The work process is characterized by the following basic steps:
1) Identification and notification of a potential change
2) Preparation and verification of the change report
3) Review of change request by other affected areas
4) Review of change request by quality department
5) Approval of the change report
6) Approved change request
7) Rejected change request
8) Planning and implementation of change
9) Closure of change request
10) Follow up actions
This document is a project charter that outlines the scope, objectives, risks, and management approach for an unnamed project. It includes sections that define the background, objectives, success criteria, scope across processes, organizations, locations, applications and data, assumptions, constraints, risks and mitigation strategies, documentation, timeline, and management roles. The project charter establishes a baseline for tracking work activities and managing the scope, schedule and budget of the project.
Change Management is the process of monitoring and controlling changes within a project to reduce impacts, identify new issues and risks, ensure objectives are still achievable, and control costs. It begins with documenting change requests, which are then reviewed by the Project Manager to determine if the change is critical. Critical changes are approved by the Project Board and implemented according to the project schedule. Finally, the Project Manager reviews implemented changes to ensure desired outcomes were achieved before closing the change request.
The document outlines the objectives and schedule for Module 3 of a Project Management course. Module 3 focuses on planning and cost management techniques. It will include reviewing case studies, presentations of case study work, and sessions on contract management, cost control, claims and change management, and cash flow. The schedule provides details of the topics and activities to be covered each day for both planners and cost controllers.
The document outlines a quality management process for a project. It involves establishing quality criteria and standards, measuring the quality of deliverables, and enhancing quality. Key steps include identifying quality targets, quality assurance techniques like audits and reviews, quality control techniques like testing and inspections, addressing any deficiencies found, and reporting on quality achieved. Quality roles include a quality manager responsible for the quality system and quality reviewers who assess deliverables.
This document provides a change management plan template for the Inventory Services Project. It outlines the change management approach, definitions of change, roles of the Change Control Board, and the change control process. The change management approach ensures all proposed changes are properly defined, reviewed, approved, implemented, and communicated. The change control board reviews and approves or denies all change requests. The change control process involves identifying needs, logging requests, submitting to the board, obtaining a decision, and implementing any approved changes.
The document discusses establishing an effective change control process for construction projects. It emphasizes that changes should be minimized but rigorously controlled. It outlines establishing a change control strategy early, defining the process, documenting it, establishing a log to track changes, agreeing whether changes are acceptable, and reporting costs with agreed changes. The key aspects of the change control process are defining the baseline, tracking changes, approving or rejecting changes, adjusting budgets and schedules, and regularly reporting on changes.
This document provides information about quality management procedures including forms, tools, and strategies. It discusses the purpose and requirements of quality management procedures such as having quality objectives and using procedures/deliverables like a project management plan, communication management procedure, risk management procedure, and checklists. Quality management tools explained include check sheets, control charts, Pareto charts, scatter plots, Ishikawa diagrams, and histograms. Other related topics like quality management systems and standards are also listed.
This Quality Assurance Plan outlines the processes and procedures to ensure quality in a software project. It includes sections on quality objectives, management tasks and responsibilities, documentation requirements, standards, metrics, reviews, testing, problem resolution, tools, configuration management, subcontractor controls, records, training, and risk management. The plan references various other project documents and artifacts to define its scope and how quality assurance activities are integrated into the project lifecycle.
This document is a project charter that outlines the scope, objectives, risks, and management approach for an unnamed project. It includes sections that define the background, objectives, success criteria, scope across processes, organizations, locations, applications and data, assumptions, constraints, risks and mitigation strategies, documentation, timeline, and management roles. The project charter establishes a baseline for tracking work activities and managing the scope, schedule and budget of the project.
Change Management is the process of monitoring and controlling changes within a project to reduce impacts, identify new issues and risks, ensure objectives are still achievable, and control costs. It begins with documenting change requests, which are then reviewed by the Project Manager to determine if the change is critical. Critical changes are approved by the Project Board and implemented according to the project schedule. Finally, the Project Manager reviews implemented changes to ensure desired outcomes were achieved before closing the change request.
The document outlines the objectives and schedule for Module 3 of a Project Management course. Module 3 focuses on planning and cost management techniques. It will include reviewing case studies, presentations of case study work, and sessions on contract management, cost control, claims and change management, and cash flow. The schedule provides details of the topics and activities to be covered each day for both planners and cost controllers.
The document outlines a quality management process for a project. It involves establishing quality criteria and standards, measuring the quality of deliverables, and enhancing quality. Key steps include identifying quality targets, quality assurance techniques like audits and reviews, quality control techniques like testing and inspections, addressing any deficiencies found, and reporting on quality achieved. Quality roles include a quality manager responsible for the quality system and quality reviewers who assess deliverables.
This document provides a change management plan template for the Inventory Services Project. It outlines the change management approach, definitions of change, roles of the Change Control Board, and the change control process. The change management approach ensures all proposed changes are properly defined, reviewed, approved, implemented, and communicated. The change control board reviews and approves or denies all change requests. The change control process involves identifying needs, logging requests, submitting to the board, obtaining a decision, and implementing any approved changes.
The document discusses establishing an effective change control process for construction projects. It emphasizes that changes should be minimized but rigorously controlled. It outlines establishing a change control strategy early, defining the process, documenting it, establishing a log to track changes, agreeing whether changes are acceptable, and reporting costs with agreed changes. The key aspects of the change control process are defining the baseline, tracking changes, approving or rejecting changes, adjusting budgets and schedules, and regularly reporting on changes.
This document provides information about quality management procedures including forms, tools, and strategies. It discusses the purpose and requirements of quality management procedures such as having quality objectives and using procedures/deliverables like a project management plan, communication management procedure, risk management procedure, and checklists. Quality management tools explained include check sheets, control charts, Pareto charts, scatter plots, Ishikawa diagrams, and histograms. Other related topics like quality management systems and standards are also listed.
This Quality Assurance Plan outlines the processes and procedures to ensure quality in a software project. It includes sections on quality objectives, management tasks and responsibilities, documentation requirements, standards, metrics, reviews, testing, problem resolution, tools, configuration management, subcontractor controls, records, training, and risk management. The plan references various other project documents and artifacts to define its scope and how quality assurance activities are integrated into the project lifecycle.
The document discusses preconstruction coordination and project management planning. It covers establishing communication protocols, reviewing contracts and schedules, coordinating with stakeholders, and organizing job files and record keeping. The project manager takes a leadership role to plan the project, monitor progress, control costs, and coordinate all parties. An effective communication system and weekly meetings are key to project coordination.
