SlideShare a Scribd company logo
1 of 133
Download to read offline
*
WELCOME
K R SURI April 161K R SURI
* April 162K R SURI
Emerging Prospects
*Energy and Global
Practices for
Indian Power Market
April 163K R SURI
*
*PRESENT GENERATION & TRANSMISSION
*CHALLENGES AHEAD
* RESOURCES & SCOPE IN INDIA
*LOSSES
*ELECTRICITY REGULATIONS
*INTEGRATION WITH
* NEIGHBOURING / ASIAN COUNTRIES
April 164K R SURI
April 16 K R SURI 5
INSTALLED CAPACITY ( Feb. 16 )-------- MW
Mar-30
FEB. 2016
DEC. 2011
1950
9,30,000
2,88,665
1,88,000
1713
THERMAL
HYDRO
NUCLEAR
OTHERS
2,03,604
Break up
2,88,665
42,473
36,808
5,780
April 16 6K R SURI
Fuel MW % age
Total Thermal 2,03,604 70.52
Coal 178,138 61.71
Gas 24,473 08.47
Oil 994 00.34
Hydro 42,473 14.71
Nuclear 5,780 02.00
RES** ( RE etc) 36,808 12.75
Total 288,665 100.00
BREAK UP ---- Feb.2016
April 167K R SURI
* April 168K R SURI
14181.6
2015-16
*
2,88,665 mw
April 169K R SURI
Central Grid
S
W
N
E
NE
NEW Grid
South
Grid
October 1991
East & North-East
synchronized
March 2003
West synchronized
With East & North-East
August 2006
North synchronized
with Central Grid
Five Regional Grids
Five Frequencies
Raichur-Sholapur
Inter-Regional Link commissioned
One Nation
One Grid
One Frequency
National Grid - Evolution
One Nation - One Grid – One Frequency
A long cherished dream turned into
reality
Dec’2013
South
synchronized
with
NEW Grid
Present inter-regional power transfer
capacity: 46, 450MW
April 1610K R SURI
11
7,930 MW
1,260 MW
4,220 MW
1,720 MW
3,630 MW
SR
WR
NR
NER
ER
Inter Regional Power Transfer
Capacity by 2016 end - 35,000 MW
Present Inter Regional
Power Transfer Capacity
23,800 MW
SR
August 2006
North synchronized
With Central Grid
October 1991
East and Northeast
synchronized
March 2003
West synchronized
With East & Northeast
Future: Country wide
synchronous Grid
Earlier, Five Regional
Grids Five Frequencies
4,220 MW
1,260 MW
4,220 MW
1,260 MW
4,220 MW
1,260 MW
4,220 MW
3,630 MW
1,260 MW
4,220 MW
1,720 MW
3,630 MW
4,390 MW
1,260 MW
4,220 MW
28560 CKM
4195 CKM
18710 CKM
12500 CKM
17500 CKM
ESTABLISHMENT OF NATIONAL GRID
- Excluding 600 MW of IR capacity at 132 kV level
April 16K R SURI
*Current Transmission(ckt. Kms)
* CTU(Power grid) ---- 1,40,000
* SEBs --- 20,000
* OTHERS ---- 7000
* STATIONS >205 nos
* 400/765/1175 kv
*1175 Kv under trial
* at BINA April 1612K R SURI
Current Energy position in country
*Installed capacity ----- Feb. 2016
2,88,665 mw
*DEMAND BY 2030 ----
9,30,000 MW
around 45,000 mw addition
REQUIRED on annual basis
April 1613K R SURI
*
*HOW TO MEET 45,000MW/YR
*400KV DC----- 42 LINES/YR
*400 KV QC --- 22 LINES /YR
*765 KV QC --- 15 LINES/YR
*These are appx. figures
*A BIG CHALLENGE FOR TRANSMISSION
April 1614K R SURI
Big
Challenge
April 1615K R SURI
April 16K R SURI 16
*
920
940
960
980
1000
1020
1040
1060
2013-14 2014-15 2015-16
BILLION UNITS
April 16K R SURI 17
*
CKT KMS
2013-14
2014-15
2015-16
2016-17
16745
17745
25721
27000
* April 1618K R SURI
43956
2015-16
*
*REQUIRED
* 45,000 MW PER YEAR
*ADDITION TREND TILL NOW
* 22,500 MW PER YEAR
*RATIO SAY 50%
April 1619K R SURI
Year Target
Achievement
%
%
target
%
%
growth
2009-10 789.511 771.551
97.73
6.6
2010-11 830.757 811.143
97.64
5.56
2011-12 855.000 876.887
102.56 8.11
2012-13 930.000 912.056 98.07
4.01
2013-14 975.000
967.150
99.19
6.04
2014-15 1023.00 1048.673
102.51 8.43
2015-16*
(Oct. 2015 663.007 654.467 98.71 5.14
PLANNED Vs ACTUAL
April 1620K R SURI
* 69%April 1621K R SURI
* April 1622K R SURI
April 16K R SURI 23
All India PLF Month-
wise
April 68.64 62.05
May 67.06 64.27
June 66.31 59.43
July 63.80 58.36
August 59.58 57.60
September 59.07 63.63
October 65.01 66.86
November 65.69 60.34
December 65.14 61.75
January 64.79 63.20
February 65.72 64.95
Figure not available
2014-15 2015-16
YEAR
*
April 16K R SURI 24
*POWER SYSTEM NETWORK
April 1625K R SURI
*Smart grid
April 1626K R SURI
BIOGAS/MASS
ETC
GEO THERMAL
Begasse
OTHERS
April 1627K R SURI
April 1628K R SURI
TOTAL ---- SAY 37,000 mw
3700
22000
April 1629K R SURI
April 1630K R SURI
BIOGAS
April 1631K R SURI
April 1632K R SURI
April 1633K R SURI
*
April 1634K R SURI
April 1635K R SURI
*GROWTHApril 1636K R SURI
*Solar resource
Big opportunity
to
capture
7500 mw in j&k
April 1637K R SURI
*COSTApril 1638K R SURI
*
*In our country
*Considering
*300 --- Clear sunny days
*10 % -- Efficiency of PV cell
*Planned to produce 5000 trillion
Kwh per year
*1,00,000 MW BY 2022
April 1639K R SURI
Wind powerApril 1640K R SURI
*GrowthApril 1641K R SURI
*PLAN
*POTENTIAL IDENTIFIED
*19,130 MW ---- 50 mtr
*1,02,788 mw -- 80 mtr
*Total – 1,22,000
*Out of which
*60,000 mw ---- 2022
*Cost
* Rs 62 lacs/mw and return in 4 yrs
April 1642K R SURI
*Geo Thermal Energy
April 1643K R SURI
ICE LAND
April 1644K R SURI
* April 1645K R SURI
*
*27,500 mw plant
*Pertamina Geothermal Energy
* USA
April 1646K R SURI
*
*INDIA HAS IDENTIFIED TOTAL 340 HOT SPOTS ( 10,600 MW)
* Locations are
* Himalayan province ---
* j&k--- Puga and Chhumathang
* HP --- Manikaran
* Aravalli hills/area
* Hazari Bagh (surajkund) -- jharkhand
* West Coast/Area
* Cambay basin --- Gujrat
* Narmada Belt --- MP
* Tatapani --- Chattisgarh
* Andaman & Nicobar islands
April 16
47
K R SURI
*
*Basins has been drilled and found that
source exists at avg. depth of
*1.4 -- 1.7 - 1.9 -- 3.4 Kms
*It has been planned by GOI to put first
plant in j&k ---- 5 Mw at puga
April 1648K R SURI
*
April 1649K R SURI
*
*Tidal wave energy is basically using sea waves
* As per survey by IIOS.(Indian institute of oceanic studies)
* TIDES CAN PRODUCE ENERGY, WHEN WAVES
ARE IN range of 5.23 Mrs. To 6.77 metres
*Gujrat and West Bengal has such waves &
