SlideShare a Scribd company logo
Introduction to Power
Plants
Endsem-70 P.A.-30
ESE - 25 P.A. - 25
After many experiments, first with carbon filaments and then
with platinum and other metals, Edison returned to a carbon
filament. The first successful test was on October 22,1879, it
lasted 13.5 hours.Edison continued to improve this design
and on November 4, 1879, filed for U.S. patent 223,898
(granted on January 27, 1880) for an electric lamp using "a
carbon filament or strip coiled and connected to platina
contact wires".This was the first commercially practical
incandescent light.
Energy consumption as
measure of prosperity
a) Commercial energy sources
b) Non commercial energy sources
Energy and power
Power kW
Energy kWh
• Electrical energy is most useful form of energy because it can be most
conveniently transformed into other forms of energy like heat light,
mechanical energy that we require in our day to day life.
• But electricity is not readily available and is required to be produced
(generated) in a factory called power station.
• Like any other manufacturing process, the production (generation) of
electricity also need some cost to be incurred - Plants and Equipment, Inputs
(water, fuel etc.), Ash smoke disposal systems, Personnel
• Cost of Transmission and Distribution to the large number of consumers of
various categories (viz. domestic, commercial, industrial, agricultural etc.)
• All these costs when added together constitutes the total cost of electricity
which in the consumers have to share according to the quantum 9of electricity
consumed taking into account the nature and time of use of electricity by
each category of consumers.
• The question is how this cost of electricity is to determined in a transparent manner.
• Some standard principles have been evolved through ages of un & sell ofelectricity
become more and more complicated.
• Methods of calculation of cost of generation of electricity in a Thermal Power station in
terms of these basic principles.
• Cost of Electricity has two components – Fixed Cost and Variable Cost
The basic difference between power and energy –
Power –
It is the capacity to Generate or consume electricity. The term “Power” specifies the
capacity of generation or consumption in terms of Kilowatt (KW) or Megawatt (MW). One
Megawatt as we know in one thousand Kilowatt.
Energy –
It is the Power Generated or Consumed by utilizing the capacity for a duration of time. It one
kilowatt Power has been generated or distributed continuously for one hour, it is said that an
energy of One Kilowatt hour has been generated or used. Similarly if Five kilowatt of Power is
generated or consumed for Two hours, an energy of 10 ( = 51X0 2) kilowatt hour has been
generated or consumed and so on.
Types of energy
Renewable
Non renewable
Coal: 192,971.5 MW (58.3%)
Large Hydro: 44,963.42 MW (13.6%)
Small Hydro: 4,389.55 MW (1.3%)
Wind Power: 32,700.64 MW (9.9%)
Solar Power: 14,771.69 MW (4.5%)
Biomass: 8,295.78 MW (2.5%)
Nuclear: 6,780 MW (2.0%)
Gas: 25,150.38 MW (7.6%)
Diesel: 837.63 MW (0.3%)
India energy consumption
330000 MW India
330 GW
•The first demonstration of an electric
light in Calcutta (now Kolkata) was
conducted on 24 July 1879 .
•India began utilizing grid management
on a regional basis in the 1960s
• India’s capacity 330 GW (2017)
• Maharashtra, Western India.[1] With a
total generation of 10,737 MW, it is the
second largest power producing company
in India
Year India
electricity
production
1947 1362 MW
2016 326840 MW
2018 340000 MW
As of December 2010, the installed power generation capacityof
India stood at 169 GW and is trying to add another 78 GW by
2012. 330 GW by 2016, The demand for electricity is expected to
be about 1,000 GW by 2030.
