SlideShare a Scribd company logo
HANDLING THE PUNCH LIST
SATISFYING CUSTOMERS AFTER THE INSTALLATION IS DONE
DEFINITION OF PUNCH LIST
 A punch list is the “snag” list. After an installation ( of any kind ), upon inspection the customer and the
contractor, developer, integrator; must agree on the outcome. Ideally, there should have been an end
objective that was agreed upon. If the contractor has not met that objective, or there are known
deficiencies, a punch list is created and it gives the customer a tool to track progress.
 On the other hand, the contractor needs to use the punch list as a springboard for engineering changes,
which would generate positive business for the contractor. Ie, did the customer change their mind.
Does the customer have additions? Does this create a new business cycle?
 Reference: Punch List 101 | Fieldwire
 How does this apply to control systems integrators?
PUNCH LIST 101
Objectives of the Punchlist:
1. Convey non-conformities.
2. Give a tool for customer/integrator interface.
3. Provide clear objectives with an assignment and an end date.
4. Reference back to original agreement as a way of distinguishing between new business and dissatisfaction.
1. THIS DOCUMENT IS CALLED SYSTEM REQUIREMENTS. If you are missing this document, then we have other things to
discuss.
5. Have an overall time period to bring a close to the project on amicable terms, based on business needs.
1. What do I mean? Integrators may not stay on site forever. It is not personal, it is not what integration companies do.
2. Application users have end goal production in mind. Ie, there is an expected outcome for purchasing a production line
or machine. Can customer and integrator make it work to meet their needs? What were the system requirements to
begin with?
DERIVING A PUNCH LIST
 Deriving a punch list is simply doing a walk down and seeing what the assembly or process line can do
or not do.
 Everything that is “unsatisfactory” should be documented.
 Next, all unsatisfactory items should be categorized.
PUNCH LIST CATEGORIES
Integrator mistake.
SAFETY. The finished
product does not match
the SCOPE or
requirements originally
put forth by the customer.
Engineering changes go
here. These are process
changes or add-ons that
were not in scope and not
an original requirement.
Customer has a change of mind
that is small, and doable. IE,
screen item placement, color
change. OR, there is a
component failure within a
warranty period and that
component should be
reevaluated.
MUST DO--
SCOPE
DISCRETION (CUSTOMER
SERVICE)
ENGINEERING CHANGE NOTICE
(ECN)
PUNCH LIST EXAMPLE
Item Unsatisfactory Reason CATEGORY Assigned to? Completion Date
HMI Stop Button is
Orange not RED
Yes Customer specified
color pallet for HMI
functions.
SCOPE Bob the
programmer.
2 Feb 2022
Add a palletizer. No There is a delay in
offloading.
ECN Customer Manager TBD
Servo motor 5 only
works 80 percent of
the time. At some
speeds it is sluggish.
Yes Possible component
failure or wiring.
Bad tuning.
CS Engineer 1 15 Feb 2022
2022=re-eval
performance.
Electrical As-builts
were redlined but
new package not
delivered.
Yes Changes made on
installation.
CS/SCOPE Drafter 1 April 2022
MANAGING THE PUNCH LIST
 Hold weekly or daily meetings.
 Check on assignments before feedback to customer.
 Convey all changes openly with the customer.
 DECIDE ON PRIORITIES IN WEEKLY MEETINGS.
 Priorities are dictated by the customer needs.
IF IT’S A NEW LINE AND NEW PROCESS
 Approach it like unit testing.
 Make small changes and evaluate priorities.
 Speed
 Capacity
 Accuracy
 Costs
 Help the customer know what the line/machine can do and show data as to where the line is at for each
run.
 Define run parameters in conjunction with customer by combining hardware/software/process
knowledge
 If the end goal is not evident (production goals) then push to do bench tests to understand current
baselines.
• OEE
• PRODUCTION GOALS
• CUSTOMER ROI ON MACHINES IS INVERSELY
PROPORTIONAL TO INTEGRATOR SUCCESS
• INTEGRATOR COSTS INCREASE LONGER ON
CUSTOMER SITE
CONCLUSION
 Start ups are a joint effort between the customer and the integrator.
 Testing starts at proposal. Propose wisely.