can produced 8mw
* Planned -- 3.75 mw Dhungadhauni ( WB.)
April 1650K R SURI
*
MAX. 19.9 MW
April 1651K R SURI
April 1652K R SURI
*
*It uses salts
*SODIUM NITRATE -- 60%
*POTASSIUM NITRATE – 40%
*HEATS THE MIXTURE TO >550 deg
* through HELIOSTATS and generate steam.
*GEMA MOLTAN PLANT – SPAIN
*CAPACITY –19.9 MW
April 1653K R SURI
LOSSES April 1654K R SURI
* April 1655K R SURI
2013—14
21.46
22.70
*
*
April 16K R SURI 56
*Losses in j&k PFC
*As on SEP. 2014 ---
app. 71%
Highest in country
April 1657K R SURI
Avoid Wastage
and harmonics April 1658K R SURI
DEBT 03/16
Rs 3234.00 Crs
*
April 1659K R SURI
*
April 1660K R SURI
Lessons
April 1661K R SURI
*J&K DISASTER - 2014
April 1662K R SURI
*J&K DISASTER CONTD
April 1663K R SURI
*Preparing for another
Disaster
Nanak
Nagar
JammuApril 1664K R SURI
April 1665K R SURI
* vs April 1666K R SURI
* April 1667K R SURI
*Rise of DemandApril 1668K R SURI
Plant load factor
April 1669K R SURI
April 1670K R SURI
*
2013-14 957
April 1671K R SURI
*WORLD VIDE COMPARISON WORLD BANK
COUNTRY PCC % ELECT. COUNTRY PCC % ELECT
USA 13000 100 JAPAN 1000 100
CANADA 17000 100 INDIA 954 78
CHINA 4000 100 Maldives 2000 100
ICELAND 7000 100 B/Desh 300 60
ENGLAND 6000 100 PAKISTAN 500 90
NORWAY 25000 100 SRI LANKA 600 88April 1672K R SURI
CHALLENGES BEFORE
April 1673K R SURI
Challenge ahead for CTU (MVA)April 1674K R SURI
*
5 yr plans Total ckt kms
9th 0
10th 2284
11th 6435
12th (July 2015) 10354
ADANI 1000kms
HVDC 500 KV
April 1675K R SURI
INDIA
SHINES April 1676K R SURI
*
POWER
MARKET
April 1677K R SURI
*POWER SYSTEM NETWORK
April 1678K R SURI
*A vibrant and growing power market
Stable growth and consolidation
*A completely voluntary market
Multiple choice/options
*Trading licensed activity as per Electricity Act 2003
50 trading licensees (mar 2015)
*Top 5 trading licensees have 80% market share
PTC leads the pack (pioneer and market leader)
*Impact of Electricity trading
Optimizing of existing energy resources
Encouraging commercial outlook in the sector
Encouraging cross-border exchange of power
Catalyzing investment into the power sector, mainly from the private sector
April 1679K R SURI
*Recent Trends in Market
*Direct bilateral growing at faster rate
and banking transactions on rise
Financial health of utilities
Discoms preferring direct and money-less transactions
*Unscheduled Interchange (UI) on
decreased pattern
Positive development as UI has implications on grid
security
Result of frequency band tightening by CERC April 1680K R SURI
Increased license fee for traders
Appears to be an entry barrier for new
players
 Burden on existing players as Trading
margin is capped
Need of Min. Fixed Exchange
rate
Fixed charges (Intermediately fees)April 1681K R SURI
*TRADINGApril 1682K R SURI
*
*IEC ---- 2003
* ENFORCED --- CERC, OA & PPT
*CERC --- REGULATES
* TARIFF
* SETTLEMENT OF DISPUTES
* TRADING MARGIN
April 1683K R SURI
* April 1684K R SURI
*BILATERAL between tradersApril 1685K R SURI
FORWARD TRADING
April 1686K R SURI
* April 1687K R SURI
* April 1688K R SURI
* April 1689K R SURI
* April 1690K R SURI
*
Tata Power and Reliance are the two major companies with huge installed capacity and large
buying and selling statistics for the same.
Punjab power corporation is also major seller now
Table shows volume transacted by major buyers and sellers in FY12 through traders
Does not include volume through banking arrangements
Top 5 sellers constitute ~59% of the total volume
Top 5 buyers constitute ~ 63% of the total volume
Total trading companies app. 50 now April 1691K R SURI
*
9300 13400
1500 3300
April 1692K R SURI
Prospects
for
Integration
April 1693K R SURI
*South Asia: Energy Cooperation
*SE Asian countries are the most rapidly
Developing Countries
*High Rate of GDP growth
*Larger growing population but low
per capita consumption
*Huge Demand for Energy against supply
* ( peak hrs – shortage, off peak hrs – surplus)
April 1694K R SURI
*South Asia: Energy Cooperation
*Energy base different for SA countries
India – one of largest coal reserves in world
Bangladesh - Gas basins
Nepal & Bhutan - Huge hydro potential
Solar and Wind - Excellent potential in region
J&K is upcoming and estimating to
touch 4000mw capacity in near future.
April 1695K R SURI
Thus, tremendous possibility for regional
energy cooperation
Regional Integration or trade
Sub-regional cooperation between India, Nepal,
Bhutan and Bangladesh has high prospects
Sharing of land boundaries
Positive response from these
Countries April 1696K R SURI
*PAKISTAN
HAS SURPLUS POWER DURING DAY TIME
2/3 VISITS CUM MEETING HAS TAKEN PLACE
TO BUILT HVDC LINK BETWEEN
LAHORE TO AMRITSAR
*SRI LANKA
THERE WERE DISCUSSIONS ON LAYING OF HV CABLE UNDER SEA
April 1697K R SURI
Prospects for Integration: Sub-Regional Market
*India is the first South-Asian country to establish a
power market
*Strong power links being built up in the sub-region
*Benefits of Indian Power Market may be extended
to neighbors, as robust transmission exists
*With the completion of India-Nepal & India - Bhutan
transmission links , the sub region is strong.
*With completion of India - Bangladesh 400 kv link
and Hvdc back to back, network has become
more stronger
April 1698K R SURI
Markets have been extended to Nepal and Bhutan
through Power Grid.
Generation sources in the region may be pooled and
traded in one common market
Trade may happen through bilateral arrangements
involving traders or power exchanges
Open Access (OA) may be granted to countries to
buy/sell power in each others territory.
Lessons may be learnt from other developed power
markets like Nord pool spot etc