Per capita consumption is also indicator of growth
India has one National Grid with an installed capacityof
Share of fossil energy 66.2%
Share of renewable energy 31.8%
GHG emissions from electricity generation (2015)
2066.01MtCO2
[2]
Average electricity use (2016-17) 1,122 kWh per capita
Transmission & Distribution losses (2015-16) 21.81
%Residential consumption = 24.32%[3]
Industrial consumption = 40.01%[3]
Agriculture consumption = 18.33%[3]
Commercial consumption = 9.22%[3]
Services
Share of private sector in generation 44% (October 17)
Maharashtra:
Thermal power plant Operational
1.Chandrapur Super Thermal Power Station - 3340 MW.
2.Koradi Thermal Power Station - 620 MW
3.Khaparkheda Thermal Power Station - 1340 MW
4.Bhusawal Thermal Power Station - 1420 MW
5.Nashik Thermal Power Station - 630 MW
6.Parli Thermal Power Station - 1130 MW
7.Paras Thermal Power Station - 500 MW
Planned / Under Development
Chandrapur Super Thermal Power Station Project U-8,9 - 2 X 500MW
Koradi Thermal Power Station Project U-8,9,10 - 3 X 660MW[5]
Parli Thermal Power Station Project U-8 - 1 X 250MW
Thermal Power Stations Gas based
Uran Gas Turbine Power Station - 4 X 108, 2 X 120 = 672 MW
Hydro Power Stations[edit]
Bhatghar- Dam
Bhatsa
Bhira - 80 MW
Dimbhe Dam
Ghatghar Pumped Storage Hydroelectric Power Plant - 250 MW
Kanher Dam
Koyna Hydroelectric Project - 1,956 MW
Manikdoh Dam
Panshet Dam
Pavana Dam
Surya Dam
Tillari Dam, Chandgad
Ujani Dam
Vaitarna Dam
Varasgaon Dam
Veer Dam
Warna Dam
Yeldari Dam
Coal: 984 billion tons , USA has 25.4 %, Russia 15.9 % China 11.6 % , India
8.9 %
Petroleum oil: global 1147 billion barrels ( 1 barrel = 160 liters) Saudi has 23
%
Gas: 176 trillion cubic meter, Russian has 27 %
World reserve will lost oil 45 years gas 65 years , coal 200 years
Global consumption : 9741 billion tones of oil equivalent (Mtoe)
Developing country energy growth rate is 2.7 %
Oil use is 39 %
Natural gas 2.2 % use
Coal predominant
Co2 emission increase is 1.9 %
1 metric ton coal = 0.41 Mtoe
India:
energy
India: 17 %
of
Type
y
Popula
India
tion consum
Total
e 3.5 % of
world
Used
energy
In
global
Will last World
will
Coal 58.3
%
92 billion
tones
662 million
tons /year,
imports 730
m t
8.6 % (4th
)
230
years
192
years
Oil 36% 763.48
million
tones
36 MTs 0.4 %
Top 10 in
world
82 %
imports
Gas 10% 1227.4
billion cu
m
31.90 BCM /
year
0.77
Nuclear
Power
2.4 70000 Mt 3310 MW
Power production scenario
MW Coal Gas Diesel Total Nucle
ar
Hydro RES
total
Grand
total
India 196097 24867 837 221802 6780 45487 72012 346082
Maha 26960 3512 0 30473 690 3331 8759 43254
• Electricity act 2003 private allowed
• Removed need of licenses for power generation
• Power plant having 1000 MW , no tax for 10
years
• Allowed 100 %FDI
• Selling bulk power to grid
• Less import duty for 1000 MW and more plant
equipment
• 40 % by private sector
• National thermal power corporation (NTPC)
established in 1975
• 45 % share in production and distribution
• Rural electrification corporation : some sate
100% (REC)
• Nuclear power corporation : it was se up in
1987 target 20000MW (NCP)
• National hydro power corporation (NHPC)
• Power grid corporation of India (PGCI)
• State Electricity Boards (SEB’s) :18
➢During power shortage , some dispensable appliances are switched
off except the essential services like water supply and streetlighting
➢This cause minor in convenience to consumer
➢Load shedding can also be done on the entire system
simultaneously or on different parts of the network in the cityin
rotation
➢In case of industries if load increases above certainmaximum
demand circuit breaker switch off power which is installed at
company premises .
➢In case of more load, few non necessary equipment can beswitch
off.
Introduction to power plants

