ITS of SMART
(Storm Management And Road Tunnel)
August 2006
by
Ir Mohd Saleh Santhiman, Director of SMART Highway, LLM
Looi Hong Weei, HOD-M&E, MGJV
Content
• Overview
• 3 Modes of Operation
• Stormwater Components
– Flood Detection System
– Flood Gate / Road Gate
• Motorway Components
– Ventilation System
– Lighting System
– Heat Detection System
– Fire and Emergency System
– Radio Communication and Cellular System
– CCTV
• Event 1 : Tunnel Closure from Mode 2 to Mode 3
• Event 2 : Traffic Accident
• Event 3 : Fire Accident
Overview
• The dual-purpose SMART tunnel
is able to solve 2 main problems
in Kuala Lumpur
a) Resolves the flood problem
in the city and other flood
prone areas, and
b) Eases traffic congestion on
the main southern gateway
to the city at Sg. Besi airfield
Overview
• 3 km in the central portion of
9.7 km tunnel is for dual
purposes
• About 6 km motorway tunnel
• Unidirectional traffic flow -
reduce accident risk
• 2 traffic lanes and 1 emergency
lane – expedite emergency
response
• Vehicle restriction - light
vehicle only, < 2.0m height
Taman
Salak
Selatan
LEGEND
LOT 10
STORMWATER TUNNEL
INGRESS AND EGRESS
CONNECTION LINKS TO MOTORWAY
Taman
Pertama
Cheras
Batu 12
HOLDING
POND
Selangor
Polo &
Equestrian
KG. BEREMBANG
Desa
Pahlawan
Pond
Jaya
Taman
Maluri
Taman
Cheras
Indah
Pandan
Kg.
Baru
Royal
Selangor
Golf Club
TWIN BOX CULVERT
SUNGAI KERAYONG IMPROVEMENT WORKS
CROSS PASSAGE @ AVERAGE 250m APART
- VENTILATION SHAFT
- VENTILATION SHAFT
JUNCTION BOX
- ESCAPE SHAFT
- FLOOD GATE
VENTILATION SHAFT
- ESCAPE SHAFT
B
M
W
TIME
P
N
M
B
W
i
s
m
a
M
a
h
S
i
n
g
R
H
B
RESERVOIR
TAMAN DESA
STORAGE
3 Modes of Operation
DUAL-PURPOSE USAGE OF SMART
HOLDING
POND
STORAGE
MODE I : NO STORMS
POND
Sg. Klang
Sg.
Kerayong
HOLDING
POND
STORAGE
POND
Sg. Klang
Sg.
Kerayong
MODE II : MOST STORMS - 7 TO 10 TIMES
MODE III : MAJOR STORMS - ANNUAL EVENTS
HOLDING
POND
STORAGE
POND
Sg. Klang
Sg.
Kerayong
(OCT '01)
Stormwater Components
• Rainfall Gauging Stations
• Water Level Gauging Stations
• River Flow Monitoring
• Warning Stations
• Remote Terminal Unit
• Radio Telemetry
• Repeater Stations
• Radar System (future)
Flood Detection System :
Catchment Monitoring & Warning System
SUNGAI BATU
CATCHMENT
SUNGAI BUNUS
CATCHMENT
SUNGAI KLANG
CATCHMENT
SUNGAI AMPANG
CATCHMENT
SUNGAI
GOMBAK
CATCHMENT
KLANGGATESDAM
CATCHMENT
KLANGGATES
DAM
BATUDAM
SG.KERAYONG
SG.KLANG
S
G
.
K
L
A
N
G
S
G
.
B
U
N
U
S
S
G
.
A
M
P
A
N
G
S
G
.
G
O
M
B
A
K
S
G
.
B
A
T
U SUNGAI
KERAYONG
CATCHMENT
3.3.5
3.3.4
3.1.14 3.3.3
3.3.2
3.3.1
3.2.9 3.2.6
3.2.4
3.1.13
3.2.12
3.1.10
3.1.4
3.1.8
3.1.3 3.1.2
3.1.1
3.1.12
3.2.5
3.1.7
3.1.9
3.1.11
3.2.2
3.1.6
3.1.5
3.2.8
3.2.11
3.2.10
3.2.7
3.2.3
3.2.1
LEGEND
CATCHMENTBOUNDRY
RIVER
PROPOSEDBYPASS
RAINFALLGAUGINGSTATION
WATERLEVERLGAUGINGSTATION
WATERLEVELANDRAINFALLGAUGINGSTATION
DAMMONITORINGSYSTEM