The document outlines the key roles and responsibilities in the change management process. The project team recognizes needed changes and submits change request forms to the project manager. The project manager investigates changes, requests approval from the project board, implements approved changes, and closes changes. The project board reviews changes, approves or denies requests based on individual merits, and identifies actions to implement approved changes. The process utilizes change request forms and a change register document.
Control is one of the key functions of any management process. The uncontrolled or unexamined project is not worth much. However effective the project plan may be without regular reviews during the life of the project neither the project progress nor the reality of the plan can be assessed. An effective and efficient control system enables! the project manager to answer the question. "How are we doing on the project ?" at any stage of the project.
According to Henry Fayol "The control means seeing that everything occurs in conformity with established rules and expressed command."
The document provides a cost management plan for the construction of a scrap tire recycling plant. It outlines the project's cost management approach, how costs will be measured using earned value management, the reporting format, cost variance response process, and cost change control process. It also includes the overall budget of $5 million for the project which is broken down into categories such as land procurement, architectural development, construction, project closeout, construction administration, and contingency surplus. The total projected cost is $4.98 million.
The document discusses monitoring and controlling construction projects. It describes monitoring as collecting and measuring performance information to assess results, while controlling involves taking corrective or preventive actions. The key aspects that must be monitored and controlled are project scope, time/schedule, cost, and quality. This includes tracking progress, managing changes, updating plans and documents, and identifying variances. The roles and responsibilities of the project manager, project team, client, consultants and contractors are also outlined.
The document provides guidance for planning building services activities within a construction project. It describes the processes involved in engineering, construction, and testing & commissioning of various building service disciplines such as mechanical, electrical, plumbing, and fire fighting systems. The manual is organized into 12 sections that provide information on activity breakdown structures, activity flow diagrams, relationships between building services and civil activities, installation guides, material procurement, and equipment information to assist planning and program managers.
Lecture slides4; Construction Project PlanningJB Nartey
Here is a draft WBS, Method Statement and Gantt Chart for the water pipe laying project:
WBS:
1.0 Water Pipe Laying Project
1.1 Pre-Construction
1.1.1 Purchase materials and equipment
1.1.2 Develop health and safety plan
1.2 Construction
1.2.1 Mobilization
1.2.2 Excavate trench
1.2.3 Lay pipe
1.2.4 Backfill trench
1.2.5 Test pipe
1.2.6 Demobilization
Method Statement:
1. Mobilize equipment such as excavator, compactor, welding equipment
2. Mark out trench
The document outlines the audit process which typically includes 4 stages - planning, fieldwork, audit report, and follow-up review. During planning, the auditor notifies the client, discusses objectives and scope, and plans remaining steps. Fieldwork involves transaction testing, communications, and working papers. The final audit report is then issued along with a follow-up review approximately one year later to verify resolution of any findings.
EXTENSION OF TIME CLAIMS IN OIL AND GAS CONSTRUCTION PROJECTSHossamNegidaPMPRMPPS
This document is dedicated to projects especially in Oil and Gas field wherein, in light of rapid and continuous development of the construction process and under intense competition in order to acquire reasonable profits, they are facing naturally lot of delays and disruptions which lead to exert huge efforts for proving these delays.
CJM Construction Consulting is a unique global construction management and consulting firm that performs construction management, project estimating, energy efficiency & sustainability consulting, disaster recovery, contractor/supplier vetting, and facility condition assessment for a variety of high-profile clients. We perform general construction and high voltage project estimating and quantity take-off for construction projects and clients all over the globe.
The document outlines a human resource plan for a "Smart Homes" project. It includes roles and responsibilities for team members, a project organization chart, and a staffing management plan covering how resources will be acquired and trained, performance reviews, and a recognition and rewards system. Key roles include a project manager, architect, structural engineer, interior decorator, procurement manager, and accountant. A resource histogram shows projected work hours needed over the course of the project timeline.
This document discusses project control and management. It defines a project as a temporary endeavor with a defined start and end, undertaken to meet unique goals. Project management is the process of planning, organizing, motivating and controlling resources to achieve specific goals. Project control refers to management actions to achieve desired results or corrective measures prompted by monitoring. The key steps in project control are project planning, project execution, and project evaluation. Project planning involves scope, schedule, cost, and risk analysis. Project execution involves comparing actual performance to estimates. Project evaluation assesses management performance, cost overruns, lessons learned, and whether objectives were achieved.
This document discusses project control and monitoring for construction management. It begins with an introduction of the presenter and defines project control as monitoring and controlling processes to track, review, and regulate a project's progress and performance. It then discusses key aspects of project control like what to monitor and control, who is responsible, and documents used. Specific project aspects that are monitored are performance, time/schedule, and cost. Resources available for project control are also outlined as money, manpower, materials, and machinery. The document concludes with discussing elements of project control like re-allocating resources, and mechanisms used like cybernetic, go/no-go, and post-control approaches.
Construction planning - Construction Technology and Project Managementsrinivas2036
The document discusses construction project planning. It defines planning as developing a method or scheme in advance. Construction planning involves optimally utilizing resources like people, equipment, materials and money. Key activities in construction planning include defining the scope of work, identifying involved activities, establishing project duration, defining resource control procedures, and updating plans. Different types of project plans may focus on schedule, cost, quality or safety. Techniques used in planning include work breakdown structure, precedence, network logic and critical path method.
The document is a Software Quality Assurance Plan (SQAP) for the Smith Jones Rapid Transit (SJ-RT) project. It outlines the SQA roles, standards and processes that will be followed, including in-stage audits, stage exit reviews, and verification and validation of requirements. The SQA consultant will audit project deliverables and work products at key milestones to ensure quality.
1) The document provides an overview of the Control Procurements process, which involves managing procurement relationships, monitoring contract performance, and making changes as needed. It describes the inputs, tools and techniques, and outputs of the process. 2) The inputs include the project management plan, project documents, agreements, procurement documentation, approved change requests, and work performance data. Tools include expert judgment, claims administration, data analysis, inspection, and audits. 3) The outputs include closed procurements, work performance information, procurement documentation updates, change requests, project management plan updates, and organizational process assets updates.
CDS Construction Execution Process ^0 StrategyRobert Doig
The document outlines the key stages and milestones in developing a construction execution plan for an engineering project from early design through construction completion. It includes: 1) Defining the work breakdown structure and construction areas in early design; 2) Developing construction planning documents like the quality plan and execution strategy in front-end engineering design; 3) Contractors providing detailed cost estimates, schedules and execution plans before starting construction; 4) Contractors reporting on progress, quality and costs during construction; and 5) Completing construction and turning the project over once complete. The overall process focuses on work planning, quality control, and performance monitoring to deliver the project on schedule and budget.
