This document contains charts and data related to maintenance performance and energy consumption at Kirloskar Brothers Limited facilities from April 2016 to December 2016. It shows trends in metrics like MTBF and MTTR as well as consumption of resources like oil, coolant, power. Overall the data indicates that maintenance performance was mostly good with metrics either meeting or below targets, while energy consumption was higher than expected/benchmarks in some areas. It also lists some specific maintenance issues addressed at different equipment during this period.
Kirloskar Brothers Limited MTBF and MTTR Analysis Jan 2017
1. This is a proprietary document of Kirloskar Brothers Limited 115-Jan-17
2. This is a proprietary document of Kirloskar Brothers Limited 215-Jan-17
Cumulative MTBF & MTTR
13.96
21.10
28.20
34.10 34.20
36.40
36.15 37.51 33.14
25
0
10
20
30
40
50
Apr-16
May-16
Jun-16
Jul-16
Aug-16
Sep-16
Oct-16
Nov-16
Dec-16
DAYS
MONTHS
TARGET - 25
MTBF Trend
GOOD
4.60 3.40 3.60 3.30 3.90
7.13 7.67 8.07
14.27
1.50
0
2
4
6
8
10
12
14
16
18
Apr-16
May-16
Jun-16
Jul-16
Aug-16
Sep-16
Oct-16
Nov-16
Dec-16
MONTHS
H
O
U
R
S
TARGET – 1.5
MTTR Trend
GOOD
3. This is a proprietary document of Kirloskar Brothers Limited 315-Jan-17
PLD Equipment – Maintenance Performance
17.85
17.82 22.76
23.70
22.62
20.76
13.88
20.45
21.80
25
10
20
30
Apr-16
May-16
Jun-16
Jul-16
Aug-16
Sep-16
Oct-16
Nov-16
Dec-16
DAYS
MONTHS
TARGET - 25
MTBF Trend
GOOD
4.80
3.20
2.82
3.24
5.67
6.62
11.06
4.54
9.37
1.50
0
2
4
6
8
10
12
Apr-16
May-16
Jun-16
Jul-16
Aug-16
Sep-16
Oct-16
Nov-16
Dec-16
MONTHS
H
O
U
R
S
TARGET – 1.5
MTTR Trend
GOOD
24.2
20.2
18
19
20
21
22
23
24
25
D
a
y
s
FY 2015-16
FY 2016-17
1.82
5.70
0
1
2
3
4
5
6
7
8
H
o
u
r
s
FY 2015-16
FY 2016-17
4. This is a proprietary document of Kirloskar Brothers Limited 415-Jan-17
Foundry Equipment – Maintenance Performance
17.52
16.50
21.82
17.87
16.69
22.82
20.17 21.85 24.02
25
0
5
10
15
20
25
30
Apr-16
May-16
Jun-16
Jul-16
Aug-16
Sep-16
Oct-16
Nov-16
Dec-16
DAYS
MONTHS
TARGET - 25
MTBF Trend
GOOD
0.81
2.40
0.80 1.23
2.78
1.28
6.23
3.08
9.8
1.50
0
2
4
6
8
10
Apr-16
May-16
Jun-16
Jul-16
Aug-16
Sep-16
Oct-16
Nov-16
Dec-16
MONTHS
H
O
U
R
S
TARGET – 1.5
MTTR Trend
GOOD
5. This is a proprietary document of Kirloskar Brothers Limited 515-Jan-17
SMPD Equipment – Maintenance Performance
25
20.25 13.73
15.87 16.08
13.49
18.22 18.02 18.18
20.82
0
5
10
15
20
25
30
Apr-16
May-16
Jun-16
Jul-16
Aug-16
Sep-16
Oct-16
Nov-16
Dec-16
DAYS
MONTHS
TARGET - 25
MTBF Trend
GOOD
10.65 5.8
4.70
4.6
8.90
15.50
4.72
3.02
1.81
1.50
0
2
4
6
8
10
12
14
16
18
Apr-16
May-16
Jun-16
Jul-16
Aug-16
Sep-16
Oct-16
Nov-16
Dec-16
MONTHS
H
O
U
R
S
TARGET – 1.5
MTTR Trend
GOOD KVBT 65-Geometrical accuracy problem
Both ball screw repaired & bearing replaced
Miven 500(RKB)-Turret indexing problem
6. This is a proprietary document of Kirloskar Brothers Limited 615-Jan-17
LPD Equipment – Maintenance Performance
15.78
23.23
30.58 37.14
37.68
21.24
16.11
21.03
21.63
25
0
10
20
30
40
50
Apr-16
May-16
Jun-16
Jul-16
Aug-16
Sep-16
Oct-16
Nov-16
Dec-16
DAYS
MONTHS
TARGET - 25
MTBF Trend
GOOD
2.93 1.44 2.97
3.88 5.34
3.07
21.6
5.37
15.60
1.50
0
3
6
9
12
15
18
21
24
Apr-16
May-16
Jun-16
Jul-16
Aug-16
Sep-16
Oct-16
Nov-16
Dec-16
MONTHS
H
O
U
R
S
TARGET – 1.5
MTTR Trend
GOOD
SK 40- Spindle gear box gear worn out.