CRUMPWEIR
ACCOSTICDOPPLERCURRENTPROFILER
WATERLEVELGAUGINGSTATION
&RAINFALLGAUGINGSTATION
WATERLEVELGAUGINGSTATION
&ACCOSTICDOPPLERCURRENTPROFILER
WATERLEVEL ANDRAINFALLGAUGINGSTATION
&CRUMPWEIR
WATERLEVEL ANDRAINFALLGAUGINGSTATION
&ACCOSTICDOPPLERCURRENTPROFILER
(A)
(B)
(C)
(D)
(E)
(F)
(B)+(A)
(B)+(F)
(C)+(E)
(C)+(F)
Flood Detection System :
Weather Stations layout
TO JLN SULTAN ISMAIL
WATER FLOW
TO KL-SEREMBAN HIGHWAY
NORTH JUNCTION
SOUTH JUNCTION
GATE SHAFT
GATE SHAFT
KEY PLAN
ROAD GATE
ROAD GATE
Flood Gates : North Junction Box / South Junction Box
TO
JLN SULTAN ISMAIL
WATER FLOW
TO KL-SEREMBAN HIGHWAY
NORTH JUNCTION
SOUTH JUNCTION
GATE SHAFT
GATE SHAFT
KEY PLAN
ROAD GATE
ROAD GATE
• Prevention of vehicles entry during
storm events
• Prevention of flood discharge
entering to the ingress/egress
connection
UPSTREAM MOTORWAY TUNNEL GATE SHAFT
MOTOR ROOM ACCESS
GROUND LEVEL
FLOODGATE
GATE MOTOR ROOM
HYDRAULIC RAM
HYDRAULIC RAM
TYPICAL MOTORWAY TUNNEL SHAFT DETAIL 1 - OPERATION OF TYPICAL ROAD GATE
PLAN SHOWING ROAD GATE ASSEMBLY
Traffic
Traffic
See Detail 1
Road Gates : North Junction Box / South Junction Box
Motorway Components
Typical Tunnel Section
600
600
200
2550
2800
PROPOSED REVISED
LANE WIDTH 8.85M - HEIGHT 2.55M
2200 3250 3250 150
8850
Traffic Lane
Traffic Lane
Emergency
Lane
Marginal
Strip
2550
Right Upper deck
600
=
=
1200
Right Lower deck
Left Upper deck
Left Lower deck
E.P
2300
1200
600
2300
E.P
Radio
Re-Broadcast
Linear Heat
Detector
CCTV
Radio
Re-Broadcast
CCTV
Linear Heat
Detector
Radio
Re-Broadcast
Radio
Re-Broadcast
-Heat Detection
-Tunnel Lighting
-Hydrant and etc.
-Leaky Feeder Cable
for Radio and Cellular
-CCTV
-Lane Traffic Signal
-Gas Analyzer
Tunnel Ventilation (Upper Deck)
Tunnel Ventilation (Lower Deck)
Th - Threshold Zone
Tr1 - Transition Zone 1
Tr2 - Transition Zone 2
Tr3 - Transition Zone 3
Tunnel Lighting
Traffic
Direction
Th
Zone
Tr1
Zone
Tr2
Zone
Tr3
Zone
Interior Zone
Exit
Zone
• To provide continuity in visual performance for motorists entering and
travelling through road tunnel.
• IP 68 enclosure and subjected to 2.5 Bar water pressure and bracket
design shall withstand 5.5 m/s flow.
• The system will respond to the rate of temperature rise, about
10 seconds.
• Programmable fire zones
• Triggering CCTV system and Fire Alarm System during the case
of tunnel fire.
Fire Detection System
INCIDENT!
CCTV
FIRE
Tunnel Heat Detection System
Tunnel Fire Protection :
Emergency Points And Equipment
• Hose Reel, Fire Extinguishers, Breakglass and Emergency
Telephone are located at each cross passages, ventilation
shafts and escape shafts.
• Hydrants & Fire Extinguisher are installed along the tunnel
NJB
NVS
SVS
SJB
Ground Level
Hydrant & Fire Extinguisher
Hose Reel, Fire Extinguisher, Break Glass & Emergency Telephone
• Re-broadcast FM radios, cellular (telco), fire department, police and
