0.45 3.15 8.19
4EAC17 1 0.2 0.45 3.15 4.095
4EAC12 1 0.2 0.45 3.15 4.095
4EAC13 1 0.2 0.45 3.15 4.095
4EAC11 1 0.2 0.45 3.15 4.095
4EAC8 1 0.2 0.6 3.15 5.04
4EAC9 1 0.2 0.45 3.15 4.095
4EAC10 1 0.2 0.375 3.15 3.6225
4EAC7 1 0.2 0.45 3.15 4.095
4EAC3 1 0.2 0.45 3.15 4.095
4EAC4 1 0.2 0.45 3.15 4.095
Time and Resource Management in Construction Project
Department of Civil Engineering, SET, Jain University
37
4EAC5 1 0.2 0.45 3.15 4.095
Sum 53.7075 m2
c) Columns of
Second Floor
4EAC11 2 0.2 0.45 3.15 8.19
4EAC8 1 0.2 0.6 3.15 5.04
4EAC18 1 0.2 0.3 3.15 3.15
Sum 16.38 m2
Total Shuttering required for Columns 127.4175 m2
8.3 Shuttering for Slabs and Beams
i) Shuttering for Slab
a) Ground Floor Slab Shuttering 130.31 m2
b) First Floor Slab Shuttering 104.41 m2
c) Second Floor Slab Shuttering 24 m2
d) Study Room Slab Shuttering 12.87 m2
d) Terrace Floor Slab Shuttering 39.6 m2
Total Shuttering required for Slabs 311.19 m2
ii) Shuttering for
Beams
a) Ground Floor Beams 58.208 m2
b) First Floor Beams 58.23 m2
c) Second Floor Beams 12.032 m2
d) Plinth Beam 36.384 m2
Total Shuttering required for Beams 164.854 m2
Quantity of Shuttering required for Slabs & Beams 476.044 m2
Quantity of Shuttering required for a villa 649.3965 m2
Quantity of Shuttering required for a villa + 10% extra 714.33615 m2
Time and Resource Management in Construction Project
Department of Civil Engineering, SET, Jain University
38
Item
Particulars and
Description
No.s Area (m2
) Comments
9. Ceiling
Plastering
9.1 Ground
Floor Ceiling
a) Guest Bedroom 1 18.153
b) Living cum Dining 1 39.767
c) Staircase 1 11.529
d) Kitchen 1 11.29
e) Utility Room 1 6.125
f) Servent Room +
Path 1 8.52
g) Lobby 1 6.12
h) Verandah 1 4.002
i) Toilet-1 1 2.15
j) Toilet-2 1 3.6
k) Sitout 1 8.9
l) Parking 1 14.7
Total Ceiling in Ground Floor 134.856 m2
9.2 First Floor
Ceiling
a) Master Bed 31.3
b) Family Lounge 28.28
c) Court 1.78
d) Toilet-1 5.48
e) Toilet-2 5.035
f) Children's Bed 18.125
Total Ceiling in First Floor 90 m2
9.3 Second
Floor Ceiling
a) Study Room 20.339
Total Ceiling in First Floor 20.339 m2
Total Area of Ceiling Plastering 245.195 m2
Table 4.1 Estimation and Quantities
Time and Resource Management in Construction Project
Department of Civil Engineering, SET, Jain University
39
Chapter 5
5. REPORTS FROM MSP
5.1. S CURVE METHOD
S-curves are an important project management tool. They allow the progress
of a project to be tracked visually over time, and form a historical record of
what has happened to date. Analyses of S-curves allow project managers to
quickly identify project growth, slippage, and potential problems that could
adversely impact the project if no remedial action is taken.
5.1.1. Generating S-curves
5.1.1.1. Project Benchmarks
Percentage S-curves may be used to calculate important project benchmarks
on an ongoing basis, including:
 Project percentage growth (Target and Baseline S-curves)
 Project percentage slippage (Target and Baseline S-curves)
 Actual percentage complete against Target percentage complete to date
 Actual percentage complete against Baseline percentage complete to
date
5.1.1.2. Steps to generate S Curve
To generate a Baseline S-curve, a Baseline Schedule is required.
The Baseline Schedules should contain the following information for each
task:
 Baseline Start Date, Finish Date
 Baseline Man Hours and/or Costs
Time and Resource Management in Construction Project
Department of Civil Engineering, SET, Jain University
40
To generate Actual and Target S-curves, a Production Schedule is required.
The Production Schedules should contain the following information for each
task:
 Actual Start Date, Finish Date
 Actual Man Hours and/or Costs
 Actual Percentage Complete
Figure 5.1 S-Curve graphs
Time and Resource Management in Construction Project
Department of Civil Engineering, SET, Jain University
41
5.2. GANTT CHART
A Gantt chart, commonly used in project management, is one of the most popular
and useful ways of showing activities (tasks or events) displayed against time.
On the left of the chart is a list of the activities and along the top is a suitable
time scale. Each activity is represented by a bar; the position and length of the
bar reflects the start date, duration and end date of the activity. This allows you
to see at a glance:
 What the various activities are
 When each activity begins and ends
 How long each activity is scheduled to last
 Where activities overlap with other activities, and by how much
 The start and end date of the whole project
To summarize, a Gantt chart shows you what has to be done (the activities) and
when (the schedule).
Figure 5.2 Simple Gantt Chart
(Reports will be submitted by Hard Copy)
Time and Resource Management in Construction Project
Department of Civil Engineering, SET, Jain University
42
Time and Resource Management in Construction Project
Department of Civil Engineering, SET, Jain University
43
Chapter 6
6. CONCLUSION & DISCUSSIONS
In this project, the effective utilization of time and resource of constructing a
3BHK villa has been studied. Time is a very important factor to complete the
work within the given deadline or even earlier. The project is done with the use
of MSP which is project management software. The procedure for the project
included understanding the project and creation of WBS, creation of level 3
activities, master construction program, resource scheduling and cash flow
projection, monitoring and tracking.
Time, resource and cost are inter-related. If we reduce the time of completion,
the price will increase and vice- versa. The price will increase as the more
amount of labour and then resources will have to be made available in short time.
If resources are available near the site of construction, then the cost of
transportation and also tax charges will be minimum in turn reducing the cost of
the project.
The time estimation results showed that the 3bhk villa can be completed in 135
days given that the work will proceeded smoothly as planned.
Time and Resource Management in Construction Project
Department of Civil Engineering, SET, Jain University
44
Chapter 7
7. REFERENCES
1. Estimation and costing in Civil Engineering by B.N Dutta 26th
edition
2. Construction Planning And Management by P.S. Gahlot and B.M. Dhir
3. http://en.wikipedia.org/wiki/Project_management
4. http://www.tutorialspoint.com/management_concepts/project_management
_triangle.htm

More Related Content

What's hot

GMR infrastructures LTD.
GMR infrastructures LTD.GMR infrastructures LTD.
GMR infrastructures LTD.Vineeta Karki
 
Poject on aviation sector in india
Poject on aviation sector in indiaPoject on aviation sector in india
Poject on aviation sector in indiaShreeraj Hariharan
 
MBA Final Year Project
MBA Final Year ProjectMBA Final Year Project
MBA Final Year ProjectArun Kumar
 
Report on information systems innovation at Airtel IT Bangladesh
Report on information systems innovation at Airtel IT BangladeshReport on information systems innovation at Airtel IT Bangladesh
Report on information systems innovation at Airtel IT BangladeshAzas Shahrier
 
R language Project report
R language Project reportR language Project report
R language Project reportTianyue Wang
 
infosys hr policies
infosys hr policiesinfosys hr policies
infosys hr policiesSneha Joy
 
Final Report for Summer internship at Software House
Final Report for Summer internship at Software HouseFinal Report for Summer internship at Software House
Final Report for Summer internship at Software HouseSaad Shahzad
 
Summer internship project report
Summer internship project reportSummer internship project report
Summer internship project reportManish Singh
 
Turnaround Of Indian Railways
Turnaround Of Indian RailwaysTurnaround Of Indian Railways
Turnaround Of Indian RailwaysRushabh Thakker
 
Comparison between TCS and DHL
Comparison between TCS and DHL Comparison between TCS and DHL
Comparison between TCS and DHL Arslan Ali Butt
 
Talent mnagement- MBA(HR) project
Talent mnagement- MBA(HR) projectTalent mnagement- MBA(HR) project
Talent mnagement- MBA(HR) projectAmol30586
 
Logistics-project-report
Logistics-project-reportLogistics-project-report
Logistics-project-reportTushar G
 
Project report on Salary structure
Project report on Salary structureProject report on Salary structure
Project report on Salary structureAyesha Hamid
 
Project report on recruitment and selection at cmpdi
Project report on recruitment and selection at cmpdiProject report on recruitment and selection at cmpdi
Project report on recruitment and selection at cmpdiKumari Pswn
 
INT217 Project Report: Excel Dashboard
INT217 Project Report: Excel DashboardINT217 Project Report: Excel Dashboard
INT217 Project Report: Excel DashboardQazi Maaz Arshad
 
Summer internship report
Summer internship reportSummer internship report
Summer internship reportSakshi Bansal
 
BBA final year internship project report
BBA final year internship project reportBBA final year internship project report
BBA final year internship project reportJaimin Patel
 

What's hot (20)

GMR infrastructures LTD.
GMR infrastructures LTD.GMR infrastructures LTD.
GMR infrastructures LTD.
 