More Related Content

What's hot

Electricity production in Pakistan
Electricity production in Pakistan Electricity production in Pakistan
Electricity production in Pakistan
Usman Qadir
 
Solar PV Sector in India: Challenges & Way Ahead
Solar PV Sector in India: Challenges & Way AheadSolar PV Sector in India: Challenges & Way Ahead
Solar PV Sector in India: Challenges & Way Ahead
TATA Strategic Management Group- Chemicals Vertical
 
OFFSHORE WIND ENERGY
OFFSHORE WIND ENERGYOFFSHORE WIND ENERGY
OFFSHORE WIND ENERGY
Madan Singh
 
Sir wind
Sir windSir wind
Sir windgvee
 
Solar energy pakistan
Solar energy pakistanSolar energy pakistan
Solar energy pakistan
Abdul Mutahher
 
Solar energy in india
Solar energy in indiaSolar energy in india
Solar energy in india
devesh soni
 
Power Sector in Pakistan - 2017
Power Sector in Pakistan - 2017Power Sector in Pakistan - 2017
Power Sector in Pakistan - 2017
Salman Haider
 
Renewable energy
Renewable energyRenewable energy
Renewable energy
Rohit Kumar
 
Raman Lambas Nuclear Power
Raman Lambas Nuclear PowerRaman Lambas Nuclear Power
Raman Lambas Nuclear Powerneeraj25
 
Present Situation of Electrical Energy Demand, Supply Projection of Them and ...
Present Situation of Electrical Energy Demand, Supply Projection of Them and ...Present Situation of Electrical Energy Demand, Supply Projection of Them and ...
Present Situation of Electrical Energy Demand, Supply Projection of Them and ...
Md Nazmul Islam
 
Solar Energy Systems Perspective about Pakistan
Solar Energy Systems Perspective about PakistanSolar Energy Systems Perspective about Pakistan
Solar Energy Systems Perspective about PakistanZed Siddy
 
Power Plant 1
Power Plant 1Power Plant 1
Power Plant 1
josy2108
 
Pakistan power sector overview issues and recommendations
Pakistan power sector overview issues and recommendations Pakistan power sector overview issues and recommendations
Pakistan power sector overview issues and recommendations
abrar younas
 
19. NECS 2016 _ Energy- Way forward for solar and wind power in NE India -Pro...
19. NECS 2016 _ Energy- Way forward for solar and wind power in NE India -Pro...19. NECS 2016 _ Energy- Way forward for solar and wind power in NE India -Pro...
19. NECS 2016 _ Energy- Way forward for solar and wind power in NE India -Pro...
FICCINorthEast
 
Solar energy – current status and future trends - Klaus Jäger
Solar energy – current status and future trends - Klaus JägerSolar energy – current status and future trends - Klaus Jäger
Solar energy – current status and future trends - Klaus Jäger
UNICORNS IN TECH
 
Renewable energy resources in Pakistan
Renewable energy resources in PakistanRenewable energy resources in Pakistan
Renewable energy resources in Pakistan
Muhammad Qasim
 
“ A walk to power scenario in INDIA”
“ A walk to power scenario in INDIA”“ A walk to power scenario in INDIA”
“ A walk to power scenario in INDIA”
DHIRENDRA SHUKLA
 
Alternate Energy Sources-solar energy abstract
Alternate Energy Sources-solar energy abstractAlternate Energy Sources-solar energy abstract
Alternate Energy Sources-solar energy abstractEr. Pavan Kumar Maganti
 
Comparison of Nuclear Energy of Bangladesh with India & Pakistan
Comparison of Nuclear Energy of Bangladesh with India & PakistanComparison of Nuclear Energy of Bangladesh with India & Pakistan
Comparison of Nuclear Energy of Bangladesh with India & Pakistan
IOSR Journals
 
Future of solar Power Projects in India
Future of solar Power Projects in IndiaFuture of solar Power Projects in India
Future of solar Power Projects in India
Harish Sharma
 

What's hot (20)

Electricity production in Pakistan
Electricity production in Pakistan Electricity production in Pakistan
Electricity production in Pakistan
 
Solar PV Sector in India: Challenges & Way Ahead
Solar PV Sector in India: Challenges & Way AheadSolar PV Sector in India: Challenges & Way Ahead
Solar PV Sector in India: Challenges & Way Ahead
 
OFFSHORE WIND ENERGY
OFFSHORE WIND ENERGYOFFSHORE WIND ENERGY
OFFSHORE WIND ENERGY
 
Sir wind
Sir windSir wind
Sir wind
 
Solar energy pakistan
Solar energy pakistanSolar energy pakistan
Solar energy pakistan
 
Solar energy in india
Solar energy in indiaSolar energy in india
Solar energy in india
 
Power Sector in Pakistan - 2017
Power Sector in Pakistan - 2017Power Sector in Pakistan - 2017
Power Sector in Pakistan - 2017
 
Renewable energy
Renewable energyRenewable energy
Renewable energy
 
Raman Lambas Nuclear Power
Raman Lambas Nuclear PowerRaman Lambas Nuclear Power
Raman Lambas Nuclear Power
 
Present Situation of Electrical Energy Demand, Supply Projection of Them and ...
Present Situation of Electrical Energy Demand, Supply Projection of Them and ...Present Situation of Electrical Energy Demand, Supply Projection of Them and ...
Present Situation of Electrical Energy Demand, Supply Projection of Them and ...
 