ambulance signal into the tunnel.
• Audio break-in facility to broadcast emergency messages from the
control center into the tunnel through FM frequencies.
• IP 68 antenna installed to enable the use of mobile phones.
• Public Address and emergency phone are provided in the cross
passages and escape shafts.
Tunnel Radio Communication and Cellular System
LEAKY FEEDER
• Tunnel Surveillance
– PTZ CCTV at selected locations
– Fixed CCTV along the tunnel
– Linked to Fire Detection System
– Linked to Control Center via Fiber Optic Cable
• Automatic Incident Detection
– Measurement of traffic flow speed, occupancy
count
– Detection of speed drop, stop vehicles, inverse
direction and smoke
CCTV
Tunnel Monitoring & Control System (TMCS)
Emer.
Tel.
CCTV
Lane
Sign
Vent.
Sys.
Fire
Alarm
Tunnel
Lights
Elect..
Dist.
Emergency
Services
Public Information
Internet (future)
Fully
Integrated
Traffic
Management and
Control
System
Electrical Distribution
System Monitoring
Tunnel Lighting Control
and Monitoring
Ventilation System
Control and Monitoring
Fire Protection System
Monitoring
Emergency Telephone
System Monitoring
Emergency Response
Plan
Automatic Incident
Detection
Alarm logging
Electrical Distribution
System Monitoring
Tunnel Lighting Control
and Monitoring
Ventilation System
Control and Monitoring
Fire Protection System
Monitoring
Emergency Telephone
System Monitoring
Emergency Response
Plan
Automatic Incident
Detection
Alarm logging
Operations
Interface
Traffic Management & Control System (TMCS)
Pump Gates FDS (JPS)
Toll Collection
Event 1
Tunnel Closure from Mode 2 to Mode 3
FDS
TMCS
Toll Booth Operator /
Patrolman
VMS
Traffic
Diversion
Radio Broadcasting
AID Estimate Quantity of Vehicle
CCTV Monitor Evacuation
SCADA
Off Road Drainage
Pump / Ventilation
Patrolman
Check XP Water Tight
Door
Regulate Diversion
Weir
Water flow
into Tunnel
Open
Flood
Gate
Close
Road
Gate
Event 2
Traffic Accident
CCTV /
AID
LHD
Patrolman Traffic Diversion
VMS Alert Motorist
Radio Broadcasting
AQME Ventilation
PA at XP Communication
Event 3
Fire Accident
Radio Broadcasting
Patrolman Traffic Diversion
Toll Booth Close
Alert Motorist
VMS
SCADA Ventilation / Lighting
CCTV
LHD
AQME
EVENT 3 : Fire Accident
Cross Passage and Emergency Escape
• Cross passages linking both tunnel road decks with stairs
spaced approximately 250m intervals.
• Shaft Buildings at approximately 1km apart with stairs and lifts
connecting the two road decks to the surface
NJB
NVS
SVS
SJB
Ground Level
~ 1 km
~ 250 m ELEVATION VIEW
South
Junction Box
South
Ventilation Shaft
North
Ventilation Shaft
North
Junction Box
EVENT 3 : Fire Accident
Ventilation System
EVENT 3 : Fire Accident
Cross Passage and Emergency Escape
South
Junction Box
South
Ventilation Shaft
North
Ventilation Shaft
North
Junction Box
THANK YOU
Terima Kasih
www.smarttunnel.com.my