Poject on aviation sector in india
Poject on aviation sector in indiaPoject on aviation sector in india
Poject on aviation sector in india
 
MBA Final Year Project
MBA Final Year ProjectMBA Final Year Project
MBA Final Year Project
 
Report on information systems innovation at Airtel IT Bangladesh
Report on information systems innovation at Airtel IT BangladeshReport on information systems innovation at Airtel IT Bangladesh
Report on information systems innovation at Airtel IT Bangladesh
 
R language Project report
R language Project reportR language Project report
R language Project report
 
infosys hr policies
infosys hr policiesinfosys hr policies
infosys hr policies
 
Final Report for Summer internship at Software House
Final Report for Summer internship at Software HouseFinal Report for Summer internship at Software House
Final Report for Summer internship at Software House
 
Dbms lab file format front page
Dbms lab file format front pageDbms lab file format front page
Dbms lab file format front page
 
Sales Function at TCS.
Sales Function at TCS.Sales Function at TCS.
Sales Function at TCS.
 
Summer internship project report
Summer internship project reportSummer internship project report
Summer internship project report
 
Turnaround Of Indian Railways
Turnaround Of Indian RailwaysTurnaround Of Indian Railways
Turnaround Of Indian Railways
 
Comparison between TCS and DHL
Comparison between TCS and DHL Comparison between TCS and DHL
Comparison between TCS and DHL
 
Talent mnagement- MBA(HR) project
Talent mnagement- MBA(HR) projectTalent mnagement- MBA(HR) project
Talent mnagement- MBA(HR) project
 
Logistics-project-report
Logistics-project-reportLogistics-project-report
Logistics-project-report
 
Project report on Salary structure
Project report on Salary structureProject report on Salary structure
Project report on Salary structure
 
Project report on recruitment and selection at cmpdi
Project report on recruitment and selection at cmpdiProject report on recruitment and selection at cmpdi
Project report on recruitment and selection at cmpdi
 
INT217 Project Report: Excel Dashboard
INT217 Project Report: Excel DashboardINT217 Project Report: Excel Dashboard
INT217 Project Report: Excel Dashboard
 
Summer internship report
Summer internship reportSummer internship report
Summer internship report
 
BBA final year internship project report
BBA final year internship project reportBBA final year internship project report
BBA final year internship project report
 
Ptcl report-2
Ptcl report-2Ptcl report-2
Ptcl report-2
 

Viewers also liked (12)

Мир света и красок
Мир света и красокМир света и красок
Мир света и красок
 
Samford University Case Study and Digital Asset Management Best Practices
Samford University Case Study and Digital Asset Management Best PracticesSamford University Case Study and Digital Asset Management Best Practices
Samford University Case Study and Digital Asset Management Best Practices
 
Pt. pks medan centre point
Pt. pks   medan centre pointPt. pks   medan centre point
Pt. pks medan centre point
 
Case study
Case studyCase study
Case study
 
Kaizen – Forms & Checklists
Kaizen – Forms & ChecklistsKaizen – Forms & Checklists
Kaizen – Forms & Checklists
 
Jindal group housing case study
Jindal group housing case studyJindal group housing case study
Jindal group housing case study
 
Yamuna apartments Case Study
Yamuna apartments Case StudyYamuna apartments Case Study
Yamuna apartments Case Study
 
HOUSING CASE STUDY
HOUSING CASE STUDYHOUSING CASE STUDY
HOUSING CASE STUDY
 
Aranya Low Cost Housing
Aranya Low Cost HousingAranya Low Cost Housing
Aranya Low Cost Housing
 
Architectural case study of Apartments
Architectural case study of ApartmentsArchitectural case study of Apartments
Architectural case study of Apartments
 
Palestra codephant
Palestra codephantPalestra codephant
Palestra codephant
 
Housing project in New Mumbai ppt
Housing project in New Mumbai pptHousing project in New Mumbai ppt
Housing project in New Mumbai ppt
 

Similar to jain university Project Report

Report on Planning & scheduling of a Minor bridge
Report on Planning & scheduling of a Minor bridgeReport on Planning & scheduling of a Minor bridge
Report on Planning & scheduling of a Minor bridgeKundan Sanap
 
final year civil engineering training report
final year civil engineering training report final year civil engineering training report
final year civil engineering training report Poojan Patel
 
Present status of apartment building approval and construction
Present status of apartment building approval and constructionPresent status of apartment building approval and construction
Present status of apartment building approval and constructionBinay Shrestha
 
Resource scheduling in Construction Project Using Microsoft Project
Resource scheduling in Construction Project Using Microsoft ProjectResource scheduling in Construction Project Using Microsoft Project
Resource scheduling in Construction Project Using Microsoft ProjectSagar Kaptan
 
Nnbc update reco-final july 2009 - Recommendation for update of National Buil...
Nnbc update reco-final july 2009 - Recommendation for update of National Buil...Nnbc update reco-final july 2009 - Recommendation for update of National Buil...
Nnbc update reco-final july 2009 - Recommendation for update of National Buil...Badan Lal Nyachhyon
 
Vocational training report l&t
Vocational training report l&tVocational training report l&t
Vocational training report l&tNishant Pandey
 
EFFECT OF W/C RATIO, ADMIXTURE, SIZE OF AGGREGATE ON COMPRESSIVE STRENGTH OF ...
EFFECT OF W/C RATIO, ADMIXTURE, SIZE OF AGGREGATE ON COMPRESSIVE STRENGTH OF ...EFFECT OF W/C RATIO, ADMIXTURE, SIZE OF AGGREGATE ON COMPRESSIVE STRENGTH OF ...
EFFECT OF W/C RATIO, ADMIXTURE, SIZE OF AGGREGATE ON COMPRESSIVE STRENGTH OF ...Ravi Thakur
 
Flood modelling of Periyar basin using SWAT
Flood modelling of Periyar basin using SWAT Flood modelling of Periyar basin using SWAT
Flood modelling of Periyar basin using SWAT RithwikMohan2
 
E secure transaction project report (Design and implementation of e-secure t...
E secure transaction project  report (Design and implementation of e-secure t...E secure transaction project  report (Design and implementation of e-secure t...
E secure transaction project report (Design and implementation of e-secure t...AJIT Singh
 
Project final report
Project final reportProject final report
Project final reportALIN BABU
 
Be project report format2012 13
Be project report format2012 13Be project report format2012 13
Be project report format2012 13vivek
 
Be project report format2012 13
Be project report format2012 13Be project report format2012 13
Be project report format2012 13vivek
 
Student's Work Experience Program (SWEP) by IGINA PAUL
Student's Work Experience Program (SWEP) by IGINA PAUL Student's Work Experience Program (SWEP) by IGINA PAUL
Student's Work Experience Program (SWEP) by IGINA PAUL iginapaul
 
Application Of Microsoft Project To Manage Successful Project
Application Of Microsoft Project To Manage Successful ProjectApplication Of Microsoft Project To Manage Successful Project
Application Of Microsoft Project To Manage Successful ProjectJennifer Daniel
 
Document Archiving & Sharing System
Document Archiving & Sharing SystemDocument Archiving & Sharing System
Document Archiving & Sharing SystemAshik Iqbal
 
Industrial training report
Industrial training reportIndustrial training report
Industrial training reportChanaka Sudheera
 
Supporting Collaboration and Harnessing of OER Within the Policy Framework of...
Supporting Collaboration and Harnessing of OER Within the Policy Framework of...Supporting Collaboration and Harnessing of OER Within the Policy Framework of...
Supporting Collaboration and Harnessing of OER Within the Policy Framework of...Saide OER Africa
 
Health OER Inter-Institutional Project Formative Evaluation of Health OER Des...
Health OER Inter-Institutional Project Formative Evaluation of Health OER Des...Health OER Inter-Institutional Project Formative Evaluation of Health OER Des...
Health OER Inter-Institutional Project Formative Evaluation of Health OER Des...Saide OER Africa
 
Project Management Leadership, And Skills : Planning And Control | Assignment...
Project Management Leadership, And Skills : Planning And Control | Assignment...Project Management Leadership, And Skills : Planning And Control | Assignment...
Project Management Leadership, And Skills : Planning And Control | Assignment...Emre Dirlik
 

Similar to jain university Project Report (20)

Report on Planning & scheduling of a Minor bridge
Report on Planning & scheduling of a Minor bridgeReport on Planning & scheduling of a Minor bridge
Report on Planning & scheduling of a Minor bridge
 
final year civil engineering training report
final year civil engineering training report final year civil engineering training report
final year civil engineering training report
 
Present status of apartment building approval and construction
Present status of apartment building approval and constructionPresent status of apartment building approval and construction
Present status of apartment building approval and construction
 
Resource scheduling in Construction Project Using Microsoft Project
Resource scheduling in Construction Project Using Microsoft ProjectResource scheduling in Construction Project Using Microsoft Project
Resource scheduling in Construction Project Using Microsoft Project
 
Nnbc update reco-final july 2009 - Recommendation for update of National Buil...
Nnbc update reco-final july 2009 - Recommendation for update of National Buil...Nnbc update reco-final july 2009 - Recommendation for update of National Buil...
Nnbc update reco-final july 2009 - Recommendation for update of National Buil...
 
Vocational training report l&t
Vocational training report l&tVocational training report l&t
Vocational training report l&t
 
EFFECT OF W/C RATIO, ADMIXTURE, SIZE OF AGGREGATE ON COMPRESSIVE STRENGTH OF ...
EFFECT OF W/C RATIO, ADMIXTURE, SIZE OF AGGREGATE ON COMPRESSIVE STRENGTH OF ...EFFECT OF W/C RATIO, ADMIXTURE, SIZE OF AGGREGATE ON COMPRESSIVE STRENGTH OF ...
EFFECT OF W/C RATIO, ADMIXTURE, SIZE OF AGGREGATE ON COMPRESSIVE STRENGTH OF ...
 