Benefit to all from economic and shared resources
scale
April 1699K R SURI
*
*Private sector accounted for 41% of capacity in 11th
Plan outpacing Central and State Sectors
*58% of the total capacity addition in FY12 from
private sector
*Private sector outperformed achieved 141% of the
target
*Share of Private Sector in total generating has
increased from 12% to 28% in last 5 yrs.
April 16100K R SURI
Bhutan
 Presently, interconnections exist with Bhutan at 400kV
level
 Alipurduar(India) – Punatsangchu-I HEP (Bhutan) 400kV
D/c is under implementation – completion expected in
2015
Nepal
 interconnections already exist with Nepal.
 Muzaffarpur (India) – Dhalkebar (Nepal) 400kV D/c is
being implemented by CPTC (Indian Portion) and PTCN
(Nepal Portion). Completion expected in 2015.
International Cooperation
Linkages with SAARC Countries
April 16101K R SURI
Bangladesh
 Baharampur (India) ---– Bheramara (Bangladesh)
HVDC back-to-back commissioned in September,
2013.
Power up to 500MW is flowing from India
Surajyamani Nagar(India) to
Comilla(South Bengladesh)
400kv line has also been completed in 2014.
April 16102K R SURI
103
JAYPURHAT
BANGLADESH
INTERCONNECTION BETWEEN INDIA AND BANGLADESH GRIDS
NIAMATPUR
BHERAMARA
KOLAGHAT
BAKRESHWAR
GOKARNADURGAPUR
KATWA
SUBHASGRAM
JEERAT
(400 KV)
BAHARAMPUR
INDIA
400kV D/c
KHEJURIA
SAGARDIGHI
RAGHUNATHGANJ
FARRAKA
KAHALGAON
DHULIAN
MALDA
BAHARAMPUR
CH. NAWABGANJ
RAJSHAHI
PUR
PABNAISHURDI
LEGEND
BAGHABARI
(SOUTH)
KHULNA
BOTTAIL FARIDPUR
Under Constr. / Future
THE PROJECT
230 kV
Existing
132 kV
400 kV
GHORASAL
SIRAJGANJ
SHAHJAD
NATORE
SOUTH
BOGRA
BARAPUKURIA
NAOGAON
BOGRA
MADHOPUR
April 16K R SURI
April 16104K R SURI
April 16105K R SURI
*Gas pipeline
ending GujratApril 16106K R SURI
*Connectivity with CHINA
*WE CAN ALSO ENTER POWER
SUPPLY AGREEMENT WITH
CHINA AT
* BRAHMPUTRA BASIN ---
Zangmu dam
April 16107K R SURI
Issues faced
by
Indian Power Market
April 16108K R SURI
*
Current power market scenario
*Power Sector’s vicious circle of challenges
Financial health of DISCOMs
Funding issues
Fuel scarcity (coal scam & gas shortage)
Transmission security/reliability bottlenecks
# Coal international regulation (import of coal is costly in India)
Regulatory issues
*Policy initiatives
* single window system
*Support to initiatives planned by IEX for market developmentApril 16109K R SURI
*
April 16110K R SURI
*
LEAKING BUCKET
SEBs April 16K R SURI 111
*
*Theft of power
*Subsidy by state Govt
*Inadequate last mile connectivity
* large scale & domestic
*Inadequate demand building measures
*Land acquisition
April 16112K R SURI
*
Aug’10 – Oct’11
Source: IEXApril 16113K R SURI
*
Rising Dependence on Imported Coal April 16114K R SURI
*
Domestic gas only meets 60% of the total requirements
April 16115K R SURI
*
*The current interregional transmission capacity is only around 13 per cent of
the total installed generation capacity
*With focus on increasing generation capacity over the next 8-10 years, the
corresponding investments in the transmission sector is also expected to
augment.
* Ministry of power plans to establish an integrated national power grid in the
country by 2016 with close to 2,50,000 mw generation capacities and 37,700
mw of inter-regional power transfer capacity
*Considering that the current interregional power transfer capacity of 25,000
mw, this is indeed an ambitious objective for the country.
*A large portion of new projects are likely to be in the North Eastern region,
Sikkim, Nepal and Bhutan.
*Another emerging trend in the transmission sector is the movement towards
"Ultra High Voltage" systems.(1200kv HVAC)(800kv hvdc 1800kms, 6000mw)
*J&K coming up with new hydro energy plants.
April 16116K R SURI
*
*Flexibility in Line Loading and Regulation of Power
*Improvement in Operational Efficiency
*Increase in Transmission Voltage/Energy Transfer/Series
Compensator(FACTS)/SVC/Statcom.
*Up gradation of HVDC Terminals and existing AC stations
*High capacity 400kV multi-circuit/bundle conductor lines
*High Surge Impedance Loading (HSIL) Line
*Compact towers (single pole/ tubular towers ) April 16117K R SURI
*
FACTS
Use of High Temp. Low Sag (HTLS) conductor in tr. Lines
Installation of GIS & reduce ROW issues
Condition Based Monitoring and Preventive Maint.
1175kV Test Station (under trial)
Power grid is having 1,40,000 circuit km of Tr.
lines. 205 sub stations up to 765kv/800 kv Hvdc.
April 16119K R SURI
• SPGVL is also having
• 2 nos 765 kv ss
• 1200 kms ----- 765 kv line
• 4000 kms ----- 400 kv line
• UNDER CONTN
• 1000 kms
• 4 nos GIS
April 16 K R SURI 120
*EXAMPLE OF ULTRA MW PROJECTS
* SASAN
* MUNDRA
* KRISHNAPATTAM
* TALLAIYA
*PLANS TO REDUCE COAL IMPORT
* GRADUALLY & FINISH BY 2017/2018
* SELF DEPENDENT & plans to Produce
1BillionTons by 2020 ON ANNUAL BASIS
April 16121K R SURI
NATIONAL GRID & Estt. of NTAMC
*ENFORCEMENT OF ENERGY EFFICIENT
BLDGS, EQPTS, LIGHT GADGETS etc.
*WRITE OFF 8000 MW
LOW EFFICIENT GEN. PLANTS
*Due to ROW -- FOR COAL & HYDRO PLANTS.
squeezing land requirement
* Example COAL BASE
2X500 MW ---- 1.42 acre/mw
8x500 mw ---- 0.68 acre/mw
*Further tried to reduce 0.38 acre /mw
*Use of HTLS conductor in Tran. lines April 16122K R SURI
*
125 125
Pole type tower in NCR area April 16K R SURI
126HOT LINE April 16K R SURI
127
Insulator cleaning with helicopter
on 400kV Meerut – Mandola D/c Transmission Line
April 16K R SURI
*HELICOPTER CLEANING VIDEO
April 16K R SURI 128
April 16129K R SURI
*
April 16130K R SURI
131
Enjoy Life
Konstanz Port,Germany
07/05/2015
April 16K R SURI
ENJOY
TEA
April 16132K R SURI
K R SURI
9419211829/9906901669
krsuri1954@gmail.com
April 16133K R SURI