More Related Content

Similar to Handling the punch list.pptx

Developing Product Configurator Tool Using CADs’ API with the help of Paramet...
Developing Product Configurator Tool Using CADs’ API with the help of Paramet...Developing Product Configurator Tool Using CADs’ API with the help of Paramet...
Developing Product Configurator Tool Using CADs’ API with the help of Paramet...ijcax
 
Take The Highway To A Successful It Project
Take The Highway To A Successful It ProjectTake The Highway To A Successful It Project
Take The Highway To A Successful It Projectsantosh singh
 
Acceptance test driven development
Acceptance test driven developmentAcceptance test driven development
Acceptance test driven developmentEditor Jacotech
 
INDUSTRIAL TRAINING REPORT
INDUSTRIAL TRAINING REPORTINDUSTRIAL TRAINING REPORT
INDUSTRIAL TRAINING REPORTSUYASH TRIVEDI
 
CTD for client signoff and early requirements validation - 11th IEEE SW Eng...
CTD for client signoff and early requirements validation   - 11th IEEE SW Eng...CTD for client signoff and early requirements validation   - 11th IEEE SW Eng...
CTD for client signoff and early requirements validation - 11th IEEE SW Eng...Saritha Route
 
An Oversight or a New Customer Phenomenon, Getting the Most of your Contact C...
An Oversight or a New Customer Phenomenon, Getting the Most of your Contact C...An Oversight or a New Customer Phenomenon, Getting the Most of your Contact C...
An Oversight or a New Customer Phenomenon, Getting the Most of your Contact C...Cisco Canada
 
Six_Sigma_Report_Template_v2 (2).pptx
Six_Sigma_Report_Template_v2 (2).pptxSix_Sigma_Report_Template_v2 (2).pptx
Six_Sigma_Report_Template_v2 (2).pptxPhngPhmTrung
 
Odoo Implementation Methodology
Odoo Implementation MethodologyOdoo Implementation Methodology
Odoo Implementation MethodologyQuang Ngoc
 
Odoo implementation
Odoo implementationOdoo implementation
Odoo implementationOdoo Thaidev
 
Asbo Vendor Performance Eval Chicago 092509
Asbo Vendor Performance Eval   Chicago   092509Asbo Vendor Performance Eval   Chicago   092509
Asbo Vendor Performance Eval Chicago 092509Richard Gay, CPPO, RSBO
 
Ambiguity_Reviews_Improving_Bus_Reqs_Schanta_StarEast2014
Ambiguity_Reviews_Improving_Bus_Reqs_Schanta_StarEast2014Ambiguity_Reviews_Improving_Bus_Reqs_Schanta_StarEast2014
Ambiguity_Reviews_Improving_Bus_Reqs_Schanta_StarEast2014Susan Schanta
 
Error Proofing And Cost Reduction 2
Error Proofing And Cost Reduction 2Error Proofing And Cost Reduction 2
Error Proofing And Cost Reduction 2Brian King
 
Owens Corning Global Fitness For Use
Owens Corning Global Fitness For UseOwens Corning Global Fitness For Use
Owens Corning Global Fitness For UseKeith Johnson
 
Product Design & Development
Product Design & DevelopmentProduct Design & Development
Product Design & DevelopmentQRCE
 
Presentation by meghna jadhav
Presentation by meghna jadhavPresentation by meghna jadhav
Presentation by meghna jadhavPMI_IREP_TP
 
Agile Development with Agile Contract
Agile Development with Agile ContractAgile Development with Agile Contract
Agile Development with Agile ContractNUS-ISS
 

Similar to Handling the punch list.pptx (20)

Developing Product Configurator Tool Using CADs’ API with the help of Paramet...
Developing Product Configurator Tool Using CADs’ API with the help of Paramet...Developing Product Configurator Tool Using CADs’ API with the help of Paramet...
Developing Product Configurator Tool Using CADs’ API with the help of Paramet...
 