Performance
PerformancePerformance
Performance
 
Flood modelling of Periyar basin using SWAT
Flood modelling of Periyar basin using SWAT Flood modelling of Periyar basin using SWAT
Flood modelling of Periyar basin using SWAT
 
E secure transaction project report (Design and implementation of e-secure t...
E secure transaction project  report (Design and implementation of e-secure t...E secure transaction project  report (Design and implementation of e-secure t...
E secure transaction project report (Design and implementation of e-secure t...
 
Project final report
Project final reportProject final report
Project final report
 
Be project report format2012 13
Be project report format2012 13Be project report format2012 13
Be project report format2012 13
 
Be project report format2012 13
Be project report format2012 13Be project report format2012 13
Be project report format2012 13
 
Student's Work Experience Program (SWEP) by IGINA PAUL
Student's Work Experience Program (SWEP) by IGINA PAUL Student's Work Experience Program (SWEP) by IGINA PAUL
Student's Work Experience Program (SWEP) by IGINA PAUL
 
Application Of Microsoft Project To Manage Successful Project
Application Of Microsoft Project To Manage Successful ProjectApplication Of Microsoft Project To Manage Successful Project
Application Of Microsoft Project To Manage Successful Project
 
Document Archiving & Sharing System
Document Archiving & Sharing SystemDocument Archiving & Sharing System
Document Archiving & Sharing System
 
Industrial training report
Industrial training reportIndustrial training report
Industrial training report
 
Supporting Collaboration and Harnessing of OER Within the Policy Framework of...
Supporting Collaboration and Harnessing of OER Within the Policy Framework of...Supporting Collaboration and Harnessing of OER Within the Policy Framework of...
Supporting Collaboration and Harnessing of OER Within the Policy Framework of...
 
Health OER Inter-Institutional Project Formative Evaluation of Health OER Des...
Health OER Inter-Institutional Project Formative Evaluation of Health OER Des...Health OER Inter-Institutional Project Formative Evaluation of Health OER Des...
Health OER Inter-Institutional Project Formative Evaluation of Health OER Des...
 
Project Management Leadership, And Skills : Planning And Control | Assignment...
Project Management Leadership, And Skills : Planning And Control | Assignment...Project Management Leadership, And Skills : Planning And Control | Assignment...
Project Management Leadership, And Skills : Planning And Control | Assignment...
 