More Related Content

Viewers also liked

Digital Marketing: How to Specify Tactics & Strategies
Digital Marketing: How to Specify Tactics & StrategiesDigital Marketing: How to Specify Tactics & Strategies
Digital Marketing: How to Specify Tactics & StrategiesGeorge Yfantis
 
Playboy1950s
Playboy1950sPlayboy1950s
Playboy1950sksomel
 
Applying cognitive computing to business operations, transforming front to ba...
Applying cognitive computing to business operations, transforming front to ba...Applying cognitive computing to business operations, transforming front to ba...
Applying cognitive computing to business operations, transforming front to ba...HfS Research
 
Increase Revenue with a Unified Digital Engagement Strategy
Increase Revenue with a Unified Digital Engagement StrategyIncrease Revenue with a Unified Digital Engagement Strategy
Increase Revenue with a Unified Digital Engagement Strategyedynamic
 
Individual behavior
Individual behaviorIndividual behavior
Individual behaviorroyneelima
 
Fenomenos paranormales
Fenomenos paranormalesFenomenos paranormales
Fenomenos paranormalesAnais Ramirez
 

Viewers also liked (8)

Digital Marketing: How to Specify Tactics & Strategies
Digital Marketing: How to Specify Tactics & StrategiesDigital Marketing: How to Specify Tactics & Strategies
Digital Marketing: How to Specify Tactics & Strategies
 
Playboy1950s
Playboy1950sPlayboy1950s
Playboy1950s
 
Applying cognitive computing to business operations, transforming front to ba...
Applying cognitive computing to business operations, transforming front to ba...Applying cognitive computing to business operations, transforming front to ba...
Applying cognitive computing to business operations, transforming front to ba...
 
Increase Revenue with a Unified Digital Engagement Strategy
Increase Revenue with a Unified Digital Engagement StrategyIncrease Revenue with a Unified Digital Engagement Strategy
Increase Revenue with a Unified Digital Engagement Strategy
 
Individual behavior
Individual behaviorIndividual behavior
Individual behavior
 
Informe empresa final
Informe empresa finalInforme empresa final
Informe empresa final
 
Veal_C_Cancer
Veal_C_CancerVeal_C_Cancer
Veal_C_Cancer
 
Fenomenos paranormales
Fenomenos paranormalesFenomenos paranormales
Fenomenos paranormales
 

Similar to Emerging Prospects for Indian Power Market

A Report to ONGC
A Report to ONGCA Report to ONGC
A Report to ONGCAakash Shah
 
PLD report Dec-16
PLD report Dec-16PLD report Dec-16
PLD report Dec-16Prateek Rai
 
Analysis of Investment of Deepwater Drilling Market
Analysis of Investment of Deepwater Drilling MarketAnalysis of Investment of Deepwater Drilling Market
Analysis of Investment of Deepwater Drilling MarketDr. Oliver Massmann
 
Power Sector Update: Generation growth buoyant - Motilal Oswal
Power Sector Update: Generation growth buoyant - Motilal OswalPower Sector Update: Generation growth buoyant - Motilal Oswal
Power Sector Update: Generation growth buoyant - Motilal OswalIndiaNotes.com
 
Ashish Modi ONGC
Ashish Modi ONGCAshish Modi ONGC
Ashish Modi ONGCAshish Modi
 
Cement Industries Prospects
Cement Industries ProspectsCement Industries Prospects
Cement Industries ProspectsNeeta Khilnani
 
CNG CONSUMPTION IN SATELITTE TOWN, RAWALPINDI
CNG CONSUMPTION IN SATELITTE TOWN, RAWALPINDICNG CONSUMPTION IN SATELITTE TOWN, RAWALPINDI
CNG CONSUMPTION IN SATELITTE TOWN, RAWALPINDIKiyani1292
 
CNG CONSUMPTION & EMISSION IN SATELITTE TOWN, RAWALPINDI
CNG CONSUMPTION & EMISSION IN SATELITTE TOWN, RAWALPINDICNG CONSUMPTION & EMISSION IN SATELITTE TOWN, RAWALPINDI
CNG CONSUMPTION & EMISSION IN SATELITTE TOWN, RAWALPINDIKiyani1292
 
NTG-Oil-Gas-Analysis-FINAL
NTG-Oil-Gas-Analysis-FINALNTG-Oil-Gas-Analysis-FINAL
NTG-Oil-Gas-Analysis-FINALRichard Exley
 
Global Development & Trends in Turkey & its Neighbours & the Rest of the Oil ...
Global Development & Trends in Turkey & its Neighbours & the Rest of the Oil ...Global Development & Trends in Turkey & its Neighbours & the Rest of the Oil ...
Global Development & Trends in Turkey & its Neighbours & the Rest of the Oil ...ITE Oil&Gas
 
Presentation given at CLSA investors' forum in Hong Kong
Presentation given at CLSA investors' forum in Hong KongPresentation given at CLSA investors' forum in Hong Kong
Presentation given at CLSA investors' forum in Hong KongSantos Ltd
 