Solar Energy Systems Perspective about Pakistan
Solar Energy Systems Perspective about PakistanSolar Energy Systems Perspective about Pakistan
Solar Energy Systems Perspective about Pakistan
 
Power Plant 1
Power Plant 1Power Plant 1
Power Plant 1
 
Pakistan power sector overview issues and recommendations
Pakistan power sector overview issues and recommendations Pakistan power sector overview issues and recommendations
Pakistan power sector overview issues and recommendations
 
19. NECS 2016 _ Energy- Way forward for solar and wind power in NE India -Pro...
19. NECS 2016 _ Energy- Way forward for solar and wind power in NE India -Pro...19. NECS 2016 _ Energy- Way forward for solar and wind power in NE India -Pro...
19. NECS 2016 _ Energy- Way forward for solar and wind power in NE India -Pro...
 
Solar energy – current status and future trends - Klaus Jäger
Solar energy – current status and future trends - Klaus JägerSolar energy – current status and future trends - Klaus Jäger
Solar energy – current status and future trends - Klaus Jäger
 
Renewable energy resources in Pakistan
Renewable energy resources in PakistanRenewable energy resources in Pakistan
Renewable energy resources in Pakistan
 
“ A walk to power scenario in INDIA”
“ A walk to power scenario in INDIA”“ A walk to power scenario in INDIA”
“ A walk to power scenario in INDIA”
 
Alternate Energy Sources-solar energy abstract
Alternate Energy Sources-solar energy abstractAlternate Energy Sources-solar energy abstract
Alternate Energy Sources-solar energy abstract
 
Comparison of Nuclear Energy of Bangladesh with India & Pakistan
Comparison of Nuclear Energy of Bangladesh with India & PakistanComparison of Nuclear Energy of Bangladesh with India & Pakistan
Comparison of Nuclear Energy of Bangladesh with India & Pakistan
 
Future of solar Power Projects in India
Future of solar Power Projects in IndiaFuture of solar Power Projects in India
Future of solar Power Projects in India
 

Similar to Introduction to power plants

Thermal power plant
Thermal power plantThermal power plant
Thermal power plant
SiraskarCom
 
Energy cost and energy shortage in nepal potential of solar, wind and other f...
Energy cost and energy shortage in nepal potential of solar, wind and other f...Energy cost and energy shortage in nepal potential of solar, wind and other f...
Energy cost and energy shortage in nepal potential of solar, wind and other f...
SINGHZEE
 
Energy
EnergyEnergy
Energy
mustafa190
 
Practices and Opportunities of Renewable Energy Resources in Bangladesh
Practices and Opportunities of Renewable Energy Resources in BangladeshPractices and Opportunities of Renewable Energy Resources in Bangladesh
Practices and Opportunities of Renewable Energy Resources in Bangladesh
Nafisa Nawal Islam
 
Conventional and Non conventional Energy sources
Conventional and Non conventional Energy sourcesConventional and Non conventional Energy sources
Conventional and Non conventional Energy sources
Hassan Sardar
 
Hydro electricity and hydro power plant
Hydro electricity and hydro power plantHydro electricity and hydro power plant
Hydro electricity and hydro power plant
Raj Kumar Parihar
 
Non conventional energy sources
Non conventional energy sourcesNon conventional energy sources
Non conventional energy sourcesNirmal Kumar
 
STEP(Solar Technology for Energy Production)
STEP(Solar Technology for Energy Production)STEP(Solar Technology for Energy Production)
STEP(Solar Technology for Energy Production)sajidpk92
 
Energy Scenario in India
Energy Scenario in IndiaEnergy Scenario in India
Energy Scenario in India
Ravijesh Kumar
 
Re-thinking Sustainability and the Green Transition.pptx
Re-thinking Sustainability and the Green Transition.pptxRe-thinking Sustainability and the Green Transition.pptx
Re-thinking Sustainability and the Green Transition.pptx
KateBooth6
 