jain university Project Report

  • 1. School of Engineering & Technology Jain Global Campus, Kanakapura Taluk - 562112 Ramanagara District, Karnataka, INDIA 2013-2014 A Project Report on Time and Resource Management of Construction Project Submitted in partial fulfilment for the award of the degree of BACHELOR OF ENGINEERING IN CIVIL ENGINEERING Submitted by Rathan Kumar N M (09BE6CV035) Amruthesh K (09BE6CV008) Sukesh Shetty (09BE6CV043) Mentor Dr. Shashishankar A HOD, Department of Civil Engineering (Internal Guide) Mr. Yashwanth Managing Director, SYConE CPMC PVT. LTD (External Guide)
  • 2. SCHOOL OF ENGINEERING & TECHNOLOGY Jain Global campus Kanakapura Taluk - 562112 Ramanagara District Karnataka, INDIA CERTIFICATE This is to certify that this project work titled ‗Time and Resource Management of Construction Project’, is carried out by ‘Rathan Kumar N M (09BE6CV035)’, ‘Amrutesh K (09BE6CV008)’ and ‘Sukesh Shetty (10BE6CV043)’, bona fide students of Bachelor of Civil Engineering at the School of Engineering & Technology, Jain University, in partial fulfilment for the award of Bachelor of Engineering in Civil Engineering, during the year 2013-2014 External Examiner: 1. 2. Dr. A Shashishankar Mr. Yashwanth C B Mohan Professor – Civil Department SET – Jain University Date: Managing Director SYConE CPMC PVT. LTD Date: Associate Director SET – Jain University Date: (HOD) (External guide) (Associate Director) (Internal Project Guide)
  • 3. DECLARATION We, ‗Rathan Kumar N M, Sukesh Shetty , Amrutesh K’, students of VIII semester B.E in Civil Engineering at School of Engineering and Technology – Jain University, hereby declare that the dissertation titled ‗Time and Resource Management of Construction Project’ has been conducted by us at School of Engineering and Technology – Jain University (SET-JU) and submitted in partial fulfilment for the award of Bachelor of Engineering in Civil Engineering, during the academic year February – May 2013-2014, under the guidance and supervision of Dr. Shashishankar A, Professor and Head, Department of Civil Engineering. Further the matter embodied in the dissertation has not been submitted previously by anybody for the award of any degree or diploma to any University, to the best of my knowledge and faith. PLACE : DATE : Rathan Kumar N M Amrutesh K Sukesh K (09BE6CV035) (09BE6CV008) (10BE6CV043)
  • 4. ABSTRACT Project management is the process and activity of planning, organizing, motivating, and controlling resources, procedure and protocols to realize completion of the project. The primary challenge of project management is to achieve all of the project goals and objectives while honouring the preconceived constraints. The constraints are scope, time, quality and budget. The purpose of this project is to utilize time and resource efficiently. The title of the project is ―Time and Resource Management‖, in-order to manage Resources such as labour, material, cost, so on. Time is a very important factor to complete the work within the given deadline or even earlier. The project is done with the use of MSP which is project management software. The procedure for the project included understanding the project and creation of WBS, creation of level 3 activities, master construction programme, resource scheduling and cash flow projection, monitoring and tracking. Detailed quantity estimation of constructing a villa is being shown in this project. Also the time estimation and management of the villa is also included in this report.
  • 5.
  • 6. CONTENTS Abstract ....................................................................................................... i Contents ......................................................................................................... ii List of tables ................................................................................................... v List of figures ................................................................................................ vi 1 Introduction ...................................................Error! Bookmark not defined. 1.1 History......................................................Error! Bookmark not defined. 1.1.1 The Pre 19th century ............................Error! Bookmark not defined. 1.1.2 The 20th century ................................................................................ 2 1.2 Approaches of project management....................................................... 2 1.3Process of project management................................................................. 2 1.3.1 initiation........................................................................................... 3 1.3.1.1 Scope of the project management company ............................. 3 1.3.2 Planning .......................................................................................... 3 1.3.3 Executing ......................................................................................... 4 1.3.4 Monitoring and controlling ............................................................... 4 1.3.5 Closing............................................................................................. 4 1.4 Constraints of a project............................................................................ 5 1.4.1 Time................................................................................................. 5 1.4.2 Cost.............................................................................................. 5 1.4.3 Scope ............................................................................................... 6 1.4.4 Quality ............................................................................................. 6
  • 7. 1.5 Time management ................................................................................... 6 1.5.1 The importance of time management for a construction project .......... 7 1.6 Resource management ............................................................................. 8 1.6.1 Labour productivity .......................................................................... 8 1.6.2 Material management ....................................................................... 9 1.7 Scheduling .............................................................................................10 1.7.1 Methods of scheduling.......................................................................11 2 Site Details ................................................................................................13 2.1 Companies involved in the project .........................................................13 2.2 Enterprise project structure....................................................................14 2.3 Organization breakdown structure............Error! Bookmark not defined.4 2.4 Work breakdown structures ....................................................................14 3 Drawing Details ..........................................................................................24 3.1 Groung floor ..........................................................................................24 3.2 First floor...............................................................................................25 3.3 Second floor...........................................................................................26 3.4 Terrace floor ..........................................................................................27 4 Estimation and Quantites............................................................................28 5 Reports obtained from MSP........................................................................39 5.1 S-Curve Method .....................................................................................39
  • 8. 5.1.1 Generating S-Curve .............................................................................39 5.1.1.1Project Benchmark ............................................................................39 5.1.1.2 Steps to generate S-Curve .................................................................39 5.2 Gantt Chart ............................................................................................41 5.3Project Summary Report..........................................................................42 5.4 Tracking Reports....................................................................................41 5.4 Cash-Flow Report ..................................................................................41 6.0 Conclusion and Discussions.....................................................................42 7.0 References ..............................................................................................43
  • 9. Time and Resource Management in Construction Project Department of Civil Engineering, SET, Jain University 1 LIST OF TABLES Table 2.1 Details of Villa at project site Table 4.1 Estimation and Quantities
  • 10. Time and Resource Management in Construction Project Department of Civil Engineering, SET, Jain University 2 LIST OF FIGURES Figure.1.1 Process group flowchart Figure 1.2 Project management triangle Figure 2.1 Organization Breakdown Structure Flowchart Figure 2.2 Typical Work Breakdown Structure Figure 2.3 Activity and Event Network Figure 3.1 Ground Floor Plan Figure 3.2 First Floor Plan Figure 3.3 Second Floor Plan Figure 3.4 Terrace Floor Plan Figure 5.1 S-Curve Graphs Figure 5.2 Simple Gantt chart
  • 11. Time and Resource Management in Construction Project Department of Civil Engineering, SET, Jain University 3
  • 12. Time and Resource Management in Construction Project Department of Civil Engineering, SET, Jain University 1 CHAPTER 1 1. INTRODUCTION Management is the process of getting activities completed efficiently and effectively with and through other people. The term Management has different meaning in different perspective. Project management is the process and activity of planning, organizing, motivating, and controlling resources, procedures and protocols to achieve specific goals in scientific or daily problems. A project is a temporary endeavor designed to produce a unique product, service or result with a defined beginning and end (usually time-constrained, and often constrained by funding or deliverables), undertaken to meet unique goals and objectives, typically to bring about beneficial change or added value. The temporary nature of projects stands in contrast with business as usual (or operations), which are repetitive, permanent, or semi-permanent functional activities to produce products or services. In practice, the management of these two systems is often quite different, and as such requires the development of distinct technical skills and management strategies. The primary challenge of project management is to achieve all of the project goals and objectives while honoring the preconceived constraints. The primary constraints are scope, time, quality and budget. The secondary — and more ambitious — challenge is to optimize the allocation of necessary inputs and integrate them to meet pre-defined objectives. 1.1. HISTORY 1.1.1. THE PRE 19TH CENTURY Until 1900, civil engineering projects were generally managed by creative architects, engineers, and master builders themselves. Project management has existed in some form for thousands of years. After all anything that requires an approach where humans organize effectively to a plan and achieve specific objectives can be loosely defined as a project. How else would have humans achieved some of stunning wonders and achievements.