New gear & bearing fitted
7. This is a proprietary document of Kirloskar Brothers Limited 715-Jan-17
Preventive maintenance
7
47 48
40 38
43
47 48
43
38
46
0
10
20
30
40
50
60
Aug-16
Sep-16
Oct-16
Nov-16
Dec-16
MONTHS
PM
Planned
achieved
M
A
C
H
I
N
E
11
16
26
14
9
18
7
9
8
10
0
10
20
30
40
50
60
Aug-16 Sep-16 Oct-16 Nov-16 Dec-16
Breakdown monitoring of PM m/cs
Nov-16 m/cs
Oct-16 m/cs
Sep-16 m/cs
Aug-16 m/cs
8. This is a proprietary document of Kirloskar Brothers Limited 815-Jan-17
Bar chart-MTBF
8
4.38 4.61
5.83
12.40 12.60
0.00
2.00
4.00
6.00
8.00
10.00
12.00
14.00
16.00
18.00
DOOSAN
HMC(RKB)
HELLER 250(DB) MIVEN 500(KPD) DYNA 100(KPDS) MIVEN 500(DB)
Top m/c With lowest MTBF(SMPD)
D
a
y
s
Turret indexing problem
Set indexing proxy & pressure setting
3.51
6.85 7.27
8.18 8.27
0.00
2.00
4.00
6.00
8.00
10.00
12.00
YOUJI
2000(ATPD)
KBL 120 CNC WOTON
RAPID
VW 4 AXIS
MACHINE
CARANAGI
Top m/c With lowest MTBF(LPD)
D
a
y
s
I/o channel prob
SMPS changed
1.13
3.55 3.63
4.15 4.21
0.00
1.00
2.00
3.00
4.00
5.00
6.00
7.00
8.00
GF MIXER K-LINE SAND PLANT 28CFT SUPERTUMBLAST SHOT
BLAST
BMD MOULDING DRAG CIF NEW SAND PLANT
Top m/c With lowest MTBF(Foundry)
D
a
y
s
Sand accumulation prob
Main chain driving shaft damage
Shaft & spockit changed
427 belt damage
Belt changed427 belt damage
Belt changed
Spindle speed problem
Replaced speed changing coil
Machine stabilizer problem
Check stabilizer & repaired
Sliding door problem
Replaced door bearing
9. This is a proprietary document of Kirloskar Brothers Limited 915-Jan-17
Bar chart-MTTR
9
24.16
6.53 6.06 5.11
4.13
1
6
11
16
21
26
KBL 46” VTL MAZAK
MULTIPLEX
DOOSAN
HMC(SC)
HELLER 250 (KPD) MKL C-600(DB)
Top m/c With lowest MTTR(SMPD)
D
a
y
s
Door jamming problem
adjusted flow control valve
Hydraulic pump problem
Replaced hydraulic pump
235.35
157.00
27.06 27.06
9.45
-30.00
20.00
70.00
120.00
170.00
220.00
270.00
MOULDING M/C NO-1 FAME SHAKE OUT CUPOLA FURNACE NO 1 RAW MATERIAL FEEDING
SYSTEM FOR CUPOLA
PLATE CONVEYOR IN CIF
Top m/c With lowest MTTR(FOUNDRY)
D
a
y
s
259.24
115.16
10.50 9.17 7.01
0.00
50.00
100.00
150.00
200.00
250.00
300.00
STANKO VBM CARANAGI VBM TITAN 3300 VBM KBL 120 CNC YOUJI 2000(ATPD)
Top m/c With lowest MTTR(LPD)
D
a
y
s
I/o channel prob
SMPS changed
Spindle rotating problem
14. This is a proprietary document of Kirloskar Brothers Limited 1415-Jan-17
Cont..