Renewable Energy.pptx
Renewable Energy.pptxRenewable Energy.pptx
Renewable Energy.pptx
mohammad773734
 
Non conventional power plants
Non conventional power plantsNon conventional power plants
Non conventional power plants
SiraskarCom
 
michaux-ppt.pptx
michaux-ppt.pptxmichaux-ppt.pptx
michaux-ppt.pptx
Tupapi16
 
CSP Basque Country Catalog 2016
CSP Basque Country Catalog 2016CSP Basque Country Catalog 2016
CSP Basque Country Catalog 2016
Cluster_Energia
 
presentation vsv.ppt
presentation vsv.pptpresentation vsv.ppt
presentation vsv.ppt
Abhishek Goswami
 
Introduction and Present Status of Renewable Energies.ppt
Introduction and Present Status of Renewable Energies.pptIntroduction and Present Status of Renewable Energies.ppt
Introduction and Present Status of Renewable Energies.ppt
RajaDesingu2
 
Scope of solar thermal power plants in India
Scope of solar thermal power plants in IndiaScope of solar thermal power plants in India
Scope of solar thermal power plants in India
RAJ BAIRWA
 
Design of solar pv grid connected system based on load requirement and also a...
Design of solar pv grid connected system based on load requirement and also a...Design of solar pv grid connected system based on load requirement and also a...
Design of solar pv grid connected system based on load requirement and also a...
Gururaj B Rawoor
 
Nuclear power
Nuclear                                                         powerNuclear                                                         power
Nuclear power
Mohd Faiz
 

Similar to Introduction to power plants (20)

Thermal power plant
Thermal power plantThermal power plant
Thermal power plant
 
Energy cost and energy shortage in nepal potential of solar, wind and other f...
Energy cost and energy shortage in nepal potential of solar, wind and other f...Energy cost and energy shortage in nepal potential of solar, wind and other f...
Energy cost and energy shortage in nepal potential of solar, wind and other f...
 
Energy
EnergyEnergy
Energy
 
Practices and Opportunities of Renewable Energy Resources in Bangladesh
Practices and Opportunities of Renewable Energy Resources in BangladeshPractices and Opportunities of Renewable Energy Resources in Bangladesh
Practices and Opportunities of Renewable Energy Resources in Bangladesh
 
Conventional and Non conventional Energy sources
Conventional and Non conventional Energy sourcesConventional and Non conventional Energy sources
Conventional and Non conventional Energy sources
 
Hydro electricity and hydro power plant
Hydro electricity and hydro power plantHydro electricity and hydro power plant
Hydro electricity and hydro power plant
 
Non conventional energy sources
Non conventional energy sourcesNon conventional energy sources
Non conventional energy sources
 
STEP(Solar Technology for Energy Production)
STEP(Solar Technology for Energy Production)STEP(Solar Technology for Energy Production)
STEP(Solar Technology for Energy Production)
 
Energy Scenario in India
Energy Scenario in IndiaEnergy Scenario in India
Energy Scenario in India
 
Re-thinking Sustainability and the Green Transition.pptx
Re-thinking Sustainability and the Green Transition.pptxRe-thinking Sustainability and the Green Transition.pptx
Re-thinking Sustainability and the Green Transition.pptx
 
Renewable Energy.pptx
Renewable Energy.pptxRenewable Energy.pptx
Renewable Energy.pptx
 
Non conventional power plants
Non conventional power plantsNon conventional power plants
Non conventional power plants
 
michaux-ppt.pptx
michaux-ppt.pptxmichaux-ppt.pptx
michaux-ppt.pptx
 
CSP Basque Country Catalog 2016
CSP Basque Country Catalog 2016CSP Basque Country Catalog 2016
CSP Basque Country Catalog 2016
 
presentation vsv.ppt
presentation vsv.pptpresentation vsv.ppt
presentation vsv.ppt
 
Introduction and Present Status of Renewable Energies.ppt
Introduction and Present Status of Renewable Energies.pptIntroduction and Present Status of Renewable Energies.ppt
Introduction and Present Status of Renewable Energies.ppt
 
Scope of solar thermal power plants in India
Scope of solar thermal power plants in IndiaScope of solar thermal power plants in India
Scope of solar thermal power plants in India
 
Arun
ArunArun
Arun
 
Design of solar pv grid connected system based on load requirement and also a...
Design of solar pv grid connected system based on load requirement and also a...Design of solar pv grid connected system based on load requirement and also a...
Design of solar pv grid connected system based on load requirement and also a...
 