  • 13. Time and Resource Management in Construction Project Department of Civil Engineering, SET, Jain University 2 The forerunners of engineers, practical artists and craftsmen, proceeded mainly by trial and error. Yet tinkering combined with imagination produced many marvelous devices. Many ancient monuments cannot fail to incite admiration. The admiration is embodied in the name ―engineer‖ itself. It originated in the eleventh century from the Latin ingeniator, meaning one with ingenium, the ingenious one. The 18th and 19th Century and the Industrial Revolutions witnessed changes in the Western World with industrial revolutions and with this the birth of management principles in the business to become the backbone of project management. 1.1.2. THE 20TH CENTURY The 20th century witnessed colossal improvements across the world with two industrial revolutions which required a far more structured approach to business and management as the scale of objectives changed. 1.2. APPROACHES OF PROJECT MANAGEMENT  The traditional approach  PRINCE2  Critical chain project management  Event chain methodology  Process-based management  Agile project management  Lean project management  Extreme project management  Benefits realization management 1.3. PROCESSES OF PROJECT MANAGEMENTS Traditionally, project management includes a number of elements: four to five process groups, and a control system. Regardless of the methodology or terminology used, the same basic project management processes will be used.
  • 14. Time and Resource Management in Construction Project Department of Civil Engineering, SET, Jain University 3 Major process groups generally include:  Initiation  Planning  Execution  Monitoring and controlling  Closing Figure 1.1 Process groups flowchart 1.3.1. INITIATION The Project Initiation Phase is the most crucial phase in the Project Life Cycle, as it's the phase in which you define your scope and hire your team. With a clearly defined scope and a suitably skilled team, you can ensure success. If this stage is not performed well, it is unlikely that the project will be successful in meeting the business‘ needs. The key project controls needed here are an understanding of the business environment and making sure that all necessary controls are incorporated into the project. Any deficiencies should be reported and a recommendation should be made to fix them. 1.3.1.1. SCOPE OF PROJECT MANAGEMENT COMPANY (PMC)  Planning and Co-ordination  Construction Supervision o Control over Master Construction Schedule (MCS)  Quality Control  Site co-ordination and Construction Execution  Personnel  PMC‘s responsibility after completion of project  Professional Misconduct 1.3.2. PLANNING After the initiation stage, the project is planned to an appropriate level of detail (see example of a flow-chart). The main purpose is to plan time, cost and
  • 15. Time and Resource Management in Construction Project Department of Civil Engineering, SET, Jain University 4 resources adequately to estimate the work needed and to effectively manage risk during project execution. As with the Initiation process group, a failure to adequately plan greatly reduces the project's chances of successfully accomplishing its goals. Additional processes, such as planning for communications and for scope management, identifying roles and responsibilities, determining what to purchase for the project and holding a kick- off meeting are also generally advisable. For new product development projects, conceptual design of the operation of the final product may be performed concurrent with the project planning activities, and may help to inform the planning team when identifying deliverables and planning activities. 1.3.3. EXECUTING Executing consists of the processes used to complete the work defined in the project plan to accomplish the project's requirements. Execution process involves coordinating people and resources, as well as integrating and performing the activities of the project in accordance with the project management plan. The deliverables are produced as outputs from the processes performed as defined in the project management plan and other frameworks that might be applicable to the type of project at hand. 1.3.4. MONITORING AND CONTROLLING Monitoring and controlling consists of those processes performed to observe project execution so that potential problems can be identified in a timely manner and corrective action can be taken, when necessary, to control the execution of the project. The key benefit is that project performance is observed and measured regularly to identify variances from the project management plan. 1.3.5. CLOSING Closing includes the formal acceptance of the project and the ending thereof. Administrative activities include the archiving of the files and documenting lessons learned.
  • 16. Time and Resource Management in Construction Project Department of Civil Engineering, SET, Jain University 5 The Closing phase consists of: Contract closure: Complete and settle each contract (including the resolution of any open items) and close each contract applicable to the project or project phase. Project closure: Finalize all activities across all of the process groups to formally close the project or a project phase. 1.4. CONSTRAINTS OF A PROJECT The project management triangle is used by managers to analyze or understand the difficulties that may arise due to implementing and executing a project. All projects irrespective of their size will have many constraints. Although there are many such project constraints, these should not be barriers for successful project execution and for the effective decision making. There are three main interdependent constraints for every project; Time, Cost and Scope. This is also known as Project Management Triangle. Fig 1.2 Project Management Triangle 1.4.1. TIME A project's activities can either take shorter or longer amount of time to complete. Completion of tasks depends on a number of factors such as the number of people working on the project, experience, skills, etc. Time is a crucial factor which is uncontrollable. On the other hand, failure to meet the deadlines in a project can create adverse effects. Most often, the main reason for organizations to fail in terms of time is due to lack of resources.
  • 17. Time and Resource Management in Construction Project Department of Civil Engineering, SET, Jain University 6 1.4.2. COST It's imperative for both the project manager and the organization to have an estimated cost when undertaking a project. Budgets will ensure that project is developed or implemented below a certain cost. Sometimes, project managers have to allocate additional resources in order to meet the deadlines with a penalty of additional project costs. 1.4.3. SCOPE Scope looks at the outcome of the project undertaken. This consists of a list of deliverables, which need to be addressed by the project team. A successful project manager will know to manage both the scope of the project and any change in scope which impacts time and cost. 1.4.4. QUALITY Quality is not a part of the project management triangle, but it is the ultimate objective of every delivery. Hence, the project management triangle represents implies quality. Many project managers are under the notion that 'high quality comes with high cost', which to some extent is true. By using low quality resources to accomplish project deadlines does not ensure success of the overall project. Like with the scope, quality will also be an important deliverable for the project. 1.5. TIME MANAGEMENT Time management is the act of taking conscious control over the amount of time spent on specific activities. One exercises time management to increase productivity, effectiveness and efficiency, also practicing skills and using tools and techniques to aid in accomplishing tasks, projects or working toward goals and deadlines. Time management is about effective scheduling of your time, goal setting, prioritizing and choosing what to do and what not to do, delegating tasks,
  • 18. Time and Resource Management in Construction Project Department of Civil Engineering, SET, Jain University 7 analyzing and reviewing spent time, organizing workspace, keeping concentration and focus at work, motivating to work towards a goal. Managing time can gain extra productive hours which can lead to increased efficiency and productivity. Time management is the strategy of organizing and implementing conscious regulation on the time-frame allocated to a particular activity, with the purpose of enhancing the effectiveness, proficiency and productivity. Time management may be assisted by an assortment of tools, devices, and techniques utilized to manage valuable time whenever undertaking particular projects, tasks and objectives complying with a deadline. Implementation of time management entails a broad range of activities, which includes preparation, allocation and delegation, evaluation, supervision, scheduling and prioritizing. 1.5.1. THE IMPORTANCE OF TIME MANAGEMENT FOR A CONSTRUCTION PROJECT  Effective time management is used to assign workers attainable goals, resources and time-frames to lower the overall cost of the project with the efficient use of their billable hours and energy.  Time management is important in construction because it organizes the allotted time set for the completion of the task for the purpose of meeting or even beating the deadline.  Time management is important to a contractor's profitability because they are given a legally binding contract in which failure to abide by its terms and deadlines can result to a partial lost in monetary payment or even cancellation of the contract.  Proper use of time management techniques can result in the completion of project, on time, and create a positive testimonial for the contractor. The effective use of time management is a vital element needed by construction companies to successfully meet the budget and allocated timeframe for the
  • 19. Time and Resource Management in Construction Project Department of Civil Engineering, SET, Jain University 8 completion of any development work. It is not just a tool used in construction management but is a key to achieving corporate profitability and success. 1.6. RESOURCE MANAGEMENT Resource management is the efficient and effective deployment of an organization's resources when they are needed. Such resources may include financial resources, inventory, human skills, production resources, or information technology. A dimension of resource development is included in resource management by which investment in resources can be retained by a smaller additional investment to develop a new capability that is demanded, at a lower investment than disposing of the current resource and replacing it with another that has the demanded capability. In conservation, resource management is a set of practices pertaining to maintaining natural systems integrity. Examples of this form of management are resource management, soil conservation, forestry, wildlife management and water resource management. The broad term for this type of resource management is natural resource management. Good project management in construction must vigorously pursue the efficient utilization of labor, material and equipment. Improvement of labour productivity should be a major and continual concern of those who are responsible for cost control of constructed facilities. Material handling, which includes procurement, inventory, shop fabrication and field servicing, requires special attention for cost reduction. The use of new equipment and innovative methods has made possible wholesale changes in construction technologies in recent decades. Organizations which do not recognize the impact of various innovations and have not adapted to