More Related Content

Similar to ITS of smart-Intelligent Transportation Systems

PROPOSED KAJANG URBAN TRAFFIC MANAGEMENT SYSTEM PRESENTATION
PROPOSED KAJANG URBAN TRAFFIC MANAGEMENT SYSTEM PRESENTATIONPROPOSED KAJANG URBAN TRAFFIC MANAGEMENT SYSTEM PRESENTATION
PROPOSED KAJANG URBAN TRAFFIC MANAGEMENT SYSTEM PRESENTATIONWael Alawsey
 
Real Time Monitoring Systems for Tunnels & Deep Excavation Projects
Real Time Monitoring Systems for Tunnels & Deep Excavation ProjectsReal Time Monitoring Systems for Tunnels & Deep Excavation Projects
Real Time Monitoring Systems for Tunnels & Deep Excavation ProjectsRekaNext Capital
 
Railway interlocking
Railway interlockingRailway interlocking
Railway interlockingMOHIT DUREJA
 
Industrial monitoring and control systems using andriod application
Industrial monitoring and control systems using andriod applicationIndustrial monitoring and control systems using andriod application
Industrial monitoring and control systems using andriod applicationAvinash Vemula
 
IRJET- Water Level Control, Monitoring and Altering System by using GSM i...
IRJET-  	  Water Level Control, Monitoring and Altering System by using GSM i...IRJET-  	  Water Level Control, Monitoring and Altering System by using GSM i...
IRJET- Water Level Control, Monitoring and Altering System by using GSM i...IRJET Journal
 
Traffic signal 32&35:DCE:FET:IIUI
Traffic signal 32&35:DCE:FET:IIUITraffic signal 32&35:DCE:FET:IIUI
Traffic signal 32&35:DCE:FET:IIUIcivilengineerf14
 
Bs ii-presentation
Bs ii-presentationBs ii-presentation
Bs ii-presentationLee Chun Yee
 
Tidal Gate Control System used during KPE C423 construction
Tidal Gate Control System used during KPE C423 constructionTidal Gate Control System used during KPE C423 construction
Tidal Gate Control System used during KPE C423 constructionRekaNext Capital
 
SMART tunnel report
SMART tunnel reportSMART tunnel report
SMART tunnel reportYap Xin
 
Pipeline leak detection system
Pipeline leak detection systemPipeline leak detection system
Pipeline leak detection systemAbhijeet Malhotra
 
POLTankFarmLayersProtection (1).pdf
POLTankFarmLayersProtection (1).pdfPOLTankFarmLayersProtection (1).pdf
POLTankFarmLayersProtection (1).pdfBHAVLEOMKARNAVNATAHR
 
Huawei LDS IDS Solution.pdf
Huawei LDS  IDS Solution.pdfHuawei LDS  IDS Solution.pdf
Huawei LDS IDS Solution.pdfssuser37b7b9
 
Huawei LDS IDS Solution.pdf
Huawei LDS  IDS Solution.pdfHuawei LDS  IDS Solution.pdf
Huawei LDS IDS Solution.pdfssuser37b7b9
 
Automated Tunnel Monitoring System (ATMS)
Automated Tunnel Monitoring System (ATMS)Automated Tunnel Monitoring System (ATMS)
Automated Tunnel Monitoring System (ATMS)RekaNext Capital
 

Similar to ITS of smart-Intelligent Transportation Systems (20)

PROPOSED KAJANG URBAN TRAFFIC MANAGEMENT SYSTEM.
PROPOSED KAJANG URBAN TRAFFIC MANAGEMENT SYSTEM.PROPOSED KAJANG URBAN TRAFFIC MANAGEMENT SYSTEM.
PROPOSED KAJANG URBAN TRAFFIC MANAGEMENT SYSTEM.
 