13 project control & closing managementDhamo daran
This document discusses project control and closing processes. It describes monitoring project work, which involves tracking performance against the project plan and identifying variances. It also discusses administering procurements, including monitoring vendor work and conducting procurement reviews. The document outlines reporting project performance through tools like variance analysis and communication methods. Finally, it describes closing the project through activities like getting customer acceptance, releasing resources, and creating a final report with an executive summary and lessons learned.
Aew Sanmai is seeking a position as a Project Controls Engineer or Cost Controller in the oil and gas industry, leveraging over 9 years of experience in project controls, cost estimating, accounting, and construction support. They have extensive skills in cost control, contract administration, financial analysis, and project management software for oil and gas projects ranging from $5M to $1B+. Aew holds certifications in accounting, administration, Oracle, SAP, and Microsoft applications.
The document discusses establishing an effective change control process for construction projects. It emphasizes that changes should be minimized but rigorously controlled. It outlines establishing a change control strategy early, defining the process, documenting it, establishing a log to track changes, agreeing whether changes are acceptable, and reporting costs with agreed changes. The key aspects of the change control process are defining the baseline, tracking changes, approving or rejecting changes, adjusting budgets and schedules, and reporting on changes regularly.
This is PMBOK Guide Monitor and Control Process Group - Part One. It includes three Knowledge Area - Project Integration Management, Project Scope Management, and Project Quality Management - with five processes - Monitor & Control Project Work, Perform Integrated Change Control, Validate Scope, Control Scope, Control Quality -.
The document discusses preconstruction coordination and project management planning. It covers establishing communication protocols, reviewing contracts and schedules, coordinating with stakeholders, and organizing job files and record keeping. The project manager takes a leadership role to plan the project, monitor progress, control costs, and coordinate all parties. An effective communication system and weekly meetings are key to project coordination.
The document outlines the key roles and responsibilities in the change management process. The project team recognizes needed changes and submits change request forms to the project manager. The project manager investigates changes, requests approval from the project board, implements approved changes, and closes changes. The project board reviews changes, approves or denies requests based on individual merits, and identifies actions to implement approved changes. The process utilizes change request forms and a change register document.
Control is one of the key functions of any management process. The uncontrolled or unexamined project is not worth much. However effective the project plan may be without regular reviews during the life of the project neither the project progress nor the reality of the plan can be assessed. An effective and efficient control system enables! the project manager to answer the question. "How are we doing on the project ?" at any stage of the project.
According to Henry Fayol "The control means seeing that everything occurs in conformity with established rules and expressed command."
The document provides a cost management plan for the construction of a scrap tire recycling plant. It outlines the project's cost management approach, how costs will be measured using earned value management, the reporting format, cost variance response process, and cost change control process. It also includes the overall budget of $5 million for the project which is broken down into categories such as land procurement, architectural development, construction, project closeout, construction administration, and contingency surplus. The total projected cost is $4.98 million.
The document discusses monitoring and controlling construction projects. It describes monitoring as collecting and measuring performance information to assess results, while controlling involves taking corrective or preventive actions. The key aspects that must be monitored and controlled are project scope, time/schedule, cost, and quality. This includes tracking progress, managing changes, updating plans and documents, and identifying variances. The roles and responsibilities of the project manager, project team, client, consultants and contractors are also outlined.
The document provides guidance for planning building services activities within a construction project. It describes the processes involved in engineering, construction, and testing & commissioning of various building service disciplines such as mechanical, electrical, plumbing, and fire fighting systems. The manual is organized into 12 sections that provide information on activity breakdown structures, activity flow diagrams, relationships between building services and civil activities, installation guides, material procurement, and equipment information to assist planning and program managers.
Lecture slides4; Construction Project PlanningJB Nartey
Here is a draft WBS, Method Statement and Gantt Chart for the water pipe laying project:
WBS:
1.0 Water Pipe Laying Project
1.1 Pre-Construction
1.1.1 Purchase materials and equipment
1.1.2 Develop health and safety plan
1.2 Construction
1.2.1 Mobilization
1.2.2 Excavate trench
1.2.3 Lay pipe
1.2.4 Backfill trench
1.2.5 Test pipe
1.2.6 Demobilization
Method Statement:
1. Mobilize equipment such as excavator, compactor, welding equipment
2. Mark out trench
The document outlines the audit process which typically includes 4 stages - planning, fieldwork, audit report, and follow-up review. During planning, the auditor notifies the client, discusses objectives and scope, and plans remaining steps. Fieldwork involves transaction testing, communications, and working papers. The final audit report is then issued along with a follow-up review approximately one year later to verify resolution of any findings.
EXTENSION OF TIME CLAIMS IN OIL AND GAS CONSTRUCTION PROJECTSHossamNegidaPMPRMPPS
This document is dedicated to projects especially in Oil and Gas field wherein, in light of rapid and continuous development of the construction process and under intense competition in order to acquire reasonable profits, they are facing naturally lot of delays and disruptions which lead to exert huge efforts for proving these delays.
CJM Construction Consulting is a unique global construction management and consulting firm that performs construction management, project estimating, energy efficiency & sustainability consulting, disaster recovery, contractor/supplier vetting, and facility condition assessment for a variety of high-profile clients. We perform general construction and high voltage project estimating and quantity take-off for construction projects and clients all over the globe.
The document outlines a human resource plan for a "Smart Homes" project. It includes roles and responsibilities for team members, a project organization chart, and a staffing management plan covering how resources will be acquired and trained, performance reviews, and a recognition and rewards system. Key roles include a project manager, architect, structural engineer, interior decorator, procurement manager, and accountant. A resource histogram shows projected work hours needed over the course of the project timeline.
This document discusses project control and management. It defines a project as a temporary endeavor with a defined start and end, undertaken to meet unique goals. Project management is the process of planning, organizing, motivating and controlling resources to achieve specific goals. Project control refers to management actions to achieve desired results or corrective measures prompted by monitoring. The key steps in project control are project planning, project execution, and project evaluation. Project planning involves scope, schedule, cost, and risk analysis. Project execution involves comparing actual performance to estimates. Project evaluation assesses management performance, cost overruns, lessons learned, and whether objectives were achieved.