  • 20. Time and Resource Management in Construction Project Department of Civil Engineering, SET, Jain University 9 changing environments have justifiably been forced out of the mainstream of construction activities. 1.6.1. LABOUR PRODUCTIVITY Productivity in construction is often broadly defined as output per labour hour. Since labour constitutes a large part of the construction cost and the quantity of labour hours in performing a task in construction is more susceptible to the influence of management than are materials or capital, this productivity measure is often referred to as labour productivity. However, it is important to note that labour productivity is a measure of the overall effectiveness of an operating system in utilizing labour, equipment and capital to convert labour efforts into useful output, and is not a measure of the capabilities of labour alone. 1.6.2. MATERIAL MANAGEMENT Materials management is an important element in project planning and control. Materials represent a major expense in construction, so minimizing procurement or purchase costs presents important opportunities for reducing costs. Poor materials management can also result in large and avoidable costs during construction. First, if materials are purchased early, capital may be tied up and interest charges incurred on the excess inventory of materials. Even worse, materials may deteriorate during storage or be stolen unless special care is taken. For example, electrical equipment often must be stored in waterproof locations. Second, delays and extra expenses may be incurred if materials required for particular activities are not available. Accordingly, insuring a timely flow of material is an important concern of project managers. Materials management is not just a concern during the monitoring stage in which construction is taking place. Decisions about material procurement may also be required during the initial planning and scheduling stages. For example, activities can be inserted in the project schedule to represent purchasing of major items such as elevators for buildings. The availability of materials may greatly influence the schedule in projects with a fast track or very tight time schedule: sufficient time for obtaining the necessary materials must be allowed. In some case, more expensive suppliers or shippers may be employed to save time.
  • 21. Time and Resource Management in Construction Project Department of Civil Engineering, SET, Jain University 10 Materials management is also a problem at the organization level if central purchasing and inventory control is used for standard items. In this case, the various projects undertaken by the organization would present requests to the central purchasing group. In turn, this group would maintain inventories of standard items to reduce the delay in providing material or to obtain lower costs due to bulk purchasing. This organizational materials management problem is analogous to inventory control in any organization facing continuing demand for particular items. Materials ordering problems lend themselves particularly well to computer based systems to insure the consistency and completeness of the purchasing process. In the manufacturing realm, the use of automated materials requirements planning systems is common. In these systems, the master production schedule, inventory records and product component lists are merged to determine what items must be ordered, when they should be ordered, and how much of each item should be ordered in each time period. The heart of these calculations is simple arithmetic: the projected demand for each material item in each period is subtracted from the available inventory. When the inventory becomes too low, a new order is recommended. For items that are non-standard or not kept in inventory, the calculation is even simpler since no inventory must be considered. With a materials requirement system, much of the detailed record keeping is automated and project managers are alerted to purchasing requirements. 1.7. SCHEDULING In project management, a schedule is a listing of project's milestones, activities, and deliverables, usually with intended start and finish dates. Those items are often estimated in terms of resource allocation, budget and duration, linked by dependencies and scheduled events. A schedule is commonly used in project planning and project portfolio management parts of project management. Elements on a schedule may be closely related to the work breakdown structure (WBS) terminal elements, the Statement of work, or a Contract Data Requirements List.
  • 22. Time and Resource Management in Construction Project Department of Civil Engineering, SET, Jain University 11 Planning, Scheduling (or organizing) and Control are considered to be basic Managerial functions, and CPM/PERT has been rightfully accorded due importance in the literature on Operations Research and Quantitative Analysis. Far more than the technical benefits, it was found that PERT/CPM provided a focus around which managers could brain-storm and put their ideas together. It proved to be a great communication medium by which thinkers and planners at one level could communicate their ideas, their doubts and fears to another level. Most important, it became a useful tool for evaluating the performance of individuals and teams. There are many variations of CPM/PERT which have been useful in planning costs, scheduling manpower and machine time. WORK BREAKDOWN STRUCTURE A work breakdown structure (WBS), in project management and systems engineering, is a deliverable-oriented decomposition of a project into smaller components. A work breakdown structure element may be a product, data, service, or any combination thereof. A WBS also provides the necessary framework for detailed cost estimating and control along with providing guidance for schedule development and control 1.7.1. METHODS OF SCHEDULING CPM (Critical Path Method) and PERT (Program Evaluation Review Technique) are project management techniques, which have been created out of the need of Western industrial and military establishments to plan, schedule and control complex projects. While CPM is easy to understand and use, it does not consider the time variations that can have a great impact on the completion time of a complex project. The Program Evaluation and Review Technique (PERT) is a network model that allows for randomness in activity completion times. PERT was developed in the late 1950's for the U.S. Navy's Polaris project having thousands of contractors. It has the potential to reduce both the time and cost required to complete a project.
  • 23. Time and Resource Management in Construction Project Department of Civil Engineering, SET, Jain University 12 Essentially, there are six steps which are common to both the techniques. The procedure is listed below: I. Define the Project and all of its significant activities or tasks. The Project (made up of several tasks) should have only a single start activity and a single finish activity. II. Develop the relationships among the activities. Decide which activities must precede and which must follow others. III. Draw the "Network" connecting all the activities. Each Activity should have unique event numbers. Dummy arrows are used where required to avoid giving the same numbering to two activities. IV. Assign time and/or cost estimates to each activity V. Compute the longest time path through the network. This is called the critical path. VI. Use the Network to help plan, schedule, and monitor and control the project. PERT planning involves the following steps: 1. Identify the specific activities and milestones. 2. Determine the proper sequence of the activities. 3. Construct a network diagram. 4. Estimate the time required for each activity. 5. Determine the critical path. 6. Update the PERT chart. Benefits of PERT • Expected project completion time. • Probability of completion before a specified date.
  • 24. Time and Resource Management in Construction Project Department of Civil Engineering, SET, Jain University 13 • The critical path activities that directly impact the completion time. • The activities that have slack time and that can lend resources to critical path activities. • Activities start and end dates.
  • 25. Time and Resource Management in Construction Project Department of Civil Engineering, SET, Jain University 14 Chapter 2 2. SITE DETAILS Project: Vaishnavi Commune 2.1. COMPANIES INVOLVED IN PROJECT Client: M/S. VAISHNAVI GROUP Contractor: Adharsh Group Architects: Eccumene Habitat Solutions PVT. LTD. PMC: SYConE CPMC PVT. LTD Structural Consultant: SHRADHA DESIGNTECH PVT.LTD Electrical Consultants: POORNA ENGINEERING CONSULTANTS PHE Consultants: PRISM CONSULTANTS Landscape Consultants: TERRA FIRMA Landscape Architecture Project Configuration:  6 Acres of land  46 Villas with Villament and Club House  3 & 4 BHK villas  3 BHK villa measures 3508 – 3787 Sq. ft.  4 BHK villa measures 4030 – 4309 Sq. ft.
  • 26. Time and Resource Management in Construction Project Department of Civil Engineering, SET, Jain University 15 Details of villa: Table 2.1 Details of villa at the project site 2.2. ENTERPRISE PROJECT STRUCTURE A Project is managed by a company which may be or may not be under its mother company. The company who is managing the project is defined as enterprise in project management. If a particular company having its branches and one of the branch is managing the project. Then we have to enter the list of all the company this list is called Enterprise Project Structure (EPS). 2.3. ORGANIZATION BREAKDOWN STRUCTURE It is the list of people in a company who will be responsible for managing either the work breakdown structure or activity in a project this is called as organization breakdown structure. 2.4. WORK BREAKDOWN STRUCTURE The functional elements of a project and their inter relationship are determined by a technique is known as Work Breakdown Structure (WBS). BHK Facing Type No. 3 East A 7 3 East B 6 3 West A 7 3 West B 6 4 East A 6 4 East B 5 4 West A 4 4 West B 4 3 North A 1 Total 46
  • 27. Time and Resource Management in Construction Project Department of Civil Engineering, SET, Jain University 16 Figure 2.1 Flow chart represents the OBS of the Project Figure 2.2 Typical WBS (Work Breakdown Structure) of a Building
  • 28. Time and Resource Management in Construction Project Department of Civil Engineering, SET, Jain University 17 ACTIVITY Performance of a specific task, operation, job or function which consumes time and resource and has a definite beginning and end is called an Activity. EVENT An instantaneous point in time marking the beginning or end of one or more activities is called an Event. NETWORK A Network is the diagrammatic representation of a work plan showing the activities step by step leading to the established goal. It depicts the inter- dependence between the various activities. Figure 2.3 Representing Activity and Event Networks