ITS presentation final
ITS presentation final ITS presentation final
ITS presentation final
 
PROPOSED KAJANG URBAN TRAFFIC MANAGEMENT SYSTEM PRESENTATION
PROPOSED KAJANG URBAN TRAFFIC MANAGEMENT SYSTEM PRESENTATIONPROPOSED KAJANG URBAN TRAFFIC MANAGEMENT SYSTEM PRESENTATION
PROPOSED KAJANG URBAN TRAFFIC MANAGEMENT SYSTEM PRESENTATION
 
Real Time Monitoring Systems for Tunnels & Deep Excavation Projects
Real Time Monitoring Systems for Tunnels & Deep Excavation ProjectsReal Time Monitoring Systems for Tunnels & Deep Excavation Projects
Real Time Monitoring Systems for Tunnels & Deep Excavation Projects
 
Railway interlocking
Railway interlockingRailway interlocking
Railway interlocking
 
PLC 5.docx
PLC 5.docxPLC 5.docx
PLC 5.docx
 
Industrial monitoring and control systems using andriod application
Industrial monitoring and control systems using andriod applicationIndustrial monitoring and control systems using andriod application
Industrial monitoring and control systems using andriod application
 
IRJET- Water Level Control, Monitoring and Altering System by using GSM i...
IRJET-  	  Water Level Control, Monitoring and Altering System by using GSM i...IRJET-  	  Water Level Control, Monitoring and Altering System by using GSM i...
IRJET- Water Level Control, Monitoring and Altering System by using GSM i...
 
Presentation2
Presentation2Presentation2
Presentation2
 
Traffic signal 32&35:DCE:FET:IIUI
Traffic signal 32&35:DCE:FET:IIUITraffic signal 32&35:DCE:FET:IIUI
Traffic signal 32&35:DCE:FET:IIUI
 
Bs ii-presentation
Bs ii-presentationBs ii-presentation
Bs ii-presentation
 
Tidal Gate Control System used during KPE C423 construction
Tidal Gate Control System used during KPE C423 constructionTidal Gate Control System used during KPE C423 construction
Tidal Gate Control System used during KPE C423 construction
 
SMART tunnel report
SMART tunnel reportSMART tunnel report
SMART tunnel report
 
Pipeline leak detection system
Pipeline leak detection systemPipeline leak detection system
Pipeline leak detection system
 
POLTankFarmLayersProtection (1).pdf
POLTankFarmLayersProtection (1).pdfPOLTankFarmLayersProtection (1).pdf
POLTankFarmLayersProtection (1).pdf
 
Huawei LDS IDS Solution.pdf
Huawei LDS  IDS Solution.pdfHuawei LDS  IDS Solution.pdf
Huawei LDS IDS Solution.pdf
 
Huawei LDS IDS Solution.pdf
Huawei LDS  IDS Solution.pdfHuawei LDS  IDS Solution.pdf
Huawei LDS IDS Solution.pdf
 
H010244147
H010244147H010244147
H010244147
 
Automated Tunnel Monitoring System (ATMS)
Automated Tunnel Monitoring System (ATMS)Automated Tunnel Monitoring System (ATMS)
Automated Tunnel Monitoring System (ATMS)
 
Carrier_Protn_08_01_16 - Copy.pdf
Carrier_Protn_08_01_16 - Copy.pdfCarrier_Protn_08_01_16 - Copy.pdf
Carrier_Protn_08_01_16 - Copy.pdf
 

Recently uploaded

MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSMANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSSIVASHANKAR N
 
Introduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxIntroduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxupamatechverse
 
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Serviceranjana rawat
 
UNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its PerformanceUNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its Performancesivaprakash250
 
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete RecordCCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete RecordAsst.prof M.Gokilavani
 
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...Call Girls in Nagpur High Profile
 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSKurinjimalarL3
 
UNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and workingUNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and workingrknatarajan
 
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...ranjana rawat
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxpurnimasatapathy1234
 
result management system report for college project
result management system report for college projectresult management system report for college project
result management system report for college projectTonystark477637
 
Introduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxIntroduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxupamatechverse
 