Asia days Oslo 2013 - Market opportunities in South & South East Asia - Energy
Asia days Oslo 2013 - Market opportunities in South & South East Asia - EnergyAsia days Oslo 2013 - Market opportunities in South & South East Asia - Energy
Asia days Oslo 2013 - Market opportunities in South & South East Asia - EnergyInnovation Norway
 
RBSA Research Report- Offshore & Marine Engineering Sector in Singapore
 RBSA Research Report- Offshore & Marine Engineering Sector in Singapore RBSA Research Report- Offshore & Marine Engineering Sector in Singapore
RBSA Research Report- Offshore & Marine Engineering Sector in SingaporeRBSA Advisors
 
Sunoco Logistics Analyst Day Presentation - Nov 2014 in Dallas, TX
Sunoco Logistics Analyst Day Presentation - Nov 2014 in Dallas, TXSunoco Logistics Analyst Day Presentation - Nov 2014 in Dallas, TX
Sunoco Logistics Analyst Day Presentation - Nov 2014 in Dallas, TXMarcellus Drilling News
 
Equity weekly report 31 july to 4 aug 2017
Equity weekly report 31 july to 4 aug 2017Equity weekly report 31 july to 4 aug 2017
Equity weekly report 31 july to 4 aug 2017tradenivesh investment
 
Oil & Gas opportunities in Southeast Asia
Oil & Gas opportunities in Southeast AsiaOil & Gas opportunities in Southeast Asia
Oil & Gas opportunities in Southeast AsiaInnovation Norway
 
Offshore market overview capt k devadas
Offshore market overview capt k devadasOffshore market overview capt k devadas
Offshore market overview capt k devadascmmindia2017
 

Similar to Emerging Prospects for Indian Power Market (20)

Coal Price review
Coal Price reviewCoal Price review
Coal Price review
 
ntpc annual presentation
ntpc annual presentationntpc annual presentation
ntpc annual presentation
 
A Report to ONGC
A Report to ONGCA Report to ONGC
A Report to ONGC
 
PLD report Dec-16
PLD report Dec-16PLD report Dec-16
PLD report Dec-16
 
Analysis of Investment of Deepwater Drilling Market
Analysis of Investment of Deepwater Drilling MarketAnalysis of Investment of Deepwater Drilling Market
Analysis of Investment of Deepwater Drilling Market
 
Power Sector Update: Generation growth buoyant - Motilal Oswal
Power Sector Update: Generation growth buoyant - Motilal OswalPower Sector Update: Generation growth buoyant - Motilal Oswal
Power Sector Update: Generation growth buoyant - Motilal Oswal
 
Ashish Modi ONGC
Ashish Modi ONGCAshish Modi ONGC
Ashish Modi ONGC
 
Cement Industries Prospects
Cement Industries ProspectsCement Industries Prospects
Cement Industries Prospects
 
CNG CONSUMPTION IN SATELITTE TOWN, RAWALPINDI
CNG CONSUMPTION IN SATELITTE TOWN, RAWALPINDICNG CONSUMPTION IN SATELITTE TOWN, RAWALPINDI
CNG CONSUMPTION IN SATELITTE TOWN, RAWALPINDI
 
CNG CONSUMPTION & EMISSION IN SATELITTE TOWN, RAWALPINDI
CNG CONSUMPTION & EMISSION IN SATELITTE TOWN, RAWALPINDICNG CONSUMPTION & EMISSION IN SATELITTE TOWN, RAWALPINDI
CNG CONSUMPTION & EMISSION IN SATELITTE TOWN, RAWALPINDI
 
Satendra bio
Satendra bioSatendra bio
Satendra bio
 
NTG-Oil-Gas-Analysis-FINAL
NTG-Oil-Gas-Analysis-FINALNTG-Oil-Gas-Analysis-FINAL
NTG-Oil-Gas-Analysis-FINAL
 
Global Development & Trends in Turkey & its Neighbours & the Rest of the Oil ...
Global Development & Trends in Turkey & its Neighbours & the Rest of the Oil ...Global Development & Trends in Turkey & its Neighbours & the Rest of the Oil ...
Global Development & Trends in Turkey & its Neighbours & the Rest of the Oil ...
 
Presentation given at CLSA investors' forum in Hong Kong
Presentation given at CLSA investors' forum in Hong KongPresentation given at CLSA investors' forum in Hong Kong
Presentation given at CLSA investors' forum in Hong Kong
 
Asia days Oslo 2013 - Market opportunities in South & South East Asia - Energy
Asia days Oslo 2013 - Market opportunities in South & South East Asia - EnergyAsia days Oslo 2013 - Market opportunities in South & South East Asia - Energy
Asia days Oslo 2013 - Market opportunities in South & South East Asia - Energy
 
RBSA Research Report- Offshore & Marine Engineering Sector in Singapore
 RBSA Research Report- Offshore & Marine Engineering Sector in Singapore RBSA Research Report- Offshore & Marine Engineering Sector in Singapore
RBSA Research Report- Offshore & Marine Engineering Sector in Singapore
 
Sunoco Logistics Analyst Day Presentation - Nov 2014 in Dallas, TX
Sunoco Logistics Analyst Day Presentation - Nov 2014 in Dallas, TXSunoco Logistics Analyst Day Presentation - Nov 2014 in Dallas, TX
Sunoco Logistics Analyst Day Presentation - Nov 2014 in Dallas, TX
 
Equity weekly report 31 july to 4 aug 2017
Equity weekly report 31 july to 4 aug 2017Equity weekly report 31 july to 4 aug 2017
Equity weekly report 31 july to 4 aug 2017
 
Oil & Gas opportunities in Southeast Asia
Oil & Gas opportunities in Southeast AsiaOil & Gas opportunities in Southeast Asia
Oil & Gas opportunities in Southeast Asia
 
Offshore market overview capt k devadas
Offshore market overview capt k devadasOffshore market overview capt k devadas
Offshore market overview capt k devadas
 

Recently uploaded

High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service NashikCall Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service NashikCall Girls in Nagpur High Profile
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...Soham Mondal
 
The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...
The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...
The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...ranjana rawat
 
Introduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxIntroduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxupamatechverse
 
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
Coefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxCoefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxAsutosh Ranjan
 
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Serviceranjana rawat
 
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...Call Girls in Nagpur High Profile
 
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...ranjana rawat
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxpurnimasatapathy1234
 
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escortsranjana rawat
 
result management system report for college project
result management system report for college projectresult management system report for college project
result management system report for college projectTonystark477637
 
KubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghlyKubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghlysanyuktamishra911
 
Porous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingPorous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingrakeshbaidya232001
 
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...ranjana rawat
 
Introduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxIntroduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxupamatechverse
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escortsranjana rawat
 

Recently uploaded (20)

High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
 
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service NashikCall Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
 
The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...
The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...
The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...
 
Introduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxIntroduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptx
 
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
Coefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxCoefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptx
 
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
 
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
 
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptx
 
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
 
result management system report for college project
result management system report for college projectresult management system report for college project
result management system report for college project
 
KubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghlyKubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghly
 
Porous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingPorous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writing
 
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
 
Introduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxIntroduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptx
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
 

Emerging Prospects for Indian Power Market

  • 1. * WELCOME K R SURI April 161K R SURI
  • 2. * April 162K R SURI
  • 3. Emerging Prospects *Energy and Global Practices for Indian Power Market April 163K R SURI
  • 4. * *PRESENT GENERATION & TRANSMISSION *CHALLENGES AHEAD * RESOURCES & SCOPE IN INDIA *LOSSES *ELECTRICITY REGULATIONS *INTEGRATION WITH * NEIGHBOURING / ASIAN COUNTRIES April 164K R SURI
  • 5. April 16 K R SURI 5 INSTALLED CAPACITY ( Feb. 16 )-------- MW Mar-30 FEB. 2016 DEC. 2011 1950 9,30,000 2,88,665 1,88,000 1713
  • 7. Fuel MW % age Total Thermal 2,03,604 70.52 Coal 178,138 61.71 Gas 24,473 08.47 Oil 994 00.34 Hydro 42,473 14.71 Nuclear 5,780 02.00 RES** ( RE etc) 36,808 12.75 Total 288,665 100.00 BREAK UP ---- Feb.2016 April 167K R SURI
  • 8. * April 168K R SURI 14181.6 2015-16
  • 10. Central Grid S W N E NE NEW Grid South Grid October 1991 East & North-East synchronized March 2003 West synchronized With East & North-East August 2006 North synchronized with Central Grid Five Regional Grids Five Frequencies Raichur-Sholapur Inter-Regional Link commissioned One Nation One Grid One Frequency National Grid - Evolution One Nation - One Grid – One Frequency A long cherished dream turned into reality Dec’2013 South synchronized with NEW Grid Present inter-regional power transfer capacity: 46, 450MW April 1610K R SURI
  • 11. 11 7,930 MW 1,260 MW 4,220 MW 1,720 MW 3,630 MW SR WR NR NER ER Inter Regional Power Transfer Capacity by 2016 end - 35,000 MW Present Inter Regional Power Transfer Capacity 23,800 MW SR August 2006 North synchronized With Central Grid October 1991 East and Northeast synchronized March 2003 West synchronized With East & Northeast Future: Country wide synchronous Grid Earlier, Five Regional Grids Five Frequencies 4,220 MW 1,260 MW 4,220 MW 1,260 MW 4,220 MW 1,260 MW 4,220 MW 3,630 MW 1,260 MW 4,220 MW 1,720 MW 3,630 MW 4,390 MW 1,260 MW 4,220 MW 28560 CKM 4195 CKM 18710 CKM 12500 CKM 17500 CKM ESTABLISHMENT OF NATIONAL GRID - Excluding 600 MW of IR capacity at 132 kV level April 16K R SURI
  • 12. *Current Transmission(ckt. Kms) * CTU(Power grid) ---- 1,40,000 * SEBs --- 20,000 * OTHERS ---- 7000 * STATIONS >205 nos * 400/765/1175 kv *1175 Kv under trial * at BINA April 1612K R SURI
  • 13. Current Energy position in country *Installed capacity ----- Feb. 2016 2,88,665 mw *DEMAND BY 2030 ---- 9,30,000 MW around 45,000 mw addition REQUIRED on annual basis April 1613K R SURI
  • 14. * *HOW TO MEET 45,000MW/YR *400KV DC----- 42 LINES/YR *400 KV QC --- 22 LINES /YR *765 KV QC --- 15 LINES/YR *These are appx. figures *A BIG CHALLENGE FOR TRANSMISSION April 1614K R SURI
  • 16. April 16K R SURI 16 * 920 940 960 980 1000 1020 1040 1060 2013-14 2014-15 2015-16 BILLION UNITS
  • 17. April 16K R SURI 17 * CKT KMS 2013-14 2014-15 2015-16 2016-17 16745 17745 25721 27000
  • 18. * April 1618K R SURI 43956 2015-16
  • 19. * *REQUIRED * 45,000 MW PER YEAR *ADDITION TREND TILL NOW * 22,500 MW PER YEAR *RATIO SAY 50% April 1619K R SURI
  • 20. Year Target Achievement % % target % % growth 2009-10 789.511 771.551 97.73 6.6 2010-11 830.757 811.143 97.64 5.56 2011-12 855.000 876.887 102.56 8.11 2012-13 930.000 912.056 98.07 4.01 2013-14 975.000 967.150 99.19 6.04 2014-15 1023.00 1048.673 102.51 8.43 2015-16* (Oct. 2015 663.007 654.467 98.71 5.14 PLANNED Vs ACTUAL April 1620K R SURI
  • 22. * April 1622K R SURI
  • 23. April 16K R SURI 23 All India PLF Month- wise April 68.64 62.05 May 67.06 64.27 June 66.31 59.43 July 63.80 58.36 August 59.58 57.60 September 59.07 63.63 October 65.01 66.86 November 65.69 60.34 December 65.14 61.75 January 64.79 63.20 February 65.72 64.95 Figure not available 2014-15 2015-16 YEAR
  • 24. * April 16K R SURI 24
  • 29. TOTAL ---- SAY 37,000 mw 3700 22000 April 1629K R SURI
  • 30. April 1630K R SURI BIOGAS
  • 37. *Solar resource Big opportunity to capture 7500 mw in j&k April 1637K R SURI
  • 39. * *In our country *Considering *300 --- Clear sunny days *10 % -- Efficiency of PV cell *Planned to produce 5000 trillion Kwh per year *1,00,000 MW BY 2022 April 1639K R SURI
  • 42. *PLAN *POTENTIAL IDENTIFIED *19,130 MW ---- 50 mtr *1,02,788 mw -- 80 mtr *Total – 1,22,000 *Out of which *60,000 mw ---- 2022 *Cost * Rs 62 lacs/mw and return in 4 yrs April 1642K R SURI
  • 45. * April 1645K R SURI
  • 46. * *27,500 mw plant *Pertamina Geothermal Energy * USA April 1646K R SURI