Take The Highway To A Successful It Project
Take The Highway To A Successful It ProjectTake The Highway To A Successful It Project
Take The Highway To A Successful It Project
 
Acceptance test driven development
Acceptance test driven developmentAcceptance test driven development
Acceptance test driven development
 
INDUSTRIAL TRAINING REPORT
INDUSTRIAL TRAINING REPORTINDUSTRIAL TRAINING REPORT
INDUSTRIAL TRAINING REPORT
 
ETCA_4
ETCA_4ETCA_4
ETCA_4
 
CTD for client signoff and early requirements validation - 11th IEEE SW Eng...
CTD for client signoff and early requirements validation   - 11th IEEE SW Eng...CTD for client signoff and early requirements validation   - 11th IEEE SW Eng...
CTD for client signoff and early requirements validation - 11th IEEE SW Eng...
 
An Oversight or a New Customer Phenomenon, Getting the Most of your Contact C...
An Oversight or a New Customer Phenomenon, Getting the Most of your Contact C...An Oversight or a New Customer Phenomenon, Getting the Most of your Contact C...
An Oversight or a New Customer Phenomenon, Getting the Most of your Contact C...
 
Agile
AgileAgile
Agile
 
Six_Sigma_Report_Template_v2 (2).pptx
Six_Sigma_Report_Template_v2 (2).pptxSix_Sigma_Report_Template_v2 (2).pptx
Six_Sigma_Report_Template_v2 (2).pptx
 
Odoo Implementation Methodology
Odoo Implementation MethodologyOdoo Implementation Methodology
Odoo Implementation Methodology
 
Odoo implementation
Odoo implementationOdoo implementation
Odoo implementation
 
Asbo Vendor Performance Eval Chicago 092509
Asbo Vendor Performance Eval   Chicago   092509Asbo Vendor Performance Eval   Chicago   092509
Asbo Vendor Performance Eval Chicago 092509
 
Ambiguity_Reviews_Improving_Bus_Reqs_Schanta_StarEast2014
Ambiguity_Reviews_Improving_Bus_Reqs_Schanta_StarEast2014Ambiguity_Reviews_Improving_Bus_Reqs_Schanta_StarEast2014
Ambiguity_Reviews_Improving_Bus_Reqs_Schanta_StarEast2014
 
Error Proofing And Cost Reduction 2
Error Proofing And Cost Reduction 2Error Proofing And Cost Reduction 2
Error Proofing And Cost Reduction 2
 
Owens Corning Global Fitness For Use
Owens Corning Global Fitness For UseOwens Corning Global Fitness For Use
Owens Corning Global Fitness For Use
 
House of Quality
House of QualityHouse of Quality
House of Quality
 
SPM presentation.pptx
SPM presentation.pptxSPM presentation.pptx
SPM presentation.pptx
 
Product Design & Development
Product Design & DevelopmentProduct Design & Development
Product Design & Development
 
Presentation by meghna jadhav
Presentation by meghna jadhavPresentation by meghna jadhav
Presentation by meghna jadhav
 
Agile Development with Agile Contract
Agile Development with Agile ContractAgile Development with Agile Contract
Agile Development with Agile Contract
 

More from Tobey Houston

Automation Security in the Cloud.pptx
Automation Security in the Cloud.pptxAutomation Security in the Cloud.pptx
Automation Security in the Cloud.pptxTobey Houston
 
Capturing Mitsubishi Packets with Wireshark.pptx
Capturing Mitsubishi Packets with Wireshark.pptxCapturing Mitsubishi Packets with Wireshark.pptx
Capturing Mitsubishi Packets with Wireshark.pptxTobey Houston
 
Industrial_Ethernet_Technologies_220529_031813 (1).pdf
Industrial_Ethernet_Technologies_220529_031813 (1).pdfIndustrial_Ethernet_Technologies_220529_031813 (1).pdf
Industrial_Ethernet_Technologies_220529_031813 (1).pdfTobey Houston
 
State Machines and PLC Programming.pptx
State Machines and PLC Programming.pptxState Machines and PLC Programming.pptx
State Machines and PLC Programming.pptxTobey Houston
 
Lean Principles that Apply to the Machinist/Machineshop
Lean Principles that Apply to the Machinist/MachineshopLean Principles that Apply to the Machinist/Machineshop
Lean Principles that Apply to the Machinist/MachineshopTobey Houston
 