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
Processing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxProcessing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxpranjaldaimarysona
 
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service NashikCall Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service NashikCall Girls in Nagpur High Profile
 

Recently uploaded (20)

MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSMANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
 
Introduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxIntroduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptx
 
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
 
UNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its PerformanceUNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its Performance
 
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete RecordCCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
 
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINEDJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
 
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
 
UNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and workingUNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and working
 
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
 
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptx
 
result management system report for college project
result management system report for college projectresult management system report for college project
result management system report for college project
 
Roadmap to Membership of RICS - Pathways and Routes
Roadmap to Membership of RICS - Pathways and RoutesRoadmap to Membership of RICS - Pathways and Routes
Roadmap to Membership of RICS - Pathways and Routes
 
Introduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxIntroduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptx
 
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
 
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
 
Processing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxProcessing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptx
 
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service NashikCall Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
 

ITS of smart-Intelligent Transportation Systems

  • 1. ITS of SMART (Storm Management And Road Tunnel) August 2006 by Ir Mohd Saleh Santhiman, Director of SMART Highway, LLM Looi Hong Weei, HOD-M&E, MGJV
  • 2. Content • Overview • 3 Modes of Operation • Stormwater Components – Flood Detection System – Flood Gate / Road Gate • Motorway Components – Ventilation System – Lighting System – Heat Detection System – Fire and Emergency System – Radio Communication and Cellular System – CCTV • Event 1 : Tunnel Closure from Mode 2 to Mode 3 • Event 2 : Traffic Accident • Event 3 : Fire Accident
  • 3. Overview • The dual-purpose SMART tunnel is able to solve 2 main problems in Kuala Lumpur a) Resolves the flood problem in the city and other flood prone areas, and b) Eases traffic congestion on the main southern gateway to the city at Sg. Besi airfield
  • 4. Overview • 3 km in the central portion of 9.7 km tunnel is for dual purposes • About 6 km motorway tunnel • Unidirectional traffic flow - reduce accident risk • 2 traffic lanes and 1 emergency lane – expedite emergency response • Vehicle restriction - light vehicle only, < 2.0m height