24780
32250
35337
31738 31951
3726136774
33007
47264
20000
25000
30000
35000
40000
45000
50000
55000
Apr-16
May-16
Jun-16
Jul-16
Aug-16
Sep-16
Oct-16
Nov-16
Dec-16
MONTHS
K
W
H
Pump testing
155475
176718
161764
179422
186708
202614
189442
196630
202869
140000
160000
180000
200000
220000
240000
Apr-16
May-16
Jun-16
Jul-16
Aug-16
Sep-16
Oct-16
Nov-16
Dec-16
MONTHS
K
W
H
Compressor
7043 7097
7314 7379
7215
7673
8293
9053
9494
6000
6500
7000
7500
8000
8500
9000
9500
10000
Apr-16
May-16
Jun-16
Jul-16
Aug-16
Sep-16
Oct-16
Nov-16
Dec-16
MONTHS
Street light
K
W
H
87746
248580
96281
272213263556
230795
326000
256628
299432
30000
80000
130000
180000
230000
280000
330000
380000
Apr-16
May-16
Jun-16
Jul-16
Aug-16
Sep-16
Oct-16
Nov-16
Dec-16
MONTHS
K
W
H
Others
15. This is a proprietary document of Kirloskar Brothers Limited 1515-Jan-17
Pareto chart for power consumption
15
864502
202869
171534 163632
140611 127898
48157 47264
9494
0.00
20.00
40.00
60.00
80.00
100.00
120.00
0
100000
200000
300000
400000
500000
600000
700000
800000
900000
1000000
Power
consumption
16. This is a proprietary document of Kirloskar Brothers Limited 1615-Jan-17
16
4139
4630
3060
3874
4519
3090
3350
3085
3628
3128
0
500
1000
1500
2000
2500
3000
3500
4000
4500
5000
5500
Apr-16 May-16 Jun-16 Jul-16 Aug-16 Sep-16 Oct-16 Nov-16 Dec-16
KWH
Consumption pattern per million
Units/million sale
Bench mark
717.2
636.9
486.4
572.5
467.2
533.9
657.4
529.7 526.2
863
0.0
100.0
200.0
300.0
400.0
500.0
600.0
700.0
800.0
900.0
1000.0
Apr-16 May-16 Jun-16 Jul-16 Aug-16 Sep-16 Oct-16 Nov-16 Dec-16
KWH
Consumption pattern per pump
Units/pump sale
Bench mark
Electricity consumption pattern
17. This is a proprietary document of Kirloskar Brothers Limited 1715-Jan-17
• Titan 2700 vertical screw nut replaced by new one & hard limit dog position corrected to seize heavy oil leakage.
• Titan CNC lubrication pressure low alarm problem corrected by replacing PLC card.
• Carnaghi CNC Z ball screw was jammed. Ball screw repaired & fitted in machine.
• 9B Lathe new rack & pinion fitted.
• Spm boring contractor replaced.
• FN3 milling noise problem solved.
• Kws 500 new telescopic cover fitted.
• Norton grinder gear box piston was damaged, New piston was prepared in house and fitted in machine.
• Woton stabilizer starting in auto mode work completed.
• VBM-150(MF) spindle disc spring replaced.
• New sliding rack & pinion fitted in 9B lathe
• Dyna-65 x & z axis ball screw overhauled.
• NFF furnace lied cover repair & refitted.
• Supetumblast machine main chain driving shaft and sprocket changed.
• Tata shakeout overhauled.
• GF mixer gear box hollow shaft changed.
• K-Line sand plant Magnet belt changed.
• 426 idler pulley remove, rework & fitted.
• 436 belt drive end pulley remove rework & fitted.
• 427 belt replaced
• 116 belt replaced
• cupola no 1 CI bricks lining done
• Arp BMD 1300 cope new scraper ring & guide bar bush fitted.
17
Major work
18. This is a proprietary document of Kirloskar Brothers Limited 1815-Jan-17
Improvement
18
• Stanko VBM gear box & spindle motor overhauled.
• Youji 2000 motor overloading ,ATC over travelled & lubrication pressure problems are permanently solved.
• Pensotti CNC lubrication made functional.
• 52” VTL panel reconditioning work started.
• 437 Elevator Belt replaced by light weight SS fabricated Bucket in K-line.
• Omega Sand Mixer(HF) arm made motor driven for movement.
• Teflon scraper inserted to minimize sand contact to Table of BMD ARPA1300 & KBMD 450 Molding Machines.
• Doosan(SC) oil leakage arrested.
• Emergency stop problem solved in mazak multiplex.
• Miven 500(DB) oil leakage from pump arrested.
• KWS-500(SC) oil leakage arrested.
19. This is a proprietary document of Kirloskar Brothers Limited 1915-Jan-17
Encon
• Replacement of 30 nos of 67W PL lamps with 30 nos of 30W LED lamps.
• Rescheduling of heavy foundry and HRC to maximize “A” zone utilization.
• Introduction of cold washing