Language Memory Stimulation
Language Memory StimulationLanguage Memory Stimulation
Language Memory StimulationTobey Houston
 
Massmart supply system upgrade
Massmart supply system upgradeMassmart supply system upgrade
Massmart supply system upgradeTobey Houston
 
Requirements and analysis needed in implementing control systems
Requirements and analysis needed in implementing control systemsRequirements and analysis needed in implementing control systems
Requirements and analysis needed in implementing control systemsTobey Houston
 
Increasing economy of scope by increasing throughput
Increasing economy of scope by increasing throughputIncreasing economy of scope by increasing throughput
Increasing economy of scope by increasing throughputTobey Houston
 
Whole foods csr plan 2013
Whole foods csr plan 2013Whole foods csr plan 2013
Whole foods csr plan 2013Tobey Houston
 

More from Tobey Houston (12)

Automation Security in the Cloud.pptx
Automation Security in the Cloud.pptxAutomation Security in the Cloud.pptx
Automation Security in the Cloud.pptx
 
Capturing Mitsubishi Packets with Wireshark.pptx
Capturing Mitsubishi Packets with Wireshark.pptxCapturing Mitsubishi Packets with Wireshark.pptx
Capturing Mitsubishi Packets with Wireshark.pptx
 
Industrial_Ethernet_Technologies_220529_031813 (1).pdf
Industrial_Ethernet_Technologies_220529_031813 (1).pdfIndustrial_Ethernet_Technologies_220529_031813 (1).pdf
Industrial_Ethernet_Technologies_220529_031813 (1).pdf
 
State Machines and PLC Programming.pptx
State Machines and PLC Programming.pptxState Machines and PLC Programming.pptx
State Machines and PLC Programming.pptx
 
Lean Principles that Apply to the Machinist/Machineshop
Lean Principles that Apply to the Machinist/MachineshopLean Principles that Apply to the Machinist/Machineshop
Lean Principles that Apply to the Machinist/Machineshop
 
Language Memory Stimulation
Language Memory StimulationLanguage Memory Stimulation
Language Memory Stimulation
 
We can do it!
We can do it!We can do it!
We can do it!
 
Massmart supply system upgrade
Massmart supply system upgradeMassmart supply system upgrade
Massmart supply system upgrade
 
Requirements and analysis needed in implementing control systems
Requirements and analysis needed in implementing control systemsRequirements and analysis needed in implementing control systems
Requirements and analysis needed in implementing control systems
 
Increasing economy of scope by increasing throughput
Increasing economy of scope by increasing throughputIncreasing economy of scope by increasing throughput
Increasing economy of scope by increasing throughput
 
Whole foods csr plan 2013
Whole foods csr plan 2013Whole foods csr plan 2013
Whole foods csr plan 2013
 
Rainwater Artworx
Rainwater ArtworxRainwater Artworx
Rainwater Artworx
 

Recently uploaded

Automobile Management System Project Report.pdf
Automobile Management System Project Report.pdfAutomobile Management System Project Report.pdf
Automobile Management System Project Report.pdfKamal Acharya
 
Quality defects in TMT Bars, Possible causes and Potential Solutions.
Quality defects in TMT Bars, Possible causes and Potential Solutions.Quality defects in TMT Bars, Possible causes and Potential Solutions.
Quality defects in TMT Bars, Possible causes and Potential Solutions.PrashantGoswami42
 
Toll tax management system project report..pdf
Toll tax management system project report..pdfToll tax management system project report..pdf
Toll tax management system project report..pdfKamal Acharya
 
Final project report on grocery store management system..pdf
Final project report on grocery store management system..pdfFinal project report on grocery store management system..pdf
Final project report on grocery store management system..pdfKamal Acharya
 
Top 13 Famous Civil Engineering Scientist
Top 13 Famous Civil Engineering ScientistTop 13 Famous Civil Engineering Scientist
Top 13 Famous Civil Engineering Scientistgettygaming1
 
Architectural Portfolio Sean Lockwood
Architectural Portfolio Sean LockwoodArchitectural Portfolio Sean Lockwood
Architectural Portfolio Sean Lockwoodseandesed
 