  • 5. Taman Salak Selatan LEGEND LOT 10 STORMWATER TUNNEL INGRESS AND EGRESS CONNECTION LINKS TO MOTORWAY Taman Pertama Cheras Batu 12 HOLDING POND Selangor Polo & Equestrian KG. BEREMBANG Desa Pahlawan Pond Jaya Taman Maluri Taman Cheras Indah Pandan Kg. Baru Royal Selangor Golf Club TWIN BOX CULVERT SUNGAI KERAYONG IMPROVEMENT WORKS CROSS PASSAGE @ AVERAGE 250m APART - VENTILATION SHAFT - VENTILATION SHAFT JUNCTION BOX - ESCAPE SHAFT - FLOOD GATE VENTILATION SHAFT - ESCAPE SHAFT B M W TIME P N M B W i s m a M a h S i n g R H B RESERVOIR TAMAN DESA STORAGE
  • 6. 3 Modes of Operation
  • 7. DUAL-PURPOSE USAGE OF SMART HOLDING POND STORAGE MODE I : NO STORMS POND Sg. Klang Sg. Kerayong HOLDING POND STORAGE POND Sg. Klang Sg. Kerayong MODE II : MOST STORMS - 7 TO 10 TIMES MODE III : MAJOR STORMS - ANNUAL EVENTS HOLDING POND STORAGE POND Sg. Klang Sg. Kerayong (OCT '01)
  • 9. • Rainfall Gauging Stations • Water Level Gauging Stations • River Flow Monitoring • Warning Stations • Remote Terminal Unit • Radio Telemetry • Repeater Stations • Radar System (future) Flood Detection System : Catchment Monitoring & Warning System
  • 10. SUNGAI BATU CATCHMENT SUNGAI BUNUS CATCHMENT SUNGAI KLANG CATCHMENT SUNGAI AMPANG CATCHMENT SUNGAI GOMBAK CATCHMENT KLANGGATESDAM CATCHMENT KLANGGATES DAM BATUDAM SG.KERAYONG SG.KLANG S G . K L A N G S G . B U N U S S G . A M P A N G S G . G O M B A K S G . B A T U SUNGAI KERAYONG CATCHMENT 3.3.5 3.3.4 3.1.14 3.3.3 3.3.2 3.3.1 3.2.9 3.2.6 3.2.4 3.1.13 3.2.12 3.1.10 3.1.4 3.1.8 3.1.3 3.1.2 3.1.1 3.1.12 3.2.5 3.1.7 3.1.9 3.1.11 3.2.2 3.1.6 3.1.5 3.2.8 3.2.11 3.2.10 3.2.7 3.2.3 3.2.1 LEGEND CATCHMENTBOUNDRY RIVER PROPOSEDBYPASS RAINFALLGAUGINGSTATION WATERLEVERLGAUGINGSTATION WATERLEVELANDRAINFALLGAUGINGSTATION DAMMONITORINGSYSTEM CRUMPWEIR ACCOSTICDOPPLERCURRENTPROFILER WATERLEVELGAUGINGSTATION &RAINFALLGAUGINGSTATION WATERLEVELGAUGINGSTATION &ACCOSTICDOPPLERCURRENTPROFILER WATERLEVEL ANDRAINFALLGAUGINGSTATION &CRUMPWEIR WATERLEVEL ANDRAINFALLGAUGINGSTATION &ACCOSTICDOPPLERCURRENTPROFILER (A) (B) (C) (D) (E) (F) (B)+(A) (B)+(F) (C)+(E) (C)+(F) Flood Detection System : Weather Stations layout
  • 11. TO JLN SULTAN ISMAIL WATER FLOW TO KL-SEREMBAN HIGHWAY NORTH JUNCTION SOUTH JUNCTION GATE SHAFT GATE SHAFT KEY PLAN ROAD GATE ROAD GATE Flood Gates : North Junction Box / South Junction Box
  • 12. TO JLN SULTAN ISMAIL WATER FLOW TO KL-SEREMBAN HIGHWAY NORTH JUNCTION SOUTH JUNCTION GATE SHAFT GATE SHAFT KEY PLAN ROAD GATE ROAD GATE • Prevention of vehicles entry during storm events • Prevention of flood discharge entering to the ingress/egress connection UPSTREAM MOTORWAY TUNNEL GATE SHAFT MOTOR ROOM ACCESS GROUND LEVEL FLOODGATE GATE MOTOR ROOM HYDRAULIC RAM HYDRAULIC RAM TYPICAL MOTORWAY TUNNEL SHAFT DETAIL 1 - OPERATION OF TYPICAL ROAD GATE PLAN SHOWING ROAD GATE ASSEMBLY Traffic Traffic See Detail 1 Road Gates : North Junction Box / South Junction Box
  • 14. Typical Tunnel Section 600 600 200 2550 2800 PROPOSED REVISED LANE WIDTH 8.85M - HEIGHT 2.55M 2200 3250 3250 150 8850 Traffic Lane Traffic Lane Emergency Lane Marginal Strip 2550 Right Upper deck 600 = = 1200 Right Lower deck Left Upper deck Left Lower deck E.P 2300 1200 600 2300 E.P Radio Re-Broadcast Linear Heat Detector CCTV Radio Re-Broadcast CCTV Linear Heat Detector Radio Re-Broadcast Radio Re-Broadcast -Heat Detection -Tunnel Lighting -Hydrant and etc. -Leaky Feeder Cable for Radio and Cellular -CCTV -Lane Traffic Signal -Gas Analyzer
  • 17. Th - Threshold Zone Tr1 - Transition Zone 1 Tr2 - Transition Zone 2 Tr3 - Transition Zone 3 Tunnel Lighting Traffic Direction Th Zone Tr1 Zone Tr2 Zone Tr3 Zone Interior Zone Exit Zone • To provide continuity in visual performance for motorists entering and travelling through road tunnel. • IP 68 enclosure and subjected to 2.5 Bar water pressure and bracket design shall withstand 5.5 m/s flow.