Nuclear power
Nuclear                                                         powerNuclear                                                         power
Nuclear power
 

Recently uploaded

ML for identifying fraud using open blockchain data.pptx
ML for identifying fraud using open blockchain data.pptxML for identifying fraud using open blockchain data.pptx
ML for identifying fraud using open blockchain data.pptx
Vijay Dialani, PhD
 
Planning Of Procurement o different goods and services
Planning Of Procurement o different goods and servicesPlanning Of Procurement o different goods and services
Planning Of Procurement o different goods and services
JoytuBarua2
 
ethical hacking-mobile hacking methods.ppt
ethical hacking-mobile hacking methods.pptethical hacking-mobile hacking methods.ppt
ethical hacking-mobile hacking methods.ppt
Jayaprasanna4
 
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
thanhdowork
 
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
zwunae
 
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&BDesign and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Sreedhar Chowdam
 
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
bakpo1
 
Investor-Presentation-Q1FY2024 investor presentation document.pptx
Investor-Presentation-Q1FY2024 investor presentation document.pptxInvestor-Presentation-Q1FY2024 investor presentation document.pptx
Investor-Presentation-Q1FY2024 investor presentation document.pptx
AmarGB2
 
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
AJAYKUMARPUND1
 
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
Amil Baba Dawood bangali
 
Architectural Portfolio Sean Lockwood
Architectural Portfolio Sean LockwoodArchitectural Portfolio Sean Lockwood
Architectural Portfolio Sean Lockwood
seandesed
 
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
obonagu
 
Water Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdfWater Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation & Control
 
AP LAB PPT.pdf ap lab ppt no title specific
AP LAB PPT.pdf ap lab ppt no title specificAP LAB PPT.pdf ap lab ppt no title specific
AP LAB PPT.pdf ap lab ppt no title specific
BrazilAccount1
 
Immunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary AttacksImmunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary Attacks
gerogepatton
 
Railway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdfRailway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdf
TeeVichai
 
power quality voltage fluctuation UNIT - I.pptx
power quality voltage fluctuation UNIT - I.pptxpower quality voltage fluctuation UNIT - I.pptx
power quality voltage fluctuation UNIT - I.pptx
ViniHema
 
Student information management system project report ii.pdf
Student information management system project report ii.pdfStudent information management system project report ii.pdf
Student information management system project report ii.pdf
Kamal Acharya
 
MCQ Soil mechanics questions (Soil shear strength).pdf
MCQ Soil mechanics questions (Soil shear strength).pdfMCQ Soil mechanics questions (Soil shear strength).pdf
MCQ Soil mechanics questions (Soil shear strength).pdf
Osamah Alsalih
 
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
ydteq
 

Recently uploaded (20)

ML for identifying fraud using open blockchain data.pptx
ML for identifying fraud using open blockchain data.pptxML for identifying fraud using open blockchain data.pptx
ML for identifying fraud using open blockchain data.pptx
 
Planning Of Procurement o different goods and services
Planning Of Procurement o different goods and servicesPlanning Of Procurement o different goods and services
Planning Of Procurement o different goods and services
 
ethical hacking-mobile hacking methods.ppt
ethical hacking-mobile hacking methods.pptethical hacking-mobile hacking methods.ppt
ethical hacking-mobile hacking methods.ppt
 
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
 
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
 
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&BDesign and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
 
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
 
Investor-Presentation-Q1FY2024 investor presentation document.pptx
Investor-Presentation-Q1FY2024 investor presentation document.pptxInvestor-Presentation-Q1FY2024 investor presentation document.pptx
Investor-Presentation-Q1FY2024 investor presentation document.pptx
 
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
 
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
 
Architectural Portfolio Sean Lockwood
Architectural Portfolio Sean LockwoodArchitectural Portfolio Sean Lockwood
Architectural Portfolio Sean Lockwood
 
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
 
Water Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdfWater Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdf
 
AP LAB PPT.pdf ap lab ppt no title specific
AP LAB PPT.pdf ap lab ppt no title specificAP LAB PPT.pdf ap lab ppt no title specific
AP LAB PPT.pdf ap lab ppt no title specific
 
Immunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary AttacksImmunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary Attacks
 
Railway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdfRailway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdf
 
power quality voltage fluctuation UNIT - I.pptx
power quality voltage fluctuation UNIT - I.pptxpower quality voltage fluctuation UNIT - I.pptx
power quality voltage fluctuation UNIT - I.pptx
 
Student information management system project report ii.pdf
Student information management system project report ii.pdfStudent information management system project report ii.pdf
Student information management system project report ii.pdf
 
MCQ Soil mechanics questions (Soil shear strength).pdf
MCQ Soil mechanics questions (Soil shear strength).pdfMCQ Soil mechanics questions (Soil shear strength).pdf
MCQ Soil mechanics questions (Soil shear strength).pdf
 
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
 

Introduction to power plants

  • 1. Introduction to Power Plants Endsem-70 P.A.-30 ESE - 25 P.A. - 25
  • 2. After many experiments, first with carbon filaments and then with platinum and other metals, Edison returned to a carbon filament. The first successful test was on October 22,1879, it lasted 13.5 hours.Edison continued to improve this design and on November 4, 1879, filed for U.S. patent 223,898 (granted on January 27, 1880) for an electric lamp using "a carbon filament or strip coiled and connected to platina contact wires".This was the first commercially practical incandescent light.
  • 3.
  • 4.
  • 5. Energy consumption as measure of prosperity a) Commercial energy sources b) Non commercial energy sources Energy and power Power kW Energy kWh
  • 6. • Electrical energy is most useful form of energy because it can be most conveniently transformed into other forms of energy like heat light, mechanical energy that we require in our day to day life. • But electricity is not readily available and is required to be produced (generated) in a factory called power station. • Like any other manufacturing process, the production (generation) of electricity also need some cost to be incurred - Plants and Equipment, Inputs (water, fuel etc.), Ash smoke disposal systems, Personnel • Cost of Transmission and Distribution to the large number of consumers of various categories (viz. domestic, commercial, industrial, agricultural etc.) • All these costs when added together constitutes the total cost of electricity which in the consumers have to share according to the quantum 9of electricity consumed taking into account the nature and time of use of electricity by each category of consumers.
  • 7. • The question is how this cost of electricity is to determined in a transparent manner. • Some standard principles have been evolved through ages of un & sell ofelectricity become more and more complicated. • Methods of calculation of cost of generation of electricity in a Thermal Power station in terms of these basic principles. • Cost of Electricity has two components – Fixed Cost and Variable Cost The basic difference between power and energy – Power – It is the capacity to Generate or consume electricity. The term “Power” specifies the capacity of generation or consumption in terms of Kilowatt (KW) or Megawatt (MW). One Megawatt as we know in one thousand Kilowatt. Energy – It is the Power Generated or Consumed by utilizing the capacity for a duration of time. It one kilowatt Power has been generated or distributed continuously for one hour, it is said that an energy of One Kilowatt hour has been generated or used. Similarly if Five kilowatt of Power is generated or consumed for Two hours, an energy of 10 ( = 51X0 2) kilowatt hour has been generated or consumed and so on.
  • 9.
  • 10. Coal: 192,971.5 MW (58.3%) Large Hydro: 44,963.42 MW (13.6%) Small Hydro: 4,389.55 MW (1.3%) Wind Power: 32,700.64 MW (9.9%) Solar Power: 14,771.69 MW (4.5%) Biomass: 8,295.78 MW (2.5%) Nuclear: 6,780 MW (2.0%) Gas: 25,150.38 MW (7.6%) Diesel: 837.63 MW (0.3%) India energy consumption 330000 MW India 330 GW
  • 11.
  • 12. •The first demonstration of an electric light in Calcutta (now Kolkata) was conducted on 24 July 1879 . •India began utilizing grid management on a regional basis in the 1960s • India’s capacity 330 GW (2017) • Maharashtra, Western India.[1] With a total generation of 10,737 MW, it is the second largest power producing company in India