Explosives Industry manufacturing process.pdf
Explosives Industry manufacturing process.pdfExplosives Industry manufacturing process.pdf
Explosives Industry manufacturing process.pdf884710SadaqatAli
 
A CASE STUDY ON ONLINE TICKET BOOKING SYSTEM PROJECT.pdf
A CASE STUDY ON ONLINE TICKET BOOKING SYSTEM PROJECT.pdfA CASE STUDY ON ONLINE TICKET BOOKING SYSTEM PROJECT.pdf
A CASE STUDY ON ONLINE TICKET BOOKING SYSTEM PROJECT.pdfKamal Acharya
 
Scaling in conventional MOSFET for constant electric field and constant voltage
Scaling in conventional MOSFET for constant electric field and constant voltageScaling in conventional MOSFET for constant electric field and constant voltage
Scaling in conventional MOSFET for constant electric field and constant voltageRCC Institute of Information Technology
 
Construction method of steel structure space frame .pptx
Construction method of steel structure space frame .pptxConstruction method of steel structure space frame .pptx
Construction method of steel structure space frame .pptxwendy cai
 
Hall booking system project report .pdf
Hall booking system project report  .pdfHall booking system project report  .pdf
Hall booking system project report .pdfKamal Acharya
 
Online blood donation management system project.pdf
Online blood donation management system project.pdfOnline blood donation management system project.pdf
Online blood donation management system project.pdfKamal Acharya
 
Cloud-Computing_CSE311_Computer-Networking CSE GUB BD - Shahidul.pptx
Cloud-Computing_CSE311_Computer-Networking CSE GUB BD - Shahidul.pptxCloud-Computing_CSE311_Computer-Networking CSE GUB BD - Shahidul.pptx
Cloud-Computing_CSE311_Computer-Networking CSE GUB BD - Shahidul.pptxMd. Shahidul Islam Prodhan
 
Democratizing Fuzzing at Scale by Abhishek Arya
Democratizing Fuzzing at Scale by Abhishek AryaDemocratizing Fuzzing at Scale by Abhishek Arya
Democratizing Fuzzing at Scale by Abhishek Aryaabh.arya
 
NO1 Pandit Amil Baba In Bahawalpur, Sargodha, Sialkot, Sheikhupura, Rahim Yar...
NO1 Pandit Amil Baba In Bahawalpur, Sargodha, Sialkot, Sheikhupura, Rahim Yar...NO1 Pandit Amil Baba In Bahawalpur, Sargodha, Sialkot, Sheikhupura, Rahim Yar...
NO1 Pandit Amil Baba In Bahawalpur, Sargodha, Sialkot, Sheikhupura, Rahim Yar...Amil baba
 
Natalia Rutkowska - BIM School Course in Kraków
Natalia Rutkowska - BIM School Course in KrakówNatalia Rutkowska - BIM School Course in Kraków
Natalia Rutkowska - BIM School Course in Krakówbim.edu.pl
 
A case study of cinema management system project report..pdf
A case study of cinema management system project report..pdfA case study of cinema management system project report..pdf
A case study of cinema management system project report..pdfKamal Acharya
 
ASME IX(9) 2007 Full Version .pdf
ASME IX(9)  2007 Full Version       .pdfASME IX(9)  2007 Full Version       .pdf
ASME IX(9) 2007 Full Version .pdfAhmedHussein950959
 
Courier management system project report.pdf
Courier management system project report.pdfCourier management system project report.pdf
Courier management system project report.pdfKamal Acharya
 
CME397 Surface Engineering- Professional Elective
CME397 Surface Engineering- Professional ElectiveCME397 Surface Engineering- Professional Elective
CME397 Surface Engineering- Professional Electivekarthi keyan
 

Recently uploaded (20)

Automobile Management System Project Report.pdf
Automobile Management System Project Report.pdfAutomobile Management System Project Report.pdf
Automobile Management System Project Report.pdf
 
Quality defects in TMT Bars, Possible causes and Potential Solutions.
Quality defects in TMT Bars, Possible causes and Potential Solutions.Quality defects in TMT Bars, Possible causes and Potential Solutions.
Quality defects in TMT Bars, Possible causes and Potential Solutions.
 