  • 47. * *INDIA HAS IDENTIFIED TOTAL 340 HOT SPOTS ( 10,600 MW) * Locations are * Himalayan province --- * j&k--- Puga and Chhumathang * HP --- Manikaran * Aravalli hills/area * Hazari Bagh (surajkund) -- jharkhand * West Coast/Area * Cambay basin --- Gujrat * Narmada Belt --- MP * Tatapani --- Chattisgarh * Andaman & Nicobar islands April 16 47 K R SURI
  • 48. * *Basins has been drilled and found that source exists at avg. depth of *1.4 -- 1.7 - 1.9 -- 3.4 Kms *It has been planned by GOI to put first plant in j&k ---- 5 Mw at puga April 1648K R SURI
  • 50. * *Tidal wave energy is basically using sea waves * As per survey by IIOS.(Indian institute of oceanic studies) * TIDES CAN PRODUCE ENERGY, WHEN WAVES ARE IN range of 5.23 Mrs. To 6.77 metres *Gujrat and West Bengal has such waves & can produced 8mw * Planned -- 3.75 mw Dhungadhauni ( WB.) April 1650K R SURI
  • 51. * MAX. 19.9 MW April 1651K R SURI
  • 53. * *It uses salts *SODIUM NITRATE -- 60% *POTASSIUM NITRATE – 40% *HEATS THE MIXTURE TO >550 deg * through HELIOSTATS and generate steam. *GEMA MOLTAN PLANT – SPAIN *CAPACITY –19.9 MW April 1653K R SURI
  • 55. * April 1655K R SURI 2013—14 21.46 22.70
  • 56. * * April 16K R SURI 56
  • 57. *Losses in j&k PFC *As on SEP. 2014 --- app. 71% Highest in country April 1657K R SURI
  • 58. Avoid Wastage and harmonics April 1658K R SURI DEBT 03/16 Rs 3234.00 Crs
  • 62. *J&K DISASTER - 2014 April 1662K R SURI
  • 66. * vs April 1666K R SURI
  • 67. * April 1667K R SURI
  • 68. *Rise of DemandApril 1668K R SURI
  • 69. Plant load factor April 1669K R SURI
  • 72. *WORLD VIDE COMPARISON WORLD BANK COUNTRY PCC % ELECT. COUNTRY PCC % ELECT USA 13000 100 JAPAN 1000 100 CANADA 17000 100 INDIA 954 78 CHINA 4000 100 Maldives 2000 100 ICELAND 7000 100 B/Desh 300 60 ENGLAND 6000 100 PAKISTAN 500 90 NORWAY 25000 100 SRI LANKA 600 88April 1672K R SURI
  • 74. Challenge ahead for CTU (MVA)April 1674K R SURI
  • 75. * 5 yr plans Total ckt kms 9th 0 10th 2284 11th 6435 12th (July 2015) 10354 ADANI 1000kms HVDC 500 KV April 1675K R SURI
  • 79. *A vibrant and growing power market Stable growth and consolidation *A completely voluntary market Multiple choice/options *Trading licensed activity as per Electricity Act 2003 50 trading licensees (mar 2015) *Top 5 trading licensees have 80% market share PTC leads the pack (pioneer and market leader) *Impact of Electricity trading Optimizing of existing energy resources Encouraging commercial outlook in the sector Encouraging cross-border exchange of power Catalyzing investment into the power sector, mainly from the private sector April 1679K R SURI
  • 80. *Recent Trends in Market *Direct bilateral growing at faster rate and banking transactions on rise Financial health of utilities Discoms preferring direct and money-less transactions *Unscheduled Interchange (UI) on decreased pattern Positive development as UI has implications on grid security Result of frequency band tightening by CERC April 1680K R SURI
  • 81. Increased license fee for traders Appears to be an entry barrier for new players  Burden on existing players as Trading margin is capped Need of Min. Fixed Exchange rate Fixed charges (Intermediately fees)April 1681K R SURI
  • 83. * *IEC ---- 2003 * ENFORCED --- CERC, OA & PPT *CERC --- REGULATES * TARIFF * SETTLEMENT OF DISPUTES * TRADING MARGIN April 1683K R SURI
  • 84. * April 1684K R SURI
  • 87. * April 1687K R SURI
  • 88. * April 1688K R SURI
  • 89. * April 1689K R SURI
  • 90. * April 1690K R SURI
  • 91. * Tata Power and Reliance are the two major companies with huge installed capacity and large buying and selling statistics for the same. Punjab power corporation is also major seller now Table shows volume transacted by major buyers and sellers in FY12 through traders Does not include volume through banking arrangements Top 5 sellers constitute ~59% of the total volume Top 5 buyers constitute ~ 63% of the total volume Total trading companies app. 50 now April 1691K R SURI
  • 94. *South Asia: Energy Cooperation *SE Asian countries are the most rapidly Developing Countries *High Rate of GDP growth *Larger growing population but low per capita consumption *Huge Demand for Energy against supply * ( peak hrs – shortage, off peak hrs – surplus) April 1694K R SURI
  • 95. *South Asia: Energy Cooperation *Energy base different for SA countries India – one of largest coal reserves in world Bangladesh - Gas basins Nepal & Bhutan - Huge hydro potential Solar and Wind - Excellent potential in region J&K is upcoming and estimating to touch 4000mw capacity in near future. April 1695K R SURI
  • 96. Thus, tremendous possibility for regional energy cooperation Regional Integration or trade Sub-regional cooperation between India, Nepal, Bhutan and Bangladesh has high prospects Sharing of land boundaries Positive response from these Countries April 1696K R SURI
  • 97. *PAKISTAN HAS SURPLUS POWER DURING DAY TIME 2/3 VISITS CUM MEETING HAS TAKEN PLACE TO BUILT HVDC LINK BETWEEN LAHORE TO AMRITSAR *SRI LANKA THERE WERE DISCUSSIONS ON LAYING OF HV CABLE UNDER SEA April 1697K R SURI
  • 98. Prospects for Integration: Sub-Regional Market *India is the first South-Asian country to establish a power market *Strong power links being built up in the sub-region *Benefits of Indian Power Market may be extended to neighbors, as robust transmission exists *With the completion of India-Nepal & India - Bhutan transmission links , the sub region is strong. *With completion of India - Bangladesh 400 kv link and Hvdc back to back, network has become more stronger April 1698K R SURI