This document discusses project control and monitoring for construction management. It begins with an introduction of the presenter and defines project control as monitoring and controlling processes to track, review, and regulate a project's progress and performance. It then discusses key aspects of project control like what to monitor and control, who is responsible, and documents used. Specific project aspects that are monitored are performance, time/schedule, and cost. Resources available for project control are also outlined as money, manpower, materials, and machinery. The document concludes with discussing elements of project control like re-allocating resources, and mechanisms used like cybernetic, go/no-go, and post-control approaches.
Construction planning - Construction Technology and Project Managementsrinivas2036
The document discusses construction project planning. It defines planning as developing a method or scheme in advance. Construction planning involves optimally utilizing resources like people, equipment, materials and money. Key activities in construction planning include defining the scope of work, identifying involved activities, establishing project duration, defining resource control procedures, and updating plans. Different types of project plans may focus on schedule, cost, quality or safety. Techniques used in planning include work breakdown structure, precedence, network logic and critical path method.
The document is a Software Quality Assurance Plan (SQAP) for the Smith Jones Rapid Transit (SJ-RT) project. It outlines the SQA roles, standards and processes that will be followed, including in-stage audits, stage exit reviews, and verification and validation of requirements. The SQA consultant will audit project deliverables and work products at key milestones to ensure quality.
1) The document provides an overview of the Control Procurements process, which involves managing procurement relationships, monitoring contract performance, and making changes as needed. It describes the inputs, tools and techniques, and outputs of the process. 2) The inputs include the project management plan, project documents, agreements, procurement documentation, approved change requests, and work performance data. Tools include expert judgment, claims administration, data analysis, inspection, and audits. 3) The outputs include closed procurements, work performance information, procurement documentation updates, change requests, project management plan updates, and organizational process assets updates.
CDS Construction Execution Process ^0 StrategyRobert Doig
The document outlines the key stages and milestones in developing a construction execution plan for an engineering project from early design through construction completion. It includes: 1) Defining the work breakdown structure and construction areas in early design; 2) Developing construction planning documents like the quality plan and execution strategy in front-end engineering design; 3) Contractors providing detailed cost estimates, schedules and execution plans before starting construction; 4) Contractors reporting on progress, quality and costs during construction; and 5) Completing construction and turning the project over once complete. The overall process focuses on work planning, quality control, and performance monitoring to deliver the project on schedule and budget.
13 project control & closing managementDhamo daran
This document discusses project control and closing processes. It describes monitoring project work, which involves tracking performance against the project plan and identifying variances. It also discusses administering procurements, including monitoring vendor work and conducting procurement reviews. The document outlines reporting project performance through tools like variance analysis and communication methods. Finally, it describes closing the project through activities like getting customer acceptance, releasing resources, and creating a final report with an executive summary and lessons learned.
Aew Sanmai is seeking a position as a Project Controls Engineer or Cost Controller in the oil and gas industry, leveraging over 9 years of experience in project controls, cost estimating, accounting, and construction support. They have extensive skills in cost control, contract administration, financial analysis, and project management software for oil and gas projects ranging from $5M to $1B+. Aew holds certifications in accounting, administration, Oracle, SAP, and Microsoft applications.
The document discusses establishing an effective change control process for construction projects. It emphasizes that changes should be minimized but rigorously controlled. It outlines establishing a change control strategy early, defining the process, documenting it, establishing a log to track changes, agreeing whether changes are acceptable, and reporting costs with agreed changes. The key aspects of the change control process are defining the baseline, tracking changes, approving or rejecting changes, adjusting budgets and schedules, and reporting on changes regularly.
This is PMBOK Guide Monitor and Control Process Group - Part One. It includes three Knowledge Area - Project Integration Management, Project Scope Management, and Project Quality Management - with five processes - Monitor & Control Project Work, Perform Integrated Change Control, Validate Scope, Control Scope, Control Quality -.
CHANGE MANAGEMENT PLAN TEMPLATEIntroductionStart the developme.docxcravennichole326
CHANGE MANAGEMENT PLAN TEMPLATE
Introduction
Start the development of your Project Change Management Plan with this template. Download the Microsoft Word version by clicking on the icon below. This template is completely free and is intended to support your project change management process.
Change Management is an important part of any project. Changes must be vetted and managed to ensure that they are within the scope of the project and are communicated to all stakeholders if they are approved. The process for submitting, reviewing, and approving changes must also be communicated to all stakeholders in order to properly set expectations. If changes are allowed to be submitted or are implemented in and unorganized way, any project is sure to fail. All projects must include a Change Management Plan as part of the overall Project Plan, it can either be included as a section in the Project Plan or as an appendix as a subsidiary management plan.
The Change Management Plan was created for the Inventory Services (IS) Project in order to set expectations on how the approach to changes will be managed, what defines a change, the purpose and role of the change control board, and the overall change management process. All stakeholders will be expected to submit or request changes to the IS Project in accordance with this Change Management Plan and all requests and submissions will follow the process detailed herein.
Change Management Approach
This section of the Change Management Plan describes the approach the organization will use for managing change throughout the project. Throughout a project’s lifecycle there may be very few or very many submitted changes. The approach taken to manage these changes must be consistent and repeatable in order to provide a quality change management plan and process.
The Change Management approach for the IS Project will ensure that all proposed changes are defined, reviewed, and agreed upon so they can be properly implemented and communicated to all stakeholders. This approach will also ensure that only changes within the scope of this project are approved and implemented.
The Change Management approach is not to be confused with the Change Management Process which will be detailed later in this plan. The Change Management approach consists of three areas:
· Ensure changes are within scope and beneficial to the project
· Determine how the change will be implemented
· Manage the change as it is implemented
The Change Management process has been designed to make sure this approach is followed for all changes. By using this approach methodology, the IS Project Team will prevent unnecessary change from occurring and focus its resources only on beneficial changes within the project scope.
Definitions of Change
This section of the Change Management Plan defines the different types of changes that may be requested and considered for the project. These changes may include schedule change, budget change, scope change, or pro ...
This change management plan outlines the process for managing changes to the Project Management Improvement, Phase 3 project. It defines the project constraints, items subject to change management, roles and responsibilities, and the five step change management process of submittal and logging, evaluation, decision, integration, and communication. The budgetary impact of changes is estimated to be between $250-$500, with approximately 5 change requests requiring 10-15 hours to evaluate and manage.
This document outlines a procedure for change control at an organization. It defines change control as a quality tool to maintain records of all changes as a history. Changes can relate to facilities, documentation, systems, equipment, instruments, procedures, layouts, and products. Changes are categorized as minor, major, or critical based on their impact. The change control process involves initiating a change, getting approvals from relevant departments, implementing the change, reviewing and closing out the change control. A numbering system is used to track changes and all records are maintained by the quality assurance department.