Toll tax management system project report..pdf
Toll tax management system project report..pdfToll tax management system project report..pdf
Toll tax management system project report..pdf
 
Final project report on grocery store management system..pdf
Final project report on grocery store management system..pdfFinal project report on grocery store management system..pdf
Final project report on grocery store management system..pdf
 
Top 13 Famous Civil Engineering Scientist
Top 13 Famous Civil Engineering ScientistTop 13 Famous Civil Engineering Scientist
Top 13 Famous Civil Engineering Scientist
 
Architectural Portfolio Sean Lockwood
Architectural Portfolio Sean LockwoodArchitectural Portfolio Sean Lockwood
Architectural Portfolio Sean Lockwood
 
Explosives Industry manufacturing process.pdf
Explosives Industry manufacturing process.pdfExplosives Industry manufacturing process.pdf
Explosives Industry manufacturing process.pdf
 
A CASE STUDY ON ONLINE TICKET BOOKING SYSTEM PROJECT.pdf
A CASE STUDY ON ONLINE TICKET BOOKING SYSTEM PROJECT.pdfA CASE STUDY ON ONLINE TICKET BOOKING SYSTEM PROJECT.pdf
A CASE STUDY ON ONLINE TICKET BOOKING SYSTEM PROJECT.pdf
 
Scaling in conventional MOSFET for constant electric field and constant voltage
Scaling in conventional MOSFET for constant electric field and constant voltageScaling in conventional MOSFET for constant electric field and constant voltage
Scaling in conventional MOSFET for constant electric field and constant voltage
 
Construction method of steel structure space frame .pptx
Construction method of steel structure space frame .pptxConstruction method of steel structure space frame .pptx
Construction method of steel structure space frame .pptx
 
Hall booking system project report .pdf
Hall booking system project report  .pdfHall booking system project report  .pdf
Hall booking system project report .pdf
 
Online blood donation management system project.pdf
Online blood donation management system project.pdfOnline blood donation management system project.pdf
Online blood donation management system project.pdf
 
Cloud-Computing_CSE311_Computer-Networking CSE GUB BD - Shahidul.pptx
Cloud-Computing_CSE311_Computer-Networking CSE GUB BD - Shahidul.pptxCloud-Computing_CSE311_Computer-Networking CSE GUB BD - Shahidul.pptx
Cloud-Computing_CSE311_Computer-Networking CSE GUB BD - Shahidul.pptx
 
Democratizing Fuzzing at Scale by Abhishek Arya
Democratizing Fuzzing at Scale by Abhishek AryaDemocratizing Fuzzing at Scale by Abhishek Arya
Democratizing Fuzzing at Scale by Abhishek Arya
 
NO1 Pandit Amil Baba In Bahawalpur, Sargodha, Sialkot, Sheikhupura, Rahim Yar...
NO1 Pandit Amil Baba In Bahawalpur, Sargodha, Sialkot, Sheikhupura, Rahim Yar...NO1 Pandit Amil Baba In Bahawalpur, Sargodha, Sialkot, Sheikhupura, Rahim Yar...
NO1 Pandit Amil Baba In Bahawalpur, Sargodha, Sialkot, Sheikhupura, Rahim Yar...
 
Natalia Rutkowska - BIM School Course in Kraków
Natalia Rutkowska - BIM School Course in KrakówNatalia Rutkowska - BIM School Course in Kraków
Natalia Rutkowska - BIM School Course in Kraków
 
A case study of cinema management system project report..pdf
A case study of cinema management system project report..pdfA case study of cinema management system project report..pdf
A case study of cinema management system project report..pdf
 
ASME IX(9) 2007 Full Version .pdf
ASME IX(9)  2007 Full Version       .pdfASME IX(9)  2007 Full Version       .pdf
ASME IX(9) 2007 Full Version .pdf
 
Courier management system project report.pdf
Courier management system project report.pdfCourier management system project report.pdf
Courier management system project report.pdf
 
CME397 Surface Engineering- Professional Elective
CME397 Surface Engineering- Professional ElectiveCME397 Surface Engineering- Professional Elective
CME397 Surface Engineering- Professional Elective
 