  • 18. • The system will respond to the rate of temperature rise, about 10 seconds. • Programmable fire zones • Triggering CCTV system and Fire Alarm System during the case of tunnel fire. Fire Detection System INCIDENT! CCTV FIRE Tunnel Heat Detection System
  • 19. Tunnel Fire Protection : Emergency Points And Equipment • Hose Reel, Fire Extinguishers, Breakglass and Emergency Telephone are located at each cross passages, ventilation shafts and escape shafts. • Hydrants & Fire Extinguisher are installed along the tunnel NJB NVS SVS SJB Ground Level Hydrant & Fire Extinguisher Hose Reel, Fire Extinguisher, Break Glass & Emergency Telephone
  • 20. • Re-broadcast FM radios, cellular (telco), fire department, police and ambulance signal into the tunnel. • Audio break-in facility to broadcast emergency messages from the control center into the tunnel through FM frequencies. • IP 68 antenna installed to enable the use of mobile phones. • Public Address and emergency phone are provided in the cross passages and escape shafts. Tunnel Radio Communication and Cellular System LEAKY FEEDER
  • 21. • Tunnel Surveillance – PTZ CCTV at selected locations – Fixed CCTV along the tunnel – Linked to Fire Detection System – Linked to Control Center via Fiber Optic Cable • Automatic Incident Detection – Measurement of traffic flow speed, occupancy count – Detection of speed drop, stop vehicles, inverse direction and smoke CCTV
  • 22. Tunnel Monitoring & Control System (TMCS) Emer. Tel. CCTV Lane Sign Vent. Sys. Fire Alarm Tunnel Lights Elect.. Dist. Emergency Services Public Information Internet (future) Fully Integrated Traffic Management and Control System Electrical Distribution System Monitoring Tunnel Lighting Control and Monitoring Ventilation System Control and Monitoring Fire Protection System Monitoring Emergency Telephone System Monitoring Emergency Response Plan Automatic Incident Detection Alarm logging Electrical Distribution System Monitoring Tunnel Lighting Control and Monitoring Ventilation System Control and Monitoring Fire Protection System Monitoring Emergency Telephone System Monitoring Emergency Response Plan Automatic Incident Detection Alarm logging Operations Interface Traffic Management & Control System (TMCS) Pump Gates FDS (JPS) Toll Collection
  • 23. Event 1 Tunnel Closure from Mode 2 to Mode 3 FDS TMCS Toll Booth Operator / Patrolman VMS Traffic Diversion Radio Broadcasting AID Estimate Quantity of Vehicle CCTV Monitor Evacuation SCADA Off Road Drainage Pump / Ventilation Patrolman Check XP Water Tight Door Regulate Diversion Weir Water flow into Tunnel Open Flood Gate Close Road Gate
  • 24. Event 2 Traffic Accident CCTV / AID LHD Patrolman Traffic Diversion VMS Alert Motorist Radio Broadcasting AQME Ventilation PA at XP Communication
  • 25. Event 3 Fire Accident Radio Broadcasting Patrolman Traffic Diversion Toll Booth Close Alert Motorist VMS SCADA Ventilation / Lighting CCTV LHD AQME
  • 26. EVENT 3 : Fire Accident Cross Passage and Emergency Escape • Cross passages linking both tunnel road decks with stairs spaced approximately 250m intervals. • Shaft Buildings at approximately 1km apart with stairs and lifts connecting the two road decks to the surface NJB NVS SVS SJB Ground Level ~ 1 km ~ 250 m ELEVATION VIEW
  • 27. South Junction Box South Ventilation Shaft North Ventilation Shaft North Junction Box EVENT 3 : Fire Accident Ventilation System
  • 28. EVENT 3 : Fire Accident Cross Passage and Emergency Escape South Junction Box South Ventilation Shaft North Ventilation Shaft North Junction Box