  • 29. Time and Resource Management in Construction Project Department of Civil Engineering, SET, Jain University 18 WORK BREAKDOWN STRUCTURE OF A VILLA 1. Sub-Structure 1.1. Marking 1.2. Earthwork 1.3. ATT 1.4. PCC 1.5. Foundation 1.5.1. Reinforcement 1.5.2. Shuttering 1.5.3. Concreting 1.6. Column 1.6.1. Column Marking 1.6.2. Reinforcement (up to soffit of plinth beam) 1.6.3. Shuttering 1.6.4. Concreting 1.7. Backfilling (up to soffit of plinth beam) 1.8. Size Stone Masonry 1.8.1. Excavation 1.8.2. PCC 1.8.3. SSM Work 1.9. DPC 1.10. Backfilling 1.11. Plinth Beam 1.11.1. Reinforcement 1.11.2. Shuttering 1.11.3. Concreting 2. Super Structure 2.1. Floor 00 2.1.1. Structural work 2.1.1.1. Backfilling 2.1.1.2. ATT for floor area 2.1.1.3. Soling 2.1.1.4. Floor PCC 2.1.1.5. Column
  • 30. Time and Resource Management in Construction Project Department of Civil Engineering, SET, Jain University 19 2.1.1.5.1. Column Layout 2.1.1.5.2. Reinforcement 2.1.1.5.3. Shuttering 2.1.1.5.4. Concreting 2.1.1.6. Staircase Flights 2.1.1.6.1. Flight 1 2.1.1.6.2. Flight 2 2.1.1.7. First floor Slab 2.1.1.7.1. Beam Shuttering 2.1.1.7.2. Slab Shuttering 2.1.1.7.3. Beam Reinforcement 2.1.1.7.4. Slab Reinforcement 2.1.1.7.5. Electrical Conduting 2.1.1.7.6. Slab Concreting 2.1.2. Civil Finishes 2.1.2.1. Wet Finishes 2.1.2.1.1. Block Masonry 2.1.2.1.2. Ceiling Plastering 2.1.2.1.3. Wall Plastering 2.1.2.1.4. Granite Counters – Kitchen 2.1.2.1.5. Dadoing – Kitchen 2.1.2.1.6. Flooring 2.1.2.1.6.1. Vitrified 2.1.2.1.6.2. Marble (Laying) 2.1.2.1.7. Putty and Primer 2.1.2.1.8. First coat painting 2.1.2.1.9. Flooring – Marble - Polishing and Finishing 2.1.2.1.10. Painting Final/Polishing 2.1.2.2. Dry Finishes 2.1.2.2.1. Windows fixing 2.1.2.2.2. Staircase railing 2.1.2.2.3. Door frames and shuttering fixing 2.1.2.2.4. Fixing of Iron mongery works 2.1.3. MEP
  • 31. Time and Resource Management in Construction Project Department of Civil Engineering, SET, Jain University 20 2.1.3.1. Electrical 2.1.3.1.1. Chasing and Wall conduting 2.1.3.1.2. Wiring and switch plate fixing 2.1.3.1.3. Testing and commissioning 2.1.3.2. PHE Toilet and Kitchen 2.1.3.2.1. Pipe Laying – Waste and soil 2.1.3.2.2. Pipe Laying – Water 2.1.3.2.3. Pipe testing 2.1.3.2.4. Sanitary fixtures 2.1.3.3. Toilet 2.1.3.3.1. Chasing 2.1.3.3.2. Dadoing – Toilet 2.1.3.3.3. Granite Counters 2.2. Floor 01 2.2.1. Structural Work 2.2.1.1. Column 2.2.1.1.1. Column Layout 2.2.1.1.2. Reinforcement 2.2.1.1.3. Shuttering 2.2.1.1.4. Concreting 2.2.1.2. First flight of stairs 2.2.1.3. Beam and Slab work 2.2.1.3.1. Beam Shuttering 2.2.1.3.2. Slab Shuttering 2.2.1.3.3. Beam Reinforcement 2.2.1.3.4. Slab Reinforcement 2.2.1.3.5. Electrical Conduting 2.2.1.3.6. Slab Concreting 2.2.2. Civil Finishes 2.2.2.1. Wet Finishes 2.2.2.1.1. Block Masonry 2.2.2.1.2. Ceiling Plastering 2.2.2.1.3. Wall Plastering 2.2.2.1.4. Flooring
  • 32. Time and Resource Management in Construction Project Department of Civil Engineering, SET, Jain University 21 2.2.2.1.4.1. Vitrified 2.2.2.1.4.2. Marble (Laying) 2.2.2.1.5. Putty and Primer 2.2.2.1.6. First coat painting 2.2.2.1.7. Flooring – Marble - Polishing and Finishing 2.2.2.1.8. Painting Final/Polishing 2.2.2.2. Dry Finishes 2.2.2.2.1. Windows fixing 2.2.2.2.2. Staircase railing 2.2.2.2.3. Door frames and shuttering fixing 2.2.2.2.4. Fixing of Iron mongery works 2.2.3. MEP 2.2.3.1. Electrical 2.2.3.1.1. Chasing and Wall conduting 2.2.3.1.2. Wiring and switch plate fixing 2.2.3.1.3. Testing and commissioning 2.2.3.2. PHE Toilet 2.2.3.2.1. Pipe Laying – Waste and soil 2.2.3.2.2. Pipe Laying – Water 2.2.3.2.3. Pipe testing 2.2.3.2.4. Sanitary fixtures 2.2.3.3. Toilet 2.2.3.3.1. Rough plastering 2.2.3.3.2. Chasing 2.2.3.3.3. Waterproofing 2.2.3.3.4. Bore Packing 2.2.3.3.5. Sunken Filling 2.2.3.3.6. Dadoing – Toilet 2.2.3.3.7. Toilet Flooring 2.2.3.3.8. Granite Counters 2.3. Study Room Slab 2.3.1. Structural Work 2.3.1.1. Column 2.3.1.1.1. Column Layout
  • 33. Time and Resource Management in Construction Project Department of Civil Engineering, SET, Jain University 22 2.3.1.1.2. Reinforcement 2.3.1.1.3. Shuttering 2.3.1.1.4. Concreting 2.3.1.2. First flight of stairs 2.3.1.3. Beam and Slab work 2.3.1.3.1. Beam Shuttering 2.3.1.3.2. Slab Shuttering 2.3.1.3.3. Beam Reinforcement 2.3.1.3.4. Slab Reinforcement – Stairs (2nd Flight) 2.3.1.3.5. Electrical Conduting 2.3.1.3.6. Slab Concreting 2.3.1.4. Roof Slab 2.3.2. Civil Finishes 2.3.2.1. Wet Finishes 2.3.2.1.1. Block Masonry 2.3.2.1.2. Ceiling Plastering 2.3.2.1.3. Wall Plastering 2.3.2.1.4. Flooring 2.3.2.1.4.1. Vitrified 2.3.2.1.4.2. Marble (Laying) 2.3.2.1.5. Putty and Primer 2.3.2.1.6. Flooring – Marble - Polishing and Finishing 2.3.2.1.7. Painting Final/Polishing 2.3.2.2. Dry Finishes 2.3.2.2.1. Windows fixing 2.3.2.2.2. Staircase railing 2.3.2.2.3. Door frames and shuttering fixing 2.3.2.2.4. Fixing of Iron mongery works 2.3.3. MEP 2.3.3.1. Electrical 2.3.3.1.1. Chasing and Wall conduting 2.3.3.1.2. Wiring and switch plate fixing 2.3.3.1.3. Testing and commissioning 2.4. Terrace
  • 34. Time and Resource Management in Construction Project Department of Civil Engineering, SET, Jain University 23 2.4.1. Parapet wall and plastering 2.4.2. Weather Proofing 2.4.3. Landscaping 3. External Finishes 3.1. Civil 3.1.1. External Plastering 3.1.2. Pergola 3.1.3. External Painting 3.1.4. Car park Flooring 3.2. MEP 3.2.1. External Sewage Lines Laying 3.2.2. Chamber Construction 3.2.3. Water Supply Line 3.3. Landscaping 3.3.1. Hard scape 3.3.2. Soft scape 4. Snagging and Desnagging 4.1. Punch list and desnagging
  • 35. Time and Resource Management in Construction Project Department of Civil Engineering, SET, Jain University 24 Chapter 3 3. DRAWINGS DETAILS 3.1. GROUND FLOOR Note: All dimensions are in mm
  • 36. Time and Resource Management in Construction Project Department of Civil Engineering, SET, Jain University 25 3.2. First FLOOR
  • 37. Time and Resource Management in Construction Project Department of Civil Engineering, SET, Jain University 26 3.3. SECOND FLOOR
  • 38. Time and Resource Management in Construction Project Department of Civil Engineering, SET, Jain University 27 3.4. TERRACE FLOOR
  • 39. Time and Resource Management in Construction Project Department of Civil Engineering, SET, Jain University 28 Chapter 4 4. ESTIMATION AND QUANTITIES Item No. Particulars and Description No.s Volume (m3 ) Percent Density of Steel Quantity of Steel (Kgs) Comments 1. Steel in RCC Works 1.1RCC Footing @ 0.5% Total Footing of a villa 1 23.854375 0.005 7850 936.2842188 Density of Steel 78.5 q/cu m 1.2 RCC Coulmn @ 1.5% a) Total Quantity Steel in Columns of Ground Floor 1 3.969 0.015 7850 467.34975 Density of Steel 78.5 q/cu m b) Total Quantity Steel in Columns of First Floor 1 3.73275 0.015 7850 439.5313125 Density of Steel 78.5 q/cu m c) Total Quantity Steel in Columns of Second Floor 1 1.134 0.015 7850 133.5285 Density of Steel 78.5 q/cu m 1.3 RCC Roof Slab @ 0.8% a) Total Quantity Steel in Ground Floor Slab 1 22.275 0.008 7850 1398.87 Density of Steel 78.5 q/cu m b) Total Quantity Steel in First Floor Slab 1 18.39 0.008 7850 1154.892 Density of Steel 78.5 q/cu m c) Total Quantity Steel in Second Floor Slab 1 3.6 0.008 7850 226.08 Density of Steel 78.5 q/cu m d) Total Quantity Steel in Study Room Slab 1 1.9305 0.008 7850 121.2354 Density of Steel 78.5 q/cu m e) Total Quantity Steel in Terrace Floor Slab 1 5.94 0.008 7850 373.032 Density of Steel 78.5 q/cu m 1.4 RCC Beam @ 1.0% a) Total Quantity Steel in Ground Floor Beam 1 8.1855 0.01 7850 642.56175
  • 40. Time and Resource Management in Construction Project Department of Civil Engineering, SET, Jain University 29 b) Total Quantity Steel in First Floor Beam 1 8.1855 0.01 7850 642.56175 c) Total Quantity Steel in Second Floor Beam 1 1.692 0.01 7850 132.822 d) Total Quantity Steel in Terrace Floor Beam 1 2.0376 0.01 7850 159.9516 1.5 RCC Plinth Beam @ 1.0% a) PB1 + PB2 1 3.9 0.01 7850 306.15 Density of Steel 78.5 q/cu m b) PB3 1 1.9 0.01 7851 149.169 Density of Steel 78.5 q/cu m Item No. Particulars and Description No.s Volume (m3 ) Comments 2. Earthwork in Foundation Quantity of Excavation for all footings 1 82.350625 Footing Type No.s Length (m) Bredth (m) Depth (m) Quantity of Excavation (m3 ) 4EACF1 1 3.4 1.9 0.5 9.69 4EAF1 2 1.75 1.5 0.35 8.6625 4EAF2 5 1.9 1.7 0.4 25.84 4EAF3 3 2.2 1.95 0.45 19.9485 4EAF4 1 2.45 2.2 0.5 8.085 4EAF5 1 2.85 2.45 0.55 10.124625 Total Quantity of Excavation (m3 ) 82.350625 Item Particulars and Description No.s Length (m) Bredth (m) Height or Depth (m) Quantity (m3 ) Comments 3. Block Work a) Ground Floor Blockwork i) 200 mm Blocks 1 76.847 0.215 2.95 48.74020975 ii) 100 mm Blocks 1 3.35 0.1 2.95 0.98825 b) First Floor Blockwork i) 200 mm Blocks 1 82.072 0.215 2.95 52.054166 ii) 100 mm Blocks 1 14.55 0.1 2.95 4.29225
  • 41. Time and Resource Management in Construction Project Department of Civil Engineering, SET, Jain University 30 c) Second Floor Blockwork i) 200 mm Blocks (Parapet) 1 61.472 0.215 0.6 7.929888 ii) 200 mm Blocks (Study Room) 1 26.65 0.215 2.95 16.9027625 Total Quantity of 200 mm Blocks 125.6270263 m3 Total Quantity of 100 mm Blocks 5.2805 m3 3.1 Deductions a) Ground Floor CW-01 1 2.7 0.2 1.65 0.891 DT-01 1 1.05 0.2 2.4 0.504 DT-02 1 0.9 0.1 2.4 0.216 DT-02 1 0.9 0.2 2.4 0.432 DT-03 2 0.85 0.2 2.4 0.816 DWT-01 1 1.5 0.2 2.4 0.72 SD-01 1 2.4 0.2 2.4 1.152 V-03 2 0.6 0.2 1.2 0.288 W-01 2 1.2 0.2 1.4 0.672 W-02 1 1.2 0.2 1.65 0.396 W-03 1 1 0.2 1.65 0.33 W-04 1 1.35 0.2 1.65 0.4455 W-05 1 0.6 0.2 1.65 0.198 b) First Floor CW-01 2 2.7 0.2 1.65 1.782 DT-02 2 0.9 0.1 2.4 0.432 DT-02 2 0.9 0.2 2.4 0.864 DT-03 2 0.85 0.1 2.4 0.408 SD-01 1 2.4 0.2 2.4 1.152 V-02 1 1 0.2 1.2 0.24 V-04 1 0.85 0.2 1.2 0.204 W-02 1 1.2 0.2 1.65 0.396 W-03 1 1 0.2 1.65 0.33 W-05 1 0.6 0.2 1.65 0.198 c) Second Floor CW-01 1 2.7 0.2 1.65 0.891 DT-04 1 0.9 0.2 2.3 0.414
  • 42. Time and Resource Management in Construction Project Department of Civil Engineering, SET, Jain University 31 W-05 1 0.6 0.2 1.65 0.198 Deductions 200 mm Wall 13.5135 m3 Deductions 100 mm Wall 1.056 m3 Quantity of Blockwork After Deduction (200 mm) + 10% wastage 123.3248789 m3 Quantity of Blockwork After Deduction (100 mm) + 10% wastage 4.64695 m3 Total Number of 200 mm Block 7707.80493 Units Total Number of 100 mm Block 580.86875 Units Item Particulars and Description No.s Length (m) Bredth (m) Height or Depth (m) Quantity (m2 ) Comments 4. Wall Plastering 4.1 Ground Floor i) Interior Walls 1 98.8 2.95 291.46 468.805 ii) Exterior Walls 1 56.3 3.15 177.345 4.2 First Floor i) Interior Walls 1 92.8 2.95 273.76 430.7875 ii) Exterior Walls 1 49.85 3.15 157.0275 4.3 Second Floor i) Interior Walls 1 18.2 2.95 53.69 116.69 ii) Exterior Walls 1 20 3.15 63 Total Wall Plastering 1016.2825 m2 Item Particulars and Description No.s Length (m) Bredth (m) Height or Depth (m) Quantity (m2 ) Comments 4.4 Deductions a) Ground Floor CW-01 1 2.7 1.65 4.455 DT-01 1 1.05 2.4 2.52 DT-02 2 0.9 2.4 4.32 DT-03 2 0.85 2.4 4.08