  • 99. Markets have been extended to Nepal and Bhutan through Power Grid. Generation sources in the region may be pooled and traded in one common market Trade may happen through bilateral arrangements involving traders or power exchanges Open Access (OA) may be granted to countries to buy/sell power in each others territory. Lessons may be learnt from other developed power markets like Nord pool spot etc Benefit to all from economic and shared resources scale April 1699K R SURI
  • 100. * *Private sector accounted for 41% of capacity in 11th Plan outpacing Central and State Sectors *58% of the total capacity addition in FY12 from private sector *Private sector outperformed achieved 141% of the target *Share of Private Sector in total generating has increased from 12% to 28% in last 5 yrs. April 16100K R SURI
  • 101. Bhutan  Presently, interconnections exist with Bhutan at 400kV level  Alipurduar(India) – Punatsangchu-I HEP (Bhutan) 400kV D/c is under implementation – completion expected in 2015 Nepal  interconnections already exist with Nepal.  Muzaffarpur (India) – Dhalkebar (Nepal) 400kV D/c is being implemented by CPTC (Indian Portion) and PTCN (Nepal Portion). Completion expected in 2015. International Cooperation Linkages with SAARC Countries April 16101K R SURI
  • 102. Bangladesh  Baharampur (India) ---– Bheramara (Bangladesh) HVDC back-to-back commissioned in September, 2013. Power up to 500MW is flowing from India Surajyamani Nagar(India) to Comilla(South Bengladesh) 400kv line has also been completed in 2014. April 16102K R SURI
  • 103. 103 JAYPURHAT BANGLADESH INTERCONNECTION BETWEEN INDIA AND BANGLADESH GRIDS NIAMATPUR BHERAMARA KOLAGHAT BAKRESHWAR GOKARNADURGAPUR KATWA SUBHASGRAM JEERAT (400 KV) BAHARAMPUR INDIA 400kV D/c KHEJURIA SAGARDIGHI RAGHUNATHGANJ FARRAKA KAHALGAON DHULIAN MALDA BAHARAMPUR CH. NAWABGANJ RAJSHAHI PUR PABNAISHURDI LEGEND BAGHABARI (SOUTH) KHULNA BOTTAIL FARIDPUR Under Constr. / Future THE PROJECT 230 kV Existing 132 kV 400 kV GHORASAL SIRAJGANJ SHAHJAD NATORE SOUTH BOGRA BARAPUKURIA NAOGAON BOGRA MADHOPUR April 16K R SURI
  • 104. April 16104K R SURI
  • 105. April 16105K R SURI
  • 107. *Connectivity with CHINA *WE CAN ALSO ENTER POWER SUPPLY AGREEMENT WITH CHINA AT * BRAHMPUTRA BASIN --- Zangmu dam April 16107K R SURI
  • 108. Issues faced by Indian Power Market April 16108K R SURI
  • 109. * Current power market scenario *Power Sector’s vicious circle of challenges Financial health of DISCOMs Funding issues Fuel scarcity (coal scam & gas shortage) Transmission security/reliability bottlenecks # Coal international regulation (import of coal is costly in India) Regulatory issues *Policy initiatives * single window system *Support to initiatives planned by IEX for market developmentApril 16109K R SURI
  • 111. * LEAKING BUCKET SEBs April 16K R SURI 111
  • 112. * *Theft of power *Subsidy by state Govt *Inadequate last mile connectivity * large scale & domestic *Inadequate demand building measures *Land acquisition April 16112K R SURI
  • 113. * Aug’10 – Oct’11 Source: IEXApril 16113K R SURI
  • 114. * Rising Dependence on Imported Coal April 16114K R SURI
  • 115. * Domestic gas only meets 60% of the total requirements April 16115K R SURI
  • 116. * *The current interregional transmission capacity is only around 13 per cent of the total installed generation capacity *With focus on increasing generation capacity over the next 8-10 years, the corresponding investments in the transmission sector is also expected to augment. * Ministry of power plans to establish an integrated national power grid in the country by 2016 with close to 2,50,000 mw generation capacities and 37,700 mw of inter-regional power transfer capacity *Considering that the current interregional power transfer capacity of 25,000 mw, this is indeed an ambitious objective for the country. *A large portion of new projects are likely to be in the North Eastern region, Sikkim, Nepal and Bhutan. *Another emerging trend in the transmission sector is the movement towards "Ultra High Voltage" systems.(1200kv HVAC)(800kv hvdc 1800kms, 6000mw) *J&K coming up with new hydro energy plants. April 16116K R SURI
  • 117. * *Flexibility in Line Loading and Regulation of Power *Improvement in Operational Efficiency *Increase in Transmission Voltage/Energy Transfer/Series Compensator(FACTS)/SVC/Statcom. *Up gradation of HVDC Terminals and existing AC stations *High capacity 400kV multi-circuit/bundle conductor lines *High Surge Impedance Loading (HSIL) Line *Compact towers (single pole/ tubular towers ) April 16117K R SURI
  • 119. Use of High Temp. Low Sag (HTLS) conductor in tr. Lines Installation of GIS & reduce ROW issues Condition Based Monitoring and Preventive Maint. 1175kV Test Station (under trial) Power grid is having 1,40,000 circuit km of Tr. lines. 205 sub stations up to 765kv/800 kv Hvdc. April 16119K R SURI
  • 120. • SPGVL is also having • 2 nos 765 kv ss • 1200 kms ----- 765 kv line • 4000 kms ----- 400 kv line • UNDER CONTN • 1000 kms • 4 nos GIS April 16 K R SURI 120
  • 121. *EXAMPLE OF ULTRA MW PROJECTS * SASAN * MUNDRA * KRISHNAPATTAM * TALLAIYA *PLANS TO REDUCE COAL IMPORT * GRADUALLY & FINISH BY 2017/2018 * SELF DEPENDENT & plans to Produce 1BillionTons by 2020 ON ANNUAL BASIS April 16121K R SURI
  • 122. NATIONAL GRID & Estt. of NTAMC *ENFORCEMENT OF ENERGY EFFICIENT BLDGS, EQPTS, LIGHT GADGETS etc. *WRITE OFF 8000 MW LOW EFFICIENT GEN. PLANTS *Due to ROW -- FOR COAL & HYDRO PLANTS. squeezing land requirement * Example COAL BASE 2X500 MW ---- 1.42 acre/mw 8x500 mw ---- 0.68 acre/mw *Further tried to reduce 0.38 acre /mw *Use of HTLS conductor in Tran. lines April 16122K R SURI
  • 123. *
  • 124.
  • 125. 125 125 Pole type tower in NCR area April 16K R SURI
  • 126. 126HOT LINE April 16K R SURI
  • 127. 127 Insulator cleaning with helicopter on 400kV Meerut – Mandola D/c Transmission Line April 16K R SURI
  • 129. April 16129K R SURI