Lesson 4 Homework 100 points totalDue Tuesday October 18th, .docxLaticiaGrissomzz
This document outlines homework assignments for an IT auditing class. The first assignment asks students to describe what a data flow diagram is and why it is useful for IT auditing in two paragraphs. The second assignment asks students to explain computer-assisted audit techniques (CAATs) and their benefits in one paragraph. The third assignment asks students to describe two techniques CAATs use to define sample size and select samples in two paragraphs. The fourth assignment asks students to explain the importance of flowcharting as an audit analysis tool in one paragraph. The document also outlines a case study assignment on change control management processes due on a later date.
The document provides guidance on assisting with policy development for client support by outlining the steps for modifying a system according to requested changes. It describes leading practices for change management processes including defining change models, roles and responsibilities, the standard change process flow with activities like planning, testing, approval and documentation, as well as approaches for expedited and emergency changes. It stresses the importance of change management tools and implementing a process improvement program to continuously assess and enhance the change processes.
This document outlines a checklist and template for submitting project change requests. The checklist includes considerations for how the change may impact deliverables, requirements, procedures, and technical or client needs. The template requires a description of the change and reason for change, an analysis of the impact on the project schedule and costs, and approval signatures from the client, sponsor, technical lead, and project manager.
EXECUTION PLAN REVISION HISTORYVersion #Implemented byReBetseyCalderon89
EXECUTION PLAN REVISION HISTORY
Version #
Implemented by
Revision Date
Approved by
Approval Date
Reason
Table of Contents
1. PROJECT OVERVIEW
1.1 Purpose, Scope and Objectives, and Business Case
1.1.1 Scope
1.1.2 Statement of Work (SOW)
1.1.3 Business Case
1.2 Project Deliverables
1.3 Project Organization
1.4 Work Breakdown Structure (WBS)
1.4.1 Task description documentation
1.4.2 Organization Breakdown Structure (OBS)
1.5 Responsibility Assignment Matrix (RAM)
1.6 Work Authorization
1.7 Project Charter
2. RISK ASSESSMENT
2.1 Risk Identification
2.2 Assessment of Probability and Consequence (Qualitative)
2.3 Assessment of Probability and Consequence (Quantitative)
2.4 Mitigation Strategies
3. PROJECT SCHEDULE
3.1 Activity Duration Estimates
3.2 Gantt Chart
3.3 Activity Network
4. PROJECT BUDGET
4.1 Project Resources
4.2 Other costs
4.3 Cost estimates
4.4 Time-phased budget
5. COMMUNICATIONS MANAGEMENT
6. TRACKING AND STATUS UPDATES
6.1 Tracking method
6.2 Notification record
6.3 Control systems
7. PROJECT CLOSE-OUT
7.1 Close cost accounts
7.2 Lessons Learned
Project Overview—This section is intended to provide a brief background description of the project, including motivation, goals and objectives, success criteria by which it will be evaluated, major project deliverables, and identified constraints. See Chapter 5 for development of project scope.
1.1Purpose, Scope and Objectives, and Business Case—Describe the purpose of the project here. What are the key deliverables, that is, the major items to be delivered to the customer, other stakeholders, suppliers, or other parties?
1.1.1Scope—Describe the project scope in general terms. Include a problem statement, detailed steps in requirements gathering (who was consulted, when?), information gathering (critical features uncovered from investigation), project constraints, alternatives analysis, and business case documentation.
1.1.2Statement of Work (SOW)—Include a detailed SOW for the project. Include:
1. Key milestones
2. Resource requirements
3. Risks and concerns
4. Acceptance criteria
1.1.3Business Case—Insert the project Business Case here. You can find an explanation of the business case in Chapter 5. Briefly identify the business needs to be satisfied, the feasibility of the project, a description of internal and external forces likely to affect the project, a comparative analysis of the costs and benefits of this project over alternative solutions, and time estimates to return on investment. Identify how the satisfaction of business needs will be determined.
1.2Project Deliverables—List the major items or project features to be delivered to the client. Include sign-off documentation from client to demonstrate their concurrence with the deliverable set.
1.3Project Organization—Indicate all project team members, their specific roles, and project organization hierarchy. Where appropriate, indicate joint responsibility between project m ...
This document outlines a schedule management plan for a project. It defines the schedule management approach, including using a work breakdown structure and MS Project to develop the schedule. It establishes bi-weekly schedule reviews and thresholds for schedule change requests. Any changes exceeding 10% of a task duration or the overall schedule require sponsor approval. Scope changes may also require re-baselining the schedule.
The document discusses various topics related to project management including reasons for project termination, methods of project visualization, priorities for monitoring, change control procedures, software configuration management, stress management techniques, types of contracts, stages in contract placement, and the review process model. Key points include that reasons for project termination can include lack of resources, incomplete requirements, or obsolete technologies, and the termination process involves project surveys, debriefing meetings, and result publication. Project visualization methods include Gantt charts, slip charts, and timeline charts. Priorities for monitoring include critical path activities, activities with no free float, and high risk activities. The review process model involves planning, preparation, a review meeting, and rework stages.
How Implementing an effective Change Control process can have a positive impact on a project. This presentation will bring you through a step by step guide to accomplish this goal.
6 I need the overall earned value analysis. (That is, overall i.docxalinainglis
6 I need the overall earned value analysis. (That is, "overall" indicates do it once for the project as a whole, not for each individual task. Though doing it for each task would be acceptable if MSP does it for you, only the overall whole-project earned value calculations are indicated for this assignment. Do not do individual task calculations of EV by hand.) You may use MS Project to do so, if you can, or you can do it yourself with a pocket calculator or (probably better yet) do it yourself in Excel; you can use the formulas on the Gold Card or the formulas in my weekly Commentary, or the formulas in the textbook. Any way, you do it, you will get most of the data from your MSP .mpp, then plug it into the formulas.
The goal is to come up with EAC and Estimated Cost to Complete (ECTC), but you'll need to calculate the rest in order to get there, therefore please calculate and submit the following figures. They need not be in a MS Word attachment, but may be answered directly in your Assignments Folder posting, as you wish.
As in a math class, show your work, i.e., show your formulas, input data, and calculations as well as your results.