Handling the punch list.pptx

  • 1. HANDLING THE PUNCH LIST SATISFYING CUSTOMERS AFTER THE INSTALLATION IS DONE
  • 2. DEFINITION OF PUNCH LIST  A punch list is the “snag” list. After an installation ( of any kind ), upon inspection the customer and the contractor, developer, integrator; must agree on the outcome. Ideally, there should have been an end objective that was agreed upon. If the contractor has not met that objective, or there are known deficiencies, a punch list is created and it gives the customer a tool to track progress.  On the other hand, the contractor needs to use the punch list as a springboard for engineering changes, which would generate positive business for the contractor. Ie, did the customer change their mind. Does the customer have additions? Does this create a new business cycle?  Reference: Punch List 101 | Fieldwire  How does this apply to control systems integrators?
  • 3. PUNCH LIST 101 Objectives of the Punchlist: 1. Convey non-conformities. 2. Give a tool for customer/integrator interface. 3. Provide clear objectives with an assignment and an end date. 4. Reference back to original agreement as a way of distinguishing between new business and dissatisfaction. 1. THIS DOCUMENT IS CALLED SYSTEM REQUIREMENTS. If you are missing this document, then we have other things to discuss. 5. Have an overall time period to bring a close to the project on amicable terms, based on business needs. 1. What do I mean? Integrators may not stay on site forever. It is not personal, it is not what integration companies do. 2. Application users have end goal production in mind. Ie, there is an expected outcome for purchasing a production line or machine. Can customer and integrator make it work to meet their needs? What were the system requirements to begin with?
  • 4. DERIVING A PUNCH LIST  Deriving a punch list is simply doing a walk down and seeing what the assembly or process line can do or not do.  Everything that is “unsatisfactory” should be documented.  Next, all unsatisfactory items should be categorized.
  • 5. PUNCH LIST CATEGORIES Integrator mistake. SAFETY. The finished product does not match the SCOPE or requirements originally put forth by the customer. Engineering changes go here. These are process changes or add-ons that were not in scope and not an original requirement. Customer has a change of mind that is small, and doable. IE, screen item placement, color change. OR, there is a component failure within a warranty period and that component should be reevaluated. MUST DO-- SCOPE DISCRETION (CUSTOMER SERVICE) ENGINEERING CHANGE NOTICE (ECN)
  • 6. PUNCH LIST EXAMPLE Item Unsatisfactory Reason CATEGORY Assigned to? Completion Date HMI Stop Button is Orange not RED Yes Customer specified color pallet for HMI functions. SCOPE Bob the programmer. 2 Feb 2022 Add a palletizer. No There is a delay in offloading. ECN Customer Manager TBD Servo motor 5 only works 80 percent of the time. At some speeds it is sluggish. Yes Possible component failure or wiring. Bad tuning. CS Engineer 1 15 Feb 2022 2022=re-eval performance. Electrical As-builts were redlined but new package not delivered. Yes Changes made on installation. CS/SCOPE Drafter 1 April 2022
  • 7. MANAGING THE PUNCH LIST  Hold weekly or daily meetings.  Check on assignments before feedback to customer.  Convey all changes openly with the customer.  DECIDE ON PRIORITIES IN WEEKLY MEETINGS.  Priorities are dictated by the customer needs.
  • 8. IF IT’S A NEW LINE AND NEW PROCESS  Approach it like unit testing.  Make small changes and evaluate priorities.  Speed  Capacity  Accuracy  Costs  Help the customer know what the line/machine can do and show data as to where the line is at for each run.  Define run parameters in conjunction with customer by combining hardware/software/process knowledge  If the end goal is not evident (production goals) then push to do bench tests to understand current baselines. • OEE • PRODUCTION GOALS • CUSTOMER ROI ON MACHINES IS INVERSELY PROPORTIONAL TO INTEGRATOR SUCCESS • INTEGRATOR COSTS INCREASE LONGER ON CUSTOMER SITE
  • 9. CONCLUSION  Start ups are a joint effort between the customer and the integrator.  Testing starts at proposal. Propose wisely.