  • 13. Year India electricity production 1947 1362 MW 2016 326840 MW 2018 340000 MW
  • 14. As of December 2010, the installed power generation capacityof India stood at 169 GW and is trying to add another 78 GW by 2012. 330 GW by 2016, The demand for electricity is expected to be about 1,000 GW by 2030.
  • 15. Per capita consumption is also indicator of growth
  • 16.
  • 17.
  • 18. India has one National Grid with an installed capacityof Share of fossil energy 66.2% Share of renewable energy 31.8% GHG emissions from electricity generation (2015) 2066.01MtCO2 [2] Average electricity use (2016-17) 1,122 kWh per capita Transmission & Distribution losses (2015-16) 21.81 %Residential consumption = 24.32%[3] Industrial consumption = 40.01%[3] Agriculture consumption = 18.33%[3] Commercial consumption = 9.22%[3] Services Share of private sector in generation 44% (October 17)
  • 19. Maharashtra: Thermal power plant Operational 1.Chandrapur Super Thermal Power Station - 3340 MW. 2.Koradi Thermal Power Station - 620 MW 3.Khaparkheda Thermal Power Station - 1340 MW 4.Bhusawal Thermal Power Station - 1420 MW 5.Nashik Thermal Power Station - 630 MW 6.Parli Thermal Power Station - 1130 MW 7.Paras Thermal Power Station - 500 MW Planned / Under Development Chandrapur Super Thermal Power Station Project U-8,9 - 2 X 500MW Koradi Thermal Power Station Project U-8,9,10 - 3 X 660MW[5] Parli Thermal Power Station Project U-8 - 1 X 250MW Thermal Power Stations Gas based Uran Gas Turbine Power Station - 4 X 108, 2 X 120 = 672 MW
  • 20. Hydro Power Stations[edit] Bhatghar- Dam Bhatsa Bhira - 80 MW Dimbhe Dam Ghatghar Pumped Storage Hydroelectric Power Plant - 250 MW Kanher Dam Koyna Hydroelectric Project - 1,956 MW Manikdoh Dam Panshet Dam Pavana Dam Surya Dam Tillari Dam, Chandgad Ujani Dam Vaitarna Dam Varasgaon Dam Veer Dam Warna Dam Yeldari Dam
  • 21. Coal: 984 billion tons , USA has 25.4 %, Russia 15.9 % China 11.6 % , India 8.9 % Petroleum oil: global 1147 billion barrels ( 1 barrel = 160 liters) Saudi has 23 % Gas: 176 trillion cubic meter, Russian has 27 % World reserve will lost oil 45 years gas 65 years , coal 200 years Global consumption : 9741 billion tones of oil equivalent (Mtoe) Developing country energy growth rate is 2.7 % Oil use is 39 % Natural gas 2.2 % use Coal predominant Co2 emission increase is 1.9 % 1 metric ton coal = 0.41 Mtoe
  • 22. India: energy India: 17 % of Type y Popula India tion consum Total e 3.5 % of world Used energy In global Will last World will Coal 58.3 % 92 billion tones 662 million tons /year, imports 730 m t 8.6 % (4th ) 230 years 192 years Oil 36% 763.48 million tones 36 MTs 0.4 % Top 10 in world 82 % imports Gas 10% 1227.4 billion cu m 31.90 BCM / year 0.77 Nuclear Power 2.4 70000 Mt 3310 MW
  • 23. Power production scenario MW Coal Gas Diesel Total Nucle ar Hydro RES total Grand total India 196097 24867 837 221802 6780 45487 72012 346082 Maha 26960 3512 0 30473 690 3331 8759 43254
  • 24.
  • 25. • Electricity act 2003 private allowed • Removed need of licenses for power generation • Power plant having 1000 MW , no tax for 10 years • Allowed 100 %FDI • Selling bulk power to grid • Less import duty for 1000 MW and more plant equipment • 40 % by private sector
  • 26. • National thermal power corporation (NTPC) established in 1975 • 45 % share in production and distribution • Rural electrification corporation : some sate 100% (REC) • Nuclear power corporation : it was se up in 1987 target 20000MW (NCP) • National hydro power corporation (NHPC) • Power grid corporation of India (PGCI) • State Electricity Boards (SEB’s) :18
  • 27. ➢During power shortage , some dispensable appliances are switched off except the essential services like water supply and streetlighting ➢This cause minor in convenience to consumer ➢Load shedding can also be done on the entire system simultaneously or on different parts of the network in the cityin rotation ➢In case of industries if load increases above certainmaximum demand circuit breaker switch off power which is installed at company premises . ➢In case of more load, few non necessary equipment can beswitch off.

Editor's Notes

  1. RV