Include at least the following EV figures (you may include more if you wish):
· Original Budget at Completion (BAC) (baselined)
· New Estimate at Completion (EAC) (changed)
· New Estimated Cost to Complete (ECTC) (changed)
· Original Planned Value (PV, BCWS) (baselined)
· Actual Cost so far (AC, ACWP) (changed)
· Earned Value so far (EV, BCWP)
· Schedule Variance (SV)
· Cost Variance (CV)
· Schedule Performance Index (SPI)
· Cost Performance Index (CPI)
–Change Management Plan
1. Executive Summary
The team was tasked with expanding the dental practice of Marley Dental Clinic, an established dentist in a non-computerized office into a digitized, computer centric office with a management system where they will be able to view appointment schedule, x-ray, face images and other imaging applications as well as videos and scanned images, intraoral cameras and web technologies. It is important to consider how changes will be handled as they occur.
Changes within the project are probable, and the goal of this change management plan is to manage them in a way that creates the smallest ripple effect possible while still meeting project goals. Change procedures will be performed through Microsoft Project Server. In general, requests will be submitted by the individual teams based on incidents, assigned work, or special request, as dictated by the situation, and annotated in the ticket.
Each team manager will then review and approve or reject the change request. If approved, the request will be allocated hours and funding from the team’s core budget, and afforded a special budget if necessary. Once complete and implemented, the change will be closed, and the totals for man hours and budget will be quantified and listed for review by the higher management teams.
2. Change Management Plan
Methodology an.
Version #Implemented byRevision DateApproved byApproval Da.docxjessiehampson
Version #
Implemented by
Revision Date
Approved by
Approval Date
Reason
EXECUTION PLAN REVISION HISTORY
Table of Contents
1. 1. PROJECT OVERVIEW
1. 1.1 Purpose, Scope and Objectives, and Business Case
1. 1.1.1 Scope
2. 1.1.2 Statement of Work (SOW)
3. 1.1.3 Business Case
2. 1.2 Project Deliverables
3. 1.3 Project Organization
4. 1.4 Work Breakdown Structure (WBS)
1. 1.4.1 Task description documentation
2. 1.4.2 Organization Breakdown Structure (OBS)
5. 1.5 Responsibility Assignment Matrix (RAM)
6. 1.6 Work Authorization
7. 1.7 Project Charter
2. 2. RISK ASSESSMENT
1. 2.1 Risk Identification
2. 2.2 Assessment of Probability and Consequence (Qualitative)
3. 2.3 Assessment of Probability and Consequence (Quantitative)
4. 2.4 Mitigation Strategies
3. 3. PROJECT SCHEDULE
1. 3.1 Activity Duration Estimates
2. 3.2 Gantt Chart
3. 3.3 Activity Network
4. 4. PROJECT BUDGET
1. 4.1 Project Resources
2. 4.2 Other costs
3. 4.3 Cost estimates
4. 4.4 Time-phased budget
5. 5. COMMUNICATIONS MANAGEMENT
6. 6. TRACKING AND STATUS UPDATES
1. 6.1 Tracking method
2. 6.2 Notification record
3. 6.3 Control systems
7. 7. PROJECT CLOSE-OUT
1. 7.1 Close cost accounts
2. 7.2 Lessons Learned
1. Project Overview—This section is intended to provide a brief background description of the project, including motivation, goals and objectives, success criteria by which it will be evaluated, major project deliverables, and identified constraints. See Chapter 5 for development of project scope.
1. 1.1 Purpose, Scope and Objectives, and Business Case—Describe the purpose of the project here. What are the key deliverables, that is, the major items to be delivered to the customer, other stakeholders, suppliers, or other parties?
1. 1.1.1 Scope—Describe the project scope in general terms. Include a problem statement, detailed steps in requirements gathering (who was consulted, when?), information gathering (critical features uncovered from investigation), project constraints, alternatives analysis, and business case documentation.
2. 1.1.2 Statement of Work (SOW)—Include a detailed SOW for the project. Include:
· 1. Key milestones
· 2. Resource requirements
· 3. Risks and concerns
· 4. Acceptance criteria
3. 1.1.3 Business Case—Insert the project Business Case here. You can find an explanation of the business case in Chapter 5. Briefly identify the business needs to be satisfied, the feasibility of the project, a description of internal and external forces likely to affect the project, a comparative analysis of the costs and benefits of this project over alternative solutions, and time estimates to return on investment. Identify how the satisfaction of business needs will be determined.
2. 1.2 Project Deliverables—List the major items or project features to be delivered to the client. Include sign-off documentation from client to demonstrate their concurrence with the deliverable set.
3. 1.3 Project Organization—Indicate al ...
This document provides a project management plan template for the SmartVoice project. It includes sections on the project management approach, scope, milestones, schedule, change management, communications, cost, procurement, scope, schedule, quality, risk, staffing, resources, cost and quality baselines, and sponsor acceptance. The project manager, Joe Green, will be responsible for managing the project according to this plan and its subsidiary plans. The project involves developing new voice recognition software and will be completed when the software and documentation are transitioned to production.
Part Time):
Design, implement and maintain the telecommunications infrastructure.
Security Consultant (Full Time):
Design and implement security protocols and procedures.
IT Consultant (Full Time):
Design, implement and maintain the IT infrastructure and systems.
30
Staff Acquisition Process:
The Project Manager will be responsible for staffing the project team. The process is as
follows:
1. Define roles and responsibilities for project team positions.
2. Develop job descriptions for open positions.
3. Advertise openings and accept applications/resumes.
4. Review applications/resumes and select candidates to interview.
5.
Project change management is important to (1) identify potential problems and take corrective action, (2) ensure an accurate understanding of project progress, and (3) carefully manage changes by rejecting or approving changes and incorporating them into revised baselines. It determines where the project currently stands compared to plans and helps get a project back on track if needed. A change management procedure typically involves identifying needed changes, analyzing feasibility, obtaining approvals, implementing, and reviewing changes.
This document outlines a change management plan for a project. It describes the purpose of change management to ensure all changes are reviewed, approved, and communicated. It defines responsibilities for managing changes and a six step process for submitting, reviewing, approving, and implementing changes. This includes maintaining a log of change requests and notifying stakeholders of approved changes.
Similar to HOW TO ESTABLISH AN EFFECTIVE CHANGE MANAGEMENT (20)
Turner construction company: Turner is the leading builder of green buildings and has extensive experience across a wide variety of sustainable construction projects.
Porter’s Five Forces & competitive advantage.
As a leading construction company in the UAE, Arabtec’s major commitment is to build on experience and to expand using our capabilities and expertise in building high rise development, hotels, residential developments, commercial development, industrial projects, airport developments, stadiums, villa communities, entertainment and mixed use developments in the MENA region, Russia and across the globe.