  • 43. Time and Resource Management in Construction Project Department of Civil Engineering, SET, Jain University 32 DWT-01 1 1.5 2.4 3.6 SD-01 1 2.4 2.4 5.76 V-03 2 0.6 1.2 1.44 W-01 2 1.2 1.4 3.36 W-02 1 1.2 1.65 1.98 W-03 1 1 1.65 1.65 W-04 1 1.35 1.65 2.2275 W-05 1 0.6 1.65 0.99 b) First Floor CW-01 2 2.7 1.65 8.91 DT-02 2 0.9 2.4 4.32 DT-02 2 0.9 2.4 4.32 DT-03 2 0.85 2.4 4.08 SD-01 1 2.4 2.4 5.76 V-02 1 1 1.2 1.2 V-04 1 0.85 1.2 1.02 W-02 1 1.2 1.65 1.98 W-03 1 1 1.65 1.65 W-05 1 0.6 1.65 0.99 c) Second Floor CW-01 1 2.7 1.65 4.455 DT-04 1 0.9 2.3 2.07 W-05 1 0.6 1.65 0.99 Total Wall Plastering 78.1275 m2 Wall Plastering After Deduction + 10% extra 1031.9705 m2 Item Particulars and Description No.s Length (m) Bredth (m) Height or Depth (m) Quantity (m3 ) Comments 5. RMC 5.1 RMC for footing 4EACF1 1 3.4 1.9 0.5 3.23 4EAF1 2 1.75 1.5 0.35 1.8375 4EAF2 5 1.9 1.7 0.4 6.46 4EAF3 3 2.2 1.95 0.45 5.7915 4EAF4 1 2.45 2.2 0.5 2.695 4EAF5 1 2.85 2.45 0.55 3.840375 Total RMC required for footing 23.854375 m3
  • 44. Time and Resource Management in Construction Project Department of Civil Engineering, SET, Jain University 33 5.2 RMC for Column Columns of Ground Floor 4EAC16 2 0.2 0.45 3.15 0.567 4EAC17 1 0.2 0.45 3.15 0.2835 4EAC12 1 0.2 0.45 3.15 0.2835 4EAC13 1 0.2 0.45 3.15 0.2835 4EAC11 1 0.2 0.45 3.15 0.2835 4EAC8 1 0.2 0.6 3.15 0.378 4EAC9 1 0.2 0.45 3.15 0.2835 4EAC10 1 0.2 0.375 3.15 0.23625 4EAC6 1 0.2 0.375 3.15 0.23625 4EAC7 1 0.2 0.45 3.15 0.2835 4EAC3 1 0.2 0.45 3.15 0.2835 4EAC4 1 0.2 0.45 3.15 0.2835 4EAC5 1 0.2 0.45 3.15 0.2835 Sum 3.969 m3 Columns of First Floor 4EAC16 2 0.2 0.45 3.15 0.567 4EAC17 1 0.2 0.45 3.15 0.2835 4EAC12 1 0.2 0.45 3.15 0.2835 4EAC13 1 0.2 0.45 3.15 0.2835 4EAC11 1 0.2 0.45 3.15 0.2835 4EAC8 1 0.2 0.6 3.15 0.378 4EAC9 1 0.2 0.45 3.15 0.2835 4EAC10 1 0.2 0.375 3.15 0.23625 4EAC7 1 0.2 0.45 3.15 0.2835 4EAC3 1 0.2 0.45 3.15 0.2835 4EAC4 1 0.2 0.45 3.15 0.2835 4EAC5 1 0.2 0.45 3.15 0.2835 Sum 3.73275 m3 Columns of Second Floor 4EAC11 2 0.2 0.45 3.15 0.567 4EAC8 1 0.2 0.6 3.15 0.378 4EAC18 1 0.2 0.3 3.15 0.189 Sum 1.134 m3 Total RMC required for Columns 8.83575 m3
  • 45. Time and Resource Management in Construction Project Department of Civil Engineering, SET, Jain University 34 Item Particulars and Description No.s Quantity (m3 ) Comments 5.3 RMC for Slab a) Total Quantity of RMC in Ground Floor Slab 1 22.275 b) Total Quantity of RMC in First Floor Slab 1 18.39 c) Total Quantity of RMC in Second Floor Slab 1 3.6 d) Total Quantity of RMC in Study Room Slab 1 1.9305 e) Total Quantity of RMC in Terrace Floor Slab 1 5.94 Total RMC required for Slabs 52.1355 m3 Item Particulars and Description No.s Quantity (m3 ) Comments 5.3 RMC for Plinth Beam a) PB1 + PB2 1 3.9 b) PB3 1 1.9 Total RMC required for Plinth Beam 5.8 m3 Item Particulars and Description No.s Length (m) Bredth (m) Height or Depth (m) Quantity (m3 ) Comments 5.3 RMC for Beam a) First Floor Beams 90.95 0.2 0.45 8.1855 b) Second Floor Beam 18.8 0.2 0.45 1.692 Total RMC required for Beams 9.8775 m3 Quantity of RMC required for a villa + 10% extra= 150.7546875 m3 Item Particulars and No.s Area (m2 ) Depth (m) Quantity (m3 ) Comments
  • 46. Time and Resource Management in Construction Project Department of Civil Engineering, SET, Jain University 35 Description 6. PCC 6.1 Ground Floor Flooring a) Guest Bedroom 1 18.153 0.1 1.8153 b) Living cum Dining 1 39.767 0.1 3.9767 c) Staircase 1 11.529 0.1 1.1529 d) Kitchen 1 11.29 0.1 1.129 e) Utility Room 1 6.125 0.1 0.6125 f) Servent Room + Path 1 8.52 0.1 0.852 g) Lobby 1 6.12 0.1 0.612 h) Verandah 1 4.002 0.1 0.4002 Total PCC required for flooring 10.5506 m3 Footing Type No.s Length (m) Bredth (m) Quantity of Excavation (m3 ) Comments 6.2 PCC below Footing 4EACF1 1 3.4 1.9 0.756 4EAF1 2 1.75 1.5 0.663 4EAF2 5 1.9 1.7 1.995 4EAF3 3 2.2 1.95 1.548 4EAF4 1 2.45 2.2 0.636 4EAF5 1 2.85 2.45 0.80825 Total PCC required for flooring 6.40625 m3 6.3 PCC @ DPC Total PCC required for Damp-Proof 1.051875 m3 6.4 PCC below Plinth (Inner Walls) Total PCC required below Plinth 1.394 m3 6.5 PCC below SSM Total PCC required below SSM 3.22575 m3 Quantity of PCC required for a villa = 22.628475 m3 Quantity of PCC required for a villa + 10% extra= 24.8913225 m3 7. Size Stone Masonry Quantity of SSM 8.415 m3
  • 47. Time and Resource Management in Construction Project Department of Civil Engineering, SET, Jain University 36 Item Particulars and Description No.s Length (m) Bredth (m) Height or Depth (m) Quantity of Shuttering (m2 ) Comments 8. Shuttering 8.1 Shuttering for footings 4EACF1 1 3.4 1.9 0.5 5.3 4EAF1 2 1.75 1.5 0.35 4.55 4EAF2 5 1.9 1.7 0.4 14.4 4EAF3 3 2.2 1.95 0.45 11.205 4EAF4 1 2.45 2.2 0.5 4.65 4EAF5 1 2.85 2.45 0.55 5.83 Quantity of Shuttering for Footings 45.935 m2 8.2 Shuttering for Column a) Columns of Ground Floor 4EAC16 2 0.2 0.45 3.15 8.19 4EAC17 1 0.2 0.45 3.15 4.095 4EAC12 1 0.2 0.45 3.15 4.095 4EAC13 1 0.2 0.45 3.15 4.095 4EAC11 1 0.2 0.45 3.15 4.095 4EAC8 1 0.2 0.6 3.15 5.04 4EAC9 1 0.2 0.45 3.15 4.095 4EAC10 1 0.2 0.375 3.15 3.6225 4EAC6 1 0.2 0.375 3.15 3.6225 4EAC7 1 0.2 0.45 3.15 4.095 4EAC3 1 0.2 0.45 3.15 4.095 4EAC4 1 0.2 0.45 3.15 4.095 4EAC5 1 0.2 0.45 3.15 4.095 Sum 57.33 m2 b) Columns of First Floor 4EAC16 2 0.2 0.45 3.15 8.19 4EAC17 1 0.2 0.45 3.15 4.095 4EAC12 1 0.2 0.45 3.15 4.095 4EAC13 1 0.2 0.45 3.15 4.095 4EAC11 1 0.2 0.45 3.15 4.095 4EAC8 1 0.2 0.6 3.15 5.04 4EAC9 1 0.2 0.45 3.15 4.095 4EAC10 1 0.2 0.375 3.15 3.6225 4EAC7 1 0.2 0.45 3.15 4.095 4EAC3 1 0.2 0.45 3.15 4.095 4EAC4 1 0.2 0.45 3.15 4.095
  • 48. Time and Resource Management in Construction Project Department of Civil Engineering, SET, Jain University 37 4EAC5 1 0.2 0.45 3.15 4.095 Sum 53.7075 m2 c) Columns of Second Floor 4EAC11 2 0.2 0.45 3.15 8.19 4EAC8 1 0.2 0.6 3.15 5.04 4EAC18 1 0.2 0.3 3.15 3.15 Sum 16.38 m2 Total Shuttering required for Columns 127.4175 m2 8.3 Shuttering for Slabs and Beams i) Shuttering for Slab a) Ground Floor Slab Shuttering 130.31 m2 b) First Floor Slab Shuttering 104.41 m2 c) Second Floor Slab Shuttering 24 m2 d) Study Room Slab Shuttering 12.87 m2 d) Terrace Floor Slab Shuttering 39.6 m2 Total Shuttering required for Slabs 311.19 m2 ii) Shuttering for Beams a) Ground Floor Beams 58.208 m2 b) First Floor Beams 58.23 m2 c) Second Floor Beams 12.032 m2 d) Plinth Beam 36.384 m2 Total Shuttering required for Beams 164.854 m2 Quantity of Shuttering required for Slabs & Beams 476.044 m2 Quantity of Shuttering required for a villa 649.3965 m2 Quantity of Shuttering required for a villa + 10% extra 714.33615 m2
  • 49. Time and Resource Management in Construction Project Department of Civil Engineering, SET, Jain University 38 Item Particulars and Description No.s Area (m2 ) Comments 9. Ceiling Plastering 9.1 Ground Floor Ceiling a) Guest Bedroom 1 18.153 b) Living cum Dining 1 39.767 c) Staircase 1 11.529 d) Kitchen 1 11.29 e) Utility Room 1 6.125 f) Servent Room + Path 1 8.52 g) Lobby 1 6.12 h) Verandah 1 4.002 i) Toilet-1 1 2.15 j) Toilet-2 1 3.6 k) Sitout 1 8.9 l) Parking 1 14.7 Total Ceiling in Ground Floor 134.856 m2 9.2 First Floor Ceiling a) Master Bed 31.3 b) Family Lounge 28.28 c) Court 1.78 d) Toilet-1 5.48 e) Toilet-2 5.035 f) Children's Bed 18.125 Total Ceiling in First Floor 90 m2 9.3 Second Floor Ceiling a) Study Room 20.339 Total Ceiling in First Floor 20.339 m2 Total Area of Ceiling Plastering 245.195 m2 Table 4.1 Estimation and Quantities
  • 50. Time and Resource Management in Construction Project Department of Civil Engineering, SET, Jain University 39 Chapter 5 5. REPORTS FROM MSP 5.1. S CURVE METHOD S-curves are an important project management tool. They allow the progress of a project to be tracked visually over time, and form a historical record of what has happened to date. Analyses of S-curves allow project managers to quickly identify project growth, slippage, and potential problems that could adversely impact the project if no remedial action is taken. 5.1.1. Generating S-curves 5.1.1.1. Project Benchmarks Percentage S-curves may be used to calculate important project benchmarks on an ongoing basis, including:  Project percentage growth (Target and Baseline S-curves)  Project percentage slippage (Target and Baseline S-curves)  Actual percentage complete against Target percentage complete to date  Actual percentage complete against Baseline percentage complete to date 5.1.1.2. Steps to generate S Curve To generate a Baseline S-curve, a Baseline Schedule is required. The Baseline Schedules should contain the following information for each task:  Baseline Start Date, Finish Date  Baseline Man Hours and/or Costs
  • 51. Time and Resource Management in Construction Project Department of Civil Engineering, SET, Jain University 40 To generate Actual and Target S-curves, a Production Schedule is required. The Production Schedules should contain the following information for each task:  Actual Start Date, Finish Date  Actual Man Hours and/or Costs  Actual Percentage Complete Figure 5.1 S-Curve graphs
  • 52. Time and Resource Management in Construction Project Department of Civil Engineering, SET, Jain University 41 5.2. GANTT CHART A Gantt chart, commonly used in project management, is one of the most popular and useful ways of showing activities (tasks or events) displayed against time. On the left of the chart is a list of the activities and along the top is a suitable time scale. Each activity is represented by a bar; the position and length of the bar reflects the start date, duration and end date of the activity. This allows you to see at a glance:  What the various activities are  When each activity begins and ends  How long each activity is scheduled to last  Where activities overlap with other activities, and by how much  The start and end date of the whole project To summarize, a Gantt chart shows you what has to be done (the activities) and when (the schedule). Figure 5.2 Simple Gantt Chart (Reports will be submitted by Hard Copy)
  • 53. Time and Resource Management in Construction Project Department of Civil Engineering, SET, Jain University 42
  • 54. Time and Resource Management in Construction Project Department of Civil Engineering, SET, Jain University 43 Chapter 6 6. CONCLUSION & DISCUSSIONS In this project, the effective utilization of time and resource of constructing a 3BHK villa has been studied. Time is a very important factor to complete the work within the given deadline or even earlier. The project is done with the use of MSP which is project management software. The procedure for the project included understanding the project and creation of WBS, creation of level 3 activities, master construction program, resource scheduling and cash flow projection, monitoring and tracking. Time, resource and cost are inter-related. If we reduce the time of completion, the price will increase and vice- versa. The price will increase as the more amount of labour and then resources will have to be made available in short time. If resources are available near the site of construction, then the cost of transportation and also tax charges will be minimum in turn reducing the cost of the project. The time estimation results showed that the 3bhk villa can be completed in 135 days given that the work will proceeded smoothly as planned.
  • 55. Time and Resource Management in Construction Project Department of Civil Engineering, SET, Jain University 44 Chapter 7 7. REFERENCES 1. Estimation and costing in Civil Engineering by B.N Dutta 26th edition 2. Construction Planning And Management by P.S. Gahlot and B.M. Dhir 3. http://en.wikipedia.org/wiki/Project_management 4. http://www.tutorialspoint.com/management_concepts/project_management _triangle.htm