ECONOMIC FOUNDATIONS OF BUSINESS AND MANAGEMENT "Activist fiscal policy in US"Alessandro Rinaldi
Activist Fiscal Policy.
During and after the “Great Recession” that began in December 2007 (according to the Business Cycle Dating Committee at the National Bureau of Economic Research), the U.S. federal government enacted several rounds of activist fiscal policy.
Short strategic analysis on costruction Industry focused on NCC DK construction company.
NCC is one of the leading construction and property development companies in the Nordic region. The Group had sales of SEK 58 billion in 2013, with approximately 18,500 employees.
Il risparmio energetico è una considerevole fonte di energia rinnovabile ed è anche la più
immediata ed accessibile a tutti, spesso con tempi di recupero dell’investimento inferiori a
qualunque tecnologia energetica e a cominciare da scale di investimento minime, anche di
poche centinaia di euro.
Dimensionamento di un sistema di movimentazione e stoccaggio dei materialiAlessandro Rinaldi
Il presente lavoro è orientato al dimensionamento di una soluzione impiantistica di un sistema di movimentazione e stoccaggio e allo studio ed implementazione di strategie per l’ottimizzazione dello stesso.
Specific ServPoints should be tailored for restaurants in all food service segments. Your ServPoints should be the centerpiece of brand delivery training (guest service) and align with your brand position and marketing initiatives, especially in high-labor-cost conditions.
408-784-7371
Foodservice Consulting + Design
Sethurathnam Ravi: A Legacy in Finance and LeadershipAnjana Josie
Sethurathnam Ravi, also known as S Ravi, is a distinguished Chartered Accountant and former Chairman of the Bombay Stock Exchange (BSE). As the Founder and Managing Partner of Ravi Rajan & Co. LLP, he has made significant contributions to the fields of finance, banking, and corporate governance. His extensive career includes directorships in over 45 major organizations, including LIC, BHEL, and ONGC. With a passion for financial consulting and social issues, S Ravi continues to influence the industry and inspire future leaders.
Employment PracticesRegulation and Multinational CorporationsRoopaTemkar
Employment PracticesRegulation and Multinational Corporations
Strategic decision making within MNCs constrained or determined by the implementation of laws and codes of practice and by pressure from political actors. Managers in MNCs have to make choices that are shaped by gvmt. intervention and the local economy.
A presentation on mastering key management concepts across projects, products, programs, and portfolios. Whether you're an aspiring manager or looking to enhance your skills, this session will provide you with the knowledge and tools to succeed in various management roles. Learn about the distinct lifecycles, methodologies, and essential skillsets needed to thrive in today's dynamic business environment.
Colby Hobson: Residential Construction Leader Building a Solid Reputation Thr...dsnow9802
Colby Hobson stands out as a dynamic leader in the residential construction industry. With a solid reputation built on his exceptional communication and presentation skills, Colby has proven himself to be an excellent team player, fostering a collaborative and efficient work environment.
12 steps to transform your organization into the agile org you deservePierre E. NEIS
During an organizational transformation, the shift is from the previous state to an improved one. In the realm of agility, I emphasize the significance of identifying polarities. This approach helps establish a clear understanding of your objectives. I have outlined 12 incremental actions to delineate your organizational strategy.
Integrity in leadership builds trust by ensuring consistency between words an...Ram V Chary
Integrity in leadership builds trust by ensuring consistency between words and actions, making leaders reliable and credible. It also ensures ethical decision-making, which fosters a positive organizational culture and promotes long-term success. #RamVChary
Org Design is a core skill to be mastered by management for any successful org change.
Org Topologies™ in its essence is a two-dimensional space with 16 distinctive boxes - atomic organizational archetypes. That space helps you to plot your current operating model by positioning individuals, departments, and teams on the map. This will give a profound understanding of the performance of your value-creating organizational ecosystem.
3. 3
DESCRIPTION OF ACTIVITIES
The work process is characterized by the following basic steps:
1) Identification and notification of a potential change
2) Preparation and verification of the change report
3) Review of change request by other affected areas
4) Review of change request by quality department
5) Approval of the change report
6) Approved change request
7) Rejected change request
8) Planning and implementation of change
9) Closure of change request
10) Follow up actions
The operating practices and responsibilities for each of the above-mentioned steps are described in
the following sections.
1) IDENTIFICATION AND NOTIFICATION OF A POTENTIAL CHANGE
Any member of a project team can request a change whenever there is a deviation or have identified
a problem or an improvement opportunity by reporting the situation to his immediate supervisor or
Project Manager. This also shall be a permanent item into the weekly department HSE meetings.
Another source for changes can be the Non Conformances raised as audits result that will require
adjustments in procedures and/or documents based on regulations or technical requirements.
Due to the importance of properly tracking the Changes, the Project manager is responsible for the
correct definition and implementation of the process with the support of the Sponsor since the
project start up. All the members of the Project Team shall be made fully aware of the paramount
importance of properly detecting, managing and tracking all the Remarkable Changes occurring
during the project life and in particular if deliverables have been already issued as “Approved for
Design” or information have been frozen. The project manager will ensure the applicability of a
change request at project level guaranteeing that Changes are promptly identified and tracked.
4. 4
Identification and notification of the occurrence involving a potential Change is ensured by each
team member. Project manager analyzes the occurrence and decides if it requires issuing a Change
Report.
For example, the following events should normally result in a Change:
Requests by Client or Sponsor causing a Change to the contractual scope of work, to the
strategy already defined and implemented or to the schedule;
Changes in the split of scope of work among partners;
Changes in the strategy, materials or services supply, that were defined in the bidding phase
and constituted the basis for building-up the budget, due to:
- Contract document review with effects on existing strategy;
- Review from which better solutions emerge;
- Review from which internal errors or underestimates emerge;
- Detection of supply nonconformities;
- Discovery of problems in the project;
Work sequences or operating practices different from those planned;
Changes or delays in the activities of a discipline that significantly affect the activities of
other disciplines;
revision of documents that have been subjected to the freezing procedure and have been
already frozen;
revision of documents corresponding to phase of the project already complete;
reworks due to configuration errors;
modifications due to vendors;
Modifications due to executing functions.
In case a project function other than the sponsor originates the Change, the originating function
notifies the need of the Change and the change control board activates the Change Management
procedure.
Project manager and Sponsor, together with the project organization positions affected by the
Change, define the impact on the project in terms of both costs and time.
5. 5
2) PREPARATION AND VERIFICATION OF THE CHANGE REPORT
On receipt of a Change Request the Project Manager shall perform an appraisal to the change
request to assess whether the change is necessary and applicable; if it is then he will issue a report
the Change Request to other affected Areas Managers, quality department, sponsor and
management.
The following aspects shall be considered:
Identify items and areas affected by the change;
Report to HSE Area about the change requirement and get the identification number for the
change requirement form;
Check whether procedures or work instructions need to be revised as a result of the change;
Identify technical requirements;
Identify additional personnel training requirements;
Require the additional affected areas their validation for the change (including client and
third party companies depending on the change effect), by sending them copy of the Change
Request;
Perform with the related areas and positions the Risk Assessment for the proposed change;
Review and update documents for those operations that will be affected with the change,
including the new conditions when introduced with the change.
Communicate the change requirement with the complementary information to Quality and
HSE areas for review and approval consideration.
Once the project manager has established that an occurrence results in a potential Change, he
ensures the preparation of the relevant Change Report and notifies all the impacted functions of the
project.
Project manager generating the Change shall fill in the form, including the collection of any
necessary related information from other project organization positions affected by the Change. The
Change Report shall summarize the items resulting from the Change and the relevant impacts in
terms of quantity, resource, cost and shall indicate whether the Change entails a Contract Change or
not.
The Change Report and the supporting documentation shall be verified and signed by Change
Control Board and then transmitted to project manager for approval. Project manager shall record
the Change as “in progress” in the Change Log.
6. 6
The quality department, supported by the Project HSE team, shall review the Change Log and the
Change Reports and fill the “HSE Impact” field in the form, to highlight any impact related to HSE
issues and identify the need for any corrective action or preventing or mitigating measures.
If the Change also entails a Contract Change, Sponsor, project manager and Contract Administrator
shall ensure, within their fields of expertise and with support from the Project Team, the preparation
of the necessary documentation for developing the Contract Change and shall support the project
functions in charge of the negotiation phase with the Client, Partner or third parties.
Whenever during the analysis the change is qualified as non-applicable, the result will be
documented, recorded on a form and a report will be done to the originator. Once the required
change has been authorized, the Project manager will implement all the required conditions for the
change to be effective, monitor the execution and feedback on the results after the change
application. For the temporary changes will keep close monitoring to maintain safe conditions
during operations. If the change is denied the Project manager will feedback the originator with the
relevant information for that decision, in any case will updated the format for Change Request Log.
3) REVIEW OF CHANGE REQUEST BY OTHER AFFECTED AREAS
Any proposed change can affect more than one area (location, procedures or personnel), in these
cases each area will be contacted and the area leader or manager will receive a copy of the change
requirement form already containing the information related to the change request, the affected
Area Manager shall:
Check the change requirement and identify the specific locations, procedures, documents,
equipment, materials or personnel under his area of responsibility will be affected.
Perform a risk assessment for the change and identify preventive actions to allow the
change, if acceptable.
Document the area analysis and decision on the change requirement form attaching all
relevant documents to be taken into account in order to apply the change in a safe manner
or reasons for deny the requirement and sign the requirement recording the decision.
Communicate the change requirement decision to the Project Manager who did the
requirement by signing on the Change Requirement Form.
7. 7
4) REVIEW OF CHANGE REQUEST BY QUALITY DEPARTMENT
Any change request must be reported to Quality Department in order to identify and verify different
documents, procedures, codes, etc. need to be taken in account during the change evaluation and
decision making process.
Quality function will report the different involved areas the necessary procedures adjustments
resulting from the proposed change, as well as any additional related technical consideration to be
validated during the process.
5) APPROVAL OF THE CHANGE REPORT
Project manager, assisted by the team members, the project control manager and the responsible of
the project functions impacted by the Change, shall analyze promptly the proposed Change Report
and, if deemed necessary, can revise the report updating the actions to be taken and the estimated
impacts in terms of costs and schedule.
Upon completion of the analysis and after obtaining any authorizations needed from the Client or
Sponsor (when necessary), project manager authorizes the Change by approving the document. A
copy of the document is sent to the concerned positions within the project organization.
Any activities related to the Change can’t be performed prior to project manager approval.
On receipt of communication related to the Change Request by the Project Manager, HSE function
shall:
Record the Change Requirement on the correspondent form Change Requirement Log.
Report to HSE Management the requirement for analysis and comments.
Advice Project Management on HSE aspects related with the change request.
Identify the need for detailed and multidisciplinary Risk Assessment and get involved in it.
Report the change requirement to the correspondent safety delegate for his comments.
6) APPROVED CHANGE REQUEST
Once the change request has been approved, the project manager shall ensure that all identified
previous requirements from different areas, necessary precautions and actions are taken to reduce or
minimize any risks incurred by the change implementation.
8. 8
The actions taken may include the amendment of a procedure or a work instruction and to
communicate this to relevant personnel, or it may mean that a meeting needs to be held to inform all
concerned parties of the impact of the change.
It also means that risk assessment analyses needs to be performed or updated with control measures
identified and implemented to minimize an risks represented by the change.
Particularly for operational, technical changes, the different area leaders should assist on the change
implementation for a final validation on conditions and arrangements prior to start the operation
under the new conditions.
7) REJECTED CHANGE REQUEST
A rejected change request shall be discussed with the originator or person who submitted it. The
reasons for the rejection shall be detailed on the change request and the Change request Register
updated. This feedback also shall be included on the department weekly meetings.
8) PLANNING AND IMPLEMENTATION OF CHANGE
Once the Change Request is approved, the implementation of the Changes is planned by the
concerned positions within the Project Team under project manager coordination and supervision.
Project manager keeps updated the Change Log. A copy of the log shall be distributed regularly to
project manager, project control, contract manager and contract administrator. The concerned
positions within Project Team will be in charge of implementing the necessary actions under the
supervision of the project manager. The project manager will be in charge of following up all
planned actions until their closure. When all necessary actions have been implemented, project
manager updates the Change status as “closed” in the Change Log.
9) CLOSURE OF CHANGE REQUEST
The project manager shall document on the change request a brief evaluation of the applied change
and any additional information related with the final implementation as additional measures taken
or specific points to monitor and feedback all the involved areas, with this final feedback the change
will be considered closed. Temporary changes must have a defined revision frequency and deadline
to return to a normal condition. Once the change is removed and back to normal condition, this also
9. 9
must be communicated to all personnel involved and included also on the welcome on board update
for the different crews.
10) FOLLOW UP ACTIONS
Based on the approval process requirements for the change implementation HSE and QAQC
functions on the location will include the specific conditions into the regular area inspections in
order to ensure proper follow up to those conditions and any other unidentified hazard that could
appear after the change implementation.